JP2019073948A - Floor slab reconstruction method - Google Patents

Floor slab reconstruction method Download PDF

Info

Publication number
JP2019073948A
JP2019073948A JP2017202222A JP2017202222A JP2019073948A JP 2019073948 A JP2019073948 A JP 2019073948A JP 2017202222 A JP2017202222 A JP 2017202222A JP 2017202222 A JP2017202222 A JP 2017202222A JP 2019073948 A JP2019073948 A JP 2019073948A
Authority
JP
Japan
Prior art keywords
floor slab
construction
bridge
work
construction area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017202222A
Other languages
Japanese (ja)
Other versions
JP7442256B2 (en
Inventor
宏之 山中
Hiroyuki Yamanaka
宏之 山中
好謙 坂本
Yoshikane Sakamoto
好謙 坂本
健三 高瀬
Kenzo Takase
健三 高瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2017202222A priority Critical patent/JP7442256B2/en
Publication of JP2019073948A publication Critical patent/JP2019073948A/en
Priority to JP2022001494A priority patent/JP7148746B2/en
Priority to JP2023003216A priority patent/JP2023029610A/en
Application granted granted Critical
Publication of JP7442256B2 publication Critical patent/JP7442256B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

To provide a floor slab reconstruction method which makes it possible to carry out the efficient reconstruction of a floor slab.SOLUTION: A floor slab reconstruction method includes setting a plurality of construction areas Ato Aby dividing a bridge 1 as an example of a structure into a plurality of construction area Ato Ain its axial direction. Each of the construction areas Ato Ahas a plurality of stages of work processes (S1(S11 to S13), S2(S21 to S23), and S3(S31, S32)) from removal of an existing floor slab 5 to installation of a new floor slab 7. The floor slab reconstruction method concerned executes different work processes at the same time in the progress direction of the floor slab reconstruction construction along the axial direction of the bridge 1 both in a construction area on a front side in the progress direction of the floor slab reconstruction construction (e.g., a construction area A) and in a construction area rearward in the progress direction of the floor slab reconstruction construction from the aforesaid construction area (e.g., a construction area A).SELECTED DRAWING: Figure 2

Description

本発明は、橋梁などの構造物を構成する床版の架け替え(既設床版の撤去とこれに替わる新設床版の設置)を行う方法に関する。   The present invention relates to a method of rebuilding a floor slab constituting a structure such as a bridge (removing an existing floor slab and installing a new floor slab to replace it).

橋梁は、例えば、複数の橋脚と、各々が複数の橋脚の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)と、複数の橋桁の上に跨がって配設される床版と、を含んで構成される。床版は、例えば鉄筋コンクリート製である。かかる床版については、長年の使用によるコンクリートの劣化や内部の鉄筋の腐食などの理由で、架け替え(既設床版の撤去と新設床版の設置)が求められる場合がある。   The bridge is disposed, for example, over a plurality of bridge piers, a plurality of bridge girder (H-shaped steel) each extending in the axial direction across the plurality of bridge piers, and a plurality of bridge girders. And a floor plate. The floor slab is made of, for example, reinforced concrete. Such floor slabs may be required to be rebuilt (removal of existing floor slabs and installation of new floor slabs) due to deterioration of concrete due to years of use and corrosion of internal rebars.

床版の架け替えに用いられる装置としては、例えば特許文献1に記載の床版架設機が知られている。これは、橋軸方向前後の門型フレームを連結してなる無軌条・自走式の門型構造体と、門型構造体の天井部の下面側に前後方向及び横方向に移動可能に設けられる吊上装置(例えばチェーンブロック)と、を備えている。ここにおいて、新設床版はプレキャストコンクリート製である。   As an apparatus used for rebuilding a floor slab, for example, a floor slab setting machine described in Patent Document 1 is known. This is provided so as to be movable in the longitudinal and lateral directions on the lower surface side of the rail-free and self-propelled portal structure connecting the portal frame front and back in the bridge axial direction and the ceiling part of the portal structure. And a lifting device (for example, a chain block). Here, the new floor is made of precast concrete.

このような架設機を用いた新設床版の架設作業は、
(1)架設機の後部での新設床版の取込み、すなわち、架設機の後部に位置させた吊上装置による、新設床版の長辺を橋軸方向に向けた状態での、新設床版の吊上げ
(2)吊上装置の前側への移動による、新設床版の架設位置までの移送
(3)新設床版の長辺を橋軸直角方向に向けるように、新設床版の向きの変更(90°回転)
(4)そして、所定位置への設置
という工程で行われる。
また、既設の床版の撤去作業は、入れ替わりで、ほぼ逆の工程で行われる。
The construction work of a new floor slab using such a construction machine is
(1) Take-in of a new floor slab at the rear of the construction machine, that is, a new floor slab with the long side of the new floor slab directed in the bridge axial direction by the lifting device positioned at the rear of the construction machine (2) Transfer of the new floor slab to the installation position by moving the lifting device to the front side (3) Changing the direction of the new floor slab so that the long side of the new floor slab is directed perpendicular to the bridge axis (90 ° rotation)
(4) And it is performed at the process of installation in a predetermined position.
In addition, the removal work of the existing floor slab is carried out in the reverse process almost in turn.

特許第3901657号公報Patent No. 3901657 gazette

しかしながら、前述の架設機を用いる床版架け替え方法では、ある施工場所で既設床版の撤去から新設床版の設置までを行った後に前述の架設機が橋軸方向に移動して、次の施工場所で既設床版の撤去から新設床版の設置までを行う。ゆえに、ある施工場所での床版の架け替え作業が完了するまでは次の施工場所で床版の架け替え作業を開始することができず、その結果、橋梁の全長にわたって床版の架け替えを行うのに時間がかかるという問題点があった。   However, in the above-mentioned method of rebuilding a floor slab using the above-mentioned construction machine, the above-mentioned construction machine moves in the axial direction of the bridge after removing the existing floor slab to installing a new floor slab at a construction site. From the removal of the existing floor version to the installation of a new floor version at the construction site. Therefore, it is not possible to start reconstruction of the floor slab at the next construction site until reconstruction of the floor slab at one construction site is completed, and as a result, reconstruction of the floor slab over the entire length of the bridge is required. There was a problem that it took time to do.

本発明は、このような実状に鑑み、橋梁などの構造物において、効率的な床版の架け替えを行うことができる、床版架け替え方法を提供することを目的とする。   An object of the present invention is to provide a method of rebuilding a floor slab that can efficiently rebuild a floor slab in a structure such as a bridge.

そのため本発明に係る床版架け替え方法は、構造物における床版の架け替え方法である。本発明に係る床版架け替え方法は、構造物を構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含む。各施工領域は、それぞれ、既設床版の撤去から新設床版の配置に至る複数段の作業工程を有する。本発明に係る床版架け替え方法では、構造物の軸方向に沿う床版架け替え施工進行方向において、床版架け替え施工進行方向前側の施工領域と、この施工領域より床版架け替え施工進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する。   Therefore, the method of rebuilding a floor plate according to the present invention is a method of rebuilding a floor plate in a structure. The floor slab rebuilding method according to the present invention includes setting a plurality of construction areas by dividing the structure into a plurality of construction areas in the axial direction of the structure. Each construction area has multiple stages of work processes from removal of the existing floor slab to arrangement of the new floor slab. In the method of rebuilding a floor slab according to the present invention, in the direction of progress of rebuilding the floor slab along the axial direction of the structure, the area of construction on the front side of the direction of rebuilding floor slab rebuilding progress Different work steps are carried out in parallel in the direction of the rear construction area.

本発明によれば、床版架け替え施工進行方向前側の施工領域と、この施工領域より床版架け替え施工進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する。これにより、床版架け替え施工の進捗状況が異なる複数の施工領域にて、並行して(すなわち同時に)施工を進めることができるので、床版の架け替えを効率良く(換言すれば短期間で)行うことができる。   According to the present invention, different work processes are carried out in parallel in the construction area on the front side of the floor slab replacement construction direction and the construction area on the rear side of the floor slab reconstruction construction direction from the construction area. As a result, the construction can be carried out in parallel (that is, simultaneously) in a plurality of construction areas where the progress of the floor slab reconstruction work is different, so the reconstruction of the floor slab is efficiently performed (in other words, in a short period of time) )It can be carried out.

既設の橋梁の一例の側面図Side view of an example of an existing bridge 本発明の第1実施形態における床版架け替え方法の施工状態を示す側面図Side view showing the installation state of the deck reconstruction method in the first embodiment of the present invention 前記第1実施形態における床版架け替え方法のメインルーチンを示すフローチャートA flow chart showing a main routine of the floor plate rebuilding method in the first embodiment 前記第1実施形態における床版架け替え方法のサブルーチンを示すフローチャートThe flowchart which shows the subroutine of the floor edition rebuilding method in the aforementioned 1st execution form 前記第1実施形態における既設床版の撤去方法を示すフローチャートFlow chart showing the method of removing the existing floor slab in the first embodiment 前記第1実施形態における新設床版の配置準備方法を示すフローチャートFlowchart showing arrangement preparation method of new floor in the first embodiment 前記第1実施形態における新設床版の配置方法を示すフローチャートA flowchart showing a method of arranging a new floor in the first embodiment 前記第1実施形態における既設床版の切断方法を示す図The figure which shows the cutting method of the existing floor slab in said 1st Embodiment. 前記第1実施形態における既設床版の切断方法を示す図The figure which shows the cutting method of the existing floor slab in said 1st Embodiment. 前記第1実施形態における既設床版の縁切り方法を示す図The figure which shows the border cutting method of the existing floor slab in said 1st Embodiment. 前記第1実施形態における既設床版の縁切り方法を示す図The figure which shows the border cutting method of the existing floor slab in said 1st Embodiment. 前記第1実施形態における新設床版の配置準備方法を示す図The figure which shows the arrangement preparation method of the new installation floor slab in the said 1st Embodiment. 前記第1実施形態における新設床版の配置準備方法を示す図The figure which shows the arrangement preparation method of the new installation floor slab in the said 1st Embodiment. 前記第1実施形態における新設床版の配置準備方法を示す図The figure which shows the arrangement preparation method of the new installation floor slab in the said 1st Embodiment. 前記第1実施形態における新設床版の配置方法を示す図A diagram showing a method of arranging a new floor in the first embodiment 前記第1実施形態における新設床版の配置方法を示す図A diagram showing a method of arranging a new floor in the first embodiment 前記第1実施形態におけるスタッドジベルの設置方法を示す図The figure which shows the installation method of the stud dowel in the said 1st Embodiment. 前記第1実施形態における時刻と各施工領域の作業工程との関係を示す図The figure which shows the relationship between the time in the said 1st Embodiment, and the work process of each construction area | region 前記第1実施形態における時刻と各施工領域の作業工程との関係を示す図The figure which shows the relationship between the time in the said 1st Embodiment, and the work process of each construction area | region 従来の床版架け替え方法の一例における時刻と各施工領域の作業工程との関係を示す図Diagram showing the relationship between the time in an example of the conventional method of rebuilding a floor slab and the work process of each construction area 本発明の第2実施形態における時刻と各施工領域の作業工程との関係を示す図The figure which shows the relationship between the time in 2nd Embodiment of this invention, and the operation process of each construction area | region 前記第2実施形態における時刻と各施工領域の作業工程との関係を示す図The figure which shows the relationship between the time in the said 2nd Embodiment, and the work process of each construction area | region 本発明の第3実施形態における新設床版の配置方法を示すフローチャートThe flowchart which shows the arrangement method of the new floor in 3rd execution form of this invention 本発明の第4実施形態における新設床版の配置準備方法を示すフローチャートThe flowchart which shows the arrangement preparation method of the new installation floor slab in 4th execution form of this invention 本発明の第5実施形態における新設床版の配置方法を示すフローチャートThe flowchart which shows the arrangement method of the new installation floor slab in 5th execution form of this invention 本発明の第6実施形態における新設床版の配置準備方法を示すフローチャートThe flowchart which shows the arrangement preparation method of the new installation floor slab in 6th execution form of this invention

以下、本発明の実施の形態について、図面を参照して説明する。尚、全図中、同一又は相当部分には同一符号を付すこととする。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. In all the drawings, the same or corresponding parts are denoted by the same reference numerals.

図1は、本発明に係る床版架け替え方法が適用され得る既設の橋梁の一例の側面図である。図2は、本発明の第1実施形態における床版架け替え方法の施工状態を示す側面図である。尚、本実施形態では、橋梁における床版架け替え施工の進行方向を前進方向として図1及び図2に示すように前後を規定して、以下説明する。ここで、床版架け替え施工進行方向は、橋梁の橋軸方向に沿う。また、本実施形態では、橋梁の橋軸直角方向を左右方向(横方向)として、以下説明する(図10A〜図12参照)。   FIG. 1 is a side view of an example of an existing bridge to which the floor slab rebuilding method according to the present invention can be applied. FIG. 2: is a side view which shows the construction state of the floor slab change method in 1st Embodiment of this invention. In the present embodiment, the front and back are defined as shown in FIGS. 1 and 2 with the direction of progress of floor slab reconstruction work in a bridge as the direction of forward movement, which will be described below. Here, the direction in which the floor slab reconstruction work proceeds is along the bridge axis direction of the bridge. Further, in the present embodiment, the direction perpendicular to the bridge axis of the bridge will be described as the lateral direction (lateral direction) (see FIGS. 10A to 12).

尚、本実施形態では、本発明の「構造物」(土木構造物)の一例として橋梁を挙げて説明するが、本発明の「構造物」は橋梁に限らない。また、前述の橋軸方向が、本発明の「構造物の軸方向」及び「橋梁の軸方向」に対応し得る。   In the present embodiment, a bridge is described as an example of the “structure” (civil engineering structure) of the present invention, but the “structure” of the present invention is not limited to the bridge. Moreover, the above-mentioned bridge shaft direction may correspond to the “axial direction of the structure” and the “axial direction of the bridge” in the present invention.

本発明の「構造物」の一例である橋梁1は、前後一対の橋台2a,2bと、橋台2a,2b間に間隔を空けて配設された複数の橋脚3と、各々が橋台2a,2b及び複数の橋脚3の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)4と、複数の橋桁4の上に跨がって配設されたコンクリート製の既設床版5と、を含んで構成される。尚、橋台2a,2b及び複数の橋脚3と複数の橋桁4との間には、図示しない支承が介装されている。ここで、本実施形態では、既設床版5が鉄筋コンクリート製である(RC床版である)として以下説明するが、この他、既設床版5は、プレストレストコンクリート製であってもよい(PC床版であってもよい)。また、橋桁4は、後述する図10A〜図10Cに示すように、ウェブ4wと、上フランジ4fと、下フランジ(図示せず)とを有している。   The bridge 1 which is an example of the "structure" of the present invention includes a pair of front and rear abutments 2a and 2b, a plurality of bridge piers 3 disposed at intervals between the abutments 2a and 2b, and abutments 2a and 2b, respectively. And a plurality of bridge girder (H-shaped steel) 4 extending in the bridge axial direction straddling on a plurality of bridge piers 3 and an existing floor slab 5 made of concrete disposed straddling a plurality of bridge girder 4 And is comprised. A bearing (not shown) is interposed between the abutments 2a and 2b and the plurality of bridge piers 3 and the plurality of bridge beams 4. Here, in the present embodiment, the existing floor slab 5 will be described below as being made of reinforced concrete (it is an RC floor slab), but in addition, the existing floor slab 5 may be made of prestressed concrete (PC floor It may be a version). The bridge girder 4 also has a web 4 w, an upper flange 4 f, and a lower flange (not shown), as shown in FIGS. 10A to 10C described later.

本実施形態では、橋梁1の全長(橋長)Ltが300mであるとして以下説明するが、橋梁1の全長Ltは300mに限らない。また、本実施形態では、橋梁1の橋軸直角方向において既設床版5を分割しない、いわゆる全断面床版架け替え施工であるとして以下説明するが、施工形態はこれに限らず、例えば、橋梁1の橋軸直角方向において既設床版5を2つに分割する、いわゆる半断面床版架け替え施工であってもよい。   In the present embodiment, the total length (bridge length) Lt of the bridge 1 will be described as 300 m, but the total length Lt of the bridge 1 is not limited to 300 m. Moreover, although this embodiment demonstrates as what is called a whole section floor slab reconstruction construction which does not divide the existing floor slab 5 in the bridge shaft right angle direction of the bridge 1 below, a construction form is not restricted to this, for example, a bridge The existing floor slab 5 may be divided into two in a direction perpendicular to the bridge axis 1 so-called a half-section floor slab replacement construction.

図1及び図2に加えて、図3及び図4を用いて、本実施形態における床版架け替え方法を説明する。図3は、本実施形態における床版架け替え方法のメインルーチンを示すフローチャートである。図4は、本実施形態における床版架け替え方法のサブルーチンを示すフローチャートである。   In addition to FIG.1 and FIG.2, the floor-plate rebuilding method in this embodiment is demonstrated using FIG.3 and FIG.4. FIG. 3 is a flow chart showing a main routine of the floor plate rebuilding method in the present embodiment. FIG. 4 is a flow chart showing a subroutine of the floor plate rebuilding method according to the present embodiment.

橋梁1の床版架け替え施工(既設床版5の撤去と、これに替わる新設床版7の設置)は、全体的には、図3に示すメインルーチンに従う。   The floor slab rebuilding construction of the bridge 1 (removal of the existing floor slab 5 and installation of the new floor slab 7 instead of this) generally follows the main routine shown in FIG.

まず、ステップS101では、橋梁1を橋軸方向に複数(本実施形態ではn個)の施工領域A〜Aに区分けすることにより、複数の施工領域A〜Aを設定する。尚、本実施形態では、施工領域A〜Aの各々の橋軸方向の長さが、それぞれ6mであるとして以下説明するが、施工領域A〜Aの各々の橋軸方向の長さは6mに限らない。例えば、橋梁1の全長Ltが300mであり、かつ、施工領域A〜Aの各々の橋軸方向の長さが、それぞれ6mである場合には、n=300/6=50となる。 First, in step S101, (in this embodiment n) of a plurality of bridge 1 to Hashijiku direction by partitioning the construction area A 1 to A n of the sets a plurality of construction areas A 1 to A n. In the present embodiment, the length of each of the bridge axis direction construction areas A 1 to A n are, will be described below as a 6m respectively, of each of the bridge axis direction construction areas A 1 to A n length Is not limited to 6m. For example, in the case where the total length Lt of the bridge 1 is 300 m and the length in the direction of the bridge axis of each of the construction areas A 1 to A n is 6 m, n = 300/6 = 50.

次に、ステップS102では、施工領域A〜Aの各々にて、既設床版5の撤去と、これに替わる新設床版7の配置とを行う。本実施形態では、例えば図2に示すように、複数の施工領域A〜Ak−6にて床版架け替え作業が並行して実施可能である。尚、本実施形態では、床版架け替え施工進行方向において、前側の施工領域(例えば施工領域Ak−4)と、この施工領域より後方の施工領域(例えば施工領域Ak−6)とにて、互いに異なる作業工程を並行して実施し得る。 Next, in step S102, performed by each of the construction area A 1 to A n, and removal of the existing deck 5, the arrangement of the new floor plate 7 an alternative thereto. In the present embodiment, for example, as shown in FIG. 2, the floor plate hung replacement work can be performed in parallel by a plurality of construction areas A k ~A k-6. In the present embodiment, in the floor slab replacement construction progressing direction, the construction area on the front side (for example, construction area Ak-4 ) and the construction area behind this construction area (for example construction area Ak-6 ) Thus, different operation steps can be performed in parallel.

施工領域A〜Aの全てで既設床版5の撤去と、これに替わる新設床版7の配置とが行われると(すなわち、橋梁1の全長Ltにわたって新設床版7の配置が完了すると)、ステップS103に進み、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化する。
このようにして、橋梁1の床版架け替え施工が行われる。
When removal of the existing floor slab 5 and placement of the new floor slab 7 replacing it are performed in all of the construction areas A 1 to A n (that is, placement of the new floor slab 7 is completed over the entire length Lt of the bridge 1) In step S103, the new installation floor 7 and the bridge girder 4 are fixed and integrated, and the new installation floor 7 adjacent to each other in the bridge axis direction is fixed and integrated.
In this way, the floor plate reconstruction work of the bridge 1 is performed.

前述のステップS102に関して、施工領域A〜Aの各々は、既設床版5の撤去から新設床版7の配置に至る複数段の作業工程を有する。この複数段の作業工程が図4に示されている。
図4に示すように、まず、ステップS1にて、前段(第1段)として、既設床版5の撤去作業を実施する。ここで、ステップS1が、本発明の「第1作業工程」に対応する。
Regarding step S102 described above, each of the construction areas A 1 to A n has a plurality of stages of work processes from removal of the existing floor slab 5 to arrangement of the new floor slab 7. The multistage working process is shown in FIG.
As shown in FIG. 4, first, at step S1, the existing floor slab 5 is removed as a front stage (first stage). Here, step S1 corresponds to the "first operation process" of the present invention.

次に、ステップS2にて、中段(第2段)として、既設床版5が撤去された施工領域に新設床版7を配置するための準備作業(新設床版7の配置準備作業)を実施する。ここで、ステップS2が、本発明の「第2作業工程」に対応する。   Next, in step S2, as the middle stage (the second stage), the preparatory work (placement preparation work for the newly installed floor version 7) for placing the newly installed floor version 7 in the construction area from which the existing floor version 5 has been removed Do. Here, step S2 corresponds to the "second operation process" of the present invention.

次に、ステップS3にて、後段(第3段)として、新設床版7の配置準備作業が実施された施工領域に新設床版7を配置する。ここで、ステップS3が、本発明の「第3作業工程」に対応する。   Next, in step S3, as a subsequent stage (third stage), the new floor slab 7 is placed in the construction area where the placement preparation work of the new floor slab 7 has been performed. Here, step S3 corresponds to the "third operation process" of the present invention.

ここで、ステップS1にて実施される既設床版5の撤去作業について、前述の図1〜図4に加えて、図5及び図8A〜図9Bを用いて説明する。
図5は、本実施形態における既設床版5の撤去方法を示すフローチャートである。図8A及び図8Bは、本実施形態における既設床版5の切断方法を示す図である。図9A及び図9Bは、本実施形態における既設床版5の縁切り方法を示す図である。
Here, the removal work of the existing floor slab 5 implemented in step S1 will be described using FIGS. 5 and 8A to 9B in addition to FIGS. 1 to 4 described above.
FIG. 5 is a flowchart showing a method of removing the existing floor slab 5 in the present embodiment. Drawing 8A and Drawing 8B are figures showing the cutting method of existing floor slab 5 in this embodiment. FIG. 9A and FIG. 9B are figures which show the border cutting method of the existing floor slab 5 in this embodiment.

図5に示すように、まず、ステップS11では、既設床版5の切断作業を実施する。このステップS11では、図8A及び図8Bに示すように、既設床版5の後端から所定長さLa分前方の箇所に切断線5bを設定し、この切断線5bに沿って、コンクリートカッターやワイヤーソーなどのコンクリート切断装置を用いて既設床版5を切断して、床版片5aを形成する。本実施形態では、前述の所定長さLaが2mであるとしているが、前述の所定長さLaは2mに限らない。   As shown in FIG. 5, first, in step S11, the existing floor plate 5 is cut. In this step S11, as shown in FIG. 8A and FIG. 8B, a cutting line 5b is set at a position ahead by a predetermined length La from the rear end of the existing floor slab 5, and along the cutting line 5b The existing floor slab 5 is cut using a concrete cutting device such as a wire saw to form the floor slab piece 5a. In the present embodiment, the above-mentioned predetermined length La is 2 m, but the above-mentioned predetermined length La is not limited to 2 m.

次に、ステップS12にて、既設床版5の床版片5aの縁切り作業を実施する。このステップS12では、まず、図9Aに示すように、床版片5aの前方と後方とに、それぞれ、短縮状態の複数のジャッキ50a,50bを設置する。ここで、ジャッキ50a,50bは上下方向に伸縮自在であり、例えば油圧ジャッキである。   Next, in step S12, the edge cutting operation of the floor slab piece 5a of the existing floor slab 5 is performed. In this step S12, first, as shown in FIG. 9A, a plurality of jacks 50a and 50b in a shortened state are installed on the front and the rear of the floor slab piece 5a, respectively. Here, the jacks 50a and 50b are extendable in the vertical direction, and are, for example, hydraulic jacks.

前側のジャッキ50aは、その下端部が既設床版5の上面に当接する。後側のジャッキ50bは、その下端部が橋桁4の上面4a(詳しくは、図10A〜図10Cに示す橋桁4の上フランジ4fの上面4a)に当接する。   The lower end of the front jack 50 a abuts on the upper surface of the existing floor plate 5. The lower end of the rear jack 50b abuts on the upper surface 4a of the bridge girder 4 (specifically, the upper surface 4a of the upper flange 4f of the bridge girder 4 shown in FIGS. 10A to 10C).

また、図9Aに示すように、ジャッキ50a,50bの上に跨がるように、梁部材51が配置されている。梁部材51は、ジャッキ50a,50bの上端部に固定されている。梁部材51は、図示しないブラケットを有し、このブラケットと、床版片5aとを貫通するように、上下方向に延びるPC鋼棒52が配置されている。PC鋼棒52については、橋桁4をかわすように配置されている。PC鋼棒52の上端部及び下端部には、それぞれ、梁部材51(前述のブラケット)及び床版片5aとPC鋼棒52とを固定するための固定部材53a,53bが取り付けられている。   Moreover, as shown to FIG. 9A, the beam member 51 is arrange | positioned so that it straddles on jack 50a, 50b. The beam member 51 is fixed to the upper end portions of the jacks 50a and 50b. The beam member 51 has a bracket (not shown), and a vertically extending PC steel rod 52 is disposed so as to penetrate the bracket and the floor slab 5a. The PC steel rods 52 are arranged to pass the bridge girder 4. Fixing members 53a and 53b for fixing the beam member 51 (the aforementioned bracket) and the floor slab piece 5a and the PC steel rod 52 are attached to the upper end portion and the lower end portion of the PC steel rod 52, respectively.

次に、図9Bに示すように、ジャッキ50a,50bを伸長作動させることにより、梁部材51(前述のブラケット)及びPC鋼棒52を介して、床版片5aが引っ張り上げられる。このようにして、床版片5aが橋桁4から分離(縁切り)されると、ジャッキ50a,50bを短縮し、PC鋼棒52、梁部材51、及びジャッキ50a,50bを撤去する。   Next, as shown in FIG. 9B, the floor slab piece 5a is pulled up via the beam member 51 (the aforementioned bracket) and the PC steel rod 52 by operating the jacks 50a and 50b to extend. Thus, when the floor slab piece 5a is separated from the bridge girder 4, the jacks 50a and 50b are shortened, and the PC steel rod 52, the beam member 51, and the jacks 50a and 50b are removed.

次に、図5のステップS13にて、橋桁4から縁切りされた床版片5aを、図2に示すクレーン装置20にて吊り上げ、床版片5aの長辺を橋軸方向に向けるように床版片5aの向きを変更して(すなわち90°回転させて)、この床版片5aを、クレーン装置20により、図示しない運搬車両の荷台に載せる。この運搬車両は、床版片5aを、施工領域A〜Aから床版架け替え施工進行方向前方に搬出し得る。尚、この運搬車両は、既設床版5上を走行可能である。 Next, in step S13 of FIG. 5, the floor slab 5a which has been cut from the bridge girder 4 is lifted by the crane device 20 shown in FIG. 2 and the floor of the floor slab 5a is oriented in the bridge axial direction. The direction of the printing piece 5a is changed (ie, rotated by 90 °), and the floor mounting piece 5a is placed by the crane device 20 on the bed of a transport vehicle (not shown). The transport vehicle is a floor plate pieces 5a, may be unloaded from the construction area A 1 to A n in construction ahead of the vehicle re hung slab. In addition, this transport vehicle can travel on the existing floor slab 5.

クレーン装置20は、前後方向に延びる左右一対の下部フレーム21と、左右一対の下部フレーム21に下端が連結された門型フレーム22と、門型フレーム22の上部に設けられた上部フレーム23と、上部フレーム23に対して前後左右に移動可能な吊上装置24と、を含んで構成されている。左右一対の下部フレーム21には、既設床版5上を転動可能な車輪が設けられている。門型フレーム22内、及び、左右一対の下部フレーム21間には、前述の運搬車両の荷台が配置され得る。   The crane device 20 includes a pair of left and right lower frames 21 extending in the front and rear direction, a gate-shaped frame 22 whose lower ends are connected to the pair of left and right lower frames 21, and an upper frame 23 provided on the gate-shaped frame 22. And a lifting device 24 movable in the front, rear, left, and right directions with respect to the upper frame 23. The pair of left and right lower frames 21 is provided with wheels capable of rolling on the existing floor slab 5. In the portal frame 22 and between the pair of left and right lower frames 21, the above-described carrier of the transport vehicle can be disposed.

本実施形態では、1つの施工領域ごとに(すなわち施工領域A〜Aの各々で)、前述のステップS11〜S13を3回実施することで、1つの施工領域の橋軸方向の長さ分である6m分の既設床版5の撤去作業を行う。
以上のようにして、図4のステップS1にて、既設床版5の撤去作業が実施される。
In this embodiment, each one construction region (i.e. in each of the construction area A 1 to A n), by three times the steps S11~S13 described above, the length of the bridge axis direction of one construction region We carry out removal work of the existing floor version 5 for 6m which is the same.
As described above, at step S1 in FIG. 4, the work of removing the existing floor plate 5 is performed.

次に、図4のステップS2にて実施される新設床版7の配置準備作業について、前述の図1〜図4に加えて、図6及び図10A〜図10Cを用いて説明する。
図6は、本実施形態における新設床版7の配置準備方法を示すフローチャートである。図10A〜図10Cは、本実施形態における新設床版7の配置準備方法を示す図である。ここで、図10A〜図10Cは、後述する図11AのI−I断面に対応している。
Next, the placement preparation work of the new installation floor plate 7 performed in step S2 of FIG. 4 will be described using FIGS. 6 and 10A to 10C in addition to the above-described FIGS. 1 to 4.
FIG. 6 is a flow chart showing a method of preparing for placement of the new installation floor plate 7 in the present embodiment. FIG. 10A to FIG. 10C are diagrams showing a method of preparing the arrangement of the newly installed floor slab 7 in the present embodiment. Here, FIGS. 10A to 10C correspond to the I-I cross section of FIG. 11A described later.

図6に示すように、まず、ステップS21では、既設床版5(床版片5a)が撤去されて外部に露出している橋桁4の上面4a(詳しくは、図10Aに示す橋桁4の上フランジ4fの上面4a)のケレン作業を実施する。ここで、ケレン作業は、橋桁4の上面4aに残留しているコンクリート片などを除去することを含み得る。   As shown in FIG. 6, first, in step S21, the upper surface 4a of the bridge girder 4 with the existing floor slab 5 (floor piece 5a) removed and exposed to the outside (more specifically, on the bridge girder 4 shown in FIG. The squeezing operation of the upper surface 4a) of the flange 4f is performed. Here, the kerening work may include removing concrete pieces and the like remaining on the upper surface 4 a of the bridge girder 4.

次に、ステップS22では、ケレン作業が実施された橋桁4の上フランジ4fの左右両側部に、例えばゴム製のフランジシール60を設置する(図10B参照)。フランジシール60は、橋軸方向に延びる板状である。このフランジシール60は、前述のステップS103にて新設床版7と橋桁4とを固定して一体化する際に新設床版7と橋桁4との間の空間9(図11B参照)内に打設されるモルタルが空間9外に漏れ出ることを防ぐためのものである。   Next, in step S22, flange seals 60 made of rubber, for example, are installed on the left and right sides of the upper flange 4f of the bridge girder 4 on which the squeezing operation is performed (see FIG. 10B). The flange seal 60 is a plate extending in the bridge axial direction. The flange seal 60 is inserted into the space 9 (see FIG. 11B) between the new floor plate 7 and the bridge girder 4 when the new floor plate 7 and the bridge girder 4 are fixed and integrated in step S103 described above. It is for preventing the mortar provided from leaking out of the space 9.

次に、ステップS23では、新設床版7の配置高さを調整するための複数の高さ調整材70を、橋桁4の上フランジ4fの上面4aに設置する(図10C参照)。高さ調整材70は、上下方向に伸縮自在であることが好ましい。高さ調整材70は、例えば、上下方向に伸縮自在な手動式のジャッキであり得る。又は、高さ調整材70は、それ自体の高さが決定された後に変形不可能な剛性を有する部材(スペーサー)により構成されてもよい。複数の高さ調整材70は、橋軸方向に互いに間隔を空けて、橋軸方向に並んでいる。   Next, in step S23, a plurality of height adjustment members 70 for adjusting the arrangement height of the newly installed floor slab 7 are installed on the upper surface 4a of the upper flange 4f of the bridge girder 4 (see FIG. 10C). It is preferable that the height adjustment member 70 be stretchable in the vertical direction. The height adjustment member 70 may be, for example, a manual jack that can extend and contract in the vertical direction. Alternatively, the height adjustment member 70 may be configured by a member (spacer) having rigidity that can not be deformed after its own height is determined. The plurality of height adjustment members 70 are arranged in the bridge axial direction at intervals in the bridge axial direction.

尚、高さ調整材70については、前述のステップS3及び後述のステップS31にて新設床版7が橋桁4上に配置されたときに、計画された新設床版7の配置高さとなるように、新設床版7の橋桁4上への配置に先立って、高さ調整材70自体の高さ調整が行われ得る。高さ調整材70自体の高さ調整は、ステップS23にて橋桁4の上フランジ4fの上面4aに設置する前に行ってもよく、また、橋桁4の上フランジ4fの上面4aに設置した後に行ってもよい。   As for the height adjusting member 70, when the newly installed floor slab 7 is disposed on the bridge girder 4 in step S3 described above and step S31 described later, the planned height of the newly installed floor slab 7 is obtained. Prior to the placement of the new floor slab 7 on the bridge girder 4, height adjustment of the height adjustment member 70 itself may be performed. The height adjustment of the height adjusting member 70 itself may be performed before installing on the upper surface 4a of the upper flange 4f of the bridge girder 4 in step S23, or after installing on the upper surface 4a of the upper flange 4f of the bridge girder 4 You may go.

本実施形態では、フランジシール60の設置後に高さ調整材70の設置を行っているが、この他、フランジシール60の設置に先立って高さ調整材70の設置を行ってもよい。すなわち、ステップS22とステップS23とを入れ替えてもよい。
以上のようにして、図4のステップS2にて、新設床版7の配置準備作業が実施される。
In the present embodiment, the height adjustment material 70 is installed after the installation of the flange seal 60. Alternatively, the height adjustment material 70 may be installed prior to the installation of the flange seal 60. That is, step S22 and step S23 may be interchanged.
As described above, in step S2 of FIG. 4, preparation work for placing the newly installed floor plate 7 is performed.

次に、図4のステップS3にて実施される新設床版7の配置作業について、前述の図1〜図4に加えて、図7、図11A、図11B及び図12を用いて説明する。
図7は、本実施形態における新設床版7の配置方法を示すフローチャートである。図11A及び図11Bは、本実施形態における新設床版7の配置方法を示す図である。ここで、図11Bは、図11AのI−I断面に対応している。図12は、スタッドジベル80の設置方法を示す図である。
Next, the placement work of the new installation floor plate 7 performed in step S3 of FIG. 4 will be described using FIGS. 7, 11A, 11B, and 12 in addition to the above-described FIGS. 1 to 4.
FIG. 7 is a flowchart showing a method of arranging the new installation floor plate 7 in the present embodiment. 11A and 11B are diagrams showing a method of arranging the new installation floor plate 7 in the present embodiment. Here, FIG. 11B corresponds to the I-I cross section of FIG. 11A. FIG. 12 is a view showing a method of installing the stud dowel 80. As shown in FIG.

図7に示すように、まず、ステップS31では、橋桁4の上フランジ4fの上面4aに設置された複数の高さ調整材70に、新設床版7を載置する(図11A及び図11B参照)。これにより、橋桁4の上フランジ4fの上面4aと、新設床版7の下面7bと、フランジシール60とによって囲まれた空間9が形成される。   As shown in FIG. 7, first, in step S31, the newly installed floor slab 7 is placed on a plurality of height adjustment members 70 installed on the upper surface 4a of the upper flange 4f of the bridge girder 4 (see FIGS. 11A and 11B). ). Thus, a space 9 surrounded by the upper surface 4 a of the upper flange 4 f of the bridge girder 4, the lower surface 7 b of the new floor slab 7, and the flange seal 60 is formed.

新設床版7は、プレキャストコンクリート製である(すなわち、PCa床版である)。新設床版7は、橋軸方向を短辺とし、橋軸直角方向を長辺とする、略矩形状である。本実施形態では、新設床版7の橋軸方向の長さが2mであるが、新設床版7の橋軸方向の長さは2mに限らない。
新設床版7には、橋桁4の上フランジ4fの上面4aに相対するように、複数の貫通孔7aが形成されている。
The new floor version 7 is made of precast concrete (ie, it is a PCa floor version). The newly installed floor slab 7 has a substantially rectangular shape, with the bridge axis direction as the short side and the bridge axis perpendicular direction as the long side. In the present embodiment, the length in the bridge axis direction of the newly installed floor version 7 is 2 m, but the length in the bridge axis direction of the newly installed floor version 7 is not limited to 2 m.
A plurality of through holes 7 a are formed in the new installation floor plate 7 so as to be opposed to the upper surface 4 a of the upper flange 4 f of the bridge girder 4.

ステップS31における新設床版7の配置作業(載置作業)には、図2に示すクレーン装置30が用いられる。クレーン装置30は、前後方向に延びる左右一対の下部フレーム31と、左右一対の下部フレーム31に下端が連結された門型フレーム32と、門型フレーム32の上部に設けられた上部フレーム33と、上部フレーム33に対して前後左右に移動可能な吊上装置34と、を含んで構成されている。左右一対の下部フレーム31には、橋桁4上に載置された新設床版7上を転動可能な車輪が設けられている。門型フレーム32内、及び、左右一対の下部フレーム31間を、搬送台車40が走行可能である。   The crane apparatus 30 shown in FIG. 2 is used for the arrangement | positioning operation | work (mounting operation | work) of the newly installed floor slab 7 in step S31. The crane device 30 includes a pair of left and right lower frames 31 extending in the front and rear direction, a gate-shaped frame 32 whose lower ends are connected to the pair of left and right lower frames 31, and an upper frame 33 provided on the top of the gate-shaped frame 32; And a lifting device 34 movable in the front, rear, left, and right directions with respect to the upper frame 33. The left and right lower frames 31 are provided with wheels capable of rolling on the new floor slab 7 placed on the bridge girder 4. The transport carriage 40 can travel in the portal frame 32 and between the pair of left and right lower frames 31.

クレーン装置30によって吊り上げられる予定の新設床版7は、搬送台車40によって、橋台2b(図1参照)に隣接する地面上からクレーン装置30まで搬送される。尚、橋桁4上に載置されて隣り合う新設床版7同士の間の隙間を上から覆うように鉄板などの板状部材を敷くことで、搬送台車40の走行安定性を向上させてもよい。搬送台車40は、自走式であってもよい。搬送台車40は、ゴム製のタイヤが使用された車輪を含んで構成されることが好ましい。   The new floor slab 7 scheduled to be lifted by the crane device 30 is transported by the transport carriage 40 from the ground adjacent to the abutment 2 b (see FIG. 1) to the crane device 30. The running stability of the transport carriage 40 can be improved by laying a plate-like member such as an iron plate so as to cover from above the gap between the newly installed floor slabs 7 mounted on the bridge girder 4 and adjacent to each other. Good. The transport carriage 40 may be self-propelled. The transport carriage 40 preferably includes a wheel on which a rubber tire is used.

橋台2bに隣接する地面上では、クレーン装置30まで搬送台車40によって搬送される予定の新設床版7が、図示しない運搬車両から、この運搬車両より重量が軽い搬送台車40に荷卸しされる。この荷卸し作業には、前述のクレーン装置20,30と同様の構成のクレーン装置を用いてもよい。
従って、本実施形態では、新設床版7を、床版架け替え施工進行方向後方から施工領域A〜Aに搬入する。
On the ground adjacent to the abutment 2b, the new floor slab 7 scheduled to be transported by the transport carriage 40 to the crane device 30 is unloaded from the transport vehicle (not shown) to the transport carriage 40 whose weight is lighter than that transport vehicle. For this unloading operation, a crane device having the same configuration as the above-described crane devices 20 and 30 may be used.
Accordingly, in the present embodiment, a new deck 7, carries the slab hung replacement construction traveling direction rearward construction area A 1 to A n.

尚、本実施形態では、搬送台車40上からクレーン装置30によって新設床版7を吊り上げた後に、クレーン装置30によって新設床版7の長辺を橋軸直角方向に向けるように新設床版7の向きを変更する(すなわち90°回転させる)。   In the present embodiment, after the new floor slab 7 is lifted by the crane device 30 from above the transfer carriage 40, the long edge of the new floor slab 7 is directed by the crane device 30 in the direction perpendicular to the bridge axis. Change the orientation (ie rotate 90 °).

本実施形態では、1つの施工領域ごとに(すなわち施工領域A〜Aの各々で)、前述のステップS31を3回実施することで、1つの施工領域の橋軸方向の長さ分である6m分(つまり3枚)の新設床版7の配置作業を行う。 In this embodiment, each one construction region (i.e. in each of the construction area A 1 to A n), by three times the step S31 described above, the bridge axis direction of one construction region length fraction Perform placement work of a new floor 7 for a certain 6m (ie 3 pieces).

次に、図7のステップS32では、図12に示すように、複数のスタッドジベル80を、新設床版7の貫通孔7a内に位置するように、橋桁4の上フランジ4fの上面4aに溶接固定する。尚、ステップS32のスタッドジベル80の設置作業の途中で搬送台車40が通過する場合には、搬送台車40の通過時にスタッドジベル80の設置作業を中断する。
以上のようにして、図4のステップS3にて、新設床版7の配置作業が実施される。
Next, in step S32 of FIG. 7, as shown in FIG. 12, a plurality of stud dowels 80 are welded to the upper surface 4a of the upper flange 4f of the bridge girder 4 so as to be positioned within the through holes 7a of the new floor slab 7. Fix it. When the transport carriage 40 passes in the middle of the installation work of the stud dowel 80 in step S32, the installation work of the stud dowel 80 is interrupted when the transport carriage 40 passes.
As described above, in step S3 of FIG. 4, the placement work of the newly installed floor plate 7 is performed.

図2に示す、ある時刻での施工状態では、施工領域Ak+1にクレーン装置20が位置する。施工領域Ak+1の後方に位置する施工領域Aでは、前述のステップS1(ステップS11〜S13)に示した作業が実施されている。施工領域Aの後方に位置する施工領域Ak−1では、前述のステップS21に示した作業が実施されている。施工領域Ak−1の後方に位置する施工領域Ak−2では、前述のステップS22に示した作業が実施されている。施工領域Ak−2の後方に位置する施工領域Ak−3では、前述のステップS23に示した作業が実施されている。施工領域Ak−3の後方に位置する施工領域Ak−4では、前述のステップS31に示した作業が実施されている。施工領域Ak−4の後方に位置する施工領域Ak−5にはクレーン装置30が位置する。施工領域Ak−5の後方に位置する施工領域Ak−6では、前述のステップS32に示した作業が実施されている。尚、図2に示す符号「α」は、前述のステップS1〜S3(ステップS11〜S32)の途中で作業を休止していることを示す。 In a construction state at a certain time shown in FIG. 2, the crane device 20 is located in the construction area Ak + 1 . In construction area A k located behind the construction area A k + 1, is performed tasks listed in step S1 described above (step S11 to S13). In construction area A k-1 located behind the construction area A k, which is implemented work shown in step S21 described above. In the construction area Ak-2 located behind the construction area Ak-1 , the work shown in step S22 described above is performed. In the construction area Ak-3 located behind the construction area Ak-2 , the work shown in step S23 described above is performed. In construction area A k-4 located behind the construction area A k-3, is performed work shown in step S31 described above. The crane apparatus 30 is located in the construction area Ak-5 located behind the construction area Ak-4 . In the construction area Ak-6 located behind the construction area Ak-5 , the work shown in step S32 described above is performed. In addition, the code | symbol "(alpha)" shown in FIG. 2 shows having stopped operation | work in the middle of above-mentioned step S1-S3 (step S11-S32).

本実施形態では、ステップS1の作業が行われている施工領域(例えば、図2に示す施工領域A)からステップS32の作業が行われている施工領域(例えば、図2に示す施工領域Ak−6)までを覆うように、仮設テント10が設けられている。それゆえ、ステップS21でのケレン作業や、ステップS32での溶接作業が、仮設テント10内で実施される。尚、仮設テント10によって覆われる施工領域は、図2に示したものに限らない。 In this embodiment, a construction area (for example, construction area A k shown in FIG. 2) from the construction area (for example, construction area Ak shown in FIG. 2) in which the operation of step S1 is performed A temporary tent 10 is provided so as to cover up to k-6 ). Therefore, the kelen work in step S21 and the welding work in step S32 are performed in the temporary tent 10. In addition, the construction area | region covered by the temporary installation tent 10 is not restricted to what was shown in FIG.

このようにして、本実施形態では、床版架け替え施工進行方向において、前側の施工領域と、この施工領域より後方の施工領域とにて、互いに異なる作業工程を並行して(すなわち同時に)実施可能である。
また、本実施形態では、床版架け替え施工進行方向において、前側の施工領域から後側の施工領域に向かうほど(例えば、図2に示す施工領域Aから施工領域Ak−6に向かうほど)、後段の作業工程となるように(すなわちステップS32に近づくように)、複数段の作業工程(ステップS1〜S32)を並行して(すなわち同時に)実施可能である。
In this manner, in the present embodiment, different work processes are performed in parallel (that is, simultaneously) in the construction area on the front side and the construction area behind the construction area in the direction of progress of floor slab replacement construction It is possible.
Further, in the present embodiment, in the direction of progress of floor slab replacement construction, as it goes from the front construction area to the rear construction area (for example, from the construction area Ak to the construction area Ak-6 shown in FIG. ), It is possible to perform a plurality of stages of work processes (steps S1 to S32) in parallel (that is, simultaneously) so as to be a work process of the latter stage (that is, approach step S32).

本実施形態では、図2に示すように、床版架け替え施工進行方向において、クレーン装置30の前方にクレーン装置20が位置している。   In the present embodiment, as shown in FIG. 2, the crane device 20 is positioned in front of the crane device 30 in the direction of progress of floor slab replacement construction.

本実施形態では、床版架け替え施工が進むのに追従して、仮設テント10及びクレーン装置20,30が前進する。ゆえに、複数段の作業工程(ステップS1〜S32)を並行して(すなわち同時に)実施可能な床版架け替えシステムも前進する。ここで、この床版架け替えシステムは仮設テント10及びクレーン装置20,30を含む。   In the present embodiment, the temporary tent 10 and the crane devices 20 and 30 move forward, following the progress of the floor plate rebuilding construction. Therefore, a floor-plate rebuilding system capable of carrying out multiple stages of work processes (steps S1 to S32) in parallel (that is, simultaneously) also advances. Here, the floor plate rebuilding system includes a temporary tent 10 and crane devices 20 and 30.

図13は、本実施形態における時刻t=t1〜t10と施工領域A〜Aの各々の作業工程との関係を示す図である。図14は、本実施形態における時刻t=t1〜t15と施工領域A〜Aの各々の作業工程との関係を示す図である。 Figure 13 is a diagram showing the relationship between each of the working processes of the time t = T 1 -T 10 in this embodiment construction area A 1 to A 9. Figure 14 is a diagram showing the relationship between each of the working processes of the time t = t1~t15 in this embodiment construction area A 1 to A 8.

尚、図13及び図14に示す符号「α」は、前述の図2と同様に、前述のステップS1〜S3(ステップS11〜S32)の途中で作業を休止していることを示す。   Note that the symbol “α” shown in FIGS. 13 and 14 indicates that the work is paused in the middle of steps S1 to S3 (steps S11 to S32) described above, as in FIG. 2 described above.

また、前述の時刻t1〜t2間の時間,時刻t2〜t3間の時間,・・・,時刻t13〜t14間の時間,時刻t14〜t15間の時間は、それぞれ、同じ時間(本実施形態では1.2時間とするが、これに限らない)である。また、1つの施工領域(すなわち施工領域A〜Aの各々)について、ステップS1,S21,S22,S23,S31,S32の作業工程時間が同じである。この作業工程時間の設定に際して、ステップS1,S21,S22,S23,S31,S32のうち、どの作業工程がクリティカルパスになっているかが考慮され得る。 Further, the time between time t1 and time t2, the time between time t2 and time t3, ..., the time between time t13 and time t14, and the time between time t14 and time t14 are the same time (in the present embodiment, respectively). 1.2 hours, but not limited to this). Further, for one construction region (i.e. each of the construction area A 1 to A n), step S1, S21, S22, S23, S31, the working process time S32 is the same. When setting the work process time, it can be considered which work process is a critical path among steps S1, S21, S22, S23, S31, and S32.

図13及び図14に示すように、本実施形態では、時刻t1〜t13の間で、施工領域A〜Aでの床版架け替え(既設床版5の撤去と、これに替わる新設床版7の配置)が完了する。 As shown in FIGS. 13 and 14, in this embodiment, between the time T1 to T13, and removal of the deck hung replacement (existing deck 5 in the construction area A 1 to A 6, new floor in place to Arrangement of version 7 is completed.

この点、図15は、従来の床版架け替え方法の一例における時刻t1〜t13と施工領域A,Aの各々の作業工程との関係を示している。図15は、施工領域Aで既設床版5の撤去と、これに替わる新設床版7の配置を行った後に、施工領域Aで既設床版5の撤去と、これに替わる新設床版7の配置を行うと、時刻t1〜t13の作業時間がかかることを示している。 In this respect, FIG. 15 shows the relationship between time t1 to t13 and each operation process of the construction areas A 1 and A 2 in an example of the conventional floor slab rebuilding method. Figure 15 is a removal of construction area A 1 in the existing slab 5, after the placement of the new floor plate 7 an alternative thereto, the removal of existing deck 5 in the construction area A 2, new deck alternative thereto The arrangement of 7 indicates that it takes time to work at times t1 to t13.

従って、図13〜図15の図示から明らかなように、本実施形態の床版架け替え方法を用いると、従来の床版架け替え方法に比べてはるかに迅速に床版架け替え施工を進めることができる。   Therefore, as is apparent from the illustrations in FIGS. 13 to 15, when the floor plate reversion method of the present embodiment is used, the floor plate reversion construction can be advanced more quickly than in the conventional floor plate reversion method. Can.

前述の図3のステップS103では、橋桁4上に配置された新設床版7の貫通孔7aから空間9内(図11B参照)にモルタルを注入・打設することで、このモルタルとスタッドジベル80(図12参照)とにより、新設床版7と橋桁4とが固定されて一体化される。また、前述の図3のステップS103では、橋軸方向で隣り合う新設床版7同士の間の間詰部(図示せず)にて鉄筋コンクリート工が実施されることで、これら新設床版7同士が固定されて一体化される。   At step S103 in FIG. 3 described above, the mortar and stud dovetail 80 are injected and poured into the space 9 (see FIG. 11B) from the through holes 7a of the new floor slab 7 disposed on the bridge girder 4. The new floor plate 7 and the bridge girder 4 are fixed and integrated by (see FIG. 12). Further, in step S103 of FIG. 3 described above, the reinforced concrete construction is carried out in the space between the new floor slabs 7 adjacent to each other in the bridge axis direction (not shown), so that these new floor slabs 7 Is fixed and integrated.

本実施形態によれば、床版架け替え方法は、構造物(橋梁1)を構造物(橋梁1)の軸方向に複数の施工領域A〜Aに区分けすることにより、複数の施工領域A〜Aを設定することを含む。施工領域A〜Aは、各々が、既設床版5の撤去から新設床版7の配置に至る複数段の作業工程(ステップS1〜S3(S11〜S32))を有する。構造物(橋梁1)の軸方向(橋軸方向)に沿う床版架け替え施工進行方向において、床版架け替え施工進行方向前側の施工領域と、この施工領域より床版架け替え施工進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する(図2、図13及び図14参照)。これにより、床版架け替え施工の進捗状況が異なる複数の施工領域にて、並行して(すなわち同時に)施工を進めることができるので、既設床版5から新設床版7への架け替えを効率良く(換言すれば短期間で)行うことができる(図13〜図15参照)。 According to the present embodiment, the floor slab rebuilding method divides a structure (bridge 1) into a plurality of construction areas A 1 to A n in the axial direction of the structure (bridge 1) to form a plurality of construction areas It includes setting the a 1 to a n. Construction regions A 1 to A n are each has a work process of a plurality of stages leading to the arrangement of the new deck 7 from removal of the existing slab 5 (step S1~S3 (S11~S32)). In the floor plan reconstruction construction progress direction along the axial direction (bridge axis direction) of the structure (bridge 1), the construction zone on the front side of the floor slab reconstruction work progress direction and the floor slab reconstruction construction direction backward from this construction area Work steps different from each other are performed in parallel (see FIGS. 2, 13 and 14). In this manner, the construction can be carried out in parallel (that is, simultaneously) in a plurality of construction areas where the progress of the floor slab reconstruction work is different, so that the reconstruction from the existing floor slab 5 to the new floor slab 7 is efficient. It can be done well (in other words, in a short period of time) (see FIGS. 13-15).

また本実施形態によれば、床版架け替え施工進行方向前側の施工領域から床版架け替え施工進行方向後側の施工領域に向かうほど後段の作業工程となるように(例えば、図2に示すように、施工領域Aから施工領域Ak−6に向かうほど、ステップS32に近づくように)、複数段の作業工程を並行して実施する(図2、図13及び図14参照)。これにより、床版架け替え施工進行方向に沿って、各作業工程を継続しつつ前進させることができるので、各作業工程の休止時間(作業待ち時間)の発生を抑制でき、ひいては、床版架け替え施工を効率良く行うことができる。 Further, according to the present embodiment, the work process in the latter stage is performed from the construction area on the front side of the floor slab replacement construction direction toward the construction area on the rear side of the floor slab replacement construction direction (for example, as shown in FIG. 2) as such, as directed from the construction area a k in the construction area a k-6, so as to approach the step S32), and performed in parallel working processes of a plurality of stages (see Fig. 2, 13 and 14). Thereby, since it can be made to advance while continuing each work process along the floor slab rebuilding construction advancing direction, generation | occurrence | production of the idle time (work waiting time) of each work process can be suppressed, and, in addition, the floor slab construction Replacement construction can be performed efficiently.

また本実施形態によれば、撤去された既設床版5(床版片5a)を施工領域A〜Aから床版架け替え施工進行方向前方に搬出し、新設床版7を施工領域A〜Aに床版架け替え施工進行方向後方から搬入する。これにより、既設床版5(床版片5a)の搬出作業と新設床版7の搬入作業とが錯綜することを抑制することができる。 According to the present embodiment, dismantled unloaded existing deck 5 (slab pieces 5a) from construction areas A 1 to A n in the construction ahead of the vehicle replacement bridged deck, applying a new floor plate 7 area A From 1 to A n , carry over from the back of the floor plate reconstruction work progress direction. Thereby, it can suppress that the carrying out operation of the existing floor slab 5 (floor piece 5a) and the carrying in operation of the newly installed floor slab 7 are mixed.

また本実施形態によれば、各施工領域A〜Aがそれぞれ有する複数段の作業工程は、施工領域の既設床版5の撤去作業を実施する第1作業工程(ステップS1)と、既設床版5が撤去された施工領域に新設床版7を配置するための準備作業を実施する第2作業工程(ステップS2)と、この準備作業が実施された施工領域に新設床版7を配置する第3作業工程(ステップS3)と、を含む。ゆえに、新設床版7の配置に先立って新設床版7の配置のための様々な準備を行うことで、新設床版7の配置を円滑に行うことができる。 Further, according to the present embodiment, the plurality of stages of work processes included in each of the construction areas A 1 to A n are the first work process (step S1) for carrying out the work of removing the existing floor slab 5 in the construction area; The second work process (step S2) for carrying out the preparation work for placing the new floor slab 7 in the construction area from which the floor slab 5 has been removed and the new construction floor 7 placed in the construction area for which the preparation work was carried out And a third operation process (step S3). Therefore, by performing various preparations for the placement of the new installation 7 before the placement of the new installation 7, the placement of the new installation 7 can be smoothly performed.

また本実施形態によれば、第2作業工程(ステップS2)は、第3作業工程(ステップS3)にて施工領域に配置される新設床版7の配置高さを調整するための高さ調整材70を橋梁1の橋桁4の上面4aに設けること(ステップS23)を含む。これにより、ステップS31(ステップS3)にて、新設床版7を、計画の配置高さで容易に施工領域に配置することができる。   Further, according to the present embodiment, the second operation process (step S2) is a height adjustment for adjusting the arrangement height of the newly installed floor slab 7 disposed in the construction area in the third operation process (step S3). Providing the members 70 on the upper surface 4a of the bridge girder 4 of the bridge 1 (step S23). Thereby, in step S31 (step S3), the newly installed floor slab 7 can be easily arranged in the construction area at the planned arrangement height.

また本実施形態によれば、第2作業工程(ステップS2)は、橋梁1の橋桁4の上面4aに対してケレン作業を実施すること(ステップS21)を含む。このケレン作業は、仮設テント10内で実施される。それゆえ、仮設テント10が雨除けとして機能し得るので、雨天でもケレン作業を実施することができる。また、ケレン作業で発生する粉じんが仮設テント10内に留まり得るので、当該粉じんの外部への飛散を抑制することができる。   Further, according to the present embodiment, the second operation process (step S2) includes carrying out the Kering operation on the upper surface 4a of the bridge girder 4 of the bridge 1 (step S21). This kelen work is carried out in the temporary tent 10. Therefore, since the temporary tent 10 can function as a rain protection, it is possible to carry out the kelen work even in rainy weather. In addition, since dust generated in the kelen work can stay in the temporary tent 10, scattering of the dust to the outside can be suppressed.

また本実施形態によれば、施工領域A〜Aの各々が有する複数段の作業工程のうち、溶接作業を含む作業工程(例えばステップS32)では、仮設テント10内で溶接作業が実施される。それゆえ、仮設テント10が雨除けとして機能し得るので、雨天でも溶接作業を実施することができる。 According to the present embodiment, among the working process of the plurality of stages each having the construction area A 1 to A n, the working process including welding operation (e.g., step S32), the welding operation in the tents 10 is performed Ru. Therefore, since the temporary tent 10 can function as a rain guard, the welding operation can be performed even in rainy weather.

また本実施形態によれば、新設床版7がプレキャストコンクリート製である。ゆえに、床版架け替えの施工現場での新設床版7の設置作業を簡素化することができる。   Further, according to the present embodiment, the newly installed floor slab 7 is made of precast concrete. Therefore, the installation work of the new floor plate 7 at the construction site of the floor plate rebuilding can be simplified.

また本実施形態によれば、橋梁1の全長にわたって新設床版7の配置が完了した後に、新設床版7と橋梁1の橋桁4とを固定して一体化すると共に、橋梁1の軸方向(橋軸方向)で隣り合う新設床版7同士を固定して一体化する(ステップS103)。これにより、新設床版7と橋桁4との一体化と、隣り合う新設床版7同士の一体化とを、橋梁1の全長にわたってまとめて行うことができるので、これらの一体化作業を短期間で効率良く行うことができる。   Further, according to the present embodiment, after the placement of the new floor slab 7 is completed over the entire length of the bridge 1, the new floor slab 7 and the bridge girder 4 of the bridge 1 are fixed and integrated, and the axial direction of the bridge 1 ( The new floor slabs 7 adjacent to each other in the bridge axis direction are fixed and integrated (step S103). Thereby, integration of the new floor slab 7 and the bridge girder 4 and integration of adjacent new floor slabs 7 can be collectively performed over the entire length of the bridge 1, so these integration work can be performed in a short time. Can be done efficiently.

尚、本実施形態では、橋梁1の全長にわたって新設床版7の配置が完了した後に、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化するが、この他、橋梁1の全長よりも短く、かつ、複数の施工領域を含む所定区間にわたって新設床版7の配置が完了した後に、この所定区間にてまとめて、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化してもよい。   In the present embodiment, after the placement of the new floor 7 is completed over the entire length of the bridge 1, the new floor 7 and the bridge girder 4 are fixed and integrated, and the new floor 7 adjacent to each other in the bridge axis direction is integrated. In addition, after the placement of the new floor slab 7 is completed over a predetermined section including a plurality of construction areas, which is shorter than the entire length of the bridge 1 and fixed together, these are collectively integrated in the predetermined section. The new installation floor 7 and the bridge girder 4 may be fixed and integrated, and the new installation floor 7 adjacent to each other in the bridge axial direction may be fixed and integrated.

図16A及び図16Bは、本発明の第2実施形態における時刻t1〜t19と施工領域A〜A20の各々の作業工程との関係を示す図である。
前述の第1実施形態と異なる点について説明する。
FIG. 16A and FIG. 16B are diagrams showing the relationship between time t1 to t19 and each operation process of construction areas A 1 to A 20 in the second embodiment of the present invention.
Points different from the first embodiment described above will be described.

本実施形態では、前述の第1実施形態に比べて、施工領域A〜Aの各々の橋軸方向の長さを短縮している。本実施形態では、施工領域A〜Aの各々の橋軸方向の長さを、それぞれ2mとしているが、施工領域A〜Aの各々の橋軸方向の長さは2mに限らない。例えば、橋梁1の全長Ltが300mであり、かつ、施工領域A〜Aの各々の橋軸方向の長さが、それぞれ2mである場合には、n=300/2=150となる。 In the present embodiment, the length in the bridge axis direction of each of the construction regions A 1 to A n is shortened as compared with the first embodiment described above. In the present embodiment, the length of each of the bridge axis direction construction areas A 1 to A n, although a 2m respectively, the length of the bridge axis direction of each of the construction area A 1 to A n are not limited to 2m . For example, when the total length Lt of the bridge 1 is 300 m and the length in the direction of the bridge axis of each of the construction areas A 1 to A n is 2 m, n = 300/2 = 150.

また、本実施形態では、前述の時刻t1〜t2間の時間,時刻t2〜t3間の時間,・・・,時刻t17〜t18間の時間,時刻t18〜t19間の時間は、それぞれ、同じ時間(本実施形態では0.4時間とするが、これに限らない)である。   In the present embodiment, the time between the times t1 and t2, the time between the times t2 and t3, ..., the time between the times t17 and t18, and the time between the times t18 and t19 are the same. (It is 0.4 hours in this embodiment, but it is not limited to this).

本実施形態では、1つの施工領域(すなわち施工領域A〜Aの各々)について、ステップS1の作業工程時間が0.4時間であり、ステップS21の作業工程時間が0.8時間(0.4時間×2)であり、ステップS22,S23の作業工程時間が、それぞれ、1.2時間(0.4時間×3)であり、ステップS31の作業工程時間が0.4時間であり、ステップS32の作業工程時間が0.4時間である。 In the present embodiment, the work process time of step S1 is 0.4 hours for one construction area (ie, each of construction areas A 1 to A n ), and the work process time of step S21 is 0.8 hours (0 4 hours × 2), and the operation process time of steps S22 and S23 is 1.2 hours (0.4 hours × 3), and the operation process time of step S31 is 0.4 hours, The work process time of step S32 is 0.4 hours.

本実施形態では、図16A及び図16Bに示すように、各作業工程の特性に応じて、各作業工程の時間配分の最適化と、各作業工程の作業範囲の最適化とを実現することができる。例えば、図16Aの時刻t6〜t7,t9〜t10、及び、図16Bの時刻t12〜t13,t15〜t16,t18〜t19において、ステップS21のケレン作業を休止することにより、仮設テント10内で粉じんが慢性的に発生することを抑制することができる。   In the present embodiment, as shown in FIGS. 16A and 16B, according to the characteristics of each work process, the optimization of the time distribution of each work process and the optimization of the work range of each work process are realized. it can. For example, dusting in the temporary tent 10 can be performed by pausing the work of step S21 at time t6 to t7 and t9 to t10 in FIG. 16A and at time t12 to t13, t15 to t16, and t18 to t19 in FIG. 16B. Can be prevented from developing chronically.

図17は、本発明の第3実施形態における新設床版7の配置方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 17 is a flow chart showing a method of arranging the new installation floor plate 7 in the third embodiment of the present invention.
Points different from the first embodiment described above will be described.

本実施形態では、ステップS103の替わりとして、ステップS32の後に、ステップS33が追加されている。すなわち、本実施形態では、1つの施工領域ごとに(すなわち施工領域A〜Aの各々で)、ステップS32のスタッドジベル80の設置作業を行い、これに続けて、ステップS33にて、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化する。これら一体化作業については、前述の第1実施形態と同様であるので、その説明を省略する。 In the present embodiment, step S33 is added after step S32 as a substitute for step S103. That is, in this embodiment, each one construction region (i.e. in each of the construction area A 1 to A n), perform installation work stud dowels 80 in step S32, followed by this, in step S33, new The floor slab 7 and the bridge girder 4 are fixed and integrated, and the new construction floor slabs 7 adjacent to each other in the bridge axial direction are fixed and integrated. The integration operations are the same as those in the first embodiment described above, and thus the description thereof is omitted.

尚、前述の第2実施形態において、本実施形態と同様に、ステップS103の替わりとして、ステップS32の後に、ステップS33を追加してもよいことは言うまでもない。   In the second embodiment described above, it is needless to say that step S33 may be added after step S32 as a substitute for step S103 as in the present embodiment.

図18は、本発明の第4実施形態における新設床版7の配置準備方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 18 is a flow chart showing a method of preparing the arrangement of the newly installed floor slab 7 in the fourth embodiment of the present invention.
Points different from the first embodiment described above will be described.

本実施形態では、前述のステップS21にて橋桁4の上フランジ4fの上面4aのケレン作業を実施した後に、ステップS24に進み、橋桁4の上フランジ4fの上面4aの形状の測量を実施する。この測量が完了した後に、ステップS22に進み、橋桁4の上フランジ4fの左右両側部に、フランジシール60を設置する。すなわち、本実施形態では、ステップS21とステップS22との間にステップS24が追加されている。   In the present embodiment, after the work of the upper surface 4a of the upper flange 4f of the bridge girder 4 is performed in step S21 described above, the process proceeds to step S24, and the survey of the shape of the upper surface 4a of the upper flange 4f of the bridge girder 4 is performed. After this surveying is completed, the process proceeds to step S22, and flange seals 60 are installed on the left and right sides of the upper flange 4f of the bridge girder 4. That is, in the present embodiment, step S24 is added between step S21 and step S22.

尚、前述の第2及び第3実施形態において、本実施形態と同様に、ステップS21とステップS22との間にステップS24を追加してもよいことは言うまでもない。   It goes without saying that in the second and third embodiments described above, step S24 may be added between step S21 and step S22 as in the present embodiment.

図19は、本発明の第5実施形態における新設床版7の配置方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 19 is a flowchart showing a method of arranging the new installation floor plate 7 in the fifth embodiment of the present invention.
Points different from the first embodiment described above will be described.

本実施形態では、前述のステップS31にて、橋桁4の上フランジ4fの上面4aに設置された複数の高さ調整材70に、新設床版7を載置した後に、ステップS34に進み、新設床版7の高さ調整を実施する。この高さ調整が完了した後に、ステップS32に進み、複数のスタッドジベル80を、新設床版7の貫通孔7a内に位置するように、橋桁4の上フランジ4fの上面4aに溶接固定する。すなわち、本実施形態では、ステップS31とステップS32との間にステップS34が追加されている。   In the present embodiment, after the new installation floor 7 is placed on the plurality of height adjustment members 70 installed on the upper surface 4a of the upper flange 4f of the bridge girder 4 in step S31 described above, the process proceeds to step S34. Adjust the floor plate 7 height. After the height adjustment is completed, the process proceeds to step S 32, and a plurality of stud dowels 80 are welded and fixed to the upper surface 4 a of the upper flange 4 f of the bridge girder 4 so as to be located in the through holes 7 a of the new floor slab 7. That is, in the present embodiment, step S34 is added between step S31 and step S32.

尚、前述の第2〜第4実施形態において、本実施形態と同様に、ステップS31とステップS32との間にステップS34を追加してもよいことは言うまでもない。   It goes without saying that in the second to fourth embodiments described above, step S34 may be added between step S31 and step S32 as in the present embodiment.

図20は、本発明の第6実施形態における新設床版7の配置準備方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 20 is a flow chart showing a method of preparing the arrangement of the newly installed floor slab 7 in the sixth embodiment of the present invention.
Points different from the first embodiment described above will be described.

本実施形態では、新設床版7に複数のインサートが埋め込まれている。各インサートは、新設床版7を上下に貫通する雌ねじ部を有する。この雌ねじ部には、上側に頭部を有するボルトの雄ねじ部が螺合している。このボルトの雄ねじ部の下端部は、新設床版7の下面7bから下方に突出しており、橋桁4の上フランジ4fの上面4aに当接可能である。このボルトの雄ねじ部の、雌ねじ部に対するねじ込み度合いを変化させることで、ボルトの雄ねじ部の下端部が新設床版7の下面7bから下方に突出する突出量が変化し得る。ゆえに、これらインサート及びボルト(以下、「インサート・ボルト」と称する)が、新設床版7の配置高さを調整するための高さ調整材として機能し得る。   In the present embodiment, a plurality of inserts are embedded in the new floor version 7. Each insert has an internal thread that passes through the new floor 7 up and down. An external thread of a bolt having a head on the upper side is screwed into the internal thread. The lower end portion of the male screw portion of the bolt protrudes downward from the lower surface 7 b of the new floor slab 7 and can abut on the upper surface 4 a of the upper flange 4 f of the bridge girder 4. By changing the degree of screwing of the male screw portion of the bolt with respect to the female screw portion, the amount by which the lower end portion of the male screw portion of the bolt protrudes downward from the lower surface 7b of the newly installed floor slab 7 may change. Therefore, these inserts and bolts (hereinafter, referred to as “insert bolts”) can function as height adjusting materials for adjusting the arrangement height of the new floor plate 7.

本実施形態では、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)が、前述のステップS31に先立って、新設床版7に複数設けられている。ゆえに、前述の高さ調整材70が不要となるので、本実施形態では、図20に示すように、前述のステップS23が省略され得る。   In the present embodiment, a plurality of height adjustment members (for example, the above-mentioned insert and bolt) for adjusting the arrangement height of the new installation floor slab 7 are provided on the new installation floor slab 7 prior to the above-mentioned step S31. There is. Therefore, since the above-mentioned height adjustment material 70 becomes unnecessary, in this embodiment, as shown in FIG. 20, above-mentioned step S23 may be omitted.

尚、前述の第2〜第5実施形態において、本実施形態と同様に、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)を、前述のステップS31に先立って新設床版7に複数設ければ、前述の高さ調整材70が不要となるので、ステップS23を省略することができることは言うまでもない。特に、前述の第5実施形態において、本実施形態と同様に、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)を、前述のステップS31に先立って新設床版7に複数設けて、ステップS23を省略した場合には、ステップS34における新設床版7の高さ調整において、これら高さ調整材(例えば、前述のインサート・ボルト)が用いられ得る。   In the second to fifth embodiments described above, as in the present embodiment, the height adjustment material (e.g., the above-mentioned insert and bolt) for adjusting the arrangement height of the newly installed floor slab 7 is the same as that described above. It is needless to say that step S23 can be omitted because the height adjustment member 70 described above becomes unnecessary if a plurality of pieces are provided on the newly installed floor plate 7 prior to step S31. In particular, in the fifth embodiment described above, as in the present embodiment, the height adjustment material (for example, the above-mentioned insert and bolt) for adjusting the arrangement height of the new installation floor slab 7 is added to the above-mentioned step S31. If a plurality of new floor slabs 7 are provided in advance and step S23 is omitted, the height adjustment material (for example, the above-mentioned insert and bolt) is used in the height adjustment of the new floor slab 7 in step S34. obtain.

前述の第1実施形態では、複数の作業工程(ステップS1,S21〜S23,S31,S32)の各々に対応するように、作業員及び装置を含む作業チームを個別に編成し(すなわち分業化し)、これら作業チームが作業工程の順序(ステップS1,S21〜S23,S31,S32)に従って橋軸方向に1列に並んでいる(つまり、これら作業チームからなる、床版架け替えのための生産ラインのようなものが形成されている)。そして、これら作業チームが並行して、各々の作業の実施と前方への移動とを繰り返すことで、床版架け替え施工が進む。ゆえに、これら作業チームによる、前方への移動を伴う流れ作業によって、床版架け替え施工が進む。この点は、第1実施形態のみならず、第2〜第6実施形態においても同様である。ここにおいて、各作業チームによる作業、及び、作業チーム同士の連携などに関して、AI(人工知能)技術などを含むICT(情報通信技術)などを活用することにより、床版架け替え施工の一部又は全部のオートメーション化を実現することができ、ひいては、大幅な生産性向上を図ることができる。従って、本発明に係る床版架け替え方法は、ICTなどの活用によるi-Construction(登録商標)化の推進をもって、インフラ維持管理更新における生産性向上を図ると共に、魅力ある職場環境の創生により若年層の建設業への入職者の増加に貢献するための基盤技術の1つとなり得るものであり、産業上の利用可能性は大である。   In the first embodiment described above, work teams including workers and devices are individually organized (ie, divided into divisions) so as to correspond to each of a plurality of work processes (steps S1, S21 to S23, S31, S32). These work teams are arranged in a row in the axial direction of the bridge in accordance with the order of work processes (steps S1, S21 to S23, S31, S32) (that is, a production line for floor plate replacement consisting of these work teams) Something like is formed). Then, these work teams repeat the execution of each work and the forward movement in parallel, and the floor plate replacement construction proceeds. Therefore, the floor plate reversion construction proceeds by the flow work accompanied by forward movement by these work teams. This point is the same not only in the first embodiment but also in the second to sixth embodiments. Here, a part of the floor plate reconstruction work or a construction work by utilizing ICT (information and communication technology) including AI (Artificial Intelligence) technology or the like with regard to work by each work team and cooperation among the work teams, etc. The entire automation can be realized, which in turn can significantly improve productivity. Therefore, the method of rebuilding a floor plate according to the present invention improves productivity in updating infrastructure maintenance and management by promoting i-Construction (registered trademark) by utilization of ICT etc., as well as creating an attractive work environment. It can be one of the basic technologies to contribute to the increase in the number of workers entering construction for young people, and its industrial applicability is great.

前述の第1〜第6実施形態において、例えば、施工領域A〜Aのいずれかにおいて作業が遅れ気味である場合には、作業が遅れ気味である施工領域の作業員の人員を増やすなど、施工の進捗状況に応じて、前述の作業チームの編成(構成)を変化できるようにしてもよい(すなわち、作業チームの編成(構成)に柔軟性を持たせてもよい)。 In the first to sixth embodiments described above, for example, in the case of the slightly delayed work in either the construction area A 1 to A n can increase the personnel workers construction area work is slightly delayed, etc. The arrangement (configuration) of the above-mentioned work team may be changed according to the progress of construction (that is, the arrangement (configuration) of the work team may be flexible).

前述の第1〜第6実施形態では、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが一定(第1及び第3〜第6実施形態では6m、第2実施形態では2m)のまま、床版架け替え施工が進行する例を示したが、この他、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが、時刻に応じて変化してもよい。すなわち、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さに柔軟性を持たせてもよい。既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが時刻に応じて変化する場合には、それに追従するように、後続の作業が適宜調整され得る。   In the first to sixth embodiments described above, the length in the bridge axis direction of the construction area in which the work of removing the existing floor slab 5 (step S1 described above) is performed is constant (the first and third to sixth embodiments In the case of 6 m in the second embodiment and 2 m in the second embodiment, an example is shown in which floor slab replacement construction proceeds, but in addition to this, in the construction area where removal work of the existing floor slab 5 (step S1 described above) is performed The length in the bridge axis direction may change according to the time. That is, flexibility may be given to the length in the bridge axial direction of the construction area where the work of removing the existing floor slab 5 (step S1 described above) is performed. If the length in the bridge axis direction of the construction area where the work of removing the existing floor slab 5 (step S1 described above) is performed changes according to the time, the subsequent work is appropriately adjusted to follow it. obtain.

前述の第1〜第6実施形態では、施工領域A〜Aの各々の橋軸方向の長さが一定(第1及び第3〜第6実施形態では6m、第2実施形態では2m)であるが、この他、施工領域A〜Aの各々の橋軸方向の長さが相互に異なっていてもよい。 In the first to sixth embodiments described above, the length in the bridge axis direction of each of the construction regions A 1 to A n is constant (6 m in the first and third to sixth embodiments, 2 m in the second embodiment) although, this addition, the length of each of the bridge axis direction construction areas a 1 to a n may be different from each other.

前述の第1実施形態では、施工領域A〜Aの各々において、前述のステップS31とステップS32との間に作業休止期間(図2に符号「α」に対応する期間)を設けているが、この作業休止期間は、前述のステップS31とステップS32との間に限らない。これに加えて、又は、これに替えて、前述のステップS1とステップS21との間、ステップS21とステップS22との間、ステップS22とステップS23との間、及び、ステップS23とステップS31との間、のうちの少なくとも1つに、任意に、作業休止期間を設けてもよい。この点は、第1実施形態に限らず、第2〜第6実施形態においても同様である。ここにおいて、作業休止期間は、各作業の作業時間の調整代として機能し得る。 In the above-described first embodiment, in each of the construction areas A 1 to A n , a work pause period (a period corresponding to the symbol “α” in FIG. 2) is provided between the above-described step S31 and step S32. However, this work suspension period is not limited to between the above-mentioned step S31 and step S32. In addition to or in place of this, between the above-described step S1 and step S21, between step S21 and step S22, between step S22 and step S23, and between step S23 and step S31. At least one of the intervals may optionally be provided with a work rest period. This point is the same not only in the first embodiment but also in the second to sixth embodiments. Here, the work suspension period can function as an adjustment fee for the work time of each work.

前述の第1〜第6実施形態では、施工領域A〜Aの各々の作業工程の順序が同じであるが、この他、施工領域A〜Aのうちの一部の作業工程の順序が、前述の第1〜第6実施形態にて説明した作業工程の順序と異なっていてもよい。 In the first to sixth embodiments described above, but the order of each of the working processes in the construction area A 1 to A n are the same, the other part of the working process of the construction area A 1 to A n The order may be different from the order of the work steps described in the first to sixth embodiments described above.

前述の第1〜第6実施形態において、既設床版5は、プレキャストコンクリート製であってもよい(PCa床版であってもよい)。既設床版5は、場所打ちコンクリート製であってもよい。既設床版5は、鋼床版や合成床版などであってもよい。   In the first to sixth embodiments described above, the existing floor slab 5 may be made of precast concrete (may be a PCa floor slab). The existing floor slab 5 may be made of cast-in-place concrete. The existing floor slab 5 may be a steel floor slab, a synthetic floor slab, or the like.

前述の第1〜第6実施形態において、新設床版7は、ハーフプレキャストコンクリート製などの、床版の一部にプレキャストコンクリートが使用される床版であってもよい。新設床版7は、プレストレストコンクリート製であってもよい(PC床版であってもよい)。新設床版7は、鋼床版や合成床版などであってもよい。   In the first to sixth embodiments described above, the new floor slab 7 may be a floor slab made of half-precast concrete or the like, in which precast concrete is used in part of the floor slab. The newly installed floor version 7 may be made of prestressed concrete (may be a PC floor version). The newly installed floor version 7 may be a steel floor version, a synthetic floor version, or the like.

前述の第1〜第6実施形態では、本発明の「構造物」の一例として橋梁を挙げて説明したが、本発明の「構造物」は橋梁に限らない。例えば、本発明の「構造物」が、床版を有するトンネルであってもよい。   In the first to sixth embodiments described above, a bridge is described as an example of the “structure” of the present invention, but the “structure” of the present invention is not limited to the bridge. For example, the "structure" of the present invention may be a tunnel having a floor slab.

図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。   The illustrated embodiments are merely illustrative of the present invention, and in addition to those directly shown by the described embodiments, various improvements and modifications made by those skilled in the art within the scope of the claims can be made. It is needless to say that it is included.

1 橋梁
2a,2b 橋台
3 橋脚
4 橋桁
4a 上面
4f 上フランジ
4w ウェブ
5 既設床版
5a 床版片
5b 切断線
7 新設床版
7a 貫通孔
7b 下面
9 空間
10 仮設テント
20,30 クレーン装置
21,31 下部フレーム
22,32 門型フレーム
23,33 上部フレーム
24,34 吊上装置
40 搬送台車
50a,50b ジャッキ
51 梁部材
52 PC鋼棒
53a,53b 固定部材
60 フランジシール
70 高さ調整材
80 スタッドジベル
〜A〜A 施工領域
1 Bridge 2a, 2b Abutment 3 Pier 4 Bridge 4a Upper surface 4f Upper flange 4w Web 5 Floor plate 5a Floor plate piece 5b Cutting line 7 New floor plate 7a Through hole 7b Lower surface 9 Space 10 Temporary tent 20, 30 Crane device 21, 31 Lower frame 22, 32 portal frame 23, 33 upper frame 24, 34 lifting device 40 transport carriage 50a, 50b jack 51 beam member 52 PC steel rod 53a, 53b fixing member 60 flange seal 70 height adjusting member 80 stud dowel A 1 to A k to A n construction area

Claims (10)

構造物における床版の架け替え方法であって、
前記構造物を前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
各施工領域は、それぞれ、既設床版の撤去から新設床版の配置に至る複数段の作業工程を有し、
前記構造物の軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側の施工領域と、この施工領域より前記進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する、床版架け替え方法。
A method of replacing floor slabs in a structure,
Setting a plurality of construction areas by dividing the structure into a plurality of construction areas in the axial direction of the structure;
Each construction area has a multi-step work process from removal of the existing floor slab to placement of the new floor slab,
In the construction direction of the floor slab rebuilding along the axial direction of the structure, work steps different from each other in the construction area on the front side of the construction direction and in the construction area on the rear side of the construction area from the construction area How to rebuild the floor version.
前記進行方向前側の施工領域から前記進行方向後側の施工領域に向かうほど後段の作業工程となるように、複数段の作業工程を並行して実施する、請求項1に記載の床版架け替え方法。   The floor slab rebuilding according to claim 1, wherein a plurality of stages of work processes are carried out in parallel so as to become a work process of a later stage from the construction area on the front side in the traveling direction toward the construction area on the rear side in the traveling direction. Method. 撤去された既設床版を前記施工領域から前記進行方向前方に搬出し、
新設床版を前記施工領域に前記進行方向後方から搬入する、請求項1又は請求項2に記載の床版架け替え方法。
Carrying out the removed existing floor slab from the construction area forward in the traveling direction,
The floor plate rebuilding method according to claim 1 or 2, wherein a new floor slab is carried into the construction area from the rear in the traveling direction.
各施工領域がそれぞれ有する複数段の作業工程は、
当該施工領域の既設床版の撤去作業を実施する第1作業工程と、
既設床版が撤去された当該施工領域に新設床版を配置するための準備作業を実施する第2作業工程と、
前記準備作業が実施された当該施工領域に新設床版を配置する第3作業工程と、
を含む、請求項1〜請求項3のいずれか1つに記載の床版架け替え方法。
The work processes of multiple stages that each construction area has respectively
A first operation process for removing the existing floor slab in the construction area;
A second operation process for performing a preparatory work for placing a new floor slab in the construction area where the existing floor slab has been removed;
A third operation process of arranging a new floor slab in the construction area in which the preparation work has been performed;
The floor plate rebuilding method according to any one of claims 1 to 3, comprising
前記構造物は橋梁であり、
前記第2作業工程は、前記第3作業工程にて当該施工領域に配置される新設床版の配置高さを調整するための高さ調整材を前記橋梁の橋桁の上面に設けることを含む、請求項4に記載の床版架け替え方法。
The structure is a bridge,
The second operation process includes providing a height adjustment material for adjusting the arrangement height of the new floor slab arranged in the construction area in the third operation process on the upper surface of the bridge girder of the bridge. The floor plate rebuilding method according to claim 4.
前記構造物は橋梁であり、
前記第2作業工程は、前記橋梁の橋桁の上面に対してケレン作業を実施することを含む、請求項4又は請求項5に記載の床版架け替え方法。
The structure is a bridge,
The method of rebuilding a floor slab according to claim 4 or 5, wherein the second operation step includes performing a kerning operation on the upper surface of the bridge girder of the bridge.
仮設テント内で前記ケレン作業が実施される、請求項6に記載の床版架け替え方法。   The floor plate rebuilding method according to claim 6, wherein the kelen work is performed in a temporary tent. 各施工領域がそれぞれ有する複数段の作業工程のうち、溶接作業を含む作業工程では、仮設テント内で前記溶接作業が実施される、請求項1〜請求項7のいずれか1つに記載の床版架け替え方法。   The floor according to any one of claims 1 to 7, wherein in the work process including the welding work among the plurality of work processes each of the construction areas has, the welding work is performed in the temporary tent How to replace the version. 前記構造物は橋梁であり、
前記橋梁の全長にわたって新設床版の配置が完了した後に、新設床版と前記橋梁の橋桁とを固定して一体化すると共に、前記橋梁の軸方向で隣り合う新設床版同士を固定して一体化する、請求項1〜請求項8のいずれか1つに記載の床版架け替え方法。
The structure is a bridge,
After the placement of the new floor is completed over the entire length of the bridge, the new floor and the bridge girder of the bridge are fixed and integrated, and the adjacent new floors in the axial direction of the bridge are fixed and integrated. The floor plate rebuilding method according to any one of claims 1 to 8, wherein
前記新設床版がプレキャストコンクリート製である、請求項1〜請求項9のいずれか1つに記載の床版架け替え方法。   The method for rebuilding a floor slab according to any one of claims 1 to 9, wherein the newly installed floor slab is made of precast concrete.
JP2017202222A 2017-10-18 2017-10-18 How to replace the floor slab Active JP7442256B2 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP2017202222A JP7442256B2 (en) 2017-10-18 2017-10-18 How to replace the floor slab
JP2022001494A JP7148746B2 (en) 2017-10-18 2022-01-07 Floor slab replacement method
JP2023003216A JP2023029610A (en) 2017-10-18 2023-01-12 Slab replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017202222A JP7442256B2 (en) 2017-10-18 2017-10-18 How to replace the floor slab

Related Child Applications (2)

Application Number Title Priority Date Filing Date
JP2022001494A Division JP7148746B2 (en) 2017-10-18 2022-01-07 Floor slab replacement method
JP2023003216A Division JP2023029610A (en) 2017-10-18 2023-01-12 Slab replacement method

Publications (2)

Publication Number Publication Date
JP2019073948A true JP2019073948A (en) 2019-05-16
JP7442256B2 JP7442256B2 (en) 2024-03-04

Family

ID=66545065

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017202222A Active JP7442256B2 (en) 2017-10-18 2017-10-18 How to replace the floor slab

Country Status (1)

Country Link
JP (1) JP7442256B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021017687A (en) * 2019-07-17 2021-02-15 中日本高速道路株式会社 Floor slab replacement method
JP7356373B2 (en) 2020-02-17 2023-10-04 鹿島建設株式会社 Floor slab removal method
JP7384310B1 (en) 2023-06-16 2023-11-21 株式会社Ihi Joint structure, floor slab and floor slab replacement method
JP7466368B2 (en) 2020-04-28 2024-04-12 鹿島建設株式会社 Deck replacement method
JP7483507B2 (en) 2019-06-19 2024-05-15 株式会社大林組 Bridge deck replacement method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011089281A (en) * 2009-10-21 2011-05-06 Taisei Corp Method for rebuilding bridge
JP2015229818A (en) * 2014-06-03 2015-12-21 オリエンタル白石株式会社 Composite structure of steel girder and precast floor slab, and construction method therefor

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011089281A (en) * 2009-10-21 2011-05-06 Taisei Corp Method for rebuilding bridge
JP2015229818A (en) * 2014-06-03 2015-12-21 オリエンタル白石株式会社 Composite structure of steel girder and precast floor slab, and construction method therefor

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
伊藤寛彦 保科和利 栗原悠: "鋼橋のPC床版架設の施工", 第19回土木施工管理技術論文集, JPN6022013539, 2 June 2015 (2015-06-02), JP, pages 13 - 16, ISSN: 0005025208 *
本間修平: "計画工程を維持するために取り組んだ『床版取替』について", 第19回土木施工管理技術論文報告集, JPN6021044029, 2 June 2015 (2015-06-02), JP, pages 53 - 56, ISSN: 0005025207 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7483507B2 (en) 2019-06-19 2024-05-15 株式会社大林組 Bridge deck replacement method
JP2021017687A (en) * 2019-07-17 2021-02-15 中日本高速道路株式会社 Floor slab replacement method
JP7299088B2 (en) 2019-07-17 2023-06-27 中日本高速道路株式会社 Floor slab replacement method
JP7356373B2 (en) 2020-02-17 2023-10-04 鹿島建設株式会社 Floor slab removal method
JP7466368B2 (en) 2020-04-28 2024-04-12 鹿島建設株式会社 Deck replacement method
JP7484439B2 (en) 2020-06-03 2024-05-16 株式会社大林組 Bridge deck replacement method
JP7384310B1 (en) 2023-06-16 2023-11-21 株式会社Ihi Joint structure, floor slab and floor slab replacement method

Also Published As

Publication number Publication date
JP7442256B2 (en) 2024-03-04

Similar Documents

Publication Publication Date Title
JP2019073948A (en) Floor slab reconstruction method
KR101844977B1 (en) Scaffolding frame for tunnel
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
JP2020002563A (en) Deck slab construction method
CN103696437B (en) A kind of construction method of cutting lattice column
JP2015183404A (en) Replacing method for stretching device and structure temporal forming plate
JP7148746B2 (en) Floor slab replacement method
JP2023029610A (en) Slab replacement method
JP5693869B2 (en) Bridge girder construction method
JP5074260B2 (en) Bridge erection method
JP2023101672A (en) Floor slab replacement method
JP6838808B2 (en) Reinforcement structure and method of abutment
CN102454298B (en) Large-sized reinforced concrete construction of frame beam method
CN102839671A (en) Concrete supporting reinforced cage prefabricated assembling technology and construction method
JP2009174185A (en) Method of constructing wide section of tunnel
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP2014134060A (en) Floor slab replacement method
JP2014240559A (en) Repair method for bridge
KR101211689B1 (en) 3-arch tunnel construction method pre-construction center tunnel part
KR20200133128A (en) Removal apparatus of steel reinforcing member for tunnel portal area and construction method therefor
JP2017052160A (en) Method for producing precast concrete floor slab and precast concrete floor slab
JP2021017687A (en) Floor slab replacement method
JP4331005B2 (en) Construction method of precast segment bridge
JP7451391B2 (en) Bridge girder replacement method
JPH06185018A (en) Construction method of concrete bridge and construction device thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200219

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201225

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210302

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210423

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211109

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220107

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220412

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220609

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20221018

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230112

C60 Trial request (containing other claim documents, opposition documents)

Free format text: JAPANESE INTERMEDIATE CODE: C60

Effective date: 20230112

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20230123

C21 Notice of transfer of a case for reconsideration by examiners before appeal proceedings

Free format text: JAPANESE INTERMEDIATE CODE: C21

Effective date: 20230124

A912 Re-examination (zenchi) completed and case transferred to appeal board

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20230407

C211 Notice of termination of reconsideration by examiners before appeal proceedings

Free format text: JAPANESE INTERMEDIATE CODE: C211

Effective date: 20230411

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240220

R150 Certificate of patent or registration of utility model

Ref document number: 7442256

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150