JP2023101672A - Floor slab replacement method - Google Patents

Floor slab replacement method Download PDF

Info

Publication number
JP2023101672A
JP2023101672A JP2023088815A JP2023088815A JP2023101672A JP 2023101672 A JP2023101672 A JP 2023101672A JP 2023088815 A JP2023088815 A JP 2023088815A JP 2023088815 A JP2023088815 A JP 2023088815A JP 2023101672 A JP2023101672 A JP 2023101672A
Authority
JP
Japan
Prior art keywords
floor slab
new
construction area
construction
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2023088815A
Other languages
Japanese (ja)
Inventor
宏之 山中
Hiroyuki Yamanaka
好謙 坂本
Yoshikane Sakamoto
健三 高瀬
Kenzo Takase
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP2023003216A external-priority patent/JP2023029610A/en
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2023088815A priority Critical patent/JP2023101672A/en
Publication of JP2023101672A publication Critical patent/JP2023101672A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

To provide a floor slab replacement method allowing efficient replacement of a floor slab.SOLUTION: A floor slab replacement method has an existing floor slab removing step, a new floor slab arranging preparation step, and a new floor slab arranging step. The existing floor slab removing step includes replacement of floor slab pieces of the existing floor slab. The new floor slab arranging preparation step includes a preparation work for arranging the new floor slab on a bridge girder from which the floor slab pieces are removed. The new floor slab arranging step includes arranging the new floor slab on the bridge girder where the preparation work is done. In the floor slab replacement proceeding direction, from the front side toward the rear side, a first construction region for performing the existing floor slab removing step, a second construction region for performing the new floor slab arranging preparation step, and a third construction region for performing the new floor slab arranging step, are arranged in this order. In the second construction region, from the front side toward the rear side in the proceeding direction, a construction region for performing surface preparation work to an upper face of the bridge girder and a construction region for performing installation work of a height adjusting material/seal to the upper face of the bridge girder are arranged.SELECTED DRAWING: Figure 2

Description

本発明は、橋梁などの構造物を構成する床版の架け替え(既設床版の撤去とこれに替わる新設床版の設置)を行う方法に関する。 The present invention relates to a method for replacing a floor slab that constitutes a structure such as a bridge (removing an existing floor slab and installing a new floor slab to replace it).

橋梁は、例えば、複数の橋脚と、各々が複数の橋脚の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)と、複数の橋桁の上に跨がって配設される床版と、を含んで構成される。床版は、例えば鉄筋コンクリート製である。かかる床版については、長年の使用によるコンクリートの劣化や内部の鉄筋の腐食などの理由で、架け替え(既設床版の撤去と新設床版の設置)が求められる場合がある。 A bridge, for example, includes a plurality of bridge piers, a plurality of bridge girders (H-shaped steel) each extending in the bridge axis direction across the plurality of piers, and a floor slab arranged across the plurality of bridge girders. The floor slab is made of reinforced concrete, for example. Such floor slabs may require replacement (removal of existing floor slabs and installation of new floor slabs) for reasons such as deterioration of concrete and corrosion of internal reinforcing bars due to long-term use.

床版の架け替えに用いられる装置としては、例えば特許文献1に記載の床版架設機が知られている。これは、橋軸方向前後の門型フレームを連結してなる無軌条・自走式の門型構造体と、門型構造体の天井部の下面側に前後方向及び横方向に移動可能に設けられる吊上装置(例えばチェーンブロック)と、を備えている。ここにおいて、新設床版はプレキャストコンクリート製である。 As a device used for replacing floor slabs, for example, a floor slab construction machine described in Patent Document 1 is known. It is equipped with a railless, self-propelled gate-shaped structure formed by connecting front and rear gate-shaped frames in the bridge axis direction, and a lifting device (for example, a chain block) provided on the lower surface of the ceiling of the gate-shaped structure so as to be movable in the longitudinal and lateral directions. Here, the new floor slabs are made of precast concrete.

このような架設機を用いた新設床版の架設作業は、
(1)架設機の後部での新設床版の取込み、すなわち、架設機の後部に位置させた吊上装置による、新設床版の長辺を橋軸方向に向けた状態での、新設床版の吊上げ
(2)吊上装置の前側への移動による、新設床版の架設位置までの移送
(3)新設床版の長辺を橋軸直角方向に向けるように、新設床版の向きの変更(90°回転)
(4)そして、所定位置への設置
という工程で行われる。
また、既設の床版の撤去作業は、入れ替わりで、ほぼ逆の工程で行われる。
Erection work of new floor slabs using such erection machines
(1) Taking in the new floor slab at the rear of the erection machine, that is, lifting the new floor slab by the lifting device located at the rear of the erection machine with the long side of the new slab facing the direction of the bridge axis (2) Transferring the new slab to the installation position by moving the lifting device forward (3) Changing the direction of the new slab so that the long side of the new slab faces the direction perpendicular to the bridge axis (rotate 90°)
(4) Then, it is carried out in a step of installation at a predetermined position.
In addition, the removal work of the existing floor slabs is carried out almost in the reverse order.

特許第3901657号公報Japanese Patent No. 3901657

しかしながら、前述の架設機を用いる床版架け替え方法では、ある施工場所で既設床版の撤去から新設床版の設置までを行った後に前述の架設機が橋軸方向に移動して、次の施工場所で既設床版の撤去から新設床版の設置までを行う。ゆえに、ある施工場所での床版の架け替え作業が完了するまでは次の施工場所で床版の架け替え作業を開始することができず、その結果、橋梁の全長にわたって床版の架け替えを行うのに時間がかかるという問題点があった。 However, in the above-mentioned floor slab replacement method using an erection machine, after removing the existing floor slab and installing a new floor slab at a certain construction site, the above-mentioned erection machine moves in the direction of the bridge axis and removes the existing floor slab and installs a new floor slab at the next construction site. Therefore, until the floor slab replacement work at a certain construction site is completed, the floor slab replacement work cannot be started at the next construction site.

本発明は、このような実状に鑑み、橋梁などの構造物において、効率的な床版の架け替えを行うことができる、床版架け替え方法を提供することを目的とする。 SUMMARY OF THE INVENTION In view of such circumstances, it is an object of the present invention to provide a floor slab replacement method that enables efficient replacement of floor slabs in a structure such as a bridge.

そのため本発明に係る床版架け替え方法の第1態様及び第2態様は、橋桁を有する構造物において、橋桁上に配設される床版を既設床版から新設床版に架け替える方法である。本発明に係る床版架け替え方法の第1態様及び第2態様は、既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、既設床版撤去工程は、既設床版の床版片を撤去することを含み、新設床版配置準備工程は、床版片が撤去された橋桁上に新設床版を配置するための準備作業をすることを含み、新設床版配置工程は、前記準備作業がなされた橋桁上に新設床版を配置することを含む。本発明に係る床版架け替え方法の第1態様において、前記準備作業は、橋桁の上面に対するケレン作業と、橋桁の上面に対する高さ調整材の設置作業と、を含む。本発明に係る床版架け替え方法の第2態様において、前記準備作業は、橋桁の上面に対するケレン作業と、橋桁の上面に対するシールの設置作業と、を含む。本発明に係る床版架け替え方法の第1態様及び第2態様では、構造物の軸方向に複数の施工領域を設定する。本発明に係る床版架け替え方法の第1態様及び第2態様では、軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、既設床版撤去工程を実施する第1施工領域と、新設床版配置準備工程を実施する第2施工領域と、新設床版配置工程を実施する第3施工領域と、が並ぶ。本発明に係る床版架け替え方法の第1態様において、第2施工領域では、前記進行方向前側から後側に向かって順に、ケレン作業を実施するケレン作業施工領域と、高さ調整材の設置作業を実施する高さ調整材設置作業施工領域と、が並ぶ。本発明に係る床版架け替え方法の第2態様において、第2施工領域では、前記進行方向前側から後側に向かって順に、ケレン作業を実施するケレン作業施工領域と、シールの設置作業を実施するシール設置作業施工領域と、が並ぶ。本発明に係る床版架け替え方法の第1態様及び第2態様では、橋桁上の既設の床版上には、既設床版撤去工程で用いられる第1クレーン装置が位置し、橋桁上に新設された床版上には、新設床版配置工程で用いられる第2クレーン装置が位置する。本発明に係る床版架け替え方法の第1態様及び第2態様において、第1施工領域と第2施工領域と第3施工領域とは、床版架け替え施工の進行に伴い前記進行方向に前進する。本発明に係る床版架け替え方法の第1態様及び第2態様では、橋桁上の既設の床版上を走行する運搬車両によって、床版片を、第1クレーン装置から進行方向前方に搬出し、橋桁上に新設された床版上を走行する搬送台車によって、新設床版を、第2クレーン装置に前記進行方向後方から搬入する。 Therefore, the first aspect and the second aspect of the floor slab replacement method according to the present invention are methods for replacing an existing floor slab on a bridge girder with a new floor slab in a structure having a bridge girder. A first aspect and a second aspect of the floor slab replacement method according to the present invention have an existing floor slab removal step, a new floor slab placement preparation step, and a new floor slab placement step, wherein the existing floor slab removal step includes removing floor slab pieces of the existing floor slab, the new floor slab placement preparation step includes preparatory work for placing the new floor slab on the bridge girders from which the floor slab pieces have been removed, and the new floor slab placement step includes the bridge girders on which the preparation work has been performed. including placement of new floor slabs on In the first aspect of the floor slab replacement method according to the present invention, the preparatory work includes shaving work on the upper surface of the bridge girder and installation work of height adjustment members on the upper surface of the bridge girder. In the second aspect of the floor slab replacement method according to the present invention, the preparatory work includes cleaning work on the upper surface of the bridge girder and installation work of seals on the upper surface of the bridge girder. In the first aspect and the second aspect of the floor slab replacement method according to the present invention, a plurality of construction areas are set in the axial direction of the structure. In the first aspect and the second aspect of the floor slab replacement method according to the present invention, the first construction area in which the existing floor slab removal process is performed, the second construction area in which the new floor slab layout preparation process is performed, and the third construction area in which the new floor slab layout process is performed are arranged in order from the front side to the rear side of the movement direction in the floor slab replacement construction progress direction along the axial direction. In the first aspect of the floor slab replacement method according to the present invention, in the second construction area, in order from the front side to the rear side in the traveling direction, a cleaning work execution area for performing cleaning work and a height adjustment material installation work execution area for performing the height adjustment material installation work are arranged. In the second aspect of the floor slab replacement method according to the present invention, in the second construction area, in order from the front side to the rear side in the traveling direction, the cleaning work execution area for performing the cleaning work and the seal installation work The seal installation work construction area for performing the work is lined up. In the first aspect and the second aspect of the floor slab replacement method according to the present invention, the first crane device used in the existing floor slab removal process is positioned on the existing floor slab on the bridge girder, and the second crane device used in the new floor slab placement process is positioned on the floor slab newly installed on the bridge girder. In the first and second aspects of the floor slab replacement method according to the present invention, the first construction area, the second construction area, and the third construction area advance in the direction of movement as the floor slab replacement construction progresses. In the first aspect and the second aspect of the floor slab replacement method according to the present invention, a floor slab piece is transported forward in the traveling direction from the first crane device by a transport vehicle traveling on an existing floor slab on a bridge girder, and a new floor slab is carried into the second crane device from behind in the traveling direction by a carriage traveling on the floor slab newly installed on the bridge girder.

本発明によれば、床版架け替え施工の進捗状況が異なる複数の施工領域にて、並行して(すなわち同時に)施工を進めることができるので、床版の架け替えを効率良く(換言すれば短期間で)行うことができる。 According to the present invention, construction can be carried out in parallel (that is, at the same time) in a plurality of construction areas where the progress of floor slab replacement construction is different, so that floor slab replacement can be performed efficiently (in other words, in a short period of time).

既設の橋梁の一例の側面図Side view of an example of an existing bridge 本発明の第1実施形態における床版架け替え方法の施工状態を示す側面図FIG. 2 is a side view showing a construction state of the floor slab replacement method according to the first embodiment of the present invention. 前記第1実施形態における床版架け替え方法のメインルーチンを示すフローチャートFlowchart showing the main routine of the floor slab replacement method in the first embodiment 前記第1実施形態における床版架け替え方法のサブルーチンを示すフローチャートFlowchart showing a subroutine of the floor slab replacement method in the first embodiment 前記第1実施形態における既設床版の撤去方法を示すフローチャートFlowchart showing the method for removing the existing floor slab in the first embodiment 前記第1実施形態における新設床版の配置準備方法を示すフローチャートFlowchart showing a method of preparing for placement of new floor slabs in the first embodiment 前記第1実施形態における新設床版の配置方法を示すフローチャートFlowchart showing a method for arranging new floor slabs in the first embodiment 前記第1実施形態における既設床版の切断方法を示す図A diagram showing a method for cutting an existing floor slab in the first embodiment. 前記第1実施形態における既設床版の切断方法を示す図A diagram showing a method for cutting an existing floor slab in the first embodiment. 前記第1実施形態における既設床版の縁切り方法を示す図A diagram showing the edge cutting method of the existing floor slab in the first embodiment. 前記第1実施形態における既設床版の縁切り方法を示す図A diagram showing the edge cutting method of the existing floor slab in the first embodiment. 前記第1実施形態における新設床版の配置準備方法を示す図A diagram showing a method of preparing for placement of a new floor slab in the first embodiment. 前記第1実施形態における新設床版の配置準備方法を示す図A diagram showing a method of preparing for placement of a new floor slab in the first embodiment. 前記第1実施形態における新設床版の配置準備方法を示す図A diagram showing a method of preparing for placement of a new floor slab in the first embodiment. 前記第1実施形態における新設床版の配置方法を示す図A diagram showing a method of arranging a new floor slab in the first embodiment. 前記第1実施形態における新設床版の配置方法を示す図A diagram showing a method of arranging a new floor slab in the first embodiment. 前記第1実施形態におけるスタッドジベルの設置方法を示す図The figure which shows the installation method of the stud dowel in the said 1st Embodiment. 前記第1実施形態における時刻と各施工領域の作業工程との関係を示す図A diagram showing the relationship between the time and the work process of each construction area in the first embodiment. 前記第1実施形態における時刻と各施工領域の作業工程との関係を示す図A diagram showing the relationship between the time and the work process of each construction area in the first embodiment. 従来の床版架け替え方法の一例における時刻と各施工領域の作業工程との関係を示す図A diagram showing the relationship between the time and the work process of each construction area in an example of the conventional floor slab replacement method 本発明の第2実施形態における時刻と各施工領域の作業工程との関係を示す図A diagram showing the relationship between the time and the work process of each construction area in the second embodiment of the present invention. 前記第2実施形態における時刻と各施工領域の作業工程との関係を示す図A diagram showing the relationship between the time and the work process of each construction area in the second embodiment. 本発明の第3実施形態における新設床版の配置方法を示すフローチャートFlowchart showing a method for arranging a new floor slab in the third embodiment of the present invention 本発明の第4実施形態における新設床版の配置準備方法を示すフローチャートFlowchart showing a new floor slab placement preparation method according to the fourth embodiment of the present invention 本発明の第5実施形態における新設床版の配置方法を示すフローチャートFlowchart showing a method for arranging new floor slabs according to the fifth embodiment of the present invention 本発明の第6実施形態における新設床版の配置準備方法を示すフローチャートFlowchart showing a method of preparing for placement of new floor slabs according to the sixth embodiment of the present invention

以下、本発明の実施の形態について、図面を参照して説明する。尚、全図中、同一又は相当部分には同一符号を付すこととする。 BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described with reference to the drawings. In all the drawings, the same reference numerals are given to the same or corresponding parts.

図1は、本発明に係る床版架け替え方法が適用され得る既設の橋梁の一例の側面図である。図2は、本発明の第1実施形態における床版架け替え方法の施工状態を示す側面図である。尚、本実施形態では、橋梁における床版架け替え施工の進行方向を前進方向として図1及び図2に示すように前後を規定して、以下説明する。ここで、床版架け替え施工進行方向は、橋梁の橋軸方向に沿う。また、本実施形態では、橋梁の橋軸直角方向を左右方向(横方向)として、以下説明する(図10A~図12参照)。 FIG. 1 is a side view of an example of an existing bridge to which the floor slab replacement method according to the present invention can be applied. FIG. 2 is a side view showing a construction state of the floor slab replacement method according to the first embodiment of the present invention. In the present embodiment, the forward and backward directions are defined as shown in FIGS. 1 and 2, with the progress direction of the floor slab replacement work on the bridge being the forward direction. Here, the progress direction of the floor slab replacement construction is along the axis direction of the bridge. Further, in this embodiment, the direction perpendicular to the axis of the bridge is defined as the lateral direction (horizontal direction) in the following description (see FIGS. 10A to 12).

尚、本実施形態では、本発明の「構造物」(土木構造物)の一例として橋梁を挙げて説明するが、本発明の「構造物」は橋梁に限らない。また、前述の橋軸方向が、本発明の「構造物の軸方向」及び「橋梁の軸方向」に対応し得る。 In this embodiment, a bridge will be described as an example of the "structure" (civil engineering structure) of the present invention, but the "structure" of the present invention is not limited to a bridge. Also, the above-mentioned bridge axial direction can correspond to the "axial direction of the structure" and the "axial direction of the bridge" of the present invention.

本発明の「構造物」の一例である橋梁1は、前後一対の橋台2a,2bと、橋台2a,2b間に間隔を空けて配設された複数の橋脚3と、各々が橋台2a,2b及び複数の橋脚3の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)4と、複数の橋桁4の上に跨がって配設されたコンクリート製の既設床版5と、を含んで構成される。尚、橋台2a,2b及び複数の橋脚3と複数の橋桁4との間には、図示しない支承が介装されている。ここで、本実施形態では、既設床版5が鉄筋コンクリート製である(RC床版である)として以下説明するが、この他、既設床版5は、プレストレストコンクリート製であってもよい(PC床版であってもよい)。また、橋桁4は、後述する図10A~図10Cに示すように、ウェブ4wと、上フランジ4fと、下フランジ(図示せず)とを有している。 A bridge 1, which is an example of the "structure" of the present invention, includes a pair of front and rear abutments 2a, 2b, a plurality of piers 3 spaced apart between the abutments 2a, 2b, a plurality of bridge girders (H-shaped steel) 4 each straddling over the abutments 2a, 2b and the plurality of piers 3 and extending in the bridge axis direction, and an existing concrete deck 5 straddling over the plurality of bridge girders 4. Supports (not shown) are interposed between the bridge abutments 2a and 2b and the plurality of bridge piers 3 and the plurality of bridge girders 4. As shown in FIG. In this embodiment, the existing floor slab 5 is made of reinforced concrete (RC floor slab), but the existing floor slab 5 may be made of prestressed concrete (PC floor slab). Moreover, the bridge girder 4 has a web 4w, an upper flange 4f, and a lower flange (not shown), as shown in FIGS. 10A to 10C, which will be described later.

本実施形態では、橋梁1の全長(橋長)Ltが300mであるとして以下説明するが、橋梁1の全長Ltは300mに限らない。また、本実施形態では、橋梁1の橋軸直角方向において既設床版5を分割しない、いわゆる全断面床版架け替え施工であるとして以下説明するが、施工形態はこれに限らず、例えば、橋梁1の橋軸直角方向において既設床版5を2つに分割する、いわゆる半断面床版架け替え施工であってもよい。 In the present embodiment, the description will be made assuming that the total length (bridge length) Lt of the bridge 1 is 300 m, but the total length Lt of the bridge 1 is not limited to 300 m. In this embodiment, the existing floor slab 5 is not divided in the direction perpendicular to the bridge axis of the bridge 1, so-called full-section floor slab replacement construction will be described below, but the construction form is not limited to this.

図1及び図2に加えて、図3及び図4を用いて、本実施形態における床版架け替え方法を説明する。図3は、本実施形態における床版架け替え方法のメインルーチンを示すフローチャートである。図4は、本実施形態における床版架け替え方法のサブルーチンを示すフローチャートである。 3 and 4 in addition to FIGS. 1 and 2, the floor slab replacement method in this embodiment will be described. FIG. 3 is a flow chart showing the main routine of the floor slab replacement method in this embodiment. FIG. 4 is a flow chart showing a subroutine of the floor slab replacement method in this embodiment.

橋梁1の床版架け替え施工(既設床版5の撤去と、これに替わる新設床版7の設置)は、全体的には、図3に示すメインルーチンに従う。 The floor slab replacement construction of the bridge 1 (removal of the existing floor slab 5 and installation of the new floor slab 7 in its place) generally follows the main routine shown in FIG.

まず、ステップS101では、橋梁1を橋軸方向に複数(本実施形態ではn個)の施工領域A~Aに区分けすることにより、複数の施工領域A~Aを設定する。尚、本実施形態では、施工領域A~Aの各々の橋軸方向の長さが、それぞれ6mであるとして以下説明するが、施工領域A~Aの各々の橋軸方向の長さは6mに限らない。例えば、橋梁1の全長Ltが300mであり、かつ、施工領域A~Aの各々の橋軸方向の長さが、それぞれ6mである場合には、n=300/6=50となる。 First, in step S101, a plurality of construction areas A 1 to A n are set by dividing the bridge 1 into a plurality of (n in this embodiment) construction areas A 1 to A n in the bridge axis direction. In this embodiment, the length of each of the construction areas A 1 to A n in the bridge axis direction is assumed to be 6 m, but the length of each of the construction areas A 1 to A n in the bridge axis direction is not limited to 6 m. For example, if the total length Lt of the bridge 1 is 300 m and the length in the bridge axis direction of each of the construction areas A 1 to A n is 6 m, then n=300/6=50.

次に、ステップS102では、施工領域A~Aの各々にて、既設床版5の撤去と、これに替わる新設床版7の配置とを行う。本実施形態では、例えば図2に示すように、複数の施工領域A~Ak-6にて床版架け替え作業が並行して実施可能である。尚、本実施形態では、床版架け替え施工進行方向において、前側の施工領域(例えば施工領域Ak-4)と、この施工領域より後方の施工領域(例えば施工領域Ak-6)とにて、互いに異なる作業工程を並行して実施し得る。 Next, in step S102, the existing floor slabs 5 are removed and the new floor slabs 7 are arranged to replace them in each of the construction areas A 1 to A n . In this embodiment, for example, as shown in FIG. 2, floor slab replacement work can be performed in parallel in a plurality of construction areas A k to A k-6 . In the present embodiment, different work processes can be performed in parallel in a construction area on the front side (for example, construction area A k-4 ) and a construction area behind this construction area (for example, construction area A k-6 ) in the progress direction of floor slab replacement construction.

施工領域A~Aの全てで既設床版5の撤去と、これに替わる新設床版7の配置とが行われると(すなわち、橋梁1の全長Ltにわたって新設床版7の配置が完了すると)、ステップS103に進み、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化する。
このようにして、橋梁1の床版架け替え施工が行われる。
When the existing floor slabs 5 are removed and the new floor slabs 7 are placed to replace them in all of the construction areas A 1 to A n (that is, when the placement of the new floor slabs 7 is completed over the entire length Lt of the bridge 1), the process proceeds to step S103, where the new floor slabs 7 and the bridge girders 4 are fixed and integrated, and the new floor slabs 7 adjacent in the bridge axis direction are fixed and integrated.
Thus, the floor slab replacement construction of the bridge 1 is performed.

前述のステップS102に関して、施工領域A~Aの各々は、既設床版5の撤去から新設床版7の配置に至る複数段の作業工程を有する。この複数段の作業工程が図4に示されている。
図4に示すように、まず、ステップS1にて、前段(第1段)として、既設床版5の撤去作業を実施する。ここで、ステップS1が、本発明の「第1作業工程」に対応する。
Regarding step S102 described above, each of the construction areas A 1 to A n has a plurality of work steps from removing the existing floor slab 5 to arranging the new floor slab 7 . This multi-stage work process is shown in FIG.
As shown in FIG. 4, first, in step S1, as the first stage (first stage), the existing floor slab 5 is removed. Here, step S1 corresponds to the "first work process" of the present invention.

次に、ステップS2にて、中段(第2段)として、既設床版5が撤去された施工領域に新設床版7を配置するための準備作業(新設床版7の配置準備作業)を実施する。ここで、ステップS2が、本発明の「第2作業工程」に対応する。 Next, in step S2, as the middle stage (second stage), preparation work for arranging the new floor slab 7 in the construction area from which the existing floor slab 5 has been removed (preparation work for arranging the new floor slab 7) is performed. Here, step S2 corresponds to the "second work process" of the present invention.

次に、ステップS3にて、後段(第3段)として、新設床版7の配置準備作業が実施された施工領域に新設床版7を配置する。ここで、ステップS3が、本発明の「第3作業工程」に対応する。 Next, in step S3, as the latter stage (third stage), the new floor slab 7 is placed in the construction area where the preparation work for the placement of the new floor slab 7 has been performed. Here, step S3 corresponds to the "third work process" of the present invention.

ここで、ステップS1にて実施される既設床版5の撤去作業について、前述の図1~図4に加えて、図5及び図8A~図9Bを用いて説明する。
図5は、本実施形態における既設床版5の撤去方法を示すフローチャートである。図8A及び図8Bは、本実施形態における既設床版5の切断方法を示す図である。図9A及び図9Bは、本実施形態における既設床版5の縁切り方法を示す図である。
Here, the work of removing the existing floor slab 5 performed in step S1 will be described using FIGS.
FIG. 5 is a flow chart showing a method for removing the existing floor slab 5 in this embodiment. 8A and 8B are diagrams showing a method of cutting the existing floor slab 5 in this embodiment. 9A and 9B are diagrams showing the edge cutting method of the existing floor slab 5 in this embodiment.

図5に示すように、まず、ステップS11では、既設床版5の切断作業を実施する。このステップS11では、図8A及び図8Bに示すように、既設床版5の後端から所定長さLa分前方の箇所に切断線5bを設定し、この切断線5bに沿って、コンクリートカッターやワイヤーソーなどのコンクリート切断装置を用いて既設床版5を切断して、床版片5aを形成する。本実施形態では、前述の所定長さLaが2mであるとしているが、前述の所定長さLaは2mに限らない。 As shown in FIG. 5, first, in step S11, the existing floor slab 5 is cut. In this step S11, as shown in FIGS. 8A and 8B, a cutting line 5b is set at a predetermined length La ahead of the rear end of the existing floor slab 5, and along this cutting line 5b, the existing floor slab 5 is cut using a concrete cutting device such as a concrete cutter or a wire saw to form a floor slab piece 5a. Although the predetermined length La is 2 m in this embodiment, the predetermined length La is not limited to 2 m.

次に、ステップS12にて、既設床版5の床版片5aの縁切り作業を実施する。このステップS12では、まず、図9Aに示すように、床版片5aの前方と後方とに、それぞれ、短縮状態の複数のジャッキ50a,50bを設置する。ここで、ジャッキ50a,50bは上下方向に伸縮自在であり、例えば油圧ジャッキである。 Next, in step S12, the floor slab piece 5a of the existing floor slab 5 is trimmed. In this step S12, first, as shown in FIG. 9A, a plurality of jacks 50a and 50b in a shortened state are installed on the front and rear sides of the floor slab piece 5a, respectively. Here, the jacks 50a and 50b are vertically extendable, and are hydraulic jacks, for example.

前側のジャッキ50aは、その下端部が既設床版5の上面に当接する。後側のジャッキ50bは、その下端部が橋桁4の上面4a(詳しくは、図10A~図10Cに示す橋桁4の上フランジ4fの上面4a)に当接する。 The lower end of the front jack 50 a abuts on the upper surface of the existing floor slab 5 . The lower end of the rear jack 50b contacts the upper surface 4a of the bridge girder 4 (specifically, the upper surface 4a of the upper flange 4f of the bridge girder 4 shown in FIGS. 10A to 10C).

また、図9Aに示すように、ジャッキ50a,50bの上に跨がるように、梁部材51が配置されている。梁部材51は、ジャッキ50a,50bの上端部に固定されている。梁部材51は、図示しないブラケットを有し、このブラケットと、床版片5aとを貫通するように、上下方向に延びるPC鋼棒52が配置されている。PC鋼棒52については、橋桁4をかわすように配置されている。PC鋼棒52の上端部及び下端部には、それぞれ、梁部材51(前述のブラケット)及び床版片5aとPC鋼棒52とを固定するための固定部材53a,53bが取り付けられている。 Moreover, as shown in FIG. 9A, a beam member 51 is arranged so as to straddle over the jacks 50a and 50b. The beam member 51 is fixed to the upper ends of the jacks 50a and 50b. The beam member 51 has a bracket (not shown), and a vertically extending PC steel rod 52 is arranged so as to pass through the bracket and the floor slab piece 5a. The PC steel rods 52 are arranged so as to avoid the bridge girder 4 . Fixing members 53a and 53b for fixing the PC steel bar 52 to the beam member 51 (the aforementioned bracket) and the floor slab piece 5a are attached to the upper end and the lower end of the PC steel bar 52, respectively.

次に、図9Bに示すように、ジャッキ50a,50bを伸長作動させることにより、梁部材51(前述のブラケット)及びPC鋼棒52を介して、床版片5aが引っ張り上げられる。このようにして、床版片5aが橋桁4から分離(縁切り)されると、ジャッキ50a,50bを短縮し、PC鋼棒52、梁部材51、及びジャッキ50a,50bを撤去する。 Next, as shown in FIG. 9B, the floor slab piece 5a is pulled up via the beam member 51 (the aforementioned bracket) and the PC steel rod 52 by operating the jacks 50a and 50b to extend. After the floor slab piece 5a is separated (edge cut) from the bridge girder 4 in this manner, the jacks 50a and 50b are shortened, and the PC steel rod 52, the beam member 51, and the jacks 50a and 50b are removed.

次に、図5のステップS13にて、橋桁4から縁切りされた床版片5aを、図2に示すクレーン装置20にて吊り上げ、床版片5aの長辺を橋軸方向に向けるように床版片5aの向きを変更して(すなわち90°回転させて)、この床版片5aを、クレーン装置20により、図示しない運搬車両の荷台に載せる。この運搬車両は、床版片5aを、施工領域A~Aから床版架け替え施工進行方向前方に搬出し得る。尚、この運搬車両は、既設床版5上を走行可能である。 Next, in step S13 of FIG. 5, the floor slab piece 5a cut off from the bridge girder 4 is lifted by the crane device 20 shown in FIG. This transport vehicle can carry out the floor slab piece 5a from the construction areas A 1 to A n forward in the direction in which the floor slab replacement construction progresses. In addition, this transport vehicle can run on the existing floor slab 5 .

クレーン装置20は、前後方向に延びる左右一対の下部フレーム21と、左右一対の下部フレーム21に下端が連結された門型フレーム22と、門型フレーム22の上部に設けられた上部フレーム23と、上部フレーム23に対して前後左右に移動可能な吊上装置24と、を含んで構成されている。左右一対の下部フレーム21には、既設床版5上を転動可能な車輪が設けられている。門型フレーム22内、及び、左右一対の下部フレーム21間には、前述の運搬車両の荷台が配置され得る。 The crane device 20 includes a pair of left and right lower frames 21 extending in the front-rear direction, a portal frame 22 whose lower ends are connected to the pair of left and right lower frames 21, an upper frame 23 provided on the upper part of the portal frame 22, and a lifting device 24 movable in the front, rear, left, and right directions with respect to the upper frame 23. A pair of left and right lower frames 21 are provided with wheels capable of rolling on the existing floor slab 5 . Inside the gate-shaped frame 22 and between the pair of left and right lower frames 21, the above-described loading platform of the transport vehicle can be arranged.

本実施形態では、1つの施工領域ごとに(すなわち施工領域A~Aの各々で)、前述のステップS11~S13を3回実施することで、1つの施工領域の橋軸方向の長さ分である6m分の既設床版5の撤去作業を行う。
以上のようにして、図4のステップS1にて、既設床版5の撤去作業が実施される。
In this embodiment, the steps S11 to S13 described above are performed three times for each construction area (that is, for each construction area A 1 to A n ), thereby removing 6 m of the existing floor slab 5, which is the length of one construction area in the bridge axis direction.
As described above, the work of removing the existing floor slab 5 is carried out in step S1 of FIG.

次に、図4のステップS2にて実施される新設床版7の配置準備作業について、前述の図1~図4に加えて、図6及び図10A~図10Cを用いて説明する。
図6は、本実施形態における新設床版7の配置準備方法を示すフローチャートである。図10A~図10Cは、本実施形態における新設床版7の配置準備方法を示す図である。ここで、図10A~図10Cは、後述する図11AのI-I断面に対応している。
6 and 10A to 10C in addition to FIGS.
FIG. 6 is a flow chart showing a method of preparing for placement of the new floor slab 7 in this embodiment. 10A to 10C are diagrams showing a method of preparing for placement of the new floor slab 7 in this embodiment. Here, FIGS. 10A to 10C correspond to the II section of FIG. 11A, which will be described later.

図6に示すように、まず、ステップS21では、既設床版5(床版片5a)が撤去されて外部に露出している橋桁4の上面4a(詳しくは、図10Aに示す橋桁4の上フランジ4fの上面4a)のケレン作業を実施する。ここで、ケレン作業は、橋桁4の上面4aに残留しているコンクリート片などを除去することを含み得る。 As shown in FIG. 6, first, in step S21, the existing floor slab 5 (floor slab piece 5a) is removed and the upper surface 4a of the bridge girder 4 exposed to the outside (specifically, the upper surface 4a of the upper flange 4f of the bridge girder 4 shown in FIG. 10A) is cleaned. Here, the cleaning work may include removing concrete pieces or the like remaining on the upper surface 4 a of the bridge girder 4 .

次に、ステップS22では、ケレン作業が実施された橋桁4の上フランジ4fの左右両側部に、例えばゴム製のフランジシール60を設置する(図10B参照)。フランジシール60は、橋軸方向に延びる板状である。このフランジシール60は、前述のステップS103にて新設床版7と橋桁4とを固定して一体化する際に新設床版7と橋桁4との間の空間9(図11B参照)内に打設されるモルタルが空間9外に漏れ出ることを防ぐためのものである。 Next, in step S22, flange seals 60 made of, for example, rubber are installed on both left and right sides of the upper flange 4f of the bridge girder 4 on which the cleaning work has been performed (see FIG. 10B). The flange seal 60 has a plate shape extending in the bridge axis direction. This flange seal 60 is to prevent the mortar cast in the space 9 (see FIG. 11B) between the new floor slab 7 and the bridge girder 4 from leaking out of the space 9 when the new floor slab 7 and the bridge girder 4 are fixed and integrated in step S103.

次に、ステップS23では、新設床版7の配置高さを調整するための複数の高さ調整材70を、橋桁4の上フランジ4fの上面4aに設置する(図10C参照)。高さ調整材70は、上下方向に伸縮自在であることが好ましい。高さ調整材70は、例えば、上下方向に伸縮自在な手動式のジャッキであり得る。又は、高さ調整材70は、それ自体の高さが決定された後に変形不可能な剛性を有する部材(スペーサー)により構成されてもよい。複数の高さ調整材70は、橋軸方向に互いに間隔を空けて、橋軸方向に並んでいる。 Next, in step S23, a plurality of height adjusting members 70 for adjusting the placement height of the new floor slab 7 are installed on the upper surface 4a of the upper flange 4f of the bridge girder 4 (see FIG. 10C). It is preferable that the height adjusting member 70 is vertically extendable. The height adjustment member 70 may be, for example, a vertically extendable manual jack. Alternatively, the height adjustment member 70 may be configured by a rigid member (spacer) that cannot be deformed after its own height is determined. The plurality of height adjusting members 70 are arranged in the longitudinal direction of the bridge at intervals.

尚、高さ調整材70については、前述のステップS3及び後述のステップS31にて新設床版7が橋桁4上に配置されたときに、計画された新設床版7の配置高さとなるように、新設床版7の橋桁4上への配置に先立って、高さ調整材70自体の高さ調整が行われ得る。高さ調整材70自体の高さ調整は、ステップS23にて橋桁4の上フランジ4fの上面4aに設置する前に行ってもよく、また、橋桁4の上フランジ4fの上面4aに設置した後に行ってもよい。 Regarding the height adjusting material 70, the height of the height adjusting material 70 itself can be adjusted prior to placing the new floor slab 7 on the bridge girder 4 so that when the new floor slab 7 is placed on the bridge girder 4 in step S3 described above and step S31 described later, the height of the new floor slab 7 will be the planned placement height. The height adjustment of the height adjusting member 70 itself may be performed before installation on the upper surface 4a of the upper flange 4f of the bridge girder 4 in step S23, or may be performed after installation on the upper surface 4a of the upper flange 4f of the bridge girder 4.

本実施形態では、フランジシール60の設置後に高さ調整材70の設置を行っているが、この他、フランジシール60の設置に先立って高さ調整材70の設置を行ってもよい。すなわち、ステップS22とステップS23とを入れ替えてもよい。
以上のようにして、図4のステップS2にて、新設床版7の配置準備作業が実施される。
In this embodiment, the height adjusting member 70 is installed after the flange seal 60 is installed, but the height adjusting member 70 may be installed before the flange seal 60 is installed. That is, step S22 and step S23 may be interchanged.
As described above, in step S2 of FIG. 4, the new floor slab 7 is prepared for placement.

次に、図4のステップS3にて実施される新設床版7の配置作業について、前述の図1~図4に加えて、図7、図11A、図11B及び図12を用いて説明する。
図7は、本実施形態における新設床版7の配置方法を示すフローチャートである。図11A及び図11Bは、本実施形態における新設床版7の配置方法を示す図である。ここで、図11Bは、図11AのI-I断面に対応している。図12は、スタッドジベル80の設置方法を示す図である。
7, 11A, 11B and 12 in addition to FIGS.
FIG. 7 is a flow chart showing a method of arranging the new floor slabs 7 in this embodiment. 11A and 11B are diagrams showing a method of arranging the new floor slab 7 in this embodiment. Here, FIG. 11B corresponds to the II section of FIG. 11A. 12A and 12B are diagrams showing a method of installing the stud dowel 80. FIG.

図7に示すように、まず、ステップS31では、橋桁4の上フランジ4fの上面4aに設置された複数の高さ調整材70に、新設床版7を載置する(図11A及び図11B参照)。これにより、橋桁4の上フランジ4fの上面4aと、新設床版7の下面7bと、フランジシール60とによって囲まれた空間9が形成される。 As shown in FIG. 7, first, in step S31, the new floor slab 7 is placed on a plurality of height adjusting members 70 installed on the upper surface 4a of the upper flange 4f of the bridge girder 4 (see FIGS. 11A and 11B). As a result, a space 9 surrounded by the upper surface 4a of the upper flange 4f of the bridge girder 4, the lower surface 7b of the new floor slab 7, and the flange seal 60 is formed.

新設床版7は、プレキャストコンクリート製である(すなわち、PCa床版である)。新設床版7は、橋軸方向を短辺とし、橋軸直角方向を長辺とする、略矩形状である。本実施形態では、新設床版7の橋軸方向の長さが2mであるが、新設床版7の橋軸方向の長さは2mに限らない。
新設床版7には、橋桁4の上フランジ4fの上面4aに相対するように、複数の貫通孔7aが形成されている。
The new floor slab 7 is made of precast concrete (that is, it is a PCa floor slab). The new floor slab 7 has a substantially rectangular shape with short sides extending in the direction of the bridge axis and long sides extending in the direction perpendicular to the axis. In this embodiment, the length of the new floor slab 7 in the bridge axis direction is 2 m, but the length of the new floor slab 7 in the bridge axis direction is not limited to 2 m.
A plurality of through holes 7a are formed in the new floor slab 7 so as to face the upper surface 4a of the upper flange 4f of the bridge girder 4. As shown in FIG.

ステップS31における新設床版7の配置作業(載置作業)には、図2に示すクレーン装置30が用いられる。クレーン装置30は、前後方向に延びる左右一対の下部フレーム31と、左右一対の下部フレーム31に下端が連結された門型フレーム32と、門型フレーム32の上部に設けられた上部フレーム33と、上部フレーム33に対して前後左右に移動可能な吊上装置34と、を含んで構成されている。左右一対の下部フレーム31には、橋桁4上に載置された新設床版7上を転動可能な車輪が設けられている。門型フレーム32内、及び、左右一対の下部フレーム31間を、搬送台車40が走行可能である。 The crane device 30 shown in FIG. 2 is used for the placement work (placing work) of the new floor slab 7 in step S31. The crane device 30 includes a pair of left and right lower frames 31 extending in the front-rear direction, a portal frame 32 whose lower ends are connected to the pair of left and right lower frames 31, an upper frame 33 provided on the upper part of the portal frame 32, and a lifting device 34 movable in the front, rear, left, and right directions with respect to the upper frame 33. A pair of left and right lower frames 31 are provided with wheels capable of rolling on the new floor slab 7 placed on the bridge girder 4 . A carriage 40 can travel inside the portal frame 32 and between the pair of left and right lower frames 31 .

クレーン装置30によって吊り上げられる予定の新設床版7は、搬送台車40によって、橋台2b(図1参照)に隣接する地面上からクレーン装置30まで搬送される。尚、橋桁4上に載置されて隣り合う新設床版7同士の間の隙間を上から覆うように鉄板などの板状部材を敷くことで、搬送台車40の走行安定性を向上させてもよい。搬送台車40は、自走式であってもよい。搬送台車40は、ゴム製のタイヤが使用された車輪を含んで構成されることが好ましい。 The new floor slab 7 scheduled to be lifted by the crane device 30 is transported from the ground adjacent to the abutment 2b (see FIG. 1) to the crane device 30 by the carriage 40 . The traveling stability of the carriage 40 may be improved by laying a plate-like member such as an iron plate so as to cover the gap between the adjacent new floor slabs 7 placed on the bridge girder 4 from above. The carriage 40 may be self-propelled. The carriage 40 preferably includes wheels with rubber tires.

橋台2bに隣接する地面上では、クレーン装置30まで搬送台車40によって搬送される予定の新設床版7が、図示しない運搬車両から、この運搬車両より重量が軽い搬送台車40に荷卸しされる。この荷卸し作業には、前述のクレーン装置20,30と同様の構成のクレーン装置を用いてもよい。
従って、本実施形態では、新設床版7を、床版架け替え施工進行方向後方から施工領域A~Aに搬入する。
On the ground adjacent to the abutment 2b, the new floor slab 7 scheduled to be transported by the carriage 40 to the crane device 30 is unloaded from a transport vehicle (not shown) to the carriage 40 lighter in weight than the transport vehicle. For this unloading work, a crane device having the same configuration as the crane devices 20 and 30 described above may be used.
Therefore, in the present embodiment, the new floor slab 7 is carried into the construction areas A 1 to A n from behind in the direction in which the floor slab replacement construction progresses.

尚、本実施形態では、搬送台車40上からクレーン装置30によって新設床版7を吊り上げた後に、クレーン装置30によって新設床版7の長辺を橋軸直角方向に向けるように新設床版7の向きを変更する(すなわち90°回転させる)。 In the present embodiment, after the new floor slab 7 is lifted from the carriage 40 by the crane device 30, the orientation of the new floor slab 7 is changed by the crane device 30 so that the long side of the new floor slab 7 is directed in the direction perpendicular to the bridge axis (i.e., rotated by 90°).

本実施形態では、1つの施工領域ごとに(すなわち施工領域A~Aの各々で)、前述のステップS31を3回実施することで、1つの施工領域の橋軸方向の長さ分である6m分(つまり3枚)の新設床版7の配置作業を行う。 In the present embodiment, the above-mentioned step S31 is performed three times for each construction area (that is, for each of the construction areas A 1 to A n ), thereby arranging the new floor slabs 7 for 6 m (that is, three pieces), which is the length of one construction area in the bridge axis direction.

次に、図7のステップS32では、図12に示すように、複数のスタッドジベル80を、新設床版7の貫通孔7a内に位置するように、橋桁4の上フランジ4fの上面4aに溶接固定する。尚、ステップS32のスタッドジベル80の設置作業の途中で搬送台車40が通過する場合には、搬送台車40の通過時にスタッドジベル80の設置作業を中断する。
以上のようにして、図4のステップS3にて、新設床版7の配置作業が実施される。
Next, in step S32 of FIG. 7, a plurality of stud dowels 80 are welded and fixed to the upper surface 4a of the upper flange 4f of the bridge girder 4 so as to be positioned within the through holes 7a of the new floor slab 7, as shown in FIG. If the carriage 40 passes during the installation work of the stud dowel 80 in step S32, the installation work of the stud dowel 80 is interrupted when the carriage 40 passes.
As described above, the work of arranging the new floor slab 7 is carried out in step S3 of FIG.

図2に示す、ある時刻での施工状態では、施工領域Ak+1にクレーン装置20が位置する。施工領域Ak+1の後方に位置する施工領域Aでは、前述のステップS1(ステップS11~S13)に示した作業が実施されている。施工領域Aの後方に位置する施工領域Ak-1では、前述のステップS21に示した作業が実施されている。施工領域Ak-1の後方に位置する施工領域Ak-2では、前述のステップS22に示した作業が実施されている。施工領域Ak-2の後方に位置する施工領域Ak-3では、前述のステップS23に示した作業が実施されている。施工領域Ak-3の後方に位置する施工領域Ak-4では、前述のステップS31に示した作業が実施されている。施工領域Ak-4の後方に位置する施工領域Ak-5にはクレーン装置30が位置する。施工領域Ak-5の後方に位置する施工領域Ak-6では、前述のステップS32に示した作業が実施されている。尚、図2に示す符号「α」は、前述のステップS1~S3(ステップS11~S32)の途中で作業を休止していることを示す。 In the construction state at a certain time shown in FIG. 2, the crane device 20 is positioned in the construction area Ak+1 . In the construction area A k located behind the construction area A k+1 , the work shown in the above step S1 (steps S11 to S13) is being performed. In the construction area A k-1 located behind the construction area A k , the work shown in step S21 is being performed. In the construction area A k- 2 located behind the construction area A k-1 , the work shown in step S22 is being performed. In the construction area A k -3 located behind the construction area A k- 2 , the work shown in step S23 is being performed. In the construction area A k-4 located behind the construction area A k-3 , the work shown in step S31 is being performed. A crane device 30 is positioned in the construction area A k-5 located behind the construction area A k-4 . In the construction area A k -6 located behind the construction area A k-5 , the work shown in step S32 is being performed. The symbol “α” shown in FIG. 2 indicates that the work is suspended during the steps S1 to S3 (steps S11 to S32) described above.

本実施形態では、ステップS1の作業が行われている施工領域(例えば、図2に示す施工領域A)からステップS32の作業が行われている施工領域(例えば、図2に示す施工領域Ak-6)までを覆うように、仮設テント10が設けられている。それゆえ、ステップS21でのケレン作業や、ステップS32での溶接作業が、仮設テント10内で実施される。尚、仮設テント10によって覆われる施工領域は、図2に示したものに限らない。 In the present embodiment, a temporary tent 10 is provided so as to cover the construction area where the work of step S1 is performed (for example, the construction area A k shown in FIG. 2) to the construction area where the work of step S32 is performed (for example, the construction area A k-6 shown in FIG.). Therefore, the cleaning work in step S<b>21 and the welding work in step S<b>32 are performed inside the temporary tent 10 . The construction area covered by the temporary tent 10 is not limited to that shown in FIG.

このようにして、本実施形態では、床版架け替え施工進行方向において、前側の施工領域と、この施工領域より後方の施工領域とにて、互いに異なる作業工程を並行して(すなわち同時に)実施可能である。
また、本実施形態では、床版架け替え施工進行方向において、前側の施工領域から後側の施工領域に向かうほど(例えば、図2に示す施工領域Aから施工領域Ak-6に向かうほど)、後段の作業工程となるように(すなわちステップS32に近づくように)、複数段の作業工程(ステップS1~S32)を並行して(すなわち同時に)実施可能である。
In this way, in the present embodiment, different work processes can be carried out in parallel (i.e., simultaneously) in the construction area on the front side and the construction area behind this construction area in the direction in which the floor slab replacement construction progresses.
Further, in the present embodiment, in the floor slab replacement construction progress direction, the more from the construction area on the front side to the construction area on the rear side (for example, the more from the construction area A k shown in FIG. 2 toward the construction area A k−6 ), the more the work process (steps S1 to S32) in a later stage (that is, closer to step S32).

本実施形態では、図2に示すように、床版架け替え施工進行方向において、クレーン装置30の前方にクレーン装置20が位置している。 In this embodiment, as shown in FIG. 2, the crane device 20 is positioned in front of the crane device 30 in the direction in which the floor slab replacement construction progresses.

本実施形態では、床版架け替え施工が進むのに追従して、仮設テント10及びクレーン装置20,30が前進する。ゆえに、複数段の作業工程(ステップS1~S32)を並行して(すなわち同時に)実施可能な床版架け替えシステムも前進する。ここで、この床版架け替えシステムは仮設テント10及びクレーン装置20,30を含む。 In this embodiment, the temporary tent 10 and the crane devices 20 and 30 move forward as the floor slab replacement construction progresses. Therefore, a floor slab replacement system capable of executing a plurality of work processes (steps S1 to S32) in parallel (that is, at the same time) also advances. Here, this floor slab replacement system includes a temporary tent 10 and crane devices 20 and 30 .

図13は、本実施形態における時刻t=t1~t10と施工領域A~Aの各々の作業工程との関係を示す図である。図14は、本実施形態における時刻t=t1~t15と施工領域A~Aの各々の作業工程との関係を示す図である。 FIG. 13 is a diagram showing the relationship between the time t=t1 to t10 and the work process of each of the construction areas A 1 to A 9 in this embodiment. FIG. 14 is a diagram showing the relationship between the times t=t1 to t15 and the work processes of the construction areas A 1 to A 8 in this embodiment.

尚、図13及び図14に示す符号「α」は、前述の図2と同様に、前述のステップS1~S3(ステップS11~S32)の途中で作業を休止していることを示す。 13 and 14, similarly to FIG. 2, indicates that the work is suspended in the middle of steps S1 to S3 (steps S11 to S32).

また、前述の時刻t1~t2間の時間,時刻t2~t3間の時間,・・・,時刻t13~t14間の時間,時刻t14~t15間の時間は、それぞれ、同じ時間(本実施形態では1.2時間とするが、これに限らない)である。また、1つの施工領域(すなわち施工領域A~Aの各々)について、ステップS1,S21,S22,S23,S31,S32の作業工程時間が同じである。この作業工程時間の設定に際して、ステップS1,S21,S22,S23,S31,S32のうち、どの作業工程がクリティカルパスになっているかが考慮され得る。 Also, the time between times t1 and t2, the time between times t2 and t3, . In addition, the work process times of steps S1, S21, S22, S23, S31, and S32 are the same for one construction area (that is, each of the construction areas A 1 to A n ). When setting the work process time, it is possible to consider which work process is the critical path among steps S1, S21, S22, S23, S31, and S32.

図13及び図14に示すように、本実施形態では、時刻t1~t13の間で、施工領域A~Aでの床版架け替え(既設床版5の撤去と、これに替わる新設床版7の配置)が完了する。 As shown in FIGS. 13 and 14, in this embodiment, between times t1 and t13, floor slab replacement (removal of the existing floor slab 5 and placement of the new floor slab 7 to replace it) in the construction areas A 1 to A 6 is completed.

この点、図15は、従来の床版架け替え方法の一例における時刻t1~t13と施工領域A,Aの各々の作業工程との関係を示している。図15は、施工領域Aで既設床版5の撤去と、これに替わる新設床版7の配置を行った後に、施工領域Aで既設床版5の撤去と、これに替わる新設床版7の配置を行うと、時刻t1~t13の作業時間がかかることを示している。 In this regard, FIG. 15 shows the relationship between the times t1 to t13 and the respective work steps in the construction areas A 1 and A 2 in an example of the conventional floor slab replacement method. FIG. 15 shows that after removing the existing floor slab 5 and placing the new floor slab 7 in place of it in the construction area A1 , the removal of the existing floor slab 5 and placement of the new floor slab 7 in place of it in the construction area A2 takes a working time of t1 to t13.

従って、図13~図15の図示から明らかなように、本実施形態の床版架け替え方法を用いると、従来の床版架け替え方法に比べてはるかに迅速に床版架け替え施工を進めることができる。 Therefore, as is clear from the illustrations in FIGS. 13 to 15, the floor slab replacement method of the present embodiment can be used to proceed with floor slab replacement construction much more quickly than the conventional floor slab replacement method.

前述の図3のステップS103では、橋桁4上に配置された新設床版7の貫通孔7aから空間9内(図11B参照)にモルタルを注入・打設することで、このモルタルとスタッドジベル80(図12参照)とにより、新設床版7と橋桁4とが固定されて一体化される。また、前述の図3のステップS103では、橋軸方向で隣り合う新設床版7同士の間の間詰部(図示せず)にて鉄筋コンクリート工が実施されることで、これら新設床版7同士が固定されて一体化される。 In step S103 of FIG. 3 described above, mortar is injected and cast into the space 9 (see FIG. 11B) from the through holes 7a of the new floor slab 7 placed on the bridge girder 4, and the new floor slab 7 and the bridge girder 4 are fixed and integrated by this mortar and the stud dowels 80 (see FIG. 12). Further, in step S103 of FIG. 3 described above, reinforced concrete work is carried out in the gaps (not shown) between the new floor slabs 7 that are adjacent in the bridge axis direction, so that these new floor slabs 7 are fixed and integrated.

本実施形態によれば、床版架け替え方法は、構造物(橋梁1)を構造物(橋梁1)の軸方向に複数の施工領域A~Aに区分けすることにより、複数の施工領域A~Aを設定することを含む。施工領域A~Aは、各々が、既設床版5の撤去から新設床版7の配置に至る複数段の作業工程(ステップS1~S3(S11~S32))を有する。構造物(橋梁1)の軸方向(橋軸方向)に沿う床版架け替え施工進行方向において、床版架け替え施工進行方向前側の施工領域と、この施工領域より床版架け替え施工進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する(図2、図13及び図14参照)。これにより、床版架け替え施工の進捗状況が異なる複数の施工領域にて、並行して(すなわち同時に)施工を進めることができるので、既設床版5から新設床版7への架け替えを効率良く(換言すれば短期間で)行うことができる(図13~図15参照)。 According to this embodiment, the floor slab replacement method includes setting a plurality of construction areas A 1 to A n by dividing the structure (bridge 1) into a plurality of construction areas A 1 to A n in the axial direction of the structure (bridge 1). Each of the construction areas A 1 to A n has a plurality of work processes (steps S1 to S3 (S11 to S32)) from removal of the existing floor slab 5 to placement of the new floor slab 7 . In the floor slab replacement construction progress direction along the axial direction (bridge axis direction) of the structure (bridge 1), different work processes are performed in parallel in the construction area on the front side of the floor slab replacement construction progress direction and the construction area behind the floor slab replacement construction progress direction from this construction area (see FIGS. 2, 13 and 14). As a result, construction can be carried out in parallel (that is, at the same time) in a plurality of construction areas where the progress of floor slab replacement construction is different, so that the replacement from the existing floor slab 5 to the new floor slab 7 can be efficiently performed (in other words, in a short period of time) (see FIGS. 13 to 15).

また本実施形態によれば、床版架け替え施工進行方向前側の施工領域から床版架け替え施工進行方向後側の施工領域に向かうほど後段の作業工程となるように(例えば、図2に示すように、施工領域Aから施工領域Ak-6に向かうほど、ステップS32に近づくように)、複数段の作業工程を並行して実施する(図2、図13及び図14参照)。これにより、床版架け替え施工進行方向に沿って、各作業工程を継続しつつ前進させることができるので、各作業工程の休止時間(作業待ち時間)の発生を抑制でき、ひいては、床版架け替え施工を効率良く行うことができる。 In addition, according to the present embodiment, a plurality of work steps are performed in parallel so that the work process becomes later as it goes from the construction area on the front side of the floor slab replacement construction progress direction to the construction area on the rear side of the floor slab replacement construction progress direction ( for example, as shown in FIG. As a result, each work process can be continued and advanced along the progress direction of the floor slab replacement construction, so that the occurrence of downtime (work waiting time) in each work process can be suppressed, and the floor slab replacement construction can be efficiently performed.

また本実施形態によれば、撤去された既設床版5(床版片5a)を施工領域A~Aから床版架け替え施工進行方向前方に搬出し、新設床版7を施工領域A~Aに床版架け替え施工進行方向後方から搬入する。これにより、既設床版5(床版片5a)の搬出作業と新設床版7の搬入作業とが錯綜することを抑制することができる。 Further, according to this embodiment, the removed existing floor slab 5 (floor slab piece 5a) is carried forward from the construction areas A 1 to An in the floor slab replacement construction progress direction, and the new floor slab 7 is carried into the construction areas A 1 to An from the rear in the floor slab replacement construction progress direction. As a result, it is possible to prevent the work of carrying out the existing floor slab 5 (floor slab piece 5a) and the work of carrying in the new floor slab 7 from being complicated.

また本実施形態によれば、各施工領域A~Aがそれぞれ有する複数段の作業工程は、施工領域の既設床版5の撤去作業を実施する第1作業工程(ステップS1)と、既設床版5が撤去された施工領域に新設床版7を配置するための準備作業を実施する第2作業工程(ステップS2)と、この準備作業が実施された施工領域に新設床版7を配置する第3作業工程(ステップS3)と、を含む。ゆえに、新設床版7の配置に先立って新設床版7の配置のための様々な準備を行うことで、新設床版7の配置を円滑に行うことができる。 According to the present embodiment, the work process of multiple steps in which each construction area A 1 to A has, each of which has the first work process (step S1), which implements the removal of the existing floor version 5 in the construction area, and the preparation work to place a new floor version 7 in the construction area where the existing floor version 5 has been removed. Includes the second work process (step S2) to be applied and the third work process (step S3), which allows the new floor version 7 to be placed in the construction area where the preparation work was implemented. Therefore, by making various preparations for the placement of the new floor slabs 7 prior to placement of the new floor slabs 7, the placement of the new floor slabs 7 can be performed smoothly.

また本実施形態によれば、第2作業工程(ステップS2)は、第3作業工程(ステップS3)にて施工領域に配置される新設床版7の配置高さを調整するための高さ調整材70を橋梁1の橋桁4の上面4aに設けること(ステップS23)を含む。これにより、ステップS31(ステップS3)にて、新設床版7を、計画の配置高さで容易に施工領域に配置することができる。 Further, according to the present embodiment, the second work process (step S2) includes providing the height adjustment material 70 on the upper surface 4a of the bridge girder 4 of the bridge 1 for adjusting the placement height of the new floor slab 7 to be placed in the construction area in the third work process (step S3) (step S23). As a result, in step S31 (step S3), the new floor slab 7 can be easily placed in the construction area at the planned placement height.

また本実施形態によれば、第2作業工程(ステップS2)は、橋梁1の橋桁4の上面4aに対してケレン作業を実施すること(ステップS21)を含む。このケレン作業は、仮設テント10内で実施される。それゆえ、仮設テント10が雨除けとして機能し得るので、雨天でもケレン作業を実施することができる。また、ケレン作業で発生する粉じんが仮設テント10内に留まり得るので、当該粉じんの外部への飛散を抑制することができる。 Further, according to the present embodiment, the second work process (step S2) includes performing the scraping work on the upper surface 4a of the bridge girder 4 of the bridge 1 (step S21). This cleaning work is carried out inside the temporary tent 10 . Therefore, since the temporary tent 10 can function as a rain cover, cleaning work can be carried out even in rainy weather. In addition, since the dust generated by the cleaning work can remain in the temporary tent 10, it is possible to suppress the scattering of the dust to the outside.

また本実施形態によれば、施工領域A~Aの各々が有する複数段の作業工程のうち、溶接作業を含む作業工程(例えばステップS32)では、仮設テント10内で溶接作業が実施される。それゆえ、仮設テント10が雨除けとして機能し得るので、雨天でも溶接作業を実施することができる。 Further, according to the present embodiment, the welding work is carried out inside the temporary tent 10 in the work process including the welding work (for example, step S32) among the multiple stages of work processes of each of the construction areas A 1 to A n . Therefore, since the temporary tent 10 can function as a rain cover, welding work can be carried out even in rainy weather.

また本実施形態によれば、新設床版7がプレキャストコンクリート製である。ゆえに、床版架け替えの施工現場での新設床版7の設置作業を簡素化することができる。 Further, according to this embodiment, the new floor slab 7 is made of precast concrete. Therefore, it is possible to simplify the installation work of the new floor slab 7 at the floor slab replacement construction site.

また本実施形態によれば、橋梁1の全長にわたって新設床版7の配置が完了した後に、新設床版7と橋梁1の橋桁4とを固定して一体化すると共に、橋梁1の軸方向(橋軸方向)で隣り合う新設床版7同士を固定して一体化する(ステップS103)。これにより、新設床版7と橋桁4との一体化と、隣り合う新設床版7同士の一体化とを、橋梁1の全長にわたってまとめて行うことができるので、これらの一体化作業を短期間で効率良く行うことができる。 Further, according to the present embodiment, after the placement of the new floor slab 7 over the entire length of the bridge 1 is completed, the new floor slab 7 and the bridge girder 4 of the bridge 1 are fixed and integrated, and the new floor slabs 7 adjacent in the axial direction of the bridge 1 (bridge axis direction) are fixed and integrated (step S103). Thus, the integration of the new floor slab 7 and the bridge girder 4 and the integration of the adjacent new floor slabs 7 can be collectively performed over the entire length of the bridge 1, so that these integration work can be efficiently performed in a short period of time.

尚、本実施形態では、橋梁1の全長にわたって新設床版7の配置が完了した後に、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化するが、この他、橋梁1の全長よりも短く、かつ、複数の施工領域を含む所定区間にわたって新設床版7の配置が完了した後に、この所定区間にてまとめて、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化してもよい。 In this embodiment, after the new floor slab 7 and the bridge girder 4 have been laid out over the entire length of the bridge 1, the new floor slab 7 and the bridge girder 4 are fixed and integrated, and the new floor slabs 7 adjacent to each other in the bridge axis direction are fixed and integrated. Adjacent new floor slabs 7 may be fixed and integrated.

図16A及び図16Bは、本発明の第2実施形態における時刻t1~t19と施工領域A~A20の各々の作業工程との関係を示す図である。
前述の第1実施形態と異なる点について説明する。
FIGS. 16A and 16B are diagrams showing the relationship between times t1 to t19 and work steps in the construction areas A 1 to A 20 in the second embodiment of the present invention.
Differences from the first embodiment described above will be described.

本実施形態では、前述の第1実施形態に比べて、施工領域A~Aの各々の橋軸方向の長さを短縮している。本実施形態では、施工領域A~Aの各々の橋軸方向の長さを、それぞれ2mとしているが、施工領域A~Aの各々の橋軸方向の長さは2mに限らない。例えば、橋梁1の全長Ltが300mであり、かつ、施工領域A~Aの各々の橋軸方向の長さが、それぞれ2mである場合には、n=300/2=150となる。 In this embodiment, the length in the bridge axis direction of each of the construction areas A 1 to A n is shortened compared to the first embodiment. In this embodiment, the length of each of the construction areas A 1 to A n in the bridge axis direction is set to 2 m, but the length of each of the construction areas A 1 to A n in the bridge axis direction is not limited to 2 m. For example, if the total length Lt of the bridge 1 is 300 m and the length in the bridge axis direction of each of the construction areas A 1 to A n is 2 m, then n=300/2=150.

また、本実施形態では、前述の時刻t1~t2間の時間,時刻t2~t3間の時間,・・・,時刻t17~t18間の時間,時刻t18~t19間の時間は、それぞれ、同じ時間(本実施形態では0.4時間とするが、これに限らない)である。 Further, in the present embodiment, the time between times t1 and t2, the time between times t2 and t3, .

本実施形態では、1つの施工領域(すなわち施工領域A~Aの各々)について、ステップS1の作業工程時間が0.4時間であり、ステップS21の作業工程時間が0.8時間(0.4時間×2)であり、ステップS22,S23の作業工程時間が、それぞれ、1.2時間(0.4時間×3)であり、ステップS31の作業工程時間が0.4時間であり、ステップS32の作業工程時間が0.4時間である。 According to the present embodiment, the work process time of step S1 is 0.4 hours for one construction area (that is, each of the construction areas A 1 to A n ), the work process time of step S21 is 0.8 hours (0.4 hours x 2), and the step S22 and S23 work time is 1.4 (0.4 (0.4). Time x 3), step S31 work processing time is 0.4 hours, and the work process time for step S32 is 0.4 hours.

本実施形態では、図16A及び図16Bに示すように、各作業工程の特性に応じて、各作業工程の時間配分の最適化と、各作業工程の作業範囲の最適化とを実現することができる。例えば、図16Aの時刻t6~t7,t9~t10、及び、図16Bの時刻t12~t13,t15~t16,t18~t19において、ステップS21のケレン作業を休止することにより、仮設テント10内で粉じんが慢性的に発生することを抑制することができる。 In this embodiment, as shown in FIGS. 16A and 16B, it is possible to optimize the time allocation for each work process and optimize the work range of each work process according to the characteristics of each work process. For example, at times t6 to t7, t9 to t10 in FIG. 16A and times t12 to t13, t15 to t16, t18 to t19 in FIG. 16B, by pausing the cleaning work in step S21, the chronic generation of dust in the temporary tent 10 can be suppressed.

図17は、本発明の第3実施形態における新設床版7の配置方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 17 is a flow chart showing a method of arranging the new floor slabs 7 according to the third embodiment of the present invention.
Differences from the first embodiment described above will be described.

本実施形態では、ステップS103の替わりとして、ステップS32の後に、ステップS33が追加されている。すなわち、本実施形態では、1つの施工領域ごとに(すなわち施工領域A~Aの各々で)、ステップS32のスタッドジベル80の設置作業を行い、これに続けて、ステップS33にて、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化する。これら一体化作業については、前述の第1実施形態と同様であるので、その説明を省略する。 In this embodiment, step S33 is added after step S32 instead of step S103. That is, in the present embodiment, the stud dowel 80 is installed in step S32 for each construction area (that is, in each construction area A 1 to A n ), and subsequently, in step S33, the new floor slab 7 and the bridge girder 4 are fixed and integrated, and the new floor slabs 7 adjacent in the bridge axis direction are fixed and integrated. These integration operations are the same as those in the first embodiment described above, so description thereof will be omitted.

尚、前述の第2実施形態において、本実施形態と同様に、ステップS103の替わりとして、ステップS32の後に、ステップS33を追加してもよいことは言うまでもない。 It goes without saying that in the above-described second embodiment, step S33 may be added after step S32 instead of step S103, as in the present embodiment.

図18は、本発明の第4実施形態における新設床版7の配置準備方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 18 is a flow chart showing a method of preparing for placement of the new floor slab 7 according to the fourth embodiment of the present invention.
Differences from the first embodiment described above will be described.

本実施形態では、前述のステップS21にて橋桁4の上フランジ4fの上面4aのケレン作業を実施した後に、ステップS24に進み、橋桁4の上フランジ4fの上面4aの形状の測量を実施する。この測量が完了した後に、ステップS22に進み、橋桁4の上フランジ4fの左右両側部に、フランジシール60を設置する。すなわち、本実施形態では、ステップS21とステップS22との間にステップS24が追加されている。 In this embodiment, after the top surface 4a of the upper flange 4f of the bridge girder 4 is cleaned in step S21, the process proceeds to step S24 to measure the shape of the top surface 4a of the upper flange 4f of the bridge girder 4. After this survey is completed, the process proceeds to step S22, and flange seals 60 are installed on both left and right sides of the upper flange 4f of the bridge girder 4. As shown in FIG. That is, in this embodiment, step S24 is added between step S21 and step S22.

尚、前述の第2及び第3実施形態において、本実施形態と同様に、ステップS21とステップS22との間にステップS24を追加してもよいことは言うまでもない。 It goes without saying that in the above-described second and third embodiments, step S24 may be added between steps S21 and S22 as in the present embodiment.

図19は、本発明の第5実施形態における新設床版7の配置方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 19 is a flow chart showing a method of arranging the new floor slabs 7 according to the fifth embodiment of the present invention.
Differences from the first embodiment described above will be described.

本実施形態では、前述のステップS31にて、橋桁4の上フランジ4fの上面4aに設置された複数の高さ調整材70に、新設床版7を載置した後に、ステップS34に進み、新設床版7の高さ調整を実施する。この高さ調整が完了した後に、ステップS32に進み、複数のスタッドジベル80を、新設床版7の貫通孔7a内に位置するように、橋桁4の上フランジ4fの上面4aに溶接固定する。すなわち、本実施形態では、ステップS31とステップS32との間にステップS34が追加されている。 In this embodiment, after placing the new floor slab 7 on the plurality of height adjustment members 70 installed on the upper surface 4a of the upper flange 4f of the bridge girder 4 in the above-described step S31, the process proceeds to step S34 to adjust the height of the new floor slab 7. After this height adjustment is completed, the process proceeds to step S32, and a plurality of stud dowels 80 are welded and fixed to the upper surface 4a of the upper flange 4f of the bridge girder 4 so as to be positioned within the through holes 7a of the new floor slab 7. That is, in this embodiment, step S34 is added between step S31 and step S32.

尚、前述の第2~第4実施形態において、本実施形態と同様に、ステップS31とステップS32との間にステップS34を追加してもよいことは言うまでもない。 It goes without saying that in the above-described second to fourth embodiments, step S34 may be added between steps S31 and S32 as in the present embodiment.

図20は、本発明の第6実施形態における新設床版7の配置準備方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 20 is a flow chart showing a method of preparing for placement of the new floor slab 7 according to the sixth embodiment of the present invention.
Differences from the first embodiment described above will be described.

本実施形態では、新設床版7に複数のインサートが埋め込まれている。各インサートは、新設床版7を上下に貫通する雌ねじ部を有する。この雌ねじ部には、上側に頭部を有するボルトの雄ねじ部が螺合している。このボルトの雄ねじ部の下端部は、新設床版7の下面7bから下方に突出しており、橋桁4の上フランジ4fの上面4aに当接可能である。このボルトの雄ねじ部の、雌ねじ部に対するねじ込み度合いを変化させることで、ボルトの雄ねじ部の下端部が新設床版7の下面7bから下方に突出する突出量が変化し得る。ゆえに、これらインサート及びボルト(以下、「インサート・ボルト」と称する)が、新設床版7の配置高さを調整するための高さ調整材として機能し得る。 In this embodiment, a plurality of inserts are embedded in the new floor slab 7 . Each insert has a female screw portion that vertically penetrates the new floor slab 7 . A male threaded portion of a bolt having a head on the upper side is screwed into the female threaded portion. The lower end of the male threaded portion of the bolt protrudes downward from the lower surface 7b of the new floor slab 7 and can abut on the upper surface 4a of the upper flange 4f of the bridge girder 4. As shown in FIG. By changing the screwing degree of the male threaded portion of the bolt with respect to the female threaded portion, the amount by which the lower end portion of the male threaded portion of the bolt protrudes downward from the lower surface 7b of the new floor slab 7 can be changed. Therefore, these inserts and bolts (hereinafter referred to as “insert bolts”) can function as height adjusting members for adjusting the height of the new floor slab 7 .

本実施形態では、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)が、前述のステップS31に先立って、新設床版7に複数設けられている。ゆえに、前述の高さ調整材70が不要となるので、本実施形態では、図20に示すように、前述のステップS23が省略され得る。 In this embodiment, a plurality of height adjusting members (for example, insert bolts described above) for adjusting the placement height of the new floor slab 7 are provided on the new floor slab 7 prior to step S31 described above. Therefore, since the height adjusting member 70 described above is not required, in this embodiment, as shown in FIG. 20, step S23 described above can be omitted.

尚、前述の第2~第5実施形態において、本実施形態と同様に、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)を、前述のステップS31に先立って新設床版7に複数設ければ、前述の高さ調整材70が不要となるので、ステップS23を省略することができることは言うまでもない。特に、前述の第5実施形態において、本実施形態と同様に、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)を、前述のステップS31に先立って新設床版7に複数設けて、ステップS23を省略した場合には、ステップS34における新設床版7の高さ調整において、これら高さ調整材(例えば、前述のインサート・ボルト)が用いられ得る。 In the above-described second to fifth embodiments, if a plurality of height-adjusting members (for example, the above-described insert bolts) for adjusting the arrangement height of the new floor slab 7 are provided on the new floor slab 7 prior to step S31, step S23 can be omitted because the height-adjusting members 70 are not required. In particular, in the above-described fifth embodiment, if a plurality of height adjusting members (for example, the above-described insert bolts) for adjusting the arrangement height of the new floor slab 7 are provided on the new floor slab 7 prior to step S31, and step S23 is omitted, these height-adjusting members (for example, the above-described insert bolts) can be used in adjusting the height of the new floor slab 7 in step S34.

前述の第1実施形態では、複数の作業工程(ステップS1,S21~S23,S31,S32)の各々に対応するように、作業員及び装置を含む作業チームを個別に編成し(すなわち分業化し)、これら作業チームが作業工程の順序(ステップS1,S21~S23,S31,S32)に従って橋軸方向に1列に並んでいる(つまり、これら作業チームからなる、床版架け替えのための生産ラインのようなものが形成されている)。そして、これら作業チームが並行して、各々の作業の実施と前方への移動とを繰り返すことで、床版架け替え施工が進む。ゆえに、これら作業チームによる、前方への移動を伴う流れ作業によって、床版架け替え施工が進む。この点は、第1実施形態のみならず、第2~第6実施形態においても同様である。ここにおいて、各作業チームによる作業、及び、作業チーム同士の連携などに関して、AI(人工知能)技術などを含むICT(情報通信技術)などを活用することにより、床版架け替え施工の一部又は全部のオートメーション化を実現することができ、ひいては、大幅な生産性向上を図ることができる。従って、本発明に係る床版架け替え方法は、ICTなどの活用によるi-Construction(登録商標)化の推進をもって、インフラ維持管理更新における生産性向上を図ると共に、魅力ある職場環境の創生により若年層の建設業への入職者の増加に貢献するための基盤技術の1つとなり得るものであり、産業上の利用可能性は大である。 In the above-described first embodiment, work teams including workers and equipment are individually organized (that is, division of labor) so as to correspond to each of a plurality of work processes (steps S1, S21 to S23, S31, and S32), and these work teams are arranged in a line in the bridge axis direction according to the order of the work processes (steps S1, S21 to S23, S31, and S32) (that is, a production line for floor slab replacement consisting of these work teams). things are formed). Then, these work teams repeat the execution of each work and the forward movement in parallel, and the floor slab replacement construction progresses. Therefore, the floor slab replacement construction progresses through assembly line work involving forward movement by these work teams. This point applies not only to the first embodiment, but also to the second to sixth embodiments. Here, by utilizing ICT (information and communication technology) including AI (artificial intelligence) technology for the work by each work team and the cooperation between work teams, part or all of the floor slab replacement construction can be automated, and as a result, productivity can be greatly improved. Therefore, the floor slab replacement method according to the present invention can improve productivity in infrastructure maintenance and management renewal by promoting i-Construction (registered trademark) by utilizing ICT, etc., and can be one of the basic technologies for contributing to an increase in the number of young people entering the construction industry by creating an attractive work environment, and has great industrial applicability.

前述の第1~第6実施形態において、例えば、施工領域A~Aのいずれかにおいて作業が遅れ気味である場合には、作業が遅れ気味である施工領域の作業員の人員を増やすなど、施工の進捗状況に応じて、前述の作業チームの編成(構成)を変化できるようにしてもよい(すなわち、作業チームの編成(構成)に柔軟性を持たせてもよい)。 In the above-described first to sixth embodiments, for example, when the work is likely to be delayed in any of the construction areas A 1 to A n , the organization (configuration) of the work team may be changed according to the progress of the construction, such as by increasing the number of workers in the construction area where the work is likely to be delayed (that is, the organization (configuration) of the work team may be flexible).

前述の第1~第6実施形態では、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが一定(第1及び第3~第6実施形態では6m、第2実施形態では2m)のまま、床版架け替え施工が進行する例を示したが、この他、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが、時刻に応じて変化してもよい。すなわち、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さに柔軟性を持たせてもよい。既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが時刻に応じて変化する場合には、それに追従するように、後続の作業が適宜調整され得る。 In the above-described first to sixth embodiments, an example was shown in which the floor slab replacement construction progresses while the length in the bridge axis direction of the construction area where the work for removing the existing floor slab 5 (step S1 described above) is performed is constant (6 m in the first and third to sixth embodiments, and 2 m in the second embodiment). In addition, the length in the bridge axis direction of the construction area where the work for removing the existing floor slab 5 (step S1 described above) is performed may change depending on the time. That is, flexibility may be given to the length in the bridge axis direction of the construction area where the work of removing the existing floor slab 5 (step S1 described above) is performed. If the length in the bridge axis direction of the construction area where the removal work of the existing floor slab 5 (step S1 described above) is performed changes according to time, subsequent work can be appropriately adjusted so as to follow it.

前述の第1~第6実施形態では、施工領域A~Aの各々の橋軸方向の長さが一定(第1及び第3~第6実施形態では6m、第2実施形態では2m)であるが、この他、施工領域A~Aの各々の橋軸方向の長さが相互に異なっていてもよい。 In the first to sixth embodiments described above, the construction areas A 1 to A n have a constant length in the bridge axis direction (6 m in the first and third to sixth embodiments, and 2 m in the second embodiment). In addition, the construction areas A 1 to A n may have different lengths in the bridge axis direction.

前述の第1実施形態では、施工領域A~Aの各々において、前述のステップS31とステップS32との間に作業休止期間(図2に符号「α」に対応する期間)を設けているが、この作業休止期間は、前述のステップS31とステップS32との間に限らない。これに加えて、又は、これに替えて、前述のステップS1とステップS21との間、ステップS21とステップS22との間、ステップS22とステップS23との間、及び、ステップS23とステップS31との間、のうちの少なくとも1つに、任意に、作業休止期間を設けてもよい。この点は、第1実施形態に限らず、第2~第6実施形態においても同様である。ここにおいて、作業休止期間は、各作業の作業時間の調整代として機能し得る。 In the above-described first embodiment, in each of the construction areas A 1 to A n , a work suspension period (a period corresponding to the symbol “α” in FIG. 2) is provided between the above-described steps S31 and S32. However, this work suspension period is not limited to between the above-described steps S31 and S32. In addition to or instead of this, at least one of between steps S1 and S21, between steps S21 and S22, between steps S22 and S23, and between steps S23 and S31 may optionally be provided with an operation pause period. This point applies not only to the first embodiment but also to the second to sixth embodiments. Here, the work suspension period can function as an adjustment allowance for the work time of each work.

前述の第1~第6実施形態では、施工領域A~Aの各々の作業工程の順序が同じであるが、この他、施工領域A~Aのうちの一部の作業工程の順序が、前述の第1~第6実施形態にて説明した作業工程の順序と異なっていてもよい。 In the first to sixth embodiments described above, the order of the work processes in the construction areas A 1 to A n is the same, but the order of some of the work processes in the construction areas A 1 to A n may differ from the order of the work processes described in the first to sixth embodiments.

前述の第1~第6実施形態において、既設床版5は、プレキャストコンクリート製であってもよい(PCa床版であってもよい)。既設床版5は、場所打ちコンクリート製であってもよい。既設床版5は、鋼床版や合成床版などであってもよい。 In the first to sixth embodiments described above, the existing floor slab 5 may be made of precast concrete (or may be a PCa floor slab). The existing floor slab 5 may be made of cast-in-place concrete. The existing floor slab 5 may be a steel floor slab, a synthetic floor slab, or the like.

前述の第1~第6実施形態において、新設床版7は、ハーフプレキャストコンクリート製などの、床版の一部にプレキャストコンクリートが使用される床版であってもよい。新設床版7は、プレストレストコンクリート製であってもよい(PC床版であってもよい)。新設床版7は、鋼床版や合成床版などであってもよい。 In the above-described first to sixth embodiments, the new floor slab 7 may be a floor slab partially made of precast concrete, such as a half precast concrete floor slab. The new floor slab 7 may be made of prestressed concrete (or may be a PC floor slab). The new floor slab 7 may be a steel floor slab, a synthetic floor slab, or the like.

前述の第1~第6実施形態では、本発明の「構造物」の一例として橋梁を挙げて説明したが、本発明の「構造物」は橋梁に限らない。例えば、本発明の「構造物」が、床版を有するトンネルであってもよい。 In the first to sixth embodiments described above, a bridge was used as an example of the "structure" of the present invention, but the "structure" of the present invention is not limited to bridges. For example, the "structure" of the present invention may be a tunnel having floor slabs.

図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。
尚、特願2017-202222号の出願当初の請求項は以下の通りであった。
[請求項1]
構造物における床版の架け替え方法であって、
前記構造物を前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
各施工領域は、それぞれ、既設床版の撤去から新設床版の配置に至る複数段の作業工程を有し、
前記構造物の軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側の施工領域と、この施工領域より前記進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する、床版架け替え方法。
[請求項2]
前記進行方向前側の施工領域から前記進行方向後側の施工領域に向かうほど後段の作業工程となるように、複数段の作業工程を並行して実施する、請求項1に記載の床版架け替え方法。
[請求項3]
撤去された既設床版を前記施工領域から前記進行方向前方に搬出し、
新設床版を前記施工領域に前記進行方向後方から搬入する、請求項1又は請求項2に記載の床版架け替え方法。
[請求項4]
各施工領域がそれぞれ有する複数段の作業工程は、
当該施工領域の既設床版の撤去作業を実施する第1作業工程と、
既設床版が撤去された当該施工領域に新設床版を配置するための準備作業を実施する第2作業工程と、
前記準備作業が実施された当該施工領域に新設床版を配置する第3作業工程と、
を含む、請求項1~請求項3のいずれか1つに記載の床版架け替え方法。
[請求項5]
前記構造物は橋梁であり、
前記第2作業工程は、前記第3作業工程にて当該施工領域に配置される新設床版の配置高さを調整するための高さ調整材を前記橋梁の橋桁の上面に設けることを含む、請求項4に記載の床版架け替え方法。
[請求項6]
前記構造物は橋梁であり、
前記第2作業工程は、前記橋梁の橋桁の上面に対してケレン作業を実施することを含む、請求項4又は請求項5に記載の床版架け替え方法。
[請求項7]
仮設テント内で前記ケレン作業が実施される、請求項6に記載の床版架け替え方法。
[請求項8]
各施工領域がそれぞれ有する複数段の作業工程のうち、溶接作業を含む作業工程では、仮設テント内で前記溶接作業が実施される、請求項1~請求項7のいずれか1つに記載の床版架け替え方法。
[請求項9]
前記構造物は橋梁であり、
前記橋梁の全長にわたって新設床版の配置が完了した後に、新設床版と前記橋梁の橋桁とを固定して一体化すると共に、前記橋梁の軸方向で隣り合う新設床版同士を固定して一体化する、請求項1~請求項8のいずれか1つに記載の床版架け替え方法。
[請求項10]
前記新設床版がプレキャストコンクリート製である、請求項1~請求項9のいずれか1つに記載の床版架け替え方法。
The illustrated embodiments are merely illustrative of the present invention, and it goes without saying that the present invention includes various improvements and modifications made by those skilled in the art within the scope of the claims in addition to those directly indicated by the described embodiments.
Incidentally, the claims at the time of filing of Japanese Patent Application No. 2017-202222 were as follows.
[Claim 1]
A method for replacing a floor slab in a structure,
setting a plurality of construction areas by dividing the structure into a plurality of construction areas in the axial direction of the structure;
Each construction area has a multi-stage work process from the removal of the existing floor slab to the placement of the new floor slab,
A method for replacing floor slabs, wherein different work processes are performed in parallel in a construction area on the front side of the construction area and a construction area on the rear side of the construction area in the construction area on the front side of the construction area in the construction progress direction of floor slab construction along the axial direction of the structure.
[Claim 2]
2. The floor slab replacement method according to claim 1, wherein a plurality of work steps are performed in parallel so that work steps become later in order from the work area on the front side in the traveling direction to the work area on the rear side in the traveling direction.
[Claim 3]
carrying out the removed existing floor slab from the construction area forward in the traveling direction;
The floor slab replacement method according to claim 1 or 2, wherein the new floor slab is carried into the construction area from behind in the traveling direction.
[Claim 4]
The multi-stage work process that each construction area has,
a first work process for removing the existing floor slabs in the construction area;
a second work process for performing preparatory work for arranging a new floor slab in the construction area from which the existing floor slab has been removed;
a third work step of arranging a new floor slab in the construction area where the preparatory work has been performed;
The floor slab replacement method according to any one of claims 1 to 3, comprising
[Claim 5]
the structure is a bridge;
5. The floor slab replacement method according to claim 4, wherein the second work step includes providing a height adjusting material on the upper surface of the bridge girder of the bridge for adjusting the placement height of the new floor slabs placed in the construction area in the third work step.
[Claim 6]
the structure is a bridge;
The floor slab replacement method according to claim 4 or 5, wherein the second work step includes performing a scraping work on the upper surface of the bridge girder of the bridge.
[Claim 7]
The floor slab replacement method according to claim 6, wherein the cleaning work is performed in a temporary tent.
[Claim 8]
The floor slab replacement method according to any one of claims 1 to 7, wherein the welding work is performed in a temporary tent in the work process including the welding work among the work processes of the plurality of stages that each construction area has.
[Claim 9]
the structure is a bridge;
The floor slab replacement method according to any one of claims 1 to 8, wherein after the placement of the new floor slabs over the entire length of the bridge is completed, the new floor slabs and the bridge girders of the bridge are fixed and integrated, and the new floor slabs adjacent to each other in the axial direction of the bridge are fixed and integrated.
[Claim 10]
The floor slab replacement method according to any one of claims 1 to 9, wherein the new floor slab is made of precast concrete.

1 橋梁
2a,2b 橋台
3 橋脚
4 橋桁
4a 上面
4f 上フランジ
4w ウェブ
5 既設床版
5a 床版片
5b 切断線
7 新設床版
7a 貫通孔
7b 下面
9 空間
10 仮設テント
20,30 クレーン装置
21,31 下部フレーム
22,32 門型フレーム
23,33 上部フレーム
24,34 吊上装置
40 搬送台車
50a,50b ジャッキ
51 梁部材
52 PC鋼棒
53a,53b 固定部材
60 フランジシール
70 高さ調整材
80 スタッドジベル
~A~A 施工領域
1 Bridge 2a, 2b Abutment 3 Bridge Pier 4 Bridge Girder 4a Upper Surface 4f Upper Flange 4w Web 5 Existing Floor Slab 5a Floor Slab Piece 5b Cutting Line 7 New Floor Slab 7a Through Hole 7b Lower Surface 9 Space 10 Temporary Tent 20, 30 Crane Device 21, 31 Lower Frame 22, 32 Gate Frame 23, 33 Upper Frame 24, 3 4 Lifting device 40 Carrier 50a, 50b Jack 51 Beam member 52 PC steel rod 53a, 53b Fixing member 60 Flange seal 70 Height adjustment member 80 Stud dowel A 1 to A k to An construction area

Claims (12)

橋桁を有する構造物において、前記橋桁上に配設される床版を既設床版から新設床版に架け替える方法であって、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、前記準備作業は、前記橋桁の上面に対するケレン作業と、前記橋桁の上面に対する高さ調整材の設置作業と、を含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記構造物の軸方向に複数の施工領域を設定し、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記新設床版配置準備工程を実施する第2施工領域と、前記新設床版配置工程を実施する第3施工領域と、が並び、
前記第2施工領域では、前記進行方向前側から後側に向かって順に、前記ケレン作業を実施するケレン作業施工領域と、前記高さ調整材の設置作業を実施する高さ調整材設置作業施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第1施工領域と前記第2施工領域と前記第3施工領域とは、床版架け替え施工の進行に伴い前記進行方向に前進し、
前記橋桁上の既設の床版上を走行する運搬車両によって、前記床版片を、前記第1クレーン装置から前記進行方向前方に搬出し、
前記橋桁上に新設された床版上を走行する搬送台車によって、前記新設床版を、前記第2クレーン装置に前記進行方向後方から搬入する、床版架け替え方法。
In a structure having a bridge girder, a method for replacing a floor slab arranged on the bridge girder from an existing floor slab to a new floor slab,
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process,
The existing floor slab removal step includes removing floor slab pieces of the existing floor slab,
The new floor slab placement preparation step includes preparing to place a new floor slab on the bridge girder from which the floor slab pieces have been removed, and the preparation work includes cleaning the upper surface of the bridge girder and installing height adjustment materials on the upper surface of the bridge girder.
The new floor slab placement step includes placing a new floor slab on the bridge girder for which the preparatory work has been performed,
setting a plurality of construction areas in the axial direction of the structure;
In the floor slab replacement construction progress direction along the axial direction, a first construction area in which the existing floor slab removal process is performed, a second construction area in which the new floor slab placement preparation process is performed, and a third construction area in which the new floor slab placement process is performed are arranged in order from the front side to the rear side of the direction of travel.
In the second construction area, in order from the front side to the rear side in the traveling direction, a cleaning work execution area where the cleaning work is performed and a height adjustment material installation work execution area where the height adjustment material installation work is performed.
A first crane device used in the existing floor slab removal process is positioned on the existing floor slab on the bridge girder,
A second crane device used in the new floor slab placement process is positioned on the floor slab newly installed on the bridge girder,
The first construction area, the second construction area, and the third construction area move forward in the direction of movement as the floor slab replacement construction progresses,
Carrying out the floor slab pieces forward in the traveling direction from the first crane device by a transport vehicle traveling on the existing floor slab on the bridge girder;
A floor slab replacement method, wherein the new floor slab is carried into the second crane device from behind in the direction of travel by a transport vehicle that travels on the floor slab newly installed on the bridge girder.
前記ケレン作業施工領域における前記ケレン作業と、前記高さ調整材設置作業施工領域における前記高さ調整材の設置作業と、を同時に実施する、請求項1に記載の床版架け替え方法。 The floor slab replacement method according to claim 1, wherein the cleaning work in the cleaning work execution area and the installation work of the height adjustment material in the height adjustment material installation work execution area are performed simultaneously. 前記第1施工領域における前記既設床版撤去工程と、前記第3施工領域における前記新設床版配置工程と、を同時に実施する、請求項1又は請求項2に記載の床版架け替え方法。 The floor slab replacement method according to claim 1 or 2, wherein the existing floor slab removal step in the first construction area and the new floor slab placement step in the third construction area are performed simultaneously. 前記床版片は、前記既設床版を切断して形成されるものであり、
前記第2施工領域の前記軸方向の長さが、前記床版片の前記軸方向の長さの6倍以上である、請求項1~請求項3のいずれか1つに記載の床版架け替え方法。
The floor slab piece is formed by cutting the existing floor slab,
The floor slab replacement method according to any one of claims 1 to 3, wherein the axial length of the second construction area is six times or more the axial length of the floor slab piece.
前記新設床版はプレキャストコンクリート製又はハーフプレキャストコンクリート製であり、
前記第2施工領域の前記軸方向の長さが、前記新設床版の前記軸方向の長さの6倍以上である、請求項1~請求項3のいずれか1つに記載の床版架け替え方法。
The new floor slab is made of precast concrete or half precast concrete,
The floor slab replacement method according to any one of claims 1 to 3, wherein the axial length of the second construction area is at least six times the axial length of the new floor slab.
前記第2施工領域の前記軸方向の長さが12m以上である、請求項1~請求項3のいずれか1つに記載の床版架け替え方法。 The floor slab replacement method according to any one of claims 1 to 3, wherein the axial length of the second construction area is 12 m or more. 橋桁を有する構造物において、前記橋桁上に配設される床版を既設床版から新設床版に架け替える方法であって、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、前記準備作業は、前記橋桁の上面に対するケレン作業と、前記橋桁の上面に対するシールの設置作業と、を含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記構造物の軸方向に複数の施工領域を設定し、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記新設床版配置準備工程を実施する第2施工領域と、前記新設床版配置工程を実施する第3施工領域と、が並び、
前記第2施工領域では、前記進行方向前側から後側に向かって順に、前記ケレン作業を実施するケレン作業施工領域と、前記シールの設置作業を実施するシール設置作業施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第1施工領域と前記第2施工領域と前記第3施工領域とは、床版架け替え施工の進行に伴い前記進行方向に前進し、
前記橋桁上の既設の床版上を走行する運搬車両によって、前記床版片を、前記第1クレーン装置から前記進行方向前方に搬出し、
前記橋桁上に新設された床版上を走行する搬送台車によって、前記新設床版を、前記第2クレーン装置に前記進行方向後方から搬入する、床版架け替え方法。
In a structure having a bridge girder, a method for replacing a floor slab arranged on the bridge girder from an existing floor slab to a new floor slab,
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process,
The existing floor slab removal step includes removing floor slab pieces of the existing floor slab,
The new floor slab placement preparation step includes preparing to place a new floor slab on the bridge girder from which the floor slab pieces have been removed, and the preparation work includes cleaning the upper surface of the bridge girder and installing a seal on the upper surface of the bridge girder.
The new floor slab placement step includes placing a new floor slab on the bridge girder for which the preparatory work has been performed,
setting a plurality of construction areas in the axial direction of the structure;
In the floor slab replacement construction progress direction along the axial direction, a first construction area in which the existing floor slab removal process is performed, a second construction area in which the new floor slab placement preparation process is performed, and a third construction area in which the new floor slab placement process is performed are arranged in order from the front side to the rear side of the direction of travel.
In the second construction area, a cleaning work construction area for performing the cleaning work and a seal installation work construction area for performing the seal installation work are arranged in order from the front side to the rear side in the traveling direction,
A first crane device used in the existing floor slab removal process is positioned on the existing floor slab on the bridge girder,
A second crane device used in the new floor slab placement process is positioned on the floor slab newly installed on the bridge girder,
The first construction area, the second construction area, and the third construction area move forward in the direction of movement as the floor slab replacement construction progresses,
Carrying out the floor slab pieces forward in the traveling direction from the first crane device by a transport vehicle traveling on the existing floor slab on the bridge girder;
A floor slab replacement method, wherein the new floor slab is carried into the second crane device from behind in the direction of travel by a transport vehicle that travels on the floor slab newly installed on the bridge girder.
前記ケレン作業施工領域における前記ケレン作業と、前記シール設置作業施工領域における前記シールの設置作業と、を同時に実施する、請求項7に記載の床版架け替え方法。 The floor slab replacement method according to claim 7, wherein the cleaning work in the cleaning work execution area and the seal installation work in the seal installation work execution area are performed simultaneously. 前記第1施工領域における前記既設床版撤去工程と、前記第3施工領域における前記新設床版配置工程と、を同時に実施する、請求項7又は請求項8に記載の床版架け替え方法。 The floor slab replacement method according to claim 7 or 8, wherein the existing floor slab removal step in the first construction area and the new floor slab placement step in the third construction area are performed simultaneously. 前記床版片は、前記既設床版を切断して形成されるものであり、
前記第2施工領域の前記軸方向の長さが、前記床版片の前記軸方向の長さの6倍以上である、請求項7~請求項9のいずれか1つに記載の床版架け替え方法。
The floor slab piece is formed by cutting the existing floor slab,
The floor slab replacement method according to any one of claims 7 to 9, wherein the axial length of the second construction area is six times or more the axial length of the floor slab piece.
前記新設床版はプレキャストコンクリート製又はハーフプレキャストコンクリート製であり、
前記第2施工領域の前記軸方向の長さが、前記新設床版の前記軸方向の長さの6倍以上である、請求項7~請求項9のいずれか1つに記載の床版架け替え方法。
The new floor slab is made of precast concrete or half precast concrete,
The floor slab replacement method according to any one of claims 7 to 9, wherein the axial length of the second construction area is six times or more the axial length of the new floor slab.
前記第2施工領域の前記軸方向の長さが12m以上である、請求項7~請求項9のいずれか1つに記載の床版架け替え方法。 The floor slab replacement method according to any one of claims 7 to 9, wherein the axial length of the second construction area is 12 m or more.
JP2023088815A 2023-01-12 2023-05-30 Floor slab replacement method Pending JP2023101672A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2023088815A JP2023101672A (en) 2023-01-12 2023-05-30 Floor slab replacement method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2023003216A JP2023029610A (en) 2017-10-18 2023-01-12 Slab replacement method
JP2023088815A JP2023101672A (en) 2023-01-12 2023-05-30 Floor slab replacement method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2023003216A Division JP2023029610A (en) 2017-10-18 2023-01-12 Slab replacement method

Publications (1)

Publication Number Publication Date
JP2023101672A true JP2023101672A (en) 2023-07-21

Family

ID=85331387

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2023088815A Pending JP2023101672A (en) 2023-01-12 2023-05-30 Floor slab replacement method

Country Status (1)

Country Link
JP (1) JP2023101672A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015229818A (en) * 2014-06-03 2015-12-21 オリエンタル白石株式会社 Composite structure of steel girder and precast floor slab, and construction method therefor

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015229818A (en) * 2014-06-03 2015-12-21 オリエンタル白石株式会社 Composite structure of steel girder and precast floor slab, and construction method therefor

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
伊藤寛彦 保科和利 栗原悠: "鋼橋のPC床版架設の施工", 第19回土木施工管理技術論文集, JPN6022013518, 2 June 2015 (2015-06-02), JP, pages 13 - 16, ISSN: 0005139868 *
本間修平: "計画工程を維持するために取り組んだ『床版取替』について", 第19回土木施工管理技術論文報告集, JPN6022013515, 2 June 2015 (2015-06-02), JP, pages 53 - 56, ISSN: 0005139867 *

Similar Documents

Publication Publication Date Title
JP7442256B2 (en) How to replace the floor slab
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
JP3954869B2 (en) Bridge girder replacement method
JP2018104972A (en) Floor slab erection method and floor slab erection device
JP5184248B2 (en) Construction method of level crossing
JP2019120115A (en) Method of constructing tunnel lining structure
JP7148746B2 (en) Floor slab replacement method
JP2023101672A (en) Floor slab replacement method
JP2006214269A (en) Erected girder
JP2023029610A (en) Slab replacement method
JPH08170486A (en) Tunnel excavated muck carry-out gantry
JP5613294B1 (en) Bridge repair method
JP5769291B2 (en) Precast synthetic slab erection method
JP2018204303A (en) Reinforced cage positioning system
JP2004263551A (en) Method for constructing underground structure and supporting structure of ground structure
JP7483507B2 (en) Bridge deck replacement method
JP2019173435A (en) Floor system replacement method and floor system replacement device
JP6549411B2 (en) Floor construction method of shield tunnel
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JPH08165881A (en) Tunnel excavating method
JP2012180678A (en) Replacement method of water elevated structure
JP2020164884A (en) Construction method of rail track for carriage travelling
JP2021188454A (en) Bridge floor slab replacement method
JP2017052160A (en) Method for producing precast concrete floor slab and precast concrete floor slab
JP7451391B2 (en) Bridge girder replacement method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230530

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20230530

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230829

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20240305