JP2021188454A - Bridge floor slab replacement method - Google Patents

Bridge floor slab replacement method Download PDF

Info

Publication number
JP2021188454A
JP2021188454A JP2020097190A JP2020097190A JP2021188454A JP 2021188454 A JP2021188454 A JP 2021188454A JP 2020097190 A JP2020097190 A JP 2020097190A JP 2020097190 A JP2020097190 A JP 2020097190A JP 2021188454 A JP2021188454 A JP 2021188454A
Authority
JP
Japan
Prior art keywords
floor slab
bridge
deck
time zone
replacement method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2020097190A
Other languages
Japanese (ja)
Other versions
JP7484439B2 (en
Inventor
康太 丈達
Kota Jotatsu
重洋 岡
Shigehiro Oka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2020097190A priority Critical patent/JP7484439B2/en
Publication of JP2021188454A publication Critical patent/JP2021188454A/en
Application granted granted Critical
Publication of JP7484439B2 publication Critical patent/JP7484439B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)

Abstract

To provide a bridge floor slab replacement method that can efficiently replace an existing floor slab with a new precast concrete floor slab.SOLUTION: A bridge floor slab replacement method includes: a first step of removing at least a part of an existing floor slab piece formed by dividing an existing floor slab of a bridge in the bridge axis direction to expose a main girder; a second step of installing a stud dowel on the upper surface of the main girder exposed in the first step; and a third step of installing a plurality of new floor slabs on the main girder on which the stud dowel is installed in the second step and joining the new floor slabs to the main girder and then joining the adjacent new floor slabs. The first step to the third step are performed during a construction traffic regulation time zone and include cases where two or more steps are continuously carried out within the construction traffic regulation time zone. When the first step or the second step is carried out immediately before a traffic release time zone comes, a temporary lining floor slab is installed on the main girder which is exposed at the end of the work.SELECTED DRAWING: Figure 4

Description

本発明は、工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、既設床版をプレキャスト造の新設床版に取替える、橋梁の床版取替え工法に関する。 The present invention relates to a bridge floor slab replacement method in which an existing floor slab is replaced with a new precast floor slab while alternately repeating a construction traffic regulation time zone and a traffic release time zone.

従来より、上り車線用の橋梁と下り車線用の橋梁とを備える大規模な道路橋において、橋梁の既設床版を新設床版に取替える更新工事を行う際には、上り車線用と下り車線用の橋梁のうち、いずれか一方の橋梁を全面通行止めにして更新工事を行い、他方の橋梁を対面通行規制している。 Conventionally, in a large-scale road bridge equipped with a bridge for the up lane and a bridge for the down lane, when performing renewal work to replace the existing floor slab of the bridge with a new floor slab, it is for the up lane and the down lane. Of the bridges in the above, one of the bridges is completely closed to renewal work, and the other bridge is restricted to face-to-face traffic.

しかし、都市部等の重交通路や長大トンネルに挟まれた山間部等では、長期間にわたって対面通行規制を実施すると、周辺地域の交通環境に悪影響を及ぼしかねない。このため、夜間のみ車線規制を行って更新工事を行い、昼間は全面交通解放する方法が望まれている。例えば、特許文献1には、夜間に道路規制を行って既設床版を新設床版に取替える橋梁床版の施工方法として、作業者をPC床版敷設班と間詰めコンクリート班に分けて実施する方法が開示されている。 However, in heavy traffic routes such as urban areas and mountainous areas sandwiched between long tunnels, if face-to-face traffic restrictions are enforced for a long period of time, the traffic environment in the surrounding area may be adversely affected. For this reason, there is a demand for a method of restricting lanes only at night, performing renewal work, and completely releasing traffic during the day. For example, in Patent Document 1, as a method of constructing a bridge deck that regulates roads at night and replaces an existing deck with a new deck, workers are divided into a PC deck laying group and a padded concrete group. The method is disclosed.

具体的には、PC床版敷設班が、主桁上の既設床版の切断・撤去したのち、新設のプレキャスト床版を橋軸方向に並列に敷設し、隣り合うプレキャスト床版の目地を仮覆工版で覆う。こののち、仮覆工版の上面に仮舗装を行って、一夜分の作業を終了する。PC床版敷設班は、取替え予定区間の床版を撤去し終えるまで、この作業を毎日繰り返す。 Specifically, after the PC floor slab laying group cuts and removes the existing floor slab on the main girder, a new precast floor slab is laid in parallel in the direction of the bridge axis, and the joints of the adjacent precast floor slabs are provisionally laid. Cover with a lining plate. After that, temporary pavement is performed on the upper surface of the temporary lining plate, and the work for one night is completed. The PC floor slab laying team repeats this work every day until the floor slab in the planned replacement section is removed.

一方、間詰めコンクリート班は数日遅れて作業を開始し、橋軸方向に並列に敷設された新設のプレキャスト床版から仮舗装及び仮覆工床版を撤去するとともに、隣り合う新設のプレキャスト床版の目地に間詰めコンクリートを打設する。そして、間詰めコンクリートの養生が終了したのちに仮舗装を行って、一夜分の作業を終了する。間詰めコンクリート班は、取替え予定区間に敷設された隣り合う新設のプレキャスト床版床版の目地すべてに間詰めコンクリートを打設し終えるまで、この作業を毎日繰り返す。 On the other hand, the padded concrete team started work a few days later, removing the temporary pavement and temporary lining deck from the new precast deck laid in parallel in the direction of the bridge axis, and the adjacent new precast floor. Pave concrete is placed at the joints of the slab. Then, after the curing of the padded concrete is completed, temporary pavement is performed to complete the work for one night. The padded concrete team repeats this work every day until the padded concrete has been placed in all the joints of the adjacent new precast deck slabs laid in the planned replacement section.

特開2012−82622号公報Japanese Unexamined Patent Publication No. 2012-82222

上記のとおり、特許文献1では、既設床版を新設のプレキャスト床版に取替えるための一連の作業のうち、新設のプレキャスト床版を敷設するまでの作業を、一夜分とすることを前提としている。しかし、特許文献1では明らかにされていないが、一般に、既設床版の撤去後に露出する主桁の上面に、ケレン作業やスタッドジベルの設置作業等の様々な処理が必要となる。 As described above, Patent Document 1 presupposes that, of the series of work for replacing the existing precast deck with the new precast deck, the work until the new precast deck is laid is for one night. .. However, although not clarified in Patent Document 1, in general, various treatments such as cleaning work and stud gibber installation work are required on the upper surface of the main girder exposed after the removal of the existing floor slab.

これらの煩雑な作業を考慮すると、工事中に何らかの不慮の事態が生じた場合には、新設のプレキャスト床版を敷設するまでの作業を一夜では終了できない恐れが生じる。また、一夜で終了できたとしても、既設床版を新設のプレキャスト床版に取替えるための一連の作業工程のうち、交通解放を実施できるタイミングは、この新設のプレキャスト床版の敷設後であって間詰めコンクリートを打設する直前の期間に限定される。 Considering these complicated works, if any unexpected situation occurs during the construction, there is a possibility that the work up to the laying of the new precast deck cannot be completed overnight. In addition, even if it can be completed overnight, in the series of work processes for replacing the existing floor slab with the new precast floor slab, the timing when traffic release can be carried out is after the laying of this new precast floor slab. Limited to the period immediately before placing the precast concrete.

このため、現場条件や施工状況等に応じて、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整することは困難である。また、前述したように、新設のプレキャスト床版を敷設するまでの作業を一夜分とすることを前提としているため、新設床版を敷設したのち、目地に間詰コンクリートを打設し本舗装するまでの一連の作業を、一夜で実施するための方法も明示されていない。 For this reason, it is difficult to adjust the progress of the work process to be carried out within one construction traffic regulation time zone according to the site conditions, construction conditions, and the like. In addition, as mentioned above, since it is assumed that the work until the new precast floor slab is laid for one night, after laying the new floor slab, the interstitial concrete is poured into the joints and the main pavement is carried out. The method for carrying out the series of work up to overnight is not specified.

本発明は、かかる課題に鑑みなされたものであって、その主な目的は、効率よく既設床版をプレキャストコンクリート造の新設床版に取換えることの可能な、橋梁の床版取替え工法を提供することである。 The present invention has been made in view of the above problems, and a main object thereof is to provide a bridge deck replacement method capable of efficiently replacing an existing deck with a new precast concrete deck. It is to be.

かかる目的を達成するため、本発明の橋梁の床版取替え工法は、工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、鋼製の主桁上に設置された既設床版をプレキャストコンクリート造の新設床版に取替える橋梁の床版取替え工法であって、橋梁の既存床版を橋軸方向に分割して形成した複数の既存床版片のうち、少なくとも一部を撤去して前記主桁を露出させる第1の工程と、前記第1の工程で露出させた前記主桁上面に、スタッドジベルを設置する第2の工程と、前記第2の工程で前記スタッドジベルを設置した前記主桁上に、複数の前記新設床版を据え付け、前記新設床版を前記主桁に接合させたのち、隣り合う新設床版を接合する第3の工程と、を備え、前記第1の工程から前記第3の工程は、前記工事交通規制時間帯に実施されるとともに、1回の前記工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含み、前記交通解放時間帯が到来する直前に前記第1の工程もしくは前記第2の工程が実施される場合、作業終了時において露出状態にある前記主桁上に、仮覆工床版を設置することを特徴とする。 In order to achieve this object, the bridge deck replacement method of the present invention precasts an existing deck installed on a steel main girder while alternately repeating a construction traffic regulation time zone and a traffic release time zone. It is a method of replacing a deck deck with a new concrete deck, and at least a part of the existing deck pieces formed by dividing the existing deck of the bridge in the direction of the bridge axis is removed. The first step of exposing the main girder, the second step of installing the stud gibber on the upper surface of the main girder exposed in the first step, and the above-mentioned step of installing the stud gibber in the second step. A third step of installing a plurality of the new floor slabs on the main girder, joining the new floor slabs to the main girder, and then joining adjacent new floor slabs is provided, and the first step is provided. The third step is carried out during the construction traffic regulation time zone, and includes a case where two or more steps are continuously carried out within one construction traffic regulation time zone, and the traffic release time. When the first step or the second step is carried out immediately before the arrival of the band, it is characterized in that a temporary lining deck is installed on the main girder which is exposed at the end of the work. ..

本発明の橋梁の床版取替え工法は、前記第1の工程から前記第3の工程を、前記工事交通規制時間帯が到来するごとに橋軸方向に繰り返すことを特徴とする。 The bridge deck replacement method of the present invention is characterized in that the first step to the third step are repeated in the direction of the bridge axis each time the construction traffic regulation time zone arrives.

本発明の橋梁の床版取替え工法によれば、既設床版を新設床版に取替えるために必要な作業工程を、工事の中断が可能な第1の工程から第3の工程に分割する。そのうえで、これらの工程を工事交通規制時間帯に実施するにあたり、1回の工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含むようにして、工事交通規制時間帯と交通解放時間帯を繰り返す。これにより、現場条件や施工状況(例えば、ケレン作業やスタッドジベルの設置作業等の進捗状況)に応じて工事を中断する段階を適宜選択できるため、交通解放時間帯の到来に備えつつ、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整することができ、効率よく新設床版の取り換え作業を実施することが可能となる。 According to the bridge floor slab replacement method of the present invention, the work process required for replacing the existing floor slab with the new floor slab is divided into a first step and a third step in which the construction can be interrupted. In addition, when carrying out these processes during the construction traffic regulation time zone, include the case where two or more processes are continuously carried out within one construction traffic regulation time zone, and the construction traffic regulation time zone and traffic release. Repeat the time zone. As a result, the stage of suspending the construction can be appropriately selected according to the site conditions and the construction status (for example, the progress status of the cleaning work and the installation work of the stud gibber), so that once while preparing for the arrival of the traffic release time zone. It is possible to adjust the progress of the work process to be carried out within the construction traffic regulation time zone, and it is possible to efficiently carry out the replacement work of the new floor slab.

したがって、工事交通規制時間帯を夜間に設定すれば、昼間の交通解放を実現することができ、既設床版取替え工法を実施しようとする橋梁が都市部等の重交通路上や長大トンネルに挟まれた山間部等にある場合にも、周辺地域の交通環境への影響を最小限に抑えつつ施工を実施することが可能となる。 Therefore, if the construction traffic regulation time zone is set at night, it is possible to realize the daytime traffic release, and the bridge that is going to implement the existing floor slab replacement method is sandwiched between heavy traffic roads such as urban areas and long tunnels. Even if it is located in a mountainous area, it is possible to carry out the construction while minimizing the impact on the traffic environment in the surrounding area.

また、本発明の橋梁の床版取替え工法は、前記既存床版片の橋軸方向からみた断面が、前記既存床版の横断面を半分に分割した半断面に形成されることを特徴とする。 Further, the deck replacement method for a bridge of the present invention is characterized in that the cross section of the existing deck piece seen from the bridge axis direction is formed into a half cross section obtained by dividing the cross section of the existing deck in half. ..

本発明の橋梁の床版取替え工法によれば、既存床版の横断面を半分に分割し、いずれか一方の半断面分の既設床版を橋軸方向に分割して複数の既存床版片を形成し、これを撤去して新設床版に取替える、いわゆる半断面床版取替え工法に採用することが可能となる。これにより、例えば、上り車線用の橋梁と下り車線用の橋梁とを備える大規模な道路橋において、いずれか一方の橋梁を交通解放したまま、他方の橋梁の車線数を減少させる規制を夜間に行えば、昼間の全面交通解放を実現しながら、既設床版の取替え工事を実施することが可能となる。 According to the bridge deck replacement method of the present invention, the cross section of the existing deck is divided in half, and the existing deck for one of the half sections is divided in the direction of the bridge axis to obtain a plurality of existing deck pieces. It is possible to use it in the so-called semi-section floor slab replacement method, in which the floor slab is removed and replaced with a new floor slab. As a result, for example, in a large-scale road bridge equipped with a bridge for an up lane and a bridge for a down lane, a regulation to reduce the number of lanes of the other bridge while leaving one of the bridges free for traffic is imposed at night. If done, it will be possible to replace the existing floor slab while realizing full daytime traffic release.

したがって、従来工法のような、いずれか一方の橋梁を全面通行止めにして工事を行い、他方の橋梁を対面通行規制とするといった道路規制を行う必要が無い。このため、通行車両に対する安全性の確保が可能になるとともに、道路構造等の事情により対面通行規制を実施できない、または、実施が可能であっても周辺地域の交通状況によっては長期間の対面通行規制が困難である等、様々な課題を有する道路環境にあっても、既設床版の取替え工事を確実に実施することが可能となる。 Therefore, unlike the conventional construction method, it is not necessary to carry out road regulation such that one of the bridges is completely closed to traffic and the other bridge is restricted to two-way traffic. For this reason, it is possible to ensure the safety of passing vehicles, and it is not possible to implement face-to-face traffic restrictions due to circumstances such as road structure, or even if it is possible, long-term face-to-face traffic may be implemented depending on the traffic conditions in the surrounding area. Even in a road environment with various issues such as difficulty in regulation, it is possible to reliably carry out replacement work for existing floor slabs.

また、本発明の橋梁の床版取替え工法は、第3の工程で、隣り合う新設床版を、該新設床板の一部として機能する本設プレートで接合することを特徴とする。 Further, the floor slab replacement method for a bridge of the present invention is characterized in that, in a third step, adjacent new floor slabs are joined by a main plate that functions as a part of the new floor plate.

本発明の橋梁の床版取替え工法によれば、新設床板の一部として機能する本設プレートで隣り合う新設床版を接合するから、この本設プレートを、隣り合う新設床版により形成される目地部の上面に配置することにより、目地部に間詰コンクリートを充填する作業に先立って、本舗装を施す作業を優先して実施することができる。これにより、本舗装を施したのちに交通解放を行いつつ、目地部に新設床版の下方側から間詰めコンクリートの充填することができるため、工事交通規制時間帯に実施する作業を減らすことができ、作業効率を大幅に向上することが可能となる。 According to the floor slab replacement method for bridges of the present invention, adjacent new floor slabs are joined by a main plate that functions as a part of the new floor plate, so that this main plate is formed by the adjacent new floor slabs. By arranging it on the upper surface of the joint portion, it is possible to prioritize the work of applying the main pavement prior to the work of filling the joint portion with the interstitial concrete. As a result, it is possible to fill the joints with padded concrete from the lower side of the new floor slab while releasing traffic after the main pavement is applied, reducing the work to be carried out during construction traffic regulation hours. It is possible to greatly improve work efficiency.

本発明の橋梁の床版取替え工法は、前記主桁上に前記仮覆工床版を設置したのち、該仮覆工床版に隣接する目地の上下面をそれぞれ開口塞ぎ板で覆い、該開口塞ぎ板どうしを締結具を介して締結することを特徴とする。 In the bridge floor slab replacement method of the present invention, after the temporary lining floor slab is installed on the main girder, the upper and lower surfaces of the joints adjacent to the temporary lining floor slab are covered with opening closing plates, and the opening is opened. It is characterized in that the closing plates are fastened to each other via a fastener.

本発明の橋梁の床版取替え工法によれば、主桁上に仮覆工床版を設置した際、この仮覆工床版に隣接して形成される目地部の間詰処理を、開口塞ぎ板を利用して容易に実施できるため、充填材を充填する場合と比較して設置及び撤去に係る作業性を大幅に向上し、工期短縮に貢献することが可能となる。 According to the bridge floor slab replacement method of the present invention, when the temporary lining floor slab is installed on the main girder, the opening of the joints formed adjacent to the temporary lining floor slab is closed. Since it can be easily carried out using a plate, it is possible to greatly improve the workability related to installation and removal as compared with the case of filling with a filler, and to contribute to shortening the construction period.

本発明によれば、現場条件や施工状況等に応じて作業を中断する段階を適宜選択できるため、交通解放時間帯の到来に備えて、車線規制時間帯を有効に活用しつつ、効率よく新設床版の取り換え作業を実施することが可能となる。 According to the present invention, it is possible to appropriately select the stage at which the work is interrupted according to the site conditions, the construction situation, etc. Therefore, in preparation for the arrival of the traffic release time zone, the lane regulation time zone is effectively utilized and the new construction is efficiently established. It becomes possible to carry out the replacement work of the floor slab.

本発明の実施の形態における半断面床版取替え工法を説明する図である。It is a figure explaining the half-section floor slab replacement method in embodiment of this invention. 本発明の実施の形態における半断面床板取替え工法の流れを示す図である。It is a figure which shows the flow of the half-section floor board replacement method in embodiment of this invention. 本発明の実施の形態における半断面床板取替え工法の概略を示す図である。It is a figure which shows the outline of the half-section floor board replacement method in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の流れを示す図である。It is a figure which shows the flow of the floor slab replacement method of a bridge in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の概略を示す図である。It is a figure which shows the outline of the floor slab replacement method of a bridge in embodiment of this invention. 本発明の実施の形態における仮覆工床版を示す図である。It is a figure which shows the temporary lining floor slab in embodiment of this invention. 本発明の実施の形態におけるプレキャストコンクリート造の新設床版を示す図である。It is a figure which shows the new floor slab of a precast concrete structure in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の第1の工程を示す図である。It is a figure which shows the 1st process of the floor slab replacement method of a bridge in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の仮間詰めの様子を示す図である。It is a figure which shows the state of the temporary space filling of the floor slab replacement method of a bridge in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の第2の工程を示す図である。It is a figure which shows the 2nd process of the floor slab replacement method of a bridge in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の第3の工程を示す図である。It is a figure which shows the 3rd process of the floor slab replacement method of a bridge in embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の第1〜第3の工程を繰り返した際の本舗装の手順を示す図である。It is a figure which shows the procedure of the main pavement when the 1st to 3rd steps of the floor slab replacement method of a bridge in embodiment of this invention are repeated. 本発明の実施の形態における走行車線の新設床版と追い越し車線の新設床版との接合を示す図である。It is a figure which shows the joining of the new floor slab of a traveling lane and the new floor slab of an overtaking lane in the embodiment of the present invention. 本発明の実施の形態における走行車線と追い越し車線の施工手順の事例を示す図である。It is a figure which shows the example of the construction procedure of the traveling lane and the overtaking lane in the embodiment of this invention. 本発明の実施の形態における橋梁の床版取替え工法の他の事例を示す図である。It is a figure which shows the other example of the floor slab replacement method of a bridge in embodiment of this invention.

本発明の橋梁の床版取替え工法は、車線規制時間帯および通行止め規制時間帯の両者を含む工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、既設床版を新設床版に取替える方法であって、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整することの可能な方法である。 In the bridge floor slab replacement method of the present invention, the existing floor slab is replaced with a new floor slab while alternately repeating the construction traffic regulation time zone and the traffic release time zone including both the lane regulation time zone and the traffic closure regulation time zone. It is a method that can adjust the progress of the work process to be carried out within one construction traffic regulation time zone.

このような橋梁の床版取替え工法は、施工車線の通行止めを行う全断面施工に採用することも可能な工法であるが、本実施の形態では、橋梁の床版取替え工法を半断面床版取替え工法に採用する場合を事例に挙げ、詳細を説明する。 Such a bridge floor slab replacement method can be adopted for all-section construction that closes the construction lane, but in this embodiment, the bridge floor slab replacement method is replaced with a half-section floor slab. The details will be explained by taking as an example the case of adopting it in the construction method.

≪≪半断面床版取替え工法≫≫
半断面床版取替え工法は、図1(a)で示すように、例えば、上り2車線用の橋梁B1と下り2車線用の橋梁B2を備える道路橋Bにおいて、橋梁B1を車線規制し、走行車線側と追い越し車線側の、いずれか一方の半断面分の既設床版1を新設床版に取替え、これと前後して、他方側の半断面分の既設床版1も同様に新設床版に取替える方法である。
≪≪Semi-section floor slab replacement method≫≫
As shown in FIG. 1A, in the half-section deck replacement method, for example, in a road bridge B provided with a bridge B1 for two up lanes and a bridge B2 for two down lanes, the bridge B1 is lane-controlled and traveled. The existing floor slab 1 for one half section of either the lane side or the overtaking lane side is replaced with a new floor slab, and before and after this, the existing floor slab 1 for the other half cross section is also a new floor slab. It is a method to replace with.

以下に、半断面床版取替え工法の流れを、図2のフロー図に沿って図3を参照しつつ説明すると、まず、図3(a)で示すように、上り2車線用の橋梁B1について、施工対象領域を橋軸方向に区分けし、複数の区画を設定する(第1ステップ)。 The flow of the half-section floor slab replacement method will be described below with reference to FIG. 3 along with the flow chart of FIG. 2. First, as shown in FIG. 3A, the bridge B1 for two lanes going up , The construction target area is divided in the direction of the bridge axis, and multiple sections are set (first step).

次に、図3(b)で示すように、各区画を橋軸直交方向に分割し、走行車線側を作業区画D1、D2、D3・・に設定するとともに追い越し車線側を作業区画O1、O2、O3・・に設定する(第2ステップ)。 Next, as shown in FIG. 3B, each section is divided in the direction orthogonal to the bridge axis, the traveling lane side is set to the working sections D1, D2, D3, and the overtaking lane side is set to the working sections O1, O2. , O3 ... (2nd step).

作業区画が設定されたところで、1区画目の走行車線側の作業区画D1に対して床版取替え工法を実施する(第3−1ステップ)。次に、1区画目の追い越し車線側の作業区画O1に対して床版取替え工法を実施する(第3−1ステップ)。 When the work section is set, the floor slab replacement method is carried out for the work section D1 on the driving lane side of the first section (step 3-1). Next, the floor slab replacement method is carried out for the work section O1 on the overtaking lane side of the first section (step 3-1).

以下、作業区画D1に着目し、床版取替え工法を説明する。本実施の形態では、図1(b)で示すように作業区画D1内の既設床版1を、上り2車線の上流側(図1の橋軸方向右側)から下流側(図1の橋軸方向左側)に向けて順次新設床版3に取替えていく。 Hereinafter, the floor slab replacement method will be described with a focus on the work section D1. In the present embodiment, as shown in FIG. 1 (b), the existing floor slab 1 in the work section D1 is moved from the upstream side (right side in the bridge axis direction in FIG. 1) to the downstream side (bridge axis in FIG. 1) of the up two lanes. It will be replaced with the new floor slab 3 in order toward the left side in the direction).

床版取替え工法の流れを、図4のフロー図に沿って図1(b)および図5の概念図を参照しつつ説明すると、まず、図1(b)で示すように、走行車線側に設定した作業区画D1に複数の既設床版片11を形成しておく(Step1)。なお、本実施の形態では、6つの既設床版片11を形成しており、これらの形状は撤去したのち車両搬送が可能な大きさに形成されている。 Explaining the flow of the floor slab replacement method with reference to the conceptual diagrams of FIGS. 1 (b) and 5 along the flow chart of FIG. 4, first, as shown in FIG. 1 (b), on the traveling lane side. A plurality of existing floor slab pieces 11 are formed in the set work section D1 (Step 1). In this embodiment, six existing floor slab pieces 11 are formed, and these shapes are formed to a size capable of transporting a vehicle after being removed.

次に、図5(a)で示すように、6枚の既設床版片11のうちの2枚を既設床版1から切り離して撤去する(Step2)。すると、既設床版片11の撤去跡に、I型鋼よりなる主桁2の一部が露出するから、この露出した主桁2の上フランジ上面に対して下処理を行うとともに(Step3)、図5(b)で示すように、スタッドジベル21を設置する(Step4)。 Next, as shown in FIG. 5A, two of the six existing deck pieces 11 are separated from the existing deck 1 and removed (Step 2). Then, a part of the main girder 2 made of I-shaped steel is exposed in the removal trace of the existing floor slab piece 11, so that the upper surface of the upper flange of the exposed main girder 2 is prepared (Step 3). As shown in 5 (b), the stud gibber 21 is installed (Step 4).

こののち、図5(c)で示すように、主桁2の上フランジにプレキャストコンクリート造の新設床版3を据え付け(Step5)、無収縮モルタル4の打設によりスタッドジベル21を利用して新設床版3を主桁2に接合する(Step6)。そして、横目地部J1(橋軸直交方向に延在する目地部)に跨って本設プレート52を設置し、新設床版3の上面縁部どうしを接合する(Step7)。 After that, as shown in FIG. 5 (c), a new precast concrete floor slab 3 is installed on the upper flange of the main girder 2 (Step 5), and a stud girder 21 is newly installed by placing a non-shrink mortar 4. The deck 3 is joined to the main girder 2 (Step 6). Then, the main plate 52 is installed across the horizontal joint portion J1 (the joint portion extending in the direction orthogonal to the bridge axis), and the upper surface edges of the new floor slab 3 are joined to each other (Step 7).

そのうえで、新設床版3の上面に本舗装6を施して車両が通行可能な状態とする作業と(Step8)、本設プレート52の下面側に位置する横目地部J1に間詰コンクリート51を打設する作業とを(Step9)、同時にもしくは前後して実施する。なお、本舗装6は、半断面床版取替え工法において本舗装と称されるグレードの舗装を指す。 Then, the work of applying the main pavement 6 to the upper surface of the new floor slab 3 to make the vehicle passable (Step 8), and striking the interstitial concrete 51 into the horizontal joint portion J1 located on the lower surface side of the main plate 52. Perform the setting work (Step 9) at the same time or before and after. The main pavement 6 refers to a grade of pavement referred to as the main pavement in the half-section floor slab replacement method.

上記のStep2〜Step9の工程を、作業区画D1内の既設床版片11がなくなるまで繰り返すことにより、作業区画D1内、つまり上り2車線用の橋梁B1の1区画のうちの走行車線側に相当する半断面分の床版取替作業が終了する。本実施の形態では、Step2の工程で6枚の既設床版片11のうちの2枚を撤去しているため、Step2〜Step9の工程を3回繰り返すが、Step2の工程で撤去する既設床版片11の数量は何れでもよい。 By repeating the above steps of Steps 2 to 9 until the existing floor slab piece 11 in the work section D1 is exhausted, it corresponds to the inside of the work section D1, that is, the traveling lane side of one section of the bridge B1 for the uphill two lanes. The floor slab replacement work for the half section is completed. In the present embodiment, since two of the six existing deck pieces 11 are removed in the Step 2 step, the Step 2 to Step 9 steps are repeated three times, but the existing deck to be removed in the Step 2 step is removed. The quantity of the pieces 11 may be any.

このような、作業区画D1内に複数の既設床版片11を形成するStep1の工程と、Step1の終了後に作業区画D1内の複数の既設床版片11に対してStep2〜9の作業を繰り返す工程とを、1サイクル分とする。したがって、1サイクル分に要する施工期間は、作業区画D1で設定する橋軸方向の距離範囲により適宜調整することができる。 Such a step of Step 1 for forming a plurality of existing floor slabs 11 in the work section D1 and steps 2 to 9 for the plurality of existing floor slabs 11 in the work section D1 are repeated after the end of Step 1. The process is for one cycle. Therefore, the construction period required for one cycle can be appropriately adjusted according to the distance range in the bridge axis direction set in the work section D1.

上記の手順による既設床版の取替え工法は、一定期間(数週間から数か月)にわたって昼夜を問わず、車線規制を行うことができる場合を示したものである。しかし、この施工期間に、昼間の交通解放時間帯を設定しようとすると、夜間に車線規制時間帯を設定して施工を実施し、交通解放時間帯が到来するまでに、施工を中断するだけでなく、中断するごとに作業区画D1を車両が通行可能な状態とする必要が生じる。 The existing floor slab replacement method according to the above procedure shows the case where lane regulation can be performed day and night for a certain period (weeks to months). However, if you try to set a traffic release time zone during the daytime during this construction period, you can set a lane regulation time zone at night and carry out the construction, and just interrupt the construction by the time the traffic release time zone arrives. Instead, it becomes necessary to make the work area D1 in a state where vehicles can pass each time it is interrupted.

このため、Step1の終了後に作業区画D1内で繰り返し実施される上記Step2〜Step9の工程を、図4のフローで示すように、工事の中断が可能な第1〜第3の工程に分割する。第1の工程は、既設床版片11の撤去及び主桁2上面を下処理する工程(Step2、3)とし、Step1の既設床版片11を作成する工程は、第1の工程を実施する前の先行作業とする。 Therefore, as shown in the flow of FIG. 4, the steps of Steps 2 to 9 that are repeatedly carried out in the work section D1 after the end of Step 1 are divided into the first to third steps in which the construction can be interrupted. The first step is a step of removing the existing floor slab piece 11 and preparing the upper surface of the main girder 2 (Steps 2 and 3), and the step of creating the existing floor slab piece 11 of Step 1 carries out the first step. It is the previous work.

また、第2の工程は、主桁2上面にスタッドジベル21を設置する工程(Step4)とする。また、第3の工程は、新設床版3の据え付けから隣り合う新設床板3の接合、及び本舗装6を施す工程(Step5〜9)とする。 The second step is a step (Step 4) of installing the stud gibber 21 on the upper surface of the main girder 2. Further, the third step is a step (Steps 5 to 9) of installing the new floor slab 3, joining the adjacent new floor boards 3, and applying the main pavement 6.

このとき、1回の工事交通規制時間帯内で、第1の工程から第3の工程のうち2つ以上の工程を連続して実施する場合を含むようにして、工事交通規制時間帯と交通解放時間帯を繰り返すとよい。 At this time, the construction traffic regulation time zone and the traffic release time include the case where two or more of the first to third steps are continuously carried out within one construction traffic regulation time zone. Repeat the band.

その組み合わせはいずれでもよいが、例えば、先行の車線規制時間帯内で、第1の工程を実施したのち、後行の車線規制時間帯内で、第2の工程と第3の工程を連続して実施する。もしくは、先行の車線規制時間帯内で、第1の工程と第2の工程を連続して実施したのち、後行の車線規制時間帯内で、第3工程を実施する。これらの場合には、交通解放時間帯を、第1の工程終了後もしくは第2の工程終了後と、第3の工程終了後の2回確保することができる。 Any combination thereof may be used, but for example, after the first step is performed within the preceding lane regulation time zone, the second step and the third step are continuously performed within the following lane regulation time zone. To carry out. Alternatively, after the first step and the second step are continuously carried out within the preceding lane regulation time zone, the third step is carried out within the following lane regulation time zone. In these cases, the traffic release time zone can be secured twice, after the end of the first process or after the end of the second process, and after the end of the third process.

または、先行の車線規制時間帯内で、第1の工程から第3の工程を連続して実施し、図5(a)〜図5(c)で示すように、作業区画D1内の一部の6枚の既設床版片11のうちの2枚を撤去して新設床版3を敷設し本舗装6を施す。こののち、後行の車線規制時間帯内で第1の工程から第3の工程を連続して実施し、作業区画D1内の残りの4枚の既設設床版片11のうちの2枚を撤去して新設床版3を敷設し本舗装6を施してもよい。この場合には、第3の工程が終了するごとに交通解放時間帯を確保することができる。 Alternatively, within the preceding lane regulation time zone, the first step to the third step are continuously carried out, and as shown in FIGS. 5 (a) to 5 (c), a part of the work section D1. Two of the six existing floor slabs 11 are removed, a new floor slab 3 is laid, and the main pavement 6 is applied. After that, the first step to the third step are continuously carried out within the lane regulation time zone of the following, and two of the remaining four existing floor slab pieces 11 in the work section D1 are used. It may be removed and a new floor slab 3 may be laid and the main pavement 6 may be applied. In this case, the traffic release time zone can be secured every time the third step is completed.

上記のような車線規制時間帯内に実施する工程の組合わせは、毎回同じでなくてもよい。例えば、先行の車線規制時間帯内で第1の工程を実施し、後行の車線規制時間帯内で第2の工程と第3の工程を連続して実施したのち、その次の車線規制時間帯内では、第1の工程から第3の工程を連続して実施してもよい。 The combination of processes performed within the lane regulation time zone as described above does not have to be the same every time. For example, the first step is carried out within the preceding lane regulation time zone, the second step and the third step are continuously carried out within the following lane regulation time zone, and then the next lane regulation time. In the band, the first step to the third step may be continuously carried out.

ところで、1回の車線規制時間帯内に実施する工程が、第1の工程までもしくは第2の工程までであった場合には、既設床版片11を撤去したのちの主桁2は、露出された状態となっている。したがってこの場合には、交通解放期間が到来する直前の主桁2上で、仮設覆工板7を設置する作業と、仮間詰め9及び仮舗装8を施す作業とを行う。これにより、交通解放時間帯が到来すると、工事を中断した状態であっても交通解放を実施することができる。 By the way, when the process to be carried out within one lane regulation time zone is up to the first step or the second step, the main girder 2 after removing the existing floor slab piece 11 is exposed. It is in the state of being done. Therefore, in this case, the work of installing the temporary lining plate 7 and the work of applying the temporary lining 9 and the temporary pavement 8 are performed on the main girder 2 immediately before the traffic release period is reached. As a result, when the traffic release time zone arrives, the traffic can be released even if the construction is interrupted.

その一方で、1回の車線規制時間帯内に第3の工程まで実施した場合には、既設床版片11を撤去したのちの主桁2上は、新設床版3が間詰コンクリート51による間詰め処理、および本舗装6を施されて設置されている。したがってこの場合には、仮設床版7を設けなくても、交通解放時間帯が到来するとそのまま、交通解放を実施することができる。 On the other hand, if the third step is carried out within one lane regulation time zone, the new floor slab 3 is made of paved concrete 51 on the main girder 2 after removing the existing floor slab piece 11. It is installed with a packing process and a main pavement 6. Therefore, in this case, even if the temporary floor slab 7 is not provided, the traffic release can be carried out as it is when the traffic release time zone arrives.

≪仮覆工床版≫
車両の通行を可能にする仮覆工床版7は、図6(a)で示すように、橋梁B1の横断面を走行車線側と追い越し車線側の半分に分割したうちの、走行車線側の半断面を一時的に賄うことの可能な部材であり、床版本体71と地覆72と高欄73とを一体に形成している。こうすると、仮覆工床版7の設置作業に係る時間を大幅に短縮できるが、床版本体71と地覆72と高欄73は別体で製造し、現場で組み立て可能な構造としてもよい。
≪Temporary lining floor slab≫
As shown in FIG. 6A, the temporary lining floor slab 7 that allows vehicles to pass is located on the traveling lane side of the cross section of the bridge B1 divided into two halves, the traveling lane side and the overtaking lane side. It is a member capable of temporarily covering a half-section, and integrally forms a deck main body 71, a ground cover 72, and a balustrade 73. By doing so, the time required for the installation work of the temporary lining floor slab 7 can be significantly shortened, but the floor slab main body 71, the ground covering 72, and the balustrade 73 may be manufactured separately and assembled on site.

また、仮覆工床版7の床版本体71は、図6(b)で示すように、外縁部近傍を除いた上面にあらかじめ仮舗装8が施され、橋軸方向長さL2は、図1(b)で示した既設床版片11の橋軸方向長さL1と略同程度に形成されている。しかし、これに限定されるものではなく、既設床版片11の橋軸方向長さL1より小さい、例えば1/2および1/4のものを2種類準備してもよい。 Further, as shown in FIG. 6B, the floor slab main body 71 of the temporary lining floor slab 7 is provided with temporary pavement 8 in advance on the upper surface excluding the vicinity of the outer edge portion, and the bridge axial length L2 is shown in FIG. It is formed to be substantially the same as the bridge axial length L1 of the existing deck piece 11 shown in 1 (b). However, the present invention is not limited to this, and two types, for example, 1/2 and 1/4, which are smaller than the bridge axial length L1 of the existing deck piece 11, may be prepared.

橋軸方向長さL2を1/2および1/4の2種類準備すると、既設床版片11の橋軸方向長さL1を施工途中で変更する必要が生じた場合であっても、既設床版片11を撤去したのちに露出する主桁2への仮覆工床版7の設置作業を容易に行うことができる。つまり、撤去した既設床版片11があらかじめ規定した橋軸方向長さL1である場合には、仮覆工床版7のうち、橋軸方向長さL2が1/2のものを必要数量だけ並列配置する。 If two types of bridge axial length L2 are prepared, 1/2 and 1/4, the existing floor even if it becomes necessary to change the bridge axial length L1 of the existing deck piece 11 during construction. The temporary lining floor slab 7 can be easily installed on the main girder 2 exposed after the slab 11 is removed. That is, when the removed existing floor slab 11 has a predetermined bridge axial length L1, only the required quantity of the temporary lining deck 7 having a bridge axial length L2 of 1/2 is used. Arrange in parallel.

一方、作業区画D1を切断して既設床版片11を作成する際、切断予定位置と、主桁2どうしの長手方向連結部であって上フランジ上面に添接板が設置されている位置とが重なる場合には、添接板を避けるべく切断位置をずらさなければならない。すると、既設床版片11の橋軸方向長さL1はあらかじめ規定した長さにならず、既設床版片11を撤去したのちに露出した主桁2の橋軸方向長さも変化する。しかし、橋軸方向長さL2が1/2および1/4の仮覆工床版7を適宜組み合わせて用いることにより、これらの不具合に対応することが可能となる。 On the other hand, when the existing floor slab piece 11 is created by cutting the work section D1, the planned cutting position and the position where the splicing plate is installed on the upper surface of the upper flange at the longitudinal connection portion between the main girders 2. If they overlap, the cutting position must be staggered to avoid the splicing plate. Then, the bridge axial length L1 of the existing deck piece 11 does not have a predetermined length, and the bridge axial length of the main girder 2 exposed after the existing deck piece 11 is removed also changes. However, by using a temporary lining floor slab 7 having a length L2 in the bridge axis direction of 1/2 and 1/4 as appropriate, it is possible to deal with these problems.

さらに、仮覆工床版7は、その部材厚に応じて主桁2の上フランジ上面に直接設置してもよいし、図6(a)で示すように、鋼材等を加工した高さ調整材74を介して設置してもよい。高さ調整材74を介して設置する場合には、高さ調整材74を床版本体71の下面にあらかじめ設置し、高さ調整材74と主桁2の上フランジとをクランプ等で挟持すると容易に、仮覆工床版7を主桁2に着脱自在に固定することができる。 Further, the temporary lining floor slab 7 may be installed directly on the upper surface of the upper flange of the main girder 2 according to the thickness of the member, or as shown in FIG. 6A, the height is adjusted by processing a steel material or the like. It may be installed via the material 74. When installing via the height adjusting material 74, the height adjusting material 74 is installed in advance on the lower surface of the floor slab main body 71, and the height adjusting material 74 and the upper flange of the main girder 2 are sandwiched by a clamp or the like. The temporary lining floor slab 7 can be easily detachably fixed to the main girder 2.

また、直接設置する場合には、床版本体71の下面形状が、平坦なものと、主桁2の上面に設置されている添接板上に載置することが可能なように加工されたものの2種類を準備しておくとよい。 Further, in the case of direct installation, the lower surface shape of the floor slab main body 71 is processed so that it can be placed on a flat one and on a splicing plate installed on the upper surface of the main girder 2. It's a good idea to prepare two types of things.

≪新設床版≫
一方、プレキャストコンクリート造の新設床版3は、図7(a)(b)で示すように、床版本体31、地覆32、接合鉄筋33、及びスタッドジベル挿通孔34を備えている。地覆32は一体に製造されていてもよいし、別体に製造して高欄(図示せず)と併せて現場にて床版本体31に設置する構造としてもよい。
≪New floor version≫
On the other hand, as shown in FIGS. 7 (a) and 7 (b), the newly installed floor slab 3 made of precast concrete includes a floor slab main body 31, a ground cover 32, a joint reinforcing bar 33, and a stud gibber insertion hole 34. The ground cover 32 may be manufactured integrally, or may be manufactured separately and installed on the floor slab main body 31 together with the balustrade (not shown).

接合鉄筋33は、床版本体31の橋軸方向に対向する両側面と、追い越し車線側の既設床版1に対向する側面の、3つの側面各々から平行に突出するように設置されている。これらは高さ方向に2列に配置されるとともに、橋軸直交方向に延在する横目地部J1および橋軸方向に延在する縦目地部J2において平面視で千鳥配置をなし、施工完了時にはこの横目地部J1及び縦目地部J2に打設される間詰めコンクリート51に埋設される。 The joint reinforcing bars 33 are installed so as to project in parallel from each of the three side surfaces of the floor slab main body 31 facing the bridge axis direction and the side surface facing the existing floor slab 1 on the overtaking lane side. These are arranged in two rows in the height direction, and are staggered in a plan view at the horizontal joint J1 extending in the direction perpendicular to the bridge axis and the vertical joint J2 extending in the direction of the bridge axis. It is buried in the padded concrete 51 placed in the horizontal joint portion J1 and the vertical joint portion J2.

そして、床版本体31に形成されるスタッドジベル挿通孔34は、新設床版3を主桁2の上フランジ上面に載置した際にスタッドジベル21が挿通可能な位置にあり、新設床版3を主桁2に接合させる際、無収縮モルタル4がこのスタッドジベル挿通孔34から充填される。 The stud gibber insertion hole 34 formed in the floor slab main body 31 is in a position where the stud gibber 21 can be inserted when the new floor slab 3 is placed on the upper surface of the upper flange of the main girder 2, and the new floor slab 3 is formed. The non-shrink mortar 4 is filled through the stud gibber insertion hole 34 when the main girder 2 is joined.

≪≪橋梁の床版取替え工法≫≫
次に、車線規制時間帯と交通解放時間帯とを交互に繰り返しながら、作業区画D1内の既設床版1をプレキャストコンクリート造の新設床版3に取替える床版取替え工法の手順を、以下に説明する。
≪≪Bridge floor slab replacement method≫≫
Next, the procedure of the floor slab replacement method for replacing the existing floor slab 1 in the work area D1 with the new floor slab 3 made of precast concrete while alternately repeating the lane regulation time zone and the traffic release time zone will be described below. do.

なお、本実施の形態では、1度目の車線規制時間帯で第1の工程を実施したのち、交通解放時間帯の終了後に2度目の車線規制時間帯で、第2の工程と第3の工程を連続して実施し、これを繰り返して1サイクルを終了する(作業区画D1を新設床版3に取替える)場合を事例に挙げる。また、使用する仮覆工床版7及び新設床版3は、橋軸方向の長さL2及びL3がともに、既設床版片11と略同一もしくは略小さいものを採用する場合を事例に挙げて説明する。 In this embodiment, after the first step is carried out in the first lane regulation time zone, the second step and the third step are carried out in the second lane regulation time zone after the end of the traffic release time zone. Is continuously carried out, and one cycle is completed by repeating this (replacement of the work section D1 with the new floor slab 3) as an example. Further, as an example, the temporary lining floor slab 7 and the new floor slab 3 to be used have the same or substantially smaller lengths L2 and L3 in the bridge axis direction as the existing floor slab piece 11. explain.

<車線規制時間帯の到来ごとに実施する準備作業>
車線規制時間帯が到来するごとに、図1(b)で示すように、橋梁B1の上り2車線を1車線とする車線規制を行うとともに、床版架設装置10を搬入し、あらかじめ施工計画時に床版取替え工法の1サイクル分として設定した作業区画D1の近傍に、この床版架設装置10を据え付ける。
<Preparatory work to be carried out each time the lane regulation time zone arrives>
As shown in FIG. 1 (b), every time the lane regulation time zone arrives, lane regulation is performed so that the two upstream lanes of the bridge B1 are one lane, and the floor slab erection device 10 is carried in at the time of construction planning in advance. This deck erection device 10 is installed in the vicinity of the work section D1 set as one cycle of the deck replacement method.

≪床版架設装置≫
床版架設装置10は、従来より既設床版1の取替え作業に採用されている装置であればいずれを用いてもよいが、車線規制時間帯ごとに搬出入を繰り返すことを考慮し、本実施の形態では、トレーラー等の車両の荷台に積込み可能に製造された門型タイプの床版架設装置10を採用している。
≪Floor slab erection device≫
As the floor slab erection device 10, any device may be used as long as it is a device conventionally used for the replacement work of the existing floor slab 1, but this implementation is carried out in consideration of repeating loading and unloading every lane regulation time zone. In this form, a gate-type floor slab erection device 10 manufactured so as to be able to be loaded on the loading platform of a vehicle such as a trailer is adopted.

床版架設装置10は、図1(b)及び図8(a)で示すように、間隔を設けて配置される一対の門型フレーム101と、門型フレーム101に架け渡される1対のクレーンガーター102と、クレーンガーター102各々に吊り下げられた天井クレーン103とを備える。天井クレーン103は、クレーンガーター102に沿って移動可能な構造を有しており、既設床版1の撤去、仮覆工床版7の据え付けもしくは撤去、及び新設床版3の据え付けに係る作業はすべて、この天井クレーン103を用いて行う。 As shown in FIGS. 1 (b) and 8 (a), the deck slab erection device 10 includes a pair of gantry frames 101 arranged at intervals and a pair of cranes spanned over the gantry frames 101. A garter 102 and an overhead crane 103 suspended from each of the crane garter 102 are provided. The overhead crane 103 has a structure that can be moved along the crane garter 102, and the work related to the removal of the existing floor slab 1, the installation or removal of the temporary lining floor slab 7, and the installation of the new floor slab 3 are performed. All are done using this overhead crane 103.

<第1の工程の前に実施する先行作業>
前述したように、1サイクル分として設定した作業区画D1の既設床版1を、図1(b)で示すように、橋軸直交方向に沿う切断線を7本設けて、6枚の既設床版片11を作成しておく(Step1)。なお、切断する間隔は等間隔が望ましいが、切断線の位置と主桁2の上フランジ上面に設置された添接板の位置が合致する場合には、添接板を避けるように切断位置を適宜変更する。
<Preceding work to be carried out before the first process>
As described above, the existing floor slab 1 of the work section D1 set as one cycle is provided with seven cutting lines along the direction orthogonal to the bridge axis as shown in FIG. 1 (b), and six existing floors are provided. A plate 11 is created (Step 1). It is desirable that the cutting intervals are equal, but if the position of the cutting line matches the position of the splicing plate installed on the upper surface of the upper flange of the main girder 2, the cutting position should be set so as to avoid the splicing plate. Change as appropriate.

<1度目の車線規制時間帯の到来:第1の工程>
図8(a)で示すように、床版架設装置10を作業区画D1の近傍の所定位置に据え付ける。次に、6枚の既設床版片11のうち、上り2車線の上流側に位置する第1枚目(図1(b)の最右端)を既設床版1から切り離すべく、作業区画D1の橋軸方向に沿う境界線に切断線を入れたのち、既設床版片11を床版架設装置10にて揚重撤去する。
<The arrival of the first lane regulation time zone: the first process>
As shown in FIG. 8A, the floor slab erection device 10 is installed at a predetermined position in the vicinity of the work section D1. Next, of the six existing floor slabs 11, the first piece (the rightmost end in FIG. 1 (b)) located on the upstream side of the up two lanes is separated from the existing floor slab 1 in the work section D1. After making a cutting line at the boundary line along the bridge axis direction, the existing deck piece 11 is lifted and removed by the deck erection device 10.

この作業を2回連続して行い、図5(a)で示したように、2枚の既設床版片11を撤去する。次に、2枚の既設床版片11を撤去したことにより形成された空間を利用して、主桁2間に必要個所に、図8(b)で示すような作業足場22を設置する(Step2)。 This work is performed twice in succession, and as shown in FIG. 5A, the two existing deck pieces 11 are removed. Next, using the space formed by removing the two existing floor slab pieces 11, a work scaffold 22 as shown in FIG. 8B is installed at a necessary place between the main girders 2 (). Step 2).

こののち、作業足場22を利用して、主桁2上フランジ上面に下処理を行う。下処理としては、例えば、主桁2の上フランジ上面に付着したコンクリートかすやアンカー鉄筋等の撤去した既設床版片11の残物をはつり取る作業や、のちにスタッドジベル21を設置するための素地調整する等、いわゆるケレン作業等を行う(Step3)。 After that, the work scaffold 22 is used to prepare the upper surface of the upper flange of the main girder 2. As the pretreatment, for example, the work of scraping off the remnants of the existing floor slab piece 11 from which the concrete debris and the anchor reinforcing bars adhering to the upper surface of the upper flange of the main girder 2 have been removed, and the work of installing the stud gibber 21 later. Perform so-called chipping work such as adjusting the substrate (Step 3).

これらの作業が終了したのち、図8(b)で示すように、主桁2の上フランジ上面に前述した仮覆工床版7を高さ調整材74を介して設置する。図9(a)で示すように、隣り合う仮覆工床版7、及び既設床版1もしくは既設床版片11と仮覆工床版7との間に形成された横目地部J1に対して仮間詰め9を行う。 After these operations are completed, as shown in FIG. 8B, the above-mentioned temporary lining floor slab 7 is installed on the upper surface of the upper flange of the main girder 2 via the height adjusting material 74. As shown in FIG. 9A, with respect to the adjacent temporary lining floor slab 7 and the horizontal joint portion J1 formed between the existing floor slab 1 or the existing floor slab piece 11 and the temporary lining floor slab 7. The temporary filling 9 is performed.

仮間詰め9は、横目地部J1の下面側を塞ぐように鉄板等の開口塞ぎ板91を設置したうえで、スポンジや砂等の充填材92を充填する。また、横目地部J1の開きが大きい場合には、上面にも開口塞ぎ板91を設置するとよい。なお、横目地部J1の上面を塞ぐようにして開口塞ぎ板91を配置した場合、横目地部J1には必ずしも充填材92を充填しなくてもよい。 In the temporary filling 9, an opening closing plate 91 such as an iron plate is installed so as to close the lower surface side of the horizontal joint portion J1, and then a filler 92 such as sponge or sand is filled. Further, when the opening of the horizontal joint portion J1 is large, it is advisable to install the opening closing plate 91 on the upper surface as well. When the opening closing plate 91 is arranged so as to close the upper surface of the horizontal joint portion J1, the horizontal joint portion J1 does not necessarily have to be filled with the filler 92.

具体的には、図9(b)で示すように、一対の開口塞ぎ板91で横目地部J1の上面側及び下面側を塞ぎ、仮覆工床版7を挟持するようにしてこれら一対の開口塞ぎ板91をボルト等の緊結具93で緊結する。このとき、上面側の開口塞ぎ板91が、横目地部J1の全面を塞いだ状態で仮覆工床版7に固定されていれば、下面側の開口塞ぎ板91は、図9(c)で示すように、横目地部J1の下面側の全面を塞ぐものであってもよいし、図9(d)で示すように、下面側の一部分を塞ぐよう配置されるものであってもよい。 Specifically, as shown in FIG. 9B, a pair of opening closing plates 91 close the upper surface side and the lower surface side of the horizontal joint portion J1 so as to sandwich the temporary lining floor slab 7. The opening closing plate 91 is fastened with a binding tool 93 such as a bolt. At this time, if the opening closing plate 91 on the upper surface side is fixed to the temporary lining floor slab 7 in a state where the entire surface of the horizontal joint portion J1 is closed, the opening closing plate 91 on the lower surface side is shown in FIG. 9 (c). As shown in FIG. 9D, the entire surface of the lower surface side of the horizontal joint portion J1 may be closed, or as shown in FIG. 9D, it may be arranged so as to cover a part of the lower surface side. ..

こうすると、横目地部J1に充填材92を充填する場合と比較して、作業性が大幅に向上し、工期短縮を図ることができる。このような処理は、横目地部J1だけでなく、仮覆工床版7と追い越し車線側の既設床版1との間に形成される縦目地部J2にも、同様に実施する。 By doing so, the workability can be significantly improved and the construction period can be shortened as compared with the case where the filler 92 is filled in the horizontal joint portion J1. Such processing is similarly performed not only on the horizontal joint portion J1 but also on the vertical joint portion J2 formed between the temporary lining floor slab 7 and the existing floor slab 1 on the overtaking lane side.

次に、仮覆工床版7の上面全面に仮舗装8を施す。前述したように、仮覆工床版7の上面にはあらかじめ先行仮舗装81が施されているから、仮覆工床版7の先行仮舗装81が施されていない縁部に対して横目地部J1及び縦目地部J2を覆うように、後行仮舗装82を施せばよい。このように、仮覆工床版7の上面にあらかじめ先行仮舗装81を施しておくと、仮舗装8全体の作業時間を大幅に短縮できる。こののち、門型タイプの床版架設装置10を搬出して第1の工程を終了し、上り2車線を車両解放可能な状態とする。 Next, the temporary pavement 8 is applied to the entire upper surface of the temporary lining floor slab 7. As described above, since the preceding temporary pavement 81 is preliminarily applied to the upper surface of the temporary lining floor slab 7, the horizontal joint is applied to the edge of the temporary lining floor slab 7 to which the preceding temporary pavement 81 is not applied. The trailing temporary pavement 82 may be applied so as to cover the portion J1 and the vertical joint portion J2. In this way, if the preceding temporary pavement 81 is previously applied to the upper surface of the temporary lining floor slab 7, the working time of the entire temporary pavement 8 can be significantly shortened. After that, the gate-type floor slab erection device 10 is carried out to complete the first step, and the two up lanes are set to be in a state where the vehicle can be released.

<2度目の車線規制時間帯の到来:第2の工程及び第3の工程>
第1の工程の開始時と同様に、床版架設装置10を作業区画D1の近傍の所定位置に据え付ける。次に、主桁2の上フランジ上面に設置した仮覆工床版7を床版架設装置10にて一時撤去し、主桁2の上フランジ上面のケレン状況を確認し、必要に応じて再度ケレン作業を行って素地調整を行う。
<The arrival of the second lane regulation time zone: the second process and the third process>
Similar to the start of the first step, the deck erection device 10 is installed at a predetermined position in the vicinity of the work section D1. Next, the temporary lining floor slab 7 installed on the upper surface of the upper flange of the main girder 2 is temporarily removed by the floor slab erection device 10, the cleaning status of the upper surface of the upper flange of the main girder 2 is confirmed, and if necessary, it is performed again. Perform the cleaning work and adjust the substrate.

こののち、第2の工程を実施する。つまり、図10で示すように、主桁2の上フランジ上面に複数のスタッドジベル21を、所定の間隔を設けて設置するとともに、防錆塗装を行う(Step4)。スタッドジベル21は、橋軸直交方向に並ぶ複数を1組とし、これを橋軸方向に間隔を設けて複数設置する。図10では、スタッドジベル21を橋軸直交方向に3本設置した場合を例示しているが、その数量は、主桁2の幅や支間の位置等に応じて適宜変更される。 After that, the second step is carried out. That is, as shown in FIG. 10, a plurality of stud gibber 21 are installed on the upper surface of the upper flange of the main girder 2 at predetermined intervals, and rust preventive coating is applied (Step 4). A plurality of stud gibber 21 arranged in the direction orthogonal to the bridge axis are set as a set, and a plurality of stud gibber 21 are installed at intervals in the bridge axis direction. FIG. 10 illustrates a case where three stud gibber 21 are installed in the direction orthogonal to the bridge axis, but the quantity thereof is appropriately changed according to the width of the main girder 2, the position of the span, and the like.

これらの作業が終了したのち、第3の工程を実施する。まず、主桁2の上フランジ上面に、同じく床版架設装置10を用いて新設床版3を据え付ける(Step5)。新設床版3は、図11(a)で示すように、スタッドジベル挿通孔34に主桁2の上フランジ上面に設置したスタッドジベル21が収納されるように配置し、このスタッドジベル挿通孔34に無収縮モルタル4を充填して、主桁2と新設床版3とを強固に接合する(Step6)。なお、新設床版3を据え付ける前に、モルタル止め41を主桁2の上フランジにおける両側部に設置しておく。 After these operations are completed, the third step is carried out. First, the new floor slab 3 is installed on the upper surface of the upper flange of the main girder 2 using the floor slab erection device 10 (Step 5). As shown in FIG. 11A, the new floor slab 3 is arranged so that the stud gibber 21 installed on the upper surface of the upper flange of the main girder 2 is housed in the stud gibber insertion hole 34, and the stud gibber insertion hole 34 is accommodated. Is filled with non-shrink mortar 4 to firmly join the main girder 2 and the new floor slab 3 (Step 6). Before installing the new floor slab 3, mortar stoppers 41 are installed on both sides of the upper flange of the main girder 2.

無収縮モルタル4の充填作業に前後してもしくは同時に、図11(b)で示すように、本設プレート52による隣り合う新設床版3どうしを接合する作業(Step7)を実施する。 Before or at the same time as the filling work of the non-shrink mortar 4, as shown in FIG. 11B, the work (Step 7) of joining the adjacent new floor slabs 3 by the main plate 52 is carried out.

本設プレート52は、隣り合う新設床版3との間に形成された横目地部J1の上方を跨ぐように設置する。本設プレート52は、横目地部J1を被覆する十分な幅と、床版本体31の橋軸直交方向長さL3に略等しい長さとを有する、間詰めコンクリート51と同様の材料で工場にて製造されたプレキャストコンクリート造の板材を使用している。 The main plate 52 is installed so as to straddle the upper part of the horizontal joint portion J1 formed between the adjacent new floor slabs 3. The main plate 52 is made of the same material as the padded concrete 51 and has a sufficient width to cover the horizontal joint portion J1 and a length substantially equal to the length L3 in the direction perpendicular to the bridge axis of the deck main body 31 at the factory. The manufactured precast concrete board is used.

本設プレート52の設置方法は、アンカーや接着剤による固定等いずれの手段により実施してもよく、設置状態も、床版本体31の上面に本設プレート52を載置するように設置してもよいが、本実施の形態では、床版本体31の縁部に設けた切欠きに載置させている。このとき切欠きは、本設プレート52の上面と床版本体31の上面が面一となるような深さに形成するとよい。 The installation method of the main plate 52 may be carried out by any means such as fixing with an anchor or an adhesive, and the installation state is also such that the main plate 52 is placed on the upper surface of the floor slab main body 31. However, in the present embodiment, the floor slab is placed in a notch provided at the edge of the main body 31. At this time, the notch may be formed at a depth such that the upper surface of the main plate 52 and the upper surface of the deck main body 31 are flush with each other.

次に、図11(c)で示すよう、新設床版3の上面に本舗装6を施す(Step8)。また、本舗装6に係る作業と同時にもしくは前後して、横目地部J1の下方にこれを跨ぐように型枠53を設置する。この型枠53に対して間詰めコンクリート51充填するための充填孔、空気穴もしくは充填確認孔(いずれに図示せず)を形成しておく。 Next, as shown in FIG. 11 (c), the main pavement 6 is applied to the upper surface of the new floor slab 3 (Step 8). Further, at the same time as or before and after the work related to the main pavement 6, the formwork 53 is installed below the horizontal joint portion J1 so as to straddle the horizontal joint portion J1. Filling holes, air holes, or filling confirmation holes (not shown in any of them) for filling the padded concrete 51 are formed in the formwork 53.

そして、図11(d)で示すよう、横目地部J1の下面側から間詰めコンクリート51を充填し、接合鉄筋33を埋設する(Step9)。間詰めコンクリート51は、高強度及び高耐久なコンクリートであればいずれを採用してもよい。 Then, as shown in FIG. 11D, the padded concrete 51 is filled from the lower surface side of the horizontal joint portion J1 and the joint reinforcing bar 33 is embedded (Step 9). As the padded concrete 51, any concrete may be used as long as it is a high-strength and highly durable concrete.

このように、本設プレート52は間詰めコンクリート51と同様の材料にて製造すると、該新設床板の一部として機能させることの可能な本設部材として取り扱うことができる。このため、本設プレート52で横目地部J1の上方を被覆すると、その直後に本舗装6を施す作業を優先して実施できることから、交通解放を行いつつ新設床版3の下方側から間詰めコンクリート51の充填作業を実施することもできる。こうすると、車線規制時間帯に実施する作業を減らすことができ、作業効率を大幅に向上することが可能となる。 As described above, when the main plate 52 is manufactured of the same material as the padded concrete 51, it can be handled as a main member capable of functioning as a part of the new floor board. For this reason, if the upper part of the horizontal joint portion J1 is covered with the main plate 52, the work of applying the main pavement 6 immediately after that can be preferentially carried out. It is also possible to carry out the filling work of the concrete 51. By doing so, it is possible to reduce the work to be carried out during the lane regulation time zone, and it is possible to greatly improve the work efficiency.

なお、縦目地部J2及び既設床版1もしくは既設床版片11と新設床版3との間に形成された横目地部J1には、本舗装6を施す前に、第1の工程で示したように、開口塞ぎ板91と充填材92による仮間詰め9を行っておく。こののち、床版架設装置10を搬出して第3の工程を終了し、上り2車線を車両解放可能な状態とする。 The vertical joint portion J2 and the existing floor slab 1 or the horizontal joint portion J1 formed between the existing floor slab piece 11 and the new floor slab 3 are shown in the first step before the main pavement 6 is applied. As described above, the temporary filling 9 is performed by the opening closing plate 91 and the filler 92. After that, the floor slab erection device 10 is carried out to complete the third step, and the two up lanes are set to be in a state where the vehicle can be released.

上記のとおり、2度目の車線規制時間帯が終了した時点で、第1〜第3の工程を経て、作業区画D1のうち、上り2車線の上流側1枚目及び2枚目の既設床版片11を新設床版3に取替える作業が終了する。なお、第3の工程のいずれかの段階で、新設床版3の地覆32に高覧を設置する。 As described above, when the second lane regulation time zone is completed, the first and second existing floor slabs on the upstream side of the up two lanes in the work section D1 are subjected to the first to third steps. The work of replacing the piece 11 with the new floor slab 3 is completed. In addition, at any stage of the third step, a high-level inspection is installed on the ground cover 32 of the new floor slab 3.

ところで、図11(d)で示すように、第3の工程では、2枚の新設床版3の全面に本舗装6を施している。したがって、次に作業区画D1の中間部に位置する3枚目及び4枚目の既設床版片11を新設床版3に取替える際には、以下の処理を追加して行う。 By the way, as shown in FIG. 11D, in the third step, the main pavement 6 is applied to the entire surface of the two new floor slabs 3. Therefore, when the third and fourth existing floor slabs 11 located in the middle portion of the work section D1 are replaced with the new floor slab 3, the following processing is added.

図12(a)で示すように、すでに本舗装6が施された2枚目の新設床版3について、本舗装6が施されていない3枚目の新設床版3と隣接する縁部近傍の本舗装6を所定の幅だけはがし取る。そのうえで、図12(b)で示すように、2枚目と3枚目の新設床版3の間に形成された横目地部J1を跨いで本設プレート52を設置し、そののち、本舗装6を施し、図12(c)で示すように、間詰めコンクリート51を充填する。 As shown in FIG. 12 (a), regarding the second new floor slab 3 already covered with the main pavement 6, the vicinity of the edge adjacent to the third new floor slab 3 not covered with the main pavement 6. Peel off the main pavement 6 by a predetermined width. Then, as shown in FIG. 12B, the main plate 52 is installed across the horizontal joint portion J1 formed between the second and third new floor slabs 3, and then the main pavement is installed. 6 is applied, and as shown in FIG. 12 (c), the padded concrete 51 is filled.

このように、交通解放時間帯の直前に実施される工程が、第1の工程の場合には、終了時に仮覆工床版7が敷設されるとともに目地が仮間詰め9で処理される。また、第3の工程の場合には、終了時に覆工床版3が敷設されるとともに、目地が間詰め51で処理され本舗装6が施される。これにより、車線規制時間帯において、いずれの工程で作業が終了した場合にも、交通解放時間帯には車両が通行可能な状態となっているため、交通解放を繰り返しながら、既設床版11を新設床版3に取替える作業を効率よく実施することが可能となる。 As described above, in the case of the first step, the step carried out immediately before the traffic release time zone is that the temporary lining floor slab 7 is laid at the end and the joints are processed by the temporary filling 9. Further, in the case of the third step, the lining floor slab 3 is laid at the end, the joints are treated with the padding 51, and the main pavement 6 is applied. As a result, no matter which process the work is completed in the lane regulation time zone, the vehicle is in a state where the vehicle can pass during the traffic release time zone. Therefore, the existing floor slab 11 is used while repeating the traffic release. It is possible to efficiently carry out the work of replacing with the new floor slab 3.

上記の手順で、第1の工程を実施する先行の車線規制時間帯と、第2の工程及び第3の工程を実施する後行の車線規制時間帯を、3回繰り返すことにより、つまり6度の車線規制時間帯を経て、作業区画D1を新設床版3に取替えることができ、これにより1サイクル分の作業が終了する。 By repeating the preceding lane regulation time zone in which the first step is carried out and the subsequent lane regulation time zone in which the second step and the third step are carried out three times in the above procedure, that is, six times. After the lane regulation time zone, the work section D1 can be replaced with the new floor slab 3, which completes the work for one cycle.

<7度目以降の車線規制時間帯の到来:2サイクル目>
次に、図3(c)で示すように、作業区画D1に並列する1区画目の追い越し車線の作業区画O1に対して、上記の手順にしたがって床版取替え工法を実施する。
<The arrival of the lane regulation time zone after the 7th time: 2nd cycle>
Next, as shown in FIG. 3C, the floor slab replacement method is carried out according to the above procedure for the work section O1 in the overtaking lane of the first section parallel to the work section D1.

つまり、追い越し車線の作業区画O1で、既設床版片11を作成する工程(Step1)を先行作業として済ませた後、第1〜第3の工程を3回繰り返す。こうして、図3(d)で示すように、橋梁B1に設定した複数の区画のうちの1区画目内の、作業区画D1及び作業区画B1における既設床版1を新設床版3に取替え、床板取り替え工法を終了する。 That is, in the work section O1 of the overtaking lane, the step of creating the existing floor slab piece 11 (Step 1) is completed as the preceding work, and then the first to third steps are repeated three times. In this way, as shown in FIG. 3D, the existing floor slab 1 in the work section D1 and the work section B1 in the first section of the plurality of sections set in the bridge B1 is replaced with the new floor slab 3. The replacement method is completed.

<作業区画O1の床版取替え工法が終了した後に到来する車線規制時間帯>
図2のフロー図に戻って(第4ステップ)、図3(d)で示すように、走行車線側の作業区画D1の新設床版3と追い越し車線側の作業区画O1の新設床版3とを接合する。
<Lane regulation time zone that arrives after the floor slab replacement method for work area O1 is completed>
Returning to the flow chart of FIG. 2 (fourth step), as shown in FIG. 3D, the new floor slab 3 of the work section D1 on the traveling lane side and the new floor slab 3 of the work section O1 on the overtaking lane side. To join.

接合作業は、図13(a)で示すように、作業区画D1の新設床版3と追い越し車線側の作業区画O1の新設床版3との間に形成された縦目地部J2に隣接する縁部の本舗装6を所定の幅だけはがし取ったうえで、縦目地部J2の上方を跨ぐように、本設プレート52を新設床版3の縁部に形成された切欠きに設置する。本設プレート52は、縦目地部J2を被覆する十分な幅を有し、その長さは、作業区画D1及び作業区画O1の橋軸方向の長さに略等しく形成されている。 As shown in FIG. 13A, the joining work is performed on the edge adjacent to the vertical joint portion J2 formed between the new floor slab 3 of the work section D1 and the new floor slab 3 of the work section O1 on the overtaking lane side. After peeling off the main pavement 6 of the portion by a predetermined width, the main plate 52 is installed in the notch formed at the edge of the new floor slab 3 so as to straddle the upper part of the vertical joint portion J2. The main plate 52 has a sufficient width to cover the vertical joint portion J2, and its length is formed to be substantially equal to the length of the work section D1 and the work section O1 in the bridge axial direction.

なお、本設プレート52の材料は、横目地部J1を被覆する際に採用したものと同様のものを使用しており、新設床版3への設置方向も、横目地部J1に設置した際の方法と同様である。 The material of the main plate 52 is the same as that used when covering the horizontal joint portion J1, and the installation direction of the new floor slab 3 is also when the horizontal joint portion J1 is installed. It is the same as the method of.

最後に、図13(b)及び(c)で示すように、本舗装6を施すとともに、間詰めコンクリート51を充填する。これにより、橋梁B1を橋軸方向に区分けしたうちの1区画目の床版取替え作業が終了する。 Finally, as shown in FIGS. 13 (b) and 13 (c), the main pavement 6 is applied and the padded concrete 51 is filled. As a result, the floor slab replacement work of the first section of the bridge B1 divided in the bridge axis direction is completed.

こののち、図2のフロー図の第2ステップに戻って、橋梁B1に設定した第2区画以降のすべての区画に対して同様の施工を上記の手順に従って、繰り返し実施する(第5ステップ)。 After that, the process returns to the second step of the flow chart of FIG. 2, and the same construction is repeatedly performed for all the sections after the second section set on the bridge B1 according to the above procedure (fifth step).

これにより、橋梁B1における施工予定領域(1区画目、2区画目、3区画目・・)の既設床版1をすべて、新設床版3に取替える施工が終了する。なお、走行車線側と追い越し車線側に対して、上記の半断面床版取替え工法を実施する順序は、上記の手順に限定されるものではない。 As a result, the construction of replacing all the existing floor slabs 1 in the planned construction area (1st section, 2nd section, 3rd section, ...) In the bridge B1 with the new floor slab 3 is completed. The order in which the above-mentioned half-section floor slab replacement method is carried out on the traveling lane side and the overtaking lane side is not limited to the above procedure.

つまり、本実施の形態では、図14(a)で示すように、1区画目の作業区画D1を新設床版3に取替えたのち、これに並列する作業区画O1を新設床版3に取替える。こののち、2区画目の作業区画D2を新設床版3に取替え、これに並列する作業区画O2を新設床版3に取替える。この作業を繰り返すこととなる。 That is, in the present embodiment, as shown in FIG. 14A, the work section D1 of the first section is replaced with the new floor slab 3, and then the work section O1 parallel to the work section O1 is replaced with the new floor slab 3. After that, the work section D2 of the second section is replaced with the new floor slab 3, and the work section O2 parallel to this is replaced with the new floor slab 3. This work will be repeated.

しかし、この手順に限定されるものではない。例えば図14(b)で示すように、1区画目の作業区画D1を新設床版3に取替えたのち、これに並列する作業区画O1を新設床版3に取替える。こののち、2区画目の作業区画O2を新設床版3に取替え、これに並列する作業区画D2を新設床版3に取替える。この作業を繰り返すといった手順を採用してもよい。 However, it is not limited to this procedure. For example, as shown in FIG. 14B, after the work section D1 of the first section is replaced with the new floor slab 3, the work section O1 parallel to the work section O1 is replaced with the new floor slab 3. After that, the work section O2 of the second section is replaced with the new floor slab 3, and the work section D2 parallel to the work section D2 is replaced with the new floor slab 3. A procedure such as repeating this work may be adopted.

このように、既設床版の取替え工法は、図4で示すような第1の工程から第3の工程までの一連の作業の中で、現場条件や施工状況(例えば、ケレン作業やスタッドジベル21の設置作業等の進捗状況)に応じて、作業を中断する段階を適宜選択できる。これにより、交通解放時間帯の到来に備えつつ、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整でき、効率よく新設床版3の取り換え作業を実施することが可能となる。 As described above, the replacement method of the existing floor slab can be applied to the site conditions and construction conditions (for example, keren work and stud gibber 21) in a series of work from the first step to the third step as shown in FIG. Depending on the progress of the installation work, etc.), the stage at which the work is interrupted can be selected as appropriate. As a result, it is possible to adjust the progress of the work process to be carried out within one construction traffic regulation time zone while preparing for the arrival of the traffic release time zone, and it is possible to efficiently carry out the replacement work of the new floor slab 3. ..

したがって、夜間に車線規制時間帯を設定することで、昼間の交通解放を実現しながら、既設床版1を新設床版3に取替えることが可能となる。これにより、既設床版取替作業を実施しようとする道路橋Bが、都市部等の重交通路上または長大トンネルに挟まれた山間部等にある場合にも、周辺地域の交通環境への影響を最小限に抑えつつ施工を実施することが可能となる。 Therefore, by setting the lane regulation time zone at night, it is possible to replace the existing floor slab 1 with the new floor slab 3 while realizing the daytime traffic release. This will affect the traffic environment in the surrounding area even if the road bridge B for which the existing floor slab replacement work is to be carried out on a heavy traffic road such as an urban area or in a mountainous area sandwiched between long tunnels. It is possible to carry out the construction while minimizing the problem.

また、既設床版片11の橋軸方向からみた断面を、既設床版1の横断面を半分に分割した半断面に形成することで、昼間は、上り2車線用の橋梁B1と下り2車線用の橋梁B2の両者を交通解放し、夜間は、上り2車線用の橋梁B1のみに車線規制を行う半断面床版取替え工法により、橋梁B1における既設床版1の取替作業を実施できる。 Further, by forming the cross section of the existing deck piece 11 as viewed from the bridge axis direction into a half cross section obtained by dividing the cross section of the existing deck 1 in half, the bridge B1 for the up two lanes and the down two lanes are formed in the daytime. By the half-section deck replacement method in which both of the bridges B2 for use are released from traffic and the lanes are restricted only to the bridge B1 for two lanes at night, the replacement work of the existing deck 1 in the bridge B1 can be carried out.

したがって、道路橋Bを構成する上り車線用と下り車線用の橋梁B1、B2のうち、いずれか一方を全面通行止めにして工事を行い、他方を対面通行規制とする必要が無いため、通行車両に対する安全性の確保が可能になるとともに、道路構造等の事情により対面通行規制を実施できない、または、実施が可能であっても周辺地域の交通状況によっては長期間の通行規制が困難である等、様々な課題を有する道路環境にあっても、既設床版1の取替工事を確実に実施することが可能となる。 Therefore, it is not necessary to make one of the bridges B1 and B2 for the up lane and the bridges B1 and B2 for the down lane constituting the road bridge B completely closed, and to restrict the other to the two-way traffic. In addition to ensuring safety, it is not possible to implement face-to-face traffic restrictions due to road structure, etc., or even if it is possible, long-term traffic restrictions are difficult depending on the traffic conditions in the surrounding area. Even in a road environment with various problems, it is possible to reliably carry out replacement work for the existing floor slab 1.

本発明の橋梁の床版取替え工法は、上記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲で種々の変更が可能である。 The floor slab replacement method for bridges of the present invention is not limited to the above embodiment, and various changes can be made without departing from the spirit of the present invention.

例えば、本実施の形態では、本設プレート52を使用することにより、隣り合う新設床版3の間に形成される横目地部J1及び縦目地部J2に対して、間詰コンクリート51を打設する前に本舗装6を実施できる。このため、第3の工程でStep5〜9を実施することとしたが、本設プレート52を使用しない場合には、第3の工程を2回に分割すればよい。 For example, in the present embodiment, by using the main plate 52, the pavement concrete 51 is placed on the horizontal joint portion J1 and the vertical joint portion J2 formed between the adjacent new floor slabs 3. The main pavement 6 can be carried out before this is done. Therefore, it was decided to carry out Steps 5 to 9 in the third step, but when the main plate 52 is not used, the third step may be divided into two steps.

この場合には、第3の前半工程は、新設床版3の据え付けから無収縮モルタル4を充填する工程(Step5、6)を実施する。また、第3の後半工程は、隣り合う新設床版3の横目地部J1に、間詰めコンクリート51を充填したのちに(Step9)、本舗装6を施す(Step8)。そして、第3の前半工程を3度目の車線規制時間帯の到来時に行い、第3の後半工程を4度目の車線規制時間帯到来時に実施する。 In this case, in the third first half step, the step of filling the non-shrink mortar 4 from the installation of the new floor slab 3 (Steps 5 and 6) is carried out. Further, in the third latter half step, the horizontal joint portion J1 of the adjacent new floor slab 3 is filled with the padded concrete 51 (Step 9), and then the main pavement 6 is applied (Step 8). Then, the third first half process is performed when the third lane regulation time zone arrives, and the third second half process is performed when the fourth lane regulation time zone arrives.

なお、第3の前半工程では、Step6で無収縮モルタル4を充填したのち、図15(a)で示すように、隣り合う新設床版3との間に形成された横目地部J1に仮間詰め9を行い、新設床版3の上面全面に一旦、仮舗装8を施す。 In the third first half step, after filling the non-shrink mortar 4 with Step 6, as shown in FIG. 15A, a temporary space is formed in the horizontal joint portion J1 formed between the adjacent new floor slabs 3. Filling 9 is performed, and temporary pavement 8 is temporarily applied to the entire upper surface of the new floor slab 3.

そして、第3の後半工程は、新設床版3の上面に施した仮舗装8をはく離するとともに、隣り合う新設床版3との間に形成された横目地部J1の仮間詰め9を取り除き、横目地部J1の底面に型枠53を設置して、横目地部J1の上方から間詰めコンクリート51を充填し養生し、本設間詰め5を行う。 Then, in the third second half step, the temporary pavement 8 provided on the upper surface of the new floor slab 3 is peeled off, and the temporary filling 9 of the horizontal joint portion J1 formed between the adjacent new floor slab 3 is removed. A formwork 53 is installed on the bottom surface of the horizontal joint portion J1, and the padded concrete 51 is filled and cured from above the horizontal joint portion J1 to perform the main filling 5.

所定時間の養生が終了したのち、図13(b)で示すように、新設床版3の上面全面に本舗装6を施す。なお、縦目地部J2と、既設床版1もしくは既設床版片11と新設床版3との間に形成された横目地部J1とは、第3の前半工程で行った仮間詰め9を残置しておき、その上面から本舗装6を施せばよい。 After the curing for a predetermined time is completed, as shown in FIG. 13B, the main pavement 6 is applied to the entire upper surface of the new floor slab 3. The vertical joint portion J2 and the horizontal joint portion J1 formed between the existing floor slab 1 or the existing floor slab piece 11 and the new floor slab 3 are the temporary pavement 9 performed in the third first half step. It may be left behind and the main pavement 6 may be applied from the upper surface thereof.

1 既設床版
11 既設床版片
2 主桁
21 スタッドジベル
22 作業足場
3 新設床版
31 床版本体
32 地覆
33 接合鉄筋
34 スタッドジベル挿通孔
4 無収縮モルタル
41 モルタル止め
5 本設間詰め
51 間詰めコンクリート
52 本設プレート
53 型枠
6 本舗装
7 仮覆工床版
71 床版本体
72 地覆
73 高欄
74 高さ調整材
8 仮舗装
81 先行仮舗装
82 後行仮舗装
9 仮間詰め
91 開口塞ぎ板
92 充填材
93 締結具
10 床版架設装置

J1 横目地部
J2 縦目地部
B 道路橋
B1 橋梁(上り2車線)
B2 橋梁(下り2車線)
1 Existing floor slab 11 Existing floor slab piece 2 Main girder 21 Stud gibber 22 Work scaffold 3 New floor slab 31 Floor slab body 32 Ground cover 33 Joint reinforcement 34 Stud gibber insertion hole 4 Non-shrink mortar 41 Mortal stopper 5 Main pavement 51 Filling concrete 52 Main plate 53 Form frame 6 Main pavement 7 Temporary lining Deck 71 Floor slab body 72 Ground covering 73 Gauge 74 Height adjustment material 8 Temporary pavement 81 Preceding temporary pavement 82 Subsequent temporary pavement 9 Temporary pavement 91 Opening closing plate 92 Filling material 93 Fastener 10 Deck erection device

J1 Horizontal joint J2 Vertical joint B Road bridge B1 Bridge (up 2 lanes)
B2 bridge (2 lanes down)

Claims (5)

工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、鋼製の主桁上に設置された既設床版をプレキャストコンクリート造の新設床版に取替える橋梁の床版取替え工法であって、
橋梁の既存床版を橋軸方向に分割して形成した複数の既存床版片のうち、少なくとも一部を撤去して前記主桁を露出させる第1の工程と、
前記第1の工程で露出させた前記主桁上面に、スタッドジベルを設置する第2の工程と、
前記第2の工程で前記スタッドジベルを設置した前記主桁上に、複数の前記新設床版を据え付け、前記新設床版を前記主桁に接合させたのち、隣り合う新設床版を接合する第3の工程と、を備え、
前記第1の工程から前記第3の工程は、前記工事交通規制時間帯に実施されるとともに、1回の前記工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含み、
前記交通解放時間帯が到来する直前に前記第1の工程もしくは前記第2の工程が実施される場合、作業終了時において露出状態にある前記主桁上に、仮覆工床版を設置することを特徴とする橋梁の床版取替え工法。
It is a bridge deck replacement method that replaces the existing deck installed on the steel main girder with a new precast concrete deck while alternately repeating the construction traffic regulation time zone and the traffic release time zone.
The first step of removing at least a part of the existing deck pieces formed by dividing the existing deck of the bridge in the direction of the bridge axis to expose the main girder.
A second step of installing a stud girder on the upper surface of the main girder exposed in the first step, and
A plurality of the new floor slabs are installed on the main girder on which the stud girder is installed in the second step, the new floor slabs are joined to the main girder, and then adjacent new floor slabs are joined. With 3 steps,
The first step to the third step include the case where the steps are carried out during the construction traffic regulation time zone and two or more steps are continuously carried out within the construction traffic regulation time zone once. ,
When the first step or the second step is carried out immediately before the traffic release time zone arrives, a temporary lining deck is installed on the main girder which is exposed at the end of the work. The floor slab replacement method for bridges, which is characterized by this.
請求項1に記載の橋梁の床版取替え工法において、
前記第1の工程から前記第3の工程を、前記工事交通規制時間帯が到来するごとに橋軸方向に繰り返すことを特徴とする橋梁の床版取替え工法。
In the deck replacement method for bridges according to claim 1,
A bridge deck replacement method, characterized in that the first step to the third step are repeated in the direction of the bridge axis each time the construction traffic regulation time zone arrives.
請求項1または2に記載の橋梁の床版取替え工法において、
前記既存床版片の橋軸方向からみた断面が、前記既存床版の横断面を半分に分割した半断面に形成されることを特徴とする橋梁の床版取替え工法。
In the bridge deck replacement method according to claim 1 or 2,
A bridge deck replacement method, characterized in that the cross section of the existing deck piece seen from the bridge axis direction is formed into a half cross section obtained by dividing the cross section of the existing deck in half.
請求項1から3のいずれか1項に記載の橋梁の床版取替え工法において、
第3の工程で、
隣り合う前記新設床版を、該新設床板の一部として機能する本設プレートで接合することを特徴とする橋梁の床版取替え工法。
In the bridge deck replacement method according to any one of claims 1 to 3,
In the third step
A bridge slab replacement method characterized by joining adjacent new floor slabs with a main plate that functions as a part of the new floor slab.
請求項1から4のいずれか1項に記載の橋梁の床版取替え工法において、
前記主桁上に前記仮覆工床版を設置したのち、
該仮覆工床版に隣接する目地の上下面をそれぞれ開口塞ぎ板で覆い、該開口塞ぎ板どうしを締結具を介して締結することを特徴とする橋梁の床版取替え工法。
In the bridge deck replacement method according to any one of claims 1 to 4,
After installing the temporary lining floor slab on the main girder,
A method for replacing a floor slab of a bridge, characterized in that the upper and lower surfaces of joints adjacent to the temporary lining floor slab are covered with opening closing plates, and the opening closing plates are fastened to each other via fasteners.
JP2020097190A 2020-06-03 2020-06-03 Bridge deck replacement method Active JP7484439B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020097190A JP7484439B2 (en) 2020-06-03 2020-06-03 Bridge deck replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020097190A JP7484439B2 (en) 2020-06-03 2020-06-03 Bridge deck replacement method

Publications (2)

Publication Number Publication Date
JP2021188454A true JP2021188454A (en) 2021-12-13
JP7484439B2 JP7484439B2 (en) 2024-05-16

Family

ID=78849023

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020097190A Active JP7484439B2 (en) 2020-06-03 2020-06-03 Bridge deck replacement method

Country Status (1)

Country Link
JP (1) JP7484439B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7384310B1 (en) 2023-06-16 2023-11-21 株式会社Ihi Joint structure, floor slab and floor slab replacement method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3702263B2 (en) 2002-10-23 2005-10-05 三菱重工業株式会社 Bridge replacement method
JP6837343B2 (en) 2017-02-03 2021-03-03 首都高速道路株式会社 Floor slab replacement method for synthetic girders
JP7442256B2 (en) 2017-10-18 2024-03-04 鹿島建設株式会社 How to replace the floor slab

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7384310B1 (en) 2023-06-16 2023-11-21 株式会社Ihi Joint structure, floor slab and floor slab replacement method

Also Published As

Publication number Publication date
JP7484439B2 (en) 2024-05-16

Similar Documents

Publication Publication Date Title
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
JP6316665B2 (en) Composite structure of steel girder and precast slab and its construction method
JP6097965B2 (en) Construction method of concrete precast slab for bridge
KR101258807B1 (en) Tunnel installation method and tunnel installation structure of crossing railroad
JP7442256B2 (en) How to replace the floor slab
KR101107826B1 (en) Slab-type box girder made by precast concrete and method constructing the bridge therewith
JP5037453B2 (en) Lined concrete structure and its construction method
CN110528403A (en) A kind of construction method of the end bay without wet seam precast segment free cantilever erection continuous beam
JP2021188454A (en) Bridge floor slab replacement method
JP2021001536A (en) Bridge floor slab replacement method
JP5143666B2 (en) PC bridge erection method
JP2013053413A (en) Construction method for slab, shear reinforcement, and concrete beam structure
TWI754158B (en) Structure for bridges and method for replacing floor slab
JP2003129403A (en) Block type traffic road, dividing bridge type traffic road and bridge traffic road
JP7306053B2 (en) Joint structure of precast floor slab and construction method of joint
JP5769291B2 (en) Precast synthetic slab erection method
JP6639964B2 (en) Road bridge telescopic device and its installation method
KR100758878B1 (en) Method for repairing bridge using integrated girder-concrete slab assembly
JP2008285944A (en) Prebacked concrete girder and its construction method
JPH023843B2 (en)
JP2020147980A (en) Repair method for existing concrete pavement, and concrete slab
JP2020133214A (en) Floor slab replacement method and vehicle going-over board
JP2022134750A (en) Temporary covering slab, installing structure of temporary covering slab, and installing method of temporary covering slab
JP2023014030A (en) Cutting method of floor slab, floor slab exchange construction method and shear reinforcement structure
JP2018197476A (en) Floor slab renewal method, floor slab joining structure and road bridge

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230518

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231130

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231212

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240130

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240220

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240312

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240402

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240415

R150 Certificate of patent or registration of utility model

Ref document number: 7484439

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150