CN110528403A - A kind of construction method of the end bay without wet seam precast segment free cantilever erection continuous beam - Google Patents

A kind of construction method of the end bay without wet seam precast segment free cantilever erection continuous beam Download PDF

Info

Publication number
CN110528403A
CN110528403A CN201910840426.0A CN201910840426A CN110528403A CN 110528403 A CN110528403 A CN 110528403A CN 201910840426 A CN201910840426 A CN 201910840426A CN 110528403 A CN110528403 A CN 110528403A
Authority
CN
China
Prior art keywords
pier
end bay
prefabricated subsection
prefabricated
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910840426.0A
Other languages
Chinese (zh)
Other versions
CN110528403B (en
Inventor
孙峻岭
董传新
雷文斌
马成林
代彬艺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc
Original Assignee
SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc filed Critical SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc
Priority to CN201910840426.0A priority Critical patent/CN110528403B/en
Publication of CN110528403A publication Critical patent/CN110528403A/en
Application granted granted Critical
Publication of CN110528403B publication Critical patent/CN110528403B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention is construction method of the end bay without wet seam precast segment free cantilever erection continuous beam, continuous beam includes beam body and pier stud, beam body, which is divided into several, bridgees across both ends end bay, across being divided into 2n across prefabricated subsection in each, end bay is divided into several end bay prefabricated subsections, and pier stud includes multiple middle piers and both ends abutment pier;Step are as follows: pier top temporary consolidation facility is arranged for each middle pier in No. 0 segment of middle pier pier top of each middle pier of installation;From No. 0 two side direction of segment of middle pier pier top of each middle pier successively it is symmetrical it is assembled it is each in across 2n in across prefabricated subsection;To in two neighboring across the wet seam casting concrete of closure section;It constructs to the end bay prefabricated subsection of each end bay, full-bridge prestressed strand is installed, stretch-draw prestressing force steel beam carries out mud jacking to prestress pipe, releases the pier top temporary consolidation facility of each middle pier, completes bridge system transform.The present invention reduces closure section, reduces construction procedure, cast-in-place concrete workload, improves construction efficiency.

Description

A kind of construction method of the end bay without wet seam precast segment free cantilever erection continuous beam
Technical field
The present invention relates to method for bridge construction, specially construction of the end bay without wet seam precast segment free cantilever erection continuous beam Method.
Background technique
Precast segment assembling technique is longitudinally split by beam body into several segments, in factory or at the construction field (site) according to predetermined Design scheme carry out it is prefabricated, by segmental erection it is in place after, stretch-draw prestressing force steel beam, which gets up each section assembling, becomes complete Beam body.Nowadays the connecting method between beam sections mostly use adhesive for concrete be bonded bonding mode or for segment between in advance The wet of armored concrete is stayed to connect mode.Bonding mode is chiefly used between precast segment block, and the wet mode that connects then is chiefly used in precast segment Between block and non-precast segment block, that is, fragment position of joining the two sections of a bridge, etc.
In prefabrication and assembly construction bridge common at present, end bay closure section and midspan closing section are still applied using cast-in-place mode Work, there are still certain rising spaces for this kind of bridge prefabrication rate, and when the construction of wet seam, are limited by field condition, closure section construction Quality is difficult to control;Set up the duration of the processes such as template, assembling reinforcement, casting concrete, concrete curing, form removal in scene It is longer.In addition, the wet seam precision of closure section is not high and speed is slower, construction efficiency is still to be improved.
Summary of the invention
The purpose of the present invention is to solve the technical problem in above-mentioned background technique, propose a kind of end bay without wet seam section The construction method of the prefabricated free cantilever erection continuous beam of section.
The present invention adopts the following technical scheme: a kind of construction party of end bay without wet seam precast segment free cantilever erection continuous beam Method, the end bay built include beam body and pier stud without wet seam precast segment free cantilever erection continuous beam, and beam body is divided into several Bridge across both ends end bay, it is each in across being divided into 2n across prefabricated subsection, it is two neighboring in the wet seam of closure section is set across between, End bay is divided into several end bay prefabricated subsections, and pier stud includes multiple middle piers and both ends abutment pier;
If it is No. 0 segment of middle pier pier top that the pier top segment of pier, which is compiled, in each, and therefrom No. 0 segment of pier pier top starts to distinguish To the left and right two sides in each across n in sequentially arrange in numerical order across prefabricated subsection;
The construction method the following steps are included:
A, No. 0 segment of middle pier pier top of each middle pier is installed, and pier top temporary consolidation facility is set for each middle pier;
B, from No. 0 two side direction of segment of the middle pier pier top of each middle pier, it is successively symmetrical assembled each in across 2n in across Prefabricated subsection;
C, concreting is carried out to the wet seam of closure section in two neighboring across between;
D, it constructs to the end bay prefabricated subsection of each end bay, installation full-bridge prestressed strand, stretch-draw prestressing force steel beam, Mud jacking is carried out to prestress pipe, releases the pier top temporary consolidation facility of each middle pier, completes bridge system transform.
In preferred embodiments, above-mentioned construction method sets therefrom No. 0 segment of pier pier top and starts to distinguish two sides to the left and right To in each across n in sequentially arrange in numerical order across prefabricated subsection be in first across in prefabricated subsection, second across prefabricated subsection ... Across prefabricated subsection in n-th;Multiple middle piers are pier in first, pier in pier ... m in second;
The step B includes the following steps:
B1, promoted in first simultaneously on the left of pier first in across in first on the right side of pier in prefabricated subsection and first across prefabricated Segment, and be placed on pier top temporary support facility, accurate adjustment contraposition carries out interim prestressed stretch-draw and splicing, to be spliced After adhesive curing, permanent prestressed strand is worn, carries out permanent prestressed stretch-draw;
B2, step B1 is repeated, completes across prefabricated subsection installation in first of two side direction of pier in second;
B3, promoted in the second of the first two sides Zhong Dun simultaneously across prefabricated subsection, in the second of the first two sides Zhong Dun across pre- Segment processed carries out symmetrical splicing, interim and permanent prestressed stretch-draw, pumping of prostressed duct;
B4, repeat step B3, successively in symmetrical assembly first in 3~n of two side direction of pier across prefabricated subsection;
B5, repeat step B3~B4, successively in symmetrical assembly second in 3~n of two side direction of pier across prefabricated subsection;
B6, step B1~B5 is repeated, completes third assembly across prefabricated subsection in each n of two side direction of pier into m.
Preferably, above-mentioned construction method sets both ends abutment pier as the first abutment pier and the second abutment pier, and both ends end bay is divided into not The (n+1)th end bay prefabricated subsection, n-th+2 end bay prefabricated subsection ... the n-th+L end bay prefabricated subsection of wet seam, the n-th side+L are set It is located at the pier top of abutment pier across prefabricated subsection;L is less than n;
Step D includes the following steps:
The (n+1)th end bay prefabricated subsection of D1, the first abutment pier of synchronous lifting and the second abutment pier, splicing, the interim prestressing force of tensioning, Wear permanent prestressed strand and the permanent prestressing force of tensioning;
D2, the n-th+L end bay prefabricated subsection for lifting the first abutment pier and the second abutment pier, and it is placed on interim branch by corresponding pier It supports on seat;
D3, the n-th+2 end bay prefabricated subsection for lifting the first abutment pier, the second abutment pier, splicing, the interim prestressing force of tensioning;
D4, step D3 is repeated, completes the assembly of the n-th+3 to n-th+L-1 end bay prefabricated subsection;
The n-th+L end bay prefabricated subsection of D5, the first abutment pier of lifting and the second abutment pier pier top, splicing exactitude position, tensioning are faced When prestressing force after, the positioning of permanent support, anchor hole and adjustment layer grouting;
D6, installation full-bridge prestressed strand, stretch-draw prestressing force steel beam carry out mud jacking to prestress pipe, release each middle pier Pier top temporary consolidation facility, complete bridge system transform.
Compared with the prior art, the advantages of the present invention are as follows:
1, the present invention reduces construction procedure by the setting of reduction closure section, reduces cast-in-place concrete workload, into And construction efficiency is improved, accelerate construction progress;
2, Cast-in-Situ Segment of the present invention is few, improves the prefabricated rate of bridge subsection, realizes the rapid implementation of bridge greenery construction.
Detailed description of the invention
Fig. 1 is that structure and segment of the end bay without wet seam precast segment free cantilever erection continuous beam divide schematic diagram;
Fig. 2 is the construction schematic diagram that end bay installs No. 0 segment of pier top without wet seam precast segment free cantilever erection continuous beam;
Fig. 3 is the construction that end bay sets up No. 1 segment without pier " T " structure beam section in wet seam precast segment free cantilever erection continuous beam Schematic diagram;
Fig. 4 is the construction that end bay sets up No. 3 segments without pier " T " structure beam section in wet seam precast segment free cantilever erection continuous beam Schematic diagram;
Fig. 5 is end bay without No. 4-No. 8 segments of pier " T " structure beam section erection in wet seam precast segment free cantilever erection continuous beam Construction schematic diagram;
Fig. 6 is construction schematic diagram of the end bay without wet seam precast segment free cantilever erection continuous beam midspan closing section;
Fig. 7 is construction schematic diagram of the end bay without No. 9 segments of wet seam precast segment free cantilever erection continuous beam end bay beam section;
Fig. 8 is construction schematic diagram of the end bay without No. 11 segments of wet seam precast segment free cantilever erection continuous beam end bay beam section;
Fig. 9 is the flow chart of construction method of the present invention;
In figure: 1 is beam body, and 2 be pier stud, and 3 be spanning equipment, and 4 be temporary support seat by middle pier pier, and 5 be to face by abutment pier pier When support base, 11 be in across 12 be end bay, and 13 be No. 0 segment of middle pier pier top, and 21 be No. 1 abutment pier, and 22 be pier in No. 2, and 23 be 3 Pier in number, 24 be pier in No. 4, and 25 be No. 5 abutment piers, 111 be in across prefabricated subsection, 112 be the wet seam of closure section, 121 be end bay Prefabricated subsection.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples, but embodiments of the present invention are not limited to This.
Embodiment
With reference to Fig. 1, the end bay that construction method of the present invention is built without wet seam precast segment free cantilever erection continuous beam, including Beam body 1 and pier stud 2, beam body 1 be divided into across 11 and both ends end bay 12, in it is unlimited across 11 quantity, can be set as several in across.Each In be divided into several across prefabricated subsection 111 again across 11, and take precast segment assembling technique assembled, it is two neighboring in across The wet seam 112 of closure section is set between 11.End bay 12 is equally divided into several end bay prefabricated subsections 121, and takes precast segment Assembling technique is assembled, but the assembly of all segments of end bay 12 is not provided with wet seam.The pier stud of bridge include multiple middle piers and Both ends abutment pier, i.e., 24, No. 1 abutment piers 21 of pier and No. 5 abutment piers 25 in pier 23,4 in pier 22,3 in No. 2.
In the present invention, continuous beam often across section number, therefrom pier pier top segment starts, pier 23,4 in pier 22,3 in No. 2 The pier top section number of 24 pier top of pier is No. 0 in number, other section numbers therefrom start two sides forwards, backwards in No. 0 segment of pier pier top Sequentially arrange in numerical order;And the spanning equipment applicable according to segment weight setting scene, with handling, unloading on site.The present embodiment In, it is each in across being divided into 16 across prefabricated subsection, it is each in the left and right sides of pier have in 8 respectively across prefabricated subsection.
The present invention is illustrated by taking one or four bridge beams as an example, and such as Fig. 9, specific implementation step is as follows:
S1, with reference to Fig. 2, No. 0 segment 13 of middle pier pier top of each middle pier is installed: being installed using spanning equipment 3 and is faced by abutment pier pier When support base 5 and middle pier pier by temporary support seat 4, spanning equipment 3 promotes No. 0 segment of pier pier top in corresponding from beam strorage area, and pacifies Fill in No. 4 No. 0 segment of middle pier pier top of pier 22 in pier 23,2 in pier 24,3;And pier top temporary consolidation is set for each middle pier Facility;
S2~S7, middle pier " T " structure beam section is assembled, i.e., successively right from No. 0 two side direction of segment of the middle pier pier top of each middle pier Claim in assembled each across 2n in across prefabricated subsection:
S2, promoted simultaneously in No. 1 in first on the left of pier across in 1 ' number on the right side of pier in prefabricated subsection and first across prefabricated Segment, and be placed on pier top temporary support facility, accurate adjustment contraposition carries out interim prestressed stretch-draw and splicing, to be spliced After adhesive curing, permanent prestressed strand is worn, carries out permanent prestressed stretch-draw;
With reference to Fig. 3, spanning equipment 3 promotes 1 ' number across prefabricated subsection and its right side in No. 1 of 23 left side of pier in No. 3 simultaneously In across prefabricated subsection, and be placed on by middle pier pier on temporary support seat 4, accurate adjustment contraposition carries out splicing and interim prestressing force Tensioning.
S3, step S2 is repeated, completes across prefabricated subsection installation in No. 1 of two side direction of pier in second;
Spanning equipment 3 is promoted simultaneously in No. 1 across 24 left side of pier in prefabricated subsection and No. 4 in No. 1 of 24 right side of pier in No. 4 It across prefabricated subsection, and is placed on by middle pier pier on temporary support seat 4, accurate adjustment contraposition carries out splicing and interim prestressing force It draws, wears permanent prestressed strand, carry out permanent prestressed stretch-draw.
S4, promoted in No. 2 and 2 ' numbers of the first two sides Zhong Dun simultaneously No. 2 across prefabricated subsection, to the first two sides Zhong Dun and The symmetrical splicing of across prefabricated subsection carry out in 2 ' numbers, interim and permanent prestressed stretch-draw, pumping of prostressed duct;
Such as Fig. 3, spanning equipment 3 promotes across prefabricated subsection installation in No. 2 and 2 ' numbers of No. 3 two sides Zhong Dun23 simultaneously.
S5, repeat step S4, successively in symmetrical assembly first in the 3rd~No. n of two side direction of pier across prefabricated subsection;
Such as Fig. 4,5, spanning equipment 3 is promoted in the 3rd~No. n of No. 3 two sides Zhong Dun23 simultaneously across prefabricated subsection, in No. 3 The symmetrical splicing of across prefabricated subsection carry out in the 3rd~No. n of 23 two sides of pier, interim and permanent prestressed stretch-draw, prestress pipe pressure Slurry.
S6, repeat step S4~S5, successively in symmetrical assembly second in 3~No. n of two side direction of pier across prefabricated subsection;
Referring to fig. 4,5, successively 24 liang of side directions of pier in symmetrical assembled No. 4, across prefabricated subsection in 3~No. 8.
S7, step S2~S6 is repeated, completes third assembly across prefabricated subsection in each n of two side direction of pier into m.
In each the assembled process across prefabricated subsection include splicing, interim and permanent prestressed stretch-draw, prestress pipe Mud jacking.Across prefabricated subsection in 1~No. 8 of No. 2 two sides Zhong Dun22, the symmetrical assembly side similar with above-mentioned steps S2~S7 is also used Method come place, splicing, interim and permanent prestressed stretch-draw, pumping of prostressed duct.
The midspan closing construction of S8~10, the construction of midspan closing section, the present embodiment is divided into 2 times, i.e., pier 23 and 4 in No. 3 22 sections of pier of midspan closing in pier 23 and No. 2 in across prefabricated subsection closure and No. 3 in 24 sections of pier in number:
S8, with reference to Fig. 6, after respectively installing 8 across prefabricated subsection in " the T structure " of pier 24 in pier 23 in No. 3 and No. 4, carry out 3 The midspan closing section of pier 24 is constructed in pier 23 and No. 4 in number, and wet 112 width of seam of midspan closing section is 1.0m, using mixed The solidifying wet joint form of soil, carries out the wet seam of closure section 112 cast-in-place;
S9, with reference to Fig. 6, remove in No. 4 temporary support seat 4 by the middle pier pier of pier 24, shift and install to pier 22 in No. 2;
S10, step S2~S7 is repeated, completes across prefabricated subsection installation in " the T structure " of pier 22 in No. 2;Step S8 is repeated, into 22 sections of pier of midspan closing section construction in pier 23 and No. 2 in row 3;
S11~S15 constructs to the end bay prefabricated subsection of end bay 12, and three end bay prefabricated subsections of each end bay 12 are not set Wet seam is set, steps are as follows for Specific construction:
S11, with reference to Fig. 7, No. 9 end bays using two spanning equipments 3 No. 5 end bays 25 of synchronous lifting and No. 1 end bay 21 are pre- Segment processed, splicing, the interim prestressing force of tensioning wear permanent prestressed strand and the permanent prestressing force of tensioning;
S12, two spanning equipments 3 lift No. 11 end bay prefabricated subsections of No. 5 abutment pier 25 and No. 1 abutment piers 21, and are placed on By corresponding pier on temporary support seat 5;
S13, two spanning equipments 3 lift No. 10 end bay prefabricated subsections of 25, No. 1 abutment piers 21 of No. 5 abutment piers, splicing, tensioning Interim prestressing force;
S14, with reference to Fig. 8, overhead traveling crane lifts by crane No. 11 end bay prefabricated subsections of No. 5 abutment piers 25 and No. 1 21 pier top of abutment pier, splicing essence Really after contraposition, the interim prestressing force of tensioning, permanent support positioning, anchor hole and adjustment layer grouting;
S15, installation full-bridge prestressed strand, stretch-draw prestressing force steel beam carry out mud jacking to prestress pipe, release in No. 2 In pier 22,3 in pier 23,4 pier 24 pier top temporary consolidation facility, complete bridge system transform.
The above embodiment is a preferred embodiment of the present invention, but embodiments of the present invention are not by above-described embodiment Limitation, other any changes, modifications, substitutions, combinations, simplifications made without departing from the spirit and principles of the present invention, It should be equivalent substitute mode, be included within the scope of the present invention.

Claims (5)

1. a kind of construction method of end bay without wet seam precast segment free cantilever erection continuous beam, which is characterized in that the side built Across including beam body and pier stud without wet seam precast segment free cantilever erection continuous beam, beam body, which is divided into several, bridgees across both ends end bay, Across being divided into 2n across prefabricated subsection in each, it is each in the left and right sides of pier have in n respectively across prefabricated subsection, adjacent two The wet seam of closure section is set across between in a, and end bay is divided into several end bay prefabricated subsections, and pier stud includes multiple middle piers and both ends Abutment pier;
If it is No. 0 segment of middle pier pier top that the pier top segment of pier, which is compiled, in each, and therefrom No. 0 segment of pier pier top starts respectively to the left Right two sides in each across n in sequentially arrange in numerical order across prefabricated subsection;
The construction method the following steps are included:
A, No. 0 segment of middle pier pier top of each middle pier is installed, and pier top temporary consolidation facility is set for each middle pier;
B, from No. 0 two side direction of segment of the middle pier pier top of each middle pier, it is successively symmetrical assembled each in across 2n in across prefabricated Segment;
C, concreting is carried out to the wet seam of closure section in two neighboring across between;
D, it constructs to the end bay prefabricated subsection of each end bay, full-bridge prestressed strand, stretch-draw prestressing force steel beam, to pre- is installed Stress pipeline carries out mud jacking, releases the pier top temporary consolidation facility of each middle pier, completes bridge system transform.
2. construction method according to claim 1, which is characterized in that set therefrom No. 0 segment of pier pier top and start respectively to the left Right two sides in each across n in sequentially arrange in numerical order across prefabricated subsection be in first across in prefabricated subsection, second across prefabricated section Section ... is across prefabricated subsection in n-th;Multiple middle piers are pier in first, pier in pier ... m in second;
The step B includes the following steps:
B1, promoted in first simultaneously on the left of pier first in across in first on the right side of pier in prefabricated subsection and first across prefabricated section Section, and be placed on pier top temporary support facility, accurate adjustment contraposition carries out interim prestressed stretch-draw and splicing, glue to be spliced After solidification, permanent prestressed strand is worn, carries out permanent prestressed stretch-draw;
B2, step B1 is repeated, completes across prefabricated subsection installation in first of two side direction of pier in second;
B3, promoted in the second of the first two sides Zhong Dun simultaneously across prefabricated subsection, in the second of the first two sides Zhong Dun across prefabricated section The symmetrical splicing of Duan Jinhang, interim and permanent prestressed stretch-draw, pumping of prostressed duct;
B4, repeat step B3, successively in symmetrical assembly first in 3~n of two side direction of pier across prefabricated subsection;
B5, repeat step B3~B4, successively in symmetrical assembly second in 3~n of two side direction of pier across prefabricated subsection;
B6, step B1~B5 is repeated, completes third assembly across prefabricated subsection in each n of two side direction of pier into m.
3. construction method according to claim 2, which is characterized in that the assembled process across prefabricated subsection includes in each Splicing, interim and permanent prestressed stretch-draw, pumping of prostressed duct.
4. construction method according to claim 2, which is characterized in that in step B, using spanning equipment to each two sides Zhong Dun It is each in promoted across prefabricated subsection.
5. construction method according to claim 1, which is characterized in that set both ends abutment pier as the first abutment pier and the second abutment pier, Both ends end bay is divided into the (n+1)th end bay prefabricated subsection for being not provided with wet seam, the n-th+2 side the n-th+L of end bay prefabricated subsection ... Across prefabricated subsection, the n-th+L end bay prefabricated subsection is located at the pier top of abutment pier;L is less than n;Step D includes the following steps:
The (n+1)th end bay prefabricated subsection of D1, the first abutment pier of synchronous lifting and the second abutment pier, splicing, are worn forever the interim prestressing force of tensioning Long prestressed strand and the permanent prestressing force of tensioning;
D2, the n-th+L end bay prefabricated subsection for lifting the first abutment pier and the second abutment pier, and it is placed on temporary support seat by corresponding pier On;
D3, the n-th+2 end bay prefabricated subsection for lifting the first abutment pier, the second abutment pier, splicing, the interim prestressing force of tensioning;
D4, step D3 is repeated, completes the assembly of the n-th+3 to n-th+L-1 end bay prefabricated subsection;
The n-th+L end bay prefabricated subsection of D5, the first abutment pier of lifting and the second abutment pier pier top, splicing exactitude position, tensioning are temporarily pre- After stress, permanent support positioning, anchor hole and adjustment layer grouting;
D6, installation full-bridge prestressed strand, stretch-draw prestressing force steel beam carry out mud jacking to prestress pipe, release the pier of each middle pier Temporary consolidation facility is pushed up, bridge system transform is completed.
CN201910840426.0A 2019-09-06 2019-09-06 Construction method for side-span non-wet joint section prefabricated cantilever assembly continuous beam Active CN110528403B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910840426.0A CN110528403B (en) 2019-09-06 2019-09-06 Construction method for side-span non-wet joint section prefabricated cantilever assembly continuous beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910840426.0A CN110528403B (en) 2019-09-06 2019-09-06 Construction method for side-span non-wet joint section prefabricated cantilever assembly continuous beam

Publications (2)

Publication Number Publication Date
CN110528403A true CN110528403A (en) 2019-12-03
CN110528403B CN110528403B (en) 2021-08-13

Family

ID=68667305

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910840426.0A Active CN110528403B (en) 2019-09-06 2019-09-06 Construction method for side-span non-wet joint section prefabricated cantilever assembly continuous beam

Country Status (1)

Country Link
CN (1) CN110528403B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119071A (en) * 2020-01-16 2020-05-08 中建七局安装工程有限公司 Construction method for assembling precast concrete segment box girder
CN111472284A (en) * 2020-04-30 2020-07-31 中建七局安装工程有限公司 Assembling method for cantilever of prefabricated segmental beam portal crane of urban viaduct
CN112095438A (en) * 2020-08-19 2020-12-18 中铁五局集团有限公司 Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment
CN116356761A (en) * 2023-04-14 2023-06-30 中水珠江规划勘测设计有限公司 Segmental prefabricated aqueduct and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2295604C2 (en) * 2005-06-03 2007-03-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Method for solid metal beam span structure assemblage
CN101684638A (en) * 2008-09-23 2010-03-31 中交第三航务工程局有限公司 Assembly method of section box girder
CN102425117A (en) * 2011-12-26 2012-04-25 中铁大桥局股份有限公司 Construction method for non-cantilever sections of sidespans of multiplex continuous beam or steel-constructed beam
CN103215898A (en) * 2013-04-02 2013-07-24 天津市市政工程设计研究院 Variable-cross-section concrete continuous bridge construction method
CN108149580A (en) * 2017-12-29 2018-06-12 广州瀚阳工程咨询有限公司 Based on cantilever balance assembly without bearing full-bridge precast segment method
CN108660902A (en) * 2018-06-19 2018-10-16 中国铁路总公司 A kind of Railway Prestressed Concrete continuous bridge of precast segment pin-connected panel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2295604C2 (en) * 2005-06-03 2007-03-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Method for solid metal beam span structure assemblage
CN101684638A (en) * 2008-09-23 2010-03-31 中交第三航务工程局有限公司 Assembly method of section box girder
CN102425117A (en) * 2011-12-26 2012-04-25 中铁大桥局股份有限公司 Construction method for non-cantilever sections of sidespans of multiplex continuous beam or steel-constructed beam
CN103215898A (en) * 2013-04-02 2013-07-24 天津市市政工程设计研究院 Variable-cross-section concrete continuous bridge construction method
CN108149580A (en) * 2017-12-29 2018-06-12 广州瀚阳工程咨询有限公司 Based on cantilever balance assembly without bearing full-bridge precast segment method
CN108660902A (en) * 2018-06-19 2018-10-16 中国铁路总公司 A kind of Railway Prestressed Concrete continuous bridge of precast segment pin-connected panel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王文: "连徐高铁最新消息", 《澎湃网》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119071A (en) * 2020-01-16 2020-05-08 中建七局安装工程有限公司 Construction method for assembling precast concrete segment box girder
CN111472284A (en) * 2020-04-30 2020-07-31 中建七局安装工程有限公司 Assembling method for cantilever of prefabricated segmental beam portal crane of urban viaduct
CN112095438A (en) * 2020-08-19 2020-12-18 中铁五局集团有限公司 Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment
CN116356761A (en) * 2023-04-14 2023-06-30 中水珠江规划勘测设计有限公司 Segmental prefabricated aqueduct and construction method thereof

Also Published As

Publication number Publication date
CN110528403B (en) 2021-08-13

Similar Documents

Publication Publication Date Title
CN110528403A (en) A kind of construction method of the end bay without wet seam precast segment free cantilever erection continuous beam
US8474080B2 (en) Construction method of steel composition girder bridge
CN102230315B (en) Prefabricated part and semi-prefabricated construction method for multistory building
WO2006062801A2 (en) Bridge construction system and method
CN104480846B (en) A kind of construction method splicing bridge
CN108915726A (en) Use the seamless tunnel structure and its construction method of ECC late poured band
CN111305081B (en) Construction process of wet joint connecting structure of prefabricated bridge deck
CN110747903A (en) Porous frame bridge and assembling construction method thereof
JP5015049B2 (en) Pier extension method
CN110761185A (en) Prestress assembly type track beam for station and construction method thereof
JP5143666B2 (en) PC bridge erection method
JP2009041271A (en) Construction method for bridge
KR20160029277A (en) Construction Method to Create Multi-span Continuity in PSC Bridges
CN115652812B (en) Asynchronous construction method of PK section composite beam cable-stayed bridge
KR101339367B1 (en) Fabrication and reinforcing method for pre-flex girder
US20230160160A1 (en) Method for the production of a deck slab for a bridge
JP5528217B2 (en) Abutment reinforcement method
KR100555046B1 (en) A tunnel structure and method for constructing of it
JP7484439B2 (en) Bridge deck replacement method
JP5139718B2 (en) Construction method of pre-packed concrete girder
CN113981808A (en) Structure and construction method of segmental precast concrete T-shaped beam
JPS5980809A (en) Construction of prestressed concrete floor panel in road bridge
CN210856909U (en) Continuous beam assembled by prefabricated cantilever of side span non-wet joint segment
EP3885491A1 (en) Method for renovating a railway line
CN111395167B (en) Construction method of continuous rigid frame bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 510220 Guangzhou Tianhe District, Guangdong Province, 23 Sicheng Road, Hongtai Wisdom Valley Building 2 Floor 239A

Applicant after: Hanyang International Engineering Consulting Co., Ltd

Address before: 510220 Guangzhou Tianhe District, Guangdong Province, 23 Sicheng Road, Hongtai Wisdom Valley Building 2 Floor 239A

Applicant before: Guangzhou Hanyang Engineering Consulting Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant