JP7484439B2 - Bridge deck replacement method - Google Patents

Bridge deck replacement method Download PDF

Info

Publication number
JP7484439B2
JP7484439B2 JP2020097190A JP2020097190A JP7484439B2 JP 7484439 B2 JP7484439 B2 JP 7484439B2 JP 2020097190 A JP2020097190 A JP 2020097190A JP 2020097190 A JP2020097190 A JP 2020097190A JP 7484439 B2 JP7484439 B2 JP 7484439B2
Authority
JP
Japan
Prior art keywords
deck
bridge
new
existing
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020097190A
Other languages
Japanese (ja)
Other versions
JP2021188454A (en
Inventor
康太 丈達
重洋 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2020097190A priority Critical patent/JP7484439B2/en
Publication of JP2021188454A publication Critical patent/JP2021188454A/en
Application granted granted Critical
Publication of JP7484439B2 publication Critical patent/JP7484439B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)

Description

本発明は、工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、既設床版をプレキャスト造の新設床版に取替える、橋梁の床版取替え工法に関する。 This invention relates to a bridge deck replacement method in which an existing deck is replaced with a new precast deck while alternating between construction traffic restriction periods and traffic-free periods.

従来より、上り車線用の橋梁と下り車線用の橋梁とを備える大規模な道路橋において、橋梁の既設床版を新設床版に取替える更新工事を行う際には、上り車線用と下り車線用の橋梁のうち、いずれか一方の橋梁を全面通行止めにして更新工事を行い、他方の橋梁を対面通行規制している。 Traditionally, when carrying out renovation work on large road bridges that have bridges for inbound and outbound lanes to replace the existing bridge deck with a new deck, one of the bridges for the inbound or outbound lanes is closed to traffic while the renovation work is carried out, and traffic is restricted in both directions on the other bridge.

しかし、都市部等の重交通路や長大トンネルに挟まれた山間部等では、長期間にわたって対面通行規制を実施すると、周辺地域の交通環境に悪影響を及ぼしかねない。このため、夜間のみ車線規制を行って更新工事を行い、昼間は全面交通解放する方法が望まれている。例えば、特許文献1には、夜間に道路規制を行って既設床版を新設床版に取替える橋梁床版の施工方法として、作業者をPC床版敷設班と間詰めコンクリート班に分けて実施する方法が開示されている。 However, in heavy traffic roads in urban areas and mountainous areas sandwiched between long tunnels, restricting two-way traffic for long periods of time can have a negative impact on the traffic environment in the surrounding areas. For this reason, there is a need for a method of restricting lanes only at night while carrying out renewal work and opening up the entire area to traffic during the day. For example, Patent Document 1 discloses a bridge deck construction method in which road restrictions are implemented at night to replace the existing deck with a new one, in which workers are divided into a PC deck laying team and a concrete filling team.

具体的には、PC床版敷設班が、主桁上の既設床版の切断・撤去したのち、新設のプレキャスト床版を橋軸方向に並列に敷設し、隣り合うプレキャスト床版の目地を仮覆工版で覆う。こののち、仮覆工版の上面に仮舗装を行って、一夜分の作業を終了する。PC床版敷設班は、取替え予定区間の床版を撤去し終えるまで、この作業を毎日繰り返す。 Specifically, the PC deck laying crew will cut and remove the existing deck above the main girders, then lay the new precast deck parallel to the axis of the bridge, and cover the joints between adjacent precast decks with a temporary covering plate. After this, temporary paving will be applied to the top surface of the temporary covering plate, completing the work for one night. The PC deck laying crew will repeat this work every day until they have removed the deck from the section scheduled for replacement.

一方、間詰めコンクリート班は数日遅れて作業を開始し、橋軸方向に並列に敷設された新設のプレキャスト床版から仮舗装及び仮覆工床版を撤去するとともに、隣り合う新設のプレキャスト床版の目地に間詰めコンクリートを打設する。そして、間詰めコンクリートの養生が終了したのちに仮舗装を行って、一夜分の作業を終了する。間詰めコンクリート班は、取替え予定区間に敷設された隣り合う新設のプレキャスト床版床版の目地すべてに間詰めコンクリートを打設し終えるまで、この作業を毎日繰り返す。 Meanwhile, the gap-filling concrete team begins work a few days later, removing the temporary pavement and temporary covering slabs from the newly constructed precast slabs that had been laid in parallel along the axis of the bridge, and pouring gap-filling concrete into the joints between the adjacent newly constructed precast slabs. Then, after the gap-filling concrete has been cured, temporary pavement is laid, completing the overnight work. The gap-filling concrete team repeats this work every day until they have poured gap-filling concrete into all of the joints between the adjacent newly constructed precast slabs that were laid in the section scheduled for replacement.

特開2012-82622号公報JP 2012-82622 A

上記のとおり、特許文献1では、既設床版を新設のプレキャスト床版に取替えるための一連の作業のうち、新設のプレキャスト床版を敷設するまでの作業を、一夜分とすることを前提としている。しかし、特許文献1では明らかにされていないが、一般に、既設床版の撤去後に露出する主桁の上面に、ケレン作業やスタッドジベルの設置作業等の様々な処理が必要となる。 As mentioned above, in Patent Document 1, it is assumed that the work up to laying the new precast deck, part of the series of work required to replace the existing deck with a new precast deck, will be carried out overnight. However, although this is not made clear in Patent Document 1, various processes such as scraping and installation of stud dowels are generally required on the top surface of the main girder that is exposed after the existing deck is removed.

これらの煩雑な作業を考慮すると、工事中に何らかの不慮の事態が生じた場合には、新設のプレキャスト床版を敷設するまでの作業を一夜では終了できない恐れが生じる。また、一夜で終了できたとしても、既設床版を新設のプレキャスト床版に取替えるための一連の作業工程のうち、交通解放を実施できるタイミングは、この新設のプレキャスト床版の敷設後であって間詰めコンクリートを打設する直前の期間に限定される。 Considering these complicated tasks, if any unforeseen incident occurs during construction, there is a risk that the work up to laying the new precast deck may not be completed overnight. Even if it were possible to complete the work overnight, the timing for reopening the road to traffic during the series of work processes for replacing the existing deck with a new precast deck would be limited to the period after the new precast deck is laid and immediately before the filling concrete is poured.

このため、現場条件や施工状況等に応じて、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整することは困難である。また、前述したように、新設のプレキャスト床版を敷設するまでの作業を一夜分とすることを前提としているため、新設床版を敷設したのち、目地に間詰コンクリートを打設し本舗装するまでの一連の作業を、一夜で実施するための方法も明示されていない。 For this reason, it is difficult to adjust the progress of work within a single traffic control period depending on the site conditions and construction status. In addition, as mentioned above, it is assumed that the work up to laying the new precast deck will be done overnight, and there is no clear method for completing the series of work from laying the new deck to pouring filler concrete into the joints and laying the actual paving in one night.

本発明は、かかる課題に鑑みなされたものであって、その主な目的は、効率よく既設床版をプレキャストコンクリート造の新設床版に取換えることの可能な、橋梁の床版取替え工法を提供することである。 The present invention was developed in consideration of these problems, and its main objective is to provide a bridge deck replacement method that can efficiently replace an existing deck with a new deck made of precast concrete.

かかる目的を達成するため、本発明の橋梁の床版取替え工法は、工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、鋼製の主桁上に設置された既設床版をプレキャストコンクリート造の新設床版に取替える橋梁の床版取替え工法であって、橋梁の既設床版を橋軸方向に分割して形成した複数の既設床版片のうち、少なくとも一部を撤去して前記主桁を露出させる第1の工程と、前記第1の工程で前記既設床版片を撤去することにより露出させた前記新設床版を据え付ける前の前記主桁上面に、スタッドジベルを設置する第2の工程と、前記第2の工程で前記スタッドジベルを設置した前記主桁上に、複数の前記新設床版を据え付け、前記新設床版を前記主桁に接合させたのち、隣り合う新設床版を接合する第3の工程と、を備え、前記第1の工程から前記第3の工程は、前記工事交通規制時間帯に実施されるとともに、1回の前記工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含み、前記交通解放時間帯が到来する直前に前記第1の工程もしくは前記第2の工程が実施される場合、作業終了時において露出状態にある前記主桁上に、撤去した前記既設床版片に替えて仮覆工床版を設置することを特徴とする。 In order to achieve this object, the bridge deck replacement method of the present invention is a bridge deck replacement method in which an existing deck installed on a steel main girder is replaced with a new deck made of precast concrete while alternating between construction traffic control time periods and traffic open time periods, and includes a first step of removing at least a portion of a plurality of existing deck pieces formed by dividing the existing deck of the bridge in the bridge axis direction to expose the main girder, a second step of installing stud dowels on the upper surface of the main girder before installing the new deck exposed by removing the existing deck pieces in the first step, and a second step of removing the stud dowels on the upper surface of the main girder before installing the new deck exposed by removing the existing deck pieces in the second step. and a third step of installing multiple new deck slabs on the main girders on which stud dowels are installed, joining the new deck slabs to the main girders, and then joining adjacent new deck slabs, wherein the first step to the third step are carried out during the traffic control time period for construction work, and include cases where two or more steps are carried out consecutively within one traffic control time period for construction work, and when the first step or the second step is carried out immediately before the traffic release time period arrives, a temporary covering deck slab is installed on the main girders, which are exposed at the time the work is completed, in place of the existing deck slab pieces that were removed.

本発明の橋梁の床版取替え工法は、前記第1の工程から前記第3の工程を、前記工事交通規制時間帯が到来するごとに橋軸方向に繰り返すことを特徴とする。 The bridge deck replacement method of the present invention is characterized in that the first to third steps are repeated in the bridge axis direction each time the construction traffic control period arrives.

本発明の橋梁の床版取替え工法によれば、既設床版を新設床版に取替えるために必要な作業工程を、工事の中断が可能な第1の工程から第3の工程に分割する。そのうえで、これらの工程を工事交通規制時間帯に実施するにあたり、1回の工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含むようにして、工事交通規制時間帯と交通解放時間帯を繰り返す。これにより、現場条件や施工状況(例えば、ケレン作業やスタッドジベルの設置作業等の進捗状況)に応じて工事を中断する段階を適宜選択できるため、交通解放時間帯の到来に備えつつ、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整することができ、効率よく新設床版の取り換え作業を実施することが可能となる。 According to the bridge deck replacement method of the present invention, the work process required to replace the existing deck with a new deck is divided into a first process, a second process, and a third process during which construction can be suspended. Then, when these processes are carried out during the traffic control period for construction work, the traffic control period for construction work and the traffic open period are repeated, including cases where two or more processes are carried out consecutively within one traffic control period for construction work. This allows the stage at which construction work is suspended to be appropriately selected according to the site conditions and construction status (for example, the progress of scraping work, stud dowel installation work, etc.), so that the progress of the work process carried out during one traffic control period for construction work can be adjusted while preparing for the arrival of the traffic open period, making it possible to efficiently carry out the replacement work for the new deck.

したがって、工事交通規制時間帯を夜間に設定すれば、昼間の交通解放を実現することができ、既設床版取替え工法を実施しようとする橋梁が都市部等の重交通路上や長大トンネルに挟まれた山間部等にある場合にも、周辺地域の交通環境への影響を最小限に抑えつつ施工を実施することが可能となる。 Therefore, by setting the traffic control hours for construction work to be at night, it is possible to open up traffic during the day. Even if the bridge on which the existing deck replacement method is to be implemented is located on a heavy traffic road in an urban area, or in a mountainous area sandwiched between long tunnels, construction can be carried out while minimizing the impact on the traffic environment in the surrounding area.

また、本発明の橋梁の床版取替え工法は、前記既設床版片の橋軸方向からみた断面が、
前記既設床版の横断面を半分に分割した半断面に形成されることを特徴とする。
In addition, the bridge deck replacement method of the present invention is such that the cross section of the existing deck piece as viewed from the bridge axis direction is:
It is characterized in that it is formed into a half cross section by dividing the cross section of the existing deck in half.

本発明の橋梁の床版取替え工法によれば、既設床版の横断面を半分に分割し、いずれか
一方の半断面分の既設床版を橋軸方向に分割して複数の既設床版片を形成し、これを撤去
して新設床版に取替える、いわゆる半断面床版取替え工法に採用することが可能となる。
これにより、例えば、上り車線用の橋梁と下り車線用の橋梁とを備える大規模な道路橋に
おいて、いずれか一方の橋梁を交通解放したまま、他方の橋梁の車線数を減少させる規制
を夜間に行えば、昼間の全面交通解放を実現しながら、既設床版の取替え工事を実施する
ことが可能となる。
According to the bridge deck replacement method of the present invention, the cross section of the existing deck is divided in half, and one of the half-sections of the existing deck is divided in the bridge axis direction to form multiple existing deck pieces, which are then removed and replaced with new deck pieces, making it possible to adopt the so-called half-section deck replacement method.
As a result, for example, in the case of a large road bridge that has a bridge for inbound and a bridge for outbound lanes, if one of the bridges is left open to traffic while the number of lanes on the other bridge is reduced at night, it will be possible to carry out replacement work on the existing deck while keeping the bridge fully open to traffic during the day.

したがって、従来工法のような、いずれか一方の橋梁を全面通行止めにして工事を行い、他方の橋梁を対面通行規制とするといった道路規制を行う必要が無い。このため、通行車両に対する安全性の確保が可能になるとともに、道路構造等の事情により対面通行規制を実施できない、または、実施が可能であっても周辺地域の交通状況によっては長期間の対面通行規制が困難である等、様々な課題を有する道路環境にあっても、既設床版の取替え工事を確実に実施することが可能となる。 Therefore, unlike conventional construction methods, there is no need to impose road restrictions such as completely closing one bridge to traffic while carrying out construction work and restricting two-way traffic on the other bridge. This not only ensures safety for passing vehicles, but also makes it possible to reliably carry out replacement work for existing decks even in road environments with various challenges, such as when two-way traffic restrictions cannot be implemented due to circumstances such as the road structure, or when long-term two-way traffic restrictions are difficult even if they are possible due to traffic conditions in the surrounding area.

また、本発明の橋梁の床版取替え工法は、第3の工程で、隣り合う新設床版を、該新設
床版の一部として機能する本設プレートで接合することを特徴とする。
In addition, in the bridge deck replacement method of the present invention, the adjacent new decks are replaced with the new decks in the third step.
It is characterized by being joined with a permanent plate that functions as part of the deck .

本発明の橋梁の床版取替え工法によれば、新設床版の一部として機能する本設プレート
で隣り合う新設床版を接合するから、この本設プレートを、隣り合う新設床版により形成
される目地部の上面に配置することにより、目地部に間詰コンクリートを充填する作業に
先立って、本舗装を施す作業を優先して実施することができる。これにより、本舗装を施したのちに交通解放を行いつつ、目地部に新設床版の下方側から間詰めコンクリートの充
填することができるため、工事交通規制時間帯に実施する作業を減らすことができ、作業
効率を大幅に向上することが可能となる。
According to the bridge deck replacement method of the present invention, adjacent new decks are joined with a permanent plate that functions as a part of the new deck , and by placing this permanent plate on the upper surface of the joints formed by the adjacent new decks, the work of laying the permanent pavement can be carried out prior to the work of filling the joints with filler concrete. This allows the joints to be filled with filler concrete from the lower side of the new deck while traffic is opened after the permanent pavement is laid, reducing the amount of work carried out during traffic control hours and making it possible to significantly improve work efficiency.

本発明の橋梁の床版取替え工法は、前記主桁上に前記仮覆工床版を設置したのち、該仮覆工床版に隣接する目地の上下面をそれぞれ開口塞ぎ板で覆い、該開口塞ぎ板どうしを締結具を介して締結することを特徴とする。 The bridge deck replacement method of the present invention is characterized in that after the temporary lining deck is installed on the main girder, the upper and lower surfaces of the joints adjacent to the temporary lining deck are covered with opening cover plates, and the opening cover plates are fastened together using fasteners.

本発明の橋梁の床版取替え工法によれば、主桁上に仮覆工床版を設置した際、この仮覆工床版に隣接して形成される目地部の間詰処理を、開口塞ぎ板を利用して容易に実施できるため、充填材を充填する場合と比較して設置及び撤去に係る作業性を大幅に向上し、工期短縮に貢献することが可能となる。 According to the bridge deck replacement method of the present invention, when a temporary lining deck is installed on the main girder, the gap filling process of the joints formed adjacent to the temporary lining deck can be easily carried out using an opening closing plate, which significantly improves the workability of installation and removal compared to when filling material is used, and contributes to shortening the construction period.

本発明によれば、現場条件や施工状況等に応じて作業を中断する段階を適宜選択できるため、交通解放時間帯の到来に備えて、車線規制時間帯を有効に活用しつつ、効率よく新設床版の取り換え作業を実施することが可能となる。 According to the present invention, the stage at which work is suspended can be appropriately selected depending on the site conditions, construction status, etc., so that replacement work for the new deck can be efficiently carried out while making effective use of lane closure periods in preparation for the arrival of traffic release periods.

本発明の実施の形態における半断面床版取替え工法を説明する図である。FIG. 2 is a diagram illustrating a half-section deck replacement method according to an embodiment of the present invention. 本発明の実施の形態における半断面床版取替え工法の流れを示す図である。FIG. 2 is a diagram showing the flow of a half-section deck replacement method in an embodiment of the present invention. 本発明の実施の形態における半断面床版取替え工法の概略を示す図である。FIG. 2 is a diagram showing an outline of a half-section deck replacement method according to an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の流れを示す図である。FIG. 2 is a diagram showing the flow of a bridge deck replacement method in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の概略を示す図である。1 is a diagram showing an outline of a bridge deck replacement method according to an embodiment of the present invention. FIG. 本発明の実施の形態における仮覆工床版を示す図である。FIG. 2 is a diagram showing a temporary covering deck in an embodiment of the present invention. 本発明の実施の形態におけるプレキャストコンクリート造の新設床版を示す図である。FIG. 2 is a diagram showing a newly constructed floor slab made of precast concrete in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の第1の工程を示す図である。FIG. 2 is a diagram showing a first step of a bridge deck replacement method in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の仮間詰めの様子を示す図である。FIG. 2 is a diagram showing the state of temporary filling in the deck replacement method of a bridge in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の第2の工程を示す図である。FIG. 11 is a diagram showing a second step of the bridge deck replacement method in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の第3の工程を示す図である。A figure showing a third step of the bridge deck replacement method in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の第1~第3の工程を繰り返した際の本舗装の手順を示す図である。FIG. 1 is a diagram showing the procedure for a permanent pavement when the first to third steps of the bridge deck replacement method in an embodiment of the present invention are repeated. 本発明の実施の形態における走行車線の新設床版と追い越し車線の新設床版との接合を示す図である。1 is a diagram showing the joint between a new deck slab of a travel lane and a new deck slab of an overtaking lane in an embodiment of the present invention. FIG. 本発明の実施の形態における走行車線と追い越し車線の施工手順の事例を示す図である。FIG. 1 is a diagram showing an example of a construction procedure for a driving lane and an overtaking lane in an embodiment of the present invention. 本発明の実施の形態における橋梁の床版取替え工法の他の事例を示す図である。FIG. 11 is a diagram showing another example of a bridge deck replacement method according to an embodiment of the present invention.

本発明の橋梁の床版取替え工法は、車線規制時間帯および通行止め規制時間帯の両者を含む工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、既設床版を新設床版に取替える方法であって、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整することの可能な方法である。 The bridge deck replacement method of the present invention is a method for replacing an existing deck with a new deck by alternating between construction traffic control periods, which include both lane control periods and road closure control periods, and traffic-free periods, and is a method that makes it possible to adjust the progress of work processes carried out within one construction traffic control period.

このような橋梁の床版取替え工法は、施工車線の通行止めを行う全断面施工に採用することも可能な工法であるが、本実施の形態では、橋梁の床版取替え工法を半断面床版取替え工法に採用する場合を事例に挙げ、詳細を説明する。 This type of bridge deck replacement method can also be used for full-section construction where the construction lane is closed to traffic, but in this embodiment, we will explain the details by taking as an example the case where the bridge deck replacement method is used for half-section deck replacement.

≪≪半断面床版取替え工法≫≫
半断面床版取替え工法は、図1(a)で示すように、例えば、上り2車線用の橋梁B1と下り2車線用の橋梁B2を備える道路橋Bにおいて、橋梁B1を車線規制し、走行車線側と追い越し車線側の、いずれか一方の半断面分の既設床版1を新設床版に取替え、これと前後して、他方側の半断面分の既設床版1も同様に新設床版に取替える方法である。
<<Half-section deck replacement method>>
The half-section deck replacement method, as shown in Figure 1(a), is a method in which, for example, in a road bridge B equipped with a bridge B1 for two lanes in the upward direction and a bridge B2 for two lanes in the downward direction, bridge B1 is restricted to traffic lanes and the existing deck slab 1 of one of the half-sections, either on the driving lane side or the passing lane side, is replaced with a new deck slab, and around the same time, the existing deck slab 1 of the other half-section is also replaced with a new deck.

以下に、半断面床版取替え工法の流れを、図2のフロー図に沿って図3を参照しつつ説明すると、まず、図3(a)で示すように、上り2車線用の橋梁B1について、施工対象領域を橋軸方向に区分けし、複数の区画を設定する(第1ステップ)。 The flow of the half-section deck replacement method will be explained below with reference to the flow diagram in Figure 2 and Figure 3. First, as shown in Figure 3(a), for bridge B1 with two up-bound lanes, the construction area is divided in the bridge axis direction and multiple sections are set (first step).

次に、図3(b)で示すように、各区画を橋軸直交方向に分割し、走行車線側を作業区画D1、D2、D3・・に設定するとともに追い越し車線側を作業区画O1、O2、O3・・に設定する(第2ステップ)。 Next, as shown in Figure 3(b), each section is divided in a direction perpendicular to the bridge axis, and the driving lane side is set as work sections D1, D2, D3, etc., and the passing lane side is set as work sections O1, O2, O3, etc. (second step).

作業区画が設定されたところで、1区画目の走行車線側の作業区画D1に対して床版取替え工法を実施する(第3-1ステップ)。次に、1区画目の追い越し車線側の作業区画O1に対して床版取替え工法を実施する(第3-1ステップ)。 Once the work zones have been set, the deck replacement method is carried out on the work zone D1 on the driving lane side of the first zone (step 3-1). Next, the deck replacement method is carried out on the work zone O1 on the passing lane side of the first zone (step 3-1).

以下、作業区画D1に着目し、床版取替え工法を説明する。本実施の形態では、図1(b)で示すように作業区画D1内の既設床版1を、上り2車線の上流側(図1の橋軸方向右側)から下流側(図1の橋軸方向左側)に向けて順次新設床版3に取替えていく。 The following describes the deck replacement method, focusing on the work area D1. In this embodiment, as shown in Figure 1(b), the existing deck 1 in the work area D1 is successively replaced with a new deck 3 from the upstream side of the two upbound lanes (the right side in the bridge axis direction in Figure 1) to the downstream side (the left side in the bridge axis direction in Figure 1).

床版取替え工法の流れを、図4のフロー図に沿って図1(b)および図5の概念図を参照しつつ説明すると、まず、図1(b)で示すように、走行車線側に設定した作業区画D1に複数の既設床版片11を形成しておく(Step1)。なお、本実施の形態では、6つの既設床版片11を形成しており、これらの形状は撤去したのち車両搬送が可能な大きさに形成されている。 The flow of the deck replacement method will be explained with reference to the flow diagram of Figure 4 and the conceptual diagrams of Figures 1(b) and 5. First, as shown in Figure 1(b), multiple existing deck pieces 11 are formed in a work area D1 set up on the driving lane side (Step 1). In this embodiment, six existing deck pieces 11 are formed, and these are sized to be transportable by vehicle after removal.

次に、図5(a)で示すように、6枚の既設床版片11のうちの2枚を既設床版1から切り離して撤去する(Step2)。すると、既設床版片11の撤去跡に、I型鋼よりなる主桁2の一部が露出するから、この露出した主桁2の上フランジ上面に対して下処理を行うとともに(Step3)、図5(b)で示すように、スタッドジベル21を設置する(Step4)。 Next, as shown in FIG. 5(a), two of the six existing deck pieces 11 are cut off and removed from the existing deck 1 (Step 2). Then, a part of the main girder 2 made of I-beam is exposed where the existing deck pieces 11 were removed, so preparatory work is carried out on the upper surface of the upper flange of this exposed main girder 2 (Step 3), and stud dowels 21 are installed as shown in FIG. 5(b) (Step 4).

こののち、図5(c)で示すように、主桁2の上フランジにプレキャストコンクリート造の新設床版3を据え付け(Step5)、無収縮モルタル4の打設によりスタッドジベル21を利用して新設床版3を主桁2に接合する(Step6)。そして、横目地部J1(橋軸直交方向に延在する目地部)に跨って本設プレート52を設置し、新設床版3の上面縁部どうしを接合する(Step7)。 After this, as shown in Figure 5 (c), a new precast concrete deck 3 is installed on the upper flange of the main girder 2 (Step 5), and the new deck 3 is joined to the main girder 2 using stud dowels 21 by pouring non-shrink mortar 4 (Step 6). Then, a permanent plate 52 is installed across the horizontal joint J1 (a joint extending perpendicular to the bridge axis), and the upper edges of the new deck 3 are joined together (Step 7).

そのうえで、新設床版3の上面に本舗装6を施して車両が通行可能な状態とする作業と(Step8)、本設プレート52の下面側に位置する横目地部J1に間詰コンクリート51を打設する作業とを(Step9)、同時にもしくは前後して実施する。なお、本舗装6は、半断面床版取替え工法において本舗装と称されるグレードの舗装を指す。 After that, the work of laying the permanent pavement 6 on the top surface of the new deck 3 to make it passable for vehicles (Step 8) and the work of pouring the filler concrete 51 into the horizontal joint J1 located on the underside of the permanent plate 52 (Step 9) are carried out simultaneously or before or after this. Note that the permanent pavement 6 refers to the grade of pavement called the permanent pavement in the half-section deck replacement method.

上記のStep2~Step9の工程を、作業区画D1内の既設床版片11がなくなるまで繰り返すことにより、作業区画D1内、つまり上り2車線用の橋梁B1の1区画のうちの走行車線側に相当する半断面分の床版取替作業が終了する。本実施の形態では、Step2の工程で6枚の既設床版片11のうちの2枚を撤去しているため、Step2~Step9の工程を3回繰り返すが、Step2の工程で撤去する既設床版片11の数量は何れでもよい。 The above steps from Step 2 to Step 9 are repeated until all existing deck pieces 11 are removed from the work section D1, completing the deck replacement work for the half cross section that corresponds to the travel lane side of one section of the bridge B1 for two up-bound lanes in the work section D1. In this embodiment, two of the six existing deck pieces 11 are removed in Step 2, so Steps 2 to 9 are repeated three times, but any number of existing deck pieces 11 can be removed in Step 2.

このような、作業区画D1内に複数の既設床版片11を形成するStep1の工程と、Step1の終了後に作業区画D1内の複数の既設床版片11に対してStep2~9の作業を繰り返す工程とを、1サイクル分とする。したがって、1サイクル分に要する施工期間は、作業区画D1で設定する橋軸方向の距離範囲により適宜調整することができる。 The process of Step 1, in which multiple existing deck pieces 11 are formed in the work area D1, and the process of repeating the work of Steps 2 to 9 on the multiple existing deck pieces 11 in the work area D1 after Step 1 is completed, constitute one cycle. Therefore, the construction period required for one cycle can be appropriately adjusted depending on the distance range in the bridge axis direction set in the work area D1.

上記の手順による既設床版の取替え工法は、一定期間(数週間から数か月)にわたって昼夜を問わず、車線規制を行うことができる場合を示したものである。しかし、この施工期間に、昼間の交通解放時間帯を設定しようとすると、夜間に車線規制時間帯を設定して施工を実施し、交通解放時間帯が到来するまでに、施工を中断するだけでなく、中断するごとに作業区画D1を車両が通行可能な状態とする必要が生じる。 The replacement method for the existing deck using the above procedure shows a case where lane restrictions can be implemented day and night for a certain period of time (several weeks to several months). However, if daytime traffic release periods are to be set during this construction period, construction would have to be carried out during lane restriction periods set at night, and not only would construction have to be suspended before the traffic release periods arrive, but each time construction is suspended, work section D1 would have to be made passable for vehicles.

このため、Step1の終了後に作業区画D1内で繰り返し実施される上記Step2~Step9の工程を、図4のフローで示すように、工事の中断が可能な第1~第3の工程に分割する。第1の工程は、既設床版片11の撤去及び主桁2上面を下処理する工程(Step2、3)とし、Step1の既設床版片11を作成する工程は、第1の工程を実施する前の先行作業とする。 For this reason, the above-mentioned Steps 2 to 9, which are repeatedly performed in the work area D1 after Step 1 is completed, are divided into the first to third steps during which construction can be interrupted, as shown in the flow in Figure 4. The first step is the process of removing the existing deck piece 11 and preparing the top surface of the main girder 2 (Steps 2 and 3), and the process of creating the existing deck piece 11 in Step 1 is a preliminary operation before carrying out the first step.

また、第2の工程は、主桁2上面にスタッドジベル21を設置する工程(Step4)とする。また、第3の工程は、新設床版3の据え付けから隣り合う新設床版3の接合、及び本舗装6を施す工程(Step5~9)とする。 The second step is a step (Step 4) of installing the stud dowels 21 on the upper surface of the main girder 2. The third step is a step (Steps 5 to 9) of installing the new deck 3, joining the adjacent new decks 3, and laying the main pavement 6.

このとき、1回の工事交通規制時間帯内で、第1の工程から第3の工程のうち2つ以上の工程を連続して実施する場合を含むようにして、工事交通規制時間帯と交通解放時間帯を繰り返すとよい。 In this case, it is advisable to alternate between the construction traffic control period and the traffic release period, including cases where two or more of the first to third steps are carried out consecutively within one construction traffic control period.

その組み合わせはいずれでもよいが、例えば、先行の車線規制時間帯内で、第1の工程を実施したのち、後行の車線規制時間帯内で、第2の工程と第3の工程を連続して実施する。もしくは、先行の車線規制時間帯内で、第1の工程と第2の工程を連続して実施したのち、後行の車線規制時間帯内で、第3工程を実施する。これらの場合には、交通解放時間帯を、第1の工程終了後もしくは第2の工程終了後と、第3の工程終了後の2回確保することができる。 Any combination is acceptable, but for example, the first step may be carried out during the preceding lane restriction time period, and then the second and third steps may be carried out consecutively during the following lane restriction time period. Or, the first and second steps may be carried out consecutively during the preceding lane restriction time period, and then the third step may be carried out during the following lane restriction time period. In these cases, two traffic-free periods can be secured, one after the end of the first or second step, and the other after the end of the third step.

または、先行の車線規制時間帯内で、第1の工程から第3の工程を連続して実施し、図5(a)~図5(c)で示すように、作業区画D1内の一部の6枚の既設床版片11のうちの2枚を撤去して新設床版3を敷設し本舗装6を施す。こののち、後行の車線規制時間帯内で第1の工程から第3の工程を連続して実施し、作業区画D1内の残りの4枚の既設設床版片11のうちの2枚を撤去して新設床版3を敷設し本舗装6を施してもよい。この場合には、第3の工程が終了するごとに交通解放時間帯を確保することができる。 Alternatively, steps 1 to 3 may be carried out consecutively during the preceding lane restriction time period, and two of the six existing deck pieces 11 in the work area D1 may be removed, a new deck 3 may be laid, and a permanent pavement 6 may be applied, as shown in Figures 5(a) to 5(c). After this, steps 1 to 3 may be carried out consecutively during the succeeding lane restriction time period, and two of the remaining four existing deck pieces 11 in the work area D1 may be removed, a new deck 3 may be laid, and a permanent pavement 6 may be applied. In this case, a traffic-free time period may be secured each time the third step is completed.

上記のような車線規制時間帯内に実施する工程の組合わせは、毎回同じでなくてもよい。例えば、先行の車線規制時間帯内で第1の工程を実施し、後行の車線規制時間帯内で第2の工程と第3の工程を連続して実施したのち、その次の車線規制時間帯内では、第1の工程から第3の工程を連続して実施してもよい。 The combination of steps performed during the lane restriction time periods described above does not have to be the same every time. For example, the first step may be performed during the preceding lane restriction time period, the second and third steps may be performed consecutively during the following lane restriction time period, and then the first through third steps may be performed consecutively during the next lane restriction time period.

ところで、1回の車線規制時間帯内に実施する工程が、第1の工程までもしくは第2の工程までであった場合には、既設床版片11を撤去したのちの主桁2は、露出された状態となっている。したがってこの場合には、交通解放期間が到来する直前の主桁2上で、仮設覆工板7を設置する作業と、仮間詰め9及び仮舗装8を施す作業とを行う。これにより、交通解放時間帯が到来すると、工事を中断した状態であっても交通解放を実施することができる。 However, if the processes carried out within one lane restriction period are up to the first process or up to the second process, the main girder 2 will be exposed after the existing deck pieces 11 are removed. In this case, the work of installing the temporary covering plate 7 and the work of applying the temporary gap filling 9 and temporary paving 8 will be carried out on the main girder 2 just before the traffic release period arrives. As a result, when the traffic release period arrives, traffic can be released even if construction work has been suspended.

その一方で、1回の車線規制時間帯内に第3の工程まで実施した場合には、既設床版片11を撤去したのちの主桁2上は、新設床版3が間詰コンクリート51による間詰め処理、および本舗装6を施されて設置されている。したがってこの場合には、仮設床版7を設けなくても、交通解放時間帯が到来するとそのまま、交通解放を実施することができる。 On the other hand, if the third step is completed within one lane restriction period, the existing deck pieces 11 are removed and the new deck 3 is installed on the main girders 2 after filling with filler concrete 51 and applying the permanent pavement 6. Therefore, in this case, traffic can be opened as soon as the traffic release period arrives, even without setting up the temporary deck 7.

≪仮覆工床版≫
車両の通行を可能にする仮覆工床版7は、図6(a)で示すように、橋梁B1の横断面を走行車線側と追い越し車線側の半分に分割したうちの、走行車線側の半断面を一時的に賄うことの可能な部材であり、床版本体71と地覆72と高欄73とを一体に形成している。こうすると、仮覆工床版7の設置作業に係る時間を大幅に短縮できるが、床版本体71と地覆72と高欄73は別体で製造し、現場で組み立て可能な構造としてもよい。
<Temporary covering deck>
As shown in Fig. 6(a), the temporary covering deck 7 that allows vehicles to pass is a member that can temporarily cover the half cross section on the driving lane side of the cross section of the bridge B1 divided into the driving lane side and the passing lane side, and is integrally formed with the deck body 71, the ground cover 72, and the balustrade 73. In this way, the time required for the installation work of the temporary covering deck 7 can be significantly reduced, but the deck body 71, the ground cover 72, and the balustrade 73 may also be manufactured separately and configured to be assembled on-site.

また、仮覆工床版7の床版本体71は、図6(b)で示すように、外縁部近傍を除いた上面にあらかじめ仮舗装8が施され、橋軸方向長さL2は、図1(b)で示した既設床版片11の橋軸方向長さL1と略同程度に形成されている。しかし、これに限定されるものではなく、既設床版片11の橋軸方向長さL1より小さい、例えば1/2および1/4のものを2種類準備してもよい。 As shown in Fig. 6(b), the deck body 71 of the temporary covering deck 7 has a temporary pavement 8 applied in advance on its upper surface except for the area near the outer edge, and the bridge axis direction length L2 is formed to be approximately the same as the bridge axis direction length L1 of the existing deck piece 11 shown in Fig. 1(b). However, this is not limited to this, and two types of deck pieces smaller than the bridge axis direction length L1 of the existing deck piece 11, for example 1/2 and 1/4, may be prepared.

橋軸方向長さL2を1/2および1/4の2種類準備すると、既設床版片11の橋軸方向長さL1を施工途中で変更する必要が生じた場合であっても、既設床版片11を撤去したのちに露出する主桁2への仮覆工床版7の設置作業を容易に行うことができる。つまり、撤去した既設床版片11があらかじめ規定した橋軸方向長さL1である場合には、仮覆工床版7のうち、橋軸方向長さL2が1/2のものを必要数量だけ並列配置する。 By preparing two types of bridge axis direction length L2, 1/2 and 1/4, even if it becomes necessary to change the bridge axis direction length L1 of the existing deck slab piece 11 during construction, it is easy to install the temporary covering deck 7 on the main girder 2 that is exposed after removing the existing deck slab piece 11. In other words, if the removed existing deck slab piece 11 has the predefined bridge axis direction length L1, the temporary covering deck slabs 7 with the bridge axis direction length L2 of 1/2 are arranged in parallel in the required number.

一方、作業区画D1を切断して既設床版片11を作成する際、切断予定位置と、主桁2どうしの長手方向連結部であって上フランジ上面に添接板が設置されている位置とが重なる場合には、添接板を避けるべく切断位置をずらさなければならない。すると、既設床版片11の橋軸方向長さL1はあらかじめ規定した長さにならず、既設床版片11を撤去したのちに露出した主桁2の橋軸方向長さも変化する。しかし、橋軸方向長さL2が1/2および1/4の仮覆工床版7を適宜組み合わせて用いることにより、これらの不具合に対応することが可能となる。 On the other hand, when cutting the work section D1 to create the existing deck piece 11, if the planned cutting position overlaps with the longitudinal connection between the main girders 2 where a splice plate is installed on the top surface of the upper flange, the cutting position must be shifted to avoid the splice plate. In that case, the bridge axis direction length L1 of the existing deck piece 11 will not be the predetermined length, and the bridge axis direction length of the exposed main girder 2 after removing the existing deck piece 11 will also change. However, by appropriately combining and using temporary covering decks 7 with bridge axis direction lengths L2 of 1/2 and 1/4, it is possible to address these problems.

さらに、仮覆工床版7は、その部材厚に応じて主桁2の上フランジ上面に直接設置してもよいし、図6(a)で示すように、鋼材等を加工した高さ調整材74を介して設置してもよい。高さ調整材74を介して設置する場合には、高さ調整材74を床版本体71の下面にあらかじめ設置し、高さ調整材74と主桁2の上フランジとをクランプ等で挟持すると容易に、仮覆工床版7を主桁2に着脱自在に固定することができる。 Furthermore, the temporary covering deck 7 may be installed directly on the upper surface of the upper flange of the main girder 2 depending on the material thickness, or it may be installed via a height adjustment material 74 made of processed steel material or the like, as shown in Figure 6 (a). When installing via a height adjustment material 74, the height adjustment material 74 is installed in advance on the underside of the deck body 71, and the temporary covering deck 7 can be easily and detachably fixed to the main girder 2 by clamping the height adjustment material 74 and the upper flange of the main girder 2 with a clamp or the like.

また、直接設置する場合には、床版本体71の下面形状が、平坦なものと、主桁2の上面に設置されている添接板上に載置することが可能なように加工されたものの2種類を準備しておくとよい。 In addition, when installing directly, it is advisable to prepare two types of deck body 71 with a flat underside shape and one that is processed so that it can be placed on the splice plate installed on the upper surface of the main girder 2.

≪新設床版≫
一方、プレキャストコンクリート造の新設床版3は、図7(a)(b)で示すように、床版本体31、地覆32、接合鉄筋33、及びスタッドジベル挿通孔34を備えている。地覆32は一体に製造されていてもよいし、別体に製造して高欄(図示せず)と併せて現場にて床版本体31に設置する構造としてもよい。
<Newly constructed floor slab>
7(a) and 7(b), the newly constructed deck 3 made of precast concrete includes a deck body 31, a pedestal 32, joint reinforcing bars 33, and stud dowel insertion holes 34. The pedestal 32 may be manufactured as an integral part, or may be manufactured separately and installed on the deck body 31 together with a parapet (not shown) on-site.

接合鉄筋33は、床版本体31の橋軸方向に対向する両側面と、追い越し車線側の既設床版1に対向する側面の、3つの側面各々から平行に突出するように設置されている。これらは高さ方向に2列に配置されるとともに、橋軸直交方向に延在する横目地部J1および橋軸方向に延在する縦目地部J2において平面視で千鳥配置をなし、施工完了時にはこの横目地部J1及び縦目地部J2に打設される間詰めコンクリート51に埋設される。 The connecting rebars 33 are installed so that they protrude parallel to each other from the three sides of the deck body 31: both sides facing the bridge axis direction, and the side facing the existing deck 1 on the passing lane side. They are arranged in two rows in the height direction, and are staggered in plan view in the horizontal joints J1 extending perpendicular to the bridge axis and the vertical joints J2 extending in the bridge axis direction. When construction is complete, they are embedded in the filling concrete 51 poured into the horizontal joints J1 and vertical joints J2.

そして、床版本体31に形成されるスタッドジベル挿通孔34は、新設床版3を主桁2の上フランジ上面に載置した際にスタッドジベル21が挿通可能な位置にあり、新設床版3を主桁2に接合させる際、無収縮モルタル4がこのスタッドジベル挿通孔34から充填される。 The stud dowel insertion hole 34 formed in the deck body 31 is located in a position where the stud dowel 21 can be inserted when the new deck 3 is placed on the top surface of the upper flange of the main girder 2, and when the new deck 3 is joined to the main girder 2, the non-shrink mortar 4 is filled through this stud dowel insertion hole 34.

≪≪橋梁の床版取替え工法≫≫
次に、車線規制時間帯と交通解放時間帯とを交互に繰り返しながら、作業区画D1内の既設床版1をプレキャストコンクリート造の新設床版3に取替える床版取替え工法の手順を、以下に説明する。
<< Bridge deck replacement method >>
Next, the procedure for the deck replacement method, in which the existing deck 1 in the work area D1 is replaced with a new deck 3 made of precast concrete while alternating between lane restriction periods and traffic-free periods, will be described below.

なお、本実施の形態では、1度目の車線規制時間帯で第1の工程を実施したのち、交通解放時間帯の終了後に2度目の車線規制時間帯で、第2の工程と第3の工程を連続して実施し、これを繰り返して1サイクルを終了する(作業区画D1を新設床版3に取替える)場合を事例に挙げる。また、使用する仮覆工床版7及び新設床版3は、橋軸方向の長さL2及びL3がともに、既設床版片11と略同一もしくは略小さいものを採用する場合を事例に挙げて説明する。 In this embodiment, the first step is carried out during the first lane restriction period, and then the second and third steps are carried out consecutively during the second lane restriction period after the end of the traffic release period, and this is repeated to complete one cycle (replace the work area D1 with the new deck 3). In addition, the temporary covering deck 7 and the new deck 3 used have lengths L2 and L3 in the bridge axis direction that are approximately the same as or approximately smaller than those of the existing deck piece 11.

<車線規制時間帯の到来ごとに実施する準備作業>
車線規制時間帯が到来するごとに、図1(b)で示すように、橋梁B1の上り2車線を1車線とする車線規制を行うとともに、床版架設装置10を搬入し、あらかじめ施工計画時に床版取替え工法の1サイクル分として設定した作業区画D1の近傍に、この床版架設装置10を据え付ける。
<Preparation work to be carried out each time a lane restriction period begins>
Each time a lane restriction period arrives, as shown in Figure 1 (b), lane restrictions are implemented to reduce the two uphill lanes of bridge B1 to one lane, and the deck erection device 10 is brought in and installed near the work area D1 that was previously set up as one cycle of the deck replacement method during the construction planning.

≪床版架設装置≫
床版架設装置10は、従来より既設床版1の取替え作業に採用されている装置であればいずれを用いてもよいが、車線規制時間帯ごとに搬出入を繰り返すことを考慮し、本実施の形態では、トレーラー等の車両の荷台に積込み可能に製造された門型タイプの床版架設装置10を採用している。
<Deck erection device>
The deck erection device 10 may be any device that has conventionally been used for replacing an existing deck 1, but in consideration of the need to repeatedly load and unload the deck during each lane restriction period, this embodiment employs a gate-type deck erection device 10 that is manufactured so that it can be loaded onto the bed of a vehicle such as a trailer.

床版架設装置10は、図1(b)及び図8(a)で示すように、間隔を設けて配置される一対の門型フレーム101と、門型フレーム101に架け渡される1対のクレーンガーター102と、クレーンガーター102各々に吊り下げられた天井クレーン103とを備える。天井クレーン103は、クレーンガーター102に沿って移動可能な構造を有しており、既設床版1の撤去、仮覆工床版7の据え付けもしくは撤去、及び新設床版3の据え付けに係る作業はすべて、この天井クレーン103を用いて行う。 As shown in Fig. 1(b) and Fig. 8(a), the deck erection device 10 comprises a pair of portal frames 101 arranged with a gap between them, a pair of crane garters 102 spanned across the portal frames 101, and an overhead crane 103 suspended from each of the crane garters 102. The overhead crane 103 has a structure that allows it to move along the crane garters 102, and all work related to removing the existing deck 1, installing or removing the temporary covering deck 7, and installing the new deck 3 is performed using this overhead crane 103.

<第1の工程の前に実施する先行作業>
前述したように、1サイクル分として設定した作業区画D1の既設床版1を、図1(b)で示すように、橋軸直交方向に沿う切断線を7本設けて、6枚の既設床版片11を作成しておく(Step1)。なお、切断する間隔は等間隔が望ましいが、切断線の位置と主桁2の上フランジ上面に設置された添接板の位置が合致する場合には、添接板を避けるように切断位置を適宜変更する。
<Preceding work to be carried out before the first process>
As described above, the existing deck 1 of the work section D1 set as one cycle is cut with seven cutting lines along the direction perpendicular to the bridge axis as shown in Fig. 1 (b) to create six existing deck pieces 11 (Step 1). Note that it is preferable to cut at equal intervals, but if the position of the cutting line coincides with the position of the splice plate installed on the upper surface of the upper flange of the main girder 2, the cutting position is appropriately changed to avoid the splice plate.

<1度目の車線規制時間帯の到来:第1の工程>
図8(a)で示すように、床版架設装置10を作業区画D1の近傍の所定位置に据え付ける。次に、6枚の既設床版片11のうち、上り2車線の上流側に位置する第1枚目(図1(b)の最右端)を既設床版1から切り離すべく、作業区画D1の橋軸方向に沿う境界線に切断線を入れたのち、既設床版片11を床版架設装置10にて揚重撤去する。
<First lane restriction period: First step>
As shown in Fig. 8(a), the deck erection device 10 is installed at a predetermined position near the work area D1. Next, in order to separate the first of the six existing deck pieces 11 (the rightmost one in Fig. 1(b)) located on the upstream side of the two up-bound lanes from the existing deck 1, a cutting line is drawn on the boundary line along the bridge axis direction of the work area D1, and then the existing deck piece 11 is lifted and removed by the deck erection device 10.

この作業を2回連続して行い、図5(a)で示したように、2枚の既設床版片11を撤去する。次に、2枚の既設床版片11を撤去したことにより形成された空間を利用して、主桁2間に必要個所に、図8(b)で示すような作業足場22を設置する(Step2)。 This work is carried out twice in succession to remove the two existing deck pieces 11 as shown in Figure 5 (a). Next, the space created by removing the two existing deck pieces 11 is used to install a work platform 22 as shown in Figure 8 (b) in the required location between the main girders 2 (Step 2).

こののち、作業足場22を利用して、主桁2上フランジ上面に下処理を行う。下処理としては、例えば、主桁2の上フランジ上面に付着したコンクリートかすやアンカー鉄筋等の撤去した既設床版片11の残物をはつり取る作業や、のちにスタッドジベル21を設置するための素地調整する等、いわゆるケレン作業等を行う(Step3)。 After this, the work scaffolding 22 is used to perform preparatory work on the upper surface of the upper flange of the main girder 2. Preparatory work includes, for example, removing concrete debris and anchor rebars that remain on the upper surface of the upper flange of the main girder 2 from the existing deck pieces 11 that have been removed, and preparing the base for later installation of the stud dowels 21, which is known as scraping work (Step 3).

これらの作業が終了したのち、図8(b)で示すように、主桁2の上フランジ上面に前述した仮覆工床版7を高さ調整材74を介して設置する。図9(a)で示すように、隣り合う仮覆工床版7、及び既設床版1もしくは既設床版片11と仮覆工床版7との間に形成された横目地部J1に対して仮間詰め9を行う。 After these operations are completed, as shown in FIG. 8(b), the temporary lining deck 7 is installed on the upper surface of the upper flange of the main girder 2 via the height adjustment material 74. As shown in FIG. 9(a), temporary gap filling 9 is performed on the horizontal joints J1 formed between the adjacent temporary lining decks 7, and between the existing deck 1 or existing deck piece 11 and the temporary lining deck 7.

仮間詰め9は、横目地部J1の下面側を塞ぐように鉄板等の開口塞ぎ板91を設置したうえで、スポンジや砂等の充填材92を充填する。また、横目地部J1の開きが大きい場合には、上面にも開口塞ぎ板91を設置するとよい。なお、横目地部J1の上面を塞ぐようにして開口塞ぎ板91を配置した場合、横目地部J1には必ずしも充填材92を充填しなくてもよい。 The temporary gap filling 9 is made by placing an opening closing plate 91 such as a steel plate to close the underside of the horizontal joint J1, and then filling it with a filler 92 such as sponge or sand. If the opening of the horizontal joint J1 is large, it is a good idea to also place an opening closing plate 91 on the top surface. Note that if an opening closing plate 91 is placed to close the top surface of the horizontal joint J1, it is not necessary to fill the horizontal joint J1 with filler 92.

具体的には、図9(b)で示すように、一対の開口塞ぎ板91で横目地部J1の上面側及び下面側を塞ぎ、仮覆工床版7を挟持するようにしてこれら一対の開口塞ぎ板91をボルト等の緊結具93で緊結する。このとき、上面側の開口塞ぎ板91が、横目地部J1の全面を塞いだ状態で仮覆工床版7に固定されていれば、下面側の開口塞ぎ板91は、図9(c)で示すように、横目地部J1の下面側の全面を塞ぐものであってもよいし、図9(d)で示すように、下面側の一部分を塞ぐよう配置されるものであってもよい。 Specifically, as shown in FIG. 9(b), a pair of opening closing plates 91 close the upper and lower sides of the horizontal joint portion J1, and the pair of opening closing plates 91 are fastened with fasteners 93 such as bolts so as to sandwich the temporary lining deck 7. At this time, if the opening closing plate 91 on the upper side is fixed to the temporary lining deck 7 in a state in which it closes the entire surface of the horizontal joint portion J1, the opening closing plate 91 on the lower side may close the entire surface of the lower side of the horizontal joint portion J1, as shown in FIG. 9(c), or may be positioned so as to close a portion of the lower side, as shown in FIG. 9(d).

こうすると、横目地部J1に充填材92を充填する場合と比較して、作業性が大幅に向上し、工期短縮を図ることができる。このような処理は、横目地部J1だけでなく、仮覆工床版7と追い越し車線側の既設床版1との間に形成される縦目地部J2にも、同様に実施する。 This significantly improves workability and shortens the construction period compared to filling the horizontal joints J1 with filler 92. This process is carried out not only for the horizontal joints J1, but also for the vertical joints J2 formed between the temporary covering deck 7 and the existing deck 1 on the passing lane side.

次に、仮覆工床版7の上面全面に仮舗装8を施す。前述したように、仮覆工床版7の上面にはあらかじめ先行仮舗装81が施されているから、仮覆工床版7の先行仮舗装81が施されていない縁部に対して横目地部J1及び縦目地部J2を覆うように、後行仮舗装82を施せばよい。このように、仮覆工床版7の上面にあらかじめ先行仮舗装81を施しておくと、仮舗装8全体の作業時間を大幅に短縮できる。こののち、門型タイプの床版架設装置10を搬出して第1の工程を終了し、上り2車線を車両解放可能な状態とする。 Next, temporary pavement 8 is applied to the entire upper surface of the temporary lining deck 7. As described above, the preliminary temporary pavement 81 has already been applied to the upper surface of the temporary lining deck 7, so the following temporary pavement 82 can be applied to the edges of the temporary lining deck 7 where the preliminary temporary pavement 81 has not been applied, so as to cover the horizontal joint portion J1 and the vertical joint portion J2. In this way, by applying the preliminary temporary pavement 81 to the upper surface of the temporary lining deck 7 in advance, the overall work time for the temporary pavement 8 can be significantly reduced. After this, the gate-type deck erection device 10 is removed, completing the first step and making the two upbound lanes available for vehicles.

<2度目の車線規制時間帯の到来:第2の工程及び第3の工程>
第1の工程の開始時と同様に、床版架設装置10を作業区画D1の近傍の所定位置に据え付ける。次に、主桁2の上フランジ上面に設置した仮覆工床版7を床版架設装置10にて一時撤去し、主桁2の上フランジ上面のケレン状況を確認し、必要に応じて再度ケレン作業を行って素地調整を行う。
<The second lane restriction period: second and third steps>
As in the start of the first process, the deck erection device 10 is installed at a predetermined position near the work area D1. Next, the temporary covering deck 7 installed on the upper surface of the upper flange of the main girder 2 is temporarily removed by the deck erection device 10, and the scraping condition of the upper surface of the upper flange of the main girder 2 is checked, and scraping work is performed again as necessary to adjust the base surface.

こののち、第2の工程を実施する。つまり、図10で示すように、主桁2の上フランジ上面に複数のスタッドジベル21を、所定の間隔を設けて設置するとともに、防錆塗装を行う(Step4)。スタッドジベル21は、橋軸直交方向に並ぶ複数を1組とし、これを橋軸方向に間隔を設けて複数設置する。図10では、スタッドジベル21を橋軸直交方向に3本設置した場合を例示しているが、その数量は、主桁2の幅や支間の位置等に応じて適宜変更される。 After this, the second step is carried out. That is, as shown in Figure 10, multiple stud dowels 21 are installed at a specified interval on the upper surface of the upper flange of the main girder 2, and anti-rust paint is applied (Step 4). The stud dowels 21 are arranged in a group of multiple dowels aligned in the direction perpendicular to the bridge axis, and multiple dowels are installed in the bridge axis direction with intervals between them. Figure 10 shows an example in which three stud dowels 21 are installed in the direction perpendicular to the bridge axis, but the number can be changed as appropriate depending on the width of the main girder 2, the position of the span, etc.

これらの作業が終了したのち、第3の工程を実施する。まず、主桁2の上フランジ上面に、同じく床版架設装置10を用いて新設床版3を据え付ける(Step5)。新設床版3は、図11(a)で示すように、スタッドジベル挿通孔34に主桁2の上フランジ上面に設置したスタッドジベル21が収納されるように配置し、このスタッドジベル挿通孔34に無収縮モルタル4を充填して、主桁2と新設床版3とを強固に接合する(Step6)。なお、新設床版3を据え付ける前に、モルタル止め41を主桁2の上フランジにおける両側部に設置しておく。 After these tasks are completed, the third step is carried out. First, the new deck 3 is installed on the upper surface of the upper flange of the main girder 2 using the deck erection device 10 (Step 5). As shown in FIG. 11(a), the new deck 3 is positioned so that the stud dowel insertion holes 34 house the stud dowels 21 installed on the upper surface of the upper flange of the main girder 2, and the stud dowel insertion holes 34 are filled with non-shrink mortar 4 to firmly join the main girder 2 and the new deck 3 (Step 6). Before installing the new deck 3, mortar stoppers 41 are installed on both sides of the upper flange of the main girder 2.

無収縮モルタル4の充填作業に前後してもしくは同時に、図11(b)で示すように、本設プレート52による隣り合う新設床版3どうしを接合する作業(Step7)を実施する。 Before, after or at the same time as the filling work with non-shrink mortar 4, the work of joining adjacent new deck slabs 3 using permanent plates 52 (Step 7) is carried out as shown in Figure 11 (b).

本設プレート52は、隣り合う新設床版3との間に形成された横目地部J1の上方を跨ぐように設置する。本設プレート52は、横目地部J1を被覆する十分な幅と、床版本体31の橋軸直交方向長さL3に略等しい長さとを有する、間詰めコンクリート51と同様の材料で工場にて製造されたプレキャストコンクリート造の板材を使用している。 The permanent plate 52 is installed so as to straddle the upper part of the horizontal joint J1 formed between the adjacent new deck slabs 3. The permanent plate 52 is made of precast concrete plate material manufactured in a factory from the same material as the filling concrete 51, and has a width sufficient to cover the horizontal joint J1 and a length approximately equal to the length L3 of the deck body 31 in the direction perpendicular to the bridge axis.

本設プレート52の設置方法は、アンカーや接着剤による固定等いずれの手段により実施してもよく、設置状態も、床版本体31の上面に本設プレート52を載置するように設置してもよいが、本実施の形態では、床版本体31の縁部に設けた切欠きに載置させている。このとき切欠きは、本設プレート52の上面と床版本体31の上面が面一となるような深さに形成するとよい。 The permanent plate 52 may be installed by any method, such as by fixing with anchors or adhesives, and may be installed by placing the permanent plate 52 on the top surface of the deck body 31. In this embodiment, however, the permanent plate 52 is placed on a notch provided on the edge of the deck body 31. In this case, the notch should be formed to a depth such that the top surface of the permanent plate 52 and the top surface of the deck body 31 are flush with each other.

次に、図11(c)で示すよう、新設床版3の上面に本舗装6を施す(Step8)。また、本舗装6に係る作業と同時にもしくは前後して、横目地部J1の下方にこれを跨ぐように型枠53を設置する。この型枠53に対して間詰めコンクリート51充填するための充填孔、空気穴もしくは充填確認孔(いずれに図示せず)を形成しておく。 Next, as shown in FIG. 11(c), the permanent pavement 6 is applied to the top surface of the new deck 3 (Step 8). In addition, simultaneously with or before or after the work related to the permanent pavement 6, a formwork 53 is installed below the horizontal joint J1 so as to straddle it. Filling holes, air holes, or filling confirmation holes (none of which are shown) for filling the interfacial concrete 51 are formed in the formwork 53.

そして、図11(d)で示すよう、横目地部J1の下面側から間詰めコンクリート51を充填し、接合鉄筋33を埋設する(Step9)。間詰めコンクリート51は、高強度及び高耐久なコンクリートであればいずれを採用してもよい。 Then, as shown in FIG. 11(d), filler concrete 51 is filled from the underside of the horizontal joint J1, and the joint reinforcing bars 33 are embedded (Step 9). Any high-strength, high-durability concrete may be used as the filler concrete 51.

このように、本設プレート52は間詰めコンクリート51と同様の材料にて製造すると、該新設床版の一部として機能させることの可能な本設部材として取り扱うことができる。このため、本設プレート52で横目地部J1の上方を被覆すると、その直後に本舗装6を施す作業を優先して実施できることから、交通解放を行いつつ新設床版3の下方側から間詰めコンクリート51の充填作業を実施することもできる。こうすると、車線規制時間帯に実施する作業を減らすことができ、作業効率を大幅に向上することが可能となる。 In this way, if the permanent plate 52 is manufactured from the same material as the interfacial concrete 51, it can be handled as a permanent member that can function as part of the new deck slab . Therefore, if the upper side of the horizontal joint J1 is covered with the permanent plate 52, the work of laying the permanent pavement 6 can be carried out immediately thereafter with priority, and therefore the work of filling the interfacial concrete 51 can be carried out from the lower side of the new deck slab 3 while opening the road to traffic. In this way, the work carried out during lane restriction hours can be reduced, making it possible to significantly improve work efficiency.

なお、縦目地部J2及び既設床版1もしくは既設床版片11と新設床版3との間に形成された横目地部J1には、本舗装6を施す前に、第1の工程で示したように、開口塞ぎ板91と充填材92による仮間詰め9を行っておく。こののち、床版架設装置10を搬出して第3の工程を終了し、上り2車線を車両解放可能な状態とする。 Before applying the permanent pavement 6, the vertical joints J2 and the horizontal joints J1 formed between the existing deck 1 or existing deck piece 11 and the new deck 3 are temporarily filled with an opening blocking plate 91 and a filler 92 as shown in the first step. After this, the deck erection device 10 is removed, the third step is completed, and the two upbound lanes are made available for vehicles to use.

上記のとおり、2度目の車線規制時間帯が終了した時点で、第1~第3の工程を経て、作業区画D1のうち、上り2車線の上流側1枚目及び2枚目の既設床版片11を新設床版3に取替える作業が終了する。なお、第3の工程のいずれかの段階で、新設床版3の地覆32に高覧を設置する。 As described above, when the second lane restriction period ends, the work of replacing the first and second existing deck pieces 11 on the upstream side of the two upbound lanes in the work section D1 with the new deck 3 will be completed through the first to third steps. At some stage in the third step, a gusset will be installed on the ground guard 32 of the new deck 3.

ところで、図11(d)で示すように、第3の工程では、2枚の新設床版3の全面に本舗装6を施している。したがって、次に作業区画D1の中間部に位置する3枚目及び4枚目の既設床版片11を新設床版3に取替える際には、以下の処理を追加して行う。 As shown in FIG. 11(d), in the third step, the permanent pavement 6 is laid over the entire surface of the two new decks 3. Therefore, when the third and fourth existing deck pieces 11 located in the middle of the work area D1 are next replaced with the new decks 3, the following additional process is performed.

図12(a)で示すように、すでに本舗装6が施された2枚目の新設床版3について、本舗装6が施されていない3枚目の新設床版3と隣接する縁部近傍の本舗装6を所定の幅だけはがし取る。そのうえで、図12(b)で示すように、2枚目と3枚目の新設床版3の間に形成された横目地部J1を跨いで本設プレート52を設置し、そののち、本舗装6を施し、図12(c)で示すように、間詰めコンクリート51を充填する。 As shown in Figure 12(a), for the second new deck 3 on which the permanent pavement 6 has already been applied, a specified width of the permanent pavement 6 is removed near the edge adjacent to the third new deck 3 on which the permanent pavement 6 has not been applied. Then, as shown in Figure 12(b), a permanent plate 52 is installed across the horizontal joint J1 formed between the second and third new deck slabs 3, after which the permanent pavement 6 is applied, and as shown in Figure 12(c), filling concrete 51 is filled in.

このように、交通解放時間帯の直前に実施される工程が、第1の工程の場合には、終了時に仮覆工床版7が敷設されるとともに目地が仮間詰め9で処理される。また、第3の工程の場合には、終了時に覆工床版3が敷設されるとともに、目地が間詰め51で処理され本舗装6が施される。これにより、車線規制時間帯において、いずれの工程で作業が終了した場合にも、交通解放時間帯には車両が通行可能な状態となっているため、交通解放を繰り返しながら、既設床版11を新設床版3に取替える作業を効率よく実施することが可能となる。 In this way, if the process carried out immediately before the traffic release period is the first process, at the end of the process, the temporary lining deck 7 is laid and the joints are filled with temporary gap filling 9. Also, in the case of the third process, at the end of the process, the lining deck 3 is laid, the joints are filled with gap filling 51, and the permanent pavement 6 is laid. As a result, no matter which process is completed during the lane restriction period, vehicles will be able to pass during the traffic release period, so it is possible to efficiently replace the existing deck 11 with the new deck 3 while repeatedly releasing traffic.

上記の手順で、第1の工程を実施する先行の車線規制時間帯と、第2の工程及び第3の工程を実施する後行の車線規制時間帯を、3回繰り返すことにより、つまり6度の車線規制時間帯を経て、作業区画D1を新設床版3に取替えることができ、これにより1サイクル分の作業が終了する。 By repeating the preceding lane restriction period during which the first step is carried out and the following lane restriction period during which the second and third steps are carried out three times using the above procedure, i.e., after six lane restriction periods, the work section D1 can be replaced with the new deck slab 3, thus completing one cycle of work.

<7度目以降の車線規制時間帯の到来:2サイクル目>
次に、図3(c)で示すように、作業区画D1に並列する1区画目の追い越し車線の作業区画O1に対して、上記の手順にしたがって床版取替え工法を実施する。
<7th and subsequent lane restriction periods: 2nd cycle>
Next, as shown in FIG. 3(c), the deck replacement method is carried out in accordance with the above-described procedure for the first passing lane work section O1 parallel to the work section D1.

つまり、追い越し車線の作業区画O1で、既設床版片11を作成する工程(Step1)を先行作業として済ませた後、第1~第3の工程を3回繰り返す。こうして、図3(d)で示すように、橋梁B1に設定した複数の区画のうちの1区画目内の、作業区画D1及び作業区画B1における既設床版1を新設床版3に取替え、床版取り替え工法を終了する。
That is, after the process (Step 1) of creating the existing deck piece 11 in the passing lane work section O1 is completed as a preceding task, the first to third steps are repeated three times. In this way, as shown in Fig. 3(d), the existing deck 1 in the work section D1 and work section B1 in the first section of the multiple sections set on the bridge B1 is replaced with the new deck 3, and the deck replacement method is completed.

<作業区画O1の床版取替え工法が終了した後に到来する車線規制時間帯>
図2のフロー図に戻って(第4ステップ)、図3(d)で示すように、走行車線側の作業区画D1の新設床版3と追い越し車線側の作業区画O1の新設床版3とを接合する。
<Lane restriction period after the deck replacement work in work area O1 is completed>
Returning to the flow chart of Figure 2 (fourth step), as shown in Figure 3(d), the new deck 3 of the work section D1 on the driving lane side and the new deck 3 of the work section O1 on the passing lane side are joined.

接合作業は、図13(a)で示すように、作業区画D1の新設床版3と追い越し車線側の作業区画O1の新設床版3との間に形成された縦目地部J2に隣接する縁部の本舗装6を所定の幅だけはがし取ったうえで、縦目地部J2の上方を跨ぐように、本設プレート52を新設床版3の縁部に形成された切欠きに設置する。本設プレート52は、縦目地部J2を被覆する十分な幅を有し、その長さは、作業区画D1及び作業区画O1の橋軸方向の長さに略等しく形成されている。 As shown in FIG. 13(a), the joining work involves removing a specified width of the permanent pavement 6 from the edge adjacent to the vertical joint J2 formed between the new deck 3 of the work section D1 and the new deck 3 of the work section O1 on the passing lane side, and then installing the permanent plate 52 in the cutout formed on the edge of the new deck 3 so as to straddle the vertical joint J2 above. The permanent plate 52 has a width sufficient to cover the vertical joint J2, and its length is formed to be approximately equal to the length of the work sections D1 and O1 in the bridge axis direction.

なお、本設プレート52の材料は、横目地部J1を被覆する際に採用したものと同様のものを使用しており、新設床版3への設置方向も、横目地部J1に設置した際の方法と同様である。 The material used for the permanent plate 52 is the same as that used to cover the horizontal joint section J1, and the installation direction on the new deck slab 3 is the same as that used when installing it on the horizontal joint section J1.

最後に、図13(b)及び(c)で示すように、本舗装6を施すとともに、間詰めコンクリート51を充填する。これにより、橋梁B1を橋軸方向に区分けしたうちの1区画目の床版取替え作業が終了する。 Finally, as shown in Figures 13(b) and (c), the permanent pavement 6 is laid and the interfacial concrete 51 is filled in. This completes the deck replacement work for the first section of the bridge B1 divided in the bridge axis direction.

こののち、図2のフロー図の第2ステップに戻って、橋梁B1に設定した第2区画以降のすべての区画に対して同様の施工を上記の手順に従って、繰り返し実施する(第5ステップ)。 After this, return to the second step of the flow diagram in Figure 2 and repeat the same construction work for all sections set on bridge B1 from the second section onwards, following the above procedure (fifth step).

これにより、橋梁B1における施工予定領域(1区画目、2区画目、3区画目・・)の既設床版1をすべて、新設床版3に取替える施工が終了する。なお、走行車線側と追い越し車線側に対して、上記の半断面床版取替え工法を実施する順序は、上記の手順に限定されるものではない。 This completes the replacement of all existing deck slabs 1 in the planned construction areas of bridge B1 (1st section, 2nd section, 3rd section, etc.) with new deck slabs 3. Note that the order in which the half-section deck replacement method is carried out on the driving lane side and the passing lane side is not limited to the above procedure.

つまり、本実施の形態では、図14(a)で示すように、1区画目の作業区画D1を新設床版3に取替えたのち、これに並列する作業区画O1を新設床版3に取替える。こののち、2区画目の作業区画D2を新設床版3に取替え、これに並列する作業区画O2を新設床版3に取替える。この作業を繰り返すこととなる。 In other words, in this embodiment, as shown in FIG. 14(a), the first work section D1 is replaced with the new deck 3, and then the parallel work section O1 is replaced with the new deck 3. After this, the second work section D2 is replaced with the new deck 3, and then the parallel work section O2 is replaced with the new deck 3. This process is repeated.

しかし、この手順に限定されるものではない。例えば図14(b)で示すように、1区画目の作業区画D1を新設床版3に取替えたのち、これに並列する作業区画O1を新設床版3に取替える。こののち、2区画目の作業区画O2を新設床版3に取替え、これに並列する作業区画D2を新設床版3に取替える。この作業を繰り返すといった手順を採用してもよい。 However, this procedure is not limited to this. For example, as shown in FIG. 14(b), the first work area D1 is replaced with the new deck slab 3, and then the parallel work area O1 is replaced with the new deck slab 3. After this, the second work area O2 is replaced with the new deck slab 3, and then the parallel work area D2 is replaced with the new deck slab 3. A procedure in which this work is repeated may be adopted.

このように、既設床版の取替え工法は、図4で示すような第1の工程から第3の工程までの一連の作業の中で、現場条件や施工状況(例えば、ケレン作業やスタッドジベル21の設置作業等の進捗状況)に応じて、作業を中断する段階を適宜選択できる。これにより、交通解放時間帯の到来に備えつつ、1回の工事交通規制時間帯内で実施する作業工程の進捗を調整でき、効率よく新設床版3の取り換え作業を実施することが可能となる。 In this way, the existing deck replacement method can appropriately select the stage at which to suspend work during the series of work steps from the first to third steps shown in Figure 4, depending on the site conditions and construction status (for example, the progress of scraping work and installation of stud dowels 21, etc.). This makes it possible to adjust the progress of work processes carried out during one construction traffic control period while preparing for the arrival of traffic release periods, making it possible to efficiently carry out the replacement work of the new deck slab 3.

したがって、夜間に車線規制時間帯を設定することで、昼間の交通解放を実現しながら、既設床版1を新設床版3に取替えることが可能となる。これにより、既設床版取替作業を実施しようとする道路橋Bが、都市部等の重交通路上または長大トンネルに挟まれた山間部等にある場合にも、周辺地域の交通環境への影響を最小限に抑えつつ施工を実施することが可能となる。 Therefore, by setting lane restriction times at night, it is possible to replace the existing deck 1 with the new deck 3 while opening up traffic during the day. This makes it possible to carry out the work while minimizing the impact on the traffic environment in the surrounding area, even if the road bridge B on which the existing deck replacement work is to be carried out is located on a heavy traffic road in an urban area, or in a mountainous area sandwiched between long tunnels.

また、既設床版片11の橋軸方向からみた断面を、既設床版1の横断面を半分に分割した半断面に形成することで、昼間は、上り2車線用の橋梁B1と下り2車線用の橋梁B2の両者を交通解放し、夜間は、上り2車線用の橋梁B1のみに車線規制を行う半断面床版取替え工法により、橋梁B1における既設床版1の取替作業を実施できる。 In addition, by forming the cross section of the existing deck piece 11 seen from the bridge axis direction into a half cross section that divides the cross section of the existing deck 1 in half, both bridge B1 for the two upbound lanes and bridge B2 for the two downbound lanes are opened to traffic during the day, and at night, lane restrictions are imposed only on bridge B1 for the two upbound lanes. This allows replacement work of the existing deck 1 on bridge B1 to be carried out using a half-section deck replacement method.

したがって、道路橋Bを構成する上り車線用と下り車線用の橋梁B1、B2のうち、いずれか一方を全面通行止めにして工事を行い、他方を対面通行規制とする必要が無いため、通行車両に対する安全性の確保が可能になるとともに、道路構造等の事情により対面通行規制を実施できない、または、実施が可能であっても周辺地域の交通状況によっては長期間の通行規制が困難である等、様々な課題を有する道路環境にあっても、既設床版1の取替工事を確実に実施することが可能となる。 As a result, there is no need to completely close one of the bridges B1 and B2 for the inbound and outbound lanes that make up road bridge B to traffic while carrying out construction work and restricting two-way traffic on the other, which ensures safety for passing vehicles and also makes it possible to reliably carry out replacement work for the existing deck 1 even in road environments with various challenges, such as when two-way traffic restrictions cannot be implemented due to circumstances such as the road structure, or when long-term traffic restrictions are difficult even if they can be implemented due to traffic conditions in the surrounding area.

本発明の橋梁の床版取替え工法は、上記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲で種々の変更が可能である。 The bridge deck replacement method of the present invention is not limited to the above embodiment, and various modifications are possible without departing from the spirit of the present invention.

例えば、本実施の形態では、本設プレート52を使用することにより、隣り合う新設床版3の間に形成される横目地部J1及び縦目地部J2に対して、間詰コンクリート51を打設する前に本舗装6を実施できる。このため、第3の工程でStep5~9を実施することとしたが、本設プレート52を使用しない場合には、第3の工程を2回に分割すればよい。 For example, in this embodiment, by using the permanent plate 52, the permanent pavement 6 can be carried out before pouring the fill concrete 51 into the horizontal joints J1 and vertical joints J2 formed between adjacent new deck slabs 3. For this reason, steps 5 to 9 are carried out in the third step, but if the permanent plate 52 is not used, the third step can be divided into two steps.

この場合には、第3の前半工程は、新設床版3の据え付けから無収縮モルタル4を充填する工程(Step5、6)を実施する。また、第3の後半工程は、隣り合う新設床版3の横目地部J1に、間詰めコンクリート51を充填したのちに(Step9)、本舗装6を施す(Step8)。そして、第3の前半工程を3度目の車線規制時間帯の到来時に行い、第3の後半工程を4度目の車線規制時間帯到来時に実施する。 In this case, the first half of the third process involves installing the new slab 3 and filling it with non-shrink mortar 4 (Steps 5 and 6). The second half of the third process involves filling the horizontal joints J1 of the adjacent new slabs 3 with filler concrete 51 (Step 9) and then laying the main pavement 6 (Step 8). The first half of the third process is carried out when the third lane restriction period arrives, and the second half of the third process is carried out when the fourth lane restriction period arrives.

なお、第3の前半工程では、Step6で無収縮モルタル4を充填したのち、図15(a)で示すように、隣り合う新設床版3との間に形成された横目地部J1に仮間詰め9を行い、新設床版3の上面全面に一旦、仮舗装8を施す。 In the third first half process, after filling with non-shrink mortar 4 in step 6, temporary gap filling 9 is performed on the horizontal joints J1 formed between the adjacent new decks 3, as shown in Figure 15 (a), and temporary paving 8 is applied to the entire top surface of the new deck 3.

そして、第3の後半工程は、新設床版3の上面に施した仮舗装8をはく離するとともに、隣り合う新設床版3との間に形成された横目地部J1の仮間詰め9を取り除き、横目地部J1の底面に型枠53を設置して、横目地部J1の上方から間詰めコンクリート51を充填し養生し、本設間詰め5を行う。 Then, in the third latter half of the process, the temporary pavement 8 applied to the top surface of the new deck 3 is peeled off, the temporary filler 9 in the horizontal joint J1 formed between the adjacent new deck slabs 3 is removed, formwork 53 is placed on the bottom of the horizontal joint J1, filler concrete 51 is filled from above the horizontal joint J1, and cured, and the permanent filler 5 is performed.

所定時間の養生が終了したのち、図13(b)で示すように、新設床版3の上面全面に本舗装6を施す。なお、縦目地部J2と、既設床版1もしくは既設床版片11と新設床版3との間に形成された横目地部J1とは、第3の前半工程で行った仮間詰め9を残置しておき、その上面から本舗装6を施せばよい。 After the prescribed curing period has been completed, as shown in FIG. 13(b), the permanent pavement 6 is applied to the entire top surface of the new deck 3. Note that for the vertical joints J2 and the horizontal joints J1 formed between the existing deck 1 or existing deck piece 11 and the new deck 3, the temporary gap filling 9 applied in the first half of the third process is left in place, and the permanent pavement 6 is applied from above.

1 既設床版
11 既設床版片
2 主桁
21 スタッドジベル
22 作業足場
3 新設床版
31 床版本体
32 地覆
33 接合鉄筋
34 スタッドジベル挿通孔
4 無収縮モルタル
41 モルタル止め
5 本設間詰め
51 間詰めコンクリート
52 本設プレート
53 型枠
6 本舗装
7 仮覆工床版
71 床版本体
72 地覆
73 高欄
74 高さ調整材
8 仮舗装
81 先行仮舗装
82 後行仮舗装
9 仮間詰め
91 開口塞ぎ板
92 充填材
93 締結具
10 床版架設装置

J1 横目地部
J2 縦目地部
B 道路橋
B1 橋梁(上り2車線)
B2 橋梁(下り2車線)
1 Existing deck 11 Existing deck piece 2 Main girder 21 Stud dowel 22 Work scaffold 3 New deck 31 Deck body 32 Ground covering 33 Joint reinforcing bar 34 Stud dowel insertion hole 4 Non-shrink mortar 41 Mortar stopper 5 Permanent interfacial filling 51 Interfacial filling concrete 52 Permanent plate 53 Formwork 6 Permanent pavement 7 Temporary covering deck 71 Deck body 72 Ground covering 73 Parapet 74 Height adjustment material 8 Temporary pavement 81 Preceding temporary pavement 82 Following temporary pavement 9 Temporary interfacial filling 91 Opening closing plate 92 Filling material 93 Fastener 10 Deck erection device

J1 Horizontal joint J2 Vertical joint B Road bridge B1 Bridge (uphill 2 lanes)
B2 Bridge (2 lanes downhill)

Claims (5)

工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、鋼製の主桁上に設置された既設床版をプレキャストコンクリート造の新設床版に取替える橋梁の床版取替え工法であって、
橋梁の既設床版を橋軸方向に分割して形成した複数の既設床版片のうち、少なくとも一部を撤去して前記主桁を露出させる第1の工程と、
前記第1の工程で前記既設床版片を撤去することにより露出させた前記新設床版を据え付ける前の前記主桁上面に、スタッドジベルを設置する第2の工程と、
前記第2の工程で前記スタッドジベルを設置した前記主桁上に、複数の前記新設床版を据え付け、前記新設床版を前記主桁に接合させたのち、隣り合う新設床版を接合する第3の工程と、を備え、
前記第1の工程から前記第3の工程は、前記工事交通規制時間帯に実施されるとともに、1回の前記工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含み、
前記交通解放時間帯が到来する直前に前記第1の工程もしくは前記第2の工程が実施される場合、作業終了時において露出状態にある前記主桁上に、撤去した前記既設床版片に替えて仮覆工床版を設置することを特徴とする橋梁の床版取替え工法。
This is a bridge deck replacement method in which an existing deck installed on a steel girder is replaced with a new deck made of precast concrete while alternating between construction traffic restriction time periods and traffic release time periods.
A first step of removing at least a portion of a plurality of existing deck pieces formed by dividing an existing deck of a bridge in the bridge axis direction to expose the main girder;
A second step of installing stud dowels on the upper surface of the main girder before installing the new deck exposed by removing the existing deck piece in the first step;
A third step of installing a plurality of the new deck slabs on the main girder on which the stud dowels were installed in the second step, joining the new deck slabs to the main girder, and then joining adjacent new deck slabs;
The first step to the third step are carried out during the construction traffic control time period, and include a case where two or more steps are carried out consecutively within one construction traffic control time period,
A bridge deck replacement method characterized in that, when the first step or the second step is carried out immediately before the traffic release period arrives, a temporary covering deck is installed on the main girder, which is exposed at the end of the work, in place of the removed existing deck piece.
請求項1に記載の橋梁の床版取替え工法において、
前記第1の工程から前記第3の工程を、前記工事交通規制時間帯が到来するごとに橋軸方向に繰り返すことを特徴とする橋梁の床版取替え工法。
In the bridge deck replacement method according to claim 1,
A bridge deck replacement method, characterized in that the first to third steps are repeated in the bridge axis direction every time the construction traffic control period arrives.
請求項1または2に記載の橋梁の床版取替え工法において、
前記既設床版片の橋軸方向からみた断面が、前記既設床版の横断面を半分に分割した半断面に形成されることを特徴とする橋梁の床版取替え工法。
In the bridge deck replacement method according to claim 1 or 2,
A bridge deck replacement method, characterized in that the cross section of the existing deck piece as viewed from the bridge axis direction is formed into a half cross section obtained by dividing the cross section of the existing deck in half.
請求項1から3のいずれか1項に記載の橋梁の床版取替え工法において、
第3の工程で、
隣り合う前記新設床版を、該新設床版の一部として機能する本設プレートで接合することを特徴とする橋梁の床版取替え工法。
In the bridge deck replacement method according to any one of claims 1 to 3,
In the third step,
A bridge deck replacement method characterized by joining adjacent new decks with a permanent plate that functions as part of the new deck .
工事交通規制時間帯と交通解放時間帯とを交互に繰り返しながら、鋼製の主桁上に設置された既設床版をプレキャストコンクリート造の新設床版に取替える橋梁の床版取替え工法であって、
橋梁の既設床版を橋軸方向に分割して形成した複数の既設床版片のうち、少なくとも一部を撤去して前記主桁を露出させる第1の工程と、
前記第1の工程で露出させた前記主桁上面に、スタッドジベルを設置する第2の工程と、
前記第2の工程で前記スタッドジベルを設置した前記主桁上に、複数の前記新設床版を据え付け、前記新設床版を前記主桁に接合させたのち、隣り合う新設床版を接合する第3の工程と、を備え、
前記第1の工程から前記第3の工程は、前記工事交通規制時間帯に実施されるとともに、1回の前記工事交通規制時間帯内で2つ以上の工程を連続して実施する場合を含み、
前記交通解放時間帯が到来する直前に前記第1の工程もしくは前記第2の工程が実施される場合、作業終了時において露出状態にある前記主桁上に、仮覆工床版を設置し、
前記主桁上に前記仮覆工床版を設置したのち、
該仮覆工床版に隣接する目地の上下面をそれぞれ開口塞ぎ板で覆い、該開口塞ぎ板どうしを締結具を介して締結することを特徴とする橋梁の床版取替え工法。
This is a bridge deck replacement method in which an existing deck installed on a steel girder is replaced with a new deck made of precast concrete while alternating between construction traffic restriction time periods and traffic release time periods.
A first step of removing at least a portion of a plurality of existing deck pieces formed by dividing an existing deck of a bridge in the bridge axis direction to expose the main girder;
a second step of installing a stud dowel on the upper surface of the main girder exposed in the first step;
A third step of installing a plurality of the new deck slabs on the main girder on which the stud dowels were installed in the second step, joining the new deck slabs to the main girder, and then joining adjacent new deck slabs;
The first step to the third step are carried out during the construction traffic control time period, and include a case where two or more steps are carried out consecutively within one construction traffic control time period,
When the first step or the second step is carried out immediately before the traffic release time period, a temporary covering deck is installed on the main girder that is exposed at the end of the work,
After the temporary covering deck is installed on the main girder,
A bridge deck replacement method characterized in that the upper and lower surfaces of the joints adjacent to the temporary covering deck are covered with opening closing plates, and the opening closing plates are fastened together using fasteners.
JP2020097190A 2020-06-03 2020-06-03 Bridge deck replacement method Active JP7484439B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020097190A JP7484439B2 (en) 2020-06-03 2020-06-03 Bridge deck replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020097190A JP7484439B2 (en) 2020-06-03 2020-06-03 Bridge deck replacement method

Publications (2)

Publication Number Publication Date
JP2021188454A JP2021188454A (en) 2021-12-13
JP7484439B2 true JP7484439B2 (en) 2024-05-16

Family

ID=78849023

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020097190A Active JP7484439B2 (en) 2020-06-03 2020-06-03 Bridge deck replacement method

Country Status (1)

Country Link
JP (1) JP7484439B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7384310B1 (en) * 2023-06-16 2023-11-21 株式会社Ihi Joint structure, floor slab and floor slab replacement method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3702263B2 (en) 2002-10-23 2005-10-05 三菱重工業株式会社 Bridge replacement method
JP2018123643A (en) 2017-02-03 2018-08-09 首都高速道路株式会社 Slab replacing method for composite girder
JP2019073948A (en) 2017-10-18 2019-05-16 鹿島建設株式会社 Floor slab reconstruction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3702263B2 (en) 2002-10-23 2005-10-05 三菱重工業株式会社 Bridge replacement method
JP2018123643A (en) 2017-02-03 2018-08-09 首都高速道路株式会社 Slab replacing method for composite girder
JP2019073948A (en) 2017-10-18 2019-05-16 鹿島建設株式会社 Floor slab reconstruction method

Also Published As

Publication number Publication date
JP2021188454A (en) 2021-12-13

Similar Documents

Publication Publication Date Title
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
JP6316665B2 (en) Composite structure of steel girder and precast slab and its construction method
US8636441B2 (en) Dual direction pre-stressed pre-tensioned precast concrete slabs and process for same
JP6004353B2 (en) Replacement method of concrete floor slab for elevated road
US10704215B2 (en) System for construction of composite U shaped reinforced girders bridge deck and methods thereof
Biswas Precast bridge deck design systems
JP6097965B2 (en) Construction method of concrete precast slab for bridge
KR101107826B1 (en) Slab-type box girder made by precast concrete and method constructing the bridge therewith
JP7484439B2 (en) Bridge deck replacement method
JP7483507B2 (en) Bridge deck replacement method
Savino et al. Corso Grosseto viaduct: Historical and technical overview
JP2007107195A (en) Steel floor slab reinforcing construction method and precast reinforcing slab used therefor
TWI754158B (en) Structure for bridges and method for replacing floor slab
Russell et al. Prefabricated bridge elements and systems in Japan and Europe
JP2016075046A (en) Widening method for existing road bridge
JP3579167B2 (en) Deck for road surface and its laying method
Lutz et al. Deck Widening and Replacement of Woodrow Wilson Memorial Bridge
JP7306053B2 (en) Joint structure of precast floor slab and construction method of joint
Culmo Rapid bridge deck replacement with full-depth precast concrete slabs
JPH023843B2 (en)
JP2018044362A (en) Method for easily constructing tunnel watchman passage using l-shaped precast concrete product
Krishnan et al. Cost analysis and benefits of construction of segmental bridges
JP2003147726A (en) Construction method for composite floor system and floor system panel used in the same
JP7272918B2 (en) Existing floor slab replacement method
Biswas On modular full depth bridge deck rehabilitation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230518

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231130

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231212

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240130

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240220

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240312

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240402

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240415

R150 Certificate of patent or registration of utility model

Ref document number: 7484439

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150