JP3702263B2 - Bridge replacement method - Google Patents
Bridge replacement method Download PDFInfo
- Publication number
- JP3702263B2 JP3702263B2 JP2002308571A JP2002308571A JP3702263B2 JP 3702263 B2 JP3702263 B2 JP 3702263B2 JP 2002308571 A JP2002308571 A JP 2002308571A JP 2002308571 A JP2002308571 A JP 2002308571A JP 3702263 B2 JP3702263 B2 JP 3702263B2
- Authority
- JP
- Japan
- Prior art keywords
- bridge
- new
- existing
- existing bridge
- jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Description
【0001】
【発明の属する技術分野】
この発明は、既設橋を撤去し、新設橋を架設する橋梁架け替え方法に関する。
【0002】
【従来の技術】
一般に、従来の橋梁架け替え方法においては、既設橋を撤去した後に新設橋を架設する方法が採用されており、この種の方法として種々の方法が提案されている。
【0003】
従来の橋梁架け替え方法としては、例えば、架け替えを必要とする旧橋の側方に、上面に第1仮ガイドレールを敷設した仮橋台を構築し、この第1仮ガイドレールの上に移動可能な自在支承を配置させる状態で仮橋台の上に新橋を仮架設する新橋仮架設工程と、この新橋を仮橋として交通の切り回しを行いながら旧橋及び旧下部工を撤去する旧橋撤去工程と、旧橋及び旧下部工を撤去したのちの架け替え位置に、上面に本ガイドレールを敷設した新下部工を新たに構築すると共に、本ガイドレールと前記第1仮ガイドレール間に敷設した第2仮ガイドレールを介して前記第1仮ガイドレールから本ガイドレールに至るように自在支承を移動させながら前記仮橋台の上から新下部工の上に新橋を移動させて、この新橋を新下部工の上に架設する新橋本架設工程と、新橋を新下部工の上に架設したのち、前記仮橋台及び仮ガイドレールを撤去する仮橋台撤去工程を備えていることを特徴とする橋梁架け替え工法がある。(特許文献1参照。)。
【0004】
【特許文献1】
特開2002−167715号公報(第1−4頁、第1図)
【0005】
【発明が解決しようとする課題】
ところで、上記従来の橋梁架け替え方法においては、既設橋から新設橋に架け替える際、周囲の状況から仮設橋を設置することが不可能となる場合、本来その橋梁上を通過する交通を通行止めとしなければならないため、交通の遮断あるいは迂回路の渋滞を招き、社会的損失が大きくなるという問題があった。また、仮設橋を設置することが可能となる場合であっても、架け替え期間中に交通を通行させる迂回路を別途設置し、架け替え終了後にその迂回路を撤去するため、その迂回路に要する設備費用が無駄になるという問題があった。特に、上記の公報に記載されているような橋梁の場合、大型化した新設橋を仮設橋に利用することにより、新設橋を支持するのに必要な仮橋台を既設橋の側方に構築しなければならず、また、架け替え終了後にその仮橋台を撤去しなければならないため、有効な経済性を得ることが困難となる。また、必ず、仮設側を通る迂回路が必要となり、迂回路を設けることができない場所での設置は困難となる。
【0006】
この発明は、このような事情を考慮してなされたもので、橋梁の架け替えを迅速に行い、橋梁の架け替え期間を短縮して、社会的損失及び経済的損失を最小限に抑制する橋梁架け替え方法を提供することを目的とする。
【0007】
【課題を解決するための手段】
この発明は、上記課題を解決するため、以下の手段を採用する。
請求項1に係る発明は、橋梁設置位置に架けられた既設橋梁を新設橋梁に架け替える橋梁架け替え方法であって、前記橋梁設置位置と並列して設けられた新設橋梁仮置位置に前記新設橋梁を底面を支持した状態で待機させた後、前記既設橋梁を移動させるときに、前記新設橋梁を底面を支持した状態で摺動させると同時に、前記橋梁設置位置と並列して設けられた既設橋梁仮置位置に前記既設橋梁を底面を支持した状態で摺動させることを特徴とする。
【0008】
この発明によれば、既設橋梁を移動させると同時に新設橋梁を移動させて架け替えを行うことにより、この架け替え作業に要する時間を大幅に短縮することになるとともに、この架け替え作業に伴って迂回路を設置する必要がない。
そして、既設橋梁を、橋梁設置位置と並列して設けられた既設橋梁仮置位置に移動させることにより、橋梁設置位置には、既設橋梁が迅速に新設橋梁に架け替えられることとなる。
さらに、既設橋梁をその既設橋梁の底面を支持した状態で摺動させると同時に、新設橋梁をその新設橋梁の底面を支持した状態で橋梁設置位置に摺動させることにより、小さい荷重をもって既設橋梁及び新設橋梁が摺動するため、既設橋梁及び新設橋梁の摺動が迅速に行われることとなる。
【0012】
この発明によれば、既設橋梁をその既設橋梁の底面を支持した状態で摺動させると同時に、新設橋梁をその新設橋梁の底面を支持した状態で橋梁設置位置に摺動させることにより、小さい荷重をもって既設橋梁及び新設橋梁が摺動するため、既設橋梁及び新設橋梁の摺動が迅速に行われることとなる。
【0013】
【発明の実施の形態】
以下、この発明の実施の形態について、図面を参照して説明する。
図1は、河川上に位置する既設橋梁及び新設橋梁を示す図である。
図1において、既設橋梁1aは、河川R上に、その河川Rが流れる方向と交差する方向に架設され、その両端部に伸縮装置81a、82aを設けて道路81、82に連接され、橋梁設置位置80に配置されている。また、新設橋梁1bは、既設橋梁1aと並列した新設橋梁仮置位置83に設置されている。これらの既設橋梁1a及び新設橋梁1bは、その底面が河川Rの底面から立設された工事用桟橋90に支持されている。この工事用桟橋90は、架け替え時に既設橋梁1a及び新設橋梁1bが移動可能となるように、その河川Rが流れる方向に延在して設置されている。
既設橋梁1aが移動する方向に延在した工事用桟橋90の端部90aに位置する既設橋梁仮置位置84には、既設橋梁仮受けベント92が複数配置されている。この既設橋梁仮受けベント92は、河川Rの底面から立設されており、その上方に既設橋梁1aが載置可能となる構造とされている。
【0014】
図2は、既設橋梁1aと、その既設橋梁1aに取付けられた架設ジャッキを示す図である。
既設橋梁1aは、その上面に設けられた床板2aと、その床板2aの下面に設けられた梁としての横桁3aとを備えて構成されている。その横桁3aの両側面に、架設ジャッキ10が設置されている。
また、新設橋梁1bは、その上面に設けられた床板2bと、その床板2bの下面に設けられた梁としての横桁3bとを備えて構成されている。その横桁3bの両側面に、架設ジャッキ10が設置されている。
ここで、既設橋梁1aと新設橋梁1bとに取付けられた架設ジャッキ10の構成については同様であるため、既設橋梁1aに取付けられた架設ジャッキ10について説明し、新設橋梁1bに取付けられた架設ジャッキ10については、同一の構成要素には同一の符号を付し、説明を省略する。
【0015】
架設ジャッキ10は、固定部20と、棒材30と、ジャッキ部40と、ベース部50とを備えて構成されている。
固定部20は、その中央部21が鉛直方向に円筒状に形成されており、その内部の全長に渡ってネジを切った構成とされている。
固定部20の側部には、その中央部21から大きく離間する位置まで突出した突出部22が設けられ、その突出部22には、既設橋梁1aを連結する連結部23が設けられている。
連結部23は、横桁3の側面に溶接もしくはボルトにて固定された矩形状の連結部材3aにボルトで締結して固定されている。
また、固定部20の下側には、その固定部20が下方への脱落を防止するように、ストッパ24が設けられている。
【0016】
棒材30は、固定部20に嵌合されてその固定部20を支持し、比較的厚肉であるパイプ材の全長に渡ってネジを切ってなり、その固定部20から下方に延在して設けられている。この棒材30は、固定部20の上下動を案内することが可能となるように、固定部20に嵌合されている。ただし、本発明の場合、固定部20は、稼動部材として使用しないため、棒材30の上部に固定して設置されている。
【0017】
ジャッキ部40は、図3に示すように、その中央部41が鉛直方向に円筒状に形成されており、その内部の全長に渡ってネジを切った構成とされている。
ジャッキ部40の側部には、その中央部41から大きく離間する位置まで突出した突出部42が設けられ、その突出部42には、ジャッキ部40に対して固定され、工事用桟橋90上に載置されたベース部50を連結する連結部43が設けられている。
連結部43は、そのベース部50の側面に溶接もしくはボルトにて固定された矩形状の連結部材50aにボルトで締結して固定されている。
【0018】
また、ジャッキ部40は、棒材30に対して移動可能となるように、この棒材30を囲繞した、すなわち、この棒材30が嵌合された構成とされている。
ジャッキ部40の下側には、そのジャッキ部40が下方への脱落を防止するように、ストッパ44が設けられている。
【0019】
ベース部50は、その側面にジャッキ部40が連結される略矩形状の架台であり、その下部には、そのベース部50と工事用桟橋90との間に介在し、既設橋梁1aを移動させる摺動部材としてスライドジャッキ51が複数設置されている。このスライドジャッキ51は、例えば、シリンダの上部に油圧により上下するピストンを備え、底部にその油圧の作用でシリンダ下端より突出する合成樹脂製の滑走部材を配置したものを使用する。
【0020】
工事用桟橋90は、図示しないが、河川Rの底面から立設された複数の杭の上部に設置され、鋼板によって構成されている。その工事用桟橋90には、既設橋梁1aのジャッキアップあるいはジャッキダウンを行う位置において、棒材30が鉛直方向に貫通可能となるように、貫通孔91が複数配置されている。
ここで、既設橋梁1aが工事用桟橋90に近い位置にある場合、固定部20の取付位置も工事用桟橋90の近くに位置する。したがって、この場合、固定部20から下方に延在する棒材30の下部30aは、貫通孔91を貫通した下方に位置することとなる。
【0021】
次に、上記の構成からなる橋梁架け替え方法について説明する。
この橋梁架け替え方法は、既設橋梁1aと道路81、82とを縁切りした後、既設橋梁1aを橋梁設置位置80から既設橋梁仮置位置84へその底面を支持した状態で移動するとともに、新設橋梁1bを新設橋梁仮置位置83から橋梁設置位置80へその底面を支持した状態で移動して、新設橋梁1bを連接するものである。
【0022】
図4に、この橋梁架け替え方法についてのフローチャートを示す。
まず、既設橋梁1aと新設橋梁1bとの架け替えに必要な仮設備工を行う(ステップS10)。この仮設備工は、例えば、工事用桟橋90、既設橋梁仮受けベント92の設置工事などである。
次に、新設橋梁1bの作業として、新設橋梁1bを組立てる(ステップS11)。この新設橋梁1bに備えられた床板2b上において、舗装工を完了させる(ステップS12)。その後、新設橋梁1bに水道管、ガス管、電気配管などの添加物を設置するとともに(ステップS13)、高欄を設置する(ステップS14)。そして、架設ジャッキ10を新設橋梁1bに設置する(ステップS15)。すなわち、新設橋梁1bの適当な複数の位置にそれぞれ架設ジャッキ10を配置し、その架設ジャッキ10を新設橋梁1bに備えられた横桁3bの側面に設置して、架設ジャッキ10に備えられた連結部23と、その横桁3bの側面に設けられた連結部材3eとをボルトで締結して固定する。この状態で、新設橋梁1bを待機させる。
【0023】
また、既設橋梁1aの作業として、この既設橋梁1aと道路81、82とを連接する伸縮装置81a、82aを撤去する(ステップS31)。このステップS31の作業において、作業開始前に、既設橋梁1aを通行する交通を遮断し、およそ一夜間の工事期間でステップS31の作業を行い、作業終了後、この既設橋梁1aと道路81、82とを覆工板によって連接して仮復旧し、交通の通行を開放する。
【0024】
その後、この既設橋梁1aに備えられた添加物を撤去して移設するとともに(ステップS32)、高欄を縁切りし(ステップS33)、支承を縁切りする(ステップS34)。必要に応じて、既設橋梁1aに対してジャッキアップに要する補強材を既設橋梁1aに取付け(ステップS35)、また、新設橋梁1bが橋梁設置位置80に設置される際に必要な支承を、道路81、82と新設橋梁1bとが連接する位置に固定する(ステップS36)。そして、架設ジャッキ10を既設橋梁1aに設置する(ステップS37)。すなわち、既設橋梁1aの適当な複数の位置にそれぞれ架設ジャッキ10を配置し、その架設ジャッキ10を既設橋梁1aに備えられた横桁3aの側面に設置して、架設ジャッキ10に備えられた連結部23と、その横桁3aの側面に設けられた連結部材3dとをボルトで締結して固定する。
これらの作業、すなわち、ステップS11〜16及びステップS31〜36の作業は、河川の渇水期に行われることが好ましい。
【0025】
架設ジャッキ10が既設橋梁1a及び新設橋梁1bに設置された後、既設橋梁1aをジャッキアップするとともに(ステップS38)、新設橋梁1bをジャッキアップし(ステップS16)、既設橋梁1aを橋梁設置位置80から既設橋梁仮置位置84まで移動させるととともに(ステップS39)、新設橋梁1bを新設橋梁仮置位置83から橋梁設置位置80まで移動させる(ステップS17)。
【0026】
すなわち、全てのジャッキ部40を同時に加圧して駆動させ、既設橋梁1a及び新設橋梁1bを所定の位置までジャッキアップする。既設橋梁1a及び新設橋梁1bを所定の位置までジャッキアップした後、ジャッキ部40の下側に設けられたストッパ44を巻き上げて締結し、ジャッキ部40の加圧を解除する。その状態を維持したまま、スライドジャッキ51を滑動可能な状態に設定し、図示しない外部からの移送手段によって、既設橋梁1a及び新設橋梁1bをそれぞれの底面を支持した状態で所定の位置まで移動し、既設橋梁1a及び新設橋梁1bが所定の位置に移動した後、スライドジャッキ51を滑動不可の状態に設定する。これらの既設橋梁1a及び新設橋梁1bの移動時には、図5に示すように、架設ジャッキ10によって既設橋梁1a及び新設橋梁1bがジャッキアップされることによって、棒材30の下部30aが工事用桟橋90に設けられた貫通孔91より上方にあるため、この状態のまま既設橋梁1a及び新設橋梁1bを移動することが可能である。
また、このステップS16〜17及びS38〜39の作業において、作業開始前に、既設橋梁1aを通行する交通を遮断し、およそ一夜間の工事期間でこれらの作業を行う。
【0027】
新設橋梁1bを新設橋梁仮置位置83から橋梁設置位置80に移動した後、ジャッキダウンして、道路81、82と新設橋梁1bとが連接する位置に固定された支承の位置に、新設橋梁1bを設置する(ステップS18)。すなわち、ジャッキ部40を加圧し、ストッパ44を巻き下げ、全てのジャッキ部40を同時に加圧して駆動させ、新設橋梁1bを所定の位置までジャッキダウンする。新設橋梁1bを所定の位置までジャッキダウンした後、ジャッキ部40の加圧を解除する。その後、架設ジャッキ10が不要となるため、新設橋梁1bに取付けられた架設ジャッキ10を撤去する。
設置完了後、この新設橋梁1bと道路81、82とを覆工板によって連接して仮復旧し(ステップS19)、交通の通行を開放する。そして、新設橋梁1bに添加物を取付ける(ステップS20)。
【0028】
その後、この新設橋梁1bと道路81、82とを連接する伸縮装置81a、82aを取付ける(ステップS21)。このステップS21の作業において、作業開始前に、新設橋梁1bを通行する交通を遮断し、およそ一夜間の工事期間でステップS21の作業を行い、作業終了後、この新設橋梁1bと道路81、82とを伸縮装置81a、82aによって連接し、交通の通行を開放する。
【0029】
また、既設橋梁1aにおいて、その既設橋梁1aを橋梁設置位置80から既設橋梁仮置位置84まで移動した後、そのまま既設橋梁仮受けベント92上に仮置きする(ステップS40)。すなわち、ジャッキ部40を加圧し、ストッパ44を巻き下げ、全てのジャッキ部40を同時に加圧して駆動させ、既設橋梁1aを所定の位置までジャッキダウンする。既設橋梁1aを所定の位置までジャッキダウンした後、ジャッキ部40の加圧を解除する。その後、架設ジャッキ10が不要となるため、既設橋梁1aに取付けられた架設ジャッキ10を撤去する。
既設橋梁1aは、その位置で解体される(ステップS41)。その解体された部材は、その位置から撤去され、搬出される(ステップS42)。
【0030】
この場合、交通の遮断を行う期間が、既設橋梁1aの伸縮装置81a、82aを撤去する際の一夜間、既設橋梁1aと新設橋梁1bとの架け替えを行う際の一夜間、及び新設橋梁1bの伸縮装置81a、82aを取付ける際の一夜間、合計三回のみとなるため、既設橋梁1aと新設橋梁1bとの架け替え作業を行う際に、交通の迂回路を別途設置する必要がない。また、架け替え作業に要する時間が一夜間で終了するため、この架け替え作業に要する時間が大幅に短縮されることとなる。
【0031】
上記の構成によれば、交通の迂回路を別途設置する必要がないので、その迂回路を設置する費用を削減することができ、経済的損失を最小限に抑制することができる。また、既設橋梁1aと新設橋梁1bとの架け替えを迅速に行うことにより、その架け替え期間を短縮するので、架け替え作業による交通の遮断に伴う社会的損失を最小限に抑制することができる。
【0032】
なお、交通の遮断を行う期間が、既設橋梁1aの伸縮装置81a、82aを撤去する際の一夜間、既設橋梁1aと新設橋梁1bとの架け替えを行う際の一夜間、及び新設橋梁1bの伸縮装置81a、82aを取付ける際の一夜間、合計三回のみとなるとしているが、この期間及び回数を限定するものではない。工事の規模により、この期間及び回数を適宜設定することによって、従来の方法と比較してこの発明によって得られる効果が大きいことに変わりがない。
【0033】
【発明の効果】
以上説明したこの発明の橋梁架け替え方法においては、以下の効果を奏する。請求項1に係る発明によれば、既設橋梁と新設橋梁とを同時に移動させて架け替えを行うことにより、この架け替え作業に要する時間を大幅に短縮することになるとともに、この架け替え作業に伴って迂回路を設置する必要がないので、架け替え作業による交通の遮断に伴う社会的損失を最小限に抑制することができ、また、迂回路を設置するための設備費用が削減されるので、経済的損失を最小限に抑制することができる。
【0034】
請求項2に係る発明によれば、既設橋梁を、橋梁設置位置と並列して設けられた既設橋梁仮置位置に退避させることにより、橋梁設置位置には、既設橋梁が迅速に新設橋梁に架け替えられることとなるので、架け替え作業による交通の遮断に伴う社会的損失を最小限に抑制することができ、また、迂回路を設置するための設備費用が削減されるので、経済的損失を最小限に抑制することができる。
【0035】
請求項3に係る発明によれば、既設橋梁をその既設橋梁の底面を支持した状態で移動させると同時に、新設橋梁をその新設橋梁の底面を支持した状態で橋梁設置位置に移動させることにより、既設橋梁及び新設橋梁の移動が迅速に行われることとなるので、架け替え作業による交通の遮断に伴う社会的損失を最小限に抑制することができ、また、迂回路を設置するための設備費用が削減されるので、経済的損失を最小限に抑制することができる。
【図面の簡単な説明】
【図1】 この発明における実施の形態に係る既設橋梁と新設橋梁の配置図である。
【図2】 この発明における実施の形態に係る架設ジャッキの正面図である。
【図3】 この発明における実施の形態に係る架設ジャッキの部分拡大図である。
【図4】 この発明における実施の形態に係る橋梁架け替え方法のフローチャートである。
【図5】 この発明における実施の形態に係る架設ジャッキの正面図である。
【符号の説明】
1a 既設橋梁
1b 新設橋梁
10 架設ジャッキ[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a bridge replacement method in which an existing bridge is removed and a new bridge is installed.
[0002]
[Prior art]
In general, in a conventional bridge replacement method, a method of installing a new bridge after removing an existing bridge is adopted, and various methods have been proposed as this type of method.
[0003]
As a conventional bridge replacement method, for example, a temporary abutment in which a first temporary guide rail is laid on the upper surface is constructed on the side of an old bridge that requires replacement, and the first temporary guide rail is moved. A new bridge temporary erection process in which a new bridge is temporarily installed on a temporary abutment with possible universal support, and the old bridge and old substructure are removed while the traffic is routed using this new bridge as a temporary bridge. A new substructure with this guide rail laid on the upper surface is newly constructed at the replacement position after the process and the old bridge and substructure are removed, and laid between this guide rail and the first temporary guide rail. The new bridge is moved from above the temporary abutment to above the new substructure while moving the free support from the first temporary guide rail to the main guide rail through the second temporary guide rail. Install on the new substructure And Hashimoto erection process, after erection of Shimbashi on the new substructure, it has bridges hung replacement method, characterized in that includes a temporary abutment removal step of removing the said temporary abutment and the temporary guide rails. (See Patent Document 1).
[0004]
[Patent Document 1]
JP 2002-167715 A (page 1-4, FIG. 1)
[0005]
[Problems to be solved by the invention]
By the way, in the above conventional bridge replacement method, when it is impossible to install a temporary bridge due to the surrounding conditions when replacing an existing bridge with a new bridge, traffic that originally passes over the bridge is closed. Therefore, there has been a problem that the social loss is increased due to traffic interruption or traffic congestion on the detour. Even if it is possible to install a temporary bridge, a separate detour that allows traffic to pass during the replacement period will be installed separately, and the detour will be removed after the replacement is completed. There was a problem that necessary equipment costs were wasted. In particular, in the case of a bridge as described in the above publication, a temporary abutment necessary to support the new bridge is built on the side of the existing bridge by using a large new bridge for the temporary bridge. Moreover, since the temporary abutment must be removed after the replacement is completed, it is difficult to obtain effective economic efficiency. In addition, a detour that passes through the temporary side is necessarily required, and installation in a place where a detour cannot be provided becomes difficult.
[0006]
The present invention has been made in consideration of such circumstances, and bridges that quickly replace bridges, shorten bridge replacement periods, and minimize social and economic losses. The purpose is to provide a replacement method.
[0007]
[Means for Solving the Problems]
The present invention employs the following means in order to solve the above problems.
The invention according to claim 1 is a bridge replacement method for replacing an existing bridge installed at a bridge installation position with a new bridge, wherein the new installation is performed at a new bridge temporary installation position provided in parallel with the bridge installation position. after waiting a bridge while supporting the bottom surface, when moving the existing bridges, and at the same time is slid while supporting a bottom of the new bridge, existing provided in parallel with the bridge installation position The existing bridge is slid in a state where the bottom surface is supported at a temporary bridge placement position.
[0008]
According to the present invention, the time required for the replacement work is greatly reduced by moving the existing bridge and moving the new bridge at the same time, thereby greatly reducing the time required for the replacement work. There is no need to install a detour.
Then, by moving the existing bridge to the existing bridge temporary placement position provided in parallel with the bridge installation position, the existing bridge is quickly replaced with the new bridge at the bridge installation position.
Furthermore, by sliding the existing bridge while supporting the bottom of the existing bridge, and simultaneously sliding the new bridge to the bridge installation position while supporting the bottom of the new bridge, the existing bridge and the Since the new bridge slides, the existing bridge and the new bridge slide quickly.
[0012]
According to the present invention, the existing bridge is slid while supporting the bottom surface of the existing bridge, and at the same time, the new bridge is slid to the bridge installation position while supporting the bottom surface of the new bridge. Therefore, the existing bridge and the new bridge slide, so that the existing bridge and the new bridge slide quickly.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
FIG. 1 is a diagram showing an existing bridge and a new bridge located on a river.
In FIG. 1, an existing
A plurality of existing bridge
[0014]
FIG. 2 is a diagram showing an
The existing
The
Here, since the construction of the
[0015]
The
The
A
The connecting
Further, a
[0016]
The
[0017]
As shown in FIG. 3, the
The side of the
The connecting
[0018]
Further, the
A
[0019]
The
[0020]
Although not shown, the
Here, when the existing
[0021]
Next, a bridge replacement method having the above configuration will be described.
In this bridge replacement method, after the existing
[0022]
FIG. 4 shows a flowchart of this bridge replacement method.
First, temporary equipment necessary for the replacement of the existing
Next, the
[0023]
Further, as the work of the existing
[0024]
Thereafter, the additive provided in the existing
These operations, that is, the operations of steps S11 to 16 and S31 to 36, are preferably performed during a river drought period.
[0025]
After the
[0026]
That is, all the
Further, in the operations in steps S16-17 and S38-39, before starting the operation, the traffic passing through the existing
[0027]
After the
After the installation is completed, the newly constructed
[0028]
Thereafter,
[0029]
In the existing
The existing
[0030]
In this case, the period during which the traffic is blocked is one night when the
[0031]
According to the above configuration, since it is not necessary to separately install a traffic detour, the cost of installing the detour can be reduced, and economic loss can be minimized. In addition, the replacement period between the existing
[0032]
It should be noted that the period during which the traffic is blocked is one night when the
[0033]
【The invention's effect】
The bridge replacement method of the present invention described above has the following effects. According to the first aspect of the invention, by replacing the existing bridge and the newly installed bridge at the same time, the time required for the replacement work can be greatly shortened. Since there is no need to install a detour, it is possible to minimize the social loss associated with the interruption of traffic due to the replacement work, and the equipment cost for installing the detour is reduced. Economic losses can be minimized.
[0034]
According to the second aspect of the present invention, the existing bridge can be quickly installed on the new bridge at the bridge installation position by retracting the existing bridge to the existing bridge temporary placement position provided in parallel with the bridge installation position. Therefore, it is possible to minimize the social loss caused by the interruption of the traffic due to the replacement work, and the equipment cost for installing the detour is reduced. It can be minimized.
[0035]
According to the invention of claim 3, by moving the existing bridge while supporting the bottom surface of the existing bridge, and simultaneously moving the new bridge to the bridge installation position while supporting the bottom surface of the new bridge, Existing bridges and new bridges will be moved quickly, so it is possible to minimize social losses due to traffic interruptions due to replacement work, and equipment costs for installing detours. Therefore, the economic loss can be minimized.
[Brief description of the drawings]
FIG. 1 is a layout diagram of an existing bridge and a new bridge according to an embodiment of the present invention.
FIG. 2 is a front view of a construction jack according to the embodiment of the present invention.
FIG. 3 is a partially enlarged view of a construction jack according to the embodiment of the present invention.
FIG. 4 is a flowchart of a bridge replacement method according to the embodiment of the present invention.
FIG. 5 is a front view of a construction jack according to the embodiment of the present invention.
[Explanation of symbols]
Claims (1)
前記橋梁設置位置と並列して設けられた新設橋梁仮置位置に前記新設橋梁を底面を支持した状態で待機させた後、前記既設橋梁を移動させるときに、前記新設橋梁を底面を支持した状態で摺動させると同時に、
前記橋梁設置位置と並列して設けられた既設橋梁仮置位置に前記既設橋梁を底面を支持した状態で摺動させることを特徴とする橋梁架け替え方法。A bridge replacement method for replacing an existing bridge built at a bridge installation position with a new bridge,
A state in which the new bridge is supported on the bottom surface when the existing bridge is moved after waiting for the newly installed bridge in a state where the bottom surface is supported at a new bridge temporary placement position provided in parallel with the bridge installation position. At the same time as sliding
A method of replacing a bridge, wherein the existing bridge is slid in a state where a bottom surface is supported at an existing bridge temporary placement position provided in parallel with the bridge installation position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002308571A JP3702263B2 (en) | 2002-10-23 | 2002-10-23 | Bridge replacement method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002308571A JP3702263B2 (en) | 2002-10-23 | 2002-10-23 | Bridge replacement method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004143757A JP2004143757A (en) | 2004-05-20 |
JP3702263B2 true JP3702263B2 (en) | 2005-10-05 |
Family
ID=32454677
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002308571A Expired - Lifetime JP3702263B2 (en) | 2002-10-23 | 2002-10-23 | Bridge replacement method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3702263B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4884082B2 (en) * | 2006-06-01 | 2012-02-22 | 三菱重工鉄構エンジニアリング株式会社 | Bridge replacement method |
JP4671912B2 (en) * | 2006-06-01 | 2011-04-20 | 三菱重工鉄構エンジニアリング株式会社 | Bridge replacement method |
JP5061874B2 (en) * | 2007-12-11 | 2012-10-31 | 株式会社大林組 | Railway bridge construction switching method |
CN108999097B (en) * | 2018-09-04 | 2023-09-15 | 杭州市交通规划设计研究院 | Modification structure and construction method of existing bridge abutment in bridge jacking |
-
2002
- 2002-10-23 JP JP2002308571A patent/JP3702263B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2004143757A (en) | 2004-05-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3954869B2 (en) | Bridge girder replacement method | |
JP4671912B2 (en) | Bridge replacement method | |
KR101305347B1 (en) | Pedestrian bridge for expanding road | |
JP3702263B2 (en) | Bridge replacement method | |
KR101971274B1 (en) | Bridge lifting apparatus and lifing method using it | |
KR20190041131A (en) | System For Lifting Bridge Upper Plate | |
KR101095449B1 (en) | Bridge deck dismembering method and its equipment | |
KR100892751B1 (en) | Bridge repairng method by upper structure lifting and hinge typeed temporary bridge construction | |
KR100415768B1 (en) | Process and frame for substituting steel girder of a railway bridge for concrete slab | |
KR100478701B1 (en) | Pulling up, repair and reinforcement method for the upper structure of a bridge | |
KR101130166B1 (en) | Apparatus and method for replacing bearings of box girder bridge | |
JP5848716B2 (en) | Floor slab replacement method | |
JP3536269B2 (en) | Construction method of concrete bridge and feed girder used for the construction method | |
KR101200246B1 (en) | Toggle link means steel-fram assembly jig system | |
CN113216015B (en) | Construction method of viaduct jacking bearing platform pier column upgrading structure | |
CN109056438B (en) | Construction method for transformation of urban elevated ramp | |
JP4217203B2 (en) | Structure construction method and lifting device | |
KR100478702B1 (en) | Successively replacement method of the upper structure of a bridge | |
KR100662807B1 (en) | The old and new superstructure rapid exchange equipment for bridges, and a method | |
JP5061874B2 (en) | Railway bridge construction switching method | |
CN114250722B (en) | Jacking device of existing continuous rigid frame bridge | |
KR100463073B1 (en) | Triangle Support Post of Bridge Deck Maintenance and Using Maintenance and Reinforce Method Thereof | |
KR102279873B1 (en) | Railway bridge rehabitation method using superstructure continuation, support trasition, and pier replacement | |
KR102451807B1 (en) | Cantilever frame unit for concrete pouring and expansion and repair method using of the same | |
KR19990009086A (en) | Remodeling method of bridge using existing bridge superstructure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050224 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050315 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050513 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050628 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050715 |
|
R151 | Written notification of patent or utility model registration |
Ref document number: 3702263 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090722 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090722 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100722 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110722 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120722 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130722 Year of fee payment: 8 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |