JP2009174185A - Method of constructing wide section of tunnel - Google Patents

Method of constructing wide section of tunnel Download PDF

Info

Publication number
JP2009174185A
JP2009174185A JP2008013833A JP2008013833A JP2009174185A JP 2009174185 A JP2009174185 A JP 2009174185A JP 2008013833 A JP2008013833 A JP 2008013833A JP 2008013833 A JP2008013833 A JP 2008013833A JP 2009174185 A JP2009174185 A JP 2009174185A
Authority
JP
Japan
Prior art keywords
tunnel
construction
mine
constructing
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008013833A
Other languages
Japanese (ja)
Inventor
Shuichi Sakaguchi
秀一 坂口
Shiro Mizukoshi
史郎 水越
Toshihiko Nishimuta
俊彦 西牟田
Sakae Oshima
栄 大島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP2008013833A priority Critical patent/JP2009174185A/en
Publication of JP2009174185A publication Critical patent/JP2009174185A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To minimize the effect of a construction method on a ground surface by adopting a method of constructing a plurality of horizontal tunnels serving as minimum small openings at intervals in the longitudinal direction of a shield tunnel when a diverging/converging wide section is constructed. <P>SOLUTION: In this method of constructing a wide section of a tunnel, the section space of the diverging/converging wide part serving as a diverging section or a converging section from a tunnel main line is constructed. The method comprises a horizontal tunnel excavating step of excavating horizontal tunnels 1, 2 from the tunnel main line T side in the diverging/converging wide section, and a skeleton construction step of constructing covering skeletons 4, 5 in the excavated horizontal tunnels. The horizontal tunnel excavating step comprises a preceding tunnel excavation step of excavating a plurality of preceding tunnels 1, 2 at intervals in the longitudinal direction of the tunnel main line and a following tunnel excavating step of excavating following tunnels 3 between these preceding tunnels. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、トンネル本線からの分岐部分または合流部分となる分合流拡幅部の断面空間を構築する技術として好適なトンネルの拡幅部施工方法に関する。   The present invention relates to a method for constructing a widened portion of a tunnel suitable as a technique for constructing a cross-sectional space of a split and widened portion that becomes a branching portion or a joining portion from a main tunnel.

近年、地下利用の進展に伴い、地下50m程度の大深度地下空間に、道路用トンネルや下水道トンネルなどを構築することが行われている。特に、地下利用が進展している都市部の地下空間にトンネルを構築する際には、軟弱地盤に対応できるシールド工法が有利である。   In recent years, along with the progress of underground use, road tunnels, sewer tunnels, etc. have been constructed in a deep underground space of about 50 m underground. In particular, when constructing a tunnel in an underground space in an urban area where underground use is progressing, a shield method that can handle soft ground is advantageous.

例えば道路トンネルの構築に際し、トンネル本線とランプトンネルの合流部においては、互いに寄り添う二本のシールドトンネルを一体的に連結する必要がある。この場合、路上から開削した合流部にシールドトンネルを接続する方法が考えられるが、地上の専有面積が幅、長さともに広範囲になり、問題が大きい。地盤が強固な場合には、所定断面のシールドトンネルを掘進した後に、セグメントを取り外し、NATM工法などにより合流部を構築することも考えられる。   For example, when a road tunnel is constructed, it is necessary to integrally connect two shield tunnels close to each other at the junction of the main tunnel and the ramp tunnel. In this case, a method of connecting a shield tunnel to a converging part excavated from the road can be considered, but the exclusive area on the ground is wide in both width and length, and this is a serious problem. When the ground is strong, it is conceivable to dig a shield tunnel having a predetermined cross section and then remove the segment and construct a junction by the NATM method or the like.

また、専ら地下空間において、トンネル本線とランプトンネルとの合流部を構築する技術として、例えば特許文献1、特許文献2に記載の技術がある。
特開2003−148086号公報 特許第3765048号公報
Moreover, as a technique for constructing a junction between a main tunnel and a lamp tunnel exclusively in an underground space, for example, there are techniques described in Patent Document 1 and Patent Document 2.
JP 2003-148086 A Japanese Patent No. 3765048

特許文献1に記載の技術においては、トンネル本線とランプトンネルとの合流部を構築する際に、開削区間を小規模に抑えることができる。しかし、この工法では、小規模とは言え、開削区間を必要とするため、依然として地表面への影響が大きく残り、場合によっては工事を実施することができないという問題がある。また、円形断面のシールドトンネルどうしを横方向に地中で接続するためには、大規模な接続構造物の構築が必要となる問題がある。   In the technique described in Patent Document 1, when constructing a junction between the main tunnel and the ramp tunnel, the cut-off section can be suppressed to a small scale. However, this construction method requires an open section even though it is a small scale, so that it still has a significant impact on the ground surface, and there is a problem that construction cannot be carried out depending on circumstances. Moreover, in order to connect shield tunnels having a circular cross section in the ground in the horizontal direction, there is a problem that it is necessary to construct a large-scale connection structure.

特許文献2に記載の技術においては、本線となる第1のシールドトンネルを、鋼繊維補強コンクリートを用いたECL工法により覆工する際に、分岐線または合流線となる第2のシールドトンネルと接する壁部を肉厚に覆工しておく。そして、第1のシールドトンネルと離間した位置からその第1のシールドトンネルに漸次接近するように地山を掘進して、第1のシールドトンネルと並設させて分岐線または合流線となる第2のシールドトンネルを構築し、並設された第1、第2のシールドトンネル間の壁部を除去して両者を連結する。これにより、工費が安価で周辺地盤への影響も少ないトンネルの構築方法を提供することができる。   In the technique described in Patent Document 2, when the first shield tunnel that becomes the main line is covered by the ECL method using steel fiber reinforced concrete, the second shield tunnel that becomes the branch line or the merge line is contacted. Cover the wall with a thick wall. Then, a ground is dug so as to gradually approach the first shield tunnel from a position away from the first shield tunnel, and the second shield tunnel is formed in parallel with the first shield tunnel to become a branch line or a merge line. The shield tunnel is constructed, and the wall portion between the first and second shield tunnels arranged in parallel is removed to connect the two. As a result, it is possible to provide a tunnel construction method with low construction cost and little influence on the surrounding ground.

しかし、この特許文献2の技術では、第1のシールドトンネルと第2のシールドトンネルの合流部分において、開削工法を用いることなく軟弱地盤内で直接連結することができるため、地表面への影響を比較的小さくすることができるものの、以下のような問題があった。   However, in the technology of this Patent Document 2, since the first shield tunnel and the second shield tunnel can be directly connected in the soft ground without using an open-cut method, the influence on the ground surface is reduced. Although it can be made relatively small, there are the following problems.

この特許文献2の技術においては、第1のシールドトンネルに合流させる第2のシールドトンネルを構築しない限り、このシールドトンネルどうしの合流部を施工することはできないという問題がある。即ち、分合流拡幅部を予め形成しておき、後からその分合流拡幅部に対して第2のシールドトンネルを合流させることで、工期短縮を図るといった工法を採用することはできない。   In the technique of this Patent Document 2, there is a problem that a joining portion between the shield tunnels cannot be constructed unless a second shield tunnel that joins the first shield tunnel is constructed. That is, it is not possible to adopt a construction method that shortens the work period by forming the split and widened portion in advance and then joining the second shield tunnel to the split and widened portion later.

また、地表面への影響を小さくする観点からは、シールドトンネル間の壁部の除去範囲を必要最小限となる小開口にすることが望ましい。しかし、従来のトンネル施工技術では、シールドトンネル同士の連結部である「分合流拡幅部」をシールドトンネルの縦断方向に沿って施工していたため、その施工範囲が大規模となり、初めから大開口になる問題があった。   Further, from the viewpoint of reducing the influence on the ground surface, it is desirable to make the opening small enough to minimize the removal range of the wall portion between the shield tunnels. However, with the conventional tunnel construction technology, the “split and widened part”, which is the connecting part between the shield tunnels, was constructed along the longitudinal direction of the shield tunnel. There was a problem.

よって、本発明の課題は、分合流拡幅部の施工に際し、必要最小限の小開口となる横坑を、シールドトンネルの縦断方向に間隔をおいて複数施工する工法を採用することで、地表面への影響を可能な限り小さくすることができ、しかも、分合流拡幅部を予め形成しておくことで、合流させるシールドトンネルの工期短縮等も併せて図ることができる技術を提供することである。   Therefore, the object of the present invention is to adopt a construction method of constructing a plurality of horizontal shafts that are the minimum necessary small openings at intervals in the longitudinal direction of the shield tunnel when constructing the split and widened portion. It is possible to provide a technique that can reduce the influence on the shield tunnel as much as possible, and can shorten the work period of the shield tunnel to be joined by forming the split and widening portion in advance. .

以上の課題を解決するため、請求項1に記載の発明は、
トンネル本線からの分岐部分または合流部分となる分合流拡幅部の断面空間を構築するトンネルの拡幅部施工方法であって、
前記分合流拡幅部においてトンネル本線側から横坑を掘削する横坑掘削工程と、
掘削した横坑内の覆工躯体を構築する躯体構築工程と、を有し、
前記横坑掘削工程では、トンネル本線の縦断方向に間隔をおいて複数の先行坑を掘削する先行坑掘削工程と、それら各先行坑間に後行坑をそれぞれ掘削する後行坑掘削工程とを行うことを特徴とする。
In order to solve the above problems, the invention described in claim 1
A tunnel widening part construction method for constructing a cross-sectional space of a split and widened part that becomes a branching part or a joining part from a tunnel main line,
A side pit excavation step of excavating a side pit from the tunnel main line side in the merging and widening portion;
A housing construction process for constructing a lining housing in the excavated horizontal shaft,
In the horizontal pit excavation process, a preceding mine excavation process for excavating a plurality of preceding mines at intervals in the longitudinal direction of the tunnel main line, and a subsequent mine excavation process for excavating a subsequent mine between each of the preceding mine shafts. It is characterized by performing.

請求項1記載の発明によれば、横坑掘削工程では、トンネル本線の縦断方向に間隔をおいて複数の先行坑を掘削する先行坑掘削工程と、それら各先行坑間に後行坑をそれぞれ掘削する後行坑掘削工程とを行うので、分合流拡幅部の施工に際し、必要最小限の小開口となる横坑を、シールドトンネルの縦断方向に間隔をおいて複数施工する工法を採用することができる。これにより、地表面への影響を可能な限り小さくすることができる。さらに、分合流拡幅部を予め形成しておくことで、合流又は分岐させるトンネルは必要に応じていつでも施工可能となり、しかも、合流又は分岐させるトンネルの施工時には分合流拡幅部を施工しなくて済むので、工期短縮等も併せて図ることができる。   According to the first aspect of the present invention, in the horizontal pit excavation process, the preceding mine excavation process for excavating a plurality of preceding mines at intervals in the longitudinal direction of the tunnel main line, and the succeeding mine between each of the preceding mine, respectively. Since the excavation process will be carried out in the subsequent mine excavation, a construction method will be adopted in which multiple horizontal pits with the minimum necessary opening are installed at intervals in the longitudinal direction of the shield tunnel when constructing the split and merged widening section. Can do. Thereby, the influence on the ground surface can be made as small as possible. Furthermore, by forming the split and widened portion in advance, the tunnel to be merged or branched can be constructed at any time as needed, and it is not necessary to construct the split and widened portion when constructing the tunnel to be merged or branched. Therefore, the construction period can be shortened.

請求項2に記載の発明は、請求項1に記載のトンネルの拡幅部施工方法において、前記躯体構築工程では、前記先行坑掘削工程に続いて躯体構築を行う先行躯体構築工程と、前記後行坑掘削工程に続いて躯体構築を行う後行躯体構築工程とを含む、ことを特徴とする。   The invention according to claim 2 is the tunnel widening portion construction method according to claim 1, wherein in the frame building step, a preceding frame building step of building a frame following the preceding mine excavation step; And a subsequent frame construction step of constructing a frame following the mine excavation step.

請求項2記載の発明によれば、躯体構築工程では、先行坑掘削工程に続いて躯体構築を行う先行躯体構築工程と、後行坑掘削工程に続いて躯体構築を行う後行躯体構築工程とを含むので、トンネルの縦断方向に間隔をおいて先行坑の躯体構築を完了させた後に、後行坑の躯体構築を完了させることができる。これにより、トンネルの縦断方向に分割した形態の小開口の躯体を順次構築しつつ連結することができる。したがって、必要最小限の小開口で施工することができる。   According to the invention described in claim 2, in the building construction step, a preceding building construction step for building a building following the preceding mine excavation step, and a trailing building construction step for building a building following the following mine excavation step, Therefore, after the building construction of the preceding mine is completed at intervals in the longitudinal direction of the tunnel, the building construction of the succeeding mine can be completed. Thereby, it is possible to connect the small opening housings in the form divided in the longitudinal direction of the tunnel while sequentially constructing them. Therefore, construction can be performed with a minimum necessary small opening.

請求項3に記載の発明は、請求項1又は2に記載のトンネルの拡幅部施工方法において、前記先行坑掘削工程では、前記トンネル本線の縦断方向に少なくとも横坑一つ分の間隔をおいて掘削することを特徴とする。   According to a third aspect of the present invention, in the tunnel widening portion construction method according to the first or second aspect, in the preceding mine excavation step, at least one horizontal pit is spaced in the longitudinal direction of the main tunnel. It is characterized by excavation.

請求項3記載の発明によれば、先行坑掘削工程において、トンネル本線の縦断方向に少なくとも横坑一つ分の間隔をおいて掘削することで、先行坑を十分に間隔をおいて掘削することができる。これにより、地山(改良地盤)を厚く残して掘削することが可能になるので、安全性並びに施工性の向上を図ることができる。   According to the invention described in claim 3, in the preceding mine excavation step, the preceding mine is excavated at a sufficient interval by excavating at least one horizontal pit in the longitudinal direction of the main tunnel. Can do. As a result, excavation can be performed while leaving the natural ground (improved ground) thick, so that safety and workability can be improved.

本発明によれば、分合流拡幅部の施工に際し、必要最小限の小開口となる横坑を、トンネルの縦断方向に間隔をおいて複数施工する工法を採用することで、地表面への影響を可能な限り小さくすることができ、しかも、分合流拡幅部を予め形成しておくことで、合流させるトンネルの工期短縮等も併せて図ることができる。   According to the present invention, in the construction of the merging and widening portion, by adopting a construction method of constructing a plurality of horizontal shafts that are the minimum necessary small openings at intervals in the longitudinal direction of the tunnel, the influence on the ground surface Can be made as small as possible. Moreover, by forming the split and widened portion in advance, it is possible to shorten the construction period of the tunnel to be joined.

(実施の形態)
以下、図面を参照し、本発明の最良の実施形態について説明する。
図1は、トンネル本線Tからの分岐部分または合流部分となる分合流拡幅部Kの概略構造を示す斜視図である。図2(a)〜図3(f)は、図1に示す分合流拡幅部Kの施工手順を示す概略斜視図(工程図)である。図4〜図15は、分合流拡幅部Kの具体的施工手順を示す工程図である。
(Embodiment)
Hereinafter, the best embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a perspective view showing a schematic structure of a split and merge widened portion K that becomes a branching part or a joining part from the tunnel main line T. FIG. FIG. 2A to FIG. 3F are schematic perspective views (process drawings) showing a construction procedure of the split and merge widened portion K shown in FIG. 4-15 is process drawing which shows the specific construction procedure of the division | segmentation merge widening part K. FIG.

まず図1〜図3を参照して、トンネル本線Tからの分岐部分または合流部分となる分合流拡幅部Kの断面空間を構築するトンネルの拡幅部施工方法について説明する。この実施の形態では、図2(a)に示すように、構築すべき分合流拡幅部Kを含む地山Gに対して地盤改良工法により改良地盤G1を施工する地盤改良工程と、図2(b)、(c)に示すように、分合流拡幅部Kの領域においてトンネル本線T側から横坑1、2、3(先行坑1、2、後行坑3)を掘削する横坑掘削工程と、図3に示すように掘削した先行坑1、2内の覆工躯体4、及び後行坑3内の覆工躯体5を構築する躯体構築工程とを行う。   First, with reference to FIGS. 1 to 3, a tunnel widening portion construction method for constructing a cross-sectional space of a split and widened portion K that becomes a branching portion or a merging portion from the tunnel main line T will be described. In this embodiment, as shown in FIG. 2 (a), a ground improvement process for constructing an improved ground G1 by a ground improvement method for a ground mountain G including a split and widened portion K to be constructed, and FIG. As shown in b) and (c), the side shaft excavation process for excavating side shafts 1, 2, and 3 (leading shafts 1, 2, and subsequent shafts 3) from the tunnel main line T side in the region of the split and widened portion K Then, as shown in FIG. 3, a skeleton construction process for constructing the lining housing 4 in the preceding pits 1 and 2 and the lining housing 5 in the succeeding mine 3 is performed.

そして、横坑掘削工程では、図2(b)、(c)に示すように、トンネル本線Tの縦断方向(トンネル軸方向)に間隔をおいて複数の先行坑1、2を掘削する先行坑掘削工程と、図3(e)に示すように、それら各先行坑間に後行坑3をそれぞれ掘削する後行坑掘削工程とを行う。   In the horizontal excavation process, as shown in FIGS. 2B and 2C, the preceding mine excavating a plurality of preceding mines 1 and 2 at intervals in the longitudinal direction of the tunnel main line T (tunnel axis direction). As shown in FIG. 3 (e), the excavation process and the subsequent mine excavation process for excavating the subsequent mine 3 between each preceding mine are performed.

また、躯体構築工程では、図3(d)に示すように、先行坑掘削工程に続いて覆工躯体4の構築を行う先行躯体構築工程と、図3(e)に示すように、後行坑掘削工程に続いて覆工躯体5の構築を行う後行躯体構築工程と、を行う。以上の行程を繰り返して図1示す分合流拡幅部Kを施工する。ここで、先行坑掘削工程では、トンネル本線Tの縦断方向に少なくとも横坑一つ分の間隔をおいて掘削することが望ましい。勿論、横坑二つ分の間隔をおいて掘削することもできる。   In addition, in the case construction process, as shown in FIG. 3 (d), a preceding case construction process in which the lining case 4 is constructed following the preceding mine excavation process, and as shown in FIG. Following the mine excavation process, a follow-up chassis construction process for constructing the lining chassis 5 is performed. The above-described process is repeated to construct the merging and widening portion K shown in FIG. Here, in the preceding mine excavation process, it is desirable to excavate at least one horizontal pit in the longitudinal direction of the tunnel main line T. Of course, it is also possible to excavate at intervals of two horizontal shafts.

この実施の形態における分合流拡幅部の施工(全体概要)は、次の手順にて行うことが好ましい。なお、数値等は一例である。
(1)止水注入…有機系ロングゲルタイム材料によるゾーン止水注入。
(2)先行部1ブロック掘削…幅4.5mにてNATM工法による横坑掘削。
(3)先行部2ブロック掘削…隣接した区間を幅4.5mにてNATM工法による横坑掘削。
(4)先行躯体構築…横坑掘削部(幅9.0m)に幅6.0mにて躯体構築。
(5)後行部掘削…先行部躯体構築完了後、先行部掘削間隔4.5mを掘削。
(6)後行部躯体構築…先行部躯体構築区間7.5mを躯体構築。
(7)躯体完成
The construction (overall outline) of the merging and widening portion in this embodiment is preferably performed by the following procedure. In addition, a numerical value etc. are an example.
(1) Water stop injection: Zone water stop injection with organic long gel time material.
(2) 1 block excavation in the leading part: Horizontal excavation by the NATM method with a width of 4.5 m.
(3) 2 block excavation in the leading part ... Horizontal excavation by the NATM method in the adjacent section with a width of 4.5 m.
(4) Predecessor structure construction ... The structure of the horizontal shaft excavation part (width 9.0m) is 6.0m wide.
(5) Trailing part excavation: After the construction of the leading part frame is completed, the leading part excavation interval of 4.5 m is excavated.
(6) Consecutive body building construction ... Building the preceding body building construction section 7.5m.
(7) Completed housing

次いで、図1〜図15を参照して各工程をより具体的に説明する。なお、図4〜図15は分合流拡幅部施工手順を示す工程図であり、各図において、(a)は分合流拡幅部の概略横断面図を、(b)はその概略縦断面図を示している。   Next, each step will be described more specifically with reference to FIGS. 4 to 15 are process diagrams showing the construction procedure of the split and widened portion. In each figure, (a) is a schematic cross-sectional view of the split and widened portion, and (b) is a schematic vertical cross-sectional view thereof. Show.

(イ)止水注入工
図1(a)に示す改良地盤G1の施工に際しては、図4(a)、(b)に示すように、トンネル本線T内から既存の止水注入工法により施工する。この止水注入工法では、トンネル本線T内の高所作業車15上に配置した高所用ボーリングマシン16、及び低所用ボーリングマシン17等により、トンネル本線Tの外側の地盤Gを削孔して多数の注入孔18を形成しつつ、止水材(地盤改良材)を注入する。この地盤改良材としては、例えば有機系ロングゲルタイム等が好適に用いられるが、他の公知の地盤改良材を用いることもできる。
(A) Water stop injection construction When the improved ground G1 shown in FIG. 1 (a) is constructed, as shown in FIGS. 4 (a) and 4 (b), construction is performed from the tunnel main line T by the existing water stop injection construction method. . In this water stop pouring method, the ground G outside the tunnel main line T is drilled by the boring machine 16 for the high place and the boring machine 17 for the low place placed on the high work vehicle 15 in the main line T of the tunnel. The water-stopping material (ground improvement material) is injected while forming the injection hole 18. As this ground improvement material, for example, organic long gel time is preferably used, but other known ground improvement materials can also be used.

(ロ)先行坑1上半施工
図4に示す地盤改良行程を終えたら、図5(a)、(b)に示すように、先行坑1の上半施工を行う。この上半施工では、例えば0.4m3クラスブレーカ等の掘削機19及びエレクター台車20等を用いてNATM工法により、支保工21を建て込みつつ掘削して施工する。ここでは、例えば1m当たりの施工サイクルとして、掘削・ずり出し、支保工建て込み、コンクリート吹き付けが行われる。なお、この実施の形態では図5(b)に示すように、A1=9.0m、A2=4.5mとして施工される。
(B) The first half construction of the preceding mine 1 After the ground improvement process shown in FIG. 4 is completed, the first half construction of the preceding mine 1 is performed as shown in FIGS. In this upper half construction, excavation equipment 19 such as a 0.4 m3 class breaker and an erector carriage 20 are used to excavate and construct the support work 21 while building the support work 21 by the NATM construction method. Here, for example, as a construction cycle per 1 m, excavation / extrusion, support construction, and concrete spraying are performed. In this embodiment, as shown in FIG. 5B, construction is performed with A1 = 9.0 m and A2 = 4.5 m.

(ハ)先行坑1上半上部施工
先行坑1上半施工に続き、図6(a)、(b)に示すように、NATM工法により先行坑1の上半上部施工を行う。ここでは、掘削機19により、先行坑1の上半上部掘削、吹き付けロボット22を用いた掘削壁面へのコンクリート吹き付け工程、クローラドリル23を用いたロックボルト24(図7参照)の打設工程等を行う。なお、この上半上部施工では、1m当たりの施工サイクルとして、掘削・ずり出し、支保工建て込み、コンクリート吹き付け、ロックボルト打設が行われる。
(C) The upper half of the preceding mine 1 The upper half of the preceding mine 1 is constructed by the NATM method as shown in FIGS. Here, the excavator 19 is used to excavate the upper half of the leading mine 1, the concrete spraying process to the excavation wall surface using the spraying robot 22, the process of placing the lock bolt 24 (see FIG. 7) using the crawler drill 23, and the like. I do. In this upper half upper construction, excavation / push-out, support construction, concrete spraying, and rock bolting are performed as a construction cycle per 1 m.

(ニ)先行坑1受桁設置工
先行坑1の上半上部施工を終えたら、図7に示すように、先行坑1の受桁設置工を行う。ここでは、例えば1t電動チェーンブロック(電動CB)25を用い、受桁26を設置、あるいは盛り換えて設置する。その際、受桁26を支持する仮設のH鋼27も併せて設置すると共に盛り換え時には取り外す作業を行う。
(D) Leading pit 1 girder installation work After the upper half upper construction of the preceding mine 1 is finished, as shown in FIG. Here, for example, a 1t electric chain block (electric CB) 25 is used, and the receiving girder 26 is installed or installed in a rearranged manner. At that time, a temporary H steel 27 for supporting the receiving beam 26 is also installed and removed at the time of replacement.

なお、先行坑2の施工は、上記(ロ)〜(ニ)の工程と同様の作業を行うことで施工できる。   In addition, the construction of the preceding mine 2 can be performed by performing the same work as the processes (b) to (d) above.

(ホ)先行坑1、2下半施工
この先行坑1、2の下半施工では、図8に示すように、バックホウ28を用いて掘削施工するが、基本的には(イ)〜(ハ)の工程を繰り返すことで施工することができる。
(E) Lower half construction of preceding mine 1, 2 In the lower half construction of preceding mine 1, 2, excavation work is performed using backhoe 28 as shown in FIG. It can be constructed by repeating the process of).

(ヘ)先行坑躯体構築
この先行坑躯体構築時において、底版の施工では、図9に示すように、均しコンクリート31、底版防水工32を施工してから底版工33を施工する。側壁の施工では、仮側壁34の内側に側壁防水工35を施工し、その内側に側壁工36を施工する。床版工37では、床版防水工38の外に空洞充填工39を施工する。
(F) Construction of preceding mine body At the time of construction of the preceding mine body, in the construction of the bottom plate, as shown in FIG. 9, the leveling concrete 31 and the bottom plate waterproofing work 32 are constructed, and then the bottom printing work 33 is constructed. In the construction of the side wall, a side wall waterproofing work 35 is constructed inside the temporary side wall 34, and a side wall construction 36 is constructed inside thereof. In the floor slab worker 37, a cavity filling worker 39 is constructed outside the floor slab waterproofer 38.

なお、躯体1カ所における施工手順としては、1.均しコンクリート、2.仮側壁、防水工、3.底版工、4.側壁坑、5.床版工、防水工、6.空洞充填工、の順序とすることが工程管理上からも望ましい。   In addition, as construction procedure in one place of the frame, 1. Leveled concrete, 2. 2. Temporary side wall, waterproof work Bottom platemaker, 4. Side wall pits, 5. Floor slab, waterproofing, 6. From the viewpoint of process control, it is desirable to adopt the order of cavity filling.

(ト)後行坑上半施工
この後行坑3の上半施工は、図10に示すように、先行坑間に施工する点を除けば、上記(イ)〜(ハ)の工程の繰り返しで施工できるので、ここでは符号を示してその説明を簡略化する。
(G) The upper half construction of the following mine The upper half construction of the following mine 3 is the repetition of the steps (b) to (c) except for the point of construction between the preceding mine as shown in FIG. Therefore, the description is simplified here by showing the reference numerals.

(チ)後行坑上半上部施工
この後行坑3の上半上部施工も、図11に示すように、先行坑間に施工する点を除けば、上記(イ)〜(ニ)の工程の繰り返しで施工できるので、ここでは符号を示してその説明を簡略化する。
(H) The upper half upper construction of the succeeding mine The upper half upper construction of the following mine 3, as shown in FIG. Therefore, the description is simplified by showing the reference numerals.

(リ)後行坑受桁設置(受け替え梁設置)
図12に示すように、後行坑3の受桁設置工を行う。ここでも、上記(ニ)で示したように、電動チェーンブロック(電動CB)25を用い、受桁26を設置、あるいは盛り換えて設置する。その際、受桁26を支持する仮設のH鋼27も併せて設置する。
(L) Installation of trailing girder girder (replacement beam installation)
As shown in FIG. 12, the girder installation work for the trailing mine 3 is performed. Also here, as shown in (d) above, using the electric chain block (electric CB) 25, the receiving girder 26 is installed or installed in a rearranged manner. At that time, a temporary H steel 27 for supporting the receiving beam 26 is also installed.

(ヌ)後行坑下半施工
この後行坑下半施工も、図13に示すように、先行坑間に施工する点を除けば、上記(イ)〜(ロ)の工程の繰り返しで施工できるので、ここでは符号を示してその説明を簡略化する。
(Nu) Subsequent mine half construction As shown in FIG. 13, this mine below half construction is repeated by repeating the steps (b) to (b) except for the construction between the preceding mine. Since this is possible, the reference numeral is shown here to simplify the description.

後行坑躯体構築
この後行坑躯体構築時において、底版の施工では、図14及び図15に示すように、均しコンクリート31、底版防水工32を施工してから底版工33を施工する。側壁の施工では、仮側壁34の内側に側壁防水工35を施工し、その内側に側壁工36を施工する。床版工37では、床版防水工38の外に空洞充填工39を施工する。なお、この躯体1カ所における施工手順としては、先行坑1,2の躯体構築と同様に、1.均しコンクリート、2.仮側壁、防水工、3.底版工、4.側壁坑、5.床版工、防水工、6.空洞充填工、の順序とすることが望ましい。
Subsequent mine body construction At the time of construction of the following mine body, in the construction of the bottom plate, as shown in FIGS. 14 and 15, the leveling concrete 31 and the bottom plate waterproofing work 32 are constructed, and then the bottom printing work 33 is constructed. In the construction of the side wall, a side wall waterproofing work 35 is constructed inside the temporary side wall 34, and a side wall construction 36 is constructed inside thereof. In the floor slab worker 37, a cavity filling worker 39 is constructed outside the floor slab waterproofer 38. In addition, as a construction procedure at this one place, as in the case of the construction of the preceding pits 1 and 2, 1. Leveled concrete, 2. 2. Temporary side wall, waterproof work Bottom platemaker, 4. Side wall pits, 5. Floor slab, waterproofing, 6. It is desirable that the order of the cavity filling work.

この実施形態によれば、分合流拡幅部Kの施工に際し、必要最小限の小開口となる横坑1、2、3を、トンネル本線Tの縦断方向に間隔をおいて複数施工する工法を採用することで、地表面への影響を可能な限り小さくすることができ、しかも、分合流拡幅部Kを予め形成しておくことで、合流又は分岐させるランプトンネルの工期短縮等も併せて図ることができる。   According to this embodiment, when constructing the merging and widening portion K, a construction method is employed in which a plurality of horizontal shafts 1, 2, and 3 that are the minimum necessary openings are spaced apart in the longitudinal direction of the main tunnel T. By doing so, the influence on the ground surface can be reduced as much as possible, and the construction time of the ramp tunnel to be merged or branched can be shortened by forming the split and widening portion K in advance. Can do.

また、躯体構築工程では、先行坑掘削工程に続いて躯体構築を行う先行躯体構築工程と、後行坑掘削工程に続いて躯体構築を行う後行躯体構築工程と、を行うので、トンネル本線Tの縦断方向に間隔をおいて先行坑1、2の躯体4の構築を完了させた後に、後行坑3の躯体5の構築を完了させることができる。これにより、トンネルの縦断方向に分割した形態の小開口hの躯体を順次構築しつつ連結することができる。したがって、必要最小限の小開口hで施工することができる。   Moreover, in the skeleton construction process, the preceding skeleton construction process that performs the skeleton construction following the preceding mine excavation process and the subsequent skeleton construction process that performs the skeleton construction following the subsequent mine excavation process are performed. After completing the construction of the chassis 4 of the preceding mine 1 and 2 with an interval in the longitudinal direction, the construction of the chassis 5 of the succeeding mine 3 can be completed. Thereby, the frame | skeleton of the small opening h of the form divided | segmented into the vertical direction of the tunnel can be connected, constructing sequentially. Therefore, it can be constructed with the minimum necessary small opening h.

また、先行坑掘削工程において、トンネル本線の縦断方向に少なくとも横坑一つ分の間隔をおいて掘削することで、先行坑を十分に間隔をおいて掘削することができる。これにより、地山(改良地盤)を厚く残して掘削することが可能になるので、安全性並びに施工性の向上を図ることができる。   Further, in the preceding mine excavation step, the preceding mine can be excavated with a sufficient interval by excavating at least one horizontal pit in the longitudinal direction of the main tunnel. As a result, excavation can be performed while leaving the natural ground (improved ground) thick, so that safety and workability can be improved.

本発明の実施形態に係る分合流拡幅部の概略構造を示す斜視図。The perspective view which shows schematic structure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の施工手順を示す概略斜視図。The schematic perspective view which shows the construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の施工手順を示す概略斜視図。The schematic perspective view which shows the construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention. 本発明の実施形態に係る分合流拡幅部の具体的施工手順を示す工程図。Process drawing which shows the concrete construction procedure of the division | segmentation merge widening part which concerns on embodiment of this invention.

符号の説明Explanation of symbols

1 先行坑(横坑)
2 先行坑(横坑)
3 後行坑(横坑)
4 覆工躯体
5 覆工躯体
T トンネル本線
K 分合流拡幅部
G 地盤
G1 改良地盤
h 小開口
1 Leading mine (horizontal mine)
2 Leading mine (horizontal mine)
3 Back pit (horizontal mine)
4 Lining enclosure 5 Lining enclosure T Tunnel main line K Split junction widening part G Ground G1 Improved ground h Small opening

Claims (3)

トンネル本線からの分岐部分または合流部分となる分合流拡幅部の断面空間を構築するトンネルの拡幅部施工方法であって、
前記分合流拡幅部においてトンネル本線側から横坑を掘削する横坑掘削工程と、
掘削した横坑内の覆工躯体を構築する躯体構築工程と、を有し、
前記横坑掘削工程では、トンネル本線の縦断方向に間隔をおいて複数の先行坑を掘削する先行坑掘削工程と、それら各先行坑間に後行坑をそれぞれ掘削する後行坑掘削工程とを行うことを特徴とするトンネルの拡幅部施工方法。
A tunnel widening part construction method for constructing a cross-sectional space of a split and widened part that becomes a branching part or a joining part from a tunnel main line,
A side pit excavation step of excavating a side pit from the tunnel main line side in the merging and widening portion;
A housing construction process for constructing a lining housing in the excavated horizontal shaft,
In the horizontal pit excavation process, a preceding mine excavation process for excavating a plurality of preceding mines at intervals in the longitudinal direction of the tunnel main line, and a subsequent mine excavation process for excavating a subsequent mine between each of the preceding mine shafts. A method for constructing a widened portion of a tunnel, characterized in that it is performed.
前記躯体構築工程では、前記先行坑掘削工程に続いて躯体構築を行う先行躯体構築工程と、前記後行坑掘削工程に続いて躯体構築を行う後行躯体構築工程とを含む、ことを特徴とする請求項1に記載のトンネルの拡幅部施工方法。   The skeleton construction step includes a preceding skeleton construction step for constructing a skeleton following the preceding mine excavation step, and a subsequent skeleton construction step for constructing a skeleton following the subsequent mine excavation step. The tunnel widening part construction method according to claim 1. 前記先行坑掘削工程では、前記トンネル本線の縦断方向に少なくとも横坑一つ分の間隔をおいて掘削することを特徴とする、請求項1又は2に記載のトンネルの拡幅部施工方法。   The method for constructing a widened portion of a tunnel according to claim 1 or 2, wherein, in the preceding mine excavation step, excavation is performed at an interval of at least one horizontal pit in the longitudinal direction of the tunnel main line.
JP2008013833A 2008-01-24 2008-01-24 Method of constructing wide section of tunnel Pending JP2009174185A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008013833A JP2009174185A (en) 2008-01-24 2008-01-24 Method of constructing wide section of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008013833A JP2009174185A (en) 2008-01-24 2008-01-24 Method of constructing wide section of tunnel

Publications (1)

Publication Number Publication Date
JP2009174185A true JP2009174185A (en) 2009-08-06

Family

ID=41029556

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008013833A Pending JP2009174185A (en) 2008-01-24 2008-01-24 Method of constructing wide section of tunnel

Country Status (1)

Country Link
JP (1) JP2009174185A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094656A (en) * 2010-12-01 2011-06-15 中国水电顾问集团华东勘测设计研究院 Grouting method for avoiding perforating steel lining
JP2013221241A (en) * 2012-04-12 2013-10-28 Ohbayashi Corp Tunnel widening method and tunnel widening structure
JP2013221240A (en) * 2012-04-12 2013-10-28 Ohbayashi Corp Tunnel widening method and tunnel widening structure
JP2014077283A (en) * 2012-10-10 2014-05-01 Nippon Civic Engineering Consultant Co Ltd Widened part construction method of tunnel and structure of tunnel widened part

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5384332A (en) * 1976-12-29 1978-07-25 Kajima Corp Method of expanding shield tunnel
JPH01163399A (en) * 1987-12-18 1989-06-27 Hazama Gumi Ltd Method of shield excavation construction
JPH07269275A (en) * 1994-03-30 1995-10-17 Taisei Corp Construction method of underground space
JP2003129788A (en) * 2001-10-26 2003-05-08 Daiho Constr Co Ltd Construction method for branch tunnel and structure of branch part of branch tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5384332A (en) * 1976-12-29 1978-07-25 Kajima Corp Method of expanding shield tunnel
JPH01163399A (en) * 1987-12-18 1989-06-27 Hazama Gumi Ltd Method of shield excavation construction
JPH07269275A (en) * 1994-03-30 1995-10-17 Taisei Corp Construction method of underground space
JP2003129788A (en) * 2001-10-26 2003-05-08 Daiho Constr Co Ltd Construction method for branch tunnel and structure of branch part of branch tunnel

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094656A (en) * 2010-12-01 2011-06-15 中国水电顾问集团华东勘测设计研究院 Grouting method for avoiding perforating steel lining
JP2013221241A (en) * 2012-04-12 2013-10-28 Ohbayashi Corp Tunnel widening method and tunnel widening structure
JP2013221240A (en) * 2012-04-12 2013-10-28 Ohbayashi Corp Tunnel widening method and tunnel widening structure
JP2014077283A (en) * 2012-10-10 2014-05-01 Nippon Civic Engineering Consultant Co Ltd Widened part construction method of tunnel and structure of tunnel widened part

Similar Documents

Publication Publication Date Title
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN107514262A (en) The construction method of shield piping lane
CN104632227A (en) Subway station excavation technology of single-layer beam arch structure
JP4132442B2 (en) Tunnel construction method
JP2007303155A (en) Construction method of underground cavity and tunnel construction method
JP2007308995A (en) Under path and construction method for the same
JP2009174185A (en) Method of constructing wide section of tunnel
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
KR100898969B1 (en) Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof
KR20140082343A (en) Method for constructing tunnel by using pipe
KR101612522B1 (en) Construction method for tunneling
JP4104781B2 (en) Construction method of underground joint structure
CN109594993A (en) A kind of tunnel enlarging construction method in the case of uninterrupted traffic
JP5246426B2 (en) Construction method of underground structure
JPH05280296A (en) Large scale underground structure and construction method thereof
JP6019690B2 (en) Tunnel widening method
KR20200026221A (en) Environmentally-friendly enlarged tunnel with integrated substructure and tunnel portal and construction method thereof
JP4485373B2 (en) Construction method of tunnel junction
JP2656892B2 (en) Underground structure construction method and continuous underground wall construction method
JP2008255614A (en) Support structure of natural ground and support method of natural ground
KR101612527B1 (en) Construction method for tunneling
JP4665834B2 (en) Side-by-side tunnel structure and its construction method
KR100661498B1 (en) Construction method of concrete structures in parallel with blasting in tunnel
JP6019689B2 (en) Tunnel widening method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110105

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20111019

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111025

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20120313