JP2014134060A - Floor slab replacement method - Google Patents

Floor slab replacement method Download PDF

Info

Publication number
JP2014134060A
JP2014134060A JP2013003808A JP2013003808A JP2014134060A JP 2014134060 A JP2014134060 A JP 2014134060A JP 2013003808 A JP2013003808 A JP 2013003808A JP 2013003808 A JP2013003808 A JP 2013003808A JP 2014134060 A JP2014134060 A JP 2014134060A
Authority
JP
Japan
Prior art keywords
floor slab
main girder
steel
existing
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013003808A
Other languages
Japanese (ja)
Other versions
JP5848716B2 (en
Inventor
Kazuo Takase
和男 高瀬
Tomoyuki Takao
智之 高尾
Mitsunori Shigeta
光則 重田
Sadanori Itagaki
定範 板垣
Yoshihiko Nakamura
善彦 中村
Seiji Okada
誠司 岡田
Shiro Saito
史朗 齊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KOMAIHALTEC Inc
IHI Infrastructure Systems Co Ltd
Original Assignee
KOMAIHALTEC Inc
IHI Infrastructure Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KOMAIHALTEC Inc, IHI Infrastructure Systems Co Ltd filed Critical KOMAIHALTEC Inc
Priority to JP2013003808A priority Critical patent/JP5848716B2/en
Publication of JP2014134060A publication Critical patent/JP2014134060A/en
Application granted granted Critical
Publication of JP5848716B2 publication Critical patent/JP5848716B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

PROBLEM TO BE SOLVED: To shorten a period necessary for traffic regulation.SOLUTION: In a bridge configurated so that main girders 2 are provided on sub-structures 1a, 1b and RC floor slabs 5 are mounted on upper sides of upper flanges 2a of the main girders 2, a new steel floor slab 11 and a side floor slab 15 are mounted on the upper part of a web 2b of the main girder 2 on a lower position of the RC floor slabs 5. Next, the RC floor slabs 5 are removed at a time to expose the new steel floor slab 11 and the side floor slab 15, a pavement is laid on the upper surface thereof, the new steel floor slab 11 and the side floor slab 15 are jacked up along with the main girder 2, and thus the height position of an upper surface of the pavement is returned to its original state to a height position of a pavement laid on the RC floor slabs 5 before the removal. A period necessary for traffic regulation is shortened by setting the traffic regulation to be from removal work of the existing RC floor slabs 5 and pavement work of the upper surfaces of the new steel floor slab 11 and the side floor slab 15 to jack-up work.

Description

本発明は、老朽化した既設床版を新設床版に取り替える工法に関するものである。   The present invention relates to a method for replacing an old floor slab with a new floor slab.

近年、都市内高速道路等の鉄筋コンクリート床版(以下、RC床版と記す)を用いた橋梁(高架橋を含む)におけるRC床版の老朽化が問題となってきている。   In recent years, aging of RC slabs in bridges (including viaducts) using reinforced concrete slabs (hereinafter referred to as RC slabs) such as urban expressways has become a problem.

そこで、上記老朽化した既設のRC床版を、新しい床版に取り替えることが考えられてきている。   Therefore, it has been considered to replace the old RC floor slab with a new one.

老朽化したRC床版を新設床版に取り替える手法の1つとしては、たとえば、先ず、鋼桁上に設けられている非合成構造のRC床版を、長手方向1.5〜2mごとに全幅切断する。次に、上記切断された床版1個を鋼桁から引き剥して撤去し、その床版撤去跡の鋼桁上面を整備してから、新規プレキャストPC床版を搬入して敷設する。その後は、この切断された床版1個ごとの撤去と敷設を繰り返して施工するようにする手法が、従来提案されている。   One way to replace an aging RC floor slab with a newly installed floor slab is, for example, that the RC floor slab with a non-synthetic structure provided on a steel girder is first widened every 1.5-2 m in the longitudinal direction. Disconnect. Next, one of the cut floor slabs is peeled off and removed from the steel girder, and the top surface of the steel girder of the floor slab removal trace is prepared, and then a new precast PC floor slab is carried in and laid. Thereafter, a method has been proposed in which the removal and laying of each cut floor slab is repeated for construction.

かかる手法によれば、鋼桁の上載荷重はほとんど変わらないため、鋼桁に新たな変形が生じることが少ない。したがって、床版の取り替え中に鋼桁の応力状態が激変するのを防止することができるとされている(たとえば、特許文献1参照)。   According to such a method, the upper load of the steel girder is hardly changed, so that the steel girder is less likely to be newly deformed. Therefore, it is said that the stress state of the steel girder can be prevented from changing drastically during replacement of the floor slab (see, for example, Patent Document 1).

又、老朽化したRC床版を新設床版に取り替えるための別の手法としては、橋脚上に架設されている既設のコンクリート製床版の上側に、路面を構成する新設の鋼製床版を設置し、この鋼製床版の下面と橋脚との間に鋼桁を設置する。これにより、既設橋を跨ぐ形で新設鋼製床版橋梁を架設するようにする手法が、従来提案されている(たとえば、特許文献2参照)。   Another method for replacing an old RC floor slab with a new floor slab is to install a new steel floor slab that constitutes the road surface above the existing concrete slab installed on the pier. Install and install a steel girder between the bottom of this steel slab and the pier. Thus, a method has been proposed in the past in which a new steel floor slab bridge is laid over the existing bridge (see, for example, Patent Document 2).

特許第2578305号公報Japanese Patent No. 2578305 特許第3841958号公報Japanese Patent No. 3841958

ところが、上記特許文献1に示された手法は、既設のRC床版の部分的な撤去と、その床版撤去跡に対する新規プレキャストPC床版の敷設を順次繰り返すようにしてあるため、工事期間中は、ほぼ全期間に亘り交通規制を行う必要が生じる。そのために、長期の交通規制が必要になる。   However, the method disclosed in Patent Document 1 repeats the partial removal of an existing RC floor slab and the laying of a new precast PC floor slab sequentially on the floor slab removal trace. Therefore, it is necessary to regulate traffic for almost the entire period. For that purpose, long-term traffic regulation is necessary.

又、上記特許文献2に示された手法は、既設橋を跨ぐ形で新設鋼製床版橋梁を架設するため、該新設鋼製床版橋梁を架設した後の既設のコンクリート製床版を解体する期間の交通規制は不要である。   In addition, the technique disclosed in Patent Document 2 described above disassembles an existing concrete floor slab after the new steel floor slab bridge has been installed in order to construct a new steel floor slab bridge across the existing bridge. There is no need to regulate traffic during the period.

しかし、上記新設鋼製床版橋梁を架設する期間は、交通規制が必要であり、この橋梁の架設に要する期間は、通常、解体に要する期間よりも長くなる。そのため、この手法においても、交通規制が長期に亘り必要になる。   However, traffic regulation is necessary for the period of erection of the new steel floor slab bridge, and the period required for erection of this bridge is usually longer than the period required for dismantling. Therefore, this method also requires traffic regulation for a long time.

そこで、本発明は、老朽化した既設の床版を、新設の床版に取り替えることができ、しかも、交通規制が必要とされる期間の大幅な短縮化を図ることができる床版取り替え工法を提供しようとするものである。   Therefore, the present invention provides a floor slab replacement method that can replace an old floor slab with a new floor slab and that can greatly shorten the period when traffic regulation is required. It is something to be offered.

本発明は、上記課題を解決するために、請求項1に対応して、主桁の上側に取り付けられている既設の床版の下方で、主桁の上部に、新設の床版を取り付け、次に、上記既設の床版を撤去することで、新設の床版の上面を露出させ、次いで、上記新設の床版の上面の高さ位置が、上記既設の床版の上面の高さ位置まで原状復帰されるように、下部構造上で、該新設の床版を上記主桁と共にジャッキアップするようにする床版取り替え工法とする。   In order to solve the above-mentioned problem, the present invention, in correspondence with claim 1, attaches a new floor slab below the existing floor slab attached to the upper side of the main girder and above the main girder, Next, the upper surface of the new floor slab is exposed by removing the existing floor slab, and then the height position of the upper surface of the new floor slab is the height position of the upper surface of the existing floor slab. The new floor slab is jacked up together with the main girder on the lower structure so that it can be restored to its original state.

更に、上記構成において、新設の床版として、鋼床版を用いるようにする。   Further, in the above configuration, a steel slab is used as a new slab.

本発明の床版取り替え工法によれば、以下のような優れた効果を発揮する。
(1)老朽化した既設の床版を、新設の床版に取り替えることができる。
(2)この床版取り替え作業の際、上記新設の床版を主桁へ取り付ける作業を行う間は、既設の床版上での通行を継続して行わせることができる。よって、交通規制は、既設の床版の撤去作業から、新設の床版を主桁と共にジャッキアップする作業までとすることができて、交通規制が必要とされる期間を、従来の手法に比して大幅に短縮させることができる。
(3)新設の床版として、鋼床版を用いるようにすることにより、該鋼床版が既設の床版よりも軽量の場合、主桁及び下部構造に作用する荷重の軽減化を図ることが可能になるため、主桁や下部構造で負担する荷重を軽減させることで、該主桁や下部構造の劣化の進行を抑制する効果が期待できる。
According to the floor slab replacement method of the present invention, the following excellent effects are exhibited.
(1) An old floor slab can be replaced with a new floor slab.
(2) During this floor slab replacement operation, while the work for attaching the newly installed floor slab to the main girder is being performed, it is possible to continue the passage on the existing floor slab. Therefore, the traffic regulation can range from the removal work of the existing floor slab to the work of jacking up the new floor slab together with the main girder. Can be greatly shortened.
(3) By using a steel slab as a new floor slab, when the steel slab is lighter than the existing floor slab, the load acting on the main girder and the substructure should be reduced. Therefore, an effect of suppressing the progress of deterioration of the main girder and the lower structure can be expected by reducing the load applied to the main girder and the lower structure.

本発明の床版取り替え工法の実施の一形態における手順を示すもので、(a)は施工前の橋梁を示す橋軸方向に直角な面での概略断面図、(b)は(a)と同じ時点での概略切断側面図である。The procedure in one embodiment of the floor slab replacement method of the present invention is shown, (a) is a schematic sectional view in a plane perpendicular to the bridge axis direction showing the bridge before construction, (b) is (a) and It is a general | schematic cut side view at the same time. 図1(a)(b)に続く手順を示すもので、(a)は既設のRC床版の下方位置で主桁のウェブ同士の間に新設の鋼床版を取り付けた状態を示す図1(a)に対応する図、(b)は(a)と同じ時点での概略切断側面図である。FIGS. 1A and 1B show a procedure following FIG. 1A, in which FIG. 1A shows a state in which a newly installed steel deck is attached between webs of main girders at a position below an existing RC deck. The figure corresponding to (a), (b) is a schematic cut side view at the same time as (a). 図2(a)(b)に続く手順を示すもので、主桁のウェブにおける新設の鋼床版の取付位置と対応する高さ位置に側床版を取り付けた状態を示す図1(a)に対応する図である。FIG. 1 (a) shows the procedure following FIG. 2 (a) and FIG. 2 (b), and shows a state in which the side floor slab is attached at a height position corresponding to the attachment position of the newly installed steel floor slab in the main girder web. It is a figure corresponding to. 図3に続く手順を示すもので、(a)は既設のRC床版を撤去して、新設の鋼床版の上面を露出させた状態を示す図1(a)に対応する図、(b)は(a)と同じ時点での概略切断側面図である。FIG. 3 shows a procedure following FIG. 3, and (a) is a view corresponding to FIG. 1 (a) showing a state in which an existing RC floor slab is removed and an upper surface of a new steel floor slab is exposed; ) Is a schematic cut side view at the same time as (a). 図4(a)(b)に続く手順を示すもので、(a)は新設した鋼床版を、主桁と一緒にジャッキアップした状態を示す図1(a)に対応する図、(b)は(a)と同じ時点での概略切断側面図である。4 (a) and 4 (b) show a procedure corresponding to FIG. 1 (a) showing a state in which a newly installed steel deck is jacked up together with a main girder, (b) ) Is a schematic cut side view at the same time as (a).

以下、本発明を実施するための形態を図面を参照して説明する。   Hereinafter, embodiments for carrying out the present invention will be described with reference to the drawings.

図1(a)(b)乃至図5(a)(b)は本発明の床版取り替え工法の実施の一形態を示すものである。   FIGS. 1A, 1B to 5A, 5B show an embodiment of the floor slab replacement method of the present invention.

ここで、先ず、本発明の床版取り替え工法の適用対象の一例として、図1(a)(b)に示す橋梁の構成について概説する。   Here, first, as an example of an application target of the floor slab replacement method of the present invention, the configuration of the bridge shown in FIGS. 1A and 1B will be outlined.

上記橋梁は、都市内高速道路の鈑桁橋であり、橋軸方向に或る間隔で、上り車線La用と下り車線Lb用の下部構造(橋台又は橋脚)1aと1bが並べて設置されている。   The bridge is a girder bridge of a highway in a city, and lower structures (abutments or piers) 1a and 1b for an up lane La and a down lane Lb are arranged side by side at a certain interval in the bridge axis direction.

又、上記各下部構造1a,1bの径間に対応して橋軸方向に延びる主桁(鈑桁)2が、橋幅方向に複数、たとえば、図1(a)に示すように、上り車線La用と下り車線Lb用に、3つずつ配列してある。該各主桁2は、長手方向両端部が、上記下部構造1a,1bの上面に、支承3を介して支持させてある。   A plurality of main girders (girder beams) 2 extending in the bridge axis direction corresponding to the spans of the lower structures 1a and 1b are provided in the bridge width direction, for example, as shown in FIG. Three are arranged for the vehicle and for the down lane Lb. Each main girder 2 is supported at both ends in the longitudinal direction on the upper surfaces of the lower structures 1 a and 1 b via a support 3.

上記各主桁2のうち、橋幅方向に隣接する主桁2同士は、長手方向の複数個所を、橋幅方向に延びる横桁4で連結してある。これにより、上記主桁2と横桁4は、格子構造の構造体を形成するようにしてある。なお、該構造体には、上記主桁2と横桁4の他に、橋軸方向に対して斜め方向に延びる図示しない補強材を備える構成としてあってもよい。   Among the main girders 2, the main girders 2 adjacent to each other in the bridge width direction are connected at a plurality of positions in the longitudinal direction by horizontal girders 4 extending in the bridge width direction. Thus, the main beam 2 and the horizontal beam 4 form a lattice structure. In addition to the main girder 2 and the cross girder 4, the structure may be provided with a reinforcing material (not shown) extending obliquely with respect to the bridge axis direction.

上記主桁2の上フランジ2aの上側には、RC床版5が取り付けてあり、該RC床版5の上側に、車両走行面となる舗装6が設けてある。   An RC floor slab 5 is attached to the upper side of the upper flange 2 a of the main girder 2, and a pavement 6 serving as a vehicle running surface is provided on the upper side of the RC floor slab 5.

以上の構成としてある橋梁を対象として本発明の床版取り替え工法を実施する場合は、後述するように、上記既設のRC床版5の下方で各主桁2のウェブ2bの上部に新設の鋼床版7を取り付けた構成とするときに、該各主桁2に作用する死荷重が増大しても、該各主桁2が耐えられるようにするために、先ず、各主桁2の補強を行う。   When the floor slab replacement method of the present invention is implemented for the bridge having the above-described structure, as will be described later, a new steel is installed below the existing RC floor slab 5 and above the web 2b of each main girder 2. When the floor slab 7 is installed, in order to withstand each main girder 2 even if the dead load acting on each main girder 2 is increased, first, the reinforcement of each main girder 2 is performed. I do.

この各主桁2の補強は、図2(a)(b)に示すように、たとえば、予め強度計算等を実施し、その結果に基づいて設定される所定の主桁2の下フランジ2cに、橋軸方向に延びる下フランジ補強材8を取り付ける。更に、各主桁2の下側(上記下フランジ補強材8が取り付けてある主桁2については該下フランジ補強材8の下側)には、偏向具9を介してアウトケーブル10を設置して、張力を導入させるようにする。   As shown in FIGS. 2 (a) and 2 (b), for example, the reinforcement of each main girder 2 is performed in advance on the lower flange 2c of a predetermined main girder 2 that is set based on the result of strength calculation and the like. The lower flange reinforcing member 8 extending in the bridge axis direction is attached. Further, an out cable 10 is installed on the lower side of each main girder 2 (below the lower flange reinforcing material 8 for the main girder 2 to which the lower flange reinforcing material 8 is attached) via a deflecting tool 9. To introduce tension.

なお、図示してないが、上記各主桁2の下方に支保工の設置が可能な場合は、支保工で各主桁2を下方から支持することにより、上記したような主桁2に作用する死荷重の増加に対応させるようにしてもよい。   In addition, although not shown in figure, when installation of a supporting work is possible under each said main girder 2, it acts on the above-mentioned main girder 2 by supporting each main girder 2 from the bottom by supporting work. You may make it respond | correspond to the increase in the dead load to do.

上記のようにして主桁2の補強が終了した後は、既設のRC床版5の下方で、上記各主桁2のウェブ2bの上部位置に、図2(a)(b)に示すように、新設の鋼床版11を取り付ける。この際、上記各主桁2のウェブ2bの上部に取り付ける上記新設の鋼床版11の配置に対し、上記各主桁2に取り付けられている既存の横桁4や図示しない補強材が干渉する場合は、該既存の横桁4や図示しない補強材における上記鋼床版11と干渉する個所を切断してから、上記新設の鋼床版11の取り付けを行うようにするものとする。又、図2(a)に示すように、既存の横桁4を切断してから、上記新設の鋼床版11の配置と干渉しないように配置した新たな横桁4aにより、隣接する主桁2のウェブ2b同士を橋幅方向に連結する構成としてもよい。   After the reinforcement of the main girder 2 is completed as described above, as shown in FIGS. 2A and 2B, below the existing RC floor slab 5, at the upper position of the web 2 b of each main girder 2. A new steel slab 11 is attached. At this time, the existing horizontal girder 4 attached to each main girder 2 or a reinforcing material (not shown) interferes with the arrangement of the new steel deck 11 attached to the upper part of the web 2b of each main girder 2. In this case, the new steel floor slab 11 is attached after cutting a portion of the existing cross beam 4 or a reinforcing material (not shown) that interferes with the steel floor slab 11. Further, as shown in FIG. 2 (a), after the existing cross beam 4 is cut, the adjacent main girder is arranged by the new cross beam 4a arranged so as not to interfere with the arrangement of the new steel deck 11 described above. The two webs 2b may be connected in the bridge width direction.

上記各主桁2のウェブ2bの上部に上記新設の鋼床版11を取り付ける場合の具体的な手順は、以下のようにする。   The specific procedure for attaching the newly installed steel deck 11 to the upper part of the web 2b of each main girder 2 is as follows.

すなわち、上記主桁2間に取り付ける新設の鋼床版11は、橋幅方向に隣接する主桁2のウェブ2bの互いに対向する面に個別に取り付けるための一対の基部部材12と、該一対の基部部材12の間に取り付ける中床版部材13とからなる三分割構造としておく。   That is, the newly installed steel deck 11 attached between the main girders 2 includes a pair of base members 12 for individually attaching to the mutually opposing surfaces of the web 2b of the main girders 2 adjacent in the bridge width direction, A three-part structure comprising an intermediate floor slab member 13 attached between the base members 12 is provided.

上記したように新設の鋼床版11の取り付けに干渉する上記横桁4や図示しない補強材を撤去した状態とした各主桁2のウェブ2bの上部には、先ず、橋幅方向の片方の側面に、上記新設の鋼床版11の基部部材12を配置して、該基部部材12の上部寄りと下部寄りの2個所を、ボルト14と図示しないナットを用いて固定する。この際、上記上り車線Laと下り車線Lbの各3本ずつの主桁2のうち、橋幅方向の両側(外側)の2本の主桁2では、それぞれのウェブ2bにおける車線LaとLbの中央寄りの側面に、上記基部部材12を取り付けるようにする。又、上記各車線LaとLbのそれぞれ中央の主桁2は、ウェブ2bのいずれか一方の側面のみに、上記基部部材12を取り付けるようにする。   As described above, on the upper part of the web 2b of each main girder 2 in a state in which the horizontal girder 4 and the reinforcing material (not shown) that interfere with the installation of the new steel deck 11 are removed, The base member 12 of the new steel floor slab 11 is arranged on the side surface, and two portions near the upper part and the lower part of the base member 12 are fixed using bolts 14 and nuts (not shown). At this time, out of the three main girders 2 in each of the up lane La and the down lane Lb, the two main girders 2 on both sides (outside) in the bridge width direction have the lanes La and Lb in the respective webs 2b. The base member 12 is attached to the side surface near the center. The base girder 2 at the center of each of the lanes La and Lb is attached to the base member 12 only on one side surface of the web 2b.

次に、上記各主桁2のウェブ2bは、上記基部部材12が取り付けられた側面とは逆の側面側から、該基部部材12の上下中間部と対応する高さ位置を、橋軸方向の全長に亘り切断する。この場合は、上記主桁2のウェブ2bを切断しても、該主桁2の上フランジ2aに上方のRC床版5側より作用する荷重(死荷重及び活荷重)は、該主桁2のウェブ2bの上部から、上記基部部材12を経由して該ウェブ2bの下部へ伝えられるようになる。このため、上記のように主桁2のウェブ2bを切断した状態であっても、橋梁の運用、すなわち、上記既設のRC床版5の上での車両の通行を停止させる必要はない。   Next, the web 2b of each main girder 2 has a height position corresponding to the upper and lower intermediate portions of the base member 12 from the side surface opposite to the side surface to which the base member 12 is attached. Cut along the entire length. In this case, even if the web 2b of the main girder 2 is cut, the load (dead load and live load) acting on the upper flange 2a of the main girder 2 from the upper RC floor slab 5 side is the main girder 2 It is transmitted from the upper part of the web 2b to the lower part of the web 2b via the base member 12. For this reason, even when the web 2b of the main girder 2 is cut as described above, it is not necessary to stop the operation of the bridge, that is, the passage of the vehicle on the existing RC floor slab 5.

次いで、上記上り車線Laと下り車線Lbのそれぞれ中央の主桁2には、ウェブ2bの上部における上記基部部材12がまだ取り付けられていない側面に、別の基部部材12を取り付ける。この取り付けも、該基部部材12の上部寄りと下部寄りの2個所をボルト14と図示しないナットを用いて上記ウェブ2bに固定することで行うようにする。   Next, another base member 12 is attached to the main girder 2 at the center of each of the ascending lane La and the descending lane Lb on the side surface of the upper portion of the web 2b where the base member 12 is not yet attached. This attachment is also performed by fixing the base member 12 near the upper part and the lower part to the web 2b using bolts 14 and nuts (not shown).

その後、隣接する主桁2のウェブ2bの対向する面に取り付けられている一対の基部部材12の間に、中床版部材13を取り付けて、上記上り車線Laと下り車線Lbの各3本の主桁2同士の間に、既設のRC床版5の下方に配置された鋼床版11を形成させる。   Thereafter, an intermediate floor slab member 13 is attached between a pair of base members 12 attached to opposite surfaces of the web 2b of the adjacent main girder 2, and each of the above-mentioned up lane La and down lane Lb. A steel deck 11 arranged below the existing RC deck 5 is formed between the main girders 2.

更に、図3に示すように、上記上り車線Laと下り車線Lbの各3本の主桁2のうち、橋幅方向の両側の主桁2のウェブ2bの上部の外側面には、該各ウェブ2bの内側面に取り付けられている上記鋼床版11と対応する高さ位置に、鋼床版としての側床版15を取り付ける。この取り付けも、該側床版15の上部寄りと下部寄りの2個所を、ボルト14と図示しないナットを用いて上記ウェブ2bに固定することで行うようにする。   Further, as shown in FIG. 3, among the three main girders 2 of the up lane La and the down lane Lb, on the outer surface of the upper part of the web 2b of the main girder 2 on both sides in the bridge width direction, A side floor slab 15 as a steel floor slab is attached to a height position corresponding to the steel floor slab 11 attached to the inner side surface of the web 2b. This attachment is also performed by fixing the two portions near the top and bottom of the side floor slab 15 to the web 2b using bolts 14 and nuts (not shown).

上記側床版15のうち、端縁部が上記既設のRC床版5の外側に張出している側床版15については、その端縁部に、橋軸方向に延びる鋼製壁高欄16を取り付ける。   Among the side floor slabs 15, for the side floor slabs 15 whose end edge extends to the outside of the existing RC floor slab 5, a steel wall rail 16 extending in the bridge axis direction is attached to the end edge. .

又、上記のようにして、主桁2のウェブ2bの上部に対する鋼床版11と側床版15の取り付けが終了した場合は、図3に示すように、上記鋼床版11や側床版15の上側に、上記既設のRC床版5より直接荷重を受けるための床版仮受点17を設けるようにしてもよい。   Moreover, when the installation of the steel deck 11 and the side deck 15 to the upper part of the web 2b of the main girder 2 is completed as described above, as shown in FIG. On the upper side of 15, a floor slab temporary receiving point 17 for receiving a load directly from the existing RC floor slab 5 may be provided.

その後、本発明の床版取り替え工法では、図4(a)(b)に示すように、既設のRC床版5を撤去する。この場合は、たとえば、該既設のRC床版5を、図示しない切断機械で適当なサイズに切断するか、又は、ブレーカー等で破砕して、撤去するようにすればよい。更に、上記各鋼床版11及び側床版15の上部寄りの個所を上記主桁2のウェブ2bに固定していたボルト14を取り外すことにより、上記予め切断してある上記主桁2のウェブ2bの上部及び上フランジ2aを、一緒に撤去する。上記主桁2のウェブ2bの上部の撤去に伴って、該ウェブ2bの上部が存在していた各鋼床版11の基部部材12同士の間や、該基部部材12と側床版15との間に形成される隙間は、図示しないフィラーを詰めて、再度ボルトとナットで固定するか、あるいは、該隙間の上側を塞ぐように図示しないプレート材を置いて、該プレート材を上記隙間の両側の鋼床版11や側床版15に固定するようにすればよい。   Thereafter, in the floor slab replacement method of the present invention, the existing RC floor slab 5 is removed as shown in FIGS. In this case, for example, the existing RC floor slab 5 may be cut into an appropriate size by a cutting machine (not shown), or may be crushed by a breaker or the like and removed. Furthermore, the web of the main girder 2 that has been cut in advance is removed by removing the bolts 14 that have fixed the portions of the steel floor slab 11 and the side floor slab 15 near the top of the web 2b of the main girder 2. The upper part of 2b and the upper flange 2a are removed together. With the removal of the upper part of the web 2b of the main girder 2, between the base members 12 of the steel decks 11 where the upper part of the web 2b existed, or between the base member 12 and the side decks 15 The gap formed between them is filled with a filler (not shown) and fixed again with bolts and nuts, or a plate material (not shown) is placed so as to close the upper side of the gap, and the plate material is placed on both sides of the gap. The steel floor slab 11 and the side floor slab 15 may be fixed.

このようにして、既設のRC床版5を撤去すると、上記新設の鋼床版11及び側床版15の表面(上面)が露出されるようになることから、該新設の鋼床版11及び側床版15の上面に、図4に二点鎖線で示すように、舗装18を施す。   When the existing RC floor slab 5 is removed in this manner, the surfaces (upper surfaces) of the new steel floor slab 11 and the side floor slab 15 are exposed. A pavement 18 is applied to the upper surface of the side floor slab 15 as shown by a two-dot chain line in FIG.

又、上記上り車線Laと下り車線Lbについて橋幅方向の内側に張出している側床版15の端縁部には、上記と同様の鋼製壁高欄16を取り付ける。   Further, a steel wall height column 16 similar to the above is attached to the end edge portion of the side floor slab 15 projecting inward in the bridge width direction with respect to the ascending lane La and the descending lane Lb.

ところで、上記新設の鋼床版11及び側床版15の上面に設けた舗装18の表面の高さ位置は、上記撤去する前の既設のRC床版5上に設けられていた舗装6の表面よりも、低くなっている。   By the way, the height position of the surface of the pavement 18 provided on the upper surfaces of the new steel floor slab 11 and the side floor slab 15 is the surface of the pavement 6 provided on the existing RC floor slab 5 before the removal. Is lower than.

そこで、図5(a)(b)に示すように、上記各鋼床版11及び側床版15は、上記主桁2と一緒に、上記舗装18の表面の高さ位置が、床版取り替え前の上記舗装6の表面の高さ位置まで原状復帰するように、ジャッキアップする。又は、図示してないが、上記各鋼床版11及び側床版15は、その上面に設けた上記舗装18の表面の高さ位置が、橋軸方向に隣接する別の主桁2上に設けてある取り替え前のRC床版5上の舗装6、あるいは、床版の取り替え工事後の別の鋼床版11と側床版15上の舗装18の上面に擦り付け可能となる高さ位置まで、上記主桁2と一緒にジャッキアップして、該ジャッキアップした各鋼床版11及び側床版15上の舗装18を、橋軸方向に隣接する舗装6,18に擦り付けるようにする。なお、上記ジャッキアップは、下部構造1a,1bの所定個所に配置した図示しないジャッキで行うようにすればよい。   Therefore, as shown in FIGS. 5 (a) and 5 (b), the steel floor slab 11 and the side floor slab 15 together with the main girder 2 are arranged so that the height position of the surface of the pavement 18 is floor slab replacement. Jack up so that it returns to the original height position on the surface of the previous pavement 6. Or although not shown in figure, the said steel floor slab 11 and the side floor slab 15 have the height position of the surface of the said pavement 18 provided in the upper surface on another main girder 2 adjacent to a bridge axis direction. Up to the height of the pavement 6 on the RC floor slab 5 before replacement, or to the upper surface of the pavement 18 on another steel floor slab 11 and the side floor slab 15 after replacement of the floor slab. The jacks are jacked up together with the main girder 2 so that the paved 18 on the steel floor slab 11 and the side floor slab 15 jacked up are rubbed against the pavements 6 and 18 adjacent in the bridge axis direction. The jack-up may be performed by a jack (not shown) arranged at a predetermined position of the lower structures 1a and 1b.

上記のようにして各鋼床版11及び側床版15を主桁2と一緒に所定量ジャッキアップした後は、該主桁2を、下部構造1a,1bの上に、厚み寸法を増した新たな支承(又は介装物)19を介装した状態で支持させる。これにより、上記各鋼床版11及び側床版15の上面に設けてある舗装18は、その上面が、橋軸方向に隣接する別の主桁2上に設けてある取り替え前のRC床版5上の舗装6、あるいは、床版の取り替え工事後の別の鋼床版11と側床版15上の舗装18の上面に連なるように配置される。よって、上記橋梁では、上記舗装6,18上での車両の通行を再開させることができるようになる。   After jacking up each steel floor slab 11 and side floor slab 15 together with the main girder 2 as described above, the thickness dimension of the main girder 2 was increased on the lower structures 1a and 1b. A new support (or intervening material) 19 is supported. Thereby, as for the pavement 18 provided in the upper surface of each said steel floor slab 11 and the side floor slab 15, the upper surface is provided on the other main girder 2 adjacent to a bridge axis direction RC floor slab before replacement | exchange. 5, or another steel floor slab 11 after the replacement work of the floor slab and the upper surface of the pavement 18 on the side floor slab 15. Therefore, in the bridge, the vehicle can be resumed on the pavements 6 and 18.

なお、上記主桁2と一緒の各鋼床版11及び側床版15のジャッキアップ作業と、該各鋼床版11及び側床版15上への舗装18を施工する作業の順番は、前後していてもよい。   The order of jacking up each steel slab 11 and side floor slab 15 together with the main girder 2 and the work of constructing the pavement 18 on each steel floor slab 11 and side floor slab 15 is You may do it.

上記においては、図3の段階で、上り車線La用の主桁2と、下り車線Lb用の主桁2との連結状態を切り離すようにしてあるため、上記図4(a)(b)及び図5(a)(b)に示した既設のRC床版5を一度に撤去する作業から、新設の各鋼床版11及び側床版15の上面に舗装18を設ける作業、及び、該各鋼床版11及び側床版15の主桁2と一緒のジャッキアップ作業までの工程は、上り車線Laと下り車線Lbごとに分けて順次行うようにすればよい。   In the above, since the main girder 2 for the up lane La and the main girder 2 for the down lane Lb are disconnected at the stage of FIG. 3, the above-described FIG. 4 (a) (b) and FIG. From the work of removing the existing RC floor slab 5 shown in FIGS. 5 (a) and 5 (b) at once, the work of providing the pavement 18 on the upper surface of each steel floor slab 11 and the side floor slab 15; The steps up to the jack-up work together with the main girder 2 of the steel floor slab 11 and the side floor slab 15 may be performed separately for each of the up lane La and the down lane Lb.

又、上記既設のRC床版5の撤去に伴い、主桁2に作用する死荷重は軽減される。このため、上記既設のRC床版5を撤去した後は、前述したように所定の主桁2の下フランジ2cに取り付けてある下フランジ補強材8、及び、偏向具9とアウトケーブル10は取り外して、撤去するようにする。又、図示しない支保工が設けてある場合は、上記既設のRC床版5の撤去後に、該支保工を撤去するようにすればよい。   Further, with the removal of the existing RC floor slab 5, the dead load acting on the main girder 2 is reduced. For this reason, after the existing RC floor slab 5 is removed, the lower flange reinforcing member 8 attached to the lower flange 2c of the predetermined main girder 2, the deflector 9 and the out cable 10 are removed as described above. And remove it. Further, when a support work (not shown) is provided, the support work may be removed after removing the existing RC floor slab 5.

このように、本発明の床版取り替え工法によれば、老朽化した既設のRC床版5を、新設の床版としての鋼床版11及び側床版15に取り替えることができる。   As described above, according to the floor slab replacement method of the present invention, the existing RC floor slab 5 that has deteriorated can be replaced with the steel floor slab 11 and the side floor slab 15 as new floor slabs.

又、上記新設の鋼床版11及び側床版15を主桁2へ取り付ける作業を行う間は、既設のRC床版5上での通行を継続して行わせることができる。更に、交通規制は、主桁2上の既設のRC床版5の撤去作業と、新設の鋼床版11及び側床版15を主桁2と共にジャッキアップする作業と、該新設の鋼床版11及び側床版15上に舗装18を施工する作業の期間中のみでよい。したがって、交通規制が必要とされる期間を、従来の手法に比して大幅に短縮させることができる。   Further, during the operation of attaching the newly installed steel floor slab 11 and the side floor slab 15 to the main girder 2, it is possible to continue the passage on the existing RC floor slab 5. Further, the traffic regulation includes the removal work of the existing RC floor slab 5 on the main girder 2, the work of jacking up the newly installed steel floor slab 11 and the side floor slab 15 together with the main girder 2, and the newly installed steel floor slab. 11 and the side floor slab 15 only during the work of constructing the pavement 18. Therefore, the period during which traffic regulation is required can be significantly shortened as compared with the conventional method.

更に、上記においては、既設のRC床版5を、より軽量な新設の鋼床版11と、鋼床版である側床版15に取り替えるようにしてあるため、主桁2及び下部構造1a,1bに作用する荷重の軽減化を図ることができる。これにより、上記主桁2及び下部構造1a,1bで負担する荷重を軽減させることができるため、該主桁2や下部構造1a,1bの劣化の進行を抑制する効果が期待できる。   Furthermore, in the above, since the existing RC floor slab 5 is replaced with a lighter steel floor slab 11 and a side floor slab 15 which is a steel floor slab, the main girder 2 and the lower structure 1a, The load acting on 1b can be reduced. Thereby, since the load borne by the main girder 2 and the lower structures 1a and 1b can be reduced, an effect of suppressing the progress of deterioration of the main girder 2 and the lower structures 1a and 1b can be expected.

なお、本発明は上記実施の形態のみに限定されるものではなく、主桁2の上側に既設の床版が取り付けられており、且つ該既設の床版の下方位置で、上記主桁の上部に、新設の床版を取り付けることが可能な橋梁であれば、本発明の床版取り替え工法は、都市内高速道路以外の任意の橋梁における床版の取り替えに適用してもよい。又、本発明の床版取り替え工法は、図示した以外の任意の数の主桁を備える形式の橋梁に対して適用してもよい。更に、本発明の床版取り替え工法は、鈑桁に代えて、箱桁を主桁とする形式の橋梁における床版の取り替えに適用してもよい。   The present invention is not limited only to the above-described embodiment, and an existing floor slab is attached to the upper side of the main girder 2 and the upper part of the main girder is positioned below the existing floor slab. In addition, as long as the bridge can be fitted with a newly installed floor slab, the floor slab replacement method of the present invention may be applied to replacement of a floor slab in any bridge other than an urban highway. Further, the floor slab replacement method of the present invention may be applied to a bridge of a type having an arbitrary number of main girders other than those illustrated. Furthermore, the floor slab replacement method of the present invention may be applied to replacement of a floor slab in a bridge having a box girder as a main girder instead of a girder.

主桁2間に取り付ける新設の鋼床版11は、一対の基部部材12と、その間に取り付ける中床版部材13とからなる三分割構造として示したが、主桁2同士の間隔に応じて、中床版部材13が、更に橋幅方向に複数に分割された構造のものとしてもよい。   The newly installed steel floor slab 11 attached between the main girders 2 is shown as a three-part structure comprising a pair of base members 12 and an intermediate floor slab member 13 attached between them, but according to the interval between the main girders 2, The intermediate floor slab member 13 may be further divided into a plurality of parts in the bridge width direction.

橋梁に必要とされる橋幅寸法に応じて、主桁2に取り付ける側床版15の幅寸法や形状は適宜変更してもよい。又、側床版15を省略した構成としてもよい
更に、上記既設の床版は、RC床版5以外の形式の床版でもよく、又、新設の床版は、既設の床版の下方で主桁の上部に取り付けることができれば、鋼床版11以外の形式の床版であってもよい。
Depending on the bridge width dimension required for the bridge, the width dimension and shape of the side floor slab 15 attached to the main girder 2 may be appropriately changed. Further, the side floor slab 15 may be omitted. Further, the existing floor slab may be a floor slab of a type other than the RC floor slab 5, and the new floor slab is located below the existing floor slab. A floor slab other than the steel slab 11 may be used as long as it can be attached to the upper part of the main girder.

新設の床版を主桁の上部に取り付けた後、既設の床版を撤去する際に、新設の床版の上方に突出する主桁の上端部を撤去する作業は、主桁の形式に応じて適宜変更してよい。   After the new floor slab is installed on the top of the main girder, when removing the existing floor slab, the work to remove the upper end of the main girder protruding above the new floor slab depends on the type of main girder. May be changed as appropriate.

又、新設の床版を支承するのに必要とされる強度や剛性に応じて、主桁及び横桁の連結構造は、適宜変化させるようにしてもよい。   Further, the connecting structure of the main girder and the cross girder may be appropriately changed according to the strength and rigidity required to support the newly installed floor slab.

上記実施の形態では、都市内高速道路等の橋梁について、上記既設のRC床版5の新設の鋼床版11及び側床版15への取り替えに伴って、上り車線Laと下り車線Lbを分離させる場合について示したが、上り車線Laと下り車線Lbを一体構造とした状態のままで床版取り替え工事を行うようにしてもよい。   In the above-described embodiment, as for the bridge of an urban highway or the like, the up lane La and the down lane Lb are separated by replacing the existing RC slab 5 with the newly installed steel slab 11 and the side slab 15. However, the floor slab replacement work may be performed while the ascending lane La and the descending lane Lb are integrated.

その他本発明の要旨を逸脱しない範囲内で種々変更を加え得ることは勿論である。   Of course, various modifications can be made without departing from the scope of the present invention.

1a,1b 下部構造
2 主桁
5 RC床版(既設の床版)
11 鋼床版(新設の床版)
15 側床版(新設の床版)
1a, 1b Substructure 2 Main girder 5 RC floor slab (existing floor slab)
11 Steel slab (new slab)
15 Side floor slab (new floor slab)

Claims (2)

主桁の上側に取り付けられている既設の床版の下方で、主桁の上部に、新設の床版を取り付け、
次に、上記既設の床版を撤去することで、新設の床版の上面を露出させ、
次いで、上記新設の床版の上面の高さ位置が、上記既設の床版の上面の高さ位置まで原状復帰されるように、下部構造上で、該新設の床版を上記主桁と共にジャッキアップするようにする
ことを特徴とする床版取り替え工法。
At the top of the main girder, install the new floor slab below the existing floor slab attached to the upper side of the main girder,
Next, by removing the existing floor slab, the upper surface of the new floor slab is exposed,
Subsequently, the new floor slab is jacked together with the main girder on the lower structure so that the height position of the upper surface of the new floor slab is restored to the original height position of the upper surface of the existing floor slab. The floor slab replacement method, characterized in that it is improved.
新設の床版として、鋼床版を用いるようにする請求項1記載の床版取り替え工法。   The floor slab replacement method according to claim 1, wherein a steel floor slab is used as the new floor slab.
JP2013003808A 2013-01-11 2013-01-11 Floor slab replacement method Active JP5848716B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013003808A JP5848716B2 (en) 2013-01-11 2013-01-11 Floor slab replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013003808A JP5848716B2 (en) 2013-01-11 2013-01-11 Floor slab replacement method

Publications (2)

Publication Number Publication Date
JP2014134060A true JP2014134060A (en) 2014-07-24
JP5848716B2 JP5848716B2 (en) 2016-01-27

Family

ID=51412533

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013003808A Active JP5848716B2 (en) 2013-01-11 2013-01-11 Floor slab replacement method

Country Status (1)

Country Link
JP (1) JP5848716B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018104970A (en) * 2016-12-26 2018-07-05 首都高速道路株式会社 Floor slab replacement method
JP2019027152A (en) * 2017-07-31 2019-02-21 鹿島建設株式会社 Reinforcement structure for use during floor slab replacement and floor slab replacement method
CN112813852A (en) * 2021-01-05 2021-05-18 四川交投建设工程股份有限公司 Repairing and reinforcing method for bridge deck subsidence of in-service bridge

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001081726A (en) * 1999-09-16 2001-03-27 Ishikawajima Harima Heavy Ind Co Ltd Method and structure for re-laying steel floor slab of concrete floor slab bridge
JP2002332612A (en) * 2001-05-10 2002-11-22 Ishikawajima Harima Heavy Ind Co Ltd Re-covering steel-plate floor deck bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001081726A (en) * 1999-09-16 2001-03-27 Ishikawajima Harima Heavy Ind Co Ltd Method and structure for re-laying steel floor slab of concrete floor slab bridge
JP2002332612A (en) * 2001-05-10 2002-11-22 Ishikawajima Harima Heavy Ind Co Ltd Re-covering steel-plate floor deck bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018104970A (en) * 2016-12-26 2018-07-05 首都高速道路株式会社 Floor slab replacement method
JP2019027152A (en) * 2017-07-31 2019-02-21 鹿島建設株式会社 Reinforcement structure for use during floor slab replacement and floor slab replacement method
CN112813852A (en) * 2021-01-05 2021-05-18 四川交投建设工程股份有限公司 Repairing and reinforcing method for bridge deck subsidence of in-service bridge

Also Published As

Publication number Publication date
JP5848716B2 (en) 2016-01-27

Similar Documents

Publication Publication Date Title
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
US10704215B2 (en) System for construction of composite U shaped reinforced girders bridge deck and methods thereof
KR100916973B1 (en) Construction method of prestressed concrete pavement and its structure
JP5848716B2 (en) Floor slab replacement method
KR100415768B1 (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
KR101118257B1 (en) Deck for concrete slab construction
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
KR100884780B1 (en) A structure of prestressed concrete pavement and its construction method
JP2007107339A (en) Structure and its construction method for steel concrete compound rigid frame bridge
JP4477467B2 (en) Bridge structure and its replacement method
JP2000017618A (en) Replacement method of concrete bridge to steel bridge
KR101241401B1 (en) Composite steel continuous bridge construction method using concrete cross beams
JP6425848B1 (en) Bridge replacement method
JP2018059313A (en) Steel floor slab unit with pavement attached and floor slab structure
KR20100026917A (en) Bridge having expansion joint and method of setting expansion joint
JP6755172B2 (en) Floor slab renewal method
JP5061874B2 (en) Railway bridge construction switching method
CN111254802A (en) Precast beam structure, assembly type temporary bridge and installation method thereof
KR100729842B1 (en) Repair work of railroad bridge and that structure
CN217810457U (en) Beam-arch combined structure
KR20200072986A (en) Pseudo jointless bridge construction made of steel plate girder with overhanged end widen and extended flange composed of concrete block
KR200240457Y1 (en) Frame for substitu ting steel girder of a railway bridge for concrete slab
JP7386824B2 (en) Girder replacement method and pier removal method
JP7124794B2 (en) Bridge replacement method
JP7272918B2 (en) Existing floor slab replacement method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20141020

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20150129

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20150129

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150226

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150717

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150728

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150909

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20151104

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20151127

R150 Certificate of patent or registration of utility model

Ref document number: 5848716

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250