KR101241401B1 - Composite steel continuous bridge construction method using concrete cross beams - Google Patents

Composite steel continuous bridge construction method using concrete cross beams Download PDF

Info

Publication number
KR101241401B1
KR101241401B1 KR1020100085717A KR20100085717A KR101241401B1 KR 101241401 B1 KR101241401 B1 KR 101241401B1 KR 1020100085717 A KR1020100085717 A KR 1020100085717A KR 20100085717 A KR20100085717 A KR 20100085717A KR 101241401 B1 KR101241401 B1 KR 101241401B1
Authority
KR
South Korea
Prior art keywords
concrete
girder
bridge
bottom plate
crossbeam
Prior art date
Application number
KR1020100085717A
Other languages
Korean (ko)
Other versions
KR20120022285A (en
Inventor
김은하
Original Assignee
김은하
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김은하 filed Critical 김은하
Priority to KR1020100085717A priority Critical patent/KR101241401B1/en
Publication of KR20120022285A publication Critical patent/KR20120022285A/en
Application granted granted Critical
Publication of KR101241401B1 publication Critical patent/KR101241401B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 지점부에서 1차 및 2차 콘크리트 가로보를 이용하여 거더의 연결 없이 다경간 교량을 연속화시킨 콘크리트 가로보를 이용한 강합성 연속교 시공 방법에 관한 것으로, 교대 또는 교각의 지점부에서 교량 받침부 설치용 보강판 상단에 1차 콘크리트 가로보와 2차 콘크리트 가로보를 설치하고, 상기 2차 콘크리트 가로보의 내부에서 거더의 연결 단부를 매립시키며, 상기 2차 콘크리트 가로보와 바닥판 콘크리트는 동시에 콘크리트 타설되어 일체로 형성됨으로서 거더간의 연결 없이 콘크리트 가로보와 거더의 합성거동으로 교량을 연속화한다.The present invention relates to a method of constructing a continuous composite bridge using a concrete crossbeam that continuous multi-span bridges without connecting girders by using primary and secondary concrete crossbeams at a point portion, and a bridge support portion at a point portion of a shift or a pier. A primary concrete crossbeam and a secondary concrete crossbeam are installed on top of the reinforcing plate for installation, and the connecting end of the girder is embedded in the inside of the secondary concrete crossbeam, and the secondary concrete crossbeam and the bottom plate concrete are simultaneously cast and integrally As it is formed, the bridge is continuous by the composite behavior of the concrete crossbeam and the girder without connecting the girders.

Description

콘크리트 가로보를 이용한 강합성 연속교 시공방법{COMPOSITE STEEL CONTINUOUS BRIDGE CONSTRUCTION METHOD USING CONCRETE CROSS BEAMS}Construction method of steel composite continuous bridge using concrete crossbeams {COMPOSITE STEEL CONTINUOUS BRIDGE CONSTRUCTION METHOD USING CONCRETE CROSS BEAMS}

본 발명은 강재 거더를 이용한 강합성 연속교 시공방법에 관한 것으로 보다 상세히는 지점부에서 1차 및 2차 콘크리트 가로보를 이용하여 거더의 연결 없이 다경간 교량을 연속화시키는 공법으로 시공 중 교량하부 공간의 점용시간이 필요 없거나 최소화되는 콘크리트 가로보를 이용한 강합성 연속교 시공 방법에 관한 것이다.The present invention relates to a method of constructing a steel composite continuous bridge using steel girders, and more specifically, by using primary and secondary concrete crossbeams at a point portion, a method of continually multi-span bridges without connection of girder, The present invention relates to a method for constructing a steel composite continuous bridge using concrete crossbeams that does not require or minimize spot time.

최근 자동차의 보급 확대등 교통수요의 증가로 인한 새로운 도로 및 철도등의 신설이 필요하다.New roads and railroads need to be established due to the recent increase in traffic demand, such as the expansion of automobiles.

이러한 새로운 도로나 철도는 기존도로와 철도시설 또는 하천을 횡단하여 설치하게 되는데, 신설교량 시공으로 인한 교량하면 공간의 점용배제와 최소화로 시공성을 개선할 수 있다.These new roads or railroads will be installed across existing roads and railroad facilities or rivers, and bridges due to the construction of new bridges can improve workability by eliminating and minimizing space.

특히, 교량 시공 시 인양중량의 감소로 소규모 장비에 의한 급속시공이 가능하도록 하여 공사를 위한 주변 점용 공간의 축소와 소요공기 단축으로 민원해소와 경제성을 확보할 수 있다.In particular, it is possible to reduce the lifting weight during construction of the bridge, enabling rapid construction by small-scale equipment, thereby reducing civil complaints and economic feasibility by reducing the surrounding spot space for construction and shortening the required air.

일반적인 다경간 연속교에서 지간 중앙부 정모멘트에 비해 지점부 부모멘트가 커서 이로 인해 단면이 비효율적으로 사용되며, 정모멘트부에 비해 크게 작용하는 과도한 부모멘트로 인한 지점부 바닥판 콘크리트에 작용하는 큰 인장응력은 지점부 바닥판 콘크리트에서 균열발생 등의 내구성 저하요인으로 작용하고 있다.In general multi-span continuous bridges, the pointal moments are larger than the center moments of the spans, so the cross section is used inefficiently. Stress acts as a deterioration factor of cracking and the like in the point deck concrete.

교량에서 주요 유지관리 항목인 교량받침부가 기존 공법에서는 거더마다 설치되어 다수의 받침에 의한 유지관리성이 저하되는 문제점이 있는바, 콘크리트 가로보를 사용하여 설치 받침수를 최소화 시키거나 또는 배제하여 교량 사용중 유지관리성 증진효과를 도모할 수 있는 방안수립이 필요하다.In the existing method, the bridge support part, which is the main maintenance item in the bridge, is installed in each girder, and thus maintainability by multiple supports is reduced. The use of the bridge is minimized or excluded by using concrete cross beams. It is necessary to establish a plan to improve the maintainability.

또한, 교량구조에서 강합성 교량형식이 콘크리트교량 형식에 비해 상부구조의 중량이 가볍고 시공이 용이하며, 공기가 짧으나 일반적으로 고가의 강재 사용에 의한 경제성이 저하되는 단점이 있으므로, 거더를 사전에 제작된 형강으로 사용할 경우, 상당한 경제성 증진 효과를 도모할 수 있다.In addition, in the bridge structure, the steel composite bridge type is lighter in weight and easier to construct than the concrete bridge type, and the air is short, but the economical efficiency of the expensive steel is generally reduced. When used as a cast steel, significant economic increase can be achieved.

도 1a 및 도 1b에는 종래의 강합성 연속교(10)가 도시되어 있다.1A and 1B show a conventional rigid composite continuous bridge 10.

이와 같은 종래의 강합성 연속교(10)는 먼저, 교각(20) 및 교대(22)를 시공하고, 교량 받침을 이용하여 교각(20) 및 교대(22) 사이에 거더(30)를 거치하여 연결시키며, 바닥판 콘크리트(40)를 타설하여 시공하게 된다.The conventional rigid composite continuous bridge 10, first, the construction of the bridge 20 and the alternating 22, and by placing the girder 30 between the bridge 20 and the alternating 22 using the bridge support. To connect, the bottom plate concrete 40 is poured by construction.

이와 같은 종래의 강합성 연속교(10)는 통상 거더(30)가 강재이므로 이들을 서로 덧댐판과 볼트/너트를 이용하여 서로 연결시키거나, 도 2a에 도시된 바와 같이, 지점부 상면에 교량받침(50)을 이용하여 거치시키고, 거더(30)의 연결 단부에 있어 덧댐판(60)을 필렛 용접(62)으로 연결하고 있다.Since the conventional steel composite continuous bridge 10 is a girder 30 is usually steel, they are connected to each other using a backing plate and bolts / nuts, or as shown in FIG. It mounts using (50) and connects the back plate 60 by the fillet welding 62 in the connection end of the girder 30. As shown in FIG.

그러나 이와 같은 종래의 강합성 연속교(10)는 거더(30)를 서로 연결하는 순간, 교각(20)과 같은 지점부에 휨 부모멘트가 크게 발생하게 된다. However, in the conventional rigid composite bridge 10, the moment of connecting the girders 30 to each other, bending moments are largely generated at the same point as the bridge 20.

통상 거더(30)의 단면은 이러한 휨 부모멘트를 기준으로 설계되는데, 이는 가장 큰 하중에 대하여 견딜수 있는 거더(30)를 제작해야 하기 때문이며, 이에 동일단 단면으로 거더(30)를 제작하게 되면 과다설계가 된다. Normally, the cross section of the girder 30 is designed based on such bending parent moment, because it is necessary to manufacture the girder 30 that can withstand the largest load, and when the girder 30 is manufactured with the same end cross section, it is excessive. It becomes a design.

즉, 거더(30)의 중간부분에는 휨 정모멘트가 발생되는데 이러한 휨 정모멘트의 크기가 상기 휨 부멘트보다 작기 때문에 굳이 거더(30) 중간부분의 단면을 크게 설계하면 과다 설계가 되는 문제점을 갖는다.That is, the bending constant moment is generated in the middle portion of the girder 30. Since the size of the bending constant moment is smaller than the bending portion, the cross section of the middle portion of the girder 30 has a problem of being excessively designed. .

종래의 강합성 연속교(10)에 대한 전체계 모델링이 도 3에 도시되어 있다.The overall modeling of the conventional rigid composite continuous bridge 10 is shown in FIG. 3.

종래의 강합성 연속교(10)에 대한 전체계 모델링에 대한 1단계는 거더를 교각(20)과 같은 지점부(70)에서 서로 연결하여 연속화한 후, 바닥판 콘크리트(40)를 타설하므로 거더(30)에는 바닥판 콘크리트 하중이 작용하여 지점부에 휨 부모멘트가 크게 발생한다.The first step for the overall modeling of the conventional rigid composite bridge 10 is to connect the girder at the same point portion 70, such as the piers 20, and to continually connect, and then pour the bottom plate concrete 40 The bottom plate concrete load acts on the 30 to generate a large bending moment.

그리고 전체계 모델링에 대한 2단계는 거더(30)의 합성 후, 연석, 난간 및 도로 포장을 설치한 다음, 사하중을 모델링하며, 3단계는 거더(30)의 합성 후 활하중을 모델링하고, 4단계로는 온도변화, 지점침하, 지진하중 및 풍하중을 고려하여 모델링한다.The second step for the overall modeling is to synthesize the girder 30, install curbs, railings and pavements, and then model dead loads. The third step is to model live loads after the girder 30 is synthesized. The furnace is modeled by considering temperature change, point settlement, seismic load and wind load.

한편, 도 2b에는 횡가로보를 사용한 종래의 연속교(80)가 도시되어 있다. 이러한 횡가로보(82)는 프리캐스트 제품으로 제작하여 교각(20)과 같은 지점부(70)에서 거더(30)에 설치한 것으로서, 양측 강재 거더(30)가 긴장재(90)를 통하여 서로 연결된 것이다.On the other hand, Figure 2b shows a conventional continuous bridge 80 using a cross-beam. The horizontal crossbeam 82 is made of a precast product and installed on the girder 30 at the same point portion 70 as the pier 20, and both steel girders 30 are connected to each other through the tension member 90. .

그러나 이와 같은 종래의 연속교(80)에서 거더(30)를 긴장재(90)로서 서로 연결시키게 공정은 매우 번거롭고, 시공 공정을 복잡하게 하여 비생산적이라 할 수 있다.However, the process is very troublesome to connect the girders 30 to each other as the tension member 90 in the conventional continuous bridge 80 as described above, and the construction process can be referred to as unproductive.

본 발명은 상기와 같은 종래의 문제점을 해소하기 위한 것으로서, 그 목적은 철도, 도로, 하천 등을 횡단하는 횡단교량이나 교량혼잡지역에서의 교량건설로 교량 시공 중, 공사를 위한 교량하면 공간의 점용 배제 또는 최소화가 가능하며, 공사를 위한 인양중량 감소로 소규모 장비에 의해 시공이 가능하게 하고, 공사를 위한 주변 점용공간 감소 및 공기단축으로 경제성 및 민원 해소성을 증진할 수 있도록 개선된 콘크리트 가로보를 이용한 강합성 연속교 시공방법을 제공함에 있다.The present invention is to solve the conventional problems as described above, the purpose of the bridge construction for the construction of the bridge, cross-crossing bridges crossing the railway, roads, rivers, etc. It can be excluded or minimized, and it can be installed by small-scale equipment by reducing the lifting weight for construction, and improved concrete crossbeams to improve economic efficiency and resolution of civil complaints by reducing surrounding space for construction and shortening of air. The present invention provides a method for constructing a steel composite bridge.

그리고 본 발명의 다른 목적은 다경간 연속구조에서 발생하는 부모멘트를 시공방법 개선 통하여 감소시켜 균형 있는 단면력 배분에 의한 교량단면의 효율성 증진과 지점부 부모멘트 감소에 의한 바닥판 콘크리트 균열억제로 교량 내구성을 크게 증진시키고, 형강의 사용으로 강합성 교량에서의 경제성 증진 및 운영중 주요유지관리 항목인 받침수가 최소화되는 콘크리트 가로보를 이용한 강합성 연속교 시공방법을 제공함에 있다.In addition, another object of the present invention is to reduce the parent moment generated in the multi-span continuous structure by improving the construction method to improve the efficiency of the bridge section by the balanced distribution of the cross-sectional force and to bridge bridge concrete crack suppression by reducing the cracks It is to provide a method of constructing a continuous composite bridge using concrete crossbeams, which greatly improves the efficiency of the steel bridge and improves economic efficiency in the steel composite bridge and minimizes the number of bearings.

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

상기와 같은 목적을 달성하기 위하여 본 발명은, According to an aspect of the present invention,

지점부 상부면에 교량 받침부 설치용 보강판을 매입 후, 1차 콘크리트 가로보 철근 배근 및 거더 받침틀을 설치하고;After installing the reinforcement plate for bridge support installation on the upper part of the branch, install the primary concrete cross beam reinforcement and girder support frame;

콘크리트 가로보와 거더의 합성 작용이 원활하도록 거더 하면보다 조금 낮은 위치까지 콘크리트를 1차 타설 및 양생하며;Primary casting and curing of concrete to a position lower than the lower surface of the girder so that the composite action of the concrete crossbeam and the girder is smooth;

사전에 제작된 거더를 콘크리트 가로보상의 거더 받침틀에 거치하고;A prefabricated girder is mounted on a girder frame of concrete crossbeam;

거치된 거더를 지지대로 하여 바닥판 타설용 동바리 및 2차 거푸집을 설치하며;Supporting the mounted girders to install bottom plate casting clubs and secondary formwork;

2차 콘크리트 가로보 철근 배근 및 바닥판 철근 배근 후, 2차 콘크리트 가로보 및 바닥판 콘크리트를 동시에 타설하여 양생시키고; 그리고After the secondary concrete cross beam reinforcement and the bottom plate reinforcement, the secondary concrete cross beam and the bottom plate concrete are poured at the same time to cure; And

바닥판 양생완료 후, 방호벽 및 난간 등을 설치하는 단계;들을 포함하여 거더간의 연결 없이 콘크리트 가로보와의 합성거동으로 교량을 연속화하는 것을 특징으로 하는 콘크리트 가로보를 이용한 강합성 연속교 시공방법을 제공한다.After completion of curing of the bottom plate, and providing a protective wall and railing; and provides a method of constructing a continuous composite bridge using a concrete crossbeam characterized in that the bridge is continuous by the composite behavior with the concrete crossbeam without connecting the girder. .

또한 본 발명은 바람직하게는 상기 거더를 설치하는 단계는 콘크리트 가로보와의 합성작용과 응력거동을 고려하여 거더 단부에 마감판을 설치하고, 설치된 마감판과 거더에 스터드 및 철근 배근용 홀을 천공하여 제작한 거더를 설치하도록 된 콘크리트 가로보를 이용한 강합성 연속교 시공방법을 제공한다.In addition, the present invention is preferably the step of installing the girder by installing a finishing plate at the end of the girder in consideration of the composite action and the stress behavior with the concrete crossbeam, by drilling a stud and reinforcement holes in the installed finishing plate and girder It provides a method of constructing a steel composite continuous bridge using concrete crossbeams to install manufactured girders.

그리고 본 발명은 바람직하게는 상기 바닥판 타설용 동바리 및 2차 거푸집을 설치하는 단계는 바닥판 콘크리트 타설용 동바리와 거푸집을 거더에 지지시켜 설치하며, 거더 자중과 바닥판 콘크리트 및 거푸집과 동바리 하중을 동시에 거더가 지지하도록 설치하도록 된 콘크리트 가로보를 이용한 강합성 연속교 시공방법을 제공한다.And the present invention is preferably the step of installing the bottom plate pour copper and secondary formwork to support the bottom plate concrete pours and formwork to the girder, the girder weight and the bottom plate concrete and formwork and the club load At the same time, it provides a method of constructing a steel composite continuous bridge using concrete crossbeams installed to support girders.

삭제delete

삭제delete

삭제delete

본 발명에 의하면, 강합성 연속교량 시공 중, 거더 연결 없이 콘크리트 가로보와 거더의 합성작용에 의해 다경간 구조를 연속구조로 실현할 수 있다.According to the present invention, the multi-span structure can be realized in a continuous structure by the composite action of the concrete cross beam and the girder without connecting the girder during the construction of the rigid composite bridge.

따라서 작업 현장에서의 거더 이음작업이 불필요하여 전문적인 인력이 불필요하고, 부모멘트 단면력의 분배를 통한 단면효율성 개선과, 감소된 부모멘트에 의한 지점부 바닥판 균열감소로 교량의 경제성과 내구성을 크게 증진시킬 수 있다.Therefore, girder joint work is unnecessary on the job site, so no professional manpower is required, and the economic efficiency and durability of the bridge are greatly improved by improving the section efficiency through the distribution of the parent section section force and reducing the cracks in the bottom plate due to the reduced parent section. Can be promoted.

그리고 본 발명에 의하면 지점부인 교각 상면에 1차 콘크리트 가로보를 먼저 설치하고, 거더의 양 단부를 거치하되 서로 연결되지 않도록 하므로써, 시공과정에서 지점부에 휨 부모멘트가 발생하지 않게 되므로 단면을 크게 설계할 필요가 없다. 또한 1차 콘크리트 가로보의 상부에 바닥판 콘크리트와 2차 콘크리트 가로보를 타설하여 교량을 완성시키게 되며, 이러한 과정에서 거더, 콘크리트 가로보, 바닥판 콘크리트가 일체화되면 거더가 서로 연결되므로 휨 부모멘트가 발생되지만 이러한 휨 부모멘트에 대하여 거더, 콘크리트 가로보, 바닥판 콘크리트가 일체화된 합성단면으로 저항하므로 거더의 단면을 획기적으로 줄일 수 있는 우수한 효과를 얻게 된다.In addition, according to the present invention, the first concrete cross beam is first installed on the upper part of the bridge piers, and both ends of the girder are mounted but not connected to each other, so that bending moments are not generated during the construction. There is no need to do it. In addition, the bridge is completed by placing the bottom concrete and the secondary concrete beam on the upper part of the first concrete crossbeam.In this process, when the girder, the concrete crossbeam, and the bottom plate concrete are integrated, the girder is connected to each other, so that bending bending moment is generated. Since the girder, the cross beam, and the bottom plate concrete are resisted by the composite section integrated with the bending parent moment, the cross section of the girder can be remarkably reduced.

또한 본 발명에 의하면 거더로서 기존의 형강제품을 사용가능하므로 자재비 및 제작비를 감소시킬 수 있고, 공사의 신속성과 경제성 증진이 가능하며, 콘크리트 가로보 설치로 인한 상부구조 지지용 소요받침 개수 감소와 교량 인상을 위한 잭업 공간의 확보로 교량받침의 유지관리성이 크게 향상된다.In addition, according to the present invention, it is possible to use the existing section steel products as girder, which can reduce the material cost and manufacturing cost, increase the speed and economic feasibility of the construction, reduce the number of supporting bases for supporting the superstructure due to the installation of concrete crossbeams and raise the bridges. Maintaining the jack-up space for the bridge greatly improves the maintainability of the bridge bearing.

그리고 본 발명의 공법을 적용하는 최대 이점중의 하나는 콘크리트 가로보와 기둥을 일체로 할 경우 교량받침을 없앨 수도 있고 개수도 줄일 수도 있게 된다. 그 이유는 교량받침에 바로 설치하는 것이 아니라 콘크리트 가로보에 설치하기 때문이며, 이와 같이 교량받침을 줄이게 되면, 교량유지 관리대상의 감소와 더불어서 유지관리비 감소 및 편의성이 크게 증진되는 효과를 얻을 수 있다.And one of the greatest advantages of applying the method of the present invention is that when the concrete cross beam and the column integrally can remove the bridge support and can also reduce the number. The reason is that it is not installed directly on the bridge support, but installed on the concrete cross beam, and if the bridge support is reduced in this way, it is possible to reduce the maintenance costs and increase the convenience of maintenance and increase the convenience of the bridge maintenance.

뿐만 아니라, 본 발명에 의하면 인양 가설중량을 감소시킬 수 있으므로 소규모 장비의 사용이 가능하며, 공사 중 교량하면의 공간 활용성과 공사장 인근주변의 점용공간 감소와 공사기간 단축으로 민원이 감소되는 우수한 효과도 얻을 수 있다. In addition, according to the present invention, it is possible to reduce the lifting construction weight, so that the use of small-scale equipment is possible. You can get it.

도 1a는 종래의 기술에 따른 강합성 연속교를 도시한 정단면도이다.
도 1b는 종래의 기술에 따른 강합성 연속교를 도시한 측단면도이다.
도 2a는 종래의 기술에 따른 강합성 연속교에서 덧댐판과 필렛 용접을 이용하여 거더들을 연결시킨 구조를 도시한 측단면 및 정단면도이다.
도 2b는 종래의 횡가로보를 사용한 연속교를 도시한 설명도이다.
도 3은 종래의 기술에 따른 강합성 연속교에 대한 전체계 모델링을 단계적으로 도시한 설명도이다.
도 4a는 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교를 도시한 정단면도이다.
도 4b는 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교를 도시한 측단면도이다.
도 5a는 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교의 지점부에서 거더들이 콘크리트 가로보를 이용하여 합성되는 구조를 도시한 측단면도이다.
도 5b는 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교의 지점부에서 거더들이 교량 받침부를 이용하지 않고, 교각 또는 교대에 직접 설치된 교량구조를 도시한 정단면도이다.
도 6a는 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교에 대한 전체계 모델링을 단계적으로 도시한 설명도이다.
도 6b는 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교의 정모멘트 구간과 부모멘트 구간에서 발생하는 압축응력과 인장응력을 기존의 강합성 연속교 구조에 비교하여 나타낸 설명도이다.
도 7은 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교 시공방법을 단계적으로 도시한 플로우 챠트이다.
도 8a는 본 발명에 따라서 지점부 상부면에 교량 받침부 설치용 보강판을 매입 후, 1차 콘크리트 가로보 철근 배근 및 거더 받침틀을 설치하는 단계를 도시한 설명도이다.
도 8b는 본 발명에 따라서 거더 하면보다 조금 낮은 위치까지 콘크리트를 1차 타설 및 양생하는 단계를 도시한 설명도이다.
도 8c는 본 발명에 따라서 사전에 제작된 거더를 콘크리트 가로보상의 거더 받침틀에 거치하는 단계를 도시한 설명도이다.
도 9a는 본 발명에 따라서 거치된 거더를 지지대로 하여 바닥판 타설용 동바리 및 2차 거푸집을 설치하는 단계를 도시한 설명도이다.
도 9b는 본 발명에 따라서 2차 콘크리트 가로보 및 바닥판 콘크리트를 동시에 타설하여 양생시키는 단계를 도시한 설명도이다.
도 9c는 본 발명에 따라서 바닥판 양생완료 후, 방호벽 및 난간 등을 설치하는 단계를 도시한 설명도이다.
1A is a front sectional view showing a steel composite continuous bridge according to the related art.
Figure 1b is a side cross-sectional view showing a rigid composite bridge according to the prior art.
Figure 2a is a side cross-sectional view and a front sectional view showing a structure in which the girder is connected by using an additional plate and fillet welding in a steel composite continuous bridge according to the prior art.
It is explanatory drawing which shows the continuous bridge using the conventional horizontal crossbeam.
FIG. 3 is an explanatory diagram showing the overall system modeling for the steel composite continuous bridge according to the prior art step by step.
Figure 4a is a front sectional view showing a steel composite continuous bridge using a concrete crossbeam according to the present invention.
Figure 4b is a side cross-sectional view showing a steel composite continuous bridge using a concrete crossbeam according to the present invention.
5A is a side cross-sectional view illustrating a structure in which girders are synthesized using a concrete cross beam at a point portion of a steel composite continuous bridge using a concrete cross beam according to the present invention.
5B is a sectional view showing a bridge structure directly installed on a pier or alternating girder at a point of a steel composite continuous bridge using a concrete crossbeam according to the present invention, without using a bridge support.
Figure 6a is an explanatory diagram showing the overall system modeling for the steel composite continuous bridge using a concrete crossbeam in accordance with the present invention step by step.
6B is an explanatory view showing the compressive and tensile stresses generated in the static moment section and the parent moment section of the steel composite continuous bridge using the concrete crossbeam according to the present invention in comparison with the conventional steel composite continuous bridge structure.
Figure 7 is a flow chart illustrating a step-by-step method of constructing a steel composite continuous bridge using a concrete crossbeam according to the present invention.
8A is an explanatory diagram illustrating a step of installing a primary concrete cross beam reinforcement and a girder support frame after buying a reinforcement plate for installing a bridge support on an upper surface of a branch according to the present invention.
8B is an explanatory view showing the steps of primary casting and curing concrete to a position slightly lower than the lower surface of the girder according to the present invention.
Figure 8c is an explanatory diagram showing the step of mounting the girder prepared in accordance with the present invention to the girder support frame of the concrete transverse compensation.
Figure 9a is an explanatory view showing the step of installing the bottom plate cast copper and secondary formwork as a support for the girder mounted in accordance with the present invention.
Figure 9b is an explanatory diagram showing the step of curing by pouring the secondary concrete crossbeam and the bottom plate concrete simultaneously in accordance with the present invention.
Figure 9c is an explanatory diagram showing a step of installing a protective wall, railings, etc. after completion of curing the bottom plate according to the present invention.

이하, 본 발명의 바람직한 실시 예를 도면을 참조하여 보다 상세히 설명하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 도 4a 및 도 4b에 도시된 바와 같이, 거더(110)간의 직접적인 연결 없이 콘크리트 가로보(150)와 거더(110)의 합성거동으로 교량을 연속화한 것이다.As shown in FIGS. 4A and 4B, the steel composite continuous bridge 100 using the concrete crossbeam according to the present invention is a bridge with the composite behavior of the concrete crossbeam 150 and the girder 110 without direct connection between the girder 110. Is a sequential sequence.

본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 교각(120) 또는 교대(122)의 지점부(130)에서 교량 받침부 설치용 보강판(140) 상단에 콘크리트 가로보(150)를 설치하고, 상기 콘크리트 가로보(150)의 내부에는 거더(110)의 연결 단부를 매립시켜서 합성 연결시킨 구조인데, 이와 같은 콘크리트 가로보(150)는 거더(110)를 지지하기 위한 1차 콘크리트 가로보(150a)와, 거더(110)에 합성되어 거더(110)를 연결시키고, 거더(110) 상부의 바닥판 콘크리트(160)와 동시에 콘크리트 타설되어 일체로 형성된 2차 콘크리트 가로보(150b)로 이루어진다.The steel composite continuous bridge 100 using the concrete cross beam according to the present invention is installed on the top of the reinforcement plate 140 for installing the bridge support at the point portion 130 of the bridge 120 or the shift 122, the concrete cross beam 150 is installed. The interior of the concrete crossbeam 150 is a structure in which the connecting end of the girder 110 is embedded in the composite connection, such a concrete crossbeam 150 is a primary concrete crossbeam 150a for supporting the girder 110. And, it is synthesized to the girder 110 to connect the girder 110, at the same time the bottom plate concrete 160 of the top of the girder 110 is made of a concrete concrete cross beam 150b formed integrally.

즉 상기 콘크리트 가로보(150)는 도 5a에 도시된 바와 같이, 교각(120) 또는 교대(122)의 지점부(130)에서 교량 받침부 설치용 보강판(140)을 설치 후, 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)을 설치하고, 상기 거더 받침틀(154)에 설치되는 거더(110) 하면보다 조금 낮은 위치까지 콘크리트를 1차 타설 및 양생시킨 1차 콘크리트 가로보(150a)를 포함한다.That is, the concrete cross beam 150 is the first concrete cross beam reinforcement after installing the reinforcing plate 140 for installing the bridge support portion at the point portion 130 of the bridge 120 or shift 122, as shown in Figure 5a Install the reinforcement 152 and the girder support frame 154, and includes the primary concrete crossbeam 150a for primary casting and curing of concrete to a position slightly lower than the lower surface of the girder 110 installed on the girder support frame 154. do.

이와 같은 1차 콘크리트 가로보(150a)는 교각(120) 또는 교대(122)의 지점부(130)에서 교량 받침부 설치용 보강판(140) 상단에 형성되는 것으로서, 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)의 둘레에 1차 거푸집(미 도시)을 설치하고, 1차 콘크리트 가로보(150a)상의 거더 받침틀(154)에 거치될 거더(110)의 하면보다 5~15cm 낮은 높이까지 콘크리트를 1차 시공한 것으로서, 바람직하게는 콘크리트 가로보(150)가 거치될 거더(110) 하면보다 조금 낮은 높이, 약 10cm까지 시공된 것이다.The first concrete cross beam 150a is formed on the bridge reinforcement plate 140 at the top of the bridge portion 120 or the bridge portion 122 of the bridge 122, the first concrete cross beam reinforcement 152 And a primary formwork (not shown) around the girder support frame 154, and the concrete to a height lower than 5-15 cm lower than the lower surface of the girder 110 to be mounted on the girder support frame 154 on the primary concrete crossbeam 150a. As the first construction, preferably a little lower than the lower surface of the girder 110, the concrete crossbeam 150 is to be mounted, it is constructed to about 10cm.

그리고 상기 콘크리트 가로보(150)는 상기 1차 콘크리트 가로보(150a)의 상부에서 거더(110)를 1차 콘크리트 가로보(150a)상의 거더 받침틀(154)에 거치하고, 상기 거더(110)를 지지대로 하여 바닥판 타설용 동바리(172) 및 2차 거푸집(174)을 설치한 다음, 2차 콘크리트 가로보 철근 배근(176) 및 바닥판 철근 배근(미 도시) 후, 바닥판 콘크리트(160)와 동시에 타설하여 양생시킨 2차 콘크리트 가로보(150b)를 포함한다.The concrete cross beam 150 is mounted on the girder 110 on the primary concrete cross beam 150a on the girder support frame 154 on the primary concrete cross beam 150a and supports the girder 110 as a support. After installing the base plate copper 172 and the secondary formwork (174), and after the secondary concrete cross beam reinforcement (176) and the bottom plate reinforcement (not shown), and poured at the same time with the bottom plate concrete (160) Cured secondary concrete crossbeam 150b is included.

이와 같은 2차 콘크리트 가로보(150b)는 사전에 제작장에서 캠버를 고려하여 제작된 거더(110)를 거더 받침틀(154) 상에 일체로 매립 설치하는 것으로서, 상기 거더(110)는 그 단부에 마감판(112)을 용접하고, 콘크리트 가로보(150)와의 부착성 및 소요의 단면력에 저항할 수 있도록 거더(110)와 마감판(112)에 다수의 스터드(114) 및 철근 배근용 홀(미 도시)을 천공한 것으로서, 이와 같은 거더(110) 단부를 먼저 타설된 1차 콘크리트 가로보(150a) 상에 거치한다. Such secondary concrete cross beam 150b is to install the girder 110 manufactured in consideration of the camber in the manufacturing site in advance integrally embedded on the girder support frame 154, the girder 110 is finished at its end A plurality of studs 114 and reinforcing bar reinforcing holes (not shown) in the girder 110 and the finishing plate 112 so as to weld the plate 112 and resist adhesion to the concrete crossbeam 150 and the required cross-sectional force. ) As perforated, such end of the girder 110 is first mounted on the first concrete cross beam 150a.

그리고 2차 콘크리트 가로보(150b)의 철근 배근(176)을 하게 되며, 이와 같은 2차 콘크리트 가로보(150b)의 철근 배근(176)시, 거더(110)와의 저촉부분은 강제 거더(110)의 천공홀(미 도시)을 통하여 배근하게 된다.Then, the reinforcement 176 of the secondary concrete crossbeam 150b is made, and when the reinforcement 176 of the secondary concrete crossbeam 150b is in contact with the girder 110, the perforated portion of the girder 110 is drilled. Through the hall (not shown), you will be in close proximity.

또한 상기 거치된 거더(110)를 지지대로 하여 바닥판 타설용 동바리(172) 및 2차 거푸집(174)을 설치한 다음, 2차 콘크리트 가로보 철근 배근(176) 및 바닥판 철근 배근(미 도시) 후, 2차 콘크리트 가로보(150b) 및 바닥판 콘크리트(160)를 동시에 타설하여 구축하게 된다. In addition, the mounted girders 110 as a support for installing the base plate copper plate 172 and the secondary formwork 174, and then the secondary concrete cross beam reinforcement 176 and bottom plate reinforcement (not shown) Afterwards, the secondary concrete crossbeam 150b and the bottom plate concrete 160 are poured and built at the same time.

이와 같이 2차 콘크리트 가로보(150b)와 바닥판 콘크리트(160)를 동시에 타설 양생시키면 바닥판 콘크리트(160) 자중과 거더(110) 자중에 의해 내부 지점부(130)의 부모멘트가 발생되지 않게 된다.As such, when the secondary concrete crossbeam 150b and the bottom plate concrete 160 are cured at the same time, the parents of the inner point 130 are not generated due to the weight of the bottom plate concrete 160 and the weight of the girder 110. .

또한 이와 같이 바닥판 콘크리트(160) 타설 및 양생완료 후, 방호벽 및 난간(180) 등을 설치하게 되며, 이때에는 바닥판 타설용 거푸집 및 동바리(172)를 해체한 후, 방호벽 및 난간(180) 등을 설치하고, 동시에 신축이음 및 교량받침부(P), 도로 포장을 시행하여 교량을 완성하게 된다.In addition, after placing the concrete slab 160 and curing, the protective wall and the railing 180, etc. will be installed. In this case, after dismantling the floor slab formwork and copper bar 172, the protective wall and railing 180 At the same time, the bridge is completed by installing new joints, bridge support (P), and pavement.

한편, 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 도 5b에 도시된 바와 같이, 거더(110)가 직접 교각(120) 또는 교대(122)의 지점부(130)에 설치되는 교량구조에도 적용가능하다.On the other hand, the steel composite continuous bridge 100 using the concrete crossbeam according to the present invention, as shown in Figure 5b, the girder 110 is directly installed on the point portion 130 of the pier 120 or alternating 122 It is also applicable to bridge structures.

이와 같은 구조에서는 교각(120) 또는 교대(122)의 지점부(130)에 교량 받침부(P) 또는 교량 받침부 설치용 보강판(140)을 설치하지 않고, 직접 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)을 설치하게 된다.In such a structure, the primary concrete cross beam reinforcement 152 is directly installed without installing the bridge support part P or the reinforcement plate 140 for installing the bridge support part at the point portion 130 of the bridge 120 or the bridge 122. ) And the girder support frame 154 is installed.

즉 상기 콘크리트 가로보(150)는 교각(120) 또는 교대(122)의 지점부(130)에 1차 콘크리트 가로보 철근 배근 및 거더 받침틀을 설치하고, 상기 거더 받침틀에 설치되는 거더(110) 하면보다 조금 낮은 위치까지 콘크리트를 1차 타설 및 양생시킨 1차 콘크리트 가로보(150a)를 포함한다.That is, the concrete cross beam 150 is installed at the point portion 130 of the pier 120 or the shift 122, the primary concrete cross beam reinforcement and girder support frame, a little than the lower surface of the girder 110 is installed on the girder support frame It includes a primary concrete crossbeam 150a to pour and cure concrete to a low position.

이와 같은 1차 콘크리트 가로보(150a)는 그 상부에 거치될 거더(110) 하면보다 5~15cm 낮은 높이까지 콘크리트를 1차 시공한 것으로서, 바람직하게는 콘크리트 가로보(150)가 거치될 거더(110) 하면보다 조금 낮은 높이, 약10cm까지 시공된 것이다.Such a primary concrete crossbeam 150a is the first construction of concrete to a height of 5 to 15cm lower than the lower surface of the girder 110 to be mounted on its upper portion, preferably the concrete crossbeam 150 is mounted on the girder 110 It is constructed up to about 10cm in height slightly lower than the lower surface.

그리고 상기 1차 콘크리트 가로보(150a)의 상부에서 거더(110)를 콘크리트 가로보(150)상의 거더 받침틀에 거치하고, 상기 거더(110)를 지지대로 하여 바닥판 타설용 동바리 및 2차 거푸집을 설치한 다음, 2차 콘크리트 가로보 철근 배근 및 바닥판 철근 배근 후, 바닥판 콘크리트(160)와 동시에 타설하여 양생시킨 2차 콘크리트 가로보(150b)를 형성한 것이다.And the girder 110 is mounted on the girder support frame on the concrete crossbeam 150 from the upper portion of the primary concrete crossbeam 150a, and the bottom plate placing copper bar and secondary formwork are installed by supporting the girder 110 as a support. Next, after the secondary concrete cross beam reinforcement and the bottom plate reinforcement, the secondary concrete cross beam (150b) was formed by placing and curing at the same time with the bottom plate concrete 160.

이와 같은 구조의 콘크리트 가로보를 이용한 강합성 연속교(100)도 2차 콘크리트 가로보(150b)와 바닥판 콘크리트(160)가 동시에 타설 양생되어 바닥판 콘크리트(160) 자중과 거더(110) 자중에 의한 내부 지점부(130)의 부모멘트가 발생되지 않게 된다.The steel composite continuous bridge (100) using the concrete cross beam of such a structure is also cured by pouring the secondary concrete cross beam (150b) and the bottom plate concrete (160) at the same time, resulting from the bottom plate concrete (160) self-weight and the girder (110) self-weight. The parent of the internal point portion 130 is not generated.

또한 이와 같이 바닥판 콘크리트(160) 타설 및 양생완료 후에는 바닥판 타설용 거푸집 및 동바리를 해체시키고, 방호벽 및 난간(180) 등을 설치하게 되며, 동시에 신축이음 및 도로 포장을 시행하여 교량을 완성하게 된다.In addition, after placing and curing curing of the bottom plate concrete 160, the formwork and copper bar for placing the bottom plate are dismantled, and a barrier and handrail 180 are installed, and at the same time, the bridge is completed by performing expansion joints and road pavement. Done.

상기와 같이 구성된 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 1차 콘크리트 가로보(150a)상에서 서로 분리되어 거치된 거더(110)에, 바닥판 콘크리트(160) 하중과 거더(110) 하중을 동시에 가하여 콘크리트 타설하고 양생시키는 것으로서, 바닥판 콘크리트(160) 타설과 동시에 내부 지점부(130)는 변위가 흡수되어 어떠한 단면력도 발생되지 않으며 단지 거더(110)에만 휨 정모멘트가 발생하게 된다.The steel composite continuous bridge 100 using the concrete cross beam according to the present invention configured as described above is mounted on the girder 110 separated from each other on the primary concrete cross beam 150a, and the bottom plate concrete 160 load and the girder 110. The concrete is placed and cured by applying a load at the same time, and at the same time as the bottom plate concrete 160 is placed, the internal point portion 130 is absorbed by displacement so that no cross-sectional force is generated and only a bending moment is generated in the girder 110 only. do.

본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 전체계 모델링의 경우, 도 3에 도시된 바와 같은 종래의 강합성 연속교(10)와는 다르게, 도 6a에 도시된 바와 같은 단계를 통해서 이루어진다.The steel composite continuous bridge 100 using the concrete crossbeam according to the present invention is different from the conventional steel composite continuous bridge 10 as shown in FIG. It is done through

먼저, 1단계는 거더(110)가 서로 분리된 상태에서 1차 콘크리트 가로보(150a) 타설분과 거더(110) 하중을 모델링하고, 2단계는 거더(110)가 2차 콘크리트 가로보(150b)에 의해서 합성되기 이전의 상태에서 2차 콘크리트 가로보(150b)와 바닥판 콘크리트(160) 사하중을 모델링한다.First, the first step is to model the first concrete cross beam 150a pours and the girder 110 load in the state that the girder 110 is separated from each other, the second step is the girder 110 by the secondary concrete cross beam 150b The secondary concrete cross beam 150b and the bottom plate concrete 160 dead weight are modeled in the state before synthesis.

그리고 3단계는 2차 콘크리트 가로보(150b)에 의한 거더(110)의 합성 후, 연석, 난간(180) 및 도로 포장을 설치한 다음, 사하중을 모델링하며, 4단계는 2차 콘크리트 가로보(150b)에 의한 거더(110)의 합성 후, 활하중을 모델링하고, 5단계로는 온도변화, 지점침하, 지진하중 및 풍하중을 고려하여 모델링한다.The third step is after the synthesis of the girder 110 by the secondary concrete crossbeam 150b, install curbstone, railing 180 and road pavement, and then model dead load, and the fourth step is the secondary concrete crossbeam 150b. After the synthesis of the girder 110 by, the live load is modeled, and in five steps modeling in consideration of the temperature change, point settlement, earthquake load and wind load.

이와 같이 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 도 6b에 도시된 바와 같이, 거더(110)의 정모멘트 구간 및 부모멘트 구간에서 거더(110)의 상,하부 플랜지간 응력차를 크게 감소시킬 수 있게 된다.As described above, the steel composite continuous bridge 100 using the concrete crossbeam according to the present invention has a stress between upper and lower flanges of the girder 110 in the constant moment section and the parent section section of the girder 110, as shown in FIG. 6B. The car can be greatly reduced.

즉, 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 상기와 같이 시공할 경우, 종래의 강합성 연속교(10)에 비하여 정모멘트 구간에서는 압축응력은 증가하고, 인장응력은 감소하며, 부모멘트 구간에서는 이와 반대로 압축응력은 감소하고, 인장응력은 증가한다.That is, when the steel composite continuous bridge 100 using the concrete crossbeam according to the present invention is constructed as described above, the compressive stress is increased in the constant moment section, the tensile stress is reduced compared to the conventional steel composite continuous bridge 10 On the contrary, compressive stress decreases and tensile stress increases in parent section.

본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)에서 얻어지는 구조단면은 최종적으로, 거더(110), 콘크리트 가로보(150), 바닥판 콘크리트(160)가 일체화되어 합성형 단면으로 거동한다.The structural cross section obtained from the steel composite continuous bridge 100 using the concrete crossbeam according to the present invention finally, the girder 110, the concrete crossbeam 150, the bottom plate concrete 160 is integrated to behave as a composite cross section.

종래의 강합성 연속교(10)의 단면 결정은 부모멘트 최대부의 지점부(70)의 단면력에 의해 내부지점부(70) 단면을 결정하고, 정모멘트가 최대인 중앙부 단면은 단면간 두께변화 차이, 대략 8~10mm와 단면변화수에 의거하여 결정되어 지점부(70)의 응력수준이 95%선에서 결정될 경우, 지간중앙부는 75%정도의 응력수준에서 단면이 결정된다.The cross section of the conventional rigid composite bridge 10 determines the cross section of the internal point portion 70 by the cross-sectional force of the point portion 70 of the parent moment maximum, the difference in the thickness change between the cross section of the central section with the largest positive moment When the stress level of the point portion 70 is determined at the 95% line, the cross section is determined at the stress level of about 75%.

또한 종래의 강합성 연속교(10)는 거더(30)를 먼저 시공하고 바닥판 콘크리트(40)를 시공하므로 바닥판 콘크리트(40) 하중이 내부 지점부(70)의 부모멘트로 발생된다. 이는 바닥판 콘크리트(40)에 프리스트레스를 도입하지 않을 경우, 바닥판에 과대한 철근배근이 요구되며 철근콘크리트 특성상 균열을 허용하는 조건이므로 바닥판 내구성 저하요인이 일어나게 된다.In addition, since the conventional rigid composite bridge 10 constructs the girder 30 first and then constructs the bottom plate concrete 40, the bottom plate concrete 40 load is generated as a parent of the inner point part 70. This is when the pre-stress is not introduced to the bottom plate concrete 40, excessive reinforcement is required in the bottom plate and because the cracking conditions due to the characteristics of the reinforced concrete causes the bottom plate durability degradation factors.

그러나 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 이전의 강합성 연속교(10)와는 다르게 바닥판 콘크리트(160) 하중이 타설되어 양생되어 합성되기 까지 휨 부모멘트는 발생하지 않고 정모멘트만 발생한다.However, the steel composite continuous bridge 100 using the concrete cross beam according to the present invention, unlike the previous composite steel continuous bridge 10, the bottom plate concrete 160 load is cast and cured without curing bending moment does not occur Only positive moment occurs.

이는 결국 지점부(130)에서 휨 부모멘트는 거더(110)가 연결되는 것과 같이, 지점부(130)에서 구조물이 연속으로 연결, 또는 바닥판 콘크리트(160) 타설과 같이 지점부(130) 위를 연속으로 형성시킬 때 발생하는 것으로 볼 수 있다.This is because the bending parent at the point portion 130, as the girder 110 is connected, the structure is continuously connected at the point portion 130, or the bottom portion 130, such as placing the bottom plate concrete 160 It can be seen that occurs when forming a continuous.

따라서 거더(110)를 기준으로 하면 휨 부모멘트는 바닥판 콘크리트(160) 양생후, 거더(110)와 합성되어 2차 사하중인 방호벽 하중, 포장하중등과 활하중등에 의해서만 휨 부모멘트가 발생하게 된다.Therefore, based on the girder 110, the bending parent moment is cured after the curing of the bottom plate concrete 160, and is combined with the girder 110 to generate the bending parent moment only by the secondary dead load of the firewall load, the paving load, and the live load. .

대략 거더(110)의 합성전 사하중(바닥판 콘크리트(160) 하중)/전체하중 ≒0.5이므로 바닥판 콘크리트(160) 하중만 휨 부모멘트를 발생하지 않아도 부모멘트 구간의 단면력은 크게 감소될 수 있게 된다.Since the approximate total transfer load of the girders 110 (the bottom plate concrete 160 load) / total load ≒ 0.5, the cross section force of the parent section section can be greatly reduced even if the sole plate concrete 160 load does not generate the bending parent moment. do.

따라서 거더(110)만을 고려하여 보면 상하부 응력배분상태가 균등한 방향으로 변하게 되며, 이는 형강사용시 더욱 중요한 강점이 될 수 있다.Therefore, considering only the girder 110, the upper and lower stress distribution state is changed in an even direction, which may be a more important strength when using the steel.

즉 형강은 상하부 플랜지의 두께가 동일하므로, 거더(110)에 등분포하중이 작용하면 상부는 압축응력, 하부는 인장응력이 발생하고 지점부(130)에서는 반대 작용이 발생한다. That is, since the upper and lower flanges have the same thickness, the upper and lower portions of the upper and lower flanges have the same compressive stress, and the lower portion generates tensile stress and the opposite portion occurs in the branch portion 130.

이때 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100)는 거더(110), 콘크리트 가로보(150), 바닥판 콘크리트(160)들이 서로 합성된 이후에 지점부(130)에서 휨 부모멘트가 발생되므로, 교량의 슬래브 완성이전까지 거더(110)의 상,하부는 각각 압축,인장응력이 균등하게 발생하게 되어 전체적으로 거더(110)의 단면력이 크게 감소되는 우수한 효과를 얻을 수 있는 것이다.At this time, the rigid composite bridge 100 using the concrete crossbeam according to the present invention is the bending girders at the point portion 130 after the girder 110, the concrete crossbeam 150, the bottom plate concrete 160 are synthesized with each other Since the upper and lower portions of the girder 110 until the completion of the slab of the bridge, the compression and the tensile stress are generated evenly, so that the overall cross-sectional force of the girder 110 can be greatly reduced.

이하, 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교 시공방법(200)을 도면을 참조하여 보다 상세히 설명하기로 한다.Hereinafter, a method of constructing a continuous composite bridge 200 using a concrete crossbeam according to the present invention will be described in more detail with reference to the accompanying drawings.

본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교 시공방법(200)은 먼저 도 7에 도시된 바와 같이, 교각(120) 및 교대(122)를 포함하는 지점부(130)의 상부면에 교량 받침부 설치용 보강판(140)을 매입 후, 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)을 설치하는 단계(S1)가 이루어진다.Steel composite continuous bridge construction method 200 using the concrete cross beam according to the present invention first, as shown in Figure 7, the bridge bearing on the upper surface of the point portion 130 including the bridge 120 and the shift 122 After purchasing the secondary installation reinforcing plate 140, a step (S1) of installing the primary concrete cross beam reinforcement 152 and the girder support frame 154 is made.

이와 같은 단계(S1)는 도 8a에 도시된 바와 같이, 교각(120) 또는 교대(122)의 지점부(130) 상부면에 교량 받침부 설치용 보강판(140)을 매입한 후, 그 위에 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)을 설치하게 된다.This step (S1) is, as shown in Figure 8a, after the bridge reinforcement plate for installing the bridge support portion 140 to the upper surface of the point portion 130 of the bridge 120 or the shift 122, and thereafter 1 Car concrete cross beam reinforcement 152 and the girder support frame 154 will be installed.

한편, 이와 같은 단계(S1)에서 도 5b에 도시된 바와 같이, 거더(110)가 직접 교각(120) 또는 교대(122)의 지점부(130)에 설치되는 교량구조에서는 이와 같은 교량 받침부 설치용 보강판(140)을 설치하지 않고, 교각(120) 또는 교대(122)의 지점부(130)에 직접 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)을 설치할 수 있음은 물론이다.Meanwhile, as shown in FIG. 5B in the step S1, in the bridge structure in which the girder 110 is directly installed at the point portion 130 of the bridge 120 or the bridge 122, such a bridge support part is installed. Without installing the reinforcing plate 140, the primary concrete cross beam reinforcement 152 and the girder support frame 154 can be installed directly on the point portion 130 of the pier 120 or alternating 122.

그리고 다음으로는 콘크리트 가로보(150)와 거더(110)의 합성 작용이 원활하도록 거더(110) 하면보다 조금 낮은 위치까지 콘크리트를 1차 타설 및 양생하는 단계(S2)가 이루어진다.Then, the first step of placing and curing concrete to a position slightly lower than the lower surface of the girder 110 so that the composite action of the concrete crossbeam 150 and the girder 110 is made (S2).

이와 같은 단계(S2)는 도 8b에 도시된 바와 같이, 교각(120) 또는 교대(122)의 지점부(130)에서 교량 받침부 설치용 보강판(140) 상단에서 1차 콘크리트 가로보 철근 배근(152) 및 거더 받침틀(154)의 둘레에 1차 거푸집(미 도시)을 설치하고, 거더(110) 하면보다 5~15cm 낮은 높이까지 콘크리트를 1차 시공하는 것으로, 바람직하게는 거더 받침틀(154)에 거치될 거더(110) 하면보다 조금 낮은 높이, 약10cm까지 시공하게 된다.This step (S2), as shown in Figure 8b, the first concrete cross beam reinforcement 152 at the top of the reinforcement plate 140 for the bridge support portion installation at the point portion 130 of the bridge 120 or shift 122 ) And the primary formwork (not shown) around the girder support frame 154, and the first construction of concrete to a height of 5 ~ 15cm lower than the lower surface of the girder 110, preferably in the girder support frame 154 A little lower than the bottom of the girder 110 to be mounted, the construction will be up to about 10cm.

또한 다음으로는 사전에 제작된 거더(110)를 콘크리트 가로보(150)상의 거더 받침틀(154)에 거치하는 단계(S3)가 이루어진다.In addition, the next step (S3) is made to mount the girder 110 prepared in advance on the girder support frame 154 on the concrete crossbeam 150.

이와 같은 단계(S3)는 도 8c에 도시된 바와 같이, 사전에 제작장에서 캠버를 고려하여 제작된 거더(110)를 거더 받침틀(154) 상에 설치하는 것으로서, 거더(110)의 단부에는 마감판(112)을 용접하고, 콘크리트 가로보(150)와의 부착성 및 소요의 단면력에 저항할 수 있도록 거더(110)와 마감판(112)에 스터드(114) 및 철근 배근용 홀(미 도시)을 천공하여 제작한 거더(110) 단부를 먼저 타설된 1차 콘크리트 가로보(150a)상에 거치하는 단계이다(도 5a 참조).This step (S3) is, as shown in Figure 8c, in advance to install the girder 110 made on the girder support frame 154 in consideration of the camber at the manufacturing site, the end of the girder 110 is finished A stud 114 and a reinforcing bar hole (not shown) are formed in the girder 110 and the finishing plate 112 to weld the plate 112 and resist adhesion to the concrete crossbeam 150 and the required cross-sectional force. A step of mounting the end of the girder 110 manufactured by drilling on the first concrete cross beam 150a that was first placed (see FIG. 5A).

그리고 2차 콘크리트 가로보(150b)의 철근배근(176)이 이루어지며, 이와 같은 2차 콘크리트 가로보(150b)의 철근 배근(176)시, 거더(110)와의 저촉부분은 강제 거더(110)의 천공홀(미 도시)을 통하여 배근하게 된다.And the reinforcement 176 of the secondary concrete crossbeam 150b is made, when the reinforcement 176 of the secondary concrete crossbeam 150b, the contact portion with the girder 110 is perforated of the girder 110. Through the hall (not shown), you will be in close proximity.

또한 다음으로는 상기 거치된 거더(110)를 지지대로 하여 바닥판 타설용 동바리(172) 및 2차 거푸집(174)을 설치하는 단계(S4)가 이루어진다.In addition, the step (S4) is made to install the bottom plate cast copper 172 and the secondary formwork 174 by supporting the mounted girders 110.

상기 바닥판 타설용 동바리(172) 및 2차 거푸집(174)을 설치하는 단계(S4)는 도 9a에 도시된 바와 같이, 바닥판 콘크리트(160) 타설용 동바리(172)와 거푸집(174)을 거더(110)에 지지시켜 설치하며, 거더(110) 자중과 바닥판 콘크리트(160) 및 거푸집(미 도시)과 동바리(172) 하중을 동시에 거더(110)가 지지하도록 설치하게 된다.Step (S4) to install the bottom plate pour copper 172 and the secondary formwork 174, as shown in Figure 9a, the bottom plate concrete 160 pour copper 172 and the formwork (174) It is installed to support the girder 110, and the girder 110 is installed to support the weight of the girder 110 and the bottom plate concrete 160 and the formwork (not shown) and the club 172 at the same time.

그리고 다음으로는 바닥판 철근 배근(미 도시) 후, 2차 콘크리트 가로보(150b) 및 바닥판 콘크리트(160)를 동시에 타설하여 양생시키는 단계(S5)가 이루어진다.Next, after the bottom plate reinforcement (not shown), a step (S5) is made by pouring the secondary concrete crossbeam 150b and the bottom plate concrete 160 at the same time.

이와 같은 단계(S5)는 도 9b에 도시된 바와 같이, 거더(110)에 지지된 바닥판 타설용 거푸집(미 도시) 내부에서 바닥판 콘크리트(160) 철근배근(미 도시)을 시행한 후, 2차 콘크리트 가로보(150b), 즉 잔여분과 바닥판 콘크리트(160)를 동시에 타설 양생하여 바닥판 콘크리트(160) 자중과 거더(110) 자중에 의해 내부 지점부(130)의 부모멘트가 발생되지 않도록 시공하게 된다.This step (S5), as shown in Figure 9b, after performing the bottom plate concrete 160 reinforcement (not shown) in the bottom plate pouring form (not shown) supported on the girder 110, The secondary concrete crossbeam 150b, that is, the remnant and the bottom plate concrete 160 are cured at the same time, so that the parents of the inner point 130 are not generated by the self weight of the bottom plate concrete 160 and the self weight of the girder 110. It will be constructed.

또한 다음으로는 상기와 같이 바닥판 콘크리트(160) 타설 및 양생완료 후, 방호벽 및 난간(180) 등을 설치하는 단계(S6)가 이루어지는데, 이와 같은 단계(S6)는 도 9c에 도시된 바와 같이, 바닥판 타설용 거푸집 및 동바리(172)를 해체한 후, 방호벽 및 난간(180) 등을 설치하게 되며, 동시에 신축이음 및 교량받침부(P), 도로 포장을 시행하여 교량을 완성하게 된다.In addition, after the bottom plate concrete 160 is placed and cured as described above, a step (S6) is performed to install a protective wall and a railing 180, and the like (S6) is shown in FIG. 9C. Likewise, after dismantling the bottom plate formwork and copper bar 172, to install the protective wall and railing 180, and at the same time to perform the expansion joint and bridge support (P), pavement to complete the bridge .

여기서 교량받침부(P)는 통상적인 방식으로 교량 받침부 설치용 보강판(140)을 대신하여 설치될 수 있다.Here, the bridge support portion (P) may be installed in place of the bridge reinforcement plate 140 for installing the bridge support in a conventional manner.

상기와 같은 본 발명에 따른 콘크리트 가로보를 이용한 강합성 연속교(100) 및 그 시공방법(200)은 강합성 연속교량 시공 중, 거더(110)간의 직접적인 연결 없이 콘크리트 가로보(150)와 거더(110)의 합성작용에 의해 다경간 구조를 연속구조로 실현할 수 있다. The steel composite continuous bridge 100 and the construction method 200 using the concrete cross beam according to the present invention as described above, the concrete crossbeam 150 and the girder 110 without a direct connection between the girder 110 during the construction of the composite continuous bridge The multi-span structure can be realized as a continuous structure by the synthesizing action.

따라서 작업 현장에서의 거더(110)의 직접적인 이음작업이 불필요하여 전문적인 인력이 불필요하고, 부모멘트 단면력의 분배를 통한 단면효율성 개선과, 감소된 부모멘트에 의한 지점부(130)의 바닥판 균열감소로 교량의 경제성과 내구성을 크게 증진시킬 수 있다.Therefore, it is not necessary to directly joint work of the girder 110 at the work site, and no professional manpower is needed, and the efficiency of the section through the distribution of the parental section force is improved, and the bottom plate crack of the branch part 130 is reduced due to the reduced parental force. Reduction can greatly increase the economics and durability of the bridge.

그리고 본 발명은 지점부(130)인 교각(120) 또는 교대(122) 상면에 1차 콘크리트 가로보(150a)를 먼저 설치하고, 거더 받침틀(154) 상에 거더(110)의 양 단부를 거치하되 서로 연결되지 않도록 하므로써, 시공과정에서 지점부(130)에 휨 부모멘트가 발생하지 않게 되므로 단면을 크게 설계할 필요가 없다. And the present invention is first installed the first concrete cross beam 150a on the pier 120 or the shift 122, the branch portion 130, and to mount both ends of the girder 110 on the girder support frame 154 By not being connected to each other, the bending portion does not occur in the point portion 130 during the construction process, it is not necessary to design a large cross section.

또한 1차 콘크리트 가로보(150a)의 상부에 바닥판 콘크리트(160)와 2차 콘크리트 가로보(150b)를 동시에 타설하여 교량을 완성시키게 되며, 이러한 과정에서 거더(110), 콘크리트 가로보(150), 바닥판 콘크리트(160)가 일체화되면 거더(110)가 서로 연결되므로 휨 부모멘트가 발생되지만, 이러한 휨 부모멘트에 대하여 거더(110), 콘크리트 가로보(150), 바닥판 콘크리트(160)가 일체화된 합성단면으로 저항하므로 거더(110)의 단면을 획기적으로 줄일 수 있는 우수한 효과를 얻게 된다.In addition, the bottom plate concrete 160 and the secondary concrete crossbeam 150b is placed at the same time on the top of the first concrete crossbeam 150a to complete the bridge. In this process, the girder 110, the concrete crossbeam 150, and the floor When the plate concrete 160 is integrated, the girder 110 is connected to each other, so that bending bending moments are generated. However, the girder 110, the concrete crossbeam 150, and the bottom plate concrete 160 are integrated with the bending bending moment. Since the resistance to the cross section is obtained an excellent effect that can significantly reduce the cross section of the girder (110).

그리고 본 발명은 거더(110)로서 기존의 형강제품을 사용할 수 있으므로, 자재비 및 제작비를 감소시킬 수 있고, 공사의 신속성과 경제성 증진이 가능하며, 콘크리트 가로보(150) 설치로 인한 상부구조 지지용 소요받침 개수 감소와 교량 인상을 위한 잭업 공간의 확보로 교량받침의 유지관리성이 크게 향상된다.And since the present invention can use the existing section steel products as girder 110, can reduce the material cost and manufacturing cost, it is possible to increase the speed and economic feasibility of the construction, required for supporting the superstructure due to the installation of concrete crossbeam 150 Maintainability of bridge bearings is greatly improved by reducing the number of bearings and securing jack-up space for raising the bridges.

또한 본 발명의 공법을 적용하는 최대 이점중의 하나는 도 5b에 도시된 바와 같이, 콘크리트 가로보(150)와 기둥, 즉 교각(120) 또는 교대(122)을 일체로 할 경우, 교량받침부(P)를 없앨 수도 있고 개수도 줄일 수도 있게 된다. In addition, one of the greatest advantages of applying the method of the present invention, as shown in Figure 5b, when the concrete cross beam 150 and the pillar, that is, the bridge 120 or alternating 122, the bridge support ( P) can be eliminated and the number can be reduced.

그 이유는 거더(110)를 교량받침부(P)에 바로 설치하는 것이 아니라 콘크리트 가로보(150)를 통해서 거더 받침틀(154)에 설치하기 때문이며, 이와 같이 교량받침부(P)를 줄이게 되면, 교량유지 관리대상의 감소와 더불어서 유지관리비 감소 및 편의성이 크게 증진되는 효과를 얻을 수 있다.The reason is that the girder 110 is not installed directly on the bridge support portion P, but is installed on the girder support frame 154 through the concrete cross beam 150, and thus, when the bridge support portion P is reduced, the bridge In addition to the reduction of maintenance targets, maintenance costs and convenience can be greatly improved.

뿐만 아니라, 본 발명은 거더(110) 단면을 축소시킬 수 있어서, 인양 가설중량을 감소시킬 수 있으므로 소규모 장비의 사용이 가능하며, 공사 중 교량하면의 공간 활용성과 공사장 인근주변의 점용공간 감소와 공사기간 단축으로 민원이 감소되는 우수한 효과도 얻을 수 있다.In addition, the present invention can reduce the cross section of the girder (110), can reduce the lifting weight, it is possible to use the small-scale equipment, the space utilization of the lower surface of the bridge during construction and the reduction of the occupied space around the construction site and construction A shorter period of time will also lead to a better effect of reducing complaints.

앞에서 설명되고, 도면에 도시된 본 발명의 일 실시예는 본 발명의 기술적사상을 한정하는 것으로 해석되어서는 안 된다. 본 발명의 보호범위는 청구범위에 기재된 사항에 의하여만 제한되고, 본 발명의 기술분야에서 통상의 지식을 가진 자는 본 발명의 기술적 사상을 다양한 형태로 개량 변경하는 것이 가능하다. 따라서 이러한 개량 및 변경은 통상의 지식을 가진 자에게 자명한 것인 한 본 발명의 보호범위에 속하게 된다.An embodiment of the present invention described above and shown in the drawings should not be construed as limiting the technical idea of the present invention. The scope of protection of the present invention is limited only by the matters described in the claims, and those skilled in the art will be able to modify the technical idea of the present invention in various forms. Accordingly, such improvements and modifications are within the scope of the present invention as long as they are obvious to those skilled in the art.

10...... 종래의 강합성 연속교
20...... 교각 22...... 교대
30...... 거더 40...... 바닥판 콘크리트
50...... 교량받침 60...... 덧댐판
62...... 필렛 용접 70...... 지점부
80...... 횡가로보를 사용한 종래의 연속교 82...... 횡가로보
90...... 긴장재 100..... 콘크리트 가로보를 이용한 강합성 연속교
110..... 거더 120...... 교각
122..... 교대 130...... 지점부
140..... 보강판 150...... 콘크리트 가로보
150a.... 1차 콘크리트 가로보 150b..... 2차 콘크리트 가로보
152..... 1차 콘크리트 가로보 철근 배근 154..... 거더 받침틀
160..... 바닥판 콘크리트 172...... 바닥판 타설용 동바리
174..... 2차 거푸집 176...... 2차 콘크리트 가로보 철근 배근
180..... 방호벽 및 난간 P...... 교량받침부
200..... 콘크리트 가로보를 이용한 강합성 연속교 시공방법
S1...... 지점부 상부면에 교량 받침부 설치용 보강판을 매입 후, 1차 콘크리트 가로보 철근 배근 및 거더 받침틀을 설치하는 단계
S2...... 거더 하면보다 낮은 위치까지 콘크리트를 1차 타설 및 양생하는 단계
S3...... 사전에 제작된 거더를 콘크리트 가로보상의 거더 받침틀에 거치하는 단계
S4...... 거더를 지지대로 하여 동바리 및 2차 거푸집을 설치하는 단계
S5...... 2차 콘크리트 가로보 및 바닥판 콘크리트를 동시에 타설,양생시키는 단계
S6...... 바닥판 양생완료 후, 방호벽 및 난간 등을 설치하는 단계
10 ...... Conventional steel composite continuous bridge
20 ...... Pier 22 ...... Shift
30 ...... Girder 40 ...... Slab Concrete
50 ...... Bridge Support 60 ...... Saddle Plate
62 ...... Fillet welding 70 ......
80 ...... A conventional continuous bridge using lateral crossbeams 82 ......
90 ...... Tension material 100 ..... Steel composite bridge using concrete crossbeams
110 ..... Girder 120 ...... Pier
122 ..... shift 130 ...... branch office
140 ..... Reinforcement plate 150 ...... Concrete crossbeam
150a .... 1st concrete crossbeam 150b ..... 2nd concrete crossbeam
152 ..... 1st concrete crossbeam reinforcement 154 ..... girder support
160 ..... Sole concrete 172 ...... Sole casting
174 ..... Secondary formwork 176 ...... Secondary concrete crossbeam reinforcement
180 ..... Firewalls and Railings P ...... Bridge Supports
200 ..... Construction method of steel composite bridge using concrete crossbeam
S1 ...... After installing the reinforcement plate for installing the bridge support on the upper part of the branch, installing the first concrete cross beam reinforcement and the girder support frame
S2 ...... Primary casting and curing of concrete to lower position than under girder
S3 ...... Mounting the prefabricated girder to the girders of concrete crossbeam
S4 ...... Step of installing club and secondary formwork with supporting girders
S5 ...... Stage and curing of secondary concrete crossbeams and bottom plate concrete at the same time
S6 ...... After curing the bottom plate, installing the protective wall and railing, etc.

Claims (11)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 지점부 상부면에 교량 받침부 설치용 보강판을 매입 후, 1차 콘크리트 가로보 철근 배근 및 거더 받침틀을 설치하고;
콘크리트 가로보와 거더의 합성 작용이 원활하도록 거더 하면보다 조금 낮은 위치까지 콘크리트를 1차 타설 및 양생하며;
사전에 제작된 거더를 콘크리트 가로보상의 거더 받침틀에 거치하고;
거치된 거더를 지지대로 하여 바닥판 타설용 동바리 및 2차 거푸집을 설치하며;
2차 콘크리트 가로보 철근 배근 및 바닥판 철근 배근 후, 2차 콘크리트 가로보 및 바닥판 콘크리트를 동시에 타설하여 양생시키고; 그리고
바닥판 양생완료 후, 방호벽 및 난간 등을 설치하는 단계;들을 포함하여 거더간의 연결 없이 콘크리트 가로보와의 합성거동으로 교량을 연속화하며,
상기 바닥판 타설용 동바리 및 2차 거푸집을 설치하는 단계는 바닥판 콘크리트 타설용 동바리와 거푸집을 거더에 지지시켜 설치하며, 거더 자중과 바닥판 콘크리트 및 거푸집과 동바리 하중을 동시에 거더가 지지하도록 설치하는 것임을 특징으로 하는 콘크리트 가로보를 이용한 강합성 연속교 시공방법.
After installing the reinforcement plate for bridge support installation on the upper part of the branch, install the primary concrete cross beam reinforcement and girder support frame;
Primary casting and curing of concrete to a position lower than the lower surface of the girder so that the composite action of the concrete crossbeam and the girder is smooth;
A prefabricated girder is mounted on a girder frame of concrete crossbeam;
Supporting the mounted girders to install bottom plate casting clubs and secondary formwork;
After the secondary concrete cross beam reinforcement and the bottom plate reinforcement, the secondary concrete cross beam and the bottom plate concrete are poured at the same time to cure; And
After completion of curing of the bottom plate, the step of installing a barrier and guardrail, etc .; including the continuous continuation of the bridge by the composite behavior with the concrete crossbeam without connecting the girder,
The step of installing the bottom plate casting clubs and secondary formwork is installed by supporting the bottom plate concrete casting clubs and formwork to the girder, and installed to support the weight of the girder and the bottom plate concrete and formwork and girder load at the same time Steel composite continuous bridge construction method using a concrete crossbeam characterized in that.
제6항에 있어서, 상기 거더를 설치하는 단계는 콘크리트 가로보와의 합성작용과 응력거동을 고려하여 거더 단부에 마감판을 설치하고, 설치된 마감판과 거더에 스터드 및 철근 배근용 홀을 천공하여 제작한 거더를 설치하는 것임을 특징으로 하는 콘크리트 가로보를 이용한 강합성 연속교 시공방법.According to claim 6, The step of installing the girder is manufactured by installing a finishing plate at the end of the girder in consideration of the composite action and the stress behavior of the concrete crossbeam, and drilling the studs and reinforcement holes in the installed finishing plate and girder Steel composite continuous bridge construction method using a concrete crossbeam, characterized in that to install a girder. 삭제delete 삭제delete 삭제delete 삭제delete
KR1020100085717A 2010-09-01 2010-09-01 Composite steel continuous bridge construction method using concrete cross beams KR101241401B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100085717A KR101241401B1 (en) 2010-09-01 2010-09-01 Composite steel continuous bridge construction method using concrete cross beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100085717A KR101241401B1 (en) 2010-09-01 2010-09-01 Composite steel continuous bridge construction method using concrete cross beams

Publications (2)

Publication Number Publication Date
KR20120022285A KR20120022285A (en) 2012-03-12
KR101241401B1 true KR101241401B1 (en) 2013-03-12

Family

ID=46130441

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100085717A KR101241401B1 (en) 2010-09-01 2010-09-01 Composite steel continuous bridge construction method using concrete cross beams

Country Status (1)

Country Link
KR (1) KR101241401B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507157B (en) * 2015-12-22 2017-03-22 深圳市福田建安建设集团有限公司 Construction method of variable curvature annular stiffening core cast-in-place concrete beam
CN106245532B (en) * 2016-08-30 2018-07-20 中国水利水电第四工程局有限公司 A method of accurately controlling cement concrete deck pavement elevation
KR102515783B1 (en) * 2021-09-16 2023-03-30 (주)에이치앤디건설 Unsupported formwork construction method using socket member

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080074832A (en) * 2008-07-24 2008-08-13 원대연 Precast concrete connection block and the continuity method of composite bridges using it
KR20100007300A (en) * 2008-07-14 2010-01-22 한국건설기술연구원 A steel composite bridge having steel plates connected by using concrete cross beams and its constructing method
KR20100089178A (en) * 2009-02-03 2010-08-12 연세대학교 산학협력단 Composite girder used steel-concrete and manufacturing method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100007300A (en) * 2008-07-14 2010-01-22 한국건설기술연구원 A steel composite bridge having steel plates connected by using concrete cross beams and its constructing method
KR20080074832A (en) * 2008-07-24 2008-08-13 원대연 Precast concrete connection block and the continuity method of composite bridges using it
KR20100089178A (en) * 2009-02-03 2010-08-12 연세대학교 산학협력단 Composite girder used steel-concrete and manufacturing method thereof

Also Published As

Publication number Publication date
KR20120022285A (en) 2012-03-12

Similar Documents

Publication Publication Date Title
KR100958014B1 (en) Construction method of steel composite girder bridge
JP4059909B2 (en) Composite panel structure and panel bridge structure and construction method of continuous composite girder bridge
KR101007708B1 (en) Semi-hinge rahman bridge and method for constructing the same
CN101851984B (en) Prefabricated steel-concrete composite beam
KR20010078870A (en) Development and construction methods of the prestressed composite truss beams
JP5050228B2 (en) Ramen bridge construction method with cane member
JP3588325B2 (en) Construction method of single span and multi span composite girder bridges
JP3908642B2 (en) Composite panel structure and panel bridge structure and construction method of continuous composite girder bridge
KR20120096605A (en) Bracket support type downward construction system and method
KR20130068158A (en) Reinforced concrete arch bridge of girder type uniting with superstructure and substructure and its automatic construction method
CN110644349A (en) Superstructure for wide box girder and short tower cable-stayed bridge and construction method
KR20120053869A (en) Bridge construction method using precast end-block with girder connection member
KR101241401B1 (en) Composite steel continuous bridge construction method using concrete cross beams
KR101601675B1 (en) The construction method of multicomposite Rahmen bridge
CN113322771A (en) Seamless bridge structure based on ultrahigh-toughness cement-based composite material and construction method
KR100621928B1 (en) Construction method of double composite plate girder railway bridge with precast concrete panels
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
KR100613862B1 (en) Light weight pc-steelgirder bridge construction
CN215482231U (en) Assembled waffle bridge panel combination case roof beam structure
CN211395312U (en) Upper structure for wide box girder and short tower cable-stayed bridge
KR100609825B1 (en) Preflexed rigid- frame bridge installed using prestressed upper structure and constructing method thereof
CN112853916A (en) Assembled waffle bridge panel combined box girder structure and construction method thereof
KR102515783B1 (en) Unsupported formwork construction method using socket member
CN220099642U (en) Perforated steel grid-high-strength concrete cast-in-situ combined bridge deck
CN212388355U (en) Bridge deck structure of steel truss bridge

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant