JP7124794B2 - Bridge replacement method - Google Patents

Bridge replacement method Download PDF

Info

Publication number
JP7124794B2
JP7124794B2 JP2019113059A JP2019113059A JP7124794B2 JP 7124794 B2 JP7124794 B2 JP 7124794B2 JP 2019113059 A JP2019113059 A JP 2019113059A JP 2019113059 A JP2019113059 A JP 2019113059A JP 7124794 B2 JP7124794 B2 JP 7124794B2
Authority
JP
Japan
Prior art keywords
superstructure
new
existing
bridge
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019113059A
Other languages
Japanese (ja)
Other versions
JP2020204209A (en
Inventor
敏 葛西
信也 中村
和人 伊佐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
JFE Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Engineering Corp filed Critical JFE Engineering Corp
Priority to JP2019113059A priority Critical patent/JP7124794B2/en
Publication of JP2020204209A publication Critical patent/JP2020204209A/en
Application granted granted Critical
Publication of JP7124794B2 publication Critical patent/JP7124794B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

特許法第30条第2項適用 説明場所 :JFE・MMB・川田・宮地・ピーエス三菱 特定建設工事共同企業体工事事務所(大阪府池田市石橋2-13-30 ニュースパークナカムラビル4F) 説 明 日:2019年5月28日Article 30, Paragraph 2 of the Patent Act applies Location of explanation: JFE/MMB/Kawada/Miyaji/PS Mitsubishi Specified Construction Joint Venture Construction Office (2-13-30 Ishibashi, Ikeda City, Osaka Prefecture) Explanation Date: May 28, 2019

本発明は、橋梁の既設上部工を新設上部工に架け替える工法に関し、詳細には、新設上部工を足場として使用する工法に関する。 The present invention relates to a construction method for replacing an existing superstructure of a bridge with a new superstructure, and more particularly to a construction method using the new superstructure as scaffolding.

供用下の道路橋を架け替える場合においては、仮設設備として設けられる足場(以下、仮設足場と記す。)を通行止め後に設置し、既設床版撤去、仮設足場撤去、既設桁撤去、新設桁架設、仮設足場設置、新設床版設置、仮設足場撤去という流れで工事を進めることが一般的である。このため、従来の一般的な架け替え工法においては、既設上部工の撤去の際に仮設足場の設置と撤去を行い、新設上部工の架設の際に、再度、仮設足場の設置と撤去というように、既設上部工撤去用の仮設足場の設置と撤去作業が、道路橋の架け替え工事の施工期間、および車両が通行できない時間が長くなる原因の1つになっている。 When replacing a road bridge in service, scaffolding installed as temporary equipment (hereinafter referred to as temporary scaffolding) will be installed after traffic is closed, removing existing floor slabs, removing temporary scaffolding, removing existing girders, erecting new girders, It is common to proceed with construction in the order of installing temporary scaffolding, installing new floor slabs, and removing the temporary scaffolding. For this reason, in the conventional general replacement method, temporary scaffolding is installed and removed when the existing superstructure is removed, and temporary scaffolding is installed and removed again when constructing the new superstructure. In addition, the installation and removal of temporary scaffolding for removing the existing superstructure is one of the causes of the lengthening of the construction period of road bridge replacement work and the length of time that vehicles cannot pass.

これに対して、特許文献1では、旧橋を撤去し新橋を架設する橋梁の撤去・架設工法において、旧橋上および旧橋付近に荷卸しされた新橋構成部材を全体またはブロック毎にクレーンまたは台車等にて架設位置に移動して仮設し、新橋にて旧橋を支持した上で旧橋をブロック毎に切断して搬出した後、新橋を架設位置に降下させて架設することにより、工期の短縮が可能となる技術が提案されている。 On the other hand, in Patent Document 1, in the bridge removal and construction method of removing the old bridge and constructing the new bridge, the new bridge constituent members unloaded on the old bridge and near the old bridge are collected by crane or trolley as a whole or for each block. After the old bridge is supported by the new bridge and cut into blocks and carried out, the new bridge is lowered to the construction position and erected, thereby shortening the construction period. Techniques that make it possible to shorten the time have been proposed.

特開2001-241012号公報Japanese Patent Application Laid-Open No. 2001-241012

しかしながら、特許文献1に記載の技術においても、足場等を構成する仮設材の添接が、架け替え対象の径間のほぼ全領域にわたって必要であり、工期の短縮が十分であるとは言えない。 However, even in the technique described in Patent Document 1, it is necessary to splice temporary materials that constitute scaffolding etc. over almost the entire area of the span to be replaced, and it cannot be said that the construction period is sufficiently shortened. .

本発明は、かかる点に鑑みてなされたものであり、橋梁を架け替える際の仮設足場を設ける領域および期間を削減して、橋梁架け替えに要する施工期間を従来よりも短縮させた橋梁架け替え工法を提供することを課題とする。 The present invention has been made in view of this point, and is a bridge replacement that reduces the construction period required for bridge replacement by reducing the area and period for providing temporary scaffolding when replacing a bridge. The task is to provide a construction method.

本発明は、以下の橋梁架け替え工法により、前記課題を解決したものである。 The present invention solves the above problems by the following bridge replacement construction method.

即ち、本発明に係る橋梁架け替え工法は、橋梁の既設上部工を新設上部工に架け替える橋梁架け替え工法であって、新設桁本体部および新設床版本体部を有してなる新設上部工本体部を、前記既設上部工の下方の第1位置にジャッキアップする第1ジャッキアップ工程と、前記第1ジャッキアップ工程でジャッキアップした前記新設上部工本体部を足場として利用して、架け替え対象の前記既設上部工を解体撤去する既設上部工解体撤去工程と、前記既設上部工解体撤去工程で前記既設上部工を解体撤去した後、前記既設上部工解体撤去工程で足場として利用した前記新設上部工本体部を、前記第1位置よりも高い供用時の高さ位置までさらにジャッキアップする第2ジャッキアップ工程と、前記第2ジャッキアップ工程で供用時の高さ位置までジャッキアップした前記新設上部工本体部の前記新設桁本体部の橋軸方向両端部に、下部工と連結する端部桁をそれぞれ連結する端部桁連結工程と、を有することを特徴とする橋梁架け替え工法である。 That is, the bridge replacement method according to the present invention is a bridge replacement method for replacing an existing bridge superstructure with a new superstructure, the new superstructure having a new girder body and a new floor slab main body. A first jack-up step of jacking up the main body to a first position below the existing superstructure, and a rebuilding using the new superstructure main body jacked up in the first jack-up step as a scaffold. An existing superstructure dismantling and removing step of dismantling and removing the existing superstructure of interest; A second jack-up step of further jacking up the superstructure main body to a height position for use higher than the first position, and the new construction jacked up to a height position for use in the second jack-up step. and an end girder connecting step of connecting end girder connecting to the substructure to both ends of the new girder main body of the superstructure main body in the bridge axis direction. .

ここで、本願において、新設桁および新設床版ならびに新設上部工の「本体部」とは、上方から見て下部工と重ならない部位であって、かつ、当該部位の橋軸方向両端部が下部工の近傍に位置する部位のことであり、当該部位は架け替え対象の径間の大部分の領域を占める部位である。 Here, in the present application, the “body portion” of the new girder, new floor slab, and new superstructure means a portion that does not overlap with the substructure when viewed from above, and both ends of the portion in the bridge axis direction are lower. It is a part located near the bridge, and the part occupies most of the area of the span to be replaced.

また、本願において、「下部工と連結」とは、少なくとも鉛直方向下向きの荷重が下部工に伝達可能な状態であることを意味する。 Further, in the present application, "connected to the substructure" means that at least a vertically downward load can be transmitted to the substructure.

前記新設上部工は、前記既設上部工の下方で作製してもよい。 The new superstructure may be fabricated below the existing superstructure.

前記橋梁は鋼橋であってもよい。 The bridge may be a steel bridge.

前記新設床版本体部は、鋼床版であってもよい。 The new floor slab main body may be a steel floor slab.

本発明に係る橋梁架け替え工法によれば、橋梁を架け替える際の仮設足場を設ける領域および期間を削減して、橋梁架け替えに要する施工期間を従来よりも短縮させた橋梁架け替え工法を提供することができる。 According to the bridge replacement method according to the present invention, there is provided a bridge replacement method that reduces the construction period required for bridge replacement by reducing the area and period for which temporary scaffolding is provided when replacing the bridge. can do.

本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 本発明の実施形態に係る橋梁架け替え工法の一工程を模式的に示す側面図FIG. 1 is a side view schematically showing one step of a bridge replacement construction method according to an embodiment of the present invention. 扛上設備16の高さを高くしていく一工程を模式的に示す側面図The side view which shows typically one process which raises the height of the lifting equipment 16. 扛上設備16の高さを高くしていく一工程を模式的に示す側面図The side view which shows typically one process which raises the height of the lifting equipment 16. 扛上設備16の高さを高くしていく一工程を模式的に示す側面図The side view which shows typically one process which raises the height of the lifting equipment 16. 扛上設備16の高さを高くしていく一工程を模式的に示す側面図The side view which shows typically one process which raises the height of the lifting equipment 16. 扛上設備16の高さを高くしていく一工程を模式的に示す側面図A side view schematically showing a process of increasing the height of the lifting equipment 16. 従来の工法において既設桁82を解体撤去する際の既設桁82の支持状況を模式的に示す側面図A side view schematically showing how the existing girder 82 is supported when the existing girder 82 is dismantled and removed in the conventional construction method.

以下、図面を参照して、本発明の実施形態に係る橋梁架け替え工法について詳細に説明する。 Hereinafter, a bridge replacement construction method according to an embodiment of the present invention will be described in detail with reference to the drawings.

図1~図8は本発明の実施形態に係る橋梁架け替え工法の各工程を模式的に示す側面図(架け替え対象径間を側方(橋軸直角方向)から見た側面図)である。 1 to 8 are side views (side views of the span to be replaced as seen from the side (perpendicular to the bridge axis)) schematically showing each step of the bridge replacement method according to the embodiment of the present invention. .

図1~図8を参照しつつ、本実施形態に係る橋梁架け替え工法の各工程(ステップS1~S8)について説明する。 Each step (steps S1 to S8) of the bridge replacement construction method according to the present embodiment will be described with reference to FIGS. 1 to 8. FIG.

なお、以下の説明では、下部工86、88の間に架設されている架け替え対象の既設上部工80を、新設上部工10で架け替えるものとして説明する。また、架け替え対象の橋梁は鋼橋であり、既設桁82は鋼桁であるものとし、また、新設桁12も鋼桁であるものとして説明する。ただし、本発明の適用対象の橋梁が鋼橋に限定されるわけではない。 In the following description, it is assumed that the existing superstructure 80 to be replaced, which is constructed between the substructures 86 and 88, is replaced with the new superstructure 10. FIG. The bridge to be replaced is a steel bridge, the existing girder 82 is a steel girder, and the new girder 12 is also a steel girder. However, the bridges to which the present invention is applied are not limited to steel bridges.

下部工86、88については、橋脚であっても橋台であってもよく、本実施形態に係る橋梁架け替え工法は、下部工の種類によらず、適用することができる。 The substructures 86 and 88 may be piers or abutments, and the bridge replacement construction method according to this embodiment can be applied regardless of the type of substructure.

<ステップS1>
架け替え対象の既設上部工80の下方の地面上に鋼板(図示せず)を敷き、その鋼板の上に橋軸方向に適当な間隔でサンドル50を配置する。そして、サンドル50の上に新設鋼桁部材を載置し、長手方向に隣り合う新設鋼桁部材同士を、図示せぬ添接鋼板および高力ボルト等を用いて連結して、新設桁本体部12Aを組み立てる。
<Step S1>
A steel plate (not shown) is laid on the ground below the existing superstructure 80 to be replaced, and the sandals 50 are placed on the steel plate at appropriate intervals in the bridge axis direction. Then, the new steel girder members are placed on the sandals 50, and the new steel girder members adjacent to each other in the longitudinal direction are connected using splicing steel plates and high-strength bolts (not shown) to form the new girder main body. Assemble 12A.

新設桁本体部12Aを組み立てた後、新設桁本体部12Aに新設床版本体部14Aを設置して、新設上部工本体部10Aを完成させる。設置する新設床版本体部14Aとして用いることができる床版の種類は特には限定されず、鋼床版、RC床版、PC床版、合成床版等を新設床版本体部14Aとして用いることができるが、他の形式の床版と比べて軽量で、かつ、新設桁本体部12Aへの設置作業も迅速に行うことができる観点から、新設床版本体部14Aの床版として鋼床版を用いることが好ましい。なお、いずれの床版を用いる場合も、舗装を行う時期は、供用時の高さまでジャッキアップさせた後であり、供用時の高さまでジャッキアップさせる前は、舗装を行うことは不要である。 After assembling the new girder main body 12A, the new floor slab main body 14A is installed on the new girder main body 12A to complete the new superstructure main body 10A. The type of floor slab that can be used as the new floor slab main body 14A to be installed is not particularly limited, and steel floor slabs, RC floor slabs, PC floor slabs, composite floor slabs, etc. can be used as the new floor slab main body 14A. However, from the viewpoint that it is lighter than other types of floor slabs and that the installation work on the new girder main body 12A can be performed quickly, a steel floor slab is used as the floor slab for the new floor slab main body 14A. is preferably used. In addition, when using any floor slab, the timing of pavement is after jacking up to the height for use, and before jacking up to the height for use, it is unnecessary to pave.

また、新設桁本体部12Aは、架け替え対象の既設上部工80の下方の地面上で組み立てなくてもよく、例えば工場等で組み立てて、大型トレーラー等により、架け替え対象の既設上部工80の下方に搬入してもよい。 Also, the new girder body 12A does not have to be assembled on the ground below the existing superstructure 80 to be replaced. You can bring it in below.

<ステップS2>
新設桁本体部12Aの両端部の下方に扛上設備16を配置する。扛上設備16は、伸縮部である油圧ジャッキ16Aと、サンドル16Bとからなる。なお、油圧ジャッキ16Aに替えて、扛上設備16の伸縮部にねじ式ジャッキを用いることも可能である。
<Step S2>
Raising facilities 16 are arranged below both ends of the newly installed girder main body 12A. The lifting equipment 16 consists of a hydraulic jack 16A, which is a telescopic part, and a sandal 16B. It is also possible to use a screw jack for the telescopic portion of the hoisting equipment 16 instead of the hydraulic jack 16A.

<ステップS3>
扛上設備16の高さを高くして、新設上部工本体部10Aを既設上部工80の解体撤去作業時の足場として必要な高さまで持ち上げる。ただし、用いる油圧ジャッキ16Aのストロークは必ずしも大きくなくてもよく、油圧ジャッキ16Aの伸縮ロッド16A1(図10参照)を伸縮させながらサンドル16Bを積み上げていくことで、扛上設備16の高さを高くしていくことができる。
<Step S3>
By increasing the height of the lifting equipment 16, the new superstructure main body part 10A is lifted up to a height required as a scaffolding for dismantling and removing the existing superstructure 80.例文帳に追加However, the stroke of the hydraulic jack 16A to be used does not necessarily have to be large. can continue.

図9~図13を用いて、扛上設備16の高さを高くしていくプロセスを説明する。 A process for increasing the height of the lifting equipment 16 will be described with reference to FIGS. 9 to 13. FIG.

図9は、新設桁本体部12Aの端部下方に油圧ジャッキ16Aとサンドル16Bを配置した状態を示している。この状態から、油圧ジャッキ16Aの伸縮ロッド16A1を伸ばし、図10に示すように、サンドル16Bの上方に空間を作る。そして、サンドル16Bの上方に作った空間に、図11に示すように、新たにサンドル16B1を挿入して、サンドル16B全体の高さを高くする。次に、図12に示すように、油圧ジャッキ16Aの伸縮ロッド16A1を一旦収縮させ、高さが高くなったサンドル16Bに荷重を移し替えるとともに、油圧ジャッキ16Aの上方に空間を作る。そして、油圧ジャッキ16Aを持ち上げて、図13に示すように、油圧ジャッキ16Aの下方にサンドル16B2を挿入して、油圧ジャッキ16Aの位置を高くする。図9~図13の作業を繰り返すことで、扛上設備16の高さを高くしていくことができるので、用いる油圧ジャッキ16Aのストロークは必ずしも大きくなくてもよい。 FIG. 9 shows a state in which a hydraulic jack 16A and a sandal 16B are arranged below the end of the new girder main body 12A. From this state, the extendable rod 16A1 of the hydraulic jack 16A is extended to create a space above the sandal 16B as shown in FIG. Then, as shown in FIG. 11, a new sandal 16B1 is inserted into the space created above the sandal 16B to increase the height of the entire sandal 16B. Next, as shown in FIG. 12, the extensible rod 16A1 of the hydraulic jack 16A is contracted once to transfer the load to the raised sandal 16B and create a space above the hydraulic jack 16A. Then, the hydraulic jack 16A is lifted, and as shown in FIG. 13, the sandal 16B2 is inserted below the hydraulic jack 16A to raise the position of the hydraulic jack 16A. By repeating the operations of FIGS. 9 to 13, the height of the lifting equipment 16 can be increased, so the stroke of the hydraulic jack 16A to be used does not necessarily have to be large.

もちろん、油圧ジャッキ16Aの1ストローク分の長さで、新設上部工本体部10Aを必要な高さまで(既設上部工80の下方近傍まで)持ち上げることができるのであれば、図9~図13の作業を行うことは不要である。 Of course, if the length of one stroke of the hydraulic jack 16A can lift the new superstructure main body 10A to the required height (up to near the bottom of the existing superstructure 80), the work of FIGS. is not required.

また、図13の段階で、油圧ジャッキ16Aの下方にサンドル16B2を挿入する代わりに、2台目の油圧ジャッキを挿入して、油圧ジャッキを2段に積み重ねて使用するようにしてもよい。 Also, at the stage of FIG. 13, instead of inserting the sandals 16B2 below the hydraulic jacks 16A, a second hydraulic jack may be inserted to stack the hydraulic jacks in two stages.

<ステップS4>
ステップS3で新設上部工本体部10Aを既設上部工80の解体撤去作業時の足場として必要な高さ(既設上部工80の下方近傍の高さ)まで持ち上げた後、図4に示すように、既設上部工80の既設桁82の下面と、新設上部工本体部10Aの新設桁本体部12Aの上面との間に、橋軸方向に適宜の間隔でサンドル18を配置し、サンドル18を介して既設上部工80の荷重が新設上部工本体部10Aに伝達されるようにして、既設上部工80をサンドル18を介して新設上部工本体部10Aで支持する。
<Step S4>
In step S3, after lifting the new superstructure main body 10A to a height required as a scaffold for dismantling and removing the existing superstructure 80 (height near the bottom of the existing superstructure 80), as shown in FIG. Between the lower surface of the existing girder 82 of the existing superstructure 80 and the upper surface of the new girder main body 12A of the new superstructure main body 10A, sandals 18 are arranged at appropriate intervals in the bridge axis direction. The existing superstructure 80 is supported by the new superstructure main body 10A via the sandals 18 so that the load of the existing superstructure 80 is transmitted to the new superstructure main body 10A.

<ステップS5>
ステップS4で既設上部工80をサンドル18を介して新設上部工本体部10Aで支持してから、既設上部工80の既設床版84を撤去し、既設床版84を撤去した後、既設桁82を撤去する。既設上部工80(既設桁82および既設床版84)の撤去を行った後の状態を図5に示す。
<Step S5>
In step S4, after the existing superstructure 80 is supported by the new superstructure main body 10A via the sandals 18, the existing floor slabs 84 of the existing superstructure 80 are removed, and after the existing floor slabs 84 are removed, the existing girders 82 are to remove. FIG. 5 shows the state after removing the existing superstructure 80 (the existing girder 82 and the existing floor slab 84).

既設上部工80を撤去する方法は、従来から一般的に用いられている方法を用いることができる。具体的には例えば、既設床版84については、ウォールソー等を用いて縦横に適宜の大きさに切断してクレーンで吊り上げて撤去すればよく、既設桁82については、高力ボルト接合を行っている高力ボルトを取り外すか、あるいはガス切断やワイヤーソー、ウォールソー等で適宜の長さに切断して、クレーンで吊り上げて撤去する。 As a method for removing the existing superstructure 80, a conventionally commonly used method can be used. Specifically, for example, the existing floor slab 84 can be cut lengthwise and crosswise into appropriate sizes using a wall saw or the like and lifted by a crane for removal. Either remove the high-strength bolts that are attached to it, or cut it to an appropriate length with a gas cutter, wire saw, wall saw, etc., lift it up with a crane, and remove it.

ここで、本実施形態に係る橋梁架け替え工法においては、新設上部工本体部10Aを足場として利用するため、既設上部工80の撤去のための仮設足場を設けることが不要であり、このため、施工期間および車両通行止めの期間を短くすることができる。 Here, in the bridge replacement construction method according to the present embodiment, since the new superstructure main body 10A is used as a scaffold, it is unnecessary to provide a temporary scaffold for removing the existing superstructure 80. Therefore, The construction period and vehicle traffic closure period can be shortened.

既設桁82を橋軸直角方向に切断する際には、切断した既設桁82の部位が落下しないように、切断位置がサンドル18の上方にくるような位置で切断する。サンドル18は、新設上部工本体部10Aの新設桁本体部12Aの上面に配置するので、サンドル18の配置位置を変えることは容易であり、本実施形態に係る橋梁架け替え工法おいては、既設桁82を橋軸直角方向に切断する際の切断位置を現場の状況に応じて変更することも容易である。一方、従来の工法では、図14に示すように、既設桁82を橋軸直角方向に切断する際の切断位置の下方にベント90が位置するように、ベント90を設ける必要があり、切断位置を変更する場合には、ベント90の位置を移動させるか、ベント90を新たに設ける必要があり、大きな労力を要していた。 When cutting the existing girder 82 in the direction perpendicular to the bridge axis, the cutting position is above the sandals 18 so that the cut part of the existing girder 82 does not drop. Since the sandals 18 are arranged on the upper surface of the new girder main body 12A of the new superstructure main body 10A, it is easy to change the arrangement position of the sandals 18. It is also easy to change the cutting position when cutting the girder 82 in the direction perpendicular to the bridge axis according to the site conditions. On the other hand, in the conventional construction method, as shown in FIG. In order to change the position of the vent 90, it is necessary to move the position of the vent 90 or provide a new vent 90, which requires a great deal of labor.

また、本実施形態に係る橋梁架け替え工法においては、図4に示すように、既設桁82を多数の箇所について容易にサンドル18で支持することができるので、既設桁82の切断位置を多数設けることも容易である。したがって、作業員を多数投入して、複数個所で既設桁82の切断作業を同時並行で行って、既設桁82の撤去に要する時間を短くすることもでき、架け替え工事の施工期間および車両通行止めの期間をより短くすることもできる。 In addition, in the bridge replacement construction method according to the present embodiment, as shown in FIG. 4, the existing girder 82 can be easily supported by the sandals 18 at a large number of locations. is also easy. Therefore, it is possible to reduce the time required to remove the existing girders 82 by using a large number of workers to simultaneously cut the existing girders 82 at a plurality of locations, thereby shortening the construction period of the rebuilding work and preventing vehicle traffic. period can be shortened.

また、本実施形態に係る橋梁架け替え工法においては、新設上部工本体部10Aを足場に用いているため、足場が非常に丈夫であり、足場上での作業の安全性を向上させることができ、また、万一、既設上部工80の部材の一部が落下するようなことがあっても受け止めることができ、この点からも安全性が高い。 In addition, in the bridge replacement construction method according to the present embodiment, since the new superstructure main body 10A is used as a scaffolding, the scaffolding is very strong, and the safety of the work on the scaffolding can be improved. In addition, even if a part of the members of the existing superstructure 80 should fall, it can be received, and the safety is high from this point as well.

<ステップS6>
ステップS5で既設上部工80(既設桁82および既設床版84)の撤去を行った後、図6に示すように、扛上設備16で新設上部工本体部10A(新設桁本体部12Aおよび新設床版本体部14A)を供用時の高さ位置まで上昇させる。
<Step S6>
After removing the existing superstructure 80 (existing girder 82 and existing floor slab 84) in step S5, as shown in FIG. The floor slab main body 14A) is raised to the height position for use.

<ステップS7>
新設上部工本体部10Aの新設桁本体部12Aを下部工86、88と連結させるための端部桁12Bを、下部工86、88上の所定の位置にそれぞれ配置して、新設上部工本体部10Aの新設桁本体部12Aの橋軸方向両端部それぞれに端部桁12Bを連結する。新設桁本体部12Aおよび端部桁12Bはどちらも鋼桁であり、添接鋼板および高力ボルトを用いた高力ボルト摩擦接合で連結し、新設桁12を完成させ、その後、端部桁12Bに取り付ける端部床版14Bを設置して、新設床版14を完成させて、新設上部工10を完成させる。
<Step S7>
The end girders 12B for connecting the new girder main body 12A of the new superstructure main body 10A to the substructures 86 and 88 are arranged at predetermined positions on the substructures 86 and 88, respectively, to complete the new superstructure main body. The end girder 12B is connected to each of the axial direction both ends of the new girder main body part 12A of 10A. Both the new girder body 12A and the end girder 12B are steel girders, which are connected by high-strength bolt friction joints using spliced steel plates and high-strength bolts to complete the new girder 12, and then the end girder 12B. A new floor slab 14 is completed by installing an end floor slab 14B to be attached to the new superstructure 10.例文帳に追加

ここで、本実施形態に係る橋梁架け替え工法においては、すでにステップS1の段階で新設上部工本体部10Aが完成しているため、新設上部工本体部10Aを組み立てるための仮設足場の設置は不要である。したがって、必要な仮設足場は、端部桁12Bと新設桁本体部12Aとの連結作業および端部床版14Bの設置作業のための仮設足場だけであり、扛上設備16および下部工86、88近傍の極めて限定的な範囲に設けるだけでよい。また、この仮設足場の設置においては、扛上設備16のサンドル16Bを活用することができ、仮設足場を容易に設置することもできる。 Here, in the bridge replacement construction method according to the present embodiment, since the new superstructure main body 10A has already been completed at the stage of step S1, there is no need to install a temporary scaffold for assembling the new superstructure main body 10A. is. Therefore, the necessary temporary scaffolding is only temporary scaffolding for connecting the end girder 12B and the new girder body 12A and installing the end floor slab 14B. It suffices to provide only in a very limited range in the vicinity. Moreover, in setting up this temporary scaffolding, the sandals 16B of the hoisting equipment 16 can be utilized, and the temporary scaffolding can be easily set up.

なお、端部桁12Bを、下部工86、88上の所定の位置にそれぞれ配置する際にはクレーンを用いるが、通常の橋梁の場合、端部桁12Bの長さは3m程度と短いことが想定されるので、吊り上げ能力が50~80トン程度のクレーン(特別な許可なく公道を走行可能なクレーン)を用いることができ、また、クレーンによる設置作業も容易である。 A crane is used to place the end girders 12B at predetermined positions on the substructures 86 and 88, but in the case of a normal bridge, the length of the end girders 12B is as short as about 3 m. Therefore, a crane with a lifting capacity of about 50 to 80 tons (a crane that can travel on public roads without special permission) can be used, and installation work using a crane is easy.

<ステップS8>
新設上部工10を完成させた後、新設上部工10の上面に舗装等を設けるとともに、扛上設備16を撤去して、既設上部工80の新設上部工10への架け替えが完了する。架け替えが完了した状態を図8に示す。
<Step S8>
After the new superstructure 10 is completed, pavement or the like is provided on the upper surface of the new superstructure 10, the lifting equipment 16 is removed, and the replacement of the existing superstructure 80 with the new superstructure 10 is completed. FIG. 8 shows the state in which the replacement is completed.

10…新設上部工
10A…新設上部工本体部
12…新設桁
12A…新設桁本体部
12B…端部桁
14…新設床版
14A…新設床版本体部
14B…端部床版
16…扛上設備
16A…油圧ジャッキ
16A1…伸縮ロッド
16B、16B1、16B2、18、50…サンドル
80…既設上部工
82…既設桁
84…既設床版
86、88…下部工
90…ベント
10 New superstructure 10A New superstructure body 12 New girder 12A New girder main body 12B End girder 14 New floor slab 14A New floor slab main body 14B End floor slab 16 Lifting equipment 16A...Hydraulic jack 16A1...Extendable rod 16B, 16B1, 16B2, 18, 50...Sandle 80...Existing superstructure 82...Existing girder 84...Existing floor slab 86, 88...Substructure 90...Bent

Claims (5)

橋梁の既設上部工を新設上部工に架け替える橋梁架け替え工法であって、
新設桁本体部および新設床版本体部を有してなる新設上部工本体部を、前記既設上部工の下方近傍であって、架け替え対象の前記既設上部工を解体撤去する作業時の足場として前記新設上部工本体部を利用するのに必要な第1高さまでジャッキアップする第1ジャッキアップ工程と、
前記第1ジャッキアップ工程でジャッキアップした前記新設上部工本体部を足場として利用して、架け替え対象の前記既設上部工を解体撤去する既設上部工解体撤去工程と、
前記既設上部工解体撤去工程で前記既設上部工を解体撤去した後、前記既設上部工解体撤去工程で足場として利用した前記新設上部工本体部を、前記第1高さよりも高い供用時の高さ位置までさらにジャッキアップする第2ジャッキアップ工程と、
前記第2ジャッキアップ工程で供用時の高さ位置までジャッキアップした前記新設上部工本体部の前記新設桁本体部の橋軸方向両端部に、下部工と連結する端部桁をそれぞれ連結する端部桁連結工程と、
を有することを特徴とする橋梁架け替え工法。
A bridge replacement method for replacing an existing bridge superstructure with a new superstructure,
A new superstructure main body having a new girder main body and a new floor slab main body is used as a scaffold in the vicinity of the lower part of the existing superstructure when dismantling and removing the existing superstructure to be replaced. a first jack-up step of jacking up to a first height required to utilize the new superstructure main body ;
an existing superstructure dismantling and removing step of dismantling and removing the existing superstructure to be replaced, using the new superstructure main body jacked up in the first jack-up step as a scaffold;
After the existing superstructure is dismantled and removed in the existing superstructure dismantling and removing step, the new superstructure main body used as a scaffold in the existing superstructure dismantling and removing step is moved to a height higher than the first height during service. a second jack-up step of further jacking up to the lower position;
Ends that connect the end girders that connect to the substructure to both ends in the bridge axis direction of the new girder main body of the new superstructure that has been jacked up to the height position for use in the second jack-up step. a girder connecting step;
A bridge replacement method characterized by having
前記第1ジャッキアップ工程後、前記新設上部工本体部の前記新設桁本体部の上面と前記既設上部工の既設桁の下面との間に、橋軸方向に所定間隔を以て複数のサンドルを配置し、前記既設上部工を橋軸直角方向に前記サンドルの上方位置で切断する工程を、前記既設上部工解体撤去工程は含むことを特徴とする請求項1に記載の橋梁架け替え工法。After the first jack-up step, a plurality of sandals are arranged at predetermined intervals in the bridge axis direction between the upper surface of the new girder body of the new superstructure main body and the lower surface of the existing girder of the existing superstructure. 2. The bridge replacement method according to claim 1, wherein said existing superstructure dismantling and removing step includes a step of cutting said existing superstructure in a direction perpendicular to the bridge axis at a position above said sandwich. 前記新設上部工は、前記既設上部工の下方で作製されることを特徴とする請求項1又は2に記載の橋梁架け替え工法。 3. The bridge replacement construction method according to claim 1, wherein the new superstructure is constructed below the existing superstructure. 前記橋梁は鋼橋であることを特徴とする請求項1~3のいずれかに記載の橋梁架け替え工法。 The bridge replacement construction method according to any one of claims 1 to 3, wherein the bridge is a steel bridge. 前記新設床版本体部は、鋼床版であることを特徴とする請求項1~のいずれかに記載の橋梁架け替え工法。 The bridge replacement construction method according to any one of claims 1 to 4 , wherein the new deck slab body is a steel deck slab.
JP2019113059A 2019-06-18 2019-06-18 Bridge replacement method Active JP7124794B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019113059A JP7124794B2 (en) 2019-06-18 2019-06-18 Bridge replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019113059A JP7124794B2 (en) 2019-06-18 2019-06-18 Bridge replacement method

Publications (2)

Publication Number Publication Date
JP2020204209A JP2020204209A (en) 2020-12-24
JP7124794B2 true JP7124794B2 (en) 2022-08-24

Family

ID=73837289

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019113059A Active JP7124794B2 (en) 2019-06-18 2019-06-18 Bridge replacement method

Country Status (1)

Country Link
JP (1) JP7124794B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001241012A (en) 2000-02-28 2001-09-04 Tomoe Corp Bridge removal and construction method
JP2003034911A (en) 2001-07-25 2003-02-07 Taisei Corp Replacing method for bridge girder
JP2004332222A (en) 2003-04-30 2004-11-25 Mitsubishi Heavy Ind Ltd Rebuilding construction method for bridge and bridge
JP2018059311A (en) 2016-10-04 2018-04-12 Jfeエンジニアリング株式会社 Floor slab replacement method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11190008A (en) * 1997-12-26 1999-07-13 Nkk Corp Rebuilding method for elevated bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001241012A (en) 2000-02-28 2001-09-04 Tomoe Corp Bridge removal and construction method
JP2003034911A (en) 2001-07-25 2003-02-07 Taisei Corp Replacing method for bridge girder
JP2004332222A (en) 2003-04-30 2004-11-25 Mitsubishi Heavy Ind Ltd Rebuilding construction method for bridge and bridge
JP2018059311A (en) 2016-10-04 2018-04-12 Jfeエンジニアリング株式会社 Floor slab replacement method

Also Published As

Publication number Publication date
JP2020204209A (en) 2020-12-24

Similar Documents

Publication Publication Date Title
KR100814388B1 (en) A bridge lifting method during vehicle passing
KR100949601B1 (en) Method for broadening width of existing bridge without Temporary road
KR20060099484A (en) The use shelf with chemical anchor and high tention long bolt for bridge deck lifting method
CN105735139A (en) Supporting system for construction of cast-in-situ box beam in overpass and construction method of box beam
JP4671912B2 (en) Bridge replacement method
JP5015049B2 (en) Pier extension method
CN106320192A (en) Beam section replacement reinforcement method for large-span concrete continuous beam bridge
KR100892751B1 (en) Bridge repairng method by upper structure lifting and hinge typeed temporary bridge construction
JP7124794B2 (en) Bridge replacement method
JP5613294B1 (en) Bridge repair method
JP4477467B2 (en) Bridge structure and its replacement method
JP5848716B2 (en) Floor slab replacement method
KR102490192B1 (en) Bridge upper structure and the method constructing bridge upper structure using the same
KR20050009806A (en) Pulling up, repair and reinforcement method for the upper structure of a bridge
JP4685341B2 (en) Viaduct construction method
JP2000017618A (en) Replacement method of concrete bridge to steel bridge
CN205501840U (en) A braced system for construction of overpass cast -in -situ box girder
CN112211426B (en) Method for repairing historical building
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
JP7134133B2 (en) Bridge railing construction method
JP7185567B2 (en) Bridge pier repair method
KR100214389B1 (en) Bridge execution method using a temporary bridge
JP6755172B2 (en) Floor slab renewal method
KR101258841B1 (en) Precast concrete slab construction method of bridge
KR102381969B1 (en) Formwork for bridge piers and construction method of piers using the same

Legal Events

Date Code Title Description
A80 Written request to apply exceptions to lack of novelty of invention

Free format text: JAPANESE INTERMEDIATE CODE: A80

Effective date: 20190619

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210909

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220428

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220510

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220609

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220712

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220725

R150 Certificate of patent or registration of utility model

Ref document number: 7124794

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150