JP2003034911A - Replacing method for bridge girder - Google Patents

Replacing method for bridge girder

Info

Publication number
JP2003034911A
JP2003034911A JP2001223897A JP2001223897A JP2003034911A JP 2003034911 A JP2003034911 A JP 2003034911A JP 2001223897 A JP2001223897 A JP 2001223897A JP 2001223897 A JP2001223897 A JP 2001223897A JP 2003034911 A JP2003034911 A JP 2003034911A
Authority
JP
Japan
Prior art keywords
bridge girder
existing
new
bridge
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001223897A
Other languages
Japanese (ja)
Inventor
Toshiaki Anzai
利昭 安斉
Masanori Hirachi
正憲 平地
Hiroyasu Inamori
宏育 稲森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2001223897A priority Critical patent/JP2003034911A/en
Publication of JP2003034911A publication Critical patent/JP2003034911A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a replacing method for a bridge girder by which replacing work of the bridge girder can be quickly executed without using a large crane. SOLUTION: In a state that an existing bridge girder 1 erected on adjacent piers in the bridge axis direction is supported from the lower direction by jacks 4a laid on trucks 4b, the both ends of the existing bridge girder 1 is cut off so as to become shorter than the span L of the bridge piers 3, and at the same time, the replacing work of the bridge girder is executed by a replacing preparing process to construct a new bridge girder 2 to be erected on the bridge piers 3 on the existing girder 1, a bridge girder lowering process to lower the existing bridge girder 1 by the jacks 4a in a state that the new bridge girder 2 is laid on the existing bridge girder 1, a new bridge girder erecting process to erect the new bridge girder 2 on the bridge piers 3, and an existing bridge girder carrying-out process to carry out the existing bridge girder 1 supported by the jacks 4a.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、橋桁の架替工法に
関する。
TECHNICAL FIELD The present invention relates to a bridge girder replacement method.

【0002】[0002]

【従来の技術】従来、橋軸方向に隣り合う橋脚に架設さ
れた既設の橋桁を架け替える場合には、以下のような手
順で行なわれている(図1,図5および図6参照。な
お、図1は本発明に係る橋桁の架替工法の手順を説明す
るものであるが、図1に示す手順については、従来の橋
桁の架替工法と共通しているので、ここでは従来の橋桁
の架替工法の手順を説明するものとして参照する)。 橋脚3,3に架設された既設橋桁1を運搬台車4b
上に設置されたジャッキ4aにより下方から支持する
(図1(b))。 既設橋桁1が橋脚3,3の径間L(橋脚前面間の距
離)よりも短くなるように既設橋桁1の両端を切除する
(図1(c))。 ジャッキ4aを操作して既設橋桁1を降下させる
(図5(a))。 ジャッキ4aで既設橋桁1を支持した状態で、運搬
台車4bにより既設橋桁1を搬出する(図5(b))。 橋桁の架替位置に隣接した橋桁上で構築された新設
橋桁2(図5(b))を大型クレーン12で一括して吊
り上げて、橋脚3,3に架設する(図5(c),図
6)。
2. Description of the Related Art Conventionally, when replacing an existing bridge girder installed on bridge piers adjacent to each other in the bridge axis direction, the following procedure has been performed (see FIGS. 1, 5 and 6). FIG. 1 illustrates the procedure of the bridge girder replacement method according to the present invention. However, the procedure shown in FIG. 1 is common to the conventional bridge girder replacement method, so here, the conventional bridge girder replacement method is used. Reference as an explanation of the procedure of the replacement method). The existing bridge girder 1 erected on the piers 3 and 3 is used as a carriage 4b.
It is supported from below by the jack 4a installed above (FIG. 1 (b)). Both ends of the existing bridge girder 1 are cut off so that the existing bridge girder 1 is shorter than the span L (distance between the front faces of the piers) of the piers 3 and 3 (Fig. 1 (c)). The jack 4a is operated to lower the existing bridge girder 1 (Fig. 5 (a)). With the existing bridge girder 1 supported by the jack 4a, the existing bridge girder 1 is carried out by the carriage 4b (FIG. 5 (b)). A new bridge girder 2 (Fig. 5 (b)) constructed on the bridge girder adjacent to the bridge girder replacement position is collectively lifted by the large crane 12 and erected on the piers 3, 3 (Fig. 5 (c), Fig. 6).

【0003】[0003]

【発明が解決しようとする課題】しかしながら、前記し
たような方法では、既設橋桁1を撤去した後でなけれ
ば、新設橋桁2を橋脚3,3へ架設することができない
ため、架替作業に時間がかかる。また、大型クレーン1
2で重厚かつ長大な新設橋桁2を一括して吊り下げた状
態で、旋回、移動させて所定の位置へ架設する作業は、
非常に難易度が高い。さらに、都市部では、作業エリア
の周辺に建物が近接していたり、橋桁の下に道路が併設
されていることも多いので、大型クレーン12による新
設橋桁2の架設作業は、より難易度が増す。また、橋桁
の下に道路が併設されている場合には、大規模な交通規
制を行って大型クレーン12の作業エリアを確保するこ
とが多く、これに伴う交通渋滞の発生などが懸念され
る。
However, in the above-mentioned method, the new bridge girder 2 can be erected on the piers 3 and 3 only after the existing bridge girder 1 has been removed, so that it takes time to perform the replacement work. Takes. Also, a large crane 1
In the state in which the heavy and long new bridge girder 2 is hung in a lump at the same time, the work of turning, moving and erection to a predetermined position is
Very difficult. Furthermore, in urban areas, there are many cases where buildings are close to the work area and roads are installed under the bridge girders. Therefore, the construction work of the new bridge girder 2 by the large crane 12 becomes more difficult. . Further, when a road is installed under the bridge girder, a large-scale traffic regulation is often performed to secure a work area for the large-sized crane 12, which may cause a traffic congestion.

【0004】このような問題に鑑み、本発明は、橋桁の
架替作業を迅速に行なうことができ、加えて、大型クレ
ーンを使用しないで橋桁の架替作業ができる橋桁の架替
工法を提供することを課題とする。
In view of the above problems, the present invention provides a bridge girder replacement method that can quickly perform bridge girder replacement work, and can also perform bridge girder replacement work without using a large crane. The task is to do.

【0005】[0005]

【課題を解決するための手段】このような課題を解決す
るために、請求項1に係る橋桁の架替工法は、橋軸方向
に隣り合う橋脚に架設された既設橋桁を台車上に載置さ
れたジャッキにより下方から支持した状態で、前記橋脚
の径間よりも短くなるように前記既設橋桁の両端を切除
するとともに、前記橋脚に架設される新設橋桁を前記既
設橋桁の上で構築する架替準備工程と、前記新設橋桁が
前記既設橋桁の上に載置された状態で、前記ジャッキに
より前記既設橋桁を降下させる橋桁降下工程と、前記新
設橋桁を前記橋脚に架設する新設橋桁架設工程と、前記
ジャッキで支持された前記既設橋桁を搬出する既設橋桁
搬出工程と、を含むことを特徴とする。
In order to solve such a problem, the bridge girder replacement method according to claim 1 is to mount an existing bridge girder installed on bridge piers adjacent to each other in the bridge axis direction on a carriage. With the jacks supported from below, both ends of the existing bridge girder are cut off so as to be shorter than the span of the bridge pier, and a new bridge girder to be built on the bridge pier is constructed on the existing bridge girder. A replacement preparation step, a bridge girder lowering step of lowering the existing bridge girder by the jack while the new bridge girder is placed on the existing bridge girder, and a new bridge girder erection step of erection of the new bridge girder on the pier And an existing bridge girder unloading step of unloading the existing bridge girder supported by the jack.

【0006】かかる橋桁の架替工法は、既設橋桁とその
上で構築した新設橋桁とをジャッキにより一括して降下
させて、既設橋桁を橋脚から撤去する作業とその橋脚へ
新設橋桁を架設する作業とを並行して行なうものであ
る。したがって、架替作業にかかる時間を大幅に短縮す
ることができる。また、既設橋桁の上で新設橋脚を構築
し、既設橋桁を下方から支持するジャッキにより既設橋
桁と新設橋桁とを降下させるので、新設橋桁を吊り込む
ための大型クレーンは不要である。
[0006] Such a bridge girder replacement method is a work in which an existing bridge girder and a new bridge girder constructed on the bridge girder are collectively lowered by a jack, the existing bridge girder is removed from the pier and the new bridge girder is erected on the pier. And are done in parallel. Therefore, the time required for the replacement work can be significantly reduced. In addition, since a new bridge pier is constructed on the existing bridge girder and the jack supporting the existing bridge girder from below lowers the existing bridge girder and the new bridge girder, a large crane for suspending the new bridge girder is not required.

【0007】請求項2に係る橋桁の架替工法は、橋軸方
向に隣り合う橋脚に架設された既設橋桁を台車上に載置
されたジャッキにより下方から支持した状態で、前記橋
脚の径間よりも短くなるように前記既設橋桁の両端を切
除するとともに、前記橋脚に架設される新設橋桁を前記
既設橋桁に隣接して設置された送出し架台の上で構築
し、前記新設橋桁を前記既設橋桁の上に送り出す架替準
備工程と、前記新設橋桁が前記既設橋桁の上に載置され
た状態で、前記ジャッキにより前記既設橋桁を降下させ
る橋桁降下工程と、前記新設橋桁を前記橋脚に架設する
新設橋桁架設工程と、前記ジャッキで支持された前記既
設橋桁を搬出する既設橋桁搬出工程と、を含むことを特
徴とする。
According to a second aspect of the present invention, there is provided a bridge girder replacement method in which an existing bridge girder installed on bridge piers adjacent to each other in the axial direction of the bridge is supported from below by a jack mounted on a trolley. Both ends of the existing bridge girder are cut off so as to be shorter than the existing bridge girder, and a new bridge girder to be erected on the pier is constructed on a sending platform installed adjacent to the existing bridge girder, and the new bridge girder is installed to the existing bridge girder. A preparatory step of sending out onto the bridge girder, a bridge girder descending step of lowering the existing bridge girder by the jack while the new bridge girder is placed on the existing bridge girder, and erection of the new bridge girder on the pier A new bridge girder erection step and an existing bridge girder unloading step of unloading the existing bridge girder supported by the jack.

【0008】かかる橋桁の架替工法は、既設橋桁と新設
橋桁とをジャッキにより一括して降下させて、既設橋桁
を橋脚から撤去する作業とその橋脚へ新設橋桁を架設す
る作業とを並行して行なうものである。また、新設橋桁
の構築作業は、撤去する既設橋桁に隣接した位置に設置
された送出し架台の上で行われるので、既設橋桁の端部
を切除する作業と並行して行なうことができる。したが
って、架替作業にかかる時間を短縮することができる。
また、ジャッキにより既設橋桁と新設橋桁とを降下させ
て橋桁を架け替えるので、新設橋桁を吊り込むための大
型クレーンは不要である。
[0008] Such a bridge girder replacement method involves simultaneously dropping the existing bridge girder and the new bridge girder with a jack, removing the existing bridge girder from the pier, and erection of the new bridge girder on the pier. It is something to do. Further, since the construction work of the new bridge girder is carried out on the sending base installed in the position adjacent to the existing bridge girder to be removed, it can be carried out in parallel with the work of cutting off the end portion of the existing bridge girder. Therefore, the time required for the replacement work can be shortened.
Moreover, since the existing bridge girder and the new bridge girder are lowered by the jack to switch the bridge girder, a large crane for suspending the new bridge girder is unnecessary.

【0009】[0009]

【発明の実施の形態】以下、本発明に係る橋桁の架替工
法の実施の形態を添付した図面を参照しながら詳細に説
明する。なお、以下の実施形態は、都市部の高速道路で
多く見られる高架橋のように橋桁が連続して架設されて
いる場合を想定しているが(図1(a)参照)、これに
限定されることはなく、跨道橋や跨線橋などを架け替え
る場合にも本発明に係る橋桁の架替工法を適用すること
ができる。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of a bridge girder replacement method according to the present invention will be described below in detail with reference to the accompanying drawings. Note that the following embodiments assume a case where bridge girders are continuously erected like a viaduct that is often found on expressways in urban areas (see FIG. 1A), but the present invention is not limited to this. However, the bridge girder replacement method according to the present invention can be applied to the case of replacing a bridge or an overpass.

【0010】図1および図2は本発明に係る橋桁の架替
工法の各工程を説明する側面図である。以下、工程ごと
に詳細に説明する。
1 and 2 are side views for explaining each step of the bridge girder replacement method according to the present invention. Hereinafter, each step will be described in detail.

【0011】(架替準備工程)架替準備工程は、図1
(a)(b)(c),図2(a)に示すように、橋軸方
向に隣り合う橋脚3に架設された既設橋桁1を台車4b
上に載置されたジャッキ4aにより下方から支持した状
態で、橋脚3の径間Lよりも短くなるように既設橋桁1
の両端を切除するとともに、橋脚3に架設される新設橋
桁2を既設橋桁1の上で構築するものである。
(Rebuilding Preparation Step) The rebuilding preparation step is shown in FIG.
As shown in (a), (b), (c), and FIG. 2 (a), the existing bridge girder 1 erected on the bridge piers 3 adjacent in the bridge axis direction is mounted on the carriage 4b.
The existing bridge girder 1 should be shorter than the span L of the pier 3 while being supported from below by the jack 4a placed on top.
Both ends of the bridge are cut off and a new bridge girder 2 to be erected on the bridge pier 3 is constructed on the existing bridge girder 1.

【0012】図1(b)に示すように、橋桁上の高欄や
地覆などを撤去するとともに、橋軸方向に隣り合う橋脚
3,3に架設された既設橋桁1をジャッキ4aにより下
方から支持する。ジャッキ4aは台車4bの上に設置さ
れている。この状態で、図1(c)に示すように、既設
橋桁1が橋脚3,3の径間L(橋脚前面間の距離)より
も短くなるように既設橋桁1の両端をワイヤーソーなど
の切断装置により切断し、クレーン10などを使用して
切断された部位を撤去する。
As shown in FIG. 1 (b), while removing the balustrade and the ground cover on the bridge girder, the existing bridge girder 1 erected on the bridge piers 3, 3 adjacent in the bridge axial direction is supported from below by the jack 4a. To do. The jack 4a is installed on the carriage 4b. In this state, as shown in FIG. 1 (c), both ends of the existing bridge girder 1 are cut with a wire saw so that the existing bridge girder 1 is shorter than the span L (distance between the front faces of the piers) of the piers 3 and 3. The device is cut, and the cut site is removed using the crane 10 or the like.

【0013】前記した各作業と並行して、もしくは終了
してから、図2(a)に示すように、既設橋桁1の上に
新設橋桁2を構築する。新設橋桁2は橋脚3,3に架設
されるので、これに合わせた桁長を有する。また、橋脚
3上に形成された新設橋桁2用の支承3b(図4参照)
の直上に新設橋桁2の端部が位置するように新設橋桁2
を構築する。なお、新設橋桁2は、複数の鋼製やコンク
リート製のプレキャスト部材2aを組み立てて構築して
もよいし、現場打ちのコンクリートにより構築してもよ
い。また、本実施形態では、架替準備工程に先立って、
図4に示すように、既設橋桁1の支承3aに隣接した位
置に新設橋桁2の支承3bを構築しておく。
As shown in FIG. 2A, a new bridge girder 2 is constructed on the existing bridge girder 1 in parallel with or after the above-mentioned respective works. Since the new bridge girder 2 is erected on the piers 3 and 3, it has a girder length adapted to this. Also, a bearing 3b for the new bridge girder 2 formed on the pier 3 (see FIG. 4)
The new bridge girder 2 so that the end of the new bridge girder 2 is located directly above
To build. The new bridge girder 2 may be constructed by assembling a plurality of precast members 2a made of steel or concrete, or may be constructed by cast-in-place concrete. Further, in this embodiment, prior to the rebuilding preparation process,
As shown in FIG. 4, the support 3b of the new bridge girder 2 is constructed at a position adjacent to the support 3a of the existing bridge girder 1.

【0014】(橋桁降下工程)橋桁降下工程は、図2
(b)に示すように、新設橋桁2が既設橋桁1の上に載
置された状態で、ジャッキ4aにより既設橋桁2を降下
させるものである。
(Bridge girder descending process) The bridge girder descending process is shown in FIG.
As shown in (b), the existing bridge girder 2 is lowered by the jack 4a while the new bridge girder 2 is placed on the existing bridge girder 1.

【0015】新設橋桁2の構築が完了したら、新設橋桁
2を既設橋桁1の上に載置した状態で、ジャッキ4aを
操作して既設橋桁1を降下させる。既設橋桁1は橋脚
3,3の径間Lよりも短くなるようにその両端が切除さ
れているので、図2(b)のように、橋脚3,3の間に
既設橋桁1を降下させることができる。また、新設橋桁
2の端部が橋脚3,3の上面に形成された支承3bに載
置されるように構築されているので、既設橋桁1を降下
させれば、必然的に新設橋桁2の位置決めがされるが、
必要に応じて、橋軸方向あるいは橋軸直角方向に微調整
を行ないつつ、既設橋桁1と新設橋桁2とを降下させ
る。また、図示した実施形態のように複数のジャッキを
設置したときには、全てのジャッキの降下スピードを同
じにして、既設橋脚1およびその上に載置されている新
設橋桁2とを水平に保った状態で降下させる。
When the construction of the new bridge girder 2 is completed, with the new bridge girder 2 placed on the existing bridge girder 1, the jack 4a is operated to lower the existing bridge girder 1. Since both ends of the existing bridge girder 1 have been cut off so as to be shorter than the span L of the bridge piers 3 and 3, lower the existing bridge girder 1 between the piers 3 and 3 as shown in Fig. 2 (b). You can Moreover, since the end of the new bridge girder 2 is constructed to be placed on the bearing 3b formed on the upper surface of the piers 3 and 3, if the existing bridge girder 1 is lowered, the new bridge girder 2 will be inevitably moved. It will be positioned,
If necessary, the existing bridge girder 1 and the new bridge girder 2 are lowered while making fine adjustments in the bridge axis direction or in the direction perpendicular to the bridge axis. Further, when a plurality of jacks are installed as in the illustrated embodiment, all the jacks have the same descent speed, and the existing pier 1 and the new bridge girder 2 mounted thereon are kept horizontal. To lower.

【0016】(新設橋桁架設工程)新設橋桁架設工程
は、図2(b)に示すように、新設橋桁2を橋脚3に架
設するものである。前記した橋桁降下工程で所定の高さ
まで降下させた新設橋桁2を橋脚3の支承3b(図4
(b)(c)参照)に固定して、新設橋桁2を橋脚3,
3に架設する。
(New bridge girder erection process) In the new bridge girder erection process, as shown in FIG. 2 (b), the new bridge girder 2 is erected on the bridge pier 3. The new bridge girder 2 lowered to a predetermined height in the above-mentioned bridge girder lowering step is supported by the support 3b of the pier 3 (Fig. 4).
(See (b) and (c)), and fix the new bridge girder 2 to the pier 3,
Install in 3.

【0017】(既設橋桁搬出工程)既設橋桁搬出工程
は、図2(c)に示すように、ジャッキ4aで支持され
た既設橋桁1を搬出するものである。新設橋桁2を橋脚
3,3に架設した後に、ジャッキ4aにより所定の高さ
まで既設橋桁1を降下させ、ジャッキ4a上に既設橋桁
1を載置した状態で、台車4bにより所定の搬出場所へ
搬出する。以上で既設橋桁1の架替作業が完了する。
(Existing Bridge Girder Unloading Step) In the existing bridge girder unloading step, as shown in FIG. 2C, the existing bridge girder 1 is unloaded. After constructing the new bridge girder 2 on the piers 3 and 3, the existing bridge girder 1 is lowered to a predetermined height by the jack 4a, and the existing bridge girder 1 is placed on the jack 4a, and is carried out to a predetermined unloading place by the trolley 4b. To do. This completes the work of replacing the existing bridge girder 1.

【0018】以上のように、本実施形態に係る橋桁の架
替工法は、既設橋桁1とその上で構築した新設橋桁2と
をジャッキ4aにより一括して降下させて、既設橋桁1
を橋脚3,3から撤去する作業とその橋脚3,3へ新設
橋桁2を架設する作業とを並行して行なうものである。
すなわち、既設橋桁1の撤去作業と新設橋桁2の架設作
業とを同時に行なうことができるので、架替作業にかか
る時間を大幅に短縮することができる。
As described above, in the bridge girder replacement method according to the present embodiment, the existing bridge girder 1 and the new bridge girder 2 constructed on the existing bridge girder 1 are collectively lowered by the jack 4a, and the existing bridge girder 1 is
The work of removing the pier from the piers 3 and 3 and the work of constructing the new bridge girder 2 on the piers 3 and 3 are performed in parallel.
That is, the work for removing the existing bridge girder 1 and the work for constructing the new bridge girder 2 can be performed at the same time, so that the time required for the replacement work can be significantly reduced.

【0019】また、既設橋桁1の上で新設橋脚2を構築
し、既設橋桁1を下方から支持するジャッキ4aにより
既設橋桁1と新設橋桁2とを一括して降下させるので、
新設橋桁2を吊り込むための大型クレーンは不要であ
る。したがって、例えば高架橋の下方に道路が併設され
ている場合などでは、この道路を通行する車両に対する
交通規制を最小限に留めることができる。
Since the new bridge pier 2 is constructed on the existing bridge girder 1 and the jack 4a supporting the existing bridge girder 1 from below lowers the existing bridge girder 1 and the new bridge girder 2 together,
There is no need for a large crane to suspend the new bridge girder 2. Therefore, for example, when a road is provided below the viaduct, it is possible to minimize traffic restrictions on vehicles passing through this road.

【0020】なお、前記した実施形態では、撤去する既
設橋桁1の上で新設橋桁2を構築する例を示したが、図
3(a)(b)に示すように、既設橋桁1に隣接して設
置された送出し架台2bの上で新設橋桁2を構築した後
に、送出し装置2cにより新設橋桁2を既設橋桁1の上
に送り出してもよい。この場合には、既設橋桁1の両端
を切除する作業と並行して新設橋桁2を構築することが
できるので、架替作業にかかる時間を短縮することが可
能である。
In the above-mentioned embodiment, the example of constructing the new bridge girder 2 on the existing bridge girder 1 to be removed is shown. However, as shown in FIGS. 3 (a) and 3 (b), it is adjacent to the existing bridge girder 1. After constructing the new bridge girder 2 on the sent-out gantry 2b installed as above, the new bridge girder 2 may be sent out onto the existing bridge girder 1 by the sending-out device 2c. In this case, since the new bridge girder 2 can be constructed in parallel with the work of cutting off both ends of the existing bridge girder 1, it is possible to shorten the time required for the replacement work.

【0021】また、高欄などの撤去作業や新設橋桁2用
の支承3bの設置作業などは施工現場の状況や、橋桁の
構造形式などを考慮して適宜行なえばよい。
Further, the work of removing the balustrade or the like and the work of installing the support 3b for the new bridge girder 2 may be appropriately performed in consideration of the situation of the construction site and the structural type of the bridge girder.

【0022】[0022]

【発明の効果】本発明に係る橋桁の架替工法によれば、
既設橋桁の撤去作業と新設橋桁の架設作業とを同時に行
なうことができるので、架替作業にかかる時間を大幅に
短縮することができる。
According to the bridge girder replacement method of the present invention,
Since the work for removing the existing bridge girder and the work for constructing the new bridge girder can be performed at the same time, the time required for the replacement work can be significantly reduced.

【0023】また、既設橋桁を下方から支持するジャッ
キにより既設橋桁と新設橋桁とを一括降下させるので、
新設橋桁を吊り込むための大型クレーンは不要である。
したがって、特に都市部において、例えば高架橋の下方
に道路が併設されている場合などでは、この道路を通行
する車両に対する交通規制を最小限に留めることができ
る。
Since the existing bridge girder and the new bridge girder are collectively lowered by the jack that supports the existing bridge girder from below,
No large crane is required to suspend the new bridge girder.
Therefore, especially in an urban area, for example, when a road is provided below the viaduct, traffic restrictions on vehicles passing through this road can be minimized.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明に係る橋桁の架替工法のうちの架替準
備工程の手順を説明する側面図である。
FIG. 1 is a side view illustrating a procedure of a rebuilding preparation step in a bridge girder replacement method according to the present invention.

【図2】 (a)図1に続く架替準備工程の手順を説明
する側面図、(b)は同じく降下工程および新設橋桁架
設工程を説明する側面図、(c)は同じく既設橋桁搬出
工程を説明する側面図である。
FIG. 2 (a) is a side view illustrating a procedure of a replacement preparation process subsequent to FIG. 1, (b) is a side view illustrating a descent process and a new bridge girder erection process, and (c) is an existing bridge girder unloading process. It is a side view explaining.

【図3】 架替準備工程の他の手順を説明する側面図で
ある。
FIG. 3 is a side view illustrating another procedure of the reassembling preparation step.

【図4】 支承部分を示す断面図である。FIG. 4 is a sectional view showing a support portion.

【図5】 従来の橋桁の架替工法の手順を説明する側面
図である。
FIG. 5 is a side view illustrating a procedure of a conventional bridge girder replacement method.

【図6】 図5に続く手順を説明する側面図である。FIG. 6 is a side view illustrating the procedure following FIG.

【符号の説明】[Explanation of symbols]

1 既設橋桁 2 新設橋桁 2a プレキャスト部材 2b 送出し架台 2c 送出し装置 3 橋脚 4a ジャッキ 4b 台車 1 Existing bridge girder 2 New bridge girder 2a Precast member 2b Sending stand 2c sending device 3 piers 4a jack 4b trolley

───────────────────────────────────────────────────── フロントページの続き (72)発明者 稲森 宏育 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 Fターム(参考) 2D059 BB39 CC03 CC04 CC08 GG41   ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Hiroyasu Inamori             1-25-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo Taisei             Construction Co., Ltd. F-term (reference) 2D059 BB39 CC03 CC04 CC08 GG41

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 橋軸方向に隣り合う橋脚に架設された既
設橋桁を台車上に載置されたジャッキにより下方から支
持した状態で、前記橋脚の径間よりも短くなるように前
記既設橋桁の両端を切除するとともに、前記橋脚に架設
される新設橋桁を前記既設橋桁の上で構築する架替準備
工程と、 前記新設橋桁が前記既設橋桁の上に載置された状態で、
前記ジャッキにより前記既設橋桁を降下させる橋桁降下
工程と、 前記新設橋桁を前記橋脚に架設する新設橋桁架設工程
と、 前記ジャッキで支持された前記既設橋桁を搬出する既設
橋桁搬出工程と、を含むことを特徴とする橋桁の架替工
法。
1. In a state in which an existing bridge girder installed on bridge piers adjacent to each other in the axial direction of the bridge is supported from below by a jack placed on a truck, the bridge girder of the existing bridge girder is made shorter than the span of the bridge pier. While excising both ends, a preparatory step of constructing a new bridge girder to be erected on the bridge pier on the existing bridge girder, with the new bridge girder placed on the existing bridge girder,
A bridge girder descending step of lowering the existing bridge girder by the jack, a new bridge girder erection step of erection of the new bridge girder on the pier, and an existing bridge girder unloading step of unloading the existing bridge girder supported by the jack. Bridge girder replacement method characterized by.
【請求項2】 橋軸方向に隣り合う橋脚に架設された既
設橋桁を台車上に載置されたジャッキにより下方から支
持した状態で、前記橋脚の径間よりも短くなるように前
記既設橋桁の両端を切除するとともに、前記橋脚に架設
される新設橋桁を前記既設橋桁に隣接して設置された送
出し架台の上で構築し、前記新設橋桁を前記既設橋桁の
上に送り出す架替準備工程と、 前記新設橋桁が前記既設橋桁の上に載置された状態で、
前記ジャッキにより前記既設橋桁を降下させる橋桁降下
工程と、 前記新設橋桁を前記橋脚に架設する新設橋桁架設工程
と、 前記ジャッキで支持された前記既設橋桁を搬出する既設
橋桁搬出工程と、を含むことを特徴とする橋桁の架替工
法。
2. An existing bridge girder that is erected on bridge piers that are adjacent to each other in the bridge axis direction is supported from below by a jack placed on a trolley so that the bridge pier of the existing bridge girder is shorter than the span of the bridge pier. A reconstructing preparatory step of cutting off both ends and constructing a new bridge girder to be erected on the bridge pier on a sending platform installed adjacent to the existing bridge girder, and sending the new bridge girder onto the existing bridge girder. , With the new bridge girder placed on the existing bridge girder,
A bridge girder descending step of lowering the existing bridge girder by the jack, a new bridge girder erection step of erection of the new bridge girder on the pier, and an existing bridge girder unloading step of unloading the existing bridge girder supported by the jack. Bridge girder replacement method characterized by.
JP2001223897A 2001-07-25 2001-07-25 Replacing method for bridge girder Pending JP2003034911A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001223897A JP2003034911A (en) 2001-07-25 2001-07-25 Replacing method for bridge girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001223897A JP2003034911A (en) 2001-07-25 2001-07-25 Replacing method for bridge girder

Publications (1)

Publication Number Publication Date
JP2003034911A true JP2003034911A (en) 2003-02-07

Family

ID=19057151

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001223897A Pending JP2003034911A (en) 2001-07-25 2001-07-25 Replacing method for bridge girder

Country Status (1)

Country Link
JP (1) JP2003034911A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100638578B1 (en) 2004-09-24 2006-10-26 (주)알티에스 Method for carrying out replacement of an upper structure of a railway bridge
JP2008190131A (en) * 2007-02-01 2008-08-21 Tomoe Corp Erection method for bridge girder
JP2009052306A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2009052305A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2011089281A (en) * 2009-10-21 2011-05-06 Taisei Corp Method for rebuilding bridge
JP2016037774A (en) * 2014-08-08 2016-03-22 大成建設株式会社 Erection method for bridge girder, and bridge body
JP2016037775A (en) * 2014-08-08 2016-03-22 大成建設株式会社 Replacement method for bridge girder
JP2019132008A (en) * 2018-01-30 2019-08-08 Jfeエンジニアリング株式会社 Carry-in/out method and carry-in/out facility
JP2020204209A (en) * 2019-06-18 2020-12-24 Jfeエンジニアリング株式会社 Bridge replacement method
JP2021070916A (en) * 2019-10-29 2021-05-06 株式会社Ihiインフラシステム Carrying-in method of bridge article, carrying-out method of bridge article, removing method of bridge article, installation method thereof and lifting device for bridge article
CN114922097A (en) * 2022-03-08 2022-08-19 中国建筑第六工程局有限公司 Reinforcing and modifying method for changing line shape of existing steel box girder continuous beam bridge

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100638578B1 (en) 2004-09-24 2006-10-26 (주)알티에스 Method for carrying out replacement of an upper structure of a railway bridge
JP2008190131A (en) * 2007-02-01 2008-08-21 Tomoe Corp Erection method for bridge girder
JP4563413B2 (en) * 2007-02-01 2010-10-13 株式会社巴コーポレーション Bridge girder construction method
JP2009052306A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2009052305A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2011089281A (en) * 2009-10-21 2011-05-06 Taisei Corp Method for rebuilding bridge
JP2016037774A (en) * 2014-08-08 2016-03-22 大成建設株式会社 Erection method for bridge girder, and bridge body
JP2016037775A (en) * 2014-08-08 2016-03-22 大成建設株式会社 Replacement method for bridge girder
JP2019132008A (en) * 2018-01-30 2019-08-08 Jfeエンジニアリング株式会社 Carry-in/out method and carry-in/out facility
JP2020204209A (en) * 2019-06-18 2020-12-24 Jfeエンジニアリング株式会社 Bridge replacement method
JP7124794B2 (en) 2019-06-18 2022-08-24 Jfeエンジニアリング株式会社 Bridge replacement method
JP2021070916A (en) * 2019-10-29 2021-05-06 株式会社Ihiインフラシステム Carrying-in method of bridge article, carrying-out method of bridge article, removing method of bridge article, installation method thereof and lifting device for bridge article
CN114922097A (en) * 2022-03-08 2022-08-19 中国建筑第六工程局有限公司 Reinforcing and modifying method for changing line shape of existing steel box girder continuous beam bridge
CN114922097B (en) * 2022-03-08 2024-02-13 中国建筑第六工程局有限公司 Reinforcing transformation method for changing line shape of continuous girder bridge of existing steel box girder

Similar Documents

Publication Publication Date Title
JP2008088782A (en) Cantilever overhang erection method of corrugated steel plate web bridge
JP2003034911A (en) Replacing method for bridge girder
JP3954869B2 (en) Bridge girder replacement method
JP4671912B2 (en) Bridge replacement method
JP2006077521A (en) Bridge constructing apparatus
JP5184248B2 (en) Construction method of level crossing
JP4796411B2 (en) Bridge removal method
JP4329535B2 (en) Mobile work vehicle for overhanging slabs
JP4040900B2 (en) 3D intersection construction method, 3D intersection and moving platform
JP6974233B2 (en) Floor slab replacement method and floor slab replacement device
JP2001098512A (en) Method for erecting and removing road striding bridge by frame with jack device
JP4339778B2 (en) How to remove a bridge
JP2001241012A (en) Bridge removal and construction method
JPH10237823A (en) Method for replacing overhead bridge
JP2005171521A (en) Work-execution method for pole head
JP2004332425A (en) Bridge construction method and bridge building apparatus
JP4047093B2 (en) Construction method of multilevel intersection road
JP2004285799A (en) Construction method of bridge section side span of multi-level crossover road
JP2000104220A (en) Erection of combined truss bridge
JPH11190008A (en) Rebuilding method for elevated bridge
JP6618116B2 (en) Construction method of pier
JPH11323838A (en) Construction method of bridge
JPH0336362B2 (en)
JPH08135182A (en) Timbering sliding construction method
JPH10114913A (en) Slab construction method