JP2004332425A - Bridge construction method and bridge building apparatus - Google Patents
Bridge construction method and bridge building apparatus Download PDFInfo
- Publication number
- JP2004332425A JP2004332425A JP2003131100A JP2003131100A JP2004332425A JP 2004332425 A JP2004332425 A JP 2004332425A JP 2003131100 A JP2003131100 A JP 2003131100A JP 2003131100 A JP2003131100 A JP 2003131100A JP 2004332425 A JP2004332425 A JP 2004332425A
- Authority
- JP
- Japan
- Prior art keywords
- bridge girder
- girder
- bridge
- pier
- movable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 61
- 238000009415 formwork Methods 0.000 claims description 34
- 239000000725 suspension Substances 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 14
- 238000009416 shuttering Methods 0.000 abstract 3
- 238000005452 bending Methods 0.000 description 6
- 239000004567 concrete Substances 0.000 description 6
- 238000010586 diagram Methods 0.000 description 4
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000011513 prestressed concrete Substances 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000010485 coping Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、立設された橋脚間に、プレストレスコンクリート等で形成された橋桁を分割して張り出し構築する橋梁構築装置に関するものである。
【従来の技術】
従来、例えばプレストレストコンクリート製からなる橋桁をいわゆる移動架設桁を用いて張り出し構築するものとしては、いわゆるP&Z工法と称される工法が一般的に知られている。
【0002】
このP&Z工法は、立設された所定の橋脚間において、架設されるスパンより例えば約15mないし20m程度長さの長い移動架設桁が使用される。
【0003】
そして、この移動架設桁には一対の橋桁形成用型枠装置が長手方向に移動可能とされて懸垂される。
【0004】
そして、この移動架設桁を使用しての作業の際には前記移動架設桁を橋脚上部等に支持する3基の架台や移動時に使用される先端補助支柱等も用いられる。
【0005】
ここで、P&Z工法では、前記移動架設桁に懸垂された一対の橋桁形成用型枠装置を橋脚の両脇に配置させ、いわゆるやじろべいの原理を利用して絶妙な平衡バランスを取りながら橋桁の分割張り出し構築を行うものである。
【0006】
しかして、このようなP&Z工法を用いることにより、いわゆる大スパンのPC橋梁の施工であっても比較的簡単に構築することが可能とされる。
【0007】
しかしながら、前記橋桁の分割張り出し構築を行うに際しては、まず橋脚上部側に橋桁柱頭部を構築することが必要となる。
【0008】
何故ならこの橋桁柱頭部を構築した後、該橋桁柱頭部を基軸にしてその両脇に一対の橋脚形成用型枠装置を配し、もって橋桁の分割張り出し構築を行うものとされるからである。
【0009】
このP&Z工法の詳細については特公昭59−47762号公報に記載されている。
【0010】
【特許文献1】
特公昭59−47762号公報
【発明が解決しようとする課題】
しかるに、従来のP&Z工法によるいわゆるP&Z装置を用いて施工する場合につき考察すると、当該従来のP&Z装置ではいわゆる前方側(橋桁を構築すべき先端方向側)の橋桁形成用型枠装置を用いて橋桁柱頭部の構築を行うが、P&Z工法の工程順序の上から橋桁の分割張り出し構築作業を常に優先しなければならない。
【0011】
すなわち、従来では、橋桁柱頭部が構築された橋脚両脇に一対の橋桁形成用型枠装置を配置し、該一対の橋桁形成用型枠装置により橋桁を分割張り出し構築し、必ずその作業の後に前方側(橋桁を構築すべき先端方向側)の橋桁形成用型枠装置を用いて橋桁柱頭部の構築するものであった。
【0012】
このように従来では橋桁の分割張り出し構築作業と、次の橋脚における橋桁柱頭部の構築作業を決して同時に行えるものではなく、もって、その結果、橋梁全体の施工工期が長くならざるを得ず、その分作業コストが嵩むとの課題があった。
【0013】
また、前方側の橋桁形成用型枠装置で橋桁柱頭部を構築するため、特に前方側橋桁形成用型枠装置は橋桁柱頭部の構築と橋桁の分割張り出し構築との双方に対応できる構造の型枠装置であることが必要であり、前記型枠装置の構造が複雑かつ重厚長大にならざるを得ず作業性の悪いものとなっていた(図13,図14参照)。
【0014】
かくして、本発明は前記従来の課題に対処すべく創案されたもので、橋梁構築の工程上、その作業を常に所定の順番に沿って行う必要がない、すなわち橋桁の分割張り出し構築を行っているときは次の橋桁柱頭部の構築作業を同時に行えないとのことがなく、例えば、従来の様に、橋桁柱頭部が構築された橋脚両脇に一対の橋桁形成用型枠装置を配置し、該一対の橋桁形成用型枠装置により橋桁を分割張り出し構築し、その後に前方側(橋桁を構築すべき先端方向側)の橋桁形成用型枠装置を用いて橋桁柱頭部の構築するものでないため、橋桁の分割張り出し構築作業と、次の橋脚の橋桁柱頭部との構築作業を同時に行うことができ、その結果、橋梁全体としての構築工期をきわめて短くすることが出来、さらには、従来のように型枠装置の構造が複雑かつ重厚長大で作業性の悪いとの懸念も生じない橋梁構築方法及び橋梁構築装置を提供することを目的とするものである。
【課題を解決するための手段】
本発明による橋梁構築方法及び橋梁構築装置は、
立設された橋脚上に移動架設桁を架設し、
該移動架設桁長手方向に沿い移動可能にして懸垂された一対の橋桁形成用型枠装置で、一の橋脚に予め形成された橋桁柱頭部両脇から均等に張り出し構築し橋桁を分割形成する工程と共に、前記移動架設桁の橋桁架設方向先端側で懸垂され、移動架設桁に沿って移動可能な橋桁柱頭部形成用型枠装置によって、前記一の橋脚に隣接する橋脚に新たに橋桁柱頭部を形成する工程を同時に実施し、
前記一の橋脚側橋桁柱頭部の一方側橋桁形成部分が、既に形成されてある橋桁形成部分に接続された後には、前記移動架線桁の先端側を次に隣接する橋脚上に位置させるよう移動させ、
前記一の橋脚に隣接する橋脚に新たに形成された橋桁柱頭部両脇からは均等に張り出し構築すべく橋桁形成用型枠装置で橋桁を分割形成する工程と共に、さらに隣接する橋脚に橋桁柱頭部形成用型枠装置で次の新たな橋桁柱頭部を形成する工程とを同時実施することを順次繰り返し、橋脚上に橋桁を形成したことを特徴とし、
または、
立設された橋脚上に架設される移動架設桁と、
前記移動架設桁から各々懸垂され、前記橋脚のうち橋桁を張り出し構築すべき一方側橋脚の両脇に配置されて移動架設桁の長手方向に移動可能とされた一対の橋桁形成用型枠装置と、
前記移動架設桁から懸垂され、移動架設桁の長手方向端部側に配されて移動架設桁の長手方向に移動可能とされた橋桁の橋桁柱頭部形成用型枠装置と、
を備え、
前記橋桁形成用型枠装置は、移動架設桁から垂下する吊り下げ部材と、該吊り下げ部材に接続され、橋桁を張り出し構築すべき橋脚の橋桁柱頭部を基軸に橋桁架設方向両脇に配置され、橋桁を前記両脇から分割して張り出し構築する橋桁形成用型枠部材と、を有し、
前記橋桁の橋桁柱頭部形成用型枠装置は、移動架設桁から垂下する吊り下げ部材と、該吊り下げ部材に接続され、移動架設桁の長手方向端部側に位置する次の橋桁柱頭部構築方向に配置され、前記橋脚上に橋桁柱頭部を構築する橋桁柱頭部形成用型枠部材と、を有する、
ことを特徴とし、
または、
前記移動架設桁の長さは、前記橋脚間の少なくとも2倍以上の長さに構成されたことを特徴とするものである。
【0015】
【発明の実施の形態】
以下本発明を図に示す実施例に基づいて説明する。
【0016】
図1から理解されるように、あらかじめ複数本の橋脚1が所定の間隔を有して立設されている。そして、図1において、向かって左側から右側に向けて橋桁2が架設、構築されることとなる。
【0017】
符号20は本発明による橋梁構築装置であり、一般に鋼材をトラス状にして構成された長尺な移動架設桁3と、該移動架設桁3から懸垂された一対の橋桁形成用型枠装置4,4と、やはり前記移動架設桁3の架設方向先端側から懸垂されてなる橋桁柱頭部形成用型枠装置5とを有して構成されている。
【0018】
移動架設桁3は橋桁2の架設方向へ移動可能とされているが、橋桁2の架設作業時には複数の支持台6によって構築途中の橋桁2上に支持される。
【0019】
前記橋桁形成用型枠装置4は移動架設桁3から垂下する吊り下げ部材7と該吊り下げ部材7に接続された橋桁形成用型枠部材8とを有して形成され、前記移動架設桁3の長手方向へ移動可能とされている。
【0020】
そして、一対の橋桁形成用型枠装置4,4は橋桁2を張り出し構築すべき橋脚1(図1では真ん中に位置する橋脚1)の橋桁柱頭部9を基軸にして橋桁2の架設方向両脇に配置されており、橋桁2を前記橋脚1の橋桁柱頭部9からその両脇へ向かって徐々に分割して張り出し構築できるよう構成されている。
【0021】
ここで、橋桁形成用型枠部材8は図7から理解されるように、構築すべき橋桁2の幅方向両側に配置される一対の側壁用外型枠10,10と構築すべき橋桁2の底面側へ配置される底型枠11とを有し、これら型枠10,10,11は接合梁12等により連結されて、いわゆる箱状をなす橋桁形成用型枠部材8が構成されている。
【0022】
しかして、このように構成された一対の橋桁形成用型枠部材8内にコンクリートが打設され、当該コンクリートの固化後、脱型されて徐々に橋桁2の分割張り出し構築がなされる。
【0023】
次に、橋桁柱頭部形成用型枠装置5は前記移動架設桁3より垂下する吊り下げ部材7と、該吊り下げ部材7に接続された橋桁柱頭部形成用型枠部材18とを有して構成されており、やはり前記移動架設桁3の長手方向へ移動可能にして構成されている。
【0024】
ここで、連続ラーメン構造による橋梁の場合には、前記橋桁柱頭部型枠部材18は、図8から理解されるように、構築されるべき橋桁2の幅方向両側に配置される一対の橋桁柱頭部側壁型枠13,13が設けられているが、底型枠は設けられていない。
【0025】
すなわち橋桁柱頭部形成用型枠18は橋桁柱頭部9を形成して橋脚1上面と連結しなければならないため、底型枠は設ける必要がないのである。
【0026】
次に、連続桁構造による橋梁の場合も、すでに完成した橋脚1の上部に底型枠11を敷き並べる方法をとるため、橋桁柱頭部形成用型枠部材18には底型枠11を設けておく必要がないのである(図9参照)。
【0027】
このように、橋桁柱頭部形成用型枠部材18は、橋脚1上に橋桁柱頭部9を形成すべく移動、配置されるが、図8,図9,図11及び図12から理解されるように、橋脚1の上面に対応する箇所に用いる底型枠11は橋桁柱頭部形成用型枠部材18には設けられてはいない。
【0028】
すなわち、ラーメン構造の橋梁の場合、橋桁柱頭部形成用型枠部材18における橋脚1の上面に対応する箇所は橋桁柱頭部9と橋脚1とを連通するための空間部14として構成されており、該空間14部から橋脚1の上面と形成すべき橋桁柱頭部9とを連結するよう型枠16が橋桁柱頭部形成用型枠部材18に配置され、該型枠16内にコンクリートが打設出来るものとなっている(図12参照)。
【0029】
このような構成を採用するため、予め立設されてなる橋脚1先端部と橋桁柱頭部9との施工境界が橋桁柱頭部9の桁下4〜5m程度であったとしても充分に対応できるのである。
【0030】
なお、連続桁構造の橋梁の場合には図9及び図11から理解されるように、支承17の周囲において、橋脚1上で底型枠11を敷き並べることとなる。しかして、橋桁柱頭部9形成用コンクリートの固化後、前記底型枠11を脱型することとなる。
【0031】
ところで、橋桁柱頭部形成用型枠装置5において、前記橋桁2の架設方向前後には前記空間14を挟んでそれぞれ張り出し型枠15,15が設けられている(図10,図11,図12参照)。さらに、この張り出し型枠15,15は同図に示すように、橋桁柱頭部9が各々架設方向前後方向に向けて延出する形をなし、かつその底面が上り勾配状の傾斜を持たせて構築出来得る構成ともなっているのである(図13参照)。
【0032】
本発明の橋梁構築装置による施工状態につき説明する。
【0033】
本発明では、図3に示すように一対の橋桁形成用型枠装置4,4での橋桁2の分割張り出し構築作業と、次の橋脚1の橋桁柱頭部9の構築作業とが同時に行える。なお、図において符号21は補助支柱を示す。
【0034】
すなわち、図3及び図4に示すように前記作業を同時に進めることが出来、図5に示す如く左側橋桁2部分の接続が完了したら移動架設桁3を橋桁2架設方向へ移動させ、次の橋脚1の上部において支持させる(図6参照)。
【0035】
そして、前述したように、また、一対の橋桁形成用型枠装置4,4での橋桁の分割張り出し構築作業と、次の橋脚1の橋桁柱頭部9の構築作業とを同時に行うのである(図3、図4参照)。
【0036】
すなわち、立設された橋脚1上に移動架設桁3を架設し、この移動架設桁3の長手方向に沿い移動可能にして懸垂された一対の橋桁形成用型枠装置4,4で、一の橋脚1に予め形成された橋桁柱頭部両脇から均等に張り出し構築し橋桁を分割形成する工程を実施する。
【0037】
と同時に、前記移動架設桁3の橋桁1架設方向先端側で懸垂され、移動架設桁3に沿って移動可能な橋桁柱頭部形成用型枠装置5によって、前記一の橋脚1に隣接する橋脚1に新たに橋桁柱頭部9を形成する工程を実施するのである((図3,図4参照)。
【0038】
そして、図5,図6から理解されるように前記一の橋脚1側橋桁柱頭部9の一方側橋桁形成部分が、既に形成されてある橋桁形成部分に接続された後には、前記移動架線桁3の先端側を次に隣接する橋脚1上に位置させるよう移動させる。
この状態で前記一の橋脚1に隣接する橋脚1に新たに形成された橋桁柱頭部9両脇からは均等に張り出し構築すべく一対の橋桁形成用型枠装置4,4で橋桁2を分割形成する工程を実施すると同時に、さらに隣接する橋脚1に橋桁柱頭部形成用型枠装置5で次の新たな橋桁柱頭部9を形成する工程を実施し(図6参照)、この工程を順次繰り返し、橋脚1上に橋桁2を形成するのである。
【0039】
ところで、本発明において移動架設桁3の長さを橋脚1,1間の長さの少なくとも2倍以上の長さとした場合には、図16から理解されるように全ての複数ある支持台6を橋脚1付近に設置することができる。
【0040】
これに対し図17には従来工法における複数支持台6の設置箇所を示す。しかして図17に示すような従来工法における複数支持台6の置き方では、特に形成途上の橋桁2先端部側に設置された支持台6の反力により橋脚1付近の橋桁2に負の曲げモーメントが発生してしまう恐れがあった。
【0041】
しかるに、図16に示すような本発明による複数支持台6の置き方であれば、橋桁2に対しての曲げモーメントの発生を防止できることこととなる。
【0042】
従って、従来曲げモーメントの発生により橋桁2が撓まないよう、形成された橋桁2のスパンや橋桁2の断面等の条件次第では、補強のための仮設ケーブル等補強部材が必要となることもあったが、本発明によれば仮設ケーブル等補強部材が全く不要となるのである。
【発明の効果】
かくして本発明は以上の構成よりなる。
【0043】
そして、本発明による橋梁構築方法及び橋梁構築装置であれば、橋梁構築の工程上、その作業を常に所定の順番に沿って行う必要がない、すなわち従来のように橋桁の分割張り出し構築を行っているときは次の橋桁柱頭部の構築作業を同時に行えないとのことがなく、例えば、橋桁柱頭部が構築された橋脚両脇に一対の橋桁形成用型枠装置を配置し、該一対の橋桁形成用型枠装置により橋桁を分割張り出し構築し、その後に前方側(橋桁を構築すべき先端方向側)の橋桁形成用型枠装置を用いて橋桁柱頭部の構築するものでないため、橋桁の分割張り出し構築作業と、次の橋脚の橋桁柱頭部との構築作業を同時に行うことができ、その結果、橋梁全体としての構築工期をきわめて短くすることが出来る。
【0044】
また、従来のように型枠装置の構造が複雑かつ重厚長大で作業性の悪くなることがないとの優れた効果を奏する。
【図面の簡単な説明】
【図1】本発明による橋梁構築装置の構成を説明する構成説明図である。
【図2】本発明による橋梁構築装置を使用して橋桁及び橋桁柱頭部を同時に構築する状態を説明する概略説明図(その1)である。
【図3】本発明による橋梁構築装置を使用して橋桁及び橋桁柱頭部を同時に構築する状態を説明する概略説明図(その2)である。
【図4】本発明による橋梁構築装置を使用して橋桁及び橋桁柱頭部を同時に構築する状態を説明する概略説明図(その3)である。
【図5】本発明による橋梁構築装置を使用して橋桁及び橋桁柱頭部を同時に構築する状態を説明する概略説明図(その4)である。
【図6】本発明による橋梁構築装置を使用して橋桁及び橋桁柱頭部を同時に構築する状態を説明する概略説明図(その5)である。
【図7】本発明による橋桁形成用型枠部材の構成を説明する構成説明図である。
【図8】本発明による橋桁柱頭部形成用型枠部材の構成を説明する構成説明図(その1)である。
【図9】本発明による橋桁柱頭部形成用型枠部材の構成を説明する構成説明図(その2)である。
【図10】本発明による橋桁柱頭部形成用型枠部材における張り出し型枠の張り出し方向を説明する説明図である。
【図11】本発明による橋桁柱頭部形成用型枠部材における張り出し型枠の張り出し方向を側面からみて説明する説明図(その1)である。
【図12】本発明による橋桁柱頭部形成用型枠部材における張り出し型枠の張り出し方向を側面からみて説明する説明図(その2)である。
【図13】本発明による橋梁構築装置を使用して橋桁を構築した状態を説明する概略説明図である。
【図14】従来例による橋桁及び橋桁柱頭部を構築する型枠装置の構成を説明する構成説明図(その1)である。
【図15】従来例による橋桁及び橋桁柱頭部を構築する型枠装置の構成を説明する構成説明図(その2)である。
【図16】本発明による移動架設桁を使用して橋桁を構築する際における橋桁の曲げモーメントを説明する概略説明図である。
【図17】従来例による移動架設桁を使用して橋桁を構築する際における橋桁の曲げモーメントを説明する概略説明図である。
【符号の説明】
1 橋脚
2 橋桁
3 移動架設桁
4 橋桁形成用型枠装置
5 橋桁柱頭部形成用型枠装置
6 支持台
7 吊り下げ部材
8 橋桁形成用型枠部材
9 橋桁柱頭部
10 側壁用型枠部材
11 底型枠
12 接合梁
13 橋桁柱頭部形成用側壁型枠
14 空間部
15 張り出し型枠
16 型枠
17 支承
18 橋桁柱頭部形成用型枠部材
20 橋梁構築装置
21 補助支柱
22 高さ及び勾配調整ブロック[0001]
TECHNICAL FIELD OF THE INVENTION
TECHNICAL FIELD The present invention relates to a bridge construction apparatus that divides a bridge girder made of prestressed concrete or the like between erected piers to project overhang.
[Prior art]
2. Description of the Related Art Conventionally, as a method of extending a bridge girder made of, for example, prestressed concrete using a so-called movable erection girder, a construction method called a so-called P & Z construction method is generally known.
[0002]
In this P & Z method, a movable erection girder having a length, for example, about 15 to 20 m longer than a span to be erected is used between predetermined erected piers.
[0003]
A pair of bridge girder forming form devices are suspended from the movable erection girder so as to be movable in the longitudinal direction.
[0004]
In the operation using the movable erection girder, three gantry for supporting the movable erection girder on an upper part of a pier or the like, and a tip support column used for movement are also used.
[0005]
Here, in the P & Z method, a pair of bridge girder forming form devices suspended from the movable erection girder are arranged on both sides of the pier, and the bridge girder is adjusted while maintaining an exquisite balance using the so-called palletization principle. Is performed to construct the split overhang.
[0006]
By using the P & Z method, it is possible to relatively easily construct a so-called large-span PC bridge.
[0007]
However, when performing the split overhang construction of the bridge girder, it is first necessary to construct the bridge girder column head on the upper side of the pier.
[0008]
This is because, after this bridge girder column head is constructed, a pair of pier forming form devices are arranged on both sides thereof with the bridge girder column head as a base axis, and the split girder construction of the bridge girder is performed. .
[0009]
The details of the P & Z method are described in JP-B-59-47762.
[0010]
[Patent Document 1]
JP-B-59-47762 [Problems to be solved by the invention]
However, considering the case of using a so-called P & Z apparatus by the conventional P & Z method, the conventional P & Z apparatus uses a bridge girder forming apparatus on a so-called front side (a front end side on which a bridge girder is to be built). The construction of the column caps is performed, but the division and overhang construction work of the bridge girder must always be given priority from the process sequence of the P & Z method.
[0011]
That is, conventionally, a pair of bridge girder forming form devices are arranged on both sides of the bridge pier on which the bridge girder column head is constructed, and the bridge girder is divided and overhanged by the pair of bridge girder forming form devices, and always after the work, The bridge girder column head was constructed using the bridge girder forming form device on the front side (the front end side where the bridge girder should be constructed).
[0012]
As described above, in the past, the work of constructing the split girder of the bridge girder and the work of constructing the bridge girder column head at the next pier could not be performed at the same time, and as a result, the construction period of the entire bridge had to be prolonged. There was a problem that the cost for the minute work was increased.
[0013]
In addition, since the bridge girder column head is constructed with the bridge girder forming form device on the front side, the front bridge girder forming form device has a structure capable of coping with both the construction of the bridge girder column head and the split girder construction of the bridge girder. It was necessary to be a frame device, and the structure of the mold device had to be complicated, heavy, and long, resulting in poor workability (see FIGS. 13 and 14).
[0014]
Thus, the present invention has been devised in order to address the above-mentioned conventional problems, and in the process of constructing a bridge, it is not necessary to always perform the work in a predetermined order, that is, to construct a projecting division of a bridge girder. Sometimes, the construction work of the next bridge girder column head can not be done simultaneously, for example, as in the past, a pair of bridge girder forming form devices are arranged on both sides of the bridge pier where the bridge girder column head is built, Since the bridge girder is divided and overhanged by the pair of bridge girder forming form devices, and then the bridge girder column head is not constructed by using the bridge girder forming form device on the front side (the front end side where the bridge girder is to be built). The construction work of the bridge girder split overhang and the construction work of the bridge girder column head of the next pier can be performed at the same time. As a result, the construction period of the bridge as a whole can be extremely shortened. To formwork equipment Concrete is an object of the present invention is to provide a bridge construction method and bridges construction apparatus that does not cause concern for poor complex and smokestack and workability.
[Means for Solving the Problems]
A bridge construction method and a bridge construction apparatus according to the present invention include:
A mobile erection girder is erected on the erected pier,
A step of forming a pair of bridge girders which are movable along the longitudinal direction of the movable girder and which are suspended from a pair of bridge girder column heads formed in advance on one pier by using a pair of bridge girder forming form devices. Along with the movable girder in the bridge girder construction direction front end side, the bridge girder column head forming form device movable along the movable girder allows a new bridge girder column head to be newly attached to the pier adjacent to the one pier. The steps of forming simultaneously
After the one bridge girder forming portion of the one pier side bridge girder column head is connected to the already formed bridge girder forming portion, the movable bridge girder is moved so that the tip side thereof is positioned on the next adjacent pier. Let
A step of dividing and forming a bridge girder with a bridge girder forming form device so as to project evenly from both sides of a bridge girder column head newly formed on a bridge pier adjacent to the one pier, and a bridge girder column head on a further adjacent pier It is characterized by forming a bridge girder on the pier by sequentially repeating the steps of forming the next new bridge girder column cap with the forming form device at the same time.
Or
A moving erection girder erected on an erect pier,
A pair of bridge girder forming form devices which are respectively suspended from the movable erection girder, are arranged on both sides of one of the piers on which the bridge girder is to be extended, and are movable in the longitudinal direction of the movable erection girder. ,
A bridge girder column head formation forming apparatus of a bridge girder suspended from the movable erection girder and arranged on a longitudinal end side of the movable erection girder and movable in the longitudinal direction of the movable erection girder;
With
The formwork device for forming a bridge girder is a suspension member hanging down from a movable construction girder, and connected to the suspension member, and arranged on both sides of the bridge girder construction direction with a bridge girder column head of a pier to be extended and constructed as a base. A bridge girder forming form member that divides the bridge girder from the both sides and overhangs the bridge girder,
The formwork device for forming a bridge girder column head of the bridge girder includes a hanging member hanging from the movable girder, and a next bridge girder column head construction connected to the hanging member and located on the longitudinal end side of the movable girder. A bridge girder column head forming form member that is arranged in the direction, and constructs a bridge girder column head on the pier,
Characterized in that
Or
The length of the movable erection girder is at least twice as long between the piers.
[0015]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, the present invention will be described based on an embodiment shown in the drawings.
[0016]
As understood from FIG. 1, a plurality of
[0017]
[0018]
The
[0019]
The bridge girder forming
[0020]
The pair of bridge girder forming
[0021]
As shown in FIG. 7, the bridge girder forming form member 8 includes a pair of side wall
[0022]
Then, concrete is poured into the pair of bridge girder forming form members 8 configured as described above, and after solidification of the concrete, the concrete is removed from the bridge girder and the
[0023]
Next, the bridge girder column head forming
[0024]
Here, in the case of a bridge having a continuous rigid frame structure, the bridge
[0025]
That is, since the bridge girder column
[0026]
Next, in the case of a bridge having a continuous girder structure, the
[0027]
As described above, the bridge girder column head forming
[0028]
That is, in the case of a bridge having a rigid frame structure, a portion corresponding to the upper surface of the
[0029]
In order to adopt such a configuration, it is possible to sufficiently cope with a case where the construction boundary between the tip of the
[0030]
In the case of a bridge having a continuous girder structure, as understood from FIGS. 9 and 11, the
[0031]
By the way, in the
[0032]
The construction state by the bridge construction apparatus of the present invention will be described.
[0033]
In the present invention, as shown in FIG. 3, the work of dividing and projecting the
[0034]
That is, as shown in FIG. 3 and FIG. 4, the above work can be performed simultaneously, and as shown in FIG. 5, when the connection of the
[0035]
Then, as described above, the work of constructing the split girder of the bridge girder by the pair of bridge girder forming
[0036]
That is, the
[0037]
At the same time, the
[0038]
Then, as understood from FIGS. 5 and 6, after the one-side bridge girder forming portion of the one pier 1-side bridge girder column head 9 is connected to the already formed bridge girder forming portion, the movable overhead girder is moved. 3 is moved so as to position the tip side on the next
In this state, the
[0039]
By the way, in the present invention, when the length of the
[0040]
On the other hand, FIG. 17 shows an installation location of the plurality of
[0041]
However, if the plurality of
[0042]
Therefore, depending on the conditions of the span of the
【The invention's effect】
Thus, the present invention has the above configuration.
[0043]
In the bridge construction method and the bridge construction apparatus according to the present invention, it is not necessary to always perform the work in a predetermined order in the bridge construction process, that is, by performing the split overhang construction of the bridge girder as in the related art. When it is, there is no possibility that the construction work of the next bridge girder can not be performed at the same time.For example, a pair of bridge girder forming form devices are arranged on both sides of the pier where the bridge girder is built, and the pair of bridge girder Since the bridge girder is divided and overhanged by the forming form device, the bridge girder column head is not constructed by using the bridge girder forming form device on the front side (front end side where the bridge girder is to be built). The overhanging construction work and the construction work of the bridge girder column head of the next pier can be performed at the same time, and as a result, the construction period of the entire bridge can be extremely shortened.
[0044]
Further, there is an excellent effect that the structure of the formwork device is complicated, heavy and long, and workability does not deteriorate as in the related art.
[Brief description of the drawings]
FIG. 1 is a configuration explanatory diagram illustrating a configuration of a bridge construction apparatus according to the present invention.
FIG. 2 is a schematic explanatory diagram (part 1) illustrating a state in which a bridge girder and a bridge girder column head are simultaneously constructed using the bridge construction apparatus according to the present invention.
FIG. 3 is a schematic explanatory view (part 2) illustrating a state in which a bridge girder and a bridge girder column head are simultaneously constructed using the bridge construction apparatus according to the present invention.
FIG. 4 is a schematic explanatory view (part 3) illustrating a state in which a bridge girder and a bridge girder column head are simultaneously constructed using the bridge construction apparatus according to the present invention.
FIG. 5 is a schematic explanatory view (part 4) illustrating a state in which a bridge girder and a bridge girder column head are simultaneously constructed using the bridge construction apparatus according to the present invention.
FIG. 6 is a schematic explanatory view (part 5) illustrating a state in which a bridge girder and a bridge girder column head are simultaneously constructed using the bridge construction apparatus according to the present invention.
FIG. 7 is a configuration explanatory view illustrating a configuration of a bridge girder forming form member according to the present invention.
FIG. 8 is a configuration explanatory view (part 1) illustrating the configuration of a form member for forming a bridge girder column head according to the present invention.
FIG. 9 is a configuration explanatory view (part 2) for explaining the configuration of the bridge girder column head forming mold member according to the present invention;
FIG. 10 is an explanatory view for explaining a projecting direction of a projecting formwork in a form member for forming a bridge girder column head according to the present invention.
FIG. 11 is an explanatory view (part 1) for explaining a projecting direction of a projecting formwork in a form member for forming a bridge girder column head according to the present invention as viewed from a side.
FIG. 12 is an explanatory view (part 2) for explaining the projecting direction of the projecting formwork in the formwork member for forming a bridge girder column head according to the present invention as viewed from the side.
FIG. 13 is a schematic explanatory diagram illustrating a state where a bridge girder has been constructed using the bridge construction apparatus according to the present invention.
FIG. 14 is a configuration explanatory view (No. 1) illustrating the configuration of a formwork device for constructing a bridge girder and a bridge girder column head according to a conventional example.
FIG. 15 is a configuration explanatory view (part 2) illustrating the configuration of a formwork device for constructing a bridge girder and a bridge girder column head according to a conventional example.
FIG. 16 is a schematic explanatory diagram illustrating a bending moment of a bridge girder when a bridge girder is constructed using the movable erection girder according to the present invention.
FIG. 17 is a schematic explanatory view for explaining a bending moment of a bridge girder when a bridge girder is constructed using a movable erection girder according to a conventional example.
[Explanation of symbols]
REFERENCE SIGNS
Claims (3)
該移動架設桁長手方向に沿い移動可能にして懸垂された一対の橋桁形成用型枠装置で、一の橋脚に予め形成された橋桁柱頭部両脇から均等に張り出し構築し橋桁を分割形成する工程と共に、前記移動架設桁の橋桁架設方向先端側で懸垂され、移動架設桁に沿って移動可能な橋桁柱頭部形成用型枠装置によって、前記一の橋脚に隣接する橋脚に新たに橋桁柱頭部を形成する工程を同時に実施し、
前記一の橋脚側橋桁柱頭部の一方側橋桁形成部分が、既に形成されてある橋桁形成部分に接続された後には、前記移動架線桁の先端側を次に隣接する橋脚上に位置させるよう移動させ、
前記一の橋脚に隣接する橋脚に新たに形成された橋桁柱頭部両脇からは均等に張り出し構築すべく橋桁形成用型枠装置で橋桁を分割形成する工程と共に、さらに隣接する橋脚に橋桁柱頭部形成用型枠装置で次の新たな橋桁柱頭部を形成する工程とを同時実施することを順次繰り返し、橋脚上に橋桁を形成したことを特徴とする橋梁構築方法。A mobile erection girder is erected on the erected pier,
A step of forming a pair of bridge girders which are movable along the longitudinal direction of the movable girder and which are suspended from a pair of bridge girder column heads formed in advance on one pier by using a pair of bridge girder forming form devices. Along with the movable girder in the bridge girder construction direction front end side, the bridge girder column head forming form device movable along the movable girder allows a new bridge girder column head to be newly attached to the pier adjacent to the one pier. The steps of forming simultaneously
After the one bridge girder forming portion of the one pier side bridge girder column head is connected to the already formed bridge girder forming portion, the movable bridge girder is moved so that the tip side thereof is positioned on the next adjacent pier. Let
A step of dividing and forming a bridge girder with a bridge girder forming form device so as to project evenly from both sides of a bridge girder column head newly formed on the bridge pier adjacent to the one pier, and a bridge girder column head on a further adjacent pier A bridge construction method, wherein a bridge girder is formed on a pier by sequentially and simultaneously repeating a step of forming a new bridge girder column head with a forming form device.
前記移動架設桁から各々懸垂され、前記橋脚のうち橋桁を張り出し構築すべき一方側橋脚の両脇に配置されて移動架設桁の長手方向に移動可能とされた一対の橋桁形成用型枠装置と、
前記移動架設桁から懸垂され、移動架設桁の長手方向端部側に配されて移動架設桁の長手方向に移動可能とされた橋桁の橋桁柱頭部形成用型枠装置と、
を備え、
前記橋桁形成用型枠装置は、移動架設桁から垂下する吊り下げ部材と、該吊り下げ部材に接続され、橋桁を張り出し構築すべき橋脚の橋桁柱頭部を基軸に橋桁架設方向両脇に配置され、橋桁を前記両脇から分割して張り出し構築する橋桁形成用型枠部材と、を有し、
前記橋桁の橋桁柱頭部形成用型枠装置は、移動架設桁から垂下する吊り下げ部材と、該吊り下げ部材に接続され、移動架設桁の長手方向端部側に位置する次の橋桁柱頭部構築方向に配置され、前記橋脚上に橋桁柱頭部を構築する橋桁柱頭部形成用型枠部材と、を有する、
ことを特徴とする橋梁構築装置。A moving erection girder erected on the erected pier,
A pair of bridge girder forming form devices which are respectively suspended from the movable erection girder, are arranged on both sides of one of the piers on which the bridge girder is to be extended, and are movable in the longitudinal direction of the movable erection girder. ,
A bridge girder column head formation forming apparatus of a bridge girder suspended from the movable erection girder and arranged on a longitudinal end side of the movable erection girder and movable in the longitudinal direction of the movable erection girder;
With
The formwork device for forming a bridge girder is a suspension member hanging down from a movable construction girder, and connected to the suspension member, and arranged on both sides of the bridge girder construction direction with a bridge girder column head of a pier to be extended and constructed as a base. A bridge girder forming form member that divides the bridge girder from the both sides and overhangs the bridge girder,
The formwork device for forming a bridge girder column head of the bridge girder includes a hanging member hanging from the movable girder, and a next bridge girder column head construction connected to the hanging member and located on the longitudinal end side of the movable girder. A bridge girder column head forming form member that is arranged in the direction and constructs a bridge girder column head on the pier,
A bridge construction apparatus, characterized in that:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003131100A JP3790229B2 (en) | 2003-05-09 | 2003-05-09 | Bridge construction method and bridge construction apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003131100A JP3790229B2 (en) | 2003-05-09 | 2003-05-09 | Bridge construction method and bridge construction apparatus |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004332425A true JP2004332425A (en) | 2004-11-25 |
JP3790229B2 JP3790229B2 (en) | 2006-06-28 |
Family
ID=33506372
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003131100A Expired - Fee Related JP3790229B2 (en) | 2003-05-09 | 2003-05-09 | Bridge construction method and bridge construction apparatus |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3790229B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100983861B1 (en) | 2008-02-20 | 2010-09-28 | 주식회사 동성엔지니어링 | Integral composite slab bridge without abutments, supports, and expansion joints, and construction method thereof |
ES2352023A1 (en) * | 2008-04-03 | 2011-02-15 | Structural Research, S.L. | Procedure for assembling prefabricated concrete dimensions. (Machine-translation by Google Translate, not legally binding) |
CN104060546A (en) * | 2014-07-11 | 2014-09-24 | 四川川交路桥有限责任公司 | Overall longitudinal movement construction method for cast-in-place support frame of box beam of continuous beam bridge |
CN110230259A (en) * | 2018-08-21 | 2019-09-13 | 中铁十八局集团有限公司 | A kind of pier top beam section that bridge cantilever pours and its rapid constructing method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103774555B (en) * | 2013-12-30 | 2016-04-27 | 江苏省交通工程集团有限公司 | Bridge pier shaft widens template |
-
2003
- 2003-05-09 JP JP2003131100A patent/JP3790229B2/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100983861B1 (en) | 2008-02-20 | 2010-09-28 | 주식회사 동성엔지니어링 | Integral composite slab bridge without abutments, supports, and expansion joints, and construction method thereof |
ES2352023A1 (en) * | 2008-04-03 | 2011-02-15 | Structural Research, S.L. | Procedure for assembling prefabricated concrete dimensions. (Machine-translation by Google Translate, not legally binding) |
CN104060546A (en) * | 2014-07-11 | 2014-09-24 | 四川川交路桥有限责任公司 | Overall longitudinal movement construction method for cast-in-place support frame of box beam of continuous beam bridge |
CN110230259A (en) * | 2018-08-21 | 2019-09-13 | 中铁十八局集团有限公司 | A kind of pier top beam section that bridge cantilever pours and its rapid constructing method |
CN110230259B (en) * | 2018-08-21 | 2021-05-28 | 中铁十八局集团有限公司 | Bridge cantilever casting pier top beam section and rapid construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP3790229B2 (en) | 2006-06-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4569878B2 (en) | Bridge girder construction method | |
CN107338727B (en) | Integrally-disassembled and assembled anti-collision wall template and walking type rail hanging and moving system thereof | |
JP2008088782A (en) | Cantilever overhang erection method of corrugated steel plate web bridge | |
JP4403051B2 (en) | Corrugated steel web bridge construction method | |
CN108589535B (en) | Reinforced concrete box type arch bridge construction method | |
JP2008038449A (en) | Bridge girder constructing method | |
CN108755421A (en) | Capping beam construction device and construction method | |
CN105401679A (en) | Large-gradient cast-in-place concrete inclined roof construction method | |
JP3845619B2 (en) | Column head construction method | |
JP4104910B2 (en) | How to build arch ribs for concrete arch bridges | |
JP3110985B2 (en) | Construction method of column capital of overhang girder bridge | |
JP2004332425A (en) | Bridge construction method and bridge building apparatus | |
JP6509096B2 (en) | Extension method | |
JP4980257B2 (en) | Construction method for column head construction, method for constructing mobile work vehicle using part thereof, and method for extending bridge | |
JP2005240353A (en) | Erection method of bridge | |
JP2000087316A (en) | Method and device for construction of floor slab | |
JP2006316506A (en) | Method of constructing bridge girder | |
JP6889010B2 (en) | Bridge construction method | |
JPH06185013A (en) | Construction method of column head section of pc diagonal tension bridge | |
CN211689932U (en) | Cast-in-place beam suspends support in midair | |
JP6449637B2 (en) | Building construction method | |
JP2556247B2 (en) | Construction method of concrete bridge and its construction equipment | |
JP2020186516A (en) | Method of constructing bridge railing | |
JP2000129633A (en) | Erection method for bridge floor slab | |
JP2000104220A (en) | Erection of combined truss bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050613 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20050623 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20050707 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051215 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060104 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060302 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060328 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060330 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3790229 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090407 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120407 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120407 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130407 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130407 Year of fee payment: 7 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130407 Year of fee payment: 7 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140407 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |