JPH07300817A - Concrete-filled steel pipe truss pier and construction method - Google Patents

Concrete-filled steel pipe truss pier and construction method

Info

Publication number
JPH07300817A
JPH07300817A JP11737194A JP11737194A JPH07300817A JP H07300817 A JPH07300817 A JP H07300817A JP 11737194 A JP11737194 A JP 11737194A JP 11737194 A JP11737194 A JP 11737194A JP H07300817 A JPH07300817 A JP H07300817A
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
pipe main
pier
filled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP11737194A
Other languages
Japanese (ja)
Inventor
Hidemi Ota
英美 太田
Akira Komatsu
章 小松
Kazunori Tomono
一徳 友野
Shigeki Mizukami
繁樹 水上
Yoshiaki Imai
義明 今井
Masaichi Horiguchi
政一 堀口
Akihiko Mochizuki
明彦 望月
Fumihide Hiuga
文英 日向
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Nippon Steel Corp
Original Assignee
Taisei Corp
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Nippon Steel Corp filed Critical Taisei Corp
Priority to JP11737194A priority Critical patent/JPH07300817A/en
Publication of JPH07300817A publication Critical patent/JPH07300817A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To provide the structure of a pier which makes it possible to shorten the construction process and enhance its load bearing capacity and reduce the weight and eliminate the eminence work. CONSTITUTION:Panel blocks 9 in which horizontal beams 2 and slanting beams 3 are joined with a plurality of steel pipe posts having a rig inside, are manufactured. The panel blocks 9 are erected on a lift rack and the horizontal beams 2 and the slanting beams 3 are joined with each other, thereby building up a 3D block. The lift rack 10 is adapted to rise and maintained at a specified position, the lower stage blocks 9 are erected in a lower space and joined with each other and then the lift rack is adapted to fall. The same process is repeated hereafter, thereby finishing a steel pipe truss. After that, concrete 1b is filled up in the steel pipe posts 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、高速道路、鉄道橋等の
橋梁や高架橋に用いられる比較的大規模な橋脚における
コンクリート充填鋼管トラス橋脚及びその施工方法に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete-filled steel pipe truss pier and a construction method thereof for a relatively large-scale pier used for bridges such as highways and railway bridges and viaducts.

【0002】[0002]

【従来の技術】従来、これらの橋脚は周知のように、鉄
筋コンクリートによる円柱、楕円柱、角柱等の構造形式
が一般的であった。それ故にこれらの橋脚を施工する場
合、型枠を組立てその内部にコンクリートを打設すると
いう作業を繰り返して立ち上げて行く方法が採用されて
いた。即ち、その施工手順は橋脚の下部から数段に分け
て足場の組立、鉄筋の組立、型枠の組立、コンクリート
の打設、コンクリートの養生、型枠の脱型、そして再び
足場の組立、という作業を繰り返す方法であった。
2. Description of the Related Art Heretofore, as is well known, these bridge piers have generally been of a structural type such as a column made of reinforced concrete, an elliptic column or a prism. Therefore, when constructing these bridge piers, the method of assembling a formwork and placing concrete inside the formwork was repeated to start up. That is, the construction procedure is divided into several stages from the lower part of the pier: scaffold assembly, rebar assembly, formwork assembly, concrete placement, concrete curing, formwork demolding, and scaffolding assembly again. It was a method of repeating the work.

【0003】[0003]

【発明が解決しようとする課題】前記従来の橋脚のコン
クリート構造形式、施工方法にあっては、次のような課
題があった。鉄筋の組立、型枠の組立は手数がかかり工
程に影響を与える作業であるが、従来の構造形式及びそ
れに伴う施工方法ではこの工程が省力化できないために
作業期間を短縮することが困難であった。高所まで型
枠、鉄筋を組み立てて立ち上げ、コンクリートを打設す
るにはその周囲に足場を組み立てる必要があり多大の手
数がかかるとともに、すべてが高所における作業となり
危険である。特に熟練した作業員が不足している最近に
おいては、高所での作業は品質の低下も招きかねない。
高所にて型枠、鉄筋を組み立てて立ち上げコンクリート
を打設するため、作業環境を一定に保持するための対策
が困難で、雨天、荒天時の作業停止を余儀なくされ工程
の短縮が難しい。また、コンクリートは打設後、強度発
現迄一定の養生期間を要するためその分工程が長くな
る。コンクリートによる橋脚構造は重量が大きいため、
基礎の規模が大きくなり多大の手数がかかる。本発明の
請求項1は、前記のような従来の課題を解決するために
なされたもので、手数のかかる鉄筋組立、型枠組立作業
等を省略して工程を短縮することができ、かつ高耐力と
橋脚重量低減を図った橋脚構造を提供することを目的と
し、また、請求項2は危険な高所での作業をなくし、低
所において通年作業ができる橋脚の施工方法を提供する
ことを目的とするものである。
The conventional concrete structure type and construction method for a bridge pier have the following problems. Reinforcing bar assembly and formwork assembly are labor-intensive and affect the process, but it is difficult to shorten the work period because the conventional structure type and the construction method accompanying it cannot save labor. It was In order to assemble and start up the formwork and reinforcing bars up to a high place, and to place concrete, it is necessary to assemble a scaffold around it, and it takes a lot of work, and all work is done at a high place, which is dangerous. Especially in recent years, when skilled workers are scarce, work at high places may cause deterioration of quality.
Since the formwork and reinforcing bars are assembled and the concrete is placed at a high place, it is difficult to take measures to keep the work environment constant, and it is difficult to shorten the process because it is necessary to stop the work in rainy or stormy weather. In addition, since concrete requires a certain curing period for strength to appear after it is poured, the process becomes longer accordingly. Since the pier structure made of concrete is heavy,
The scale of the foundation becomes large and it takes a lot of trouble. Claim 1 of the present invention has been made to solve the above-mentioned conventional problems, and it is possible to shorten the process by omitting troublesome rebar assembly, formwork assembly work, and the like. It is an object of the present invention to provide a bridge pier structure that is designed to reduce the load bearing capacity and weight of the pier, and claim 2 provides a method of constructing a pier that eliminates work in dangerous high places and can work all year long in low places. It is intended.

【0004】[0004]

【課題を解決するための手段】前記の目的を達成するた
め、本発明の請求項1に係わる橋脚構造は、耐力とじん
性の高いコンクリート充填鋼管を主部材としたトラス構
造としたもので、その構成は、内側に連続したリブ1a
を有する複数本の鋼管主柱1が間隔をおいて立設され、
各鋼管主柱1間が複数の水平梁2と斜梁3により接合さ
れ、鋼管主柱1と水平梁2および斜梁3の接合部におけ
る鋼管主柱1の内側に補剛リングプレート8が溶接され
ており、鋼管主柱1内部にはコンクリート1bが充填さ
れていることを特徴とするコンクリート充填鋼管トラス
橋脚を請求項1の発明とするものである。また、橋脚設
置地点に、複数の鉛直支柱12に沿って上下移動可能な
昇降架台11を設置し、工場または現場近くの地上にお
いて、鋼管主柱1の間に水平梁2および斜梁3を接合し
て平面状のパネルブロック9を製作し、前記パネルブロ
ック9を橋脚設置点の所定位置に面を対向して縦方向に
建込んで、前記昇降架台11に下部をクランプし、パネ
ルブロック9の対向面間に水平梁2,斜梁3を接合して
立体ブロック10とし、次に前記昇降架台11を上昇し
て立体ブロック10を所定高さまで上昇して保持し、下
方に所定の組立空間を形成し、前記組立空間に前記パネ
ルブロック9を建込み、その鋼管主柱1上端を、昇降架
台11で保持されている立体ブロック10を鋼管主柱1
下端に接合し、昇降架台11を地上部まで降下させ、以
下前述の動作を繰返し所定高さの鋼管トラスを完成させ
た後、鋼管主柱1内にコンクリート1bを充填すること
を特徴とするコンクリート充填鋼管トラス橋脚の施工方
法を請求項2の発明とするものである。さらにまた、昇
降架台11の周囲を全天候作業可能な簡易の防風・防雪
設備17で覆って作業することを特徴とする請求項2の
コンクリート充填鋼管トラス橋脚の施工法を請求項3の
発明とするものである。また、本発明の請求項2に係わ
るコンクリート充填鋼管トラス橋脚の施工法は高所作業
をなくし、地上でトラスの立体ブロックを製作・組立
し、昇降架台11で持上げた下方の組立空間で下段の立
体ブロック10を製作・組立し、先行組立の立体ブロッ
ク10と接合して、順次高さ方向に延長して鋼管トラス
を完成した後、鋼管主柱内にコンクリート1bを充填す
るもので、その手順は以下の通りである。 (イ)橋脚設置地点に、複数の鉛直支柱12に沿って上
下移動可能な昇降架台11を設置する。 (ロ)工場または現場近くの地上において、鋼管主柱1
間に水平梁2および斜梁3を接合して平面状のパネルブ
ロック9を製作する。 (ハ)前記パネルブロック9を橋脚設置点の所定位置に
面を対向して縦方向に建込み、前記昇降架台11に下部
をクランプする。 (ニ)パネルブロック9の対向面間に水平梁2、斜梁3
を接合して立体ブロック10とする。 (ホ)前記昇降架台11を上昇して立体ブロック10を
所定高さ迄持上げ保持し、下方に所定の組立空間を形成
する。 (ヘ)前記組立空間に前記(ロ)と同様にして製作した
下段のパネルブロック9を建込み、その鋼管主柱1の上
端を昇降架台11で保持している立体ブロック10の鋼
管主柱1の下端に接合する。 (ト)昇降架台11を地上部まで降下する。 (チ)以下(ハ)〜(ト)を繰返し所定高さの鋼管トラ
スを完成させた後、鋼管主柱1内にコンクリート1bを
充填する。 なお、本発明の施工法は地上部の低所作業で行うため、
昇降架台11の周囲を簡易の防風・防雪設備で覆えば、
雨天時等も作業可能とすることができる。
In order to achieve the above object, the pier structure according to claim 1 of the present invention is a truss structure having a concrete-filled steel pipe having high strength and toughness as a main member. The structure is such that the rib 1a continuous to the inside
A plurality of steel pipe main columns 1 are erected at intervals,
Each steel pipe main column 1 is joined by a plurality of horizontal beams 2 and oblique beams 3, and a stiffening ring plate 8 is welded to the inside of the steel pipe main column 1 at the joint between the steel pipe main column 1, horizontal beams 2 and oblique beams 3. The concrete-filled steel pipe truss pier is characterized in that the inside of the steel pipe main column 1 is filled with concrete 1b. Also, at the bridge pier installation point, an elevating platform 11 that can move up and down along a plurality of vertical columns 12 is installed, and horizontal beams 2 and oblique beams 3 are joined between steel pipe main columns 1 on the ground near the factory or the site. Then, a flat panel block 9 is manufactured, and the panel block 9 is vertically installed at a predetermined position of the pier installation point with its surface facing, and the lower part is clamped to the lifting platform 11, so that the panel block 9 The horizontal beam 2 and the slanted beam 3 are joined between the facing surfaces to form a solid block 10, and then the elevating stand 11 is raised to hold the solid block 10 up to a predetermined height, and a predetermined assembly space is provided below. The panel block 9 is built in the assembly space, and the upper end of the steel pipe main column 1 is connected to the three-dimensional block 10 held by the elevating platform 11 to form the steel pipe main column 1.
Concrete that is characterized in that it is joined to the lower end, the elevating platform 11 is lowered to the ground part, and the above-described operation is repeated to complete a steel pipe truss of a predetermined height, and then the steel pipe main column 1 is filled with concrete 1b. A method of constructing a filled steel pipe truss bridge pier is set forth in claim 2. Furthermore, the method of constructing a concrete-filled steel pipe truss bridge pier according to claim 2 is characterized in that the lifting platform 11 is covered with a simple windproof / snowproof facility 17 capable of working in all weather conditions. It is a thing. Further, the method for constructing a concrete-filled steel pipe truss bridge pier according to claim 2 of the present invention eliminates the work at high places, manufactures and assembles a three-dimensional block of the truss on the ground, and lifts it up and down by the elevating stand 11. The three-dimensional block 10 is manufactured and assembled, joined with the three-dimensional block 10 of the preceding assembly, and sequentially extended in the height direction to complete the steel pipe truss, and then the steel pipe main column is filled with concrete 1b. Is as follows. (B) At the bridge pier installation point, an elevating platform 11 that can move up and down along a plurality of vertical columns 12 is installed. (B) Steel pipe main pillar 1 on the ground near the factory or site
The horizontal beam 2 and the slanted beam 3 are joined together to form a flat panel block 9. (C) The panel block 9 is installed in a vertical direction at a predetermined position of the pier installation point so as to face the surface, and the lower part is clamped to the lifting platform 11. (D) Horizontal beam 2 and diagonal beam 3 between the facing surfaces of the panel block 9.
Are joined together to form a solid block 10. (E) Ascending / descending platform 11 raises and holds solid block 10 to a predetermined height, and a predetermined assembly space is formed below. (F) A steel pipe main column 1 of a three-dimensional block 10 in which a lower panel block 9 manufactured in the same manner as in (b) is built in the assembly space, and the upper end of the steel pipe main column 1 is held by an elevating platform 11. Join to the bottom of. (G) The lifting platform 11 is lowered to the ground. (H) After repeating the following (c) to (g) to complete a steel pipe truss having a predetermined height, the steel pipe main column 1 is filled with concrete 1b. In addition, since the construction method of the present invention is performed at a low place work on the ground,
If you cover the surroundings of the lifting platform 11 with simple wind and snow protection equipment,
It is possible to work even in the rain.

【0005】[0005]

【実施例】以下、図面を参照しながら本発明のコンクリ
ート充填鋼管トラス形式橋脚の構造及び施工方法の一例
について説明する。図1,図2は本発明のコンクリート
充填鋼管トラス橋脚(以下、単に橋脚という場合があ
る)の橋軸方向正面図と側面図であり、図3は図2のA
−A断面(平面図)を示す。橋脚は高さ方向に複数に分
割製作された立体ブロック10a〜10eを接合して組
立られ(本例は5分割)、橋脚の上端部は上部工4(橋
桁コンクリート)に埋込み固定され、下端部は下部工5
(基礎コンクリート)に埋め込み固定されている。それ
ぞれの部材および固定部の詳細は以下の通りである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An example of the structure and construction method of a concrete-filled steel pipe truss type pier of the present invention will be described below with reference to the drawings. 1 and 2 are a front view and a side view of a concrete-filled steel pipe truss bridge pier (hereinafter, sometimes simply referred to as a bridge pier) of the present invention in the axial direction of the bridge, and FIG.
-A cross section (plan view) is shown. The pier is assembled by joining three-dimensional blocks 10a to 10e that are divided into a plurality of pieces in the height direction (five in this example), and the upper end of the pier is embedded and fixed in the superstructure 4 (bridge girder concrete) and the lower end. Is substructure 5
It is embedded and fixed in (base concrete). The details of each member and the fixed portion are as follows.

【0006】〔使用する部材〕4本の鋼管主柱1を鋼管
やH型鋼等からなる水平梁2及び斜梁3で結合して使用
する。鋼管主柱1内にはコンクリートが充填されてい
る。 〔コンクリート充填鋼管主柱〕鋼管主柱1は図4,図5
に示すように内面に連続したリブ1aを有している。こ
のリブ1aにより充填コンクリート1bと鋼管の一体化
を図る。コンクリート充填鋼管主柱1に作用する圧縮力
応力、引張応力及び曲げ応力はコンクリートと鋼管が合
成断面として負担するものとして、小径で耐力及びじん
性の高い断面を形成する。
[Members to be used] Four steel pipe main columns 1 are connected by a horizontal beam 2 and a diagonal beam 3 made of a steel pipe or H-shaped steel. Concrete is filled in the steel pipe main pillar 1. [Concrete-filled steel pipe main column] Steel pipe main column 1 is shown in Figs.
As shown in (1), the inner surface has continuous ribs 1a. The filling concrete 1b and the steel pipe are integrated by the rib 1a. The compressive stress, the tensile stress and the bending stress acting on the concrete-filled steel pipe main column 1 are borne by the concrete and the steel pipe as a composite cross section, and form a cross section having a small diameter and high yield strength and toughness.

【0007】〔上部工接合部〕上部工接合部4aは、図
6に示すように上部工コンクリート4bに埋め込まれる
部分の鋼管主柱1に2本のずれ止め7を接合している。
このずれ止め7は上部工4のコンクリート4bとの一体
化を目的としたものであり、上部工接合部4aに作用す
る鉛直力及び水平力、モーメントは、上部工4のコンク
リート4bの押し抜き・引き抜き剪断及び水平押し抜き
剪断の許容応力を満足する。図8はずれ止め7の詳細断
面で鋼管又は丸鋼を螺旋状に巻き付けて溶接する。
[Superstructure Joining Part] As shown in FIG. 6, the superstructure connecting part 4a is formed by joining two shift stoppers 7 to the steel pipe main column 1 in a portion to be embedded in the superstructure concrete 4b.
This slip stopper 7 is intended to be integrated with the concrete 4b of the superstructure 4, and the vertical and horizontal forces and moments acting on the superstructure joint 4a can be obtained by pushing out the concrete 4b of the superstructure 4 Satisfies the allowable stress of pull-out shear and horizontal push-out shear. FIG. 8 is a detailed sectional view of the shift stopper 7 in which a steel pipe or round steel is spirally wound and welded.

【0008】〔下部工接合部〕下部工接合部は、図7に
示すように、上部工接合部4aと同様に鋼管主柱1に2
本のずれ止め7を溶接接合している。下部工接合部5a
に作用する鉛直力及び水平力、モーメントは、下部工5
のコンクリート5aの押し抜き・引き抜き剪断及び水平
押し抜き剪断の許容応力を満足する。
[Substructure Joining Part] As shown in FIG. 7, the substructure connecting part is formed on the steel pipe main pillar 1 in the same manner as the superstructure connecting part 4a.
The book stopper 7 is welded and joined. Substructure joint 5a
Vertical force, horizontal force, and moment acting on the
The concrete 5a satisfies the allowable stresses of the punching / pulling shear and the horizontal punching shear.

【0009】〔格点部〕図9,図10に示すように、コ
ンクリート充填鋼管主柱1と鋼管水平梁2、鋼管斜梁3
が接合される格点部6には、力が集中する部分であるた
め、その格点部6の局部変形を防ぐために、コンクリー
ト充填鋼管主柱1の内面に単数または複数の補剛リング
プレート8を溶接する。この補剛リングプレート8は、
コンクリート充填鋼管主柱1内のコンクリート1bと鋼
管の剪断によるずれを防ぐ役割を持つ。
[Grading] As shown in FIGS. 9 and 10, concrete-filled steel pipe main columns 1, steel pipe horizontal beams 2, and steel pipe oblique beams 3
Since the force is concentrated on the graded portion 6 to which is joined, in order to prevent local deformation of the graded portion 6, one or more stiffening ring plates 8 are provided on the inner surface of the concrete-filled steel pipe main column 1. To weld. This stiffening ring plate 8
It has the role of preventing the concrete 1b in the concrete-filled steel pipe main column 1 from shifting due to shearing of the steel pipe.

【0010】次に本発明のコンクリート充填鋼管トラス
橋脚の施工方法について説明する。図11ないし図17
は施工工程を示したものである。又、図18,図19は
本発明の施工に用いる昇降架台の平面図および側面図で
ある。先ず橋脚設置点の基礎コンクリート部5に鉛直支
柱12を4本建て込み固定し、設置された鉛直支柱12
の上方から架台13を挿入して、昇降架台11を設置し
ておく。この昇降架台11は、図18,図19に示すよ
うに、4本の鉛直支柱12とこの鉛直支柱に沿って上下
に上昇、下降可能な架台13で構成されており、この架
台13はX形に配置された2本のビーム13a,13b
とこのビームの両端に固定された移動支持機構14を備
えている。各ビーム13a,13bの上側には後述する
橋脚のパネルブロック9の水平梁2を支持クランプする
半円形のブロック受台15が設けられている。また、ビ
ーム両端の移動支持機構14は、鉛直支柱12を遊嵌ま
たは把持可能な移動クランプ14a,14bが架台13
の下側に1台とビームの上方に1台配置されている。架
台13はこの他連結ビーム13cで連結されている。こ
のうち、上方の移動クランプ14aには上下方向に伸縮
する複数のジャッキ16の一端が固定され、ジャッキ1
6の他端は架台13に固定されている。
Next, a method for constructing a concrete-filled steel pipe truss bridge pier of the present invention will be described. 11 to 17
Shows the construction process. 18 and 19 are a plan view and a side view of an elevating stand used in the construction of the present invention. First, four vertical columns 12 were built in and fixed to the foundation concrete part 5 at the pier installation point, and the vertical columns 12 were installed.
The pedestal 13 is inserted from above and the elevating pedestal 11 is installed. As shown in FIG. 18 and FIG. 19, the elevating platform 11 is composed of four vertical columns 12 and a platform 13 that can be vertically moved up and down along the vertical columns, and the platform 13 is X-shaped. The two beams 13a, 13b arranged at
And a moving support mechanism 14 fixed to both ends of this beam. A semi-circular block pedestal 15 for supporting and clamping the horizontal beam 2 of the panel block 9 of the bridge pier, which will be described later, is provided on the upper side of each beam 13a, 13b. In addition, the movable support mechanisms 14 at both ends of the beam include movable clamps 14 a and 14 b capable of loosely fitting or gripping the vertical support columns 12 and a pedestal 13.
One on the lower side and one on the beam. The pedestal 13 is also connected by a connecting beam 13c. Of these, one end of a plurality of jacks 16 that extend and contract in the vertical direction is fixed to the upper movable clamp 14a, and the jack 1
The other end of 6 is fixed to the mount 13.

【0011】このように構成した移動支持機構14によ
り、上下の移動クランプ14a,14bの遊嵌、把持操
作とジャッキ16のストローク伸縮操作の組合わせによ
り鉛直支柱12に沿って架台13を上下に昇降又は一定
位置に停止させることができる。なお、昇降架台13は
この本例以外の公知手段(例えばウインチやラックピニ
オン方式等)を用いた昇降機構としたものにしてもよ
い。
By the movement support mechanism 14 thus constructed, the pedestal 13 is vertically moved up and down along the vertical support column 12 by a combination of loose fitting of the upper and lower moving clamps 14a and 14b, a grasping operation and a stroke expanding and contracting operation of the jack 16. Alternatively, it can be stopped at a fixed position. The elevating platform 13 may be an elevating mechanism using a known means other than this example (for example, a winch or a rack and pinion system).

【0012】以下、この昇降架台11を用いて鋼管トラ
スを製作、組立る手順を説明する。 (1)工場または現場近くの地上において、各ブロック
の鋼管主柱1間に水平梁2および斜梁3を溶接接合し
て、平面状のパネルブロック9を製作する(図11参
照)。 (2)2枚のパネルブロック9を橋脚設置点の所定位置
に面を対向して、縦方向に建込み、下部の水平梁2を前
記昇降架台11のブロック受台15にクランプする(図
12参照)。 (3)パネルブロック9の対向面間に水平梁2,斜梁3
を溶接接合して立体ブロック10とする。なお、水平梁
2,斜梁3の端部は工場であらかじめ調整切断されてい
る(図13参照)。 (4)前記昇降架台11を上昇した立体ブロック10を
所定高さ迄持上げ保持し、下方に所定の組立空間を形成
する(図14参照)。 (5)組立空間に前記(1)と同様にして製作した下段
の2枚のパネルブロック9を建込み、その鋼管主柱1の
上端を昇降架台11で保持している立体ブロック10の
鋼管主柱1の下端に接合する(図15参照)。 (6)立体ブロック10を2面のパネルブロック9で支
持した状態で昇降架台11を地上部まで降下し、下部の
水平梁2を昇降架台11のブロック受台15にクランプ
する(図16参照)。 (7)以下(3)〜(6)を繰返し行なって、所定高さ
の鋼管トラスを完成させた後、鋼管主柱1内にコンクリ
ート1bを圧入する。この圧入コンクリートは、超流動
コンクリートのような流動性の良好なコンクリート1b
を使用すると鋼管内部にコンクリートを下から押し上げ
て充填することができる。以上の工程により、コンクリ
ート充填鋼管トラス橋脚を完成する(図17参照)。
The procedure for manufacturing and assembling a steel pipe truss using the lifting platform 11 will be described below. (1) On the ground near the factory or the site, the horizontal beam 2 and the oblique beam 3 are welded and joined between the steel pipe main columns 1 of each block to manufacture a flat panel block 9 (see FIG. 11). (2) Two panel blocks 9 are built vertically in a predetermined position of the pier installation point so as to face each other, and the lower horizontal beam 2 is clamped to the block pedestal 15 of the elevator pedestal 11 (FIG. 12). reference). (3) Horizontal beam 2 and diagonal beam 3 between the facing surfaces of the panel block 9.
Are welded together to form a solid block 10. The ends of the horizontal beams 2 and the oblique beams 3 are adjusted and cut in advance at the factory (see FIG. 13). (4) The three-dimensional block 10 that has risen from the lift base 11 is lifted and held to a predetermined height, and a predetermined assembly space is formed below (see FIG. 14). (5) The steel pipe main of the three-dimensional block 10 in which the lower two panel blocks 9 manufactured in the same manner as in the above (1) are built in the assembly space, and the upper end of the steel pipe main column 1 is held by the lifting platform 11. It is joined to the lower end of the pillar 1 (see FIG. 15). (6) With the three-dimensional block 10 supported by the two panel blocks 9, the elevating platform 11 is lowered to the ground portion, and the lower horizontal beam 2 is clamped to the block pedestal 15 of the elevating platform 11 (see FIG. 16). . (7) The following steps (3) to (6) are repeated to complete a steel pipe truss having a predetermined height, and then concrete 1b is press-fitted into the steel pipe main column 1. This press-fitted concrete is concrete 1b with good fluidity such as superfluid concrete.
By using, you can push up concrete from below to fill the inside of the steel pipe. Through the above steps, the concrete-filled steel pipe truss bridge pier is completed (see FIG. 17).

【0013】次に本発明の実施例に示した昇降架台につ
いて詳細説明する。昇降架台11は図18、図19に示
すように4本の鉛直支柱12の上下に上側クランプ14
aと下側クランプ14bの2対のクランプを付随した4
体の油圧ジャッキ16を有している。架台13を上昇さ
せるには、昇降架台11の下側クランプ14bを鉛直支
柱12に固定し、解放した上側クランプ14aを油圧ジ
ャッキ16によってジャッキ16のストローク分の高さ
まで上昇させる。次に上側クランプ14aを鉛直支柱1
2に固定し、解放した下側クランプ14bを油圧ジャッ
キ16によってジャッキのストローク分収縮させる。
Next, a detailed description will be given of the lifting / lowering stand according to the embodiment of the present invention. As shown in FIGS. 18 and 19, the elevating base 11 includes upper and lower clamps 14 above and below four vertical columns 12.
4 with 2 pairs of clamps, a and lower clamp 14b
It has a body hydraulic jack 16. To raise the pedestal 13, the lower clamp 14b of the lifting pedestal 11 is fixed to the vertical column 12, and the released upper clamp 14a is raised to the height of the stroke of the jack 16 by the hydraulic jack 16. Next, attach the upper clamp 14a to the vertical support 1.
The lower clamp 14b fixed to 2 and released is contracted by the hydraulic jack 16 by the stroke of the jack.

【0014】この繰り返しによって昇降架台11は必要
な高さまで上昇することができる。昇降架台11を降下
させる場合は、前述の逆の手順を行う。また、昇降架台
と各ブロック10a〜10eは、各ブロックの最下段の
水平梁2をブロック受台15によって固定し、ゆれやず
れが生じないようにする。各ブロックの最下段の水平梁
2は局部変形を考慮して内部に補強リングプレートを加
工時に取り付けておくのが望ましい。昇降架台11のブ
ロック受台15は各ブロックの最下段水平梁2の幅が異
なるため移動可能なようにボルト着脱式としている。
By repeating this, the lifting platform 11 can be raised to a required height. When lowering the elevating / lowering platform 11, the reverse procedure described above is performed. Further, the elevating platform and each of the blocks 10a to 10e fix the lowermost horizontal beam 2 of each block by the block pedestal 15 so as not to cause shake or shift. The lowermost horizontal beam 2 of each block is preferably provided with a reinforcing ring plate inside during processing in consideration of local deformation. The block pedestal 15 of the lifting / lowering platform 11 is of a detachable bolt type so that it can be moved because the width of the lowermost horizontal beam 2 of each block is different.

【0015】本発明のコンクリート充填鋼管トラスの橋
脚の施工は、パネルブロックの平面組立は地上で、パネ
ルブロックの立体組立は地上に近い低所作業となるた
め、図18,図19に示すように、プレハブ建家やシー
トを用いた防風・防雪設備17を設置してこの中で行う
ことができる。このようにすれば、雨天や強風,降雪等
の荒天時においても稼動率,品質,安全性を損なうこと
なく作業を行うことができる。
In the construction of the bridge pier of the concrete-filled steel pipe truss of the present invention, the plane assembly of the panel block is performed on the ground, and the three-dimensional assembly of the panel block is performed at a low place close to the ground. Therefore, as shown in FIGS. A prefabricated building or a windproof / snowproof facility 17 using a sheet can be installed in the building. By doing so, work can be performed without impairing the operation rate, quality, and safety even in the case of rough weather such as rainy weather, strong wind, or snowfall.

【0016】[0016]

【発明の効果】本発明のコンクリート充填鋼管トラス橋
脚の構造及び施工方法は、次のような効果を得ることが
できる。 (1)鋼管の内部にコンクリートを充填することによっ
て、コンクリートと鋼管の合成断面として圧縮応力,引
張応力,曲げ応力を負担する構造となり鉄筋を省略する
ことができる。また、鋼管が型枠としても活用されるこ
とから、鉄筋及び型枠の組立の手数を省略することがで
きる。 (2)地上でトラスの立体ブロックを製作・組立し、昇
降用架台で持ち上げた下方の組立空間で下段の立体ブロ
ック10を製作・組立し、先行組立の立体ブロック10
と接合して順次高さ方向に延長して鋼管トラスを完成し
た後、鋼管主柱1内にコンクリートを充填するものであ
るため、地上部での低所作業で施工でき、そのため従来
のような高所において型枠を組立てて解体して行く作業
を必要とせず、能率よく工程を短縮することができ、高
所における危険作業を軽減できる。 (3)橋脚の立ち上げには昇降架台を採用し、比較的低
所での作業となるため全天候型の設備を設置することが
でき、通年施工が可能となる。 (4)コンクリートの充填は、橋脚の立ち上げ完了後に
一括して行うため、従来のように各工程間での養生期間
を特別に必要としない。 (5)本発明のコンクリート充填鋼管トラス橋脚の構造
は、従来のコンクリート橋脚の構造に比較して自重を低
減することができ、このため、従来のようなコンクリー
ト橋脚に較べて基礎の規模を縮小することができるの
で、より経済的である。
The structure and construction method of a concrete-filled steel pipe truss pier of the present invention can obtain the following effects. (1) By filling the inside of the steel pipe with concrete, the composite cross section of the concrete and the steel pipe bears compressive stress, tensile stress, and bending stress, and the reinforcing bar can be omitted. Further, since the steel pipe is also used as a mold, the labor of assembling the reinforcing bar and the mold can be omitted. (2) Manufacture and assemble a three-dimensional truss block on the ground, and manufacture and assemble the lower three-dimensional block 10 in the lower assembling space lifted by the elevating pedestal.
After the steel pipe truss is completed by joining it to the steel pipe and sequentially extending it in the height direction, the steel pipe main column 1 is filled with concrete, so it can be constructed by working at a low place above the ground, and therefore it can The work of assembling and disassembling the formwork at a high place is not required, the process can be efficiently shortened, and dangerous work at a high place can be reduced. (3) An elevator platform is used to start the piers, and since the work is performed in a relatively low place, all-weather equipment can be installed and construction can be performed all year round. (4) Since the concrete is filled all at once after the completion of the start-up of the bridge pier, there is no need for a special curing period between each step as in the conventional case. (5) The structure of the concrete-filled steel pipe truss pier of the present invention can reduce its own weight as compared with the structure of the conventional concrete pier, and therefore the scale of the foundation is reduced as compared to the conventional concrete pier. It is more economical because you can.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のコンクリート充填鋼管トラス橋脚構造
の一例を示す正面図である。
FIG. 1 is a front view showing an example of a concrete-filled steel pipe truss pier structure of the present invention.

【図2】本発明のコンクリート充填鋼管トラス橋脚構造
の一例を示す側面図である。
FIG. 2 is a side view showing an example of a concrete-filled steel pipe truss pier structure of the present invention.

【図3】鋼管主柱の一部切欠断面図である。FIG. 3 is a partially cutaway sectional view of a steel pipe main column.

【図4】内面に多数のリブを備えている鋼管主柱を示す
一部縦断側面図である。
FIG. 4 is a partially longitudinal side view showing a steel pipe main column having a large number of ribs on its inner surface.

【図5】鋼管主柱内にコンクリート充填した状態を示す
一部縦断側面図である。
FIG. 5 is a side view, partly in vertical section, showing a state where concrete is filled in the main column of the steel pipe.

【図6】鋼管主柱の上端部と上部工との結合部を示す一
部縦断側面図である。
FIG. 6 is a partially longitudinal side view showing a joint between an upper end of a steel pipe main column and a superstructure.

【図7】本発明のコンクリート充填鋼管トラス橋脚の下
部と下部工との結合部を示す一部縦断側面図である。
FIG. 7 is a partially longitudinal side view showing a connecting portion between the lower portion and the substructure of the concrete-filled steel pipe truss pier of the present invention.

【図8】ずれ止めを有する鋼管主柱と水平梁との関係を
示す一部縦断側面図である。
FIG. 8 is a partially longitudinal side view showing a relationship between a steel pipe main column having a slip stopper and a horizontal beam.

【図9】本発明の格点部を示す一部縦断斜視図である。FIG. 9 is a partial vertical perspective view showing a rating portion of the present invention.

【図10】本発明の格点部を示す横断平面図である。FIG. 10 is a cross-sectional plan view showing a graded portion of the present invention.

【図11】本発明を実施してフレームユニットを組立て
ている状態を示す斜視図である。
FIG. 11 is a perspective view showing a state where the present invention is carried out to assemble a frame unit.

【図12】クレーンを使用して第1のフレームユニット
を組立てている状態を示す一部縦断側面図である。
FIG. 12 is a partially longitudinal side view showing a state where the first frame unit is assembled using the crane.

【図13】クレーンを使用して水平梁を取付けるときの
状態を示す一部縦断側面図である。
FIG. 13 is a partially longitudinal side view showing a state where a horizontal beam is attached using a crane.

【図14】第2列目の立体ブロックを組立てている状態
を示す一部縦断側面図である。
FIG. 14 is a partial vertical cross-sectional side view showing a state where the solid block in the second row is assembled.

【図15】第2列目の立体ブロックの組立てを終了した
状態を示す一部縦断側面図である。
FIG. 15 is a partially longitudinal side view showing a state in which the assembling of the solid block in the second row has been completed.

【図16】第2の立体ブロックに斜梁を取付けるときの
状態を示す一部縦断側面図である。
FIG. 16 is a partially longitudinal side view showing a state in which the oblique beam is attached to the second solid block.

【図17】全数の立体ブロックの組立てを終了し、かつ
鋼管主柱にコンクリートを充填した状態を示す一部縦断
側面図である。
FIG. 17 is a partially longitudinal side view showing a state where the assembly of all the three-dimensional blocks is completed and the steel pipe main columns are filled with concrete.

【図18】下部フレームの横断平面図である。FIG. 18 is a cross-sectional plan view of the lower frame.

【図19】下部フレームを示す側面図である。FIG. 19 is a side view showing a lower frame.

【図20】立体フレームの構築を行なっている状態を示
す一部縦断側面図である。
FIG. 20 is a partially longitudinal side view showing a state in which a three-dimensional frame is being constructed.

【符号の説明】[Explanation of symbols]

1 鋼管主柱 1a リブ 1b 充填コンクリート 2 水平梁 3 斜梁 4 上部工(橋桁) 4a 上部工接合部 4b コンクリート 5 下部工(基礎) 5a 下部工接合部 6 格点部 7 ずれ止め 8 補剛リングプレート 9 パネルブロック 10 立体ブロック 11 昇降架台 12 鉛直支柱 13 架台 13a ビーム 13b ビーム 14 移動支持機構 15 ブロック受台 16 油圧ジャッキ 17 防風・防雪設備 1 Steel pipe main column 1a Rib 1b Filled concrete 2 Horizontal beam 3 Oblique beam 4 Superstructure (bridge girder) 4a Superstructure joint 4b Concrete 5 Substructure (foundation) 5a Substructure joint 6 Grade 7 Slip 8 Stiffening ring Plate 9 Panel block 10 Space block 11 Lifting platform 12 Vertical column 13 Platform 13a Beam 13b Beam 14 Moving support mechanism 15 Block cradle 16 Hydraulic jack 17 Wind / snowproof equipment

───────────────────────────────────────────────────── フロントページの続き (72)発明者 友野 一徳 神奈川県相模原市西橋本5−9−1 新日 本製鐵株式会社鉄構海洋事業部内 (72)発明者 水上 繁樹 神奈川県相模原市西橋本5−9−1 新日 本製鐵株式会社鉄構海洋事業部内 (72)発明者 今井 義明 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 (72)発明者 堀口 政一 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 (72)発明者 望月 明彦 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 (72)発明者 日向 文英 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Kazunori Tomono 5-9-1 Nishihashimoto, Sagamihara City, Kanagawa Pref., Nippon Steel Corporation Marine & Steel Division (72) Inventor Shigeki Mizukami Nishihashimoto, Sagamihara City, Kanagawa Prefecture 5-9-1 Nippon Steel Corporation, Steel Construction & Marine Division (72) Inventor Yoshiaki Imai 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo Taisei Corporation (72) Inventor Masaichi Horiguchi Tokyo 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo Within Taisei Construction Co., Ltd. (72) Inventor Akihiko Mochizuki Within 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo Taisei Construction Co., Ltd. (72) Inventor Fumihide Hinata, Shinjuku Tokyo 1-25-1 Nishi-Shinjuku, Ward Taisei Construction Co., Ltd.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 内側に連続したリブ1aを有する複数本
の鋼管主柱1が間隔をおいて立設され、各鋼管主柱1間
が複数の水平梁2と斜梁3により接合され、鋼管主柱1
と水平梁2および斜梁3の接合部における鋼管主柱1の
内側に補剛リングプレート8が溶接されており、鋼管主
柱1内部にはコンクリート1bが充填されていることを
特徴とするコンクリート充填鋼管トラス橋脚。
1. A plurality of steel pipe main columns 1 having continuous ribs 1a on the inner side are erected at intervals, and the respective steel pipe main columns 1 are joined by a plurality of horizontal beams 2 and oblique beams 3 to form a steel pipe. Main pillar 1
Concrete in which a stiffening ring plate 8 is welded to the inside of the steel pipe main column 1 at the joint between the horizontal beam 2 and the oblique beam 3 and the steel pipe main column 1 is filled with concrete 1b. Filled steel pipe truss pier.
【請求項2】 橋脚設置地点に、複数の鉛直支柱12に
沿って上下移動可能な昇降架台11を設置し、工場また
は現場近くの地上において、鋼管主柱1の間に水平梁2
および斜梁3を接合して平面状のパネルブロック9を製
作し、前記パネルブロック9を橋脚設置点の所定位置に
面を対向して縦方向に建込んで、前記昇降架台11に下
部をクランプし、パネルブロック9の対向面間に水平梁
2,斜梁3を接合して立体ブロック10とし、次に前記
昇降架台11を上昇して立体ブロック10を所定高さま
で上昇して保持し、下方に所定の組立空間を形成し、前
記組立空間に前記パネルブロック9を建込み、その鋼管
主柱1上端を、昇降架台11で保持されている立体ブロ
ック10を鋼管主柱1下端に接合し、昇降架台11を地
上部まで降下させ、以下前述の動作を繰返し所定高さの
鋼管トラスを完成させた後、鋼管主柱1内にコンクリー
トを充填することを特徴とするコンクリート充填鋼管ト
ラス橋脚の施工方法。
2. A horizontal beam 2 is provided between steel pipe main columns 1 on the ground near a factory or a site by installing a vertically movable pedestal 11 along a plurality of vertical columns 12 at a pier installation point.
And the slant beam 3 are joined together to produce a flat panel block 9, and the panel block 9 is vertically installed at a predetermined position of the pier installation point with the surfaces facing each other, and the lower part is clamped to the lifting platform 11. Then, the horizontal beams 2 and the oblique beams 3 are joined between the facing surfaces of the panel block 9 to form a solid block 10, and then the elevating / lowering platform 11 is raised to raise and hold the solid block 10 to a predetermined height. A predetermined assembling space is formed, the panel block 9 is built in the assembling space, and the upper end of the steel pipe main pillar 1 is joined to the lower end of the steel pipe main pillar 1 by the solid block 10 held by the elevating platform 11. Construction of a concrete-filled steel pipe truss pier characterized by filling the inside of the steel pipe main column 1 with concrete after lowering the elevating platform 11 to the ground part and repeating the above-mentioned operation to complete the steel pipe truss of a predetermined height Person .
【請求項3】 昇降架台11の周囲を全天候作業可能な
簡易の防風・防雪設備17で覆って作業することを特徴
とする請求項2のコンクリート充填鋼管トラス橋脚の施
方法。
3. The method for applying a concrete-filled steel pipe truss pier according to claim 2, wherein the lifting platform 11 is covered with a simple windproof and snowproof facility 17 capable of all-weather work.
JP11737194A 1994-05-09 1994-05-09 Concrete-filled steel pipe truss pier and construction method Withdrawn JPH07300817A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11737194A JPH07300817A (en) 1994-05-09 1994-05-09 Concrete-filled steel pipe truss pier and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11737194A JPH07300817A (en) 1994-05-09 1994-05-09 Concrete-filled steel pipe truss pier and construction method

Publications (1)

Publication Number Publication Date
JPH07300817A true JPH07300817A (en) 1995-11-14

Family

ID=14710009

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11737194A Withdrawn JPH07300817A (en) 1994-05-09 1994-05-09 Concrete-filled steel pipe truss pier and construction method

Country Status (1)

Country Link
JP (1) JPH07300817A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100453737C (en) * 2007-06-15 2009-01-21 四川省交通厅公路规划勘察设计研究院 Steel-pipe concrete assembled pier
CN102152038A (en) * 2011-04-18 2011-08-17 武船重型工程有限公司 Installation method of K brace of steel pipe truss arch
CN103643626A (en) * 2013-12-17 2014-03-19 中南大学 Method for controlling temperature stress cracks of curved ultrahigh bridge pier body
CN107254835A (en) * 2017-08-03 2017-10-17 四川交通职业技术学院 The connecting structure and its construction method of a kind of overall pier beam build-in
CN110886200A (en) * 2019-11-01 2020-03-17 天津大学 Corner-reinforced double-steel-plate combined hollow pier and construction method thereof
CN113699884A (en) * 2021-08-27 2021-11-26 四川省公路规划勘察设计研究院有限公司 Rectangular concrete-filled steel tube cable tower adopting prefabricated web plates
JP2021195827A (en) * 2020-06-17 2021-12-27 鹿島建設株式会社 Bridge pier and bridge
CN114348197A (en) * 2022-01-13 2022-04-15 东北石油大学 Fabricated FRP concrete guyed tower type small displacement platform group and construction method thereof
CN114635506A (en) * 2022-03-30 2022-06-17 浙江东南网架股份有限公司 Prismatic steel pipe truss arch springing and mounting method thereof

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100453737C (en) * 2007-06-15 2009-01-21 四川省交通厅公路规划勘察设计研究院 Steel-pipe concrete assembled pier
CN102152038A (en) * 2011-04-18 2011-08-17 武船重型工程有限公司 Installation method of K brace of steel pipe truss arch
CN103643626A (en) * 2013-12-17 2014-03-19 中南大学 Method for controlling temperature stress cracks of curved ultrahigh bridge pier body
CN103643626B (en) * 2013-12-17 2015-09-02 中南大学 A kind of control method of superrelation on curve type bridge pier pier shaft thermal stress cracks
CN107254835A (en) * 2017-08-03 2017-10-17 四川交通职业技术学院 The connecting structure and its construction method of a kind of overall pier beam build-in
CN107254835B (en) * 2017-08-03 2023-06-02 四川交通职业技术学院 Integral pier beam embedded connection structure and construction method thereof
CN110886200A (en) * 2019-11-01 2020-03-17 天津大学 Corner-reinforced double-steel-plate combined hollow pier and construction method thereof
JP2021195827A (en) * 2020-06-17 2021-12-27 鹿島建設株式会社 Bridge pier and bridge
CN113699884A (en) * 2021-08-27 2021-11-26 四川省公路规划勘察设计研究院有限公司 Rectangular concrete-filled steel tube cable tower adopting prefabricated web plates
CN114348197A (en) * 2022-01-13 2022-04-15 东北石油大学 Fabricated FRP concrete guyed tower type small displacement platform group and construction method thereof
CN114348197B (en) * 2022-01-13 2024-04-19 东北石油大学 Assembled FRP concrete guy cable tower type small displacement platform group and construction method thereof
CN114635506A (en) * 2022-03-30 2022-06-17 浙江东南网架股份有限公司 Prismatic steel pipe truss arch springing and mounting method thereof

Similar Documents

Publication Publication Date Title
KR100522170B1 (en) Method of constructing simple and continuous composite bridges
KR100837608B1 (en) J.K Bracket Method
CN112081016A (en) Lifting and folding device for bridge arch rib
KR102477955B1 (en) Bridge pier and the construction method using maintained concrete mold
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
KR20070010449A (en) Construction method for arched bridge
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
KR100605514B1 (en) Bracket support type downward construction system and construction method using the same
JP4103574B2 (en) Construction method of beam-like structure
JPH0959924A (en) Slab form construction method
JPH03125755A (en) Constructing method for cylindrical multistoried structure
KR100402146B1 (en) The method of a continuous preflex composite girder with shifting up and down
KR20000054500A (en) Construction method that introduces compressive stress to bottom plate concrete and bottom moment flange of parent section by using and adjusting the descending and rising process of end point in short span and multi span composite structures
CN115075143B (en) Bridge tower column construction method
JPH11323838A (en) Construction method of bridge
CN115162697B (en) Special-shaped column construction work I-shaped steel cantilever platform and construction method
JPH1113017A (en) Construction method of hollow cylindrical skeleton
CN217438744U (en) Pier reinforcing device for pushing construction of three-main-truss steel truss girder bridge
KR102707466B1 (en) Method for Manufacturing Deck-Integrated Composite Girder, Deck-Integrated Composite Girder Produced Thereby, and Method of Constructing Bridge Upper Structure
CN220246640U (en) Semi-assembled oblique leg rigid frame bridge structure
JPH05148817A (en) Construction of pc bridge
CN116427278A (en) Large multi-span self-propelled automatic die carrier
CN117661457A (en) Large-inclination-angle bridge tower active cross brace and bracket mounting and dismounting method
CN116397536A (en) Hoop type combined beam

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20010731