CN106320192A - Beam section replacement reinforcement method for large-span concrete continuous beam bridge - Google Patents

Beam section replacement reinforcement method for large-span concrete continuous beam bridge Download PDF

Info

Publication number
CN106320192A
CN106320192A CN201610957575.1A CN201610957575A CN106320192A CN 106320192 A CN106320192 A CN 106320192A CN 201610957575 A CN201610957575 A CN 201610957575A CN 106320192 A CN106320192 A CN 106320192A
Authority
CN
China
Prior art keywords
concrete
steel
cutting
beam section
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610957575.1A
Other languages
Chinese (zh)
Other versions
CN106320192B (en
Inventor
何雄君
朱慈祥
张晶
杨阳
范诚
刘鑫
陈云汉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201610957575.1A priority Critical patent/CN106320192B/en
Publication of CN106320192A publication Critical patent/CN106320192A/en
Application granted granted Critical
Publication of CN106320192B publication Critical patent/CN106320192B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种用于大跨径混凝土连续梁桥的梁段置换加固方法,包括如下步骤:将置换混凝土梁段从混凝土连续梁的待加固跨上切割并吊运;待加固跨切割后形成两个固定段,在两个固定段的切割端面上均设置钢砼接头;将钢梁吊至两个钢砼接头之间并与钢砼接头连接。通过钢梁替代已经出现病害的置换混凝土梁段,从而可彻底地解决跨中下挠、开裂等病害,改善桥面线形,同时也提高了混凝土连续梁桥的整体承载力;具有安全可靠、操作性好、实用性强的优点,可用于大跨径混凝土连续梁(刚构)桥的维修加固。

The invention discloses a beam section replacement and reinforcement method for a long-span concrete continuous beam bridge, which comprises the following steps: cutting and lifting the replaced concrete beam section from the concrete continuous beam's span to be reinforced; Two fixed sections are formed, steel-concrete joints are arranged on the cutting end faces of the two fixed sections; steel beams are hoisted between the two steel-concrete joints and connected with the steel-concrete joints. By replacing the damaged concrete beam sections with steel beams, it can completely solve the mid-span deflection, cracking and other diseases, improve the alignment of the bridge deck, and also improve the overall bearing capacity of the concrete continuous beam bridge; it is safe, reliable, and easy to operate. With the advantages of good performance and strong practicability, it can be used for maintenance and reinforcement of long-span concrete continuous beam (rigid frame) bridges.

Description

一种用于大跨径混凝土连续梁桥的梁段置换加固方法A Beam Segment Replacement Reinforcement Method for Long-span Concrete Continuous Beam Bridge

技术领域technical field

本发明涉及混凝土桥梁的加固技术,具体涉及一种用于大跨径混凝土连续梁桥的梁段置换加固方法。The invention relates to the reinforcement technology of concrete bridges, in particular to a beam section replacement reinforcement method for long-span concrete continuous beam bridges.

背景技术Background technique

国内于上世纪70年代开始大跨径混凝土连续梁(刚构)桥的建设工作,因其良好适应性和经济性迅速成为跨径60m~300m范围内最具竞争力的桥型,被广泛运用于公路大型桥梁及市政高架桥梁。由于当时桥梁结构设计和材料理论不完善、日益递增的交通运输量、养护管理的局限性和近年来恶劣的自然条件,引发了部分桥梁的各种问题和结构性病害,主要表现为开裂(“腹板开裂”、“底板开裂”、“顶板开裂”)和“跨中下挠”等问题,轻者影响结构耐久性和美观,严重者将限制桥梁的正常使用或导致结构丧失承载能力。对旧桥、危桥的加固维修,已引起了世界性的关注。The construction of long-span concrete continuous beam (rigid frame) bridges began in the 1970s in China. Because of its good adaptability and economy, it quickly became the most competitive bridge type within the range of 60m to 300m, and was widely used. Large highway bridges and municipal viaducts. Due to the imperfection of bridge structure design and material theory at that time, the increasing traffic volume, the limitation of maintenance management and the harsh natural conditions in recent years, various problems and structural diseases of some bridges have been caused, mainly manifested as cracking (" web cracking", "bottom plate cracking", "roof cracking") and "mid-span deflection", the light ones will affect the durability and aesthetics of the structure, and the severe ones will limit the normal use of the bridge or cause the structure to lose its bearing capacity. The reinforcement and maintenance of old and dangerous bridges has attracted worldwide attention.

目前,桥梁加固技术主要分为三种。一是增加恒载加固法,提高承载力的同时增加了结构的恒载,主要包括粘贴钢板法、增大截面法等,多为被动加固法,加固效率较低。二是基本维持恒载加固法,如改变结构体系加固法、体外预应力加固法等,为主动加固方法,理论上加固效果较好,但耐久性、可靠性有待提升。三是减轻恒载加固法,主要包括减轻桥面铺装,更换轻质护栏等,为主动加固法,但由于多为减轻附属结构的重量,加固效果有限。At present, there are mainly three types of bridge reinforcement technologies. The first is to increase the dead load reinforcement method, which increases the bearing capacity and increases the dead load of the structure at the same time. It mainly includes the method of pasting steel plates and the method of increasing the section. Most of them are passive reinforcement methods, and the reinforcement efficiency is low. The second is to basically maintain the constant load reinforcement method, such as changing the structural system reinforcement method, external prestressing reinforcement method, etc., which are active reinforcement methods. Theoretically, the reinforcement effect is better, but the durability and reliability need to be improved. The third is to reduce the dead load reinforcement method, which mainly includes reducing bridge deck pavement and replacing light guardrails. It is an active reinforcement method, but because most of it is to reduce the weight of auxiliary structures, the reinforcement effect is limited.

发明内容Contents of the invention

本发明的目的在于克服上述技术不足,提出一种用于大跨径混凝土连续梁桥的梁段置换加固方法,其既能主动加固减轻恒载,又能从改变结构体系的方法入手,彻底地解决跨中下挠、梁段开裂等病害。The purpose of the present invention is to overcome the above-mentioned technical deficiencies, and propose a beam segment replacement and reinforcement method for long-span concrete continuous beam bridges, which can not only actively reinforce and reduce dead loads, but also start with the method of changing the structural system, thoroughly Solve problems such as mid-span deflection and beam segment cracking.

为达到上述目的,本发明的技术方案提供一种用于大跨径混凝土连续梁桥的梁段置换加固方法,包括如下步骤:In order to achieve the above object, the technical solution of the present invention provides a beam segment replacement and reinforcement method for long-span concrete continuous beam bridges, comprising the following steps:

S1、将置换混凝土梁段从混凝土连续梁的待加固跨上切割并吊运;S1. Cut and lift the replacement concrete beam section from the span of the concrete continuous beam to be reinforced;

所述步骤S1包括:Said step S1 comprises:

S11、拆除置换混凝土梁段的桥面铺装及其附属设施,对混凝土连续梁进行局部加固,并在两个固定段上均对应设置支撑系统及与支撑系统连接的吊装系统,并通过吊装系统将置换混凝土梁段吊装固定;S11. Remove the bridge deck pavement and ancillary facilities for the replacement concrete beam section, partially reinforce the concrete continuous beam, and set up a supporting system and a hoisting system connected to the supporting system on the two fixed sections, and pass the hoisting system Lift and fix the replacement concrete beam section;

S12、在置换混凝土梁段的两端呈八字形对称切割,并采用临时体外预应力或桥下主动受力支架保护边跨梁体,确保中间梁段拆除过程安全;S12. The two ends of the replacement concrete beam section are cut symmetrically in a figure-eight shape, and the side-span beam body is protected by temporary external prestressing or active stress support under the bridge to ensure the safety of the demolition process of the middle beam section;

S13、切割完成后,控制吊装系统将切割后的置换混凝土梁段吊装下放至相对应的放置平台。S13. After the cutting is completed, control the hoisting system to hoist and lower the cut replacement concrete beam section to the corresponding placement platform.

S2、待加固跨切割后形成两个固定段,在两个固定段的切割端面上均设置钢砼接头;S2. Two fixed sections are formed after the reinforced span is cut, and steel-concrete joints are arranged on the cut end faces of the two fixed sections;

S3、将钢梁吊至两个钢砼接头之间并与钢砼接头连接。S3. Lift the steel beam between the two steel-concrete joints and connect with the steel-concrete joints.

按上述方案,所述步骤S11中局部加固包括:在待加固跨的相邻两跨上张拉体外预应力,在固定段的箱梁内浇筑横隔板,且在固定段靠近其切割端面一端的上下面凿孔至预应力筋束,并对预应力筋束进行灌浆浇筑。According to the above scheme, the local reinforcement in step S11 includes: stretching the external prestress on the two adjacent spans of the span to be reinforced, pouring a diaphragm in the box girder of the fixed section, and placing a diaphragm near the cut end surface of the fixed section Drill holes to the prestressed tendons, and grout the prestressed tendons.

按上述方案,所述步骤S12还包括在切割至设定厚度时,在固定段的切割端面上设置防冲击挑梁,防冲击挑梁的前端设置液压装置,液压装置一端抵接置换混凝土梁段的切割端面。According to the above scheme, the step S12 also includes setting an anti-impact cantilever on the cutting end surface of the fixed section when cutting to a set thickness, and setting a hydraulic device at the front end of the anti-impact cantilever, and one end of the hydraulic device abuts the replacement concrete beam section cutting end face.

按上述方案,所述步骤S13还包括在吊装下放过程监控置换混凝土梁段四个角的相对高度,使置换混凝土梁段任意两个角之间的竖直相对高度小于10mm。According to the above scheme, the step S13 also includes monitoring the relative heights of the four corners of the replaced concrete beam section during the hoisting and lowering process, so that the vertical relative height between any two corners of the replaced concrete beam section is less than 10 mm.

按上述方案,所述步骤S2包括:According to the above scheme, the step S2 includes:

S21、凿除固定段靠近其切割端面的1m内的混凝土,并将固定段的凿除混凝土后的梁端整形、凿毛、清洗、切割剪力健,并保留固定段内原有的支撑钢筋和预应力筋;S21. Chisel away the concrete within 1m of the fixed section close to its cut end face, and reshape, chisel, clean, cut and shear the beam end of the fixed section after the concrete has been chiseled out, and retain the original supporting steel bars and prestressed tendon;

S22、将钢砼接头吊至安装位置,并与固定段的混凝土凿除端固定连接;S22. Hoist the steel-concrete joint to the installation position, and fix it with the concrete chiseled end of the fixed section;

S23、在钢砼接头与固定段连接处浇筑混凝土并养护,至混凝土达到设定强度后张拉预应力。S23. Concrete is poured and cured at the connection between the steel-concrete joint and the fixed section, and the prestress is stretched after the concrete reaches the set strength.

钢砼接头由钢砼接头混凝土梁段和钢砼接头钢箱梁段组成,采用填充砼后板式的方式,先竖向放置钢砼接头钢结构,浇筑填充混凝土,再平置钢砼接头,通过船运输至桥位,最后将钢箱梁端部的顶板、底板和腹板做成双璧板,将填充的混凝土与紧邻的混凝土箱梁段的顶板、底板和腹板通过PBL剪力板、预应力钢筋和普通钢筋连接,并向前延伸将其与混凝土横隔板连接,预应力短束钢筋锚固在混凝土横隔板和钢箱横隔板上,预应力长束钢筋锚固在混凝土横隔板后梁段的顶板、底板的齿块上。The steel-concrete joint is composed of the concrete beam section of the steel-concrete joint and the steel box beam section of the steel-concrete joint. The steel structure of the steel-concrete joint is placed vertically first, the filling concrete is poured, and then the steel-concrete joint is placed horizontally. Ship to the bridge site, and finally the top plate, bottom plate and web at the end of the steel box girder are made into double wall plates, and the filled concrete and the top plate, bottom plate and web of the adjacent concrete box girder section are passed through the PBL shear plate, prefabricated Stressed steel bars are connected with ordinary steel bars and extended forward to connect them with concrete diaphragms, prestressed short beams are anchored to concrete diaphragms and steel box diaphragms, and prestressed long beams are anchored to concrete diaphragms On the tooth blocks of the top plate and the bottom plate of the rear beam section.

按上述方案,所述步骤S3包括:According to the above scheme, the step S3 includes:

S31、制作与两个钢砼接头相配合的钢梁,将钢梁运至钢砼接头下方并吊至两个钢砼接头之间;S31, making a steel beam matching the two steel-concrete joints, transporting the steel beam to the bottom of the steel-concrete joint and hoisting it between the two steel-concrete joints;

S32、将钢梁一端通过高强螺栓与其中一个钢砼接头固定后焊接,然后将钢梁另一端通过高强螺栓与另一个钢砼接头固定后焊接。S32. Fixing one end of the steel beam to one of the steel-concrete joints through high-strength bolts and then welding, and then fixing the other end of the steel beam to the other steel-concrete joint through high-strength bolts and then welding.

S33、张拉钢梁预应力。S33. Tension steel beam prestressed.

按上述方案,所述步骤S33中用于钢梁张拉预应力的钢束两端分别锚固于钢梁离其一端10m位置。According to the above scheme, in the step S33, the two ends of the steel bundle used for the tension and prestressing of the steel beam are respectively anchored at a position 10 m away from one end of the steel beam.

与现有技术相比,本发明通过钢梁替代已经出现病害的置换混凝土梁段,从而可彻底地解决跨中下挠、开裂等病害,改善桥面线形,同时也提高了混凝土连续梁桥的整体承载力。具有安全可靠、操作性强、加固成本低廉、实用性强的优点。Compared with the prior art, the present invention substitutes steel girders for the replaced concrete girder sections that have already suffered from diseases, so as to completely solve the problems of mid-span deflection, cracking, etc., improve the alignment of the bridge deck, and also improve the performance of the concrete continuous girder bridge. Overall carrying capacity. The utility model has the advantages of safety and reliability, strong operability, low reinforcement cost and strong practicability.

附图说明Description of drawings

图1是本发明的置换混凝土梁段的拆除示意图。Fig. 1 is a schematic diagram of dismantling a replaced concrete beam section of the present invention.

图2是本发明的钢砼接头的安装示意图。Fig. 2 is a schematic diagram of the installation of the steel-concrete joint of the present invention.

图3是本发明的钢梁安装示意图。Fig. 3 is a schematic diagram of steel beam installation of the present invention.

图4是本发明的钢砼接头结构示意图。Fig. 4 is a structural schematic diagram of the steel-concrete joint of the present invention.

具体实施方式detailed description

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

如图1、图2、图3所示,本发明的实施例以一中跨为98m、相邻两个边跨3为65m的混凝土连续梁桥为例,对应的设置中间两个为主墩2、靠近边缘两个为边墩1,两个主墩2之间为中跨,边墩1与主墩2之间为边跨3。其中,中跨中部受损,本实施例选取中跨中受损的中间梁段为置换混凝土梁段4,并将其置换为钢梁9。该中间梁段需有足够的自承载能力,并且两端处于弯矩较小的区域,该梁段混凝土可以采用整节段下放拆除,也可以分段拆除,图中所示为整节段下放拆除。As shown in Figure 1, Figure 2, and Figure 3, the embodiment of the present invention takes a concrete continuous beam bridge with a middle span of 98m and two adjacent side spans 3 of 65m as an example, and the corresponding middle two are set as main piers 2. The two near the edge are side piers 1, the middle span is between two main piers 2, and the side span 3 is between side piers 1 and main piers 2. Wherein, the middle part of the mid-span is damaged. In this embodiment, the damaged middle beam section of the mid-span is selected as the replacement concrete beam section 4 and replaced with a steel beam 9 . The middle beam section needs to have sufficient self-supporting capacity, and the two ends are in the area with small bending moment. The concrete of this beam section can be demolished by lowering the entire section, or it can be removed in sections. The figure shows that the whole section is lowered tear down.

参阅图1,其为本实施例的置换混凝土梁段4的拆除示意图,其具体置换步骤如下:Referring to Fig. 1, it is the dismantling schematic diagram of the replacement concrete beam section 4 of the present embodiment, and its specific replacement steps are as follows:

S1、将置换混凝土梁段4从混凝土连续梁的待加固跨上切割并吊运;S1, cutting and lifting the replacement concrete beam section 4 from the span to be reinforced of the concrete continuous beam;

需要说明的是,本实施例所述待加固跨即为上述中跨,所述置换混凝土梁段4即为受损的混凝土中间梁段。It should be noted that the span to be reinforced in this embodiment is the above-mentioned middle span, and the replacement concrete beam section 4 is the damaged concrete middle beam section.

具体切割、吊运步骤如下:The specific cutting and lifting steps are as follows:

S11、拆除置换混凝土梁段4的桥面铺装及其附属设施,对混凝土连续梁进行局部加固,并在两个固定段上均对应设置支撑系统5及与支撑系统5连接的吊装系统6,并通过吊装系统6将置换混凝土梁段4吊装固定;S11. Remove and replace the bridge deck pavement of the concrete beam section 4 and its auxiliary facilities, partially reinforce the concrete continuous beam, and set the support system 5 and the hoisting system 6 connected to the support system 5 on the two fixed sections correspondingly, And the replacement concrete beam section 4 is hoisted and fixed by the hoisting system 6;

在切割前首先需要将置换混凝土梁段4的桥面铺装及其附属设置拆散,例如栏杆等。拆除后,在待加固跨的相邻两跨上张拉体外预应力,即在两边跨3上张拉预应力,具体可通过在两边跨3上设置预应力钢束10。同时,由于固定段上需要设置支撑系统5及吊装系统6以便于置换混凝土梁段4和钢梁9的吊装,由于置换混凝土梁段4和钢梁9的重力较大,易在吊装过程中给予固定段较大的压力,故本实施例在固定段用于承载支撑系统5的位置的箱梁内浇筑横隔板11以增加固定段内箱梁的承载能力;而且,在固定段靠近其切割端面一端的上下面凿孔至预应力筋束,并对预应力筋束进行灌浆浇筑,具体在固定段靠近其切割端面5m左右的范围内预应力孔道进行分段凿孔,而对凿孔内的预应力筋波纹管进行二次灌浆浇筑,增强预应力孔道灌浆饱满度。Before cutting, it is first necessary to disassemble the bridge deck pavement of the replacement concrete beam section 4 and its auxiliary settings, such as railings and the like. After dismantling, stretch the external prestress on the two adjacent spans of the span to be reinforced, that is, stretch the prestress on the two side spans 3, specifically by setting the prestressed steel tendons 10 on the two side spans 3. At the same time, since the support system 5 and the hoisting system 6 need to be installed on the fixed section to facilitate the hoisting of the replaced concrete beam section 4 and steel beam 9, due to the relatively large gravity of the replaced concrete beam section 4 and steel beam 9, it is easy to give weight during the hoisting process. The pressure of the fixed section is relatively large, so in this embodiment, the transverse diaphragm 11 is poured in the box girder at the position of the fixed section for carrying the support system 5 to increase the bearing capacity of the box girder in the fixed section; Drill holes on the upper and lower sides of one end face to the prestressed tendons, and grout the prestressed tendons. Specifically, the prestressed channels are drilled in sections within a range of about 5m from the fixed section to the cut end face, and the inside of the drilled holes The prestressed rib bellows are used for secondary grouting to enhance the fullness of prestressed channel grouting.

加固后,可现场拼装支撑系统5和吊装系统6,本实施例的支撑系统5和吊装系统6均为现有的常规设备,以简单、方便、安全且能够满足需求为佳,拼装完成后,可进行试吊,并监控固定段受到的应力变化及支撑系统5和吊装系统6受到的应力变化,易保证混凝土连续梁桥的箱梁结构和施工的安全性。After reinforcement, the support system 5 and the hoisting system 6 can be assembled on site. The support system 5 and the hoisting system 6 of this embodiment are all existing conventional equipment, which are simple, convenient, safe and able to meet the needs. After the assembly is completed, Can carry out trial lifting, and monitor the stress change of the fixed section and the stress change of the support system 5 and the hoisting system 6, which can easily ensure the safety of the box girder structure and construction of the concrete continuous girder bridge.

S12、在置换混凝土梁段4的两端呈八字形对称切割;S12, the two ends of the replacement concrete beam section 4 are symmetrically cut in a figure-eight shape;

具体切割时,先用两个吊装系统6将置换混凝土梁段4两端吊住,然后再进行切割,切割时采用八字形切割。在切割至设定厚度时,一般切割至置换混凝土梁段4厚度的二分之一至三分之一时,在固定段的切割端面上设置防冲击挑梁,防冲击挑梁的前端设置液压装置,液压装置一端抵接置换混凝土梁段4的切割端面,液压装置可采用常规的千斤顶,切割时可通过千斤顶调节固定段的切割端面与置换混凝土梁段4的切割端面之间的受力,防止置换混凝土梁段4发生突然的不均匀下沉和冲击。During specific cutting, first use two hoisting systems 6 to hang the two ends of the replacement concrete beam section 4, and then cut, adopt a figure-eight cut during cutting. When cutting to the set thickness, generally when cutting to one-half to one-third of the thickness of the replacement concrete beam section 4, an anti-impact cantilever is set on the cutting end face of the fixed section, and a hydraulic pressure is set at the front end of the anti-impact cantilever. One end of the hydraulic device abuts the cutting end face of the replacement concrete beam section 4. The hydraulic device can use a conventional jack, and the force between the cutting end face of the fixed section and the cutting end face of the replacement concrete beam section 4 can be adjusted by the jack during cutting. Prevent sudden uneven subsidence and impact of the replacement concrete beam section 4.

而且,应先等置换混凝土梁段4一端切割完成后,再切割另一端。置换混凝土梁段4两端均切割完成后,可通过千斤顶调节其顶推力缓慢释放切断时的冲击力。Moreover, the other end should be cut after one end of the replacement concrete beam section 4 is cut first. After both ends of the replacement concrete beam section 4 are cut, the impact force during cutting can be slowly released by adjusting the jacking force of the jack.

其中,当置换混凝土梁段4较长时,可分段切割下方,例如可将中间梁段置换混凝土梁段4先切割中部的19m,然后分段对称向边跨切割,具体分段可为两个3m、两个3m、两个3m、两个2m。其具体切割可根据实际需要进行,在此不作限定。Wherein, when the replacement concrete beam section 4 is longer, the lower section can be cut in sections. For example, the middle beam section replacement concrete beam section 4 can be cut to 19m in the middle first, and then sectionally symmetrically cut to the side span. The specific section can be two sections. One 3m, two 3m, two 3m, two 2m. The specific cutting can be carried out according to actual needs, which is not limited here.

S13、切割完成后,控制吊装系统6将切割后的置换混凝土梁段4吊装下放至相对应的放置平台7。S13. After the cutting is completed, the hoisting system 6 is controlled to hoist and lower the cut replacement concrete beam section 4 to the corresponding placement platform 7 .

具体吊装下放过程中,需要实时监控置换混凝土梁段4四个角的相对高度,保证置换混凝土梁段4任意两个角之间的竖直相对高度小于10mm,且该竖直相对高度越小越好,尤其是置换混凝土梁段4处于水平状态为佳。During the specific hoisting and lowering process, it is necessary to monitor the relative heights of the four corners of the replacement concrete beam section 4 in real time to ensure that the vertical relative height between any two corners of the replacement concrete beam section 4 is less than 10mm, and the smaller the vertical relative height, the higher the height. Well, it is especially good that the replacement concrete beam section 4 is in a horizontal state.

如图2所示,其为本实施例的钢砼接头8的安装示意图,其安装步骤如下:As shown in Figure 2, it is a schematic diagram of the installation of the steel-concrete joint 8 of this embodiment, and its installation steps are as follows:

S2、待加固跨切割后形成两个固定段,在两个固定段的切割端面上均设置钢砼接头8;如图4所示,钢砼接头钢结构设计:接头纵向长4m,其中钢箱部分长2.5m,内填充混凝土部分8.1长1.5m,在结合面设置一块50mm的承压板8.3,连接钢箱梁部分8.2顶板采用加劲板,与混凝土部分内的加劲板(PBL)对应;先竖向放置钢砼接头钢结构,浇筑填充混凝土,再平置钢砼接头。S2. Two fixed sections are formed after the reinforced span is cut, and steel-concrete joints 8 are arranged on the cutting end faces of the two fixed sections; The length of the part is 2.5m, and the length of the inner concrete part 8.1 is 1.5m. A 50mm bearing plate 8.3 is set on the joint surface, and the top plate of the connecting steel box girder part 8.2 adopts a stiffening plate, which corresponds to the stiffening plate (PBL) in the concrete part; first Place the steel structure of the steel-concrete joint vertically, pour the filling concrete, and then place the steel-concrete joint horizontally.

钢砼接头8的具体安装流程如下The specific installation process of steel concrete joint 8 is as follows

S21、凿除固定段靠近其切割端面一段的混凝土,且沿固定段长度方向凿除,凿除长度为1m左右,并将固定段的凿除混凝土后的梁端整形、凿毛、清洗、切割剪力健,并保留固定段内原有的支撑钢筋和预应力筋;S21. Chisel off the concrete of the fixed section close to its cutting end face, and chisel off along the length direction of the fixed section, the chiseled length is about 1m, and shape, chisel, clean and cut the beam end of the fixed section after the concrete is chiseled The shear force is strong, and the original supporting steel bars and prestressed tendons in the fixed section are retained;

且在步骤S21之前,需要将支撑系统5和吊装系统6向边跨移动一定距离;And before step S21, it is necessary to move the support system 5 and the hoisting system 6 to the side span for a certain distance;

S22、将钢砼接头8吊至安装位置,将钢箱梁端部的顶板、底板和腹板做成双璧板,将填充的混凝土与紧邻的混凝土箱梁段的顶板、底板和腹板通过PBL剪力板8.4、预应力钢筋和普通钢筋等得到很好地连接,再稍往前延伸将其与混凝土横隔板8.5连接,预应力短束钢筋锚固在混凝土横隔板和钢箱横隔板上,预应力长束钢筋锚固在混凝土横隔板后梁段的顶板、底板的齿块上,为了保证安装的精确性,需要对钢砼接头8进行精确定位,定位后与固定段的混凝土凿除端固定连接;S22. Hoist the steel-concrete joint 8 to the installation position, make the top plate, bottom plate and web plate at the end of the steel box girder into double wall plates, pass the filled concrete and the top plate, bottom plate and web plate of the adjacent concrete box girder section through the PBL Shear plate 8.4, prestressed steel bars and ordinary steel bars are well connected, and then extended slightly forward to connect it with concrete diaphragm 8.5, and prestressed short beams are anchored to the concrete diaphragm and steel box diaphragm Above, the prestressed long-beam steel bars are anchored on the top plate and bottom plate tooth blocks of the rear beam section of the concrete diaphragm. In order to ensure the accuracy of installation, the steel-concrete joint 8 needs to be precisely positioned. terminal fixed connection;

S23、在钢砼接头8与固定段连接处浇筑混凝土并养护,至混凝土达到设定强度后张拉预应力,该设定强度按本领域的常规方式实施,在此不作赘述。张拉预应力后,按常规方式进行钢砼接头8的防护和涂装。S23. Concrete is poured and cured at the connection between the steel-concrete joint 8 and the fixed section, and the prestress is stretched after the concrete reaches a set strength. After tensioning and prestressing, the steel-concrete joint 8 is protected and painted in a conventional manner.

如图3所示,其为本实施例的钢梁9的安装示意图,其安装步骤如下:As shown in Figure 3, it is the installation schematic diagram of the steel beam 9 of the present embodiment, and its installation steps are as follows:

S3、将钢梁9吊至两个钢砼接头8之间并与钢砼接头8连接。S3. Lift the steel beam 9 between the two steel-concrete joints 8 and connect with the steel-concrete joint 8 .

S31、制作与两个钢砼接头8相配合的钢梁9,将钢梁9运至钢砼接头8下方并吊至两个钢砼接头8之间;S31, making a steel beam 9 matching the two steel-concrete joints 8, transporting the steel beam 9 below the steel-concrete joint 8 and hoisting it between the two steel-concrete joints 8;

钢梁9具体可在工厂或设定位置制作,钢梁9长度应根据来个钢砼接头8之间的距离进行设置,本实施例的钢梁9为45m。钢梁9为在整体总拼胎架上无应力状态下制作,且制作时根据混凝土连续梁桥的实际荷载进行计算分析,并根据计算分析的数据设置钢梁9的预拱度。The steel girder 9 can be manufactured in a factory or at a set location. The length of the steel girder 9 should be set according to the distance between the steel-concrete joints 8. The steel girder 9 of this embodiment is 45m. The steel girder 9 is manufactured under the stress-free state on the overall tire frame, and is calculated and analyzed according to the actual load of the concrete continuous girder bridge, and the pre-camber of the steel girder 9 is set according to the calculated and analyzed data.

在钢梁9吊运前,需要钢梁9与两个钢砼接头8精确对应,即钢梁9在防止平台的位置7需要定位,以保证钢梁9竖直吊上来后与两个钢砼接头8相契合。而且,吊装过程中,钢梁9的四个角中任意两个角之间的竖直高度差应小于10mm,具体可通过监控系统实时监控,以保证钢梁9吊装过程中的平稳度。Before the steel girder 9 is hoisted, it is necessary for the steel girder 9 to correspond precisely to the two steel-concrete joints 8, that is, the steel girder 9 needs to be positioned at the position 7 to prevent the platform, so as to ensure that the steel girder 9 is vertically hoisted up and connected to the two steel-concrete joints 8. Connector 8 matches. Moreover, during the hoisting process, the vertical height difference between any two corners of the four corners of the steel beam 9 should be less than 10mm, which can be monitored in real time by the monitoring system to ensure the stability of the steel beam 9 during the hoisting process.

S32、将钢梁9一端通过高强螺栓与其中一个钢砼接头8固定后焊接,然后将钢梁9另一端通过高强螺栓与另一个钢砼接头8固定后焊接。S32. Fix one end of the steel beam 9 to one of the steel-concrete joints 8 through high-strength bolts and weld them, and then fix the other end of the steel beam 9 to the other steel-concrete joint 8 through high-strength bolts and weld them.

将钢梁9吊装定位后,首先将钢梁9一端通过高强螺栓与钢砼接头8临时固定,然后焊接进行永久固定,最后将钢梁9另一端通过高强螺栓连接,连接后调整位置然后进行焊接。After hoisting and positioning the steel beam 9, first temporarily fix one end of the steel beam 9 with the steel-concrete joint 8 through high-strength bolts, and then perform permanent fixation by welding, and finally connect the other end of the steel beam 9 through high-strength bolts, adjust the position after connection and then perform welding .

S33、张拉钢梁9预应力,用于钢梁9张拉预应力的钢束两端分别锚固于钢梁9离其一端10m位置。S33. Prestressing the tensioned steel beam 9, the two ends of the steel bundle used for the tensioning and prestressing of the steel beam 9 are respectively anchored to the position 10m away from one end of the steel beam 9.

钢梁9预应力张拉后,可进行钢梁9桥面铺装及其附属设施的安装。After the steel girder 9 is prestressed and stretched, the steel girder 9 bridge deck pavement and the installation of its ancillary facilities can be carried out.

以上所述本发明的具体实施方式,并不构成对本发明保护范围的限定。任何根据本发明的技术构思所做出的各种其他相应的改变与变形,均包含在本发明权利要求的保护范围内。The specific embodiments of the present invention described above do not constitute a limitation to the protection scope of the present invention. Any other corresponding changes and modifications made according to the technical concept of the present invention are included in the protection scope of the claims of the present invention.

Claims (7)

1. the beam section replacing and reinforcing method for large span concrete continuous beam bridge, it is characterised in that comprise the steps:
S1, by displacement Concrete Beam Segment from concrete continuous beam treat reinforcing step up cutting and handling;Specifically include:
S11, the deck paving removing displacement Concrete Beam Segment and affiliated facility thereof, carry out local stiffening to concrete continuous beam, And on two canned paragraphs, be all correspondingly arranged support system and the Lift-on/Lift-off System being connected with support system, and incited somebody to action by Lift-on/Lift-off System Displacement Concrete Beam Segment lifting is fixing;
S12, it is the cutting of splayed symmetry at the two ends of displacement Concrete Beam Segment, and uses under interim external prestressing or bridge actively Stress support protection end bay beam body, it is ensured that middle beam section demolishing process safety;
S13, cut after, control Lift-on/Lift-off System will cutting after displacement Concrete Beam Segment lifting transfer to corresponding placement Platform.
S2, wait reinforce across cutting after formed two canned paragraphs, the cutting end face of two canned paragraphs is respectively provided with steel concrete joint;
S3, winch to girder steel be connected between two steel concrete joints and with steel concrete joint.
Beam section replacing and reinforcing method the most according to claim 1, it is characterised in that local stiffening bag in described step S11 Include: wait to reinforce across adjacent two step up stretch-draw external prestressing, in the box beam of canned paragraph, pour diaphragm plate, and at canned paragraph Punching to Prestress tendon near top and bottom of its cutting end face one end, and Prestress tendon is carried out grouting pour.
Beam section replacing and reinforcing method the most according to claim 1 and 2, it is characterised in that described step S12 is additionally included in cuts Cutting to when setting thickness, arrange protecting against shock outrigger on the cutting end face of canned paragraph, the front end of protecting against shock outrigger arranges hydraulic pressure dress Putting, hydraulic means one end abuts the cutting end face of displacement Concrete Beam Segment.
Beam section replacing and reinforcing method the most according to claim 3, it is characterised in that described step S13 is additionally included in lifting The relative altitude at decentralization process monitoring displacement four angles of Concrete Beam Segment, makes erecting between displacement Concrete Beam Segment any two angle Straight relative altitude is less than 10mm.
Beam section replacing and reinforcing method the most according to claim 4, it is characterised in that described step S2 includes:
S21, cut canned paragraph concrete in the 1m of its cutting end face, and by the beam-ends cut after concrete of canned paragraph Shaping, dabbing, clean, cut shearing and be good for, and original spacer bar and presstressed reinforcing steel in retaining canned paragraph;
S22, steel concrete joint is winched to installation site, and fixing with the concrete chisel removal end of canned paragraph be connected;
S23, in steel concrete joint and canned paragraph junction casting concrete maintenance, reach to set intensity post-stretching to concrete pre- Stress.
Steel concrete joint is made up of steel concrete joint Concrete Beam Segment and steel concrete joint steel box-girder section, uses side board-like after filling concrete Formula, the most vertical placement steel concrete joint steel construction, pour fill concrete, then horizontal steel concrete joint, transport to bridge location by shipping, After top board, base plate and the web of steel box-girder end made double ancient piece of jade, round, flat and with a hole in its centre plate, by the concrete box beam section of the concrete filled with next-door neighbour Top board, negative and web connect by PBL shear plate, deformed bar and regular reinforcement, and extend itself and coagulation forward Soil diaphragm plate connect, prestressing force short bundle Bar Anchorage on concrete diaphragm plate and steel case diaphragm plate, prestressing force long bundle reinforcing bar anchor Gu after concrete diaphragm plate on the tooth block of the top board of beam section, base plate.
Beam section replacing and reinforcing method the most according to claim 5, it is characterised in that described step S3 includes:
The girder steel that S31, making match with two steel concrete joints, is transported to girder steel below steel concrete joint and winches to two steel concretes and connect Between Tou;
S32, girder steel one end is fixed by high-strength bolt and one of them steel concrete joint after weld, then the girder steel other end is led to Cross after high-strength bolt is fixed with another steel concrete joint and weld.
S33, stretch-draw girder steel prestressing force.
Beam section replacing and reinforcing method the most according to claim 6, it is characterised in that open for girder steel in described step S33 Prestressed steel bundle two ends are drawn to be anchored in girder steel respectively from 10m position, its one end.
CN201610957575.1A 2016-10-27 2016-10-27 A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge Active CN106320192B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610957575.1A CN106320192B (en) 2016-10-27 2016-10-27 A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610957575.1A CN106320192B (en) 2016-10-27 2016-10-27 A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge

Publications (2)

Publication Number Publication Date
CN106320192A true CN106320192A (en) 2017-01-11
CN106320192B CN106320192B (en) 2018-10-09

Family

ID=57819245

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610957575.1A Active CN106320192B (en) 2016-10-27 2016-10-27 A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge

Country Status (1)

Country Link
CN (1) CN106320192B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108004928A (en) * 2017-12-01 2018-05-08 中铁二十局集团第工程有限公司 A kind of asymmetric rigid frame-continuous girder construction technology
CN109577162A (en) * 2019-01-23 2019-04-05 中铁大桥科学研究院有限公司 A kind of Continuous Bridge and its construction method with UHPC hanging hole construction
CN110761202A (en) * 2018-07-25 2020-02-07 江苏省科佳工程设计有限公司 Prestress applying method in pre-pressing construction process
CN114687274A (en) * 2022-03-25 2022-07-01 中铁第四勘察设计院集团有限公司 Rigid frame-continuous steel-concrete mixed beam railway bridge structure
CN119308237A (en) * 2024-11-29 2025-01-14 中铁第一勘察设计院集团有限公司 A construction method for rebuilding a steel truss beam into a concrete simply supported beam

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08218327A (en) * 1995-02-09 1996-08-27 Sho Bond Constr Co Ltd Preventive construction of main-girder lateral buckling to be generated in replacement of floor slab of composite girder with precast floor slab
CN201648959U (en) * 2009-12-04 2010-11-24 上海市政工程设计研究总院 Replaceable connecting device for new and old bridge main beams
KR20120118884A (en) * 2011-04-20 2012-10-30 김근택 Deck repairing construction method of bridge using precast concrete slab
CN103498427A (en) * 2013-10-29 2014-01-08 苏州荣生大方路桥建设工程有限公司 Quick replacement method of overpass bridge section
CN203411915U (en) * 2013-06-17 2014-01-29 北京市政路桥管理养护集团有限公司 Carrying device for bridge overall replacement
CN104047367A (en) * 2014-06-26 2014-09-17 清华大学 Novel connecting structure capable of achieving replacement of steel coupling beams

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08218327A (en) * 1995-02-09 1996-08-27 Sho Bond Constr Co Ltd Preventive construction of main-girder lateral buckling to be generated in replacement of floor slab of composite girder with precast floor slab
CN201648959U (en) * 2009-12-04 2010-11-24 上海市政工程设计研究总院 Replaceable connecting device for new and old bridge main beams
KR20120118884A (en) * 2011-04-20 2012-10-30 김근택 Deck repairing construction method of bridge using precast concrete slab
CN203411915U (en) * 2013-06-17 2014-01-29 北京市政路桥管理养护集团有限公司 Carrying device for bridge overall replacement
CN103498427A (en) * 2013-10-29 2014-01-08 苏州荣生大方路桥建设工程有限公司 Quick replacement method of overpass bridge section
CN104047367A (en) * 2014-06-26 2014-09-17 清华大学 Novel connecting structure capable of achieving replacement of steel coupling beams

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李宏江: "预应力混凝土斜拉桥合龙段置换加固施工过程分析", 《土木建筑与环境工程》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108004928A (en) * 2017-12-01 2018-05-08 中铁二十局集团第工程有限公司 A kind of asymmetric rigid frame-continuous girder construction technology
CN108004928B (en) * 2017-12-01 2019-09-17 中铁二十局集团第一工程有限公司 A kind of asymmetric rigid frame-continuous girder construction technology
CN110761202A (en) * 2018-07-25 2020-02-07 江苏省科佳工程设计有限公司 Prestress applying method in pre-pressing construction process
CN109577162A (en) * 2019-01-23 2019-04-05 中铁大桥科学研究院有限公司 A kind of Continuous Bridge and its construction method with UHPC hanging hole construction
CN114687274A (en) * 2022-03-25 2022-07-01 中铁第四勘察设计院集团有限公司 Rigid frame-continuous steel-concrete mixed beam railway bridge structure
CN114687274B (en) * 2022-03-25 2024-03-26 中铁第四勘察设计院集团有限公司 Rigid frame-continuous steel-concrete mixed beam railway bridge structure
CN119308237A (en) * 2024-11-29 2025-01-14 中铁第一勘察设计院集团有限公司 A construction method for rebuilding a steel truss beam into a concrete simply supported beam

Also Published As

Publication number Publication date
CN106320192B (en) 2018-10-09

Similar Documents

Publication Publication Date Title
CN100590266C (en) Reverse sequence demolition method of prestressed concrete tied arch bridge
CN114892552B (en) Box girder type bridge reconstruction construction method
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN106320192B (en) A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge
CN109695206B (en) Method for dismantling superstructure of cable-stayed bridge of water-borne lean cable system
CN110552296B (en) Cable-stayed bridge dismantling construction method
CN106677049A (en) Assembled steel-concrete combination structure bridge and construction method
CN102839601A (en) Consolidated structure of steel piers and caps of portal-type rigid frame overpass and its construction method
CN108104284B (en) Wall panel connection structure and assembly method with steel arm of shear wall embedded in floor slab
CN110387822A (en) Cast-in-place cover beam assembled steel pipe support and construction method thereof
CN108342973A (en) Whole H profile steel-concrete composite beam bridge and construction method across prefabricated installation
CN108824221B (en) Web replacement and strengthening method of concrete continuous girder bridge based on corrugated steel plate
CN106012872B (en) Cable-stayed reinforcement system and construction method for continuous rigid frame bridges without back-cable
CN108060636A (en) The construction method of overall assembled composite beam bridge
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN110863417A (en) A fast-installed steel-concrete composite girder bridge and its construction method
CN102322025A (en) Pre-stressing reinforced and widened bridge structure
CN106638265A (en) Steel reinforced concrete beam rigid framework bridge
CN101122115A (en) A construction method for tower crane displacement
CN109629576B (en) Suspension protection system for water supply pipe crossing foundation pit and construction method
CN114134820A (en) Formwork support and construction method for cast-in-place bridge deck of I-shaped composite beam
CN102808375B (en) Hinge structure of steel pier column of portal frame platform bridge and bearing platform and construction method thereof
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN205934687U (en) Antinode worker roof beam - steel concrete roof - external prestress combination T type simple beam
CN110700112A (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant