JP2017172247A - Removal method of solidification object in pile head part of precast pile - Google Patents

Removal method of solidification object in pile head part of precast pile Download PDF

Info

Publication number
JP2017172247A
JP2017172247A JP2016060311A JP2016060311A JP2017172247A JP 2017172247 A JP2017172247 A JP 2017172247A JP 2016060311 A JP2016060311 A JP 2016060311A JP 2016060311 A JP2016060311 A JP 2016060311A JP 2017172247 A JP2017172247 A JP 2017172247A
Authority
JP
Japan
Prior art keywords
pile
ready
concrete
made pile
filled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016060311A
Other languages
Japanese (ja)
Other versions
JP6656972B2 (en
Inventor
本田 和久
Kazuhisa Honda
和久 本田
春樹 岡山
Haruki Okayama
春樹 岡山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Mitani Sekisan Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd, Mitani Sekisan Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP2016060311A priority Critical patent/JP6656972B2/en
Publication of JP2017172247A publication Critical patent/JP2017172247A/en
Application granted granted Critical
Publication of JP6656972B2 publication Critical patent/JP6656972B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a removal method of a solidification object of a pile inside in a pile head part of a precast pile, for easily removing the solidification object composed of a cement component filled in the precast pile in a sinking process of the precast pile, for forming an upper structure establishing hole for installing a part of a concrete structure constructed in an upper part of the precast pile even in the precast pile as infilling concrete.SOLUTION: A precast pile 1 of a both-end opening shape is sunk from one end side 1a of the precast pile 1 in uncured concrete 4 poured into an excavation hole 3 excavated for installing the precast pile 1 in a ground 2, and water 6 is injected from the other end side 1b of the precast pile 1 into uncured filling concrete 5 so as to become lean-mix capable of removing the uncured filling concrete 5 taken in a pile head part on the inside of the precast pile 1 by this sinking, and an upper structure establishing hole 12 is formed by removing the filling concrete 5 becoming the lean-mix by injection of this water up to a position for placing infilling concrete from aboveground.SELECTED DRAWING: Figure 1

Description

本発明は、支柱や壁、基礎等の既製杭の上部に構築するコンクリート構造物との一体性を高めるために、コンクリート構造物の一部を中詰めコンクリートとして既製杭内にも打設するための上部構造物樹立用孔を既製杭の内部の杭頭部に形成するために、既製杭の沈設過程で既製杭内に充填されたセメント成分からなる固化物の撤去方法に関する。   In order to increase the integrity of the concrete structure built on the upper part of the ready-made piles such as columns, walls, and foundations, the present invention places a part of the concrete structure in the ready-made piles as infilled concrete. It is related with the removal method of the solidified material which consists of a cement component with which the ready-made pile was filled in the settling process of a ready-made pile, in order to form the hole for superstructure establishment of No. in the pile head inside a ready-made pile.

図3を用いて、特許文献1で開示された支柱等の上部構造物樹立用孔119を既製杭101の内部に形成する方法について説明する。図3のa図に示したように、両端開口形の既製杭101の上側内にセメント抜取用具102が設置される。セメント抜取用具102は、逆U字状になった一対の支持部材103が紙管104の内外に跨がるように配置されて紙管104に固定され、合成樹脂からなる内側被覆体105及び合成樹脂からなる外側被覆体106が紙管104の外側及び一対の支持部材103の外側を被覆いかつ紙管104に固定され、一対の支持部材103の紙管104よりも上側の折曲部107を貫通した止棒108の両端部が既製杭101の上端面に取り付けられる。このようにセメント抜取用具102が設置された既製杭101は、一端側から、地盤111に掘削された掘削孔112に流し込まれた未硬化なコンクリート113の中に沈設されるのに伴って、掘削孔112中の未硬化なコンクリート113が上昇して既製杭101と掘削孔112との隙間114、既製杭101とセメント抜取用具102との隙間115、セメント抜取用具102の内空間116に取り込まれる。   With reference to FIG. 3, a method of forming the upper structure establishment hole 119 such as a support column disclosed in Patent Document 1 inside the ready-made pile 101 will be described. As shown in FIG. 3a, a cement removal tool 102 is installed in the upper side of a ready-made pile 101 having an opening at both ends. The cement extraction tool 102 has a pair of inverted U-shaped support members 103 arranged so as to straddle the inside and outside of the paper tube 104 and fixed to the paper tube 104, and an inner covering 105 made of synthetic resin and a synthetic resin. An outer covering 106 made of resin covers the outside of the paper tube 104 and the outside of the pair of support members 103 and is fixed to the paper tube 104, and has a bent portion 107 above the paper tube 104 of the pair of support members 103. Both end portions of the penetrating stop rod 108 are attached to the upper end surface of the ready-made pile 101. The ready-made pile 101 in which the cement removal tool 102 is installed in this way is excavated as it is set in the unhardened concrete 113 poured into the excavation hole 112 excavated in the ground 111 from one end side. The uncured concrete 113 in the hole 112 rises and is taken into the gap 114 between the ready-made pile 101 and the excavation hole 112, the gap 115 between the ready-made pile 101 and the cement removal tool 102, and the inner space 116 of the cement removal tool 102.

そして、図3のb図に示したように、未硬化なコンクリート113が養生させて硬化した後、止棒108が既製杭101から外され、セメント抜取用具102の一対の支持部材103が図示のされていない建柱機でワイヤロープ等の吊り部材118を介して吊り上げられる。この吊り上げに伴って、セメント抜取用具102の内空間116に取り込まれて硬化したコンクリート113が既製杭101内で硬化したコンクリート113並びに既製杭101とセメント抜取用具102との隙間115で硬化したコンクリート113から切断されて引き上げられ、内側被覆体105及び外側被覆体106が紙管104から剥がされるとともに既製杭101とセメント抜取用具102との隙間115で硬化したコンクリート113から剥がされ、既製杭101の上側内に上部構造物樹立用孔119が形成される。   Then, as shown in FIG. 3b, after the uncured concrete 113 is cured and hardened, the stop rod 108 is removed from the ready-made pile 101, and the pair of support members 103 of the cement removal tool 102 are illustrated. It is lifted through a suspension member 118 such as a wire rope by a construction machine that is not used. With this lifting, the concrete 113 that has been taken in and hardened in the inner space 116 of the cement removal tool 102 has hardened in the ready-made pile 101 and the concrete 113 hardened in the gap 115 between the ready-made pile 101 and the cement removal tool 102. The inner covering 105 and the outer covering 106 are peeled off from the paper tube 104 and peeled off from the concrete 113 hardened in the gap 115 between the ready-made pile 101 and the cement removal tool 102, and the upper side of the ready-made pile 101. An upper structure establishment hole 119 is formed therein.

しかしながら、上部構造物樹立用孔119の計画深さが例えば3mもある場合、セメント抜取用具102を容易に撤去できなかった。また、セメント抜取用具102が撤去できた場合でも、図3のb図に示すように、上部構造物樹立用孔119と既製杭101の内面との間には、既製杭101とセメント抜取用具102との隙間115で硬化したコンクリート113が残存する。この残存したコンクリート113は、上部構造物を構築する際に用いられるコンクリート113と品質が異なることが一般的である。そのため、既製杭101とセメント抜取用具102との隙間115で硬化して残存したコンクリート113は、オーガー削孔機で削り、さらに、ケレン等で除去している。けれども、残存したコンクリート113が孔径600mmで、深さ1mの場合、ケレン等で残存したコンクリート113を除去することは困難であった。   However, when the planned depth of the upper structure establishment hole 119 is, for example, 3 m, the cement removal tool 102 cannot be easily removed. Further, even when the cement removal tool 102 can be removed, the ready-made pile 101 and the cement removal tool 102 are between the upper structure establishment hole 119 and the inner surface of the ready-made pile 101 as shown in FIG. The hardened concrete 113 remains in the gap 115. The remaining concrete 113 is generally different in quality from the concrete 113 used in constructing the superstructure. Therefore, the concrete 113 which has hardened and remains in the gap 115 between the ready-made pile 101 and the cement removal tool 102 is shaved with an auger drilling machine and further removed with kelen or the like. However, when the remaining concrete 113 has a hole diameter of 600 mm and a depth of 1 m, it is difficult to remove the remaining concrete 113 with kelen or the like.

特開平5−247930号公報JP-A-5-247930

本発明は、上記背景技術に鑑みてなされたものであり、既製杭の上部に構築するコンクリート構造物の一部を中詰めコンクリートとして既製杭内にも打設するための上部構造物樹立用孔を既製杭の内部の杭頭部に形成するために、既製杭の沈設過程で既製杭内に充填されたセメント成分からなる固化物の撤去が容易になる、既製杭の杭頭部における固化物の撤去方法の提供を目的とする。   The present invention has been made in view of the above-described background art, and a hole for establishing an upper structure for placing a part of a concrete structure constructed on an upper portion of an already-made pile also as an inside-filled concrete in the already-made pile. In the pile head inside the ready-made pile, it is easy to remove the solidified material consisting of the cement component filled in the ready-made pile during the set-up process of the ready-made pile. The purpose is to provide the removal method.

本発明は、既製杭の上部に構築するコンクリート構造物の一部を中詰めコンクリートとして既製杭内にも打設するための上部構造物樹立用孔を既製杭の内部の杭頭部に形成するために、地盤に掘削された掘削孔に流し込まれた未硬化なコンクリートの中に両端開口形の既製杭を一端側から沈設し、この沈設により既製杭内に充填された未硬化な充填コンクリートが除去可能な貧配合のセメント成分からなる固化物となるように当該既製杭の他端側から水を上記既製杭内に充填された未硬化な充填コンクリートに注入し、この水の注入で貧配合となったセメント成分からなる固化物を既製杭の杭頭部から除去することを特徴とする。   The present invention forms a hole for establishing an upper structure in a pile head inside the ready-made pile for placing a part of the concrete structure constructed on the upper part of the ready-made pile as an inside-filled concrete also in the ready-made pile. For this purpose, a ready-made pile with open ends is submerged from one end side in unhardened concrete poured into the excavation hole excavated in the ground, and the unhardened filled concrete filled in the ready-made pile by this sinking Water is poured from the other end of the ready-made pile into the uncured filled concrete filled in the ready-made pile so that it becomes a solidified product composed of a poorly-mixed cement component that can be removed. The solidified material composed of the cement component is removed from the pile head of the ready-made pile.

本発明は、既製杭の沈設過程で既製杭内に充填された未硬化な充填コンクリートに水を注入して上記充填コンクリートを除去可能な貧配合のセメント成分からなる固化物と成し、この貧配合のセメント成分からなる固化物を既製杭の杭頭部から除去するので、上記既製杭内の充填コンクリートが硬化した後でも容易に撤去することができる。本発明において、上記既製杭内に充填された未硬化な充填コンクリートに注入する場合に掘削ロッドで行えば、注水用の専用パイプを用いる必要がない。本発明において、上記既製杭内に充填された未硬化な充填コンクリートに水を注入する場合に中詰めコンクリートを打設する位置まで上記水を注入すれば、貧配合のセメント成分からなる固化物の除去後に既製杭の上部に構築されるコンクリート構造物と既製杭との一体性が高くなる。本発明において、上記貧配合のセメント成分からなる固化物の除去をオーガー削孔機で行えば、上部構造物樹立用孔が深くても、貧配合のセメント成分からなる固化物を容易に撤去することができる。   The present invention is a solidified product comprising a poorly blended cement component capable of removing the filled concrete by injecting water into the uncured filled concrete filled in the ready-made pile during the set-up process of the ready-made pile. Since the solidified material composed of the blended cement component is removed from the pile head of the ready-made pile, it can be easily removed even after the filled concrete in the ready-made pile is cured. In the present invention, it is not necessary to use a dedicated pipe for pouring water if the excavation rod is used when pouring into uncured filled concrete filled in the ready-made pile. In the present invention, when water is poured into unfilled filled concrete filled in the above-mentioned ready-made piles, if the water is poured up to a position where medium-filled concrete is placed, The integrity of the concrete structure built on top of the ready-made pile after removal and the ready-made pile is increased. In the present invention, if the solidified material composed of the poorly blended cement component is removed by an auger drilling machine, the solidified material composed of the poorly blended cement component is easily removed even if the upper structure establishment hole is deep. be able to.

なお、前記発明の概要は、本発明の必要な全ての特徴を列挙したものではなく、これらの特徴群のサブコンビネーションもまた、発明となりうる。   The summary of the invention does not list all necessary features of the present invention, and sub-combinations of these feature groups can also be the invention.

本発明を実施するための形態1に係る既製杭の杭頭部における固化物の撤去方法を示し、a図は既製杭の充填コンクリート撤去準備作業の縦断面図、b図は既製杭の充填コンクリート撤去作業前を示した縦断面図、c図は既製杭の充填コンクリート撤去作業後を示した縦断面図。The solidified material removal method in the pile head of the ready-made pile concerning the form 1 for implementing this invention is shown, a figure is a longitudinal cross-sectional view of the filling concrete removal preparation work of a ready-made pile, b figure is the filling concrete of a ready-made pile The longitudinal cross-sectional view which showed before the removal work, and c figure are the longitudinal cross-sectional views which showed the filling concrete removal work of a ready-made pile. 本発明を実施するための形態1に係る既製杭の杭頭部における固化物の撤去方法よりも前工程の作業を示し、a図は地盤に掘削孔を掘削する作業を示した縦断面図、b図は掘削孔に未硬化なコンクリートを流し込む作業を示した縦断面図、c図は掘削孔に流し込まれた未硬化なコンクリートに既製杭を沈設した作業を示した縦断面図。The work of a previous process is shown rather than the removal method of the solidified material in the pile head of the ready-made pile concerning form 1 for carrying out the present invention, a figure is a longitudinal section showing work which excavates an excavation hole in the ground, Fig. b is a longitudinal sectional view showing the operation of pouring uncured concrete into the excavation hole, and Fig. c is a longitudinal sectional view showing the operation of laying a ready-made pile on the uncured concrete poured into the excavation hole. 従来の上部構造物樹立用孔を既製杭の内部に形成する方法を示し、a図はセメント抜取用具を備えた既製杭が地盤に掘削された掘削孔に流し込まれた未硬化なコンクリートの中に沈設される作業を示した縦断面図、b図はセメント抜取用具の吊り上げで既製杭の上側内に上部構造物樹立用孔を形成する作業を示した縦断面図。A conventional method for forming a hole for establishing a superstructure inside a prefabricated pile is shown. FIG. A shows a prefabricated pile equipped with a cement removal tool in unhardened concrete poured into a drilling hole excavated in the ground. The longitudinal cross-sectional view which showed the operation | work set up, FIG. B is the longitudinal cross-sectional view which showed the operation | work which forms the hole for upper structure establishment in the upper side of a ready-made pile by lifting of a cement extraction tool.

本発明を実施するための形態1に係る既製杭1の沈設過程において杭頭部内に流れ込み(充填)硬化したセメント成分からなる固化物、例えば、固化物としての充填コンクリートの撤去方法は、図1のa図に示した充填コンクリート撤去準備作業と、図1のb図及びc図に示した充填コンクリート撤去作業からなる。まず、図1のa図を用いて、充填コンクリート撤去準備作業について説明する。図1のa図に示した既製杭1の充填コンクリート撤去準備作業は、地盤2に既製杭1を設置するために掘削された掘削孔3に流し込まれた未硬化なコンクリート4の中に両端開口形の既製杭1が既製杭1の一端側1aから沈設され、この沈設により既製杭1の内部の杭頭部に取り込まれた未硬化な充填コンクリート5が除去可能な貧配合となるように、既製杭1の内部の杭頭部における未硬化な充填コンクリート5に既製杭1の他端側1bから水6が注入されることにより、既製杭1の内部における充填コンクリート5が貧配合のまま硬化して貧配合のセメント成分からなる固化物に成るので、充填コンクリート5が硬化した後でも、貧配合のセメント成分からなる固化物としての充填コンクリート5を容易に撤去することができる。   The removal method of the solidified material which consists of the cement component which flowed into the pile head in the setting process of the ready-made pile 1 which concerns on form 1 for implementing this invention (filling) hardening, for example, the filling concrete as a solidified material, 1 consists of a filling concrete removal preparation work shown in FIG. 1a and a filling concrete removal work shown in FIGS. 1b and 1c. First, the filling concrete removal preparation work will be described with reference to FIG. The preparatory work for removing the filled concrete of the ready-made pile 1 shown in FIG. 1A is performed by opening both ends in the unhardened concrete 4 poured into the excavation hole 3 excavated to install the ready-made pile 1 on the ground 2. The shape ready-made pile 1 is sunk from one end side 1a of the ready-made pile 1, so that the uncured filled concrete 5 taken into the pile head inside the ready-made pile 1 becomes a poor compound that can be removed. By injecting water 6 from the other end 1b of the ready-made pile 1 into the unhardened filled concrete 5 at the pile head inside the ready-made pile 1, the filled concrete 5 inside the ready-made pile 1 is hardened while being poorly mixed. Thus, since the solidified product made of the poorly blended cement component is formed, the filled concrete 5 as the solidified product composed of the poorly blended cement component can be easily removed even after the filled concrete 5 is hardened.

本実施形態1の未硬化なコンクリート4は、流動性を有するコンクリートであるが、セメントミルクや、モルタル等のセメント成分からなる水硬性部材でも良い。また、水6が注入される場合、地上において、オーガー削孔機における掘削ロッド7の先端部から掘削ヘッド11が取り外された後、オーガー削孔機で掘削ロッド7の先端部が地上から既製杭1の内部における未硬化な充填コンクリート5の中に上部構造物樹立用孔12(図1のc図参照)の中詰めコンクリートを打設する計画深さまで挿入され、この充填コンクリート5の中に挿入されかつ上昇する掘削ロッド7の先端部から水6が既製杭1の内部における未硬化な充填コンクリート5に注入終了後、上昇される。その際、水が掘削孔3から地上溢れ出すことを確認することが望ましい。掘削ロッド7は、地上から掘削ロッド7の内部を経由して下側に水6及び未硬化なコンクリート4を通すことが可能な中空になっている。上記上部構造物樹立用孔12の中詰めコンクリートを打設する計画深さは、中詰めコンクリートを打設する位置と同義語である。上記のように中詰めコンクリートを打設する位置まで水を注入すれば、図1のc図に示した貧配合の充填コンクリート5が除去された後の上部構造物樹立用孔12に、既製杭1の上部に構築されるコンクリート構造物の一部が中詰めコンクリートとして打設された場合において、中詰めコンクリートと既製杭との一体性が高くなる。   The uncured concrete 4 of the first embodiment is fluid concrete, but may be a hydraulic member made of cement components such as cement milk and mortar. In addition, when water 6 is injected, after the excavation head 11 is removed from the tip of the excavation rod 7 in the auger drilling machine on the ground, the tip of the excavation rod 7 is ready-made from the ground with the auger drilling machine. 1 is inserted into the uncured filled concrete 5 in the interior 1 to the planned depth for placing the filled concrete 12 in the upper structure establishment hole 12 (see FIG. 1 c), and inserted into this filled concrete 5 Then, water 6 is raised from the tip of the excavating rod 7 that is raised and then poured into the uncured filled concrete 5 inside the ready-made pile 1 after completion. At that time, it is desirable to confirm that the water overflows from the excavation hole 3. The excavation rod 7 is hollow so that the water 6 and the uncured concrete 4 can be passed from the ground via the inside of the excavation rod 7 to the lower side. The planned depth for placing the filling concrete for the upper structure establishment hole 12 is synonymous with the position for placing filling concrete. If water is poured up to the position where the filled concrete is placed as described above, the prefabricated pile is formed in the upper structure establishment hole 12 after the poor blended concrete 5 shown in FIG. When a part of the concrete structure constructed on the upper part of 1 is placed as medium-filled concrete, the integrity of the medium-filled concrete and the ready-made pile is increased.

掘削孔3は、上側の縦孔8と下側の拡底部としての拡大根固め孔9とから構成される。拡大根固め孔9の底部は、既製杭1の上に構築される図示のされていない上部構造物の重さに耐えられる硬い地盤2としての支持層になっている。既製杭1は、1本のように図示したが、1本に限定されるものはなく、先端杭15(図2参照)と複数本の接続杭16(図2参照)を接続した既製杭1とからなる。   The excavation hole 3 includes an upper vertical hole 8 and an enlarged rooting hole 9 as a lower bottom enlarged portion. The bottom of the enlarged rooting hole 9 is a support layer as a hard ground 2 that can withstand the weight of an upper structure (not shown) constructed on the ready-made pile 1. The ready-made pile 1 is illustrated as one, but is not limited to one, and the ready-made pile 1 in which a tip pile 15 (see FIG. 2) and a plurality of connecting piles 16 (see FIG. 2) are connected. It consists of.

尚、図1のa図に示した既製杭1の充填コンクリート撤去準備作業が実行される以前において、地盤2に掘削孔3が掘削され、掘削孔3に既製杭1が沈設されるまでの工程については、図2で説明する。   In addition, before the filling concrete removal preparatory work of the ready-made pile 1 shown to a figure of FIG. 1 is performed, the process until the excavation hole 3 is excavated in the ground 2 and the ready-made pile 1 is sunk in the excavation hole 3 Will be described with reference to FIG.

次に、図1のb図及びc図を用いて、本発明を実施するための形態1に係る充填コンクリート撤去作業について説明する。図1のb図及びc図に示した充填コンクリート撤去作業は、図1のa図に示した充填コンクリート撤去準備作業の後工程として行われる。   Next, the filling concrete removing operation according to the first embodiment for carrying out the present invention will be described with reference to FIGS. The filled concrete removal work shown in FIGS. 1b and 1c is performed as a post-process of the filled concrete removal preparation work shown in FIG. 1a.

図1のb図に示したように、既製杭1の杭頭部の一部が露出するように地盤2の掘削と、その杭頭部の周囲及び、上部にあるコンクリートを除去した後、杭頭部の上方に掘削ヘッド11が掘削ロッド7の先端部に取り付けられているオーガー削孔機を準備する。掘削ヘッド11の外径は、既製杭1の内径よりも小寸法になっている。そして、掘削ロッド7の下降運動と回転運動とにより、掘削ヘッド11が掘削ヘッド11の上下方向に延びる中心線を回転中心として水平方向に回転しかつ下降するのに伴って、掘削ヘッド11が地上から既製杭1の内部に存在する貧配合となった充填コンクリート5としての貧配合のセメント成分からなる固化物を上部構造物樹立用孔12(図1のc図参照)の計画深さまで掘削する。このとき発生する充填コンクリート5の掘削物は、地上に設置されたサンドポンプで地上に吸い上げられる。   As shown in FIG. 1b, after excavating the ground 2 so that a part of the pile head of the ready-made pile 1 is exposed, and removing the concrete around and above the pile head, the pile An auger drilling machine in which the excavation head 11 is attached to the tip of the excavation rod 7 above the head is prepared. The outer diameter of the excavation head 11 is smaller than the inner diameter of the ready-made pile 1. Then, as the excavation head 11 rotates and moves downward, the excavation head 11 rotates in the horizontal direction around the center line extending in the vertical direction of the excavation head 11 and moves downward. To excavate the solidified material composed of the poorly mixed cement component as the poorly filled concrete 5 existing inside the ready-made pile 1 to the planned depth of the upper structure establishment hole 12 (see FIG. 1 c). . The excavated material of the filled concrete 5 generated at this time is sucked up to the ground by a sand pump installed on the ground.

掘削ヘッド11の外径が既製杭1の内径よりも小寸法になっていることから、掘削中においては、掘削ヘッド11が水平方向に回転しかつ直線的に下降するだけではなく、掘削ヘッド11の上下方向に延びる中心線が水平面内で円形を描くように、掘削ヘッド11が水平方向に回転しながら旋回し、掘削ヘッド11の周縁部の一部が既製杭1の内面をガイドとして接触することで、充填コンクリート5を既製杭1の内面に残存することなく撤去できる。このような掘削ヘッド11による掘削により、図1のc図に示したように、上部構造物樹立用孔12が既製杭1の内部の杭頭部に形成される。   Since the outer diameter of the excavation head 11 is smaller than the inner diameter of the ready-made pile 1, during the excavation, the excavation head 11 not only rotates in the horizontal direction and descends linearly, but also the excavation head 11 The excavation head 11 turns while rotating in the horizontal direction so that the center line extending vertically in the horizontal plane is circular, and a part of the peripheral edge of the excavation head 11 contacts the inner surface of the ready-made pile 1 as a guide. Thus, the filled concrete 5 can be removed without remaining on the inner surface of the ready-made pile 1. By excavation by such excavation head 11, an upper structure establishment hole 12 is formed in the pile head inside the ready-made pile 1 as shown in FIG.

既製杭1の内部に存在する貧配合となった充填コンクリート5は、未硬化な状態でも硬化した状態でもよい。例えば、現場の状況等から、図1のa図に示した既製杭1の充填コンクリート撤去準備作業の完了から数ヶ月後乃至1年後に、図1のb図及びc図に示した既製杭1の充填コンクリート撤去作業を実施しても、上記充填コンクリート5を除去できることが確認できた。   The impregnated filled concrete 5 existing inside the ready-made pile 1 may be in an uncured state or a cured state. For example, the ready-made pile 1 shown in FIGS. 1 b and c after several months to one year from the completion of the preparatory work for removing the filled concrete of the ready-made pile 1 shown in FIG. It was confirmed that the above-mentioned filled concrete 5 could be removed even when the filled concrete removal work was performed.

図1において、既製杭1は、1本のように図示したが、1本に限定されるものはなく、図2のc図に示したように、両端開口形の先端杭15と、先端杭15の上に同軸状に接続された両端開口形の接続杭16とから構成される。接続杭16は、1本でも複数本でも良い。接続杭16が複数本の場合、複数本の接続杭16が互いに同軸状に接続される。   In FIG. 1, the ready-made pile 1 is illustrated as one, but is not limited to one, and as shown in FIG. It is comprised from the connection pile 16 of the both ends opening type connected on 15 coaxially. One or more connecting piles 16 may be used. When there are a plurality of connection piles 16, the plurality of connection piles 16 are connected to each other coaxially.

図2を用いて、本発明を実施するための形態1に係る充填コンクリート撤去準備作業の前工程として、地盤2に既製杭1を設置するための掘削孔3が掘削され、掘削孔3に既製杭1が沈設されるまでの工程について説明する。   Using FIG. 2, as a pre-process for filling concrete removal preparatory work according to Embodiment 1 for carrying out the present invention, an excavation hole 3 for installing the ready-made pile 1 on the ground 2 is excavated, and the excavation hole 3 is ready-made. A process until the pile 1 is sunk will be described.

図2のa図において、オーガー削孔機における掘削ロッド7の下降運動と回転運動とにより、掘削ヘッド11が掘削ヘッド11の上下方向に延びる中心線を回転中心として水平方向に回転しかつ下降するのに伴って、上側の縦孔8と下側の拡大根固め孔9とからなる掘削孔3がベントナイト等の安定液の供給を受けながら地盤2が掘削される。拡大根固め孔9の底部は、既製杭1の上に構築される上部構造物の重さに耐えられる硬い地盤2としての支持層になっている。   In FIG. 2 a, the excavation head 11 rotates and descends in the horizontal direction about the center line extending in the vertical direction of the excavation head 11 by the downward movement and the rotation movement of the excavation rod 7 in the auger drilling machine. Accordingly, the ground 2 is excavated while the excavation hole 3 including the upper vertical hole 8 and the lower enlarged rooting hole 9 is supplied with a stabilizing liquid such as bentonite. The bottom of the enlarged root hole 9 is a support layer as a hard ground 2 that can withstand the weight of the upper structure constructed on the ready-made pile 1.

次に、図2のb図に示したように、拡大根固め孔9の掘削が完了後に未硬化なコンクリート4が地上から掘削ロッド7の内部を経由して拡大根固め孔9側から縦孔8へと流し込まれる。未硬化なコンクリート4の縦孔8に流し込まれる量が上昇するのに伴って、掘削ロッド7が上昇する。そして、未硬化なコンクリート4の縦孔8に流し込まれる量が計画量に達すると、未硬化なコンクリート4の縦孔8への流し込みが完了する。   Next, as shown in FIG. 2 b, after the excavation of the enlarged rooting hole 9 is completed, the uncured concrete 4 passes through the inside of the excavation rod 7 from the ground and is extended from the side of the enlarged rooting hole 9 to the vertical hole. It is poured into 8. As the amount poured into the vertical holes 8 of the uncured concrete 4 rises, the excavation rod 7 rises. When the amount poured into the vertical hole 8 of the uncured concrete 4 reaches the planned amount, the pouring of the uncured concrete 4 into the vertical hole 8 is completed.

そして、図2のc図に示したように、先端杭15及び接続杭16が自重で掘削孔3の内部における未硬化なコンクリート4に沈設された後に図示のされていない掘削ロッド等で回転を与えられて計画深度まで沈設される。先端杭15及び接続杭16からなる既製杭1の計画深度への沈設により、先端杭15が拡大根固め孔9の未硬化なコンクリート4に定着され、既製杭1の掘削孔3への沈設工程が完了する。その後、未硬化なコンクリート4が固くならないで、図1のa図に示す掘削ロッド7が未硬化なコンクリート4に挿入可能なうちに、図1のa図に示す既製杭1の充填コンクリート撤去準備作業が施工される。   Then, as shown in FIG. 2c, the tip pile 15 and the connecting pile 16 are rotated by an unillustrated excavating rod or the like after being set on the uncured concrete 4 inside the excavating hole 3 by its own weight. Given, it will be submerged to the planned depth. By laying the ready-made pile 1 composed of the tip pile 15 and the connecting pile 16 to the planned depth, the tip pile 15 is fixed to the uncured concrete 4 of the enlarged rooting hole 9 and the ready-made pile 1 is set in the excavation hole 3. Is completed. Thereafter, while the uncured concrete 4 does not become hard and the excavation rod 7 shown in FIG. 1a can be inserted into the uncured concrete 4, preparation for removing the filled concrete of the ready-made pile 1 shown in FIG. Work is performed.

以上、本発明を実施の形態を用いて説明したが、本発明の技術的範囲は前記実施の形態に記載の範囲には限定されない。前記実施の形態に、多様な変更または改良を加えることが可能であることが当業者にも明らかである。そのような変更または改良を加えた形態も本発明の技術的範囲に含まれ得ることが、特許請求の範囲から明らかである。   As mentioned above, although this invention was demonstrated using embodiment, the technical scope of this invention is not limited to the range as described in the said embodiment. It will be apparent to those skilled in the art that various modifications or improvements can be added to the embodiment. It is apparent from the claims that the embodiments added with such changes or improvements can be included in the technical scope of the present invention.

1 既製杭
1b 既製杭1の他端側
1a 既製杭1の一端側
2 地盤
4 コンクリート
5 充填コンクリート
6 水
7 掘削ロッド
8 縦孔
9 拡大根固め孔
11 掘削ヘッド
12 上部構造物樹立用孔
15 先端杭
16 接続杭
DESCRIPTION OF SYMBOLS 1 Ready-made pile 1b The other end side 1a of the ready-made pile 1 One end side 2 of the ready-made pile 1 Ground 4 Concrete 5 Filled concrete 6 Water 7 Drilling rod 8 Vertical hole 9 Expansion rooting hole 11 Drilling head 12 Upper structure establishment hole 15 Tip Pile 16 Connection pile

Claims (4)

既製杭の上部に構築するコンクリート構造物の一部を中詰めコンクリートとして既製杭内にも打設するための上部構造物樹立用孔を既製杭の内部の杭頭部に形成するために、地盤に掘削された掘削孔に流し込まれた未硬化なコンクリートの中に両端開口形の既製杭を一端側から沈設し、この沈設により既製杭内に充填された未硬化な充填コンクリートが除去可能な貧配合のセメント成分からなる固化物となるように当該既製杭の他端側から水を上記既製杭内に充填された未硬化な充填コンクリートに注入し、この水の注入で貧配合となったセメント成分からなる固化物を既製杭の杭頭部から除去することを特徴とする既製杭の杭頭部における固化物の撤去方法。   In order to form a hole in the pile head inside the ready-made pile to form a hole for setting up the upper structure for placing a part of the concrete structure built on the upper part of the ready-made pile into the ready-made pile as filled concrete, In the unhardened concrete poured into the excavation hole drilled in, a pre-made pile with open ends is submerged from one end side, and this pre-installation can remove the unhardened filled concrete filled in the pre-made pile Cement that is poorly blended by injecting water into the uncured filled concrete filled in the prefabricated pile from the other end of the prefabricated pile so that it becomes a solidified product composed of the blended cement component The removal method of the solidified material in the pile head of a ready-made pile characterized by removing the solidified material which consists of a component from the pile head of a ready-made pile. 上記既製杭内に充填された未硬化な充填コンクリートに注入する場合に掘削ロッドで行うことを特徴とする請求項1記載の既製杭の杭頭部における固化物の撤去方法。   The method for removing a solidified product from a pile head of a prefabricated pile according to claim 1, wherein the excavation rod is used when pouring the uncured filled concrete filled in the prefabricated pile. 上記既製杭内に充填された未硬化な充填コンクリートに水を注入する場合に中詰めコンクリートを打設する位置まで上記水を注入することを特徴とする請求項1又は請求項2に記載の既製杭の杭頭部における固化物の撤去方法。   3. The ready-made article according to claim 1, wherein when water is poured into uncured filled concrete filled in the ready-made pile, the water is poured up to a position at which intermediate-filled concrete is placed. Method of removing solidified material from the pile head. 上記貧配合のセメント成分からなる固化物の除去をオーガー削孔機で行うことを特徴とする請求項1乃至請求項3のいずれかに記載の既製杭の杭頭部における固化物の撤去方法。   The removal method of the solidified substance in the pile head of the ready-made pile in any one of the Claims 1 thru | or 3 which removes the solidified substance which consists of the said poor mixing | blending cement component with an auger drilling machine.
JP2016060311A 2016-03-24 2016-03-24 Removal method of solidified material from pile head of ready-made pile Active JP6656972B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016060311A JP6656972B2 (en) 2016-03-24 2016-03-24 Removal method of solidified material from pile head of ready-made pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016060311A JP6656972B2 (en) 2016-03-24 2016-03-24 Removal method of solidified material from pile head of ready-made pile

Publications (2)

Publication Number Publication Date
JP2017172247A true JP2017172247A (en) 2017-09-28
JP6656972B2 JP6656972B2 (en) 2020-03-04

Family

ID=59970613

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016060311A Active JP6656972B2 (en) 2016-03-24 2016-03-24 Removal method of solidified material from pile head of ready-made pile

Country Status (1)

Country Link
JP (1) JP6656972B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241817A (en) * 2019-06-28 2019-09-17 重庆渝高科技产业(集团)股份有限公司 A kind of impaired after-construction method of the friction pile stake holes of emergency repair engineering

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58168720A (en) * 1982-03-31 1983-10-05 Shimizu Constr Co Ltd Treatment of head of on-site pile
JPS6250517A (en) * 1985-08-29 1987-03-05 Asahi Chem Ind Co Ltd Method and apparatus for construction of ready-made hollow pile
JPS63197715A (en) * 1987-02-12 1988-08-16 Mitsui Constr Co Ltd Device for treating extra-concrete banking of cast-in-place pile
JPH04108910A (en) * 1990-08-28 1992-04-09 Daido Concrete Kogyo Kk Method for processing pile head of sunk concrete pile
US5320453A (en) * 1991-04-11 1994-06-14 Roger Bullivant Of Texas, Inc. Composite sectional concrete piles
JPH11193524A (en) * 1997-12-26 1999-07-21 Kankyo Create:Kk Treatment method and agent for existing concrete pile head
JP2000240070A (en) * 1999-02-24 2000-09-05 Aizawa Koatsu Concrete Kk Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section
JP2002115249A (en) * 2000-10-12 2002-04-19 Geotop Corp Device and method for treating pile head

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58168720A (en) * 1982-03-31 1983-10-05 Shimizu Constr Co Ltd Treatment of head of on-site pile
JPS6250517A (en) * 1985-08-29 1987-03-05 Asahi Chem Ind Co Ltd Method and apparatus for construction of ready-made hollow pile
JPS63197715A (en) * 1987-02-12 1988-08-16 Mitsui Constr Co Ltd Device for treating extra-concrete banking of cast-in-place pile
JPH04108910A (en) * 1990-08-28 1992-04-09 Daido Concrete Kogyo Kk Method for processing pile head of sunk concrete pile
US5320453A (en) * 1991-04-11 1994-06-14 Roger Bullivant Of Texas, Inc. Composite sectional concrete piles
JPH11193524A (en) * 1997-12-26 1999-07-21 Kankyo Create:Kk Treatment method and agent for existing concrete pile head
JP2000240070A (en) * 1999-02-24 2000-09-05 Aizawa Koatsu Concrete Kk Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section
JP2002115249A (en) * 2000-10-12 2002-04-19 Geotop Corp Device and method for treating pile head

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241817A (en) * 2019-06-28 2019-09-17 重庆渝高科技产业(集团)股份有限公司 A kind of impaired after-construction method of the friction pile stake holes of emergency repair engineering

Also Published As

Publication number Publication date
JP6656972B2 (en) 2020-03-04

Similar Documents

Publication Publication Date Title
CN111705830B (en) Pile foundation and construction method thereof
JP5202708B2 (en) Steel pipe pile and pile foundation method using the steel pipe pile
KR20110041391A (en) Pile structure
KR101840226B1 (en) The guide holes of the form for soil auger dredges
EP3318677A1 (en) Method for forming a reinforced pile and accessory for use therein
JP2015218516A (en) Construction method of foundation pile whose pile head is reinforced, foundation pile structure whose pile head is reinforced
JP5690864B2 (en) Construction method of mountain retaining wall, construction method of cast-in-place pile
KR101045625B1 (en) Construction method of retaining wall using cast-in-place pile
KR100975988B1 (en) The Method for Constructing Underwater Structure
CN108978742A (en) One kind cutting stake forced-landing tilt correcting structure, method
JP4811176B2 (en) Construction method of ready-made piles
JP2017172247A (en) Removal method of solidification object in pile head part of precast pile
US20150299976A1 (en) Method for manufacturing a pile
JP6645098B2 (en) Removal method of existing pile
JP5648085B2 (en) How to build a pile
KR101616846B1 (en) Precast concrete pile with sheath and the construction method therewith
RU2550620C1 (en) Method for construction of injection pile
JP2013155577A (en) Construction method for pile using anchor in combination
JP5634036B2 (en) Method for constructing retaining wall, method for constructing pile, retaining wall, pile
JP4872561B2 (en) Construction method of ready-made piles
CN109989415B (en) Construction method of fabricated foundation
JP2005188237A (en) Columnar ground improving device and columnar ground improving construction method
KR0148168B1 (en) Woorking method of underground foundation wall
JP2015063878A (en) Method of constructing steel pipe pile and steel pipe pile
JP4623577B2 (en) How to build cast-in-place piles

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20181120

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190827

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190830

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190926

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200204

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200205

R150 Certificate of patent or registration of utility model

Ref document number: 6656972

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250