JP2002115249A - Device and method for treating pile head - Google Patents

Device and method for treating pile head

Info

Publication number
JP2002115249A
JP2002115249A JP2000311417A JP2000311417A JP2002115249A JP 2002115249 A JP2002115249 A JP 2002115249A JP 2000311417 A JP2000311417 A JP 2000311417A JP 2000311417 A JP2000311417 A JP 2000311417A JP 2002115249 A JP2002115249 A JP 2002115249A
Authority
JP
Japan
Prior art keywords
pile head
pile
main body
head
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000311417A
Other languages
Japanese (ja)
Other versions
JP3911121B2 (en
Inventor
Reiji Takate
玲司 高手
Michinobu Sato
道信 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Geotop Corp
Original Assignee
Geotop Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Geotop Corp filed Critical Geotop Corp
Priority to JP2000311417A priority Critical patent/JP3911121B2/en
Publication of JP2002115249A publication Critical patent/JP2002115249A/en
Application granted granted Critical
Publication of JP3911121B2 publication Critical patent/JP3911121B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a device and a method for treating a pile head, enabling the formation of a pitching-of-pile hole whereinto a cage can be inserted without conducting cumbersome work for removing soil cement, etc., within a pile head part. SOLUTION: The device is provided with the lower part 11 of a main body, a pile-head contact plate 13 located on the top surface of the lower part 11 and seated on the top surface of the pile head, and the upper part 12 of the main body, which is coupled to the lower part 11. An air vent 17 is formed between the upper part 12 and the contact plate 13. A pile is sunk to a prescribed depth into the excavated hole formed with a soil cement column in such a state that the lower part 11 is inserted into the pile head part of a hollow pile by means of a pile-head treating device having a jetting means for jetting water or air from the lower part 11 toward the inner wall surface of the pile head part. Concurrently with that or after that, water or air is jetted toward the inner wall surface of the pile head part by means of the above jetting means for the purpose of removing adhesive matter.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は既製杭の沈設工にお
いて、フーチングと杭頭部とを結合するために行う、杭
頭内部の処理技術に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technique for treating the inside of a pile head for connecting a footing and a pile head in a laying operation of a ready-made pile.

【0002】[0002]

【従来の技術】既製のコンクリート杭の施工では、プレ
ボーリング工法が多く実施されている。そして、沈設さ
れた既製杭の頭部とフーチングを結合する際は、杭頭の
中空部に杭頭結合用の鉄筋カゴを挿入し、そこにコンク
リートを打設して鉄筋カゴを杭に固定し、この鉄筋カゴ
を介してフーチングと杭を連結する方法が一般的に行わ
れている。
2. Description of the Related Art In the construction of ready-made concrete piles, a pre-boring method is often used. Then, when connecting the head of the sunk ready-made pile to the footing, insert a reinforcing rod cage for connecting the pile head into the hollow part of the pile head, pour concrete there and fix the reinforcing rod cage to the pile. In general, a method of connecting a footing and a pile via the reinforcing bar is generally used.

【0003】ところで、スクリューオーガーで排土しな
がら杭孔を形成し、セメントミルクを注入した後、杭を
沈設するセメントミルク工法においては、セメントミル
ク量を抑えてコストダウンを図るために先端閉塞杭を使
用するので、杭の沈設にあたって杭中空部内にセメント
ミルクが侵入(流入)することはない。
[0003] In the cement milk method, in which a pile hole is formed while soil is removed by a screw auger, cement milk is injected, and then the pile is laid, a tip-closed pile is used to reduce the amount of cement milk and reduce costs. Since cement is used, cement milk does not enter (inflow) into the hollow portion of the pile when the pile is laid.

【0004】一方、排土量を抑える目的で、杭孔を掘削
する際に、杭孔の土壌に固化剤等の充填剤を撹拌してソ
イルセメント柱を形成し、このソイルセメント柱に杭を
沈設する工法においては、先端開放杭を使用して杭中空
部内へソイルセメントを侵入させて排土量を抑えること
が行われている。
[0004] On the other hand, when excavating a pile hole, a filler such as a solidifying agent is stirred into the soil of the pile hole to form a soil cement column. In the submersion method, soil cement is introduced into the hollow part of the pile using an open-ended pile to reduce the amount of soil removal.

【0005】そこで、杭中空部内にソイルセメントが侵
入する施工では、杭頭部内に侵入し、固化したソイルセ
メントを杭頭から所要の深さまで除去した後、鉄筋カゴ
の挿入とコンクリートの打設を行うようにしている。
[0005] Therefore, in the construction in which the soil cement penetrates into the hollow portion of the pile, the soil cement that has penetrated into the pile head and is removed from the pile head to a required depth, and then the rebar cage is inserted and the concrete is poured. To do.

【0006】しかし、杭頭部内に浸入し固化したソイル
セメントの除去は非常に困難で、機械を導入して掘削す
るなど、多くの労力と時間を要するばかりでなく、除去
が不十分な場合は杭に鉄筋カゴが固定できなくなる等の
問題があった。
[0006] However, it is very difficult to remove the soil cement that has infiltrated into the pile head and solidified. In addition, it takes a lot of labor and time to introduce and excavate a machine, and when the removal is insufficient. There was a problem that the reinforcing cage could not be fixed to the pile.

【0007】このような問題に対処するため、杭頭部内
壁へ所定長さの段ボール紙を仮着し、その内側に入った
ソイルセメントの硬化後、前記硬化物を取出す方法が提
案されている(特開平7−189243号)。
In order to cope with such a problem, there has been proposed a method in which a predetermined length of corrugated paper is temporarily attached to the inner wall of a pile head, and after the soil cement inside the pile is hardened, the hardened material is taken out. (JP-A-7-189243).

【0008】また他の発明として杭頭部の必要空間と同
一大きさの栓体を設置し、該栓体を除去する方法が提案
されている(特開平9−324423号)。
As another invention, there has been proposed a method of installing a plug having the same size as a required space of a pile head and removing the plug (Japanese Patent Application Laid-Open No. 9-324423).

【0009】更に他の発明として、杭頭部の必要空間と
同一大きさの栓体を充填する杭頭充填材が提案されてい
る(特開平10−184003号)。
As still another invention, a pile head filler for filling a plug having the same size as the required space of the pile head has been proposed (Japanese Patent Laid-Open No. Hei 10-184003).

【0010】[0010]

【発明により解決しようとする課題】前述のように、杭
頭部内へ鉄筋カゴを挿入し、更にコンクリートを打設し
て、鉄筋コンクリートとした際に、杭頭部と、鉄筋カゴ
を含む鉄筋コンクリートとを一体的に連結する為には、
杭頭部内壁にソイルセメントその他の付着物がないこと
が望ましい。
As described above, when a reinforced cage is inserted into a pile head and concrete is cast to form reinforced concrete, the pile head and the reinforced concrete including the reinforced cage are combined. In order to connect
It is desirable that there is no soil cement or other deposits on the inner wall of the pile head.

【0011】しかしながら、前記従来の各発明において
は、段ボール紙や栓体の装着状態が悪いと、杭頭部内壁
にソイルセメントが付着してしまう。このため、かかる
付着物を除去する工程が必要となり、この除去が不十分
であると構造的に問題である。
However, in each of the above-mentioned conventional inventions, if the cardboard paper or the plug is not properly attached, soil cement adheres to the inner wall of the pile head. For this reason, a step of removing such deposits is required, and if the removal is insufficient, there is a structural problem.

【0012】また、上記の栓体等を使用する方法では、
実際には、栓体の取り出しが面倒でその作業に多くの時
間と労力を要するとともに、栓体は価格が高くしかも使
い捨てとなるので、施工コストが高くなると共に、産業
廃棄物の増大を招くといった問題もあった。
[0012] In the method using the above-mentioned plug or the like,
In fact, taking out the plug is troublesome and takes a lot of time and labor for the work, and since the plug is expensive and disposable, the construction cost increases and the industrial waste increases. There were also problems.

【0013】本発明は上記の事情に鑑みなされたもの
で、特に、杭頭部内のソイルセメントの面倒な除去作業
を行うことなく、鉄筋カゴが挿入できるようにした杭頭
処理の新規な技術を提供しようとするものである。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and in particular, a novel technique for treating a pile head capable of inserting a reinforcing bar cage without performing troublesome work of removing soil cement from the pile head. It is intended to provide.

【0014】[0014]

【課題を解決するための手段】上記の目的を達成するた
めに成された本発明の構成は、以下の通りである。
The configuration of the present invention made to achieve the above object is as follows.

【0015】すなわち、本発明は、中空杭の杭頭部内に
挿入される本体下部と、本体下部の上面に位置し杭頭上
面に着座される杭頭接触板と、本体下部と連結され杭頭
接触板との間に所定の通路を形成している本体上部とを
具備する杭頭処理装置であって、前記本体下部より前記
杭頭部内壁面に向けて水又は空気を噴出させる噴出手段
を有することを特徴とする杭頭処理装置である。
That is, the present invention provides a lower part of a main body inserted into a pile head of a hollow pile, a pile head contact plate located on the upper surface of the lower part of the main body and seated on the upper surface of the pile head, and a pile connected to the lower part of the main body. A pile head processing device comprising: a main body upper part forming a predetermined passage between the head body and a head contact plate; and a jetting means for jetting water or air from the lower part of the main body toward the inner wall surface of the pile head. It is a pile head processing device characterized by having.

【0016】上記本発明の杭頭処理装置においては、前
記杭頭接触板の下面に緩衝材が設けられ、且つ、前記本
体上部に重錘が設けられていること、あるいは、前記杭
頭接触板は、前記中空杭の頭部に設けられる嵌合部材に
嵌合せしめる嵌合手段を有し、且つ、前記本体上部に回
転圧入用の回転手段が設けられていること、が好まし
い。
In the pile head processing apparatus of the present invention, a cushioning material is provided on a lower surface of the pile head contact plate and a weight is provided on an upper portion of the main body, or the pile head contact plate is provided. It is preferable that the body has a fitting means for fitting to a fitting member provided on the head of the hollow pile, and a rotating means for rotary press fitting is provided on the upper part of the main body.

【0017】また、本発明は、上記本発明の杭頭処理装
置を用いて杭頭の処理を行う方法であって、掘削孔に所
定の充填液を注入して土壌と撹拌しソイルセメント柱を
形成した後、この掘削孔内に、中空杭の杭頭部内へ前記
本体下部を挿入した状態で所定深度まで杭を沈設すると
共に、もしくは沈設した後、前記噴出手段より前記杭頭
部内壁面に向けて水又は空気を噴出させる付着物除去工
程を有することを特徴とする杭頭処理方法である。
The present invention also relates to a method for treating a pile head using the pile head treatment apparatus according to the present invention, wherein a predetermined filling liquid is injected into a drilling hole and agitated with soil to form a soil cement column. After forming the pile, the pile is sunk to a predetermined depth in a state where the lower part of the main body is inserted into the pile head of the hollow pile, or after the sunk, The method according to claim 1, further comprising a deposit removing step of ejecting water or air toward the pile head.

【0018】上記本発明の杭頭処理方法においては、前
記付着物除去工程の後に、前記本体下部を杭頭より引き
抜き、杭頭上面をキャップ材で覆うこと、が好ましい。
In the pile head treatment method of the present invention, it is preferable that after the adhering matter removing step, the lower part of the main body is pulled out from the pile head and the upper surface of the pile head is covered with a cap material.

【0019】本発明によれば、中空杭の杭頭部内に挿入
された本体下部から杭頭部内壁面に向かって水又は空気
を噴出させることにより、杭頭中空部内に付着したソイ
ルセメント等を除去することができ、面倒なこれらの除
去作業を行うことなく、鉄筋カゴを挿入できる穴を形成
することのできるものである。
According to the present invention, water cement or the like adhered in the hollow portion of the pile head by ejecting water or air from the lower portion of the main body inserted into the pile head of the hollow pile toward the inner wall surface of the pile head. Can be formed, and a hole into which a reinforcing bar cage can be inserted can be formed without performing troublesome removal operations.

【0020】[0020]

【発明の実施の形態】以下、本発明の実施の形態例を説
明するが、本発明はこれらの形態例に限定されるもので
はなく、本発明の要旨の範囲内で適宜設計変更し得るも
のである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below, but the present invention is not limited to these embodiments, and can be appropriately designed and modified within the scope of the present invention. It is.

【0021】図1は、本発明の杭頭処理装置の一構成例
を示したものである。
FIG. 1 shows an example of a configuration of a pile head processing apparatus according to the present invention.

【0022】本例の杭頭処理装置10は、基本的な構成
として、中空杭の杭頭部内に挿入される本体下部11
と、杭頭上面に着座される杭頭接触板13と、本体下部
11と連結され杭頭接触板13との間に所定の通路(排
出口)17を形成している本体上部12と、本体下部1
1より杭頭部内壁面に向かって水又は空気を噴出させる
噴出手段を有している。
The pile head processing apparatus 10 of the present embodiment has a basic configuration in which a lower part 11 of a main body is inserted into a pile head of a hollow pile.
A pile head contact plate 13 seated on a pile head upper surface, a main body upper portion 12 connected to the main body lower portion 11 and forming a predetermined passage (discharge port) 17 between the pile head contact plate 13, Lower 1
1 has jetting means for jetting water or air toward the inner wall surface of the pile head.

【0023】本例における噴出手段は、注入管14、注
入口15および噴出口16によって構成されており、本
体上部12に取付けた注入管14は、本体下部11の内
面中空部を通して噴出口16に接続してある。したがっ
て、この噴出手段は、注入口15から水または圧縮空気
を送り込み、噴出口16から噴出させることにより、杭
頭部内面に付着したソイルセメント等を除去することが
できる。
The jetting means in this embodiment is composed of an injection pipe 14, an injection port 15 and an injection port 16. The injection pipe 14 attached to the upper part 12 of the main body is connected to the injection port 16 through the inner hollow portion of the lower part 11 of the main body. Connected. Therefore, this jetting means can remove soil cement or the like attached to the inner surface of the pile head by sending water or compressed air from the injection port 15 and jetting it out from the jet port 16.

【0024】また、本発明の杭頭処理方法は、杭孔を掘
削する際に、杭孔の土壌に固化剤等の充填剤を撹拌して
ソイルセメント柱を形成し、このソイルセメント柱に杭
を沈設する工法を対象として行われる。かかる工法にお
いては、施工の仕様により、杭頭を施工基盤(GL)よ
り下方に位置させる場合と、杭頭を施工基盤より少し上
方に位置させる場合とがある。
Further, in the pile head treatment method of the present invention, when excavating a pile hole, a filler such as a solidifying agent is stirred into the soil of the pile hole to form a soil cement column. It is performed for the construction method of submerging. In such a construction method, there are a case where the pile head is located below the construction base (GL) and a case where the pile head is located slightly above the construction base depending on the construction specifications.

【0025】図5(a)〜(d)は、図1に示したような本
発明の杭頭処理装置を用い、杭頭を施工基盤より下方に
位置させる場合における本発明による杭頭処理方法の施
工の態様を順次示したものである。
FIGS. 5 (a) to 5 (d) show a pile head processing method according to the present invention in a case where the pile head is located below the construction base using the pile head processing apparatus of the present invention as shown in FIG. Are sequentially shown.

【0026】以下、本発明の一実施形態例の詳細をこれ
らの図面を参照して説明する。
The details of one embodiment of the present invention will be described below with reference to these drawings.

【0027】既製杭の沈設工においては、先ず、図5
(a)に示すように、杭孔の土壌に固化剤等の充填剤を
撹拌してソイルセメント(ソイルセメント柱)102が
形成された掘削孔内に、中空杭(既製杭)101を建て
込み、杭頭が地上に見える位置で本発明の杭頭処理装置
10をセットする。具体的には、本体下部11を杭中空
部に挿入し、杭頭上面に杭頭接触板13を着座させる。
In the submerging of a ready-made pile, first, FIG.
As shown in (a), a filler such as a solidifying agent is agitated in the soil of a pile hole, and a hollow pile (ready-made pile) 101 is built in an excavation hole in which a soil cement (soil cement column) 102 is formed. The pile head processing device 10 of the present invention is set at a position where the pile head can be seen on the ground. Specifically, the lower part 11 of the main body is inserted into the hollow part of the pile, and the pile head contact plate 13 is seated on the upper surface of the pile head.

【0028】本体下部11は、これを杭頭部に挿入した
際、その中空杭101の内周との間に、ソイルセメント
が流通できる程度の狭い間隙が生じる外径とし、また、
その長さは、後述の鉄筋カゴ106(図5(d)参照)
を挿入するに足る十分な長さである。
The lower body 11 has an outer diameter that, when it is inserted into the pile head, forms a narrow gap with the inner periphery of the hollow pile 101 such that soil cement can flow therethrough.
The length is the rebar basket 106 described later (see FIG. 5D).
Is long enough to insert the

【0029】本体下部11の外径は、具体的には中空杭
101の内径よりも5〜10cm程度小さくなってお
り、本体下部11を杭中空部に挿入すると、中空杭10
1の内壁面との隙間をソイルセメント102が上昇し
て、杭頭接触板13と本体上部12との隙間(即ち、通
路17)から矢印のように排出される。このため、本体
下部11の挿入作業を簡単に行うことができる。特に、
本例の杭頭処理装置10の本体下部11の下端には、先
細り形状の案内板18が設けられているため、この挿入
作業を極めて簡単に行うことができる。
The outer diameter of the lower body 11 is specifically smaller than the inner diameter of the hollow pile 101 by about 5 to 10 cm.
The soil cement 102 rises in the gap between the pile head 1 and the inner wall surface, and is discharged from the gap (that is, the passage 17) between the pile head contact plate 13 and the main body upper part 12 as shown by the arrow. For this reason, the insertion work of the main body lower part 11 can be easily performed. In particular,
Since the tapered guide plate 18 is provided at the lower end of the main body lower portion 11 of the pile head treatment device 10 of this example, this insertion operation can be performed extremely easily.

【0030】また、杭頭処理装置10の本体下部11を
杭中空部に挿入する際、予め設置した控え芯(逃げ芯)
と本体上部12の外面との距離を測定し、ズレがあれ
ば、装置10を前後左右に動かすことによって、杭芯合
わせを容易に行うこともできる。
Also, when inserting the lower body 11 of the pile head treatment device 10 into the hollow portion of the pile, a retaining core (relief core) that has been installed in advance.
By measuring the distance between the main body 12 and the outer surface of the main body upper part 12, if there is a deviation, the pile core can be easily aligned by moving the device 10 back and forth and right and left.

【0031】次に、図5(b)に示すように、中空杭1
01の杭頭部内へ本体下部11を挿入した状態で所定深
度まで中空杭101を沈設する。
Next, as shown in FIG.
The hollow pile 101 is sunk to a predetermined depth with the main body lower part 11 inserted into the pile head No. 01.

【0032】本発明においては、この中空杭101を沈
設する際、もしくは沈設した後、前記噴出手段より杭頭
部内壁面に向かって水又は空気を噴出させる付着物除去
工程を行う。
In the present invention, when the hollow pile 101 is laid or after the hollow pile 101 is laid, an adhering matter removing step of jetting water or air toward the inner wall surface of the pile head from the jetting means is performed.

【0033】具体的には、例えば杭頭処理装置10が装
着された中空杭101を沈設する際に、注入口15から
水を送り込み、噴出口16から杭頭部内壁面に向けて噴
出させ、この後さらに水を噴出させながら噴出口16が
中空杭101の上端部近傍に達するまで杭頭処理装置1
0を持ち上げ、この後再度図5(b)の状態まで杭頭処
理装置10を降下させる。これにより、杭頭部内壁面に
付着したソイルセメント等が剥離され、杭頭処理装置1
0の降下に伴って通路17より排出することができる。
尚、杭頭処理装置全体を持ち上げる際には、本体上部1
2に取り付けられている吊り環19にワイヤー等を接続
して行うことができる。
Specifically, for example, when the hollow pile 101 on which the pile head treatment device 10 is mounted is laid, water is fed from the injection port 15 and jetted from the jet port 16 toward the inner wall surface of the pile head. Thereafter, the pile head treatment device 1 is further ejected with water until the ejection port 16 reaches near the upper end of the hollow pile 101.
Then, the pile head processing device 10 is lowered again to the state shown in FIG. As a result, soil cement and the like adhering to the inner wall surface of the pile head are peeled off, and the pile head treatment device 1
It can be discharged from the passage 17 with the descent of zero.
In addition, when lifting the entire pile head treatment device,
A wire or the like can be connected to the suspension ring 19 attached to the second member 2.

【0034】本発明においては、上記杭頭処理装置10
の上げ下げを複数回行うこともできる。また、特に最後
の杭頭処理装置10の下降時には、水に代えて圧縮空気
を噴出口16より噴出させることにより、杭頭中空部に
残留する水を最小限に抑えると共に、杭頭部内面に付着
したソイルセメント等をより効率良く通路17より排出
することができるため、好ましい。。
In the present invention, the pile head treatment device 10
Can be raised and lowered multiple times. In addition, when the last pile head treatment device 10 descends, compressed air is spouted from the jet port 16 instead of water to minimize water remaining in the hollow portion of the pile head and to reduce the amount of water remaining inside the pile head. This is preferable because the attached soil cement and the like can be more efficiently discharged from the passage 17. .

【0035】上記の付着物除去工程において使用する水
および圧縮空気は、既製杭101の内径や本体下部11
の外径にもよるが、水の場合であれば例えば1×106
〜2×106Pa(Gauge)程度の圧力で毎分15
0〜300リットル程度供給するのが好ましく、圧縮空
気の場合であれば例えば5×105〜1×106Pa(G
auge)程度の圧力で毎分3〜10m3程度供給する
のが好ましい。
The water and compressed air used in the adhering matter removing step are the inner diameter of the ready-made pile 101 and the lower part 11 of the main body.
In the case of water, it depends, for example, on 1 × 10 6
15 minutes per minute at a pressure of about 2 × 10 6 Pa (Gauge).
It is preferable to supply about 0 to 300 liters. In the case of compressed air, for example, 5 × 10 5 to 1 × 10 6 Pa (G
Preferably, the pressure is about 3 to 10 m 3 per minute at a pressure of about aug.

【0036】本例のように杭頭を施工基盤(GL)より
下方に位置させる場合には、図5(c)に示すように、
中空杭101から杭頭処理装置10を引き上げた後、杭
頭部にパイルキャップ(キャップ材)104を被せるこ
とが好ましい。これにより、次工程における地表面の掘
削時に鉄筋カゴの建込穴103に掘削土が侵入するのを
防止することができ、建込穴103を良好な状態に保持
することができる。尚、このパイルキャップ104の装
着は、地表から投入して簡単に行うことができる。
When the pile head is located below the construction base (GL) as in this example, as shown in FIG.
After lifting the pile head processing apparatus 10 from the hollow pile 101, it is preferable to put a pile cap (cap material) 104 on the pile head. Thereby, it is possible to prevent excavated soil from entering the building hole 103 of the rebar cage at the time of excavating the ground surface in the next process, and it is possible to maintain the building hole 103 in a good state. The mounting of the pile cap 104 can be easily performed by throwing it from the ground surface.

【0037】このパイルキャップ104としては、この
上に土砂が落下した場合にも変形しないものが用いら
れ、例えばブリキ等の金属製や樹脂製のもの等を用いる
ことができる。
As the pile cap 104, one that does not deform even when earth and sand falls thereon is used. For example, a metal or resin material such as tin can be used.

【0038】次に、図5(d)に示すように、ソイルセ
メント102が硬化した後、地表部を掘削して杭頭を露
出させ、パイルキャップ104を回収し、必要に応じて
捨てコンクリート105を打設すると共に、建込穴10
3に鉄筋カゴ106を配設する。この後は、所定の配筋
を行った後、コンクリートを打設して鉄筋カゴ106と
既製杭101を結合し、既製杭101を鉄筋カゴ106
を介してフーチング(不図示)と一体的に施工する。
Next, as shown in FIG. 5 (d), after the soil cement 102 has hardened, the surface of the ground is excavated to expose the pile head, the pile cap 104 is collected, and if necessary, the concrete 105 is discarded. And a hole 10
3 is provided with a reinforcing bar cage 106. After that, after a predetermined reinforcing arrangement is made, concrete is cast and the reinforcing bar 106 and the ready-made pile 101 are joined, and the ready-made pile 101 is
And is integrated with a footing (not shown).

【0039】このように、本発明によれば、既製杭(中
空杭)101の杭頭部内に挿入された本体下部11から
杭頭部内壁面に向かって水又は空気を噴出させることに
より、杭頭中空部内に付着したソイルセメント等を極め
て効率良くほぼ完全に除去することができる。従って、
これにより形成された建込穴103は極めて良好な状態
となっており、面倒なソイルセメント等の除去作業を行
うことなく、鉄筋カゴを挿入することができると共に、
既製杭101とフーチングは一体性の高い構造とするこ
とができる。
As described above, according to the present invention, water or air is blown out from the lower part 11 of the main body inserted into the pile head of the ready-made pile (hollow pile) 101 toward the inner wall surface of the pile head. Soil cement and the like adhering to the pile head hollow can be almost completely removed with high efficiency. Therefore,
The building hole 103 thus formed is in an extremely good state, and the reinforcing cage can be inserted without performing troublesome work of removing soil cement and the like,
The ready-made pile 101 and the footing can have a highly integrated structure.

【0040】次に、本発明の杭頭処理装置の別の形態例
を説明する。図2及び図3は、本発明の杭頭処理装置の
別の構成例を示したものである。
Next, another embodiment of the pile head treatment apparatus of the present invention will be described. 2 and 3 show another example of the configuration of the pile head treatment device of the present invention.

【0041】図2に示した杭頭処理装置20は、杭頭接
触板13の下面に緩衝材21を設け、且つ、本体上部1
2の中空部に重錘22を挿入してある点を除けば、図1
に示した杭頭処理装置10と基本的な構成は同じであ
る。
In the pile head treatment device 20 shown in FIG. 2, a cushioning material 21 is provided on the lower surface of the pile
1 except that the weight 22 is inserted into the hollow portion of FIG.
Is basically the same as the pile head processing apparatus 10 shown in FIG.

【0042】この杭頭処理装置20を用いた場合には、
前述した中空杭101の杭頭部内へ本体下部11を挿入
した状態で所定深度まで中空杭101を沈設する際(図
5(b)参照)、重錘22の上部に取り付けられている
吊り環23にワイヤー等を接続し、重錘22を持ち上げ
て落下させることで簡単に行うことができる。尚、杭頭
処理装置全体を持ち上げる際には、本体上部12に取り
付けられている吊り環24にワイヤー等を接続して行う
ことができる。
When this pile head processing device 20 is used,
When the hollow pile 101 is sunk to a predetermined depth with the lower body 11 inserted into the pile head of the hollow pile 101 described above (see FIG. 5B), a suspension ring attached to the upper part of the weight 22. This can be easily performed by connecting a wire or the like to 23, lifting the weight 22 and dropping it. In addition, when lifting the entire pile head processing apparatus, a wire or the like can be connected to the suspension ring 24 attached to the main body upper part 12.

【0043】図3に示した杭頭処理装置30は、杭頭接
触板13に中空杭の頭部に固定して設けられる嵌合部材
に嵌合せしめる嵌合手段31を有し、且つ、本体上部1
2に回転圧入用の六角フランジからなる回転手段32が
設けられている点を除けば、図1に示した杭頭処理装置
10と基本的な構成は同じである。
The pile head processing apparatus 30 shown in FIG. 3 has a fitting means 31 for fitting a fitting member fixed to the head of the hollow pile on the pile head contact plate 13 and has a main body. Top one
The basic configuration is the same as that of the pile head processing apparatus 10 shown in FIG. 1 except that a rotating means 32 composed of a hexagonal flange for rotary press-fitting is provided in 2.

【0044】この嵌合手段31は、杭頭部を収容できる
キャップ状のものであり、所定形状の嵌合用切欠部31
aが形成されているものである。中空杭の頭部との嵌合
は具体的には、例えば図4(a)に示すような嵌合部材
41が頭部に固定された中空杭40に対して、図4
(b)に示すように、嵌合手段31の嵌合用切欠部31
a内に嵌合部材41を収容させて行う。そして、本体上
部12に設けられている六角フランジからなる回転手段
32をオーガーマシンに連結して所定方向に回転させる
ことにより、上下動を行うことができる。
The fitting means 31 is a cap-shaped one capable of accommodating the pile head, and has a fitting notch 31 of a predetermined shape.
a is formed. Specifically, the fitting of the hollow pile with the head is performed, for example, on a hollow pile 40 having a fitting member 41 fixed to the head as shown in FIG.
As shown in (b), the notch 31 for fitting of the fitting means 31
This is performed while the fitting member 41 is accommodated in a. The rotating means 32 formed of a hexagonal flange provided on the upper part 12 of the main body is connected to the auger machine and rotated in a predetermined direction, so that it can be moved up and down.

【0045】尚、図2及び図3に示した杭頭処理装置で
は、本体下部11の周囲に複数の板状のスペーサ11a
を所定の間隔で設け、これらのスペーサ11aの間にそ
れぞれ噴出口16を設けている。このような構成によれ
ば、中空杭内に本体下部11が偏心した状態で挿入され
たとしても、中空杭の内周との間にソイルセメントが流
通できる間隙を確実に形成することができると共に、各
噴出口16から確実に水および空気を噴出させることが
でき、杭頭中空部内に付着した周辺固定液をより一層効
率良く除去することができる。
In the pile head treatment apparatus shown in FIGS. 2 and 3, a plurality of plate-like spacers 11a
Are provided at predetermined intervals, and a jet port 16 is provided between these spacers 11a. According to such a configuration, even if the main body lower part 11 is inserted eccentrically into the hollow pile, a gap through which soil cement can flow can be reliably formed between the hollow pile and the inner periphery of the hollow pile. Thus, water and air can be reliably ejected from each ejection port 16, and the peripheral fixation liquid attached to the pile head hollow portion can be more efficiently removed.

【0046】また、以上説明した杭頭処理装置では、本
体下部11の下端近傍にのみ噴出口16を設けている
が、例えば本体下部11の中間部にも噴出口16を設け
た場合には、噴出口16から水又は空気を噴出させなが
ら杭頭処理装置の上げ下げを行う際に、そのストローク
を短くすることができる。さらに、噴出口16から噴射
される水又は空気の向きが所望の方向(例えば杭頭部内
面に斜め上向き若しくは斜め下向き)になるように、噴
出口16の構造を適宜設計することもできる。
Further, in the pile head treatment apparatus described above, the spout 16 is provided only near the lower end of the lower body 11, but for example, when the spout 16 is also provided in the middle of the lower body 11, When raising or lowering the pile head treatment device while ejecting water or air from the ejection port 16, the stroke can be shortened. Furthermore, the structure of the spout 16 can be appropriately designed so that the direction of water or air jetted from the spout 16 is in a desired direction (for example, obliquely upward or obliquely downward on the inner surface of the pile head).

【0047】[0047]

【発明の効果】以上説明したように、本発明によれば、
既製杭(中空杭)の杭頭部内に挿入された本体下部から
杭頭部内壁面に向かって水又は空気を噴出させることに
より、杭頭中空部内に付着したソイルセメント等を極め
て効率良くほぼ完全に除去することができるため、面倒
なソイルセメント等の除去作業を行うことなく、建込穴
に鉄筋カゴを挿入することができると共に、既製杭とフ
ーチングは一体性の高い構造を容易に実現することがで
きる。
As described above, according to the present invention,
By spouting water or air from the lower part of the main body inserted into the pile head of the ready-made pile (hollow pile) toward the inner wall surface of the pile head, soil cement and the like attached to the hollow part of the pile head can be almost efficiently removed. Since it can be completely removed, a reinforced cage can be inserted into the mounting hole without performing troublesome work such as removing soil cement, etc., and the ready-made pile and footing can easily realize a highly integrated structure can do.

【0048】また、従来用いられていた栓体等は反復し
て使用することができず、使い捨てとなるので、施工コ
ストが高くなると共に、産業廃棄物の増大を招いていた
が、本発明によればこのような産業廃棄物が発生せず、
環境にも優しくコスト的にも有利な工法が実現される。
The plugs and the like conventionally used cannot be used repeatedly and are disposable, so that the construction cost is increased and the industrial waste is increased. According to this, no such industrial waste is generated,
An environment-friendly and cost-effective construction method is realized.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の杭頭処理装置の一構成例を示した図で
ある。
FIG. 1 is a diagram showing an example of a configuration of a pile head processing device of the present invention.

【図2】本発明の杭頭処理装置の別の構成例を示した図
である。
FIG. 2 is a diagram showing another example of the configuration of the pile head treatment device of the present invention.

【図3】本発明の杭頭処理装置の別の構成例を示した図
である。
FIG. 3 is a diagram showing another example of the configuration of the pile head treatment device of the present invention.

【図4】図3の杭頭処理装置の嵌合手段を説明するため
の図である。
FIG. 4 is a view for explaining a fitting means of the pile head processing device of FIG. 3;

【図5】図1の杭頭処理装置を用い、杭頭を施工基盤よ
り下方に位置させる場合における本発明による杭頭処理
方法の施工の態様を順次示した図である。
FIG. 5 is a view sequentially showing the construction mode of the pile head processing method according to the present invention when the pile head is positioned below the construction base using the pile head processing apparatus of FIG. 1;

【符号の説明】[Explanation of symbols]

10、20、30 杭頭処理装置 11 本体下部 11a スペーサ 12 本体上部 13 杭頭接触板 14 注入管 15 注入口 16 噴出口 17 通路 18 案内板 19 本体上部に取り付けられた吊り環 21 緩衝部材 22 重錘 23 重錘に取り付けられた吊り環 24 本体上部に取り付けられた吊り環 31 嵌合手段 31a 嵌合用切欠部 32 回転手段 40 中空杭 41 嵌合部材 101 既製杭(中空杭) 102 ソイルセメント(ソイルセメント柱) 103 建込穴 104 パイルキャップ104 105 捨てコンクリート 106 鉄筋カゴ 10, 20, 30 Pile head treatment device 11 Lower body 11a Spacer 12 Upper body 13 Pile head contact plate 14 Injection pipe 15 Inlet 16 Spout port 17 Passage 18 Guide plate 19 Suspension ring attached to upper body 21 Buffer member 22 Weight Weight 23 Suspension ring attached to the weight 24 Suspension ring attached to the upper part of the main body 31 Fitting means 31a Notch for fitting 32 Rotating means 40 Hollow pile 41 Fitting member 101 Ready-made pile (hollow pile) 102 Soil cement (Soil) Cement column) 103 Building hole 104 Pile cap 104 105 Discarded concrete 106 Reinforced basket

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 中空杭の杭頭部内に挿入される本体下部
と、本体下部の上面に位置し杭頭上面に着座される杭頭
接触板と、本体下部と連結され杭頭接触板との間に所定
の通路を形成している本体上部とを具備する杭頭処理装
置であって、 前記本体下部より前記杭頭部内壁面に向けて水又は空気
を噴出させる噴出手段を有することを特徴とする杭頭処
理装置。
1. A lower part of a main body inserted into a pile head of a hollow pile, a pile head contact plate located on an upper surface of the lower part of the body and seated on an upper surface of the pile head, and a pile head contact plate connected to the lower part of the main body. And a main body upper part forming a predetermined passage between the main body and a pile head processing device, comprising a jetting means for jetting water or air from the lower part of the main body toward the inner wall surface of the pile head. Characteristic pile head processing equipment.
【請求項2】 前記杭頭接触板の下面に緩衝材が設けら
れ、且つ、前記本体上部に重錘が設けられていることを
特徴とする請求項1に記載の杭頭処理装置。
2. The pile head treatment apparatus according to claim 1, wherein a cushioning material is provided on a lower surface of the pile head contact plate, and a weight is provided on an upper portion of the main body.
【請求項3】 前記杭頭接触板は、前記中空杭の頭部に
設けられる嵌合部材に嵌合せしめる嵌合手段を有し、且
つ、前記本体上部に回転圧入用の回転手段が設けられて
いることを特徴とする請求項1に記載の杭頭処理装置。
3. The pile head contact plate has a fitting means for fitting to a fitting member provided on a head of the hollow pile, and a rotating means for rotary press fitting is provided on an upper part of the main body. The pile head treatment device according to claim 1, wherein
【請求項4】 請求項1乃至3のいずれかに記載の杭頭
処理装置を用いて杭頭の処理を行う方法であって、 掘削孔に所定の充填液を注入して土壌と撹拌しソイルセ
メント柱を形成した後、この掘削孔内に、中空杭の杭頭
部内へ前記本体下部を挿入した状態で所定深度まで杭を
沈設すると共に、もしくは沈設した後、前記噴出手段よ
り前記杭頭部内壁面に向けて水又は空気を噴出させる付
着物除去工程を有することを特徴とする杭頭処理方法。
4. A method for treating a pile head using the pile head treatment device according to claim 1, wherein a predetermined filling liquid is injected into a drilling hole, agitated with soil, and a soil is removed. After the cement pillar is formed, the pile is sunk to a predetermined depth in a state where the lower part of the main body is inserted into the stake head of the hollow stake, or after the sunk, A pile head treatment method, comprising: an adhering matter removing step of jetting water or air toward an inner wall surface.
【請求項5】 前記付着物除去工程の後に、前記本体下
部を杭頭より引き抜き、杭頭上面をキャップ材で覆うこ
とを特徴とする請求項4に記載の杭頭処理方法。
5. The pile head treatment method according to claim 4, wherein after the adhering matter removing step, the lower portion of the main body is pulled out from the pile head, and the upper surface of the pile head is covered with a cap material.
JP2000311417A 2000-10-12 2000-10-12 Pile head processing apparatus and pile head processing method Expired - Fee Related JP3911121B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000311417A JP3911121B2 (en) 2000-10-12 2000-10-12 Pile head processing apparatus and pile head processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000311417A JP3911121B2 (en) 2000-10-12 2000-10-12 Pile head processing apparatus and pile head processing method

Publications (2)

Publication Number Publication Date
JP2002115249A true JP2002115249A (en) 2002-04-19
JP3911121B2 JP3911121B2 (en) 2007-05-09

Family

ID=18791182

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000311417A Expired - Fee Related JP3911121B2 (en) 2000-10-12 2000-10-12 Pile head processing apparatus and pile head processing method

Country Status (1)

Country Link
JP (1) JP3911121B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733380A (en) * 2012-06-17 2012-10-17 张永忠 Lag pile and construction method thereof
KR101924494B1 (en) * 2009-07-22 2018-12-04 오더블유이씨 타워 에이에스 Method and device for controlling transmission of power between a structure and its base during installation
CN115198750A (en) * 2022-06-21 2022-10-18 中交二公局铁路建设有限公司 Cast-in-place pile head blocking and cutting device and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101924494B1 (en) * 2009-07-22 2018-12-04 오더블유이씨 타워 에이에스 Method and device for controlling transmission of power between a structure and its base during installation
CN102733380A (en) * 2012-06-17 2012-10-17 张永忠 Lag pile and construction method thereof
CN115198750A (en) * 2022-06-21 2022-10-18 中交二公局铁路建设有限公司 Cast-in-place pile head blocking and cutting device and method
CN115198750B (en) * 2022-06-21 2023-09-19 中交二公局铁路建设有限公司 Cast-in-place pile head blocking and cutting device and method

Also Published As

Publication number Publication date
JP3911121B2 (en) 2007-05-09

Similar Documents

Publication Publication Date Title
JPH0791930B2 (en) Underground drilling machine cement soil equipment
JP3049527B2 (en) Ground improvement method and its equipment
JP2002115249A (en) Device and method for treating pile head
JP2863487B2 (en) Pile pull-out method and device
CN113356190B (en) Pile forming method for cast-in-place pile in karst development area
JPS6354093B2 (en)
JP2006322190A (en) Pile head processing method of cast-in-place concrete pile and concrete processing agent mixing device
JPH1150451A (en) Method and device for removing pile head extra-banking part concrete
JPH073054B2 (en) Foundation pile construction method
JP2000273900A (en) Air suction type soil discharge device and construction method
JP3973401B2 (en) Ground compaction method
JP3005741B2 (en) Ground improvement method
JP3047330U (en) Sheet pile driving equipment
JPH10131172A (en) Soil improvement method
JPH02289719A (en) Press-in method of concrete sheet pile
JP2697693B2 (en) Sheet pile driving method
JPH02492B2 (en)
JP2002275884A (en) Soft ground improving method and pile constructing device
JP2001336147A (en) Rotary cap with pile top treatment function, pile top treatment method, and embedding method of pile
JPH0224419A (en) Simultaneous backfilling with pile drawing, and pile drawer
JP3470954B2 (en) Method of laying interruption of manhole to existing buried pipe
JP2005200977A (en) Pile extracting method and pile extraction assisting device
JPH10280407A (en) Pile driving device into rock-bed
JPH1150450A (en) Device for texture embrittlement and method for pile-head embrillement
JP2016132951A (en) Foundation pile construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040818

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060816

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060905

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061102

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070116

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070126

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees