JP2000240070A - Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section - Google Patents

Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section

Info

Publication number
JP2000240070A
JP2000240070A JP11045838A JP4583899A JP2000240070A JP 2000240070 A JP2000240070 A JP 2000240070A JP 11045838 A JP11045838 A JP 11045838A JP 4583899 A JP4583899 A JP 4583899A JP 2000240070 A JP2000240070 A JP 2000240070A
Authority
JP
Japan
Prior art keywords
pile
mesh
pile head
foundation pile
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11045838A
Other languages
Japanese (ja)
Inventor
Katsuya Tsunoda
勝弥 角田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Aizawa Koatsu Concrete KK
Original Assignee
Aizawa Koatsu Concrete KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aizawa Koatsu Concrete KK filed Critical Aizawa Koatsu Concrete KK
Priority to JP11045838A priority Critical patent/JP2000240070A/en
Publication of JP2000240070A publication Critical patent/JP2000240070A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a securing method for a pile head reinforcing bar insertion space in a foundation pile with a hollow section which can accurately form and secure the pile head reinforcing bar insertion space, does not require the wasteful removing work of a cement milk hardened body, and can accurately prevent a drop accident of a worker into the hollow section. SOLUTION: A mesh 2 is provided at the upper end of a foundation pile 1, a mesh 4 is provided below the mesh 2, by the height for burying pile head reinforcing bars 3, and a protective plate 5 is fitted to the upper mesh 2. After the foundation pile 1 is executed and a pit excavation is made around the pile head, the upper mesh 2 is cut, the protective plate 5 is moved onto the lower mesh 4, and the pile head reinforcing bars 3 are buried on it and connected to an upper mount structure, or an area injection doughnut body may be inflated and inserted into the upper end of the hollow section of the foundation pile 1.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明が属する技術分野】 本発明は、橋や建物構造等
の上載構造物の基礎に用いられる中空部を有する基礎杭
に関し、更に詳細の述べれば、上載構造物との連結部分
になる杭頭部分に杭頭補強筋挿入用スペースを確保する
ための方法に関するするものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation pile having a hollow portion used as a foundation for an overlying structure such as a bridge or a building structure, and more specifically, a pile head serving as a connecting portion with an overlying structure. The present invention relates to a method for securing a space for inserting a pile head reinforcement in a portion.

【0002】[0002]

【従来の技術】 従来の基礎杭工法は、それまで主流で
あった杭打ち工法が振動、騒音を非常に発生させてしま
うので規制が厳しくなり、かわりにセメントミルク工法
またはセメント根固め拡底工法が多く採用されている。
杭は剛性を高めるために円筒形状をしており杭末端部の
根固めや基礎杭上端部の上載構造物との連結において
は、空洞内部に補強筋を入れ、該補強筋を生コンクリー
トで固定させていることが多い。
[Prior art] The conventional foundation pile method has been strictly regulated because the pile driving method, which had been the mainstream until then, generates a lot of vibration and noise, and the cement milk method or the cement consolidation method is used instead. Many are adopted.
The pile has a cylindrical shape to increase rigidity, and when reinforcing piles at the end of the pile and connecting to the upper structure at the upper end of the foundation pile, a reinforcing bar is inserted inside the cavity, and the reinforcing bar is fixed with ready-mixed concrete It is often done.

【0003】しかし杭上端部に杭頭補強筋を挿入するた
めには上端に空洞が必要であるが、図9に示したように
杭孔に注入したセメントペースト11や周囲の土砂が上
昇してきて基礎杭1の空洞を埋めてしまうので、図10
に示したようにセメントペースト11や土砂を取り除く
のに費用がかかってしまう。また、杭打設後に周囲の掘
削作業や床付け作業をしているとき、杭頭補強筋を入れ
るまでの間は、作業員が誤って杭穴に落下してしまう危
険性がある。
However, a cavity is required at the upper end to insert a pile head reinforcing bar at the upper end of the pile, but as shown in FIG. 9, the cement paste 11 injected into the pile hole and the surrounding earth and sand rise. As it fills the cavity of the foundation pile 1, FIG.
As shown in (1), it is expensive to remove the cement paste 11 and the earth and sand. In addition, when excavation work or flooring work is performed after the pile is put into place, there is a risk that the worker may accidentally fall into the pile hole until the reinforcement for the pile head is inserted.

【0004】これらの問題に対していくつかの対処例が
報告されている。例えば杭頭補強筋を挿入するためのス
ペースを杭頭部分に確保し、かつ、空洞への作業者の落
下を防止するために、図11に示したようにベニヤ板を
杭上端にあてがい、ベニヤ板を土嚢などで抑え付けて、
必要になるまで杭の空洞の上面開口を封鎖することもあ
る。だが、この方法では土嚢が動いて外れてしまう等、
確実性の点でいささか問題がある。
[0004] There have been several reports on how to deal with these problems. For example, in order to secure a space for inserting a pile head reinforcing bar at a pile head portion and to prevent a worker from falling into a cavity, a plywood plate is applied to a pile upper end as shown in FIG. Hold it down with sandbags,
The top opening of the pile cavity may be blocked until needed. However, this method may cause the sandbag to move and come off,
There are some problems with certainty.

【0005】[0005]

【発明が解決しようとする課題】 したがって本発明の
目的は、橋や建物等の基礎杭工事において、杭頭補強筋
挿入用スペースの形成確保を的確に行なえ、無駄なセメ
ントミルク硬化体の除去作業が不要であり、作業員の空
洞部への転落事故を的確に防止できる、中空部を有する
基礎杭における杭頭補強筋挿入用スペースの確保方法を
提供することである。
SUMMARY OF THE INVENTION Accordingly, an object of the present invention is to ensure the formation of a space for inserting a pile head reinforcing bar in a foundation pile work such as a bridge or a building, and to remove a waste cement milk hardened body. It is therefore an object of the present invention to provide a method for securing a space for inserting a pile head reinforcing bar in a foundation pile having a hollow portion, which can accurately prevent an accident of a worker falling into a hollow portion.

【0006】[0006]

【課題を解決するための手段】 以下、添付図面中の参
照符号を用いて説明すると、請求項1の発明による杭頭
補強筋挿入スペースの確保方法では、基礎杭の施工方法
として公知の打撃工法を使用する。図1に示したように
中空を有する基礎杭1の上端にはメッシュ2が設置さ
れ、該メッシュ2から上載構造物へ連結される杭頭補強
筋3を埋め込む高さだけ下に位置するメッシュ4が設置
され、図2に示したように上位のメッシュ2には防護板
5が取り付けられる。
Means for Solving the Problems Hereinafter, the method for securing a pile head reinforcing bar insertion space according to the first aspect of the present invention will be described with reference to the accompanying drawings. Use As shown in FIG. 1, a mesh 2 is installed at the upper end of a hollow foundation pile 1, and a mesh 4 is located at a height lower than a height for embedding a pile head reinforcing bar 3 connected to the upper structure from the mesh 2. Is installed, and a protection plate 5 is attached to the upper mesh 2 as shown in FIG.

【0007】基礎杭1を地盤6に掘削された杭孔にハン
マー等の打撃によって打設し、杭頭周辺を根掘りして杭
頭を露出させた後、上位のメッシュ2を切断して防護板
5を下位のメッシュ4上に移動させる。図3に示したよ
うに防護板5とメッシュ4の上側の空洞部に杭頭補強筋
3を挿入して生コンクリートで定着して上載構造物へと
結合させる。
[0007] The foundation pile 1 is driven into the pile hole excavated in the ground 6 by hitting with a hammer or the like, excavating around the pile head to expose the pile head, and cutting the upper mesh 2 to protect the pile. The plate 5 is moved onto the lower mesh 4. As shown in FIG. 3, the pile head reinforcement 3 is inserted into the cavity above the protective plate 5 and the mesh 4 and is fixed with ready-mixed concrete to be connected to the upper structure.

【0008】請求項2の発明による杭頭補強筋挿入用ス
ペースの確保方法では、基礎杭1の施工方法として公知
のセメントミルク工法を使用する。図4に示したよう
に、中空部を有する基礎杭1を地盤6に掘削された杭孔
に挿入して周囲にセメントミルクを流し込んで養生硬化
させる。杭頭周辺を根掘りした後、上位のメッシュ2を
切断して防護板5を下位のメッシュ4上に移動させる。
図5に示したように、その上に杭頭補強筋3を挿入し、
生コンクリートで定着させて上載構造物へと結合させ
る。
In the method for securing a space for inserting a pile head reinforcing bar according to the second aspect of the present invention, a known cement milk method is used as a method for constructing the foundation pile 1. As shown in FIG. 4, the foundation pile 1 having a hollow portion is inserted into a pile hole excavated in the ground 6, and cement milk is poured into the periphery to cure and harden. After excavating around the pile head, the upper mesh 2 is cut and the protection plate 5 is moved onto the lower mesh 4.
As shown in FIG. 5, the pile head reinforcement 3 is inserted thereon,
It is fixed with ready-mixed concrete and bonded to the overlying structure.

【0009】請求項3の発明による杭頭補強筋挿入用ス
ペースの確保方法では、基礎杭の施工方法として公知の
セメントミルク根固め拡底工法を使用する。中空部を有
する基礎杭1の上端には上載構造物へ連結される杭頭補
強筋3を埋め込む高さに、強化ビニール等で作製された
円筒状のエア注入用ドーナツ体を設置し、図6及び図7
に示したように空気注入によってエア注入用ドーナツ体
7を膨張させて中空部内壁に密着させる。基礎杭1を地
盤6に掘削した杭孔に挿入し、セメントミルク中で回転
埋設する。この過程で余剰なセメントミルクが基礎杭1
の中空部分を伝って、またエア注入用ドーナツ体7の中
空部を伝って外部に流出する。その後、セメントミルク
を養生硬化させる。さらに杭頭周辺を根掘りした後、エ
ア注入用ドーナツ体7の空気を抜き、エア注入用ドーナ
ツ体7の中空内に進入硬化したセメントミルク硬化部分
を、それより下部のセメントミルク硬化体より折り分け
て、エア注入用ドーナツ体7ごと除去させる。これによ
って確保されたスペースに図8に示したように杭頭補強
筋3を挿入し、生コンクリートで定着させる。
In the method for securing a space for inserting a pile head reinforcing bar according to the third aspect of the present invention, a publicly known cement milk consolidation method is used as a method for constructing a foundation pile. At the upper end of the foundation pile 1 having a hollow portion, a cylindrical doughnut for air injection made of reinforced vinyl or the like is installed at a height to embed the pile head reinforcement 3 connected to the upper structure. And FIG.
As shown in (2), the donut 7 for air injection is inflated by air injection, and is brought into close contact with the inner wall of the hollow portion. The foundation pile 1 is inserted into a pile hole excavated in the ground 6, and is buried in cement milk by rotation. In this process, excess cement milk turns into the foundation pile 1
Along the hollow portion of the donut body 7 and flows out along the hollow portion of the donut body 7 for air injection. Thereafter, the cement milk is cured and hardened. Further, after digging around the pile head, the air of the donut body 7 for air injection is evacuated, and the hardened portion of cement milk that has entered and hardened into the hollow of the donut body 7 for air injection is folded from the hardened cement milk body below it. Then, the donut 7 for air injection is removed. As shown in FIG. 8, the pile head reinforcing bar 3 is inserted into the space thus secured, and is fixed with ready-mixed concrete.

【0010】[0010]

【発明の実施の形態】 メッシュ2,4としては、複数
本の鉄筋を縦横に適当な間隔で配置して互いに接合した
もの、打ち抜き金網、溶接金網、編み上げ金網などを適
宜採用することができる。メッシュ2,4は基礎杭1の
製造時に所要箇所に設置されるが、基礎杭1の製造後に
取り付けることもできる。上位メッシュ2とともに作業
員の転落を防止する一方、下位メッシュ4とともに杭頭
補強筋挿入スペースの底部を画定し、生コンクリートの
落下を防止する防護板5は、鉄板で構成されているが、
これは他の材料で作製することもできる。防護板5は通
常、基礎杭1を施工現場に搬入した時点でメッシュ2に
取り付けられる。
BEST MODE FOR CARRYING OUT THE INVENTION As the meshes 2 and 4, a plurality of reinforcing bars arranged at appropriate intervals in the vertical and horizontal directions and joined to each other, a punched wire mesh, a welded wire mesh, a braided wire mesh, and the like can be appropriately adopted. The meshes 2 and 4 are installed at required locations when the foundation pile 1 is manufactured, but may be attached after the foundation pile 1 is manufactured. While the upper mesh 2 prevents the workers from falling down, the lower mesh 4 defines the bottom of the pile head reinforcing bar insertion space, and the protective plate 5 for preventing the falling of the ready-mixed concrete is made of iron plate.
It can be made of other materials. The protection plate 5 is usually attached to the mesh 2 when the foundation pile 1 is carried into the construction site.

【0011】[0011]

【発明の効果】 以上のように本発明では、基礎杭の施
工方法として打撃工法を用いる場合、基礎杭1の中空部
上端に上下二段にメッシュ2,4を設置し、上位のメッ
シュ2に防護板5を取り付けることで、杭頭補強筋3を
埋め込む高さの位置まで確実にセメントペースト及び土
砂の侵入を防ぐことができる。また、杭頭補強筋3を挿
入するまでは、防護板5により中空を確実に塞いでおく
ことができるので、作業員らの不慮の落下事故を防ぐこ
とができる。
As described above, according to the present invention, when using the hammering method as the method of constructing the foundation pile, the meshes 2 and 4 are installed at the upper end of the hollow portion of the foundation pile 1 in the upper and lower stages, and By attaching the protection plate 5, it is possible to reliably prevent the cement paste and the earth and sand from invading to the position where the pile head reinforcement 3 is embedded. Moreover, since the hollow can be reliably closed by the protection plate 5 until the pile head reinforcement 3 is inserted, an accidental fall accident of the workers can be prevented.

【0012】また、基礎杭1の施工方法としてセメント
ミルク工法を用いる場合、上位メッシュ2に取り付けた
防護板5によって、基礎杭1の中空部へのセメントミル
クの流入が阻止されるため、硬化したセメントミルクの
面倒な除去作業がなくなる。また、打撃工法とセメント
ミルク工法のいずれにおいても、上位のメッシュ2の切
除後、防護板5を下位のメッシュ4上に設置することに
よって、杭頭補強筋挿入スペースの底部が閉塞され、メ
ッシュ4より下方への生コンクリートの落下を的確に防
止することができる。
When the cement milk method is used as a method of constructing the foundation pile 1, the protective plate 5 attached to the upper mesh 2 prevents cement milk from flowing into the hollow portion of the foundation pile 1 and thus hardens. Eliminates the cumbersome work of removing cement milk. In both the impact method and the cement milk method, after the upper mesh 2 is cut off, the protective plate 5 is placed on the lower mesh 4 so that the bottom of the pile head reinforcing bar insertion space is closed and the mesh 4 is removed. It is possible to accurately prevent the falling of the ready-mixed concrete from lowering.

【0013】基礎杭1の施工方法としてセメントミルク
根固め拡底工法を使用し、基礎杭1の中空部上端にエア
注入用ドーナツ体7を膨張密着させた場合には、エア注
入用ドーナツ体7の中空部にまで上昇して硬化したセメ
ントミルクによってエア注入用ドーナツ体7の上面開口
が閉塞されているため、作業員の落ち込み事故が発生し
ない。また、エア注入用ドーナツ体7から空気を抜き、
中空部内のセメントミルク硬化部分をそれより下方のセ
メントミルク硬化体からエア注入用ドーナツ体7ととも
に折り取ることによって、杭頭補強筋挿入スペースが簡
単に形成されることになる。
When the dough 7 for air injection is inflated and adhered to the upper end of the hollow portion of the foundation pile 1 by using the cement milk consolidation expanding method as a construction method of the foundation pile 1, Since the upper surface opening of the doughnut body 7 for air injection is closed by the cement milk which has risen to the hollow part and hardened, the worker does not fall down. In addition, air is extracted from the donut body 7 for air injection,
By cutting off the hardened portion of cement milk in the hollow portion together with the doughnut body 7 for injecting air from the hardened cement milk below, a space for inserting a pile head reinforcing bar can be easily formed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明方法の一実施例に使用される基礎杭の
平面図であり、防護板は未設置状態にある。
FIG. 1 is a plan view of a foundation pile used in an embodiment of the method of the present invention, in which a guard plate is not installed.

【図2】 打撃工法で施工した図1の基礎杭のA−A線
縦断面図であり、上位のメッシュに防護板が取り付けら
れている。
FIG. 2 is a vertical sectional view taken along the line AA of the foundation pile of FIG. 1 constructed by a percussion method, and a protective plate is attached to an upper mesh.

【図3】 図1の基礎杭の縦断面図であり、防護板を下
位のメッシュ上に移動して杭頭補強筋を挿入した状態を
示している。
FIG. 3 is a longitudinal sectional view of the foundation pile of FIG. 1, showing a state in which a protection plate is moved onto a lower mesh and a pile head reinforcing bar is inserted.

【図4】 セメントミルク工法で施工された基礎杭の縦
断面図であり、上位のメッシュに取り付けた防護板によ
って基礎杭の上面開口が閉塞されている状態を示してい
る。
FIG. 4 is a longitudinal sectional view of a foundation pile constructed by a cement milk method, showing a state in which an upper surface opening of the foundation pile is closed by a protection plate attached to an upper mesh.

【図5】 図4の基礎杭において、防護板を下位のメッ
シュ上に移動して杭頭補強筋を挿入した状態の縦断面図
である。
FIG. 5 is a longitudinal sectional view of the foundation pile of FIG. 4 in a state where a protective plate is moved onto a lower mesh and a pile head reinforcing bar is inserted.

【図6】 セメントミルク根固め拡底工法で施工された
基礎杭の平面図であり、エア注入用ドーナツ体が中空部
に膨張装着されている状態を示している。
FIG. 6 is a plan view of a foundation pile constructed by the cement milk solidification method, showing a state in which a donut for air injection is inflated and mounted in a hollow portion.

【図7】 図6のB−B線縦断面図である。FIG. 7 is a vertical sectional view taken along the line BB of FIG. 6;

【図8】 図6の基礎杭において、エア注入用ドーナツ
体とセメントミルク硬化部分を取り除いて確保されたス
ペースに杭頭補強筋を挿入した状態を示す縦断面図であ
る。
8 is a longitudinal sectional view showing a state in which a dough for air injection and a hardened portion of cement milk are removed and a pile head reinforcing bar is inserted into a space secured in the foundation pile of FIG. 6;

【図9】 従来工法において基礎杭の上面開口からセメ
ントミルクが中空部に入り込んだ状態を示す縦断面図で
ある。
FIG. 9 is a vertical cross-sectional view showing a state in which cement milk has entered a hollow portion from an upper surface opening of a foundation pile in a conventional method.

【図10】 図9の基礎杭において中空部上端のセメン
トミルク硬化体を除去した状態を示す縦断面図である。
FIG. 10 is a longitudinal sectional view showing a state in which the hardened cement milk at the upper end of the hollow portion has been removed from the foundation pile of FIG. 9;

【図11】 従来工法において基礎杭の上面開口をベニ
ヤ板で閉塞し、土嚢で押さえ付けた状態を示す縦断面図
である。
FIG. 11 is a longitudinal sectional view showing a state in which an upper surface opening of a foundation pile is closed with a plywood and pressed with a sandbag in a conventional method.

【符号の説明】[Explanation of symbols]

1 基礎杭 2 メッシュ 3 杭頭補強筋 4 メッシュ 5 防護板 6 地盤 7 エア注入用ドーナツ体 9 土嚢 10 ベニア板 11 セメントミルク 12 空気口 REFERENCE SIGNS LIST 1 foundation pile 2 mesh 3 pile head reinforcement 4 mesh 5 protective plate 6 ground 7 donut body for air injection 9 sandbag 10 veneer plate 11 cement milk 12 air port

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 中空を有する基礎杭1と、該基礎杭1の
上端に設けられるメッシュ2と、該メッシュ2から上載
構造物へ連結される杭頭補強筋3を埋め込む高さだけ下
に設けられるメッシュ4と、上位のメッシュ2に取り付
けられる防護板5とからなり、基礎杭1を地盤6に打撃
工法によって施工し、杭頭周辺を根掘りした後、上位の
メッシュ2を切断して防護板5を下位のメッシュ4上に
移動させ、その上に杭頭補強筋3を埋め込んで上載構造
物に結合させていくことを特徴とする、中空部を有する
基礎杭における杭頭補強筋挿入用スペースの確保方法
1. A foundation pile 1 having a hollow, a mesh 2 provided at an upper end of the foundation pile 1, and a pile head reinforcing bar 3 connected from the mesh 2 to an overlying structure are provided at a height lower than a height for embedding. And a protection plate 5 attached to the upper mesh 2. The foundation pile 1 is constructed on the ground 6 by a hammering method, and after excavating around the pile head, the upper mesh 2 is cut and protected. The board 5 is moved onto the lower mesh 4 and the pile head reinforcing bar 3 is embedded therein and connected to an overlying structure, for inserting a pile head reinforcing bar in a foundation pile having a hollow portion. How to secure space
【請求項2】 中空を有する基礎杭1と、該基礎杭1の
上端に設けられるメッシュ2と、該メッシュ2から上載
構造物へ連結される杭頭補強筋3を埋め込む高さだけ下
に設けられるメッシュ4と、上位のメッシュ2に取り付
けられる防護板5とからなり、基礎杭1を地盤6に掘削
した杭孔にセメントミルク工法によって施工し、杭頭周
辺を根掘りした後、上位のメッシュ2を切断して防護板
5を下位のメッシュ4上に移動させ、その上に杭頭補強
筋3を埋め込んで上載構造物に結合させていくことを特
徴とする、中空部を有する基礎杭における杭頭補強筋挿
入用スペースの確保方法
2. A foundation pile 1 having a hollow, a mesh 2 provided at an upper end of the foundation pile 1, and a pile head reinforcing bar 3 connected from the mesh 2 to an upper structure are provided at a height lower than a height for embedding. And a protection plate 5 attached to the upper mesh 2. The foundation pile 1 is constructed in a pile hole excavated in the ground 6 by a cement milk method, and after excavating around a pile head, the upper mesh is formed. 2, the protective plate 5 is moved onto the lower mesh 4, and the pile head reinforcing bar 3 is buried on the mesh 4 and connected to the upper structure. How to secure space for insertion of pile head reinforcement
【請求項3】 中空を有する基礎杭1と、該基礎杭1の
上端に上載構造物へ連結される杭頭補強筋3を埋め込む
高さに設置される強化ビニール等で作製された円筒状の
エア注入用ドーナツ体7とからなり、該エア注入用ドー
ナツ体7を空気注入によって膨張させて杭中空部内壁に
密着させ、基礎杭1を地盤6に掘削した杭孔に挿入して
セメントミルク根固め拡底工法により施工し、杭頭周辺
を根掘りした後、該エア注入用ドーナツ体7内の空気を
抜き、エア注入用ドーナツ体7の中空に進入硬化したセ
メントミルク硬化部分を、それより下部のセメントミル
ク硬化体から折り分けてエア注入用ドーナツ体7ごと除
去することを特徴とする、中空部を有する基礎杭におけ
る杭頭補強筋挿入用スペースの確保方法
3. A cylindrical pile made of reinforced vinyl or the like which is installed at a height at which an upper end of the hollow foundation pile 1 and a pile head reinforcing bar 3 connected to an upper structure are embedded at an upper end of the foundation pile 1. The donut body 7 for air injection is expanded by air injection and brought into close contact with the inner wall of the pile hollow part, and the foundation pile 1 is inserted into the pile hole excavated on the ground 6 to remove the cement milk root. After constructing by the hardening method and excavating around the pile head, the air inside the donut body 7 for air injection is evacuated, and the hardened portion of the cement milk that has entered and hardened into the hollow of the donut body 7 for air injection is moved downward. A method for securing a space for inserting a pile head reinforcing bar in a foundation pile having a hollow portion, wherein the space is removed from the hardened cement milk body and the donut body 7 for air injection is removed.
JP11045838A 1999-02-24 1999-02-24 Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section Pending JP2000240070A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11045838A JP2000240070A (en) 1999-02-24 1999-02-24 Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11045838A JP2000240070A (en) 1999-02-24 1999-02-24 Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section

Publications (1)

Publication Number Publication Date
JP2000240070A true JP2000240070A (en) 2000-09-05

Family

ID=12730376

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11045838A Pending JP2000240070A (en) 1999-02-24 1999-02-24 Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section

Country Status (1)

Country Link
JP (1) JP2000240070A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017172247A (en) * 2016-03-24 2017-09-28 株式会社熊谷組 Removal method of solidification object in pile head part of precast pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017172247A (en) * 2016-03-24 2017-09-28 株式会社熊谷組 Removal method of solidification object in pile head part of precast pile

Similar Documents

Publication Publication Date Title
KR100428018B1 (en) File head treatment of concrete mortar, file head treatment method, and mortar concrete mortar method
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR100869815B1 (en) Apparatus to upgrade end bearing capacity of pile and pile construction method
JP4623574B2 (en) How to build a pile
JP5274145B2 (en) Cast-in-place pile and its construction method
JP4693423B2 (en) Pile head reinforcement method
KR20110041391A (en) Pile structure
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR101840226B1 (en) The guide holes of the form for soil auger dredges
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
JP5480744B2 (en) Foundation for structure and its construction method
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR100583880B1 (en) Method for constructing foundation work using concrete pile
JP2000240070A (en) Securing method for pile head reinforcing bar insertion space in foundation pile with hollow section
JPH08209686A (en) Pile head processing tool and pile head processing construction method for cast-in-place pile
KR102070912B1 (en) Phc pile for soil retaining wall, mold assembly and manufacturing method thereof
JP7112939B2 (en) Joint structure between pile and foundation concrete, precast concrete body, and construction method
KR100401330B1 (en) A method of construction for earth-protection walls of building
JP2003055985A (en) Connecting method of column to pile
JP2000192454A (en) Removing method for extra-banking part of cast-in-place concrete pile and its removing device
KR100689080B1 (en) A method of construction for reinforcement and landscape architecture to an incline plane
KR100266391B1 (en) Nail removal type nailling method in digging work
JP4324057B2 (en) Slope treatment method
JP2004316207A (en) Structure for connecting earth retaining wall with floor slab, and construction method therefor
JP4137172B1 (en) Reinforcing bar construction in cast-in-place pile

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20000926