KR100862387B1 - Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this - Google Patents

Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this Download PDF

Info

Publication number
KR100862387B1
KR100862387B1 KR1020080030944A KR20080030944A KR100862387B1 KR 100862387 B1 KR100862387 B1 KR 100862387B1 KR 1020080030944 A KR1020080030944 A KR 1020080030944A KR 20080030944 A KR20080030944 A KR 20080030944A KR 100862387 B1 KR100862387 B1 KR 100862387B1
Authority
KR
South Korea
Prior art keywords
acupressure
tension
anchor
kit
pressure plate
Prior art date
Application number
KR1020080030944A
Other languages
Korean (ko)
Inventor
유성진
이성락
박우영
Original Assignee
주식회사 신도이엔아이
동남이엔씨(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 신도이엔아이, 동남이엔씨(주) filed Critical 주식회사 신도이엔아이
Priority to KR1020080030944A priority Critical patent/KR100862387B1/en
Application granted granted Critical
Publication of KR100862387B1 publication Critical patent/KR100862387B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1685Shapes cylindrical
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A tensional kit for top-down construction of a pressure type permanent anchor and a top-down construction method for a pressure permanent anchor using the same are provided to increase the degree of space efficiency in a limited space by forming an incline plane at a vertical angle or an angle near to a vertical angle. A tensional kit for top-down construction of a pressure type permanent anchor comprises a first pressure plate(11), a cylindrical casing(12) and a second pressure plate. The first pressure plate is supported by an incline plane formed by excavation. The casing is buried to the underground by passing through the first pressure plate. The second pressure plate is detachably coupled with an end of the casing to press the incline plane through the first pressure plate. A plurality of reinforcing ribs(15) are formed at the peripheral portion of the casing. A cylindrical fixing head(14) protrudes from the second pressure plate.

Description

지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트와 이를 이용한 지압형 영구 앵커의 탑다운 시공 방법{Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this}Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this}

본 발명은 앵커 시공 방법에 관한 것으로서, 더욱 상세하게는 굴착과 앵커 시공을 지상에서부터 지중으로 가면서 진행하여 공기를 단축할 수 있고, 법면을 연직 또는 연직에 근접되는 각도로 형성하여 제한된 공간에서 공간활용도를 높일 수 있는 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트와 이를 이용한 지압형 영구 앵커의 탑다운 시공 방법에 관한 것이다.The present invention relates to an anchor construction method, and more particularly, it is possible to shorten the air by going through the excavation and anchor construction from the ground to the ground, and to form a normal surface at an angle close to the vertical or vertical space utilization in a limited space The present invention relates to a tension kit for top-down construction of acupressure-type permanent anchors that can increase the pressure, and a top-down construction method of acupressure-type permanent anchors using the same.

사면을 굴착 후 사면의 붕괴방지, 사면안정화 등을 위해서 통상 사면부에는 영구앵커, 쏘일네일링, 계단식 및 기대기 옹벽, 사면 녹화 등 다양한 사면 안정 공법이 적용된다.After excavation of slopes, various slope stabilization methods such as permanent anchors, soil nailing, stepped and leaning retaining walls, and slope greening are applied to slopes to prevent slope collapse and slope stability.

앵커는 절개지 등에서의 절개면의 붕괴방지 및 사면안정, 빌딩 또는 댐 등과 같은 대형 구조물의 지하수에 의한 부상방지, 대형 건물의 지하층 토목 공사시 굴착벽면의 붕괴방지 등에 사용되며, 또한 지진 발생시 등의 건축물이나 대형 철탑 시공시 구축물의 이동이나 왜곡을 방지하기 위해 설치되는 것이다.Anchors are used to prevent the collapse of incisions in incisions, to stabilize slopes, to prevent injuries caused by groundwater in large structures such as buildings or dams, and to prevent the collapse of excavated walls in underground construction of large buildings. It is installed to prevent the movement or distortion of the construction when constructing a large steel tower.

기존의 앵커공법은 붕괴염려가 있는 지반에 천공기를 이용하여 굴착공을 천공하고, 이 구멍에 그라우트 호스(grout hose)와 복수개의 인장재 및 내하체를 하나의 유닛으로 마련하여 삽입한 다음, 그라우트 호스를 통해 그라우트(grout)를 주입하며, 주입된 그라우트가 내하체와 함께 양생되면 인장재의 다른 한쪽끝단에 고정구를 체결한 후 긴장재를 유압장비 등을 사용하여 인장하여 대상 구조물을 안정시키는 것이다.Conventional anchoring method drills an excavation hole using a perforator in the ground where there is a risk of collapse, and inserts a grout hose, a plurality of tension members and a load body into a single unit, and then inserts a grout hose into the hole. Injecting grout through the grout, and when the injected grout is cured together with the lower body, the fastener is fastened to the other end of the tension member and the tension member is tensioned using hydraulic equipment to stabilize the target structure.

그러나 종래 기술에 의한 앵커의 시공방법에 따르면 다음과 같은 문제점이 있다.However, according to the construction method of the anchor according to the prior art has the following problems.

도 1에서 보이는 것처럼, 지상에서부터 굴착을 시작하여 바닥으로 진행하거나 기존 도로의 확장시에는 바닥에서부터 지상으로 올라가면서 굴착을 진행한 후 바닥에서부터 앵커(1)를 지상으로 올라가면서 시공하기 때문에 공기가 길어지고 그에 따른 비용이 상승하며 법면(2)이 안정되는데 오랜 시간이 소요되는 문제점이 있고, 기존의 앵커 공법은 그라우트 타설 후 최소 양생기간이 필요하므로 양생기간 동안 공기가 길어지는 문제점이 있다.As shown in Figure 1, starting the excavation from the ground to proceed to the ground or when expanding the existing road proceeds to the excavation while going up from the ground to the ground, and then the construction of the anchor (1) to the ground from the ground to the long There is a problem that it takes a long time to increase the cost and stabilize the surface (2), and the conventional anchor method has a problem that the air is long during the curing period because the minimum curing period is required after the grout placement.

그리고, 앵커(1)를 시공하기 위해서 최소의 사면 활동 안전율을 확보하는 법면 경사로 시공 구역 모두를 굴토한 후 바닥에서부터 지상측으로 올라가면서 차례로 앵커(1)를 다단(도면에는 2개를 예로 들어 설명함)으로 설치한다. 따라서, 절토 에 의한 법면(2)의 구배가 사면 활동 안전율을 확보하기 위해서는 커질 수밖에 없으므로 그만큼 사용 부지가 좁아지며, 굴착폭원 과다로 산지부 환경 훼손이 과다해지고, 공사비가 증대되는 등의 문제점도 있다.In addition, in order to construct the anchor 1, the slope slopes are secured to secure the minimum slope safety factor, and then the anchor 1 is multistage in order from the bottom to the ground side. Install with). Therefore, the slope of the slope (2) due to cutting is inevitably increased in order to secure the slope safety rate, so the site for use is narrowed. Excessive excavation width causes excessive damage to the environment of the mountain region, and there is also a problem of increasing construction cost. .

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 굴착과 앵커 시공을 지상에서부터 지중으로 가면서 진행하여 공기를 단축할 수 있는 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트와 이를 이용한 지압형 영구 앵커의 탑다운 시공 방법을 제공하는데 그 목적이 있다.The present invention is to solve the problems as described above, the tension kit for the top-down construction of the pressure-type permanent anchor that can shorten the air by proceeding excavation and anchor construction from the ground to the ground and acupressure-type permanent using the same Its purpose is to provide an anchor top-down construction method.

그리고, 본 발명의 다른 목적은 법면을 연직 또는 연직에 근접되는 각도로 형성하여 사(死)공간을 최소함으로써 제한된 면적에서 최대의 사용 부지를 확보하려는데 있다.In addition, another object of the present invention is to ensure the maximum use site in a limited area by forming a legal surface at an angle close to the vertical or vertical to minimize dead space.

전술한 바와 같은 목적을 달성하기 위한 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트는, 사면부에 안정적 거치를 위해 앵커공의 입구측에 삽입되며 내부에 앵커의 자유장이 통과하는 케이싱, 상기 케이싱에 길이방향을 따라 일정 간격을 두고 각각 결합되는 제1,2지압판, 제2지압판에 형성되며 긴장기가 지지되는 정착헤드를 포함하여 구성된 것을 특징으로 한다.The tension kit for the top-down construction of acupressure permanent anchor according to the present invention for achieving the object as described above, is inserted into the inlet side of the anchor hole for stable mounting on the slope and the free length of the anchor passes through Casing, the first and second pressure plate, respectively coupled to the casing at a predetermined interval along the longitudinal direction, characterized in that it comprises a fixing head which is formed on the second pressure plate and the tensioner is supported.

그리고, 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트를 이용한 지압형 영구 앵커의 탑다운 시공 방법은, 지상에서부터 연직방향으로 일정 깊이를 굴착 - 법면에 기초 보강벽 형성 - 키트와 앵커 시공 - 앵커 1차 긴장의 공정을 지상에서부터 아래로 내려가면서 수행하고, 원하는 깊이로 굴착이 완료되면 상기 기초 보강벽 전면에 콘크리트 옹벽을 시공한 후 2차 긴장용 지압판을 콘크리트 사면에 설치하여 상기 앵커를 2차 긴장하는 것을 특징으로 한다.In addition, the top-down construction method of acupressure-type permanent anchor using a tension kit for top-down construction of acupressure-type permanent anchor according to the present invention, excavation of a certain depth in the vertical direction from the ground-Foundation reinforcement wall formation-Kit And anchor construction-Anchor 1st tension process is carried out from the ground down, and when excavation is completed to the desired depth, a concrete retaining wall is installed in front of the foundation reinforcement wall, and then a second tension acupressure plate is installed on the concrete slope. It characterized in that the anchor is tensioned second.

본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트와 이를 이용한 지압형 영구 앵커의 탑다운 시공 방법에 의하면, 지상에서부터 순차적으로 내려가면서 앵커를 시공하여 지반에 1차 긴장에 의한 인장력을 가하면 굴착면의 활동 안전율이 확보되어 윗단의 앵커 시공 중에 아래측의 굴착을 진행할 수 있으므로 즉 윗단과 아랫단의 일부 공정을 동시에 진행할 수 있으므로 공기를 단축할 수 있으며, 굴착공사중에 사면이 붕괴되는 것을 방지할 수 있어 굴착과 앵커 시공이 함께 이루어져 공기 대폭 단축과 사면 안정성을 확보할 수 있다.According to the tension kit for the top-down construction of acupressure permanent anchor according to the present invention and the top-down construction method of acupressure permanent anchor using the same, the tensile force by the first tension on the ground by constructing the anchor while descending from the ground sequentially By applying, the safety factor of the excavation surface is secured, and the excavation of the lower side can be carried out during the construction of the anchor at the upper end, that is, some processes of the upper end and the lower end can be carried out simultaneously, so that the air can be shortened. As it can be prevented, excavation and anchor construction are performed together, which greatly reduces the air and ensures slope stability.

그리고, 법면을 연직 또는 연직에 가까운 각도로 형성함으로써 최대한 모든 면적을 사용할 수 있으므로 공간활용도를 높일 수 있고 부지의 구입에 따른 비용을 절감할 수 있고, 대규모 절토사면 발생을 방지함과 아울러 환경 훼손 면적의 과대 발생을 예방할 수 있다.In addition, by forming the surface at an angle perpendicular to or near to the vertical, all areas can be used as much as possible, thereby increasing the space utilization, reducing the cost of purchasing the site, preventing large cut slopes, and reducing the environmental damage. Overuse can be prevented.

도 2와 도 3에서 보이는 바와 같이 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트(10)는, 굴착에 의한 법면(2)에 지지되는 제1지압판(11), 앵커공(2a)의 입구측에 삽입되어 앵커공(2a)을 지지함과 아울러 내부에 지압형 영구 앵커(1)의 자유장(1a)(도 5참조)이 통과하는 케이싱(12), 긴장기(100)(도 5 참고)에 의해 법면(2)을 지압하는 제2지압판(13), 긴장기(100)의 고정을 위한 정착헤드(14), 케이싱(12)의 강도를 보강하기 위한 보강리브(15)로 구성된다.As shown in FIGS. 2 and 3, the tension kit 10 for top-down construction of acupressure-type permanent anchors according to the present invention includes a first acupressure plate 11 and an anchor hole supported on a surface 2 by excavation. Casing 12, tensioner (2a) is inserted into the inlet side of the (2a) to support the anchor hole (2a) and the free field (1a) (see Fig. 5) of the acupressure-type permanent anchor (1) therein. Reinforcing ribs for reinforcing the strength of the second pressure plate 13, the fixing head 14 for fixing the tensioner 100, the casing 12 for pressing the surface (2) by 100 (see FIG. 5) It consists of 15 pieces.

제1지압판(11)은 평평한 판상 예컨대 4각 판상이며 법면(2)(실질적으로는 숏크리트부)에 지지된다. 제1지압판(11)은 케이싱(12)에 의해 법면(2) 내부에 지지됨과 아울러 별도의 앵커(미도시)를 통해 고정될 수 있다.The first pressure plate 11 is a flat plate shape, for example, a quadrilateral plate shape, and is supported on the surface 2 (substantially shotcrete portion). The first pressure plate 11 may be supported by the casing 12 inside the legal surface 2 and may be fixed through a separate anchor (not shown).

케이싱(12)은 내부에 양측이 관통되는 중공부가 형성된 원통형이며, 제1지압판(11)이 관통 형성된다. 즉, 제1지압판(11)과 케이싱(12)을 일체로 형성하거나, 제1지압판(11)(케이싱(12)의 결합을 위한 구멍 성형)과 케이싱(12)을 각각 제조한 후 이들을 용접 등으로 결합할 수 있다. The casing 12 has a cylindrical shape in which both sides penetrate therein, and the first pressure plate 11 is formed therethrough. That is, the first pressure plate 11 and the casing 12 are integrally formed, or the first pressure plate 11 (hole forming for joining the casing 12) and the casing 12 are manufactured, respectively, and then welded to each other. Can be combined.

케이싱(12)은 제조 방식에 상관없이 제1지압판(11)의 양측으로 돌출되는 형태이다. 즉, 제1지압판(11)의 앞쪽으로 돌출된 부분은 앵커공(2a)에 삽입되는 삽입부(12a)인 것이다.The casing 12 protrudes to both sides of the first pressure plate 11 regardless of the manufacturing method. That is, the portion protruding toward the front of the first pressure plate 11 is the insertion portion 12a inserted into the anchor hole 2a.

케이싱(12)은 삽입부(12a)가 법면(2) 내부에 형성된 앵커공(2a)에 삽입되어 법면(2)에 고정된다.The casing 12 has an insertion portion 12a inserted into an anchor hole 2a formed inside the law surface 2 and fixed to the law surface 2.

제2지압판(13)은 케이싱(12)에 제1지압판(11)으로부터 일정 거리(이 거리는 후술하는 콘크리트의 타설 구간이다) 이격 형성되며 후술하는 콘크리트부에 지지되어 긴장기(100)에 의해 법면(2)을 지압하는 것으로, 판상으로 이루어지며 정착헤드(14)가 결합되는 지압부(13a), 지압부(13a)에 관통 결합되며 케이싱(12)에 연결되는 연결부로 이루어질 수 있다. 제2지압판(13)은 2차 긴장시 1차 긴장때보다 넓은 분포로 지압력을 발생할 수 있도록 케이싱(12)의 단부로부터 일정 거리 이격 배치된다.The second acupressure plate 13 is formed on the casing 12 from the first acupressure plate 11 by a predetermined distance (this distance is a casting section of concrete to be described later) and is supported by a concrete part to be described later, and the surface is tensioned by the tensioner 100. By acupressure (2), it is made of a plate-like, the acupressure portion 13a to which the fixing head 14 is coupled, it may be made of a coupling portion connected to the casing 12 through and coupled to the acupressure portion 13a. The second pressure plate 13 is spaced apart from the end of the casing 12 so that the pressure can be generated in a wider distribution than the first tension during the second tension.

상기 연결부는 케이싱(12)과 동일한 직경의 제1연결부(13b) 및 제1연결부(13b)의 내부에 용접 등으로 결합되며 케이싱(12)에 내접 결합되는 제2연결부(13c)로 이루어질 수 있다.The connection part may be composed of a first connection part 13b having the same diameter as that of the casing 12 and a second connection part 13c which is coupled to the inside of the first connection part 13b by welding or the like and which is internally coupled to the casing 12. .

여기서 제2지압판(13)을 제1지압판(11)에서 분리한 것은 1차 긴장력이 제1지압판(11)에서부터 발생되도록 하고, 2차 긴장력은 제1지압판(11)에 의해 발생되는 지압력 보다 넓은 면적에서 지압력이 발생되도록 하기 위함이다.Here, the separation of the second pressure plate 13 from the first pressure plate 11 so that the primary tension force is generated from the first pressure plate 11, the secondary tension force is less than the pressure pressure generated by the first pressure plate 11 This is to allow the earth pressure to be generated in a large area.

제2지압판(13)은 2차 긴장시 콘크리트 옹벽에서 분리되며, 이를 위하여 외주면 표면에 분리가 용이하도록 박리막이 형성되도록 박리제를 도로한다.The second pressure plate 13 is separated from the concrete retaining wall during the secondary tension, and for this purpose, the release agent is applied so that a release film is formed on the outer circumferential surface to facilitate separation.

정착헤드(14)는 제2지압판(13)에 돌출 형성되며 긴장기(100)가 지지된다.The fixing head 14 protrudes from the second pressure plate 13 and the tensioner 100 is supported.

정착헤드(14)는 앵커(1)의 자유장(1a)이 관통되는 원통형인 것으로, 단품으로 이루어져 제2지압판(13)에 고정될 수 있다. 예를 들어 제2지압판(13)에 안착홈을 형성하여 정착헤드(14)가 삽입되도록 함으로써 정착헤드(14)와 제2지압판(13)간의 결속력을 증대 및 정착헤드(14)의 이탈을 막으며, 아울러, 볼트 등으로 고정될 수도 있다.The fixing head 14 has a cylindrical shape through which the free field 1a of the anchor 1 penetrates, and may be fixed to the second pressure plate 13 as a single piece. For example, by forming a mounting groove in the second pressure plate 13 so that the fixing head 14 is inserted, the binding force between the fixing head 14 and the second pressure plate 13 is increased and the separation of the fixing head 14 is prevented. In addition, it may be fixed with a bolt or the like.

즉, 케이싱(12)이나 정착헤드(14) 중 어느 하나만 변형되거나 파손된 경우 케이싱(12)과 정착헤드(14)를 분리하여 교체가 필요한 부분만 골라 보수할 수 있으므로 유지비용을 절감할 수 있다.That is, when only one of the casing 12 or the fixing head 14 is deformed or broken, the maintenance cost can be reduced since the casing 12 and the fixing head 14 can be separated and repaired by selecting only the parts requiring replacement. .

보강리브(15)는 케이싱(12)의 축방향 변형 방지 및 케이싱 강성 증진을 위하여 형성되는 것으로, 다수개가 케이싱(12)의 둘레부에 원주방향을 따라 일정 간격을 두고 방사형으로 형성된다.The reinforcing rib 15 is formed to prevent axial deformation of the casing 12 and to enhance casing rigidity. A plurality of reinforcing ribs 15 are radially formed at regular intervals along the circumferential direction at the circumference of the casing 12.

보강리브(15)에는 후술하는 보강 철근(20)이 지지되는 철근 걸이홈(15a)이 형성될 수 있다.The reinforcing rib 15 may be provided with a reinforcing bar groove 15a to which the reinforcing bar 20 to be described later is supported.

본 발명에 의한 키트(10)는 기존에 사용되고 있는 모든 앵커, 네일링 등에 적용 가능하다.Kit 10 according to the present invention is applicable to all anchors, nailing, and the like used in the past.

도 4를 참고하여 이와 같이 구성된 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트를 이용한 지압형 영구 앵커의 탑다운 시공 방법을 설명한다.Referring to Figure 4 will be described the top-down construction method of acupressure-type permanent anchor using a tension kit for the top-down construction of the acupressure-type permanent anchor according to the present invention configured as described above.

(S10) 굴착.(S10) excavation.

본 발명에 의한 시공 방법은 앵커를 지상에서부터 아래로 내려가면서 차례로 시공하는 것으로, 일정 높이로 설계하여 이 설계에 맞춰 단계별로 시공되는 것이다. 예를 들어 3m씩 시공하는 것으로 설계가 이루어질 경우, 지상에서부터 3m 깊이로 굴착을 한다. 이때, 앵커가 시공될 법면은 종래 하부에서부터 시공할 때보다 경사 각도가 작으며 거의 연직에 가까워도 전혀 문제가 없다. 따라서, 연직의 법 면(2a)이 형성되도록 굴착을 하며 그 아랫단의 시공이 용이하도록 평탄면의 작업 공간을 형성한다.The construction method according to the present invention is to construct the anchor while descending from the ground in order, it is designed to a certain height to be constructed step by step in accordance with this design. For example, if the design consists of 3m installations, excavate 3m deep from the ground. At this time, the anchor surface is to be constructed is less problem than when the construction from the conventional construction from the lower side is almost no problem even if close to vertical. Therefore, excavation is performed so that the vertical law surface 2a is formed, and the work space of the flat surface is formed so that the construction of the lower end may be easy.

(S20) 법면 보강.(S20) surface reinforcement.

법면(2)은 토사로 이루어지기 때문에 지반 내 응력해방으로 인한 토사 유실이 일어날 수 있으며 이를 보강하기 위하여 기초 보강벽(3)을 형성한다. 기초 보강벽(3)은 숏크리트 타설에 의해 형성될 수 있으며 두께는 4 내지 6cm일 수 있고, 숏크리트와 분사기는 통상적으로 사용되고 있는 제품이 사용된다.Since the surface 2 is made of soil, soil loss due to stress release in the ground may occur, and a foundation reinforcement wall 3 is formed to reinforce it. The foundation reinforcement wall 3 may be formed by shotcrete casting and may have a thickness of 4 to 6 cm, and the shotcrete and the injector are commonly used products.

(S30) 앵커공 천공.(S30) anchor hole perforation.

굴착된 평탄면에 천공기 등을 거치하여 기초 보강벽(3) 후방의 지중에 앵커공(2a)을 천공한다. 도면에서는 하나의 앵커공(2a)만을 천공한 것으로 도시하였으나, 기초 보강벽(3)에 폭방향을 따라 서로 같은 높이로 2개 이상의 앵커공(2a)을 천공한다. 앵커공(2a)의 앵커(1)의 크기 및 정착부의 위치에 따라 직경과 깊이 달라질 것이며, 이는 현장 여건(지반 상태)에 따라 달라지므로 구체적인 수치로 한정하지는 않는다.Anchor hole 2a is drilled in the ground behind the foundation reinforcement wall 3 by mounting a perforator on the excavated flat surface. Although only one anchor hole 2a is illustrated in the drawing, two or more anchor holes 2a are drilled at the same height in the width direction of the foundation reinforcing wall 3. Depending on the size of the anchor hole (2a) and the position of the fixing portion of the anchor hole (2a) will vary depending on the site conditions (ground condition), so it is not limited to specific values.

(S40) 키트와 앵커 설치.(S40) Kit and anchor installation.

전술한 본 발명에 의한 키트(10)를 앵커공(2a)의 입구측에 설치하고, 키트(10) 내부를 통하여 앵커(1)를 앵커공(2a)에 삽입한다. 앵커(1)는 정착부(1b)와 자유장(1a)으로 이루어지며, 정착부(1b)를 앵커공(2a)의 안쪽 바닥까지 삽입하고 자유장(1a)은 정착헤드(14)를 관통시켜 바깥쪽으로 인출한다. The kit 10 according to the present invention described above is installed at the inlet side of the anchor hole 2a, and the anchor 1 is inserted into the anchor hole 2a through the kit 10. The anchor 1 consists of a fixing part 1b and a free field 1a, inserts the fixing part 1b to the inner bottom of the anchor hole 2a, and the free field 1a penetrates the fixing head 14. To draw it outward.

(S50) 1차 긴장.(S50) primary tension.

긴장기(100)를 정착헤드(14)에 지지한 상태에서 자유장(1a)을 긴장기(100)에 연결한 후 자유장(1a)을 인장한다. 자유장(1a)을 인장하면 정착부(1b)가 지중에 정착됨과 아울러 제1지압판(11)을 통해 지압력이 작용되어 지반이 압축됨으로써 보강된다. 앵커(1)의 1차 긴장이 완료되면 앵커공(2a) 내부에 시멘트 밀크를 충전하거나 앵커공(2a)의 입구측만 시멘트 밀크를 채워 밀봉할 수 있다. 본 발명의 키트(10)는 현재 사용되고 있는 모든 앵커 즉, 자유장을 인장하면 정착부가 벌어져 앵커공에 정착되는 앵커(예컨대 본 출원인에 의해 등록된 특허 제746879호)에 적용될 수 있으며, 이러한 앵커에 대해서는 구체적으로 설명하지 않았지만, 당업자라면 충분히 실시할 수 있는 것이다.After the tensioner 100 is supported by the fixing head 14, the free field 1a is connected to the tensioner 100, and then the free field 1a is tensioned. When the free field 1a is tensioned, the fixing unit 1b is fixed in the ground, and the ground pressure is applied through the first pressure plate 11 to reinforce the ground. When the first tension of the anchor 1 is completed, the cement milk may be filled in the anchor hole 2a or the cement milk may be filled by sealing only the inlet side of the anchor hole 2a. The kit 10 of the present invention can be applied to all anchors currently used, that is, anchors (e.g., patent No. 746879 registered by the applicant) that anchor the anchoring hole when the tensioner is opened to secure the free field. Although not specifically described, it can be sufficiently carried out by those skilled in the art.

한편 굴착 이후 기초 보강벽(3)을 타설 양생 및 앵커를 시공한 동안 아래측을 굴착하여도 무방하기 때문에 윗단과 아랫단의 축차 진행이 가능하여 공기가 단축될 수 있다.On the other hand, after the excavation of the foundation reinforcing wall (3) during the construction of the curing and anchoring may be excavated the lower side, it is possible to proceed with the succession of the upper and lower ends can be shortened air.

이상의 공정을 통해 1단계의 시공이 완료되며, 이러한 공정을 지하를 향해 반복 수행함으로써 원하는 높이의 시공이 완료된다. 3단을 예로 들어 설명할 경우 전술한 바와 같이 1단을 시공한 후 1단의 아래측에 전술한 공정을 반복 수행하여 2단을 시공하고(S51), 2단의 시공이 완료된 후 3단을 시공한다(S60). 1단의 숏크리트 양생 후 2단의 굴착 등을 진행할 수 있고, 2단 숏크리트의 양생 후 3단의 굴착 등을 진행할 수 있으므로 공기를 단축할 수 있다.The construction of the first stage is completed through the above process, the construction of the desired height is completed by repeating this process toward the basement. In the case of explaining the third stage as an example, the first stage is constructed as described above, and the second stage is constructed by repeating the above-described process on the lower side of the first stage (S51), and the third stage is completed after the construction of the second stage is completed. Construct (S60). After one stage of shotcrete curing, two stages of excavation and the like can be carried out, and two stages of shotcrete can be carried out after three stages of excavation and the like, so that the air can be shortened.

1차 긴장력은 70~80%(2차 긴장력을 100%라 할 때 1차 긴장력을 70~80%로 함)로 할 수 있으며, 이는 제1지압판(11)의 지압면적이 작고 숏크리트의 강도가 콘크리트 옹벽보다 약하므로 과인장시 제1지압판(11)의 토사 내 관입을 예방하기 위함이다. 이와 같은 1차 긴장시에는 도 5에서 보이는 것처럼, 제1지압판(11)을 기점으로 하는 압축 분포선(F1)이 형성된다.The primary tension can be 70 to 80% (when the secondary tension is 100%, the primary tension is 70 to 80%), which means that the pressure area of the first pressure plate 11 is small and the strength of the shotcrete is Since it is weaker than the concrete retaining wall, it is to prevent infiltration of soil in the first acupressure plate 11 at the time of overtension. At such a first tension, as shown in FIG. 5, a compression distribution line F1 is formed starting from the first pressure plate 11.

(S70) 콘크리트 옹벽 시공.(S70) Concrete retaining wall construction.

(S60) 공정과 같이 원하는 높이의 굴착이 완료되면 기초 보강벽(3)의 전면에 거푸집(4)을 설치한다. 거푸집(4)은 콘크리트 옹벽(5)의 두께에 따라 설치 위치가 달라질 것이며, 단 키트(10)의 제2지압판(13)이 노출되는 위치로 설치된다. 거푸집(4)의 설치시 키트(10) 주변 보강과 최종 옹벽의 철근 배근 용이를 위해 보강 철근(20)(도 6참고)을 배근한다. 보강 철근(20)은 다수의 철근이 종횡방향으로 결합되어 예를 들어 육면체의 형태일 수 있으며 키트(10)의 주변을 덮도록 설치된다. 콘크리트 옹벽(5)의 강도 보강을 위하여 거푸집 내부에는 철근이 배근되며, 이 철근은 보강 철근(20)에 연결되어 배근될 수 있다.When the excavation of the desired height is completed as in step (S60), the formwork 4 is installed on the front surface of the foundation reinforcement wall 3. Formwork 4 will be installed according to the thickness of the concrete retaining wall (5), provided that the second pressure plate 13 of the kit 10 is exposed to the position. When installing the formwork (4) reinforce the reinforcing bar 20 (see Fig. 6) for the reinforcement around the kit 10 and easy reinforcement of the final retaining wall. Reinforcing bar 20 is a plurality of reinforcing bars are coupled in the longitudinal direction may be, for example in the form of a hexahedron and is installed to cover the periphery of the kit (10). In order to reinforce the strength of the concrete retaining wall 5, the reinforcing bar is arranged inside the formwork, which may be connected to the reinforcing bar 20 and reinforced.

거푸집(4)의 설치가 완료되면 거푸집(4)과 기초 보강벽(3) 사이에 콘크리트를 타설하여 양생한다. 콘크리트 옹벽(5)의 양생이 완료되면 거푸집(4)을 탈형한다.When the installation of the formwork (4) is completed, the concrete is poured between the formwork (4) and the foundation reinforcement wall (3) to cure. When curing of the concrete retaining wall 5 is completed, the formwork 4 is demolded.

(S80) 2차 긴장.(S80) 2nd tension.

긴장기(100)를 이용하여 앵커(1)의 자유장(1b)을 설계긴장력 100%로 긴장한다. 도 7에서 보이는 바와 같이, 제2지압판(13)을 분리한 후 긴장기(100)(긴장기와 지압판을 포함하는 것으로 기존에 사용되고 있는 것을 그대로 사용할 수 있음)를 콘크리트 옹벽(5)의 표면에 설치하여 2차 긴장한다. 이때의 압력 분포선(F2)은 긴장기(100)를 기점으로 하여 형성되어 1차 긴장때보다 큰 분포로 이루어진다.Using the tensioner 100, the free field 1b of the anchor 1 is tensioned to 100% of the design tension. As shown in FIG. 7, after removing the second pressure plate 13, a tensioner 100 (including a tensioner and a pressure plate may be used as it is) may be installed on the surface of the concrete retaining wall 5. 2nd tension. At this time, the pressure distribution line (F2) is formed from the tensioner 100 as a starting point is made of a larger distribution than the first tension.

참고로, 비탈면의 활동 안전율은 공사기간 중 Fs(Factor Safety) ≥ 1.0, 건기시 Fs ≥ 1.5, 우기시(지하수위 지표면 위치시) Fs ≥ 1.2 이상으로 비탈면 설계 기준에 규정되어 있다. 일반적인 사면은 대부분 우기시에 안전율이 부족하여 집중 호우시 사면의 활동파괴가 발생된다.For reference, slope safety activity is defined in slope design criteria during the construction period: Fs (Factor Safety) ≥ 1.0, dry season Fs ≥ 1.5, and rainy season (at ground level) Fs ≥ 1.2. Most slopes lack safety during the rainy season, resulting in the destruction of activities during heavy rains.

본 발명에서는 굴착 공사중에는 1차 긴장력을 최종 설계 긴장력의 70~80%로 긴장시에도 공사중 및 건기시 소요 안전율을 확보할 수 있고, 콘크리트 옹벽 타설후 우기시 안전율을 확보할 수 있도록 2차 긴장력을 설계긴장력 100%로 재긴장하는 것이다.In the present invention, during the excavation work, the primary tension force is 70-80% of the final design tension force to secure the required safety factor during construction and dry season even during tension, and the secondary tension force to ensure safety factor during the rainy season after the concrete retaining wall is placed. It is to re-tension to 100% of design tension.

도 1은 종래 기술에 의한 앵커 시공 상태도.1 is an anchor construction state diagram according to the prior art.

도 2는 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트의 사시도.Figure 2 is a perspective view of the tension kit for the top-down construction of acupressure permanent anchor according to the present invention.

도 3은 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트의 설치 상태 확대도.Figure 3 is an enlarged view of the installation state of the tension kit for the top-down construction of acupressure permanent anchor according to the present invention.

도 4는 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트를 이용한 지압형 영구 앵커의 탑다운 시공 방법의 공정도.Figure 4 is a process diagram of the top-down construction method of acupressure permanent anchor using a tension kit for the top-down construction of acupressure permanent anchor according to the present invention.

도 5는 본 발명에 의한 1차 긴장시의 상태도.Figure 5 is a state diagram at the time of the first tension according to the present invention.

도 6은 본 발명에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트를 이용한 지압형 영구 앵커의 탑다운 시공 방법에 적용된 보강철근을 보인 확대도.Figure 6 is an enlarged view showing the reinforcing bar applied to the top-down construction method of acupressure permanent anchor using a tension kit for the top-down construction of acupressure permanent anchor according to the present invention.

도 7은 본 발명에 의한 2차 긴장시의 상태도.Figure 7 is a state diagram at the time of the secondary tension according to the present invention.

< 도면의 주요 부분에 대한 부호 설명><Description of Signs for Main Parts of Drawings>

1 : 앵커, 2 : 법면1: anchor, 2: face

3 : 기초 보강벽, 5 : 콘크리트 옹벽3: foundation reinforcement wall, 5: concrete retaining wall

10 : 키트, 11,13 : 지압판10: kit, 11,13: pressure plate

12 : 케이싱, 14 : 정착헤드12: casing, 14: fixing head

20 : 보강철근, 20: rebar,

Claims (5)

삭제delete 굴착에 의한 법면에 지지되는 제1지압판(11)과;A first acupressure plate 11 supported on the surface by excavation; 원통형상이며 상기 제1지압판을 관통하여 지중에 매설되면서 지상으로 돌출되고 내부에는 지압형 영구 앵커의 긴장재가 통과되는 케이싱(12)과;A casing 12 having a cylindrical shape and penetrating the first pressure plate to be buried in the ground and protruding to the ground, and having a tension member of the acupressure permanent anchor therein; 상기 케이싱의 단부로부터 일정 거리 이격되도록 분리 가능하게 결합되며 긴장기가 거치되어 상기 제1지압판을 통해 법면을 지압하는 제2지압판(13)과; A second pressure plate (13) detachably coupled to be spaced apart from an end of the casing by a tensioner to pressurize the surface through the first pressure plate; 상기 케이싱의 둘레부에 원주방향을 따라 형성되는 다수의 보강리브(15)와; 그리고, A plurality of reinforcing ribs 15 formed along the circumferential direction of the circumference of the casing; And, 상기 제2지압판에 상기 제2지압판보다 돌출 형성되며 긴장기가 지지되는 원통형 정착헤드(14)를 포함하고, A cylindrical fixing head 14 protruding from the second acupressure plate and supported by a tensioner on the second acupressure plate, 상기 제2지압판은 판상으로 이루어지며 상기 정착헤드가 결합되는 지압부(13a), 상기 지압부에 관통 결합되며 상기 케이싱에 연결되는 연결부로 이루어진 것을 특징으로 하는 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트.The second acupressure plate is made in a plate shape for the top-down construction of the acupressure-type permanent anchor, characterized in that the acupressure part 13a to which the fixing head is coupled, the acupressure part is connected to the casing and connected to the casing. Tension kit. 삭제delete 지상에서부터 연직방향으로 일정 깊이를 1차 굴착하는 제1단계와;First digging a predetermined depth in the vertical direction from the ground; 상기 제1단계에 의해 형성된 1차 굴착된 법면(2)에 기초 보강벽(3)을 형성하는 제2단계와;A second step of forming a foundation reinforcement wall (3) on the primary excavated method (2) formed by the first step; 상기 제2단계에 의해 형성된 기초 보강벽과 지중에 지압형 영구 앵커의 시공을 위하여 앵커공(2a)을 천공하는 제3단계와;A third step of drilling an anchor hole (2a) for the construction of acupressure-type permanent anchor in the foundation reinforcement wall and the ground formed by the second step; 상기 제3단계서 천공된 앵커공의 입구측에 청구항 2에 의한 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트(10)를 설치하고, 상기 앵커공에 지압형 영구 앵커(1)를 삽입하는 제4단계와;At the inlet side of the anchor hole drilled in the third step, a tension kit for top-down construction of the acupressure permanent anchor according to claim 2 is installed, and the acupressure permanent anchor 1 is inserted into the anchor hole. Performing a fourth step; 상기 제4단계 이후 상기 키트의 제2지압판에 긴장기(100)를 지지한 상태에서 상기 지압형 영구 앵커의 긴장재를 1차 긴장시켜 지압하는 제5단계와;A fifth step of applying pressure by tensioning the tension member of the acupressure-type permanent anchor to a primary pressure in a state in which the tension device 100 is supported on the second pressure plate of the kit after the fourth step; 지중을 향하여 상기 제1 내지 제5단계를 반복 수행함으로써 원하는 높이의 법면을 형성한 후, 상기 모든 높이의 법면에 대해 기초 보강벽의 표면에서부터 상기 키트의 제2지압판이 노출되는 두께로 콘크리트 옹벽(5)을 시공하는 제6단계와; 그리고, After repeating the first to fifth steps toward the ground to form a normal surface of the desired height, the concrete retaining wall to a thickness that exposes the second pressure plate of the kit from the surface of the foundation reinforcement wall for the normal surface of all height ( A sixth step of constructing 5); And, 상기 제6단계완료 후 상기 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트의 제2지압판을 분리한 후 상기 콘크리트 옹벽의 표면에 긴장기를 설치하여 상기 앵커의 긴장재를 2차 긴장하여 지압하는 제7단계를 포함하는 것을 특징으로 하는 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트를 이용한 지압형 영구 앵커의 탑다운 시공 방법.After the sixth step is completed, after removing the second pressure plate of the tension kit for the top-down construction of the acupressure-type permanent anchor and install a tensioner on the surface of the concrete retaining wall secondary tension of the tension member of the anchor to pressure Top-down construction method of acupressure-type permanent anchor using a tension kit for the top-down construction of acupressure-type permanent anchor comprising a seven step. 청구항 4에 있어서, 상기 제5단계에서는 최종 설계 긴장력의 70~80%로 긴장하고, 상기 제7단계에서는 최종 설계 긴장력의 100%로 긴장하는 것을 특징으로 하는 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트를 이용한 지압형 영구 앵커의 탑다운 시공 방법.The method of claim 4, wherein in the fifth step, the tension of 70 ~ 80% of the final design tension, and in the seventh step for the top-down construction of the acupressure-type permanent anchor, characterized in that the tension to 100% of the final design tension Top-down construction method of acupressure permanent anchor using tension kit.
KR1020080030944A 2008-04-02 2008-04-02 Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this KR100862387B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080030944A KR100862387B1 (en) 2008-04-02 2008-04-02 Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080030944A KR100862387B1 (en) 2008-04-02 2008-04-02 Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this

Publications (1)

Publication Number Publication Date
KR100862387B1 true KR100862387B1 (en) 2008-10-13

Family

ID=40152996

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080030944A KR100862387B1 (en) 2008-04-02 2008-04-02 Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this

Country Status (1)

Country Link
KR (1) KR100862387B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101018771B1 (en) 2008-10-22 2011-03-07 나라앤텍 주식회사 Retaining wall applied by method soil-nailing construction
KR101086673B1 (en) * 2011-06-13 2011-11-24 (주)신승이앤씨 Construction method for expanding road for slope edge
CN108708756A (en) * 2018-08-31 2018-10-26 四川路桥华东建设有限责任公司 A kind of tunnel anchorage is interior to utilize the construction system and method that dissipate cable saddle buttress anchoring cat road head-rope
CN112695778A (en) * 2021-03-24 2021-04-23 北京市政建设集团有限责任公司 Accurate positioner with adjustable road bed bank protection

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01312164A (en) * 1988-06-09 1989-12-15 Kajima Corp Retension and anchoring method of tensile material
JPH05311665A (en) * 1992-05-12 1993-11-22 Kensetsu Kiso Eng Co Ltd Slope face protective structure
JPH0931993A (en) * 1995-07-24 1997-02-04 Daiwa Kogyo Kk Installation of pressure-receiving board for side slope protection
JPH0931996A (en) * 1995-07-17 1997-02-04 Kubota Corp Method for driving landslide-preventing pile, anchor base and landslide preventing pile
JPH09111761A (en) * 1995-10-17 1997-04-28 Nippon Steel Metal Prod Co Ltd Bearing pressure metal fitting for stabilizing slope and slope stabilizing method
JPH1193176A (en) 1997-09-22 1999-04-06 Nippon Steel Metal Prod Co Ltd Bearing member for method of slope stabilizing construction
JPH1193177A (en) 1997-09-22 1999-04-06 Nippon Steel Metal Prod Co Ltd Bearing member for method of slope stabilizing construction
JPH11303087A (en) 1998-04-16 1999-11-02 Kinki Nippon Railway Co Ltd Retaining wall using corrosion-resistant structure anchor
JP2000186326A (en) 1998-12-18 2000-07-04 Okabe Co Ltd Slope stabilizing method
JP2002275905A (en) 2001-03-14 2002-09-25 Toko Corp Separation type bearing plate
KR100793743B1 (en) 2007-08-13 2008-01-10 (주)엠케이 Method for fixing permanent anchor assembly and apparatus thereof

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01312164A (en) * 1988-06-09 1989-12-15 Kajima Corp Retension and anchoring method of tensile material
JPH05311665A (en) * 1992-05-12 1993-11-22 Kensetsu Kiso Eng Co Ltd Slope face protective structure
JPH0931996A (en) * 1995-07-17 1997-02-04 Kubota Corp Method for driving landslide-preventing pile, anchor base and landslide preventing pile
JPH0931993A (en) * 1995-07-24 1997-02-04 Daiwa Kogyo Kk Installation of pressure-receiving board for side slope protection
JPH09111761A (en) * 1995-10-17 1997-04-28 Nippon Steel Metal Prod Co Ltd Bearing pressure metal fitting for stabilizing slope and slope stabilizing method
JPH1193176A (en) 1997-09-22 1999-04-06 Nippon Steel Metal Prod Co Ltd Bearing member for method of slope stabilizing construction
JPH1193177A (en) 1997-09-22 1999-04-06 Nippon Steel Metal Prod Co Ltd Bearing member for method of slope stabilizing construction
JPH11303087A (en) 1998-04-16 1999-11-02 Kinki Nippon Railway Co Ltd Retaining wall using corrosion-resistant structure anchor
JP2000186326A (en) 1998-12-18 2000-07-04 Okabe Co Ltd Slope stabilizing method
JP2002275905A (en) 2001-03-14 2002-09-25 Toko Corp Separation type bearing plate
KR100793743B1 (en) 2007-08-13 2008-01-10 (주)엠케이 Method for fixing permanent anchor assembly and apparatus thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101018771B1 (en) 2008-10-22 2011-03-07 나라앤텍 주식회사 Retaining wall applied by method soil-nailing construction
KR101086673B1 (en) * 2011-06-13 2011-11-24 (주)신승이앤씨 Construction method for expanding road for slope edge
CN108708756A (en) * 2018-08-31 2018-10-26 四川路桥华东建设有限责任公司 A kind of tunnel anchorage is interior to utilize the construction system and method that dissipate cable saddle buttress anchoring cat road head-rope
CN112695778A (en) * 2021-03-24 2021-04-23 北京市政建设集团有限责任公司 Accurate positioner with adjustable road bed bank protection

Similar Documents

Publication Publication Date Title
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR100917044B1 (en) Concrete retaining wall construction method with dual wall jointed by anchor
KR100855098B1 (en) Strut structure as temporary system using a vertical truss at the end and the method thereof
WO2011114507A1 (en) Method of constructing underground structure to be newly built
KR100966148B1 (en) Ground adhering soil nailing structure and ground reinforcement method using the same
KR101510297B1 (en) A removable prestressing steel pipe soil nailing structure
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
JP4433066B2 (en) Wall structure with permanent anchor construction, wall construction method with permanent anchor construction,
KR101169732B1 (en) Earth anchor and retaining wall using it
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR200426634Y1 (en) Structure of Permanent Anchor
KR101175112B1 (en) Multipurpose nailing anchor and construction method thereof
JP5124007B2 (en) Retaining wall construction method
KR100770250B1 (en) Construnction method of retaining wall and retaining wall structure using the same
KR101078080B1 (en) Earth retaining wall and it&#39;s construction method using the precast pile and ground reinforcement
KR100842372B1 (en) Pretension soil nail method of top-down
JP2004293281A (en) Construction method for permanent anchor-applied wall structure and permanent anchor-applied wall structure
KR20080025219A (en) Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall
KR101864857B1 (en) Construction method of foundation pile with reinforced casing structure
KR101297679B1 (en) Self-supporting Temporary Structure Using Steel Wire And Method Of The Same
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
KR100793510B1 (en) Tension soil nail and construction method of underground wall using the same
KR200308379Y1 (en) Dismemberment removal type nail composition
KR100397958B1 (en) The structure timbering of cut with separating wale and the construction method thereof
KR101175741B1 (en) Double grouting injection module and earth reinforcing method using the same

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120928

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20130930

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140930

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20151001

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20161004

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20171010

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20181001

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20191001

Year of fee payment: 12