KR100793510B1 - Tension soil nail and construction method of underground wall using the same - Google Patents

Tension soil nail and construction method of underground wall using the same Download PDF

Info

Publication number
KR100793510B1
KR100793510B1 KR1020060127332A KR20060127332A KR100793510B1 KR 100793510 B1 KR100793510 B1 KR 100793510B1 KR 1020060127332 A KR1020060127332 A KR 1020060127332A KR 20060127332 A KR20060127332 A KR 20060127332A KR 100793510 B1 KR100793510 B1 KR 100793510B1
Authority
KR
South Korea
Prior art keywords
wall
underground
nail
tension
steel wire
Prior art date
Application number
KR1020060127332A
Other languages
Korean (ko)
Inventor
박시삼
주영수
박주석
Original Assignee
(주) 공인건설
지에스건설 주식회사
대한주택공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 공인건설, 지에스건설 주식회사, 대한주택공사 filed Critical (주) 공인건설
Priority to KR1020060127332A priority Critical patent/KR100793510B1/en
Application granted granted Critical
Publication of KR100793510B1 publication Critical patent/KR100793510B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • E02D5/805Ground anchors with deformable anchoring members
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A tension soil nail and a construction method of an underground wall using the same are provided to simplify excavation work and to minimize an interval between underground walls by building the underground continual walls vertically and repeating process of constructing the tension soil nail. A tension soil nail comprises a lower fixed member(120) and an upper fixed member(130) by nuts, and includes steel wires(150) for tensile force from the upper fixed member to the lower fixed member. The upper fixed member has a front bearing force plate(131) having a rectangular hole(131), a plate-shaped mounting body(133) having wedge holes(135), and wedges(136) inserted in the wedge holes to hold the steel wires. The lower fixed member has a female screw(121) and a steel wire through hole(122). A grouting material injection hole(123) is formed at the center of the lower fixed member.

Description

텐션 소일네일 및 이를 이용한 지하벽체의 시공방법{TENSION SOIL NAIL AND CONSTRUCTION METHOD OF UNDERGROUND WALL USING THE SAME}Tension Soil Nail and Construction Method of Underground Wall Using It {TENSION SOIL NAIL AND CONSTRUCTION METHOD OF UNDERGROUND WALL USING THE SAME}

도 1은 기존의 소일네일이 적용된 지하벽체의 구축상태를 나타낸 단면도,1 is a cross-sectional view showing a state of construction of an underground wall to which a conventional small nail is applied,

도 2a 내지 도 2f는 도 1의 지하벽체에 대한 시공과정을 나타낸 공정도,2a to 2f is a process diagram showing the construction process for the basement wall of FIG.

도 3은 도 1과 같이 기존 소일네일을 적용하여 수직 굴착하였을 때의 지반변위상태를 나타낸 도면,3 is a view showing a ground displacement state when vertical excavation by applying the existing small nail as shown in FIG.

도 4는 본 발명에 따른 일실시예의 텐션 소일네일을 나타낸 분해사시도,Figure 4 is an exploded perspective view showing a tension thumbnail of an embodiment according to the present invention,

도 5는 도 4의 조립 단면도,5 is an assembly cross-sectional view of FIG.

도 6은 본 발명에 따른 다른 실시예의 텐션 소일네일을 나타낸 분해사시도,6 is an exploded perspective view showing a tension thumbnail of another embodiment according to the present invention,

도 7은 도 6의 조립 단면도,7 is an assembly cross-sectional view of FIG.

도 8은 본 발명의 텐션 소일네일을 이용하여 구축한 지하벽체의 단면도,8 is a cross-sectional view of an underground wall constructed using the tension nail of the present invention,

도 9a 내지 도 9f는 도 8에서 지하연속벽체의 구축과정을 나타낸 공정도,9A to 9F are process diagrams illustrating a process of constructing an underground continuous wall in FIG. 8;

도 10a는 본 발명에 의하여 지하연속벽체가 구축 완료된 상태의 평면도,10a is a plan view of a state in which the underground continuous wall is completed in accordance with the present invention,

도 10b는 도 10a의 내측에서 바라 본 상태의 정면도이다.FIG. 10B is a front view of a state viewed from the inside of FIG. 10A.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100: 텐션 소일네일 110: 파이프100: tension thumbnail 110: pipe

120: 하부고정부재 121: 암나사120: lower fixing member 121: female thread

122: 강선관통공 123: 그라우팅재주입공122: steel wire through hole 123: grouting injection hole

130: 상부고정부재 131: 전면지압판130: upper fixing member 131: front pressure plate

132: 장방형홀 133: 정착몸체132: rectangular hole 133: fixing body

134: 파이프홀 135: 웨지홀134: pipe hole 135: wedge hole

136: 웨지 140: 너트136: wedge 140: nut

150: 강선 151: 외피150: liner 151: shell

160: 간격유지부재 200: 외벽160: spacing member 200: outer wall

220: 지하벽체220: underground wall

본 발명은 텐션 소일네일 및 이를 이용한 지하연속벽체의 시공방법에 관한 것으로서, 더욱 상세하게는, 평면에서 보았을 때 건축물의 벽체를 시공하고자 하는 형상대로 지하연속벽체를 시공하고 지하연속벽체의 내측을 굴착하면서 이 굴착으로 의해 현출된 지하연속벽체에 하향경사지게 텐션 소일네일을 시공하는 과정을 수회에 걸쳐 반복 시공한 다음 지하연속벽체의 내측에 건축물 본체인 지하벽체를 시공하는 공법을 채택함으로써 텐션 소일네일에 의해 지하연속벽체 주위의 지반보강이 이루어지고 건축물본체의 지하벽체두께를 줄일 수 있는 텐션 소일네일 및 이를 이용한 지하연속벽체의 시공방법에 관한 것이다.The present invention relates to a tension soil nail and a method for constructing a continuous wall using the same, and more particularly, to construct a continuous wall in the shape of the construction of the wall of the building in plan view and excavate the inner side of the underground continuous wall However, the process of constructing the tension sole nail to be inclined downward on the underground continuous wall exhibited by this excavation is repeated several times, and then adopts the method of constructing the underground wall which is the main body of the building inside the underground continuous wall. The present invention relates to a tension soil nail which can be reinforced with ground around a continuous underground wall and reduce the thickness of the underground wall of a building body, and a construction method of an underground continuous wall using the same.

통상, 지하연속벽체의 시공방법은 여러 가지가 알려져 있는데, 이들 중에서 네일(보강재)을 이용하여 지반보강을 하면서 소정깊이로 굴착, 즉 터파기한 후 그 내측에 지하벽체를 구축하고 있다. In general, various construction methods for the underground continuous wall are known. Among them, underground walls are constructed inside of them after excavation, ie, destruction at a predetermined depth while reinforcing the ground using nails (reinforcement materials).

기존의 소일네일을 이용하여 구축하는 지하벽체는, 도 1에 나타낸 바와 같이, 지면에서 하부로 굴착된 굴착측벽(10)에 1차 숏크리트(11)가 타설되어 있고, 이 1차 숏크리트(11)에 대하여 하향경사지게 소일네일(13)이 삽입 시공된 후 다시 2차 숏크리트(12)가 타설되어 있으며, 상기 2차 숏크리트(12)와 어느 정도 이격된 내측에 건축물본체인 지하벽체(14)가 타설되어 있고 상기 2차 숏크리트(12)와 지하벽체(14) 사이의 공간에 시멘트몰탈로 뒤채움한 뒤채움부(15)가 마련되어 있다. 상기 소일네일(13)은 강관이나 이형강봉을 사용하고 있다. As shown in FIG. 1, the primary shotcrete 11 is poured into the excavation side wall 10 excavated downward from the ground, and the primary shotcrete 11 is constructed as an existing underground nail using the existing small nail. Secondary shotcrete 12 is poured again after the small nail 13 is inserted and constructed to be inclined downwardly, and an underground wall 14, which is a main body of the building, is placed inside the spaced to some extent from the secondary shotcrete 12. In the space between the secondary shotcrete 12 and the subterranean wall 14, a back filling portion 15 backfilled with cement mortar is provided. The small nail 13 uses a steel pipe or a release steel bar.

상기와 같은 기존의 지하벽체 구조에서, 1차, 2차 숏크리트(11,12)의 두께는 a′이고 뒤채움부(15)의 두께는 b′이고, 지하벽체(14)의 두께는 c′로 표기하였다.In the existing underground wall structure as described above, the thickness of the primary and secondary shotcrete (11, 12) is a ', the thickness of the backfill portion 15 is b', the thickness of the underground wall 14 is c ' Indicated as.

상기와 같이 소일네일(보강재)을 이용하여 구축하는 지하연속벽체의 시공 과정에 대하여 상세하게 열거하여 본다. 먼저, 도 2a와 같이 굴착장비의 하나인 포크레인(21) 등을 이용하여 대략 1.5~3M 정도의 깊이까지 굴축측벽(10)을 갖도록 굴착하고, 도 2b와 같이 굴착측벽(10)의 표면에 굴착측벽(10)이 붕괴되지 않도록 하기 위하여 소정의 두께만큼 1차 숏크리트(shot-crete)(11)를 타설하여 양생시킨 다음, 도 2c와 같이 천공기(22)를 이용하여 하향경사지게 소일네일 설치용 구멍인 천공홀(23)을 천공한다. As described above, the construction process of the continuous continuous wall to be constructed by using a small nail (reinforcement material) will be listed in detail. First, the excavation side wall 10 is excavated to have a depth of about 1.5 to 3M by using a fork lane 21, which is one of the excavating equipments as shown in FIG. 2A, and excavation to the surface of the excavation side wall 10 as shown in FIG. 2B. In order to prevent the side wall 10 from collapsing, the first shotcrete 11 is poured by a predetermined thickness and cured, and then the hole for installing the nailnail is inclined downwardly using the perforator 22 as shown in FIG. The drilling hole 23 is drilled.

이후에 도 2d와 같이 상기 천공홀(23)로 소일네일(보강재)(13)을 삽입한 후 시멘트밀크 또는 시멘트몰탈 등을 주입하여 그라우팅하고, 도 2e와 같이 2차 숏크리트(12)를 타설하여 양생시킨 다음, 도 2f와 같이 다시 대략 1.5~3M 정도의 깊이까지 굴착측벽(10)을 갖도록 더 굴착한 후, 이후의 단계부터 도 2b부터 도 2e와 같은 공정을 수회에 걸쳐 반복함으로써 불규칙한 표면인 수직의 굴착측벽(10)을 갖는 상태로의 터파기 작업을 완료한다. 이때, 상기 소일네일(13)의 삽입깊이는 주동토압의 영역이 파괴선을 따라 거동되지 않도록 가상 파괴선을 넘어 수동토압의 영역까지 설치되어야 한다.Thereafter, as shown in FIG. 2D, the nail nail (reinforcement material) 13 is inserted into the drilling hole 23, and then cement grout or cement mortar is injected and grouted, and the second shotcrete 12 is poured as shown in FIG. 2E. After curing, it is further excavated to have the excavation side wall 10 to a depth of about 1.5 ~ 3M, as shown in Figure 2f, and then repeats the process as shown in Figure 2b to Figure 2e several times from a later step is an irregular surface The excavation work in the state which has a vertical digging side wall 10 is completed. At this time, the insertion depth of the small nail 13 should be installed to the area of passive earth pressure beyond the virtual destruction line so that the area of the main earth pressure does not move along the break line.

상기와 같이 도 2a 내지 도 2f의 순서대로 소일네일(13)을 소정깊이마다 시공하여 토체의 안정화를 꾀하면서 수직굴착하는 경우에는, 도 3에 나타낸 바와 같이 지면에서 소정깊이(H)로 수직의 굴착측벽(10)을 갖도록 굴착하였다면, 굴착측벽(10)의 상부가 터파기한 안쪽으로 변형되는 수평변위(δh)와, 이 수평변위(δh)에 상응하여 침하되는 수직변위(δv)가 공법상 발생되기 쉽고, 또한 터파기가 이루어진 굴착측벽(10)으로부터 일정거리(L1) 떨어진 배면위치에서도 수평변위(δO)가 발생되는 것으로 알려져 있다.In the case of vertical excavation while stabilizing the soil by constructing the small nails 13 at predetermined depths in the order of FIGS. 2A to 2F as described above, as shown in FIG. When excavation is carried out to have the excavation side wall 10, the horizontal displacement δh, which is deformed inwardly when the upper portion of the excavation side wall 10 is deformed, and the vertical displacement δv, which is settled corresponding to the horizontal displacement δh, It is known that a horizontal displacement δO is generated even at a rear surface position which is easy to be generated and is separated by a predetermined distance L1 from the excavation side wall 10 on which the trench is formed.

상기에서 설명한 바와 같이 소정의 깊이까지 터파기 작업(수직굴착)을 완료한 후에는 굴착측벽(10)의 내측위치에 배근작업과 거푸집을 설치하고, 상기 거푸집 내에 콘크리트를 타설하여 양생시킨 후, 거푸집을 철거하고 굴착측벽(10)의 2차 숏 크리트(12)와 지하벽체(14) 사이공간인 뒤채움부(15)에 콘크리트몰탈을 타설하여 뒤채움 작업을 수행함으로써 지하벽체의 시공을 완료한다. As described above, after completion of the excavation work (vertical excavation) to a predetermined depth, the reinforcement work and the formwork is installed in the inner position of the excavation side wall 10, the concrete is poured into the formwork and cured, Dismantle and finish the construction of the underground wall by placing concrete mortar in the back filling part 15, which is a space between the second shotcrete 12 and the underground wall 14 of the excavation side wall 10, and performing the back filling operation. .

그러나 상기와 같이 소일네일을 이용하여 터파기 후 지하벽체를 구축 시공하는 기존의 공법에 있어서는 굴착측벽(10)에 단순히 1,2차 숏크리트(11,12)를 타설하여 양생시킨 것인바, 그 강도가 취약할 수밖에 없으며, 이로 인하여 소일네일(13)의 시공을 위하여 천공기(22)로 천공할 때의 충격이나 진동 때문에 굴착측벽(10)에 국부적인 크랙이나 떨어지는 등의 파손이 발생되기 쉬운 것이었다.However, in the existing method of constructing and constructing an underground wall after digging using a small nail as described above, the primary and secondary shotcretes (11, 12) are simply cast on the excavation side wall (10), and the strength thereof. Is inevitably weak, because of this, due to the impact or vibration when drilling with the punching machine 22 for the construction of the small nail (13) was likely to cause local cracks or breakage, such as local cracks or falling on the excavation side wall (10).

또한 소일네일(13)은 수직으로 터파기한 굴착측벽(10)에 천공된 천공홀(23)로 삽입하고 그라우팅하는 것, 다시 말해서 소일네일을 이용하여 토체를 안정화시키는 것이나, 연약지반이므로 지면에서 소정깊이(H)로 터파기한 굴착측벽(10)의 상부가 쉽게 파손되는 등의 변위문제, 즉 수평변위(δh)와 수직변위(δv)가 발생된다는 단점을 가지고 있다. In addition, the small nail 13 is inserted and grouted into the drilled hole 23 in the excavated side wall 10 which has been vertically excavated, that is, stabilizing the soil by using the small nail, or because it is soft ground, Displacement problems, ie, a horizontal displacement δh and a vertical displacement δv, are generated such that the upper part of the excavation side wall 10 that has been excavated at the depth H is easily broken.

그리고 기존의 터파기 작업에서 포크레인(21) 등의 굴착장비를 이용하여 굴착측벽(10)을 굴착하기 때문에 불규칙한 곡면으로 굴착될 수밖에 없고 여기에 지하벽체(14)의 구축을 위한 거푸집의 설치 및 철거공간이 확보되어야 하므로 뒤채움공간이 넓어질 수밖에 없으며, 이로 인하여 2차 숏크리트(12)와 지하벽체(14) 사이의 넓은 뒤채움공간에 시멘트몰탈을 채워야 하는바 건설자재의 과다한 소비와 시공비가 증대된다는 문제점이 있었다.In addition, since the excavation side wall 10 is excavated by using excavation equipment such as a fork lane 21 in the conventional excavation work, there is no choice but to excavate an irregular curved surface and install and demolish the formwork for the construction of the underground wall 14 here. Since the space to be secured must be secured, the backfill space must be widened. As a result, a large backfill space between the secondary shotcrete 12 and the underground wall 14 must be filled with cement mortar. Therefore, excessive consumption of construction materials and construction costs are increased. There was a problem.

특히, 1차 숏크리트(11)가 타설된 굴착측벽(10)에 소일네일(13)이 삽입 설치되고 상기 1차 숏크리트(11)의 표면에 재차 2차 숏크리트(12)가 타설되어있기는 하 나, 구조적으로 벽체로서의 강도를 가질 수 없는 구조이므로 지하벽체(14)로서의 활용이 불가능하고, 여기에 뒤채움부(15)가 넓기 때문에 1,2차 숏크리트(11,12)와 뒤채움부(15) 및 지하벽체(14)를 포함하는 두께가 두꺼워질 수밖에 없으며, 이로 인하여 결국에는 건축면적이 줄어들게 된다는 문제점이 있었다.In particular, the small nail 13 is inserted into the excavation side wall 10 on which the primary shotcrete 11 is poured, and the secondary shotcrete 12 is poured on the surface of the primary shotcrete 11 again. Since it is structurally incapable of having strength as a wall, it cannot be used as an underground wall 14, and since the back filling portion 15 is wide, the first and second shotcretes 11 and 12 and the back filling portion 15 are wide. ) And the base wall 14 has to be thick, which in turn has a problem that the building area is reduced.

본 발명은 상기와 같은 종래의 제반 문제점을 해결하기 위해 연구 개발한 것으로서, 그 목적은, 평면에서 보았을 때 건축물의 벽체를 시공하고자 하는 형상대로 지하연속벽체를 시공하고, 지하연속벽체의 내측을 굴착하면서 이 굴착으로 의해 현출된 지하연속벽체에 하향경사지게 텐션 소일네일을 시공하는 과정을 수회에 걸쳐 반복 시공한 다음, 지하연속벽체의 내측에 건축물 본체인 지하벽체를 시공하는 공법을 채택함으로써, 텐션 소일네일에 의해 지하연속벽체는 물론 그 주위의 지반이 보강되어지고, 지하연속벽체를 건축물본체의 지하벽체로 활용할 수 있어 전체적인 건축물본체의 지하벽체두께를 줄일 수 있으며, 이로 인하여 지하벽체가 줄어드는 만큼의 건축면적을 늘일 수 있도록 한 텐션 소일네일 및 이를 이용한 지하연속벽체의 시공방법을 제공하는데 있다.The present invention has been researched and developed in order to solve the above-mentioned conventional problems, the object is to construct a continuous underground wall in the shape to intend the construction of the wall of the building when viewed in plan, and excavate the inner side of the underground continuous wall By repeating the process of constructing the tension sole nail down to the underground continuous wall exhibited by this excavation several times, and then adopting the method of constructing the underground wall which is the main body of the building inside the underground continuous wall. As well as the underground continuous wall by the nail, the surrounding ground is reinforced, and the underground continuous wall can be used as the underground wall of the building body, thereby reducing the thickness of the entire underground wall of the building body. Tension Soil Nails to Increase Construction Area and Construction Method of Underground Continuous Wall Using the Same To provide.

또한 본 발명은 굴착측벽에 1,2차 숏크리트를 타설하고 소일네일을 설치하는 기존 지하벽체의 시공방법과는 달리, 수직으로 지하연속벽체를 구축한 후에 그 내측을 굴착하면서 텐션 소일네일을 시공하는 과정을 수회에 걸쳐 반복 시공하므로 굴착작업의 단순화는 물론 시공이 용이하며, 굴착측벽이 수직이고 측벽표면이 비교 적 평탄하여 그 내측에 구축되는 지하벽체의 사이간격이 최소화되고 이로 인하여 뒤채움을 위한 건설자재를 절감과 그 작업시간을 줄일 수 있도록 한 텐션 소일네일 및 이를 이용한 지하연속벽체의 시공방법을 제공하는데 있다.In addition, the present invention, unlike the existing construction method of the construction of the existing underground wall to install the first and second shotcrete on the excavation side wall, and install the nail nail, after constructing the underground continuous wall vertically and excavating the inside of the tension soil nail Since the process is repeated several times, the excavation work is simplified and construction is easy, and the excavation side wall is vertical and the side wall surface is relatively flat, so that the gap between the underground walls built inside is minimized, thereby The present invention is to provide a tension sole nail and construction method of underground continuous wall using the same to reduce construction materials and reduce working time.

상기와 같은 목적을 달성하기 위한 본 발명은 네일(보강재)의 한쪽끝단에 하부고정부재가 고정되고 다른 한쪽끝단에 상부고정부재가 너트에 의해 체결 설치되되 상부고정부재에서 하부고정부재에 이르기까지 긴장력을 부여하기 위해 연결 설치된 강선을 포함하는 텐션 소일네일에 있어서, 상기 네일을 파이프로 사용하는 경우 시공여건이나 설계에 따라 선택적으로 파이프의 내측 또는 외측으로 강선을 관통시켜 텐션을 부여할 수 있는 것을 특징으로 한다. 이때, 강선은 외피가 씌워져 있는 것이며, 강선외측의 외피는 강선에 텐션을 부여하여 신장될 때 강선이 그 축방향으로의 유동을 허용하여야 한다.The present invention for achieving the above object is the lower fixing member is fixed to one end of the nail (reinforcement) and the upper fixing member is fastened and installed by the nut on the other end of the tension from the upper fixing member to the lower fixing member In the tension sole nail including a steel wire connected to provide a connection, when the nail is used as a pipe, the tension can be imparted by selectively passing the steel wire inside or outside the pipe according to the construction conditions or design. It is done. In this case, the steel wire is covered with an outer sheath, and the outer skin of the steel wire should be allowed to flow in the axial direction when the steel wire is tensioned and extended.

본 발명의 텐션 소일네일에 있어서, 상기 하부고정부재는 파이프 끝단외면과 체결을 위한 암나사가 형성되고 파이프의 내측 또는 외측으로 강선이 관통되도록 강선관통공이 형성되면서 중앙에 그라우팅재주입공이 형성된 캡형으로 마련됨이 바람직하다. In the tension nail of the present invention, the lower fixing member is provided with a cap type formed with a grouting material injection hole in the center while a steel thread through hole is formed so that a female thread for fastening with an outer surface of the pipe end is formed and a steel wire penetrates into or out of the pipe. This is preferred.

본 발명의 텐션 소일네일에 있어서, 파이프의 외측으로 강선이 설치되는 경우의 상부고정부재는, 적어도 인접하는 하나이상의 파이프가 관통되도록 장방형홀이 형성된 전면지압판과, 이 전면지압판과 접하여 설치되어 파이프의 외측에 강선 이 설치되는 웨지홀을 갖는 판형의 정착몸체와, 이 정착몸체의 웨지홀에 삽입되어 강선을 파지하는 웨지로 구성된다.In the tension nail of the present invention, the upper fixing member in the case where the steel wire is provided to the outside of the pipe, the front pressure plate formed with a rectangular hole so that at least one adjacent pipe passes therethrough, and is provided in contact with the front pressure plate to It consists of a plate-shaped fixing body having a wedge hole in which the steel wire is provided on the outside, and a wedge inserted into the wedge hole of the fixing body to grip the steel wire.

본 발명의 텐션 소일네일에 있어서, 파이프의 내측으로 강선이 관통되는 경우의 상부고정부재는, 적어도 인접하는 하나이상의 파이프가 관통되도록 장방형홀이 형성된 전면지압판과, 이 전면지압판과 접하여 설치되어 상기 파이프의 끝단 및 이에 체결되는 너트를 덮어씌우는 캡형으로 형성되고 상기 파이프의 내측에서 강선이 관통되는 웨지홀을 갖는 정착몸체와, 이 정착몸체의 웨지홀에 삽입되어 강선을 파지하는 웨지로 구성된다. In the tension nail of the present invention, the upper fixing member when the steel wire penetrates into the inside of the pipe includes a front pressure plate formed with a rectangular hole so that at least one adjacent pipe passes therethrough, and is provided in contact with the front pressure plate. It consists of a fixing body having a wedge hole formed in a cap shape to cover the end of the end and the nut is fastened to the inside of the pipe, and a wedge inserted into the wedge hole of the fixing body to grip the steel wire.

본 발명의 텐션 소일네일에 있어서, 상기 강선은 상부고정부재로부터 파이프끝단의 하부고정부재를 거쳐 상부고정부재로 되돌아와 상부고정부재에서 1가닥의 강선 양단을 고정시키거나, 2가닥의 강선을 이용하여 상부고정부재와 하부고정부재에 강선 단부가 각각 고정시킬 수 있다. In the tension sole nail of the present invention, the steel wire is returned from the upper fixing member to the upper fixing member through the lower fixing member at the end of the pipe to fix both ends of the steel wire in the upper fixing member, or using two strands of steel wire. The steel wire ends can be fixed to the upper fixing member and the lower fixing member, respectively.

또한 본 발명에 따른 텐션 소일네일을 이용한 지하연속벽체의 시공방법은, 평면에서 보았을 때 건축물의 지하벽체를 시공하고자 하는 형상대로 지하연속벽체를 시공하는 제1단계, 상기 지하연속벽체의 내측을 소정깊이까지 굴착하는 제2단계, 굴착으로 인해 현출된 지하연속벽체에 하향경사지게 소일네일설치용 구멍을 천공하는 제3단계, 상기 지하연속벽체의 소일네일설치용 구멍에 텐션 소일네일을 삽입하고 파이프 내면을 통해 그라우팅재를 주입하여 양생시킨 다음 강선을 인장하여 강선에 인장력을 부여하는 제4단계, 상기 제3 및 제4단계를 수회에 걸쳐 반복 시공하는 제5단계, 상기 제1단계부터 제5단계에 이르기까지 수행하여 얻은 지하연속벽 체의 내측에 배근 및 거푸집을 설치하고 시멘트몰탈을 타설하여 건축물 본체인 지하벽체를 시공하는 제6단계, 상기 제6단계에서 시멘트몰탈이 양생된 후 거푸집을 철거하고 지하연속벽체와 지하벽체 사이의 공간에 시멘트몰탈을 채워 뒤채움하는 제7단계로 되는 것을 특징으로 한다.In addition, according to the present invention, a method of constructing a continuous underground wall using a tension sole nail is a first step of constructing an underground continuous wall in a shape intended to construct an underground wall of a building when viewed in a plan view, and the inside of the underground continuous wall is predetermined. The second step of drilling to the depth, the third step of drilling the hole for the nail nail installation to be inclined downward to the underground continuous wall caused by the excavation, inserting the tension sole nail into the hole for the nail nail installation hole of the underground continuous wall and through the pipe inner surface Injecting and curing the grouting material and then tensioning the steel wire to give tensile force to the steel wire, the fifth step of repeating the third and fourth steps several times, the first step to the fifth step The construction of underground wall which is the main body of the building by installing the reinforcement and formwork inside the continuous continuous wall body obtained by After the cement mortar is cured in the sixth step and the sixth step, the formwork is removed and the seventh step of filling the cement mortar in the space between the continuous wall and the underground wall is filled.

상기 제1단계의 지하연속벽체를 시공하는 과정은 먼저 건축물의 지하벽체를 시공하고자 하는 형상대로 오거(auger), 하이드로 밀(hydro mill), 장방형의 연속벽 굴착기, 보링기 등의 굴착장비를 이용하여 소정형상의 트렌치(trench)를 굴착하고 상기 트렌치에 철근망이나 H형 강재, 강관, 시트파일(sheet pile), 패널(panel) 등의 응력재를 삽입설치한 후 시멘트몰탈을 타설하되 상기 트렌치를 소정간격으로 굴착하여 시공을 완료하여 선행패널을 구축한 다음 그 사이에 트렌치를 굴착하여 시공함으로써 연속적으로 구축되게 된다.The process of constructing the first continuous underground wall of the first step is to use excavation equipment such as auger, hydro mill, rectangular continuous wall excavator, boring machine and the like to construct the underground wall of the building. Excavate a trench of a predetermined shape and insert a stress material such as a reinforcing steel bar or H type steel, steel pipe, sheet pile, panel, etc., and then install cement mortar. After excavating at a predetermined interval to complete the construction to build the preceding panel and then to build a continuous by excavating the trench between the construction.

이하, 본 발명의 텐션 소일네일 및 이를 이용한 지하연속벽체의 시공방법을 첨부도면에 의거 상세하게 설명하고자 한다.Hereinafter, the construction method of the tension sole nail of the present invention and the underground continuous wall using the same will be described in detail with reference to the accompanying drawings.

도 4는 본 발명에 따른 일실시예의 텐션 소일네일을 나타낸 분해사시도이고, 도 5는 도 4의 조립 단면도이며, 도 6은 본 발명에 따른 다른 실시예의 텐션 소일네일을 나타낸 분해사시도이고, 도 7은 도 6의 조립 단면도이다.Figure 4 is an exploded perspective view showing a tension thumbnail of one embodiment according to the present invention, Figure 5 is an assembled cross-sectional view of Figure 4, Figure 6 is an exploded perspective view showing a tension thumbnail of another embodiment according to the present invention, Figure 7 Is an assembled cross-sectional view of FIG.

도면에 나타낸 바와 같이, 본 발명의 텐션 소일네일(100)은 보강재인 네일이 파이프(110)로 마련되며, 상기 파이프(110)의 한쪽끝단에 하부고정부재(120)가 체결 고정되어있고 다른 한쪽끝단에 상부고정부재(130)가 너트(140)에 의해 지지되어있다. 강선(150)은 상기 상부고정부재(130)에서 파이프(110)와 하부고정부재(120) 에 이르기까지 긴장력을 부여하기 위한 것이며, 시공여건이나 설계에 따라 선택적으로 파이프(110)의 내측 또는 외측으로 텐션을 부여할 수 있도록 설치된다. 상기 강선(150)은 외피(151)가 씌워져 있으며, 강선(150)외측의 외피(151)는 강선(150)에 텐션을 부여하여 신장될 때 강선(150)이 그 축방향으로의 유동을 허용할 수 있어야 한다.As shown in the figure, the tension nail of the present invention 100 is provided with a nail reinforcement as a pipe 110, the lower fixing member 120 is fastened and fixed to one end of the pipe 110 and the other The upper fixing member 130 at the end is supported by the nut 140. Steel wire 150 is to impart a tension force from the upper fixing member 130 to the pipe 110 and the lower fixing member 120, depending on the construction conditions or design selectively inside or outside the pipe 110 It is installed to give tension. The steel wire 150 is covered with an outer shell 151, the outer shell 151 of the outer steel wire 150 allows the steel wire 150 to flow in its axial direction when it is extended by applying tension to the steel wire 150 You should be able to.

상기 하부고정부재(120)는 파이프(110) 끝단외면과 체결을 위한 암나사(121)가 형성되고 파이프(110)의 내측 또는 외측으로 강선(150)이 안내되도록 강선관통공(122)이 형성되면서 중앙에 그라우팅재주입공(123)이 형성된 캡형으로 마련되어 있다. The lower fixing member 120 is formed with a female thread 121 for fastening with the outer surface of the end of the pipe 110 and the steel wire through-hole 122 is formed to guide the steel wire 150 to the inside or the outside of the pipe 110. Grouting material injection hole 123 is provided in the center cap shape.

상기 상부고정부재(130)는 강선이 파이프(110)의 내측으로 관통되는 경우와 파이프(110)의 외측에 설치되는 경우가 다르게 구성된다. 상기 파이프(110)의 외측으로 강선(150)이 설치되는 경우의 상부고정부재(130)는 도 4,5와 같이, 적어도 인접하는 하나이상의 파이프(110)가 관통되도록 장방형홀(132)을 갖는 전면지압판(131)이 마련되고, 이 전면지압판(131)에 접하여 설치되되 파이프(110)와 그 외측의 강선(150)이 관통되는 파이프홀(134)과 웨지홀(135)을 갖는 판형의 정착몸체(133)가 마련되며, 이 정착몸체(133)의 웨지홀(135)에 삽입되어 강선(150)을 파지하는 웨지(136)로 마련된다.The upper fixing member 130 is configured to be different from the case where the steel wire is penetrated to the inside of the pipe 110 and the outside of the pipe 110. When the steel wire 150 is installed to the outside of the pipe 110, the upper fixing member 130 has a rectangular hole 132 to pass through at least one or more adjacent pipe 110, as shown in Figs. The front pressure plate 131 is provided, it is installed in contact with the front pressure plate 131, the plate-shaped fixing having a pipe hole 134 and the wedge hole 135 through which the pipe 110 and the steel wire 150 of the outside passes through The body 133 is provided, and is inserted into the wedge hole 135 of the fixing body 133 and is provided as a wedge 136 for gripping the steel wire 150.

상기 파이프(110)의 내측으로 강선(150)이 관통되는 경우의 상부고정부재(130)는, 도 6,7과 같이 적어도 인접하는 하나이상의 파이프(110)가 관통되도록 장방형홀(132)을 갖는 전면지압판(131)이 마련되고, 이 전면지압판(131)에 접하여 설치되되 상기 파이프(110)의 끝단 및 이에 체결되는 너트(140)를 덮어씌우는 캡형으로 형성되고 상기 파이프(110)의 내측에서 강선(150)이 관통되는 웨지홀(135)을 갖는 정착몸체(133a)가 마련되며, 이 정착몸체(133a)의 웨지홀(135)에 삽입되어 강선(150)을 파지하는 웨지(136)로 마련된다. The upper fixing member 130 when the steel wire 150 penetrates into the pipe 110 has a rectangular hole 132 such that at least one adjacent pipe 110 penetrates as shown in FIGS. 6 and 7. The front pressure plate 131 is provided, is installed in contact with the front pressure plate 131 is formed in a cap shape covering the end of the pipe 110 and the nut 140 fastened thereto and a steel wire inside the pipe 110 A fixing body 133a having a wedge hole 135 through which the 150 is penetrated is provided, and is provided as a wedge 136 inserted into the wedge hole 135 of the fixing body 133a to grip the steel wire 150. do.

상기 파이프(110)는 강관으로 마련함이 바람직하나 비철금속관이나 섬유강화플라스틱(FRP: fiber reinforced plastics)파이프 등으로 마련할 수도 있다. The pipe 110 is preferably provided as a steel pipe, but may be provided as a non-ferrous metal pipe or a fiber reinforced plastics (FRP) pipe.

본 발명의 텐션 소일네일에서 타인의 대지경계로 침범하여 시공되더라도 타인의 대지공사에 악영향을 미치지 않아야 하므로 파이프(110)를 강관으로 적용하면 소일네일로는 시공할 수 없다. Even if the construction is invaded by the land boundary of others in the tension soil nail of the present invention should not adversely affect the land construction of others, if the pipe 110 is applied to the steel pipe can not be constructed as a small nail.

특히, 상기 파이프(110)를 섬유강화플라스틱으로 마련하면 지하연속벽체의 구축을 완료한 후에는 지하연속벽체를 관통하여 지중에 설치된 본 발명의 텐션 소일네일에서 강선(150)의 텐션을 해제한 후 강선끝단을 잡아당겨 강선만을 제거하기만 된다. 지중에 시공된 상태로 유지되는 섬유강화플라스틱의 파이프(110)는 파손되기 쉬운 재료인바 타인의 대지공사에 악영향을 미치지 않으므로 제거할 필요가 없다.In particular, when the pipe 110 is provided with fiber-reinforced plastic, after completing the construction of the underground continuous wall, the tension of the wire 150 is released from the tension sole nail of the present invention installed in the ground through the underground continuous wall. Pulling on the ends of the liner only removes the liner. Pipe 110 of fiber-reinforced plastic that is maintained in the ground construction does not need to be removed because it does not adversely affect the land work of others, which is a fragile material.

상기 상부고정부재(130)와 하부고정부재(120) 사이의 파이프(110)에는 파이프(110) 외측에 강선(150)이 설치되는 경우 강선(150)을 지지하는 복수개의 간격유지부재(160)가 설치되어 있다.In the pipe 110 between the upper fixing member 130 and the lower fixing member 120, when the steel wire 150 is installed outside the pipe 110, a plurality of gap maintaining members 160 supporting the steel wire 150 are provided. Is installed.

그리고 상기 강선(150)은 첨부도면과 같이 상부고정부재(130)로부터 파이프(110) 선단의 하부고정부재(120)를 거쳐 상부고정부재(130)로 되돌아와 상부고정 부재(130)에서 1가닥의 강선(150) 양단을 고정시키는 것으로만 도시하고 설명하였으나, 2가닥의 강선을 이용하여 상부고정부재와 하부고정부재에서 강선 단부를 각각 고정시킬 수 있음은 당연하다 할 것이다. The steel wire 150 is returned from the upper fixing member 130 to the upper fixing member 130 through the lower fixing member 120 at the tip of the pipe 110 as shown in the accompanying drawings, and has one strand at the upper fixing member 130. Although only shown and described as fixing both ends of the steel wire 150, it will be obvious that the steel wire ends can be fixed in the upper fixing member and the lower fixing member, respectively, using two strands of steel wire.

상기와 같이 구성된 본 발명의 텐션 소일네일을 이용하여 지하벽체를 구축하는 과정에 대하여 상세하게 설명하여 본다.It will be described in detail with respect to the process of building the underground wall using the tension nail of the present invention configured as described above.

먼저, 도 9a와 같이 평면에서 보았을 때 건축물의 지하벽체를 시공하고자 하는 형상대로 지하연속벽체인 외벽(200)을 시공한다. 상기 외벽(200)을 시공하는 과정은, 먼저 건축물의 지하벽체를 시공하고자하는 형상대로 오거(auger), 보링기 등의 굴착장비를 이용하여 원형이 연속 연결된 형상의 트렌치(trench)(201)를 설계치대로의 깊이로 굴착하고 상기 트렌치(201)에 시공설계에 따라 선택적으로 응력재(202)인 H형 강재를 삽입설치한 후 시멘트몰탈(203)을 타설하여 양생시킨다. First, as shown in FIG. 9A, the outer wall 200, which is a continuous continuous wall, is constructed in a shape that intends to construct an underground wall of a building. In the process of constructing the outer wall 200, a trench 201 having a circular shape is continuously connected using an excavation equipment such as an auger, a boring machine, and the like to construct an underground wall of a building. Excavation to the depth according to the design value and inserting the H-type steel, which is a stress material 202 selectively in the trench 201 according to the construction design, the cement mortar 203 is poured and cured.

상기 트렌치의 형상은, 하이드로 밀(hydro mill), 장방형의 연속벽 굴착기 등을 이용하여 직사각형으로 굴착할 수 있고 이렇게 직사각형의 트렌치(201)로 굴착하는 경우에는 이를 소정간격으로 굴착하여 선행패널의 시공을 완료한 다음 그 사이에 트렌치를 굴착하여 후행패널의 시공을 완료함으로써 연속적인 지하연속벽체가 구축되게 된다. 이러한 사각형의 트렌치에도 응력재(202)를 설치하여야 하는데, 상기 응력재(202)는 트렌치가 직사각형이므로 철근망이나 강관, 시트파일(sheet pile), 패널(panel) 등을 다양하게 적용할 수 있다.The trench may be excavated in a rectangular shape using a hydro mill, a rectangular continuous wall excavator, and the like in the case of excavation with a rectangular trench 201 at a predetermined interval to construct the preceding panel. After completing the process, excavation of the trench between them completes the construction of the trailing panel, so that a continuous underground continuous wall is constructed. The stress material 202 should also be installed in the rectangular trench. Since the trench is rectangular, the stress material 202 may be variously applied to rebar networks, steel pipes, sheet piles, panels, and the like. .

상기와 같이 지하연속벽체인 외벽(200)의 구축을 완료한 후에는 도 9a의 점선표시 부분인 외벽(200)의 내측을 도 9b와 같이 굴착하되, 굴착장비의 하나인 포 크레인(21) 등을 이용하여 대략 1.5~3M 정도의 깊이까지 굴착한다.After completing the construction of the outer continuous wall 200, which is an underground continuous wall as described above, excavate the inner side of the outer wall 200, which is a dotted line shown in FIG. 9A, as shown in FIG. Excavate to a depth of approximately 1.5 ~ 3M using.

상기와 같이 외벽(200)의 내측을 굴착함에 따라 현출된 외벽(200)에는 도 9c와 같이 천공장비인 천공기(22)를 이용하여 하향경사지게 소일네일설치용 구멍인 천공홀(23)을 천공하고, 이어서 도 와 같이 상기 외벽(200)의 천공홀(23)에 본 발명의 텐션 소일네일(100)을 삽입하여 마무리인장까지 완료한다. As the above-mentioned excavation of the inner side of the outer wall 200, the outer wall 200 is drilled down the perforated hole 23, which is a hole for installation of the nail nail, to be inclined downward using the perforator 22, which is a punching equipment, as shown in FIG. Subsequently, the tension sole nail 100 of the present invention is inserted into the perforation hole 23 of the outer wall 200 to complete the finish tension.

이때, 텐션 소일네일(100)의 시공과정은, 외벽(200)의 수평선상에 위치한 천공홀(23)로 텐션 소일네일(100)의 파이프(110)를 삽입하되, 텐션 소일네일(100)에서 전면지압판(131)과 정착몸체(133)를 제거한 상태에서 하부고정부재(120)가 지중으로 삽입되도록 한 후, 파이프(110)의 끝단에 그라우트호스를 연결하고 상기 그라우트호스를 통하여 파이프(110)내면으로 시멘트밀크나 시멘트몰탈인 그라우팅재를 가압 주입하여 양생시킨다.At this time, the construction process of the tension soil nail 100, the pipe 110 of the tension soil nail 100 is inserted into the drilling hole 23 located on the horizontal line of the outer wall 200, but in the tension soil nail 100 After removing the front pressure plate 131 and the fixing body 133, the lower fixing member 120 is inserted into the ground, and then the grout hose is connected to the end of the pipe 110, and the pipe 110 through the grout hose. The grouting material, either cement milk or cement mortar, is injected into the inner surface to cure.

이후에 외벽(200)의 수평선상에 가시공된 텐션 소일네일(100)중에서 서로 이웃하는 2개 이상의 텐션 소일네일(100)의 파이프(110)가 전면지압판(131)의 장방형홀(132)을 관통하여 돌출되게 설치하고, 상기 전면지압판(131)의 장방형홀(132)을 관통하여 돌출된 파이프(110)의 끝단은 정착몸체(133)의 파이프홀(134)에, 강선(150)의 끝단은 정착몸체(133)의 웨지홀(135)로 삽입 관통되도록 정착몸체(133)를 설치한 다음, 파이프(110)엔 너트(140)를 체결하고 웨지홀(135)엔 강선(150)이 파지되도록 웨지(136)를 설치한 후, 인장기로 강선(150)을 인장하여 강선(150)에 인장력을 부여한 후 인장기를 제거한다.Afterwards, the pipe 110 of the two or more tension sole nails 100 adjacent to each other among the tension soil nails 100 visible on the horizontal line of the outer wall 200 opens the rectangular hole 132 of the front pressure plate 131. It is installed to protrude through, the end of the pipe 110 protruding through the rectangular hole 132 of the front pressure plate 131 is in the pipe hole 134 of the fixing body 133, the end of the steel wire 150 The fixing body 133 is installed so as to be inserted into the wedge hole 135 of the fixing body 133, and then the nut 110 is fastened to the pipe 110 and the steel wire 150 is gripped by the wedge hole 135. After installing the wedge 136 as much as possible, tension the steel wire 150 with a tensioner to give a tensile force to the steel wire 150 and then remove the tensioner.

위에서 설명한 외벽(200)의 내측을 다시 소정깊이로 굴착하고 현출된 외 벽(200)에 천공장비인 천공기(22)를 이용하여 천공홀(23)을 천공하고, 상기 외벽(200)의 천공홀(23)에 본 발명의 텐션 소일네일(100)을 삽입하여 마무리인장까지 완료하는 과정을 수회에 걸쳐 반복 시공하여 도 9f와 같이 터파기 작업을 완료함으로써 외벽(200)을 얻는다.The inner side of the outer wall 200 described above is excavated again to a predetermined depth, and the punched hole 23 is drilled using the punching machine 22 which is a drilling equipment on the outer wall 200 that is present, and the punched hole of the outer wall 200. The outer wall 200 is obtained by inserting the tension sole nail 100 of the present invention in (23) and repeating it several times to complete the digging work as shown in FIG. 9F.

상기 지하연속벽체인 외벽(200)의 내측에 배근하고 거푸집을 설치한 다음, 시멘트몰탈을 타설하여 양생시킴으로써 건축물 본체인 지하벽체(220)를 구축하며, 지하벽체(220)의 시멘트몰탈이 양생되고 나면 거푸집을 철거하고 외벽(200)과 지하벽체(220) 사이의 공간에 시멘트몰탈을 채워 뒤채움 함으로써 도 8에 나타낸 바와 같은 건축물본체인 지하벽체(220)의 구축이 완료되게 된다. Reinforce the inside of the outer wall 200 which is the underground continuous wall and install the formwork, and then by pouring cement mortar to cure to build the underground wall 220 as a building body, the cement mortar of the underground wall 220 is cured and After the formwork is removed and the cement mortar is filled in the space between the outer wall 200 and the basement wall 220, the construction of the basement wall 220, which is the building body as shown in FIG. 8, is completed.

본 발명의 지하벽체 구조에서 외벽(200)의 두께는 a이고 뒤채움부의 두께는 b이고, 지하벽체(220)의 두께는 c로 표기하였듯이 외벽(200)이 수직상태여서 뒤채움부의 공간이 작아지므로 건설골재의 소모가 줄어들고 벽체의 전체가 두께가 줄어들게 된다.In the basement wall structure of the present invention, the thickness of the outer wall 200 is a and the thickness of the backfill portion is b, and the thickness of the basement wall 220 is represented by c. As the outer wall 200 is vertical, the space of the backfill portion is small. This reduces the consumption of construction aggregates and reduces the thickness of the entire wall.

이상에서 상세하게 설명한 바와 같이, 본 발명에 따른 텐션 소일네일 및 이를 이용한 지하연속벽체의 시공방법은, 평면에서 보았을 때 건축물의 벽체를 시공하고자 하는 형상대로 지하연속벽체를 시공하고, 지하연속벽체의 내측을 굴착하면서 이 굴착으로 의해 현출된 지하연속벽체에 하향경사지게 텐션 소일네일을 시공하는 과정을 수회에 걸쳐 반복 시공한 다음, 지하연속벽체의 내측에 건축물 본체인 지하벽체를 시공하는 공법을 채택함으로써, 텐션 소일네일에 의해 지하연속벽체는 물론 그 주위의 지반이 보강되어지고, 지하연속벽체를 건축물본체의 지하벽체로 활용할 수 있어 전체적인 건축물본체의 지하벽체두께를 줄일 수 있으며, 이로 인하여 지하벽체가 줄어드는 만큼의 건축면적을 늘일 수 있는 유용한 발명이다.As described in detail above, the construction method of the tension sole nail and the underground continuous wall using the same according to the present invention, the construction of the underground continuous wall in the shape to plan the construction of the wall of the building in plan view, By excavating the inside and repeating the process of constructing the tension soil nail down to the underground continuous wall that was exposed by this excavation several times, and then adopting the construction method of constructing the underground body which is the main body of the building inside the underground continuous wall. In addition, the underground continuous wall can be reinforced by tension tension nails, and the underground continuous wall can be used as the base wall of the building body, thereby reducing the thickness of the base wall of the entire building body. It is a useful invention that can increase the building area by decreasing.

또한 본 발명은 굴착측벽에 1,2차 숏크리트를 타설하고 소일네일을 설치하는 기존 지하벽체의 시공방법과는 달리, 수직으로 지하연속벽체를 구축한 후에 그 내측을 굴착하면서 텐션 소일네일을 시공하는 과정을 수회에 걸쳐 반복 시공하므로 굴착작업의 단순화는 물론 시공이 용이하며, 굴착측벽이 수직이고 측벽표면이 비교적 평탄하여 그 내측에 구축되는 지하벽체의 간격이 최소화되고 이로 인하여 뒤채움을 위한 건설자재를 절감과 그 작업시간을 줄일 수 있다.In addition, the present invention, unlike the existing construction method of the construction of the existing underground wall to install the first and second shotcrete on the excavation side wall, and install the nail nail, after constructing the underground continuous wall vertically and excavating the inside of the tension soil nail As the process is repeated several times, the excavation work is simplified and construction is easy, and the excavation side wall is vertical and the side wall surface is relatively flat, so that the gap between the underground walls to be built inside is minimized. Can reduce the working time.

Claims (6)

삭제delete 삭제delete 네일(보강재)의 한쪽끝단에 하부고정부재가 고정되고 다른 한쪽끝단에 상부고정부재가 너트에 의해 체결 설치되되 상부고정부재에서 하부고정부재에 이르기까지 긴장력을 부여하기 위해 연결 설치된 강선을 포함하는 텐션 소일네일에 있어서, The lower fixing member is fixed to one end of the nail (reinforcement material) and the upper fixing member is fastened and installed by the nut on the other end, and includes a tension wire connected to provide a tension force from the upper fixing member to the lower fixing member. For small nails, 파이프의 외측으로 강선이 설치된 상부고정부재는, 적어도 인접하는 하나이상의 파이프가 관통되도록 장방형홀이 형성된 전면지압판과, 이 전면지압판과 접하여 설치되어 파이프의 외측에 강선이 설치되는 웨지홀을 갖는 판형의 정착몸체와, 이 정착몸체의 웨지홀에 삽입되어 강선을 파지하는 웨지로 구성되고,The upper fixing member provided with steel wires on the outside of the pipe is a plate-shaped plate having a front pressure plate formed with a rectangular hole so that at least one adjacent pipe passes therethrough, and a wedge hole provided in contact with the front pressure plate to install a steel wire outside the pipe. A fixing body and a wedge inserted into a wedge hole of the fixing body and holding a steel wire, 하부고정부재는 파이프 끝단외면과 체결을 위한 암나사가 형성되고 파이프의 내측 또는 외측으로 강선이 관통되도록 강선관통공이 형성되면서 중앙에 그라우팅재주입공이 형성된 캡형으로 마련되는 것을 특징으로 하는 텐션 소일네일.The lower fixing member is a tension sole nail, characterized in that the female screw is formed for fastening with the pipe end outer surface and the steel wire through-hole is formed so that the steel wire penetrates into or out of the pipe. 삭제delete 삭제delete 평면에서 보았을 때 건축물의 지하벽체를 시공하고자 하는 형상대로 지하연속벽체를 시공하는 제1단계, 상기 지하연속벽체의 내측을 소정깊이까지 굴착하는 제2단계, 굴착으로 인해 현출된 지하연속벽체에 하향경사지게 소일네일설치용 구멍을 천공하는 제3단계, 상기 지하연속벽체의 소일네일설치용 구멍에 연속된 하나의 강선이 설치되어있는 텐션 소일네일을 삽입하고 파이프 내면을 통해 그라우팅재를 주입하여 양생시킨 다음 강선을 인장하여 강선에 인장력을 부여하는 제4단계, 상기 제3 및 제4단계를 수회에 걸쳐 반복 시공하는 제5단계, 상기 제1단계부터 제5단계에 이르기까지 수행하여 얻은 지하연속벽체의 내측에 배근 및 거푸집을 설치하고 시멘트몰탈을 타설하여 건축물 본체인 지하벽체를 시공하는 제6단계, 상기 제6단계에서 시멘트몰탈이 양생된 후 거푸집을 철거하고 지하연속벽체와 지하벽체 사이의 공간에 시멘트몰탈을 채워 뒤채움하는 제7단계로 되는 것을 특징으로 하는 텐션 소일네일을 이용한 지하벽체의 시공방법.When viewed from a plan, the first step of constructing the underground continuous wall in the shape of the construction of the underground wall of the building, the second step of excavating the inner side of the underground continuous wall to a predetermined depth, down to the underground continuous wall exhibited by the excavation In the third step of obliquely drilling the holes for installing the nail nail, insert a tension sole nail in which one continuous steel wire is installed in the small nail installation hole of the underground continuous wall, inject and cure the grouting material through the inner surface of the pipe, and then The fourth step of applying the tensile force to the steel wire by tensioning, the fifth step of repeating the third and fourth steps of construction several times, the inner side of the underground continuous wall obtained by performing the steps from the first step to the fifth step In the sixth step, the cement mortar in the sixth step to install the base wall and formwork in the building and to install the cement mortar, the underground wall which is the main body of the building A method of constructing an underground wall using a tension soil nail, characterized in that the seventh step of removing the formwork after curing and filling the mortar with cement mortar in the space between the underground continuous wall and the underground wall.
KR1020060127332A 2006-12-13 2006-12-13 Tension soil nail and construction method of underground wall using the same KR100793510B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060127332A KR100793510B1 (en) 2006-12-13 2006-12-13 Tension soil nail and construction method of underground wall using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060127332A KR100793510B1 (en) 2006-12-13 2006-12-13 Tension soil nail and construction method of underground wall using the same

Publications (1)

Publication Number Publication Date
KR100793510B1 true KR100793510B1 (en) 2008-01-14

Family

ID=39217434

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060127332A KR100793510B1 (en) 2006-12-13 2006-12-13 Tension soil nail and construction method of underground wall using the same

Country Status (1)

Country Link
KR (1) KR100793510B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101303534B1 (en) * 2011-09-05 2013-09-10 신세영 Apparatus for yieldable arch umbrella arch reinforcement and construction method for yieldable arch umbrella arch reinforcement
JP2017089319A (en) * 2015-11-16 2017-05-25 鹿島建設株式会社 Vertical shaft construction method
JP2020023818A (en) * 2018-08-07 2020-02-13 鹿島建設株式会社 Rectangular pit and its construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57104719A (en) 1980-12-18 1982-06-29 Kurosawa Kensetsu Kk Removal work for anchoring
JPH03262822A (en) * 1990-03-14 1991-11-22 Nittoc Constr Co Ltd Anchor trunk body
JPH0492042U (en) * 1990-12-27 1992-08-11
JPH04221117A (en) * 1990-12-20 1992-08-11 Taisei Corp Removal type anchoring
JPH0959976A (en) * 1995-08-28 1997-03-04 Katsumura Kensetsu Kk Fixing structure of anchor head section
US5730556A (en) 1992-07-01 1998-03-24 Keller Limited Removable ground anchor
KR20040008309A (en) * 2002-07-18 2004-01-31 홍지기술산업주식회사 Ground Stabilization Device and Method of Ground Stabilization Using the Device
KR20040008308A (en) * 2002-07-18 2004-01-31 홍지기술산업주식회사 Ground Stabilization Device and Method of Ground Stabilization Using the Device
KR20050050732A (en) * 2003-11-26 2005-06-01 (주) 코리아에스이 Anchor for ground and retaining wall structure using anchor

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57104719A (en) 1980-12-18 1982-06-29 Kurosawa Kensetsu Kk Removal work for anchoring
JPH03262822A (en) * 1990-03-14 1991-11-22 Nittoc Constr Co Ltd Anchor trunk body
JPH04221117A (en) * 1990-12-20 1992-08-11 Taisei Corp Removal type anchoring
JPH0492042U (en) * 1990-12-27 1992-08-11
US5730556A (en) 1992-07-01 1998-03-24 Keller Limited Removable ground anchor
JPH0959976A (en) * 1995-08-28 1997-03-04 Katsumura Kensetsu Kk Fixing structure of anchor head section
KR20040008309A (en) * 2002-07-18 2004-01-31 홍지기술산업주식회사 Ground Stabilization Device and Method of Ground Stabilization Using the Device
KR20040008308A (en) * 2002-07-18 2004-01-31 홍지기술산업주식회사 Ground Stabilization Device and Method of Ground Stabilization Using the Device
KR20050050732A (en) * 2003-11-26 2005-06-01 (주) 코리아에스이 Anchor for ground and retaining wall structure using anchor

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101303534B1 (en) * 2011-09-05 2013-09-10 신세영 Apparatus for yieldable arch umbrella arch reinforcement and construction method for yieldable arch umbrella arch reinforcement
JP2017089319A (en) * 2015-11-16 2017-05-25 鹿島建設株式会社 Vertical shaft construction method
JP2020023818A (en) * 2018-08-07 2020-02-13 鹿島建設株式会社 Rectangular pit and its construction method
JP7053402B2 (en) 2018-08-07 2022-04-12 鹿島建設株式会社 Rectangular shaft and its construction method

Similar Documents

Publication Publication Date Title
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR100917044B1 (en) Concrete retaining wall construction method with dual wall jointed by anchor
KR100913569B1 (en) Phc pile for retaining wall
KR101212972B1 (en) Retaining wall using multi reinforcment and construction method thereof
KR102082333B1 (en) Prestressed pile and Self reliance retaining wall construction method using the same
KR102312008B1 (en) Two Rows type Self reliance retaining wall construction method Using the Prestressed pile
CN109235490B (en) Retaining wall and construction method thereof
KR100415809B1 (en) precast pile for braced wall and the method using the same
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR101065017B1 (en) A shoring method using arch plate pile and H-Pile
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
KR100818504B1 (en) Tension soil nail and construction method of precast concrete panel using the same
KR100793510B1 (en) Tension soil nail and construction method of underground wall using the same
KR100546998B1 (en) Construction method of temporary apparatus of thnnel for direct digging
KR102113291B1 (en) Soil retaining wall using phc pile and construction method thererof
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR101032408B1 (en) Method of reinforced earth retaining wall for cutting face through reinforcing execution and concrete block
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
KR100562686B1 (en) The underground structure and it&#39;s construction method is using sheet pile and cast in a place concrete
KR100711054B1 (en) A construction method of concrete retaining wall using anchor
KR20180112453A (en) Soil Retaining Wall using PHC Pile and Construction Method
KR100401330B1 (en) A method of construction for earth-protection walls of building
JP2011157719A (en) Earth retaining method
KR100996848B1 (en) Soil nailing method and the ground reinforcement structure used soil nailing

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20130103

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140103

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150105

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20160104

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20170103

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180103

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20190103

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20200103

Year of fee payment: 13