JPH0931993A - Installation of pressure-receiving board for side slope protection - Google Patents
Installation of pressure-receiving board for side slope protectionInfo
- Publication number
- JPH0931993A JPH0931993A JP18729595A JP18729595A JPH0931993A JP H0931993 A JPH0931993 A JP H0931993A JP 18729595 A JP18729595 A JP 18729595A JP 18729595 A JP18729595 A JP 18729595A JP H0931993 A JPH0931993 A JP H0931993A
- Authority
- JP
- Japan
- Prior art keywords
- tendon
- formwork
- slope
- peripheral wall
- pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、法面保護用受圧板
の施工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a pressure receiving plate for slope protection.
【0002】[0002]
【従来の技術】従来の法面保護用受圧板の施工法として
は、図15に示すように、地中に打設されたアンカー(5
1)におけるテンドン(51a) の地上突出部を法面に設置さ
れた支圧板(53)の伝達筒(53a) に通し、テンドン(51a)
を仮緊張して支圧板(53)に仮定着した後、支圧板(53)上
に鉄筋籠(54)を取付け、支圧板(53)の周囲を囲むように
金網製型枠(55)を設置し、該型枠(55)内にコンクリート
(C) を吹付けて充填し、受圧板の形成後に、テンドン(5
1a) を本緊張して支圧板(53)に定着させていた。2. Description of the Related Art As a conventional construction method of a pressure receiving plate for slope protection, as shown in FIG. 15, an anchor (5
Pass the ground protrusion of the tendon (51a) in 1) through the transmission tube (53a) of the bearing plate (53) installed on the slope to the tendon (51a).
After provisionally tensioning and attaching it to the bearing plate (53), attach the rebar cage (54) on the bearing plate (53), and attach the wire mesh form (55) to surround the bearing plate (53). Install and place concrete in the formwork (55)
(C) is sprayed and filled, and after the pressure plate is formed, the tendon (5
1a) was permanently strained and fixed on the bearing plate (53).
【0003】[0003]
【発明が解決しようとする課題】しかしながら、上述し
た従来工法では、金網製型枠を設置するのに、トラック
クレーン等の大型機械が必要であるばかりでなく、金網
を組んで型枠を形成するのが面倒であった。本発明は、
施工にあたり、大型機械を必要とせず、しかも型枠を容
易に設置することができる法面保護用受圧板の施工法の
提供を目的とするものである。However, in the above-mentioned conventional method, not only a large machine such as a truck crane is required to install the wire netting mold, but also a wire net is assembled to form the mold. It was troublesome. The present invention
It is an object of the present invention to provide a method for constructing a pressure receiving plate for slope protection that does not require a large machine for construction and can easily install a formwork.
【0004】[0004]
【課題を解決するための手段】請求項1記載の発明は、
地中に打設されたアンカーにおけるテンドンの地上突出
部の周辺における法面に平面部を形成し、平面部に鉄筋
を所要形態に組んだ状態で配置した後、その上方から、
上壁、周壁、上壁の中央に形成されたテンドン挿通孔の
周縁から下方に伸び且つ周壁と同じ高さの筒状部および
グラウト供給ホースが接続される注入口を備えた組立式
合成樹脂製型枠を、テンドン挿通孔にテンドンの地上突
出部を通した状態で鉄筋に被せて平面部に設置し、テン
ドンを仮緊張して型枠に仮定着させた後、型枠内にコン
クリートまたはモルタルを注入充填して硬化させること
により受圧板を形成し、型枠を取外した後、テンドンを
本緊張して受圧板に定着させるものである。According to the first aspect of the present invention,
After forming a flat part on the slope around the ground protrusion of the tendon in the anchor cast in the ground, and arranging the flat part in a state where the reinforcing bars are assembled in the required form, from above,
Made of synthetic resin with an upper wall, a peripheral wall, a cylindrical part extending downward from the peripheral edge of the tendon insertion hole formed in the center of the upper wall and having the same height as the peripheral wall, and an injection port to which the grout supply hose is connected. Place the formwork on the flat part with the tendon insertion hole passing through the projecting part of the tendon over the rebar, and temporarily attach the tendon to the formwork and then attach it to the formwork, then concrete or mortar inside the formwork. Is filled and cured to form a pressure receiving plate, and after removing the mold, the tendon is fully tensioned and fixed to the pressure receiving plate.
【0005】請求項2記載の発明は、地中に打設された
アンカーにおけるテンドンの地上突出部の近傍における
法面を不陸整正した後、テンドンの地上突出部を中心と
して法面に鉄筋を所要形態に組んだ状態で配置した後、
その上方から、上壁、周壁、上壁の中央に形成されたテ
ンドン挿通孔の周縁から下方に伸び且つ周壁と同じ高さ
の筒状部およびグラウト供給ホースが接続される注入口
を備えた組立式合成樹脂製型枠を、テンドン挿通孔にテ
ンドンの地上突出部を通した状態で鉄筋に被せて平面部
に設置し、テンドンを仮緊張して型枠に仮定着させた
後、型枠の周壁下端と法面との間の隙間を塞ぐように型
枠補助部材を型枠の周壁外面の所要部分に沿わせて法面
に設置した後、型枠内にコンクリートまたはモルタルを
注入充填して硬化させることにより受圧板を形成し、型
枠を取外した後、テンドンを本緊張して受圧板に定着さ
せるものである。According to a second aspect of the present invention, the slope of the anchor placed in the ground in the vicinity of the above-ground protrusion of the tendon is rectified, and then the reinforcing bar is formed on the slope centering on the above-ground protrusion of the tendon. After arranging in a state where it is assembled into the required form,
An assembly including an upper wall, a peripheral wall, a cylindrical portion extending downward from the peripheral edge of a tendon insertion hole formed in the center of the upper wall and having the same height as the peripheral wall, and an inlet to which a grout supply hose is connected. The synthetic resin mold is placed on the flat part with the tendon insertion hole passing through the projecting part of the tendon over the rebar, and the tendon is temporarily tensioned and put on the formwork. After placing the formwork auxiliary member on the slope along the required part of the outer surface of the peripheral wall of the formwork so as to close the gap between the lower end of the peripheral wall and the slope, concrete or mortar is poured and filled into the formwork. The pressure receiving plate is formed by curing, the mold is removed, and then the tendon is fully tensioned and fixed to the pressure receiving plate.
【0006】[0006]
【発明の実施の形態】以下、本発明の実施の形態を図面
に従って説明する。図1に示すように、法面(N) から地
中の定着層へ向かってアンカー穴(1) を掘削し、該穴
(1) 内に、シース(2) に通されたテンドン(3) を挿入す
ると共に、グラウト材(4) を該穴(1) の開口部近くまで
充填することにより地中にアンカーを打設する。Embodiments of the present invention will be described below with reference to the drawings. As shown in Fig. 1, the anchor hole (1) was excavated from the slope (N) to the underground fixing layer, and the hole was formed.
Insert the tendon (3) passed through the sheath (2) into the (1) and fill the grout material (4) up to near the opening of the hole (1) to set the anchor in the ground. To do.
【0007】次に、図2に示すように、テンドン(3) の
上部から鋼製の保穴用管(5) をシース(2) に被せ通して
グラウト材(4) の上部に位置せしめ、アンカー穴(1) お
よびその周辺に不陸整正用モルタル(6) を流して平面部
(7) を形成する。Next, as shown in FIG. 2, a steel retaining tube (5) is put over the sheath (2) from the upper part of the tendon (3) and positioned on the upper part of the grout material (4). Pour the uneven mortar (6) into the anchor hole (1) and its surroundings, and
Form (7).
【0008】その後、図3に示すように、アンカーピン
(9) により平面部(7) 上にスペーサー(8) を介してエポ
キシ樹脂塗装鉄筋籠(11)を固定し、鉄筋籠(11)からシー
ス(2) に通されたテンドン(3) の地上突出部が上方へ突
出するようにする。Thereafter, as shown in FIG. 3, the anchor pin
(9) fix the epoxy resin coated rebar cage (11) on the flat part (7) via the spacer (8), and the ground of the tendon (3) passed from the rebar cage (11) to the sheath (2). The protrusion should protrude upward.
【0009】平面部(7) に鉄筋籠(11)を固定した後、図
4に示すように、その上方から、上壁(12a) 、周壁(12
b) 、上壁(12a) の中央に形成されたテンドン挿通穴(3
7)の周縁から下方に伸び且つ周壁(12b) と同じ高さの筒
状部(38)およびグラウト供給ホース(20)が接続される注
入口(39)を備えた平面からみて正方形の組立式硬質塩化
ビニル製型枠(12)を、その筒状部(38)およびテンドン挿
通穴(37)にテンドン(3)の地上突出部を通した状態で鉄
筋籠(11)に被せて平面部(7) に設置する。型枠(12)の周
壁(12b) および筒状部(38)の各下端部にはゴムパッキン
(13)が取付けられている。After fixing the rebar cage (11) to the flat portion (7), as shown in FIG. 4, from above, the upper wall (12a) and the peripheral wall (12
b), the tendon insertion hole (3) formed in the center of the upper wall (12a)
Assembled type that is square in plan view, with a cylindrical portion (38) extending downward from the peripheral edge of (7) and having the same height as the peripheral wall (12b) and an inlet (39) to which the grout supply hose (20) is connected. Form the rigid vinyl chloride formwork (12) over the reinforcing bar cage (11) with the tubular part (38) and the tendon insertion hole (37) passing the above-ground protruding part of the tendon (3) into the flat part ( Install in 7). Rubber packing is attached to the peripheral wall (12b) of the formwork (12) and each lower end of the tubular part (38).
(13) is installed.
【0010】型枠(12)は、その上壁(12a) の縁部と周壁
(12b) に形成された鍔部とをボルト(30a) およびナット
(30b) で締止めることにより、組立てられるようになさ
れている。(41)は、型枠(12)の周壁(12b) において注入
口(39)の上方に形成された排気口を示す。The formwork (12) consists of the edge of the upper wall (12a) and the peripheral wall.
The flange formed on (12b) and the bolt (30a) and nut.
It can be assembled by tightening at (30b). Reference numeral (41) denotes an exhaust port formed above the injection port (39) in the peripheral wall (12b) of the mold (12).
【0011】次に、型枠(12)の上壁(12a) 上に、該上壁
(12a) の全幅にわたって2本の鋼製角パイプ(14)を並列
に配置し、その上に支圧板(15)を配してその上からジャ
ッキ(16)によりテンドン(3) を仮緊張して型枠(12)に仮
定着させる。仮緊張力は型枠(12)内にコンクリートを充
填する際に該型枠(12)にかかる圧力に相当するものとす
る。上記仮緊張の際、型枠(12)の周壁(12b) および筒状
部(38)の各下端部に取付けられたゴムパッキン(13)が平
面部(7) に圧接することにより、型枠(12)内が水密状態
となされる。Next, on the upper wall (12a) of the formwork (12), the upper wall
The two steel square pipes (14) are arranged in parallel over the entire width of (12a), the pressure bearing plate (15) is arranged on it, and the tendon (3) is temporarily tensioned by the jack (16). The formwork (12). The temporary tension force corresponds to the pressure applied to the formwork (12) when the formwork (12) is filled with concrete. During the temporary tension, the rubber packings (13) attached to the peripheral wall (12b) of the mold (12) and the lower ends of the tubular part (38) are pressed against the flat surface (7) to form the mold. (12) The inside is made watertight.
【0012】なお、上記角パイプ(14)は井桁状に組んで
も良い。また、角パイプ(14)を型枠(12)の上壁(12a) に
配置した際に、該角パイプ(14)が滑らないような加工を
上壁(12a) に施しておくのが好ましい。The square pipe (14) may be assembled in a cross beam shape. Further, when the square pipe (14) is arranged on the upper wall (12a) of the formwork (12), it is preferable that the upper wall (12a) be processed so that the square pipe (14) does not slip. .
【0013】次に、図5に示すように、型枠(12)の注入
口(39)にグラウト供給ホース(20)を接続して、型枠(12)
内にコンクリートを注入充填する。そして、その硬化に
より、図6に示すように、受圧板(17)を形成せしめ、受
圧板(17)の強度を確認した後、型枠(12)を取外し、受圧
板(17)の中央に形成された貫通穴(43)に防錆油(18)を流
込み、受圧板(17)の上に支圧板(15)を配してその上から
ジャッキ(16)によりテンドン(3) を本緊張して受圧板(1
7)に定着させる。Next, as shown in FIG. 5, the grout supply hose (20) is connected to the inlet (39) of the mold (12) to form the mold (12).
Pour concrete into the inside. Then, by the curing, as shown in FIG. 6, the pressure receiving plate (17) is formed, and after confirming the strength of the pressure receiving plate (17), the form (12) is removed and the pressure receiving plate (17) is placed at the center. Pour the rust preventive oil (18) into the formed through hole (43), place the pressure bearing plate (15) on the pressure receiving plate (17), and then use the jack (16) to place the tendon (3) on it. Tension and pressure plate (1
Fix in 7).
【0014】なお、型枠(12)内にはコンクリートに代え
てモルタルを充填することもある。その後、図7に示す
ように、支圧板(15)上にヘッドキャップ(19)を装着する
と共に、該ヘッドキャップ(19)内に防錆油(18)を入れて
おく。また、受圧板(17)周辺の法面(N) には、植生基材
の厚層(21)を形成すると共に、受圧板(17)における法面
(N) の上手側部にツタ(22)を植生したり、或いは法面
(N) に植生シート(23)を張付けると共に、種子(24)を吹
付け、受圧板(17)における法面(N) の上手側部に植栽ボ
ックス(25)を配し、該ボックス(25)をロックボルト(26)
で法面(N) および受圧板(17)の上手側部に固定し、植栽
ボックス(25)内に低木(27)を植えたりする。The formwork (12) may be filled with mortar instead of concrete. Then, as shown in FIG. 7, the head cap (19) is mounted on the pressure bearing plate (15), and the rust preventive oil (18) is put in the head cap (19). In addition, a thick layer (21) of vegetation base material is formed on the slope (N) around the pressure receiving plate (17), and the slope on the pressure receiving plate (17) is also formed.
(N) Ivy (22) is vegetated on the right side or slope
While vegetation sheet (23) is attached to (N), seeds (24) are sprayed, and a planting box (25) is arranged on the upper side of the slope (N) of the pressure receiving plate (17), and the box is placed. Lock bolt (25) (26)
Secure the slope (N) and the pressure plate (17) to the upper side of the plant, and plant shrubs (27) in the planting box (25).
【0015】型枠(12)の筒状部(38)は、上述した防錆油
(18)が入れられる受圧板(17)中央の貫通穴(43)を形成す
ると共に、型枠(12)をアンカー打設後の平面部(7) に設
置するさいのすべり止めの役目をするものである。The cylindrical portion (38) of the form (12) is made of the above-mentioned rust preventive oil.
It forms a through hole (43) in the center of the pressure receiving plate (17) in which (18) is inserted, and also serves as a non-slip when installing the formwork (12) on the flat part (7) after anchoring. It is a thing.
【0016】図8は、法面の不陸が大きい場合における
本発明の他の実施形態を示す。地中にアンカーを打設し
た後、まず、アンカー穴(1) に不陸整正用モルタル(6)
を流し込んで該穴(1) を埋めた後、鉄筋籠(11)および型
枠(12)の設置を行い、型枠(12)の周壁(12b) 下端と法面
(N) 間に隙間(S) がある箇所について、該隙間(S) を塞
ぎ得る大きさに切断加工した硬質塩化ビニル製板状型枠
補助部材(28)を、隙間(S) を塞ぐように型枠(12)の周壁
(12b) 外面の所要部分に沿わせて法面(N) に配し、該型
枠補助部材(28)外面に接するようにして法面(N) にアン
カーピン(29)を打込むことにより、型枠補助部材(28)を
法面(N) に固定した後、型枠補助部材(28)の外面からそ
の外側の法面(N) にかけて発泡ポリウレタン樹脂(31)を
吹付けることにより、型枠補助部材(28)と法面(N) 間を
水密状態とするものである。FIG. 8 shows another embodiment of the present invention when the unevenness of the slope is large. After placing the anchor in the ground, first fix the uneven mortar (6) in the anchor hole (1).
After filling the hole (1) by pouring, the rebar cage (11) and the formwork (12) are installed, and the lower end of the peripheral wall (12b) of the formwork (12b) and the slope.
For places where there is a gap (S) between (N), use a plate-shaped frame auxiliary member (28) made of hard vinyl chloride that has been cut to a size that can close the gap (S), and close the gap (S). On the perimeter wall of the formwork (12)
(12b) By arranging on the slope (N) along the required part of the outer surface, and by driving the anchor pin (29) on the slope (N) so as to contact the outer surface of the formwork auxiliary member (28). After fixing the formwork auxiliary member (28) to the slope (N), by spraying the foamed polyurethane resin (31) from the outer surface of the formwork auxiliary member (28) to the outside slope (N), The space between the formwork auxiliary member (28) and the slope (N) is kept watertight.
【0017】上記2つの実施形態において、型枠(12)に
は、図9に示すように、平面からみて正方形のものを用
いたが、この形状に限定されず、図10〜図14に示す
ように、平面からみて、長方形型枠(32)、円形型枠(3
3)、十字形型枠(34)、正六角形型枠(35)、正八角形型枠
(36)等必要に応じて任意の形状の型枠を用いることがで
きる。In the above-described two embodiments, the formwork 12 has a square shape in plan view as shown in FIG. 9, but is not limited to this shape and is shown in FIGS. As seen from the plane, the rectangular formwork (32) and the circular formwork (3
3), cross-shaped formwork (34), regular hexagonal formwork (35), regular octagonal formwork
A mold of any shape can be used as necessary such as (36).
【0018】[0018]
【発明の効果】本発明の施工法は、型枠を法面に設置
し、型枠内にモルタルまたはコンクリートを注入して受
圧板を形成するようにしたものであり、型枠は合成樹脂
製であって軽量でありかつ組立式であるため、従来の金
網製型枠のようにトラッククレーン等の大型機械を必要
せず、型枠を分解した状態で人力により現場まで運んだ
後、作業者が該型枠を容易に組立てることができて便利
である。また、本発明の施工法は、合成樹脂製型枠内に
モルタル等を注入するものであるため、粉塵の発生、騒
音、振動が従来工法に比べて大幅に少なく、住宅が隣接
する場所での受圧板施工に最適である。According to the construction method of the present invention, a mold is installed on the slope and mortar or concrete is poured into the mold to form a pressure receiving plate. The mold is made of synthetic resin. Since it is lightweight, and it is an assembly type, it does not require a large machine such as a truck crane unlike the conventional wire mesh formwork, and after the formwork is disassembled it is manually transferred to the site and then the worker It is convenient because the mold can be easily assembled. Further, since the construction method of the present invention is to inject mortar and the like into the synthetic resin mold, the generation of dust, noise, and vibration are significantly less than those of the conventional construction method. Most suitable for pressure plate construction.
【0019】また、本発明の施工法によれば、従来の金
網製型枠内への吹付け工法と異なり、合成樹脂製型枠内
に流動性の良いモルタルまたはコンクリートを注入する
ものであるから、得られた受圧板は、水密性が高くボイ
ドの発生が少なくて仕上り面が美しいばかりか、モルタ
ルまたはコンクリートにセメント量が多くかつ早強型の
ものが使用でき、従来方法に比べて、小さい断面積で大
きなアンカー緊張力を受圧できる高強度の受圧板を経済
的に短期間に得ることができる。また、型枠は、合成樹
脂製であるため、依頼者の要求に応じて複雑な形状や色
とすることもできる。Further, according to the construction method of the present invention, unlike the conventional method of spraying into a wire mesh mold, mortar or concrete having good fluidity is poured into the synthetic resin mold. The obtained pressure plate has high watertightness, few voids, and has a beautiful finished surface.Moreover, mortar or concrete with a large amount of cement and a fast-strength type can be used, which is smaller than conventional methods. It is possible to economically obtain a high-strength pressure receiving plate having a cross-sectional area and capable of receiving a large anchor tension force in a short period of time. Further, since the mold is made of synthetic resin, it can have a complicated shape and color according to the request of the client.
【0020】更に、本発明の施工法は、受圧板を独立に
施工するものであるため、地層変化の激しい箇所や地盤
強度の弱い箇所で、アンカーにおけるテンドンの緊張に
伴う地盤沈下に受圧板が追随し、他の受圧板への影響が
ない。Further, in the construction method of the present invention, since the pressure-receiving plate is constructed independently, the pressure-receiving plate is not affected by the ground subsidence due to the tension of tendon at the anchor at a place where the formation changes drastically or a place where the ground strength is weak. It follows and has no effect on other pressure receiving plates.
【0021】請求項2記載の発明の場合、型枠の周壁下
端と法面との間の隙間を塞ぐように型枠補助部材を型枠
の周壁外面の所要部分に沿わせて法面に設置するもので
あるため、不陸が顕著な法面における受圧板の施工に適
している。According to the second aspect of the present invention, a mold auxiliary member is installed on the slope along a required portion of the outer surface of the peripheral wall of the mold so as to close the gap between the lower end of the peripheral wall of the mold and the slope. Therefore, it is suitable for construction of the pressure receiving plate on the slope where the unevenness is remarkable.
【図1】本発明におけるアンカーの打設状態を示す断面
図である。FIG. 1 is a cross-sectional view showing how an anchor is driven in the present invention.
【図2】本発明における法面の不陸整正状態を示す断面
図である。FIG. 2 is a cross-sectional view showing an unrectified state of a slope in the present invention.
【図3】本発明における鉄筋籠の設置状態を示す断面図
である。FIG. 3 is a cross-sectional view showing an installed state of a reinforcing bar cage according to the present invention.
【図4】本発明におけるテンドンの仮緊張状態を示す断
面図である。FIG. 4 is a cross-sectional view showing a temporary tension state of the tendon according to the present invention.
【図5】本発明における型枠へのモルタル等の注入状態
を示す断面図である。FIG. 5 is a cross-sectional view showing a state of injecting mortar or the like into a mold according to the present invention.
【図6】本発明における受圧板形成後のテンドンの本緊
張状態を示す断面図である。FIG. 6 is a cross-sectional view showing a main tension state of the tendon after forming the pressure receiving plate in the present invention.
【図7】テンドンの本緊張後における受圧板周辺の植生
工の実施形態を示す断面図である。FIG. 7 is a sectional view showing an embodiment of vegetation around the pressure receiving plate after the main tension of the tendon.
【図8】型枠補助部材を使用し、型枠と法面との隙間を
塞ぐ施工状態を示す断面図である。FIG. 8 is a cross-sectional view showing a construction state in which a mold frame auxiliary member is used to close a gap between the mold frame and a slope.
【図9】本発明における型枠の平面図である。FIG. 9 is a plan view of a mold according to the present invention.
【図10】本発明における型枠の変形例を示す平面図で
ある。FIG. 10 is a plan view showing a modified example of the mold according to the present invention.
【図11】本発明における型枠の他の変形例を示す平面
図である。FIG. 11 is a plan view showing another modified example of the mold according to the present invention.
【図12】本発明における型枠の他の変形例を示す平面
図である。FIG. 12 is a plan view showing another modification of the mold according to the present invention.
【図13】本発明における型枠の他の変形例を示す平面
図である。FIG. 13 is a plan view showing another modified example of the mold according to the present invention.
【図14】本発明における型枠の更に他の変形例を示す
平面図である。FIG. 14 is a plan view showing still another modified example of the mold according to the present invention.
【図15】従来の施工法を示す断面図である。FIG. 15 is a cross-sectional view showing a conventional construction method.
(3) :テンドン (7) :平面部 (11):鉄筋籠 (12):合成樹脂製型枠 (12a) :型枠の上壁 (12b) :型枠の周壁 (17):受圧板 (20):グラウト供給ホース (28):型枠補助部材 (37):テンドン挿入穴 (38):筒状部 (39):注入口 (3): Tendon (7): Plane part (11): Reinforcing bar cage (12): Synthetic resin formwork (12a): Formwork upper wall (12b): Formwork peripheral wall (17): Pressure plate ( 20): Grout supply hose (28): Formwork auxiliary member (37): Tendon insertion hole (38): Cylindrical part (39): Filling port
Claims (2)
ドンの地上突出部周辺における法面に平面部を形成し、
平面部に鉄筋を所要形態に組んだ状態で配置した後、そ
の上方から、上壁、周壁、上壁の中央に形成されたテン
ドン挿通孔の周縁から下方に伸び且つ周壁と同じ高さの
筒状部およびグラウト供給ホースが接続される注入口を
備えた組立式合成樹脂製型枠を、テンドン挿通孔にテン
ドンの地上突出部を通した状態で鉄筋に被せて平面部に
設置し、テンドンを仮緊張して型枠に仮定着させた後、
型枠内にコンクリートまたはモルタルを注入充填して硬
化させることにより受圧板を形成し、型枠を取外した
後、テンドンを本緊張して受圧板に定着させる、ことを
特徴とする法面保護用受圧板の施工法。1. A flat portion is formed on a slope around an overhanging portion of a tendon of an anchor placed in the ground,
After arranging the reinforcing bars in the required shape on the flat part, from above, extend downward from the peripheral wall of the upper wall, the peripheral wall, and the tendon insertion hole formed in the center of the upper wall, and have the same height as the peripheral wall. The assembly type synthetic resin mold with an injection port to which the shaped part and the grout supply hose are connected is placed on the flat part with the tendon insertion hole passing the above-mentioned protruding part of the tendon on the reinforcing bar, and the tendon is attached. After temporary tension and hypothetical fitting to the formwork,
Slope protection, characterized in that the pressure receiving plate is formed by pouring and filling concrete or mortar into the form and hardening it, and after removing the form, the tendon is fully tensioned and fixed on the pressure receiving plate. Construction method of pressure plate.
ドンの地上突出部の近傍における法面を不陸整正した
後、テンドンの地上突出部を中心として法面に鉄筋を所
要形態に組んだ状態で配置した後、その上方から、上
壁、周壁、上壁の中央に形成されたテンドン挿通孔の周
縁から下方に伸び且つ周壁と同じ高さの筒状部およびグ
ラウト供給ホースが接続される注入口を備えた組立式合
成樹脂製型枠を、テンドン挿通孔にテンドンの地上突出
部を通した状態で鉄筋に被せて平面部に設置し、テンド
ンを仮緊張して型枠に仮定着させた後、型枠の周壁下端
と法面との間の隙間を塞ぐように型枠補助部材を型枠の
周壁外面の所要部分に沿わせて法面に設置した後、型枠
内にコンクリートまたはモルタルを注入充填して硬化さ
せることにより受圧板を形成し、型枠を取外した後、テ
ンドンを本緊張して受圧板に定着させる、ことを特徴と
する法面保護用受圧板の施工法。2. After fixing the slope in the vicinity of the ground protrusion of the tendon of the anchor placed in the ground, rebar is assembled into the required shape around the ground protrusion of the tendon. After arranging in a state, the cylindrical portion and the grout supply hose extending downward from the upper wall, the peripheral wall, and the peripheral edge of the tendon insertion hole formed in the center of the upper wall and having the same height as the peripheral wall are connected. Place a prefabricated synthetic resin mold with a pouring port on the rebar with the tendon insertion hole through the ground protrusion of the tendon, and place it on the flat surface. Then, after installing the formwork auxiliary member on the slope along the required portion of the outer surface of the peripheral wall of the formwork so as to close the gap between the lower end of the peripheral wall of the formwork and the slope, concrete or Injecting and filling mortar and hardening it to form a pressure plate A method for constructing a pressure receiving plate for slope protection, which is characterized in that after forming and removing the formwork, the tendon is fully tensioned and fixed to the pressure receiving plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18729595A JPH0931993A (en) | 1995-07-24 | 1995-07-24 | Installation of pressure-receiving board for side slope protection |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18729595A JPH0931993A (en) | 1995-07-24 | 1995-07-24 | Installation of pressure-receiving board for side slope protection |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0931993A true JPH0931993A (en) | 1997-02-04 |
Family
ID=16203505
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18729595A Pending JPH0931993A (en) | 1995-07-24 | 1995-07-24 | Installation of pressure-receiving board for side slope protection |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0931993A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100506489B1 (en) * | 2004-11-05 | 2005-08-08 | 주식회사 오륙개발 | A method of construction for stability and afforestation of a sloping surface |
KR100858315B1 (en) * | 2008-04-08 | 2008-09-11 | 박태영 | Method of stabilization of slope using flowerbed and longitudinal type member for slope stabilization |
KR100862387B1 (en) * | 2008-04-02 | 2008-10-13 | 주식회사 신도이엔아이 | Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this |
JP2010106433A (en) * | 2008-10-28 | 2010-05-13 | Yahagi Construction Co Ltd | Slope reinforcing method |
KR102461148B1 (en) * | 2022-03-28 | 2022-11-01 | 주식회사 동운 | Slope reinforcement method and slope reinforcement structure using artificial rock blocks |
-
1995
- 1995-07-24 JP JP18729595A patent/JPH0931993A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100506489B1 (en) * | 2004-11-05 | 2005-08-08 | 주식회사 오륙개발 | A method of construction for stability and afforestation of a sloping surface |
KR100862387B1 (en) * | 2008-04-02 | 2008-10-13 | 주식회사 신도이엔아이 | Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this |
KR100858315B1 (en) * | 2008-04-08 | 2008-09-11 | 박태영 | Method of stabilization of slope using flowerbed and longitudinal type member for slope stabilization |
JP2010106433A (en) * | 2008-10-28 | 2010-05-13 | Yahagi Construction Co Ltd | Slope reinforcing method |
KR102461148B1 (en) * | 2022-03-28 | 2022-11-01 | 주식회사 동운 | Slope reinforcement method and slope reinforcement structure using artificial rock blocks |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100930829B1 (en) | Pannel have rockbolt coupler | |
US20220380996A1 (en) | Methods for constructing tensionless concrete pier foundations and foundations constructed thereby | |
JP2829825B2 (en) | Close-contact protection net construction method for falling rocks and its rope / net anchor structure | |
KR100467170B1 (en) | reinforced earth retaining wall construction method | |
KR102332144B1 (en) | Combined construction structure of pc pillar and pc beam for construction of warehouse | |
JPH0931993A (en) | Installation of pressure-receiving board for side slope protection | |
JP2004293281A (en) | Construction method for permanent anchor-applied wall structure and permanent anchor-applied wall structure | |
US20070068105A1 (en) | Concrete form | |
KR100661301B1 (en) | Support structure for concreting in a head of steel pile and construction method using it | |
KR20110136987A (en) | Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow | |
KR102043124B1 (en) | Functional anchor plate | |
KR101189041B1 (en) | Soundproofing walls using piles for constructing foundation and supporting posts and construction method the same | |
JP2003221831A (en) | Tightening device for bar-shaped member | |
JPH06207415A (en) | Slope stabilizing construction method | |
JP2003082680A (en) | Construction method for structural body using solidifying agent and formwork forming method | |
JP4111992B1 (en) | Foundation unit and foundation | |
KR102353664B1 (en) | Removal Pre-Stressed Beam and Construction Methods thereof | |
JP7537982B2 (en) | Pile head seismic isolation structure and construction method thereof | |
JPH06173273A (en) | Slope stabilizing construction method | |
JPS6136597Y2 (en) | ||
JPH0549768B2 (en) | ||
JP2922789B2 (en) | Formwork, its manufacturing method and slope stabilization method | |
JP2003253668A (en) | Member for tightening bar-like member | |
JPH04155013A (en) | Formwork on concrete subslab | |
JPH0549769B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 19990706 |