JP2003079054A - 蓄電池を備えた太陽光発電システム - Google Patents
蓄電池を備えた太陽光発電システムInfo
- Publication number
- JP2003079054A JP2003079054A JP2001264837A JP2001264837A JP2003079054A JP 2003079054 A JP2003079054 A JP 2003079054A JP 2001264837 A JP2001264837 A JP 2001264837A JP 2001264837 A JP2001264837 A JP 2001264837A JP 2003079054 A JP2003079054 A JP 2003079054A
- Authority
- JP
- Japan
- Prior art keywords
- power
- storage battery
- solar cell
- electric power
- cell device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010248 power generation Methods 0.000 title claims abstract description 92
- 238000007599 discharging Methods 0.000 claims description 16
- 230000005611 electricity Effects 0.000 claims description 9
- 229910052739 hydrogen Inorganic materials 0.000 claims description 8
- 239000001257 hydrogen Substances 0.000 claims description 8
- HBBGRARXTFLTSG-UHFFFAOYSA-N Lithium ion Chemical compound [Li+] HBBGRARXTFLTSG-UHFFFAOYSA-N 0.000 claims description 4
- OJIJEKBXJYRIBZ-UHFFFAOYSA-N cadmium nickel Chemical compound [Ni].[Cd] OJIJEKBXJYRIBZ-UHFFFAOYSA-N 0.000 claims description 4
- 229910001416 lithium ion Inorganic materials 0.000 claims description 4
- 238000006243 chemical reaction Methods 0.000 abstract description 2
- 230000000630 rising effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 11
- 230000003111 delayed effect Effects 0.000 description 6
- 230000005855 radiation Effects 0.000 description 5
- 238000004891 communication Methods 0.000 description 4
- 230000012447 hatching Effects 0.000 description 4
- 230000002123 temporal effect Effects 0.000 description 3
- 230000036962 time dependent Effects 0.000 description 3
- 229910021417 amorphous silicon Inorganic materials 0.000 description 2
- 230000002457 bidirectional effect Effects 0.000 description 2
- 229910021419 crystalline silicon Inorganic materials 0.000 description 2
- 238000010438 heat treatment Methods 0.000 description 2
- 101150000715 DA18 gene Proteins 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000000052 comparative effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000001816 cooling Methods 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000002803 fossil fuel Substances 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/28—Arrangements for balancing of the load in a network by storage of energy
- H02J3/32—Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/381—Dispersed generators
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J7/00—Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
- H02J7/34—Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
- H02J7/35—Parallel operation in networks using both storage and other dc sources, e.g. providing buffering with light sensitive cells
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02S—GENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES
- H02S40/00—Components or accessories in combination with PV modules, not provided for in groups H02S10/00 - H02S30/00
- H02S40/30—Electrical components
- H02S40/38—Energy storage means, e.g. batteries, structurally associated with PV modules
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/22—The renewable source being solar energy
- H02J2300/24—The renewable source being solar energy of photovoltaic origin
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
- Y02E10/56—Power conversion systems, e.g. maximum power point trackers
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E70/00—Other energy conversion or management systems reducing GHG emissions
- Y02E70/30—Systems combining energy storage with energy generation of non-fossil origin
Abstract
要の削減できるシステムを提供する。 【解決手段】 電力系統に連系し、太陽電池装置にて発
生される電力をインバータ装置に与えて、交流に変換
し、電力消費部に供給する太陽光発電システムにおい
て、太陽電池装置からの電力を充電する蓄電池と、太陽
電池装置からの電力を蓄電池またはインバータ装置に切
り替えて出力させる切り替え制御手段と、を備え、日の
出後の電力需要のオフピーク時内での太陽電池装置での
発電電力または夜間の電力系統からの電力から選ばれる
1つ以上の電力にて蓄電池を充電するように制御し、電
力需要の高い特定の時間帯の電力需要の変動曲線に応じ
て前記蓄電池に蓄電された電力の放電を制御し、太陽電
池装置からの発電量に加えてインバータ装置に電力を与
えることを特徴とする。
Description
太陽光発電システムに関し、電力需要の変動曲線に応じ
て出力を制御して電力需要時のピークに応じた最適な電
力出力を行う蓄電池を備えた太陽光発電システムに関す
る。
描き、それに比して夜間には大きく落ち込む。このよう
な電力需要の負荷格差は、季節間、昼夜間において、そ
の差が年々広がりつつある。特に、夏期の冷房需要の増
加に伴い、昼ピーク時の電力需要が大きくなっている。
電力不足による停電等の虞をなくすためには、最大の電
力需要に応じた発電量を確保する必要がある。
る。図12に、東京における代表的な電力の負荷曲線を
示す。なお、図12において縦軸は正規化している。こ
の図12に示すように、電力需要は、季節と時間に応じ
て、大きく変化する。最大電力需要に応じて、発電量を
確保するために、発電所を建設し、その需要に応じてい
ては、他の時間帯、季節においては、不要な発電所を増
やすことになる。
などの構築は、近年の地球環境問題などを考慮すると、
むやみに増大させることは好ましくない。
は、毎秒42兆kcalにも達し、世界の年間エネルギ
ー総需要量の約100倍という膨大な量である。この膨
大な太陽エネルギーを活用し、太陽エネルギーから電力
を得る太陽電池発電システムが注目されている。
季節、時間、場所そして天候などの影響を受けてすべて
を利用できない。日本全土平均で、一平方メートルの面
積に1日当たり、3.84kWh時の日射エネルギー量
がある。この日射量により太陽電池装置で、電力を得る
とすると、太陽電池の変換効率を10%と仮定しても1
日1平方メートル当たり0.38kWhの電力が得られ
る。
その発電電力により日中の消費電力を賄うとともに、余
剰電力を電力会社に売電する太陽光発電システムが実用
化されている。この太陽光発電システムとしては、現在
公称の発電設備容量が3kWのものが多く用いられてい
る。この3kWの太陽電池発電システムにより、上記の
日照条件から年間約2700kWhの発電がされる。
の太陽電池発電システムを設置したとすれば、年間約5
40億kWhの電力が得られることになる。この電力量
は日本の総発電量の6%程度に相当する。しかも、太陽
電池発電システムは、日射量が多い夏により多くの発電
量が得られる。
電力を有効に利用することで、特に、夏期の電力需要を
緩和し、ピーク時の電力を抑制することが期待できる。
ク時間より2時間から3時間ずれているので、単に太陽
電池発電システムで発電した発電電力をそのまま利用す
るのでは、ピーク需要の緩和には適したものとは言えな
い。
(Int.Cl.H02J 7/35)には、太陽電池
発電システムで発電した電力を蓄電池に充電させ、太陽
光発電量を所定時間遅延して商用電力に重畳させること
で、太陽電池発電システムで生成されたピークの電力を
商用電力の電力需要のピーク時に供給する太陽光発電出
力制御方式が提案されている。
れば、太陽電池発電システムの定格相当分の電力需要を
ピーク電力需要時に削減させることができる。しかし、
上記したシステムにおいては、太陽光発電量を所定時間
遅延させるために、日照時間でのピーク時までの発電電
力を蓄電池に充電させる必要があり、蓄電池の電池容量
が大きくなるという問題がある。
に、電力需要のピークは、季節によっても異なり、所定
時間遅延させるだけでは、各季節の電力需要に適した利
用にはならない。また、北海道では、冬は日没が早く、
工場などの稼働時間帯に家庭用の照明が灯されること、
また雪や寒波により暖房機器が高稼働になる等の要因に
より、東京、大阪などの他の地域とは異なり、冬季に最
大電力が発生する。このような地域では、太陽光発電量
を所定時間遅延させるだけでは、最大電力需要のピーク
を削減させることには寄与しない。
電池を用いて、電力需要のピーク時の時間帯のみ太陽光
発電量に蓄電池の放電量を重畳して与えることで、最適
なピーク電力需要の削減をできるシステム提供すること
を目的とする。
置にて発生される電力をインバータ装置に与え、このイ
ンバータ装置で交流に変換し、電力消費部に供給する太
陽光発電システムにおいて、電力を蓄電する蓄電池を備
え、電力需要の高い特定の時間帯の電力需要の変動曲線
に応じて前記蓄電池に蓄電された電力の放電を制御し、
前記インバータ装置に、前記太陽電池装置からの発電電
力とともに前記蓄電池からの電力を与えることを特徴と
する。
要のオフピーク時内での太陽電池装置での発電電力また
は夜間の電力系統からの電力から選ばれる1つ以上の電
力にて行えばよい。
陽電池装置にて発生される電力をインバータ装置に与
え、このインバータ装置で交流に変換し、電力消費部に
供給する太陽光発電システムにおいて、電力を蓄電する
蓄電池と、太陽電池装置からの電力を前記蓄電池または
インバータ装置に切り替えて出力させる切り替え制御手
段と、を備え、日の出後の電力需要のオフピーク時内で
の太陽電池装置での発電電力または夜間の電力系統から
の電力から選ばれる1つ以上の電力にて前記蓄電池を充
電するように制御し、電力需要の高い特定の時間帯の電
力需要の変動曲線に応じて前記蓄電池に蓄電された電力
の放電を制御し、前記インバータ装置に、前記太陽電池
装置からの発電電力とともに前記蓄電池からの電力を与
えることを特徴とする。
太陽電池装置にて発生される電力をインバータ装置に与
え、このインバータ装置で交流に変換し、電力消費部に
供給する太陽光発電システムにおいて、電力を蓄電する
蓄電池と、前記蓄電池の充放電を制御する制御手段と、
を備え、日の出後の電力需要のオフピーク時内での太陽
電池装置での発電電力または夜間の電力系統からの電力
から選ばれる1つ以上の電力にて前記蓄電池を充電する
ように制御し、電力需要の高い特定の時間帯の電力需要
の変動曲線に応じて前記蓄電池に蓄電された電力の放電
を制御し、前記インバータ装置に、前記太陽電池装置か
らの発電電力とともに前記蓄電池からの電力を与えるこ
とを特徴とする。
出から日没までの時間を100とし、日の出時間を0
%、日没時間を100%と表した場合、40から100
%の範囲である。
池装置からの発電量に重畳する時間帯は、太陽電池装置
の発電量のオフピーク時で且つ電力需要のピーク時であ
り、日の出から日没までの時間を100とし、日の出時
間を0%、日没時間を100%と表した場合、55から
85%の範囲であることを特徴とする。
の時間を100とし、日の出時間を0%、日没時間を1
00%と表した場合、55%までの最大の太陽電池装置
の発電量と電力需要ピーク時間帯の太陽電池装置の発電
量及び蓄電池の放電量を重畳した電力量がほぼ同じにな
るか大きくなるように前記蓄電池への蓄電量を制御する
ように構成することができる。
電池に充電する時間帯が、日の出から日没までの時間を
100とし、日の出時間を0%、日没時間を100%と
表した場合、0から40%の範囲にするとよい。
池1kW当たり、0.1から0.8kWhの範囲にする
とよい。
でに達した以降は、太陽電池装置の発電量は負荷に使用
され、余剰電力は電力系統に逆潮流するとよい。
ッケル・カドミウム蓄電池又はリチウムイオン電池の中
から選択するとよく、前記ニッケル・水素蓄電池の容量
が、太陽電池1kW当たり、0.125から1.0kW
hの範囲のものを用いればよい。
クの小さい朝方に発電した電力を蓄電池に充電し、電力
需要のピーク時の時間帯のみ太陽光発電量に蓄電池の放
電量を加えて与えるので、小さい電池容量の蓄電池で最
適なピーク時の最大電力の削減をはかることができる。
に基づいて説明する。図1は、この発明の第1の実施形
態にかかる太陽光発電システムを搭載した住宅を示す構
成図である。
陽電池装置1が設置される。この太陽電池装置1は、た
とえば、公称の発電設備容量が3kWのものであり、結
晶系シリコン太陽電池、非晶質シリコン太陽電池などの
太陽電池モジュールを所定の個数を並列、または直列に
接続して構成される。この太陽電池装置1から発電され
た直流電力が図示しない直流側開閉器を介して電流制御
部4に与えられる。この電流制御部4は、後述するよう
に、制御回路3の制御に基づき、太陽電池装置1からの
直流電力を蓄電池部2へ与えるか、インバータ装置5へ
与えるか切り替え制御を行う。この実施の形態として
は、インバータ装置5として、双方向インバータ装置を
用いている。
2へ与えると、蓄電池部2内に内蔵した蓄電池が充電さ
れる。太陽電池装置1からの直流電力がインバータ装置
5に与えられると、このインバータ装置5にて直流電力
が交流に変換され、交流電力が分電盤6を介して住宅の
コンセント等の電気系統に与えられ、家庭内負荷7に電
力が与えられる。
介して商用の電力系統8からも電力が供給されるように
構成されており、夜間など太陽電池装置1から供給され
る電力が不足した場合には、電力系統8からの電力が利
用できるように構成されている。
から与えられた交流電力を直流電力に変換する機能も有
しており、電力系統8からの電力を電流制御部4を介し
て蓄電池部2に与え、蓄電池部2の蓄電池を充電できる
ように構成されている。
備え、与えられた直流電力に基づき蓄電池が充電または
放電される。蓄電池部2の充放電制御は、蓄電池部2か
ら与えられる電圧等の信号に基づき制御回路3により行
われる。
2、インバータ装置5、分電盤6等の動作を制御する。
した電力が家庭内負荷の使用量以上の場合には、余った
電力を分電盤6から電力系統8に逆潮流し、余剰電力を
電力会社に売電する。また、電力系統8に停電が生じた
場合には、太陽電池装置1による電力供給により家庭内
の電気機器を作動させるように構成されている。
制御回路3の制御により、需要ピークの小さい朝方に発
電した電力を蓄電池部2へ充電する。そして、電力需要
ピーク時の時間帯のみに太陽電池装置1で発電した電力
に蓄電池部2から放電電力を加えるように、蓄電池部2
の充電、放電を制御するものである。
回路3は、CPU等により構成されたコントローラ3
1、データメモリ32、プログラムメモリ33、I/O
34で構成される。コントローラ31は、プログラムメ
モリ33に格納されたプログラムに従って、各回路を制
御する。データメモリ32は、各季節、気温、湿度など
の天候情報、地域等に応じた電力需要の変動曲線に基づ
いたデータが格納されている。
種パラメータにより電力需要の変動曲線は変化し、最大
ピーク時間帯、発受電総量などが変わる。データメモリ
32には、これらの各データが格納されている。
モリ32に格納された電力需要の変動曲線に基づいたデ
ータにより、コントローラ31は、蓄電池部2への充電
開始時間および充電終了時間、蓄電池部2からの放電開
始時間、放電量、放電時間等を制御する。コントローラ
31は、各種制御信号をI/O34から各回路へ与え、
各回路等からのデータはI/O34を介して、コントロ
ーラ31に与えられ、必要なデータはデータメモリ32
に格納される。
6ないし図8を参照してさらに説明する。図6は、大阪
(あるいは東京)における夏期の電力需要変動曲線と3
kWの太陽光発電システムの発電量の経時変化を示す図
である。図6において、日の出から日没までの時間を1
00とし、日の出時間を0%、日没時間を100%と表
している。太陽電池発電システムの発電量のピークは1
2時から13時であり、また、電力需要のピークは太陽
電池発電システムの発電量のピークより2時間程度遅く
なる。また、電力需要の高い時間帯は、日の出から日没
までの時間を100とし、日の出時間を0%、日没時間
を100%と表した場合、40から100%に当たる時
間帯である。
態からこの発明の第1の実施形態による太陽電池システ
ムの出力制御を行った場合を示す図であり、電力需要変
動曲線と電力の出力制御を行った時の出力の経時変化を
示す図である。この図7に示すように、早朝に太陽電池
装置1で発電した電力を蓄電池部2に充電し、その蓄電
池部2に蓄電した電力を14時から15時に放電し、1
4時から15時の電力を太陽電池装置1からの発電量に
加えて出力したものである。図7から分かるように、こ
の実施形態によれば、電力需要量が高くなる時間帯のほ
とんどを太陽電池システムからの電力で効率よく賄うこ
とができている。
8において、ハッチングを施しているのが、この発明の
実施形態により電力の出力制御を行った時の状態、白抜
きの部分は、太陽電池システムが発電した発電量を示し
ている。
で発電した電力を充電し、その蓄電した電力を14時か
ら15時に放電するように、制御回路3が蓄電池部2へ
の充電、蓄電池部2からの放電を制御する。
時半)から11時まで、白抜きの領域で示す量が太陽電
池装置1にて発電される。その発電した電力を蓄電池部
2へ与え、蓄電池部2に太陽電池装置1で発電した電力
を充電する。制御回路3は電流制御部4を制御し、太陽
電池装置1からの直流電流を蓄電池部2へ与え充電す
る。図8において、点々でハッチングを施しているもの
が充電されている電力量を示している。白抜きで示した
発電量のうち点々でハッチングを施しているa、b、c
で示している量の電力が蓄電池部2で充電される。
の電力を蓄電池が充電すると充電完了としている。制御
回路3は、蓄電池部2の電圧等をモニターし、蓄電池部
2内の蓄電池の充電が完了すると、電流制御部4を制御
し、太陽電池装置1からの直流電力をインバータ装置5
へ与えるように制御する。
間は電力需要のピーク時の前の11時まで設定している
が、8時台で蓄電池部2の充電が完了したので、制御回
路3は電流制御部4を制御し、太陽電池装置1からの電
力をインバータ装置5へ与えるように切り替えている。
蓄電池部2には、図8のa、b、cで示す発電量が蓄電
されたことになる。また、日照が足らず、11時までに
蓄電池部2が満充電にならなかった場合にも、制御回路
3は、蓄電池部2への充電を停止し、電流制御部4を制
御し、太陽電池装置1からの電力をインバータ装置5へ
与えるように制御する。
蓄電池、ニッケル・カドミウム蓄電池又はリチウムイオ
ン電池が好適である。これらの電池は、それぞれの特色
を持っており、それらの特色を勘案し、使用する状態を
考慮して、用いる蓄電池の種類を決めればよい。なお、
鉛電池は、後記の表に示すように、この発明の使用例で
は、大きな電池容量を必要とし、好ましくはない。
置1からの電力だけをインバータ装置5に与える。そし
て、最大ピーク時の14時になると、蓄電池部2に充電
されている電力を放電する。この実施形態では、14時
から16時まで2時間放電を行うように蓄電池部2を制
御し、太陽電池装置1からの電力に蓄電池部2からの電
力を加えて、インバータ装置5へ与える。図8に示すよ
うに、クロスにハッチングしているh、iの部分が蓄電
池部2からの放電電力である。14時から16時までの
間、太陽電池装置1の発電電力にクロスにハッチングし
ているh、iの電力がそれぞれ加えられて、ハッチング
で示す出力電力となる。この2時間で蓄電池部2に充電
された電力はすべて放電する。
らの発電量に重畳する時間帯は、太陽電池装置1の発電
量のオフピーク時で且つ電力需要のピーク時であり、日
の出から日没までの時間を100とし、日の出時間を0
%、日没時間を100%と表した場合、55から85%
の範囲となる。
から日没までの時間を100とし、日の出時間を0%、
日没時間を100%と表した場合、55%までの最大の
太陽電池装置1の発電量と電力需要ピーク時間帯の太陽
電池装置の発電量及び蓄電池の放電量を重畳した電力量
がほぼ同じになるか大きくなるように蓄電池部2への蓄
電量を制御している。
部2は電流制御部4を太陽電池装置1からの電力のみを
インバータ装置5に与えるように制御する。
光発電量を所定時間、例えば、2時間遅延させるシステ
ムとを比較する。図9は、図6に示す発電パターンを2
時間遅延させて、発電のピークを14時にした出力制御
したパターンの電力需要変動曲線と電力の出力制御を行
った時の出力の経時変化を示す図である。この従来の出
力制御を図10に従いさらに説明する。
2時間遅延の出力制御を行った時の状態(図9に示すも
のと同じ)、白抜きの部分は、太陽電池システムが発電
した発電量を示している。点々は蓄電池に充電されてい
る電力量、クロスにハッチングを施しているのが蓄電池
からの放電電力である。この図10から分かるように、
日の出から12時までの間、充電を行い、13時から蓄
電池の放電が始まる。すなわち、6時台、7時台の発電
電力a、bは全てされ、8時台の発電量から2時間前の
6時台の発電量を除いた発電量cが充電される。以下、
同様に発電量を2時間遅延させて、2時間前の発電量以
上の発電量eからgの部分が充電される。この例では、
日の出から12時まで、図10中のaからgまで電力の
充電を行うので、蓄電池の電池容量は3.16kWhは
必要となり、大きな電池容量の蓄電池が必要となる。そ
して、太陽電池装置1の発電出力を2時間遅延した状態
で出力するように、図中クロスのハッチングで施したよ
うに、太陽電池装置1からの発電電力に蓄電池から放電
電力を加えて出力される。
要が高くなる12時頃も発電した電力の1/3程度蓄電
池への充電に利用しているので、電力需要が高いにも関
わらず、太陽電池装置1からの電力をすべて用いること
ができないという難点もある。
合と2時間遅延させる上記比較例との電池容量を比較し
た。ここでは、蓄電池として、ニッケル・水素電池と鉛
電池を用いる場合を示している。
容量の蓄電池で最適な出力制御が行えることが分かる。
なお、ニッケル・カドミウム蓄電池又はリチウムイオン
電池を用いても同様に構成できる。
池部2からの放電を太陽電池装置1で発電し充電した電
力を2時間放電しているが、あらかじめ16時まで、す
なわち、15時から16時の重畳する電力量を電気系統
8より夜間電力を用いて蓄電池部2に充電しておき、太
陽電池装置1からの充電時間を増やすことなく放電時間
を3時間にすることもできる。なお、この場合、蓄電池
部2の蓄電池の容量はその分大きくなる。
京)における夏期の電力需要変動曲線に基づいて、充
電、放電制御を行った例を示しているが、他の季節、地
域はその時の電力需要変動曲線に基づいて充電、放電制
御を行えばよい。例えば、北海道であれば、放電開始す
る時間を15時あるいは16時にするなど、電力需要変
動曲線に応じて制御回路3が最適な充電、放電の制御を
行うように制御すればよい。
システムにおいて、最も日射量が大きい12時から13
時の発電量は、1.65kWh、14時から15時の発
電量は1.32kWhであり、14時から15時に加算
する蓄電池の放電量としては、0.33kWh(=1.
65−1.3)必要となる。従って、太陽電池1kWに
対して、0.1kWh(=0.33/3)より大きい蓄
電池容量があることが望ましい。
置1からの発電量に加える時間帯55%から85%の間
中最も大会太陽電池装置1の発電量と同じ電力量を得る
には、トータル2.18kWh(=0.12(13時)
+0.3(14時)+0.66(15時)+1.1(1
6時))の蓄電池の放電容量が必要となる。これは、太
陽電池1kWh当たり蓄電池の容量0.73kWhに相
当する。0.8kWhまでの電池容量があれば、この発
明の効果を満足させることができる。0.8kWh以上
の容量の蓄電池を使用することは電池及び制御回路のコ
ストも高くなるため、適当ではない。
慮した場合、充電深度0〜80%の間で充放電するのが
好ましいため、本システムに使用するニッケル・水素蓄
電池の定格容量としては、0.125(=0.1/80
×100)〜1(=0.8/80×100)の範囲とな
る。
図3に従い説明する。上記した第1の実施形態では、早
朝に太陽電池装置1で発電した電力で蓄電池部2を充電
していたが、曇りなど日照が不足する場合には、太陽電
池装置1で発電した電力では蓄電池部2への充電が十分
に行えない場合がある。そこで、この第2の実施形態で
は、天気予報により翌日の天候状態を考慮し、電気系統
8より夜間電力により蓄電池部2を充電するものであ
る。この図3の実施形態では、天気予報供給者9より、
翌日の時間別の天気、気温等がインターネット91を介
して交換局92から各住宅10に与えられる。各住宅1
0へは通信線93を介して天気予報供給者9からの天気
情報が制御回路3のデータメモリに格納される。制御回
路3は、与えられた天気予報情報に基づき、明日充電に
十分な発電電力が得られるか、また、気温などの条件か
ら電力消費が多くなるか否かを予測する。予測した最大
電力のピーク時に蓄電池部2から電力を必要とし、日照
の予報からあらかじめ決められた充電時間で蓄電池部2
への充電が不可能であると判断すると、予想した日照時
間で足らない分の充電用電力を夜間電力を用いて蓄電池
部2へ充電するように制御回路3が分電盤6、インバー
タ装置5、電流制御部4を制御し、蓄電池部2へ夜間電
力を用いて充電する。このよう構成することで、天気予
報を考慮し、安価な夜間電力を使用して、翌日の最大ピ
ーク時に加える電力を確保することができる。
り、電力需要ピーク時を予想し、蓄電池部2からの放電
開始時間、蓄電池部2への充電量等を制御するように構
成することもできる。
図4に従い説明する。上記した第2の実施形態では、天
気予報供給者9から天気情報を入手し、電気系統8より
夜間電力により蓄電池部2を充電するように構成した
が、この図4の実施形態では、電力会社20より、翌日
の電力需要ピーク情報等がインターネット21を介して
交換局22から各住宅10に与えられる。各住宅10へ
は通信線23を介して電力会社20からの電力需要ピー
ク情報が制御回路3のデータメモリに格納される。制御
回路3は、与えられた電力需要ピーク情報に基づき、蓄
電池部2への充電量、放電量を予測する。予測した最大
電力のピーク時に蓄電池部2から電力を必要とし、あら
かじめ決められた充電時間で蓄電池部2への充電が不可
能であると判断すると、日照時間で足らない分の充電用
電力を夜間電力を用いて蓄電池部2へ充電するように制
御回路3が分電盤6、インバータ装置5、電流制御部4
を制御し、蓄電池部2へ夜間電力を用いて充電する。こ
のように構成することで、電力会社20から与えられる
電力需要ピーク情報に合わせて、安価な夜間電力を使用
して、翌日の最大ピーク時に加える電力を確保すること
ができる。
電池部2からの放電開始時間、蓄電池部2への充電量等
を制御するように構成することもできる。
してデータを送るように構成しているが、電力線をデー
タ通信用に兼用しても用い、電力線を用いてデータ通信
を構成することもできる。
図5に従い説明する。上記した第2の実施形態では、天
気予報供給者9から天気情報を入手し、電気系統8より
夜間電力により蓄電池部2を充電するように構成した
が、この図5の実施形態では、各住宅に自動天気予報計
25を設け、自動天気予報計25の天気予報により翌日
の天候状態を考慮し、電気系統8より夜間電力により蓄
電池部2を充電するものである。この図4の実施形態で
は、天気予報計25から翌日の時間別の天気、気温等の
天気情報が制御回路3のデータメモリに格納される。制
御回路3は、与えられた天気予報情報に基づき、明日充
電に十分な発電電力が得られるか、また、気温などの条
件から電力消費が多くなるか否かを予測する。予測した
最大電力のピーク時に蓄電池部2から電力を必要とし、
日照の予報からあらかじめ決められた充電時間で蓄電池
部2への充電が不可能であると判断すると、予想した日
照時間で足らない分の充電用電力を夜間電力を用いて蓄
電池部2へ充電するように制御回路3が分電盤6、イン
バータ装置5、電流制御部4を制御し、蓄電池部2へ夜
間電力を用いて充電する。このように構成することで、
天気予報を考慮し、安価な夜間電力を使用して、翌日の
最大ピーク時に加える電力を確保することができる。
電力需要ピーク時を予想し、蓄電池部2からの放電開始
時間、蓄電池部2への充電量等を制御するように構成す
ることもできる。
ては、インバータ装置5として、双方向インバータ装置
を用いたが、通常のインバータ装置を用いた第5の実施
形態につき図11を参照して説明する。図11は、第1
の実施形態の構成を通常のインバータ装置を用いて構成
した場合の構成図である。
太陽電池装置1が設置される。この太陽電池装置1は、
たとえば、公称の発電設備容量が3kWのものであり、
結晶系シリコン太陽電池、非晶質シリコン太陽電池など
の太陽電池モジュールを所定の個数を並列、または直列
に接続して構成される。この太陽電池装置1から発電さ
れた直流電力が図示しない直流側開閉器を介してインバ
ータ装置5a及び充放電制御部4aに与えられる。この
充放電制御部4aは、後述するように、制御回路3の制
御に基づき、太陽電池装置1からの直流電力を蓄電池部
2へ与えて蓄電池部2の蓄電池を充電したり、蓄電池部
2から放電電力をインバータ装置5へ与える制御を行
う。また、この実施形態では、電力系統8から与えられ
た交流電力を直流電力に変換する充電回路51を備えて
おり、充電回路51からの直流電力が充放電制御部4a
を介して蓄電池部2に与えられ、蓄電池部2の蓄電池を
充電できるように構成されている。
御部4aを介して蓄電池部2へ与えると、蓄電池部2内
に内蔵した蓄電池が充電される。太陽電池装置1からの
直流電力がインバータ装置5に与えられると、このイン
バータ装置5にて直流電力が交流に変換され、交流電力
が分電盤6を介して住宅のコンセント等の電気系統に与
えられ、家庭内負荷7に電力が与えられる。
介して商用の電力系統8からも電力が供給されるように
構成されており、夜間など太陽電池装置1から供給され
る電力が不足した場合には、電力系統8からの電力が利
用できるように構成されている。
ら与えられる電圧等の信号に基づき制御回路3により行
われる。
部2、インバータ装置5a、分電盤6等の動作を制御す
る。
した電力が家庭内負荷の使用量以上の場合には、余った
電力を分電盤6から電力系統8に逆潮流し、余剰電力を
電力会社に売電する。また、電力系統8に停電が生じた
場合には、太陽電池装置1による電力供給により家庭内
の電気機器を作動させるように構成されている。
制御回路3の制御により、需要ピークの小さい朝方に発
電した電力を蓄電池部2へ充電する。そして、電力需要
ピーク時の時間帯のみに太陽電池装置1で発電した電力
に蓄電池部2から放電電力を加えるように、蓄電池部2
の充電、放電を制御するものである。
さらに説明する。第1の実施形態と同じく、早朝に太陽
電池装置1で発電した電力を蓄電池部2に充電し、その
蓄電池部2に蓄電した電力を14時から15時に放電
し、14時から15時の電力を太陽電池装置1からの発
電量に加えて出力する(図7参照)。
装置1で発電した電力を充電し、その蓄電した電力を1
4時から15時に放電するように、制御回路3が蓄電池
部2への充電、蓄電池部2からの放電を制御する。
池装置1にて発電される。その発電した電力を充放電制
御部4aを介して蓄電池部2及びインバータ装置5aに
並列に与える。蓄電池部2が所定の充電量になるまで、
制御回路3はインバータ装置5aの駆動を停止し、太陽
電池装置1からの発電電力は、蓄電池部2へ与えられ、
蓄電池部2に太陽電池装置1で発電した電力を充電す
る。
の電力を蓄電池が充電すると充電完了としている。制御
回路3は、蓄電池部2の電圧等をモニターし、蓄電池部
2内の蓄電池の充電が完了、もしくは完了する少し前に
なると、インバータ装置5aを駆動し、太陽電池装置1
からの直流電力をインバータ装置5aで交流電力に変換
するように制御する。
部2が満充電にならなかった場合にも、制御回路3は、
蓄電池部2への充電を停止し、太陽電池装置1からの電
力を全てインバータ装置5へ与えるように制御する。
置1からの電力だけをインバータ装置5に与える。そし
て、最大ピーク時の14時になると、蓄電池部2に充電
されている電力を放電する。この実施形態では、14時
から16時まで2時間放電を行うように蓄電池部2を制
御し、太陽電池装置1からの電力に蓄電池部2からの電
力を加えて、インバータ装置5aへ与える。この2時間
で蓄電池部2に充電された電力はすべて放電する。
バータ装置5aは、太陽電池装置1からの電力を交流電
力に変換して出力する。
池部2へ充電する場合には、制御回路3が分電盤6、充
電回路置51、充放電制御部4aを制御し、蓄電池部2
へ夜間電力を用いて充電する。このように構成すること
で、安価な夜間電力を使用して、ピーク時の重畳する電
力を確保することもできる。
ても、第5の実施形態と同様に、通常のインバータ装置
を用いて構成してもよい。
ば、小さな電池容量で電力需要ピーク時に対応した電力
の出力制御が行え、最適なピーク電力需要の削減をでき
るシステムを提供することができる。また、地域、季節
等に適した出力電力制御を容易に行うことができる。
システムを搭載した住宅を示す構成図である。
ロック図である。
システムを搭載した住宅を示す構成図である。
システムを搭載した住宅を示す構成図である。
システムを搭載した住宅を示す構成図である。
変動曲線と3kWの太陽光発電システムの発電量の経時
変化を示す図である。
テムの出力制御を行った場合を示す電力需要変動曲線と
太陽光発電システムの発電量と放電量との合計の出力の
経時変化を示す図である。
テムの出力制御を行った場合を示す電力需要変動曲線と
太陽光発電システムの発電量と放電量との合計の出力の
経時変化を示す図である。
ピークを14時にしたパターンの出力の経時変化を示す
図である。
のピークを14時にしたパターンの出力の経時変化を示
す図である。
電システムを搭載した住宅を示す構成図である。
る。
Claims (12)
- 【請求項1】 太陽電池装置にて発生される電力をイン
バータ装置に与え、このインバータ装置で交流に変換
し、電力消費部に供給する太陽光発電システムにおい
て、電力を蓄電する蓄電池を備え、電力需要の高い特定
の時間帯の電力需要の変動曲線に応じて前記蓄電池に蓄
電された電力の放電を制御し、前記インバータ装置に、
前記太陽電池装置からの発電電力とともに前記蓄電池か
らの電力を与えることを特徴とする蓄電池を備えた太陽
光発電システム。 - 【請求項2】 前記蓄電池への充電は、日の出後の電力
需要のオフピーク時内での太陽電池装置での発電電力ま
たは夜間の電力系統からの電力から選ばれる1つ以上の
電力にて行われることを特徴とする請求項1に記載の蓄
電池を備えた太陽光発電システム。 - 【請求項3】 電力系統に連系し、太陽電池装置にて発
生される電力をインバータ装置に与え、このインバータ
装置で交流に変換し、電力消費部に供給する太陽光発電
システムにおいて、電力を蓄電する蓄電池と、太陽電池
装置からの電力を前記蓄電池またはインバータ装置に切
り替えて出力させる切り替え制御手段と、を備え、日の
出後の電力需要のオフピーク時内での太陽電池装置での
発電電力または夜間の電力系統からの電力から選ばれる
1つ以上の電力にて前記蓄電池を充電するように制御
し、電力需要の高い特定の時間帯の電力需要の変動曲線
に応じて前記蓄電池に蓄電された電力の放電を制御し、
前記インバータ装置に、前記太陽電池装置からの発電電
力とともに前記蓄電池からの電力を与えることを特徴と
する蓄電池を備えた太陽光発電システム。 - 【請求項4】 電力系統に連系し、太陽電池装置にて発
生される電力をインバータ装置に与え、このインバータ
装置で交流に変換し、電力消費部に供給する太陽光発電
システムにおいて、電力を蓄電する蓄電池と、前記蓄電
池の充放電を制御する制御手段と、を備え、日の出後の
電力需要のオフピーク時内での太陽電池装置での発電電
力または夜間の電力系統からの電力から選ばれる1つ以
上の電力にて前記蓄電池を充電するように制御し、電力
需要の高い特定の時間帯の電力需要の変動曲線に応じて
前記蓄電池に蓄電された電力の放電を制御し、前記イン
バータ装置に、前記太陽電池装置からの発電電力ととも
に前記蓄電池からの電力を与えることを特徴とする蓄電
池を備えた太陽光発電システム。 - 【請求項5】 前記電力需要の高い特定の時間帯が、日
の出から日没までの時間を100とし、日の出時間を0
%、日没時間を100%と表した場合、40から100
%の範囲であることを特徴とする請求項1ないし4のい
ずれかに記載の蓄電池を備えた太陽光発電システム。 - 【請求項6】 前記蓄電池から放電し、前記太陽電池装
置からの発電量に重畳する時間帯は、太陽電池装置の発
電量のオフピーク時で且つ電力需要のピーク時であり、
日の出から日没までの時間を100とし、日の出時間を
0%、日没時間を100%と表した場合、55から85
%の範囲であることを特徴とする請求項1ないし4のい
ずれかに記載の蓄電池を備えた太陽光発電システム。 - 【請求項7】 前記蓄電池の放電量が日の出から日没ま
での時間を100とし、日の出時間を0%、日没時間を
100%と表した場合、55%までの最大の太陽電池装
置の発電量と電力需要ピーク時間帯の太陽電池装置の発
電量及び蓄電池の放電量を重畳した電力量がほぼ同じに
なるか大きくなるように前記蓄電池への蓄電量を制御す
ることを特徴とする請求項1ないし4のいずれかに記載
の蓄電池を備えた太陽光発電システム。 - 【請求項8】 前記電力需要のオフピーク時内の蓄電池
に充電する時間帯が、日の出から日没までの時間を10
0とし、日の出時間を0%、日没時間を100%と表し
た場合、0から40%の範囲であることを特徴とする請
求項1ないし4のいずれかに記載の蓄電池を備えた太陽
光発電システム。 - 【請求項9】 前記蓄電池の常時使用する容量が、太陽
電池1kW当たり、0.1から0.8kWhの範囲であ
ることを特徴とする請求項1ないし4のいずれかに記載
の蓄電池を備えた太陽光発電システム。 - 【請求項10】 前記蓄電池の充電で、蓄電池の所定容
量までに達した以降は、太陽電池装置の発電量は負荷に
使用され、余剰電力は電力系統に逆潮流されることを特
徴とする請求項3または4に記載の蓄電池を備えた太陽
光発電システム。 - 【請求項11】 前記蓄電池が、ニッケル・水素蓄電
池、ニッケル・カドミウム蓄電池又はリチウムイオン電
池の中から選択されることを特徴とする請求項1ないし
10のいずれかに記載の蓄電池を備えた太陽光発電シス
テム。 - 【請求項12】 前記ニッケル・水素蓄電池の容量が、
太陽電池1kW当たり、0.125から1.0kWhの
範囲であることを特徴とする請求項11に記載の蓄電池
を備えた太陽光発電システム。
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001264837A JP2003079054A (ja) | 2001-08-31 | 2001-08-31 | 蓄電池を備えた太陽光発電システム |
US10/231,096 US20030047209A1 (en) | 2001-08-31 | 2002-08-30 | Photovoltaic power generation system with storage batteries |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001264837A JP2003079054A (ja) | 2001-08-31 | 2001-08-31 | 蓄電池を備えた太陽光発電システム |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003079054A true JP2003079054A (ja) | 2003-03-14 |
JP2003079054A5 JP2003079054A5 (ja) | 2005-08-25 |
Family
ID=19091378
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001264837A Pending JP2003079054A (ja) | 2001-08-31 | 2001-08-31 | 蓄電池を備えた太陽光発電システム |
Country Status (2)
Country | Link |
---|---|
US (1) | US20030047209A1 (ja) |
JP (1) | JP2003079054A (ja) |
Cited By (38)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007052671A1 (ja) * | 2005-10-31 | 2007-05-10 | Showa Shell Sekiyu K.K. | Cis系薄膜太陽電池モジュール及びその製造方法 |
WO2007086472A1 (ja) * | 2006-01-27 | 2007-08-02 | Sharp Kabushiki Kaisha | 電力供給システム |
JP2007201257A (ja) * | 2006-01-27 | 2007-08-09 | Sharp Corp | 太陽光発電システム |
JP2007295718A (ja) * | 2006-04-25 | 2007-11-08 | Sharp Corp | 電力供給システム |
JP2007330057A (ja) * | 2006-06-08 | 2007-12-20 | Kawasaki Plant Systems Ltd | 二次電池付太陽光システムの充電制御方法 |
JP2008048544A (ja) * | 2006-08-17 | 2008-02-28 | Sharp Corp | 太陽光発電システム |
JP2008079458A (ja) * | 2006-09-22 | 2008-04-03 | Sharp Corp | 給電システムおよび給電システムの制御方法 |
JP2010213507A (ja) * | 2009-03-11 | 2010-09-24 | Chugoku Electric Power Co Inc:The | 自然エネルギー併用型蓄電システム、および自然エネルギー併用型蓄電方法 |
EP2262077A2 (en) | 2009-06-12 | 2010-12-15 | Sharp Kabushiki Kaisha | Power operation system, power operation method, photovoltaic power generator and controller |
CN102064574A (zh) * | 2009-11-16 | 2011-05-18 | 夏普株式会社 | 电力运用系统、电力运用方法及太阳光发电装置 |
WO2011065375A1 (ja) | 2009-11-25 | 2011-06-03 | シャープ株式会社 | 電力変換装置、発電システム、及び充放電制御方法 |
JP2011152043A (ja) * | 2007-03-19 | 2011-08-04 | Sanyo Electric Co Ltd | 冷熱機器制御装置 |
JP2012055162A (ja) * | 2010-04-14 | 2012-03-15 | Sekisui Chem Co Ltd | 電力制御システム |
JP2012109530A (ja) * | 2010-11-17 | 2012-06-07 | Samsung Electronics Co Ltd | 太陽電池部及びそれを有する表示装置 |
KR101167971B1 (ko) * | 2010-05-27 | 2012-07-24 | 한국토지주택공사 | 복합형 태양발전 컨트롤러의 제어방법 |
JP2012152093A (ja) * | 2010-12-28 | 2012-08-09 | Panasonic Corp | 電力制御装置 |
WO2012132282A1 (ja) | 2011-03-29 | 2012-10-04 | パナソニック株式会社 | 電力制御装置および電力制御方法 |
JP2012196022A (ja) * | 2011-03-15 | 2012-10-11 | Omron Corp | 充電制御装置および充電制御方法、並びに太陽光発電システム |
JP2012228103A (ja) * | 2011-04-21 | 2012-11-15 | Sekisui Chem Co Ltd | 電力制御システム |
JP2012257406A (ja) * | 2011-06-09 | 2012-12-27 | Daiwa House Industry Co Ltd | 建物用電力供給システム及び建物用電力供給方法 |
JP2013017284A (ja) * | 2011-07-01 | 2013-01-24 | Inagaki Ryuichi | 電力制御システム、電気機器、および充放電制御部 |
WO2013054617A1 (ja) * | 2011-10-13 | 2013-04-18 | ソニー株式会社 | 電力制御装置およびプログラム |
JP2013093917A (ja) * | 2011-10-24 | 2013-05-16 | Panasonic Corp | エネルギーマネジメント装置、エネルギーマネジメントシステムおよびプログラム |
CN103199747A (zh) * | 2013-04-07 | 2013-07-10 | 华北电力大学 | 利用电池储能系统平滑光伏发电系统功率的方法 |
CN101802399B (zh) * | 2007-10-09 | 2013-09-04 | 福特全球技术公司 | 太阳能充电混合动力系统 |
JP2014131477A (ja) * | 2010-06-30 | 2014-07-10 | Sanyo Electric Co Ltd | 充放電制御装置、充電池システム、及び充放電制御方法 |
JP2014168315A (ja) * | 2013-01-30 | 2014-09-11 | Sekisui Chem Co Ltd | 地域内電力需給制御システム |
JP2015042983A (ja) * | 2011-06-24 | 2015-03-05 | ソニー株式会社 | 監視装置、電源装置、監視方法、蓄電システム、電子機器、電動車両および電力システム |
WO2015033819A1 (ja) | 2013-09-06 | 2015-03-12 | 積水化学工業株式会社 | 蓄電装置の放電開始時刻決定システム及び蓄電装置の放電開始時刻の決定方法 |
CN104917442A (zh) * | 2015-05-25 | 2015-09-16 | 华南农业大学 | 基于无线网络的太阳能智能收集利用装置及控制方法 |
JP5796189B2 (ja) * | 2010-03-24 | 2015-10-21 | パナソニックIpマネジメント株式会社 | 電力供給システム |
JP2015195726A (ja) * | 2011-07-01 | 2015-11-05 | パナソニックIpマネジメント株式会社 | 電力管理装置、電力管理システム、蓄電池、電力管理方法 |
JP2016001958A (ja) * | 2014-06-12 | 2016-01-07 | 三菱電機株式会社 | 太陽光発電システム |
CN105552963A (zh) * | 2016-02-04 | 2016-05-04 | 苏州高创特新能源发展股份有限公司 | 一种基于锂离子电池储能的光伏发电并网系统 |
CN106394317A (zh) * | 2016-11-10 | 2017-02-15 | 中广核太阳能开发有限公司 | 一种高效节能的铁路牵引供电系统 |
CN106411144A (zh) * | 2016-11-10 | 2017-02-15 | 西南交通大学 | 一种基于光伏发电的铁路牵引供电系统 |
JP2019097333A (ja) * | 2017-11-24 | 2019-06-20 | トヨタ自動車株式会社 | 車両 |
CN111301199A (zh) * | 2020-03-02 | 2020-06-19 | 河南简行能源科技有限公司 | 一种用于纯电动车的移动式应急充电装置 |
Families Citing this family (126)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070005195A1 (en) * | 2005-01-10 | 2007-01-04 | Nicholas Pasquale | Distributed energy storage for reducing power demand |
US20060158037A1 (en) * | 2005-01-18 | 2006-07-20 | Danley Douglas R | Fully integrated power storage and supply appliance with power uploading capability |
US7274975B2 (en) * | 2005-06-06 | 2007-09-25 | Gridpoint, Inc. | Optimized energy management system |
AT501261B8 (de) * | 2005-07-08 | 2007-02-15 | Fronius Int Gmbh | Vorrichtung zum schutz einer photovoltaik-anlage vor bissschäden durch nagetiere |
US7388348B2 (en) * | 2005-07-15 | 2008-06-17 | Mattichak Alan D | Portable solar energy system |
US7921604B2 (en) * | 2006-01-04 | 2011-04-12 | Siaosi Kaihau Lino | Storm proof aluma-foam housing unit |
US20070203860A1 (en) * | 2006-02-24 | 2007-08-30 | Gridpoint, Inc. | Energy budget manager |
JP5137820B2 (ja) * | 2006-04-24 | 2013-02-06 | シャープ株式会社 | 太陽光発電システムおよび太陽光発電システム制御方法 |
US8103389B2 (en) * | 2006-05-18 | 2012-01-24 | Gridpoint, Inc. | Modular energy control system |
US7388299B2 (en) * | 2006-06-21 | 2008-06-17 | Tracy Blackman | Retrofittable power distribution system for a household |
US7388298B2 (en) * | 2006-06-21 | 2008-06-17 | Tracy Blackman | Retrofittable power distribution system for a household |
WO2008015502A1 (en) * | 2006-07-31 | 2008-02-07 | Azordegan, Amir | Bilaterlal uninterruptable power supply (ups) unit |
US7810571B2 (en) * | 2006-11-09 | 2010-10-12 | Baker Hughes Incorporated | Downhole lubricator valve |
CN100453926C (zh) * | 2006-11-09 | 2009-01-21 | 中国科学技术大学 | 光伏太阳能热泵多功能一体化系统 |
US20080236654A1 (en) * | 2007-03-27 | 2008-10-02 | Tsnergy, Inc. | WINDOW CONSTRUCTION COMBININB NiMH TECHNOLOGY AND SOLAR POWER |
IE20080291A1 (en) * | 2007-04-17 | 2008-11-26 | Timothy Patrick Cooper | A load management controller for a household electrical installation |
US20090014049A1 (en) * | 2007-07-13 | 2009-01-15 | Miasole | Photovoltaic module with integrated energy storage |
US20090173589A1 (en) * | 2008-01-09 | 2009-07-09 | Nejmeh Mark J | System and Method for Generating Electricity from Automobile Traffic |
CA2713017A1 (en) * | 2008-01-23 | 2009-07-30 | Alpha Technologies, Inc. | Simplified maximum power point control utilizing the pv array voltage at the maximum power point |
EP2083170A1 (en) * | 2008-01-23 | 2009-07-29 | Flexenclosure AB | Method and device for controlling operation of a power supply system |
GB2457506A (en) * | 2008-02-18 | 2009-08-19 | Zeta Controls Ltd | Solar power system with storage element and mains electricity supply |
US9077206B2 (en) * | 2008-05-14 | 2015-07-07 | National Semiconductor Corporation | Method and system for activating and deactivating an energy generating system |
GB0809235D0 (en) * | 2008-05-21 | 2008-06-25 | Poweroasis Ltd | Supervisory system controller for use with a renewable energy powered radio telecommunications site |
US7800247B2 (en) * | 2008-05-30 | 2010-09-21 | Chun-Chieh Chang | Storage system that maximizes the utilization of renewable energy |
SI2319152T1 (sl) * | 2008-07-30 | 2014-06-30 | Compagni Emidio Emilio Delli | Elektrarna za dobavo prednostno enofazne elektrike majhne moči bivalnim in poslovnim zgradbam |
US8476523B2 (en) * | 2008-08-25 | 2013-07-02 | Enpulz, L.L.C. | Solar panel ready tiles |
US8548638B2 (en) * | 2008-09-15 | 2013-10-01 | General Electric Company | Energy management system and method |
US9225285B2 (en) * | 2008-09-24 | 2015-12-29 | Sunpower Corporation | Photovoltaic installation with automatic disconnect device |
US20100181838A1 (en) * | 2009-01-20 | 2010-07-22 | Wayne Farris | Roof Power Generator |
GB0901844D0 (en) * | 2009-02-05 | 2009-03-11 | Eco Design Labs Ltd | Power management system |
US8222765B2 (en) * | 2009-02-13 | 2012-07-17 | First Solar, Inc. | Photovoltaic power plant output |
CN102422242A (zh) * | 2009-04-30 | 2012-04-18 | 夏普株式会社 | 控制设备和控制方法 |
EP2425515A2 (en) * | 2009-05-01 | 2012-03-07 | Alpha Technologies Inc. | Solar power systems optimized for use in cold weather conditions |
US8108081B2 (en) * | 2009-08-12 | 2012-01-31 | Sunpower Corporation | System and method for associating a load demand with a variable power generation |
DE102009040090A1 (de) | 2009-09-04 | 2011-03-10 | Voltwerk Electronics Gmbh | Inseleinheit für ein Energienetz mit einer Steuereinheit zum Steuern eines Energieflusses zwischen der Energieerzeugungseinheit, der Energiespeichereinheit, der Lasteinheit und/oder dem Energienetz |
JP5568271B2 (ja) * | 2009-09-17 | 2014-08-06 | 東芝三菱電機産業システム株式会社 | 熱回収装置 |
JP5685715B2 (ja) * | 2009-09-28 | 2015-03-18 | パナソニックIpマネジメント株式会社 | 系統連系形給電システム |
JP5344759B2 (ja) * | 2009-09-30 | 2013-11-20 | パナソニック株式会社 | 配電システム |
JP2011083082A (ja) * | 2009-10-05 | 2011-04-21 | Panasonic Electric Works Co Ltd | 蓄電システム |
JP5507959B2 (ja) * | 2009-10-26 | 2014-05-28 | パナソニック株式会社 | 売電システム |
US20110109165A1 (en) * | 2009-11-11 | 2011-05-12 | International Business Machines Corporation | Apparatus and method for managing a power source |
DE102009054078A1 (de) * | 2009-11-20 | 2011-05-26 | Li-Tec Battery Gmbh | Batterieproduktionseinrichtung |
EP2509180A4 (en) * | 2009-11-30 | 2017-07-26 | Kyocera Corporation | Control apparatus and control method |
KR101084215B1 (ko) * | 2009-12-16 | 2011-11-17 | 삼성에스디아이 주식회사 | 에너지 저장 시스템 및 이의 제어 방법 |
KR101084216B1 (ko) * | 2009-12-23 | 2011-11-17 | 삼성에스디아이 주식회사 | 에너지 저장 시스템 및 이의 제어 방법 |
US9819182B1 (en) * | 2010-01-12 | 2017-11-14 | Sunpower Corporation | Systemic optimization of photovoltaic apparatus |
JP5577717B2 (ja) * | 2010-01-25 | 2014-08-27 | ソニー株式会社 | 電力を効率的に管理する方法 |
JP5552817B2 (ja) * | 2010-01-25 | 2014-07-16 | ソニー株式会社 | 電力管理システム、電力管理装置、電力管理方法、蓄電装置、及び電動移動体 |
KR101097265B1 (ko) * | 2010-02-25 | 2011-12-22 | 삼성에스디아이 주식회사 | 전력 저장 시스템 및 그 제어방법 |
US8338989B2 (en) * | 2010-03-11 | 2012-12-25 | First Solar, Inc. | Inverter power system |
IT1399892B1 (it) | 2010-03-15 | 2013-05-09 | Spi Tecno Srl | Sistema per l illuminazione pubblica |
CN102208815B (zh) * | 2010-03-31 | 2013-09-18 | 比亚迪股份有限公司 | 一种家庭多能源系统及其控制方法 |
US9379549B2 (en) * | 2010-04-26 | 2016-06-28 | Nec Corporation | Electric power control system and method |
KR101174891B1 (ko) | 2010-06-01 | 2012-08-17 | 삼성에스디아이 주식회사 | 전력 저장 시스템 및 그 제어방법 |
KR101853661B1 (ko) * | 2010-08-20 | 2018-05-03 | 엘지전자 주식회사 | 전자기기 및 그 전원제어방법 |
US9577430B2 (en) * | 2010-08-20 | 2017-02-21 | Lg Electronics Inc. | Electronic device and method of controlling power supply therein |
JPWO2012049910A1 (ja) * | 2010-10-15 | 2014-02-24 | 三洋電機株式会社 | 電力供給システムの出力回路 |
US9030048B2 (en) | 2010-10-18 | 2015-05-12 | Alpha Technologies Inc. | Uninterruptible power supply systems and methods for communications systems |
US9774198B2 (en) * | 2010-11-08 | 2017-09-26 | Brandon Culver | Wind and solar powered heat trace with homeostatic control |
US9300139B2 (en) * | 2010-12-16 | 2016-03-29 | Ashot Nazarian | Method and apparatus for integrated electric power generation, storage and supply distributed and networked at the same time |
JP5541549B2 (ja) | 2010-12-21 | 2014-07-09 | 日本電気株式会社 | 急速充電システム、制御装置、蓄電量の制御方法、及びプログラム |
US8854004B2 (en) * | 2011-01-12 | 2014-10-07 | Samsung Sdi Co., Ltd. | Energy storage system and controlling method thereof |
EP2485356A1 (en) * | 2011-02-02 | 2012-08-08 | Arista Power, Inc. | Energy storage and power management system |
US20120217800A1 (en) * | 2011-02-11 | 2012-08-30 | Alpha Technologies Inc. | Solar power systems optimized for use in communications networks |
JP2012186950A (ja) * | 2011-03-07 | 2012-09-27 | Denso Corp | 電力供給システム |
US20120227788A1 (en) * | 2011-03-09 | 2012-09-13 | Advanced Technology & Research Corp. (ATR) | Low cost sun tracking pole mount for solar panels |
CN103477526B (zh) * | 2011-04-20 | 2017-07-18 | 瑞典爱立信有限公司 | 配电网络中的方法和器件 |
US20120286052A1 (en) * | 2011-05-11 | 2012-11-15 | GM Global Technology Operations LLC | System and method for solar-powered engine thermal management |
JP5162008B2 (ja) * | 2011-06-14 | 2013-03-13 | 株式会社東芝 | 電源制御方法、電子機器及び電源制御システム |
JP5799228B2 (ja) * | 2011-06-17 | 2015-10-21 | パナソニックIpマネジメント株式会社 | 電力供給システム |
ES2699163T3 (es) * | 2011-06-29 | 2019-02-07 | Acciona Energia Sa | Procedimiento de control de suministro y acumulación de energía eléctrica proporcionada por una planta de generación de energía renovable |
JP5327407B2 (ja) * | 2011-07-15 | 2013-10-30 | 日本電気株式会社 | 蓄電池システム及びその制御方法 |
CN103843217A (zh) * | 2011-09-20 | 2014-06-04 | 艾思玛太阳能技术股份公司 | 借助光伏设备的调节功率提供 |
US9037443B1 (en) | 2011-10-16 | 2015-05-19 | Alpha Technologies Inc. | Systems and methods for solar power equipment |
US9515489B2 (en) * | 2011-11-07 | 2016-12-06 | Global Link Co., Ltd. | Feed system to be used in residence such as multi-unit apartment complex |
JP5967516B2 (ja) | 2011-11-22 | 2016-08-10 | パナソニックIpマネジメント株式会社 | 電力管理装置、電力管理プログラム、及び、電力分配システム |
CN102545365B (zh) * | 2011-12-30 | 2015-07-29 | 华为技术有限公司 | 一种发电机控制方法及装置、通信基站 |
ITTO20120008A1 (it) * | 2012-01-10 | 2013-07-11 | Gianluca Giannuzzi | Circuito e procedimento per l'accumulo di energia prodotta da sorgenti di energia rinnovabili. |
JP5806132B2 (ja) * | 2012-01-23 | 2015-11-10 | 京セラ株式会社 | 発電量予測装置、発電量予測補正方法、および自然エネルギー発電システム |
CN102545711B (zh) * | 2012-02-17 | 2015-06-24 | 振发能源集团有限公司 | 一种新型的离网/并网一体化太阳能发电系统与控制方法 |
KR20130104771A (ko) * | 2012-03-15 | 2013-09-25 | 삼성에스디아이 주식회사 | 에너지 저장 시스템 및 그의 제어 방법 |
ITMI20120968A1 (it) * | 2012-06-05 | 2013-12-06 | Fabrizio Bernini | Cella fotovoltaica e impianto fotovoltaico comprendente tale cella |
DE102012212654A1 (de) * | 2012-07-19 | 2014-01-23 | Robert Bosch Gmbh | Energiespeicher für Photovoltaikanalage, Energiespeicherkraftwerk, Steuereinrichtung und Verfahren zum Betreiben eines Energiespeichers |
JP6145670B2 (ja) * | 2012-08-31 | 2017-06-14 | パナソニックIpマネジメント株式会社 | 電力潮流制御システム、管理装置、プログラム |
US9312699B2 (en) | 2012-10-11 | 2016-04-12 | Flexgen Power Systems, Inc. | Island grid power supply apparatus and methods using energy storage for transient stabilization |
US10289080B2 (en) | 2012-10-11 | 2019-05-14 | Flexgen Power Systems, Inc. | Multi-generator applications using variable speed and solid state generators for efficiency and frequency stabilization |
US9553517B2 (en) | 2013-03-01 | 2017-01-24 | Fllexgen Power Systems, Inc. | Hybrid energy storage system and methods |
WO2014140962A1 (en) * | 2013-03-14 | 2014-09-18 | Koninklijke Philips N.V. | Solar power supply system |
CN103178751A (zh) * | 2013-04-07 | 2013-06-26 | 王世国 | 一种太阳能发电装置 |
JP5798594B2 (ja) * | 2013-06-18 | 2015-10-21 | トヨタ自動車株式会社 | 充電制御装置 |
US9742188B2 (en) * | 2013-06-26 | 2017-08-22 | Energy Development Llc | System and method for installing solar panels based on number of panels and output of panels |
WO2014208059A1 (ja) * | 2013-06-27 | 2014-12-31 | パナソニック株式会社 | 電力調整装置、電力調整方法、電力調整システム、蓄電装置、サーバ、プログラム |
JP6142925B2 (ja) * | 2013-09-09 | 2017-06-07 | 富士通株式会社 | 運転計画生成装置、運転計画生成方法、運転計画生成プログラムおよび蓄電池システム |
AT515032B1 (de) | 2013-11-12 | 2016-09-15 | Schipfer Gottfried | Energiespeichersystem |
CN103618374A (zh) * | 2013-12-10 | 2014-03-05 | 南京工业职业技术学院 | 一种智能型方波输出不间断电源 |
TWI559648B (zh) | 2014-01-21 | 2016-11-21 | 台達電子工業股份有限公司 | 動態充電之充電裝置及其操作方法 |
WO2015159388A1 (ja) * | 2014-04-16 | 2015-10-22 | 三菱電機株式会社 | 制御装置、制御システム、制御方法及びプログラム |
US9843189B2 (en) * | 2014-05-19 | 2017-12-12 | The University Of North Carolina At Charlotte | Grid tied system controller including logic coupled to a photovoltaic station and an energy storage system |
US20160087433A1 (en) | 2014-07-04 | 2016-03-24 | Stefan Matan | Data aggregation with operation forecasts for a distributed grid node |
US10879695B2 (en) * | 2014-07-04 | 2020-12-29 | Apparent Labs, LLC | Grid network gateway aggregation |
US11063431B2 (en) | 2014-07-04 | 2021-07-13 | Apparent Labs Llc | Hierarchical and distributed power grid control |
US20160011616A1 (en) * | 2014-07-11 | 2016-01-14 | Microsoft Technology Licensing, Llc | Power management |
US10574055B2 (en) | 2014-12-30 | 2020-02-25 | Flexgen Power Systems, Inc. | Transient power stabilization device with active and reactive power control |
CH711204A1 (de) * | 2015-06-05 | 2016-12-15 | Bkw Energie Ag | Verfahren zur Steuerung eines lokalen Stromverbrauchers. |
DE102015008305A1 (de) * | 2015-06-29 | 2016-12-29 | Karlsruher Institut für Technologie | Energiemanagementsystem für ein Energieerzeugungssystem |
CN104967139A (zh) * | 2015-07-29 | 2015-10-07 | 阳光电源股份有限公司 | 一种光伏发电装置 |
CN105226690B (zh) * | 2015-10-27 | 2017-12-12 | 四川科陆新能电气有限公司 | 一种光储电站的并网功率平抑方法 |
CN107230974A (zh) * | 2016-03-23 | 2017-10-03 | 国网青海省电力公司 | 基于储能运行状态的光伏功率稳定输出控制方法 |
CN105896598A (zh) * | 2016-04-21 | 2016-08-24 | 北京四方继保自动化股份有限公司 | 一种用于远礁海岛独立型预装式一体化微电网系统 |
BE1023677B1 (nl) * | 2016-04-29 | 2017-06-13 | Futech Bvba | Werkwijze en inrichting voor het ontladen van een energie-opslagsysteem in een zonnepaneelinstallatie |
US10628897B2 (en) * | 2017-01-10 | 2020-04-21 | Solaredge Technologies Ltd. | System and method for controlling a stand-alone direct current power system |
WO2018193395A1 (en) * | 2017-04-19 | 2018-10-25 | Abb Schweiz Ag | A system and a method for providing uninterrupted power in a microgrid system |
US10581266B2 (en) * | 2018-04-16 | 2020-03-03 | Dynapower Company Llc | Energy storage system and method for direct coupling energy storage and power source |
CN108377001B (zh) * | 2018-04-24 | 2024-02-06 | 上海振华重工电气有限公司 | 一种用于用电量削峰填谷的光伏储能系统和方法 |
US11196258B2 (en) | 2018-08-03 | 2021-12-07 | Sacramento Municipal Utility District | Energy control and storage system for controlling power based on a load shape |
US11722026B2 (en) | 2019-04-23 | 2023-08-08 | Dpm Technologies Inc. | Fault tolerant rotating electric machine |
EP3731363A1 (fr) * | 2019-04-25 | 2020-10-28 | Homsphere SA | Système et méthode de distribution d'énergie électrique |
CN110112773A (zh) * | 2019-04-28 | 2019-08-09 | 厦门理工学院 | 一种可弯曲单晶硅太阳能发电装置 |
CN110182389B (zh) * | 2019-06-04 | 2023-01-17 | 沈观清 | 临近空间无人机组合动力系统全自动能量控制系统和方法 |
US11444473B2 (en) * | 2019-10-15 | 2022-09-13 | Inventus Holdings, Llc | Dynamic battery charging for maximum wind/solar peak clipping recapture |
US11309712B2 (en) * | 2019-10-28 | 2022-04-19 | Enphase Energy, Inc. | Methods and apparatus including an energy management system |
EP4075623A1 (de) * | 2021-04-16 | 2022-10-19 | Siemens AG Österreich | Verfahren zum betreiben einer energiegemeinschaft |
CN113266896B (zh) * | 2021-04-22 | 2023-06-23 | 深圳市豫知科技有限公司 | 套箱式洁净手术室的清洁能源供电系统 |
US11897362B2 (en) | 2021-05-04 | 2024-02-13 | Exro Technologies Inc. | Systems and methods for individual control of a plurality of controllable units of battery cells |
US11451060B1 (en) * | 2022-01-31 | 2022-09-20 | 8Me Nova, Llc | Consistent power delivery via power delivery limits |
CN115566787A (zh) * | 2022-10-25 | 2023-01-03 | 亿鸿精密科技有限公司 | 一种智能备电管理设备 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6450723A (en) * | 1987-08-20 | 1989-02-27 | Mitsubishi Electric Corp | Solar power generator |
JPH01303022A (ja) * | 1987-12-03 | 1989-12-06 | Sanyo Electric Co Ltd | 太陽光発電装置 |
JPH0511428B2 (ja) * | 1985-06-28 | 1993-02-15 | Shikoku Denryoku Kk | |
JPH05252671A (ja) * | 1992-02-29 | 1993-09-28 | Central Res Inst Of Electric Power Ind | 太陽光発電出力制御方式 |
JP2612639B2 (ja) * | 1990-11-29 | 1997-05-21 | ミサワホーム株式会社 | 太陽電池システム |
JPH1146458A (ja) * | 1997-07-08 | 1999-02-16 | Seinan Sogo Kaihatsu Kk | 太陽光発電システム |
JPH11113189A (ja) * | 1997-09-29 | 1999-04-23 | Suzuki Motor Corp | 充電装置 |
JPH11155242A (ja) * | 1997-11-20 | 1999-06-08 | Yuasa Corp | 太陽光発電装置の運転方法 |
JP2000023364A (ja) * | 1998-06-30 | 2000-01-21 | Yoshihiro Shigyo | 電気蓄浄装置 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
IL96989A0 (en) * | 1991-01-21 | 1992-03-29 | Amitec Information Industry Lt | Multi-purpose solar energy conversion system |
JP2947372B2 (ja) * | 1991-04-25 | 1999-09-13 | 株式会社関電工 | 多機能電力変換システム |
CA2225159C (en) * | 1996-12-19 | 2006-10-17 | Showa Pole Co., Ltd. | Pole having solar cells |
US6372978B1 (en) * | 2000-12-21 | 2002-04-16 | Carmine Cifaldi | Wind/sun solar collection system (HS2) |
-
2001
- 2001-08-31 JP JP2001264837A patent/JP2003079054A/ja active Pending
-
2002
- 2002-08-30 US US10/231,096 patent/US20030047209A1/en not_active Abandoned
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0511428B2 (ja) * | 1985-06-28 | 1993-02-15 | Shikoku Denryoku Kk | |
JPS6450723A (en) * | 1987-08-20 | 1989-02-27 | Mitsubishi Electric Corp | Solar power generator |
JPH01303022A (ja) * | 1987-12-03 | 1989-12-06 | Sanyo Electric Co Ltd | 太陽光発電装置 |
JP2612639B2 (ja) * | 1990-11-29 | 1997-05-21 | ミサワホーム株式会社 | 太陽電池システム |
JPH05252671A (ja) * | 1992-02-29 | 1993-09-28 | Central Res Inst Of Electric Power Ind | 太陽光発電出力制御方式 |
JPH1146458A (ja) * | 1997-07-08 | 1999-02-16 | Seinan Sogo Kaihatsu Kk | 太陽光発電システム |
JPH11113189A (ja) * | 1997-09-29 | 1999-04-23 | Suzuki Motor Corp | 充電装置 |
JPH11155242A (ja) * | 1997-11-20 | 1999-06-08 | Yuasa Corp | 太陽光発電装置の運転方法 |
JP2000023364A (ja) * | 1998-06-30 | 2000-01-21 | Yoshihiro Shigyo | 電気蓄浄装置 |
Cited By (54)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007052671A1 (ja) * | 2005-10-31 | 2007-05-10 | Showa Shell Sekiyu K.K. | Cis系薄膜太陽電池モジュール及びその製造方法 |
JP2007123725A (ja) * | 2005-10-31 | 2007-05-17 | Showa Shell Sekiyu Kk | Cis系薄膜太陽電池モジュール及びその製造方法 |
US7960642B2 (en) | 2005-10-31 | 2011-06-14 | Showa Shell Sekiyu K.K. | CIS based thin-film photovoltaic module and process for producing the same |
WO2007086472A1 (ja) * | 2006-01-27 | 2007-08-02 | Sharp Kabushiki Kaisha | 電力供給システム |
JP2007201257A (ja) * | 2006-01-27 | 2007-08-09 | Sharp Corp | 太陽光発電システム |
US8310094B2 (en) | 2006-01-27 | 2012-11-13 | Sharp Kabushiki Kaisha | Power supply system |
JP2007295718A (ja) * | 2006-04-25 | 2007-11-08 | Sharp Corp | 電力供給システム |
JP2007330057A (ja) * | 2006-06-08 | 2007-12-20 | Kawasaki Plant Systems Ltd | 二次電池付太陽光システムの充電制御方法 |
JP2008048544A (ja) * | 2006-08-17 | 2008-02-28 | Sharp Corp | 太陽光発電システム |
JP2008079458A (ja) * | 2006-09-22 | 2008-04-03 | Sharp Corp | 給電システムおよび給電システムの制御方法 |
JP2011152043A (ja) * | 2007-03-19 | 2011-08-04 | Sanyo Electric Co Ltd | 冷熱機器制御装置 |
CN101802399B (zh) * | 2007-10-09 | 2013-09-04 | 福特全球技术公司 | 太阳能充电混合动力系统 |
JP2010213507A (ja) * | 2009-03-11 | 2010-09-24 | Chugoku Electric Power Co Inc:The | 自然エネルギー併用型蓄電システム、および自然エネルギー併用型蓄電方法 |
JP2010288393A (ja) * | 2009-06-12 | 2010-12-24 | Sharp Corp | 電力運用システム、電力運用方法、太陽光発電装置、およびコントローラ |
CN101924375A (zh) * | 2009-06-12 | 2010-12-22 | 夏普株式会社 | 电力运用系统、电力运用方法、太阳光发电装置及控制器 |
EP2262077A2 (en) | 2009-06-12 | 2010-12-15 | Sharp Kabushiki Kaisha | Power operation system, power operation method, photovoltaic power generator and controller |
CN102064574A (zh) * | 2009-11-16 | 2011-05-18 | 夏普株式会社 | 电力运用系统、电力运用方法及太阳光发电装置 |
US8922059B2 (en) | 2009-11-16 | 2014-12-30 | Sharp Kabushiki Kaisha | Power operation system, power operation method and photovoltaic power generator |
US9030168B2 (en) | 2009-11-25 | 2015-05-12 | Sharp Kabushiki Kaisha | Power conversion device, power generation system and charge and discharge control method |
WO2011065375A1 (ja) | 2009-11-25 | 2011-06-03 | シャープ株式会社 | 電力変換装置、発電システム、及び充放電制御方法 |
US9172247B2 (en) | 2010-03-24 | 2015-10-27 | Panasonic Intellectual Property Management Co., Ltd. | Power supply system with controlled power storage |
JP5796189B2 (ja) * | 2010-03-24 | 2015-10-21 | パナソニックIpマネジメント株式会社 | 電力供給システム |
JP2012055162A (ja) * | 2010-04-14 | 2012-03-15 | Sekisui Chem Co Ltd | 電力制御システム |
KR101167971B1 (ko) * | 2010-05-27 | 2012-07-24 | 한국토지주택공사 | 복합형 태양발전 컨트롤러의 제어방법 |
US9071068B2 (en) | 2010-06-30 | 2015-06-30 | Panasonic Intellectual Property Management Co., Ltd. | Charge/discharge control apparatus |
JP2014131477A (ja) * | 2010-06-30 | 2014-07-10 | Sanyo Electric Co Ltd | 充放電制御装置、充電池システム、及び充放電制御方法 |
JP2012109530A (ja) * | 2010-11-17 | 2012-06-07 | Samsung Electronics Co Ltd | 太陽電池部及びそれを有する表示装置 |
JP2012152093A (ja) * | 2010-12-28 | 2012-08-09 | Panasonic Corp | 電力制御装置 |
JP2012196022A (ja) * | 2011-03-15 | 2012-10-11 | Omron Corp | 充電制御装置および充電制御方法、並びに太陽光発電システム |
CN103026580A (zh) * | 2011-03-29 | 2013-04-03 | 松下电器产业株式会社 | 电力控制装置及电力控制方法 |
US9106077B2 (en) | 2011-03-29 | 2015-08-11 | Panasonic Intellectual Property Management Co., Ltd. | Power control apparatus and power control method |
WO2012132282A1 (ja) | 2011-03-29 | 2012-10-04 | パナソニック株式会社 | 電力制御装置および電力制御方法 |
JP2012228103A (ja) * | 2011-04-21 | 2012-11-15 | Sekisui Chem Co Ltd | 電力制御システム |
US8860253B2 (en) | 2011-04-21 | 2014-10-14 | Sekisui Chemical Co., Ltd. | Power control system |
JP2012257406A (ja) * | 2011-06-09 | 2012-12-27 | Daiwa House Industry Co Ltd | 建物用電力供給システム及び建物用電力供給方法 |
JP2015042983A (ja) * | 2011-06-24 | 2015-03-05 | ソニー株式会社 | 監視装置、電源装置、監視方法、蓄電システム、電子機器、電動車両および電力システム |
JP2015195726A (ja) * | 2011-07-01 | 2015-11-05 | パナソニックIpマネジメント株式会社 | 電力管理装置、電力管理システム、蓄電池、電力管理方法 |
JP2013017284A (ja) * | 2011-07-01 | 2013-01-24 | Inagaki Ryuichi | 電力制御システム、電気機器、および充放電制御部 |
JP2013090362A (ja) * | 2011-10-13 | 2013-05-13 | Sony Corp | 電力制御装置およびプログラム |
CN103858303A (zh) * | 2011-10-13 | 2014-06-11 | 索尼公司 | 电力控制单元和程序 |
WO2013054617A1 (ja) * | 2011-10-13 | 2013-04-18 | ソニー株式会社 | 電力制御装置およびプログラム |
JP2013093917A (ja) * | 2011-10-24 | 2013-05-16 | Panasonic Corp | エネルギーマネジメント装置、エネルギーマネジメントシステムおよびプログラム |
JP2014168315A (ja) * | 2013-01-30 | 2014-09-11 | Sekisui Chem Co Ltd | 地域内電力需給制御システム |
CN103199747B (zh) * | 2013-04-07 | 2015-08-12 | 华北电力大学 | 利用电池储能系统平滑光伏发电系统功率的方法 |
CN103199747A (zh) * | 2013-04-07 | 2013-07-10 | 华北电力大学 | 利用电池储能系统平滑光伏发电系统功率的方法 |
WO2015033819A1 (ja) | 2013-09-06 | 2015-03-12 | 積水化学工業株式会社 | 蓄電装置の放電開始時刻決定システム及び蓄電装置の放電開始時刻の決定方法 |
JP2016001958A (ja) * | 2014-06-12 | 2016-01-07 | 三菱電機株式会社 | 太陽光発電システム |
CN104917442A (zh) * | 2015-05-25 | 2015-09-16 | 华南农业大学 | 基于无线网络的太阳能智能收集利用装置及控制方法 |
CN105552963A (zh) * | 2016-02-04 | 2016-05-04 | 苏州高创特新能源发展股份有限公司 | 一种基于锂离子电池储能的光伏发电并网系统 |
CN106394317A (zh) * | 2016-11-10 | 2017-02-15 | 中广核太阳能开发有限公司 | 一种高效节能的铁路牵引供电系统 |
CN106411144A (zh) * | 2016-11-10 | 2017-02-15 | 西南交通大学 | 一种基于光伏发电的铁路牵引供电系统 |
CN106411144B (zh) * | 2016-11-10 | 2018-07-17 | 西南交通大学 | 一种基于光伏发电的铁路牵引供电系统 |
JP2019097333A (ja) * | 2017-11-24 | 2019-06-20 | トヨタ自動車株式会社 | 車両 |
CN111301199A (zh) * | 2020-03-02 | 2020-06-19 | 河南简行能源科技有限公司 | 一种用于纯电动车的移动式应急充电装置 |
Also Published As
Publication number | Publication date |
---|---|
US20030047209A1 (en) | 2003-03-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2003079054A (ja) | 蓄電池を備えた太陽光発電システム | |
Bhatti et al. | A critical review of electric vehicle charging using solar photovoltaic | |
Bhatti et al. | Electric vehicles charging using photovoltaic: Status and technological review | |
JP5584763B2 (ja) | 直流配電システム | |
US8922059B2 (en) | Power operation system, power operation method and photovoltaic power generator | |
JP2007330057A (ja) | 二次電池付太陽光システムの充電制御方法 | |
US11689118B2 (en) | Converter with power management system for household users to manage power between different loads including their electric vehicle | |
Qadrdan et al. | Smart grid and energy storage | |
US20100313931A1 (en) | Power operation system, power operation method, photovoltaic power generator and controller | |
CN107210606B (zh) | 能源管理的方法 | |
Zeman | Photovoltaic systems | |
Alramlawi et al. | Optimal operation of pv-battery-diesel microgrid for industrial loads under grid blackouts | |
Dagdougui et al. | Power management strategy for sizing battery system for peak load limiting in a university campus | |
JP2010259303A (ja) | 分散発電システム | |
Alramlawi et al. | Optimal operation strategy of a hybrid PV-battery system under grid scheduled blackouts | |
WO2015001767A1 (ja) | 制御装置、電力管理システム | |
Rauf et al. | Application of DC-AC hybrid grid and solar photovoltaic generation with battery storage using smart grid | |
JP5841279B2 (ja) | 電力充電供給装置 | |
JP2004312798A (ja) | 分散エネルギーシステムおよびその制御方法 | |
Tangwiwat et al. | Benefit and cost analysis of the installation of rooftop solar PV with battery system | |
JP6146624B1 (ja) | エネルギーマネジメントシステム | |
CN102097820A (zh) | 太阳能峰谷电力调节系统 | |
Kgopana et al. | Improved utilization of hybrid energy for low-income houses based on energy consumption pattern. | |
Dagdougui et al. | Optimization and control based energy management for a smart building integrated microgrid | |
Tachikawa et al. | Economical evaluation of photovoltaic and battery systems under real-time pricing (RTP) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050208 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050208 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20061027 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061107 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061228 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20070320 |