EP2534310B1 - Procédé de production de colonnes de matériau et dispositif vibrant comprenant une unité de levage - Google Patents
Procédé de production de colonnes de matériau et dispositif vibrant comprenant une unité de levage Download PDFInfo
- Publication number
- EP2534310B1 EP2534310B1 EP11711259.9A EP11711259A EP2534310B1 EP 2534310 B1 EP2534310 B1 EP 2534310B1 EP 11711259 A EP11711259 A EP 11711259A EP 2534310 B1 EP2534310 B1 EP 2534310B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- vibrator
- carriage
- vibrating arrangement
- arrangement
- mast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000000463 material Substances 0.000 title claims description 203
- 238000004519 manufacturing process Methods 0.000 title claims description 18
- 238000000034 method Methods 0.000 claims description 34
- 230000000903 blocking effect Effects 0.000 claims description 9
- FGUUSXIOTUKUDN-IBGZPJMESA-N C1(=CC=CC=C1)N1C2=C(NC([C@H](C1)NC=1OC(=NN=1)C1=CC=CC=C1)=O)C=CC=C2 Chemical compound C1(=CC=CC=C1)N1C2=C(NC([C@H](C1)NC=1OC(=NN=1)C1=CC=CC=C1)=O)C=CC=C2 FGUUSXIOTUKUDN-IBGZPJMESA-N 0.000 claims 1
- 230000007423 decrease Effects 0.000 claims 1
- 238000003780 insertion Methods 0.000 claims 1
- 230000037431 insertion Effects 0.000 claims 1
- 239000002689 soil Substances 0.000 description 31
- 238000005056 compaction Methods 0.000 description 6
- 230000035515 penetration Effects 0.000 description 4
- 239000004576 sand Substances 0.000 description 4
- 230000003213 activating effect Effects 0.000 description 3
- 230000001419 dependent effect Effects 0.000 description 3
- 238000006073 displacement reaction Methods 0.000 description 3
- 239000003673 groundwater Substances 0.000 description 3
- 238000005096 rolling process Methods 0.000 description 3
- 230000006641 stabilisation Effects 0.000 description 2
- 238000011105 stabilization Methods 0.000 description 2
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000013016 damping Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- -1 however Substances 0.000 description 1
- 239000012535 impurity Substances 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/046—Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/08—Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Definitions
- the present invention relates to a method for producing material columns in the soil using a vibrator arrangement and a device with a vibrator arrangement.
- Jogger arrangements for the production of columns of material in the soil or for compaction of the soil are known in principle.
- Such vibrator assemblies include a material tube having a material outlet at a lower end and a vibrator disposed on the material tube.
- the vibrator In Studttleran elevenen, which are designed as a deep vibrator, the vibrator is disposed at a lower end of the material tube and is located during operation in the ground in Aufsatzrüttêt the vibrator sits on top of the material tube.
- the vibrator assembly is secured to a support device which is capable of moving the vibrator assembly in its longitudinal direction and which comprises, for example, a broker or a support arm of an earthworks implement.
- a support device which is capable of moving the vibrator assembly in its longitudinal direction and which comprises, for example, a broker or a support arm of an earthworks implement.
- the vibrator assembly is held by the carrier to a predetermined depth into the ground.
- the vibrator assembly is then progressively stepped out of the ground by the support, with a desired material, such as sand or gravel, being introduced into a cavity created after lifting below the vibrator assembly via the material tube.
- the vibrator arrangement is lowered at least once, but usually several times, into the material introduced in order to compact it and if necessary to drive it laterally into the ground.
- the support device for the deep vibrator can for example comprise a broker, to which the vibrator assembly is moved by means of a cable tensioning device in its longitudinal direction.
- a broker to which the vibrator assembly is moved by means of a cable tensioning device in its longitudinal direction.
- the DE 198 14 021 A1 describes a device for introducing an impurity into soils or compaction of the soil, with at least one torpedo deep vibrator as a processing tool, which is attached to a vibration isolating connector, which is connected to an at least three-membered boom mounted on a movable equipped with a turntable earthmover is.
- the device is provided with a material conveying tube along the vibrator, through which the foreign matter (preferably gravel, sand or pumped concrete) is conveyed to the Rüttlerspitze.
- the foreign matter is advantageously transported via a lock chamber first in an extension tube before it arrives in the material delivery pipe. Of the two closures of the lock chamber only one is open at all times.
- the extension tube is held by a compressed air connection not shown here permanently under an overpressure relative to the groundwater pressure at the Rüttlerspitze.
- the DE 103 10 727 A1 describes a device for introducing lime, gravel, sand, gravel or dry mortar or concrete into soft, displaceable trays for the production of vertical columns.
- a displacement device in particular a deep vibrator with lock tube or a displacement tube with closure is shaken from the soil surface into a viable or at least sustainable soil layer
- a lower column section which is supported directly by at least supportable soil layers is built up, in particular by means of the displacement device, from below to above from a rolling material
- a tubular casing is inserted from the bottom surface, passing through at least one unsupportable bottom layer, extending into the lower column section
- the wrapper is filled with rolling material to form an envelope-supported upper column section.
- the EP 1 273 714 A2 describes a method for compacting mobile floors for the purpose of ground improvement by post-raster compacting operations performed respectively with the following method steps: a deep vibrator is vibrated into the ground from the ground surface; the deep vibrator is pulled up shaking with compaction of the soil; as a feed material, at least in phases fiber-displaced rolling material is added during the pulling of the deep vibrator from the surface.
- the object of the present invention is to provide an improved method for the production of columns of material in the soil and an improved device with a vibrator arrangement for the production of columns of material in the soil.
- the device according to the invention comprises a device comprising: a vibrator arrangement comprising a vibrator, at least one first material tube having a longitudinal direction, and a material outlet at a lower end of the first material tube; and a vibrator assembly support device configured to move the vibrator assembly in the longitudinal direction of the first material tube.
- At least one lifting unit is arranged between the carrying device and the first material tube, which is designed to move at least the first material tube in its longitudinal direction.
- the leran eleven with the material outlet, which is arranged at least one material tube and a material inlet, starting from the support device below the lifting unit.
- the lifting unit of the vibrator is movable together with the first material tube in the longitudinal direction of the first material tube relative to the support device.
- the at least one lifting unit can be arranged between the vibrator arrangement and the carrying device. In this case, during operation, the entire vibrator arrangement can be moved by the lifting unit.
- a second material tube is provided which is slidably mounted relative to the first material tube, wherein the at least one lifting unit is arranged between the first and the second material tube.
- the at least one lifting unit is arranged between the first and the second material tube.
- a feed opening for feeding material into the pipe arrangement which has the first and second material pipes, can be arranged on the second material pipe. This feed opening remains stationary in a method of the first material tube by means of the lifting unit, so that even during the movement of the first material tube with the vibrator material can be fed into the tube assembly.
- the carrying device and the lifting unit are designed to move the vibrator arrangement in its longitudinal direction, wherein the longitudinal direction of the vibrator arrangement is defined by the longitudinal direction of the first material pipe.
- the maximum distance over which at least the first material tube can be moved with the vibrator is less than the maximum distance over which the vibrator arrangement can be moved by the carrier device.
- a maximum stroke of the lifting unit is thus less than a maximum stroke of the support device.
- the maximum stroke of the lifting unit is in particular less than a maximum possible penetration depth of the vibrator arrangement in the ground.
- the lifting unit allows longitudinal movements of the vibrator without requiring movement of the carrying device.
- Alternate up and down movements of the vibrator with a relatively small stroke, as they are required when introducing and compacting material can be carried out by means of the lifting unit, while the support device is required only for movements with a larger stroke, such as when introducing the Hinttleran eleven in the ground.
- the support device so that lower requirements to be made than in conventional devices for the production of columns of material in the ground, in which the movements with a small stroke must be performed by the support device.
- the support device may be a conventional deep shaker support such as a cable device, an earthmover support arm, or a tower device.
- the support device comprises a carriage which is movable on a tower or broker.
- the carriage By means of the carriage movement of the Ganttleranowski gloves over long distances is possible, as required for example when retracting the Trottleranowski whatsoever in the ground.
- the slide can be detected at the leader, which are possible movements of the Trottleranowski whatsoever means of the lifting unit in the carriage determined.
- the carriage may, for example, be moved by means of a conventional mechanism, such as a cable mechanism, on the leader.
- a second carriage is provided, which is also movable on the leader and can be fixed thereto.
- the lifting unit is arranged between the two carriages. With this arrangement, any up and down movements of the vibrator assembly on the broker are possible without the need for a rope device is required. If one of the carriages is detected, the other carriage can be released in this device and moved by means of the lifting unit on the leader. By alternately releasing and locking the carriage can be carried out any up and down movements, the direction of movement is dependent on the order in which the carriages are released and detected.
- An example of a method for making a column of material in the ground comprises providing a previously discussed apparatus, introducing the vibrator assembly to a predetermined depth into the ground, retracting the vibrator assembly so that a cavity remains beneath the vibrator assembly, introducing material into it the cavity for producing a material reservoir, retracting the vibrator assembly into the material reservoir using the lifting unit, and at least partially retracting the vibrator assembly from the material reservoir using the lifting unit.
- This method is suitable for both deep and top vibrators.
- the up and down movement of the vibrator assembly by means of the lifting unit for compressing the introduced material can be performed several times in succession. Here, each time the vibrator assembly is moved upwardly by the lifting unit, new material can be introduced into the resulting cavity below the vibrator assembly.
- FIG. 1 schematically shows a first embodiment of an apparatus for producing columns of material in the soil and / or for compaction of the soil.
- This apparatus comprises a vibrator arrangement 1, which has a feed pipe or material pipe 11 with an upper and a lower end, wherein at the lower end of the material tube 11, a vibrator 12 is arranged.
- the vibrator 12 is mounted vibration-damped in a manner not shown in detail on the material tube 11, so that vibrations resulting from vibrating the vibrator 12 vibrations are not transmitted or at least only to a small extent on the material tube 11.
- the material pipe 11 is in FIG. 1 - As also explained in the following FIG. 2 - Shown in cross-section, the other components are shown in side view.
- the material tube 11 which is also referred to as a silo tube, has at its lower end an outlet to which a further tube 16 is connected, which is guided parallel to the vibrator 12 to a tip of the vibrator 12 and in the region of the tip the vibrator forms a material outlet 13 of the vibrator arrangement 1.
- the further tube 16 may be mounted vibration-damped on the material pipe 11.
- the material tube 11 has, for example, a cylindrical geometry.
- the further tube 16 can be realized such that it partially surrounds the vibrator 12, and then has, for example, a crescent-shaped geometry in cross-section.
- the vibrator arrangement according to FIG. 1 in which the vibrator 12 is disposed at a lower end of the material pipe 11 is also referred to as a deep vibrator.
- FIG. 2 shows a device with a vibrator, which is designed as Aufsatzrüttler and in which the vibrator 12 is arranged on top of the material tube 11.
- the vibrator 12 and the material tube are not decoupled in terms of vibration, so that shaking movements of the vibrator 12 are transmitted to the material tube.
- a material supply which in the FIGS. 1 and 2 is shown only schematically and in the example has a laterally arranged on the material pipe 11 material container 14 and disposed between the material container 14 and the interior of the material tube 11 flap 15.
- the flap 15 can be opened and closed, wherein with the flap open material G, such as gravel, gravel or sand, can flow from the material container 14 into the interior of the material tube 11.
- the flap 15 is closed by means of its pressure device, not shown, an overpressure in the interior of the material tube 11, the in FIG. 1 is shown in cross section, can be generated.
- the production of such overpressure may be necessary, in particular, when material columns are to be produced in the ground, which reach below the groundwater level. An overpressure is required to bring material against the pressure of groundwater in the soil.
- a material lock (not shown) with two flaps can be provided, via which the material G is introduced into the interior of the material tube 11.
- Such a material lock can prevent a built-up in the interior of the material tube 11 overpressure escapes each time when material is re-supplied.
- any known material feeds can be used, such as, for example, those in which material is introduced via a delivery hose under pressure directly into the material tube 11.
- the device also comprises a support device 2 with a support element 21.
- the support device 2 can be realized in different ways, as will be explained below.
- the device comprises a lifting unit 3, which is realized in the illustrated example as a lifting cylinder with a cylinder piston 31 and a cylinder housing 32, wherein the cylinder piston 31 can be extended out of the cylinder housing 32 and retracted into the cylinder housing 32.
- the lifting cylinder 3 can be realized as a hydraulically, pneumatically or electrically operable cylinder.
- a lifting cylinder as a lifting unit is to be understood merely as an example and that any devices capable of carrying out lifting movements, such as, for example, electrically driven cable, belt or spindle arrangements, can be used.
- the lifting unit 3 is arranged so that it can move the vibrator arrangement in its longitudinal direction.
- the longitudinal direction of the vibrator assembly 1 in this case corresponds to the longitudinal direction of the silo tube 11, wherein the longitudinal direction of the silo tube 11 is the direction in which the silo tube 11 has its maximum extent.
- the lifting unit 3 is in the examples according to the FIGS. 1 and 2 between the support member 21 and the Trottleran onion 1, wherein in the illustrated lifting cylinder 3, the cylinder housing 32 is fixed to the support member 21 and the cylinder piston 31 by means of a mounting plate 33 at the upper end of the Studttleran eleven 1.
- the activating cylinder 3 can also be turned over, that is to say the cylinder piston 31 could be attached to a support member 21 and the cylinder housing 32 could be attached to the vibrator assembly 1.
- "Arranged between the support element 21 and the vibrator arrangement 1" in this context means, in particular, that the parts of the vibrator arrangement 1, that is, the vibrator 12, the silo tube 11 and a material feed opening, which in the examples according to the FIGS. 1 and 2 is represented by the flap 15, are arranged starting from the support device 2 below the lifting unit 3.
- a damping element (not shown) may be present between the support element 21 and the vibrator arrangement, which prevents or at least reduces the transmission of vibrations from the vibrator 12 to the support device 2.
- a method for producing a column of material in a soil B which is incorporated into the FIGS. 1 and 2 is also shown schematically, will be explained below.
- Stopf yarnlen by means of Hinttleran extract the vibrator assembly 1 is first introduced to a desired depth in the bottom B.
- the introduction of the vibrator 1 is carried out by shaking the vibrator 12, wherein the vibrator 1 is tracked by the support device 2 accordingly.
- the penetration of the deep vibrator 1 in the ground can be supported by the support device 2.
- the depth to which the vibrator arrangement 1 penetrates maximally into the ground B corresponds to the later depth of the material column.
- a flap 17 may be provided, which automatically closes during downward movements of the vibrator assembly by the pressure of the surrounding soil and thus prevents the ingress of soil material into the material tube 11, and that when lifting the Trottleranixtler below automatically opens the pressure of existing material in the material tube 11 material to deliver material.
- the tube 16 may extend in the region of the outlet obliquely with respect to the longitudinal direction of the material pipe 11, whereby the penetration of soil material can also be prevented or reduced.
- the lifting unit 3 may be extended when the vibrator assembly 11 reaches the maximum depth. In this case, the lifting of the deep vibrator 1 can be carried out by the lifting unit 3, a lifting of the deep vibrator 1 by the support device 2 is not required in this case. However, the lifting unit 3 can also remain retracted until the vibrator arrangement 1 has reached its maximum depth. In this case, the piecemeal lifting of the vibrator arrangement 1 is still carried out by the carrying device 2.
- the material introduced during the lifting of the vibrator arrangement 1 into the cavity below the vibrator arrangement 1 is then compacted or driven laterally into the soil.
- the vibrator 1 is guided by the lifting unit 3 at least once moved by shaking down into the material introduced.
- it is provided to move the vibrator assembly up and down several times using the lifting unit, with each lifting of the vibrator assembly 1 optionally new material can be introduced into the area below the Studttleran eleven.
- the height of the stroke, by which the vibrator arrangement 1 can be moved up and down by the lifting unit 3, is predetermined by the maximum stroke of the lifting unit 3. This stroke is for example in the range between 60cm and 150cm, especially in the range of 100cm.
- the lifting of the vibrator arrangement 1 takes place, for example, such that the lifting unit 3 is completely retracted.
- the lifting unit 3 can then be fully extended again in each case, in which case material is forced laterally into the soil by the vibrator arrangement in a lateral direction, which results in particularly thick stuffing columns.
- the lifting unit 3 in case of repeated moving up and down, although fully retract when moving upwards, but then no longer fully extend the vibrator assembly, and in particular to reduce the exit depth with increasing number of repetition steps.
- compaction step The operation of moving the vibrator assembly 1 downward by means of the lifting unit 3 is hereinafter referred to as compaction step.
- the lifting unit is extended by 80% of its extension path during a first compression step, only by 60% in a second repetition step, then by only 40%, and then only by 20%.
- the vibrator arrangement 1 is again lifted a little by the carrying device 2 when the lifting unit 3 is retracted, the lifting height corresponding to the height of a further column section to be produced.
- material is introduced into the cavity between the previously prepared column section and the vibrator assembly 1. This material is then summarized in an illustrated manner by repeated moving up and down of the vibrator assembly using the lifting unit 3, wherein optionally with each lifting of the Vibrator assembly 1 new material is introduced into the soil.
- the lifting unit has at least one hydraulic cylinder, which is retracted for lifting the Hinttlervorides 1 and extended to lower the Hinttlervorides.
- the extension This hydraulic cylinder of the lifting unit 3 required force can be detected by means of a building up in the hydraulic cylinder pressure.
- FIGS. 3A and 3B illustrate in each case devices for the production of columns of material in the soil and / or for compaction of the soil, in which the supporting devices 2 rope devices, for example, rope devices of a cable excavator.
- These cable device each comprise a pulley 22 which is rotatably mounted on the support member 21, and a guided by the pulley 22 circulating cable 23.
- the vibrator 1 is movable by the support device in its longitudinal direction.
- the lifting unit 3 is also at the in FIGS. 3A and 3B illustrated embodiments between the support member 21 and the Hinttleran angel 1 arranged.
- the vibrator arrangement 1 is in the embodiments according to the FIGS. 3A and 3B as well as the ones explained below FIGS. 4 to 7 , each designed as a deep vibrator. However, this is only an example, so the vibrator arrangement could for example be realized as Aufsatzrüttler.
- FIGS. 3A and 3B illustrated embodiments differ with respect to the attachment of the lifting unit 3 to the Studttleran eleven 1. While in the embodiment according to FIG. 3B the activating cylinder 3 is arranged in the region of a center axis of the material pipe 11 is in accordance with the embodiment FIG. 2A the activating cylinder 3 is fastened outside the center of the material tube 11, in the direction of the feed device 14. If the feeder 14 is filled with material, this will happen in the central suspension according to FIG. 3B that the material pipe 11 is tilted with respect to the vertical. A stabilization against such tilting is in a cable system as a support device 2 not possible. Such tilting is in the arrangement according to FIG. 3A prevented or at least reduced by the attachment of the lifting unit 3 to the deep vibrator 1 on a line in which a virtual fulcrum of the vibrator 1 is located takes place.
- the lifting unit is secured in the illustrated embodiments by means of a mounting plate 33 to the vibrator assembly.
- this mounting plate 33 can be moved during operation in order to explore the deep vibrator 1, regardless of the level of the feed device 14 in each case in the vertical.
- a controller with a tilt sensor can be used to control the position of the mounting plate 33, which is movable in this case by means of a mechanism, not shown in the horizontal direction.
- the inclination sensor determines the inclination of the vibrator assembly 1 relative to the vertical, wherein the controller adjusts the position of the mounting plate depending on the determined inclination.
- a tilt-dependent sliding mounting plate 33 can be provided regardless of the presence of the lifting unit.
- FIG. 4 shows a further embodiment of an apparatus for producing columns of material in the ground.
- the support device 2 is a support arm of a Erdbau réelles, at the top of the support member 21 is attached.
- FIG. 5 shows a further embodiment of an apparatus for producing columns of material in the ground.
- the support device 2 in this device comprises a tower or broker 25, on which a first carriage 24 in the longitudinal direction of the tower 25 is movable.
- the tower 25 can stand upright to make vertical columns in the ground.
- the tower 25 could also be inclined to the surface to make inclined columns in the floor in this case.
- the support member 21 is disposed on the first carriage 24, the lifting unit 3 is located between the support member 21 and the Studttleran onion 1 and is attached at one end to the support member 21 and the other end of the Ganttleran onion 1.
- the material tube of the vibrator arrangement 1 runs approximately parallel to the tower 25, so that by moving the carriage 24 on the tower 25, the vibrator arrangement 1 can be moved in its longitudinal direction.
- a cable device, a gear device, or the like is present.
- the deep-drawing apparatus 1 is moved over long distances, for example during the first introduction of the vibrator arrangement 1 into the ground, by means of the first carriage 24, while lifting movements of the vibrator arrangement 1 for compacting the introduced material are carried out with the aid of the lifting unit.
- the vibrator assembly 1 can only penetrate into the ground due to its own weight and the shaking movements of the vibrator. In one embodiment, it is therefore intended to release the carriage 24 when retracting the vibrator assembly 1 into the ground, so that the carriage follows the penetration movement of the vibrator arrangement 1 into the ground, but without exerting an additional force on the vibrator arrangement 1 via the carriage 24.
- the material column is produced in segments. For the production of each segment, the carriage 24 is detected and the Rüttlervorides 1 is raised and lowered several times by the lifting unit 3, wherein between the raising and lowering material can be applied.
- a lifting of the Garttlervorides 1 after making a segment can be done by means of the traversing device having, for example, the above-mentioned cable device, gear device or the like.
- FIG. 6A illustrates another example of an apparatus for producing columns of material in the ground. This device is based on the previously with reference to FIG. 5 explained device.
- the support device 2 additionally has a second carriage 26, which can be moved along the leader 25.
- the second carriage 26 is attached to the upper end of the vibrator assembly 1.
- the lifting unit 2 is arranged between the first and the second carriage 24, 26 or is arranged between the first carriage 24 and the upper end of the vibrator arrangement 1.
- FIG. 6B An example of a blocking device for blocking a carriage is shown in FIG FIG. 6B illustrated in which the first carriage 24 is shown together with the mast 25 in vertical cross section in a sectional plane CC.
- the carriage 24 comprises in the illustrated example rollers 27, by means of which the carriage 24 along a running surface of the tower 25 is movable.
- the running surface of the tower 25 is formed in the illustrated example by a side wall of the tower 25, which projects transversely to a longitudinal direction of the tower on both sides.
- Rollers 27 of the carriage 24 are arranged along a front side and a rear side of the tread.
- the carriage comprises, for example, at least eight rollers, namely four at the front and four at the rear of the tread, wherein in each case two rollers may be arranged opposite to the tread.
- the carriage 24 has a substantially U-shaped geometry in cross section, wherein the rollers 27 are arranged in the region of the ends of the U-legs.
- a brake or blocking device is present, which has a brake pad 29 and a brake cylinder 28.
- the Brake cylinder 28 is adapted to press the brake pad 29 in the activated state of the blocking device against the running surface of the tower 25, thereby pulling the carriage 24 away from the tread, whereby the blocking device 28, 29 together the wheels 27, along the back the tread are arranged to block the carriage.
- the structure of the second carriage 26 may correspond to the structure of the first carriage 24.
- the vibrator arrangement 1 can be moved as desired along the tower 25, without this - as in the embodiment according to FIG. 5 - A rope device or other pulling device would be required.
- the two carriages 24, 26 are sufficient in conjunction with the lifting unit 3, as will be explained below.
- the vibrator arrangement 1 is to be moved downwards along the tower 25, as is required, for example, during the first retraction of the vibrator arrangement 1 into the ground.
- the two slides 24, 26 alternately blocked on the mast 25, wherein when one of the carriage is blocked and the other is released, the lifting unit 3 is actuated.
- the lift unit 3 is initially retracted and that both carriages 24, 26 are blocked from the mast 25. If now the lower of the two carriages, ie the second carriage 26, is released while the first carriage 24 remains blocked, then the vibrator arrangement 1 can be moved downward by extending the lifting unit 3.
- the first carriage 24 can be "made up” by retracting the lifting unit 3.
- the vibrator arrangement 1 can then continue to be moved down. This process can be repeated until a desired position of the vibrator assembly 1 in the bottom or along the tower 25 is reached.
- the start-up of the deep vibrator 1 is carried out in a similar manner as the shutdown, the carriages 24, 26 are solved and blocked in reverse order.
- To start up the first first slide 24 is first released at first blocked carriage 24, 26 and retracted lifting unit 3 and then driven using the lifting unit 3 upwards.
- lifting movements ie, in the previously described devices
- H Up and down movements, the vibrator 1 carried out by means of the lifting unit 3.
- the lower carriage 26 is required in this device in conjunction with the first carriage 24 and the lifting unit 3 only when movements of the vibrator assembly 1 along the tower 25 are required to go beyond the maximum stroke of the lifting unit 3.
- FIG. 7 illustrates another embodiment of a device for the production of columns of material in the ground, which has a vibrator arrangement 1.
- the vibrator arrangement 1 is in FIG. 7 partially shown in cross-section.
- a supporting device 2 for holding the vibrator assembly 1 having a support member 21 is shown in FIG FIG. 7 shown only schematically.
- the lifting units 3A, 3B are in the device according to FIG. 7 arranged in the vibrator 1, which in this case has two material tubes: a first material tube 11 1 in the lower region of the vibrator 1, and a second material tube 11 2 in the upper part of the vibrator.
- the FIG. 7 illustrated vibrator arrangement is realized as a deep vibrator.
- the vibrator 12 is in this case arranged below the first material tube 11 1 .
- the statements apply in connection with FIG. 1 with respect to the arrangement of the vibrator on the material pipe 11 shown there accordingly.
- the vibrator arrangement could also be realized as a topping vibrator.
- the vibrator is arranged on the upper material pipe 11 2 .
- the feed arrangement with the material container 14 and the material opening is arranged on the upper material pipe 11 2 .
- Filling assembly 14, 15 shown any other filling arrangements could be provided.
- a closure 17 shown in phantom
- An optionally required overpressure would have to then not in the entire tube assembly with the first and second material tube, but only in the region of the first material tube below the closure 17 are generated.
- the first material pipe 11 1 and the second material pipe 11 2 are realized so that they are mutually displaceable in the longitudinal direction of the vibrator 1.
- the lifting units 3A, 3B are arranged between the first and second material pipes 11 1 , 11 2 and are designed to displace the first material pipe 11 1 in the longitudinal direction of the vibrator arrangement relative to the second material pipe 11 2 .
- the second material pipe 11 2 is fixedly attached to the support member 21 of the support device 2.
- the feed arrangement 14, 15 also remains stationary if strokes of the first material pipe 11 1 are carried out using the lifting units 3A, 3B for the purpose of compacting introduced material.
- the lifting units 3A, 3B for the purpose of compacting introduced material.
- the lifting units 3A, 3B are each arranged outside the material pipes 11 1 , 11 2 , the material pipes 11 1 , 11 2 being realized in the example in such a way that they taper in the area of the lifting units 3A, 3B.
- the lifting units 3A, 3B do not project beyond the vibrator arrangement 1 in the lateral direction.
- the dimensions of the vibrator arrangement 1 are predetermined in the lateral direction essentially by the diameter of the first material tube 11 1 in the lower region of the vibrator arrangement 1 and the diameter of the second material tube 112 in the upper region of the vibrator arrangement 1.
- the lifting units 3A, 3B can be protected to the side by a cover 18 2 , which is attached to the second material tube 11 2 and protects the lifting units 3A, 3B against pollution in the ground.
- first and second material tubes 11 1 , 11 2 in their longitudinal directions can also be coordinated so that during operation of the vibrator 1 not the upper second material tube 11 2 but only the lower first material tube 11 1 penetrates into the ground , In this case, can be dispensed with special protective measures in favor of lifting units 3A, 3B, and these can then protrude laterally beyond the Studttleran eleven 1.
- any other lifting devices can be provided as lifting units, which is able - compared to the total length of the Hinttleran Ich 1 - small stroke of Hinttleran Ich 1 or at least the top of the Hinttleran Ich as required, for example, when compacting introduced material.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Claims (24)
- Procédé de production d'une colonne de matériau dans le sol, qui comprend :a) la mise à disposition d'un dispositif, comprenant :i) un agencement (1) de vibrateur, qui a un vibrateur (12), au moins un premier tube (11; 111) de matériau, ayant une direction longitudinale, et une sortie (13) de matériau à une extrémité inférieure du premier tube (11; 111) de matériau,ii) un dispositif (2) porteur pour l'agencement (1) de vibrateur, qui est constitué pour déplacer l'agencement (1) de vibrateur dans la direction longitudinale du premier tube de matériau,iii) au moins une unité (3) à mouvement alternatif, qui est disposée entre le dispositif (2) porteur et le premier tube (11 ; 111) de matériau et qui est constituée pour déplacer le premier tube (11; 111) de matériau dans sa direction longitudinale,b) le recul de l'agencement (1) de vibrateur de manière à ce qu'un espace vide reste en dessous de l'agencement (1) de vibrateur,d) l'introduction de matériau dans l'espace vide pour la production d'un réservoir de matériau,e) l'introduction de l'agencement (1) de vibrateur dans le réservoir de matériau en utilisant la au moins une unité (3) à mouvement alternatif,f) au moins le recul partiel de l'agencement de vibrateur du réservoir de matériau en utilisant la au moins une unité (3) à mouvement alternatif.
- Procédé suivant la revendication 1, dans lequel on effectue les stades e) et f) du procédé plusieurs fois successivement.
- Procédé suivant la revendication 2, dans lequel, entre un stade e) du procédé et un stade f) du procédé, on sort du matériau par la sortie pour le matériau.
- Procédé suivant la revendication 2 ou 3, dans lequel la profondeur d'introduction de l'agencement de vibrateur au stade e) diminue au fur et à mesure qu'augmente le nombre des répétitions.
- Procédé suivant l'une des revendications précédentes, dans lequel le dispositif (2) porteur a au moins une poulie et au moins un câble passant sur la au moins une poulie.
- Procédé suivant l'une des revendications 1 à 4, dans lequel le dispositif (2) porteur a une potence d'un matériel de terrassement.
- Procédé suivant l'une des revendications 1 à 4, dans lequel le dispositif porteur a un mât (25) et au moins un premier chariot (24) pouvant se déplacer sur le mât.
- Procédé suivant l'une des revendications 1 à 4, dans lequel le premier chariot (24) a un dispositif (26, 27) d'arrêt, qui est constitué pour empêcher le au moins un premier chariot (24) de se déplacer sur le mât.
- Procédé suivant la revendication 8, dans lequel le chariot est arrêté par le dispositif (26, 27) d'arrêt pendant les stades e) et f) du procédé.
- Procédé suivant l'une des revendications précédentes, dans lequel le dispositif (2) porteur a un élément (21) porteur, l'unité (3) à mouvement alternatif étant fixée par une extrémité à l'élément porteur et par une autre extrémité à l'agencement (1) de vibrateur.
- Procédé suivant l'une des revendications 1 à 9, dans lequel l'agencement de vibrateur comporte, en outre :un deuxième tube (112) de matériau, qui est monté coulissant par rapport au premier tube de matériau,la au moins une unité (3A, 3B) à mouvement alternatif étant disposée entre le premier et le deuxième tubes (11; 111) de matériau.
- Procédé suivant l'une des revendications précédentes, dans lequel l'agencement de vibrateur est constitué sous la forme d'un vibrateur profond, le vibrateur (12) étant monté à une extrémité inférieure de l'agencement de vibrateur.
- Procédé suivant l'une des revendications 1 à 11, dans lequel l'agencement de vibrateur est constitué sous la forme d'un vibrateur couronne, le vibrateur (12) étant monté à une extrémité supérieure de l'agencement (1) de vibrateur.
- Procédé suivant la revendication 7 ou 8, dans lequel le dispositif porteur comporte, en outre :un deuxième chariot (26), qui peut se déplacer sur le mât (25), qui peut être arrêté par rapport au mât (25) et qui est fixé à l'agencement (1) de vibrateur,l'unité (3) à mouvement alternatif étant disposée entre le premier et le deuxième chariots (25, 26).
- Procédé suivant l'une des revendications précédentes, dans lequel l'unité (3) à mouvement alternatif comporte :un vérin à mouvement alternatif ou un entraînement motorisé à câble, à poulie ou à broche.
- Dispositif, qui comporte :un agencement (1) de vibrateur, ayant un vibrateur (12), un premier tube (11) de matériau, qui a une direction longitudinale, une sortie (13) de matériau à une extrémité inférieure du premier tube (11) de matériau et une entrée (15) de matériau,un dispositif (2) porteur de l'agencement (1) de vibrateur, qui est constitué pour déplacer l'agencement (1) de vibrateur dans la direction longitudinale du premier tube de matériau,au moins une unité (3) à mouvement alternatif, qui est disposée entre le dispositif (2) porteur et l'agencement (1) de vibrateur et qui est constituée pour déplacer l'agencement de vibrateur dans la direction longitudinale du premier tube (11) de matériau.
- Dispositif suivant la revendication 16, dans lequel le dispositif (2) porteur a au moins une poulie et au moins un câble passant sur la au moins une poulie.
- Dispositif suivant la revendication 16, dans lequel le dispositif (2) porteur a une potence d'un matériel de terrassement.
- Dispositif suivant la revendication 16, dans lequel le dispositif porteur a un mât (25) et au moins un premier chariot (24) pouvant se déplacer sur le mât.
- Dispositif suivant la revendication 19, dans lequel le premier chariot (24) a un dispositif (26, 27) d'arrêt, qui est constitué pour empêcher le au moins un premier chariot (24) de se déplacer sur le mât.
- Dispositif suivant l'une des revendications précédentes, dans lequel l'agencement de vibrateur est constitué sous la forme d'un vibrateur profond, le vibrateur (12) étant monté à une extrémité inférieure de l'agencement de vibrateur.
- Dispositif suivant l'une des revendications 16 à 20, dans lequel l'agencement de vibrateur est constitué sous la forme d'un vibrateur couronne, le vibrateur (12) étant monté à une extrémité supérieure de l'agencement (1) de vibrateur.
- Dispositif suivant la revendication 19 ou 20, le dispositif porteur comporte, en outre :un deuxième chariot (26), qui peut se déplacer sur le mât (25), qui peut être arrêté par rapport au mât (25) et qui est fixé à l'agencement (1) de vibrateur,l'unité (3) à mouvement alternatif étant disposée entre le premier et le deuxième chariots (25, 26).
- Dispositif suivant l'une des revendications 16 à 23, dans lequel l'unité (3) à mouvement alternatif comporte :un vérin à mouvement alternatif ou un entraînement motorisé à câble, à poulie ou à broche.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PL11711259T PL2534310T3 (pl) | 2010-02-09 | 2011-02-09 | Sposób wytwarzania słupów materiałowych i urządzenie wibracyjne z podnośnikiem |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102010001728 | 2010-02-09 | ||
DE102010001839A DE102010001839A1 (de) | 2010-02-09 | 2010-02-11 | Rüttlervorrichtung mit einer Hubeinheit und Verfahren zur Herstellung von Materialsäulen |
PCT/DE2011/050004 WO2011098081A2 (fr) | 2010-02-09 | 2011-02-09 | Procédé de production de colonnes de matériau et dispositif vibrant comprenant une unité de levage |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2534310A2 EP2534310A2 (fr) | 2012-12-19 |
EP2534310B1 true EP2534310B1 (fr) | 2015-09-09 |
Family
ID=44316444
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP11711259.9A Active EP2534310B1 (fr) | 2010-02-09 | 2011-02-09 | Procédé de production de colonnes de matériau et dispositif vibrant comprenant une unité de levage |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP2534310B1 (fr) |
DE (1) | DE102010001839A1 (fr) |
PL (1) | PL2534310T3 (fr) |
WO (1) | WO2011098081A2 (fr) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2642031B1 (fr) * | 2012-03-22 | 2019-07-10 | Keller Holding GmbH | Procédé de fabrication d'un équipement de protection pour la protection contre les vibrations dans le sol ainsi que dispositif correspondant |
EP3112535B1 (fr) * | 2015-07-03 | 2018-01-10 | BAUER Spezialtiefbau GmbH | Tuyau de remplissage destine a fabriquer une colonne de remplissage dans le sol et dispositif et procede associes |
CN111593724B (zh) * | 2020-05-30 | 2022-01-21 | 凤阳凯晨建设工程有限公司 | 一种施工用高效打夯机 |
DE102021128776A1 (de) | 2021-11-04 | 2023-05-04 | Alexander Degen | Rüttelvorrichtung und Verfahren zur Bodenverdichtung |
CN116732966B (zh) * | 2023-08-15 | 2023-10-13 | 江阴振博机械有限公司 | 一种双向振冲器 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02292410A (ja) * | 1989-04-28 | 1990-12-03 | Fudo Constr Co Ltd | 砂杭施工機 |
US5279502A (en) * | 1991-10-24 | 1994-01-18 | Geotechnics America, Inc. | Apparatus and method for constructing compacted granular or stone columns in soil masses |
DE19814021A1 (de) * | 1998-03-30 | 1999-10-14 | Degen Wilhelm | Gerät zum Einbringen eines Fremdstoffes in Böden oder zur Verdichtung des Bodens |
DE10108602A1 (de) * | 2001-02-22 | 2002-09-12 | Keller Grundbau Gmbh | Verfahren zum Herstellen von Säulen |
DE10133121A1 (de) * | 2001-07-07 | 2003-01-23 | Keller Grundbau Gmbh | Verfahren zur Verdichtung von Böden |
DE10310727B4 (de) * | 2003-03-12 | 2007-09-13 | Bauer Spezialtiefbau Gmbh | Füllrohr |
-
2010
- 2010-02-11 DE DE102010001839A patent/DE102010001839A1/de not_active Withdrawn
-
2011
- 2011-02-09 EP EP11711259.9A patent/EP2534310B1/fr active Active
- 2011-02-09 WO PCT/DE2011/050004 patent/WO2011098081A2/fr active Application Filing
- 2011-02-09 PL PL11711259T patent/PL2534310T3/pl unknown
Also Published As
Publication number | Publication date |
---|---|
WO2011098081A2 (fr) | 2011-08-18 |
WO2011098081A3 (fr) | 2012-06-28 |
EP2534310A2 (fr) | 2012-12-19 |
DE102010001839A1 (de) | 2011-08-11 |
PL2534310T3 (pl) | 2016-04-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2553112C2 (de) | Bohrgerät | |
EP2534310B1 (fr) | Procédé de production de colonnes de matériau et dispositif vibrant comprenant une unité de levage | |
DE19707687C1 (de) | Vorrichtung zum Herstellen von Materialsäulen im Boden | |
EP2133508A1 (fr) | Appareil de construction doté d'un mât téléscopique et procédé de fonctionnement d'un tel appareil | |
DE102012223992B3 (de) | Vorrichtung und Verfahren zur Bodenverdichtung und/oder Bodenverfestigung | |
EP3926099A1 (fr) | Vibrofonceur | |
DE102014011878B4 (de) | Bodenfräsmaschine, Verfahren zum Ausbau und Verfahren zum Einbau einer Fräseinrichtung | |
EP3152366B1 (fr) | Vibrofonceur | |
EP2103742B1 (fr) | Agitateur destiné à la fabrication de colonnes de matériau dans le sol | |
EP2683874B1 (fr) | Dispositif pour produire des pieux dans un sol | |
DE19941302A1 (de) | Vorrichtung und Verfahren zur Herstellung von im Boden versenkten Tragsäulen | |
DE3729561C2 (fr) | ||
DE102005008679A1 (de) | Verfahren zur Herstellung von Rammpfählen mit mindestens einem doppelwandigen Rammrohr | |
EP3911801B1 (fr) | Vibro-flottation pour compactage d'un sol | |
EP0903440B1 (fr) | Procédé et dispositif pour amélioration des sols avec un liant a poudre | |
DE3208492A1 (de) | Verfahren und vorrichtung zum einbringen von hohlpfaehlen in den boden | |
DE202010017629U1 (de) | Verbaueinrichtung | |
WO2022200096A1 (fr) | Engin de chantier, tuyau de déplacement et procédé de production d'une colonne de matériau de remplissage dans le sol | |
DE10329356B4 (de) | Vorrichtung zum Erstellen eines Fundaments entlang von Gleisen | |
WO2015091476A1 (fr) | Procédé de compactage du sol et/ou de stabilisation du sol | |
DE102013226121B4 (de) | Vorrichtung und Verfahren zur Bodenverdichtung und/oder Bodenverfestigung | |
EP2697437B1 (fr) | Vibreur comportant une suspension par câbles pénétrant dans le sol | |
DE102011111036A1 (de) | Verfahren und Vorrichtung zum Einbringen eines Gründungsrohres in den Meeresboden, insbesondere für die Gründung einer Offshore-Windenergieanlage | |
DE2639980A1 (de) | Verfahren zur herstellung von ortbetonpfaehlen |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20120828 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
DAX | Request for extension of the european patent (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
INTG | Intention to grant announced |
Effective date: 20150225 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 748246 Country of ref document: AT Kind code of ref document: T Effective date: 20150915 Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502011007811 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20150909 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151209 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151210 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160109 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160111 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160229 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502011007811 Country of ref document: DE |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20160610 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160209 Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160229 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160229 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160209 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 7 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 8 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20180221 Year of fee payment: 8 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20110209 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20180226 Year of fee payment: 8 Ref country code: PL Payment date: 20180119 Year of fee payment: 8 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150909 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20190209 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190209 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190228 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190209 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20240216 Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20240319 Year of fee payment: 14 |