EP2261430A2 - Bau eines Überhangs - Google Patents
Bau eines Überhangs Download PDFInfo
- Publication number
- EP2261430A2 EP2261430A2 EP20100165500 EP10165500A EP2261430A2 EP 2261430 A2 EP2261430 A2 EP 2261430A2 EP 20100165500 EP20100165500 EP 20100165500 EP 10165500 A EP10165500 A EP 10165500A EP 2261430 A2 EP2261430 A2 EP 2261430A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- slab
- beams
- concrete
- set forth
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/003—Balconies; Decks
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C2/00—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
- E04C2/02—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
- E04C2/04—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
Definitions
- the invention deals with construction engineering and relates to constructing an overhang on the wall of a building.
- the invention is particularly applicable to the construction of balconies.
- Concrete slab overhangs have been constructed earlier in such a way that to the wall are attached protruding I-beams, around the beams is fabricated a casting mold, followed by pouring concrete therein for producing a slab. After the slab has dried, the mold is removed and handrail posts and other accessories are secured to the slab.
- a commonly applied technique of renovating such balconies is to chisel away the old slab while leaving the beams in place, followed by casting a new slab on site. Even the beams are sometimes cut off, followed by constructing columns upon which is mounted an entirely new balcony.
- Publication JP 10-331250 A discloses a method for the construction of a balcony, said method comprising laying concrete boards to rest on top of wall cantilever I-beams.
- the boards have threaded holes in a bottom surface and the beams are provided with holes in the top flange in alignment therewith.
- the board is attached to the beams by screwing bolts through the holes into the holes of the board.
- a completed concrete slab having its bottom surface provided with an enclosure in alignment with each beam for accommodating the beam therein.
- the slab is pushed to its position supported on the beams, such that the beams become pushed into the enclosures.
- the slab is secured to the beams.
- the method is particularly suitable for constructing balconies. The method does not require on-site assembling and dismantling a casting mold, which reduces labor and facilitates construction. From the standpoint of technology and economy, the concrete slab is most beneficially fabricated at a precast concrete plant.
- the best way of securing the slab to the beams is by pouring concrete into the enclosures. At the same time, concrete works as a protection material against fire and corrosion.
- the slab can be secured also in another way.
- the slab is provided with a suitable fastening element for securing the slab to the beams, for example by welding.
- the enclosure must be filled with a fire protection material. This is most preferably done beforehand during the slab fabrication process. Another option is to fill the enclosures after placing the slab in its position.
- the slab has openings in line with the enclosure for bringing concrete or some other filler inside the enclosure.
- the openings can also be filled with concrete or some other filler mass.
- a rear end of the enclosure is sealed against the wall for a casting operation. If necessary, a separate sealing block can also be used.
- the method is particularly beneficial in renovation.
- the replaceable slab is just chiseled off, the beams are left in place, and a new slab is mounted thereupon.
- the distance of a slab from each beam is preferably adjustable.
- the slabs can be set precisely at a desired height, even if the top surfaces of the slabs had a slight mutual height discrepancy.
- This also enables the use of a rougher dimensional tolerance in the installation process of slabs.
- the slab may have openings in line with the beam, and those openings can be provided with a plate which is parallel to the slab plane and includes a threaded hole. Into the hole can be screwed a bolt for adjusting thereby the slab to an exactly flat position and correct height. Accordingly, prior to the setting of concrete, the slab can be carried by bolts responding to the top flange of a beam. This type of adjustment is easy and quick to perform in the installation process.
- a bottom plate for providing an enclosed structure.
- fig. 1 shows one slab of the invention placed to be supported by wall-mounted beams
- fig. 2 shows a section of fig. 1 in enlargement
- fig. 3 shows a partial enlargement.
- the concrete slab 3 is preferably made of fiber-reinforced concrete. It can be for example about 50-100 mm in thickness and about 1200-2500 * 3000-5000 mm in external dimensions. In order to provide a drain slope, the top surface of a slab can be appropriately declining.
- each opening In line with each beam 2, the slab 3 has two openings 4, one close to the rear edge and the other close to the front edge. In the cross-direction of a beam, each opening is wider than the beam's top flange. At the bottom surface of a slab, each opening is provided with a cross-beam extending steel flat bar 5 with a threaded hole 6 in the middle of it.
- the steel flat bar has a width which is less than the opening's diameter lengthwise of the beam.
- the holes have been made and the steel flat bars have been attached in conjunction with the casting operation. The holes are adapted to receive bolts by screwing for thereby setting the slab by means of the bolts to be supported by the beams in a precisely straight position.
- a steel enclosure 7 Fixed to a bottom surface of the slab 3 in line with each beam 2 is a steel enclosure 7, within which the beam settles as the slab is pushed to its position to be supported by the beams.
- a steel enclosure 7 Fixed to a bottom surface of the slab 3 in line with each beam 2 is a steel enclosure 7, within which the beam settles as the slab is pushed to its position to be supported by the beams.
- side plates 8 Along lateral edges of the slab are mounted side plates 8 of steel and a front edge is provided with a front plate 9, whereby to both of these plates is fixed a bottom plate 10 of appropriate material.
- the slab 3 is hoisted up and pushed to be supported on top of the beams 2 all the way to a panel or insulation present on a wall surface. If necessary, bolts are screwed into the holes 6 and the slab is adjusted to a flat position. Thereafter, the enclosures 7 are filled up with concrete by pouring it in through the openings 4. If necessary, the rear end of the enclosures can be closed by means of a separate plate for the duration of a casting operation.
- the holes 4 can also be filled with concrete. However, these can also be filled with some other appropriate mass. If desirable, the mass can even be in a different color than the slab surface.
- the side plates 8 and 9 can be fitted beforehand also with balcony handrails and other possible accessories, or these can be installed in a slab which has already been stabilized in its position.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Finishing Walls (AREA)
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FI20095644A FI123579B (fi) | 2009-06-10 | 2009-06-10 | Menetelmä betoniulokkeen muodostamiseksi ja betonilaatta |
Publications (3)
Publication Number | Publication Date |
---|---|
EP2261430A2 true EP2261430A2 (de) | 2010-12-15 |
EP2261430A3 EP2261430A3 (de) | 2012-08-22 |
EP2261430B1 EP2261430B1 (de) | 2016-04-06 |
Family
ID=40825350
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP10165500.9A Not-in-force EP2261430B1 (de) | 2009-06-10 | 2010-06-10 | Bau eines Überhangs |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP2261430B1 (de) |
FI (1) | FI123579B (de) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2666918A3 (de) * | 2012-05-21 | 2014-06-25 | LO Rakenne Oy | Balkon |
WO2014174269A1 (en) * | 2013-04-22 | 2014-10-30 | Sapphire Balustrades Ltd | Balcony |
FR3031530A1 (fr) * | 2015-01-14 | 2016-07-15 | Tbi | Balcon a consoles coulissantes |
EP3061880A1 (de) * | 2015-02-24 | 2016-08-31 | FEHR Groupe | Fertigbalkon mit rippen |
GB2558272A (en) * | 2016-12-23 | 2018-07-11 | Brooksby Projects Ltd | Balcony structures |
CN108842964A (zh) * | 2018-06-27 | 2018-11-20 | 中国二十二冶集团有限公司 | 钢结构装配式住宅预制叠合梁施工方法 |
SE544321C2 (en) * | 2021-04-28 | 2022-04-05 | Nordiska Balco Ab | Suspension system for a balcony, a method for suspending a balcony on an exterior wall structure of a building and the use of such suspension system |
GB2600746A (en) * | 2020-11-09 | 2022-05-11 | Sapphire Balconies Ltd | Balcony developments |
WO2024110218A1 (en) * | 2022-11-22 | 2024-05-30 | Svein Berg Holding As | Cantilevered corner balcony |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110172912A (zh) * | 2019-05-04 | 2019-08-27 | 湖北省路桥集团有限公司 | 一种实心墩盖梁加工施工方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10331250A (ja) | 1997-05-29 | 1998-12-15 | Sekisui House Ltd | バルコニー・廊下の構造とそれに使用する床板 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3114486A1 (de) * | 1981-04-10 | 1982-10-28 | Hans Veit 8602 Schlüsselfeld Dennert | Als balkonkragplatte ausgebildete deckenplatte fuer gebaeude-geschossdecken |
BE1007398A3 (fr) * | 1993-08-20 | 1995-06-06 | Rebuild World Rbw Sa | Supports pour bow-windows et balcons et batiment comportant ces supports. |
-
2009
- 2009-06-10 FI FI20095644A patent/FI123579B/fi active IP Right Grant
-
2010
- 2010-06-10 EP EP10165500.9A patent/EP2261430B1/de not_active Not-in-force
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10331250A (ja) | 1997-05-29 | 1998-12-15 | Sekisui House Ltd | バルコニー・廊下の構造とそれに使用する床板 |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2666918A3 (de) * | 2012-05-21 | 2014-06-25 | LO Rakenne Oy | Balkon |
WO2014174269A1 (en) * | 2013-04-22 | 2014-10-30 | Sapphire Balustrades Ltd | Balcony |
AU2014259192B2 (en) * | 2013-04-22 | 2017-09-21 | Sapphire Balconies Ltd | Balcony |
US10400437B2 (en) | 2013-04-22 | 2019-09-03 | Sapphire Balconies Limited | Balcony |
FR3031530A1 (fr) * | 2015-01-14 | 2016-07-15 | Tbi | Balcon a consoles coulissantes |
EP3061880A1 (de) * | 2015-02-24 | 2016-08-31 | FEHR Groupe | Fertigbalkon mit rippen |
GB2559872B (en) * | 2016-12-23 | 2019-08-21 | Brooksby Projects Ltd | Balcony structures |
GB2559872A (en) * | 2016-12-23 | 2018-08-22 | Brooksby Projects Ltd | Balcony structures |
GB2558272A (en) * | 2016-12-23 | 2018-07-11 | Brooksby Projects Ltd | Balcony structures |
CN108842964A (zh) * | 2018-06-27 | 2018-11-20 | 中国二十二冶集团有限公司 | 钢结构装配式住宅预制叠合梁施工方法 |
GB2600746A (en) * | 2020-11-09 | 2022-05-11 | Sapphire Balconies Ltd | Balcony developments |
GB2600746B (en) * | 2020-11-09 | 2023-03-08 | Sapphire Balconies Ltd | Balcony developments |
SE544321C2 (en) * | 2021-04-28 | 2022-04-05 | Nordiska Balco Ab | Suspension system for a balcony, a method for suspending a balcony on an exterior wall structure of a building and the use of such suspension system |
SE2150533A1 (en) * | 2021-04-28 | 2022-04-05 | Nordiska Balco Ab | Suspension system for a balcony, a method for suspending a balcony on an exterior wall structure of a building and the use of such suspension system |
WO2022229075A1 (en) * | 2021-04-28 | 2022-11-03 | Nordiska Balco Ab | Suspension system for a framework structure, a method for suspending a framework structure on an exterior wall structure of a building and the use of such suspension system |
WO2024110218A1 (en) * | 2022-11-22 | 2024-05-30 | Svein Berg Holding As | Cantilevered corner balcony |
Also Published As
Publication number | Publication date |
---|---|
EP2261430B1 (de) | 2016-04-06 |
EP2261430A3 (de) | 2012-08-22 |
FI123579B (fi) | 2013-07-31 |
FI20095644A (fi) | 2010-04-08 |
FI20095644A0 (fi) | 2009-06-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2261430B1 (de) | Bau eines Überhangs | |
KR100533547B1 (ko) | 프리캐스트 바닥판과 거더의 연결구조 | |
CN109707173B (zh) | 装配式叠合梁板安装辅助装置的施工方法 | |
US10837173B2 (en) | Beam-column connection structure and method of making the same | |
KR100541965B1 (ko) | 강재가 콘크리트의 자중을 부담하는 강합성 거더의 제작장치 및 그 제작 방법 | |
US7908804B2 (en) | Structural lintel assembly and building construction method using the same | |
JP4738886B2 (ja) | 設備用基礎 | |
US8844224B2 (en) | Utility dowel bracket | |
CN113356582B (zh) | 一种浇筑钢梁外包混凝土的模具及施工方法 | |
CN110337519B (zh) | 永久性混凝土模壳及使用这种模壳制造金属混凝土复合结构的方法 | |
CN114368696A (zh) | 一种塔吊附墙连墙件的预埋施工方法 | |
CN113482007A (zh) | 一种腰梁支护结构及其施工方法 | |
JP2008255724A (ja) | アンカーボルト付基礎構造の施工用治具 | |
KR101880813B1 (ko) | 샌드위치 피씨 패널 구조물 및 이를 이용한 구조물 시공방법 | |
KR100860592B1 (ko) | Pc블럭 적층시공용 가설구조 | |
RU122678U1 (ru) | Опалубочный щит | |
KR100450113B1 (ko) | 다층 건축물의 계단 형성구조 | |
KR101078292B1 (ko) | 슬래브 거푸집 조립체 및 슬래브 시공 방법 | |
US20170254070A1 (en) | Wall Construction | |
JP7143208B2 (ja) | プレキャストコンクリート用型枠及び基礎ブロックの製造方法 | |
EP3134586B1 (de) | Vorrichtung und verfahren zur verankerung eines überhängenden elements an eine konstruktion | |
JP7479228B2 (ja) | プレキャストコンクリート板、およびコンクリート構造物の構築方法 | |
CN211647445U (zh) | 一种用于建筑工程中的装配式建筑支撑座 | |
CN211647433U (zh) | 一种钢筋混凝土梁加固结构 | |
JP6085151B2 (ja) | 床開口部穴埋め工法及びそれに使用する型枠 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME RS |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E04B 1/00 20060101AFI20120531BHEP |
|
PUAF | Information related to the publication of a search report (a3 document) modified or deleted |
Free format text: ORIGINAL CODE: 0009199SEPU |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME RS |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
D17D | Deferred search report published (deleted) | ||
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E04B 1/00 20060101AFI20120703BHEP |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME RS |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: LO RAKENNE OY |
|
17P | Request for examination filed |
Effective date: 20130208 |
|
17Q | First examination report despatched |
Effective date: 20150312 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
INTG | Intention to grant announced |
Effective date: 20151028 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 788004 Country of ref document: AT Kind code of ref document: T Effective date: 20160415 Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602010031987 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D Ref country code: NL Ref legal event code: MP Effective date: 20160406 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 788004 Country of ref document: AT Kind code of ref document: T Effective date: 20160406 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160706 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160806 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160707 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160808 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602010031987 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
26N | No opposition filed |
Effective date: 20170110 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20160706 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20170228 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160610 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160706 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20100610 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160610 Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 Ref country code: MT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20180619 Year of fee payment: 9 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160406 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602010031987 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200101 |