EP1811127A1 - Verfahren für den Meeresbodenabbau - Google Patents

Verfahren für den Meeresbodenabbau Download PDF

Info

Publication number
EP1811127A1
EP1811127A1 EP06447012A EP06447012A EP1811127A1 EP 1811127 A1 EP1811127 A1 EP 1811127A1 EP 06447012 A EP06447012 A EP 06447012A EP 06447012 A EP06447012 A EP 06447012A EP 1811127 A1 EP1811127 A1 EP 1811127A1
Authority
EP
European Patent Office
Prior art keywords
seabed
vessel
throughput
dredging unit
solid material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP06447012A
Other languages
English (en)
French (fr)
Inventor
Nick Heude
Bart Verboomen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dredging International NV
Original Assignee
Dredging International NV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dredging International NV filed Critical Dredging International NV
Priority to EP06447012A priority Critical patent/EP1811127A1/de
Priority to BE2007/0025A priority patent/BE1018431A3/nl
Priority to NL1033266A priority patent/NL1033266C2/nl
Publication of EP1811127A1 publication Critical patent/EP1811127A1/de
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/88Dredgers; Soil-shifting machines mechanically-driven with arrangements acting by a sucking or forcing effect, e.g. suction dredgers
    • E02F3/90Component parts, e.g. arrangement or adaptation of pumps
    • E02F3/907Measuring or control devices, e.g. control units, detection means or sensors
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C50/00Obtaining minerals from underwater, not otherwise provided for

Definitions

  • Aggregate products such as sand and gravel are commonly manufactured by mining the seabed.
  • a vessel equipped with a dredging unit may be employed, which dredging unit may stir up the sea bed using an agitation means and bring the resulting slurry to the surface through a suction pipe.
  • the solid material is then separated from the water which is returned to the sea.
  • the dredged solid material is retained.
  • the pumped suspension can be conveyed by pipeline to another location, and the desired product separated at the alternate location.
  • the solid material recovered by dredging is processed by extracting desirable components such as sand and gravel. Other components may also be extracted such as clay, larger particulates etc.
  • a problem with obtaining solid material from offshore locations is expense of the operation.
  • the increase in demand for construction materials has brought aggregate prices down to a minimum sustainable level.
  • the environmental impact of sea bed mining is also a concern, possibly affecting inner shelf flows, coastal erosion and retreat and fauna, flora and water quality in the area of mining.
  • the present invention relates to a method for mining the seabed by means of a shipping vessel equipped with dredging unit for removing material from the seabed, which method monitors the quantity of a suspension of solid material extracted from the seabed over a period of time i.e. the throughput. If the throughput monitored during extraction is above a threshold value, the extraction is considered efficient; below the threshold, it is deemed inefficient.
  • An efficient extraction means the extraction is economic and/or has low environmental impact. Thus, the suitable regions for extraction can be determined.
  • the method can be used to make a real-time assessment, thus, it can be determined during an extraction by a dredging vessel whether or not to continue in the same area, or to extract from another area.
  • the threshold can be set to continue only with low-environmental impact or profitable extractions or both.
  • An excavation map of an area indicating suitable and unsuitable extraction regions.
  • An area of seabed may be surveyed in a short period using the method in order to provide an overview of the best and poorest areas.
  • the dredging vessel may return to perform a full extraction of the most preferred seabed regions, planning the extraction timetable and route efficiently using the map prepared during the survey.
  • the method allows dredging to continue when sufficient loose material is available. Dense or deeply seated sand, requiring extensive extraction may be set to fall below the threshold, which would stop extraction. Thus, the seabed is somewhat preserved by refraining from deep excavation.
  • the environmental impact of mining is limited by restricting extraction to areas of relatively loose material. These regions are not as established with sealife. Consequently, implementing the present method reduces environmental impact, while restricting excavation to loose material which is more economical to extract.
  • the present method monitors several parameters during extraction in order to automatically arrive at a throughput value. There is no need to make manual adjustments to take account of seabed height, contact with the sea, or position of the suction pipe, as these are automatically implemented in the method.
  • a dredging vessel can actively pass across a sea bed, in a survey operation or in an extraction process, and indicate throughput, while conditions such as rough seas and variable seabed depth which might otherwise affect readings are accounted in the calculation.
  • a dredging unit 3 suspended from the vessel 1, which moves across the sea bed 12 principally in concert with the movements of the vessel 1. Solid material present on the seabed 12 is optionally stirred up, and a suspension thereof is sucked up and deposited for storage and/or processing in the vessel 1.
  • a pipe 2, suspended from the vessel 1 couples the underwater dredging unit 3 to extraction pumps 13 located on the vessel 1, through which extracted material flows from the seabed 12.
  • the dredging unit 3 is equipped with a suction head 4 for taking up loosened solid material and water i.e. the suspension.
  • the material may be loose per se, or may become loose with the contact of the dredging unit 4 with seabed 12, for example, by the dragging-effect of the unit across the seabed by the vessel.
  • the dredging unit 4 may optionally be equipped with a means to agitate the seabed 12, which means loosens solid material for subsequent take-up by the suction head 4.
  • the agitation means can be any suitable means, for example, water jets, rotating metal blades, compressed air, or metal scoops. To minimise environmental impact and to minimise wear and maintenance, water jets may be the most suitable agitation means.
  • the position of the dredging unit 3 may be adjustable independently of the position of the vessel to allow a fine control of the position of the unit.
  • the independent movement can be achieved, for example, by the use of local (underwater) hydraulic joints or by propulsion means located in the underwater dredging unit 3.
  • the dredging unit 3 is connected to the vessel 1 by means of a pipe 2.
  • the pipe 2, and associated supply cables and/or piping 11, can be the only principal means of attachment to the vessel 1, necessitating requirements of strength and durability of the pipe 2 and joints.
  • the pipe 2 can be flexible, in which case the pipe 2 is preferably suspended substantially horizontally from the vessel by means of cables 8, 9 which are unwound or wound from winches 5, 6 present on the vessel 1.
  • a pipe 2 having a comparative long length can be supported by a few spaced-apart cables 8, 9 by disposing the pipe 2 in the longitudinal direction of the vessel.
  • the pipe 2 When the vessel 1 has arrived at the desired location, the pipe 2 can be lowered by paying out cables 8, 9 by means of the winches 5, 6.
  • the position of the pipe underwater can be horizontal or at an incline to the sea surface as is indicated in Fig. 1.
  • the flexible pipe 2 is preferably suspended short of the seabed 12, e.g . 1 to 3 m at the lowest point above the sea bed, while the dredging unit 3 is allowed to contact the seabed 12.
  • the cables 8, 9 connected to the pipe 2 are continually adjusted by a swell compensation device so that the weight of the pipe 2 is compensated by the pull-force in the cables 8, 9.
  • swell compensation systems are known in the art of dredging, and can be, for example, the DEICO system.
  • the dredging unit 3 is allowed to contact the seabed 12.
  • a separate cable 10 may be connected to the dredging unit 3, which allows contact of the dredging unit 3 with the seabed 12.
  • the same swell compensation device can be implemented in the cable 10 attached to the dredging unit 3, such device maintains the contact of the dredging unit 3 with the sea bed 12, and can indicate when the dredging unit 3 contacts the seabed 12 or not.
  • the present invention determines the throughput achieved during extraction at a particular location by monitoring:
  • the suspension speed (i) can be measured using in-line detectors present in the pump or tubing, giving a real-time indication. Alternatively, it may be determined by monitoring the change in level of suspension in on-board storage tanks and noting the time.
  • the suspension concentration (ii) can be measured by also by use of inline detectors which calculate a proportion of solid matter to water in the flow through. Alternatively, it may be determined by monitoring the changing mass storage tanks as they fill, and comparing the mass with the mass expected for the same volume of sea water. Other techniques and devices for measuring (i) and (ii) are known in the art, and may be implemented in the present invention.
  • the rate of extraction of solid material i.e. the throughput at a particular location is obtained. It can be measured, for example in kg/hour or tonnes/hour. From the throughput, it can be determined whether the material is sufficiently loose to warrant an economical / low environmental impact extraction, or whether another site should be chosen.
  • the throughput calculation is distorted owing to periods of non-contact by the dredging unit 3 with the seabed 12.
  • Non-contact can arise, for example, due to pitching of the vessel 1.
  • the inventors have discovered that monitoring the swell compensation device associated with the cable 10 attached to the dredging unit 3, gives an indication of contact with the seabed 12. Rather than try to compensate for every episode of non-contact by paying out more cable, or introducing a linear correction factor, the inventors have found it is most efficient to set a threshold for implementing swell compensation for only larger changes in the depth of the seabed. Thus, for minor variations in sea bed depth, the mixture concentration and mixture speed data are ignored for the periods when the dredging unit 3 is not engaged with the seabed 12.
  • Another embodiment of the present invention is a method as described herein, where mixture concentration and mixture speed data are ignored for the periods when the dredging unit 3 does not contact the seabed 12.
  • the calculation of throughput may be derived from intermittently collected data.
  • the state of contact of the dredging unit 3 with the seabed 12 can be determined from the swell compensation device e.g . the DEICO system.
  • the throughput data can advantageously be indicated on a survey map of a region.
  • the survey map allows an operator to most efficiently mine the seabed using a planned route, and also estimate time it would take to obtain the payload limit. Where the survey site is large, and regions of suitable material are located in separate, discrete areas, such map can indicate the viability of a complete or targeted extraction.
  • the position of the vessel is known using a satellite navigation system such as, for example, global positioning satellite system (GPS), Galileo, Beidou etc.
  • GPS global positioning satellite system
  • Galileo Galileo
  • Beidou Beidou
  • Such navigation system is routinely present on shipping vessels.
  • a correction to the co-ordinate of the vessel 1 is applied in the present invention, to yield more precise co-ordinates of the dredging unit 3.
  • the displacement of the dredging unit 3 from the satellite receiver can be derived by any known technique.
  • signal from a radio beacon placed on the dredging unit 3 may be detected by two or more receivers on the vessel, and the location of the unit calculated by triangulation.
  • the length of cable and the angle of inclination gives the displacement of the dredging unit 3 by simple geometry.
  • a survey map of a region indicating suitable regions for extraction can be calculated.
  • the map can be represented in any suitable form. For example, as a series of throughput contours, as a coloured 'heat' map, as a relief map etc.
  • the throughput values may be converted into particle density, and displayed so.
  • the map may display regions above a certain threshold in one colour (e.g. green), and below such threshold in an alternate indication (e.g. red). Further indicated may be depth of the sea bed, relief features of the sea bed, water currents, wind speeds, atmospheric pressured, or adapted as required.
  • the method described herein allows determination of the most efficient areas for mining, and can be implemented economically using systems and technologies which already exist on most vessels.
  • the method can be incorporated into a device which is configured to carry out the steps of the method.
  • a device which is configured to carry out the steps of the method.
  • Such device receives information allowing a calculation of throughput.
  • a dredging vessel typically comprises a marine integrated computer system which receives information from a variety of ship sensors such as the satellite navigation system and dredging sensors; it presents pertinent information to one or more operators, and can accept commands for controlling devices which as steering, engine speed or other aspects of interest.
  • the system comprises several components as indicated in Figure 2, including:
  • I/O-systems This is an array of computers 21 disposed with input/output (I/O) modules which communicate with a plurality of hardware devices. It may receive input sensor data from, for example, a satellite navigation system, fathometer, gyrocompass, velocity profiler, temperature sensor, dredging unit etc. It may provide output data to control the steering, engine speed, suction pipe depth etc.
  • I/O input/output
  • HMI Workstations These are work stations or terminals 23 which can display I/O information, for example, as a processed graphical or numerical representations. This can inform an operator about the status of the vessel such as sailing course, vessel speed, wind speed, sea depth, depth of dredging unit etc.
  • the HMI workstations also allow the operator to provide commands, which are passed via the integrated I/O systems to the relevant device.
  • a command to steer the ship can be received by an HMI workstation 23, which command is passed 22 to an integrated I/O system 21 for remote control of, for example, a rudder.
  • Survey computer This is a computer 24 which displays geographical information, for example, a map indicating the position and direction of the vessel to the dredge master and steer officer, ensuring the course of the vessel is correct. It may also indicate zones suitable for dredging determined, for instance, by satellite imagery. It may also be capable of receiving information 25 from the integrated I/O systems such as satellite navigation data.
  • a common version of a survey computer is a Dredge Track Presentation System (DTPS).
  • DTPS Dredge Track Presentation System
  • the present invention may be implemented into the HMI workstation 23 and/or into the survey computer 24. Alternatively, it can be implemented on any computer capable of receiving data from the relevant sensors.
  • the program typically used in marine HMI workstations allows the operator to change the configuration of the display and input choices for a particular task.
  • data from sensors pertinent to the present invention i.e. those which measure the suspension speed, suspension concentration, swell compensation, and optionally location of the vessel can be processed and displayed by an existing HMI workstation.
  • An example of a display from HMI workstation implementing the present invention as an extension is given in Figure 3.
  • Such displayed data can allow an operator to monitor the dredging process, which can be controlled. Therefrom, the operator can determine an economical dredging operation.
  • the standard survey visualisation program which is used by the dredge crew can be modified to process sensor data, and display information obtained by the present invention.
  • the survey computer indicates the route and course of the vessel, providing additional information such as depth and differential height data as an overlay.
  • the survey computer may be connected to the integrated 1/0-systems, thus data from sensors pertinent to the present invention i.e. those which measure the suspension speed, suspension concentration, swell compensation, and location of the vessel can be processed and displayed by the survey computer.
  • an extra visualisation layer may be added which indicates suitable regions for extraction based on the calculation of throughput from the I/O data.
  • the throughput information may be provided in graded colours e.g . from green (best) to red (worst) overlaid on the map.
  • the data can be that obtained from an earlier survey, or from a survey in progress.
  • an overlay may indicate blue for a throughput of, for example, 1000 tonnes/h which is updated with another colour when the throughput changes.
  • the number of colours can be user defined (e.g. just two colours, a pallet of colours, or a smooth gradient of colours).
  • one track can be indicated; more than one dredging unit can be reflected by displaying throughput of each unit separately.
  • An example of a survey chart is provided in Figure 4.
  • modules which can interface with HMI workstation and /or survey computer. These modules might be present in the HMI workstation, in the integrated I/O systems or in the survey computer. The use of modules permits faster and/or more complex processing, and may allow smooth communication between the various hardware and software elements making up the systems.
  • One embodiment of the present invention is a method of determining an efficient extraction of solid material from a seabed (12) by means of a vessel (1) equipped with a dredging unit (3) for removing a suspension of solid material from the seabed (12), which method comprises the steps:
  • Another embodiment of the present invention is a method as described above, wherein the throughput is determined by measuring a speed and concentration of extracted suspension passing through a suction pipe (2) connecting the dredging unit (3) to the vessel (1), in order to arrive at the throughput.
  • Another embodiment of the present invention is a method as described above, wherein the suspension speed and suspension concentration data are excluded from determining throughput for periods when the dredging unit (3) does not contact the seabed (12).
  • Another embodiment of the present invention is a method as described above, wherein the dredging unit (3) is suspended from the vessel (1) by a cable coupled to a swell compensation system and the contact of the dredging unit (3) with the seabed (12) is determined from said swell compensation system.
  • Another embodiment of the present invention is a method for creating a survey map of a seabed (12) indicating efficient areas for extraction of solid material comprising the steps of performing the method of claim 1, while identifying the location of the dredging unit (3).
  • Another embodiment of the present invention is a method for creating a survey map as described above, wherein the location of the dredging unit (3) is identified by applying an offset to the location of the vessel (1) as determined by a satellite navigation system.
  • Another embodiment of the present invention is a survey map of a seabed (12) indicating efficient areas for extraction of solid material obtained using a method for creating a survey map as described above.
  • Another embodiment of the present invention is a device configured to perform a method according to any of the methods described above.
  • Another embodiment of the present invention is a computer program stored on a computer readable storage device capable of performing any of the methods described above.
  • Another embodiment of the present invention is a marine human-machine interface workstation (23) configured to perform any of the methods described above.
  • Another embodiment of the present invention is a marine survey computer (24) configured to perform any of the methods described above.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Position Fixing By Use Of Radio Waves (AREA)
  • Geophysics And Detection Of Objects (AREA)
EP06447012A 2006-01-20 2006-01-20 Verfahren für den Meeresbodenabbau Withdrawn EP1811127A1 (de)

Priority Applications (3)

Application Number Priority Date Filing Date Title
EP06447012A EP1811127A1 (de) 2006-01-20 2006-01-20 Verfahren für den Meeresbodenabbau
BE2007/0025A BE1018431A3 (nl) 2006-01-20 2007-01-22 Werkwijze voor het ontginnen van de zeebodem.
NL1033266A NL1033266C2 (nl) 2006-01-20 2007-01-22 Werkwijze voor het ontginnen van de zeebodem.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP06447012A EP1811127A1 (de) 2006-01-20 2006-01-20 Verfahren für den Meeresbodenabbau

Publications (1)

Publication Number Publication Date
EP1811127A1 true EP1811127A1 (de) 2007-07-25

Family

ID=36685808

Family Applications (1)

Application Number Title Priority Date Filing Date
EP06447012A Withdrawn EP1811127A1 (de) 2006-01-20 2006-01-20 Verfahren für den Meeresbodenabbau

Country Status (3)

Country Link
EP (1) EP1811127A1 (de)
BE (1) BE1018431A3 (de)
NL (1) NL1033266C2 (de)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014528524A (ja) * 2011-10-03 2014-10-27 マリーン リソーシーズ エクスプロレイション インターナショナル ビーヴイ 海底地盤から堆積物を回収する方法
CN104712003A (zh) * 2015-03-17 2015-06-17 中国电建集团贵阳勘测设计研究院有限公司 一种小型水电站清淤设备
WO2015086856A1 (en) * 2013-12-13 2015-06-18 Baggerwerken Decloedt En Zoon Method for dredging an underwater bottom in an area using a dredging device
CN106592674A (zh) * 2016-12-16 2017-04-26 浙江海洋大学东海科学技术学院 一种采排一体挖泥船
EP3717704B1 (de) 2018-02-22 2021-03-17 Michael Detering Vorrichtung für einen sedimenttransfer in gewässern als auch ein verfahren für eine transferierung von sediment in gewässern

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3512281A (en) * 1966-11-28 1970-05-19 Mineraal Technologisch Inst Swell compensator for a drag suction dredger
JPS5888636A (ja) 1981-11-24 1983-05-26 Mitsubishi Heavy Ind Ltd 浚渫船の含泥率検出装置
JPH10159125A (ja) 1996-11-27 1998-06-16 Honmagumi:Kk 浚渫装置
JPH11286957A (ja) 1998-04-03 1999-10-19 Ishikawajima Harima Heavy Ind Co Ltd 浚渫船のranc自動制御方法
JP2000017684A (ja) 1998-06-30 2000-01-18 Ishikawajima Harima Heavy Ind Co Ltd 浚渫船の浚渫制御方法及びその装置

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE384452B (sv) * 1974-08-29 1976-05-10 Sandbergs N A Industrikonstruk Sett att styra en rorlig suganordning for sugning av suspenderbart material fran botten av en vetskesamling och anordning for utovning av settet
SE416107B (sv) * 1977-03-31 1980-12-01 Sanbergs Industrikonstruktione Reglersett vid en anleggning med rorlig suganordning for sugning av suspenderbart material samt anordning for settets genomforande
NL174577C (nl) * 1979-03-27 1984-07-02 Ihc Holland Nv Werkwijze voor het regelen van de productie bij een baggerwerktuig.
JPS5885169A (ja) * 1981-11-17 1983-05-21 Mitsubishi Heavy Ind Ltd 浚渫船排泥管内の土砂排送分布監視装置
SE459742B (sv) * 1985-01-31 1989-07-31 Industrikonstruktioner Ab Saett foer reglering av slamkoncentrationen hos slam, som uppsuges medelst aatminstone en inom en vattensamling roerlig, foersta sugenhet efter en uppgjord plan foer slammets omhaendertagande, vilket kraever ett foerutbestaemt minsta vatteninnehaall
US5172497A (en) * 1991-10-25 1992-12-22 Lor, Inc. Slurry density control system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3512281A (en) * 1966-11-28 1970-05-19 Mineraal Technologisch Inst Swell compensator for a drag suction dredger
JPS5888636A (ja) 1981-11-24 1983-05-26 Mitsubishi Heavy Ind Ltd 浚渫船の含泥率検出装置
JPH10159125A (ja) 1996-11-27 1998-06-16 Honmagumi:Kk 浚渫装置
JPH11286957A (ja) 1998-04-03 1999-10-19 Ishikawajima Harima Heavy Ind Co Ltd 浚渫船のranc自動制御方法
JP2000017684A (ja) 1998-06-30 2000-01-18 Ishikawajima Harima Heavy Ind Co Ltd 浚渫船の浚渫制御方法及びその装置

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 007, no. 188 (P - 217) 17 August 1983 (1983-08-17) *
PATENT ABSTRACTS OF JAPAN vol. 1998, no. 11 30 September 1998 (1998-09-30) *
PATENT ABSTRACTS OF JAPAN vol. 2000, no. 01 31 January 2000 (2000-01-31) *
PATENT ABSTRACTS OF JAPAN vol. 2000, no. 04 31 August 2000 (2000-08-31) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014528524A (ja) * 2011-10-03 2014-10-27 マリーン リソーシーズ エクスプロレイション インターナショナル ビーヴイ 海底地盤から堆積物を回収する方法
WO2015086856A1 (en) * 2013-12-13 2015-06-18 Baggerwerken Decloedt En Zoon Method for dredging an underwater bottom in an area using a dredging device
US9777462B2 (en) 2013-12-13 2017-10-03 Baggerwerken Decloedt En Zoon Method for dredging an underwater bottom in an area using a dredging device
CN104712003A (zh) * 2015-03-17 2015-06-17 中国电建集团贵阳勘测设计研究院有限公司 一种小型水电站清淤设备
CN106592674A (zh) * 2016-12-16 2017-04-26 浙江海洋大学东海科学技术学院 一种采排一体挖泥船
CN106592674B (zh) * 2016-12-16 2018-10-23 浙江海洋大学东海科学技术学院 一种采排一体挖泥船
EP3717704B1 (de) 2018-02-22 2021-03-17 Michael Detering Vorrichtung für einen sedimenttransfer in gewässern als auch ein verfahren für eine transferierung von sediment in gewässern
EP3717704B2 (de) 2018-02-22 2024-01-24 Michael Detering Verwendung einer vorrichtung für einen sedimenttransfer in gewässern

Also Published As

Publication number Publication date
BE1018431A3 (nl) 2010-11-09
NL1033266C2 (nl) 2009-04-07
NL1033266A1 (nl) 2007-07-23

Similar Documents

Publication Publication Date Title
CN105547261B (zh) 一种边远岛礁水下地形地貌勘测系统与方法
EP1811127A1 (de) Verfahren für den Meeresbodenabbau
EP2201183B1 (de) Verfahren und system zur optimierung des baggerns
US8965607B2 (en) Device for dredging soil material under water
JP2011007038A (ja) 3次元ソナーによる施工管理方法とその施工管理装置
JP4678789B2 (ja) 捨石投入作業支援装置及び捨石投入シミュレーション作業支援装置
CN106795705A (zh) 用于控制工作机械的布置
CN108570990A (zh) 浅水海底缆线石块精确填埋设备及方法
JP6406967B2 (ja) 浅層地盤改良工事支援システム及び浅層地盤改良工事方法
KR20150006478A (ko) 선박 감시 장치
CN102174827A (zh) 一种疏浚集成监控系统
CN104652442B (zh) 一种深水回填作业定位系统
WO2024037120A1 (zh) 液压冲击锤精确定位系统
EP2386001A1 (de) Aushubvorrichtung zum ausheben von erdreich unter wasser und verfahren zum ausheben von erdreich
CN107620341B (zh) 一种用于绞吸式挖泥船的浚测一体化水深测量系统
CN204753675U (zh) 耙吸挖泥船耙臂姿态测量设备
CN107916678A (zh) 基于bim的沉管施工系统及方法
CN210288280U (zh) 开敞式无围堰珊瑚砂岛礁吹填系统
KR102051731B1 (ko) 심해 urf 작업을 위한 설치 구조물 모니터링 시스템 및 그 방법
CN110952562A (zh) 一种吊点入水精确定位系统及其使用方法
CN115791524B (zh) 一种用于测量采空区注浆浆液性质的测量装置及测量方法
KR20150092869A (ko) 레저선박의 안전 항로 설정기능을 갖는 네비게이션 장치
CN211503926U (zh) 一种智能盐田测矿系统
JP2019203297A (ja) 管理システム
CN201489111U (zh) 挖泥船定位系统

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA HR MK YU

17P Request for examination filed

Effective date: 20071116

17Q First examination report despatched

Effective date: 20080122

AKX Designation fees paid

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20091120