EP1776507B1 - Method for producing an infrastructure channel - Google Patents
Method for producing an infrastructure channel Download PDFInfo
- Publication number
- EP1776507B1 EP1776507B1 EP05775062A EP05775062A EP1776507B1 EP 1776507 B1 EP1776507 B1 EP 1776507B1 EP 05775062 A EP05775062 A EP 05775062A EP 05775062 A EP05775062 A EP 05775062A EP 1776507 B1 EP1776507 B1 EP 1776507B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- cast
- infrastructure channel
- parts
- place concrete
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/04—Pipes or fittings specially adapted to sewers
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
Definitions
- the invention relates to a method for producing an infrastructure channel, which consists of at least two sections of predetermined length.
- An infrastructure channel is used in particular in new housing areas or in larger refurbishment projects to summarize all supply and disposal lines in a single, preferably walk-in and sealed channel. Due to its spatial design, a direct and permanent control of the supply and disposal lines is possible. Leakage of piping and emissions to cables within a conduit of the infrastructure channel reach the bottom of the structure in liquid or semi-solid form or can escape in gaseous form in the air-filled space of the conduit. Leakage of piping can be detected by installed leak detection systems without the need for excavation. Furthermore, an exchange or a new installation of supply and disposal lines within the infrastructure channel is easy to accomplish, since access openings are made via excavation openings without excavation. In addition, an inspection of both the supply and disposal lines and the interior of the infrastructure channel by means of a commercially available sewer inspection camera system.
- the DE 201 13 897 U1 discloses an infrastructure channel consisting of individual one-piece finished segments which are assembled into one continuous channel. Each finished segment has a base plate to which connect two lateral walls, which are interconnected via a top-side curvature.
- the prefabricated segments are factory made of concrete and assembled on site using face seals. So that the finished segments can be transported without damage, at least a cost-intensive transport reinforcement is required. Furthermore, the production of a flat trench for full-surface support of the base plates of the finished segments proves to be very labor-intensive. In addition, the frontal sealing adjacent finished segments can be realized only with considerable effort. Furthermore, the factory made finished segments have the disadvantage that their length is very limited for manufacturing reasons.
- channels are known both as prefabricated constructions as well as in-situ concrete solutions, which have a reinforcement made of steel, which are disadvantageous in as cracks or efflorescence, the reinforcement is exposed and can rust, creating a total destruction of the channels, eg , B. by explosive action, goes along. Even with a fire, the concrete from the steel of the reinforcement breaks and the channel is destroyed afterwards.
- this object is achieved in that each section poured cast on site from in-situ concrete or ready-mixed concrete, spanned an inner formwork with a drainage fleece and closed the beginning and the end of the infrastructure channel during drying of the in-situ concrete by means of wood panels and / or a foil strip curtain becomes.
- Every single section of the infrastructure channel will open the site created continuously from in-situ concrete or ready-mixed concrete in one-piece design, the term in-situ concrete is used in the present description equally well for ready-mixed concrete.
- the length of each section to be created is such that the section can be created in a single daily cycle, the length between 4m and 40m, preferably between 10m and 20m, preferably 15m.
- a steel reinforcement is not required. Due to the lack of steel reinforcement and the relatively large length of each section and the relatively low preparations a quick and cost-effective production of the infrastructure channel is guaranteed.
- the drainage fleece spanning the inner formwork is provided.
- the foil strip curtain can be attached to the inner formwork, for example at the end of the infrastructure channel.
- a sealing and expansion joint band is cast between two adjacent sections.
- the sealing and expansion joint band comprises two sealing bands, which are connected to each other by means of a middle tube, each sealing band being associated with an end face of a section.
- the sealing and expansion joint band is used with sealing parts in the respective end face, the sections.
- an end formwork is used, which is provided with slots for the sealing and expansion joint band, which is securely connected after curing of the in-situ concrete with the sections, which is why leaks are almost impossible.
- a component made of a foamed polymer, in particular polystyrene is provided on the front side, which ensures the function of the sealing and expansion joint band.
- a humidifier is preferably placed in the interior of the stripping of the section.
- a film wall is expediently placed inside the infrastructure channel depending on the number of existing cuts. The film wall can be made portable and be adjusted according to the construction progress, so that the treatment with the humidifier takes place in about three sections per section.
- thermally insulated Exterior formwork used in order to allow a relatively early stripping of the section despite a relatively high proportion of fly ash in the in-situ concrete.
- the sections are covered during stripping with at least one bubble wrap.
- the bubble wrap prevents unwanted temperature stresses in the in-situ concrete, which can lead to cracking, and causes a relatively short stripping time.
- the bubble wrap sheets can be laid over the infrastructure channel by means of the cable crane in such a way that they cover three to six sections.
- the temperature of the in-situ concrete is measured.
- the temperature measurement can be at several spaced locations of the section, preferably, seen over the cross section, in its outer and inner circumference and in the middle, and serves primarily to determine the optimum time for stripping the section and for determining the curing time of the hardening in-situ concrete .
- the data of the temperature measurements are delivered to a concrete maturing computer, with which the Ausschalzeit is to be determined.
- Bubble wrap installed a sprinkler hose, especially a micro-sprinkler hose for irrigation of in-situ concrete.
- the sprinkler hose is designed so that a washing out of the solidifying in-situ concrete is prevented, which is why it preferably has micro-openings.
- a controllable heating is operated inside the inner formwork.
- the heater which may include one or more gas burners, is needed especially at a low ambient temperature and may be controlled by the data of the temperature measurement by the concrete maturity computer.
- a reinforcement with plastic fibers, in particular polypropylene fibers is formed, wherein the plastic fibers are mixed with the in-situ concrete, and the in-situ concrete has a short-term stiffening and a green strength of in particular 6 N / mm 2 on. This allows fast shuttering.
- the in-situ concrete comprises a disproportionately high proportion of fly ash.
- fly ash may be higher than that of the cement.
- Such a recipe is inadmissible according to the German standard for reinforced concrete.
- the individual parts of the infrastructure channel do not contain steel, this standard is irrelevant in the present case.
- the high percentage of fly ash offers both economic and ecological benefits.
- the heat development is lower than with standard formulations, thus reducing the risk of the formation of shrinkage cracks accompanied.
- an upper vault of a section has a lid which is dimensioned such that a pipeline, in particular a high-voltage line, can be inserted into the interior.
- the cover must be relatively large, so that the usually rigid pipe can be introduced into the interior of the infrastructure channel.
- the opening for receiving the lid, which can be lifted in particular for later measures, is made by a conical recess of the inner formwork and the opening corresponding to an outer contour having a lid is accurately made in a corresponding precast formwork
- At least one of the side walls is provided with at least one console for supporting a pipeline.
- the console can be fastened for example by means of tension anchors.
- the cross-sectionally, for example, L-shaped or Z-shaped console ensures a secure support of the pipeline and allows an end-side welding of two lines to be connected to one another.
- the console is dimensioned to support rollers for a displacement of the pipeline.
- the console consists of fiber cement.
- the infrastructure channel 1 consists of a larger number of sections 2, which are sealed with their respective adjacent end faces 3 together.
- joint 4 is provided for sealing a sealing and expansion joint strip 5, which comprises a central tube 6 with both sides adjoining sealing parts 7, 8, the front side abut the respective section 2.
- Each section 2 of the infrastructure channel 1 is on site continuously from in-situ concrete 9 in one-piece construction created. For this purpose, a largely flat and compacted floor space is created in an excavation pit. Each section 2 to be created is dimensioned in its length such that it can be manufactured in a single daily cycle.
- an inner formwork 11 is first mounted with open floor of sheets, which is provided with hinges 12, wherein the hinges 12 serve after curing of the in-situ concrete 9 for pivoting parts of the inner formwork 11 to the inside.
- the process of concreting takes place in coupled sub-steps, wherein first on the flat bottom surface a sole 10 with, wall approaches is poured. Before concreting side walls 16 and a vault 17 a break is inserted so that the in-situ concrete 9 of the sole 10 binds something.
- a drainage fleece 15 is stretched over the inner formwork 11, which absorbs the water emerging during compression of the in-situ concrete and releases it again during the subsequent hardening of the in-situ concrete 9.
- a heat-insulating outer formwork 19 is mounted for the walls 16 and the vault 17.
- the infrastructure channel 1 forms a walkable shell in the supply and disposal lines of any diameter can be laid. A dismantling or repair of the supply and disposal lines is possible at any time without excavation, as at least partially manholes are assigned to the infrastructure channel 1.
- a formulation for the in-situ concrete 9 is necessary, which stiffens early, a high green strength of about 6 N / mm 2 ensures and allows a slow further hardening with low heat of hydration.
- the in-situ concrete 9, a reinforcement 13 is mixed in the form of plastic fibers 14 to ensure a special resistance of the in-situ concrete 9, in particular prevents stress or shrinkage cracks and an early, shock, shock and abrasion resistance can be increased.
- a pipe 24 are arranged one above the other Consoles 25 provided on one of the side walls 26 of the infrastructure channel 1, wherein the brackets 25 are formed so as to securely hold the pipe 24 on the one hand and on the other both allow an end-side welding of the pipe 24 with another pipe 24 and a support for rollers for moving the pipeline 24 provide.
Abstract
Description
Die Erfindung bezieht sich auf ein Verfahren zur Herstellung eines Infrastruktur-Kanals, der aus mindestens zwei Teilstücken vorbestimmter Länge besteht.The invention relates to a method for producing an infrastructure channel, which consists of at least two sections of predetermined length.
Ein Infrastruktur-Kanal wird insbesondere in Neubaugebieten oder bei größeren Sanierungsvorhaben verwendet, um alle Ver- und Entsorgungsleitungen in einem einzigen, vorzugsweise begehbaren und abgedichteten Kanal zusammenzufassen. Durch seine räumliche Gestaltung ist eine direkte und permanente Kontrolle der Ver- und Entsorgungsleitungen möglich. Leckagen an Rohrleitungen und Emissionen an Kabeln innerhalb eines Leitungsgangs des Infrastruktur-Kanals erreichen die Sohle des Bauwerks in flüssiger oder halbfester Form bzw. können gasförmig im luftgefüllten Raum des Leitungsganges entweichen. Undichtigkeiten von Rohrleitungen können durch installierte Leckwarnsysteme angezeigt werden, ohne dass Aufgrabungen notwendig sind. Im Weiteren ist ein Auswechseln oder eine Neuinstallation von Ver- und Entsorgungsleitungen innerhalb des Infrastruktur-Kanals einfach zu bewerkstelligen, da über Montageöffnungen der Zugang ohne Aufgrabungen erfolgt. Darüber hinaus kann eine Inspektion sowohl der Ver- und Entsorgungsleitungen als auch des Inneren des Infrastruktur-Kanals mittels eines handelsüblichen-Kanalinspektions-Kamerasystems erfolgen.An infrastructure channel is used in particular in new housing areas or in larger refurbishment projects to summarize all supply and disposal lines in a single, preferably walk-in and sealed channel. Due to its spatial design, a direct and permanent control of the supply and disposal lines is possible. Leakage of piping and emissions to cables within a conduit of the infrastructure channel reach the bottom of the structure in liquid or semi-solid form or can escape in gaseous form in the air-filled space of the conduit. Leakage of piping can be detected by installed leak detection systems without the need for excavation. Furthermore, an exchange or a new installation of supply and disposal lines within the infrastructure channel is easy to accomplish, since access openings are made via excavation openings without excavation. In addition, an inspection of both the supply and disposal lines and the interior of the infrastructure channel by means of a commercially available sewer inspection camera system.
Durch die Trennung der statischen Teile des Infrastruktur-Kanals von den Ver- und Entsorgungsleitungen im Leitungsgang ist ein relativ hohes Sicherheitsniveau gegenüber dem Auftreten von Leckagen und Undichtigkeiten aufgrund von Setzungen des Infrastruktur-Kanals gegeben, wobei eine Erschließungslösung mit einem Infrastruktur-Kanal die Schutzfunktion eines doppelwandigen Rohres übertrifft. Auch können Wurzeln über undichte Teilstückverbindungen und rissförmige Schäden nicht in die Ver- und Entsorgungsleitungen eindringen.By separating the static parts of the infrastructure channel from the supply and disposal lines in the line a relatively high level of security against the occurrence of leaks and leaks due to subsidence of the infrastructure channel is given, with a development solution with an infrastructure channel the protective function of a double-walled pipe surpasses. Also, roots can not penetrate into the supply and disposal lines via leaky part connections and crack-shaped damage.
Die
Ferner sind aus der Praxis Kanäle sowohl als Fertigteil-Konstruktionen als auch als Ortbetonlösungen bekannt, die eine Armierung aus Stahl aufweisen, die insofern nachteilig sind, als bei Rissen oder Ausblühungen die Armierung freigelegt wird und rosten kann, womit eine völlige Zerstörung der Kanäle, z. B. durch Sprengwirkung, einhergeht. Auch bei einem Brand platzt der Beton von dem Stahl der Armierung ab und der Kanal ist danach zerstört.Furthermore, in practice channels are known both as prefabricated constructions as well as in-situ concrete solutions, which have a reinforcement made of steel, which are disadvantageous in as cracks or efflorescence, the reinforcement is exposed and can rust, creating a total destruction of the channels, eg , B. by explosive action, goes along. Even with a fire, the concrete from the steel of the reinforcement breaks and the channel is destroyed afterwards.
Die Herstellung von Kanälen aus mindestens zwei Teilstücken vorbestimmter Länge, wobei jedes Teilstück auf der Baustelle aus Ortbeton oder Transportbeton einstückig gegossen wird, ist aus:
-
DE 38 38 239 A1 -
DE 37 00159 A1 -
GB 1 353 037 A -
WO 00 39 414 A
-
DE 38 38 239 A1 -
DE 37 00159 A1 -
GB 1 353 037 A -
WO 00 39 414 A
Darüber hinaus offenbart die
Schließlich zeigt die
Es ist Aufgabe der Erfindung, ein Verfahren der eingangs genannten Art zu schaffen, das eine schnelle und kostengünstige Herstellung eines Infrastruktur-Kanals sicherstellt.It is an object of the invention to provide a method of the type mentioned, which ensures a fast and cost-effective production of an infrastructure channel.
Erfindungsgemäß wird die Aufgabe dadurch gelöst, dass jedes Teilstück auf der Baustelle aus Ortbeton oder Transportbeton einstückig gegossen gegossen, eine Innenschalung mit einem Drainagevlies überspannt und der Anfang sowie das Ende des Infrastruktur-Kanals während der Trocknung des Ortbetons mittels Holzplatten und/oder eines Folienstreifenvorhangs verschlossen wird.According to the invention, this object is achieved in that each section poured cast on site from in-situ concrete or ready-mixed concrete, spanned an inner formwork with a drainage fleece and closed the beginning and the end of the infrastructure channel during drying of the in-situ concrete by means of wood panels and / or a foil strip curtain becomes.
Jedes einzelne Teilstück des Infrastruktur-Kanals wird auf der Baustelle durchgehend aus Ortbeton bzw. Transportbeton in einstückiger Bauweise erstellt, wobei der Begriff Ortbeton in der vorliegenden Beschreibung gleichermaßen auch für Transportbeton verwendet wird. Die Länge des jeweils zu erstellenden Teilstücks ist derart bemessen, dass das Teilstück in einem einzigen Tagestakt geschaffen werden kann, wobei die Länge zwischen 4m und 40m, vorzugsweise zwischen 10m und 20m, bevorzugt 15m beträgt. Eine Stahlarmierung ist nicht erforderlich. Aufgrund der fehlenden Stahlarmierung sowie der verhältnismäßig großen Länge jedes Teilstücks und der relativ geringen Vorbereitungen ist eine schnelle und kostengünstige Herstellung des Infrastruktur-Kanals gewährleistet. Um das beim Verdichten des Ortbetons austretende Wasser aufzusaugen und beim anschließenden Aushärten des Ortbetons wieder an diesen abzugeben, ist das die Innenschalung überspannende Drainagevlies vorgesehen. Die aus Stahl gefertigte Innenschalung, eine in eine Betonierstellung und eine Fahrstellung klappbare Schalung aus Stahl, wird mit einem Kunststoffgitter, das mittels Kunststoffnieten an der Innenschalung festgelegt ist, überspannt und auf dem Kunststoffgitter wird das mehrfach zu verwendende Drainagevlies angebracht, das die Innenschalung in der Betonierstellung straff überspannt. Darüber hinaus ist es sinnvoll, den Anfang des Infrastrukturkanals mit eine Tür aufweisenden Holzplatten und das Ende jeder Schalung des zu fertigenden Teilstücks mit einem Folienstreifenvorhang zu verschließen, um einen unerwünschten Luftzug innerhalb des Infrastruktur-Kanals zu vermeiden. Der Folienstreifenvorhang kann an der Innenschalung, beispielsweise am Ende des Infrastrukturkanals befestigt werden. Im Weiteren können die Holzplatten zur Festlegung eines Handhabungsgerätes, insbesondere eines Seilkrans, zur Verlagerung von Teilen, insbesondere Isolierfolien, auf der Baustelle dienen.Every single section of the infrastructure channel will open the site created continuously from in-situ concrete or ready-mixed concrete in one-piece design, the term in-situ concrete is used in the present description equally well for ready-mixed concrete. The length of each section to be created is such that the section can be created in a single daily cycle, the length between 4m and 40m, preferably between 10m and 20m, preferably 15m. A steel reinforcement is not required. Due to the lack of steel reinforcement and the relatively large length of each section and the relatively low preparations a quick and cost-effective production of the infrastructure channel is guaranteed. In order to absorb the water emerging during the compaction of the in-situ concrete and to return it to the in situ curing of the in-situ concrete, the drainage fleece spanning the inner formwork is provided. The steel formwork inside formwork, one in a concreting position and a driving position hinged formwork made of steel, is covered with a plastic grid, which is fixed by plastic rivets on the inner formwork, and on the plastic grid, the multiple use drainage fleece is applied, which is the inner formwork in the Concrete construction tightly spanned. In addition, it is useful to seal the beginning of the infrastructure channel with wood panels with a door and the end of each formwork of the piece to be manufactured with a foil strip curtain to avoid unwanted draft within the infrastructure channel. The foil strip curtain can be attached to the inner formwork, for example at the end of the infrastructure channel. Furthermore, the wood panels for fixing a handling device, in particular a cable crane, for the displacement of parts, in particular insulating foils, to serve on the construction site.
Vorzugsweise wird zwischen zwei benachbarten Teilstücken ein Dichtungs- und Dehnungsfugen-Band eingegossen. Das Dichtungs- und Dehnungsfugen-Band umfasst zwei Dichtungsbänder, die mittels eines Mittelschlauches miteinander verbunden sind, wobei jedes Dichtungsband einer Stirnseite eines Teilstückes zugeordnet ist. Zweckmäßigerweise wird das Dichtungs- und Dehnungsfugen-Band mit Dichtteilen in die jeweilige Stirnfläche, der Teilstücke eingesetzt. Hierzu wird eine Stirnschalung eingesetzt, die mit Schlitzen für das Dichtungs- und Dehnungsfugen-Band versehen ist, das nach dem Aushärten des Ortbetons sicher mit den Teilstücke verbunden ist, weshalb Undichtigkeiten nahezu ausgeschlossen sind. Im Weiteren ist stirnseitig ein Bauteil aus einem geschäumten Polymer, insbesondere Polystyrol, vorgesehen, das die Funktion des Dichtungs- und Dehnungsfugen-Bandes gewährleistet.Preferably, a sealing and expansion joint band is cast between two adjacent sections. The sealing and expansion joint band comprises two sealing bands, which are connected to each other by means of a middle tube, each sealing band being associated with an end face of a section. Appropriately, the sealing and expansion joint band is used with sealing parts in the respective end face, the sections. For this purpose, an end formwork is used, which is provided with slots for the sealing and expansion joint band, which is securely connected after curing of the in-situ concrete with the sections, which is why leaks are almost impossible. Furthermore, a component made of a foamed polymer, in particular polystyrene, is provided on the front side, which ensures the function of the sealing and expansion joint band.
Für eine Nachbehandlung des Ortbetons wird bevorzugt nach dem Ausschalen des Teilstückes ein Luftbefeuchter in dessen Innerem aufgestellt. Um die Wirkung des Luftbefeuchters zu gewährleisten, wird zweckmäßigerweise im Inneren des Infrastrukturkanals in Abhängigkeit von der Anzahl der vorhandenen Teilstücke eine Folienwand aufgestellt. Die Folienwand kann tragbar ausgebildet sein und entsprechend dem Baufortschritt verstellt werden, damit die Nachbehandlung mit dem Luftbefeuchter in etwa drei Abschnitten pro Teilstück erfolgt.For a post-treatment of in-situ concrete, a humidifier is preferably placed in the interior of the stripping of the section. In order to ensure the effect of the humidifier, a film wall is expediently placed inside the infrastructure channel depending on the number of existing cuts. The film wall can be made portable and be adjusted according to the construction progress, so that the treatment with the humidifier takes place in about three sections per section.
Um ein verhältnismäßig frühes Ausschalen des Teilstückes trotz eines verhältnismäßig hohen Flugascheanteils in dem Ortbeton zu ermöglichen, wird vorzugsweise eine wärmeisolierte Außenschalung verwendet.In order to allow a relatively early stripping of the section despite a relatively high proportion of fly ash in the in-situ concrete, preferably a thermally insulated Exterior formwork used.
Nach einer Weiterbildung werden die Teilstücke beim Ausschalen mit mindestens einer Luftpolsterfolie abgedeckt. Die Luftpolsterfolie verhindert unerwünschte Temperaturspannungen im Ortbeton, die zu einer Rissbildung führen können, und bewirkt eine verhältnismäßig kurze Ausschalzeit. Die Luftpolsterfolien können beispielsweise mittels des Seilkrans derart über den Infrastruktur-Kanal gelegt werden, dass sie drei bis sechs Teilstücke überdecken. Der Seilkran, der beispielsweise mit seinem einen Ende an den Holzplatten zum Verschließen des Eingangs des Infrastruktur-Kanals und mit seinem anderen Ende an der Schalung befestigt ist, wird, ebenso wie die Luftpolsterfolie, beim Ausschalen mitgezogen, wodurch eine dem Ausschalungsfortschritt folgende Abdeckung gewährleistet ist. Bei einer aus der Praxis bekannten Abdeckung mit so genannten Winterbauschutzmatten, die lediglich in verhältnismäßig kleinen Abmessungen im Handel sind, besteht die Gefahr eines zu großen Temperaturgefälles zwischen dem Kern des Ortbetons sowie der Umgebungstemperatur und darüber hinaus ist mit den Winterbauschutzmatten keine sofortige und unterbrechungsfreie Isolierung möglich.According to a development, the sections are covered during stripping with at least one bubble wrap. The bubble wrap prevents unwanted temperature stresses in the in-situ concrete, which can lead to cracking, and causes a relatively short stripping time. By way of example, the bubble wrap sheets can be laid over the infrastructure channel by means of the cable crane in such a way that they cover three to six sections. The cable crane, which is fastened, for example with its one end to the wood panels for closing the entrance of the infrastructure channel and with its other end to the formwork, as well as the bubble wrap, pulled during stripping, whereby a Ausschaltungsfortschritt the following cover is guaranteed , In a well-known from practice coverage with so-called winter construction mats, which are only in relatively small dimensions in the trade, there is the danger of too great a temperature gradient between the core of the in-situ concrete and the ambient temperature and beyond is not possible with the Winterbauschutzmatten immediate and uninterrupted insulation ,
Zur Bestimmung der Betonreife, die von der Temperatur und der Zeit abhängig ist, wird vorzugsweise die Temperatur des Ortbetons gemessen. Die Temperaturmessung kann an mehreren zueinander beabstandeten Stellen des Teilstücks, vorzugsweise, über den Querschnitt gesehen, in dessen äußerem und inneren Umfang sowie in der Mitte, erfolgen und dient vorrangig der Ermittlung des optimalen Zeitpunktes zum Ausschalen des Teilstückes sowie zur Festlegung der Nachbehandlungsdauer des aushärtenden Ortbetons. Die Daten der Temperaturmessungen werden an einen Betonreife-Computer geliefert, mit dem die Ausschalzeit zu ermitteln ist.To determine the concrete maturity, which is dependent on the temperature and the time, preferably the temperature of the in-situ concrete is measured. The temperature measurement can be at several spaced locations of the section, preferably, seen over the cross section, in its outer and inner circumference and in the middle, and serves primarily to determine the optimum time for stripping the section and for determining the curing time of the hardening in-situ concrete , The data of the temperature measurements are delivered to a concrete maturing computer, with which the Ausschalzeit is to be determined.
Um die für die Nachbehandlung des Ortbetons erforderliche Wassermenge bereitzustellen, wird zweckmäßigerweise unter der Luftpolsterfolie ein Berieselungsschlauch, insbesondere ein Micro-Berieselungsschlauch, zur Bewässerung des Ortbetons installiert. Der Berieselungsschlauch ist derart ausgelegt, dass ein Auswaschen des erstarrenden Ortbetons verhindert ist, weshalb er vorzugsweise Micro-Öffnungen aufweist.In order to provide the amount of water required for the aftertreatment of the in-situ concrete is expediently under Bubble wrap installed a sprinkler hose, especially a micro-sprinkler hose for irrigation of in-situ concrete. The sprinkler hose is designed so that a washing out of the solidifying in-situ concrete is prevented, which is why it preferably has micro-openings.
In weiterer Ausgestaltung wird im Inneren der Innenschalung eine steuerbare Heizung betrieben. Die Heizung, die einen oder mehrere Gasbrenner umfassen kann, wird insbesondere bei einer niedrigen Umgebungstemperatur benötigt und kann mittels der Daten der Temperaturmessung durch den Betonreife-Computer geregelt werden.In a further embodiment, a controllable heating is operated inside the inner formwork. The heater, which may include one or more gas burners, is needed especially at a low ambient temperature and may be controlled by the data of the temperature measurement by the concrete maturity computer.
Bei einem Ortbeton zur Herstellung des Infrastruktur-Kanals ist eine Armierung mit Kunststoff-Fasern, insbesondere Polypropylen-Fasern, gebildet, wobei die Kunststoff-Fasern dem Ortbeton zugemischt werden, und der Ortbeton weist eine kurzzeitige Ansteifung sowie eine Grünstandsfestigkeit von insbesondere 6 N/mm2 auf. Damit ist eine schnelle Ausschalung möglich.In an in-situ concrete for the production of the infrastructure channel a reinforcement with plastic fibers, in particular polypropylene fibers is formed, wherein the plastic fibers are mixed with the in-situ concrete, and the in-situ concrete has a short-term stiffening and a green strength of in particular 6 N / mm 2 on. This allows fast shuttering.
Im Weiteren umfasst der Ortbeton einen überproportional hohen Anteil Flugasche. In Abhängigkeit von der Außentemperatur kann der Anteil Flugasche höher als der des Zements bemessen sein. Eine solche Rezeptur ist nach deutscher Norm für Stahlbeton unzulässig. Da die einzelnen Teilstücke des Infrastruktur-Kanals jedoch keinen Stahl aufweisen, ist diese Norm vorliegend bedeutungslos. Der hohe Anteil Flugasche bietet sowohl wirtschaftliche als auch ökologische Vorteile. Insbesondere ist jedoch die Wärmeentwicklung geringer als bei Standardrezepturen, womit eine Verringerung der Gefahr der Entstehung von Schwindrissen einhergeht.Furthermore, the in-situ concrete comprises a disproportionately high proportion of fly ash. Depending on the outside temperature, the proportion of fly ash may be higher than that of the cement. Such a recipe is inadmissible according to the German standard for reinforced concrete. However, since the individual parts of the infrastructure channel do not contain steel, this standard is irrelevant in the present case. The high percentage of fly ash offers both economic and ecological benefits. In particular, however, the heat development is lower than with standard formulations, thus reducing the risk of the formation of shrinkage cracks accompanied.
Bei einem Infrastrukturkanal weist ein oberes Gewölbe eines Teilstückes einen Deckel auf, der derart bemessen ist, dass eine Rohrleitung, insbesondere Hochspannungsleitung, in das Innere einführbar ist. Der Deckel muss verhältnismäßig groß dimensioniert sein, damit die in der Regel starre Rohrleitung in das Innere des Infrastruktur-Kanals eingebracht werden kann. Die Öffnung zur Aufnahme des Deckels, der insbesondere auch für spätere Maßnahmen abgehoben werden kann, wird durch eine konische Aussparung der Innenschalung und der eine zur Öffnung korrespondierende Außenkontur aufweisende Deckel wird passgenau in einer entsprechenden Fertigteilschalung hergestelltIn an infrastructure channel, an upper vault of a section has a lid which is dimensioned such that a pipeline, in particular a high-voltage line, can be inserted into the interior. The cover must be relatively large, so that the usually rigid pipe can be introduced into the interior of the infrastructure channel. The opening for receiving the lid, which can be lifted in particular for later measures, is made by a conical recess of the inner formwork and the opening corresponding to an outer contour having a lid is accurately made in a corresponding precast formwork
Bevorzugt ist zumindest eine der Seitenwandungen mit mindestens einer Konsole zur Auflage einer Rohrleitung versehen. Die Konsole kann beispielsweise mittels Spannanker befestigt sein. Die im Querschnitt beispielsweise L- oder Z-förmige Konsole gewährleistet eine sichere Auflage der Rohrleitung und ermöglicht ein stirnseitiges Verschweißen von zwei miteinander zu verbindenden Leitungen. Darüber hinaus ist die Konsole zur Auflage von Rollen für eine Verschiebung der Rohrleitung dimensioniert. Zweckmäßigerweise besteht die Konsole aus Faserzement.Preferably, at least one of the side walls is provided with at least one console for supporting a pipeline. The console can be fastened for example by means of tension anchors. The cross-sectionally, for example, L-shaped or Z-shaped console ensures a secure support of the pipeline and allows an end-side welding of two lines to be connected to one another. In addition, the console is dimensioned to support rollers for a displacement of the pipeline. Conveniently, the console consists of fiber cement.
Es versteht sich, dass die vorstehend genannten und nachstehend noch zu erläuternden Merkmale nicht nur in der jeweils angegebenen Kombination, sondern auch in anderen Kombinationen verwendbar sind. Der Rahmen der Erfindung ist nur durch die Ansprüche definiert.It goes without saying that the features mentioned above and those yet to be explained below can be used not only in the respectively specified combination but also in other combinations. The scope of the invention is defined only by the claims.
Die Erfindung wird im Folgenden anhand eines Ausführungsbeispieles unter Bezugnahme auf die zugehörigen Zeichnungen näher erläutert. Es zeigt:
- Fig.1
- einen Längsschnitt durch einen nach dem erfindungsge- mäßen Verfahren hergestellten Infrastruktur-Kanal mit einem vollständigen und zwei angedeuteten Teilstü- cken,
- Fig.2
- einen Querschnitt durch ein Teilstück des Infrastruk- tur-Kanals nach
Fig. 1 , - Fig.3
- eine perspektivische Darstellung des Infrastruktur- Kanals nach
Fig. 1 , - Fig.4
- eine Vorderansicht des Infrastruktur-Kanals nach
Fig. 3 und - Fig.5
- eine vergrößerte Darstellung von Konsolen für den Infrastruktur-Kanal.
- Fig.1
- 3 a longitudinal section through an infrastructure channel produced according to the method according to the invention with a complete and two indicated parts,
- Fig.2
- a cross section through a section of the infrastructure channel after
Fig. 1 . - Figure 3
- a perspective view of the infrastructure channel after
Fig. 1 . - Figure 4
- a front view of the infrastructure channel
Fig. 3 and - Figure 5
- an enlarged view of consoles for the infrastructure channel.
Der Infrastruktur-Kanal 1 besteht aus einer größeren Anzahl von Teilstücken 2, die mit ihren jeweils benachbarten Stirnflächen 3 abgedichtet aneinander liegen. In der zwischen zwei Stirnflächen 3 vorhandenen Fuge 4 ist zur Abdichtung ein Dichtungs- und Dehnungsfugenband 5 vorgesehen, das einen Mittelschlauch 6 mit beidseitig daran anschließenden Dichtteilen 7, 8 umfasst, die stirnseitig an dem jeweiligen Teilstück 2 anliegen.The infrastructure channel 1 consists of a larger number of
Jedes Teilstück 2 des Infrastruktur-Kanals 1 wird auf der Baustelle durchgehend aus Ortbeton 9 in einstückiger Bauweise erstellt. Dazu wird in einer Baugrube eine weitestgehend ebene und verdichtete Bodenfläche geschaffen. Das jeweils zu erstellende Teilstück 2 ist in seiner Länge derart bemessen, dass es in einem einzigen Tagestakt gefertigt werden kann.Each
Zur Erstellung des Teilstückes 2 wird zunächst eine Innenschalung 11 mit offenem Boden aus Blechen montiert, die mit Scharnieren 12 versehen ist, wobei die Scharniere 12 nach dem Aushärten des Ortbetons 9 zum Verschwenken von Teilen der Innenschalung 11 nach innen dienen. Der Vorgang des Betonierens erfolgt in gekoppelten Teilschritten, wobei zuerst auf der ebenen Bodenfläche eine Sohle 10 mit,Wandansätzen gegossen wird. Vor dem Betonieren von Seitenwänden 16 und einem Gewölbe 17 wird eine Pause eingelegt, damit der Ortbeton 9 der Sohle 10 etwas bindet.To create the
Über die innere Schalung 11 wird ein Dränagevlies 15 gespannt, das das beim Verdichten des Ortbetons austretende Wasser aufsaugt und beim anschließenden Aushärten des Ortbetons 9 wieder an diesen abgibt. Nach dem Verlegen des Drainagevlieses 15 wird für die Wände 16 und das Gewölbe 17 eine wärmeisolierende Außenschalung 19 montiert.A
Stirnseitig wird jeweils eine Stirnschalung mit Schlitzen für das Dichtungs- und Dehnungsfugen-Band 5 eingesetzt. Nach der Fertigstellung des Teilstückes 2 und dem Abbinden des Ortbetons 9 wird die Innenschalung 11 zusammengeklappt und danach in Richtung des Pfeils 18 aus dem fertigen Teilstück 2 herausgezogen. Das Teilstück 2 wird nun eingangsseitig mit eine Tür aufweisenden Holzplatten 20 verschlossen.On the front side, an end formwork with slots for the sealing and expansion joint band 5 is used in each case. After completion of the
Mit dem Abbau der Außenschalung 19 werden kontinuierlich zum Ausschalungsfortschritt Luftpolsterfolien mittels eines Seilkrans 21 über das Teilstück 2 gezogen, wobei ein Gestell 22 am Anfang des Infrastrüktur-Kanals 1 und ein weiteres Gestell 23 an dessen Ende befestigt ist und entsprechend dem Baufortschritt versetzt wird.With the degradation of the
Auf die gleiche Weise wird dann das nächste Teilstück 2 des Infrastruktur-Kanals 1 gefertigt und zwar solange bis der Infrastruktur-Kanal 1 über seine gesamte Länge fertig gestellt ist. Der Infrastruktur-Kanal 1 bildet eine begehbare Hülle, in der Ver- und Entsorgungsleitungen beliebiger Durchmesser verlegt werden können. Auch ein Rückbau oder eine Reparatur der Ver- und Entsorgungsleitungen ist jederzeit ohne Aufgrabungen möglich, da zumindest abschnittsweise Mannlöcher dem Infrastruktur-Kanal 1 zugeordnet sind.In the same way then the
Um zum einen das Teilstück 2 des Infrastruktur-Kanals 1 einstückig und zum anderen ohne Qualitätsverlust, insbesondere im Hinblick auf eine Rissbildung, zu erstellen, ist eine Rezeptur für den Ortbeton 9 notwendig, die früh ansteift, eine hohe Grünstandsfestigkeit von etwa 6 N/mm2 gewährleistet und ein langsames Weitererhärten mit niedriger Hydratationswärme ermöglicht. Dem Ortbeton 9 wird eine Armierung 13 in Form von Kunststoff-Fasern 14 zugemischt, um eine besondere Widerstandsfähigkeit des Ortbetons 9 sicherzustellen, wobei insbesondere Spannungs- bzw. Schwindrisse verhindert und eine Früh-, Schlag-, Schock- und Abriebfestigkeit erhöht werden.In order to create the
Zur Auflagerung einer Rohrleitung 24 sind übereinander angeordnete Konsolen 25 an einer der Seitenwandungen 26 des Infrastruktur-Kanals 1 vorgesehen, wobei die Konsolen 25 derart ausgebildet sind dass sie zum einen die Rohrleitung 24 sicher haltern und zum anderen sowohl ein stirnseitiges Verschweißen der Rohrleitung 24 mit einer weiteren Rohrleitung 24 ermöglichen als auch eine Auflage für Rollen zum Verschieben der Rohrleitung 24 zur Verfügung stellen.For Auflagerung a
Claims (11)
- A method for producing an infrastructure channel (1), comprising at least two parts (2) of predetermined length, each part (2) being cast in one piece on the construction site from cast-in-place concrete (9) or ready-mix concrete, characterized in that an inner formwork (11) is spanned using a drainage nonwoven material (15), and the beginning and the end of the infrastructure channel (1) are closed during the drying of the cast-in-place concrete (9) using wood plates and/or a filmstrip curtain.
- The method according to Claim 1, characterized in that a seal and expansion joint strip (5) is embedded between two adjacent parts (2).
- The method according to Claim 2, characterized in that the seal and expansion joint strip (5) is inserted using seal parts (7, 8) in the respective front face (3) of the parts (2).
- The method according to one of Claims 1 to 3, characterized in that after the stripping of the part (2), an air humidifier is set up in its interior.
- The method according to one of Claims 1 to 4, characterized in that a film wall is set up in the interior of the infrastructure channel (1) as a function of the number of the provided parts (2).
- The method according to one of Claims 1 to 5, characterized in that a thermally-insulated outer formwork (19) is used.
- The method according to one of Claims 1 to 6, characterized in that the parts (2) are covered using at least one air cushion film during the stripping.
- The method according to Claim 7, characterized in that a sprinkler tube, in particular a microsprinkler tube, is installed under the air cushion film to water the cast-in-place concrete (9).
- The method according to one of Claims 1 to 8, characterized in that the temperature of the cast-in-place concrete (9) is measured.
- The method according to one of Claims 1 to 9, characterized in that a controllable heater is operated in the interior of the inner formwork (11).
- The method according to one of Claims 1 to 10, characterized in that, if cast-in-place concrete (9) is used, a reinforcement (13) is formed using plastic fibers (14), in particular polypropylene fibers, and the cast-in-place concrete (9) has a disproportionately high component of fly ash and/or a short-term stiffening and a green stability of 6 N/mm2 in particular.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE202004011702U DE202004011702U1 (en) | 2004-07-26 | 2004-07-26 | Infrastructure Channel |
PCT/DE2005/001318 WO2006012855A1 (en) | 2004-07-26 | 2005-07-25 | Method for producing an infrastructure channel |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1776507A1 EP1776507A1 (en) | 2007-04-25 |
EP1776507B1 true EP1776507B1 (en) | 2010-10-13 |
Family
ID=33395387
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP05775062A Not-in-force EP1776507B1 (en) | 2004-07-26 | 2005-07-25 | Method for producing an infrastructure channel |
Country Status (11)
Country | Link |
---|---|
EP (1) | EP1776507B1 (en) |
KR (1) | KR101295224B1 (en) |
AT (1) | ATE484631T1 (en) |
CA (1) | CA2574892C (en) |
DE (2) | DE202004011702U1 (en) |
DK (1) | DK1776507T3 (en) |
EG (1) | EG24424A (en) |
ES (1) | ES2350986T3 (en) |
NO (1) | NO338129B1 (en) |
WO (1) | WO2006012855A1 (en) |
ZA (1) | ZA200700468B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102004026013B4 (en) * | 2004-05-27 | 2007-05-03 | Theodor Cordes Gmbh & Co Kg | Drainable pipeline with root protection, and method for laying a pipeline |
DE102007061802B3 (en) * | 2007-12-19 | 2009-03-05 | Frank Dupre | Channel system for receiving power cables |
US9844524B2 (en) * | 2015-06-29 | 2017-12-19 | Vanguard Soap LLC | Soap compositions and methods |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5035931B1 (en) | 1970-03-30 | 1975-11-20 | ||
DE2944385A1 (en) * | 1979-11-02 | 1981-05-14 | Josef Riepl Bau-Aktiengesellschaft, 8000 München | METHOD FOR PRODUCING SLOT WALLS |
DE3524687A1 (en) | 1985-07-11 | 1986-02-27 | Josef Riepl Bau-Aktiengesellschaft, 8000 München | Method and apparatus for producing cast-in-situ concrete conduits with inserted inner lining in a monolithic type of construction |
BG44644A1 (en) | 1986-01-10 | 1989-01-16 | Pet R Kh Shivarov | |
DE3838239A1 (en) | 1988-09-07 | 1990-03-15 | Niederberg Chemie | Collector pipe and sewer pipe in which it is possible to walk |
JPH08165700A (en) * | 1994-12-12 | 1996-06-25 | Seibu Polymer Corp | Joint for closed conduit |
HU223387B1 (en) | 1998-12-28 | 2004-06-28 | Béla Boldoghy | Light-structural building with internal drag tross and buried form profile, besides form profile and framework, and process for making of building, from profile and framework |
GB2360472A (en) | 2000-03-24 | 2001-09-26 | Joseph Ash Storage Tanks Ltd | Method of coating storage tanks with concrete |
-
2004
- 2004-07-26 DE DE202004011702U patent/DE202004011702U1/en not_active Expired - Lifetime
-
2005
- 2005-07-25 AT AT05775062T patent/ATE484631T1/en active
- 2005-07-25 WO PCT/DE2005/001318 patent/WO2006012855A1/en active Application Filing
- 2005-07-25 ES ES05775062T patent/ES2350986T3/en active Active
- 2005-07-25 CA CA2574892A patent/CA2574892C/en not_active Expired - Fee Related
- 2005-07-25 KR KR1020077004526A patent/KR101295224B1/en not_active IP Right Cessation
- 2005-07-25 DE DE502005010392T patent/DE502005010392D1/en active Active
- 2005-07-25 EP EP05775062A patent/EP1776507B1/en not_active Not-in-force
- 2005-07-25 DK DK05775062.2T patent/DK1776507T3/en active
-
2007
- 2007-01-16 ZA ZA200700468A patent/ZA200700468B/en unknown
- 2007-01-23 EG EGNA2007000068 patent/EG24424A/en active
- 2007-02-26 NO NO20071081A patent/NO338129B1/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
NO338129B1 (en) | 2016-08-01 |
CA2574892C (en) | 2012-09-18 |
CA2574892A1 (en) | 2006-02-09 |
NO20071081L (en) | 2007-04-26 |
ES2350986T3 (en) | 2011-01-28 |
KR101295224B1 (en) | 2013-08-12 |
DE502005010392D1 (en) | 2010-11-25 |
ATE484631T1 (en) | 2010-10-15 |
KR20070083512A (en) | 2007-08-24 |
EG24424A (en) | 2009-06-10 |
ZA200700468B (en) | 2008-04-30 |
DE202004011702U1 (en) | 2004-10-21 |
WO2006012855A1 (en) | 2006-02-09 |
DK1776507T3 (en) | 2011-01-24 |
EP1776507A1 (en) | 2007-04-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3521557B1 (en) | Multi-function frame for tubular structures | |
EP1776507B1 (en) | Method for producing an infrastructure channel | |
DE102006036540A1 (en) | Arrangement for the foundation of a building with prefabricated building elements | |
DE3809963A1 (en) | Collecting chamber for fluids which are stored in storage tanks and constitute a hazard for water, and process for producing a collecting chamber | |
DE19807036C1 (en) | Sealing method for tunnel machined-lined with tube segments | |
DE10108316A1 (en) | Building service shafts break sealing uses low volumetric weight ceramic-based grout plus lost shuttering plate and foam sealing collars round pipes etc. | |
EP0148173B1 (en) | Isolation or post isolation method, particularly for building walls and insertion element for implementing such method | |
EP0059702A1 (en) | Foundation, especially for single-storey buildings without cellar | |
DE102012205034A1 (en) | System of formwork components, building erected therewith, as well as methods of constructing a building | |
AT409621B (en) | METHOD FOR PRODUCING A SLEEPER LINING AND TUB WITH A LIQUID-TIGHT LINING | |
DE2422586A1 (en) | Underground or sunken wall prefabricated concrete component - comprises integral panel and ribs at equal intervals | |
EP0063616B1 (en) | Tubing made of cast-in-situ concrete, and method for its production | |
DE102022000421A1 (en) | Easy-to-handle ironing device for aligning a string-shaped seal | |
EP1632613B1 (en) | Cellar for buildings | |
EP3176330B1 (en) | Cover of a substrate | |
EP1264943B1 (en) | Wall, ceiling and sound proofing element | |
DE4011736A1 (en) | Shaft construction system | |
DE8005152U1 (en) | PRE-FITTED RING COMPOSITE DUCT SHAFT, IN WHICH THE EXAMPLE OF CONCRETE, STEEL CONCRETE OR ALSO PLASTIC COMPLETE PART RINGS WITH THE INTERMEDIATION OF GASKET INSERTS ARE LAYING ONTO OTHER | |
EP1482098A1 (en) | Water-impermeable cellar and method of its construction | |
WO1999042674A1 (en) | Set of construction members for realising a construction body and method for producing and using the same | |
EP1457609B1 (en) | Floor for a building | |
DE2155456A1 (en) | KIT OF PRECAST CONCRETE ELEMENTS FOR CONSTRUCTION OF A BASEMENT FOR A BUILDING | |
DE102021124483A1 (en) | Method for producing a concrete ceiling, ceiling system from concrete ceiling and existing ceiling, concrete ceiling, building | |
DE20311076U1 (en) | Method for building waterproof cellar using prefabricated double skin floor plate and wall plates with concrete filling for monobloc construction | |
EP1081291A2 (en) | Method for protecting basements against groundwater or infiltration water |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20070117 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR |
|
DAX | Request for extension of the european patent (deleted) | ||
17Q | First examination report despatched |
Effective date: 20091126 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP Ref country code: CH Ref legal event code: NV Representative=s name: SCHMAUDER & PARTNER AG PATENT- UND MARKENANWAELTE |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
REG | Reference to a national code |
Ref country code: SE Ref legal event code: TRGR |
|
REF | Corresponds to: |
Ref document number: 502005010392 Country of ref document: DE Date of ref document: 20101125 Kind code of ref document: P |
|
REG | Reference to a national code |
Ref country code: DK Ref legal event code: T3 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Effective date: 20110118 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: T3 |
|
LTIE | Lt: invalidation of european patent or patent extension |
Effective date: 20101013 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20110113 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20110213 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20110214 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20110114 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 |
|
26N | No opposition filed |
Effective date: 20110714 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502005010392 Country of ref document: DE Effective date: 20110714 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20110731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20110725 Ref country code: CY Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION Effective date: 20101013 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20101013 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 12 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IE Payment date: 20160725 Year of fee payment: 12 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: TR Payment date: 20160725 Year of fee payment: 12 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 13 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20170721 Year of fee payment: 13 Ref country code: CZ Payment date: 20170724 Year of fee payment: 13 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 20170720 Year of fee payment: 13 Ref country code: SE Payment date: 20170725 Year of fee payment: 13 Ref country code: DK Payment date: 20170721 Year of fee payment: 13 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20180131 Year of fee payment: 13 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20170725 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20180823 Year of fee payment: 14 Ref country code: DE Payment date: 20180823 Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20180823 Year of fee payment: 14 Ref country code: CH Payment date: 20180823 Year of fee payment: 14 Ref country code: AT Payment date: 20180827 Year of fee payment: 14 |
|
REG | Reference to a national code |
Ref country code: DK Ref legal event code: EBP Effective date: 20180731 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MM Effective date: 20180801 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20180731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CZ Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180725 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180801 Ref country code: SE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180726 Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180731 Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180725 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20190917 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180726 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 502005010392 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MM01 Ref document number: 484631 Country of ref document: AT Kind code of ref document: T Effective date: 20190725 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20190725 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200201 Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190725 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190725 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190731 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20190731 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20170725 |