ZA200700468B - Method for producing an infrastructure channel - Google Patents

Method for producing an infrastructure channel Download PDF

Info

Publication number
ZA200700468B
ZA200700468B ZA200700468A ZA200700468A ZA200700468B ZA 200700468 B ZA200700468 B ZA 200700468B ZA 200700468 A ZA200700468 A ZA 200700468A ZA 200700468 A ZA200700468 A ZA 200700468A ZA 200700468 B ZA200700468 B ZA 200700468B
Authority
ZA
South Africa
Prior art keywords
accordance
situ concrete
infrastructure channel
segment
segments
Prior art date
Application number
ZA200700468A
Inventor
Dupru Frank
Original Assignee
Dupru Frank
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dupru Frank filed Critical Dupru Frank
Publication of ZA200700468B publication Critical patent/ZA200700468B/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems

Abstract

The invention concerns a method for producing an infrastructure channel (1) which consists of at least two sub-pieces (2) of predetermined length, each sub-piece (2) being cast on-site from cast-in-place concrete (9) or from ready-mixed concrete to form a single piece.

Description

A method for the production of an infrastructure channel
The invention relates to a method for producing an infrastructure channel consisting of at least two segments of a predetermined length.
Infrastructure channels are employed in particular in new building construction areas - or large redevelopment projects in order to combine all supply and drainage lines in a single, preferably man-sized, sealed channel. Thanks to its spatial design, the supply and drainage lines can be directly and permanently monitored. Pipe leakage and cable emissions within a multi-utility duct of an infrastructure channel reach the sole of the building in liquid or semi-solid form or can leak out as a gas in the air filled space of the utility duct. Leaks in pipelines can be indicated by installed leakage warning systems, without excavation being necessary. Furthermore, replacing or installing new supply and drainage lines within the infrastructure channel can be done easily as access is possible via construction openings without excavation. In addition, not only the supply and drainage lines, but also the inside of the infrastructure channel can be inspected using a commercially available channel inspection camera system.
Separating the static parts of the infrastructure channel from the supply and drainage lines in the multi-utility duct provides a relatively high level of safety with respect to leakage resulting from infrastructure channel subsidence, with the protective function of a double-walled pipe being exceeded by a development solution employing an infrastructure channel. Moreover, roots are unable to penetrate the supply and drainage lines through unsealed segment joints and crack damage.
DE 20113897 U1 makes known an infrastructure channel consisting of individual, single-piece prefabricated segments that are combined to create a continuous channel. Each prefabricated segment is provided with a base plate, onto which two lateral walls are connected, which are connected to each other by means of vaulting at the top. The prefabricated segments are manufactured on a production line and combined on the construction site by means of seals on the front faces. In order to be able to transport the prefabricated segments without damage, at the least it is necessary to provide expensive reinforcing protection during transportation.
Furthermore, producing a flat trench for accommodating the full surface of the prefabricated segment base plates requires a huge amount of work. In addition, sealing the facing ends of the adjacent prefabricated segments can only be achieved with great effort. Moreover, the factory-made prefabricated segments have the . disadvantage that their length is very limited due to the constraints of production technology.
Furthermore, in practice channels are known that are not only prefabricated constructions, but also cast-in-situ concrete solutions provided with steel reinforcement, which have the disadvantage that in the event of cracking or efflorescence the reinforcing is exposed and can rust, initiating the complete destruction of the channels, e.g. due to the rupturing effect. In the event of fire the concrete pops off the steel reinforcement and the channel is subsequently destroyed.
The object of the invention is to provide a method of the kind mentioned at the outset that ensures the rapid and inexpensive production of an infrastructure channel.
In accordance with the invention, the object is fulfilled by pouring each segment in one piece on site using in-situ concrete or ready-mixed concrete.
Each individual segment of the infrastructure channel is produced as a single piece on the construction site continuously from in-situ concrete or ready mixed concrete; inthe present description the term "in-situ concrete" also encompasses ready mixed concrete. The length of each segment being produced is dimensioned in each case such that the segment can be produced as one day's work, with the length being between 4m and 40m, preferably between 10m and 20m, preferentially 15m. Steel reinforcement is not required. Owing to the lack of steel reinforcement and the relatively large length of each segment and the relatively minimal preparation, it can be ensured that the infrastructure channel is produced quickly and cost effectively.
Preferably, an expansion joint waterstop is poured in between two adjacent segments. The expansion joint waterstop comprises two sealing strips connected to each other by means of a central tube, with each sealing strip corresponding to one end of one segment. For reasons of functionality, the expansion joint waterstop with sealing components is inserted into the end surface of each segment. For this purpose an end shutter is employed, which is provided with slits for the expansion joint waterstop, which is connected securely to the segments after the in-situ concrete has set, virtually ruling out any leakage. Furthermore, provision is made for a component consisting of foamed polymer, in particular polystyrene, that ensures . the functionality of the expansion joint waterstop. - In order to absorb the water expelled during compacting of the in-situ concrete and to provide it again to the in-situ concrete during its subsequent setting, the inner formwork is preferably spanned by a drainage geotextile. The steel inner formwork, a hinged steel shutter movable into a concreting position and a driving position, is covered by a plastic mesh that is firmly attached to the inner formwork by means of plastic rivets. The reusable drainage geotextile, which is tightly spanned across the inner formwork in the concreting position, is attached to the plastic mesh.
In the embodiment, the beginning and the end of the infrastructure channel are closed by wooden panels and/or a strip sheet curtain while the in-situ concrete is drying. It makes sense to close the beginning of the infrastructure channel with wooden panels provided with a door and to close the end of each form of the segment being made with a strip sheet curtain in order to prevent any undesirable drafts of air within the infrastructure channel. The strip sheet curtain can be fastened onto the inner formwork, for instance at the end of the infrastructure channel. In addition, the wooden panels could be useful for securing a handling device, in particular a cableway crane, for moving parts on the construction site, in particular sheet insulation.
Preferably, an atmospheric humidifier to cure the in-situ concrete is set up inside the segment after the formwork has been removed from it. In order to ensure the efficacy of the atmospheric humidifier, for reasons of functionality a sheet wall is erected inside the infrastructure channel as a function of the number of segments involved.
The sheet wall can be developed in portable form and be moved in accordance with construction progress in order for curing with the atmospheric humidifier to be completed in about three sections for each segment.
in order to remove the formwork of each segment relatively early despite the high proportion of fly ash in the in-situ concrete, thermally insulated external formwork is preferred.
According to another embodiment, the segments are covered by at least one air bubble film after the removal of the formwork. The air bubble film prevents undesirable thermal stresses in the in-situ concrete that could cause cracking and - results in a relatively short formwork removal time. The air bubble films could for instance be laid over the infrastructure channel by means of the cableway crane such that they cover three to six segments. The cableway crane, fastened for instance at one end to the wooden panels closing the entrance to the infrastructure channel and at the other end to the formwork, is also drawn forward during the removal of formwork, as is the air bubble film, ensuring that the cover follows the advance of the removal of formwork. If cover known in practice using so-called winter construction protective matting is employed, which is only commercially available in relatively small dimensions, there is the risk of the temperature differential being too great between the core of the in-situ concrete and the ambient temperature. In addition, the winter construction protective matting does not provide immediate and continuous insulation.
Preferably, the temperature of the in-situ concrete is measured to ascertain the maturity of the concrete, which is a function of the temperature and time. The temperature can be measured at several spatial intervals along the segment, preferably at the outer and the inner diameter and in the middle with respect to the cross-section, serving primarily to determine the optimal point in time to remove the formwork from the segment and to specify the duration of curing for the setting in-situ concrete. The temperature measurement data is supplied to a concrete maturity computer, which is used to calculate the formwork removal time.
In order to make the required quantity of water available for curing the in-situ concrete, it is expedient to install a sprinkler hose undemeath the air bubble film, in particular a micro sprinkler hose, to irrigate the in-situ concrete. The sprinkler hose is developed such that the setting in-situ concrete is prevented from eroding, which is why a development is preferred with micro-openings.
In a further embodiment, a controllable heating system is operated inside the internal formwork. The heating, that can comprise one or a plurality of gas burners, is especially required when the ambient temperature is low and can be controlled by the concrete maturity computer by means of the temperature measurement data. 5 In the case of in-situ concrete for the production of an infrastructure channel, ) reinforcement is formed by means of artificial fibres, in particular polypropylene fibres, . with the artificial fibres being mixed into the in-situ concrete.
Preferably, the in-situ concrete has a short stiffening time and a green strength of 6
N/mm2 in particular. This allows the formwork to be removed quickly. Furthermore, the in-situ concrete comprises a disproportionately large proportion of fly ash.
Depending on the external temperature, the proportion of fly ash can be larger than the proportion of cement. Such a formula is not permitted under the German standard for reinforced concrete. However, as the individual segments of the infrastructure channel are not provided with steel, this standard is meaningless in the present case. The high proportion of fly ash offers not only economic, but also ecological benefits. However, heat generation in particular is less than with standard formulas, with a reduction in the risk of shrinkage cracks developing.
In the case of one infrastructure channel, an upper vault of a segment is provided with a cover, dimensioned in such a manner that tubing, in particular a high-voltage conduit, can be introduced into the inside. The cover must be provided with relatively large dimensions so that the tubing, which is generally rigid, can be introduced into the centre of the infrastructure channel. The opening for accommodating the cover, which can be opened for subsequent activities in particular, is produced by means of a conical cut out in the inner formwork and a cover provided with an outer contour corresponding to the opening is manufactured accordingly in a prefabricated mould to fit perfectly.
Preferably, at least one of the side walls is provided with at least one corbel to support the conduit. The corbel can for instance be fastened by means of a tie rod.
The corbel, which has for instance an L-shaped or Z-shaped cross-section, ensures a reliable support for the conduit and allows the ends of two pipes being connected to be welded together. Furthermore, the corbel is dimensioned to support rollers for displacing the conduit. For reasons of functionality, the corbel consists of fibrous cement.
It goes without saying that the characteristics mentioned above and those to be discussed below can be utilised in combinations other than those indicated in each specific case. The scope of the invention is only defined by the claims.
The invention is described in more detail below on the basis of one embodiment with reference to the corresponding drawings. In the drawing:
Fig. 1 shows a longitudinal view through an infrastructure channel produced using the method in accordance with the invention, with a one complete segment and two outlined segments,
Fig. 2 shows a cross-section through a segment of the infrastructure channel in accordance with Fig. 1,
Fig. 3 shows a representation of the infrastructure channel in perspective in accordance with Fig. 1,
Fig. 4 shows a front view of the infrastructure channel in accordance with Fig. 3, and
Fig. 5 shows a magnified representation of corbels for the infrastructure channel.
The infrastructure channel 1 consists of a large number of segments 2, with the facing ends 3 of each segment abutting the said facing ends of the adjacent segments in a sealed manner. Provision is made for an expansion joint waterstop 5 to seal the joint 4 existing between two facing ends 3, with said waterstop comprising a central hose 6, with sealing components 7, 8 connected on both sides of it that abut against the segment 2 in each case.
Each segment 2 of the infrastructure channel 1 is produced continuously on the construction site from in-situ concrete 9 by means of a one-piece construction method 9.To do this, a predominantly flat and compressed ground surface is created in an excavation pit. The length of each segment 2 to be produced is dimensioned such that it can be completed in a single day's work.
To produce a segment 2, intemal formwork 11 without a floor, consisting of sheet metal and provided with hinges 12, is installed first, with the hinges 12 serving to swing the sections of internal formwork 11 inward after the in-situ concrete 9 has cured. The concreting process is performed in linked partial steps, with a sole 10 with . wall stubs being poured first on the flat ground surface. There is a short waiting period before the side walls 16 and a vault 17 are concreted in order for the in-situ concrete 9 of the sole 10 to set.
A drainage geotextile 15 is spanned over the internal formwork 11 that absorbs the water escaping from the settling in-situ concrete and then makes it available to it again during subsequent curing of the in-situ concrete 9. After the drainage geotextile has been installed, a thermally insulating outer shell 19 is installed for the walls 16 and the vault 17. 15 An end shutter with slits for the expansion joint waterstop 5 is employed at each facing end. After the segment 2 is completed and the in-situ concrete 9 has set, the inner formwork 11 is folded together and then drawn out of the finished segment 2 in the direction of the arrow 18. The segment 2 is now closed on the entry side by means of wooden panels 20 provided with a door.
With the dismantling of the outer shell 19, sheets of air bubble film are pulled continuously with the progress of dismantling by means of a cableway crane 21 over the segment 2, with a frame 22 attached at the beginning of the infrastructure channel 1 and another frame 23 attached at its end, being displaced in accordance with construction progress.
The next segment 2 of the infrastructure channel 1 is then produced in the same manner, until the entire length of the infrastructure channel 1 is completed. The infrastructure channel 1 forms an accessible shell in which supply and drainage lines of any desired diameter can be laid. A reversal of or repair to the supply and drainage lines is possible at any time without excavations as manholes are arranged along the infrastructure channel 1 at least at intervals.
In order on the one hand to produce the segment 2 of the infrastructure channel 1 in one piece and on the other to do so without a loss of quality, in particular with respect to the formation of cracks, a formula for the in-situ concrete 9 is required that sets quickly, ensures a high green strength of around 6 N/mm2 and allows slow continuing curing with low hydration heat. Reinforcement 13 in the form of artificial . fibres 14 is added to the in-situ concrete 9 in order to ensure special resilience of the in-situ concrete 9, in particular with tension and stress cracks being prevented and : early, impact, shock and abrasion strength being increased.
Provision is made for corbels 25 to be arranged one above the other on one of the side walls 26 of the infrastructure channel 1 to support a conduit 24, with the corbels 25 developed in such a way that on the one hand they hold the conduit 24 securely, and on the other not only allow the conduit 24 to be welded to another conduit 24 at their facing ends, but also to provide a support for rollers for displacing the conduit 24.

Claims (19)

Claims
1. A method for the production of an infrastructure channel (1) consisting of at least two segments (2) of predetermined length, wherein each segment (2) is poured in one piece on the construction site using in-situ concrete (9) or ready mixed concrete.
2. Method in accordance with Claim 1, wherein an expansion joint waterstop (5) } is poured between two adjacent segments (2).
3. Method in accordance with Claim 2, wherein the expansion joint waterstop (5) with sealing components (7, 8) is inserted into each facing end (3) of the segments (2).
4. Method in accordance with any one of Claims 1 to 3, wherein an inner shell (11) is spanned by a drainage geotextile (15).
5. Method in accordance with any one of the Claims 1 to 4, wherein the beginning and the end of the infrastructure channel (1) is closed by means of wooden panels and/or a strip sheet curtain while the in-situ concrete (9) is drying.
6. Method in accordance with any one of the Claims 1 to 5, wherein an atmospheric humidifier is installed in the middle of the segment (2) after the formwork has been removed from it.
7. Method in accordance with any one of the Claims 1 to 6, wherein a sheet wall is positioned inside the infrastructure channel (1) as a function of the number of existing segments (2).
8. Method in accordance with any one of the Claims 1 to 7, wherein a thermally insulated outer shell (19) is employed.
9. Method in accordance with any one of the Claims 1 to 8, wherein the segments (2) are covered by at least one air bubble film during the removal of formwork.
10. Method in accordance with Claim 9, wherein a sprinkler hose, in particular a micro- sprinkler hose, is installed under the air bubble film to irrigate the in-situ concrete (9).
11. Method in accordance with any one of the Claims 1 to 10, wherein the temperature of the in-situ concrete (9) is measured.
12. Method in accordance with any one of the Claims 1 to 11, wherein a controllable heating system is operated inside the inner shell (11).
13. In-situ concrete to be utilised with the method in accordance with any one of the Claims 1 to 12, wherein the reinforcement (13) is constituted by artificial fibres (14), in particular polypropylene fibres.
14. In-situ concrete in accordance with Claim 13, characterised by rapid stiffening and in particular a green strength of 6 N/mm2.
15. In-situ concrete in accordance with either Claim 13 or 14, characterised by a disproportionately large proportion of fly ash.
16. Infrastructure channel, produced in particular in accordance with any one of Claims 1 to 12, wherein an upper vault of a segment (2) is provided with a cover, dimensioned in such a manner that a conduit, in particular a high voltage line, can be introduced into the centre.
17. Infrastructure channel in accordance with Claim 16, wherein at least one of the side walls (26) is provided with at least one corbel (25) for supporting a conduit (24).
18. Infrastructure channel in accordance with Claim 17, wherein the corbel (25) is attached to the side wall (26) with pre-tensioning.
19. Infrastructure channel in accordance with Claim 17 or 18, wherein the corbel (25) consist of fibrous cement.
ZA200700468A 2004-07-26 2007-01-16 Method for producing an infrastructure channel ZA200700468B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE202004011702U DE202004011702U1 (en) 2004-07-26 2004-07-26 Infrastructure Channel

Publications (1)

Publication Number Publication Date
ZA200700468B true ZA200700468B (en) 2008-04-30

Family

ID=33395387

Family Applications (1)

Application Number Title Priority Date Filing Date
ZA200700468A ZA200700468B (en) 2004-07-26 2007-01-16 Method for producing an infrastructure channel

Country Status (11)

Country Link
EP (1) EP1776507B1 (en)
KR (1) KR101295224B1 (en)
AT (1) ATE484631T1 (en)
CA (1) CA2574892C (en)
DE (2) DE202004011702U1 (en)
DK (1) DK1776507T3 (en)
EG (1) EG24424A (en)
ES (1) ES2350986T3 (en)
NO (1) NO338129B1 (en)
WO (1) WO2006012855A1 (en)
ZA (1) ZA200700468B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004026013B4 (en) * 2004-05-27 2007-05-03 Theodor Cordes Gmbh & Co Kg Drainable pipeline with root protection, and method for laying a pipeline
DE102007061802B3 (en) * 2007-12-19 2009-03-05 Frank Dupre Channel system for receiving power cables
US9844524B2 (en) * 2015-06-29 2017-12-19 Vanguard Soap LLC Soap compositions and methods

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5035931B1 (en) 1970-03-30 1975-11-20
DE2944385A1 (en) * 1979-11-02 1981-05-14 Josef Riepl Bau-Aktiengesellschaft, 8000 München METHOD FOR PRODUCING SLOT WALLS
DE3524687A1 (en) 1985-07-11 1986-02-27 Josef Riepl Bau-Aktiengesellschaft, 8000 München Method and apparatus for producing cast-in-situ concrete conduits with inserted inner lining in a monolithic type of construction
BG44644A1 (en) 1986-01-10 1989-01-16 Pet R Kh Shivarov
DE3838239A1 (en) 1988-09-07 1990-03-15 Niederberg Chemie Collector pipe and sewer pipe in which it is possible to walk
JPH08165700A (en) * 1994-12-12 1996-06-25 Seibu Polymer Corp Joint for closed conduit
HU223387B1 (en) 1998-12-28 2004-06-28 Béla Boldoghy Light-structural building with internal drag tross and buried form profile, besides form profile and framework, and process for making of building, from profile and framework
GB2360472A (en) 2000-03-24 2001-09-26 Joseph Ash Storage Tanks Ltd Method of coating storage tanks with concrete

Also Published As

Publication number Publication date
NO338129B1 (en) 2016-08-01
EP1776507B1 (en) 2010-10-13
CA2574892C (en) 2012-09-18
CA2574892A1 (en) 2006-02-09
NO20071081L (en) 2007-04-26
ES2350986T3 (en) 2011-01-28
KR101295224B1 (en) 2013-08-12
DE502005010392D1 (en) 2010-11-25
ATE484631T1 (en) 2010-10-15
KR20070083512A (en) 2007-08-24
EG24424A (en) 2009-06-10
DE202004011702U1 (en) 2004-10-21
WO2006012855A1 (en) 2006-02-09
DK1776507T3 (en) 2011-01-24
EP1776507A1 (en) 2007-04-25

Similar Documents

Publication Publication Date Title
CN108505805B (en) Large cast-in-situ water pool with expansion reinforcing belt for crack control and construction method thereof
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN111828056B (en) Shallow-buried underground excavation tunnel waterproof construction method
CN110905523A (en) Subway vertical shaft construction method
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN202660067U (en) Waterproof sleeve preventing wall body leakage
CA2574892C (en) A method for the production of an infrastructure channel
CN211286072U (en) Post-cast strip seals structure in advance
CN111456085A (en) Cast-in-place concrete construction method for pipe gallery segment
CN108360573B (en) Device for preventing post-cast strip of basement floor from leaking and construction method thereof
CN115898469A (en) Tunnel secondary lining construction method
WO2022198848A1 (en) Construction method of pre-laid waterproof roll lap joint edge of bottom plate and bottom plate side formwork supporting structure
EP2941517B1 (en) Method and device for drainage and detection of leakage
CN107905351B (en) Outer wall structure of ultra-long underground garage and construction method thereof
JP2764252B2 (en) Underground concrete structure repair material and repair method
CN110409508B (en) Post-cast strip waterproof structure and construction method thereof
CN217537031U (en) Deep basal pit raft, sump pit, elevartor shaft integration construction structures
CN108532975B (en) Early maintenance device and method for cast-in-place concrete wall surface
KR100580881B1 (en) Waterproof construction method of farming channel underground valve room
CN108532627B (en) Temporary plugging method for pipe gallery port of bolt-fixed prefabricated plate
Demis et al. Round Peg in a Square Hole for Combating SOB’s–Using FRP Tanks for Replacing H2S Damaged Structures in the City of Aurora Collection System
CN117385927A (en) Comprehensive construction method for underground comprehensive pipe rack
CN114658085A (en) Construction method of modular prefabricated combined thin-wall reinforced concrete inspection well
CN114961047A (en) Novel construction method of composite concrete shear wall structure
CN115435147A (en) Construction method for centralized arrangement of hydraulic pipelines of converter station