EP0231304B1 - Securing of rails with a spring clamp - Google Patents

Securing of rails with a spring clamp Download PDF

Info

Publication number
EP0231304B1
EP0231304B1 EP86904805A EP86904805A EP0231304B1 EP 0231304 B1 EP0231304 B1 EP 0231304B1 EP 86904805 A EP86904805 A EP 86904805A EP 86904805 A EP86904805 A EP 86904805A EP 0231304 B1 EP0231304 B1 EP 0231304B1
Authority
EP
European Patent Office
Prior art keywords
clamp
rail
ribs
ribbed plate
free ends
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
EP86904805A
Other languages
German (de)
French (fr)
Other versions
EP0231304A1 (en
Inventor
Horst Bauernfeind
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Vossloh Werke GmbH
Original Assignee
Vossloh Werke GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Vossloh Werke GmbH filed Critical Vossloh Werke GmbH
Priority to AT86904805T priority Critical patent/ATE47172T1/en
Publication of EP0231304A1 publication Critical patent/EP0231304A1/en
Application granted granted Critical
Publication of EP0231304B1 publication Critical patent/EP0231304B1/en
Priority to LVP-92-214A priority patent/LV15686D/en
Expired legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B9/00Fastening rails on sleepers, or the like
    • E01B9/38Indirect fastening of rails by using tie-plates or chairs; Fastening of rails on the tie-plates or in the chairs
    • E01B9/44Fastening the rail on the tie-plate
    • E01B9/46Fastening the rail on the tie-plate by clamps
    • E01B9/48Fastening the rail on the tie-plate by clamps by resilient steel clips
    • E01B9/483Fastening the rail on the tie-plate by clamps by resilient steel clips the clip being a shaped bar

Definitions

  • the invention relates to a rail fastening that can be preassembled on sleepers by means of a ribbed plate and sleeper screw by means of an elastic tension clamp made of steel bar in the form of a W, the middle part of which wraps around the shaft of the hook screw anchored in a groove of the rib of the ribbed plate, the opposing free ends of the tension clamp in the installed position press the rail foot and the middle part comes to lie at a small distance above the rail foot and the bracket parts of the tension clamp facing away from the rail foot are supported on the outer flank of the rib of the rib plate.
  • the base plate lies on the threshold with its guide ribs which are pulled up laterally next to the rail.
  • the rail is fastened by means of the sleeper screw, which presses with the screw head plate onto the elastic clamp made of steel bar.
  • the bent ends of the clamp press on the rail foot, while the inversions of the clamp are supported against rotation on the base plate against its outer strips.
  • the middle part of the clamp is arched up under the screw head and wraps around the screw shaft. When the screw is tightened, the middle part of the clamp is depressed and its middle section, which comes to rest on the rib of the base plate, limits the span of travel. This prevents the clamp from being overstressed and the base plate is screwed onto the threshold sufficiently.
  • the rail fastening according to DE-PS 19 54 008 does not limit its span of travel on the rib of the ribbed plate, but rather the middle part of the tension clamp extends into the area of the rail foot itself, where it lies either in the mounting position on the rail foot or at the free ends of the tension clamp or is located close to the same, so that the central part forms a direct or indirect hard-spring limit for lifting movements of the rail foot there.
  • the rail fastenings described meet the requirements of modern railway operations in their operating position (assembly position), d. H. the rail fastening is suitable for ensuring that the rail foot is securely fastened to the wooden sleeper, even at high speeds and with increased axle loads.
  • the rails are moved more strongly in the vertical direction due to the increased axle loads, although lifting of the rail foot can occur despite the tensioning forces of the bow-shaped clamps acting on the rail foot. Even when cornering, there are increased stresses on the rail due to horizontal force components that try to cause the rail to tilt.
  • the object of the invention is therefore to provide a rail fastening of the type mentioned at the outset with a non-rotatable pre-mountable tensioning clamp with rear support for use on ribbed plates.
  • this aim is achieved with a rail fastening according to the preamble of claim 1, which is characterized by the features of the characterizing part of claim 1. Appropriate developments of such a rail fastening result from the subclaims.
  • This new rail fastening is characterized by a more stable position of the bond between the hook screw and the preassembled tension clamp against lateral impact forces acting on the tension screw, i.e. against forces acting in the longitudinal axis of the sleeper, as is often the case, for example, when loading, unloading or when laying on the web body or when inserting the rail during track construction.
  • So z. B. with the tension clamp according to PS 33 34 119 (Alpha 1400 ) cannot be avoided by the inclined position of the threaded bolt (hook screw) this jumps back into the vertical position or that the diagonally clamped clamping clamp falls down from this unstable position due to even a slight vibration and thus prevents the rail from being inserted.
  • the more stable position with the new tension clamp is achieved in that the hook screw is pushed back vertically into the mushroom cut in the ribbed plate into the pre-assembly position.
  • the tension clamp with the hook screw is brought into the screwed position by a hammer blow in the direction of the rail web and then braced. None has to be removed, turned or plugged in again.
  • the anti-rotation device is provided by the rear support of the tension clamp on the rib plate directly on the outer flank of the rib and additionally by the free ends of the tension clamp on the inner flank of the rib. This ensures that during the transition from the pre-assembly - in the assembly position, d. H. when tightening the nut of the hook screw, the tension clamp does not turn in the direction of rotation and can therefore take an unfavorable position on the rail foot.
  • Fig. 1 the rail fastening according to the invention is shown in view on the left half and in section on the right half.
  • the left side shows the track exterior in the assembly position and the right side shows the track interior in the pre-assembly position, with the tensioning clamp lying outside the outer edge of the rail foot 1b 6.
  • Figures 1 and 2 show the new rail fastening on wooden sleepers.
  • the rail 1 is fastened to a wooden sleeper 4 by means of an elastic intermediate layer 2 between the ribs 3a and 3b of the ribbed plate 3.
  • the rib plate 3 is fastened to the wooden sleeper 4 with four sleeper screws 5, which clamp the ribbed plate 3 onto the wooden sleeper 4 by means of high-tension spring washers 6.
  • the inclined position of the axis of symmetry 7 of the rail 1, z. B. 1:40, is achieved by appropriate inclination of the surface of the rib plate between the ribs.
  • a small step 8 is provided in the outside area in a known manner.
  • the rail 1 In the installed position, the rail 1 is held down non-positively between the ribs 3a, 3b of the ribbed plate 3 in the region of the rail foot 1a, 1 on both sides by means of the tensioning clamps 9.
  • the tensioning clamp 9 is shown on the left-hand side of FIGS. 1 and 2 in the assembly position, the free ends 9a to be pressed towards one another pressing on the rail foot 1a, while the middle part 9e in the installation position lies at a small distance a above the rail foot 1a.
  • the tension clamps are tightened by means of the hook screws 11 anchored in the grooves 10a, 10b of the ribs 3a, 3b with nuts 12 and washers 13.
  • the ribbed plate 3 with the tensioning clamps 9 is already pre-assembled on the sleeper 4 in the position 9 'in the sleeper unit.
  • the ribbed plate 3 is tightened on the sleeper 4 by means of the sleeper screws 5 and the tensioning clamp 9 is positioned in the position 9 'by means of the hook screw 11 of the nut 12 and the washer 13. It can be seen that the tensioning clamp 9 'is so inclined in this position that the free arms 9a rest on the rib 3b and the central part 9e in the untensioned state lie above and outside the free space of the rail.
  • the support legs 9c of the tensioning clamp 9 facing away from the rail 1 are bent outwards and are somewhat concave in the plan view, which can be seen particularly well from FIG.
  • the parts of the tension clamp 9 that wrap around the shaft of the hook screw 11, namely its central part 9e and the two lateral legs 9d, which have corresponding flats 14 in their parts that come into engagement with the washer 13, are also somewhat inclined in the preassembly position, the Hook screw slightly offset to the side and is only slightly tightened so that the tension clamp is just sufficiently fixed in the preassembly position 9 '.
  • the middle part 9e-9d of the tension clamp 9 is bent so far that the legs 9d run up to a distance 15, which is less than the diameter of the shaft of the hook screw 11.
  • the somewhat complicated spatial shape of the new tension clamp can be seen particularly well when looking at FIGS. 3 and 4.
  • the ends 9a are shaped in such a way that when the tension clamp is pressed together they do not adhere to the head loop 9e, 9d in Come into contact.
  • the spatial shape of the tensioning clamp 9 can be seen even better from the perspective illustration according to FIG. 6.
  • the shape of the tension clamp 9 also ensures that it cannot rotate when the hook screw 11 is tightened in the direction of rotation of the nut, because during tensioning and in the mounting position, the outer support legs 9c and the free ends 9a are each on the outer flank or inner flank of the Support the ribs 3a, 3b of the ribbed plate 3.
  • the middle part 9e of the tensioning clamp is brought into the tensioning position by means of the hook screw 11 in such a way that it does not touch the rail foot 1a, 1b, but remains at a distance a.
  • the hook screw 11 is only tightened to such an extent that a small distance a remains between the middle part 9e and the rail foot 1 a or 1 b. This distance ensures that the relatively hard spring characteristic of the middle part 9e of the tensioning clamp 9 only comes into effect when the rail foot is lifted over the distance a, namely when the soft resilient ends 9a are raised to the height of the middle part 9e.
  • the pre-assembly position and the assembly position are characterized in that the surface of the ribs 3a, 3b of the fin plate does not come into contact with the different parts of the tension clamp 9.
  • This surface of the ribs serves only as a support for the free ends 9a in the pre-assembly position 9 'of the tension clamp .
  • the correct positioning of the tension clamp is ensured by the outer and inner flanks of the ribs 3a, 3b of the ribbed plate 3.

Abstract

Rails are fixed by a W-shaped steel spring clamp (9) made from bar steel, in which the central part passes round the shank of a square-headed bolt (11) anchored in a slot (10a, 10b) in the ribs (3a, 3b) of the sole plate (3); the free and closely-located ends (9a) of the clamp (9) exert a pressure on the rail foot (1a, 1b) and the pressure arms (9c) of the clamp (9) opposite the rail foot (1a, 1b) press on the outer side of the ribs (3a, 3b) of the sole plate. To enable pre-assembly, the free ends (9a') of the clamp (9') rest, in the pre-assembly position, on the upper surface of the ribs (3a, 3b) of the sole plate (3) in such a way that they provide a tight closure with the lower edge of the ribs and the two clamps of a support point form a rail-guide with their two free ends. In the assembly position, the free ends (9a) of the clamp (9) press on the rail foot (1a, 1b), by means of the square-headed bolt (11). The middle part (9e) is then located slightly above (a) the rail foot (1a, 1b) and the pressure arms (9c) opposite the rail foot rest on the outer side of the ribs (3a, 3b) and press on the sole-plate (3).

Description

Die Erfindung betrifft eine auf Schwellen mittels Rippenplatte und Schwellenschraube vormontierbare Schienenbefestigung mittels einer elastischen Spannklemme aus Stabstahl in Form eines W, deren Mittelteil den Schaft der in einer Nut der Rippe der Rippenplatte verankerten Hakenschraube umschlingt, wobei die gegeneinanderlaufenden freien Enden der Spannklemme in der Montagestellung auf den Schienenfuß drücken und der Mittelteil in einem kleinen Abstand über dem Schienenfuß zu liegen kommt und wobei sich die dem Schienenfuß abgewandten Bügelteile der Spannklemme an der Außenflanke der Rippe der Rippenplatte abstützen.The invention relates to a rail fastening that can be preassembled on sleepers by means of a ribbed plate and sleeper screw by means of an elastic tension clamp made of steel bar in the form of a W, the middle part of which wraps around the shaft of the hook screw anchored in a groove of the rib of the ribbed plate, the opposing free ends of the tension clamp in the installed position press the rail foot and the middle part comes to lie at a small distance above the rail foot and the bracket parts of the tension clamp facing away from the rail foot are supported on the outer flank of the rib of the rib plate.

Bei einer in der DE-PS 1 261 151 beschriebenen vorbekannten Schienenbefestigung liegt die Unterlagsplatte mit ihren seitlich neben der Schiene hochgezogenen Führungsrippen auf der Schwelle. Die Befestigung der Schiene erfolgt dabei mittels der Schwellenschraube, die mit ihrem Schraubenkopfteller auf die elastische Klemme aus Stabstahl drückt. Die hereingebogenen Enden der Klemme drücken auf den Schienenfuß, während sich die Umkehrungen der Klemme auf der Unterlagsplatte gegen deren äußere Leisten verdrehungssicher abstützen. Der Mittelteil der Klemme ist unter dem Schraubenkopf hochgewölbt und umschlingt den Schraubenschaft. Beim Anziehen der Schraube wird der Mittelteil der Klemme niedergedrückt und erfährt durch seinen auf der Rippe der Unterlagsplatte zur Auflage kommenden mittleren Abschnitt eine Spannwegbegrenzung. Dadurch wird eine Überbeanspruchung der Klemme verhindert und die Unterlagsplatte genügend fest auf der Schwelle verschraubt.In a known rail fastening described in DE-PS 1 261 151, the base plate lies on the threshold with its guide ribs which are pulled up laterally next to the rail. The rail is fastened by means of the sleeper screw, which presses with the screw head plate onto the elastic clamp made of steel bar. The bent ends of the clamp press on the rail foot, while the inversions of the clamp are supported against rotation on the base plate against its outer strips. The middle part of the clamp is arched up under the screw head and wraps around the screw shaft. When the screw is tightened, the middle part of the clamp is depressed and its middle section, which comes to rest on the rib of the base plate, limits the span of travel. This prevents the clamp from being overstressed and the base plate is screwed onto the threshold sufficiently.

Im Gegensatz zu der beschriebenen vorbekannten Konstruktion gemäß DE-PS 12 61 151 erfährt die Schienenbefestigung gemäß DE-PS 19 54 008 (siehe Oberbegriff des Anspruchs 1) ihre Spannwegbegrenzung nicht auf der Rippe der Rippenplatte, sondern der Mittelteil der Spannklemme erstreckt, sich bis in den Bereich des Schienenfusses selbst, wo er in Montagestellung entweder am Schienenfuß oder an den freien Enden der Spannklemme anliegt oder sich dicht über demselben befindet, so daß der Mittelteil dort eine direkte oder indirekte hartfedernde Begrenzung für Abhebebewegungen des Schienenfusses bildet. Dadurch erreicht man, daß die bügelförmige Klemme in ihrer Montagestellung einerseits mit Teilen der Klemme die Schiene über einen langen Federweg niederdrückt und andererseits entweder durch die Abstützung dieser Klemmteile gegen einen anderen hartfedernden Teil der Klemme oder bei gemeinsamer Anlage des einen wie des anderen Klemmteils an der Oberfläche des Schienenfusses erhöhten Abhebekräften der Schiene sowie einer etwaigen Kippbewegung derselben über einen kurzen Federweg mit erhöhter Haltekraft entzgegenwirkt. (vgl. DE-PS 19 54 008, Spalte 1, Zeilen 45-56).In contrast to the previously described construction according to DE-PS 12 61 151, the rail fastening according to DE-PS 19 54 008 (see preamble of claim 1) does not limit its span of travel on the rib of the ribbed plate, but rather the middle part of the tension clamp extends into the area of the rail foot itself, where it lies either in the mounting position on the rail foot or at the free ends of the tension clamp or is located close to the same, so that the central part forms a direct or indirect hard-spring limit for lifting movements of the rail foot there. This ensures that the bow-shaped clamp depresses the rail on the one hand with parts of the clamp over a long spring travel in its mounting position and on the other hand either by supporting these clamping parts against another hard resilient part of the clamp or by jointly engaging one or the other clamping part on the Counteracted surface of the rail foot increased lifting forces of the rail and any tilting movement of the rail over a short spring travel with increased holding force. (see DE-PS 19 54 008, column 1, lines 45-56).

Die beschriebenen Schienenbefestigungen genügen den Anforderungen des neuzeitlichen Eisenbahnbetriebes in ihrer Betriebsspannstellung (Montagestellung), d. h. die Schienenbefestigung ist geeignet, auch bei erhöhten Geschwihdigkeiten und erhöhten Achslasten eine gute Befestigung des Schienenfusses auf der Holzschwelle zu gewährleisten. Durch die erhöhten Achslasten werden die Schienen bekanntlich stärker in vertikaler Richtung bewegt, wobei trotz der auf den Schienenfuß wirkenden Spannkräfte der bügelförmigen Klemmen ein Abheben des Schienenfusses auftreten kann. Auch bei der Kurvenfahrt ergeben sich erhöhte Beanspruchungen der Schiene durch horizontale Kraftkomponenten, die ein Kippen der Schiene herbeizuführen suchen.The rail fastenings described meet the requirements of modern railway operations in their operating position (assembly position), d. H. the rail fastening is suitable for ensuring that the rail foot is securely fastened to the wooden sleeper, even at high speeds and with increased axle loads. As is known, the rails are moved more strongly in the vertical direction due to the increased axle loads, although lifting of the rail foot can occur despite the tensioning forces of the bow-shaped clamps acting on the rail foot. Even when cornering, there are increased stresses on the rail due to horizontal force components that try to cause the rail to tilt.

Um einen noch gleichmäßigere Anpressdruck der Federklemme auf den Schienenfuß auch über große Federwege zu gewährleisten, ist auch bereits eine Schienenbefestigung mit einer elastischen Klemme aus Stabstahl in Form eines W geschaffen worden, bei welcher die vom Schienenfuß abgewandten Umkehrungen der Klemme sich nicht mehr auf der Rippenplatte abstützen, sondern freischwebend etwa in der Höhe der Oberfläche der Rippe der Rippenplatte verlaufen. Eine derartige Schienenbefestigung ist in der DE-PS 33 34 119 (Vossloh) dargestellt. Die schlanke Formgebung der Spannklemme gemäß dieser Konstruktion gestattet auch bereits eine für den Gleisbau vorteilhafte Vormontage. Dabei ist allerdings die für die Montage gewünschte Verdrehsicherung nicht mehr gegeben. Bei der erstgenannten Konstruktion gemäß DE-PS 1 261 151 wird eine solche Verdrehsicherung erst durch die Abstützung der Umkehrungen an besonderen auf den Rippenplatten angeordneten Leisten erreicht.In order to ensure an even more even contact pressure of the spring clamp on the rail foot even over long spring travel, a rail fastening with an elastic clamp made of steel bar in the form of a W has already been created, in which the inversions of the clamp facing away from the rail foot no longer lie on the ribbed plate support, but free-floating approximately at the height of the surface of the rib of the rib plate. Such a rail attachment is shown in DE-PS 33 34 119 (Vossloh). The slim shape of the tension clamp according to this construction also allows pre-assembly that is advantageous for track construction. However, the anti-rotation lock required for assembly is no longer provided. In the first-mentioned construction according to DE-PS 1 261 151, such an anti-rotation device is only achieved by supporting the reversals on special strips arranged on the ribbed plates.

Aufgabe der Erfindung ist es daher, eine Schienenbefestigung der eingangs genannten Art mit einer verdrehsicheren vormontierbaren Spannklemme mit hinterer Abstützung für den Einsatz auf Rippenplatten zu schaffen. Erfindungsgemäß wird dieses Ziel mit einer Schienenbefestigung nach dem Oberbegriff von Patentanspruch 1 erreicht, die sich durch die Merkmale des kennzeichnenden Teils von Patentanspruch 1 auszeichnet. Zweckmäßige Weiterbildungen einer derartigen Schienenbefestigung ergeben sich aus den Unteransprüchen.The object of the invention is therefore to provide a rail fastening of the type mentioned at the outset with a non-rotatable pre-mountable tensioning clamp with rear support for use on ribbed plates. According to the invention, this aim is achieved with a rail fastening according to the preamble of claim 1, which is characterized by the features of the characterizing part of claim 1. Appropriate developments of such a rail fastening result from the subclaims.

Diese neue Schienenbefestigung zeichnet sich durch eine stabilere Lage des Verbundes zwischen der Hakenschraube und der vormontierten Spannklemme gegenüber seitlichen auf die Spannschraube einwirkenden Anstoßkräften aus, d. h. gegenüber in Längsachse der Schwelle wirkenden Kräften, wie sie häufig beispielsweise beim Verladen, Endladen oder beim Verlegen auf den Bahnkörper oder beim Einführen der Schiene beim Gleisbau, auftreten. So kann z. B. bei der Spannklemme nach PS 33 34 119 (Alpha 1400) nicht vermieden werden, daß durch die Schrägstellung des Gewindebolzens (Hakenschraube) dieser wieder in die senkrechte Stellung zurückspringt oder daß die schräg hochkant eingeklemmte Spannklemme durch eine auch nur geringe Erschütterung aus dieser labilen Lage nach unten fällt und damit ein Einlegen der Schiene verhindert. Die stabilere Lage bei der neuen Spannklemme wird dadurch erreicht, daß die Hakenschraube senkrecht in die Pilzfräsung der Rippenplatte in die Vormontagestellung zurückgeschoben ist.This new rail fastening is characterized by a more stable position of the bond between the hook screw and the preassembled tension clamp against lateral impact forces acting on the tension screw, i.e. against forces acting in the longitudinal axis of the sleeper, as is often the case, for example, when loading, unloading or when laying on the web body or when inserting the rail during track construction. So z. B. with the tension clamp according to PS 33 34 119 (Alpha 1400 ) cannot be avoided by the inclined position of the threaded bolt (hook screw) this jumps back into the vertical position or that the diagonally clamped clamping clamp falls down from this unstable position due to even a slight vibration and thus prevents the rail from being inserted. The more stable position with the new tension clamp is achieved in that the hook screw is pushed back vertically into the mushroom cut in the ribbed plate into the pre-assembly position.

Durch die besondere Gestaltung der freien Federarme der neuen Spannklemme, die in der Vormontagestellung mit der Rippeninnenkante abschließen, erleichtern die beiden auf der Schwelle gegenüberliegenden Spannklemmen mit ihren jeweils beiden freien Armen die Schieneneinführung. Die Schieneneinfädelung wird gegenüber allen bisherigen Verfahren so wesentlich vereinfacht, daß Arbeiten, wie das Nachrichten von Schwellen, nicht mehr erforderlich werden.Due to the special design of the free spring arms of the new tension clamp, which end in the preassembly position with the inside edge of the ribs, the two tension clamps opposite on the threshold with their two free arms each facilitate the insertion of the rails. Rail threading is simplified so much compared to all previous methods that work such as the notification of sleepers is no longer necessary.

Bei der vorliegenden Anmeldung wird die Spannklemme mit der Hakenschraube durch einen Hammerschlag in Richtung Schienensteg in die Verschraubungsposition gebracht und anschließend verspannt. Es muß nichts mehr entnommen, gedreht oder wieder eingesteckt werden.In the present application, the tension clamp with the hook screw is brought into the screwed position by a hammer blow in the direction of the rail web and then braced. Nothing has to be removed, turned or plugged in again.

Die Verdrehsicherung ergibt sich einmal durch die hintere Abstützung der Spannklemme auf der Rippenplatte unmittelbar an der Außenflanke der Rippe und zusätzlich durch Anlage der freien Enden der Spannklemme an der Innenflanke der Rippe. Dadurch ist gewährleistet, daß beim Übergang von der Vormontage - in die Montagestellung, d. h. beim Anziehen der Mutter der Hakenschraube die Spannklemme sich nicht in Drehrichtung verdrehen und so eine ungünstige Position auf dem Schienenfuß einnehmen kann.The anti-rotation device is provided by the rear support of the tension clamp on the rib plate directly on the outer flank of the rib and additionally by the free ends of the tension clamp on the inner flank of the rib. This ensures that during the transition from the pre-assembly - in the assembly position, d. H. when tightening the nut of the hook screw, the tension clamp does not turn in the direction of rotation and can therefore take an unfavorable position on the rail foot.

Weitere Einzelheiten der erfindungsgemäßen Schienenbefestigung ergeben sich aus der Zeichnung. In der Zeichnung zeigen :

  • Fig. 1 Einen Querschnitt durch ein Schienenprofil, bei welchem die linke Seite die Schienenbefestigung in Montagestellung (verspannte Stellung) im Gleisaußenraum und die rechte Seite die Schienenbefestigung in Vormontagestellung im Gleisinnenraum im Schnitt darstellt ;
  • Fig. 2 die Draufsicht auf die Schienenbefestigung gemäß Fig. 1, d. h. die linke Seite von Fig. 2 in Montagestellung und die rechte Seite in Vormontagestellung ;
  • Fig. 3 eine Draufsicht auf die Spannklemme der erfindungsgemäßen Schienenbefestigung ;
  • Fig. 4 eine Seitenansicht der Spannklemme von der Schiene her gesehen ;
  • Fig. 5 einen Schnitt nach der Linie V-V in Fig. 4;
  • Fig. 6 eine perspektivische Ansicht der Spannklemme.
Further details of the rail fastening according to the invention emerge from the drawing. The drawing shows:
  • Fig. 1 shows a cross section through a rail profile, in which the left side represents the rail fastening in the assembly position (tensioned position) in the track exterior and the right side shows the rail fastening in the pre-assembly position in the track interior in section;
  • FIG. 2 shows the top view of the rail fastening according to FIG. 1, ie the left side of FIG. 2 in the assembly position and the right side in the pre-assembly position;
  • 3 shows a plan view of the tensioning clamp of the rail fastening according to the invention;
  • Figure 4 is a side view of the tension clamp seen from the rail.
  • 5 shows a section along the line VV in Fig. 4.
  • Fig. 6 is a perspective view of the tension clamp.

In Fig. 1 ist die erfindungsgemäße Schienenbefestigung auf der linken Hälfte in Ansicht und auf der rechten Hälfte im Schnitt dargestellt. Die linke Seite zeigt den Gleisaußenraum in Montagestellung und die rechte Seite den Gleisinnenraum in Vormontagestellung, wobei die Spannklemme außerhalb des Außenrandes des Schienenfusses 1b 6 liegt.In Fig. 1, the rail fastening according to the invention is shown in view on the left half and in section on the right half. The left side shows the track exterior in the assembly position and the right side shows the track interior in the pre-assembly position, with the tensioning clamp lying outside the outer edge of the rail foot 1b 6.

Die Figuren 1 und 2 zeigen die neue Schienenbefestigung auf Holzschwellen. Dabei ist die Schiene 1 unter Vermittlung einer elastischen Zwischenlage 2 zwischen den Rippen 3a und 3b der Rippenplatte 3 auf einer Holzschwelle 4 befestigt. Die Befestigung der Rippenplatte 3 auf der Holzschwelle 4 erfolgt mit vier Schwellenschrauben 5, welche die Rippenplatte 3 unter Vermittlung von hochspannenden Federringen 6 auf die Holzschwelle 4 spannen.Figures 1 and 2 show the new rail fastening on wooden sleepers. The rail 1 is fastened to a wooden sleeper 4 by means of an elastic intermediate layer 2 between the ribs 3a and 3b of the ribbed plate 3. The rib plate 3 is fastened to the wooden sleeper 4 with four sleeper screws 5, which clamp the ribbed plate 3 onto the wooden sleeper 4 by means of high-tension spring washers 6.

Die von verschiedenen Bahnverwaltungen vorgeschriebene Schräglage der Symmetrieachse 7 der Schiene 1, z. B. 1 :40, wird durch entsprechende Neigung der Oberfläche der Rippenplatte zwischen den Rippen erreicht. Um die Rippenplatte 3 nicht zu schwer werden zu lassen, ist eine kleine Stufe 8 im Außenbereich in bekannter Weise vorgesehen.The inclined position of the axis of symmetry 7 of the rail 1, z. B. 1:40, is achieved by appropriate inclination of the surface of the rib plate between the ribs. In order not to make the ribbed plate 3 too heavy, a small step 8 is provided in the outside area in a known manner.

In Montagestellung wird die Schiene 1 zwischen den Rippen 3a, 3b der Rippenplatte 3 im Bereich des beiderseitigen Schienenfusses 1 a, 1 mittels der Spannklemmen 9 dauernd kraftschlüssig niedergehalten. Die Spannklemme 9 ist auf der jeweils linken Seite der Figuren 1 und 2 in Montagestellung gezeigt, wobei die aufeinanderzulaufenden freien Enden 9a auf den Schienenfuß 1 a drücken, während der Mittelteil 9e in Montagestellung mit einem kleinen Abstand a über dem Schienenfuß 1a liegt. Die Spannklemmen werden mittels der in den Nuten 10a, 10b der Rippen 3a, 3b verankerten Hakenschrauben 11 mit Muttern 12 und Unterlagscheiben 13 gespannt.In the installed position, the rail 1 is held down non-positively between the ribs 3a, 3b of the ribbed plate 3 in the region of the rail foot 1a, 1 on both sides by means of the tensioning clamps 9. The tensioning clamp 9 is shown on the left-hand side of FIGS. 1 and 2 in the assembly position, the free ends 9a to be pressed towards one another pressing on the rail foot 1a, while the middle part 9e in the installation position lies at a small distance a above the rail foot 1a. The tension clamps are tightened by means of the hook screws 11 anchored in the grooves 10a, 10b of the ribs 3a, 3b with nuts 12 and washers 13.

Zur Vereinfachung und Verbilligung der Gleismontage wird die Rippenplatte 3 mit den Spannklemmen 9 in der Stellung 9' auf der Schwelle 4 bereits im Schwellenwerk vormontiert. Dabei wird die Rippenplatte 3 auf der Schwelle 4 mittels der Schwellenschrauben 5 festgezogen und die Spannklemme 9 in der Position 9' mittels der Hakenschraube 11 der Mutter 12 und der Unterlagscheibe 13 positioniert. Man erkennt, daß die Spannklemme 9' in dieser Stellung so schräg gestellt ist, daß die freien Arme 9a auf der Rippe 3b aufliegen und der Mittelteil 9e im unverspannten Zustand darüber und außerhalb des Freiraumes der Schiene liegen.To simplify and reduce the cost of the track assembly, the ribbed plate 3 with the tensioning clamps 9 is already pre-assembled on the sleeper 4 in the position 9 'in the sleeper unit. The ribbed plate 3 is tightened on the sleeper 4 by means of the sleeper screws 5 and the tensioning clamp 9 is positioned in the position 9 'by means of the hook screw 11 of the nut 12 and the washer 13. It can be seen that the tensioning clamp 9 'is so inclined in this position that the free arms 9a rest on the rib 3b and the central part 9e in the untensioned state lie above and outside the free space of the rail.

In dieser Stellung ist die Einführung der Schiene 1 zwischen die beiden Rippen 3a, 3b nicht behindert. Die der Schiene 1 abgewandten Abstützschenkel 9c der Spannklemme 9 sind dabei nach außen so abgebogen und in der aus Fig. 3 besonders gut erkennbaren Draufsicht nach außen etwas konkav geformt, daß sie sich an den Köpfen der Schwellenschrauben 5 abstützen können. Die den Schaft der Hakenschraube 11 umschlingenden Teile der Spannklemme 9, nämlich ihr Mittelteil 9e und die beiden seitlichen Schenkel 9d, die in ihrem mit der Beilagscheibe 13 in Eingriff kommenden Teilen entsprechende Abflachungen 14 aufweisen, sind gleichfalls in der Vormontagestellung etwas schräg gestellt, wobei die Hakenschraube etwas seitlich versetzt und nur soweit leicht angezogen ist, daß die Spannklemme in der Vormontagestellung 9' gerade ausreichend fixiert ist.In this position, the insertion of the rail 1 between the two ribs 3a, 3b is not hindered. The support legs 9c of the tensioning clamp 9 facing away from the rail 1 are bent outwards and are somewhat concave in the plan view, which can be seen particularly well from FIG. The parts of the tension clamp 9 that wrap around the shaft of the hook screw 11, namely its central part 9e and the two lateral legs 9d, which have corresponding flats 14 in their parts that come into engagement with the washer 13, are also somewhat inclined in the preassembly position, the Hook screw slightly offset to the side and is only slightly tightened so that the tension clamp is just sufficiently fixed in the preassembly position 9 '.

Wie man aus den Ansichten der Figuren 3 und 4 erkennt, ist der Mittelteil 9e-9d der Spannklemme 9 soweit zusammengebogen, daß die Schenkel 9d bis auf einen Abstand 15 gegeneinander laufen, der geringer ist als der Durchmesser des Schaftes der Hakenschraube 11. Nach dem Bereich der dichtesten Annäherung der beiden Schenkel beim Abstand 15 entfernen sie sich wieder symmetrisch zur Mittellinie V-V voneinander, um anschliessend abwärts zu laufen und in die Abstützschenkel 9c überzugehen, die etwa parallel zur Schiene verlaufen, dann jedoch wieder aufwärts gebogen sind und in die Außenflügel 9b übergehen, die schliessüch in die gegen den Schienenfuß abgebogenen freien Enden 9a münden. Die freien Enden 9a verlaufen etwa parallel zu den Schenkeln 9c und zum Schienenfuß.As can be seen from the views of Figures 3 and 4, the middle part 9e-9d of the tension clamp 9 is bent so far that the legs 9d run up to a distance 15, which is less than the diameter of the shaft of the hook screw 11. After the In the area of the closest approach of the two legs at the distance 15, they again move away from each other symmetrically to the center line VV, in order to then run downwards and merge into the support legs 9c, which run approximately parallel to the rail, but are then bent upwards again and into the outer wings 9b pass over, which finally open into the free ends 9a bent against the rail foot. The free ends 9a run approximately parallel to the legs 9c and to the rail foot.

Die etwas komplizierte Raumform der neuen Spannklemme erkennt man besonders gut aus einer Zusammenschau der Figuren 3 und 4. Wie man aus Fig. 3 erkennt, sind die Enden 9a so geformt, daß sie bei einem Zusammenpressen der Spannklemme nicht mit der Kopfschlinge 9e, 9d in Berührung kommen. Noch besser läßt sich die Raumform der Spannklemme 9 aus der perspektivischen Darstellung gemäß Fig. 6 erkennen.The somewhat complicated spatial shape of the new tension clamp can be seen particularly well when looking at FIGS. 3 and 4. As can be seen from FIG. 3, the ends 9a are shaped in such a way that when the tension clamp is pressed together they do not adhere to the head loop 9e, 9d in Come into contact. The spatial shape of the tensioning clamp 9 can be seen even better from the perspective illustration according to FIG. 6.

Die Formgebung der Spannklemme 9 stellt auch sicher, daß sie sich beim Anziehen der Hakenschraube 11 nicht in Drehrichtung der Mutter mitdrehen kann, weil beim Verspannen und in der Montagestellung die äußeren Abstützschenkel 9c und die freien Enden 9a sich jeweils an der Außenflanke bzw. Innenflanke der Rippen 3a, 3b der Rippenplatte 3 abstützen.The shape of the tension clamp 9 also ensures that it cannot rotate when the hook screw 11 is tightened in the direction of rotation of the nut, because during tensioning and in the mounting position, the outer support legs 9c and the free ends 9a are each on the outer flank or inner flank of the Support the ribs 3a, 3b of the ribbed plate 3.

Der Mittelteil 9e der Spannklemme wird mittels der Hakenschraube 11 derart in Spannstellung gebracht, daß er den Schienenfuß 1a, 1b nicht berührt, sondern im Abstand a verbleibt. Dadurch ist eine weiche Federcharakteristik gewährleistet. Dies erreicht man dadurch, daß bei der Montage mit dem entsprechenden Werkzeug die Mutter 12 auf. der Hakenschraube 11 nur soweit angezogen wird, daß zwischen dem Mittelteil 9e und dem Schienenfuß 1 a bzw. 1 b noch ein kleiner Abstand a verbleibt. Dieser Abstand stellt sicher, daß die relativ harte Federcharakteristik des Mittelteils 9e der Spannklemme 9 erst bei einer den Abstand a überwindenden Abhebebewegung des Schienenfusses zur Wirkung kommt, dann nämlich, wenn die weichfedernden Enden 9a bis in die Höhe des Mittelteils 9e angehoben sind.The middle part 9e of the tensioning clamp is brought into the tensioning position by means of the hook screw 11 in such a way that it does not touch the rail foot 1a, 1b, but remains at a distance a. This ensures a soft spring characteristic. This is achieved in that the nut 12 on assembly with the appropriate tool. the hook screw 11 is only tightened to such an extent that a small distance a remains between the middle part 9e and the rail foot 1 a or 1 b. This distance ensures that the relatively hard spring characteristic of the middle part 9e of the tensioning clamp 9 only comes into effect when the rail foot is lifted over the distance a, namely when the soft resilient ends 9a are raised to the height of the middle part 9e.

Vormontagestellung und Montagestellung zeichnen sich dadurch aus, daß die Oberfläche der Rippen 3a, 3b der Rippenplatte nicht in Kontakt kommt mit den verschiedenen Teilen der Spannklemme 9. Diese Oberfläche der Rippen dient lediglich als Auflage für die freien Enden 9a in der Vormontagestellung 9' der Spannklemme. Beim Montieren ist die korrekte Positionierung der Spannklemme durch die äußeren und inneren Flanken der Rippen 3a, 3b der Rippenplatte 3 gewährleistet.The pre-assembly position and the assembly position are characterized in that the surface of the ribs 3a, 3b of the fin plate does not come into contact with the different parts of the tension clamp 9. This surface of the ribs serves only as a support for the free ends 9a in the pre-assembly position 9 'of the tension clamp . When mounting, the correct positioning of the tension clamp is ensured by the outer and inner flanks of the ribs 3a, 3b of the ribbed plate 3.

Die Abflachungen 14 gelangen beim Montieren aus ihrer. auf der rechten Seite von Fig. 1 gezeigten Schräglage in die horizontale Lage unter der Unterlagscheibe 13. Um die Montage zu bewerkstelligen, genügt es, die Hakenschraube 11 in der Nut 10 etwas nach innen zu schieben und die Mutter 12 soweit anzuziehen, bis der Mittelteil 9e in die Montagestellung im Abstand a über dem Schienenfuß 1a, 1b gebracht ist. Wie schon erwähnt, gestattet die aus Fig. 3 und aus dem rechten Bereich von Fig. 2 besonders gut erkennbare nach außen konkave Formgebung der Abstützschenkel 9c der Spannklemme 9 ihren besonders günstigen Einsatz für die Vormontage der erfindungsgemäßen Schienenbefestigung.The flats 14 get out of their assembly. on the right side of Fig. 1 inclined position in the horizontal position under the washer 13. To accomplish the assembly, it is sufficient to push the hook screw 11 in the groove 10 slightly inward and tighten the nut 12 until the middle part 9e is brought into the mounting position at a distance a above the rail foot 1a, 1b. As already mentioned, the outwardly concave shape of the support legs 9c of the tensioning clamp 9, which can be seen particularly well from FIG. 3 and from the right-hand area of FIG. 2, allows it to be used particularly advantageously for the preassembly of the rail fastening according to the invention.

Claims (6)

1. Rail fastener pre-mountable on sleepers (4) by means of a ribbed plate (3) and a rail bolt with a resilient clamp (9) of steel rod in the form of a W, whose middle part embraces the shaft of the clip bolt (11) anchored in a groove (10a, 10b) of the rib (3a, 3b) of the ribbed plate (3), the opposed free ends (9a) of the clamp (9) in the mounted position pressing via the clip bolt (11) on the base of the rail (1a, 1 b) and the middle part (9e) coming to lie a small distance (a) above the base of the rail (1 a, 1 b), and the supporting legs (9c) of the clamp (9), which face away from the base of the rail (1a, 1b), abutting the outer flank of the rib (3a, 3b) of the ribbed plate (3), characterised in that the free ends (9a) of the clamp (9) in the pre-mounted condition rest on the surface of the ribs (3a, 3b) of the ribbed plate (3) in such a manner that the free spring arms (9a') do not hinder installation of the rail, the two clamps (9') of a rail support point forming, with their free arms (9a'), a rail insertion guide and in that to achieve torsional security of the clamp in the mounted position additionally the free ends (9a) of the clamp (9) lie against the inner flank of the ribs (3a, 3b) directly on the outer edge of the ribs (3a, 3b), next to the rear support of the clamp (9) on the ribbed plate (3).
2. Rail fastener according to claim 1, characterised in that in the pre-mounted position of the clamp the clip bolt is outwardly offset and stands upright in a semi-circular cut-out of the ribs (3a, 3b).
3. Rail fastener according to claim 1 or 2, characterised in that the side limbs (9d) and the outer wing (9b) of the clamp (9) are so formed that the clamp, in its mounted position, does not contact the surface of the ribs (3a, 3b) of the ribbed plate (3).
4. Rail fastener according to any one of claims 1-3, characterised in that the rear support limbs (9c) are so formed that, in the pre-mounted condition of the clamp (9'), the rail screws (5) are partly embraced.
5. Rail fastener according to any one of claims 1-4, characterised in that the head loop which embraces the clip bolt (11 ) formed of a central part (9e) and side legs (9d) has flattened surfaces for cooperation with the washer (13), and/or the nut (12).
6. Rail fastener according to claim 5, characterised in that the side legs (9d), after forming the head loop for receiving the shaft of the clip bolt (11), approach each other at a spacing which is smaller than the diameter of the clip bolt, so that the clamp (9), even when pre-mounted, is captively connected with the bolt (11 ).
EP86904805A 1985-07-25 1986-07-23 Securing of rails with a spring clamp Expired EP0231304B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
AT86904805T ATE47172T1 (en) 1985-07-25 1986-07-23 RAIL FASTENING USING AN ELASTIC TENSION CLAMP.
LVP-92-214A LV15686D (en) 1985-07-25 1992-11-25 A device for fixing rails.

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE19853526653 DE3526653A1 (en) 1985-07-25 1985-07-25 RAIL MOUNTING BY AN ELASTIC TENSION CLAMP
DE3526653 1985-07-25

Publications (2)

Publication Number Publication Date
EP0231304A1 EP0231304A1 (en) 1987-08-12
EP0231304B1 true EP0231304B1 (en) 1989-10-11

Family

ID=6276767

Family Applications (1)

Application Number Title Priority Date Filing Date
EP86904805A Expired EP0231304B1 (en) 1985-07-25 1986-07-23 Securing of rails with a spring clamp

Country Status (12)

Country Link
EP (1) EP0231304B1 (en)
AT (1) ATE47172T1 (en)
DD (1) DD249059A5 (en)
DE (2) DE3526653A1 (en)
ES (1) ES2001395A6 (en)
GE (1) GEP19960346B (en)
HU (1) HU195862B (en)
LT (1) LT2264B (en)
LV (1) LV15686D (en)
MD (1) MD435C2 (en)
SU (1) SU1482536A3 (en)
WO (1) WO1987000566A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006002682A1 (en) 2004-07-01 2006-01-12 Vossloh-Werke Gmbh Angled guide plate and system for fixing rails for rail vehicles
RU204247U1 (en) * 2020-08-10 2021-05-17 Общество с ограниченной ответственностью "Триэс" BAR RAIL TERMINAL

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE8906790U1 (en) 1989-06-02 1989-08-31 Vossloh-Werke Gmbh, 5980 Werdohl, De
US5735458A (en) * 1991-12-18 1998-04-07 Pandrol Limited Fastening railway rails
IN185922B (en) * 1991-12-18 2001-05-19 Pandrol Ltd
DE4432257C1 (en) * 1994-09-10 1996-03-07 Zueblin Ag Rail fixing device
DE20120831U1 (en) 2001-12-21 2002-05-08 Deutsche Bahn Ag Rail fastening for the operation of track conveyor systems
EP1533420A3 (en) 2003-11-24 2006-10-04 RTE Technologie GmbH Method for making a ballastless railway track
CA2622561C (en) 2007-02-21 2015-09-29 Portec Rail Products, Inc. Grease guide
DE102007046543A1 (en) * 2007-09-27 2009-04-16 Vossloh-Werke Gmbh System for securing a rail and tension clamp for such a system
WO2010033907A2 (en) * 2008-09-19 2010-03-25 Portec Rail Products, Inc. Hinged clamp
CN102164802B (en) * 2008-09-19 2016-01-20 L.B.福斯特铁路技术有限公司 Wiping bar quick clamp
US9914465B2 (en) 2009-05-29 2018-03-13 L.B. Foster Rail Technologies, Inc. Top of rail resilient bar
US8955645B2 (en) 2009-05-29 2015-02-17 L.B. Foster Rail Technologies, Inc. Top of rail foam bar
MD169Z5 (en) * 2009-11-26 2010-11-30 Ивановский Анатолий Алексеевич Rail fixing device
BG1330U1 (en) * 2010-01-20 2010-06-30 Георги Бахаров Elastic padding clamp for railway track at curves
BG1383U1 (en) * 2010-06-16 2010-11-30 Георги Бахаров A construction for a rail joint
US9045866B2 (en) 2010-11-04 2015-06-02 Vossloh-Werke Gmbh Tensioning clamp for fastening a rail and system equipped with a tensioning clamp of this type
DE102010050199A1 (en) * 2010-11-04 2012-05-10 Vossloh-Werke Gmbh Tension clamp for fastening a rail and system equipped with such a tension clamp
DE102010050200A1 (en) * 2010-11-04 2012-05-10 Vossloh-Werke Gmbh Tension clamp for fastening a rail and system equipped with such a tension clamp
DE102011000896A1 (en) * 2011-02-23 2012-08-23 Vossloh-Werke Gmbh System for fastening a rail
MD832Z (en) * 2014-03-18 2015-06-30 Игорь ЧЕТУЛЯН Process for the production of dried food product from vegetables
DE102016103316B4 (en) 2016-02-25 2022-12-29 Semperit Ag Holding rail fastening system
DE102020122553A1 (en) 2020-08-28 2022-03-03 Deutsche Bahn Aktiengesellschaft ANCHOR POINT DEVICE AND RAIL MOUNTING

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE8505959U1 (en) * 1985-03-01 1985-06-27 Vossloh-Werke Gmbh, 5980 Werdohl Kit for fastening rails

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1011208A (en) * 1910-05-02 1911-12-12 John W Kendrick Tie-plate.
US2008941A (en) * 1932-02-01 1935-07-23 Engineering Materials Ltd Railway rail movement restraining means
US2324134A (en) * 1941-03-26 1943-07-13 Jacob R Snyder Rail clamp
DE808239C (en) * 1950-01-31 1951-07-12 Lorenz Jaeger Rail fastening on rib shims
GB772821A (en) * 1955-02-22 1957-04-17 George Turton Platts & Co Ltd Means for securing rails to rail chairs or other supporting base
FR1323628A (en) * 1962-02-27 1963-04-12 Rail fixing device facilitating the installation of the latter in long bars
DE1858928U (en) * 1962-06-27 1962-09-27 Bundesbahn Bundesbahn Zentrala DEVICE FOR FASTENING RAILS ON RAILWAY SLEEPERS
US3549090A (en) * 1968-10-30 1970-12-22 Shigetaro Toyama Railroad tracks
DE2032915A1 (en) * 1970-07-02 1972-01-13 Vossloh Werke GmbH, 5980 Werdohl Fastening of rails without thresholds on tunnel floors, railway slabs and the like
DE2623944A1 (en) * 1976-05-28 1977-12-08 Schwihag Gmbh Railway track force locked elastic rail fixture - has clamp bracing unit lying on rail foot in rounding radius area
HU182120B (en) * 1980-04-03 1983-12-28 Schmitthelm Fa Ernst Flexible rail fastening device for concrete sleepers
DE3334119C2 (en) * 1983-09-21 1985-07-11 Vossloh-Werke Gmbh, 5980 Werdohl Device for fastening the rails by means of an elastic tension clamp

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE8505959U1 (en) * 1985-03-01 1985-06-27 Vossloh-Werke Gmbh, 5980 Werdohl Kit for fastening rails

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006002682A1 (en) 2004-07-01 2006-01-12 Vossloh-Werke Gmbh Angled guide plate and system for fixing rails for rail vehicles
RU204247U1 (en) * 2020-08-10 2021-05-17 Общество с ограниченной ответственностью "Триэс" BAR RAIL TERMINAL

Also Published As

Publication number Publication date
DE3526653A1 (en) 1987-02-05
HU195862B (en) 1988-07-28
SU1482536A3 (en) 1989-05-23
LV5310A3 (en) 1993-10-10
GEP19960346B (en) 1996-02-21
DE3666242D1 (en) 1989-11-16
DE3526653C2 (en) 1989-07-20
ES2001395A6 (en) 1988-05-16
LT2264B (en) 1993-12-15
DD249059A5 (en) 1987-08-26
EP0231304A1 (en) 1987-08-12
LV15686D (en) 2020-07-20
ATE47172T1 (en) 1989-10-15
WO1987000566A1 (en) 1987-01-29
HUT43345A (en) 1987-10-28
MD435C2 (en) 1996-09-30

Similar Documents

Publication Publication Date Title
EP0231304B1 (en) Securing of rails with a spring clamp
EP0295685B1 (en) Rail-holding device on rigid railroad
DE102007045466B3 (en) System for fastening a rail
DD291593A5 (en) RAIL MOUNTING ON CONCRETE SHAFTS OD. DGL. BY ELASTIC TERMINALS
DE102005048829A1 (en) Positive-elastic rail fastening for track systems
DE3243895A1 (en) FASTENING ARRANGEMENT FOR RAILS ON SILLS
EP0194550B1 (en) Securing clamp and fastening device for railway rails
WO2009043822A1 (en) System for fastening a rail and tensioning clamp for such a system
EP2204494A1 (en) Elastic tensioning clamp and rail attachment for same
DE3400110C2 (en)
EP0987368B1 (en) Guard rail fastening
EP2297402B9 (en) System for fixing a rail to a substrate
EP0343149B1 (en) Device for securing stock rails in switches
DE3334119C2 (en) Device for fastening the rails by means of an elastic tension clamp
EP0794289A1 (en) Elastic rail fastening
DE3507310A1 (en) Rail fastening
DE19642971C2 (en) Resilient rail fastening
DE3230612A1 (en) Device for fastening stock rails or travel rails in railway switches
DE1257817B (en) Rail fastening on concrete sleepers or the like.
DE3820243C2 (en) Tension clamp and fastening arrangement for railroad tracks
DE2602869C2 (en) Spring-loaded rail fastening
DE3743701A1 (en) Bracket anchor
EP0156149B1 (en) Anchorage for a sleeper of a railway track embedded in the ballast
DE3509473C2 (en)
DE8505959U1 (en) Kit for fastening rails

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19870602

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH DE IT LI LU NL

17Q First examination report despatched

Effective date: 19880425

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH DE IT LI LU NL

ITF It: translation for a ep patent filed

Owner name: BARZANO' E ZANARDO MILANO S.P.A.

REF Corresponds to:

Ref document number: 47172

Country of ref document: AT

Date of ref document: 19891015

Kind code of ref document: T

REF Corresponds to:

Ref document number: 3666242

Country of ref document: DE

Date of ref document: 19891116

RIN2 Information on inventor provided after grant (corrected)
PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
ITTA It: last paid annual fee
EPTA Lu: last paid annual fee
PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: IT

Payment date: 20050623

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20050627

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: LU

Payment date: 20050630

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20050715

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20050720

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20050722

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20050725

Year of fee payment: 20

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20060723

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

NLV7 Nl: ceased due to reaching the maximum lifetime of a patent

Effective date: 20060723

BE20 Be: patent expired

Owner name: *VOSSLOH-WERKE G.M.B.H.

Effective date: 20060723