EP0168103A2 - Wagengruppe zum Auswechseln von Gleisen - Google Patents

Wagengruppe zum Auswechseln von Gleisen Download PDF

Info

Publication number
EP0168103A2
EP0168103A2 EP85201038A EP85201038A EP0168103A2 EP 0168103 A2 EP0168103 A2 EP 0168103A2 EP 85201038 A EP85201038 A EP 85201038A EP 85201038 A EP85201038 A EP 85201038A EP 0168103 A2 EP0168103 A2 EP 0168103A2
Authority
EP
European Patent Office
Prior art keywords
vehicle
sleepers
renewal
railway
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP85201038A
Other languages
English (en)
French (fr)
Other versions
EP0168103A3 (en
EP0168103B1 (de
Inventor
Enrico Dr. Ing. Valditerra
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
VALDITERRA SpA
Original Assignee
VALDITERRA SpA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by VALDITERRA SpA filed Critical VALDITERRA SpA
Priority to AT85201038T priority Critical patent/ATE50008T1/de
Publication of EP0168103A2 publication Critical patent/EP0168103A2/de
Publication of EP0168103A3 publication Critical patent/EP0168103A3/fr
Application granted granted Critical
Publication of EP0168103B1 publication Critical patent/EP0168103B1/de
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/06Transporting, laying, removing or renewing sleepers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/02Placing the ballast; Making ballastway; Redistributing ballasting material; Machines or devices therefor; Levelling means
    • E01B27/023Spreading, levelling or redistributing ballast already placed
    • E01B27/025Spreading, levelling or redistributing ballast already placed by means of non-driven tools
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/05Transporting, laying, removing, or renewing both rails and sleepers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B35/00Applications of measuring apparatus or devices for track-building purposes
    • E01B35/06Applications of measuring apparatus or devices for track-building purposes for measuring irregularities in longitudinal direction
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/16Guiding or measuring means, e.g. for alignment, canting, stepwise propagation

Definitions

  • the present invention relates to a railway train intended to be used for the renewal or laying of railways.
  • the object of the present invention is to improve the railway trainsets intended for the indicated function, so as to considerably reduce their weight, size and cost, and to make them easier and more rational to use, that is to say concerns operations to renew damaged equipment while maintaining the previous route, that is to say with regard to the possible introduction of corrections to the route of the track.
  • the railway train according to the present invention is mainly characterized in that it comprises an operating assembly formed by two reciprocally coupled vehicles, the first vehicle being provided with two axles (or bogies), while the second is articulated, by one from its ends, to a point on the first vehicle, located in overhang with respect to the axles, and it is provided with a single axle (or bogie), located near the end opposite to said articulation; that the first vehicle is provided with means, situated between the two axles, for removing the old rails, means for allowing the second axle to move on the old sleepers already devoid of the rails, and means for handling the old and the new material; that the second vehicle is provided with means for removing the old sleepers, means for leveling or moving or loosening the ballast and means for laying the new sleepers, as well as means for allowing the second vehicle to move on the new ones sleepers still without new rails; and that in the articulation zone between the two vehicles are arranged means for correcting, as necessary, the position of the second vehicle and, consequently
  • the first vehicle of the operational set of the railway train according to the invention (preceded, as usual, by storage wagons which transport the new materials to be laid and which are intended to receive the old materials who have been removed) rolls with its first axle on the track to be renewed, previously freed from the fasteners, removes the old rails and advances with its second axle on the sleepers still laid, following. therefore faithfully the pre-existing route.
  • the second vehicle of the operating unit for its part, being articulated at a point on the first vehicle which is cantilevered with respect to the axles, spontaneously tends to be arranged with its own longitudinal axis tangential to the trajectory of the pre-existing line when the latter moves away from the straight line, so that the installation of new sleepers spontaneously tends to be made while respecting the previous line, thus minimizing the importance of the necessary corrections, which can be carried out manually or automatically , using the special means provided in the articulation area, either to maintain the old layout with the greatest precision, or to carry out the latter desired modifications.
  • the invention also relates, specifically, to means for laying new sleepers, means for correcting, as necessary, the position of the second vehicle, and a depot for special sleepers.
  • a railway train for the renewal of railways generally comprises an operating assembly according to FIG. 1 (predisposed to advance from right to left according to the drawing), subsequent operating means, known per se, mounted on wagons , not shown, which follow the operational assembly, and a certain number of storage wagons, intended to carry the new materials which must be laid and to receive the old materials which have been removed, disposed (in the direction of advancement of the train) in front of the operating unit shown in Figure I.
  • the operating assembly according to FIG. 1 comprises two vehicles defined by their chassis 1 and 2, which are reciprocally articulated in a spherical manner at 3.
  • the chassis of vehicle 1 has a first axle 4 and a second axle 5 (these axles can however be replaced by corresponding bogies), while the chassis of the vehicle 2 rests anteriorly, through the articulation 3, on the chassis 1, and later on its own axles 6 (which could also be replaced by a bogie).
  • the articulation point 3 is located in overhang relative to the axles 4 and 5 of the first vehicle I.
  • Figure 2 are shown schematically, by their axes, the path of the track along which is or must be arranged track B, and the first and second vehicles 1 and 2, reciprocally articulated in 3.
  • the axis of track B forms a curve
  • the axis of vehicle 1 which rests on axles 4 and 5
  • the articulation point 3 which is cantilevered, moves outside the curve.
  • the chassis 1 of the first vehicle carries, in its upper part, a transporter 7 connected to a depot B for the old removed sleepers, a depot 9 for the new sleepers to be laid, and a service track 10 for a portal transporter (known per se and not shown) intended for the handling of materials between depots 8 and 9 and the storage wagons arranged in front of the operating unit 1-2.
  • the chassis 1 carries, in its lower part, an engine group 11, generally a diesel engine actuating a hydrodynamic power station and an electric generator for supplying the various operating members of the assembly, a chassis 12 provided with pliers.
  • rollers 13 arranged (in a manner known per se) for lifting the underlying sleepers and drawing away the old rails which have to be removed, and an auxiliary bogie 14 (which can be lifted by means of a hydraulic cylinder 15) forming part of the means intended to allow to the second axle 5 to move on the old sleepers already devoid of the rails.
  • the chassis 2 of the second vehicle carries in its upper part a transporter 16, connected to the transporter 7 of the first vehicle, for the old sleepers removed, a transporter 17, connected to the depot 9 of the first vehicle, for the new sleepers to be laid, a parapet - stage 18 for the control of the installation and for possible interventions on the respective mechanisms, an operating cabin 19 and a depot 20 (described in more detail below with reference to FIGS. 5 and 6) for special sleepers to install in special places, such as at level crossings.
  • the chassis l carries, in its lower part, a device 21 for removing the old sleepers, which supplies the conveyor 16, a share 22 for leveling or removing the ballast, the group 23 for laying the new sleepers (described more in detail below with reference to Figure 4), a distributor 24 for special sleepers coming from the depot 20, and a tracked support 25 which can be lifted, for example, by means of a hydraulic cylinder 26.
  • the latter assembly which is raised during the approach walk on the track, when the axle 6 is active, is lowered (in the position shown) during work and allows the second vehicle 2 to proceed by relying on the new crosspieces laid, still devoid of rails (or, according to one; possible alternative, laterally to said sleepers).
  • a hydraulic cylinder 26A can be provided to fix the orientation of the tracked support 25 when the latter is active.
  • the operating assembly described acts by proceeding continuously to the left according to figure 1, by rolling by means of axle 4 on the old unbolted rails, by lifting and removing the old rails by means 12-13 while the old sleepers remain placed on the ballast, by rolling on these old sleepers by means of the axle 5 and the auxiliary bogie 14, removing by means of the removal device 21 the old sleepers that the carriers 16 and 7 send to the depot 8, by leveling or moving the ballast by means of the plowshare 22 and associated operating means, and by placing in the point C new sleepers, on which the assembly advances by means of the tracked support 25.
  • the subsequent operations (laying of new rails, compacting of the ballast, etc.) are carried out by successive operating means which are not part of the present invention and which are neither described nor illustrated here.
  • the second vehicle 2 is articulated to the first vehicle in the manner already described, thanks to which the point C of laying the new sleepers results located, with a good approximation, on the curve formed locally by the track, the laying of the sleepers takes place specifically in a very close to optimal manner. Only small corrections may be necessary, especially in the event of an abnormality of the route, or when for any reason we want to modify the previous route of the track.
  • two horizontal hydraulic cylinders 52, 53 are installed which allow the modification of the angle A (FIG. 2) formed between the axis of the chassis 2 of the second vehicle and the axis of the chassis 1 of the first vehicle, thereby modifying, as necessary, transverse to the track, the position of the point C of installation of the new sleepers.
  • the angle A formed between the two chassis 1 and 2 can be determined exactly by reading devices 54, for example potentiometers, installed on a chassis and connected to the other chassis by means of 'Between flexible rods 55.
  • the calculation of the corrections and the maneuvering of the cylinders 52 and 53 can be carried out manually or by automatic means programmed in an appropriate manner, on the basis of the knowledge of said angle A and of the local geometrical parameters of the track.
  • two vertical cylinders 56 making it possible to block and correct the transverse inclination of the corresponding anterior end of the chassis 2.
  • all these correction devices indicated as formed by hydraulic cylinders, can also be produced in the form of mechanical or electromechanical devices.
  • the various operating devices 21-24 installed on the chassis 2 can conveniently be provided with means for individual adjustment of the operating position of these devices.
  • a corridor or strip is usually used which reaches as close as possible to the ballast and onto which the sleepers descend one after the other under the control of a shutter which lets them proceed one by one. times at the appropriate time; installation on the ballast is done by falling from the lower end of the corridor or strip.
  • This arrangement has the disadvantage that, when a sleeper is about to leave the corridor or strip, all the load of its weight is concentrated on its lower posterior edge, which is often damaged, especially if it 's' acts of concrete sleepers.
  • the variability of the distance between the end of the corridor and the ballast, and other accidental conditions can lead to some irregularities in the installation of the sleepers by this process.
  • the gripping device 49 raised in the position represented by broken lines, is fed each time by a crosspiece which it grasps while it is pressed on the flap 47, and successively the flap 47 is lowered and the device 49 allows to place the cross member on the ballast by adjusting its position with the desired precision. During this operation, no concentration of forces is applied in any part of the crosspiece which, therefore, is laid under completely intact conditions.
  • the depot 20 installed in the operative assembly has the purpose of providing special sleepers T intended to be used in particular places of the line, for example in correspondence ⁇ ⁇ s level crossings, these special sleepers being able to be laid, in point C, by means of a special laying device 24.
  • the depot 20 comprises a horizontal conveyor 66 arranged to carry the special sleepers of the depot 20 to the laying device 24, and a conveyor vertical 69 provided with a plurality of pairs of horizontal consoles 70, 71, 72, etc., superimposed on each other with a uniform pitch, supporting superimposed rows of special sleepers T.
  • each pair of consoles has a different spacing than that of the other pairs of consoles and the spacing of the horizontal conveyor 68; for example, as shown in Figure 6, the spacing may increase from bottom to top.
  • the pairs of consoles 70, 71, etc. as they arrive below the level of the horizontal conveyor 68, s, accumulate alongside this conveyor at the level of the chassis 2, in the positions indicated by broken lines. Thanks to this arrangement, a compact deposit is produced which contains in a small space a considerable number of crosspieces T, and which can be loaded and unloaded by simple and rapid operations.
  • railway train according to the invention can have all the characteristics described or even just a part of these, depending on the particular applications for which it is intended. Different modifications can be made to the details described, and all parts and groups can be replaced by their technical equivalents.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Vehicle Cleaning, Maintenance, Repair, Refitting, And Outriggers (AREA)
  • Compositions Of Oxide Ceramics (AREA)
  • Ceramic Products (AREA)
  • Handcart (AREA)
  • Train Traffic Observation, Control, And Security (AREA)
  • Magnetic Heads (AREA)
  • Superconductors And Manufacturing Methods Therefor (AREA)
EP85201038A 1984-07-10 1985-06-28 Wagengruppe zum Auswechseln von Gleisen Expired - Lifetime EP0168103B1 (de)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AT85201038T ATE50008T1 (de) 1984-07-10 1985-06-28 Wagengruppe zum auswechseln von gleisen.

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
IT6770084 1984-07-10
IT67700/84A IT1179729B (it) 1984-07-10 1984-07-10 Convoglio per il rinnovamento di strade ferrate

Publications (3)

Publication Number Publication Date
EP0168103A2 true EP0168103A2 (de) 1986-01-15
EP0168103A3 EP0168103A3 (en) 1987-01-21
EP0168103B1 EP0168103B1 (de) 1990-01-31

Family

ID=11304609

Family Applications (1)

Application Number Title Priority Date Filing Date
EP85201038A Expired - Lifetime EP0168103B1 (de) 1984-07-10 1985-06-28 Wagengruppe zum Auswechseln von Gleisen

Country Status (7)

Country Link
US (1) US4867068A (de)
EP (1) EP0168103B1 (de)
JP (1) JPS6168902A (de)
AT (1) ATE50008T1 (de)
CA (1) CA1290619C (de)
DE (1) DE3575749D1 (de)
IT (1) IT1179729B (de)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0294700A2 (de) * 1987-06-08 1988-12-14 Enrico Valditerra Schienenfahrzeuge zur Erneuerung von Schienenwegen
GB2207165A (en) * 1987-07-23 1989-01-25 Plasser Bahnbaumasch Franz A railway sleeper changing machine
EP0388573A1 (de) * 1989-03-20 1990-09-26 Scheuchzer S.A. Gelenkzug zum Erneuern von Eisenbahnen
FR2759101A1 (fr) * 1997-01-31 1998-08-07 Desquenne & Giral Procede, dispositif et engin pour remplacer des traverses usagees
US7895950B2 (en) 2004-08-20 2011-03-01 Loram Maintenance Of Way, Inc. Long rail pick-up and delivery system
US8211184B2 (en) 2009-04-20 2012-07-03 Michael D. Ries Acetabular cup

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3876990D1 (de) * 1988-08-18 1993-02-04 Scheuchzer Sa Zug zur erneuerung eines eisenbahngleises.
IT1232099B (it) * 1989-05-23 1992-01-23 Valditerra S P A Procedimento per la saldatura continua di tronchi di rotaia, e rotabile attrezzato per la sua attuazione
DE19524285A1 (de) * 1995-07-04 1997-01-09 Robel Georg Gmbh & Co Schienenladewagen
US5664498A (en) * 1995-10-31 1997-09-09 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Track renewal machgine
ATA96796A (de) * 1996-06-04 1997-09-15 Plasser Bahnbaumasch Franz Maschine zum verlegen eines gleises
AT409979B (de) * 1997-10-06 2002-12-27 Plasser Bahnbaumasch Franz Gleisbaumaschine mit einem bezugsystem zur steuerung eines arbeitsaggregates und verfahren
AT3919U3 (de) * 2000-07-13 2001-08-27 Plasser Bahnbaumasch Franz Maschine zum abbau eines alten und verlegen eines neuen gleises
AT5708U3 (de) * 2002-07-17 2003-09-25 Plasser Bahnbaumasch Franz Maschine zur aufnahme von schwellen eines gleises
AT5769U3 (de) * 2002-09-05 2003-09-25 Plasser Bahnbaumasch Franz Maschine zum abbau und verlegen eines gleises und verfahren
DE502006008191D1 (de) * 2005-08-11 2010-12-09 Plasser Bahnbaumasch Franz Maschine zum erneuern eines gleises
ES2326403B2 (es) * 2009-03-27 2010-04-07 Tecsa Empresa Constructora, S.A. Maquina de posicionamiento y escuadrado de traviesas de vias de ferrocarril.
CH711720B1 (de) * 2015-11-03 2020-04-30 Matisa Materiel Ind Sa Verfahren zur Einleitung eines Schwellenwechselverfahrens zur Erneuerung von Schwellen eines aus Schienen und den Schwellen gebildeten Gleises und Gleisbaumaschine.

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1540376A (fr) * 1967-04-20 1968-09-27 Perfectionnement aux machines de réfection des voies ferrées
CH600046A5 (de) * 1977-04-22 1978-06-15 Matisa Materiel Ind Sa
GB2016562A (en) * 1978-03-15 1979-09-26 Canron Inc Renewing railway track
GB2023207A (en) * 1978-06-14 1979-12-28 Plasser Bahnbaumasch Franz Travelling rallway sleeper-laying machine
EP0019984A1 (de) * 1978-04-19 1980-12-10 Les Fils D'auguste Scheuchzer S.A. Zug zum Erneuern eines Eisenbahngleises
US4363274A (en) * 1978-10-13 1982-12-14 Canron Corporation Center line follower

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3473482A (en) * 1967-08-14 1969-10-21 Robert Pouget Wagons for transporting and positioning railway sleepers
AT305332B (de) * 1968-10-16 1973-02-26 Plasser Bahnbaumasch Franz Fahrbare Vorrichtung zum Verlegen und bzw. oder Aufnehmen der Querschwellen eines Gleises
AT351069B (de) * 1977-09-02 1979-07-10 Plasser Bahnbaumasch Franz Fahrbare einrichtung zum kontinuierlichen aus- wechseln bzw. erneuern eines aus schienen und schwellen bestehenden gleises
AT359537B (de) * 1978-09-14 1980-11-10 Plasser Bahnbaumasch Franz Gleisumbauzug mit portalfahrzeugen fuer schwellentransport
JPS557481A (en) * 1978-12-18 1980-01-19 Taigaasu Polymer Kk Production device for steel wire-reinforced resin hose
AT363116B (de) * 1979-01-22 1981-07-10 Plasser Bahnbaumasch Franz Selbstfahrbare gleisbett-reinigungsmaschine mit hebevorrichtung
JPS557482A (en) * 1979-03-24 1980-01-19 Onda Tekkosho Jugen Tenoning machine
CH646480A5 (fr) * 1982-03-12 1984-11-30 Canron Inc Crissier Train de pose d'une nouvelle voie ferree.

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1540376A (fr) * 1967-04-20 1968-09-27 Perfectionnement aux machines de réfection des voies ferrées
CH600046A5 (de) * 1977-04-22 1978-06-15 Matisa Materiel Ind Sa
GB2016562A (en) * 1978-03-15 1979-09-26 Canron Inc Renewing railway track
EP0019984A1 (de) * 1978-04-19 1980-12-10 Les Fils D'auguste Scheuchzer S.A. Zug zum Erneuern eines Eisenbahngleises
GB2023207A (en) * 1978-06-14 1979-12-28 Plasser Bahnbaumasch Franz Travelling rallway sleeper-laying machine
US4363274A (en) * 1978-10-13 1982-12-14 Canron Corporation Center line follower

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0294700A2 (de) * 1987-06-08 1988-12-14 Enrico Valditerra Schienenfahrzeuge zur Erneuerung von Schienenwegen
EP0294700A3 (en) * 1987-06-08 1989-05-31 Enrico Dr.Ing. Valditerra Railcar for renovating railways
AU601286B2 (en) * 1987-06-08 1990-09-06 Harsco Corporation Railcar for renovating railways
GB2207165A (en) * 1987-07-23 1989-01-25 Plasser Bahnbaumasch Franz A railway sleeper changing machine
GB2207165B (en) * 1987-07-23 1991-08-14 Plasser Bahnbaumasch Franz A sleeper changing machine
EP0388573A1 (de) * 1989-03-20 1990-09-26 Scheuchzer S.A. Gelenkzug zum Erneuern von Eisenbahnen
FR2759101A1 (fr) * 1997-01-31 1998-08-07 Desquenne & Giral Procede, dispositif et engin pour remplacer des traverses usagees
US7895950B2 (en) 2004-08-20 2011-03-01 Loram Maintenance Of Way, Inc. Long rail pick-up and delivery system
US8211184B2 (en) 2009-04-20 2012-07-03 Michael D. Ries Acetabular cup
US8574306B2 (en) 2009-04-20 2013-11-05 Michael D. Ries Acetabular cup

Also Published As

Publication number Publication date
DE3575749D1 (de) 1990-03-08
IT8467700A1 (it) 1986-01-10
CA1290619C (en) 1991-10-15
IT1179729B (it) 1987-09-16
IT8467700A0 (it) 1984-07-10
EP0168103A3 (en) 1987-01-21
US4867068A (en) 1989-09-19
ATE50008T1 (de) 1990-02-15
EP0168103B1 (de) 1990-01-31
JPS6168902A (ja) 1986-04-09

Similar Documents

Publication Publication Date Title
EP0168103B1 (de) Wagengruppe zum Auswechseln von Gleisen
EP0004985B1 (de) Zug zum Erneuern eines Eisenbahngleises
US4211170A (en) Mobile apparatus for the continuous replacement of an old track by a new track
EP0431092B1 (de) Verfahren zum kontinuierlichen Verschweissen von Schienensträngen und Zugfahrzeug für dessen Durchführung
US4000699A (en) Apparatus for replacement of rail tracks
FR2618466A1 (fr) Machine d'echange de traverses
HU209000B (en) Method and machine arrangement for renewing track
EP0355240A1 (de) Zug zur Erneuerung eines Eisenbahngleises
EP0168101B1 (de) Mit Mitteln zum Abstützen und Führen beim Vorrücken versehene Eisenbahnwagengarnitur für die Erneuerung von Eisenbahngleisen
US4261264A (en) Mobile track tie transport apparatus with traveling gantry
EP3892776A1 (de) Mechanismus zum hin- und herbewegen von schwellenstapeln und schienenfahrzeug, das einen solchen mechanismus umfasst
FR2666102A1 (fr) Machine pour le remplacement des traverses d'une voie ferree.
FR2667883A1 (fr) Machine de ramassage de selles nervurees d'une voie ferree.
SK336692A3 (en) Device for production of protected layer of plain and method of maintenance of plain
EP0146164A1 (de) Verfahren zum Erneuern von Gleisweichen und Eisenbahnvorrichtung zu seiner Durchführung
FR2519924A1 (fr) Installation deplacable sur rails pour le transport de deblais
JPH0258601A (ja) 軌道走行型レール設置/撤去装置
EP0061227B1 (de) Auf dem Gleis fahrbare Schotterplaniermaschine
CH657649A5 (en) Railway site machine for the at least partial repair of a railway track portion
US4606274A (en) Travelling railroad tie removal machine
CH680865A5 (de)
EP0467001B1 (de) Zug zum Verlegen neuer Gleise und Verfahren zum Verlegen derselben mit einem solchen Zug
EP0775780B1 (de) Verfahren zur Erneuerung von Gleisanlagen
JPH0738322Y2 (ja) 鉄道軌道更新用鉄道組列車
EP3892775A1 (de) Waggon für die verlegung von schwellen und entsprechendes schienenfahrzeug

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Designated state(s): AT BE CH DE FR GB LI SE

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AT BE CH DE FR GB LI SE

17P Request for examination filed

Effective date: 19870704

17Q First examination report despatched

Effective date: 19880705

DIN1 Information on inventor provided before grant (deleted)
RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: VALDITERRA S.P.A.

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH DE FR GB LI SE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Effective date: 19900131

REF Corresponds to:

Ref document number: 50008

Country of ref document: AT

Date of ref document: 19900215

Kind code of ref document: T

REF Corresponds to:

Ref document number: 3575749

Country of ref document: DE

Date of ref document: 19900308

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Effective date: 19900630

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

BERE Be: lapsed

Owner name: VALDITERRA S.P.A.

Effective date: 19900630

26N No opposition filed
REG Reference to a national code

Ref country code: CH

Ref legal event code: PUE

Owner name: VALDITERRA LAVORI FERROVIARI S.P.A. TRANSFER- HARS

Ref country code: CH

Ref legal event code: PFA

Free format text: VALDITERRA S.P.A. TRANSFER- VALDITERRA LAVORI FERROVIARI S.P.A.

REG Reference to a national code

Ref country code: FR

Ref legal event code: TP

REG Reference to a national code

Ref country code: GB

Ref legal event code: 732E

REG Reference to a national code

Ref country code: GB

Ref legal event code: 732E

REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20040623

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20040625

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20040628

Year of fee payment: 20

Ref country code: FR

Payment date: 20040628

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20040820

Year of fee payment: 20

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20050627

REG Reference to a national code

Ref country code: GB

Ref legal event code: PE20

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL