DE60025521T2 - METHOD FOR FORMING A CONTAINER - Google Patents

METHOD FOR FORMING A CONTAINER Download PDF

Info

Publication number
DE60025521T2
DE60025521T2 DE60025521T DE60025521T DE60025521T2 DE 60025521 T2 DE60025521 T2 DE 60025521T2 DE 60025521 T DE60025521 T DE 60025521T DE 60025521 T DE60025521 T DE 60025521T DE 60025521 T2 DE60025521 T2 DE 60025521T2
Authority
DE
Germany
Prior art keywords
concrete
joint
elements
tank
joints
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
DE60025521T
Other languages
German (de)
Other versions
DE60025521D1 (en
Inventor
Ulf Kumlin
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ABETONG TEKNIK AB
Original Assignee
ABETONG TEKNIK AB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from SE0000038A external-priority patent/SE522349C2/en
Application filed by ABETONG TEKNIK AB filed Critical ABETONG TEKNIK AB
Application granted granted Critical
Publication of DE60025521D1 publication Critical patent/DE60025521D1/en
Publication of DE60025521T2 publication Critical patent/DE60025521T2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/02Containers for fluids or gases; Supports therefor
    • E04H7/18Containers for fluids or gases; Supports therefor mainly of concrete, e.g. reinforced concrete, or other stone-like material
    • E04H7/20Prestressed constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Making Paper Articles (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Processing And Handling Of Plastics And Other Materials For Molding In General (AREA)
  • Blow-Moulding Or Thermoforming Of Plastics Or The Like (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Electrical Discharge Machining, Electrochemical Machining, And Combined Machining (AREA)

Abstract

Method for casting together a plurality of prestressed concrete elements (103) to a tank (100) with joints (1-19) between each respective concrete element (103) and pre-stress cables (43) guided through the concrete elements (103), where a first joint (1) starts to be filled and then, with a time delay, the subsequent respective joints (2, 3), etc., until all the joints (1-19) are filled. The joints are formed in such a way that joint concrete rises in a transcend hole positioned beside an embedded tube going through the concrete elements. Further, a tank comprising concrete elements prestressed both horizontally and vertically.

Description

Gebiet der ErfindungTerritory of invention

Die vorliegende Erfindung bezieht sich allgemein darauf, dass Betonelemente zusammengegossen werden, und insbesondere darauf, dass vorgespannte Betonelemente zusammen zu einem Tank gegossen werden.The The present invention relates generally to concrete elements be merged, and in particular that biased Concrete elements are poured together to a tank.

Hintergrund der Erfindungbackground the invention

Heutzutage besteht der Bedarf nach einem Tank, der leicht zusammenzusetzen ist. Es ist leichter und weniger arbeitsintensiv, Vorspannungsdrahtseile im Inneren von Betonelementen als äußerlich durch Löcher in Rippen zu führen, wobei mechanische Vorrichtungen, so genannte Durchschiebemaschinen verwendet werden. Außerdem besteht eine geringere Gefahr, dass die Vorspannungsdrahtseile reißen oder aufgrund von Sabotage durchgeschnitten werden, wenn die Vorspannungsdrahtseile innerhalb der Betonelemente und nicht außen an den Betonelementen verlaufen.nowadays There is a need for a tank that is easy to assemble is. It is lighter and less labor intensive, bias wire ropes in Interior of concrete elements as external through holes to lead in ribs, using mechanical devices, so-called push-through machines become. Furthermore There is less risk that the Vorspannungsdrahtseile rupture or be cut through due to sabotage when the prestressing wire ropes within the concrete elements and not on the outside of the concrete elements.

Vorgespannte Betonelemente für Tanks sind in der EP 0 514 583 (Parenti) und in BFT Nr. 4/89 "Concrete Precasting Plant and Technology" ("Betongießanlage und – Verfahren"), Seiten 90–93 von Josef Imkamp beschrieben. Ein kreisförmiger Tank, der Betonfertigteile aufweist, geht aus der DE 3335141 hervor.Prestressed concrete elements for tanks are in the EP 0 514 583 (Parenti) and in BFT No. 4/89 "Concrete Precasting Plant and Technology", pages 90-93 by Josef Imkamp described. A circular tank, which has precast concrete parts, goes out of the DE 3335141 out.

Vorgespannte Betonelemente werden normalerweise als ganze Teile hergestellt. Wenn diese letzteren zu einem Tank zusammen vergossen werden, der zum Beispiel eine Flüssigkeit ohne Leckage enthalten sollte, werden einerseits vorgespannte Drahtseile verwendet, um die Betonelemente zusammenzuhalten, und werden andererseits die Fugen zwischen den Betonelementen zusammengegossen. Die Vorspannungsdrahtseile, welche durch die Betonelemente verlaufen, werden durch eingebettete Rohre, z.B. Plastikrohre, geführt. Die Vorspannungsdrahtseile müssen gegen Korrosion geschützt werden, was unter anderem voraussetzt, dass sie keinen Kontakt mit der Luft haben sollten. Um die Vorspannungsdrahtseile gegen Korrosion zu schützen, werden sie mit einer Fett enthaltenden Kunststoffhülle versehen.Preloaded Concrete elements are usually made as whole parts. If these latter are shed to a tank together, the for example, a liquid Without leakage should be on the one hand prestressed wire ropes used to hold the concrete elements together, and on the other hand the joints are poured together between the concrete elements. The prestressing wire ropes, which pass through the concrete elements are defined by embedded tubes, e.g. Plastic pipes, guided. The prestressing wire ropes need protected against corrosion which, among other things, requires that they have no contact with should have air. To the prestressing wire ropes against corrosion to protect, They are provided with a grease-containing plastic wrap.

Die Fuge zwischen zwei Betonelementen muss so ausgebildet werden, dass sie mehrere Probleme löst. Weil der Tank aus geraden Betonelementen ausgebildet wird, besteht beim Führen der Vorspannungsdrahtseile um den Tank herum die Gefahr, dass sie in den Fugen hängen bleiben, wenn sie nicht geradewegs zum nächsten Rohreinlass geführt werden. Die Fugen zwischen den Betonelementen sind bei der Montage an sich nicht fest, was sie günstigerweise wären, da der in die Fugen zu vergießende Fugenbeton sehr flüssig ist. Wenn beim regelmäßigen Gießen der Fugen Probleme auftreten, ist es manchmal notwendig, jede Fuge einzeln neu zu vergießen. Von oben zu gießen und gleichzeitig die Luft zu beseitigen, welche den Guss schwächen könnte, ist kompliziert.The Fugue between two concrete elements must be designed so that she solves several problems. Because the tank is made of straight concrete elements, there is while guiding the prestressing wire ropes around the tank are in danger of being damaged to hang in the joints stay if they are not led straight to the next tube inlet. The joints between the concrete elements are in the assembly itself not sure what she favorably would, because the to be poured in the joints Joint concrete very liquid is. If the regular pouring of Fugitive problems occur, it is sometimes necessary to separate each joint individually to shed again. From to pour up and at the same time eliminating the air that could weaken the cast is complicated.

Zusammenfassung der ErfindungSummary the invention

Aufgabe der vorliegenden Erfindung ist es, einen widerstandsfähigen Tank herzustellen.task It is the object of the present invention to provide a durable tank manufacture.

Eine weitere Aufgabe der vorliegenden Erfindung besteht darin, einen Tank herzustellen, bei dem der Schutz gegen Korrosion und mechanische Beschädigung der Vorspannungsdrahtseile verbessert ist.A Another object of the present invention is to provide a Tank in which the protection against corrosion and mechanical damage the prestressing wire ropes is improved.

Noch eine weitere Aufgabe der vorliegenden Erfindung besteht darin, Betonelemente mit senkrechten Abschnitten herzustellen, die einen mechanischen Fugenguss von unten nach oben mittels einer Pumpe ermöglichen.Yet Another object of the present invention is to provide concrete elements to produce with vertical sections that have a mechanical Allow pouring from bottom to top by means of a pump.

Noch eine weitere Aufgabe der vorliegenden Erfindung besteht darin, einen Tank mit verbesserter struktureller Festigkeit herzustellen.Yet Another object of the present invention is to provide a To produce tank with improved structural strength.

Gemäß der vorliegenden Erfindung ist ein Tank mit den Merkmalen von Anspruch 4 sowie ein Betonelement für einen Tank gemäß den Merkmalen von Anspruch 1 vorgesehen.According to the present Invention is a tank with the features of claim 4 and a concrete element for one Tank according to the characteristics of Claim 1 provided.

Um die Vorspannungsdrahtseile ferner gegen Korrosion zu schützen, werden die die Vorspannungsdrahtseile führenden eingebetteten Rohre beim Gießen der Fugen ebenfalls mit Fugenbeton gefüllt.Around Furthermore, to protect the Vorspannungsdrahtseile against corrosion leading the bias wire ropes embedded pipes during casting the joints are also filled with joint concrete.

Um zu verhindern, dass sich Lufteinschlüsse bilden, wenn der Fugenbeton eingefüllt wird, wird ein Verfahren verwendet, bei dem mit dem Auffüllen einer ersten Fuge begonnen wird und nach einer Zeitverzögerung mit dem Befüllen der nächsten Fugen auf beiden Seiten der ersten Fuge begonnen wird. Nach einer weiteren Zeitverzögerung wird mit dem Befüllen der folgenden Fugen begonnen und so weiter, bis mit dem Befüllen aller Fugen begonnen wurde. Durch ein Vergießen der Fugen wird ein zusammenhängender Tank erhalten.Around To prevent air bubbles from forming when the joint concrete filled is a method is used in which with the filling of a first fugue is started and after a time delay with the filling the next Joints on both sides of the first joint is started. After a further time delay will be filled with the following joints started and so on, until with the filling of all joints was started. By casting the joints becomes a coherent Tank received.

Die zum Führen der Vorspannungsdrahtseile um den Tank herum innerhalb der Betonelemente verwendeten Kunststoffrohre haben an einem Ende eine trichterförmige Ausbildung, damit sie das Vorspannungsdrahtseil an diesem Ende besser aufnehmen können, wenn es um den Tank herumgeführt wird.The to lead used the Vorspannungsdrahtseile around the tank inside the concrete elements Plastic pipes have a funnel-shaped design at one end, so that they better absorb the prestressing wire rope at that end can, when it comes around the tank.

Vorzugsweise werden Abdichtungsvorrichtungen in die äußeren Teile der Fuge eingefügt, um den Fugenbeton daran zu hindern, beim Gießen auszulaufen.Preferably Sealing devices are inserted into the outer parts of the joint to the Prevent joint concrete from leaking when pouring.

Der Hohlraum bzw. das Durchgangsloch, das seitlich von den waagrechten Rohren und von der Spur der Vorspannungsdrahtseile angeordnet ist, dient teilweise zum Einleiten des Fugenbetons beim Gießen des Tanks und teilweise als ein Sicherheitskanal für ein manuelles Befüllen mit Fugenbeton, wenn beim gewöhnlichen Befüllen des Fugenbetons ein Problem auftritt.Of the Cavity or the through hole, the side of the horizontal Pipes and is arranged by the track of the Vorspannungsdrahtseile serves partly for introducing the joint concrete when pouring the tank and partly as a security channel for a manual filling with joint concrete, if in the ordinary fill the joint concrete is a problem.

Weitere Merkmale und Vorteile der vorliegenden Erfindung werden aus der folgenden Beschreibung ersichtlich.Further Features and advantages of the present invention will become apparent from the following description.

Kurze Beschreibung der ZeichnungenShort description the drawings

Die vorliegende Erfindung wird aus der nun folgenden detaillierten Beschreibung von Ausführungsformen anhand der beiliegenden Figuren deutlich, die lediglich zu Veranschaulichungszwecken und nicht zur Einschränkung der vorliegenden Erfindung dient. Es zeigt:The The present invention will become more apparent from the following detailed description of embodiments With reference to the accompanying figures clear, the only for illustrative purposes and not for limitation of the present invention. It shows:

1 einen Tank mit einer Pumpe zum Einfüllen des Fugenbetons; 1 a tank with a pump for filling the joint concrete;

2 einen Teil eines Rohrleitungssystems zum Einfüllen von Fugenbeton in einen Tank gemäß einer bevorzugten Ausführungsform; 2 a portion of a piping system for filling joint concrete in a tank according to a preferred embodiment;

3 einen Schwimmer zum Anzeigen, dass eine Fuge vollgefüllt ist; 3 a float to indicate that a joint is full;

4 einen Schnitt durch eine Fuge zwischen zwei Betonelementen; und 4 a section through a joint between two concrete elements; and

5 ein System zum Einfüllen von Fugenbeton in einen Tank gemäß einer weiteren Ausführungsform. 5 a system for filling joint concrete in a tank according to another embodiment.

Detaillierte Beschreibung von Ausführungsformendetailed Description of embodiments

In der folgenden Beschreibung sind zu Erläuterungszwecken und nicht als Einschränkung spezifische Einzelheiten, wie zum Beispiel bestimmte Verfahren und Anwendungen genannt, um zu einem gründlichen Verständnis der vorliegenden Erfindung zu führen. Einem Fachmann auf diesem Gebiet wird jedoch ersichtlich sein, dass die vorliegende Erfindung auch in anderen Ausführungsformen in die Praxis umgesetzt werden kann, die von diesen spezifischen Einzelheiten abweicht. In anderen Fällen wird auf eine detaillierte Beschreibung bekannter Verfahren und Vorrichtungen verzichtet, um die Beschreibung der vorliegenden Erfindung nicht mit unnötigen Einzelheiten zu belasten.In The following description is for explanatory purposes and not as restriction specific details, such as specific procedures and Applications called to a thorough understanding of the to lead present invention. However, one skilled in the art will recognize that the present invention in other embodiments in the practice can be implemented by these specific details differs. In other cases is based on a detailed description of known methods and Devices dispensed with the description of the present invention not with unnecessary details to charge.

Es folgt die Beschreibung der Erfindung durch veranschaulichende Beispiele anhand der Zeichnungen.It The description of the invention follows by way of illustrative examples based on the drawings.

Es folgt eine eingehendere Beschreibung einer bevorzugten Ausführungsform.It follows a more detailed description of a preferred embodiment.

Ein Tank 100, der neunzehn Betonelemente 103 aufweist, ist in 1 gezeigt. Außerdem sind eine Pumpe 101 und ein Rohrleitungssystem 102, das an jede Fuge 119 angeschlossen ist, gezeigt. Jedes Betonelement 103 weist mehrere eingebettete Rohre 42, Kunststoffrohre, auf, welche zum Führen von Vorspannungsdrahtseilen 43, z.B. Stahldrahtseilen, um den Tank 100 herum gedacht sind. Die Vorspannungsdrahtseile 43 werden dazu verwendet, die Betonelemente 103 zusammenzuhalten, wenn die Fugen 119 zusammengegossen werden. Damit eine gleichmäßige Befüllung mit Fugenbeton in allen Fugen 119 und allen eingebetteten Rohren 42 in einem Tank 100 ohne Lufteinschlüsse zu erreichen ist, wird ein Verfahren eingesetzt, bei dem das Befüllen mit Fugenbeton zuerst in der Fuge 1 begonnen wird. Nach einer Zeitverzögerung wird mit dem Befüllen der Fugen 2 und 3 begonnen, und dann nach einer weiteren Zeitverzögerung mit dem Befüllen der Fugen 4 und 5, und so weiter, bis mit dem Befüllen aller Fugen 119 mit Fugenbeton begonnen wurde. Der Fugenbeton wird unter Druck beginnend mit dem unteren Ende eingefüllt.A tank 100 , the nineteen concrete elements 103 is in 1 shown. There is also a pump 101 and a piping system 102 to every fugue 1 - 19 is connected, shown. Every concrete element 103 has several embedded tubes 42 , Plastic pipes, which for guiding bias wire ropes 43 , eg steel wire ropes, around the tank 100 are thought around. The prestressing wire ropes 43 are used to concrete elements 103 hold together when the joints 1 - 19 be poured together. So that a uniform filling with joint concrete in all joints 1 - 19 and all embedded pipes 42 in a tank 100 can be achieved without air pockets, a method is used, in which the filling with joint concrete first in the joint 1 is started. After a time delay is filled with the joints 2 and 3 started, and then after a further time delay with the filling of the joints 4 and 5 , and so on, until with the filling of all joints 1 - 19 started with joint concrete. The joint concrete is filled under pressure beginning with the lower end.

Eine Pumpe 101 und Rohrleitungen 102 zum Verteilen des Fugenbetons unter Druck werden in den Tank 100 eingesetzt. Ein System von Rohrleitungen, wobei 2 einen Teil des Rohrleitungssystems zeigt, zur Verteilung des Fugenbetons auf die verschiedenen Fugen 119 wird so zusammengesetzt, dass eine erste Rohrleitung von der Pumpe 101 zu einer Drei-Weg-Verzweigung 20 in der Nähe der Betonelemente 103 führt. Die beiden folgenden Rohrleitungen in der Drei-Weg-Verzweigung 20 führen weiter um die Innenseite der Betonelemente 103 herum. Bei jeder Fuge ist eine Drei-Weg-Verzweigung 20 angeordnet, die weiter an der Innenseite der Betonelemente entlang und in eine Düse in der Fuge führt. An jeder Fuge ist ein Ventil 21, z.B. ein Kugelventil oder ein Schieberventil, angeordnet, das als ein Verschlussventil 21 für jede entsprechende Fuge dient. Außerdem sind noch Ventile 22 gezeigt, wie zum Beispiel Kugelventile, die im Rohrleitungssystem 102 zwischen den entsprechenden Fugen 119 angeordnet sind und zur Zeitverzögerung des Starts der Belieferung mit Fugenbeton der unterschiedlichen Fugen 119 verwendet werden.A pump 101 and piping 102 to distribute the joint concrete under pressure will be in the tank 100 used. A system of pipelines, where 2 shows a part of the piping system, to distribute the joint concrete on the various joints 1 - 19 is assembled so that a first pipe from the pump 101 to a three-way junction 20 near the concrete elements 103 leads. The two following pipelines in the three-way junction 20 continue around the inside of the concrete elements 103 around. Every fugue has a three-way branch 20 arranged further along the inside of the concrete elements and into a nozzle in the joint. There is a valve at each joint 21 For example, a ball valve or a spool valve arranged as a shut-off valve 21 for each corresponding joint. There are also valves 22 shown, such as ball valves, in the piping system 102 between the corresponding joints 1 - 19 are arranged and at the time delay of the start of delivery of joint concrete of different joints 1 - 19 be used.

Wenn die in 1 gezeigte Pumpe 101 gestartet wird und das Mischen des Fugenbetons beginnt, ist die Pumpe 101 vom Rohrleitungssystem 102 getrennt, sind alle Ventile 22 zwischen den entsprechenden Fugen 119 geschlossen und sind alle Rückschlagventile 21 geöffnet. Wenn der Fugenbeton in der Pumpe 101 eine akzeptable Qualität erreicht hat, wird die Pumpe 101 mit dem Rohrleitungssystem 102 verbunden und wird der Fugenbeton in das Rohrleitungssystem 102 hinausgedrückt. Zuerst kommt der Fugenbeton bei einer Drei-Weg-Verzweigung 20 an und, da die Ventile 21, 22 entsprechend eingestellt sind, wird zur ersten Fuge 1 geleitet. Der Fugenbeton wird über ein eingebettetes gebogenes Rohr in die jeweilige Fuge eingebracht. Das gebogene Rohr ist am unteren Ende der Betonelemente 103 eingebettet. Der Fugenbeton füllt die Fuge 1 und die Rohre 42, die zum Führen der Vorspannungsdrahtseile 43 zu den benachbarten Betonelementen verwendet werden, und wenn der Fugenbeton das obere Ende der Fuge 1 erreicht, so steigt ein in 3 gezeigter Schwimmer 34 auf, der anzeigt, dass die erste Fuge 1 gefüllt ist. Der Schwimmer 34 ist in einer oberen Abdichtung angeordnet und wird ferner dazu verwendet, ein Auslaufen von Fugenbeton zu verhindern.When the in 1 shown pump 101 is started and the mixing of the joint concrete begins, is the pump 101 from the piping system 102 disconnected, are all valves 22 between the corresponding joints 1 - 19 closed and are all check valves 21 open. When the joint concrete in the pump 101 has reached an acceptable quality, the pump will 101 with the piping system 102 connected and is the joint concrete in the pipeline system 102 forced out. First, the joint concrete comes in a three-way junction 20 on and, as the valves 21 . 22 are adjusted accordingly becomes the first joint 1 directed. The joint concrete is introduced into the respective joint via an embedded bent pipe. The bent pipe is at the bottom of the concrete elements 103 embedded. The joint concrete fills the joint 1 and the pipes 42 used to guide the prestressing wire ropes 43 be used to the adjacent concrete elements, and if the joint concrete the top of the joint 1 reached, so in 3 shown float 34 on, indicating that the first fugue 1 is filled. The swimmer 34 is disposed in an upper seal and is further used to prevent leakage of joint concrete.

Eine untere Abdichtung der Fugen wird erhalten, wenn um das untere Ende der Betonelemente ein Guss durchgeführt wird, ansonsten muss eine vorübergehende Abdichtung dadurch geschaffen werden, dass eine Abdichtungsvorrichtung eingeführt wird, die mit Keilen am unteren Ende der Fuge festgehalten wird.A bottom seal of the joints is obtained when around the lower end the concrete elements a casting is performed, otherwise one must temporary Seal be created by a sealing device is introduced which is held with wedges at the bottom of the joint.

Damit Luft im System austreten kann, sind in jeder Fuge um die Schwimmer herum Löcher vorgesehen. Wenn der Schwimmer 34 dadurch aufsteigt, dass Fugenbeton die Fuge 1 erreicht, dann dichtet ein Dichtungsring 33 auf dem Schwimmer 34 den oberen Teil der Fuge 1 ab und verhindert, dass Fugenbeton ausläuft. Wenn der Schwimmer 34 aufsteigt und den oberen Teil der Fuge 1 abdichtet, dann ist dies ein Anzeichen dafür, dass die Fuge 1 gefüllt ist. Der oberste Teil 35 des Schwimmers 34 könnte zum Beispiel eingefärbt sein, um klar kenntlich zu machen, wenn er sich nach oben bewegt.To allow air to escape through the system, holes are provided in each joint around the floats. When the swimmer 34 Rises through that joint concrete the joint 1 achieved, then seals a sealing ring 33 on the float 34 the upper part of the fugue 1 prevents and prevents joint concrete from leaking. When the swimmer 34 ascends and the upper part of the fugue 1 seals, then this is an indication that the fugue 1 is filled. The top part 35 of the swimmer 34 For example, it could be colored to make it clear when it moves up.

Der Luft im System sollte ebenfalls ermöglicht werden, aus jedem eingebetteten Rohr zu entweichen. Damit dies möglich ist, ist jedes eingebettete Rohr mit einem Entlüftungsrohr 105 an den Löchern versehen, wo die Vorspannungsdrahtseile in die Betonelemente eingeführt werden. Die Entlüftungsrohre 105 münden in das Innere des Tanks 100. Jedes Entlüftungsrohr 105 ist mit einem Verschlussventil, z.B. einem Kugelventil, versehen. Wenn der Fugenbeton durch ein Entlüftungsrohr 105 entweicht, dann zeigt dies an, dass das Rohr gefüllt ist, und das entsprechende Verschlussventil wird geschlossen.The air in the system should also be allowed to escape from any embedded pipe. For this to be possible, any embedded pipe is with a vent pipe 105 provided at the holes where the Vorspannungsdrahtseile be introduced into the concrete elements. The vent pipes 105 flow into the interior of the tank 100 , Each vent pipe 105 is provided with a closing valve, eg a ball valve. When the joint concrete through a vent pipe 105 escapes, this indicates that the tube is filled and the corresponding closure valve is closed.

Ein alternatives Verfahren zum entweichen Lassen der Luft aus jedem eingebetteten Rohr ist das Verwenden von kleinen Löchern anstelle von Entlüftungsrohren. Aus einem kleinen Loch mit einem Durchmesser von ungefähr 3 mm entweicht Luft und Wasser aus den eingebetteten Rohren, während der Beton im Inneren bleibt.One alternative method to let the air out of each embedded pipe is using small holes instead of vent pipes. From a small hole with a diameter of about 3 mm Air and water escapes from the embedded pipes while the concrete is escaping stays inside.

Nach einer Zeitverzögerung von ein paar Minuten, nachdem mit dem Befüllen der ersten Fuge 1 begonnen wurde, werden die beiden Ventile 22 geöffnet, um den Fugenbeton weiter in die Fugen 2 und 3 einzulassen. Nach einer weiteren Zeitverzögerung von einigen Minuten werden die den Fugenbeton weiter in die Fugen 4 und 5 einlassenden Ventile geöffnet und so weiter. Hiermit wird fortgefahren, bis der Fugenbeton damit begonnen hat, alle Fugen 119 zu füllen. Wenn dann die Schwimmer 34 im oberen Teil der jeweiligen Fugen ansteigen und anzeigen, dass die jeweilige entsprechende Fuge gefüllt ist, wird das jeweilige Rückschlagventil 21 geschlossen. Das Schließen der Rückschlagventile 21 findet mit einer bestimmten Zeitverzögerung statt. Wenn angezeigt wurde, dass die Fugen 2 und 3 sowie auch die Fuge 1 gefüllt sind, dann wird das Rückschlagventil 21 an der Fuge 1 geschlossen. Hierdurch wird verhindert, dass der Fugenbeton zurücksackt. Wenn nun der nächste Schwimmer anzeigt, dass seine Fuge voll ist, dann wird das Rückschlagventil 21, das zur benachbarten Fuge gehört, deren Schwimmer schon vorher eine gefüllte Fuge angezeigt hat, geschlossen. Wenn schließlich alle Schwimmer anzeigen, dass ihre entsprechenden Fugen voll sind, werden schließlich alle Ventile 21, 22 geschlossen.After a delay of a few minutes, after filling the first joint 1 started, the two valves 22 Open the joint concrete further into the joints 2 and 3 involved. After a further time delay of a few minutes, the joint concrete will continue in the joints 4 and 5 opening valves open and so on. This continues until the joint concrete has begun to fill all the joints 1 - 19 to fill. If then the floats 34 in the upper part of the respective joints rise and indicate that the respective corresponding gap is filled, the respective check valve 21 closed. Closing the check valves 21 takes place with a certain time delay. If it was indicated that the joints 2 and 3 as well as the fugue 1 are filled, then the check valve 21 at the fugue 1 closed. This prevents the joint concrete from sagging backwards. Now when the next swimmer indicates that his joint is full, then the check valve 21 , which belongs to the adjacent fugue whose swimmer has previously indicated a filled gap, closed. Finally, when all swimmers indicate that their respective joints are full, eventually all the valves will become 21 . 22 closed.

Sollte beim vollständigen Gießen des Tanks 100 ein Problem auftreten, können die Fugen auch im Nachhinein gefüllt werden. Durch Herablassen eines Rohrs in das Durchgangsloch 41 und Einfüllen von Fugenbeton von oben von dem Punkt, an dem der unvollständige Guss endete, und durch Anheben des Einfüllrohrs mit dem steigenden Fugenbeton können Lufteinschlüsse vermieden werden.Should when completely pouring the tank 100 If there is a problem, the joints can also be filled in hindsight. By lowering a tube into the through hole 41 and filling of joint concrete from above from the point where the incomplete casting ended, and by raising the filler pipe with the rising joint concrete air inclusions can be avoided.

Hiernach wird das Rohrleitungssystem abgebaut und gereinigt, was bedeutet, dass es wiederverwendbar ist.hereafter the pipeline system is dismantled and cleaned, which means that it is reusable.

4 zeigt einen Schnitt durch eine Fuge zwischen zwei Betonelementen 103. Die Fuge ist so ausgelegt, dass Vorspannungsdrahtseile 43 sicher über die Fuge hinweggeführt werden können, wenn das Vorspannungsdrahtseil 43 um den Tank 100 herumgeführt wird. Das Rohr 42, welches das Vorspannungsdrahtseil 43 in der Richtung des Einsatzes aus der Fuge heraus und in das nachfolgende Betonelement des Vorspannungsdrahtseils 43 führt, hat einen Trichter, der das Vorspannungsdrahtseil 43 auffängt. Das Rohr 42, welches das Vorspannungsdrahtseil in die Fuge hineinführt, soll mit dem Rohr 42, welches das Vorspannungsdrahtseil aus der Fuge herausführt, ausgerichtet sein. Wenn bei der Herstellung eines Betonelements am Schluss ein Rohr etwas schief ist, dann ist der oben erwähnte Trichter besonders wichtig, da bei der Montage ein Vorspannungsdrahtseil dann nicht gerade in den Einlass des nächsten Rohrs geführt wird. 4 shows a section through a joint between two concrete elements 103 , The joint is designed so that prestressing wire ropes 43 safely over the joint can be carried away when the Vorspannungsdrahtseil 43 around the tank 100 is led around. The pipe 42 which is the bias wire rope 43 in the direction of the insert out of the joint and into the subsequent concrete element of the prestressing wire rope 43 leads, has a funnel, which is the bias wire rope 43 fields. The pipe 42 , which introduces the Vorspannungsdrahtseil in the joint, should with the pipe 42 Aligning the Vorspannungsdrahtseil out of the joint, be aligned. If in the production of a concrete element at the end of a pipe is slightly wrong, then the funnel mentioned above is special This is important because during assembly a biasing wire rope is not then fed straight into the inlet of the next tube.

Um zu verhindern, dass Fugenbeton beim Einfüllen des Fugenbetons ausläuft, sind in den äußeren Teilen der Fuge Abdichtungsvorrichtungen 40 angeordnet, z.B. vorkomprimierte Kompressionsbänder oder eine Abdichtungsverbindung, und sind am oberen und am unteren Ende der Fuge Abdichtungsplatten angebracht. Diese zusätzliche Abdichtungsvorrichtung 40 wird bevorzugt, da der Fugenbeton unter Druck eingebracht wird. Außerdem ist neben den Pfaden der Vorspannungsdrahtseile 43 auch ein Hohlraum (Durchgangsloch) 41 ausgebildet, damit der Fugenbeton im Fugenzwischenraum aufsteigen und auch die Rohre 42 mit Fugenbeton ausfüllen kann (jedes Betonelement hat mehrere Rohre 42, die je nach der Höhe des Betonelements auf unterschiedliche Ebenen verteilt sind). Die Anordnung des Durchgangslochs 41 neben dem Pfad des Vorspannungsdrahtseils ist wichtig, falls während des Gießens ein Problem auftritt. Damit das Gießen des Tanks 100 auf einfache Weise fortschreiten kann, auch wenn ein Teil des Fugenbetons schon in den Tank 100 gefüllt wurde, kann durch das Durchgangsloch 41 ein Rohr hinuntergelassen werden und Fugenbeton vom oberen Teil der Fuge aus eingefüllt werden, wobei der Fugenbeton jedoch immer noch von unten her aufgefüllt wird (wobei da fortgefahren wird, wo der Guss unterbrochen worden ist). Wenn das Durchgangsloch 41 am Vorspannungsdrahtseil angeordnet wäre, könnte man kein Rohr durch das Durchgangsloch hindurch herunterlassen.In order to prevent joint concrete from leaking when filling the joint concrete, sealing devices are provided in the outer parts of the joint 40 arranged, for example, precompressed compression bands or a sealing connection, and are attached to the upper and at the lower end of the joint sealing plates. This additional sealing device 40 is preferred because the joint concrete is introduced under pressure. Besides, besides the paths of the prestressing wire ropes 43 also a cavity (through hole) 41 designed so that the joint concrete rise in the joint gap and also the pipes 42 can fill with joint concrete (each concrete element has several pipes 42 , which are distributed on different levels depending on the height of the concrete element). The arrangement of the through hole 41 next to the path of the prestressing wire rope is important if there is a problem during casting. So that the pouring of the tank 100 can progress easily, even if a part of the joint concrete already in the tank 100 could be filled through the through hole 41 a pipe can be lowered and joint concrete poured from the top of the joint, but the joint concrete is still filled from below (which continues where the casting has been interrupted). When the through hole 41 placed on the Vorspannungsdrahtseil, one could not lower a pipe through the through hole.

Der Abstand zwischen den Betonelementen am Durchgangsloch 41 ist größer als der Abstand beim Vorspannungsdrahtseil 43, um die Menge Fugenbeton zu minimieren, die zum Gießen des Tanks notwendig ist. Das Durchgangsloch 41 hat vorzugsweise einen Durchmesser von ungefähr 40 mm, um von unten Fugenbeton aufzunehmen oder um das Wiederauffüllrohr von oben aufzunehmen. Der Abstand zwischen den Betonelementen an den Vorspannungsdrahtseilen ist vorzugsweise 10–15 mm, was außer einer Minimierung der Menge des Fugenbetons auch das Führen der Vorspannungsdrahtseile durch eine Fuge erleichtert. Außerdem hat die Fuge Steckaufnahmen zur Ermöglichung eines einfachen Einsetzens von Abdichtungsvorrichtungen 40 sowie vorstehende und entsprechende ausgenommene Teile, die miteinander in Eingriff kommen, welche die Betonelemente während der Montage in ihrer Position halten. Die vorstehenden und ausgenommenen Teile sind konvex bzw. konkav, und sie verringern die durch die Vorspannung auf die Betonelemente wirkende Belastung.The distance between the concrete elements at the through hole 41 is greater than the distance in the Vorspannungsdrahtseil 43 to minimize the amount of joint concrete needed to pour the tank. The through hole 41 preferably has a diameter of about 40 mm to receive joint cement from below or to receive the refilling tube from above. The distance between the concrete elements on the prestressing wire ropes is preferably 10-15 mm, which, in addition to minimizing the amount of joint concrete, also facilitates guiding the prestressing wire ropes through a joint. In addition, the joint plug-in receptacles to allow easy insertion of sealing devices 40 and protruding and corresponding recessed parts which engage with each other to hold the concrete elements in position during assembly. The protruding and recessed parts are convex and concave, respectively, and they reduce the stress imposed on the concrete elements by the bias.

Der Schwimmer 34, der dazu verwendet wird, den Fugenbeton an einem Austreten aus dem oberen Ende der Fuge zu hindern, und dazu verwendet wird, eine aufgefüllte Fuge anzuzeigen, ist in 3 näher gezeigt. Der Schwimmer umfasst ein Kunststoffrohr mit einer Abdichtung 31 an der unteren Seite, die den Fugenbeton daran hindert, aus dem Rohr auszutreten, und stattdessen verursacht, dass das Rohr ansteigt, wenn der Fugenbeton in der Fuge nach oben steigt. Um das Rohr herum wird es der Luft erlaubt, auszutreten. Sie wird durch den eingegossenen Fugenbeton herausgedrückt. Außerdem weist das Rohr auch einen Dichtungsring 33 auf, der den die Luft auslassenden Zwischenraum abdichtet, so dass der Fugenbeton nicht austritt, wenn er das obere Ende der Fuge erreicht. Der Dichtungsring 33 wird durch einen Behälter 32 an Ort und Stelle gehalten. Wenn der Schwimmer 34 ansteigt, wird auch eine Flagge 35, d.h. das Ende des Rohrs, angehoben, die zum Beispiel eingefärbt sein kann und anzeigt, dass die Fuge gefüllt ist.The swimmer 34 which is used to prevent the joint concrete from escaping from the top of the joint, and is used to indicate a filled-in joint, is disclosed in U.S. Pat 3 shown closer. The float includes a plastic tube with a seal 31 on the lower side, which prevents the joint concrete from escaping from the pipe, and instead causes the pipe to rise as the joint concrete rises in the joint. Around the pipe, the air is allowed to escape. It is pushed out by the poured joint concrete. In addition, the tube also has a sealing ring 33 on, which seals the air leaking gap, so that the joint concrete does not escape when it reaches the top of the joint. The sealing ring 33 is through a container 32 kept in place. When the swimmer 34 goes up, also becomes a flag 35 that is, the end of the tube raised, which may be colored, for example, indicating that the gap is filled.

Eine weitere Ausführungsform wird nun im Einzelnen anhand von 5 beschrieben.Another embodiment will now be described in detail with reference to FIG 5 described.

Bei dieser Ausführungsform wird der Fugenbeton lediglich durch ein Einlassrohr 23 in die Betonelemente eingeführt. Dieses Rohr leitet den Fugenbeton vorzugsweise durch Fuge 1, die dem Betonelement mit den Entlüftungsrohren 105 gegenüberliegt. Bei dieser Ausführungsform wird ein zusätzliches dickes eingebettetes Rohr im untersten Teil der Betonelemente eingesetzt, um es dem Fugenbeton zu erlauben, sich gut auf alle Betonelemente zu verteilen. Nachdem das unterste Rohr gefüllt wurde, steigt der Fugenbeton in den Fugen 119 in der gleichen Weise an, wie das oben beschrieben wurde, ohne dass Ventile geöffnet zu werden brauchen. Diese Ausführungsform verwendet außer am einzigen Einlassrohr keine weiteren Zufuhrventile. Auf die gleiche Weise, wie oben beschrieben, werden Entlüftungsventile geschlossen, wenn die Fugen gefüllt sind.In this embodiment, the joint concrete is merely through an inlet pipe 23 introduced into the concrete elements. This pipe passes the joint concrete preferably through joint 1 that the concrete element with the ventilation pipes 105 opposite. In this embodiment, an additional thick embedded pipe is used in the lowermost part of the concrete elements to allow the joint concrete to spread well over all the concrete elements. After the bottom pipe has been filled, the joint concrete rises in the joints 1 - 19 in the same way as described above, without needing to open valves. This embodiment uses no other supply valves except for the single inlet tube. In the same way as described above, vent valves are closed when the joints are filled.

Unter der Verwendung dieses Verfahrens ist das einzige Rohrleitungssystem, das zum Verteilen des Fugenbetons auf die Fugen notwendig ist, dasjenige innerhalb der Betonelemente, und die Pumpe kann in beträchtlicher Nähe zur Fuge 1 angeordnet werden. Da nur ein Einlassrohr notwendig ist, kann dieses Rohr außerhalb des Tanks angeordnet werden, und es ist nicht notwendig, eine Pumpe in den Tank hineinzuheben, sondern sie kann von außerhalb des Tanks angeschlossen werden. Als eine Vorsichtsmaßnahme können zum Beispiel an den Fugen 12 und 13 zusätzliche Einlassrohre 24 angeordnet werden. Wenn die Pumpe außerhalb des Tanks angeordnet ist, können die Entlüftungsrohre auch aus dem Tank heraus gerichtet sein. Da das ganze System von einem Punkt zu befüllen ist, ist ein höherer Druck vonnöten, der an die Abdichtungsvorrichtungen höhere Ansprüche stellt. Um den nach rückwärts wirkenden Druck im System zu verringern, ist es möglich, in den Fugen 119 zwischen unterschiedlichen Niveaus Rückschlagventile zu verwenden, z.B. wo die die Vorspannungsdrahtseile führenden Rohre verteilt sind.Using this method, the only piping system necessary to distribute the joint concrete to the joints is that within the concrete elements, and the pump can be in substantial proximity to the joint 1 to be ordered. Since only one inlet tube is necessary, this tube can be located outside the tank and it is not necessary to lift a pump into the tank but it can be connected from outside the tank. As a precaution, for example, at the joints 12 and 13 additional inlet pipes 24 to be ordered. If the pump is located outside the tank, the vent pipes may also be directed out of the tank. Since the entire system is to be filled from one point, a higher pressure is needed, which places greater demands on the sealing devices. To the backwards To reduce acting pressure in the system, it is possible in the joints 1 - 19 to use check valves between different levels, eg where the tubes carrying the prestressing wire ropes are distributed.

Ein Rückschlagventil kann zum Beispiel einfach ein waagrechter Deckel sein, der an einem Ende gelenkig gelagert ist und von der waagrechten Ebene an seinem anderen Ende nach oben beweglich ist, und auch eine Anschlagvorrichtung aufweist, die den beweglichen Teil daran hindert, sich von der waagrechten Ebene nach unten zu bewegen. Der von der Pumpe ausgeübte Druck hebt den Deckel nach oben an, und wenn der Druck von oben größer sein sollte, fällt der Deckel zurück und hindert den Fugenbeton daran, in das System zurückzufließen.One check valve For example, it can simply be a horizontal lid attached to a End is hinged and from the horizontal plane at his other end is movable upwards, and also a stop device that prevents the moving part from moving horizontally Level to move down. The pressure exerted by the pump raises the lid up and when the pressure from above is greater should, falls the lid back and prevents the joint concrete from flowing back into the system.

Bei einer weiteren nicht gezeigten Ausführungsform ist das Rohrleitungssystem so aufgebaut, dass es von einer einzigen Person innerhalb des Tanks bedient werden könnte. Nach der Pumpe ist eine Drei-Weg-Verzweigung angeordnet, und an jeder weiteren Verzweigung ist eine weitere Drei-Weg-Verzweigung angeordnet. Jede weitere Verzweigung hat Ventile, z.B. Kugelventile, die zum Steuern des Flusses des Fugenbetons zu jeder einzelnen Fuge verwendet werden. Das Einfüllen von Fugenbeton erfolgt so, wie es auch für die oben erwähnte Ausführungsform beschrieben wurde, jedoch mit dem Unterschied, dass das Stoppen des Flusses nun mit demselben Ventil erfolgen kann, das den Fluss des Fugenbetons ermöglichte. Die Rückschlagventile werden geschlossen, nachdem der gesamte Gießvorgang abgeschlossen ist und alle Fugen mit dem Fugenbeton gefüllt sind.at another embodiment, not shown, is the piping system designed to be of a single person inside the tank could be served. After the pump, a three-way junction is arranged, and on each further branch is another three-way branch arranged. Each further branch has valves, e.g. Ball Valves, to control the flow of joint concrete to each joint be used. The filling Fugenbeton done as well as for the above-mentioned embodiment was described, but with the difference that stopping the river can now be done with the same valve that controls the flow of joint concrete allowed. The check valves are closed after the entire casting process is completed and all joints are filled with joint concrete.

Systeme der oben erwähnten Art können natürlich auch ganz leicht automatisiert werden. Statt dass eine Flagge mechanisch angehoben wird, wenn eine Fuge gefüllt ist, könnte auch ein Sensor ein Signal, z.B. einen elektrischen Impuls, an eine Steuerungseinheit ausgeben, die dann die Ventile weiter steuert, um nach einer geeigneten Zeitverzögerung ein weiteres Einfüllen von Fugenbeton zu stoppen. Dieselbe Steuerungseinheit könnte dann auch die Pumpe und die Ventile zum Öffnen sowie zum Schließen steuern.systems the above mentioned Kind of can Naturally also be easily automated. Instead of having a flag mechanical is raised, if a gap is filled, a sensor could also signal, e.g. output an electrical pulse to a control unit, which then further controls the valves to turn on after a suitable time delay further filling to stop from joint concrete. The same control unit could then also control the pump and valves for opening and closing.

Bei einer bevorzugten Ausführungsform sind die Betonelemente des Tanks sowohl senkrecht als auch waagrecht vorgespannt. Senkrecht vorgespannte Betonelemente werden durch Einformen von Vorspannungsdrahtseilen in die Betonelemente während der Herstellung erhalten. Waagrecht vorgespannte Betonelemente werden wie oben beschrieben hergestellt. Durch das Vorspannen der Betonelemente sowohl in der waagrechten als auch in der senkrechten Richtung wird eine erheblich verbesserte strukturelle Festigkeit erzielt. Elemente für höhere Tanks, d.h. bei ihrem Guss längere Elemente, sind bei ihrer Handhabung robuster. Derartige senkrecht vorgespannten Elemente sind gegenüber Gradientenkräften, wie zum Beispiel Temperaturunterschieden oder waagrechter Vorspannung, weniger empfindlich. Außerdem sind die senkrechten Vorspannungsdrahtseile in die Betonelemente eingebettet, während die waagrechten Vorspannungsdrahtseile an einem der Betonelemente verankert sind.at a preferred embodiment The concrete elements of the tank are both vertical and horizontal biased. Vertically prestressed concrete elements are formed by molding Prestressed wire ropes in the concrete elements during manufacture. Horizontal prestressed concrete elements are as described above produced. By preloading the concrete elements both in the horizontal as well as in the vertical direction becomes a significant improved structural strength achieved. Elements for higher tanks, i.e. longer in their casting Elements are more robust in their handling. Such vertically biased Elements are opposite gradient forces, such as temperature differences or horizontal preload, less sensitive. Furthermore are the vertical prestressing wire ropes in the concrete elements embedded while the horizontal prestressing wire ropes on one of the concrete elements are anchored.

Es ist offensichtlich, dass die vorliegende Erfindung auf vielfältige Weise variiert werden kann. Derartige Variationen sollen nicht als eine Abweichung vom Umfang der vorliegenden Erfindung betrachtet werden. Alle derartigen Variationen, die für einen Fachmann auf diesem Gebiet ersichtlich sind, sollen in den Umfang der in den Ansprüchen definierten vorliegenden Erfindung fallen.It It is obvious that the present invention has many uses can be varied. Such variations should not be considered one Deviation from the scope of the present invention. All such variations, for a person skilled in this Area are to be understood, within the scope of defined in the claims present invention.

Claims (4)

Betonelement (103) für einen Tank (100), wobei das Element eingebettete waagrechte Rohre (42) aufweist, die zum Aufnehmen von Vorspannungskabeln (43) angeordnet sind, wobei das Element so ausgebildet ist, dass bei einer Anordnung von zwei Elementen nebeneinander ein Fugenzwischenraum zum Zusammengießen der beiden Elemente zwischen ihnen definiert ist, dadurch gekennzeichnet, dass der Fugenzwischenraum einen Hohlraum (41) neben den waagrechten Rohren (42) aufweist, um einen Fugenbeton ansteigen zu lassen und ein Einfüllrohr nach unten einzuführen, wobei im Fugenzwischenraum der Abstand zwischen den beiden Betonelementen am Hohlraum größer als an den waagrechten Rohren (42) ist.Concrete element ( 103 ) for a tank ( 100 ), where the element embedded horizontal tubes ( 42 ) for receiving bias cables ( 43 are arranged, wherein the element is formed so that in an arrangement of two elements side by side, a joint gap for the casting together of the two elements is defined between them, characterized in that the joint gap a cavity ( 41 ) next to the horizontal pipes ( 42 ) to allow a joint concrete to rise and introduce a filler pipe down, wherein in the joint gap, the distance between the two concrete elements on the cavity larger than on the horizontal tubes ( 42 ). Betonelement nach Anspruch 1, wobei Abdichtungsvorrichtungen (40), vorzugsweise vorkomprimierte Kompressionsbänder, an den äußeren Teilen des Fugenzwischenraums angeordnet sind.Concrete element according to claim 1, wherein sealing devices ( 40 ), preferably precompressed compression bands, are disposed on the outer parts of the joint space. Betonelement nach Anspruch 1 oder Anspruch 2, wobei eine Seite des Elements eine Vertiefung und eine gegenüberliegende Seite einen vorstehenden Teil aufweist, wobei die Seiten so ausgebildet sind, dass beim Anordnen von zwei Elementen nebeneinander der vorstehende Teil des einen der Elemente mit der Vertiefung des anderen Elements in Eingriff kommt.Concrete element according to claim 1 or claim 2, wherein one side of the element has a depression and an opposite one Side has a protruding part, wherein the sides are formed are that when arranging two elements side by side the above Part of one of the elements with the depression of the other element engages. Tank (100) mit mehreren Betonelementen (103) die zusammengegossen sind, wobei die Betonelemente senkrecht vorgespannt sind und waagrecht eingebettete Rohre (42) aufweisen, die waagrechte Vorspannungskabel (43) enthalten, wobei die eingebetteten Rohre und die Fugen zwischen den nebeneinander angeordneten Betonelementen mit Fugenbeton ausgefüllt sind, wobei der Tank dadurch gekennzeichnet ist, dass die Betonelemente so ausgebildet sind, dass jede der Fugen einen mit Beton gefüllten Fugenzwischenraum aufweist, der neben den die Vorspannungskabel (43) enthaltenden waagrechten Rohren einen Hohlraum (41) aufweist, in den der Fugenbeton gefüllt wurde, und in jedem mit Beton gefüllten Fugenzwischenraum der Abstand zwischen zwei nebeneinander angeordneten Betonelementen an dem Hohlraum größer als an den waagrechten Rohren ist.Tank ( 100 ) with several concrete elements ( 103 ) which are cast together, wherein the concrete elements are biased vertically and horizontally embedded tubes ( 42 ), the horizontal bias cables ( 43 ), wherein the embedded pipes and the joints between the adjacent concrete elements are filled with joint concrete, wherein the tank is characterized in that the concrete elements so out are formed, that each of the joints has a filled with concrete joint gap, in addition to the bias cable ( 43 ) containing a horizontal cavity ( 41 ), in which the joint concrete was filled, and in each filled with concrete joint gap, the distance between two juxtaposed concrete elements on the cavity is greater than on the horizontal tubes.
DE60025521T 2000-01-10 2000-11-10 METHOD FOR FORMING A CONTAINER Expired - Lifetime DE60025521T2 (en)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
SE0000038 2000-01-10
SE0000038A SE522349C2 (en) 2000-01-10 2000-01-10 Casting method for producing concrete tank involves filling joints between prestressed concrete elements predetermined time delay
SE0000686A SE0000686D0 (en) 2000-01-10 2000-03-02 Method and apparatus for molding containers and such containers
SE0000686 2000-03-02
PCT/SE2000/002207 WO2001051740A1 (en) 2000-01-10 2000-11-10 Casting of tank

Publications (2)

Publication Number Publication Date
DE60025521D1 DE60025521D1 (en) 2006-04-06
DE60025521T2 true DE60025521T2 (en) 2006-08-24

Family

ID=26654938

Family Applications (1)

Application Number Title Priority Date Filing Date
DE60025521T Expired - Lifetime DE60025521T2 (en) 2000-01-10 2000-11-10 METHOD FOR FORMING A CONTAINER

Country Status (10)

Country Link
EP (1) EP1246985B1 (en)
AT (1) ATE315701T1 (en)
AU (1) AU778554B2 (en)
DE (1) DE60025521T2 (en)
EE (1) EE04504B1 (en)
ES (1) ES2256061T3 (en)
PL (1) PL206445B1 (en)
PT (1) PT1246985E (en)
SE (1) SE0000686D0 (en)
WO (1) WO2001051740A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2007231C2 (en) * 2011-08-05 2013-02-06 Mecal B V A method of assembling a wall from prefabricated wall parts and a wall assembly.
JP6977927B2 (en) * 2016-11-28 2021-12-08 株式会社昇和産業 In-pipe excavator and in-pipe excavation method
CN113494180A (en) * 2020-03-18 2021-10-12 耐当科环境工程河北有限公司 Filter plate mold convenient to assemble and disassemble and filter plate manufacturing method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH658492A5 (en) * 1982-12-13 1986-11-14 Brun Ag Elementwerk CONTAINER MADE OF PRE-PREPARED CONCRETE ELEMENTS AND THEIR PRODUCTION.
IT1247587B (en) * 1990-04-18 1994-12-28 Giuseppe Parenti MANUFACTURES AND METHOD FOR THE CREATION OF CIRCULAR TANKS.
ATE134245T1 (en) * 1991-05-23 1996-02-15 Giuseppe Parenti ABOVE GROUND ROUND POOLS

Also Published As

Publication number Publication date
PL356330A1 (en) 2004-06-28
EE04504B1 (en) 2005-06-15
AU778554B2 (en) 2004-12-09
DE60025521D1 (en) 2006-04-06
AU1428401A (en) 2001-07-24
PL206445B1 (en) 2010-08-31
ATE315701T1 (en) 2006-02-15
WO2001051740A1 (en) 2001-07-19
SE0000686D0 (en) 2000-03-02
EE200200388A (en) 2003-10-15
EP1246985B1 (en) 2006-01-11
EP1246985A1 (en) 2002-10-09
ES2256061T3 (en) 2006-07-16
PT1246985E (en) 2006-05-31

Similar Documents

Publication Publication Date Title
DE102008010660B3 (en) Construction of a wind turbine
DE2040997C3 (en) Leak protection device on pipeline systems for the transport of hydrocarbons
DE2365950C2 (en) Potting process for an offshore construction
DE60025521T2 (en) METHOD FOR FORMING A CONTAINER
DE1653766B1 (en) Device for connecting and releasing a pump in a well shaft
WO2019162102A1 (en) Floating base for an off-shore system and off-shore system having a floating base
EP0052722B1 (en) Process and installation for separating a liquid waste product, such as manure or sewage, into a liquid phase and a solid phase
DE102010004356A1 (en) Plate-like foam-shower base element for use in house, has odor trap formed by vertical flow deflection and partially formed outside of drain bowl, and drain channel and drain line arranged on top of each other in level
DE3806759C2 (en) Method for renovating a hollow cylindrical building body and kit system therefor
DE3523747A1 (en) CONTAINER WITH A RING-SHAPED TERMINAL BUILT ON A FLOOR PANEL
DE3634906A1 (en) Precast concrete member and method of constructing a trench wall with the use of the precast concrete member
DE3044022A1 (en) METHOD FOR PRODUCING SOLID FERTILIZER BY SEPARATING GUELL AND DEVICE FOR IMPLEMENTING THIS METHOD
DE2206104A1 (en) Concrete piles cast-in-place and methods of making them
EP2158368A2 (en) Formwork devices and method for producing monolithic concrete structures
WO2019238678A1 (en) Flushable pressure vessel
DE29700069U1 (en) Planter
DE19746728C1 (en) Initiation of a casting process to produce an accurately dimensioned metal strip
CH653724A5 (en) METHOD FOR PRODUCING A BUILDING IN ANCHORED CONCRETE TUBE pile.
DE2653342A1 (en) METHOD FOR PREVENTING LEAK DAMAGE FROM SUB-GROUND CONTAINERS, IN PARTICULAR OIL CONTAINERS
DE1805381B2 (en) PRE-FABRICATED REINFORCED CONCRETE CABLE SHELL
DE3119404C2 (en)
DE3437607C2 (en)
DE102015011481A1 (en) Plastic container with at least one hollow body
AT379370B (en) METHOD AND DEVICE FOR PRODUCING SOLID FERTILIZERS BY SEPARATING GUELL IN A SOLID AND LIQUID PHASE
DD281848A5 (en) METHOD FOR REPAIRING CONSTRUCTION CONSTRUCTIONS

Legal Events

Date Code Title Description
8364 No opposition during term of opposition