DE19931231A1 - Structured module for the construction of a cellar/basement has prefabricated upper and lower blocks of reinforced concrete to be fitted together with a seal between them - Google Patents
Structured module for the construction of a cellar/basement has prefabricated upper and lower blocks of reinforced concrete to be fitted together with a seal between themInfo
- Publication number
- DE19931231A1 DE19931231A1 DE1999131231 DE19931231A DE19931231A1 DE 19931231 A1 DE19931231 A1 DE 19931231A1 DE 1999131231 DE1999131231 DE 1999131231 DE 19931231 A DE19931231 A DE 19931231A DE 19931231 A1 DE19931231 A1 DE 19931231A1
- Authority
- DE
- Germany
- Prior art keywords
- basement
- structural block
- block
- blocks
- surrounding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/161—Handling units comprising at least considerable parts of two sides of a room or like enclosed space
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/22—Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0007—Base structures; Cellars
- E04B1/0015—Cellars constructed from prefabricated units
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/348—Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
- E04B1/34815—Elements not integrated in a skeleton
- E04B1/34823—Elements not integrated in a skeleton the supporting structure consisting of concrete
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
Die vorliegende Erfindung bezieht sich auf Blöcke aus Stahlbeton zum Bau eines Fundaments bzw. eines Unterbaus oder Keller- bzw. Unterge schosses, welcher(s) als ein bewohnbarer Raum oder ein Lager- bzw. Speicher raum verwendet werden kann, als auch auf Verfahren zur Herstellung, zum Transport und zur Installation vor Ort von Blöcken aus Stahlbeton.The present invention relates to blocks made of reinforced concrete for Construction of a foundation or a substructure or a basement or base schosses, which (s) as a habitable space or a storage or storage space can be used, as well as on manufacturing processes to Transport and installation on site of blocks made of reinforced concrete.
In jüngsten Jahren entstand eine wachsende Tendenz, Untergeschoß- bzw. Kellerräume in gewöhnlichen Häusern einzubauen, um beschränkte Bauplätze effizient zu nützen. Ein bekanntes Verfahren für eine Keller- bzw. Untergeschoßkonstruktion vor Ort beinhaltet die Schritte eines Bauens von Formen bzw. Verschalungen, in welche Beton gegossen wird, eines Anordnens von Bewehrungsstäben in den Formen, eines Eingießens von Beton in die Formen und eines nachfolgenden Aushärten des Betons, wobei dies eine lange Zeitdauer erfordert. Das bekannte Verfahren einer Untergeschoß- bzw. Kellerkonstruktion ist, wie oben beschrieben, sehr kompliziert und erfordert nicht nur einen beträchtlichen Arbeitseinsatz und Kosten, sondern auch eine lange Fertigstellungszeit. Derartige Beschränkungen haben bis dato die Ver breitung von Untergeschoß- bzw. Kellerkonstruktionen verhindert.In recent years there has been a growing tendency to or to build basements in ordinary houses to restrict Use building sites efficiently. A known method for a basement or Local basement construction involves the steps of building Forms or casings in which concrete is poured, an arrangement of reinforcing bars in the molds, pouring concrete into the Forming and a subsequent hardening of the concrete, this being a long Time required. The known method of a basement or As described above, basement construction is very complicated and requires not only a considerable amount of work and costs, but also one long completion time. To date, such restrictions have Spread of basement or basement structures prevented.
Um das obengenannte Problem zu vermeiden, offenbaren beispielsweise die japanischen, nicht-geprüften Patentveröffentlichungen Nr. 3-76933, 8-92973 und 8-92974 sogenannte Einheitstyp-Untergeschoßstrukturen, welche in einer Fabrik in Massenproduktion hergestellt werden können. Gemäß der Offenbarung dieser Veröffentlichungen werden Untergeschoß- bzw. Keller geschoßblöcke aus Stahlbeton mit standardisierten Abmessungen zur Erleich terung des Transports und der Handhabung in einer Fabrik hergestellt. Diese Betonblöcke werden zu einem Bauplatz transportiert und nebeneinander ange ordnet und miteinander in einer bereits ausgehobenen Baugrube verbunden, um eine vollständige Kellergeschoß- bzw. Untergeschoßeinheit zu bilden. Da dieses Verfahren das Erfordernis für ein Einbringen bzw. Einfüllen von Beton vor Ort und die zugehörige Arbeit vermeidet, ist es möglich, Konstruktions kosten zu reduzieren und die Zeit für die Fertigstellung zu verkürzen.For example, to avoid the above problem, disclose Japanese Unexamined Patent Publications No. 3-76933, 8-92973 and 8-92974 so-called unit type basement structures, which in one Factory can be mass-produced. According to the Disclosure of these publications become basement or basement floor blocks made of reinforced concrete with standardized dimensions for ease Made in one factory for transportation and handling. This Concrete blocks are transported to a building site and placed next to each other arranges and interconnects in an already excavated pit, to form a complete basement or basement unit. There this method meets the requirement for pouring or pouring concrete on site and avoids the associated work, it is possible to construct reduce costs and shorten the time to complete.
In der Einheitstyp-Untergeschoßstruktur, welche in der japanischen, nicht-geprüften Patentveröffentlichung Nr. 3-76933 geoffenbart ist, wird jede Untergeschoßeinheit durch Verbinden einer Mehrzahl von vertikal geschnitte nen Betonblöcken gebildet. Ein großes Problem dieser Struktur ist eine Schwie rigkeit, ein Eindringen von Grundwasser durch vertikale Verbindungen zwischen benachbarten Betonblöcken zu vermeiden.In the unit type basement structure, which in the Japanese, Unexamined Patent Publication No. 3-76933, each Basement unit by connecting a plurality of vertical cuts NEN concrete blocks formed. A big problem with this structure is Schwie penetration of groundwater through vertical connections between to avoid neighboring concrete blocks.
Ein Zugang, welcher in der Struktur gemäß dieser Patentveröffentlichung zur Lösung dieses Problems verwendet wird, ist wie folgt. Jeder der schachtel- bzw. kastenartigen Betonblöcke wird mit Löchern ausgebildet, welche sich entlang ihrer vier Ecken für ein Hindurchführen von Drähten bzw. Kabeln erstreckt. Nach dem Anordnen der Betonblöcke nebeneinander mit zwischengeschalteten Abdichtelementen, werden Kabel bzw. Drähte durch die Löcher von einem äußersten Ende der Untergeschoßeinheit zu dem anderen hindurchgeführt und gespannt, um sicher die einzelnen Betonblöcke zu halten, wodurch ein Eindringen von Wasser durch die Verbindungen zwischen den benachbarten Betonblöcken vermieden wird.An approach which is in the structure according to this patent publication used to solve this problem is as follows. Each of the box or box-like concrete blocks is formed with holes, which are along its four corners for passing wires or cables through it extends. After placing the concrete blocks side by side with intermediate sealing elements, cables or wires through the Holes from one extreme end of the basement unit to the other passed through and tensioned to securely hold the individual concrete blocks, which prevents water from entering through the connections between the neighboring concrete blocks is avoided.
Ein Vorsehen von derartigen Löchern zum Einbringen der Kabel für das Verbinden der Vielzahl von Betonblöcken wird jedoch ein neues Problem von erhöhten Produktionskosten mit sich bringen. Darüberhinaus können sich die die Betonblöcke verbindenden Kabel dehnen oder über eine lange Zeitdauer korrodieren, wobei dies in einer Reduktion ihrer Haltekraft und gegebenenfalls einem Eindringen von Wasser durch Spalte, welche zwischen den einzelnen Betonblöcken gebildet werden, resultiert.Providing such holes for the insertion of the cables for the Joining the multitude of concrete blocks, however, becomes a new problem bring increased production costs with it. In addition, the stretch the cables connecting the concrete blocks or over a long period of time corrode, this in a reduction in their holding force and possibly penetration of water through gaps between the individual Concrete blocks are formed, results.
In den japanischen, nicht-geprüften Patentveröffentlichungen Nr. 8-92973 und 8-92974 ist jede Untergeschoßeinheit in kleinere Betonblöcke als jene, welche in der japanischen, nicht-geprüften Patentveröffentlichung Nr. 3-76933 geoffenbart sind, unterteilt. Während blockweise Verbindungen unter Verwendung von metallischen Verbindungsstücken, welche in den einzelnen Betonblöcken eingebettet sind (insbesondere in der Patentveröffentlichung Nr. 8-92973), anstelle der Kabel erzielt wird, zeigen diese Strukturen dasselbe Problem eines Eindringens von Grundwasser wie die Untergeschoßeinheit der japanischen, nicht-geprüften Patentveröffentlichung Nr. 3-76933.In Japanese Unexamined Patent Publication No. 8-92973 and 8-92974 is each basement unit in smaller concrete blocks than those described in Japanese Unexamined Patent Publication No. 3-76933 are divided. During block connections under Use of metallic connectors, which in the individual Concrete blocks are embedded (especially in patent publication no. 8-92973), instead of the cables being achieved, these structures show the same thing Problem of groundwater intrusion like the basement unit of the Japanese Unexamined Patent Publication No. 3-76933.
Weiters sind die Untergeschoßeinheitsstrukturen der japanischen, nicht- geprüften Patentveröffentlichungen Nr. 8-92973 und 8-92974 nachteilig bei der Bereitstellung einer verkürzten Konstruktionszeitdauer, da der Boden bzw. das Fundament der Untergeschoßeinheit unter Verwendung einer bekannten Baustellen-Anordnungs- bzw. -Aufbringungsmethode von Beton gebildet wird.Furthermore, the basement unit structures of the Japanese, non- examined patent publications Nos. 8-92973 and 8-92974 adversely by Provision of a shortened construction period because the floor or the Foundation of the basement unit using a known one Construction site arrangement or application method of concrete is formed.
Darüberhinaus sind die obengenannten Patentveröffentlichungen ledig lich auf die Konstruktion eines einzigen Untergeschoß- bzw. Kellerraumes ge richtet, ohne ein Konzept zur Herstellung von Untergeschoßräumen unter schiedlicher Formen zu offenbaren, welche möglicherweise durch Kombination von mehreren Untergeschoßeinheiten realisiert werden könnten. Die japa nische, nicht-geprüfte Patentveröffentlichung Nr. 4-44526 offenbart andererseits ein Konstruktionsverfahren zur Herstellung von mehreren Keller- bzw. Unter geschoßräumen durch Zusammenbau von vorgegossenen bzw. vorgebildeten Betonplatten vor Ort. Das Verfahren gemäß dieser Patentveröffentlichung erfordert jedoch ziemlich komplizierte Installationsarbeiten vor Ort bzw. auf der Baustelle, wobei dies es schwierig macht, die Konstruktions- bzw. Bauperiode zu verkürzen.In addition, the above patent publications are single Lich on the construction of a single basement or basement room teaches without a concept for the production of basement rooms to reveal different forms, which may be due to combination of several basement units could be realized. The Japan niche, unexamined patent publication No. 4-44526, on the other hand, discloses a design process for the production of several basement or sub storey spaces by assembling pre-cast or pre-formed Concrete slabs on site. The method according to this patent publication however, requires fairly complicated on-site or on-site installation work Construction site, which makes it difficult the construction or construction period To shorten.
Ein Ansatz zur Lösung des obigen Problems würde darin bestehen, mehrere Kellerräume durch Anordnen einer Vielzahl von Kellereinheiten zu er zeugen, welche bereits nebeneinander in einem Untergrundbereich verbunden sind. Dies würde jedoch ein neues Problem mit sich bringen, daß Regenwasser oder Grundwasser in das Innere der Untergeschoß- bzw. Kellerräume durch Verbindungen zwischen Türöffnungen der nebeneinander liegenden Keller geschoßeinheiten eindringen kann. Die nebeneinander liegenden Unterge schoßeinheiten könnten aneinander durch Vorsehen von Abdichtelementen zwischen benachbarten Untergeschoßeinheiten und Verbinden derselben mit Seilen oder unter Verwendung von Bolzen und Muttern oder Zugstangen gesichert werden, um Spalte zwischen diesen in einem Versuch, dieses Pro blem zu lösen, zu vermeiden. Selbst wenn derartige Maßnahmen getroffen werden, ist jedoch von Verbindungen zwischen benachbarten Unter geschoßeinheiten zu erwarten, daß sie sich lockern und daß Spalte zwischen diesen nach einer größeren Zeitdauer auftreten können, wobei dies gegebe nenfalls ein Eindringen von Wasser bewirken kann. Der obige Ansatz zu der Konstruktion von mehreren Kellerräumen unter Verwendung von bereits miteinander verbundenen Untergeschoßeinheiten ist daher von einem Langzeit- Gesichtspunkt nicht zufriedenstellend.One approach to solving the problem above would be several basement rooms by arranging a variety of basement units witness, which are already connected side by side in an underground area are. However, this would bring with it a new problem that rainwater or groundwater into the interior of the basement or basement Connections between door openings in the adjacent basement bullet units can penetrate. The side by side lap units could be against each other by providing sealing elements between adjacent basement units and connecting them with Ropes or using bolts and nuts or tie rods be saved to column between these in an attempt to pro this to solve problems, to avoid. Even if such measures are taken but is of connections between neighboring sub Missile units are expected to loosen and that gaps between this can occur after a longer period of time, this being the case can also cause water to penetrate. The above approach to that Construction of several basements using already interconnected basement units is therefore of a long-term Not satisfactory point of view.
Zur Lösung des obigen Problems hat der Anmelder der vorliegenden Er findung erfindungsgemäße Strukturblöcke zum Bauen einer Untergeschoß- bzw. Unterbau- oder Kellerstruktur wie folgt und erfindungsgemäße Verfahren zur Herstellung und zur Installation vor Ort der Untergeschoßstruktur entwickelt (japanische, nicht-geprüfte Patentveröffentlichung Nr. 9-96105). Der erfindungs gemäße Strukturblock ist derart ausgebildet, daß eine Untergeschoßeinheit durch Stapeln bzw. Anordnen von wenigstens einem oberen Strukturblock aus Stahlbeton, welcher lediglich umgebende Wände aufweist, auf der Oberseite eines unteren Strukturblocks aus Stahlbeton, welcher einen Bodenabschnitt und umgebende Wände aufweist und dieselbe Form wie der untere Strukturblock in der Draufsicht aufweist, so daß die obere Endoberfläche des unteren Strukturblocks und die untere Endoberfläche des oberen Strukturblocks in Kontakt miteinander gehalten werden, und wobei ein Abdichtelement zwischen den oberen und unteren Endoberflächen angeordnet wird. Derartige Strukturblöcke weisen einen Vorteil einer Verkürzung der Bau- bzw. Konstruk tionszeit für das Untergeschoß, während mit Sicherheit das Eindringen von Regenwasser und Grundwasser in das Untergeschoß vermieden wird, und einen Vorteil eines Verhinderns eines Eindringens von Regenwasser und Grundwasser in das Untergeschoß durch die Verbindungen zwischen Türöff nungen für den Fall auf, daß eine Vielzahl von Untergeschoß-Strukturblöcken miteinander verbunden sind. Dieser Ansatz ist wirkungsvoll bei der Lösung der entsprechenden, obengenannten Probleme.To solve the above problem, the applicant of the present Er structure blocks according to the invention for building a basement or substructure or cellar structure as follows and method according to the invention developed for the manufacture and installation on site of the basement structure (Japanese Unexamined Patent Publication No. 9-96105). The invention structure block is designed such that a basement unit by stacking or arranging at least one upper structural block Reinforced concrete, which only has surrounding walls, on the top a lower structural block made of reinforced concrete, which has a floor section and surrounding walls and has the same shape as the lower one Has structural block in plan view, so that the upper end surface of the lower structure block and the lower end surface of the upper structure block are kept in contact with each other, and being a sealing member is placed between the upper and lower end surfaces. Such Structural blocks have the advantage of shortening the construction time for the basement, while the penetration of Rainwater and groundwater in the basement is avoided, and an advantage of preventing rainwater from entering and Groundwater in the basement through the connections between the door opener on the case that a variety of basement structure blocks are interconnected. This approach is effective in solving the corresponding problems mentioned above.
Diese Untergeschoßstruktur umfaßt jedoch den mit einem Boden ausge bildeten, unteren Strukturblock und den oberen Strukturblock, welcher keine Decke aufweist und eine offene, obere Oberfläche aufweist, wenn er im Boden angeordnet wird. Demgemäß ist eine Arbeit vor Ort notwendig, um diese Öffnung zu schließen.However, this basement structure includes the one with a floor formed, lower structure block and the upper structure block, which none Ceiling and has an open top surface when in the floor is arranged. Accordingly, on-site work is necessary to do this Close opening.
Unter Berücksichtigung der obengenannten, im Stand der Technik be stehenden Probleme ist ein Ziel der vorliegenden Erfindung, eine Unterge schoß- bzw. Kellergeschoßstruktur, welche weiter eine Konstruktionszeit für ein Untergeschoß durch Reduktion der Anzahl von Arbeitsschritten auf der Baustelle verkürzen kann und sicherer das Eindringen von Regenwasser oder Grundwasser durch Verbindungen zwischen Türöffnungen für den Fall, daß eine Vielzahl von Untergeschoßstrukturen nebeneinander liegend verbunden werden, vermeiden kann, als auch Verfahren zur Herstellung, zum Transport und zur Installation vor Ort der Untergeschoß-Strukturblöcke zur Verfügung zu stellen.Taking into account the above, be in the prior art problems is an object of the present invention, a subs lap or basement structure, which further a construction time for a Basement by reducing the number of work steps on the Construction site can shorten and the penetration of rainwater or Groundwater through connections between door openings in the event that a large number of basement structures connected side by side can be avoided, as well as methods of manufacture, for transport and for installation on site of the basement structure blocks put.
Demgemäß ist ein erster Aspekt der Erfindung auf eine Untergeschoß- bzw. Kellergeschoßstruktur gerichtet, umfassend: einen unteren Strukturblock aus Stahlbeton mit einem Bodenabschnitt und umgebenden Wänden; und wenigstens einen oberen Strukturblock aus Stahlbeton mit umgebenden Wän den und einem Deckenabschnitt und derselben Form wie der untere Struk turblock in Draufsicht, wobei der obere Strukturblock auf der Oberseite des unteren Strukturblocks gestapelt bzw. angeordnet wird, wobei ein Abdichtele ment zwischen dem oberen Ende des unteren Strukturblocks und dem unteren Ende des oberen Strukturblocks angeordnet wird, wodurch eine Untergeschoß- bzw. Kellergeschoßeinheit gebildet wird, wobei das obere Ende des unteren Strukturblocks über seine Wanddicke abgestuft bzw. abgesetzt ist und das untere Ende des oberen Strukturblocks entsprechend über seine Wanddicke abgestuft bzw. abgesetzt ist, wodurch das obere Ende des unteren Struktur blocks mit dem unteren Ende des oberen Strukturblocks in Eingriff gelangt bzw. zusammenwirkt.Accordingly, a first aspect of the invention is directed to a basement or basement structure, comprising: a lower structural block made of reinforced concrete with a bottom section and surrounding walls; and at least one upper structural block made of reinforced concrete with surrounding walls and a section of ceiling and the same shape as the lower structure Turblock in plan view, with the upper structural block on the top of the lower structural blocks is stacked or arranged, with a sealing ment between the upper end of the lower structural block and the lower End of the upper structural block is arranged, whereby a basement or basement unit is formed, the upper end of the lower Structural blocks is stepped or stepped over its wall thickness and that lower end of the upper structural block corresponding to its wall thickness is graduated or offset, creating the upper end of the lower structure blocks engages with the lower end of the upper structural block or cooperates.
Darüberhinaus ist ein zweiter Aspekt der Erfindung auf ein Verfahren zur Herstellung einer Untergeschoßeinheit gerichtet, umfassend die Schritte eines Stapelns bzw. Aufstellens von wenigstens einem oberen Strukturblock aus Stahlbeton mit umgebenden Wänden und einem Deckenabschnitt auf der Ober seite eines unteren Strukturblocks aus Stahlbeton mit einem Bodenabschnitt und umgebenden Wänden und derselben Form wie der obere Strukturblock in Draufsicht, wobei ein Dichtelement zwischen dem oberen Ende des unteren Strukturblocks und dem unteren Ende des oberen Strukturblocks angeordnet wird. Furthermore, a second aspect of the invention is a method for Production of a basement unit directed, comprising the steps of a Stacking or setting up from at least one upper structural block Reinforced concrete with surrounding walls and a section of ceiling on the upper side of a lower structural block made of reinforced concrete with a floor section and surrounding walls and the same shape as the upper structural block in Top view, with a sealing element between the upper end of the lower Structure blocks and the lower end of the upper structure block arranged becomes.
Gemäß der obengenannten Untergeschoßstruktur und ihrem Herstel lungsverfahren ist jede Untergeschoßeinheit in getrennte Blöcke, beinhaltend einen unteren Strukturblock und wenigstens einen oberen Strukturblock aus Stahlbeton, unterteilt. Die Untergeschoßeinheit dieser Struktur kann in einer Fabrik hergestellt werden, selbst wenn es sich um eine Struktur mit großen Ab messungen handelt, wobei dies in einer beträchtlichen Reduktion von Kon struktionskosten vor Ort bzw. auf der Baustelle im Vergleich zu bekannten Untergeschoß-Konstruktionstechniken resultiert, in welchen die gesamte Untergeschoß- bzw. Kellerstruktur vor Ort hergestellt wird.According to the above basement structure and its manufacture Each basement unit is divided into separate blocks a lower structure block and at least one upper structure block Reinforced concrete, divided. The basement unit of this structure can be in one Factory manufactured even if it is a structure with large ab measurements, this results in a considerable reduction of Kon construction costs on site or at the construction site compared to known ones Basement construction techniques result in which the entire Basement or basement structure is produced on site.
Da weiters das Abdichtelement zwischen dem oberen Ende und dem unteren Ende der entsprechenden, getrennten Strukturblöcke angeordnet ist, dichtet dieses einen Verbindungsbereich zwischen den Strukturblöcken ab, wobei der obere Strukturblock auf der Oberseite des unteren Strukturblocks angeordnet bzw. aufgerichtet ist, wodurch das Eindringen von Grundwasser in das Untergeschoß bzw. den Keller vermieden wird.Since further the sealing element between the upper end and the the lower end of the corresponding, separate structural blocks is arranged, seals a connection area between the structure blocks, with the top structure block on top of the bottom structure block is arranged or erected, whereby the penetration of groundwater in the basement or the basement is avoided.
Im Fall einer bekannten Untergeschoßstruktur, welche entlang einer ver tikalen Ebene unterteilt ist, sind eine Vielzahl von Strukturblöcken durch Kabel oder dgl. gesichert bzw. festgelegt, um sicher das Dichtelement zu halten. Dies resultiert jedoch in erhöhten Konstruktionskosten und einem Nachteil, daß ein zuverlässiger Abdichteffekt aufgrund einer reduzierten Spannkraft, welche durch eine Dehnung und/oder Korrosion der Kabel bewirkt werden kann, nicht erhalten werden kann. Im Gegensatz dazu ist das Abdichtelement konstant durch das Gewicht des oberen Strukturblocks gemäß der vorliegenden Erfin dung gepreßt. Dies macht ein Anspannen der Kabel oder dgl. im Gegensatz zum Stand der Technik nicht notwendig, wobei dies zu einer Reduktion in den Konstruktionskosten beiträgt, und verhindert konstant und sicher das Ein dringen von Grundwasser in das Untergeschoß.In the case of a known basement structure, which runs along a ver tical level is divided into a variety of structural blocks by cables or the like. Secured or fixed to securely hold the sealing element. This however, results in increased construction costs and a disadvantage that a reliable sealing effect due to a reduced clamping force, which cannot be caused by stretching and / or corrosion of the cables can be obtained. In contrast, the sealing element is constant by the weight of the upper structural block according to the present invention manure pressed. This makes tensioning the cables or the like in contrast not necessary to the prior art, which leads to a reduction in the Construction costs contribute, and constantly and safely prevents the on penetrate from groundwater into the basement.
Da darüberhinaus die Untergeschoßstruktur bereits mit dem Deckenbe reich ausgebildet ist, wenn sie im Boden installiert wird, vermeidet dies das Erfordernis für eine derartige Arbeit vor Ort bzw. auf der Baustelle, wie die An ordnung von Trägern an dem oberen Ende des oberen Strukturblocks, um die obere Öffnung der Untergeschoßeinheit zu schließen, wodurch die Kosten für die Arbeit vor Ort reduziert werden.In addition, the basement structure already with the ceiling if it is installed in the ground, this avoids that Requirement for such work on site or on the construction site, such as the An order of beams at the top of the top structural block to support the to close the upper opening of the basement unit, reducing the cost of the work on site can be reduced.
Da weiters das obere Ende des unteren Strukturblocks und das untere Ende des oberen Strukturblocks mit abgestuften bzw. abgesetzten Bereichen ausgebildet sind, welche miteinander in Eingriff bringbar sind bzw. zusammen wirken, können die oberen und unteren Strukturblöcke sicher positioniert werden und es kann das horizontale Verschieben derselben wirkungsvoll ver hindert werden. Dadurch, daß die oberen und unteren abgestuften Abschnitte ein geringes Spiel in horizontaler Richtung aufweisen, können die abgestuften Bereiche mit einem erhöhten Freiheitsgrad miteinander in Eingriff gebracht werden. Dies erlaubt Abmessungsfehler der oberen und unteren Strukturblöcke und ermöglicht eine Feineinstellung in aufgebautem bzw. übereinander angeordnetem Zustand. Daher können die oberen und unteren Strukturblöcke leichter hergestellt werden und es wird die Konstruktion vor Ort für das Keller geschoß einfacher.Then there is the upper end of the lower structural block and the lower one End of the upper structure block with stepped or stepped areas are formed, which can be brought into engagement with one another or together the upper and lower structural blocks can be securely positioned and the horizontal shifting of the same can effectively ver be prevented. In that the upper and lower stepped sections have a slight play in the horizontal direction, the graded Areas with an increased degree of freedom engaged with each other become. This allows dimensional errors of the upper and lower structure blocks and enables fine adjustment in a built-up or on top of each other ordered state. Therefore, the top and bottom structure blocks be made easier and there will be construction on site for the basement bullet easier.
Vorzugsweise ist das Abdichtelement aus Gummi hergestellt. Da Gummi eine exzellente Flexibilität und Wasserabdichteigenschaft aufweist, kann, der Verbindungsbereich zwischen den oberen und unteren Strukturblöcken sicher wasserdicht gehalten werden.The sealing element is preferably made of rubber. Because rubber has excellent flexibility and waterproofing properties Connection area between the upper and lower structure blocks securely be kept waterproof.
Vorzugsweise ist eine Wasserabdichtbehandlung zusätzlich an einer oder beiden der inneren und äußeren Wandoberflächen der Untergeschoßein heit angewandt.A waterproofing treatment is preferably in addition to one or both of the inner and outer wall surfaces of the basement applied.
In dieser Untergeschoßstruktur kann das Eindringen von Grundwasser in das Untergeschoß durch die umgebenden Wände durch die Wasserabdichtbe handlung vermieden werden.In this basement structure, groundwater can enter the basement through the surrounding walls through the waterproofing action can be avoided.
Vorzugsweise sind die oberen und unteren Strukturblöcke aus Beton mit einer Druckfestigkeit von wenigstens 210 kgf/cm2 gebildet und es weisen der Bodenabschnitt des unteren Strukturblocks und die umgebenden Wände der unteren und oberen Strukturblöcke eine Dicke von wenigstens 150 mm auf.Preferably, the upper and lower structural blocks are made of concrete with a compressive strength of at least 210 kgf / cm 2 and the bottom portion of the lower structural block and the surrounding walls of the lower and upper structural blocks have a thickness of at least 150 mm.
In dieser Untergeschoßstruktur weist das Untergeschoß selbst eine ausreichend hohe Stärke bzw. Festigkeit auf, wenn dieses durch Installation der Untergeschoßeinheit im Boden installiert wird, und das obere Ende der Unter geschoßeinheit kann als ein Fundament für ein auf Bodenniveau zu bauendes Gebäude dienen.In this basement structure, the basement itself has one sufficiently high strength or firmness if this by installing the Basement unit is installed in the floor, and the upper end of the sub floor unit can be used as a foundation for a building to be built at ground level Serve buildings.
Vorzugsweise ist der Beton mit einem Wasserabdichtzusatz vermischt.The concrete is preferably mixed with a waterproofing additive.
Durch eine aus einem derartigen Beton hergestellte Untergeschoßstruktur kann das Eindringen von Wasser durch die umgebenden Wände verhindert werden. Vorzugsweise ist jeder der unteren und oberen Strukturblöcke 2,5 bis 3 m breit, 0,8 bis 1,6 m hoch und 2,5 bis 9 m lang.By a basement structure made of such a concrete can the penetration of water through the surrounding walls can be prevented. Preferably, each of the lower and upper structural blocks is 2.5 to 3 m wide, 0.8 to 1.6 m high and 2.5 to 9 m long.
Die Strukturblöcke, welche die obigen Abmessungen aufweisen, sind für eine Produktion, Förderung, Handhabung und Transport geeignet. Insbe sondere können sie auf öffentlichen Straßen unter Verwendung eines beson deren Kraftfahrzeuges transportiert werden, wenn die Untergeschoßstruktur von einer Fabrik zu einer Baustelle transportiert wird, wo das Untergeschoß kon struiert bzw. aufgebaut wird.The structural blocks having the above dimensions are for a production, promotion, handling and transport suitable. In particular in particular, they can be used on public roads using a special whose motor vehicle are transported if the basement structure of a factory is transported to a construction site, where the basement con is structured or built.
Vorzugsweise umfaßt der untere Strukturblock einen oberen Ausschnitt, welcher durch Ausschneiden eines Bereiches eines flachen Teils der umgebenden Wände von seinem oberen Ende gebildet ist, und es umfaßt der obere Strukturblock einen unteren Ausschnitt entsprechend dem oberen Aus schnitt, wobei die unteren und oberen Ausschnitte eine Öffnung bilden, wenn der obere Strukturblock auf der Oberseite des unteren Strukturblocks angeord net wird, wobei eine erste, umgebende Vertiefung bzw. Ausnehmung, welche ihren Boden zu der Außenseite der umgebenden Wände gerichtet aufweist, in der inneren Oberfläche der Öffnung ausgebildet ist, und eine zweite, um gebende Vertiefung bzw. Ausnehmung, welche ihren Boden zu der Außenseite der umgebenden Wände gerichtet aufweist, an der inneren Oberfläche der ersten, umgebenden Vertiefung ausgebildet ist.The lower structural block preferably comprises an upper cutout, which by cutting out an area of a flat part of the surrounding walls is formed by its upper end, and it includes the upper structure block a lower cutout corresponding to the upper Aus cut, with the lower and upper cutouts forming an opening when the upper structure block is arranged on the top of the lower structure block is net, wherein a first, surrounding recess or recess, which has its floor facing the outside of the surrounding walls, in the inner surface of the opening, and a second one to giving indentation or recess which its bottom to the outside of the surrounding walls facing the inner surface of the first, surrounding recess is formed.
Mit dieser Untergeschoßstruktur wird eine Türöffnung, welche einen Zutritt zwischen zwei Untergeschoßeinheiten zur Verfügung stellt, durch An ordnung der einen und der anderen Untergeschoßeinheiten nebeneinander derart erzielt, daß die Öffnungen zueinander gerichtet sind. An dieser Türöff nung ist eine schmale Nut durch die erste, umgebende bzw. umschließende Vertiefung der entsprechenden Untergeschoßeinheiten gebildet und es ist eine breite Nut durch die zweiten, umgebenden Vertiefungen derselben gebildet. Daher kann das Eindringen von Grundwasser in die Untergeschoßeinheiten durch die Öffnungen der entsprechenden Untergeschoßeinheiten durch Anbringen bzw. Aufbringen einer Vergußmasse, d. h. eines Vorgangs eines Ein bringens von Transportbeton bzw. Fertigbeton (beispielsweise wasserab weisendem Mörtel), in die breite Nut nach Einpassen des Dichtgliedes in die schmale Nut verhindert werden.With this basement structure, a door opening, which one Access between two basement units is provided by An Order of the one and the other basement units side by side achieved in such a way that the openings face each other. At this door opening is a narrow groove through the first, surrounding or enclosing Deepening of the corresponding basement units formed and it is a wide groove formed by the second, surrounding depressions thereof. Therefore, groundwater can enter the basement units through the openings of the corresponding basement units Applying or applying a potting compound, d. H. a process of an on bringing ready-mixed concrete or ready-mixed concrete (e.g. water pointing mortar) into the wide groove after fitting the sealing element into the narrow groove can be prevented.
Vorzugsweise sind Metallteile, welche einstückig mit Armierungsstäben bzw. Bewehrungsstäben, welche in den oberen und unteren Strukturblöcken angeordnet sind, auf dem unteren Ende des oberen Strukturblocks und dem oberen Ende des unteren Strukturblocks vorgesehen und es werden die Metallteile, welche zu den oberen und unteren Strukturblöcken gehören, mit einander verbunden, wenn der obere Strukturblock auf der Oberseite des unteren Strukturblocks angeordnet bzw. gestapelt ist.Metal parts, which are in one piece with reinforcing bars, are preferred or reinforcement bars, which are in the upper and lower structural blocks are arranged on the lower end of the upper structural block and the provided the upper end of the lower structural block and it will be the Metal parts, which belong to the upper and lower structural blocks, with connected to each other when the top structural block is on top of the lower structure blocks is arranged or stacked.
In der obigen Untergeschoßstruktur ist die Untergeschoßeinheit in eine einzelne bzw. einstückige Einheit durch Verbinden der Metallelemente des unteren Strukturblocks mit denjenigen des oberen Strukturblocks ausgebildet. In the above basement structure, the basement unit is in one single or one-piece unit by connecting the metal elements of the lower structure blocks formed with those of the upper structure block.
Demgemäß wird dieser Untergeschoßeinheit ermöglicht, einen höheren Scher widerstand und Biegewiderstand gegenüber einer in horizontaler Richtung wirkenden Kraft aufzuweisen, wobei dies sicher ein unerwünschtes Ereignis verhindert, bei welchem die oberen und unteren Strukturblöcke voneinander getrennt werden. Daher wird der obere Strukturblock nicht in horizontaler Richtung von dem unteren Strukturblock während eines Erdbebens verscho ben, wobei daraus resultiert, daß die Untergeschoßstruktur eine exzellente Erd bebensicherheit bzw. -widerstandsfähigkeit aufweist.Accordingly, this basement unit is enabled, a higher shear resistance and bending resistance to one in the horizontal direction have acting force, which is certainly an undesirable event prevents the upper and lower structural blocks from each other be separated. Therefore, the top structure block does not become horizontal Direction shifted from the lower structure block during an earthquake ben, with the result that the basement structure an excellent Erd quake safety or resistance.
Vorzugsweise ist in dem Verfahren gemäß dem zweiten Aspekt der Erfin dung der untere Strukturblock durch Anordnung von Bewehrungsstäben in einer ersten Form, deren Ausnehmung bzw. Hohlraum dieselbe dreidimensio nale Form wie der untere Strukturblock aufweist, und Einbringen von Liefer beton bzw. Fertigbeton in die erste Form hergestellt und es wird der obere Strukturblock durch Anordnen von Bewehrungsstäben in einer zweiten Form, deren Ausnehmung bzw. Hohlraum dieselbe dreidimensionale Form wie der obere Strukturblock aufweist, und Einbringen von Fertigbeton in die zweite Form hergestellt.Preferably in the method according to the second aspect of the invention the lower structural block by arranging reinforcing bars in a first shape, the recess or cavity of which is the same three-dimensional nale shape as the lower structural block, and introducing delivery Concrete or ready-mixed concrete is made in the first form and it becomes the upper one Structure block by arranging reinforcing bars in a second form, whose recess or cavity has the same three-dimensional shape as the has upper structural block, and placing ready-mixed concrete in the second Shape.
Gemäß diesem Verfahren werden die entsprechenden Bau- bzw. Struk turblöcke durch Gießen von Fertigbeton in die Formen hergestellt. Insbeson dere kann der untere Strukturblock leicht entfernt werden, da die Form ihren Boden nach oben gerichtet aufweist.According to this method, the corresponding construction or structure door blocks are made by pouring ready-mixed concrete into the molds. In particular The lower structural block can be easily removed because of the shape Bottom facing upwards.
Ein dritter Aspekt der Erfindung ist auf ein Verfahren zum Transport der unteren und oberen Strukturblöcke der Untergeschoßeinheit gemäß Anspruch 6 gerichtet, umfassend die Schritte: Drehen jedes Strukturblocks um 90°, so daß seine längere Seitenwand parallel zu einer horizontalen Ebene wird; Montage jedes Strukturblocks in einem Schutzgestell bzw. -aufbau; und Laden von jedem in einem Gestell montierten Strukturblock auf ein Fahrzeug gemeinsam mit einer Palette, welche derart angeordnet wird, daß ein Freiraum zwischen einer Ladeoberfläche derselben und der Straßenoberfläche 30 cm nicht übersteigt, während er auf dem Fahrzeug festgelegt ist.A third aspect of the invention is a method of transporting the lower and upper structural blocks of the basement unit according to claim 6 directed, comprising the steps: Rotate each structural block by 90 ° so that its longer side wall becomes parallel to a horizontal plane; Assembly each structural block in a protective frame or structure; and loading from common to each structural block mounted in a frame on one vehicle with a pallet, which is arranged such that a space between a loading surface of the same and the road surface 30 cm exceeds while fixed on the vehicle.
Entsprechend diesem Transportverfahren kann die Höhe und Breite der Last auf einem speziellen Transportfahrzeug innerhalb von Bereiche in Übereinstimmung mit Straßenverkehrsgesetzen und -bestimmungen durch Wenden des Strukturblocks um 90° fallen, so daß dieser auf seiner Seite liegt, woraus resultiert, daß die einzelnen Strukturblöcke auf öffentlichen Straßen befördert werden können. Darüberhinaus kann der Strukturblock vor einer Stoßbeanspruchung während des Transports durch Montage in einem Rahmen oder Gestell geschützt werden.According to this transportation method, the height and width of the Load on a special transport vehicle within areas in Compliance with road traffic laws and regulations Turn the structural block 90 ° so that it lies on its side, which results in the individual structural blocks on public roads can be promoted. In addition, the structure block can be in front of a Shock stress during transport by mounting in a frame or frame are protected.
Vorzugsweise umfaßt das Gestell eine Support- bzw. Abstützplatte zum Abstützen von jedem Strukturblock und einen Rahmen, welcher über jedem auf der Supportplatte angeordneten Strukturblock festgelegt ist, und der Rahmen kann fest mit der Supportplatte verbunden, während er über dem Strukturblock festgelegt ist.The frame preferably comprises a support plate for Support each structural block and a frame, which is placed over each the support plate arranged structure block is fixed, and the frame can be firmly attached to the support plate while it is over the structure block is set.
Mit einem derartigen Gestell kann der Strukturblock in dem Gestell durch Anordnen des Rahmens über dem Strukturblock nach Anordnen desselben auf der Supportplatte und nachfolgendem, festem Verbinden der Supportplatte und des Rahmens erhalten werden. Derart kann der Strukturblock leicht in dem Gestell montiert werden.With such a frame, the structural block can pass through the frame Arrange the frame over the structure block after arranging it the support plate and subsequent, firm connection of the support plate and of the frame. In this way, the structure block can easily be placed in the Frame can be mounted.
Vorzugsweise umfaßt das Transportverfahren weiters den Schritt eines Entladens des im Gestell bzw. Aufbau montierten Strukturblocks, wobei der Schritt des Endadens umfaßt: Anheben des Gestells, welches den Strukturblock hält, in eine geneigte Position unter Verwendung einer Hebe- bzw. Kran vorrichtung; Absenken des Gestells auf eine lastaufnehmende Vorrichtung, welche schwenkbar an einer horizontalen Welle zum Aufnehmen des Boden endes des Gestells abgestützt ist; und Legen des Gestells auf seine Seite durch Kippen bzw. Schwenken der lastaufnehmenden Vorrichtung um die hori zontale Welle.The transport method preferably further comprises the step of Unloading the structural block mounted in the frame or superstructure, the The end of step comprises: lifting the frame which is the structural block holds in an inclined position using a lifting or crane contraption; Lowering the frame onto a load-bearing device, which swivels on a horizontal shaft to pick up the floor end of the frame is supported; and placing the rack on its side by tilting or swiveling the load-bearing device around the hori zonal wave.
Gemäß diesem Verfahren wird ein Stoß, welcher auf das den Struktur block enthaltende Gestell während des Entladens einwirkt, durch die lastauf nehmende Vorrichtung gedämpft werden.According to this method, a shock is applied to the structure frame containing block acts during unloading, by the load taking device are damped.
Ein vierter Aspekt der Erfindung ist auf ein Verfahren zur Installation der Untergeschoßstruktur gemäß einem der Ansprüche 1 bis 6 gerichtet, umfas send die Schritte: Ausheben einer vertikalen Grube bzw. Ausnehmung im Boden, welche zumindest einen unteren Strukturblock aufnehmen kann; Ausbilden eines Steinfundaments durch Anordnen von zerkleinerten Steinen am Boden der Grube bzw. Ausnehmung; Anordnen des unteren Strukturblocks, welcher mit seiner Bodenseite nach unten angehoben ist, auf dem Steinfundament; und Anordnen des oberen Strukturblocks auf der Oberseite des unteren Strukturblocks, wobei das Abdichtelement zwischen dem oberen Ende des unteren Strukturblocks und dem unteren Ende des oberen Struk turblocks angeordnet wird, wodurch das Dichtelement einen Verbindungs bereich zwischen den oberen und unteren Strukturblöcken abdichtet. A fourth aspect of the invention is directed to a method of installing the Basement structure directed according to one of claims 1 to 6, comprises send the steps: excavate a vertical pit or recess in the Floor which can accommodate at least one lower structural block; Form a stone foundation by arranging crushed stones at the bottom of the pit or recess; Arranging the lower structure block, which is raised with its bottom side down, on the Stone foundation; and placing the top structural block on top of the lower structural block, the sealing element between the upper End of the lower structure block and the lower end of the upper structure Turblocks is arranged, whereby the sealing element connects seals between the upper and lower structural blocks.
Gemäß diesem Installationsverfahren wird das Untergeschoß in der vertikalen Grube durch Anordnen der entsprechenden Strukturblöcke über einander in der vertikalen Grube ausgebildet. Da die zerkleinerten Steine unter dem unteren Strukturblock angeordnet sind, wenn das Untergeschoß ausge bildet wird, kann der Boden des unteren Strukturblocks einheitlich oder eben durch dieses Steinfundament abgestützt werden. Da weiters der Verbin dungsbereich zwischen den oberen und unteren Strukturblöcken durch das dazwischen angeordnete Abdichtelement abgedichtet wird, kann das Ein dringen von Grundwasser in das Untergeschoß durch die Verbindung verhin dert werden.According to this installation procedure, the basement in the vertical pit by arranging the corresponding structural blocks above each other trained in the vertical pit. Because the crushed stones underneath the lower structural block are arranged when the basement is out is formed, the bottom of the lower structural block can be uniform or flat be supported by this stone foundation. Then there is the verb area between the upper and lower structural blocks through the the sealing element arranged between them is sealed, the on penetrate from groundwater into the basement through the connection be changed.
Das Installationsverfahren umfaßt vorzugsweise weiters den Schritt eines Anbringens einer Wasserabdichtauskleidung von der Innenseite der Untergeschoßeinheit in dem Verbindungsbereich zwischen den oberen und unteren Strukturblöcken, wo das Abdichtelement angeordnet ist.The installation process preferably further comprises the step of Attach a waterproof lining from the inside of the Basement unit in the connection area between the upper and lower structural blocks, where the sealing element is arranged.
Gemäß diesem Verfahren ist der Verbindungsbereich zwischen den oberen und unteren Strukturblöcken nicht nur durch das Abdichtelement, sondern auch durch die Wasserabdichtauskleidung abgedichtet. Derart kann ein Eindringen von Grundwasser in das Untergeschoß durch die Verbindungs stelle noch sicherer verhindert werden.According to this method, the connection area between the upper and lower structural blocks not only through the sealing element, but also sealed by the waterproof lining. That can penetration of groundwater into the basement through the connection be prevented even more safely.
Das Installationsverfahren kann weiters den Schritt eines Einbringens einer vorgegebenen Anzahl von Reibungspfählen in den Boden der Grube vor Anordnen des unteren Strukturblocks darin umfassen.The installation process can further include the step of inserting a predetermined number of friction piles in the bottom of the pit Placing the lower structural block therein.
Gemäß diesem Verfahren weist, da ein starkes Fundament am Boden der vertikalen Grube durch Eintreiben der Reibungspfähle in diese ausgebildet werden kann, das Untergeschoß einen verbesserten Widerstand gegenüber Erdbeben auf und die durch die Reibungspfähle abgestützte Untergeschoß struktur kann als ein stabiles Fundament für ein auf Bodenniveau zu bauendes Gebäude dienen.According to this procedure, there is a strong foundation on the ground the vertical pit by driving the friction piles into them can be, the basement has an improved resistance to Earthquakes and the basement supported by the friction piles structure can serve as a stable foundation for a building to be built at ground level Serve buildings.
Ein fünfter Aspekt der Erfindung ist auf ein Verfahren zur Installation der Untergeschoßstruktur gemäß einem der Ansprüche 1 bis 8 gerichtet, welches die Schritte umfaßt: Ausheben einer vertikalen Grube bzw. Ausnehmung im Boden, welche zumindest die Fundamentplatte aufnehmen kann; Anordnen einer Beton-Fundamentplatte auf dem Boden der vertikalen Grube; Anordnen von Abstandhaltern, welche von elastischen Elementen gebildet sind, auf der Fundamentplatte in vorgegebenen Intervallen zum Abstützen des unteren Strukturblocks; Anordnen von gemischtem Mörtel, welcher durch Mischen bzw. Kneten von Zement und Sand gebildet wird, auf der Fundamentplatte in der selben Dicke in einem Ausmaß, daß die Abstandhalter bedeckt werden, wobei eine Schicht aus gemischtem Mörtel gebildet wird; Anordnen des unteren Strukturblocks auf der Schicht aus gemischtem Mörtel; und Anordnen des oberen Strukturblocks auf der Oberseite des unteren Strukturblocks, wobei das Abdichtelement zwischen dem oberen Ende des unteren Strukturblocks und dem unteren Ende des oberen Strukturblocks angeordnet wird, wodurch das Abdichtelement einen Verbindungsbereich zwischen den oberen und unteren Strukturblöcken abdichtet.A fifth aspect of the invention is directed to a method of installing the Basement structure according to one of claims 1 to 8, which the steps include: excavating a vertical pit or recess in the Floor which can at least accommodate the foundation plate; Arrange a concrete foundation slab on the bottom of the vertical pit; Arrange of spacers, which are formed by elastic elements on the Foundation plate at predetermined intervals to support the lower one Structure blocks; Arranging mixed mortar, which by mixing or Kneading of cement and sand is formed on the foundation plate in the same thickness to the extent that the spacers are covered, whereby a layer of mixed mortar is formed; Arrange the lower one Structural blocks on the layer of mixed mortar; and arranging the upper structure block on top of the lower structure block, the Sealing element between the upper end of the lower structural block and the lower end of the upper structure block is arranged, whereby the Sealing element a connection area between the upper and lower Seals structural blocks.
Gemäß diesem Verfahren kann der untere Strukturblock durch eine Vielzahl von Abstandhaltern auf der Fundamentplatte durch Anordnen des unteren Strukturblocks auf dem Boden der vertikalen Grube nach dem Ausbil den der Schicht aus gemischtem Mörtel auf der Fundamentplatte angeordnet werden. Die Vielzahl von Abstandhaltern, welche aus elastischen Elementen hergestellt sind, werden elastisch durch das Gewicht des unteren Struktur blocks komprimiert bzw. verformt. In diesem Zustand wird die Mörtelschicht auch komprimiert, wodurch sie ihre Dicke in Abhängigkeit von der Unebenheit der Fundamentplatte und der Bodenoberfläche des unteren Strukturblocks ändert. Daraus resultierend wird die Mörtelschicht zwischen der Bodenober fläche des unteren Strukturblocks und der oberen Oberfläche der Fundament platte gehalten, während sie Abmessungsfehler der Fundamentplatte und des unteren Strukturblocks kompensiert. Durch Belassen für eine lange Zeit in diesem Zustand absorbiert die Schicht aus gemischtem bzw. geknetetem Mörtel Feuchtigkeit in der Erde, wobei dies die Durchführung einer speziellen chemischen Reaktion bewirkt. Dies verfestigt die Mörtelschicht, um dadurch ein Fundament in Übereinstimmung mit der Bodenoberfläche des unteren Struk turblocks zu bilden.According to this method, the lower structural block can be replaced by a Variety of spacers on the foundation plate by arranging the lower structural blocks on the bottom of the vertical pit after training the layer of mixed mortar arranged on the foundation plate become. The variety of spacers, which are made of elastic elements are made elastic by the weight of the lower structure blocks compressed or deformed. In this state, the layer of mortar also compressed, which makes their thickness dependent on the unevenness the foundation plate and the bottom surface of the lower structural block changes. This results in the layer of mortar between the top of the floor area of the lower structural block and the upper surface of the foundation plate while holding dimensional errors of the foundation plate and the lower structure blocks compensated. By leaving in for a long time the layer of mixed or kneaded absorbs this state Mortar moisture in the soil, this being the implementation of a special chemical reaction. This solidifies the mortar layer, thereby causing a Foundation in line with the bottom surface of the lower structure to form turblocks.
Durch Ausbilden des Fundaments mit gemischtem bzw. geknetetem
Mörtel auf diese Weise wird die Arbeit zur Ausbildung des Fundaments ein
facher im Vergleich zu einem Fall, in welchem Fertigbeton eingegossen wird,
und es kann das Gewicht der Untergeschoßstruktur durch den Boden bzw.
Untergrund über die Fundamentplatte aufgenommen werden, wobei dies das
Auftreten eines Nachteils bzw. von Unannehmlichkeiten verhindert, daß sich die
Untergeschoßstruktur aufgrund einer nicht ausgeglichenen Belastung neigt.
Ein sechster Aspekt der Erfindung ist auf ein Verfahren zur Installation
der Untergeschoßstruktur nach Anspruch 7 gerichtet, umfassend die Schritte:
Anordnen von zwei unteren Strukturblöcken auf dem Boden einer vertikalen
Grube bzw. Ausnehmung nebeneinander, so daß die oberen Ausschnitte
derselben zueinander gerichtet sind; Anordnen der oberen Strukturblöcke auf
der Oberseite der entsprechenden unteren Strukturblöcke, so daß die unteren
Ausschnitte derselben zueinander gerichtet sind; Einpassen des Abdichtele
ments in eine schmale Nut bzw. Rille, welche durch ein Paar von ersten, um
gebenden Vertiefungen einer ausgebildeten Türöffnung gebildet wird; und Ein
füllen von wasserabweisendem Mörtel in eine breite Nut bzw. Rille, welche
durch ein Paar von zweiten, umgebenden Vertiefungen der Türöffnung gebildet
wird.By forming the foundation with mixed or kneaded mortar in this way, the work of forming the foundation becomes easier compared to a case in which precast concrete is poured in, and the weight of the basement structure through the floor or sub-floor over the foundation plate are recorded, which prevents the occurrence of a disadvantage or inconvenience that the basement structure tilts due to an unbalanced load. A sixth aspect of the invention is directed to a method of installing the basement structure according to claim 7, comprising the steps:
Arranging two lower structural blocks on the bottom of a vertical pit or recess next to one another so that the upper cutouts thereof are directed towards one another; Placing the upper structural blocks on top of the corresponding lower structural blocks so that the lower cutouts thereof face each other; Fitting the sealing element into a narrow groove, which is formed by a pair of first, surrounding recesses of a formed door opening; and filling water-repellent mortar into a wide groove formed by a pair of second surrounding recesses in the door opening.
Gemäß diesem Verfahren wird die Türöffnung, welche durch Anordnen der zwei Untergeschoßeinheiten unmittelbar nebeneinander in der vertikalen Grube ausgebildet wird, doppelt durch das Abdichtelement, welches in die schmale Nut eingepaßt ist, welche in der inneren Oberfläche der Türöffnung ausgebildet ist, und durch den in die breite Nut eingefüllten, wasserabweisen den Mörtel abgedichtet. Derart kann das Eintreten von Grundwasser in die Untergeschoßeinheiten durch die Öffnungen der entsprechenden Unterge schoßeinheiten sicher verhindert werden.According to this method, the door opening, which by arranging of the two basement units directly next to each other in the vertical Pit is formed twice by the sealing element, which in the narrow groove is fitted, which in the inner surface of the door opening is formed, and by the filled in the wide groove, water-repellent sealed the mortar. In this way, the entry of groundwater into the Basement units through the openings of the corresponding basement lap units can be prevented safely.
Vorzugsweise umfassen die obigen Installationsverfahren weiters den Schritt eines Anbringens von Kopf-Querbalken an den oberen Enden der umgebenden Wände.Preferably, the above installation methods further include the Step of attaching cross head beams to the upper ends of the surrounding walls.
Gemäß diesem Verfahren kann, da ein Gebäude auf den Kopf-Quer balken gebaut werden kann, die Untergeschoßeinheit als ein Fundament für ein auf Bodenniveau zu bauendes Gebäude dienen.According to this procedure, since a building is upside down beams can be built, the basement unit as a foundation for one serve building to be built at ground level.
Vorzugsweise umfassen die Installationsverfahren weiters nach einem Anordnen der Untergeschoßeinheit am Boden der vertikalen Grube den Schritt eines Anordnens eines umgebenden Fundaments, in welchem Armierungs stäbe bzw. Bewehrungsstäbe an dem oberen Ende der vertikalen Grube derart angeordnet sind, daß die innere Oberfläche derselben in Kontakt mit der äußeren Oberfläche der Untergeschoßeinheit gehalten wird.Preferably, the installation methods further include one Placing the basement unit on the bottom of the vertical pit step an arrangement of a surrounding foundation, in which reinforcement bars or reinforcement bars at the top of the vertical pit are arranged so that the inner surface thereof in contact with the outer surface of the basement unit is held.
Gemäß diesem Verfahren wird ein Boden- bzw. Erddruck, welcher auf die Untergeschoßeinheit einwirken wird, durch das umgebende Fundament, welches die Untergeschoßeinheit umgibt, ausgeglichen. Insbesondere, falls ein Pfeiler- oder Pfählungsfundament und/oder ein Trägerfundament um die Unter geschoßeinheit vorgesehen ist, wirkt das Gewicht eines auf diesen Funda menten gebauten Gebäudes auf die Untergeschoßeinheit als Erddruck. Das umgebende Fundament blockiert jedoch den ausgeübten Erddruck, um da durch seinen Einfluß auf die Untergeschoßeinheit zu reduzieren. Demgemäß kann ein Nachteil bzw. eine Unannehmlichkeit eines verschwenderischen Ge brauchs des Bauplatzes durch Verstärken der Wände der Untergeschoßeinheit, ein Anwenden von Rammen am Boden des Pfählungsfundaments oder Trägerfundaments und weiters ein Anordnen eines Bodenabschnitts (Boden platte) des Gebäudefundaments in einer Position in Abstand von der Unterge schoßeinheit vermieden werden.According to this method, a soil or earth pressure, which is the basement unit will act through the surrounding foundation, which surrounds the basement unit, balanced. Especially if one Pillar or pile foundation and / or a beam foundation around the sub floor unit is provided, the weight of one acts on this funda ment of the building on the basement unit as earth pressure. The surrounding foundation, however, blocks the earth pressure exerted around there by reducing its influence on the basement unit. Accordingly can be a disadvantage or inconvenience of a wasteful ge of the building site by strengthening the walls of the basement unit, applying rams to the bottom of the pile foundation or Carrier foundations and further an arrangement of a floor section (floor plate) of the building foundation in a position at a distance from the base lap unit can be avoided.
Weiters kann in Abhängigkeit von der Situation das auf Bodenniveau gebaute Gebäude durch das umgebende Fundament abgestützt werden, woraus resultiert, daß die Fundamente, umfassend die Untergeschoßeinheit, als ein Mattenfundament wirken.Furthermore, depending on the situation, this can be done at ground level built buildings are supported by the surrounding foundation, which means that the foundations, including the basement unit, act as a mat foundation.
Vorzugsweise umfaßt das obige Verfahren weiters die Schritte eines Einbettens einer vorbestimmten Anzahl von Ankerelementen, welche nach außen um einen vorbestimmten Abstand in Bereichen der Untergeschoßeinheit entsprechend dem umgebenden Fundament vorragen, und eines Anordnens des umgebenden Fundaments mit angeordneten Ankerelementen und Be wehrungs- bzw. Armierungsstäben.Preferably, the above method further comprises the steps of Embedding a predetermined number of anchor elements, which after outside by a predetermined distance in areas of the basement unit protrude according to the surrounding foundation, and an arrangement of the surrounding foundation with arranged anchor elements and loading reinforcement bars.
Gemäß diesem Verfahren werden das umgebende Fundament und die Untergeschoßeinheit fest durch Anordnen der Ankerelemente und der Bewehrungsstäbe verbunden. Derart wird, selbst wenn ein Gebäude auf dem umgebenden Fundament gebaut wird, das Gewicht des Gebäudes, welches auf das umgebende Fundament wirkt, sowohl durch die Bodenoberfläche der Untergeschoßeinheit als auch durch die Bodenoberfläche des umgebenden Fundaments abgestützt. Daraus resultierend ist das Gebäude sicherer abge stützt und es wird ermöglicht, daß dieses eine bessere Widerstandsfähigkeit gegenüber Erdbeben aufweist.According to this procedure, the surrounding foundation and the Basement unit fixed by arranging the anchor elements and the Reinforcing bars connected. This will be the case even if a building on the surrounding foundation is built, the weight of the building which is on the surrounding foundation works, both through the floor surface of the Basement unit as well as through the floor surface of the surrounding Foundations supported. As a result, the building is more secure supports and it is made possible that this has a better resilience against earthquakes.
Ein siebenter Aspekt der Erfindung ist auf ein Verfahren zur Installation
der Untergeschoßstruktur gemäß Anspruch 7 gerichtet, umfassend die Schritte:
Ausheben einer vertikalen Grube im Boden, welche wenigstens zwei untere
Strukturblöcke aufnehmen kann; Anordnen einer Beton-Fundamentplatte am
Boden der vertikalen Grube; Anordnen von Abstandhaltern, welche durch
elastische Elemente gebildet sind, auf der Fundamentplatte in vorgegebenen
Intervallen zum Abstützen des unteren Strukturblocks und danach Anordnen
von gemischtem Mörtel, welcher durch Kneten bzw. Mischen von Zement und
Sand hergestellt wird, auf der Fundamentplatte bis zur selben Dicke in einem
Ausmaß, daß die Abstandhalter bedeckt werden, wodurch eine Schicht aus
gemischtem Mörtel gebildet wird; Anordnen von einem der unteren
Strukturblöcke auf der gemischten Mörtelschicht; Anordnen von einem der
oberen Strukturblöcke auf der Oberseite des unteren Strukturblocks, wobei das
Abdichtelement zwischen dem oberen Ende des unteren Strukturblocks und
dem unteren Ende des oberen Strukturblocks angeordnet wird, wodurch eine
erste Untergeschoßeinheit gebildet wird; Anbringen eines umgebenden
Abdichtelements an der Außenwandoberfläche der ersten Untergeschoßeinheit
um deren Öffnung; und folgendes Anordnen der anderen unteren und oberen
Strukturblöcke, wobei das Abdichtelement zwischen dem oberen Ende des
unteren Strukturblocks und dem unteren Ende des oberen Strukturblocks
angeordnet wird, um eine zweite Untergeschoßeinheit zu bilden, so daß die
Öffnung der zweiten Untergeschoßeinheit fluchtend zu derjenigen der ersten
Untergeschoßeinheit angeordnet wird und das umgebende Abdichtelement fest
zwischen den ersten und zweiten Untergeschoßeinheiten gehalten wird.A seventh aspect of the invention is directed to a method for installing the basement structure according to claim 7, comprising the steps:
Digging a vertical pit in the ground, which can accommodate at least two lower structural blocks; Placing a concrete foundation slab on the bottom of the vertical pit; Arranging spacers, which are formed by elastic elements, on the foundation plate at predetermined intervals for supporting the lower structural block and then arranging mixed mortar, which is produced by kneading or mixing cement and sand, on the foundation plate to the same thickness in an extent that the spacers are covered, forming a layer of mixed mortar; Placing one of the lower structural blocks on the mixed mortar layer; Disposing one of the upper structural blocks on top of the lower structural block, the sealing member being disposed between the upper end of the lower structural block and the lower end of the upper structural block, thereby forming a first basement unit; Attaching a surrounding sealing member to the outer wall surface of the first basement unit around its opening; and subsequently arranging the other lower and upper structural blocks, the sealing member being positioned between the upper end of the lower structural block and the lower end of the upper structural block to form a second basement unit so that the opening of the second basement unit is flush with that of the first basement unit is arranged and the surrounding sealing element is held firmly between the first and second basement units.
Gemäß diesem Verfahren wird das umgebende Abdichtglied in den Öff nungen der ersten und zweiten Untergeschoßeinheiten unter Druck elastisch deformiert, wobei es fest zwischen den ersten und zweiten Untergeschoßein heiten gehalten wird. Daher kann das Eintreten von Grundwasser oder dgl. in das Untergeschoß durch die entsprechenden Öffnungen sicher verhindert werden.According to this method, the surrounding sealing member in the opening Solutions of the first and second basement units elastic under pressure deformed, being firmly between the first and second basements units is held. Therefore, the occurrence of ground water or the like in the basement is safely prevented through the corresponding openings become.
Diese und andere Ziele, Merkmale und Vorteile der vorliegenden Erfindung werden bei einer Lektüre der nachfolgenden, detaillierten Beschrei bung und aus den beigeschlossenen Zeichnungen deutlicher werden.These and other objectives, features, and advantages of the present Invention will become apparent upon reading the following detailed description exercise and become clearer from the attached drawings.
Fig. 1 ist eine perspektivische Explosionsdarstellung, teilweise wegge schnitten, welche eine Ausführungsform einer Untergeschoß- bzw. Kellereinheit gemäß der Erfindung illustriert; Fig. 1 is an exploded perspective view, partially cut away, illustrating an embodiment of a basement or basement unit according to the invention;
Fig. 2 ist eine perspektivische Ansicht der Untergeschoßeinheit der Fig. 1 in ihrem zusammengebauten Zustand; Fig. 2 is a perspective view of the basement unit of Fig. 1 in its assembled state;
die Fig. 3A und 3B sind Querschnittsansichten, welche die abgestuften Enden der unteren und oberen Strukturblöcke illustrieren, wobei sie einen Zu stand, unmittelbar bevor der obere Strukturblock auf dem unteren Strukturblock angeordnet wird, und einen Zustand zeigen, nachdem der obere Strukturblock auf dem unteren Strukturblock angeordnet wurde; FIGS. 3A and 3B are cross-sectional views illustrating the stepped ends of the lower and upper structural blocks, it too was immediately before the upper structure block is placed on the lower structural block, and showing a state after the upper structure block on the lower Structure block was arranged;
die Fig. 4A und 4B sind Querschnittsansichten, welche die Herstellung einer Untergeschoßeinheit illustrieren, wobei Fig. 4A einen Zustand zeigt, nach dem Fertigbeton in eine Form für den unteren Strukturblock mit darin bereits angeordneter Stahlbewehrung bzw. -verstärkung gegossen wurde, und wobei Fig. 4B einen Zustand zeigt, nachdem Fertigbeton in eine Form für den oberen Strukturblock mit darin bereits angeordneten Stahlverstärkung bzw. -armierung gegossen wurde; FIGS. 4A and 4B are cross-sectional views illustrating the production of a basement unit, in which Fig. 4A shows a state after the ready-mixed concrete into a mold for the lower structure block is already arranged steel reinforcement or amplification was poured, and wherein Fig. 4B shows a state after ready-mixed concrete has been poured into a mold for the upper structural block with steel reinforcement or reinforcement already arranged therein;
die Fig. 5A und 5B sind Darstellungen, welche den unteren bzw. den oberen Strukturblock auf die Seite gelegt zeigen; Figs. 5A and 5B are diagrams showing the lower set and the upper block structure to the side;
die Fig. 6A und 6B sind Darstellungen, welche ein Beispiel eines För derns der einzelnen Strukturblöcke illustrieren, wobei Fig. 6A zeigt, wie jeder Strukturblock durch einen Hebearm angehoben wird, und wobei Fig. 6B einen der Strukturblöcke zeigt, welcher durch einen Förderer C gefördert wird;, as each structural block raised by a lifting arm to FIGS. 6A and 6B are diagrams illustrating an example of a För Dern of the individual structural units, wherein, FIG. 6A and FIG. 6B shows one of the structural blocks formed by a conveyor C is promoted;
Fig. 7 ist eine perspektivische Ansicht eines einen Block tragenden Gestells; Fig. 7 is a perspective view of a frame supporting a block;
die Fig. 8A und 8B sind Darstellungen, welche Vorbereitungsarbeiten für das Laden von jedem Strukturblock illustrieren, wobei Fig. 8A zeigt, wie eine mit einem Strukturblock beladene Gestellbasis durch einen Haken eines Krans angehoben wird, und wobei Fig. 8B einen Zustand zeigt, nachdem die Gestellbasis auf einer Transportpalette durch den Kran angeordnet wurde;, the Figs. 8A and 8B are diagrams showing preparatory work illustrate for loading each structural block, wherein, FIG. 8A as a loaded with a structural block rack base lifted by a hook of a crane, and Fig. 8B shows a state after the rack base was placed on a transport pallet by the crane;
Fig. 9 ist eine Darstellung, welche illustriert, wie ein Gestellrahmen auf einer Gestellbasis montiert wird; Fig. 9 is a diagram illustrating how a rack frame is mounted on a rack base;
die Fig. 10A und 10B sind Darstellungen, welche illustrieren, wie der in dem Gestell montierte Strukturblock auf ein Transportfahrzeug verladen wird, wobei Fig. 10A einen Zustand zeigt, nachdem sich das Kraftfahrzeug der auf dem Grund liegenden Transportpalette angenähert hat, und wobei Fig. 10B einen Zustand zeigt, nachdem der auf dem Gestell montierte Strukturblock auf der Ladefläche des Kraftfahrzeuges gemeinsam mit der Palette geladen wurde; FIGS. 10A and 10B are diagrams illustrating how the mounted in the frame structure block is loaded on a transport vehicle, FIG. 10A shows a state after the motor vehicle of the transport pallet lying on the ground has approached, and wherein Fig. 10B shows a state after the structural block mounted on the frame has been loaded on the loading surface of the motor vehicle together with the pallet;
Fig. 11 ist eine teilweise Querschnittsansicht entlang der Linien A-A der Fig. 10A; Fig. 11 is a partial cross-sectional view taken along lines AA of Fig. 10A;
Fig. 12 ist eine Seitenansicht eines lastaufnehmenden Montagegestells, welches auf dem Boden angeordnet ist, wenn der Strukturblock von dem Fahrzeug abgeladen wird; Fig. 12 is a side view of a load bearing mounting frame which is placed on the floor when the structural block is unloaded from the vehicle;
die Fig. 13A bis 13C sind Darstellungen, welche einen Vorgang eines Entladens des den Strukturblock enthaltenden Gestells illustrieren, wobei Fig. 13A einen Zustand zeigt, in welchem das den Strukturblock enthaltende Gestell durch einen Kranhaken angehoben wird, wobei Fig. 13B einen Zustand zeigt, in welchem das durch den Kranhaken angehobene Gestell geneigt bzw. gekippt wird, und wobei Fig. 13C einen Zustand zeigt, in welchem das durch den Kranhaken angehobene Gestell auf dem lastaufnehmenden Montagegestell placiert wurde; FIGS. 13A to 13C are diagrams illustrating an operation of unloading of the structural block containing frame, FIG. 13A shows a state in which the frame of the structural block containing is lifted by a crane hook, in which Fig. 13B shows a state in which the frame raised by the crane hook is tilted, and Fig. 13C shows a state in which the frame raised by the crane hook has been placed on the load-bearing mounting frame;
Fig. 14 ist eine perspektivische Explosionsdarstellung, welche eine Untergeschoßstruktur mit zwei Räumen gemäß einer zweiten Ausführungsform der Erfindung zeigt, in welcher eine zweite Untergeschoßeinheit unmittelbar benachbart einer ersten Untergeschoßeinheit installiert ist; Fig. 14 is an exploded perspective view showing a lower floor structure with two spaces according to a second embodiment of the invention, in which a second basement unit immediately adjacent a first basement unit is installed;
Fig. 15 ist eine perspektivische Ansicht, welche die Zweiraum-Unterge schoßstruktur zeigt, in welcher die zweite Untergeschoßeinheit benachbart der ersten Untergeschoßeinheit installiert ist; Fig. 15 is a perspective view showing the two-room basement structure in which the second basement unit is installed adjacent to the first basement unit;
Fig. 16 ist eine vertikale Schnittansicht entlang der Linien B-B der Fig. 15; Fig. 16 is a vertical sectional view taken along lines BB of Fig. 15;
Fig. 17 ist eine perspektivische Ansicht, welche einen Zustand illustriert, in welchem ein Quer- bzw. Deckenbalken an der Oberseite der fertiggestellten Zweiraum-Untergeschoßstruktur der zweiten Ausführungsform angeordnet wird; Fig. 17 is a perspective view illustrating a state in which a cross beam is placed on the top of the completed two-room basement structure of the second embodiment;
Fig. 18 ist eine perspektivische Ansicht, welche eine Modifikation der Zweiraum-Untergeschoßstruktur gemäß der zweiten Ausführungsform der Erfindung illustriert; Fig. 18 is a perspective view illustrating a modification of the two-room basement structure according to the second embodiment of the invention;
die Fig. 19A und Fig. 19B sind Darstellungen, welche ein Verfahren einer Installation vor Ort für die Modifikation der zweiten Ausführungsform illustrieren, wobei Fig. 19A zeigt, wie ein zweiter, unterer Strukturblock eines zweiten Untergeschoß-Strukturblocks benachbart einem bereits installierten, ersten Untergeschoß-Strukturblock abgesenkt wird, und wobei Fig. 19B den abgesenkten, zweiten, unteren Strukturblock zeigt; FIG. 19A and FIG. 19B are diagrams illustrating a method of an installation site for the modification of the second embodiment, FIG, FIG. 19A as a second, lower structural block of a second basement structure block adjacent to an already installed, the first basement Structure block is lowered, and Fig. 19B shows the lowered second lower structure block;
die Fig. 20A und 20B sind Darstellungen, welche das Verfahren zur Installation vor Ort bzw. auf der Baustelle für die Modifikation der zweiten Ausführungsform zeigen, wobei Fig. 20A zeigt, wie ein zweiter, oberer Struktur block auf dem zweiten, unteren Strukturblock abgesenkt wird, und wobei Fig. 20B zeigt, wie der zweite, obere Strukturblock auf den zweiten, unteren Strukturblock placiert ist;is FIGS. 20A and 20B are diagrams showing the method of installation on site or on the site of the modification of the second embodiment, wherein Fig. 20A shows how a second, upper structure block on the second lower structural block lowered , and where Fig. 20B shows how the second upper structure block is placed on the second lower structure block;
Fig. 21 ist eine perspektivische Explosionsdarstellung, teilweise wegge schnitten, welche eine dritte Ausführungsform des Untergeschoß-Strukturblocks gemäß der Erfindung zeigt; Fig. 21 is an exploded perspective view, partially cut away, showing a third embodiment of the basement structure block according to the invention;
Fig. 22 ist eine perspektivische Ansicht, teilweise weggeschnitten, welche die dritte Ausführungsform des Untergeschoß-Strukturblocks gemäß der Erfindung zeigt, wobei ein oberer Strukturblock auf einem unteren Strukturblock angeordnet ist; Fig. 22 is a perspective view, partially cut away, according to the invention which shows the third embodiment of the basement structure block, an upper block structure is arranged on a lower structural block;
die Fig. 23A und 23B sind Querschnittsansichten, welche die abgestuften Enden der oberen und unteren Strukturblöcke zeigen, wobei Fig. 23A einen Zustand zeigt, unmittelbar bevor der obere Strukturblock auf dem unteren Strukturblock angeordnet wird, und wobei Fig. 23B einen Zustand zeigt, nachdem der obere Strukturblock auf dem unteren Strukturblock angeordnet wurde; FIGS. 23A and 23B are cross-sectional views showing the stepped ends of the upper and lower structural blocks, Fig. 23A shows a state immediately before the upper structural block is placed on the lower structural block, and FIG. 23B shows a state after the upper structure block was placed on the lower structure block;
die Fig. 24A und 24B sind Querschnittsansichten, welche illustrieren, wie eine Untergeschoßeinheit hergestellt wird, wobei Fig. 24A einen Zustand zeigt, nachdem Fertigbeton in eine Form für den unteren Strukturblock mit darin ange ordneten Bewehrungen bzw. Armierungen eingegossen wurde, und wobei Fig. 24B einen Zustand zeigt, nachdem Fertigbeton in eine Form für den oberen Strukturblock mit bereits darin angeordneten Bewehrungen bzw. Armierungen gegossen wurde; FIGS. 24A and 24B are cross-sectional views illustrating how a lower floor unit is made, in which FIG. 24A shows a state after finished concrete was poured into a mold for the lower structural block with integrally therein arranged reinforcement or reinforcements, and wherein Fig. 24B shows a state after ready-mixed concrete has been poured into a mold for the upper structural block with reinforcements or reinforcements already arranged therein;
Fig. 25 ist eine Seitenansicht im Schnitt eines umgebenden Fundaments zur Erläuterung einer zweiten Ausführungsform des Verfahrens zur Installation vor Ort gemäß der Erfindung; Fig. 25 is a side view in section of a surrounding foundation for explaining a second embodiment of the method for on-site installation according to the invention;
Fig. 26 ist eine Draufsicht auf das umgebende Fundament für die Erläu terung der zweiten Ausführungsform des Baustellen-Installationsverfahrens gemäß der Erfindung; Fig. 26 is a plan view of the surrounding foundation for the esterification Erläu the second embodiment of the construction site installation method according to the invention;
Fig. 27 ist eine südseitige Ansicht eines Hauses, bei welchem der Unter geschoß-Strukturblock gemäß der Erfindung angewandt wurde; Fig. 27 is a south-side view of a house to which the sub-floor structure block according to the invention has been applied;
Fig. 28 ist ein Geschoßplan des Erdgeschosses des Hauses gemäß Fig. 27; Fig. 28 is a floor plan of the ground floor of the house shown in Fig. 27;
Fig. 29 ist eine perspektivische, teilweise Schnittansicht des in Fig. 27 gezeigten Untergeschosses bzw. Kellers; Fig. 29 is a perspective, partial sectional view of the basement shown in Fig. 27;
Fig. 30 ist eine Seitenschnittansicht, welche eine Fundamentstruktur und eine Blockanordnungsarbeit zeigt; und Fig. 30 is a sectional side view showing a foundation structure and block arrangement work; and
Fig. 31 ist eine Draufsicht auf eine Grube, in welcher die Strukturblöcke angeordnet wurden. Figure 31 is a top view of a pit in which the structural blocks have been placed.
Fig. 1 ist eine teilweise weggeschnittene Ansicht von Strukturblöcken zum Bauen eines Untergeschosses bzw. Kellers gemäß einer ersten Ausfüh rungsform der Erfindung und Fig. 2 ist eine perspektivische Darstellung, welche die Strukturblöcke der Fig. 1 in ihrem zusammengebauten Zustand zeigt. Wie aus diesen Figuren ersichtlich, umfaßt eine Untergeschoß- bzw. Kellereinheit 10 als wesentliche bzw. prinzipielle Elemente einen unteren Strukturblock 1, welcher eine untere Hälfte der Untergeschoß- bzw. Kellereinheit 10 bildet, und einen oberen Strukturblock 2, welche seine obere Hälfte bildet. In einer rechteckigen Form in der Draufsicht geformt, weist der untere Strukturblock 1 einen Geschoßabschnitt bzw. -bereich (Bodenabschnitt) 11, welcher am Boden ausgebildet ist, und umgebende Wände 12 auf, welche sich von allen Seiten des Grund- bzw. Bodenabschnittes 11 nach oben erstrecken. Fig. 1 is a partially cutaway view of structural blocks for building a basement according to a first embodiment of the invention, and Fig. 2 is a perspective view showing the structural blocks of Fig. 1 in their assembled state. As can be seen from these figures, a basement or basement unit 10 comprises, as essential or principal elements, a lower structural block 1 , which forms a lower half of the basement or basement unit 10 , and an upper structural block 2 , which forms its upper half. Shaped in a rectangular shape in plan view, the lower structural block 1 has a floor section or area (floor section) 11 , which is formed on the floor, and surrounding walls 12 , which extend from all sides of the base or floor section 11 extend above.
Der Bodenabschnitt 11 weist auch eine rechteckige Form in der Drauf sicht, wie dargestellt, auf. Die umgebenden Wände 12 des unteren Struktur blocks 1 beinhalten ein Paar kurzer Seitenwände 13, welche vertikal an den gegenüberliegenden, kurzen Seiten des Bodenabschnitts 11 gebildet sind, und ein Paar langer Seitenwände 14, welche vertikal an den gegenüberliegenden Längsseiten des Bodenabschnitts 11 ausgebildet sind. Die Oberseite von jeder umgebenden Wand 12 ist derart ausgebildet, daß sie ein abgestuftes bzw. abgesetztes Ende 15 aufweist, welches einen äußeren, tieferen Endabschnitt 15a und einen inneren, höheren Endabschnitt 15b aufweist.The bottom portion 11 also has a rectangular shape in the top view, as shown. The surrounding walls 12 of the lower structural block 1 include a pair of short side walls 13 formed vertically on the opposite short sides of the bottom portion 11 and a pair of long side walls 14 vertically formed on the opposite long sides of the bottom portion 11 . The top of each surrounding wall 12 is formed such that it has a stepped end 15 , which has an outer, lower end portion 15 a and an inner, higher end portion 15 b.
Konstruiert mit derselben rechteckigen Form und Abmessung wie der untere Strukturblock 1 in der Draufsicht, weist der obere Strukturblock 2 um gebende Wände 21 auf, welche ein Paar kurzer Seitenwände 22 entsprechend den kurzen Seitenwänden 13 und ein Paar von langen Seitenwänden 23 entsprechend den Längsseitenwänden 14 umfassen. Der Boden von jeder umgebenden Wand 21 ist ausgebildet, um ein abgestuftes bzw. abgesetztes Ende 24 aufzuweisen, welches einen äußeren, unteren bzw. tieferen Endab schnitt 24a, welcher dem unteren Endabschnitt 15a von jeder umgebenden Wand 12 entspricht, und einen inneren, höheren Endabschnitt 24b aufweist, der dem höheren Endabschnitt 15b von jeder umgebenden Wand 12 entspricht.Constructed with the same rectangular shape and dimension as the lower structural block 1 in plan view, the upper structural block 2 has surrounding walls 21 , which comprise a pair of short side walls 22 corresponding to the short side walls 13 and a pair of long side walls 23 corresponding to the longitudinal side walls 14 . The bottom of each surrounding wall 21 is formed to have a stepped or stepped end 24 which cut an outer, lower or lower Endab 24 a, which corresponds to the lower end portion 15 a of each surrounding wall 12 , and an inner, has higher end portion 24 b, which corresponds to the higher end portion 15 b of each surrounding wall 12 .
An der Oberseite des oberen Strukturblocks 2 ist eine Deckenwand 20 vorgesehen, welche auf den umgebenden Wänden 21 abgestützt ist. Ein rechteckiger Durchgang 20a ist in einer speziellen Position der Deckenwand 20 ausgebildet, um jemandem zu ermöglichen, in die Untergeschoßeinheit 10 durch den Durchgang 20a bei auf dem unteren Strukturblock 1 aufgesetztem Strukturblock 2 zu gehen und aus dieser zu gelangen (siehe Fig. 2). Die Untergeschoß- bzw. Kellereinheit 10 ist ausgebildet, wenn der obere Struk turblock 2 auf dem unteren Strukturblocks 1 derart angeordnet bzw. gestapelt ist, daß die Bodenoberflächen der umgebenden Wände 21 des oberen Struk turblocks 2 exakt mit den oberen Oberflächen der entsprechenden umgeben den Wände 12 des unteren Strukturblocks 1 ausgerichtet und in Kontakt mit diesen angeordnet sind.At the top of the upper structural block 2 , a ceiling wall 20 is provided, which is supported on the surrounding walls 21 . A rectangular passage 20 a is formed in a special position of the ceiling wall 20 in order to enable someone to go into the basement unit 10 through the passage 20 a with the structure block 2 placed on the lower structure block 1 and to get out of it (see FIG. 2 ). The basement or basement unit 10 is formed when the upper structural block 2 is arranged or stacked on the lower structural block 1 in such a way that the bottom surfaces of the surrounding walls 21 of the upper structural block 2 exactly match the upper surfaces of the corresponding surrounding walls 12 of the lower structural block 1 are aligned and arranged in contact therewith.
Die Fig. 3A und 3B sind teilweise Schnittansichten der abgestuften Enden 15, 24 der oberen und unteren Strukturblöcke 1, 2, wobei Fig. 3A einen Zustand zeigt, bevor der obere Strukturblock 2 an der Oberseite des unteren Strukturblocks 1 angeordnet ist, und wobei Fig. 3B einen Zustand zeigt, nachdem der obere Strukturblock 2 auf dem unteren Strukturblock 1 angeord net wurde. Wie aus Fig. 3A ersichtlich, sind die unteren Endabschnitte 24a des oberen Strukturblocks 2 gegenüberliegend den unteren Endabschnitten 15a des unteren Strukturblocks 1 positioniert und es sind die höheren Endab schnitte 24b des oberen Strukturblocks 2 gegenüberliegend den höheren Endabschnitten 15b des unteren Strukturblocks 1 positioniert, wenn der obere Strukturblock 2 in seine Position über dem unteren Strukturblock 1 auf eine in Fig. 3A gezeigte Weise angehoben wird. Die Breiten der einzelnen unteren Endabschnitte 15a, 24a und der höheren Endabschnitte 15b, 24b sind derart eingestellt, daß die abgestuften Enden 24 des oberen Strukturblocks 2 in Eingriff mit den entsprechenden, abgestuften Enden 15 des unteren Struktur blocks 1 gelangen, wie dies in Fig. 3B gezeigt ist, wenn der obere Strukturblock 2 aus dem Zustand gemäß Fig. 3A abgesenkt wird, bis seine abgestuften Enden 24 in Kontakt mit den entsprechenden, abgestuften Enden 15 des unteren Strukturblocks 1 gelangen. Diese Anordnung verhindert sicher, daß der obere Strukturblock 2, sobald er ordnungsgemäß auf dem unteren Strukturblock 1 angeordnet bzw. aufgerichtet ist, in horizontalen Richtungen verschoben wird. FIGS. 3A and 3B are partially sectional views of the stepped ends 15, 24 of the upper and lower structural blocks 1, 2, wherein Fig. 3A shows a state before the upper structural block is arranged on the top of the lower structure of block 1 2, and wherein Fig . 3B shows a state after the upper structural block was angeord net on the lower structural block 1 2. As shown in FIG. 3A, the lower end portions 24 are a of the upper structural block 2 opposite to the lower end portions 15 a of the lower structural block 1 is positioned and it is the higher Endab sections 24 b of the upper structural block 2 opposite to the higher end portions 15 b of the lower structural block 1 positioned when the upper structure block 2 is raised into position over the lower structure block 1 in a manner shown in Fig. 3A. The widths of the individual lower end portions 15 a, 24 a and the higher end portions 15 b, 24 b are set such that the stepped ends 24 of the upper structural block 2 come into engagement with the corresponding stepped ends 15 of the lower structural block 1 , such as This is shown in FIG. 3B when the upper structural block 2 is lowered from the state according to FIG. 3A until its stepped ends 24 come into contact with the corresponding stepped ends 15 of the lower structural block 1 . This arrangement certainly prevents the upper structural block 2 from being displaced in horizontal directions once it is properly arranged or erected on the lower structural block 1 .
Der obere und untere Strukturblock 1, 2 sind aus Stahlbeton gebildet, welcher Stahlbewehrungsstäbe F enthält, welche angeordnet sind, um ein kreuzweises Muster zu bilden, und im Beton eingebettet sind. Bevor der obere Strukturblock 2 auf dem unteren Strukturblock 1 angeordnet bzw. gestapelt wird, wird ein Abdichtelement 3, welches aus einem elastischen Material, wie beispielsweise Gummi, ausgebildet ist, welches eine gute Flexibilität und Wasserabweisungs- bzw. Wasserabdichteigenschaften aufweist, auf den abge stuften bzw. abgesetzten Enden 15 der umgebenden Wände 12 angeordnet, wie dies in Fig. 3A gezeigt ist. Wenn der obere Strukturblock 2 auf dem unteren Strukturblock 1 angeordnet wird, wird das Abdichtelement 3 fest durch das Gewicht des oberen Strukturblocks 2 gepreßt und zwischen den abgestuften Enden 15 und 24 der umgebenden Wände 12, 21 gehalten, wie dies in Fig. 3B gezeigt ist. Wenn die Untergeschoßeinheit 10 derart unter dem Bodenniveau zusammengebaut ist, verhindert das Abdichtelement 3 ein Eindringen von Grundwasser zwischen den Verbindungsoberflächen der abgestuften Enden 15, 24.The upper and lower structural blocks 1 , 2 are made of reinforced concrete, which contains steel reinforcing bars F, which are arranged to form a cross pattern, and are embedded in the concrete. Before the upper structural block 2 is arranged or stacked on the lower structural block 1 , a sealing element 3 , which is formed from an elastic material, such as rubber, which has good flexibility and water repellency or water sealing properties, is graded on the or offset ends 15 of the surrounding walls 12 , as shown in Fig. 3A. When the upper structural block 2 is placed on the lower structural block 1 , the sealing member 3 is pressed firmly by the weight of the upper structural block 2 and held between the stepped ends 15 and 24 of the surrounding walls 12 , 21 as shown in Fig. 3B . When the basement unit 10 is assembled below the floor level in this way, the sealing element 3 prevents groundwater from penetrating between the connecting surfaces of the stepped ends 15 , 24 .
In dieser Ausführungsform weisen die umgebenden Wände 12, 21 der einzelnen Strukturblöcke 1, 2 und der Bodenabschnitt 11 des unteren Struktur blocks 1 eine Mindestdicke von 150 mm auf, so daß die Deckenwand 20 des oberen Strukturblocks 2, welche über das Bodenniveau vorragen würde, wenn die Untergeschoßeinheit 10 in der Position unter Bodenniveau angeordnet ist, als ein Fundament für eine über dem Boden konstruierte Struktur dienen kann.In this embodiment, the surrounding walls 12 , 21 of the individual structural blocks 1 , 2 and the bottom portion 11 of the lower structural block 1 have a minimum thickness of 150 mm, so that the top wall 20 of the upper structural block 2 , which would protrude above the floor level if the basement unit 10 is located in the position below floor level can serve as a foundation for a structure constructed above the floor.
Jeder der Armierungs- bzw. Bewehrungsstäbe F, welcher in dieser Aus führungsform verwendet wird, weist einen Durchmesser von 13 mm auf. Die Bewehrungsstäbe F beinhalten Hauptbewehrungsstäbe, welche parallel zu der Längsachse von jedem Strukturelement angeordnet sind, und Verteilungsstäbe, welche unter rechten Winkeln zu den Hauptbewehrungs- bzw. -armie rungsstäben angeordnet sind. Die Verteilungsstäbe und die Hauptbewehrungs stäbe sind einzeln parallel in bestimmten Intervallen verlegt und unter rechten Winkeln relativ zueinander durch ein bekanntes Verfahren zusammengebaut, in welchem die Abstände zwischen den Verteilungsstäben und zwischen den Hauptbewehrungs- bzw. -armierungsstäben in Abhängigkeit von spezifischen Anwendungen der Untergeschoßeinheit 10 (beispielsweise, ob die Untergeschoßeinheit 10 einfach als ein Kellerraum verwendet wird oder auch als ein Fundament dienen soll, auf welchem eine über dem Bodenniveau gebaute Struktur aufruhen soll) bestimmt werden.Each of the reinforcement bars F, which is used in this embodiment, has a diameter of 13 mm. The reinforcing bars F include main reinforcing bars which are arranged parallel to the longitudinal axis of each structural element, and distribution bars which are arranged at right angles to the main reinforcing bars. The distribution bars and the main reinforcement bars are individually laid in parallel at certain intervals and assembled at right angles relative to each other by a known method in which the distances between the distribution bars and between the main reinforcement or reinforcement bars depending on specific applications of the basement unit 10 ( for example, whether the basement unit 10 is simply to be used as a basement room or is also to serve as a foundation on which a structure built above ground level should rest).
Wenn der untere Strukturblock 1 unter dem Bodenniveau angeordnet ist, so daß der Bodenabschnitt 11 1,8 bis 2,0 m unter dem Bodenniveau angeordnet ist, beträgt der auf die Umgebungswände 12 in einem Abstand von 0,6 m vom Boden wirkende Erddruck 1,0 tf/m unter Normalbedingungen und 1,7 bis 2,0 tf/m während eines Erdbebens, unter der Bedingung, daß der interne Reibungswinkel 30° beträgt, wenn die Erdaufschüttung gewöhnlicher Boden mit einem normalen, gesättigten Wassergehalt und der seitliche, seismische Koeffizient k 0,3 ist. Der obengenannte Durchmesser (13 mm) der Bewehrungs- bzw. Verstärkungsstäbe F wurde unter Berücksichtigung dieser Bedingungen ausgewählt, wodurch die Untergeschoßeinheit 10 gut potentiellen, äußeren Beanspruchungen nicht nur unter Normalbedingungen, sondern auch während Erdbeben widerstehen kann.If the lower structural block 1 is arranged below the floor level, so that the floor section 11 is arranged 1.8 to 2.0 m below the floor level, the earth pressure acting on the surrounding walls 12 at a distance of 0.6 m from the floor is 1, 0 tf / m under normal conditions and 1.7 to 2.0 tf / m during an earthquake, on the condition that the internal angle of friction is 30 ° when the earth is normal soil with a normal, saturated water content and the lateral, seismic coefficient k is 0.3. The above-mentioned diameter (13 mm) of the reinforcement bars F was selected taking these conditions into account, whereby the basement unit 10 can withstand potential external stresses not only under normal conditions, but also during earthquakes.
Die Bewehrungs- bzw. Armierungsstäbe F sind auch in den vorragenden, höheren Endabschnitten 15b des unteren Strukturblocks 1 und den unteren Endabschnitten 24a des oberen Strukturblocks 2 angeordnet, wie dies. in den Fig. 3A und 3B gezeigt ist. Mit dieser Anordnung wird die mechanische Festig keit der höheren Endabschnitte 15b und der unteren Endabschnitte 24a beträchtlich erhöht, so daß die inhärente Schwäche des Verbindungsbereichs zwischen dem unteren Strukturblock 1 und dem oberen Strukturblock 2 wirksam ausgeglichen wird.The reinforcement bars F are also arranged in the protruding, higher end portions 15 b of the lower structural block 1 and the lower end portions 24 a of the upper structural block 2 , as this. As shown in FIGS. 3A and 3B. With this arrangement, the mechanical strength of the higher end portions 15 b and the lower end portions 24 a is increased considerably, so that the inherent weakness of the connection area between the lower structural block 1 and the upper structural block 2 is effectively compensated.
Die Breite (d. h. die horizontale Abmessung der kurzen Seitenwände 13, 22) und die Länge (d. h. die horizontale Abmessung der Längsseitenwände 14, 23) der Untergeschoßeinheit 10 sind in Vielfachen von 0,9 m in den Außen abmessungen hergestellt, um mit gewöhnlichen japanischen Abmessungen übereinzustimmen. Weiters ist die Höhe der einzelnen Strukturblöcke 1, 2 auf 1,2 m oder 1,3 m eingestellt, so daß die Höhe der Untergeschoßeinheit 10 2,4 oder 2,6 m wird. In dieser Ausführungsform kann die Untergeschoßeinheit 10 auf jede beliebigen, standardisierten Größen eingestellt werden, welche 4,5-, 6-, 8- und 10-Matten- (Tatami-)Größen umfassen können, welche beispielsweise für eine Fabriksherstellung geeignet sind. Tabelle 1 unten zeigt Abmessungs spezifikationen, welche auf die Untergeschoßeinheit 10 gemäß dieser Ausführungsform angewandt werden können.The width (ie the horizontal dimension of the short side walls 13 , 22 ) and the length (ie the horizontal dimension of the long side walls 14 , 23 ) of the basement unit 10 are made in multiples of 0.9 m in the outer dimensions, in order to have ordinary Japanese dimensions agree. Furthermore, the height of the individual structural blocks 1 , 2 is set to 1.2 m or 1.3 m, so that the height of the basement unit 10 becomes 2.4 or 2.6 m. In this embodiment, the basement unit 10 can be set to any standardized sizes, which may include 4.5, 6, 8, and 10 mat (tatami) sizes, which are suitable, for example, for factory manufacture. Table 1 below shows dimensional specifications that can be applied to the basement unit 10 according to this embodiment.
Die oben gezeigten Abmessungsspezifikationen der Ausführungsform sollten lediglich als typische Beispiele der Erfindung betrachtet werden. Diese Abmessungen wurden gewählt, um einige typische Konfigurationen zur Verfü gung zu stellen, da diese gut für gewöhnliche, japanische Häuser und eine Fab riksproduktion geeignet sind und da die einzelnen Strukturblöcke 1, 2, welche entsprechend den obigen Dimensionen konstruiert sind, über öffentliche Straßen in Übereinstimmung mit Straßenverkehrsgesetzen und -bestimmungen transportiert werden können, wenn die Strukturblöcke 1, 2 auf ihre Seite gelegt werden.The dimensional specifications of the embodiment shown above should only be considered as typical examples of the invention. These dimensions were chosen in order to provide some typical configurations, since these are well suited for ordinary Japanese houses and a factory production and because the individual structural blocks 1 , 2 , which are constructed according to the above dimensions, over public streets in Compliance with road traffic laws and regulations can be transported if the structure blocks 1 , 2 are placed on their side.
Unter Bezugnahme auf die Fig. 4A und 4B wird ein Verfahren zur Her stellung der einzelnen Strukturblöcke 1, 2 beschrieben. Die Fig. 4A und 4B sind Schnittansichten, welche illustrieren, wie die Untergeschoßeinheit 10 produziert wird, wobei Fig. 4A einen Zustand zeigt, nachdem Fertigbeton bzw. Trans portbeton in eine Form für den unteren Strukturblock mit bereits angeordneten Stahlbewehrungen gegossen wurde, und wobei Fig. 4B einen Zustand zeigt, nachdem Fertigbeton in eine Form für den oberen Strukturblock 2 mit bereits angeordneten Stahlbewehrungen eingegossen wurde.With reference to FIGS. 4A and 4B, a method for the manufacture of the individual structural blocks 1 , 2 is described. FIGS. 4A and 4B are sectional views illustrating how the basement unit 10 is produced, in which Fig. 4A shows a state after finished concrete or trans-mixed concrete was poured into a mold for the lower structural block with pre-arranged steel reinforcements, and wherein Fig . 4B shows a state after finished concrete was poured into a mold for the upper structural block 2 with pre-arranged steel reinforcements.
Mit 41 ist in Fig. 4A eine erste Form bezeichnet, welche zur Herstellung des unteren Strukturblocks 1 verwendet wird. Die erste Form 41 weist eine Vertiefung bzw. Ausnehmung 41a auf, welche dieselbe, jedoch inverse, dreidi mensionale Form wie der untere Strukturblock 1 aufweist. Nach Anordnen der Armierungs- bzw. Bewehrungsstäbe F in der Ausnehmung bzw. dem Hohlraum 41a wird Fertigbeton in die Ausnehmung 41a eingegossen, während die Form 41 unter Verwendung eines nicht dargestellten Formrüttlers gerüttelt wird. Die erste Form 41 wird dann ruhen gelassen, um dem Beton ein Setzen zu ermög lichen. Nachdem der Beton ausgehärtet ist und eine ausreichende Festigkeit erlangt hat, wird der neu hergestellte, untere Strukturblock 1 aus der Ausnehmung 41a der ersten Form 41 entfernt. Während des Verfahrens des Aushärtens des Betons kann der Beton durch Zufuhr von Dampf in die erste Form 41 beheizt bzw. erwärmt werden, um das Aushärten des Betons zu beschleunigen. 41 in FIG. 4A denotes a first mold which is used to produce the lower structural block 1 . The first shape 41 has a recess or recess 41 a, which has the same, but inverse, three-dimensional shape as the lower structure block 1 . After arranging the reinforcing or reinforcing bars F in the recess or the cavity 41 a, ready-mixed concrete is poured into the recess 41 a, while the mold 41 is vibrated using a form vibrator, not shown. The first mold 41 is then left to allow the concrete to settle. After the concrete has hardened and has acquired sufficient strength, the newly produced, lower structural block 1 is removed from the recess 41 a of the first mold 41 . During the process of hardening the concrete, the concrete may be heated by supplying steam to the first mold 41 to accelerate the hardening of the concrete.
Mit 42 ist in Fig. 4B eine zweite Form bezeichnet, welche für eine Her stellung des oberen Strukturblocks 2 verwendet wird. Die zweite Form 42 weist einen Hohlraum bzw. eine Ausnehmung 42a auf, welche dieselbe, nichtinver tierte, dreidimensionale Form wie der obere Strukturblock 2 aufweist. Nach Anordnen der Bewehrungsstäbe F in der Ausnehmung 42a wird Fertigbeton in die Ausnehmung 42a eingegossen und setzen gelassen, bis der obere Struk turblock 2 im wesentlichen auf dieselbe Art wie die Herstellung des unteren Strukturblocks 1 fertig gestellt ist. With 42 in Fig. 4B, a second form is designated, which is used for a manufacture of the upper structural block 2 . The second shape 42 has a cavity or a recess 42 a, which has the same, non-inverted, three-dimensional shape as the upper structure block 2 . After arranging the reinforcing bars F in the recess 42 a, ready-mixed concrete is poured into the recess 42 a and allowed to set until the upper structure block 2 is completed in essentially the same way as the manufacture of the lower structural block 1 .
Die derart hergestellten, unteren und oberen Strukturblöcke 1, 2 werden um 90° gedreht, um auf ihre Seite gefegt zu werden, wie dies in den Fig. 5A bzw. 5B gezeigt ist. Dies wird beträchtlich die Handhabung und Förderung in der Fabrik und den Transport der Strukturblöcke 1, 2 unter Verwendung eines L-förmigen Hebearms H erleichtern. Eine nicht dargestellte Blockwendema schine wird verwendet, wenn die Strukturblöcke 1, 2 auf ihre Seite gelegt wer den. Ein Paar von Dreharmen der Blockwendemaschine, welche fest gegen die kurzen Seitenwände 13, 22 gepreßt sind, heben jeden Strukturblock 1, 2 an. Dann drehen die Dreharme jeden Strukturblock 1, 2 um 90° und legen ihn auf seine Seite.The lower and upper structural blocks 1 , 2 thus manufactured are rotated 90 ° to be swept to their side, as shown in Figs. 5A and 5B, respectively. This will greatly facilitate the handling and conveyance in the factory and the transportation of the structural blocks 1 , 2 using an L-shaped lifting arm H. A Blockwendema machine, not shown, is used when the structural blocks 1 , 2 are placed on their side. A pair of rotating arms of the block turning machine, which are pressed firmly against the short side walls 13 , 22 , raise each structural block 1 , 2 . Then the rotating arms turn each structure block 1 , 2 by 90 ° and place it on its side.
Die Fig. 6A und 6B sind Darstellungen, welche ein Beispiel einer Förde rung bzw. Beförderung der Strukturblöcke 1, 2 illustrieren, wobei Fig. 6A zeigt, wie jeder Strukturblock 1, 2 durch den Hebearm H angehoben wird, und wobei Fig. 6B einen der Strukturblöcke 1, 2 zeigt, welcher durch einen Förderer C ge fördert wird. Jeder von der Form 41, 42 entfernte Strukturblock 1, 2 wird durch die obengenannte Blockwendemaschine an dem Punkt auf seine Seite gelegt, wo er von den Formen 41, 42 entfernt wird. Dann wird ein horizontales Teil des Hebearmes H, welcher an einem oberhalb fahrenden Kran oder einer ähnlichen Fördereinrichtung festgelegt ist, in den Strukturblock 1, 2 eingeführt und angehoben und zu dem Förderer C bewegt. FIGS. 6A and 6B are diagrams tion an example of a conveyor or carriage of the structure blocks 1, 2 illustrate, FIG. 6A shows how each pattern block 1 is lifted by the lifting arm H 2, and Fig. 6B is a of the structural blocks 1 , 2 shows which is promoted by a conveyor C ge. Each structural block removed from the mold 41, 42 1, 2 is determined by the above-mentioned block turning machine at the point on its side, where it is removed from the forms 41, 42nd Then, a horizontal part of the lifting arm H, which is fixed to a crane or a similar conveying device traveling above, is inserted into the structural block 1 , 2 and raised and moved to the conveyor C.
Der in eine Position oberhalb des Förderers C transportierte Struktur block 1, 2 wird dann auf einer Gestellbasis (Support- bzw. Abstützplatte) 61, welche bereits auf dem Förderer C angeordnet wurde, durch Absenken durch den Hebearm H angeordnet. Der Förderer C trägt den Strukturblock 1, 2 zu einer Verladestation, wo der Strukturblock 1, 2 auf ein Transportfahrzeug 7 ge meinsam mit der Gestellbasis 61 verladen wird.The structure block 1 , 2 transported into a position above the conveyor C is then arranged on a frame base (support plate) 61 , which has already been arranged on the conveyor C, by being lowered by the lifting arm H. The conveyor C carries the structure block 1 , 2 to a loading station, where the structure block 1 , 2 is loaded onto a transport vehicle 7 together with the frame base 61 .
Als nächstes wird der Transport der Strukturblöcke 1, 2 durch das Trans portfahrzeug 7 beschrieben. Die Strukturblöcke 1, 2 werden in einem Gestell 6 für einen Schutz vor einer Verladung auf das Transportfahrzeug 7 angeordnet, um zu verhindern, daß diese während des Transports gedreht und zerstört wer den. Nachfolgend wird das Gestell 6 beschrieben. Fig. 7 ist eine perspek tivische Ansicht des Gestells 6. Wie dies in Fig. 7 gezeigt ist, besteht das Ge stell 6 aus einer Gestellbasis 61 und einem Gestellrahmen 62, welcher entfern bar an der Gestellbasis 61 festgelegt ist. Der Gestellrahmen 62 wird über den Strukturblock 1, 2 gelegt, welcher bereits auf der Gestellbasis 61 angeordnet ist und an der Gestellbasis 61 festgelegt bzw. gesichert, um den Strukturblock 1, 2 während des Transports zu schützen. Next, the transport of the structural blocks 1 , 2 by the trans port vehicle 7 will be described. The structural blocks 1 , 2 are arranged in a frame 6 for protection against loading onto the transport vehicle 7 in order to prevent them from being rotated and destroyed during transport. The frame 6 is described below. Fig. 7 is a perspec asset-side view of the frame 6. As shown in Fig. 7, the Ge stell 6 consists of a frame base 61 and a frame 62 , which is removably fixed to the frame base 61 bar. The rack frame 62 is placed over the structural block 1, 2, which is already arranged on the base frame 61 and fixed to the frame base 61 and secured to the structural block 1, 2 to protect during transport.
Die Gestellbasis 61 weist einen flachen Bodenplattenabschnitt 61a, ein Paar von Seitenplattenabschnitten 61b mit niedrigem Profil, welche sich nach oben von beiden Längsseiten des Bodenplattenabschnitts 61a erstrecken, und Flansche 61c auf, welche sich nach außen von der Oberseite der Seitenplatten abschnitte 61b erstrecken. Der Gestellrahmen 62 umfaßt ein Rahmenwerk bzw. Fachwerk 62a, welches durch Verbinden von Vierkantstahlstäben in eine kastenartige Form konstruiert ist, und ein Paar von Flanschen 62b, welche sich nach außen von beiden Längsseiten des Bodens des Rahmenwerks 62a ent sprechend den Flanschen 61c der Gestellbasis 61 erstrecken.The stand base 61 has a flat bottom plate portion 61 a, a pair of side plate portions 61b with a low profile, which extend upward from both longitudinal sides of the bottom plate portion 61a, and flanges 61c on which portions extending outwardly from the top of the side plates 61 b extend. The frame 62 includes a framework or truss 62 a, which is constructed by connecting square steel bars in a box-like shape, and a pair of flanges 62 b, which outwards from both long sides of the bottom of the frame 62 a accordingly the flanges 61st c extend the frame base 61 .
Der Gestellrahmen 62 wird auf der Gestellbasis 61 angeordnet, wobei die Flansche 62b des ersteren mit den Flanschen 61c der letzteren fluchten. Die Gestellbasis 61 und der Gestellrahmen 62 werden miteinander durch Sichern der Flansche 62b, 61c mit Bolzen B verbunden. Das Rahmenwerk 62a wird mit nach oben vorragenden Heberingen bzw. -ösen 62c eingepaßt, welche nahe den vier Ecken an der Oberseite des Rahmenwerks angeordnet sind. Wenn der Gestellrahmen von der Gestellbasis entfernt wird, wird der Gestell rahmen 62 durch diese Hebeösen 62c hindurchgeführte Seilschlaufen beispielsweise unter Verwendung eines Krans angehoben.The rack frame 62 is arranged on the rack base 61 , the flanges 62 b of the former being flush with the flanges 61 c of the latter. The frame base 61 and the frame 62 are connected to each other by securing the flanges 62 b, 61 c with bolts B. The framework 62 a is fitted with upwardly projecting lifting rings or eyelets 62 c, which are arranged near the four corners at the top of the framework. If the frame frame is removed from the frame base, the frame frame 62 is lifted through these lifting eyes 62 c rope loops, for example using a crane.
Die Fig. 8A und 8B sind Darstellungen, welche Vorbereitungsarbeiten zum Laden jedes Strukturblocks 1, 2 zeigen, wobei Fig. 8A zeigt, wie die Ge stellbasis 61, welche mit einem Strukturblock 1, 2 beladen ist, durch einen Kranhaken S angehoben wird, und wobei Fig. 8B einen Zustand zeigt, nach dem die Gestellbasis 61 auf einer Transportpalette 5 durch den Kran angeord net wurde. Fig. 9 ist eine Darstellung, welche illustriert, wie der Gestellrahmen 62 an der Oberseite bzw. oberhalb der Gestellbasis 61 angeordnet bzw. mon tiert wird. Die Fig. 10A und 10B sind Darstellungen, welche illustrieren, wie der auf dem Gestell 6 montierte Strukturblock 1, 2 auf das Transportfahrzeug 7 verladen wird, wobei Fig. 10A einen Zustand zeigt, nachdem das Kraftfahrzeug 7 zu der auf dem Boden liegenden Transportpalette gezogen wurde, und wobei Fig. 10B einen Zustand zeigt, nachdem der in dem Gestell montierte Struk turblock 1, 2 gemeinsam mit der Palette 5 an Bord des Kraftfahrzeuges 7 gela den wurde. Fig. 11 ist eine teilweise Schnittansicht entlang einer Linie A-A der Fig. 10A zur Darstellung von Funktionsmerkmalen des Fahrzeuges 7.As will be raised the Ge alternate base 61 that is loaded with a structural block 1, 2 by a crane hook S FIGS. 8A and 8B are diagrams showing preparatory work for loading each structural block 1, 2, wherein, FIG. 8A, and wherein Fig. 8B shows a state after the base frame 61 is net angeord on a transport pallet 5 by the crane. Fig. 9 is a diagram illustrating how the frame 62 is arranged on the top or above the frame base 61 or mounted. FIGS. 10A and 10B are diagrams illustrating how the mounted on the frame 6 structural block 1, is loaded onto the transport vehicle 7 2, wherein Fig. 10A shows a state after the motor vehicle 7 drawn to the lying on the ground transport pallet was, and FIG. 10B shows a state after the mounted in the frame structural turblock 1, 2 gela together with the pallet 5 on board the motor vehicle to 7 was. Fig. 11 is a partial sectional view taken along a line AA of Fig. 10A for displaying of features of the vehicle. 7
Unter Bezugnahme auf die Fig. 6B und 8 bis 11 wird nachfolgend ein Verfahren zum Laden jedes Strukturblocks 1, 2 auf das Transportfahrzeug 7 beschrieben. Wenn der auf der Gestellbasis 61 montierte Strukturblock 1, 2 zu der Beladungsstation bzw. -position durch den in Fig. 6B gezeigten Förderer C gebracht wurde, werden vier Kabel bzw. Drähte W (nur zwei Kabel bzw. Drähte W sind in Fig. 8A und 8B gezeigt) an den vier Ecken der Flansche 61c der Gestellbasis 61 festgelegt. Diese vier Drähte W sind an ihren oberen Enden miteinander gebündelt und durch den Haken S des nicht dargestellten Krans ergriffen und die Gestellbasis 61, welche mit dem Strukturblock 1, 2 beladen ist, wird angehoben.A method for loading each structural block 1 , 2 onto the transport vehicle 7 will be described below with reference to FIGS. 6B and 8 to 11. When the structural block 1 , 2 mounted on the frame base 61 is brought to the loading station by the conveyor C shown in FIG. 6B, four cables or wires W (only two cables or wires W are shown in FIG. 8A) and 8B) shown at the four corners of the flanges 61 c of the frame base 61 fixed. These four wires W are bundled together at their upper ends and gripped by the hook S of the crane, not shown, and the frame base 61 , which is loaded with the structural block 1 , 2 , is raised.
Die durch die Drähte W angehobene Gestellbasis 61 wird dann auf der Palette 5, welche auf dem Boden liegt, derart angeordnet, daß kein Teil der Gestellbasis 61 sich seitlich außerhalb der Palette 5 erstreckt, wie dies in Fig. 8 gezeigt ist.The frame base 61 raised by the wires W is then placed on the pallet 5 lying on the floor such that no part of the frame base 61 extends laterally outside the pallet 5 , as shown in FIG .
Die oben genannte Transportpalette 5 ist eine zwischengeschaltete Support- bzw. Abstützvorrichtung, welche zwischen dem Gestell 6 und dem Transportfahrzeug 7 (Fig. 10A und 10B) angeordnet wird, wenn das Gestell 6 auf das Fahrzeug 7 verladen wird. Die Palette 5 umfaßt ein Paar von Abstütz schienen 51, welche sich entlang der Längsachse des Fahrzeugs 7 (oder einer Richtung normal auf die Ebene der Fig. 8A und 8B) erstrecken, wenn sie an Bord verladen wird, und obere und untere Deckbretter bzw. -balken 52, welche einzeln die Supportschienen 51 überrücken. Eine U-förmige Nut 53 ist in der äußeren Seitenoberfläche von jeder Supportschiene 51 entlang ihrer Längsachse ausgebildet. Die Nuten 53 in den Supportschienen 51 werden verwendet, wenn die Palette 5, welche den in dem Gestell montierten Struktur block 1, 2 trägt, auf das Fahrzeug 7 verladen wird.The above-mentioned transport pallet 5 is an intermediate support device which is arranged between the frame 6 and the transport vehicle 7 ( FIGS. 10A and 10B) when the frame 6 is loaded onto the vehicle 7 . The pallet 5 includes a pair of support rails 51 which extend along the longitudinal axis of the vehicle 7 (or a direction normal to the plane of FIGS. 8A and 8B) when loaded on board, and upper and lower deck boards or -bars 52 , which individually overlap the support rails 51 . A U-shaped groove 53 is formed in the outer side surface of each support rail 51 along its longitudinal axis. The grooves 53 in the support rails 51 are used when the pallet 5 , which carries the structure block 1 , 2 mounted in the frame, is loaded onto the vehicle 7 .
Wenn die mit dem Strukturblock 1, 2 beladene Gestellbasis 61 auf der Palette 5 angeordnet wurde, wie dies in Fig. 8B gezeigt ist, werden die Drähte W von der Gestellbasis 61 gelöst. Der Gestellrahmen 62, welcher durch den Kranhaken S und die Drähte W aufgehängt ist, wird dann auf der Gestellbasis 61 angeordnet, so daß der Gestellrahmen 62 den Strukturblock 1, 2 umgibt, und es werden dann die oberen und unteren Flansche 62b, 61c, welche in Kontakt miteinander gebracht wurden und miteinander ausgerichtet wurden, wie dies mit strichlierten Linien gezeigt ist, miteinander durch Bolzen bzw. Schrauben B verbunden, wie dies in Fig. 9 gezeigt ist. Zu diesem Zeitpunkt ist der Strukturblock 1, 2 vollkommen in dem Gestell angeordnet bzw. gesetzt. Die Kabel W werden von dem Gestellrahmen 62 entfernt, um die Vorbereitungs arbeit für ein Laden des Strukturblocks 1, 2 auf das Fahrzeug 7 zu vervoll ständigen.When the frame base 61 loaded with the structural block 1 , 2 has been arranged on the pallet 5 , as shown in FIG. 8B, the wires W are detached from the frame base 61 . The frame 62 , which is suspended by the crane hook S and the wires W, is then placed on the frame base 61 so that the frame 62 surrounds the structural block 1 , 2 , and then the upper and lower flanges 62 b, 61 c , which have been brought into contact with each other and aligned with each other as shown in broken lines, are connected to each other by bolts B as shown in FIG. 9. At this time, the structure block 1 , 2 is completely arranged or set in the frame. The cables W are removed from the frame 62 to complete the preparatory work for loading the structural block 1 , 2 onto the vehicle 7 .
Es wird dann der im Gestell montierte Strukturblock 1, 2, welcher auf die Palette 5 montiert ist, auf das Kraftfahrzeug 7 verladen, wie dies in den Fig. 10A und 10B gezeigt wird. Das Fahrzeug 7 ist ein Sattelschlepper mit sehr niedriger Ladefläche, welcher getrennte rechte und linke Achsen und getrennte rechte und linke, lasttragende Ladeflächen 71 aufweist, wie dies in den Fig. 10A und 10B gezeigt ist. Dieses Fahrzeug 7 weist die Fähigkeit auf, die geladene Palette 5 anzuheben und abzusenken, so daß der Abstand zwischen dem Boden der Palette 5 und der Straßenoberfläche zwischen 4 cm und 30 cm variiert werden kann.The structural block 1 , 2 which is mounted in the frame and which is mounted on the pallet 5 is then loaded onto the motor vehicle 7 , as is shown in FIGS. 10A and 10B. Vehicle 7 is a very low bed semi-trailer truck having separate right and left axles and separate right and left load carrying beds 71 as shown in FIGS. 10A and 10B. This vehicle 7 has the ability to raise and lower the loaded pallet 5 so that the distance between the bottom of the pallet 5 and the road surface can be varied between 4 cm and 30 cm.
Wie dies in Fig. 11 gezeigt ist, umfaßt jede(r) der lastaufnehmenden Träger bzw. Ladeflächen 71 eine Bodenplatte 72, welche sich parallel zu der Längsachse des Fahrzeugs 7 erstreckt, ein Paar von Seitenplatten 73, welche sich vertikal nach oben von beiden Seiten der Bodenplatten 72 relativ zu ihrer Breitenrichtung (oder Richtung normal auf die Ebene der Fig. 11) erstrecken, eine obere Platte 74, welche sich zwischen den oberen Enden des Paares von Seitenplatten 73 erstreckt, einen Hebemechanismus 75, welcher in einem Maschinenraum 70 angeordnet ist, welcher durch die Bodenplatte 72, die Sei tenplatten 73 und die obere Platte 74 umschlossen ist. Weiters ragt ein Paar von die Palette abstützenden Platten 72a horizontal von den inneren Enden der Bodenplatten 72 von den beiden rechten und linken, lastaufnehmenden Ladeflächen bzw. Trägern 71 vor. Der Abstand zwischen den rechten und lin ken, Paletten-abstützenden Platten 72a wird ein wenig größer als der Abstand zwischen den Böden der U-förmigen Nuten gemacht, so daß die die Palette abstützenden Platten 72a in die rechten und linken, U-förmigen Nuten 53 eintauchen können.As shown in Fig. 11, each of the load-bearing beams 71 includes a bottom plate 72 which extends parallel to the longitudinal axis of the vehicle 7 , a pair of side plates 73 which extend vertically upward from both sides of the bottom plates 72 extend relative to their width direction (or direction normal to the plane of FIG. 11), an upper plate 74 which extends between the upper ends of the pair of side plates 73 , a lifting mechanism 75 which is arranged in a machine room 70 , which is enclosed by the bottom plate 72 , the tenplatten 73 and the upper plate 74 . Furthermore, a pair of the pallet-supporting plates 72 a protrude horizontally from the inner ends of the base plates 72 from the two right and left load-bearing loading areas or beams 71 . The distance between the right and left ken, pallet-supporting plates 72 a is made a little larger than the distance between the bottoms of the U-shaped grooves, so that the pallet-supporting plates 72 a in the right and left, U-shaped Grooves 53 can immerse.
Der Hebemechanismus 75, welcher in dem Maschinenraum 70 von jeder lastaufnehmenden Deckfläche 71 installiert ist, umfaßt eine Vielzahl von Nocken bzw. Mitnehmern 76, welche eine in Seitenansicht dreieckige Form aufweisen und in einer Reihe entlang der Längsachse des Fahrzeugs 7 angeordnet sind, eine Vielzahl von Zylinder-Betätigungseinrichtungen 77, welche den einzelnen Nocken 76 für ein Antreiben derselben zugeordnet sind, und mit Reifen ausgestattete Räder 78, welche mit den Nocken 76 verbunden sind. Jeder der dreieckförmigen Nocken 76 ist so angeordnet, daß seine Basis (Bodenseite) im wesentlichen parallel zu der Straßenoberfläche liegt und ist schwenkbar an einer Stützwelle 76a angeordnet, welche sich zwischen den Seitenplatten 73 in einem linken Eckabschnitt von jedem Nocken 76 in Fig. 11 erstreckt. Die Räder 78 sind drehbar an Achsen 76b montiert, welche einzeln mit rechten Eckabschnitten der Nocken 76 verbunden sind. The lifting mechanism 75 , which is installed in the machine room 70 of each load-bearing cover surface 71 , comprises a plurality of cams 76 , which have a triangular shape in side view and are arranged in a row along the longitudinal axis of the vehicle 7 , a plurality of Cylinder actuators 77 associated with the individual cams 76 for driving the same and tires 78 equipped with tires connected to the cams 76 . Each of the triangular cams 76 is arranged so that its base (bottom side) is substantially parallel to the road surface and is pivotally mounted on a support shaft 76 a which is located between the side plates 73 in a left corner portion of each cam 76 in Fig. 11th extends. The wheels 78 are rotatably mounted on axles 76 b, which are individually connected to right corner sections of the cams 76 .
Jede der Zylinder-Betätigungseinrichtungen 77 umfaßt einen Luftzylinder 77a, welcher parallel zur Längsachse fixiert ist, und eine Kolbenstange 77b, welche von dem Luftzylinder 77a zu dem Nocken 76 vorragt. Das äußerste Ende von jeder Kolbenstange 77b ist in Kontakt mit einer geneigten Kante des entsprechenden Nockens 76 über seiner Stützwelle 76a gehalten, so daß eine Drehbewegung des Nockens 76 um die Abstützwelle 76a im Gegenuhr zeigersinn vermieden bzw. verhindert wird.Each of the cylinder actuators 77 comprises an air cylinder 77 a, which is fixed parallel to the longitudinal axis, and a piston rod 77 b, which projects from the air cylinder 77 a to the cam 76 . The extreme end of each piston rod 77 b is held in contact with an inclined edge of the corresponding cam 76 above its support shaft 76 a, so that a rotational movement of the cam 76 around the support shaft 76 a in the counterclockwise direction is avoided or prevented.
Die Kolbenstangen 77b bewegen sich aus den entsprechenden Luftzylin dern 77a, wenn die Zylinder-Betätigungseinrichtungen 77 betätigt werden. Daraus resultierend schwenken die einzelnen Nocken 76 in einer Richtung im Uhrzeigersinn um ihre entsprechenden Abstützwellen 76a, wodurch bewirkt wird, daß die einzelnen, lastaufnehmenden Ladeflächen 71 angehoben werden. Wenn die Zylinder-Betätigungseinrichtungen 77 in der Gegenrichtung betätigt werden, werden die Kolbenstangen 77b in die entsprechenden Luftzylinder 77a zurückgezogen und es wird bewirkt, daß sich die lastaufnehmenden Deckflächen 71 absenken. Die rechten und linken, lastaufnehmenden Deckflä chen 71 des Fahrzeugs 7 können durch Betätigen der Zylinder-Betätigungsein richtungen 77 in ihren Vorwärts- und Rückwärtsrichtungen, wie oben beschrie ben, angehoben und abgesenkt werden, und die Palette 5, welche den auf dem Gestell montierten Strukturblock 1, 2 trägt, kann mit diesem Deck- bzw. Ladeflächen-Hebe- und -Absenkvorgang auf das Fahrzeug geladen und von diesem entladen werden.The piston rods 77 b move from the corresponding Luftzylin countries 77 a when the cylinder actuators 77 are actuated. As a result, the individual cams 76 pivot in a clockwise direction around their corresponding support shafts 76 a, which causes the individual load-bearing loading areas 71 to be raised. When the cylinder actuators 77 are actuated in the opposite direction, the piston rods 77 b are retracted into the corresponding air cylinders 77 a and the load-bearing cover surfaces 71 are caused to lower. The right and left load-bearing deck surfaces 71 of the vehicle 7 can be raised and lowered by operating the cylinder actuators 77 in their forward and backward directions as described above, and the pallet 5 , which is the structural block mounted on the frame 1 , 2 carries, can be loaded onto and unloaded from the vehicle with this deck or loading area lifting and lowering process.
Ein detailliertes Verfahren eines Ladens des in dem Gestell montierten Strukturblocks 1, 2, welcher auf der Palette 5 angeordnet ist, wird unten unter Bezugnahme auf die Fig. 10A und 10B diskutiert. Zuerst wird die Höhe der ent sprechenden, lastaufnehmenden Ladeflächen 71 durch Betätigen der Zylinder- Betätigungseinrichtungen 77 derart eingestellt, daß sowohl die rechten als auch linken, Paletten-abstützenden Platten 72a in derselben Höhe mit den U- förmigen Nuten 53 der Palette 5 ausgerichtet sind. Das Fahrzeug 7 wird dann nach hinten bewegt, so daß die Palette 5 unmittelbar zwischen den rechten und linken, lastaufnehmenden Deck- bzw. Ladeflächen 71 angeordnet ist. Wenn das Fahrzeug 7 in seiner korrekten Position angehalten wird, werden die rechten und linken, Paletten-abstützenden Platten 72a geeignet in den ent sprechenden, U-förmigen Nuten 53 der Palette 5 angeordnet, wie dies in Fig. 10A gezeigt ist.A detailed method of loading the rack-mounted structural block 1 , 2 located on the pallet 5 is discussed below with reference to FIGS. 10A and 10B. First, the height of the corresponding load-bearing loading areas 71 is adjusted by actuating the cylinder actuating devices 77 such that both the right and left, pallet-supporting plates 72 a are aligned at the same height with the U-shaped grooves 53 of the pallet 5 . The vehicle 7 is then moved to the rear so that the pallet 5 is arranged directly between the right and left, load-bearing deck or loading surfaces 71 . When the vehicle 7 is stopped in its correct position, the right and left, pallet-supporting plates 72 a are suitably arranged in the corresponding U-shaped grooves 53 of the pallet 5 , as shown in Fig. 10A.
Nachfolgend werden die Zylinder-Betätigungseinrichtungen 77 in Betrieb genommen, um ein Ausfahren der Kolbenstangen 77b zu bewirken. Als eine Konsequenz drehen sich die einzelnen Nocken 76 im Uhrzeigersinn (wie in Fig. 11 dargestellt) um die entsprechenden Abstützwellen 76a. Dies bewirkt, daß die rechten und linken, lasttragenden Deck- bzw. Ladeflächen 71 angehoben werden, und es wird die Palette 5, welche durch die Paletten-abstützenden Platten 72a abgestützt wird, vom Boden in eine für eine Lieferung geeignete Position angehoben. Der Strukturblock 1, 2, welcher durch das Gestell 6 geschützt ist, wird durch das Fahrzeug 7 zu einer Baustelle in diesem Zustand transportiert.Subsequently, the cylinder actuators 77 are taken into operation to extension of the piston rods 77 to effect b. As a consequence, the individual cams 76 rotate clockwise (as shown in Fig. 11) around the corresponding support shafts 76 a. This causes the right and left load-bearing deck or loading areas 71 to be raised, and the pallet 5 , which is supported by the pallet-supporting plates 72 a, is raised from the floor into a position suitable for delivery. The structure block 1 , 2 , which is protected by the frame 6 , is transported by the vehicle 7 to a construction site in this state.
Kabel bzw. Seile W sind zwischen den Heberingen 62c an der Oberseite des Gestells 6 und Ringelementen 74a, welche von den Deckplatten 74 der Deckflächen 71 vorragen, gespannt, um zu verhindern, daß das Gestell 6 während des Transports zur Seite kippt. Eine Winde bzw. Spanneinrichtung W1 ist an jedem Kabel W montiert, um die Einstellung eines Spanngrades des Kabels W zu ermöglichen. Derart können die Kabel W sicher in geeignete Zu stände gespannt bzw. gedehnt werden.Cables or ropes W are stretched between the lifting rings 62 c on the top of the frame 6 and ring elements 74 a, which protrude from the cover plates 74 of the cover surfaces 71 , to prevent the frame 6 from tipping to the side during transport. A winch or tensioning device W1 is mounted on each cable W in order to enable the degree of tensioning of the cable W to be set. In this way, the cables W can be securely tensioned or stretched to suitable states.
Nachfolgend wird ein Verfahren zum Entladen des Strukturblocks 1, 2, welcher an der Baustelle angelangt ist, beschrieben. Fig. 12 ist eine Seitenan sicht eines lastaufnehmenden Montagegestells bzw. Hebels (Drehgestell) 8, welches(r) am Boden montiert ist, wenn der Strukturblock 1, 2 von dem Fahr zeug 7 entladen wird. Wie dies in Fig. 12 gezeigt ist, umfaßt das lastaufneh mende Montagegestell 8 eine Gestellbasis 81, welche von einem im allge meinen rechteckigen Rahmen gebildet ist, eine horizontale Welle 82, welche sich zwischen gegenüberliegenden Rahmenelementen der Gestellbasis 81 erstreckt, ein lastaufnehmendes Teil 83, welches schwenkbar an der hori zontalen Welle 82 festgelegt ist, und ein Palettenelement (lastschützendes Element) 84, welches zwischen den Rahmenelementen außerhalb des Schwenkbereichs des lastaufnehmenden Teils 83 angeordnet ist.A method for unloading the structural block 1 , 2 which has reached the construction site is described below. Fig. 12 is a Seitenan view of a load-bearing mounting frame or lever (bogie) 8 , which (r) is mounted on the ground when the structural block 1 , 2 is unloaded from the vehicle 7 . As shown in Fig. 12, the load-bearing mounting frame 8 comprises a frame base 81 which is formed by a generally rectangular frame, a horizontal shaft 82 which extends between opposite frame members of the frame base 81 , a load-bearing part 83 , which is pivotally attached to the horizontal shaft 82 , and a pallet element (load-protecting element) 84 which is arranged between the frame elements outside the pivoting range of the load-bearing part 83 .
Die Gestellbasis 81 ist mit einer Vielzahl von Dornen bzw. Stacheln 81a an ihrem Boden versehen. Wenn das lastaufnehmende Montagegestell 8 auf dem Boden angeordnet ist, graben sich die Dorne 81a sicher in den Grund ein, um eine stabile Positionierung des lastaufnehmenden Montagegestells 8 sicher zustellen.The frame base 81 is provided with a plurality of thorns or spikes 81 a on its bottom. If the load-bearing mounting frame 8 is arranged on the floor, the mandrels 81 a dig themselves securely into the ground in order to ensure stable positioning of the load-bearing mounting frame 8 .
Das lastaufnehmende Teil 83 ist in Seitenansicht in einer L-förmigen Form konstruiert, beinhaltend ein erstes Element 83a und ein zweites Element 83b, welche unter rechten Winkeln miteinander in eine einteilige Struktur verbunden sind. Wenn der auf dem Gestell montierte Strukturblock 1, 2 unter Verwendung eines Krans entladen wird, wird eine Bodenkante des Gestells 6 mit einem Schnitt zwischen den ersten und zweiten Elementen 83a, 83b des lastaufnehmenden Teils 83 ausgerichtet und das lastaufnehmende Teil 83 schwenkt um die horizontale Welle 82, wenn das Gestell 6 im Uhrzeigersinn verschwenkt bzw. gedreht wird (wie dies in Fig. 12 gezeigt ist). Dieser Schwenkvorgang des lastaufnehmenden Teils 83 verhindert oder dämpft Stoß beanspruchungen auf den Strukturblock 1, 2 während des Entladevorgangs.The load-bearing part 83 is constructed in a side view in an L-shaped form, including a first element 83 a and a second element 83 b, which are connected at right angles to one another in a one-piece structure. If the structural block 1 , 2 mounted on the frame is unloaded using a crane, a bottom edge of the frame 6 is aligned with a cut between the first and second elements 83 a, 83 b of the load-bearing part 83 and the load-bearing part 83 pivots about that horizontal shaft 82 when the frame 6 is rotated clockwise (as shown in Fig. 12). This pivoting process of the load-bearing part 83 prevents or dampens shock loads on the structural block 1 , 2 during the unloading process.
Die Montagebasis 81 ist mit einem Anschlag- bzw. Stopelement 81b auf der linken Seite des ersten Elements 83a in Fig. 12 ausgebildet. Der Anschlag 81b ist derart angeordnet, daß das erste Element 83a einen speziellen Winkel α relativ zu der horizontalen Richtung einschließt, wenn das erste Element 83a in Kontakt mit dem Anschlag 81b gelangt. Derart wird dem lastaufnehmenden Teil 83 nicht gestattet, in der Gegenuhrzeigerrichtung (wie in Fig. 12 illustriert) über diesen Winkel hinaus zu schwenken.The mounting base 81 is formed with a stop element 81 b on the left side of the first element 83 a in FIG. 12. The stop 81 b is arranged such that the first element 83 a encloses a special angle α relative to the horizontal direction when the first element 83 a comes into contact with the stop 81 b. In this way, the load-bearing part 83 is not permitted to pivot in the counterclockwise direction (as illustrated in FIG. 12) beyond this angle.
In der vorliegenden Ausführungsform sind die Abmessungen und die Position des Anschlags 81b so eingestellt, daß der Winkel zwischen dem ersten Element 83a und der horizontalen Ebene etwa 30° wird, wenn das lastaufnehmende Teil 83 die Grenze seiner Schwenkbewegung in Gegen uhrzeigerrichtung erreicht hat. Das lastaufnehmende Teil 83 ist auch um die horizontale Welle 82 bis zu etwa 90° in Richtung des Uhrzeigersinns von der Position schwenkbar, wo das erste Element 83a in Kontakt mit dem Anschlag 81b ist.In the present embodiment, the dimensions and the position of the stop 81 b are set such that the angle between the first element 83 a and the horizontal plane becomes approximately 30 ° when the load-bearing part 83 has reached the limit of its pivoting movement in the counterclockwise direction. The load-bearing part 83 is also pivotable about the horizontal shaft 82 up to about 90 ° in the clockwise direction from the position where the first element 83 a is in contact with the stop 81 b.
Das Palettenelement 84 ist nach oben durch ein elastisches Element, wie beispielsweise eine Schraubenfeder, belastet bzw. vorgespannt, so daß es normalerweise über die Montagebasis 81 in einem gewissen Ausmaß vorragt. Wenn das Gestell 6 auf das Palettenelement 84 aufgelegt wird, zieht es sich in die Montagebasis 81 entgegen einer durch das elastische Element ausgeübten Druckkraft zurück. Wenn das den Strukturblock 1, 2 enthaltende Gestell 6, welches auf dem lastaufnehmenden Teil 83 angeordnet ist, um die horizontale Welle 82 verschwenkt wird, bis das Gestell 6 in Kontakt mit dem Palettenelement 84 gelangt, so dämpft das sich in die Montagebasis 81 zurück ziehende Palettenelement 84 Stoßbeanspruchungen, welche gegebenenfalls auf den Strukturblock 1, 2 ausgeübt werden können, wenn das Gestell 6 auf seine Seite gelegt wird.The pallet member 84 is biased upward by an elastic member such as a coil spring so that it normally protrudes beyond the mounting base 81 to a certain extent. When the frame 6 is placed on the pallet element 84 , it retracts into the mounting base 81 against a compressive force exerted by the elastic element. If the frame 6 containing the structural block 1 , 2 , which is arranged on the load-bearing part 83 , is pivoted about the horizontal shaft 82 until the frame 6 comes into contact with the pallet element 84 , the damping retracts into the mounting base 81 Pallet element 84 impact loads, which can optionally be exerted on the structural block 1 , 2 when the frame 6 is placed on its side.
Ein quadratisches Holz 85 wird an der rechten Seite des lastaufneh menden Montagegestells 8 angeordnet, wie dies in Fig. 12 gezeigt ist. Dieses quadratische Holz bzw. der quadratische Holzbalken 85, welcher auf dem Boden angeordnet ist, weist dieselbe Höhe wie die Montagebasis 81 über dem Bodenniveau auf, so daß das auf die Seite unter Verwendung des last aufnehmenden Montagegestells 8 gelegte Gestell 6 in einer korrekten, horizon talen Position angeordnet ist.A square wood 85 is arranged on the right side of the load-bearing mounting frame 8 , as shown in Fig. 12. This square wood or square wooden beam 85 , which is arranged on the floor, has the same height as the mounting base 81 above the floor level, so that the frame 6 laid on the side using the load-bearing mounting frame 8 in a correct, horizon tal position is arranged.
Die Fig. 13A bis 13C sind Darstellungen, welche das Verfahren des Ent ladens des den Strukturblock 1, 2 enthaltenden Gestells 6 illustrieren, wobei Fig. 13A einen Zustand zeigt, in welchem das Gest 84800 00070 552 001000280000000200012000285918468900040 0002019931231 00004 84681ell 6, welches den Struk turblock 1, 2 enthält, durch einen Haken S eines nicht dargestellten Krans an gehoben wird, wobei Fig. 13B einen Zustand zeigt, in welchem das durch den Kranhaken S angehobene Gestell 6 gekippt bzw. geneigt wird, und wobei Fig. 13C einen Zustand zeigt, in welchem das durch den Kranhaken S angehobene Gestell 6 auf dem lastaufnehmenden Montagegestell 8 angeordnet ist. FIGS. 13A to 13C are diagrams showing charging of illustrate the process of unloading the structural block 1, 2 containing frame 6, FIG. 13A shows a state in which the knitted 84800 00070 552 001000280000000200012000285918468900040 0002019931231 00004 84681ell 6 which the structural includes turblock 1 , 2 , by a hook S of a crane, not shown, FIG. 13B shows a state in which the frame 6 raised by the crane hook S is tilted, and FIG. 13C shows a state , in which the frame 6 raised by the crane hook S is arranged on the load-bearing mounting frame 8 .
Wenn das den in dem Gestell montierten Strukturblock 1, 2 tragende Fahrzeug 7 an der Baustelle angekommen ist, wird die Transportpalette 5 zuerst auf dem Boden aufgelegt, wobei die in Fig. 10 gezeigten Schritte in der umgekehrten Reihenfolge durchgeführt werden (Fig. 10B zu Fig. 10A). Zwei Kabel W, welche jeweils mit zwei Heberingen bzw. Ösen 62c an jedem gegen überliegenden Ende des Gestells 6 verbunden sind, werden an dem Kranhaken S eingehängt und es wird das Gestell 6 angehoben, wie dies in Fig. 13A gezeigt ist.When the vehicle 7 carrying the structural block 1 , 2 mounted in the frame has arrived at the construction site, the transport pallet 5 is first placed on the floor, the steps shown in FIG. 10 being carried out in the reverse order ( FIG. 10B to FIG . 10A). Two cables W, which are each connected to two lifting rings or eyelets 62 c at each opposite end of the frame 6 , are hung on the crane hook S and the frame 6 is raised, as shown in FIG. 13A.
Das Gestell 6 wird dann im Uhrzeigersinn durch Betätigen einer Winde W1, welche an jedem Kabel W festgelegt ist, wie dies in Fig. 13B gezeigt ist, gekippt, zu einer Position bewegt, wo die unterste Bodenkante des Gestells 6 über dem lastaufnehmenden Teil 83 des lastaufnehmenden Montagegestells 8 angeordnet ist und auf das lastaufnehmende Teil 83 gesenkt, so daß die unterste Bodenkante des Gestells 6 nach unten zu dem Schnitt zwischen den ersten und zweiten Elementen 83a, 83b des lastaufnehmenden Teils 83 gleitet, wie dies in Fig. 13C gezeigt ist.The frame 6 is then moved clockwise by operating a winch W1 attached to each cable W as shown in Fig. 13B to a position where the bottom bottom edge of the frame 6 over the load-bearing part 83 of the load-bearing mounting frame 8 is arranged and lowered onto the load-bearing part 83 , so that the bottom bottom edge of the frame 6 slides down to the cut between the first and second elements 83 a, 83 b of the load-bearing part 83 , as shown in Fig. 13C is.
Der Haken S wird langsam durch Betätigen des Krans abgesenkt und daraus resultierend wird das Gestell 6, welches den Strukturblock 1, 2 enthält und welches durch das lastaufnehmende Teil 83 abgestützt ist, weiter um die horizontale Welle 82 gekippt und liegt schließlich auf dem lastaufnehmenden Gestell 8 und dem quadratischen Holz 85 in einer horizontalen Position auf, wie dies durch abwechselnde, strichlierte Linien in Fig. 13C gezeigt ist. Das Gestell 6 wird in dieser horizontalen Position unter Verwendung von speziellen Werkzeugen und Einrichtungen, welche nicht dargestellt sind, von dem Stru kturblock 1, 2 entfernt. Der Strukturblock 1, 2 wird dann in einer bereits ausge hobenen Grube angeordnet, um ein Untergeschoß bzw. Kellergeschoß zu bilden.The hook S is slowly lowered by operating the crane and as a result the frame 6 , which contains the structural block 1 , 2 and which is supported by the load-bearing part 83 , is further tilted about the horizontal shaft 82 and finally lies on the load-bearing frame 8 and the square wood 85 in a horizontal position as shown by alternate dashed lines in Fig. 13C. The frame 6 is removed from the structure block 1 , 2 in this horizontal position using special tools and devices which are not shown. The structure block 1 , 2 is then arranged in an already excavated pit to form a basement or basement.
Es wird nun ein detailliertes Verfahren einer Konstruktion des Unter- bzw. Kellergeschosses auf der Baustelle beschrieben. Eine vertikale Grube bzw. Ausnehmung, welche wenigstens den unteren Strukturblock 1 aufnehmen kann, sollte auf der Baustelle vor der Installation der Untergeschoßeinheit 10 ausgehoben worden sein. Ein Steinfundament wird durch Anordnen von zerkleinertem Stein auf dem Boden der Grube ausgebildet. Danach wird der untere Strukturblock 1 mit seinem Boden nach unten auf dem Steinfundament positioniert. Das obengenannte Dichtelement 3 wird auf den umgebenden Wän den 12 des unteren Strukturblocks 1 angeordnet und es wird der obere Strukturblock 2 auf dem unteren Strukturblock 1 aufgerichtet, um die Unterge schoßeinheit 10 in der Grube zu vervollständigen.A detailed method of constructing the basement or basement on the construction site will now be described. A vertical pit or recess, which can at least accommodate the lower structural block 1 , should have been excavated at the construction site before installing the basement unit 10 . A stone foundation is formed by placing crushed stone on the bottom of the pit. The lower structural block 1 is then positioned with its bottom facing down on the stone foundation. The above-mentioned sealing member 3 is placed on the surrounding WAEN the structure 12 of the lower block 1 and it is the upper block structure erected on the lower structural unit 1 2 to the underweight body skirt unit to complete in the pit 10th
Es kann eine Verkleidung entlang des Dichtelements 3, welches zwi schen dem unteren Strukturblock 1 und dem oberen Strukturblock 2 angeordnet ist, von der Innenseite der Untergeschoßeinheit 10 durchgeführt werden, um eine verbesserte Wasserabdichtung zur Verfügung zu stellen und dadurch in einer zuverlässigeren Weise ein Eindringen von Wasser zu verhindern.A lining along the sealing element 3 , which is arranged between the lower structural block 1 and the upper structural block 2 , can be carried out from the inside of the basement unit 10 in order to provide improved water sealing and thereby penetration in a more reliable manner To prevent water.
Weiters kann eine spezielle Anzahl von Reibungspfählen bzw. Reibungs stempeln in den Boden der Grube vor dem Anordnen des unteren Struktur blocks 1 in seiner Position eingetrieben werden. Dies wird erlauben, daß ein oberer Teil der Untergeschoßeinheit 10 als ein Fundament verwendet wird, welches sicher eine über dem Bodenniveau zu bauende Struktur abstützen kann.Furthermore, a special number of friction piles or friction stamps can be driven into position in the bottom of the pit before arranging the lower structure block 1 . This will allow an upper part of the basement unit 10 to be used as a foundation which can surely support a structure to be built above ground level.
Fig. 14 ist eine perspektivische Explosionsdarstellung, welche eine Zweiraum-Untergeschoßstruktur gemäß einer zweiten Ausführungsform der Erfindung illustriert, in welcher eine zweite Untergeschoßeinheit 10b benachbart einer ersten Untergeschoßeinheit 10a installiert wird. Fig. 15 ist eine pers pektivische Ansicht, welche die Zweiraum-Untergeschoßstruktur illustriert, in welcher die zweite Untergeschoßeinheit 10b benachbart der ersten Unterge schoßeinheit 10a installiert wurde. Fig. 16 ist eine vertikale Schnittansicht entlang B-B von Fig. 15. Als eine Festlegung in der in dieser Beschreibung nachfolgenden Erläuterung wird die Richtung parallel zu der in Fig. 14 und 15 gezeigten X-Achse als die Querrichtung und die Richtung parallel zu der Y- Richtung als die Längsrichtung bezeichnet. Wie in diesen Figuren dargestellt, sind die benachbarte, erste Untergeschoßeinheit 10a und die zweite Unterge schoßeinheit 10b auf einer gemeinsamen Fundamentplatte 100 festgelegt, welche eine bestimmte Dicke und eine rechteckige Form in der Draufsicht aufweist. Fig. 14 is a perspective exploded view showing a two-room basement structure illustrated according to a second embodiment of the invention, in which a second basement unit 10 b adjacent to a first basement unit 10 is installed a. Fig. 15 is a perspective view illustrating the two-room basement structure in which the second basement unit 10 b has been installed adjacent to the first basement unit 10 a. FIG. 16 is a vertical sectional view along BB of FIG. 15. As a determination in the explanation hereinafter in this description, the direction parallel to the X-axis shown in FIGS. 14 and 15 becomes the transverse direction and the direction parallel to the Y. - Direction referred to as the longitudinal direction. As shown in these figures, the adjacent, first basement unit 10 a and the second basement unit 10 b are fixed on a common foundation plate 100 , which has a certain thickness and a rectangular shape in plan view.
Die erste Untergeschoßeinheit 10a umfaßt einen ersten, unteren Struk turblock 1a und einen ersten, oberen Strukturblock 2a, welcher auf dem ersten, unteren Strukturblock 1a aufgerichtet ist. In ähnlicher Weise umfaßt die zweite Untergeschoßeinheit 10b einen zweiten, unteren Strukturblock 1b und einen zweiten, oberen Strukturblock 2b, welcher auf der Oberseite des zweiten, unteren Strukturblocks 1b aufgerichtet ist. Die Zweiraum-Untergeschoßstruktur wird durch Installation der Untergeschoßeinheit 10a und der zweiten Unterge schoßeinheit 10b nebeneinander auf der Fundamentplatte 100 konstruiert.The first basement unit 10 a includes a first, lower structural turblock 1 a and a first upper structural block 2 a, which is erected on the first lower structural block 1 a. Similarly, the second basement unit 10 b comprises a second, lower structural block 1 b and a second, upper structural block 2 b, which is erected on the top of the second, lower structural block 1 b. The two-room basement structure is constructed by installing the basement unit 10 a and the second basement unit 10 b side by side on the foundation plate 100 .
Obwohl der erste, obere Strukturblock 2a und der zweite, obere Struktur block 2b im wesentlichen dieselbe Konstruktion wie der obere Strukturblock 2 der ersten Ausführungsform aufweisen, weisen der erste, obere Strukturblock 2a und der zweite, obere Strukturblock 2b jeweils einen rechteckigen, unteren Ausschnitt 201 in den Bodenenden ihrer zueinander gerichteten Wände auf, welche sich parallel zu der Längsrichtung erstrecken. In ähnlicher Weise weisen der erste, untere Strukturblock 1a und der zweite, untere Strukturblock 1b jeweils einen oberen Ausschnitt 202 in den oberen Enden ihrer zueinander gerichteten Wände an einer Position entsprechend jenem unteren Ausschnitt 201 auf. Wenn der erste und zweite, obere Strukturblock 2a, 2b auf dem ersten und zweiten, unteren Strukturblock 1a, 1b aufgerichtet bzw. aufgestapelt werden oder wenn die erste Untergeschoßeinheit 10a und die zweite Untergeschoßeinheit 10b vervollständigt wurden, wird eine rechteckige Türöffnung (Öffnungsabschnitt) 200 durch den unteren Ausschnitt 201 und den oberen Ausschnitt 202 in den zueinander gerichteten Wänden ausgebildet.Although the first, upper structural block 2 a and the second, upper structural block 2b has substantially the same construction as the upper structural block 2 of the first embodiment have, 2 comprise the first, upper structural block a and the second, upper structural block 2 b each have a rectangular , lower cutout 201 in the bottom ends of their mutually facing walls, which extend parallel to the longitudinal direction. Similarly, the first, lower structural block 1a and the second, lower structural block 1b each have an upper cutout 202 in the upper ends of their mutually facing walls at a position corresponding to that lower cutout 201 . If the first and second, upper structural block 2 a, 2 b are erected or stacked on the first and second, lower structural block 1 a, 1 b or if the first basement unit 10 a and the second basement unit 10 b have been completed, a rectangular becomes Door opening (opening section) 200 formed by the lower cutout 201 and the upper cutout 202 in the mutually facing walls.
Die Fundamentplatte 100 liegt in Form einer flachen Platte, bestehend aus Beton, und mit einer bestimmten Dicke vor und die Abmessungen der selben in der Draufsicht sind geringfügig größer eingestellt als eine Summe der ersten und zweiten Untergeschoßeinheiten 10a und 10b. Auf der Oberfläche der Fundamentplatte 100 sind eine Vielzahl von Abstandhaltern 101, welche aus einem druckfesten Gummi als elastische Elemente ausgebildet sind, gleichmäßig verteilt und es wird gemischter bzw. gekneteter Mörtel 102 (in Fig. 14 punktiert) ausgebracht bzw. aufgeschichtet, um eine Schicht auszubilden, welche eine Dicke aufweist, daß nur die Oberseiten der Abstandhalter 101 geringfügig bedeckt sind. Die erste und zweite Untergeschoßeinheit 10a, 10b werden aufeinanderfolgend auf die Fundamentplatte 100 in einem derartigen Zustand abgesenkt, woraus resultiert, daß sie auf der Fundamentplatte 100 über die Abstandhalter 101 und den gekneteten Mörtel 102 abgestützt sind.The foundation plate 100 is in the form of a flat plate consisting of concrete and with a certain thickness and the dimensions of the same in the plan view are set slightly larger than a sum of the first and second basement units 10 a and 10 b. On the surface of the foundation plate 100 , a plurality of spacers 101 , which are formed from a pressure-resistant rubber as elastic elements, are uniformly distributed and mixed or kneaded mortar 102 (dotted in FIG. 14) is applied or layered to form a layer form, which has a thickness that only the tops of the spacers 101 are slightly covered. The first and second basement units 10 a, 10 b are successively lowered onto the foundation plate 100 in such a state, resulting in that they are supported on the foundation plate 100 via the spacers 101 and the kneaded mortar 102 .
Jeder Abstandhalter 101 weist seine Größe seines Abstützbereichs, Gewichts und Form derart eingestellt auf, daß er eine ausreichende Stärke bzw. Festigkeit aufweist, um die Untergeschoßeinheiten 10a, 10b abzustützen.Each spacer 101 has its size of its support area, weight and shape set in such a way that it has sufficient strength or strength to support the basement units 10 a, 10 b.
Durch Anordnung einer Vielzahl von Abstandhaltern 101 in einer vorbestimmten Dichteverteilung werden die Untergeschoßeinheiten 10a, 10b auf der Funda mentplatte 100 installiert, während ein vorbestimmter Abstand sichergestellt wird.By arranging a plurality of spacers 101 in a predetermined density distribution, the basement units 10 a, 10 b are installed on the foundation plate 100 while a predetermined distance is ensured.
Der gemischte Mörtel 102 wird durch Kneten bzw. Mischen von Zement und Sand ohne Zusatz von Wasser erhalten. Durch Anordnen eines derartigen gemischten Mörtels 102 zwischen den Untergeschoßeinheiten 10a, 10b und der Fundamentplatte 100 stellt die Schicht aus gemischtem bzw. geknetetem Mörtel 102 ihre Dicke auf die Unebenheit der Außenoberfläche der Fundamentplatte 100 und der Bodenoberflächen der Untergeschoßeinheiten 10a, 10b ein, unmittelbar nachdem die Untergeschoßeinheiten 10a, 10b auf den Abstandhaltern 101 installiert wurden. Im Verlauf der Zeit absorbiert der Mörtel 102 Feuchtigkeit aus dem Boden und verfestigt sich, während eine chemische Reaktion mit dieser Feuchtigkeit fortschreitet. Als ein Resultat wird das Gewicht der Untergeschoßeinheiten 10a, 10b gleichmäßig auf der Fundamentplatte 100 über den verfestigten Mörtel 102 verteilt, so daß die Untergeschoßeinheiten 10a, 10b stabiler auf der Fundamentplatte 100 aufruhen.The mixed mortar 102 is obtained by kneading or mixing cement and sand without adding water. By arranging such a mixed mortar 102 between the basement units 10 a, 10 b and the foundation plate 100 , the layer of mixed or kneaded mortar 102 adjusts its thickness to the unevenness of the outer surface of the foundation plate 100 and the bottom surfaces of the basement units 10 a, 10 b , immediately after the basement units 10 a, 10 b were installed on the spacers 101 . Over time, mortar 102 absorbs moisture from the soil and solidifies as a chemical reaction with that moisture proceeds. As a result, the weight of the basement units 10 a, 10 b is evenly distributed on the foundation plate 100 over the solidified mortar 102 , so that the basement units 10 a, 10 b rest more stable on the foundation plate 100 .
In jeder der Türöffnungen 200 der entsprechenden Untergeschoßein heiten 10a, 10b (d. h. sowohl den unteren als auch den oberen Ausschnitten 201, 202 der Untergeschoßeinheiten 10a, 10b) ist eine erste umgebende bzw. umlaufende Vertiefung 203 ausgebildet, welche sich entlang aller vier Seiten der Türöffnung 200 erstreckt und welche zu der Außenseite der umgebenden Wände offen ist. Weiters ist eine zweite, umgebende Vertiefung 204, welche sich ähnlich entlang aller vier Seiten der Türöffnung 200 erstreckt und zu der Außenseite der umgebenden Wände offen ist, in der inneren Oberfläche der ersten Ausnehmung 203 ausgebildet. Demgemäß ist die innere Oberfläche der Türöffnung 200 ausgebildet, daß sie eine stufenartige bzw. abgestufte Form aufweist.In each of the door openings 200 of the corresponding Untergeschoßein units 10 a, 10 b (that is, both the lower and the upper cutouts 201, 202 of the lower floor units 10 a, 10 b) is formed a first surrounding or peripheral recess 203, which along which all extends four sides of the door opening 200 and which is open to the outside of the surrounding walls. Furthermore, a second, surrounding recess 204 , which similarly extends along all four sides of the door opening 200 and is open to the outside of the surrounding walls, is formed in the inner surface of the first recess 203 . Accordingly, the inner surface of the door opening 200 is formed to have a step-like shape.
Durch Anordnung der ersten und zweiten Untergeschoßeinheiten 10a, 10b unmittelbar nebeneinander werden die ersten umgebenden Vertiefungen 203 nebeneinander bei den Türöffnungen 200 der Untergeschoßeinheiten 10a, 10b angeordnet, um derart eine breite Nut 205 auszubilden. Auf dem Boden der breiten Nut 205 ist eine schmale Nut bzw. Rille 206 durch die zweiten, umgebenden bzw. umlaufenden Vertiefungen 204 ausgebildet, welche unmittelbar nebeneinander angeordnet sind.By arranging the first and second basement units 10 a, 10 b directly next to one another, the first surrounding depressions 203 are arranged next to one another at the door openings 200 of the basement units 10 a, 10 b in order to form a wide groove 205 in this way . On the bottom of the wide groove 205 , a narrow groove or groove 206 is formed by the second, surrounding or circumferential depressions 204 , which are arranged directly next to one another.
Ein Abdichtelement 31, welches aus einem elastischen Material, wie beispielsweise Gummi, hergestellt ist, wird in die enge Nut 206 eingepaßt, wie dies in Fig. 16 gezeigt ist. Dieses Abdichtelement 31 weist vorzugsweise eine Eigenschaft eines Expandierens bei einer Absorption von Wasser auf und verbessert dadurch einen Abdichteffekt.A sealing member 31 made of an elastic material such as rubber is fitted in the narrow groove 206 as shown in FIG. 16. This sealing element 31 preferably has a property of expanding when water is absorbed and thereby improves a sealing effect.
Nachdem das Abdichtelement 31 in die schmale Rille 206 eingepaßt ist, wird ein sogenanntes Verfüllen, d. h. ein Vorgang eines Eingießens von wasserabweisendem Mörtel 32, welcher aus frisch bereitetem Beton hergestellt ist, in die breite Nut 205 durchgeführt, wie dies in Fig. 16 gezeigt ist. Als eine Konsequenz kann das Eintreten von beispielsweise Grundwasser in die Untergeschoße durch die Türöffnung 200 sicher vermieden werden.After the sealing member 31 is fitted into the narrow groove 206 , a so-called filling, that is, a process of pouring water-repellent mortar 32 made of freshly prepared concrete is carried out in the wide groove 205 , as shown in FIG. 16 . As a consequence, entry of, for example, groundwater into the basement through the door opening 200 can be safely avoided.
Gemäß den Strukturblöcken der zweiten Ausführungsform sind die Untergeschoßeinheiten 10a, 10b einstückig mit der Fundamentplatte 100 unter Verwendung des verfestigten Mörtels 102 ausgebildet. Dies verhindert, daß die Untergeschoßeinheiten 10a, 10b in Querrichtung relativ zur Fundamentplatte 100 verschoben werden, selbst wenn eine Horizontalkraft, welche aus einem seitlichen und in Querrichtung verlaufenden Rütteln während eines Erdbebens resultiert, auf die Untergeschoßeinheiten 10a, 10b einwirkt.According to the structural blocks of the second embodiment, the basement units 10 a, 10 b are formed in one piece with the foundation plate 100 using the solidified mortar 102 . This prevents the basement units 10 a, 10 b from being displaced in the transverse direction relative to the foundation plate 100 , even if a horizontal force, which results from lateral and transverse shaking during an earthquake, acts on the basement units 10 a, 10 b.
Obwohl die Türöffnungen 200 an der Verbindungsfläche zwischen den entsprechenden Untergeschoßeinheiten 10a, 10b ausgebildet sind, ist es normalerweise schwierig, zufriedenstellend die umgebenden Wände der ersten Untergeschoßeinheit 10a und jene der zweiten Untergeschoßeinheit 10b aufgrund von Abmessungsfehlern der Untergeschoßeinheiten. 10a, 10b und von Fehlern, welche während der Installation bzw. dem Aufstellen auftreten, miteinander in Kontakt zu bringen. Demgemäß kann ein ungewünschter Effekt, in welchem Grundwasser in die Untergeschoße durch Freiräume bzw. Spalte, welche zwischen den umgebenden Wänden ausgebildet sind, auftreten. Die zweite Nut bzw. Rille 205 ist jedoch in der inneren Oberfläche der Türöffnung 200 ausgebildet, die schmale Nut 206 ist weiters am Boden der breiten Nut 205 ausgebildet und der wasserabweisende Mörtel 32 ist in die breite Nut 205 gefüllt, wobei das Abdichtelement 32 in die schmale Nut 206 eingepaßt ist. Auf diese Weise kann ein Eintreten von beispielsweise Grundwasser sicher durch die doppelten, wasserabweisenden Behandlungen durch das Abdichtelement 31 und den wasserabweisenden Mörtel 32 verhindert werden. Although the door openings 200 are formed on the connection surface between the corresponding basement units 10 a, 10 b, it is normally difficult to satisfactorily the surrounding walls of the first basement unit 10 a and those of the second basement unit 10 b due to dimensional errors of the basement units. 10a, 10b and of errors which occur during installation or erection. Accordingly, an undesirable effect in which groundwater enters the basement through spaces or gaps formed between the surrounding walls can occur. However, the second groove 205 is formed in the inner surface of the door opening 200 , the narrow groove 206 is further formed on the bottom of the wide groove 205 , and the water-repellent mortar 32 is filled in the wide groove 205 , with the sealing member 32 in the narrow groove 206 is fitted. In this way, entry of groundwater, for example, can be reliably prevented by the double, water-repellent treatments by the sealing element 31 and the water-repellent mortar 32 .
Fig. 17 ist eine perspektivische Ansicht, welche die Zweiraum-Unterge schoßstruktur der zweiten Ausführungsform zeigt, welche durch Anpassen von Kopf-Querbalken an der Oberseite der einzelnen Untergeschoßeinheiten vervollständigt ist. Wie dies in Fig. 17 gezeigt ist, sind die ersten und zweiten Untergeschoßeinheiten 10a, 10b mit einem verbindenden Kopf-Querbalken 301, vier querverlaufenden Kopf-Querbalken 302 und zwei in Längsrichtung verlaufenden Kopf-Querbalken 303 an der Oberseite ausgestattet. Der Verbin dungs-Kopf-Querbalken 301 ist an den oberen Enden der zueinander gerich teten Wände der ersten und zweiten Untergeschoßeinheiten 10a, 10b festge legt, wodurch diese überbrückt werden. Die querverlaufenden Kopf-Querbalken bzw. -Träger 302 sind an den oberen Enden der Wände der ersten und zweiten Untergeschoßeinheiten 10a, 10b festgelegt, welche parallel zu der Querrichtung verlaufen, während die Längs-Kopf-Querbalken 303 an den oberen Enden der Außenwände festgelegt sind, welche parallel zu der Längsrichtung verlaufen. Fig. 17 is a perspective view showing the two-room basement structure of the second embodiment, which is completed by fitting cross head beams on the top of each basement unit. As shown in Fig. 17, the first and second basement units 10 a, 10 b are equipped with a connecting head crossbar 301 , four transverse head crossbars 302 and two longitudinal head crossbars 303 on the top. The connec tion head crossbar 301 is festge at the upper ends of the mutually directed walls of the first and second basement units 10 a, 10 b, whereby these are bridged. The transverse head cross beams or beams 302 are fixed to the upper ends of the walls of the first and second basement units 10 a, 10 b, which run parallel to the transverse direction, while the longitudinal head cross beams 303 at the upper ends of the outer walls are fixed, which run parallel to the longitudinal direction.
Sämtliche dieser Kopf-Querbalken 301, 302, 303 weisen eine vorbe stimmte Anzahl von Bolzen- bzw. Schraubenlöchern auf, durch welche Anker bolzen 400 hindurchgeführt werden, wobei deren Köpfe in den Wänden der Untergeschoßeinheiten 10a, 10b eingebettet sind und deren Gewindeteile nach oben vorragen. Die Kopf-Querbalken 301, 302, 303 sind in ihrer Position durch Anbringen von Muttern an den einzelnen Ankerbolzen 400 gesichert. Diese Konstruktion erlaubt, daß auf der Oberseite der Kopf-Querbalken 301, 302, 303 eine auf Bodenniveau befindliche Struktur gebaut wird. Obwohl die in dieser Ausführungsform verwendeten Kopf-Querbalken bzw. Träger 301, 302, 303 aus Holz bestehen, können sie aus Betonfertigteilen oder einem synthetischen Harzmaterial gebildet sein.All of these head crossbars 301 , 302 , 303 have a predetermined number of bolt or screw holes, through which anchor bolts 400 are passed, the heads of which are embedded in the walls of the basement units 10 a, 10 b and their threaded parts protrude above. The head crossbeams 301 , 302 , 303 are secured in their position by attaching nuts to the individual anchor bolts 400 . This construction allows a structure at ground level to be built on top of the crosshead beams 301 , 302 , 303 . Although the head crossbars 301 , 302 , 303 used in this embodiment are made of wood, they may be made of precast concrete or a synthetic resin material.
Wie dies aus der obigen Diskussion ersichtlich ist, ist es möglich, eine Struktur auf Bodenniveau, wie beispielsweise ein Haus, direkt auf den Kopf Querbalken 301, 302, 303 unter Verwendung der ersten und zweiten Unterge schoßeinheiten 10a, 10b als ein Fundament zu bauen, wenn die Kopf Querbalken 301 bis 303 an die einzelnen Untergeschoßeinheiten 10a, 10b an gepaßt sind, welche auf der Fundamentplatte 100 festgelegt sind. Insbesondere sind die ersten und zweiten Untergeschoßeinheiten 10a, 10b miteinander durch den verbindenden Kopf-Querbalken 301, welcher die zueinander gerichteten Wände an der Oberseite überbrückt, und durch die Fundamentplatte 100 verbunden, welche sicher ihre Bodenabschnitte hält. Derart sind die ersten und zweiten Untergeschoßeinheiten 10a, 10b miteinander mit erhöhter Festigkeit und Zuverlässigkeit der Konstruktion verbunden. As can be seen from the above discussion, it is possible to provide a structure at ground level, such as a house, directly on the head cross beam 301, 302, 303 using the first and second underweight body fired units 10 a, 10 b as a foundation build when the head crossbars 301 to 303 are fitted to the individual basement units 10 a, 10 b, which are fixed on the foundation plate 100 . In particular, the first and second basement units 10 a, 10 b are connected to one another by the connecting head crossbeam 301 , which bridges the mutually facing walls at the top, and by the foundation plate 100 , which securely holds their floor sections. In this way, the first and second basement units 10 a, 10 b are connected to one another with increased strength and reliability of the construction.
Da die entsprechenden Untergeschoßeinheiten 10a, 10b mit den Decken ausgebildet sind, ist es möglich, die Querbalken bzw. Träger in jeglichen Positionen an den oberen Oberflächen der Decken anzuordnen, unter der Voraussetzung, daß sie stark genug sind, um Trennwände, welche einen relativ geringen Querschnitt aufweisen, abzustützen. Derart können die Querträger mit einem verbesserten bzw. erhöhten Freiheitsgrad angeordnet werden.Since the corresponding basement units 10 a, 10 b are formed with the ceilings, it is possible to arrange the crossbeams or beams in any position on the upper surfaces of the ceilings, provided that they are strong enough to separate partitions have a relatively small cross-section. In this way, the cross members can be arranged with an improved or increased degree of freedom.
Fig. 18 ist eine perspektivische Ansicht, welche eine Modifikation der Strukturblöcke der zweiten Ausführungsform gemäß der Erfindung zeigt. Obwohl diese Modifikation im wesentlichen dieselbe Konstruktion wie die zweite Ausführungsform aufweist, unterscheidet sich die Struktur an der inneren Oberfläche der Türöffnung 200. Insbesondere ist in dieser Modifikation nur die erste, umgebende Vertiefung 203 in den inneren Oberflächen der Türöffnungen 200 der ersten und zweiten Untergeschoßeinheiten 10a, 10b, ohne Ausbildung der zweiten, umgebenden Vertiefungen 204 im Gegensatz zu der zweiten Ausführungsform ausgebildet. Derart ist die abgestufte Struktur in der inneren Oberfläche der Türöffnung 200 einfacher. Fig. 18 is a perspective view of the invention showing a modification of the structure of blocks of the second embodiment. Although this modification has substantially the same construction as the second embodiment, the structure on the inner surface of the door opening 200 differs. In particular, in this modification only the first, surrounding recess 203 is formed in the inner surfaces of the door openings 200 of the first and second basement units 10 a, 10 b, without forming the second, surrounding recesses 204, in contrast to the second embodiment. In this way, the stepped structure in the inner surface of the door opening 200 is simpler.
Stattdessen wird ein Abdichtelement 33, welches aus einem elastischen Material, wie beispielsweise wasserdichtem Gummi, hergestellt ist, an der äußeren Wandoberfläche um die Türöffnung 200 der ersten Untergeschoßein heit 10a festgelegt, um die Türöffnung 200 zu umschließen. Dieses Abdicht element 33 wird zwischen den ersten und zweiten Untergeschoßeinheiten 10a, 10b gequetscht, wodurch das Eindringen von Grundwasser und dgl. in die entsprechenden Untergeschoße verhindert wird.Instead, a sealing member 33 , which is made of an elastic material such as waterproof rubber, is set on the outer wall surface around the door opening 200 of the first sub-floor unit 10 a to enclose the door opening 200 . This sealing element 33 is squeezed between the first and second basement units 10 a, 10 b, thereby preventing the penetration of groundwater and the like into the corresponding basement.
Ein besserer Wasserabdichteffekt wird bei Zusammenwirken des Ab dichtelements 33 und des Abdichtelements 31, welches in die breite Nut 205, welche durch die ersten, umlaufenden Vertiefungen 203 ausgebildet wird, erzielt, wenn die ersten und zweiten Untergeschoßeinheiten 10a, 10b nebeneinander angeordnet werden.A better water sealing effect is achieved when the sealing element 33 and the sealing element 31 interact, which is formed in the wide groove 205 , which is formed by the first circumferential recesses 203 , when the first and second basement units 10 a, 10 b are arranged side by side.
Die Fig. 19A, 19B, 20A und 20B sind Darstellungen, welche ein Verfah ren einer Installation auf der Baustelle für die Modifikation der zweiten Ausfüh rungsform zeigen. Fig. 19A zeigt einen zweiten, unteren Strukturblock eines zweiten Untergeschoß-Strukturblocks, welcher benachbart einem bereits installierten, ersten Untergeschoß-Strukturblock angeordnet wird, Fig. 19B zeigt den abgesenkten, zweiten, unteren Strukturblock, Fig. 20A zeigt einen zweiten, oberen Strukturblock, welcher auf den zweiten, unteren Strukturblock abgesenkt wird, und Fig. 20B zeigt den zweiten, oberen, auf dem zweiten, unteren Strukturblock angeordneten Strukturblock. Figs. 19A, 19B, 20A and 20B are diagrams showing a procedural ren an installation at the construction site for the modification of the second exporting show approximate shape. FIG. 19A shows a second lower structural block of a second basement structure block which is adjacent an already installed, the first basement structure block is arranged, Fig. 19B shows the lowered, second lower structural block, Fig. 20A shows a second, upper structural block, which is lowered onto the second, lower structure block, and FIG. 20B shows the second, upper structure block arranged on the second, lower structure block.
Beim Anordnen der zwei Untergeschoßeinheiten 10a, 10b in einer vorbestimmten, bereits ausgegrabenen, vertikalen Grube wird der gemischte Mörtel 102 zuerst verteilt, wobei die Abstandhalter 101 auf der Fundamentplatte 100 verteilt angeordnet sind, wie dies in Fig. 19A gezeigt ist, und es wird die erste Untergeschoßeinheit 10a auf die Schicht aus gemischtem Mörtel 102 abgesenkt. Die Abstandhalter 101 werden elastisch komprimiert und es wird der gemischte Mörtel 102 ausreichend durch das Gewicht der abgesenkten, ersten Untergeschoßeinheit 10a komprimiert. Nachdem sichergestellt wurde, daß die erste Untergeschoßeinheit 10a nicht mehr weiter absinken wird, wird der zweite, untere Strukturblock 1b auf die Schicht aus gemischtem Mörtel 102 be nachbart der ersten Untergeschoßeinheit 10a unter Verwendung eines Krans oder einer ähnlichen Arbeitsmaschine abgesenkt.When arranging the two basement units 10 a, 10 b in a predetermined, already excavated, vertical pit, the mixed mortar 102 is first distributed, with the spacers 101 being distributed on the foundation plate 100 , as shown in FIG. 19A, and it the first basement unit 10 a is lowered onto the layer of mixed mortar 102 . The spacers 101 are elastically compressed and the mixed mortar 102 is sufficiently compressed by the weight of the lowered, first basement unit 10 a. After it has been ensured that the first basement unit 10 a will no longer sink further, the second, lower structural block 1 b is lowered onto the layer of mixed mortar 102 adjacent to the first basement unit 10 a using a crane or a similar working machine.
Es ist ideal, den zweiten, unteren Strukturblock 1b zu placieren, nach dem der gemischte Mörtel 102 unter der ersten Untergeschoßeinheit 10a aus reichend Feuchtigkeit absorbiert hat und verfestigt ist. Es kann jedoch der zweite, untere Strukturblock 1b placiert werden, nachdem sichergestellt wurde, daß der gemischte Mörtel 102 ausreichend komprimiert, jedoch noch nicht verfestigt ist.It is ideal to place the second, lower structural block 1 b, after which the mixed mortar 102 has absorbed sufficient moisture under the first basement unit 10 a and has solidified. However, the second, lower structural block 1 b can be placed after it has been ensured that the mixed mortar 102 has been sufficiently compressed but has not yet solidified.
Während des Absenkens wird der zweite, untere Strukturblock 1b relativ zu der ersten Untergeschoßeinheit 10a gekippt. Insbesondere wird die erste Untergeschoßeinheit 10a so gekippt, daß der obere Ausschnitt 203 des zweiten, unteren Strukturblocks 1b der Türöffnung 200 der ersten Unterge schoßeinheit 10a gegenüberliegt, wobei ein Bodenende P der Wandoberfläche des zweiten, unteren Strukturblocks 1b, welches zur Türöffnung 200 gerichtet ist, unterhalb des Abdichtelements 33 angeordnet ist, welches vorab um die Türöffnung festgelegt bzw. angeklebt wurde, und ein Bodenende Q der gegen überliegenden Wandoberfläche auf der Schicht aus gemischtem Mörtel 102 angeordnet ist (siehe Fig. 19A).During the lowering, the second, lower structural block 1 b is tilted relative to the first basement unit 10 a. In particular, the first basement unit 10 a is tilted so that the upper cutout 203 of the second, lower structural block 1 b of the door opening 200 of the first basement unit 10 a is opposite, with a bottom end P of the wall surface of the second, lower structural block 1 b, which leads to the door opening 200 is arranged, is arranged below the sealing element 33 , which was previously fixed or glued around the door opening, and a bottom end Q of the opposite wall surface is arranged on the layer of mixed mortar 102 (see FIG. 19A).
Der zweite, untere Strukturblock 1b wird entgegen dem Uhrzeigersinn um das Bodenende Q durch Absenken des zweiten, unteren Strukturblocks 1b verschwenkt. Daraus resultierend nähert sich die gesamte Wandoberfläche des zweiten, unteren Strukturblocks 1b, welche zu der ersten Untergeschoßeinheit 10a gerichtet ist, der ersten Untergeschoßeinheit 10a an. Wenn die Boden oberfläche des zweiten, unteren Strukturblocks 1b in Kontakt mit der oberen Oberfläche der Schicht aus gemischtem Mörtel 102 gebracht wird, drückt die dorthin gewandte Wandoberfläche des zweiten, unteren Strukturblocks 1b das Abdichtelement 33, wie dies in Fig. 19B gezeigt ist. Daraus resultierend wird die untere Hälfte des Abdichtelements 33 unter Druckbeanspruchung elastisch deformiert, um zwischen den ersten und zweiten, unteren Strukturblöcken 1a, 1b gepreßt bzw. gequetscht zu werden.The second lower structural block 1 b is pivoted counterclockwise about the bottom end of Q by lowering the second lower structural block 1 b. As a result, the entire wall surface of the second lower structural block approaches 1 b, which is directed to the first basement unit 10 a, the first unit 10 a basement on. When the bottom surface of the second lower structural block 1 b in contact with the upper surface of the layer of mixed mortar 102 is placed, pushes the thereto facing wall surface of the second lower structural block 1 b, the sealing member 33, as shown in FIG. 19B . As a result, the lower half of the sealing element 33 is elastically deformed under pressure in order to be pressed or squeezed between the first and second, lower structural blocks 1 a, 1 b.
Nachfolgend wird der zweite, obere Strukturblock 2b auf den zweiten, unteren Strukturblock 1b abgesenkt, wie dies in Fig. 20A gezeigt ist. Zu diesem Zeitpunkt ist der zweite, obere Strukturblock 2b geneigt aufgehängt, so daß ein Bodenende R der rechten Seitenwand des zweiten, oberen Strukturblocks 2b in Kontakt mit dem oberen Ende der rechten Seitenwand des zweiten, unteren Strukturblocks 1b gelangt. Danach wird der zweite, obere Strukturblock 2b entgegen dem Uhrzeigersinn um das Bodenende R verschwenkt, woraus resul tiert, daß die ersten und zweiten Untergeschoßeinheiten 10a, 10b neben einander angeordnet sind, wobei der zweite, obere Strukturblock 2b auf der Oberseite des zweiten, unteren Strukturblocks 1b aufgerichtet ist, und es wird die obere Hälfte des Abdichtelements 33 unter Druckbeanspruchung elastisch deformiert, um zwischen den ersten und zweiten Untergeschoßeinheiten 10a, 10b gepreßt bzw. gequetscht zu werden.Subsequently, the second, upper structure block 2 b is lowered onto the second, lower structure block 1 b, as shown in FIG. 20A. At this time, second upper structural block 2 is b hung inclined so that a bottom end R of the right side wall of the second structure block 2 upper b in contact with the upper end of the right side wall of the second lower structural block 1 b passes. Then the second, upper structural block 2 b is pivoted counterclockwise around the bottom end R, resulting in that the first and second basement units 10 a, 10 b are arranged next to each other, the second, upper structural block 2 b on the top of the second, lower structural block 1 b is erected, and the upper half of the sealing element 33 is elastically deformed under pressure in order to be pressed or squeezed between the first and second basement units 10 a, 10 b.
Wenn die obige Konstruktion für eine vorbestimmte Zeitdauer stehen gelassen wird, wobei die ersten und zweiten Untergeschoßeinheiten 10a, 10b nebeneinander angeordnet sind, absorbiert der gemischte Mörtel 102 zur Verfügung stehende Feuchtigkeit und verfestigt sich, während er durch das Ge wicht der zweiten Untergeschoßeinheit 10b komprimiert wird, wodurch ein Absinken der zweiten Untergeschoßeinheit 10b bewirkt wird. Dies erlaubt, daß die ersten und zweiten Untergeschoßeinheiten 10a, 10b dasselbe Höhenniveau aufweisen, wie dies in Fig. 20B gezeigt ist. Nachdem die ersten und zweiten Untergeschoßeinheiten 10a, 10b auf dasselbe Höhenniveau gelangt sind, wird das Abdichtelement 31 in die breitere Nut 205 eingepaßt, welche in den Innenoberflächen der Türöffnungen 200 ausgebildet ist. Da die Türöffnungen 200 doppelt durch die Abdichtelemente 31 und 33 abgedichtet sind, kann ein zuverlässiger Wasserabdichteffekt eines Verhinderns des Eindringens von Grundwasser oder dgl. in die Untergeschoße erhalten werden.If the above construction is left for a predetermined period of time with the first and second basement units 10 a, 10 b arranged side by side, the mixed mortar 102 absorbs available moisture and solidifies as it passes through the weight of the second basement unit 10 b is compressed, whereby a decrease in the second basement unit 10 b is effected. This allows the first and second basement units 10 a, 10 b to have the same height level as shown in Fig. 20B. After the first and second basement units 10 a, 10 b have reached the same height level, the sealing element 31 is fitted into the wider groove 205 , which is formed in the inner surfaces of the door openings 200 . Since the door openings 200 are double sealed by the sealing members 31 and 33 , a reliable water sealing effect of preventing the ingress of ground water or the like into the basement can be obtained.
Die Fig. 21 und 22 sind teilweise weggeschnittene, perspektivische Ansichten, welche eine dritte Ausführungsform der Untergeschoß-Struktur blöcke gemäß der Erfindung illustrieren, wobei Fig. 21 einen Zustand zeigt, in welchem die unteren und oberen Strukturblöcke voneinander gelöst sind, und Fig. 22 einen Zustand zeigt, in welchem der obere Strukturblock auf dem unteren Strukturblock placiert ist. Ähnlich zu dem obigen wird die Unterge schoßstruktur von einer Untergeschoßeinheit 10 gebildet, welche eine recht eckige, schachtelartige Form aufweist. Die Untergeschoßeinheit 10 weist eine derartige Basiskonstruktion auf, welche einen unteren Strukturblock 1, welcher eine untere Hälfte der Untergeschoßeinheit 10 bildet, und einen oberen Struk turblock 2 umfaßt, welcher eine obere Hälfte derselben ausbildet. Der untere Strukturblock 1 weist eine rechteckige Form in der Draufsicht auf und umfaßt einen rechteckigen Bodenabschnitt 11 am Boden und umgebende Wände 12, welche sich von allen Seiten nach oben von dem Bodenabschnitt 11 erstrecken. FIGS. 21 and 22 are partially cutaway perspective views illustrating a third embodiment of the basement structure blocks according to the invention, in which Fig. 21 shows a state in which the lower and upper structure blocks are disengaged from each other, and Fig. 22 shows a state in which the upper structure block is placed on the lower structure block. Similar to the above, the basement structure is formed by a basement unit 10 , which has a rectangular, box-like shape. The basement unit 10 has such a basic construction, which comprises a lower structural block 1 , which forms a lower half of the basement unit 10 , and an upper structure block 2 , which forms an upper half thereof. The lower structural block 1 has a rectangular shape in plan view and comprises a rectangular floor section 11 on the floor and surrounding walls 12 which extend upwards from the floor section 11 from all sides.
Die umgebenden Wände 12 beinhalten ein Paar von kurzen Seitenwän den 13, welche vertikal an gegenüberliegenden, kurzen Seiten des Boden abschnitts 11 ausgebildet sind, und ein Paar von Längsseitenwänden 14, welche vertikal an gegenüberliegenden Längsseiten des Bodenabschnitts 11 ausgebildet sind. Die Oberseite von jeder umgebenden Wand 12 ist ausge bildet, um ein abgestuftes, oberes Ende 15 zu formen, welches einen äußeren, unteren Endabschnitt 15a und einen inneren, höheren Endabschnitt 15b aufweist.The surrounding walls 12 include a pair of short side walls 13 , which are formed vertically on opposite, short sides of the bottom section 11 , and a pair of long side walls 14 , which are vertically formed on opposite long sides of the bottom section 11 . The top of each surrounding wall 12 is formed out to form a stepped, upper end 15 which has an outer, lower end portion 15 a and an inner, higher end portion 15 b.
Der obere Strukturblock 2 weist umgebende Wände 21 auf, welche ebenfalls ein Paar von kurzen Seitenwänden 22, welche den kurzen Seiten wänden 13 entsprechen, und ein Paar von langen Seitenwänden 23 beinhalten, welche den langen Seitenwänden 14 entsprechen. Der Boden jeder um gebenden Wand 21 ist gebildet, um ein abgestuftes, unteres Ende 24 zu formen, welches einen äußeren, unteren Endabschnitt 24a, welcher dem unte ren Endabschnitt 15a von jeder umgebenden Wand 12 entspricht, und einen inneren, höheren Endabschnitt 24b aufweist, welcher dem höheren Endab schnitt 15b von jeder umgebenden Wand 12 entspricht.The upper structural block 2 has surrounding walls 21 which also include a pair of short side walls 22 which correspond to the short side walls 13 and a pair of long side walls 23 which correspond to the long side walls 14 . The bottom of each surrounding wall 21 is formed to form a stepped lower end 24 , which has an outer, lower end portion 24 a, which corresponds to the lower end portion 15 a of each surrounding wall 12 , and an inner, higher end portion 24 b, which corresponds to the higher end section 15 b of each surrounding wall 12 .
An der Oberseite des oberen Strukturblocks 2 ist eine Deckenwand bzw. ein Deckenelement 20 eingepaßt, welche(s) durch die umgebenden Wände 12 abgestützt ist. In einer speziellen Position der Deckenwand 20 ist eine rechteckige Durchtrittsöffnung 20a ausgebildet, um einen Zutritt zwischen dem oberen Geschoß und der Untergeschoßeinheit 10 durch die Durchtrittsöffnung 20a zur Verfügung zu stellen, wenn der obere Strukturblock 2 auf der Oberseite des unteren Strukturblocks 1 aufgestapelt ist (siehe Fig. 22). Es soll festge halten werden, daß die Durchtrittsöffnung 20a für die Untergeschoßeinheit 10 ausgebildet ist, um einen Zutritt von dem und zu dem oberen Geschoß zu haben, und daß andernfalls keine Durchtrittsöffnung 20a vorgesehen sein kann. In speziellen Positionen der umgebenden Wand 12 des unteren Struktur blocks 1 sind obere Ausschnitte 201 ausgebildet, welche sich nach unten zu den abgestuften, unteren Enden 15 erstrecken und vorgegebene Breiten aufweisen. Andererseits sind untere Ausschnitte 202, welche sich nach oben von den abgestuften, unteren Enden 24 erstrecken, derart in den umgebenden Wänden 12 des oberen Strukturblocks 2 ausgebildet, um den oberen Aus schnitten 201 zu entsprechen. Bei Anordnen des oberen Strukturblocks 2 auf dem unteren Strukturblock 1 werden Türöffnungen 200 durch die oberen und unteren Ausschnitte 201, 202 gebildet, wie dies in Fig. 22 gezeigt ist. In dieser Ausführungsform werden insgesamt zwei Türöffnungen 200 ausgebildet: eine in den kurzen Seitenwänden 13, 22 und die andere in den langen Seitenwänden 14, 23. Die Anzahl der Türöffnungen 200 pro Untergeschoßeinheit 10 ist nicht auf zwei beschränkt, sondern kann eins oder drei oder mehr betragen. Die Abmessungen derselben können ebenfalls entsprechend eingestellt bzw. gewählt werden.At the top of the upper structural block 2 , a ceiling wall or a ceiling element 20 is fitted, which (s) is supported by the surrounding walls 12 . In a special position of the ceiling wall 20 , a rectangular passage opening 20 a is formed to provide access between the upper floor and the basement unit 10 through the passage opening 20 a when the upper structural block 2 is stacked on the top of the lower structural block 1 (see Fig. 22). It should be kept festge that the passage opening 20 a is designed for the basement unit 10 to have access to and from the upper floor, and that otherwise no passage opening 20 a can be provided. In special positions of the surrounding wall 12 of the lower structural block 1 , upper cutouts 201 are formed which extend downward to the stepped, lower ends 15 and have predetermined widths. On the other hand, lower cutouts 202 , which extend upward from the stepped lower ends 24 , are formed in the surrounding walls 12 of the upper structural block 2 in order to correspond to the upper cuts 201 . When the upper structural block 2 is arranged on the lower structural block 1 , door openings 200 are formed by the upper and lower cutouts 201 , 202 , as shown in FIG. 22. In this embodiment, a total of two door openings 200 are formed: one in the short side walls 13 , 22 and the other in the long side walls 14 , 23 . The number of door openings 200 per basement unit 10 is not limited to two, but can be one or three or more. The dimensions of the same can also be set or selected accordingly.
Die abgestuften, oberen Enden 15 des ersten Strukturblocks 1 und die abgestuften, unteren Enden 24 des zweiten Strukturblocks 2 gelangen in Eingriff miteinander durch Anordnen des oberen Strukturblocks 2 auf dem unteren Strukturblock 1, so daß die Bodenenden der umgebenden Wände 21 des oberen Strukturblocks 2 in Kontakt mit den entsprechenden oberen Enden der umgebenden Wände 12 des unteren Strukturblocks 1 gehalten werden. Als ein Resultat werden die unteren und oberen Strukturblöcke 1, 2 miteinander verbunden, um die Untergeschoßeinheit 10 zu bilden.The stepped, upper ends 15 of the first structural block 1, and the stepped lower ends 24 of the second structural block 2 engage with each other by arranging the upper structure of the block 2 on the lower structural block 1 so that the bottom ends of the surrounding walls 21 of the upper structural block 2 in To be held in contact with the corresponding upper ends of the surrounding walls 12 of the lower structural block 1 . As a result, the lower and upper structural blocks 1 , 2 are connected to each other to form the lower floor unit 10 .
Die Fig. 23A und 23B sind Querschnittsansichten, welche die abge stuften bzw. abgesetzten, oberen und unteren Enden 15, 24 der oberen und unteren Strukturblöcke 1, 2 zeigen, wobei Fig. 23A einen Zustand zeigt, unmit telbar bevor der obere Strukturblock 2 auf dem unteren Strukturblock placiert wird, und wobei Fig. 23B einen Zustand zeigt, nachdem der obere Strukturblock 2 auf dem unteren Strukturblock 1 angeordnet wurde. Wie aus Fig. 23A ersehen werden kann, sind die höheren Endabschnitte 24b der umgebenden Wände 21 gegenüberliegend den höheren Endabschnitten 15b der umgeben den Wände 12 positioniert und es sind die unteren Endabschnitte 24a der um gebenden Wände 21 gegenüberliegend den unteren Endabschnitten 15a der umgebenden Wände 12 positioniert, wenn der obere Strukturblock 2 in Position über dem unteren Strukturblock 1 derart angehoben wird, daß die einzelnen, abgestuften, unteren Enden 24 des oberen Strukturblocks 2 mit den entspre chenden, abgestuften, oberen Enden 15 des unteren Strukturblocks 1 fluchten bzw. mit diesen ausgerichtet sind. Die Breiten der einzelnen unteren Endabschnitte 15a, 24a und der hohen Endabschnitte 15b, 24b sind derart eingestellt bzw. gewählt, daß die abgestuften, unteren Enden 24 des oberen Strukturblocks 2 in Eingriff mit den entsprechenden, abgestuften Enden 15 des unteren Strukturblocks 1 gelangen bzw. mit diesen zusammenwirken, wie dies in Fig. 23B gezeigt ist, wenn der obere Strukturblock 2 von dem Zustand gemäß Fig. 23A abgesenkt wird, bis seine abgestuften, unteren Enden 24 in Kontakt mit den entsprechenden, abgestuften, oberen Enden 15 des unteren Strukturblocks 1 gelangen. Diese Anordnung stellt sicher, daß der obere Strukturblock 2, sobald er ordnungsgemäß auf dem unteren Strukturblock 1 aufgerichtet ist, nicht in horizontalen Richtungen verschoben wird. FIG. 23A and 23B are cross-sectional views showing the abge classified or remote, upper and lower ends 15, 24 of the upper and lower structural blocks 1, 2, show in which Fig. 23A shows a state UNMIT telbar before the upper structure block 2 is placed on the lower structure block, and FIG. 23B shows a state after the upper structure block 2 is placed on the lower structure block 1 . As can be seen from Fig. 23A, the higher end portions 24 b of the surrounding walls 21 are positioned opposite the higher end portions 15 b of the surrounding walls 12 and there are the lower end portions 24 a of the surrounding walls 21 opposite the lower end portions 15 a the surrounding walls 12 positioned when the upper structural block 2 is raised in position above the lower structural block 1 such that the individual, stepped, lower ends 24 of the upper structural block 2 are aligned with the corresponding, stepped, upper ends 15 of the lower structural block 1 or are aligned with them. The widths of the individual lower end sections 15 a, 24 a and the high end sections 15 b, 24 b are set or selected such that the stepped, lower ends 24 of the upper structural block 2 engage with the corresponding stepped ends 15 of the lower structural block 1 , as shown in FIG. 23B, when the upper structural block 2 is lowered from the state shown in FIG. 23A until its stepped lower ends 24 come into contact with the corresponding stepped upper ends 15 of the lower structural block 1 . This arrangement ensures that the upper structural block 2 , once properly erected on the lower structural block 1 , does not move in horizontal directions.
Eine Stahlwinkelplatte L1 ist an ein äußeres Eck von jedem unteren Endabschnitt 15a des abgestuften, oberen Endes 15 derart angepaßt, um dieses Eck über seine gesamte Länge zu schützen, und eine Stahlwinkelplatte L2 ist in ähnlicher Weise in ein inneres Eck von jedem oberen Endabschnitt 15b zum selben Zweck eingepaßt. Dies verhindert, daß die Ecken bzw. Kanten der abgestuften, oberen Enden 15 abgeschlagen bzw. zerstört werden. In ähnlicher Weise sind Stahlwinkelplatten L3, L4 an den äußeren Ecken der unteren Endabschnitte 24a der abgestuften, unteren Enden 24 und an den inneren Ecken der oberen Endabschnitte 24b entsprechend eingepaßt. Die Winkelplatten L1, L2, L3, L4 sind in den Strukturblöcken 1, 2 eingebettet und an sich in vertikaler Richtung erstreckenden Bewehrungsstäben F, welche später beschrieben werden, durch Verschweißen gesichert. Dies stellt die Verbindung zwischen den jeweiligen Strukturblöcken 1, 2 sicher.A steel angle plate L1 is adapted to an outer corner of each lower end portion 15 a of the stepped upper end 15 so as to protect this corner over its entire length, and a steel angle plate L2 is similarly in an inner corner of each upper end portion 15 b fitted for the same purpose. This prevents the corners or edges of the stepped, upper ends 15 from being knocked off or destroyed. Similarly, steel angle plates L3, L4 at the outer corners of the lower end portions 24 a of the stepped lower ends 24 and at the inner corners of the upper end portions 24 b are fitted accordingly. The angle plates L1, L2, L3, L4 are embedded in the structure blocks 1 , 2 and are secured by welding to reinforcing bars F which extend in the vertical direction and which are described later. This ensures the connection between the respective structure blocks 1 , 2 .
Die entsprechenden Winkelplatten L1, L2, L3, L4 sind in Abschnitten, welche von den Außenoberflächen der Umgebungswände 12, 21 nach innen zurückgesetzt sind, vorgesehen, so daß abgestufte Abschnitte 10c, welche eine geringe Abmessung aufweisen, zwischen den äußeren Oberflächen der umgebenden Wände 12, 21 und den Winkelplatten L1, L2, L3, L4 ausgebildet werden.The corresponding angle plates L1, L2, L3, L4 are in sections which are set back from the outer surfaces of the surrounding walls 12, 21 inwardly, provided so that stepped portions 10 c, which have a small dimension, between the outer surfaces of the surrounding walls 12 , 21 and the angle plates L1, L2, L3, L4 are formed.
Die oberen und unteren Strukturblöcke 1, 2 sind aus Stahlbeton gebildet, welcher Stahlbewehrungsstäbe bzw. -stangen F enthält, welche angeordnet sind, um ein kreuzweises Muster auszubilden, und welche im Beton eingebettet sind. Bevor der obere Strukturblock 2 auf der Oberseite des unteren Struktur blocks 1 aufgerichtet wird, wird ein Abdichtelement 3, welches aus einem elastischen Material, wie beispielsweise Gummi, mit guter Flexibilität und Wasserabdichteigenschaft ausgebildet ist, an den abgestuften Enden 15 der umgebenden Wände 12 angeordnet, wie dies in Fig. 23A gezeigt ist. Wenn der obere Strukturblock 2 auf dem unteren Strukturblock 1 angeordnet wird, wird das Abdichtelement 3 fest durch das Gewicht des oberen Strukturblocks 2 gepreßt und zwischen den abgestuften Enden 15 und 24 der umgebenden Wände 12, 21 gehalten, wie dies in Fig. 23B gezeigt ist. Wenn die Unter geschoßeinheit 10 derart unter Bodenniveau zusammengebaut ist, verhindert das Abdichtelement 3 das Eindringen von Grundwasser zwischen den Verbindungsoberflächen der abgestuften Enden 15, 24. In dieser Ausfüh rungsform wird synthetischer Gummi für das Abdichtelement 3 verwendet.The upper and lower structural blocks 1 , 2 are made of reinforced concrete, which contains steel reinforcing bars F, which are arranged to form a cross pattern, and which are embedded in the concrete. Before the upper structural block 2 is erected on the top of the lower structure of blocks 1, a sealing member 3 which is formed of an elastic material such as rubber with good flexibility and Wasserabdichteigenschaft, arranged on the stepped ends 15 of the surrounding walls 12, as shown in Fig. 23A. When the upper structural block 2 is placed on the lower structural block 1 , the sealing member 3 is pressed firmly by the weight of the upper structural block 2 and held between the stepped ends 15 and 24 of the surrounding walls 12 , 21 as shown in Fig. 23B . If the sub-floor unit 10 is assembled below ground level, the sealing element 3 prevents the penetration of ground water between the connecting surfaces of the stepped ends 15 , 24 . In this embodiment, synthetic rubber is used for the sealing element 3 .
Nach einem Eingreifen bzw. Zusammenwirken der abgestuften, unteren Enden 24 des oberen Strukturblocks 2 mit den abgestuften, oberen Enden des unteren Strukturblocks 1 durch das Abdichtelement 3, werden gegenüber liegende Abschnitte der Winkelplatten L1 und L3 miteinander verschweißt und es werden auch die Winkelplatten L2 und L4 miteinander verschweißt. Dies stellt die Verbindung zwischen den unteren und oberen Strukturblöcken 1, 2 sicher. Nachdem die Winkelplatten miteinander verschweißt sind (L1 mit L3 und L2 mit L4) wird Mörtelverfüllmasse M zwischen den oberen und unteren, abge stuften Abschnitten 10c angebracht, wodurch den umgebenden Wänden 12, 21 ein besseres Aussehen verliehen wird und ein Wasserabdichteffekt verbessert wird.After an engagement or interaction of the stepped, lower ends 24 of the upper structural block 2 with the stepped, upper ends of the lower structural block 1 by the sealing element 3 , opposite sections of the angle plates L1 and L3 are welded together and the angle plates L2 and L4 welded together. This ensures the connection between the lower and upper structure blocks 1 , 2 . After the angle plates are welded together (L1 with L3 and L2 with L4), mortar filling compound M is applied between the upper and lower, stepped sections 10 c, which gives the surrounding walls 12 , 21 a better appearance and improves a waterproofing effect.
In dieser Ausführungsform weisen die umgebenden Wände 12, 21 der entsprechenden Strukturblöcke 1, 2, die Deckenwand 20 des oberen Struktur blocks 2 und der Bodenabschnitt 11 eine Dicke von jeweils mindestens 120 mm auf. Demgemäß kann mit der unter Bodenniveau installierten Unterge schoßeinheit 10 die Decke 20 des oberen Strukturblocks 2, welche zum Boden gerichtet ist, als ein Fundament dienen, auf welchem eine über Bodenniveau gebaute Struktur aufruhen kann.In this embodiment, the surrounding walls 12 , 21 of the corresponding structural blocks 1 , 2 , the top wall 20 of the upper structural block 2 and the bottom portion 11 each have a thickness of at least 120 mm. Accordingly, with the sub-floor unit 10 installed below the floor, the ceiling 20 of the upper structural block 2 , which is directed towards the floor, can serve as a foundation on which a structure built above the floor can rest.
Jeder der in dieser Ausführungsform verwendeten Bewehrungsstäbe F weist einen Durchmesser von 13 mm auf. Die Armierungs- bzw. Bewehrungs stäbe F beinhalten Hauptverstärkungsstäbe, welche parallel zu der Längsachse von jedem Strukturelement angeordnet sind, und Verteilungsstäbe, welche unter rechten Winkeln zu den Hauptarmierungs- bzw. Bewehrungsstäben angeordnet sind. Die Verteilungsstäbe und die Hauptbewehrungsstäbe sind einzeln parallel in vorbestimmten Abständen verlegt und unter rechten Winkeln miteinander durch ein konventionelles Verfahren verbunden, wobei die Abstände zwischen den Verteilungsstäben und zwischen den Hauptbe wehrungsstäben in Abhängigkeit von bestimmten Anwendungen der Unterge schoßeinheit 10 bestimmt werden (beispielsweise ob die Untergeschoßeinheit 10 einfach als ein Untergeschoßraum bzw. Kellerraum verwendet wird oder ob beabsichtigt ist, daß dieser auch als ein Fundament dienen soll, auf welchem eine über Bodenniveau gebaute Struktur ruhen soll).Each of the reinforcing bars F used in this embodiment has a diameter of 13 mm. The reinforcing bars F include main reinforcing bars which are arranged parallel to the longitudinal axis of each structural element and distribution bars which are arranged at right angles to the main reinforcing bars. The distribution bars and the main reinforcement bars are individually laid in parallel at predetermined intervals and connected at right angles to one another by a conventional method, the distances between the distribution bars and between the main reinforcement bars being determined depending on certain applications of the basement unit 10 (e.g. whether the basement unit 10 is simply used as a basement or cellar room or whether it is intended that this should also serve as a foundation on which a structure built above ground level should rest).
Nachfolgend wird ein Verfahren einer Herstellung der Strukturblöcke gemäß der dritten Ausführungsform unter Bezugnahme auf die Fig. 24A und 24B beschrieben. Die Fig. 24A und 24B sind Schnittansichten, welche ein Verfahren einer Herstellung der Untergeschoßeinheit 10 zeigen, wobei Fig. 24A einen Zustand zeigt, nachdem Fertigbeton in eine Form für den unteren Strukturblock mit bereits angeordneten Stahlbewehrungen gegossen wurde, und wobei Fig. 24B einen Zustand zeigt, nachdem Fertigbeton in eine Form für den oberen Strukturblock mit bereits darin angeordneten Stahlbewehrungen gegossen wurde.A method of manufacturing the structural blocks according to the third embodiment will be described below with reference to FIGS. 24A and 24B. FIG. 24A and 24B are sectional views showing a method of production of the lower floor unit 10, wherein FIG. 24A shows a state after finished concrete was poured into a mold for the lower structural block with pre-arranged steel reinforcements, and Fig. 24B a state shows after ready-mixed concrete was poured into a mold for the upper structural block with steel reinforcements already arranged in it.
Eine erste Form 42, wie sie in Fig. 24A gezeigt ist, wird verwendet, um den unteren Strukturblock 1 herzustellen. Die erste Form 42 weist eine Aus nehmung bzw. einen Hohlraum 41a auf, welche(r) dieselbe, jedoch invertierte, dreidimensionale Form wie der untere Strukturblock 1 aufweist. Die Beweh rungsstäbe F werden zuerst in der Ausnehmung 41a angeordnet. Die Winkel platten L1, L2 werden an den Bodenenden der Bewehrungsstäbe F in Fig. 24A angeschweißt. Nachfolgend wird Fertigbeton in die Ausnehmung 41a einge gossen, während die erste Form 41 unter Verwendung eines Formvibrators bzw. -rüttlers, welcher nicht dargestellt ist, gerüttelt wird. Die erste Form 41 wird dann stehen gelassen, um ein Setzen des Betons zu erlauben. Nachdem der Beton ausgehärtet wurde und ausreichende Festigkeit erlangt hat, wird der neu hergestellte, untere Strukturblock 1 aus der Ausnehmung 41a der ersten Form 41 entfernt. Während des Vorgangs des Betonaushärtens kann der Beton durch Zufuhr von Dampf in die erste Form 41 erwärmt bzw. erhitzt werden, um das Aushärten des Betons zu beschleunigen.A first mold 42 , as shown in FIG. 24A, is used to manufacture the lower structural block 1 . The first shape 42 has a recess or a cavity 41 a, which has the same, but inverted, three-dimensional shape as the lower structure block 1 . The reinforcement bars F are first arranged in the recess 41 a. The angle plates L1, L2 are welded to the bottom ends of the reinforcing bars F in Fig. 24A. Subsequently, ready-mixed concrete is poured into the recess 41 a, while the first mold 41 is vibrated using a vibrator or vibrator, which is not shown. The first mold 41 is then left to allow setting of the concrete. After the concrete has hardened and has gained sufficient strength, the newly produced, lower structural block 1 is removed from the recess 41 a of the first mold 41 . During the concrete hardening process, the concrete may be heated by supplying steam to the first mold 41 to accelerate the hardening of the concrete.
Zur Herstellung des oberen Strukturblocks 2 wird eine zweite Form 42, wie sie in Fig. 24B gezeigt ist, verwendet. Diese zweite Form 42 weist eine Öffnung bzw. einen Hohlraum 42a auf, welche(r) dieselbe, nichtinvertierte, dreidimensionale Form wie der obere Strukturblock 2 aufweist. Nach einem An ordnen der Bewehrungsstäbe F in dem Hohlraum 42a wird Fertigbeton in den Hohlraum 42a eingebracht, um den oberen Strukturblock 2 auszubilden. An den Bodenenden der Bewehrungsstäbe F werden die Winkelplatten L3, L4 ähnlich wie oben angeschweißt. Dann wird der eingegossene Beton setzen gelassen, bis der obere Strukturblock 2 im wesentlichen auf dieselbe Weise wie die Produktion des unteren Strukturblocks 1 fertig gestellt ist. A second mold 42 , as shown in FIG. 24B, is used to produce the upper structural block 2 . This second shape 42 has an opening or cavity 42 a, which has the same, non-inverted, three-dimensional shape as the upper structure block 2 . After arranging the reinforcing bars F in the cavity 42 a, ready-mixed concrete is introduced into the cavity 42 a to form the upper structural block 2 . At the bottom ends of the reinforcing bars F, the angle plates L3, L4 are welded on similarly as above. Then the poured concrete is allowed to set until the upper structural block 2 is completed in substantially the same manner as the production of the lower structural block 1 .
Fig. 25 ist eine Seitenansicht im Schnitt, welche ein umgebendes Fundament 91 illustriert, welches eine zweite Ausführungsform der Installation auf der Baustelle gemäß der Erfindung darstellt, und Fig. 26 ist eine Draufsicht darauf. Obwohl die Untergeschoßeinheit 10, welche keine Türöffnung in ihrer Wand aufweist, im wesentlichen in dieser Ausführungsform verwendet wird, kann das Verfahren zur Installation auf der Baustelle nicht nur auf derartige Untergeschoßeinheiten angewandt werden, sondern auch auf solche, welche mit Türöffnungen gemäß der Erfindung ausgebildet sind. Fig. 25 is a side view in section illustrating a surrounding foundation 91 which according illustrating a second embodiment of the installation at the construction site of the invention, and Fig. 26 is a plan view thereof. Although the basement unit 10 , which has no door opening in its wall, is used essentially in this embodiment, the method for installation on the construction site can be applied not only to such basement units, but also to those which are designed with door openings according to the invention .
Zur Anwendung des Baustellen-Installationsverfahrens gemäß dieser Ausführungsform wird eine Mehrzahl von Gruppen von Ankerstäben (Ankerele menten) 9, wobei jede Gruppe aus drei Ankerstäben besteht, an den oberen Abschnitten der umgebenden Wände 21 jedes oberen Strukturblocks 2 in regelmäßigen Abständen entlang einer vertikalen Richtung derart eingebettet, daß sie sich entlang der Umfangsrichtung der umgebenden Wände 21 er strecken. Die Ankerstäbe 9 sind derart vorgesehen, daß ihre freien bzw. vor deren Enden horizontal von den umgebenden Wänden 21 des oberen Struk turblocks 2 um einen vorbestimmten Abstand vorragen.To apply the construction site installation method according to this embodiment, a plurality of groups of anchor rods (anchor elements) 9 , each group consisting of three anchor rods, are formed on the upper portions of the surrounding walls 21 of each upper structural block 2 at regular intervals along a vertical direction embedded that they stretch along the circumferential direction of the surrounding walls 21 he. The anchor rods 9 are provided in such a way that their free or in front of their ends project horizontally from the surrounding walls 21 of the upper structural block 2 by a predetermined distance.
Derartige Ankerstäbe 9 sind in dem oberen Strukturblock 2 durch Anordnen der Ankerstäbe 9 in der zur Herstellung des oberen Strukturblocks 2 verwendeten Form und nachfolgendes Eingießen von Fertigbeton in die Form eingebettet. In dieser Ausführungsform werden Eisenstäbe bzw. -stangen, deren Basisenden gebogen sind, für die Ankerstäbe 9 verwendet. Alternativ kann der obere Strukturblock 2 mit den Ankerstäben 9 durch Einbetten von länglichen, zylindrischen Muttern darin, deren Öffnungen nach außen gerichtet sind, und spiralweises Eingreifen bzw. Einschrauben der Ankerstäbe 9 darin mit an der Außenseite ausgebildeten Gewindeabschnitten in diese Muttern ausgestattet werden.Such anchor rods 9 are embedded in the upper structural block 2 by arranging the anchor rods 9 in the shape used to produce the upper structural block 2 and then pouring ready-mixed concrete into the mold. In this embodiment, iron rods or bars, the base ends of which are bent, are used for the anchor rods 9 . Alternatively, the upper structural block 2 can be provided with the anchor rods 9 by embedding elongated, cylindrical nuts therein, the openings of which are directed outwards, and spirally engaging or screwing in the anchor rods 9 therein with threaded sections formed on the outside in these nuts.
Nachdem die mit derartigen Ankerstangen 9 versehene Untergeschoß einheit 10 in einer bereits ausgegrabenen, vertikalen Grube auf der Baustelle angeordnet wird, wird eine bestimmte Anzahl von Bewehrungsstäben F so angeordnet, um die freien bzw. vorragenden Enden der entsprechenden Anker stangen 9 zu kreuzen. Das umgebende Fundament 91 wird an der Oberseite des oberen Strukturblocks 2, wie dies in den Fig. 25 und 26 gezeigt ist, durch Eingießen von Fertigbeton in die Grube auf der Baustelle ausgebildet, um die Bewehrungsstäbe F gemäß einem bekannten Verfahren einzugraben bzw. zu umgeben. After the basement unit 10 provided with such anchor rods 9 is arranged in an already excavated, vertical pit on the construction site, a certain number of reinforcement bars F are arranged so as to cross the free or projecting ends of the corresponding anchor rods 9 . The surrounding foundation 91 is formed on the top of the upper structural block 2 , as shown in FIGS. 25 and 26, by pouring ready-mixed concrete into the pit on the construction site to dig in or surround the reinforcing bars F according to a known method .
Da das umgebende Fundament 91 die Untergeschoßeinheit 10 gemäß dem Baustellen-Installationsverfahren gemäß der zweiten Ausführungsform umgibt, kann ein auf die Untergeschoßeinheit 10 wirkender Erddruck durch das umgebende Fundament 91 gemildert bzw. vergleichmäßigt werden. Insbe sondere in dem Fall, in welchem ein Pfählungsfundament oder ein Träger fundament um die Untergeschoßeinheit 10 vorliegt, wirkt das Gewicht eines auf diesen Fundamenten gebauten Gebäudes als Erddruck auf die Unterge schoßeinheit 10. Das umgebende Fundament 91 blockiert jedoch den ausge übten Erddruck, um dadurch seinen Einfluß auf die Untergeschoßeinheit 10 zu verringern. Demgemäß kann der Nachteil einer überflüssigen Verschwendung von Bauplatz durch verstärkte Wände der Untergeschoßeinheit, Anbringen von Rammen am Boden des Pfahlfundaments und Trägerfundaments und weiters Anordnen eines Bodenabschnitts (Bodenbereich) des hergestellten Geschoß fundaments in einer Position entfernt von der Untergeschoßeinheit 10 vermie den werden.Since the surrounding foundation 91 surrounds the basement unit 10 in accordance with the construction site installation method according to the second embodiment, an earth pressure acting on the basement unit 10 can be mitigated or evened out by the surrounding foundation 91 . In particular, in the particular case in which a pile foundation or a support foundation is present around the basement unit 10 , the weight of a building built on these foundations acts as earth pressure on the basement unit 10 . However, the surrounding foundation 91 blocks the earth pressure exercised, thereby reducing its influence on the basement unit 10 . Accordingly, the disadvantage of an unnecessary waste of space by reinforced walls of the basement unit, attaching rams to the bottom of the pile foundation and support foundation and further arranging a floor portion (floor area) of the manufactured floor foundation in a position away from the basement unit 10 can be avoided.
Weiters, in Abhängigkeit von der Situation, kann das auf Bodenniveau gebaute Gebäude durch das umgebende Fundament 91 abgestützt werden, woraus resultiert, daß die Fundamente, umfassend die Untergeschoßeinheit 10, als ein Mattenfundament besser standhalten können.Furthermore, depending on the situation, the ground level building can be supported by the surrounding foundation 91 , resulting in the foundations, including the basement unit 10 , being better able to withstand than a mat foundation.
Das umgebende Fundament 91 und die Untergeschoßeinheit 10 werden in eine einstückige Einheit durch Einbetten einer bestimmten Anzahl von Ankerstäben 9 geformt, welche nach außen um einen vorbestimmten Abstand in Bereichen entsprechend dem umgebenden Fundament 91 von der Unter geschoßeinheit 10 vorragen und indem das umgebende Fundament 91 mit den Ankerstäben 9 und den angeordneten Verstärkungs- bzw. Bewehrungsstäben F installiert bzw. ausgebildet wird. Demgemäß wird, selbst wenn ein Gebäude auf dem umgebenden Fundament 91 gebaut wird, das Gewicht des Gebäudes, welches auf das umgebende Fundament 91 wirkt, durch die Bodenoberfläche der Untergeschoßeinheit 10 als auch durch die Bodenoberfläche des umgeben den Fundaments 91 abgestützt, wodurch eine zuverlässigere Abstützung des Gebäudes und eine Verbesserung der Erdbebenwiderstandsfähigkeit erzielbar ist.The surrounding foundation 91 and the basement unit 10 are formed in a one-piece unit by embedding a certain number of anchor rods 9 , which project outwards by a predetermined distance in areas corresponding to the surrounding foundation 91 from the lower storey unit 10 and by surrounding the surrounding foundation 91 the anchor bars 9 and the arranged reinforcement bars F is installed or formed. Accordingly, even when a building is built on the surrounding foundation 91 , the weight of the building acting on the surrounding foundation 91 is supported by the floor surface of the basement unit 10 as well as the floor surface of the surrounding foundation 91 , thereby providing more reliable support of the building and an improvement in earthquake resistance can be achieved.
Die Erfindung ist nicht auf die vorangehenden Ausführungsformen
beschränkt, sondern umfaßt auch die folgenden Ausführungsformen.
1. In den vorangehenden Ausführungsformen sind die oberen Enden des
unteren Strukturblocks 1 und die Bodenenden des oberen Strukturblocks 2 mit
miteinander in Eingriff bringbaren bzw. zusammenwirkenden, abgestuften bzw.
abgesetzten Enden 15, 24 ausgebildet, wenn die oberen und unteren
Strukturblöcke 1, 2 verbunden sind. Die Erfindung ist jedoch nicht auf eine
derartige Konstruktion beschränkt, in welcher abgestufte Enden 15, 24 in
beiden Enden ausgebildet sind. Es können sich in Längsrichtung erstreckende
Nuten entweder an den oberen Enden des unteren Strukturblocks 1 und den
Bodenenden des oberen Strukturblocks 2 ausgebildet sein, während längliche
Vorsprünge, welche in diese Nuten bzw. Rillen einpaßbar sind, in dem anderen
der Bauteile ausgebildet sein können. Der Querschnitt der Nuten und
Vorsprünge kann eine geeignete Form, wie beispielsweise einen Bogen oder
ein Dreieck, aufweisen. Alternativ können diese Enden flach sein, ohne mit den
abgestuften Enden 15, 24 oder Nuten und Vorsprüngen ausgebildet zu sein.
2. Obwohl ein plattenförmiges Gummiprodukt als das Abdichtelement 3
in den vorangehenden Ausführungsformen verwendet wird, ist das Abdicht
element 3 gemäß der Erfindung nicht darauf beschränkt. Beispielsweise kann
das Abdichtelement 3 aus synthetischem Harz gebildet sein, welches exzellente
Flexibilität und Wasserwiderstandsfähigkeit aufweist, oder durch Aufbringen
einer Gummi oder ein synthetisches Harz, welches eine hohe Viskosität
aufweist, als eine Hauptkomponente enthaltenden Emulsion gebildet sein. Ein
weiteres Beispiel ist die Anbringung eines Epoxy-Klebers auf Kontaktoberflä
chen und eine Verwendung einer resultierenden Kleberschicht als das Abdicht
element 3.
3. Eine Wasserabdichtbehandlung kann an der innenliegenden oder
außenliegenden Oberfläche oder beiden der einzelnen Wände der Unterge
schoßeinheit 10 (10a, 10b) aufgebracht werden. Dies wird das Eindringen von
Grundwasser durch die umgebenden Wände 12, 21 in einer zuverlässigeren
Weise verhindern.
4. Obwohl die Untergeschoßeinheit 10 (10a, 10b) der obengenannten
Ausführungsformen eine zweilagige Konfiguration, umfassend den unteren
Strukturblock 1 (1a, 1b) und den oberen Strukturblock 2 (2a, 2b), aufweist, kann
eine Konfiguration, welche drei oder mehr übereinander aufgestapelte bzw.
aufgerichtete Blöcke gemäß der Erfindung einsetzt, verwendet werden.
5. Obwohl die Abmessungen der Fundamentplatte 100 gewählt sind, um
ein Paar von Untergeschoßeinheit 10a, 10b in der zweiten Ausführungsform
aufzunehmen, können Fundamentplatten 100 in unterschiedlichen Größen,
beinhaltend diejenige für eine einzelne Untergeschoßeinheit und drei oder mehr
Untergeschoßeinheiten gemäß der Erfindung, konstruiert werden.
6. Obwohl ein druckbeständiger Gummi für die Abstandhalter 101,
welche aus elastischen Elementen gebildet sind, zwischen dem unteren Struk
turblock 1 (1a, 1b) und der Fundamentplatte 100 in den vorangehenden Aus
führungsformen vorgesehen ist, ist das Material für die Abstandhalter 101 nicht
auf einen derartigen Gummi gemäß der Erfindung beschränkt. Jegliches
elastisches Element kann verwendet werden, vorausgesetzt, daß es eine
bestimmte Druckbeständigkeit aufweist. Beispielsweise kann synthetisches
Harz oder Stahlstücke verwendet werden. Die Verwendung von Kunststoffabfall
als synthetisches Harz trägt zur Reduktion der Materialkosten bei und ist aus
Umweltschutzgründen angenehmer. Vorzugsweise können Stahlstücke in Form
einer Feder oder U-Form oder einer Schraubenfeder verwendet werden.
7. In der Modifikation der zweiten Ausführungsform werden der zweite,
untere und obere Strukturblock 1b und 2b geneigt relativ zu der ersten Unterge
schoßeinheit 10a angehoben und abgesenkt, wie dies in den Fig. 19 und 20 ge
zeigt ist, so daß das umgebende Abdichtelement 33 zwischen den zwei Unter
geschoßeinheiten 10a und 10b gepreßt wird, wenn die zweite Unterge
schoßeinheit 10b abschließend unmittelbar benachbart der ersten Unterge
schoßeinheit 10a installiert wird. Stattdessen können die zweiten, unteren und
oberen Strukturblöcke 1b, 2b benachbart der ersten Untergeschoßeinheit 10a
abgesenkt werden, während sie horizontal orientiert sind, und das umgebende
Abdichtelement 33 kann zwischen den Untergeschoßeinheiten 10a und 10b
durch Bewegen der zweiten Untergeschoßeinheit 10b in Richtung zur ersten
Untergeschoßeinheit 10a durch ein Klemmen oder dgl. gepreßt werden.
The invention is not limited to the preceding embodiments, but also includes the following embodiments.
1. In the foregoing embodiments, the upper ends of the lower structural block 1 and the bottom ends of the upper structural block 2 are formed with interlocking, stepped ends 15 , 24 when the upper and lower structural blocks 1 , 2 are connected are. However, the invention is not limited to such a construction in which stepped ends 15 , 24 are formed in both ends. Longitudinally extending grooves can be formed either at the upper ends of the lower structural block 1 and the bottom ends of the upper structural block 2 , while elongated projections which can be fitted into these grooves or grooves can be formed in the other of the components. The cross section of the grooves and protrusions may have a suitable shape, such as an arc or a triangle. Alternatively, these ends can be flat without being formed with the stepped ends 15 , 24 or grooves and protrusions.
2. Although a plate-shaped rubber product is used as the sealing member 3 in the previous embodiments, the sealing member 3 according to the invention is not limited to this. For example, the sealing member 3 may be formed of synthetic resin which has excellent flexibility and water resistance, or may be formed by applying a rubber or a synthetic resin having a high viscosity as an emulsion containing a main component. Another example is the application of an epoxy adhesive to contact surfaces and the use of a resulting adhesive layer as the sealing element 3 .
3. A waterproofing treatment can be applied to the inside or outside surface or both of the individual walls of the basement unit 10 ( 10 a, 10 b). This will prevent groundwater from entering through the surrounding walls 12 , 21 in a more reliable manner.
4. Although the basement unit 10 ( 10 a, 10 b) of the above embodiments has a two-layer configuration comprising the lower structural block 1 ( 1 a, 1 b) and the upper structural block 2 ( 2 a, 2 b), one configuration may be used which uses three or more stacked blocks according to the invention.
5. Although the dimensions of the foundation slab 100 are selected to accommodate a pair of basement units 10 a, 10 b in the second embodiment, foundation slabs 100 can be constructed in different sizes, including that for a single basement unit and three or more basement units according to the invention become.
6. Although a pressure-resistant rubber for the spacers 101 , which are formed from elastic elements, is provided between the lower structure block 1 ( 1 a, 1 b) and the foundation plate 100 in the preceding embodiments, the material for the spacers 101 not limited to such a rubber according to the invention. Any elastic element can be used provided that it has a certain pressure resistance. For example, synthetic resin or steel pieces can be used. The use of plastic waste as a synthetic resin helps to reduce material costs and is more pleasant for environmental reasons. Steel pieces in the form of a spring or U-shape or a helical spring can preferably be used.
7. In the modification of the second embodiment, the second, lower and upper structural block 1 b and 2 b are inclined relative to the first lower floor unit 10 a raised and lowered, as shown in FIGS . 19 and 20, so that the surrounding sealing element 33 between the two lower floor units 10 a and 10 b is pressed when the second lower floor unit 10 b is finally installed immediately adjacent to the first lower floor unit 10 a. Instead, the second, lower and upper structural blocks 1 b, 2 b adjacent to the first basement unit 10 a can be lowered while being oriented horizontally, and the surrounding sealing element 33 can be between the basement units 10 a and 10 b by moving the second basement unit 10 b pressed towards the first basement unit 10 a by clamping or the like.
Ein praktisches Beispiel eines Hauses, welches die Untergeschoß- bzw. Kellerstruktur dieser Erfindung verwirklicht, wird nun beschrieben. In diesem praktischen Beispiel wird zerkleinertes Gestein am Boden einer vertikalen Grube anstelle der Fundamentplatte 100 angeordnet. Fig. 27 ist ein Aufriß des Hauses, wie es von der Südseite gesehen ist, Fig. 28 ist ein Geschoßplan des ersten Geschosses des in Fig. 27 gezeigten Hauses und Fig. 29 ist eine perspektivische Ansicht, teilweise im Schnitt, eines Untergeschosses U, welches in Fig. 27 gezeigt ist. Wie in diesen Figuren gezeigt, war das Untergeschoß U von einer Sechsmatten-Größe-Untergeschoßeinheit 10 gemäß der Erfindung (siehe Tabelle 1) konstruiert, welche unter einem nach Süden gerichteten Achtmatten-Wohnraum L des Hauses angeordnet ist. Glasschiebetüren, welche jeweils eine Breite von etwa 1,8 m aufweisen, und eine Stiege bzw. Treppe U1, die einen Zutritt zu dem Untergeschoß U ermöglicht, waren an der Südseite des Wohnraums L montiert, um eine Tageslichtbeleuchtung des Untergeschosses U zu erleichtern.A practical example of a house which realizes the basement structure of this invention will now be described. In this practical example, crushed rock is placed at the bottom of a vertical pit instead of the foundation plate 100 . Fig. 27 is an elevation of the house as seen from the south side, Fig. 28 is a floor plan of the first floor of the house shown in Fig. 27 and Fig. 29 is a perspective view, partly in section, of a basement U, which is shown in Fig. 27. As shown in these figures, the basement U was constructed by a six mat size basement unit 10 according to the invention (see Table 1) which is located under a south facing eight mat living space L of the house. Glass sliding doors, each with a width of about 1.8 m, and a staircase or staircase U1, which allows access to the basement U, were mounted on the south side of the living room L to facilitate daylight illumination of the basement U.
In diesem Beispiel war die Untergeschoßeinheit 10 unter Verwendung von hochfestem Schnellbinder-Portlandzement (JISR 5710) hergestellt. Der Zement wurde mit Zusäuen, umfassend ein Luftaufnahme- und Wasserredu ziermittel und geblähtes Kieselgel und Leichtgewicht-Aggregatmaterialien, be inhaltend feine Partikel und grobe Partikel (MA 317), zusätzlich zu Wasser, vermischt, um eine verbesserte Wasserabdicht- und Leichtgewichtseigenschaft des fertiggestellten Betons zur Verfügung zu stellen. Zwei Arten von Bewehrungsstäben F mit einem Durchmesser von 9 mm und 13 mm wurden in jedem Strukturblock 1, 2 (Fig. 1) angeordnet. Das Abdichtelement 3 (Fig. 3A und 3B), welches aus pastenartigem Gummi und einer Asphaltemulsion ge bildet war, wurde zwischen dem unteren Strukturblock 1 und dem oberen Struk turblock 2 angeordnet. Tabelle 2 unten zeigt die detaillierten Eigenschaften des Betons. In this example, the basement unit 10 was made using high strength quick binder Portland cement (JISR 5710). The cement was mixed with acidifying agents including an air intake and water reducing agent and expanded silica gel and lightweight aggregate materials containing fine particles and coarse particles (MA 317) in addition to water to provide improved waterproofing and lightweight properties of the finished concrete To make available. Two types of reinforcing bars F with a diameter of 9 mm and 13 mm were arranged in each structural block 1 , 2 ( Fig. 1). The sealing element 3 ( FIGS. 3A and 3B), which was formed from paste-like rubber and an asphalt emulsion, was arranged between the lower structural block 1 and the upper structural block 2 . Table 2 below shows the detailed properties of the concrete.
Es ist möglich, eine Druckfestigkeit von 210 kgf/cm2 oder darüber mit dem zur Herstellung der einzelnen Strukturblöcke 1, 2 zu verwendendem Beton und einen Diffusionskoeffizienten (ein Index, welcher die Wasserabdichteigen schaft repräsentiert) von 10 × 104 cm2/s oder weniger unter Verwendung der oben genannten Materialien gemäß dem in Tabelle 2 gezeigten Schema zu erreichen. Bei der Herstellung der Strukturblöcke 1, 2 dieses praktischen Beispiels in einer Fabrik wurde Fertigbeton, welcher durch Mischen der oben genannten Materialien vorbereitet wurde, in die ersten und zweiten Formen 41 und 42 gegossen, und nachdem drei Stunden nach dem Einbringen des Betons verstrichen waren, wurde Dampf in die einzelnen Formen 41, 42 eingeblasen, um den Beton auf 65°C mit einer Rate von 20°C pro Stunde aufzuheizen. Der Beton wurde auf dieser Temperatur für eine Dauer von 4 h gehalten, um ein Setzen zu ermöglichen. Nachdem der Beton auf übliche Weise auf Normaltemperatur abgekühlt wurde, wurden die Strukturblöcke 1, 2 aus den Formen 41, 42 entfernt. Die derart hergestellten Strukturblöcke 1, 2 wurden in diesem praktischen Beispiel verwendet. Tabelle 3 unten gibt Spezifikationen der Strukturblöcke 1, 2 an. It is possible to have a compressive strength of 210 kgf / cm 2 or more with the concrete to be used for producing the individual structural blocks 1 , 2 and a diffusion coefficient (an index representing the water-proof property) of 10 × 104 cm 2 / s or less using the above materials according to the scheme shown in Table 2. In manufacturing the structural blocks 1 , 2 of this practical example in a factory, precast concrete prepared by mixing the above materials was poured into the first and second molds 41 and 42 , and after three hours had passed after the concrete was poured, steam was blown into the individual molds 41 , 42 to heat the concrete to 65 ° C at a rate of 20 ° C per hour. The concrete was held at this temperature for a period of 4 hours to allow setting. After the concrete was cooled to normal temperature in the usual way, the structural blocks 1 , 2 were removed from the molds 41 , 42 . The structural blocks 1 , 2 thus produced were used in this practical example. Table 3 below gives specifications of structure blocks 1 , 2 .
Die folgende Diskussion beschreibt, wie die einzelnen Strukturblöcke 1, 2 unter Bodenniveau in diesem praktischen Beispiel installiert wurden, wobei auf Fig. 30 und 31 Bezug genommen wird. Fig. 30 ist eine Seitenansicht im Schnitt, welche eine Fundamentstruktur und eine Blockaufstellarbeit illustriert, und Fig. 31 ist eine Draufsicht auf eine Grube bzw. Aushebung U2, in welcher die Strukturblöcke 1, 2 angeordnet wurden. Die schachtelförmige Grube U2 entsprechend dem Wohnraum L (siehe Fig. 28) wurde zuerst unter Verwendung einer konventionellen Grabenschneidtechnik oder einer anderen geeigneten Methode an der Südseite (rechte Seite in Fig. 30) einer Fundamentwand X ausgegraben, welche in der Ost-West-Richtung auf der Nordseite des Wohnraumes L verlief, wie dies in Fig. 30 gezeigt ist. Die in diesem Beispiel vorbereitete Grube U2 war 1,9 m tief, 4,5 m lang in der Ost-West-Richtung und 3,5 m lang in der Nord-Süd-Richtung.The following discussion describes how the individual structural blocks 1 , 2 were installed below floor level in this practical example, with reference to FIGS. 30 and 31. Fig. 30 is a sectional side view illustrating a foundation structure and block erection work, and Fig. 31 is a plan view of a pit U2 in which the structure blocks 1 , 2 have been arranged. The box-shaped pit U2 corresponding to the living space L (see Fig. 28) was first excavated using a conventional trench cutting technique or another suitable method on the south side (right side in Fig. 30) of a foundation wall X, which is in the east-west direction was on the north side of the living space L, as shown in FIG. 30. The pit U2 prepared in this example was 1.9 m deep, 4.5 m long in the east-west direction and 3.5 m long in the north-south direction.
Vier Beton-Reibungspfähle U4 mit einem quadratischen Querschnitt von 30 × 30 cm und einer Länge von 6 m wurden in den Boden der Grube U2 eingetrieben, wobei ihre oberen Abschnitte bis zu 10 cm über dem Boden der Grube U2 vorragten, wie dies in Fig. 31 gezeigt ist. Nachfolgend wurde zer kleinerter Stein U3, wobei einzelne Teile im Durchschnitt etwa 40 mm Durch messer aufwiesen, auf dem Boden der Grube U2 angeordnet und auf eine Dicke von etwa 10 cm verdichtet, um ein Fundamentbett zu bilden. Da jeder Reibungspfahl U4 dieses praktischen Beispiels eine Lastaufnahmekapazität von 7,2 tf aufwies, stellten die vier Beton-Reibungspfähle U4 die gesamte Last aufnahmekapazität von 28,8 tf zur Verfügung. Da diese Lastaufnahmekapazität mehr als zweimal so groß wie das Gewicht (11,7 tf) der Untergeschoßeinheit 10 dieses Beispiels war, wies die derart hergestellte Fundamentstruktur die Möglichkeit auf, sicher eine differentielle Setzung des Hauses zu vermeiden.Four concrete friction piles U4 with a square cross section of 30 × 30 cm and a length of 6 m were driven into the bottom of the pit U2, their upper sections protruding up to 10 cm above the bottom of the pit U2, as shown in Fig. 31 is shown. Subsequently, crushed stone U3, with individual parts having an average diameter of about 40 mm, was arranged on the bottom of the pit U2 and compacted to a thickness of about 10 cm to form a foundation bed. Since each friction pile U4 of this practical example had a load bearing capacity of 7.2 tf, the four concrete friction piles U4 provided the total load bearing capacity of 28.8 tf. Since this load bearing capacity was more than twice the weight (11.7 tf) of the basement unit 10 of this example, the foundation structure produced in this way had the possibility of safely avoiding differential settlement of the house.
Nach Beendigung der oben beschriebenen Fundamentarbeiten wurde der untere Strukturblock 1 durch einen Kran angehoben und an seinen Platz auf dem Boden der Grube U2 gestellt. Die obengenannte, pastenartige Emul sion wurde auf die abgestuften Enden 15 des unteren Strukturblocks 1 mit einer Dicke von 30 mm aufgebracht, um das Abdichtelement 3 auszubilden.After completion of the foundation work described above, the lower structure block 1 was lifted by a crane and placed in its place on the bottom of the pit U2. The above-mentioned paste-like emulsion was applied to the stepped ends 15 of the lower structural block 1 with a thickness of 30 mm to form the sealing member 3 .
Nachdem das Abdichtelement 3 getrocknet war, wurde der obere Strukturblock 2 durch den Kran angehoben und auf den unteren Strukturblock 1 aufgelegt, um die Untergeschoßeinheit 10 in der Grube U2 zu bilden, wie dies durch strichlierte Linien in Fig. 30 gezeigt ist.After the sealing member 3 dried, the upper structural block 2 was lifted by the crane and placed on the lower structural block 1 to form the lower floor unit 10 in the pit U2, as shown by broken lines in FIG. 30.
Der obere Strukturblock 2 ragte um etwa 60 cm über die oberen Kanten der Grube U2 vor, wenn die Untergeschoßeinheit 10 in der Grube U2 ausge bildet war. Spalte zwischen der Untergeschoßeinheit 10 und der Grube U2 wurden dann mit zerkleinertem Stein U3 aufgefüllt, so daß die Untergeschoß einheit 10 unter Bodenniveau mit Ausnahme seines vorragenden Abschnitts eingegraben war. Nachfolgend wurde die obere Öffnung der Untergeschoßein heit 10 mit einer Deckenplatte abgedeckt und es wurde die Stiege bzw. Treppe U1, welche als ein Zutritt zu und von dem Wohnraum L dienen sollte, installiert. Das Innere der Untergeschoßeinheit 10 wurde dann fertiggestellt, um das Untergeschoß U fertigzustellen, wie dies in Fig. 29 gezeigt ist. Der obere Abschnitt der Untergeschoßeinheit 10, welche über Bodenniveau vorragte, wurde als ein Fundament für den Wohnraum L verwendet.The upper structural block 2 protruded about 60 cm above the upper edges of the pit U2 when the basement unit 10 was formed in the pit U2. Gaps between the basement unit 10 and the pit U2 were then filled with crushed stone U3, so that the basement unit 10 was buried below ground level with the exception of its protruding section. Subsequently, the upper opening of the Untergeschoßein unit 10 was covered with a ceiling plate and it was installed the stairs or stairs U1, which should serve as an access to and from the living room L. The interior of the basement unit 10 was then completed to complete the basement U, as shown in FIG. 29. The upper portion of the basement unit 10 , which protruded above the floor level, was used as a foundation for the living space L.
In diesem praktischen Beispiel betrug der Zeitraum der Baustellen-Kon struktionsarbeit von der Montage der Strukturblöcke 1, 2 in der Grube U2 bis zur Fertigstellung der Installation der Deckenplatte 11/2 Tage, wobei dies 1/10 bis 1/20 der Zeit war, welche für die Fertigstellung eines ähnlichen Unterge schosses durch konventionelle Baustellen-Betonverlegetechniken erforderlich war. Dies zeigt, daß die Untergeschoßstruktur gemäß der Erfindung eine signi fikante Reduktion der Zeit und der Kosten, welche für die Untergeschoßkon struktion erforderlich sind, zur Verfügung stellen kann.In this practical example of period 2 the ceiling panel 1 1/2 days was the construction site Kon constructive tion work of assembling the structure blocks 1, in the pit U2 until completion of the installation, where this was 1/10 to 1/20 of the time, which was necessary for the completion of a similar basement by conventional construction site concrete laying techniques. This shows that the basement structure according to the invention can provide a significant reduction in the time and cost required for the basement construction.
Wie oben beschrieben, umfaßt gemäß der erfindungsgemäßen Unterge schoßstruktur und ihrer Herstellungsmethode die Untergeschoßstruktur den unteren Strukturblock aus Stahlbeton, welcher den Bodenabschnitt und die um gebenden Wände aufweist, und wenigstens einen oberen Strukturblock aus Stahlbeton, welcher umgebende Wände und den Deckenabschnitt und dieselbe Form wie der untere Strukturblock in der Draufsicht aufweist, wobei der obere Strukturblock auf der Oberseite des unteren Strukturblocks angeordnet bzw. gestapelt wird, wobei das Abdichtelement zwischen dem oberen Ende des unteren Strukturblocks und dem Bodenende des oberen Strukturblocks an geordnet ist, wodurch eine Untergeschoßeinheit gebildet wird. Derart kann durch Unterteilen jeder Untergeschoßeinheit in einen unteren Strukturblock und wenigstens einen oberen Strukturblock aus Stahlbeton die Untergeschoßeinheit dieser Struktur in einer Fabrik hergestellt werden, selbst wenn sie eine große Größe aufweist, wobei dies in einer beträchtlichen Reduktion der Konstruktionskosten auf der Baustelle im Vergleich zu bekannten Unterge schoß-Konstruktionstechniken resultiert, bei welchen die gesamte Unterge schoßstruktur auf der Baustelle konstruiert wird.As described above, according to the invention structure and its method of manufacture the basement structure lower structural block made of reinforced concrete, which the floor section and around giving walls, and at least one upper structural block Reinforced concrete, which surrounding walls and the ceiling section and the same Shape as the lower structural block in plan view, the upper Structure block arranged on the top of the lower structure block or is stacked, the sealing element between the upper end of the lower structural block and the bottom end of the upper structural block is arranged, whereby a basement unit is formed. That can by dividing each basement unit into a lower structural block and at least one upper structural block made of reinforced concrete the basement unit This structure can be manufactured in a factory, even if it is a large one Size, with a considerable reduction in the Construction costs on the construction site in comparison to known sub-structures lap construction techniques result in which the entire base lap structure is constructed on the construction site.
Da darüberhinaus das Abdichtelement zwischen dem oberen Ende und dem unteren Ende der entsprechenden getrennten Strukturblöcke angeordnet wird, dichtet dieses den Verbindungsbereich zwischen den Strukturblöcken ab, wenn der obere Strukturblock auf der Oberseite des unteren Strukturblocks angeordnet ist, wodurch das Eindringen von Grundwasser in das Untergeschoß vermieden wird.In addition, since the sealing element between the upper end and the lower end of the corresponding separate structural blocks this seals the connection area between the structure blocks, if the top structure block is on top of the bottom structure block is arranged, which prevents the penetration of groundwater into the basement is avoided.
Im Fall einer konventionellen Untergeschoßstruktur, welche entlang einer vertikalen Ebene unterteilt ist, werden eine Vielzahl von Strukturblöcken durch Kabel oder dgl. befestigt, um das Abdichtelement zu halten. Dies resultiert je doch in erhöhten Konstruktionskosten und einem Nachteil, daß ein zuver lässiger Abdichteffekt aufgrund einer reduzierten Spannkraft nicht erzielt werden mag, welcher durch ein Verlängern und/oder Korrosion der Drähte bzw. Kabel bewirkt wird. Im Gegensatz dazu wird das Abdichtelement konstant durch das Gewicht des oberen Strukturblocks gemäß der vorliegenden Erfindung gepreßt. Dies macht ein Verspannen durch Kabel oder dgl. unnotwendig im Gegensatz zum bekannten Stand der Technik, wobei dies zu einer Reduktion der Konstruktionskosten beiträgt und konstant sicher das Eindringen von Grundwasser in das Untergeschoß vermeidet.In the case of a conventional basement structure, which runs along a vertical plane is divided, a variety of structural blocks are made by Cable or the like. Attached to hold the sealing element. This always results but in increased construction costs and a disadvantage that a verver casual sealing effect not achieved due to reduced tension which may be caused by lengthening and / or corrosion of the wires or Cable is effected. In contrast, the sealing element is constantly through the weight of the upper structural block according to the present invention pressed. This makes bracing by cables or the like unnecessary in the Contrary to the known prior art, this leads to a reduction which contributes to construction costs and constantly ensures the penetration of Avoids groundwater in the basement.
Da darüberhinaus die Untergeschoßstruktur bereits mit dem Deckenab schnitt ausgebildet ist, wenn dieser im Untergrund installiert wird, vermeidet dies die Notwendigkeit für eine derartige Arbeit vor Ort, wie ein Verlegen von Trägern am oberen Ende des oberen Strukturblocks, um die obere Öffnung der Untergeschoßeinheit zu schließen, wodurch die Kosten für die Baustellenarbeit verringert wird.In addition, since the basement structure already with the ceiling cut is avoided if this is installed underground this is the need for such work on site, such as relocating Beams at the top of the top structural block to the top opening of the Close basement unit, reducing the cost of construction site work is reduced.
Da darüberhinaus das obere Ende des unteren Strukturblocks und das untere Ende des oberen Strukturblocks mit den abgestuften bzw. abgesetzten Abschnitten ausgebildet sind, welche miteinander in Eingriff bringbar sind bzw. zusammenwirken, können die oberen und unteren Strukturblöcke sicher positio niert werden und ein horizontales Verschieben derselben kann wirkungsvoll verhindert werden. Indem zugelassen wird, daß die oberen und unteren, abgestuften Abschnitte ein geringes Spiel entlang der horizontalen Richtung aufweisen, können die abgestuften Bereiche miteinander mit einem erhöhten Freiheitsgrad in Eingriff gebracht werden. Dies erlaubt Abmessungsfehler der oberen und unteren Strukturblöcke und ermöglicht eine Feinjustierung im aufgerichteten Zustand. Daher können die oberen und unteren Strukturblöcke leichter hergestellt werden und die Baustellenkonstruktion des Untergeschosses wird einfacher.Furthermore, since the upper end of the lower structural block and the lower end of the upper structural block with the stepped or stepped Sections are formed which can be brought into engagement with one another or the upper and lower structural blocks can positively interact be niert and a horizontal displacement of the same can be effective be prevented. By allowing the upper and lower, graded sections a little play along the horizontal direction have, the stepped areas with each other with an elevated Degree of freedom can be engaged. This allows dimensional errors of the upper and lower structural blocks and allows fine adjustment in the erect state. Therefore, the top and bottom structure blocks easier to manufacture and the construction of the basement is getting easier.
Wenn das Abdichtelement aus Gummi hergestellt ist, kann der Verbin dungsbereich der oberen und unteren Strukturblöcke sicher wasserdicht gehal ten werden, da Gummi eine exzellente Flexibilität und Wasserabdichteigen schaft aufweist.If the sealing element is made of rubber, the connector can area of the upper and lower structural blocks safely waterproof because rubber has excellent flexibility and is waterproof shaft.
Wenn die Wasserabdichtbehandlung entweder auf einer oder beiden inneren und äußeren Wandoberflächen der Untergeschoßeinheit aufgebracht wird, kann das Eintreten von Grundwasser in das Untergeschoß durch die umgebenden Wände sicher verhindert werden.If the waterproofing treatment is on either or both inner and outer wall surfaces of the basement unit applied , groundwater can enter the basement through the surrounding walls can be prevented safely.
Wenn die unteren und oberen Strukturblöcke aus Beton gebildet sind, welcher eine Druckfestigkeit von wenigstens 210 kgf/cm2 aufweist, und der Bodenabschnitt des unteren Strukturblocks und die umgebenden Wände der unteren und oberen Strukturblöcke eine Dicke von wenigstens 150 mm auf weisen, weist das Untergeschoß selbst eine beträchtlich große Festigkeit auf, wenn es durch Installation der Untergeschoßeinheit unter Bodenniveau ausge bildet wird, und das obere Ende der Untergeschoßeinheit kann als ein Funda ment für ein auf Bodenniveau zu bauendes Gebäude dienen.When the lower and upper structural blocks are made of concrete having a compressive strength of at least 210 kgf / cm 2 and the bottom portion of the lower structural block and the surrounding walls of the lower and upper structural blocks are at least 150 mm thick, the lower floor has itself has a considerably large strength when it is formed by installing the lower floor unit below floor level, and the upper end of the lower floor unit can serve as a foundation for a building to be built at floor level.
Wenn der Beton mit einer Wasserabdichtmischung gemischt ist, kann das Eindringen von Wasser durch die umgebenden Wände sicher verhindert werden.If the concrete is mixed with a waterproofing mixture, can the penetration of water through the surrounding walls is safely prevented become.
Wenn jeder der unteren und oberen Strukturblöcke 2,5 bis 3,5 m breit, 0,8 bis 1,6 m hoch und 2,5 bis 9,0 m lang ist, sind die Strukturblöcke für eine Produktion, Förderung, Handhabung und einen Transport geeignet. Insbeson dere können sie auf öffentlichen Straßen unter Verwendung eines speziellen Fahrzeugs transportiert werden, wenn die Untergeschoßstruktur von einer Fabrik zu einer Baustelle transportiert wird, wo das Untergeschoß konstruiert bzw. aufgerichtet wird. If each of the lower and upper structural blocks is 2.5 to 3.5 m wide, The structural blocks for one are 0.8 to 1.6 m high and 2.5 to 9.0 m long Production, promotion, handling and transport suitable. In particular They can be used on public roads using a special Vehicle can be transported if the basement structure of a Factory is transported to a construction site where the basement is constructed or is erected.
Der untere Strukturblock umfaßt den oberen Ausschnitt, welcher durch Ausschneiden eines Bereiches eines flachen Teils der umgebenden Wände von dem oberen Ende ausgebildet wird, und der obere Strukturblock umfaßt den unteren Ausschnitt entsprechend dem oberen Ausschnitt, wobei die unteren und oberen Ausschnitte eine Öffnung ausbilden, wenn der obere Strukturblock auf der Oberseite des unteren Strukturblocks aufgerichtet wird, wobei die erste, umgebende bzw. umlaufende Vertiefung ihren Boden zur äußeren Seite der umgebenden Wände gerichtet hat, welche in der inneren Seite der Öffnung ausgebildet sind, und die zweite, umlaufende Vertiefungen im Boden zu der äußeren Seite der umgebenden Wände gerichtet ist und in der inneren Ober fläche der ersten, umlaufenden Vertiefung ausgebildet ist. Mit dieser Unter geschoßstruktur wird die Türöffnung, welche einen Zutritt zwischen zwei Untergeschoßeinheiten zur Verfügung stellt, durch Anordnen der einen und der anderen Untergeschoßeinheit unmittelbar nebeneinander ausgebildet, so daß die Öffnungen zueinander gerichtet sind. In dieser Türöffnung ist eine schmale Nut durch die ersten, umlaufenden Vertiefungen der entsprechenden Untergeschoßeinheiten gebildet und es ist die breite Nut durch die zweiten, umlaufenden Vertiefungen derselben ausgebildet. Daher kann das Eintreten von Grundwasser in die Untergeschoßeinheiten durch die Öffnungen der ent sprechenden Untergeschoßeinheiten durch Anbringen einer Verfüllung, d. h. eines Vorgangs eines Vergießens von Fertigbeton (beispielsweise wasserab weisenden Mörtel) in die breite Nut nach einem Einpassen des Abdichtglieds in die schmale Nut vermieden werden.The lower structure block includes the upper cutout, which through Cut out an area of a flat part of the surrounding walls from the upper end is formed, and the upper structural block comprises the lower cutout corresponding to the upper cutout, the lower and upper cutouts form an opening when the upper structural block is erected on top of the lower structure block, the first, surrounding or encircling depression their bottom to the outer side of the surrounding walls, which is in the inner side of the opening are formed, and the second, circumferential depressions in the bottom to the outer side of the surrounding walls is directed and in the inner upper surface of the first circumferential recess is formed. With this sub storey structure is the door opening, which gives access between two Provides basement units by arranging the one and the other basement unit immediately next to each other, so that the openings face each other. There is a narrow one in this door opening Groove through the first circumferential recesses of the corresponding Basement units formed and it's the wide groove through the second, circumferential depressions of the same. Hence the entry of groundwater into the basement units through the openings of the ent speaking basement units by attaching backfill, d. H. a process of pouring ready-mixed concrete (e.g. water pointing mortar) into the wide groove after fitting the sealing member into the narrow groove can be avoided.
Metallteile, welche einstückig mit Bewehrungsstäben verbunden sind, welche in den oberen und unteren Strukturblöcken angeordnet sind, sind an dem Bodenende des oberen Strukturblocks und an dem oberen Ende des unteren Strukturblocks vorgesehen, und die zu den oberen und unteren Struk turblöcken gehörenden Metallteile werden miteinander verbunden, wenn der obere Strukturblock auf der Oberseite des unteren Strukturblocks aufgerichtet ist. In dieser Untergeschoßstruktur wird die Untergeschoßeinheit als eine ein zige Einheit durch Verbindung der Metallelemente des unteren Strukturblocks mit denjenigen des oberen Strukturblocks ausgebildet. Demgemäß wird der Untergeschoßeinheit ermöglicht, einen größeren Scherwiderstand und Biege widerstand gegenüber einer in horizontaler Richtung wirkenden Kraft aufzu weisen, wobei dies sicher ein unerwünschtes Ereignis vermeidet, bei welchem die oberen und unteren Strukturblöcke voneinander getrennt werden. Daher wird der obere Strukturblock nicht in horizontaler Richtung gegenüber dem unteren Strukturblock während eines Erdbebens verschoben, woraus resultiert, daß die Untergeschoßeinheit eine exzellente Erdbebensicherheit aufweist.Metal parts, which are connected in one piece with reinforcing bars, which are arranged in the upper and lower structure blocks are on the bottom of the top structural block and at the top of the provided lower structure blocks, and those to the upper and lower structure Metal parts belonging to the door blocks are connected to each other when the upper structure block erected on top of the lower structure block is. In this basement structure, the basement unit becomes one unit by connecting the metal elements of the lower structural block formed with those of the upper structural block. Accordingly, the Basement unit allows greater shear resistance and bending resistance to a force acting in the horizontal direction point, which certainly avoids an undesirable event in which the upper and lower structure blocks are separated. Therefore the upper structure block is not in a horizontal direction compared to the lower structural block shifted during an earthquake, which results in that the basement unit has excellent earthquake resistance.
In einer bevorzugten Ausführungsform des erfindungsgemäßen Verfah rens wird der untere Strukturblock durch Anordnen von Bewehrungsstäben in der ersten Form, deren Ausnehmung bzw. Hohlraum dieselbe dreidimensionale Form wie der untere Strukturblock aufweist, und durch Gießen von Fertigbeton in die erste Form ausgebildet, und es wird der obere Strukturblock durch Anord nen von Bewehrungsstäben in einer zweiten Form, deren Ausnehmung bzw. Hohlraum dieselbe dreidimensionale Form wie der obere Strukturblock aufweist, und Eingießen von Fertigbeton in die zweite Form hergestellt. Gemäß diesem Verfahren werden die entsprechenden Strukturblöcke durch Gießen von Fertigbeton in die Formen hergestellt. Insbesondere kann der untere Strukturblock leicht entfernt werden, da die Form mit nach oben gerichtetem Boden verwendet wird.In a preferred embodiment of the method according to the invention The lower structural block is created by arranging reinforcing bars in the first shape, the recess or cavity of which is the same three-dimensional Form as the lower structural block and by pouring ready-mixed concrete formed into the first shape, and it becomes the upper structural block by arrangement reinforcement bars in a second form, their recess or Cavity has the same three-dimensional shape as the upper structural block, and pouring ready-mixed concrete into the second mold. According to this Process the corresponding structural blocks by casting Ready-made concrete made in the molds. In particular, the lower one Structure block can be easily removed as the shape is facing upwards Floor is used.
In dem erfindungsgemäßen Transportverfahren werden die Schritte eines Wendens jedes Strukturblocks um 90°, so daß seine längere Seitenwand parallel zu einer horizontalen Ebene wird; einer Montage jedes Strukturblocks in dem Schutzgestell; und ein Laden jedes in einem Gestell montierten Struktur blocks auf ein Kraftfahrzeug gemeinsam mit der Palette, welche derart angeordnet ist, daß ein Freiraum zwischen einer Auflageoberfläche derselben und der Straßenoberfläche 30 cm nicht übersteigt, während sie auf dem Fahrzeug montiert ist, zur Verfügung gestellt. Gemäß dem Transportverfahren kann die Höhe und Breite der Last auf einem speziellen Transportfahrzeug innerhalb von Bereichen in Übereinstimmung mit Straßenverkehrsgesetzen und -bestimmungen durch Drehen bzw. Verschwenken des Strukturblocks um 90°, so daß dieser auf seiner Seite liegt, fallen, woraus resultiert, daß die einzelnen Strukturblöcke über öffentliche Straßen transportiert werden können. Weiters kann der Strukturblock von einer Schlag- bzw. Stoßbeanspruchung während des Transports durch Montage in dem Gestell geschützt werden.The steps are in the transport method according to the invention turning each structural block 90 ° so that its longer side wall becomes parallel to a horizontal plane; an assembly of each structural block in the protective frame; and loading each structure mounted in a rack blocks on a motor vehicle together with the pallet, which such is arranged that a space between a support surface thereof and the road surface does not exceed 30 cm while on the road Vehicle is mounted, provided. According to the transportation procedure can adjust the height and width of the load on a special transport vehicle within areas in accordance with road traffic laws and -Determinations by rotating or swiveling the structural block through 90 °, so that it lies on its side, which results in the individual Structural blocks can be transported on public roads. Furthermore can the structural block from a shock or impact stress during during transport are protected by mounting in the frame.
In einer bevorzugten Ausführungsform des erfindungsgemäßen Trans portverfahrens umfaßt das Gestell die Abstützplatte zum Abstützen jedes Strukturblocks und den Rahmen, welcher über jedem Strukturblock, welcher auf der Supportplatte angeordnet ist, montiert ist, und der Rahmen kann fest mit der Supportplatte verbunden werden, während er über dem Strukturblock montiert ist. Demgemäß kann der Strukturblock in dem Gestell durch Montage des Rahmens über dem Strukturblock nach Anordnen desselben auf der Supportplatte und anschließendes, festes Verbinden der Supportplatte und des Rahmens gehalten bzw. aufgenommen werden. Derart kann der Strukturblock leicht in dem Gestell montiert bzw. festgelegt werden.In a preferred embodiment of the trans according to the invention port process, the frame includes the support plate for supporting each Structure blocks and the frame which over each structure block which is on the support plate is arranged, is mounted, and the frame can be firmly attached to the Support plate can be connected while it is mounted over the structural block is. Accordingly, the structural block can be mounted in the frame by mounting the Frame over the structure block after placing it on the Support plate and subsequent, firm connection of the support plate and the Frames are held or recorded. The structure block can do this can be easily mounted or fixed in the frame.
In einer anderen bevorzugten Ausführungsform des Transportverfahrens wird weiters der Schritt eines Entladens bzw. Abladens des auf dem Gestell montierten Strukturblocks zur Verfügung gestellt, wobei der Schritt des Entladens bzw. Abladens beinhaltet: Anheben des den Strukturblock enthal tenden Gestells in eine geneigte Position unter Verwendung der Hebevorrich tung; Absenken des Gestells auf die lastaufnehmende Vorrichtung, welche schwenkbar an einer horizontalen Welle zur Aufnahme des Bodenendes des Gestells abgestützt ist; und Legen des Gestells auf seine Seite durch Kippen bzw. Verschwenken der lastaufnehmenden Vorrichtung um die horizontale Welle. Demgemäß kann ein Schlag, welcher auf das den Strukturblock aufneh mende Gestell während des Erstladens einwirken wird, durch die last aufnehmende Vorrichtung gedämpft werden. Dies ist vorteilhaft für ein Entladen des Strukturblocks ohne Beschädigung desselben.In another preferred embodiment of the transport method further the step of unloading or unloading the on the frame assembled structural blocks provided, the step of Unloading or unloading includes: lifting the structure block rack in an inclined position using the lifting device tung; Lowering the frame onto the load-bearing device, which swiveling on a horizontal shaft for receiving the bottom end of the Frame is supported; and placing the rack on its side by tilting it or pivoting the load-bearing device around the horizontal Wave. Accordingly, a blow to the structural block may occur frame during initial charging will be affected by the load receiving device are damped. This is advantageous for unloading of the structural block without damaging it.
Das erfindungsgemäße Installationsverfahren umfaßt die Schritte: Aus graben der vertikalen Grube im Boden, welche wenigstens den unteren Struk turblock aufnehmen kann; Ausbilden des Steinfundaments durch Ablagern von zerkleinertem Gestein auf dem Boden der Grube; Anordnen des unteren Struk turblocks, welcher mit seiner Bodenseite nach unten angehoben ist, auf dem Steinfundament; und Anordnen des oberen Strukturblocks auf der Oberseite des unteren Strukturblocks, wobei das Abdichtelement zwischen dem oberen Ende des unteren Strukturblocks und dem unteren Ende des oberen Strukturblocks angeordnet ist, wodurch das Abdichtelement einen Verbindungs bereich zwischen den oberen und unteren Strukturblöcken abdichtet. Derart kann das Untergeschoß leicht in der vertikalen Grube durch nacheinander folgendes Anordnen der entsprechenden Strukturblöcke in der vertikalen Grube ausgebildet werden. Da der zerkleinerte Stein unter dem unteren Strukturblock angeordnet ist, wenn das Untergeschoß ausgebildet wird, kann der Boden des unteren Strukturblocks einheitlich oder eben durch dieses Steinfundament abgestützt werden, wodurch sicher ein Kippen bzw. Neigen des Untergeschosses vermieden wird. Da darüberhinaus der Verbindungsbereich zwischen den oberen und unteren Strukturblöcken durch das dazwischen ange ordnete Abdichtelement abgedichtet ist, kann das Eindringen von Grundwasser in das Untergeschoß durch die Verbindung sicher verhindert werden.The installation method according to the invention comprises the steps: off dig the vertical pit in the ground, which is at least the lower structure turblock can accommodate; Form the stone foundation by depositing crushed rock on the bottom of the pit; Arrange the bottom structure turblocks, which is raised with its bottom side down, on the Stone foundation; and placing the top structural block on top of the lower structural block, the sealing element between the upper End of the lower structural block and the lower end of the upper Structural blocks is arranged, whereby the sealing element connects seals between the upper and lower structural blocks. Such the basement can easily be moved through in the vertical pit then placing the corresponding structural blocks in the vertical pit be formed. Because the crushed stone under the lower structural block is arranged when the basement is formed, the bottom of the lower structural blocks uniformly or precisely through this stone foundation are supported, thereby safely tilting or tilting the Basement is avoided. Furthermore, the connection area between the upper and lower structure blocks by the in between orderly sealing element is sealed, the penetration of groundwater into the basement can be prevented by the connection.
In einer bevorzugten Ausführungsform des Installationsverfahrens ist weiters der Schritt eines Anbringens einer wasserdichten Verkleidung an der Innenseite der Untergeschoßeinheit im Verbindungsbereich zwischen den oberen und unteren Strukturblöcken vorgesehen, wo das Abdichtelement an geordnet ist. Demgemäß wird der Verbindungsbereich zwischen den oberen und unteren Strukturblöcken nicht nur durch das Abdichtelement, sondern auch durch die wasserdichte Auskleidung abgedichtet. Derart kann das Eindringen von Grundwasser in das Untergeschoß durch die Verbindung noch sicherer vermieden werden.In a preferred embodiment of the installation process further the step of attaching a waterproof panel to the Inside of the basement unit in the connection area between the Upper and lower structural blocks are provided where the sealing element attaches is ordered. Accordingly, the connection area between the top and lower structural blocks not only through the sealing element, but also sealed by the waterproof lining. So can the intrusion from groundwater to the basement through the connection even more secure be avoided.
In einer anderen bevorzugten Ausführungsform des Installationsver fahrens wird weiters der Schritt eines Eintreibens einer speziellen Anzahl von Reibungspfählen in den Boden der Grube vor dem Anordnen des unteren Strukturblocks in dieser zur Verfügung gestellt. Da ein starkes Fundament am Boden der vertikalen Grube durch Eintreiben der Reibungspfähle in diese aus gebildet werden kann, weist das Untergeschoß eine verbesserte Widerstands fähigkeit gegenüber Erdbeben auf und die durch die Reibungspfähle abge stützte Untergeschoßstruktur kann als ein stabiles Fundament für ein auf Bodenniveau zu bauendes Gebäude dienen.In another preferred embodiment of the installation ver driving becomes the step of driving in a special number of Friction piles in the bottom of the pit before placing the lower one Structure blocks provided in this. Since a strong foundation on Bottom of the vertical pit by driving the friction piles into it can be formed, the basement has an improved resistance ability to withstand earthquakes and which is reflected by the friction piles Supported basement structure can serve as a stable foundation for one Serve the building to be built at ground level.
Gemäß einem anderen erfindungsgemäßen Installationsverfahren um faßt dieses die Schritte: Ausheben einer vertikalen Grube bzw. Ausnehmung im Boden, welche zumindest die Fundamentplatte aufnehmen kann; Anordnen der Beton-Fundamentplatte auf dem Boden der vertikalen Grube; Anordnen von Abstandhaltern, welche von elastischen Elementen gebildet sind, auf der Fundamentplatte in vorgegebenen Abständen zum Abstützen des unteren Strukturblocks; Anordnen von gemischtem bzw. geknetetem Mörtel, welcher durch Mischen bzw. Kneten von Zement und Sand gebildet wird, auf der Funda mentplatte in derselben Dicke in einem Ausmaß, daß die Abstandhalter bedeckt werden, wodurch eine Schicht aus gemischtem Mörtel gebildet wird; Anordnen des unteren Strukturblocks auf der Schicht aus gemischtem Mörtel; und Anordnen des oberen Strukturblocks auf der Oberseite des unteren Strukturblocks, wobei das Abdichtelement zwischen dem oberen Ende des unteren Strukturblocks und dem unteren Ende des oberen Strukturblocks angeordnet wird, wodurch das Abdichtelement den Verbindungsbereich zwischen den oberen und unteren Strukturblöcken abdichtet. Demgemäß kann der untere Strukturblock durch eine Vielzahl von Abstandhaltern auf der Fundamentplatte durch Anordnen des unteren Strukturblocks auf dem Boden der vertikalen Grube abgestützt werden, nachdem die Schicht aus gemischtem Mörtel auf der Fundamentplatte ausgebildet wurde. Die Mörtelschicht wird zwischen der Bodenoberfläche des unteren Strukturblocks und der oberen Oberfläche der Fundamentplatte gehalten, während sie Abmessungsfehler der Fundamentplatte und des unteren Strukturblocks kompensiert. Durch Belassen für eine lange Zeit in diesem Zustand absorbiert die Schicht aus gemischtem Mörtel Feuchtigkeit aus der Erde, wobei dies das Ablaufen einer bestimmten chemischen Reaktion bewirkt. Dies verfestigt die Mörtelschicht, um dadurch ein Fundament in Übereinstimmung mit der Bodenoberfläche des unteren Strukturblocks zu bilden.According to another installation method according to the invention this summarizes the steps: digging a vertical pit or recess in the Floor which can at least accommodate the foundation plate; Arrange the Concrete foundation slab on the bottom of the vertical pit; Arrange Spacers, which are formed by elastic elements on the Foundation plate at predetermined intervals to support the lower one Structure blocks; Arranging mixed or kneaded mortar, which is formed by mixing or kneading cement and sand on the funda ment plate in the same thickness to an extent that the spacers covered forming a layer of mixed mortar; Arrange the lower structural block on the layer of mixed mortar; and Arrange the top structure block on top of the bottom one Structural blocks, the sealing element between the upper end of the lower structure block and the lower end of the upper structure block is arranged, whereby the sealing element connects the connection area seals between the upper and lower structural blocks. Accordingly the lower structural block by a variety of spacers on the Foundation plate by placing the lower structural block on the floor the vertical pit to be supported after the layer of mixed Mortar was formed on the foundation plate. The mortar layer is between the bottom surface of the lower structural block and the upper one Surface of the foundation plate is held while making dimensional errors Foundation plate and the lower structure block compensated. By leaving for a long time in this state the layer of mixed absorbs Mortar moisture from the earth, doing this a certain drain chemical reaction. This solidifies the mortar layer, thereby causing a Foundation in line with the bottom surface of the bottom To form structural blocks.
Durch Ausbilden des Fundaments aus gemischtem Mörtel auf diese Weise ist die Fundament-Herstellungsarbeit einfacher im Vergleich zu einem Fall, in welchem der Fertigbeton gegossen wird, und es kann das Gewicht der Untergeschoßstruktur durch den Boden über die Fundamentplatte aufgenom men werden, wobei dies ein Neigen bzw. Kippen der Untergeschoßstruktur auf grund einer nicht ausgeglichenen Belastung vermeidet.By forming the foundation from mixed mortar on this Way, the foundation manufacturing work is easier compared to one Case in which the precast concrete is poured and it can support the weight of the Basement structure through the floor over the foundation plate Men, this is a tilt or tilt of the basement structure avoided due to an unbalanced load.
Ein noch weiteres erfindungsgemäßes Verfahren umfaßt die Schritte:
Anordnen von zwei unteren Strukturblöcken auf dem Boden einer vertikalen
Ausnehmung nebeneinander, so daß die oberen Ausschnitte derselben zu
einander gerichtet sind; Anordnen der oberen Strukturblöcke auf der Oberseite
der entsprechenden unteren Strukturblöcke, so daß die unteren Ausschnitte
derselben zueinander gerichtet sind; Einpassen des Abdichtelements in die
schmale Nut bzw. Rille, welche durch ein Paar von ersten, umgebenden Vertie
fungen der ausgebildeten Türöffnung gebildet wird; und Einfüllen von wasser
abweisendem Mörtel in die breite Nut bzw. Rille, welche durch ein Paar von
zweiten, umgebenden Ausnehmungen der Türöffnung gebildet wird. Dem
gemäß ist die Türöffnung, welche durch Anordnen der zwei Untergeschoßein
heiten unmittelbar nebeneinander in der vertikalen Grube ausgebildet wird,
doppelt durch das Abdichtelement, welches in die schmale, in der inneren
Oberfläche der Türöffnung ausgebildete Nut eingepaßt ist, und den in die breite
Nut eingefüllten, wasserabweisenden Mörtel abgedichtet. Derart kann das
Eindringen von Grundwasser in die Untergeschoßeinheiten durch die Öff
nungen der entsprechenden Untergeschoßeinheiten sicher vermieden werden.A still further method according to the invention comprises the steps:
Arranging two lower structural blocks on the bottom of a vertical recess next to one another so that the upper cutouts thereof are directed towards one another; Placing the upper structural blocks on top of the corresponding lower structural blocks so that the lower cutouts thereof face each other; Fitting the sealing element into the narrow groove, which is formed by a pair of first, surrounding recesses of the formed door opening; and pouring water-repellent mortar into the wide groove, which is formed by a pair of second, surrounding recesses of the door opening. Accordingly, the door opening, which is formed by arranging the two Untergeschoßein units directly next to each other in the vertical pit, is double through the sealing element, which is fitted into the narrow groove formed in the inner surface of the door opening, and the filled in the wide groove , water-repellent mortar sealed. In this way, the penetration of groundwater into the basement units can be safely avoided by opening the corresponding basement units.
In einer bevorzugten Ausführungsform des erfindungsgemäßen Installa tionsverfahrens ist weiters der Schritt eines Anbringens von Kopf-Querbalken bzw. -Trägern an den oberen Enden der umgebenden Wände vorgesehen. Da ein Gebäude auf den Kopf-Querbalken gebaut werden kann, kann die Unter geschoßeinheit wirksam als ein Fundament für ein auf Bodenniveau zu bauendes Gebäude dienen. In a preferred embodiment of the Installa according to the invention tion process is also the step of attaching cross-head beams or carriers are provided at the upper ends of the surrounding walls. There a building can be built on the crossbar head, the sub floor unit effective as a foundation for a ground level too building to serve.
In einer weiters bevorzugten Ausführungsform des erfindungsgemäßen Installationsverfahrens wird weiters nach dem Anordnen der Untergeschoß einheit am Boden der vertikalen Grube der Schritt eines Anordnens des um gebenden Fundaments zur Verfügung gestellt, in welchem Bewehrungsstäbe an dem oberen Ende der vertikalen Grube derart angeordnet sind, daß die innere Oberfläche derselben in Kontakt mit der äußeren Oberfläche der Unter geschoßeinheit gehalten wird. Demgemäß wird Erddruck, welcher auf die Untergeschoßeinheit einwirken wird, durch das umgebende Fundament, wel ches die Untergeschoßeinheit umgibt, gemildert bzw. ausgeglichen. Insbe sondere, wenn ein Pfahlfundament und/oder ein Trägerfundament um die Untergeschoßeinheit existiert, wirkt das Gewicht eines auf diesen Fundamenten gebauten Gebäudes auf die Untergeschoßeinheit als Erddruck. Das um gebende Fundament blockiert jedoch den ausgeübten Erddruck, um dadurch seinen Einfluß auf die Untergeschoßeinheit zu reduzieren. Demgemäß kann ein Nachteil einer verschwenderischen Verwendung des Bauplatzes durch Verstärken der Wände der Untergeschoßeinheit, eines Einbringens von Rammen in den Boden des Pfahlfundaments und Trägerfundaments und weiters Anordnen eines Bodenabschnittes (Bodenbereichs) des Gebäude fundaments in einer Position entfernt von der Untergeschoßeinheit vermieden werden.In a further preferred embodiment of the invention Installation procedure is further after arranging the basement unit at the bottom of the vertical pit the step of arranging the um providing the foundation in which reinforcement bars are arranged at the upper end of the vertical pit such that the inner surface thereof in contact with the outer surface of the sub floor unit is held. Accordingly, earth pressure, which on the Basement unit will act through the surrounding foundation, wel ches the basement unit surrounds, mitigated or balanced. In particular especially if a pile foundation and / or a support foundation around the Basement unit exists, the weight of one acts on these foundations built building on the basement unit as earth pressure. That around Giving foundation, however, blocks the applied earth pressure to thereby reduce its influence on the basement unit. Accordingly, one Disadvantage of wasteful use of the building site by Reinforcing the walls of the basement unit, bringing in Ramming into the bottom of the pile foundation and support foundation and further arranging a floor section (floor area) of the building Avoid foundations in a position away from the basement unit become.
Weiters kann in Abhängigkeit von der Situation das auf dem Boden niveau gebaute Gebäude durch das umgebende Fundament abgestützt wer den, woraus resultiert, daß die die Untergeschoßeinheit enthaltenden Funda mente besser als ein Mattenfundament dienen können.Depending on the situation, this can also happen on the floor level buildings supported by the surrounding foundation which results in the Funda containing the basement unit can serve better than a mat foundation.
In einer anderen bevorzugten Ausführungsform des erfindungsgemäßen Installationsverfahrens werden weiters die Schritte eines Einbettens einer speziellen Anzahl von Ankerelementen, welche nach außen um einen vorbestimmten Abstand in Bereichen der Untergeschoßeinheit entsprechend dem umgebenden Fundament vorragen, und eines Anordnens des umgeben den Fundaments zur Verfügung gestellt, wobei die Ankerelemente und die Be wehrungsstäbe angeordnet sind. Demgemäß werden das umgebende Funda ment und die Untergeschoßeinheit fest durch Anordnen der Ankerelemente und der Bewehrungsstäbe verbunden. Derart wird, selbst wenn ein Gebäude auf dem umgebenden Fundament gebaut wird, das Gewicht dieses Gebäudes, welches auf das umgebende Fundament wirkt, durch die Bodenoberfläche der Untergeschoßeinheit als auch durch die Bodenoberfläche des umgebenden Fundaments abgestützt. Daraus resultierend wird das Gebäude besser abge stützt und es wird ihm eine bessere Widerstandsfähigkeit gegenüber Erdbeben ermöglicht.In another preferred embodiment of the invention Installation procedure will also be the steps of embedding one special number of anchor elements which extend outwards by one predetermined distance in areas of the basement unit accordingly protrude from the surrounding foundation, and an arrangement of the surround the foundations provided, the anchor elements and the loading reinforcement bars are arranged. Accordingly, the surrounding funda ment and the basement unit firmly by arranging the anchor elements and of the reinforcing bars connected. This is even when a building is open the surrounding foundation is built, the weight of this building, which acts on the surrounding foundation through the floor surface of the Basement unit as well as through the floor surface of the surrounding Foundations supported. As a result, the building is better removed supports and it will make it more resilient to earthquakes enables.
Gemäß dem anderen, weiteren, erfindungsgemäßen Installationsverfah ren werden die unteren und oberen Strukturblöcke der ersten und zweiten Untergeschoßeinheiten aufeinanderfolgend derart placiert, daß sie das um gebende Abdichtelement, welches um die Öffnung des ersten Untergeschosses anhaftet, pressen. Derart wird das umgebende Abdichtelement an den Öff nungen der ersten und zweiten Untergeschoßeinheiten unter Druckbean spruchung elastisch deformiert, indem es zwischen den ersten und zweiten Untergeschoßeinheiten gequetscht wird. Daher kann das Eindringen von Grundwasser oder dgl. in die Untergeschoße durch die entsprechenden Öff nungen sicher verhindert werden.According to the other, further, installation procedure according to the invention the lower and upper structural blocks of the first and second Basement units sequentially placed in such a way that they by giving sealing element, which around the opening of the first basement clinging, pressing. In this way, the surrounding sealing element on the opening the first and second basement units under pressure stress deformed elastically by being between the first and second Basement units is squeezed. Therefore, the intrusion of Groundwater or the like in the basement through the corresponding public can be prevented safely.
Da diese Erfindung in unterschiedlichen Formen ohne Verlassen des Geistes von wesentlichen Merkmalen derselben verwirklicht werden kann, ist die vorliegende Ausführungsform lediglich illustrativ und nicht-einschränkend, da der Umfang der Erfindung eher durch die beigeschlossenen Ansprüche als durch die vorhergehende Beschreibung definiert ist und sämtliche Änderungen, welche innerhalb der Grenzen und Beschränkungen der Ansprüche liegen, oder Äquivalente derartiger Grenzen oder Beschränkungen sollen von den Ansprüchen mit umfaßt sein.Because this invention comes in different forms without leaving the Spirit of essential characteristics of the same can be realized the present embodiment is only illustrative and not restrictive, since the scope of the invention is determined by the appended claims rather than is defined by the previous description and all changes, which are within the limits and limitations of the claims, or Equivalents of such limits or limitations are intended to Claims to be included.
Claims (22)
einen unteren Strukturblock (1, 1a, 1b) aus Stahlbeton mit einem Boden abschnitt (11) und umgebenden Wänden (12); und
wenigstens einem oberen Strukturblock (2, 2a, 2b) aus Stahlbeton mit umgebenden Wänden (21) und einem Deckenabschnitt (20) und derselben Form wie der untere Strukturblock in Draufsicht, wobei der obere Strukturblock (2, 2a, 2b) auf der Oberseite des unteren Strukturblocks (1, 1a, 1b) gestapelt bzw. angeordnet ist, wobei ein Abdichtelement (3) zwischen dem oberen Ende (15, 15a, 15b) des unteren Strukturblocks (1, 1a, 1b) und dem unteren Ende (24, 24a, 24b) des oberen Strukturblocks (2, 2a, 2b) angeordnet ist, wodurch eine Untergeschoß- bzw. Kellergeschoßeinheit (10, 10a, 10b) gebildet ist,
wobei das obere Ende (15, 15a, 15b) des unteren Strukturblocks (1, 1a, 1b) einen abgestuften Bereich aufweist und das untere Ende (24, 24a, 24b) des oberen Strukturblocks (2, 2a, 2b) einen entsprechenden abgestuften Bereich aufweist, wodurch das obere Ende des unteren Strukturblocks (1, 1a, 1b) mit dem unteren Ende des oberen Strukturblocks (2, 2a, 2b) in Eingriff gelangt bzw. zusammenwirkt.1. Basement or basement structure comprising:
a lower structural block ( 1 , 1 a, 1 b) made of reinforced concrete with a bottom section ( 11 ) and surrounding walls ( 12 ); and
at least one upper structural block ( 2 , 2 a, 2 b) made of reinforced concrete with surrounding walls ( 21 ) and a ceiling section ( 20 ) and the same shape as the lower structural block in plan view, the upper structural block ( 2 , 2 a, 2 b) on the top of the lower structural block ( 1 , 1 a, 1 b) is stacked or arranged, with a sealing element ( 3 ) between the upper end ( 15 , 15 a, 15 b) of the lower structural block ( 1 , 1 a, 1 b) and the lower end ( 24 , 24 a, 24 b) of the upper structural block ( 2 , 2 a, 2 b) is arranged, whereby a basement or basement unit ( 10 , 10 a, 10 b) is formed,
wherein the upper end ( 15 , 15 a, 15 b) of the lower structural block ( 1 , 1 a, 1 b) has a stepped area and the lower end ( 24 , 24 a, 24 b) of the upper structural block ( 2 , 2 a , 2 b) has a corresponding stepped area, whereby the upper end of the lower structural block ( 1 , 1 a, 1 b) engages or cooperates with the lower end of the upper structural block ( 2 , 2 a, 2 b).
Drehen jedes Strukturblocks (1, 1a, 1b, 2, 2a, 2b) um 90°, so daß seine längere Seitenwand parallel zu einer horizontalen Ebene wird;
Montieren jedes Strukturblocks (1, 1a, 1b, 2, 2a, 2b) in einem Schutz gestell bzw. -aufbau (6); und
Laden von jedem in einem Gestell montierten Strukturblock auf ein Fahrzeug (7) gemeinsam mit einer Palette (5), welche derart angeordnet wird, daß ein Freiraum zwischen einer Ladeoberfläche derselben und der Straßen oberfläche 30 cm nicht übersteigt, während er auf dem Fahrzeug (7) festgelegt ist.11. A method for transporting the lower and upper structural blocks of the basement or basement unit according to claim 6, comprising the steps:
Rotate each structural block ( 1 , 1 a, 1 b, 2 , 2 a, 2 b) by 90 ° so that its longer side wall becomes parallel to a horizontal plane;
Assemble each structural block ( 1 , 1 a, 1 b, 2 , 2 a, 2 b) in a protective frame or structure ( 6 ); and
Loading of each structural block mounted in a frame onto a vehicle ( 7 ) together with a pallet ( 5 ) which is arranged in such a way that a space between its loading surface and the road surface does not exceed 30 cm while it is on the vehicle ( 7 ) is set.
Anheben des Gestells (6), welches den Strukturblock (1, 1a, 1b, 2, 2a, 2b) hält, in eine geneigte Position unter Verwendung einer Hebe- bzw. Kran vorrichtung;
Absenken des Gestells (6) auf eine lastaufnehmende Vorrichtung (8), welche schwenkbar an einer horizontalen Welle (82) zum Aufnehmen des Bodenendes des Gestells (86) abgestützt ist; und
Legen des Gestells (6) auf seine Seite durch Kippen bzw. Schwenken der lastaufnehmenden Vorrichtung (8) um die horizontale Welle.13. The method of claim 11 or 12, further comprising the steps of unloading the structural block ( 1 , 1 a, 1 b, 2 , 2 a, 2 b) mounted in the frame ( 6 ), the step of unloading comprising:
Lifting the frame ( 6 ), which holds the structural block ( 1 , 1 a, 1 b, 2 , 2 a, 2 b), in an inclined position using a lifting or crane device;
Lowering the frame ( 6 ) onto a load bearing device ( 8 ) which is pivotally supported on a horizontal shaft ( 82 ) for receiving the bottom end of the frame ( 86 ); and
Place the frame ( 6 ) on its side by tilting or pivoting the load-bearing device ( 8 ) around the horizontal shaft.
Ausheben einer vertikalen Grube bzw. Ausnehmung im Boden, welche zumindest den unteren Strukturblock (1, 1a, 1b) aufnehmen kann;
Ausbilden eines Steinfundaments durch Ablagern von zerkleinerten Steinen am Boden der Grube bzw. Ausnehmung;
Anordnen des unteren Strukturblocks (1, 1a, 1b), welcher mit seiner Bodenseite nach unten angehoben ist, auf dem Steinfundament; und
Anordnen des oberen Strukturblocks (2, 2a, 2b) auf der Oberseite des unteren Strukturblocks (1, 1a, 1b), wobei das Abdichtelement (3) zwischen dem oberen Ende (15) des unteren Strukturblocks (1, 1a, 1b) und dem unteren Ende (24) des oberen Strukturblocks (2, 2a, 2b) angeordnet wird, wodurch das Ab dichtelement (3) den Verbindungsbereich zwischen den oberen und unteren Strukturblöcken (1, 1a, 1b, 2, 2a, 2b) abdichtet.14. A method for installing the basement or basement structure according to one of claims 1 to 6, comprising the steps:
Digging a vertical pit or recess in the ground, which can accommodate at least the lower structural block ( 1 , 1 a, 1 b);
Forming a stone foundation by depositing crushed stones on the bottom of the pit or recess;
Arranging the lower structural block ( 1 , 1 a, 1 b), which is raised with its bottom side down, on the stone foundation; and
Arranging the upper structural block ( 2 , 2 a, 2 b) on the upper side of the lower structural block ( 1 , 1 a, 1 b), the sealing element ( 3 ) between the upper end ( 15 ) of the lower structural block ( 1 , 1 a , 1 b) and the lower end ( 24 ) of the upper structural block ( 2 , 2 a, 2 b) is arranged, whereby the sealing element ( 3 ) from the connection area between the upper and lower structural blocks ( 1 , 1 a, 1 b, 2 , 2 a, 2 b) seals.
Ausheben einer vertikalen Grube bzw. Ausnehmung im Boden, welche zumindest die Fundamentplatte (100) aufnehmen kann;
Anordnen einer Beton-Fundamentplatte (100) auf dem Boden der verti kalen Grube;
Anordnen von Abstandhaltern (101), welche von elastischen Elementen gebildet sind, auf der Fundamentplatte (100) in vorgegebenen Abständen zum Abstützen des unteren Strukturblocks (1, 1a, 1b);
Anordnen von gemischtem Mörtel (102), welcher durch Mischen bzw. Kneten von Zement und Sand gebildet wird, auf der Fundamentplatte in der selben Dicke in einem Ausmaß, daß die Abstandhalter (101) bedeckt werden, wodurch eine Schicht aus gemischtem Mörtel (102) gebildet wird;
Anordnen des unteren Strukturblocks (1, 1a, 1b) auf der Schicht (102) aus gemischtem Mörtel; und
Anordnen des oberen Strukturblocks (2, 2a, 2b) auf der Oberseite des unteren Strukturblocks (1, 1a, 1b), wobei das Abdichtelement (3) zwischen dem oberen Ende (15) des unteren Strukturblocks (1, 1a, 1b) und dem unteren Ende (24) des oberen Strukturblocks (2, 2a, 2b) angeordnet wird, wodurch das Ab dichtelement (3) einen Verbindungsbereich zwischen den oberen und unteren Strukturblöcken (1, 1a, 1b, 2, 2a, 2b) abdichtet.17. A method for installing the basement or basement structure according to one of claims 1 to 8, comprising the steps:
Digging a vertical pit or recess in the ground, which can at least accommodate the foundation plate ( 100 );
Placing a concrete foundation plate ( 100 ) on the bottom of the vertical pit;
Arranging spacers ( 101 ), which are formed by elastic elements, on the foundation plate ( 100 ) at predetermined intervals for supporting the lower structural block ( 1 , 1 a, 1 b);
Placing mixed mortar ( 102 ), which is formed by mixing or kneading cement and sand, on the foundation plate to the same thickness to the extent that the spacers ( 101 ) are covered, whereby a layer of mixed mortar ( 102 ) is formed;
Placing the lower structural block ( 1 , 1 a, 1 b) on the layer ( 102 ) of mixed mortar; and
Arranging the upper structural block ( 2 , 2 a, 2 b) on the upper side of the lower structural block ( 1 , 1 a, 1 b), the sealing element ( 3 ) between the upper end ( 15 ) of the lower structural block ( 1 , 1 a , 1 b) and the lower end ( 24 ) of the upper structural block ( 2 , 2 a, 2 b) is arranged, whereby the sealing element ( 3 ) from a connecting area between the upper and lower structural blocks ( 1 , 1 a, 1 b, 2 , 2 a, 2 b) seals.
Anordnen von zwei unteren Strukturblöcken (1a, 1b) auf dem Boden einer vertikalen Grube bzw. Ausnehmung nebeneinander, so daß die oberen Ausschnitte (202) derselben zueinander gerichtet sind;
Anordnen der oberen Strukturblöcke (2a, 2b) auf der Oberseite der ent sprechenden unteren Strukturblöcke (1a, 1b), so daß die unteren Ausschnitte (201) derselben zueinander gerichtet sind;
Einpassen des Abdichtelements (3) in eine schmale Nut bzw. Rille, welche durch ein Paar von ersten, umgebenden Vertiefungen einer ausgebilde ten Türöffnung (200) gebildet wird; und
Einfüllen von wasserabweisendem bzw. -blockierendem Mörtel in eine breite Nut bzw. Rille, welche durch ein Paar von zweiten, umgebenden Ver tiefungen der Türöffnung (200) gebildet wird.18. The method for installing the basement or basement structure according to claim 7, comprising the steps:
Arranging two lower structural blocks ( 1 a, 1 b) on the bottom of a vertical pit or recess next to one another so that the upper cutouts ( 202 ) thereof are directed towards one another;
Arranging the upper structural blocks ( 2 a, 2 b) on the top of the corresponding lower structural blocks ( 1 a, 1 b), so that the lower cutouts ( 201 ) of the same are directed towards each other;
Fitting the sealing element ( 3 ) into a narrow groove, which is formed by a pair of first, surrounding recesses in a door opening ( 200 ); and
Pouring water-repellent or blocking mortar into a wide groove, which is formed by a pair of second, surrounding recesses in the door opening ( 200 ).
Ausheben einer vertikalen Grube im Boden, welche wenigstens zwei untere Strukturblöcke (1a, 1b) aufnehmen kann;
Anordnen einer Beton-Fundamentplatte (100) auf dem Boden der verti kalen Grube;
Anordnen von Abstandhaltern (101), welche durch elastische Elemente gebildet sind, auf der Fundamentplatte (100) in vorgegebenen Abständen zum Abstützen des unteren Strukturblocks (1a, 1b) und danach Anordnen von ge mischtem Mörtel (102), welcher durch Kneten bzw. Mischen von Zement und Sand hergestellt wird, auf der Fundamentplatte (100) bis zur selben Dicke in einem Ausmaß, daß die Abstandhalter (101) bedeckt werden, wodurch eine Schicht (102) aus gemischtem Mörtel gebildet wird,
Anordnen von einem der unteren Strukturblöcke (1a) auf der Schicht (102) aus gemischtem Mörtel;
Anordnen von einem der oberen Strukturblöcke (2a) auf der Oberseite des unteren Strukturblocks (1a), wobei das Abdichtelement (3) zwischen dem oberen Ende (15) des unteren Strukturblocks (1a) und dem unteren Ende (24) des oberen Strukturblocks (2a) angeordnet wird, wodurch eine erste Unterge schoßeinheit (10a) gebildet wird;
Anbringen bzw. Festkleben eines umgebenden Abdichtelements an der Außenwandoberfläche der ersten Untergeschoßeinheit (10a) um deren Öff nung; und
aufeinanderfolgendes Anordnen der anderen der unteren und oberen Strukturblöcke (1a, 1b), wobei das Abdichtelement (3) zwischen dem oberen Ende (15) des unteren Strukturblocks (1b) und dem unteren Ende (24) des oberen Strukturblocks (2b) angeordnet wird, um eine zweite Untergeschoßein heit (10b) zu bilden, so daß die Öffnung der zweiten Untergeschoßeinheit (10b) fluchtend zu derjenigen der ersten Untergeschoßeinheit (10a) angeordnet wird und das umgebende Abdichtelement (3) fest zwischen den ersten und zweiten Untergeschoßeinheiten (10a, 10b) gehalten wird.22. The method for installing the basement or basement structure according to claim 7, comprising the steps:
Digging a vertical pit in the ground, which can hold at least two lower structural blocks ( 1 a, 1 b);
Placing a concrete foundation plate ( 100 ) on the bottom of the vertical pit;
Arranging spacers ( 101 ), which are formed by elastic elements, on the foundation plate ( 100 ) at predetermined intervals for supporting the lower structural block ( 1 a, 1 b) and then arranging mixed mortar ( 102 ), which by kneading or Mixing cement and sand is made on the foundation plate ( 100 ) to the same thickness to the extent that the spacers ( 101 ) are covered, thereby forming a layer ( 102 ) of mixed mortar,
Arranging a lower structural blocks (1 a) on the layer (102) of mixed mortar;
Arranging one of the upper structural blocks ( 2 a) on the top of the lower structural block ( 1 a), the sealing element ( 3 ) between the upper end ( 15 ) of the lower structural block ( 1 a) and the lower end ( 24 ) of the upper Structural blocks ( 2 a) is arranged, whereby a first lower storey unit ( 10 a) is formed;
Attaching or sticking a surrounding sealing element on the outer wall surface of the first basement unit ( 10 a) around the opening thereof; and
successively arranging the other of the lower and upper structural blocks ( 1 a, 1 b), the sealing element ( 3 ) between the upper end ( 15 ) of the lower structural block ( 1 b) and the lower end ( 24 ) of the upper structural block ( 2 b ) is arranged to form a second Untergeschoßein unit ( 10 b), so that the opening of the second basement unit ( 10 b) is aligned with that of the first basement unit ( 10 a) and the surrounding sealing element ( 3 ) firmly between the first and second basement units ( 10 a, 10 b) is held.
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19193098 | 1998-07-07 | ||
JP29574398 | 1998-10-16 | ||
JP15566999A JP3236834B2 (en) | 1998-07-07 | 1999-06-02 | Basement structure, its manufacturing method, its transportation method and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
DE19931231A1 true DE19931231A1 (en) | 2000-05-04 |
Family
ID=27320869
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1999131231 Withdrawn DE19931231A1 (en) | 1998-07-07 | 1999-07-07 | Structured module for the construction of a cellar/basement has prefabricated upper and lower blocks of reinforced concrete to be fitted together with a seal between them |
Country Status (2)
Country | Link |
---|---|
JP (1) | JP3236834B2 (en) |
DE (1) | DE19931231A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ITMC20100043A1 (en) * | 2010-03-22 | 2011-09-23 | Manufatti In Cemento Tedeschi Di Tedeschi G | ACCOMMODATION CABIN FOR FIRE PUMPS, MADE WITH PREFABRICATED MODULAR UNITS. |
EP2147167A4 (en) * | 2007-05-08 | 2015-04-08 | Hans-Berth Klersy | A process of combining two modular units with one another, and a thus combined house body |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102828624B (en) * | 2012-09-10 | 2016-01-20 | 谢秀英 | A kind of container house and preparation method thereof |
JP5678224B1 (en) * | 2014-05-07 | 2015-02-25 | 北陸鋼産株式会社 | Lining concrete heating curing method and formwork with heating device |
RU2712845C1 (en) * | 2018-11-30 | 2020-01-31 | Общество с ограниченной ответственностью "Концерн МонАрх" | Method of manufacturing large-sized finished three-dimensional module and method of building construction from large-size finished 3d modules |
-
1999
- 1999-06-02 JP JP15566999A patent/JP3236834B2/en not_active Expired - Fee Related
- 1999-07-07 DE DE1999131231 patent/DE19931231A1/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2147167A4 (en) * | 2007-05-08 | 2015-04-08 | Hans-Berth Klersy | A process of combining two modular units with one another, and a thus combined house body |
ITMC20100043A1 (en) * | 2010-03-22 | 2011-09-23 | Manufatti In Cemento Tedeschi Di Tedeschi G | ACCOMMODATION CABIN FOR FIRE PUMPS, MADE WITH PREFABRICATED MODULAR UNITS. |
Also Published As
Publication number | Publication date |
---|---|
JP2000186329A (en) | 2000-07-04 |
JP3236834B2 (en) | 2001-12-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6032421A (en) | Structural blocks for building a basement, block manufacturing method, block transporting method, and block installing method | |
DE69107339T2 (en) | Precast concrete cellar and process for its manufacture. | |
DE69611931T2 (en) | UNDERGROUND CONSTRUCTION, ESPECIALLY FOR THE PRODUCTION OF TUNNELS, UNDERWAYS, UNDERGROUND GARAGE, ETC. AND ITS MANUFACTURING PROCESS | |
EP3112542B1 (en) | Device and method for heat decoupling of concreted parts of buildings | |
DE69017364T2 (en) | PRE-FABRICATED ARMORED CONCRETE WALL SYSTEM. | |
EP3085843A1 (en) | Device and method for heat decoupling of concreted parts of buildings | |
EP0361025A1 (en) | Noise barrier device | |
DE19931231A1 (en) | Structured module for the construction of a cellar/basement has prefabricated upper and lower blocks of reinforced concrete to be fitted together with a seal between them | |
DE60015772T2 (en) | FOUNDATION AND MANUFACTURING PROCESS THEREOF | |
DE69002434T2 (en) | Prefabricated component for use as a basement. | |
DE69003222T2 (en) | Building with foundations. | |
DE2612048A1 (en) | PRE-FABRICATED ELEMENTS IN MODULAR DESIGN | |
DE19807914A1 (en) | Prefabricated parts for building construction | |
EP2948601B1 (en) | Prefabricated element and method for erecting a structure | |
DE825889C (en) | Method and device for the series production of houses from precast concrete parts which are produced on the building site of the house | |
DE2431606A1 (en) | Transportable prefabricated reinforced-concrete garage or cell unit - incorporating wall comprising separately fabricated, distinctive externally faced slab subsequently | |
AT394232B (en) | Storey-high, solid structural element for walls, in particular cellar walls, and wall assembly comprising such structural elements | |
DE3439559A1 (en) | Self-supporting structural element | |
AT311620B (en) | Method for creating masonry | |
DE870600C (en) | Building board and building board wall and procedures for their construction | |
DE102020208628A1 (en) | Wood-based building panel element, in particular wall or ceiling element, and method for its production | |
DE10227801B3 (en) | Procedure for the construction of a track body | |
DE102022004371A1 (en) | Wall element and method for setting such wall elements | |
DE3203980A1 (en) | Underpass structure and method of producing it | |
DE831905C (en) | Process for the production of structures from large structural elements |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8110 | Request for examination paragraph 44 | ||
8139 | Disposal/non-payment of the annual fee |