DE10227801B3 - Procedure for the construction of a track body - Google Patents
Procedure for the construction of a track body Download PDFInfo
- Publication number
- DE10227801B3 DE10227801B3 DE2002127801 DE10227801A DE10227801B3 DE 10227801 B3 DE10227801 B3 DE 10227801B3 DE 2002127801 DE2002127801 DE 2002127801 DE 10227801 A DE10227801 A DE 10227801A DE 10227801 B3 DE10227801 B3 DE 10227801B3
- Authority
- DE
- Germany
- Prior art keywords
- binder
- track
- layer
- concrete
- filling material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/004—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/008—Drainage of track
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Railway Tracks (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Abstract
Zur Neuerrichtung eines Gleiskörpers (1) oder insbesondere zur Ausbildung einer festen Fahrbahn für Schienenfahrzeuge auf ehemaligen Schottergleisen wird auf eine vorhandene Schotterfläche (2) Füllmaterial und Bindemittel aufgetragen, wonach der Schotter mit dem Bindemittel und dem Füllmaterial am Platz vermischt wird. Nach Verdichten und Ausfräsen von Längsausnehmungen (11, 12) werden Bewehrungskörbe (16, 17) und ein Gleisrost (24) über der zuvor ausgebildeten Fundationsschicht (9) positioniert. Nach Ausrichten des Gleisrosts (24) wird dieser mit Beton ausgegossen, so dass sich eventuell vorhandene Hohlräume unterhalb des Gleisrosts (24) und in demselben füllen, bis der Beton etwa 7 cm oberhalb der vorhandenen Schwellen (23) steht. Nach Aushärten des Betons ist der Gleiskörper (1) befahrbar.To rebuild a track body (1) or in particular to form a solid track for rail vehicles on former ballast tracks, filler material and binder are applied to an existing ballast surface (2), after which the ballast is mixed with the binder and the filler material in place. After compacting and milling out longitudinal recesses (11, 12), reinforcement cages (16, 17) and a track grate (24) are positioned over the previously formed foundation layer (9). After aligning the track grate (24), it is poured out with concrete so that any cavities below and in the track grate (24) fill until the concrete is about 7 cm above the existing sleepers (23). After the concrete has hardened, the track body (1) can be driven over.
Description
Die Erfindung betrifft ein Verfahren zur Errichtung eines Gleiskörpers sowie den betreffenden Gleiskörper selbst.The invention relates to a method for the erection of a track body as well as the track body in question self.
Häufig sollen Gleiskörper als feste Fahrbahn errichtet werden, bei der die Schienen von einem durchgehenden, nicht aus Einzelschwellen bestehenden Betonkörper gehalten sind. Dies kann sowohl bei Neubaustrecken als auch bei Gleisen der Fall sein, die früher vorhandene Gleise ersetzen sollen. In beiden Fällen ist es ein Anliegen, die Gleise mit möglichst geringem Aufwand in einem effizienten Verfahren errichten zu können. Außerdem soll das Verfahren möglichst so flexibel sein, dass es sowohl bei Neubaustrecken als auch dort anwendbar ist, wo zuvor Gleise im Schotterbett vorhanden waren.Frequently are supposed to track bodies be built as a fixed carriageway, in which the rails of a continuous, concrete bodies consisting of individual sleepers are not held. This can be the case for both new lines and for tracks that earlier to replace existing tracks. In both cases, it is a concern that Tracks with if possible to be able to erect with little effort in an efficient process. In addition, should the procedure if possible be so flexible that it is both on new lines and there is applicable where previously there were tracks in the ballast bed.
Aus der
Die Herstellung dieses Gleiskörpers ist relativ anspruchsvoll.The manufacture of this track body is relatively demanding.
Davon ausgehend ist es Aufgabe der Erfindung, ein flexibles Verfahren zur Errichtung eines Gleiskörpers zu schaffen.Based on this, it is the task of Invention, a flexible method for erecting a track body too create.
Diese Aufgabe wird mit dem Verfahren
nach Anspruch 1 gelöst:
Bei
dem erfindungsgemäßen Verfahren
wird von einer vorhandenen Schotterfläche ausgegangen oder alternativ
zunächst
eine solche Schotterfläche
hergestellt. Die vorhandene Schotterfläche kann beispielsweise entstanden
sein, indem von einem vorherigen Gleiskörper mit Schotterbettung die
Gleisroste, d.h. die Schienen und die Schwellen entfernt worden sind.
Der vorhandene Schotter wird jedoch am Ort belassen, bedarfsweise
auch teilweise entfernt oder ergänzt.
Er kann, falls erforderlich, auch noch planiert werden. Solche Schotterflächen sind
beispielsweise beim Rückbau
von Industriegleisen oder in Güterbahnhöfen sowie
in sonstigen Industriezonen anzutreffen. Der Schotter ist in der
Regel ein Kalkschotter oder ein Hartschotter, der gewisse Verschmutzungen enthält. Dieser
verbleibt am Ort und bildet die Basis für das erfindungsgemäße Verfahren
zur Errichtung des Gleiskörpers.
Unter dem Schotter befindet sich in der Regel eine Planumsschicht
aus Kies und/oder eine kombinierte Frost-Tragschicht, die die kapillare Wasserführung unterbricht.This object is achieved with the method according to claim 1:
In the method according to the invention, an existing ballast surface is assumed or, alternatively, such a ballast surface is first produced. The existing ballast surface can be created, for example, by removing the track gratings, ie the rails and the sleepers, from a previous track body with ballast bedding. However, the existing ballast is left in place, if necessary partially removed or supplemented. If necessary, it can also be leveled. Such gravel areas can be found, for example, when dismantling industrial tracks or in freight stations and in other industrial zones. The gravel is usually a limestone gravel or a hard gravel that contains certain contaminants. This remains in place and forms the basis for the method according to the invention for erecting the track body. There is usually a layer of gravel under the ballast and / or a combined frost base layer that interrupts the capillary water flow.
Beim Neubau eines Gleiskörpers nach dem erfindungsgemäßen Verfahren wird zunächst eine solche Planumsschicht mit einer kombinierten Frost-Tragschicht errichtet, wonach auf dieser Schicht eine Schotterschüttung aufgebracht wird.When building a new track body after the inventive method will first such a formation layer with a combined frost base layer erected, after which a layer of ballast was applied to this layer becomes.
In beiden Fällen ist die Schotterschicht in der Regel etwa 25 bis 30 cm dick, wobei sie bedarfsweise auch dicker oder dünner sein kann.In both cases the gravel layer is usually about 25 to 30 cm thick, but also if necessary thicker or thinner can be.
Zur Errichtung des Gleiskörpers werden auf den Schotter zunächst Füllmaterial und Bindemittel aufgebracht, wonach der Schotter mit dem Füllmaterial und dem Bindemittel in liegendem Zustand durchmischt werden. Dabei ist es nicht erforderlich, den Schotter, das Füllmaterial und das Bindemittel aufzunehmen. Vielmehr kann die Mischung am Boden mit geeigneten Mischwerkzeugen erfolgen. Als solche können Fräseinrichtungen, wie beispielsweise eine Großfräse, eingesetzt werden. Das Bindemittel kann dabei trocken sein. Es ist jedoch auch möglich, vor dem Mischen des Schotters, des Füllmaterials und des Bindemittels oder während des Mischens wenigstens geringe Wassermengen zuzugeben, um den Binder zu aktivieren.To build the track body on the gravel first filling material and binder applied, after which the ballast with the filler and mixed with the binder lying down. there it is not necessary to use the ballast, the filler and the binder take. Rather, the mixture can be grounded with suitable Mixing tools are done. As such, milling devices, such as a large milling machine become. The binder can be dry. However, it is also possible, before mixing the ballast, filler and binder or during of mixing at least small amounts of water to add the binder to activate.
Nach dem Herstellen der gemischten Schicht wird diese planiert und vorzugsweise verdichtet. Dadurch wird eine auch als Fundationsschicht bezeichnete Tragschicht oder Fundamentierungsschicht gebildet, die in ihrer Belastbarkeit einer Betonschicht B5 auf einer kapillarbrechenden Schicht gleichzusetzen ist. Es können EV2-Werte von ≥500 MN/m2 erreicht werden.After the mixed layer has been produced, it is leveled and preferably compacted. This forms a base layer or foundation layer, which is also referred to as a foundation layer and, in terms of its resilience, is equivalent to a concrete layer B5 on a capillary-breaking layer. EV2 values of ≥500 MN / m 2 can be achieved.
Nach der Herstellung der Fundationsschicht werden vorzugsweise vor dem Abbinden des Bindemittels zwei Längsvertiefungen ausgehoben, die sich unterhalb der später zu verlegenden Schienen befinden. Die Längsvertiefungen werden vorzugsweise nachverdichtet. Dies kann mittels Rüttelplatte geschehen.After the foundation layer is made preferably two longitudinal depressions before the binding agent sets excavated, which is below the rails to be laid later are located. The longitudinal depressions are preferably recompressed. This can be done using a vibrating plate happen.
Auch bei noch nicht ausgehärtetem Bindemittel ist diese so vorbereitete Fundationsschicht begehbar. Es wird nun in den Längsvertiefungen eine Bewehrung angeordnet, die insbesondere längs verlaufende Bewehrungseisen aufweist. Diese können durch Querbügel untereinander verbunden sein. Die Bewehrungen der beiden Längsausnehmungen sind untereinander vorzugsweise nicht verbunden, d.h. voneinander unabhängig.Even if the binder has not yet hardened this foundation layer prepared in this way is accessible. It will now in the longitudinal depressions a reinforcement arranged, in particular the longitudinal reinforcing bars having. This can be done by locking latch be connected to each other. The reinforcements of the two longitudinal recesses are preferably not interconnected, i.e. from one another independently.
Im nächsten Schritt wird oberhalb der gemischten Schicht ein Schienenrost so positioniert, dass dessen Schienen oberhalb der Längsausnehmungen positioniert sind.The next step is above a rail grate positioned in the mixed layer so that its Rails above the longitudinal recesses are positioned.
Der Schienenrost weist mehrere schwellenartige Verbindungselemente auf, die unterhalb der Schienen angeordnet sind. Diese Verbindungselemente können beispielsweise Stahlschwellen oder andere ähnliche Körper sein. Der Schienenrost wird vorzugsweise mittels Hängeböcken über der Fundationsschicht angeordnet. Er kann dabei auf der Fundationsschicht aufliegen oder auch über dieser schweben. Dies ermöglicht auf einfache Weise die Ausrichtung der Schienen, unabhängig von kleineren Unebenheiten der Fundationsschicht.The rail grate has several threshold-like Connecting elements, which are arranged below the rails. These fasteners can for example steel sleepers or other similar bodies. The rail grate is preferably by means of trestles over the Foundation layer arranged. He can do this on the foundation layer lying on or over this hover. this makes possible easily align the rails regardless of minor bumps in the foundation layer.
Ist der Gleisrost ausgerichtet, werden die Längsausnehmungen und die Zwischenräume zwischen den Schwellen des Gleisrosts mit Beton ausgegossen und zwar vorzugsweise etwa bis 7 cm über der Oberkante der schwellenartigen Elemente. Nach Aushärten dieser Betonschicht ist der Gleiskörper durch Schienenfahrzeuge befahrbar.If the track grate is aligned, the longitudinal recesses and the spaces between the sleepers of the track grate are poured with concrete, preferably up to 7 cm above the upper edge of the sleeper-like elements. After this concrete layer has hardened, the track body can be driven on by rail vehicles.
Das insoweit beschriebene Verfahren ist flexibel und sowohl für Gleisneubau als auch für die Errichtung von Gleiskörpern auf alten Gleisflächen geeignet. Es nutzt die am Ort vorhandenen Materialien und Strukturen. Beispielsweise kann eine unterhalb der Schotterschicht vorhandene Planumsschicht unbeeinträchtigt weiter verwendet werden. Außerdem können bestehende Gleisdrainagen weiter verwendet werden.The procedure described so far is flexible and for both New track construction as well the construction of track bodies on old track surfaces suitable. It uses the materials and structures available on site. For example, an existing one below the gravel layer Flat layer unaffected continue to be used. In addition, existing Track drainages continue to be used.
Der Gleiskörper bietet eine gute Basis für einen weiteren, mit Straßenfahrzeugen befahrbaren Aufbau. Dazu ist beispielsweise lediglich an der Radinnenseite der Gleise ein Spurrillensystem anzubringen und eine Belagoberfläche auf den Betonkörper aufzubringen. Dies kann beispielsweise ein Asphaltbelag (Bitumenkies 0/32) und Asphaltfeinbeton (0/11 S) sein.The track body provides a good basis for one another, with road vehicles accessible structure. For this purpose, for example, is only on the inside of the wheel attach a track groove system to the tracks and a covering surface the concrete body applied. This can be, for example, an asphalt surface (bituminous gravel 0/32) and fine asphalt concrete (0/11 S).
Bei einer vorteilhaften Ausführungsform des Verfahrens wird als Füllmaterial mineralisches Material mit einer bei Null beginnenden Körnung eingesetzt. Dies kann beispielsweise Recyclingmaterial sein, das in einer etwa 10 cm starken Schicht auf das vorhandene Schottergerüst aufgetragen wird. Hat der Schotter eine Körnung 32/56 kann somit eine etwa gleichmäßige Kornverteilung 0/56 erreicht werden.In an advantageous embodiment the process is called filler mineral material with a grain size starting from zero. This can be, for example, recycling material that is roughly 10 cm thick layer is applied to the existing ballast structure. The gravel has a grain 32/56 can therefore achieve an approximately even grain size 0/56 become.
Als Bindemittel wird vorzugsweise ein Tragschichtbinder HT35 mit zehn bis hundert Kilogramm pro Kubikmeter Schotter und Füllmaterial aufgetragen. Das Bindemittel kann mit dem Füllmaterial vermischt, als separate Schicht unter dem Füllmaterial oder als Schicht auf dem Füllmaterial aufgetragen werden. In jedem Fall ist eine nachfolgende Durchmischung im liegenden Zustand des Materials anzustreben.The preferred binder is a HT35 base layer binder weighing ten to one hundred kilograms per cubic meter Crushed stone and filling material applied. The binder can be mixed with the filler material as a separate one Layer under the filler or as a layer on the filling material be applied. In any case there is a subsequent mixing to strive for in the lying state of the material.
Bei dem erfindungsgemäßen Verfahren weisen die in die vorbereitete Fundationsschicht einzubringenden Längsvertiefungen vorzugsweise eine Tiefe von etwa lediglich 10 cm, dabei aber eine Breite von etwa 50 cm auf. Die Vertiefungen definieren Längsbalken, die beim späteren Ausgießen mit Beton längs unter den Schienen entstehen.In the method according to the invention indicate the ones to be placed in the prepared foundation layer longitudinal recesses preferably a depth of only about 10 cm, but one Width of about 50 cm. The depressions define longitudinal beams, the later pour out with concrete lengthways arise under the rails.
Bei einer bevorzugten Ausführungsform weist der Gleisrost Stahlschwellen auf, die beispielsweise aus einem Gleisabriss stammen können. Durch die vollständige Einbettung in den Beton wird eine gute Tragfähigkeit und Dauerhaftigkeit des errichteten Gleiskörpers erhalten.In a preferred embodiment the track grate has steel sleepers that, for example, from a track demolition can originate. By the complete Embedding in the concrete will have good load-bearing capacity and durability of the erected track body receive.
Weitere Einzelheiten vorteilhafter Ausführungsformen des Verfahrens sind Gegenstand der nachfolgenden Beschreibung oder von Unteransprüchen. In der Zeichnung sind Einzelstadien bei der Herstellung eines Gleiskörpers nach dem erfindungsgemäßen Verfahren veranschaulicht. Es zeigen:More details more advantageous embodiments The procedure is the subject of the following description or of subclaims. In the drawing, individual stages in the manufacture of a track body are shown the inventive method illustrated. Show it:
In den
Im ersten Schritt wird zur Errichtung
des Gleiskörpers
auf der so vorhandenen oder vorbereiteten Schotterfläche
Zur Ausbildung der Fundationsschicht
werden nun der in der Schotterfläche
Auf die so vorbereitete Fundationsschicht
Die Schwellen
Wie
Nach Ausrichten der Gleisroste
Der Gleiskörper
Soll der Gleiskörper
Der Straßenbelag
Der dargestellte Gleiskörper
Zur Neuerrichtung eines Gleiskörpers
Claims (23)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE20220484U DE20220484U1 (en) | 2002-06-21 | 2002-06-21 | Platform construction method for fixed train track involves ballast surface and a rear formed surface using bringing the filling material and binding material to the ballast surface and mixing together |
DE2002127801 DE10227801B3 (en) | 2002-06-21 | 2002-06-21 | Procedure for the construction of a track body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE2002127801 DE10227801B3 (en) | 2002-06-21 | 2002-06-21 | Procedure for the construction of a track body |
Publications (1)
Publication Number | Publication Date |
---|---|
DE10227801B3 true DE10227801B3 (en) | 2004-01-29 |
Family
ID=29795843
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE2002127801 Expired - Lifetime DE10227801B3 (en) | 2002-06-21 | 2002-06-21 | Procedure for the construction of a track body |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE10227801B3 (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4104683A1 (en) * | 1991-02-15 | 1992-08-20 | Wayss & Freytag Ag | Rail road bed - uses liq. mortar to form a plate in upper section of the ballast, with structured ballast particles to prevent downwards dispersion |
DE19916586A1 (en) * | 1999-04-13 | 2000-10-19 | Gsg Knape Gleissanierung Gmbh | Process for renewing a track system |
DE29917553U1 (en) * | 1999-10-05 | 2001-02-15 | Heilit + Woerner Bau-AG, 81677 München | Track system support plate, track system substructure and track system |
-
2002
- 2002-06-21 DE DE2002127801 patent/DE10227801B3/en not_active Expired - Lifetime
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4104683A1 (en) * | 1991-02-15 | 1992-08-20 | Wayss & Freytag Ag | Rail road bed - uses liq. mortar to form a plate in upper section of the ballast, with structured ballast particles to prevent downwards dispersion |
DE19916586A1 (en) * | 1999-04-13 | 2000-10-19 | Gsg Knape Gleissanierung Gmbh | Process for renewing a track system |
DE29917553U1 (en) * | 1999-10-05 | 2001-02-15 | Heilit + Woerner Bau-AG, 81677 München | Track system support plate, track system substructure and track system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE4236766C2 (en) | Method for renovating a dam construction for a roadway | |
DE102007046249B4 (en) | Track with glued troughs | |
WO2021005015A1 (en) | Ballast-plastic composite body | |
WO2012130425A2 (en) | Track way for rail-bound vehicles and track support for such a track way | |
EP1576240B1 (en) | Method for constructing a rigid track and a communication track | |
DE10133246A1 (en) | Conversion of ballasted trackbed to solid roadbed starts by removing rails and ballast used for concrete aggregate once crushed to size for concrete plate laid on bearing layer to complete solid roadbed. | |
DE10227801B3 (en) | Procedure for the construction of a track body | |
WO2003104562A1 (en) | Precast concrete part and method | |
AT219641B (en) | Process for the production of highly resilient road surfaces for motor vehicle expressways | |
DE2233263A1 (en) | CONSTRUCTION PROCEDURES FOR UNDERPASSES (RAILWAYS, ROADS) IN PARTICULAR FOR CASES WHERE TRAFFIC MUST NOT BE INTERRUPTED ON THE ROUTE TO BE UNDERPASSED | |
DE4325476A1 (en) | Method for producing a substructure for a track for rail vehicles | |
DE10327467A1 (en) | Platform construction method for fixed train track involves ballast surface and a rear formed surface using bringing the filling material and binding material to the ballast surface and mixing together | |
EP3101176A2 (en) | Method for generating a road structure and road construction device | |
DE102007056408B4 (en) | System and method for building a roadway | |
DE20220484U1 (en) | Platform construction method for fixed train track involves ballast surface and a rear formed surface using bringing the filling material and binding material to the ballast surface and mixing together | |
AT500876B1 (en) | METHOD FOR MANUFACTURING A FIXED RAILWAY RAILWAY | |
DE872959C (en) | Road paving made of blocks and their production | |
DE10319298A1 (en) | Construction method for permanent way for railways, with construction of track bed incorporating antifreeze layer, sub base, concrete sub base, and thin asphalt layer to compensate for unevenness | |
DE10218309B4 (en) | Track for railway vehicles with a ballast bed for tracks, process for its manufacture and a binder mixture for use in the process | |
DE4308072A1 (en) | Method and device for working up a track substructure | |
DE19818338C1 (en) | Platform construction for providing access to and from trains, trams etc. | |
DE102021127502A1 (en) | Track for track-guided rail vehicles and method for its construction | |
DE102007038461A1 (en) | Method for rehabilitating a rail track and associated rail track | |
EP1298251A1 (en) | Ballast-free railway track structure and method of building such structure | |
DE19706032C2 (en) | Process for the construction of paved routes and device for this process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8100 | Publication of patent without earlier publication of application | ||
8364 | No opposition during term of opposition | ||
R071 | Expiry of right |