DE102015012634A1 - Assembly platform for in particular the construction of tower segments of wind turbines - Google Patents

Assembly platform for in particular the construction of tower segments of wind turbines Download PDF

Info

Publication number
DE102015012634A1
DE102015012634A1 DE102015012634.2A DE102015012634A DE102015012634A1 DE 102015012634 A1 DE102015012634 A1 DE 102015012634A1 DE 102015012634 A DE102015012634 A DE 102015012634A DE 102015012634 A1 DE102015012634 A1 DE 102015012634A1
Authority
DE
Germany
Prior art keywords
assembly platform
arms
movable
support mast
baskets
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE102015012634.2A
Other languages
German (de)
Inventor
Ralf Hermanns
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Goracon Engineering GmbH
Original Assignee
Goracon Engineering GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Goracon Engineering GmbH filed Critical Goracon Engineering GmbH
Priority to DE102015012634.2A priority Critical patent/DE102015012634A1/en
Publication of DE102015012634A1 publication Critical patent/DE102015012634A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/342Arrangements for stacking tower sections on top of each other
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2230/00Manufacture
    • F05B2230/30Manufacture with deposition of material
    • F05B2230/31Layer deposition
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Wind Motors (AREA)

Abstract

Die Erfindung bezieht sich auf eine Montagebühne (1) für insbesondere den Aufbau von Turmsegmenten (8) für Windkraftanlagen mit bewegbaren Arbeitskörben 2.1, 2.2, 3.1, 3.2, die an dem Stützmast (5) befestigt sind. Um die Montagebühne (1) in einfacher baulicher Gestaltung so ausgerüstet zu haben, dass diese auch bei sich verjüngenden Turmsegmenten (8) noch sicher aus einem gebauten Turm herausgebracht werden kann, ist vorgesehen, dass in einer Arbeitshochebene des Stützmastes (5) zumindest zwei unabhängig voneinander und relativ zueinander horizontal und vertikal von dem Stützmast (5) weg und auf diesen zu bewegbare Arbeitskörbe 2.1, 2.2, 3.1, 3.2 vorgesehen sind, die jeweils um eine vertikale Achse und/oder verfahrbar am Stützmast (5) festgelegt sind.The invention relates to a mounting platform (1) for in particular the construction of tower segments (8) for wind turbines with movable work baskets 2.1, 2.2, 3.1, 3.2, which are attached to the support mast (5). In order to have the assembly platform (1) equipped in a simple structural design so that it can be safely brought out of a built tower even with tapered tower segments (8), it is provided that in a working plateau of the support mast (5) at least two independent from each other and relative to each other horizontally and vertically from the support mast (5) away and on this to movable work baskets 2.1, 2.2, 3.1, 3.2 are provided, which are each fixed to a vertical axis and / or movable on the support mast (5).

Description

Die Erfindung bezieht sich auf einen Montageturm für insbesondere den Aufbau von Turmsegmenten von Windkraftanlagen mit bewegbaren Arbeitskröben, die an einem Stützmast befestigt sind.The invention relates to a mounting tower for in particular the construction of tower segments of wind turbines with movable Arbeitskröben, which are attached to a support mast.

Türme von Windkraftanlagen werden herkömmlicherweise aus Betonringen hergestellt, die sich kegelstumpfartig verjüngend bis zum oberen Bereich erstrecken, an denen das Windrad drehbeweglich abgestützt ist. Alternativ sind Gittermasten als Stützmasten für Windkraftanlagen bekannt, die ebenfalls abschnittsweise aufgebaut werden.Towers of wind turbines are conventionally made of concrete rings which taper in a frustoconical manner to the upper area where the wind turbine is rotatably supported. Alternatively, lattice towers are known as support masts for wind turbines, which are also constructed in sections.

Zur Herstellung derartiger Stützmasten werden Lifteinrichtungen verwendet mit Armen, zwischen denen ein Seil gespannt ist mit Kranhaken und zusätzlichen Befestigungsvorrichtungen. Solche herkömmlichen Montagebühnen sind aufwendig und erfordern einen hohen Installationsaufwand. Auch der Deinstallationsaufwand ist nicht unerheblich, da aufgrund der sich nach oben hin verjüngenden Geometrie eines Turmes, die in einem unteren Bereich sehr langen Stützteile aus oberen Bereichen und mit einem erhöhten Aufwand herauszubringen sind.For the preparation of such support poles lifting devices are used with arms, between which a rope is stretched with crane hooks and additional fasteners. Such conventional mounting platforms are expensive and require a high installation cost. Also, the Deinstallationsaufwand is not insignificant, since due to the upwardly tapered geometry of a tower, which are in a lower region very long support parts from the upper areas and bring out an increased effort.

Es ist Aufgabe der vorliegenden Erfindung, eine Montagebühne für insbesondere den Bau von Windkraftanlagen aus Turmsegmenten zur Verfügung zu stellen, die mit einem verminderten Installationsaufwand betrieben werden kann.It is an object of the present invention to provide a mounting platform for in particular the construction of wind turbines tower segments available that can be operated with a reduced installation cost.

Zur Lösung dieser Aufgabe zeichnet sich die Montagebühne der eingangs genannten Art dadurch aus, dass in einer Arbeitshöhe des Stützmastes zumindest zwei unabhängig voneinander und relativ zueinander horizontal und vertikal von dem Stützmast weg und auf diesen zubewegbare Arbeitskörbe vorgesehen sind, die jeweils um eine vertikale Achse schwenkbar und/oder verfahrbar am Stützmast festgelegt sind.To solve this problem, the assembly platform of the type mentioned is characterized in that at a working height of the support mast at least two independently and relative to each other horizontally and vertically away from the support mast and provided on this zubewegbare work baskets, each pivotable about a vertical axis and / or movably fixed to the support mast.

Damit ist eine Montagebühne zur Verfügung gestellt, bei der die Arbeitskörbe in eine eng aneinander liegende Ruheposition gebracht werden können, so dass damit Außenabmessungen eingenommen werden können, die es ermöglichen, dass die Montagebühne auch durch relativ kleine Öffnungen wieder aus einem hochgebauten Turm herausgebracht werden kann. Es ist ebenfalls es möglich, mit Arbeitskörben Turmsegmente mit relativ großem Innendurchmesser zu erreichen, indem die jeweils um die horizontalen Achsen schwenkbaren Arbeitskörbe über die Gelenkarme zu verfahren sind. Vorzugsweise sind in verschiedenen Hochebenen des Stützmastes jeweils Arbeitskörbe vorgesehen, insbesondere jeweils zwei, die eine Arbeitsplattform haben mit annähernd halbkreisförmiger Gestalt, so dass diese in der Ruhstellung sich im Bereich des Stützmastes eine eng anliegende Ruhestellung einnehmen können und sich somit in etwa zu einer kreisförmigen Gestalt ergänzen.Thus, a mounting platform is provided, in which the work baskets can be placed in a closely spaced rest position so that it can be taken outside dimensions that allow the assembly platform can be brought out of relatively tall openings again from a tower built tall , It is also possible to achieve with working baskets tower segments with a relatively large inner diameter by the workhorses pivoting about the horizontal axes are about the articulated arms to move. Preferably, work baskets are provided in each case in different high levels of the support mast, in particular two, which have a working platform with an approximately semicircular shape, so that they can assume a close resting position in the rest position in the area of the support mast and thus approximately in a circular shape complete.

Vorzugsweise ist vorgesehen, dass die Montagebühne als Klettermontagebühne ausgebildet ist. Dazu kann sie in einer Ausgestaltung mit entsprechend ausfahrbaren und arretierbaren bzw. feststellbaren Kletterarmen ausgerüstet sein, die sich an Innenwandungen von Turmsegmenten arretieren und/oder mit diesen verbinden lassen. Bevorzugterweise sind wiederum in zwei verschiedenen Hochebenen jeweils eine Gruppe aus zwei, drei oder mehr Kletterarmen vorgesehen, die relativ zueinander bewegbar sind. Zwischen den zwei Gruppen von Kletterarmen kann eine Hebevorrichtung, beispielsweise in Gestalt einer Scherenhebevorrichtung, vorgesehen sein, so dass nach Arretierung der Montagebühne durch eine Gruppe von Kletterarmen die andere gelöst und über die Hebevorrichtung in eine andere Höhenposition bewegt werden kann und danach dort an der Innenwandung eines Turmsegmentes montiert wird. Danach kann die andere Gruppe von Kletterarmen nachgeführt sein.It is preferably provided that the mounting platform is designed as a climbing mounting platform. For this purpose, it can be equipped in an embodiment with appropriately extendable and lockable or lockable climbing arms, which can be locked to inner walls of tower segments and / or connect with them. Preferably, in turn, a group of two, three or more climbing arms are provided in two different plateaus, which are movable relative to each other. Between the two groups of climbing arms, a lifting device, for example in the form of a scissor lift, be provided, so that after locking the mounting platform by a group of climbing arms, the other can be solved and moved via the lifting device in a different height position and then there on the inner wall a tower segment is mounted. After that, the other group of climbing arms can be tracked.

Alternativ ist es jedoch auch möglich, die Montagebühne mit einem Gittermast auszurüsten, der entsprechende Verfahrschienen hat, an denen zum Beispiel ein Drehkranz, an dem die Arbeitskörbe festgelegt sind, vertikal verfahrbar montiert ist. An dem Drehkranz können die Arbeitskörbe über entsprechende Gelenkarme wieder verfahren werden. Ist dieser rund ausgebildet, kann der Arbeitskorb eine entsprechende 360° aber auch 180°-Bewegung nach links und rechts durchführen.Alternatively, however, it is also possible to equip the assembly platform with a lattice mast, which has corresponding travel rails on which, for example, a turntable on which the work baskets are fixed, is mounted vertically movable. On the turntable, the work baskets can be moved again via appropriate articulated arms. If this is round, the work basket can perform a corresponding 360 ° but also 180 ° movement to the left and right.

Zur weiteren Erläuterung der Erfindung wird auf weitere Unteransprüche, die nachfolgende Beschreibung und die Zeichnung verwiesen.To further explain the invention, reference is made to further subclaims, the following description and the drawings.

In der Zeichnung zeigen:In the drawing show:

1: ausschnittsweise einen Turm einer Windkraftanlage während der Bauphase, mit einem Ausführungsbeispiel der Montagebühne; 1 a partial view of a tower of a wind turbine during the construction phase, with an embodiment of the assembly platform;

2: eine zu 1 analoge Darstellung bei weiterem Baufortschritt mit drei Turmsegmenten und zwei Gruppen von Kletterarmen; 2 : one too 1 analogue representation with further construction progress with three tower segments and two groups of climbing arms;

3: eine Einzeldarstellung von einander zugeordenten Arbeitskörben mit Gelenkarmen und Kletterarmen; 3 an individual representation of associated working baskets with articulated arms and climbing arms;

4: vergrößert die Gelenkarme und den Drehkranz der Montagebühne nach den 1 bis 3; 4 : increases the articulated arms and the turntable of the assembly platform to the 1 to 3 ;

5: ausschnittsweise eine Seitendarstellung auf das Ausführungsbeispiel nach den 1 bis 4; 5 : partial page presentation on the embodiment of the 1 to 4 ;

6: ein alternatives Ausführungsbeispiel einer Montagebühne nach der Erfindung mit einem Gittermast als Stützmast; 6 an alternative embodiment of a mounting platform according to the invention with a lattice mast as a support mast;

7: vergrößert das Ausführungsbeispiel nach 6 und 7 : enlarges the embodiment after 6 and

8: nochmals vergrößert einen Teilbereich des Stützmast mit Arbeitskorb. 8th : again increases a portion of the support mast with work basket.

In dem ersten Ausführungsbeispiel der Montagebühne nach den 1 bis 5 hat die Montagebühne 1 jeweils in zwei Hochebenen jeweils zwei Arbeitskörbe 2.1 und 2.2, beziehungsweise 3.1 und 3.2. Diese Arbeitskörbe 2.1, 2.2, 3.1, 3.2 sind jeweils an Gelenkarmen 4 befestigt, die bei den Arbeitskörben 3.1 und 3.2 in aufrechter Stellung an dem Stützmast 5 eng anliegend angeordnet sind, so dass die Arbeitskörbe 3.1 und 3.2 in dieser Ruheposition einen nur geringen Raum beanspruchen. Die Arbeitskörbe 2.1 und 2.2 befinden sich in einer ausgefahrenen Arbeitsstellung. Die Gelenkarme 4 sind jeweils an einem Drehkranz 6 und dem Stützmast 5 festgelegt (siehe auch vergrößerte Darstellung nach 4). Die Gelenkarmabschnitte sind um horizontale Achsen 7 schwenkbar. So können sie in verschiedenen Höhenlagen und mit verschiedenen Abständen zum Stützmast 5 an ein Turmsegment 8 heranbewegt werden.In the first embodiment of the assembly platform according to the 1 to 5 has the assembly platform 1 two work baskets each in two plateaus 2.1 and 2.2 , respectively 3.1 and 3.2 , These work baskets 2.1 . 2.2 . 3.1 . 3.2 are each on articulated arms 4 attached to the work baskets 3.1 and 3.2 in an upright position on the support mast 5 are arranged snugly, leaving the work baskets 3.1 and 3.2 occupy only a small space in this rest position. The work baskets 2.1 and 2.2 are in an extended working position. The articulated arms 4 are each on a turntable 6 and the support mast 5 fixed (see also enlarged illustration after 4 ). The Gelenkarmabschnitte are about horizontal axes 7 pivotable. So you can at different altitudes and with different distances to the support pole 5 to a tower segment 8th be moved up.

Die Montagebühne 1 ist über Kletterarme 9, 10 an der Innenwandung der Turmsegmente 8 festzuklemmen. Dazu sind die Kletterarme 9 in der oberen Hochebene und die Kletterarme 10 in einer darunter befindlichen Hochebene angeordnet. Zwischen der Gruppe mit den Kletterarmen 9 und der Gruppe mit den Kletterarmen 10 ist eine Hebevorrichtung 11 in Gestalt einer Scherenhebevorrichtung vorgesehen (siehe auch 5), so dass die Arbeitskörbe 2.1, 2.2 und 3.1, 3.2 einen unterschiedlichen Höhenabstand zueinander einnehmen können, wie dies die 2 zeigt.The assembly platform 1 is about climbing arms 9 . 10 on the inner wall of the tower segments 8th clamp. These are the climbing arms 9 in the upper plateau and the climbing arms 10 arranged in an underlying plateau. Between the group with the climbing arms 9 and the group with the climbing arms 10 is a lifting device 11 provided in the form of a scissor lift (see also 5 ), so the work baskets 2.1 . 2.2 and 3.1 . 3.2 can take a different height distance from each other, as the 2 shows.

In der 2 sind die oberen Arbeitskörbe 2.1 und 2.2 über die Hebevorrichtung 11 verfahren, wobei auch die Klemmarme 9 und 10 einen größeren Abstand zueinander einnehmen. So ist nicht nur in unterschiedlichen Hochebenen zu arbeiten. Vielmehr kann auch durch das wechselseitige Festklemmen der Klemmarme 9 mit der Innenwandung der Mauersegmente 8 ein autarkes Klettern der Montagebühne 1 erfolgen.In the 2 are the upper work baskets 2.1 and 2.2 over the lifting device 11 procedure, whereby also the clamping arms 9 and 10 occupy a greater distance from each other. This is not just working in different high levels. Rather, can also by the mutual clamping of the clamping arms 9 with the inner wall of the wall segments 8th a self-sufficient climbing of the assembly platform 1 respectively.

Die Kletterarme 9 und 10 sind teleskopierbar, beispielsweise durch entsprechende hydraulische Mittel und über die Anschlag 10.1 bzw. 9.1 mit der Innenwandung der Turmsegmente 8 zu verspannen. Anstelle einer Scherenhebeeinrichtung können selbstverständlich auch andere geeignete Hebemittel Einsatz finden.The climbing arms 9 and 10 are telescopic, for example, by appropriate hydraulic means and the stop 10.1 respectively. 9.1 with the inner wall of the tower segments 8th to tense. Of course, other suitable lifting means can be used instead of a scissors lifting device.

Wie 5 veranschaulicht, können alle Teile in eine Ruheposition überführt werden, in der die gesamte Montagebühne außerordentlich klein und schmal baut, so dass diese auch noch aus hochemporragenden Türmen wie von Windkraftanlagen nach oben heraus gehoben werden kann, obgleich in einer Anfangsbauphase, wie diese in 1 und in 2 dargestellt ist, die Montagebühne auch Innenwandungen von Mauersegmenten erreichen kann, die einen recht großen Innendurchmesser aufweisen.As 5 illustrated, all parts can be transferred to a rest position in which the entire assembly platform is extremely small and narrow, so that it can be lifted even from towering towers such as wind turbines upwards, albeit in an initial phase, such as in 1 and in 2 is shown, the mounting platform can also reach the inner walls of wall segments, which have a fairly large inner diameter.

In den 6 bis 8 ist eine alternative Ausführungsvariante der Montagebühne 1 dargestellt mit einem Gittermasten als Stützmast 5, der wiederum in zwei unterschiedlichen Hochebenen Arbeitskörbe 2.1 und 2.2 sowie 3.1 und 3.2 aufweist, die über Gelenkarme 9 bzw. 10 an einem Drehkranz 13 entlang verfahrbar festgelegt sind, so dass sie sich über drei Segmente im Inneren der Turmsegmente 8 entlang verfahren lassen. Diese Drehkränze 13 sind ebenfalls auf- und abzuverfahren über Führungsschienen 14 entlang von Vertikalpfosten des Stützmastes 5.In the 6 to 8th is an alternative embodiment of the assembly platform 1 represented with a lattice mast as a support mast 5 who in turn works baskets in two different plateaus 2.1 and 2.2 such as 3.1 and 3.2 which has articulated arms 9 respectively. 10 on a turntable 13 are set along movable so that they are spread over three segments inside the tower segments 8th to be moved along. These slewing rings 13 are also moved up and down via guide rails 14 along vertical posts of the support mast 5 ,

Claims (16)

Montagebühne (1) für insbesondere den Aufbau von Turmsegmenten (8) von Windkraftanlagen mit bewegbaren Arbeitskörben, die an einem Stützmast (5) befestigt sind, dadurch gekennzeichnet, dass in zumindest einer Arbeitshochebene des Stützmastes (5) zumindest zwei unabhängig voneinander und relativ zueinander horizontal und vertikal von dem Stützmast (5) weg und auf diesen zu bewegbare Arbeitskörbe (2.1, 2.2, 3.1, 3.2) vorgesehen sind, die jeweils um eine vertikale Achse schwenkbar und/oder verfahrbar am Stützmast (5) festgelegt sind.Assembly platform ( 1 ) for in particular the construction of tower segments ( 8th ) of wind turbines with moveable baskets mounted on a support pole ( 5 ) are fastened, characterized in that in at least one working plateau of the support mast ( 5 ) at least two independently and relative to each other horizontally and vertically from the support mast ( 5 ) away and on these movable work baskets ( 2.1 . 2.2 . 3.1 . 3.2 ) are provided, each pivotable about a vertical axis and / or movable on the support mast ( 5 ). Montagebühne (1) nach Anspruch 1, dadurch gekennzeichnet, dass die Arbeitskörbe (2.1, 2.2, 3.1, 3.2) über Gelenkarme (4) mit dem Stützmast (5) verbunden sind.Assembly platform ( 1 ) according to claim 1, characterized in that the working baskets ( 2.1 . 2.2 . 3.1 . 3.2 ) via articulated arms ( 4 ) with the support mast ( 5 ) are connected. Montagebühne (1) nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass die Gelenkarme (4) um horizontale Achsen schwenkbar aufeinander zu und voneinander weg bewegbare Armteile aufweisen.Assembly platform ( 1 ) according to claim 1 or 2, characterized in that the articulated arms ( 4 ) pivotable about horizontal axes towards each other and away from each other movable arm parts. Montagebühne (1) nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass zumindest zwei aufeinander zu und voneinander wegbewegbare Arbeitskörbe (2.1, 2.2, 3.1, 3.2) vorgesehen sind, die in eine Ruhestellung aufeinander zu bewegbar sind, in der sie aneinander angrenzend angeordnet sind.Assembly platform ( 1 ) according to one of claims 1 to 3, characterized in that at least two working baskets movable towards and away from each other ( 2.1 . 2.2 . 3.1 . 3.2 ) are provided, which are movable towards each other in a rest position in which they are arranged adjacent to each other. Montagebühne (1) nach Anspruch 4, dadurch gekennzeichnet, dass ein Arbeitskorb (2.1, 2.2, 3.1, 3.2) im Wesentlichen eine halbkreisähnliche Gestalt hat. Assembly platform ( 1 ) according to claim 4, characterized in that a work basket ( 2.1 . 2.2 . 3.1 . 3.2 ) has a substantially semi-circular shape. Montagebühne (1) nach einem der Ansprüche 1 bis 5, dadurch gekennzeichnet, dass an dem Stützmast (5) und in einer Stützmasthochebene zumindest zwei ausfahrbare und in einer ausgefahrenen Stellung feststellbare Kletterarme (9) vorgesehen sind.Assembly platform ( 1 ) according to one of claims 1 to 5, characterized in that on the support mast ( 5 ) and in a Stützmasthöchbene at least two extendable and lockable in an extended position climbing arms ( 9 ) are provided. Montagebühne (1) nach Anspruch 6, dadurch gekennzeichnet, dass in einer zweiten Stützmasthochebene des Stützmastes (5) eine zweite Gruppe von ausfahrbaren und feststellbaren Kletterarmen (10) vorgesehen sind.Assembly platform ( 1 ) according to claim 6, characterized in that in a second Stützmasthöchbene the support mast ( 5 ) a second group of extendable and lockable climbing arms ( 10 ) are provided. Montagebühne (1) nach Anspruch 6 oder 7, dadurch gekennzeichnet, dass die Kletterarme (9) der einen Stützmasthochebene relativ bewegbar sind zu den Kletterarmen (10) der anderen Stützmasthochebene.Assembly platform ( 1 ) according to claim 6 or 7, characterized in that the climbing arms ( 9 ) of a Stützmasthochebene are relatively movable to the climbing arms ( 10 ) of the other support mast plateau. Montagebühne (1) nach einem der Ansprüche 6 bis 8, dadurch gekennzeichnet, dass zwischen den beiden Stützmasthochebenen der Kletterarme (9, 10) ein ausfahrbarer und einfahrbarer Stützmastabschnitt vorgesehen ist.Assembly platform ( 1 ) according to one of claims 6 to 8, characterized in that between the two Stützmasthoenbenen the climbing arms ( 9 . 10 ) an extendable and retractable support pole section is provided. Montagebühne (1) nach Anspruch 9, dadurch gekennzeichnet, dass der ein- und ausfahrbare Stützmastabschnitt als Scherenhebevorrichtung (11) ausgebildet ist.Assembly platform ( 1 ) according to claim 9, characterized in that the retractable and extendable support pole section as a scissor lift ( 11 ) is trained. Montagebühne (1) nach einem der Ansprüche 6 bis 10, dadurch gekennzeichnet, dass die Kletterarme (9, 10) als Teleskoparme ausgebildet sind.Assembly platform ( 1 ) according to one of claims 6 to 10, characterized in that the climbing arms ( 9 . 10 ) are designed as telescopic arms. Montagebühne (1) nach einem der Ansprüche 2 bis 11, dadurch gekennzeichnet, dass die Gelenkarme (4) der Arbeitskörbe (2.1, 2.2, 3.1, 3.2) an einem Drehkranz (6) des Montageturms befestigbar sind.Assembly platform ( 1 ) according to one of claims 2 to 11, characterized in that the articulated arms ( 4 ) of the work baskets ( 2.1 . 2.2 . 3.1 . 3.2 ) on a turntable ( 6 ) of the assembly tower can be fastened. Montagebühne (1) nach Anspruch 12, dadurch gekennzeichnet, dass der Drehkranz (6) ortsfest an dem Stützmast (5) befestigt ist.Assembly platform ( 1 ) according to claim 12, characterized in that the turntable ( 6 ) fixed to the supporting mast ( 5 ) is attached. Montagebühne (1) nach Anspruch 12, dadurch gekennzeichnet, dass der Drehkranz (6, 13) vertikal beweglich an dem Stützmast (5) befestigt ist.Assembly platform ( 1 ) according to claim 12, characterized in that the turntable ( 6 . 13 ) vertically movable on the support mast ( 5 ) is attached. Montagebühne (1) nach Anspruch 14, dadurch gekennzeichnet, dass an dem Drehkranz (13) ein Arbeitskorb (2.1, 2.2, 3.1, 3.2) verfahrbar ist.Assembly platform ( 1 ) according to claim 14, characterized in that on the turntable ( 13 ) a work basket ( 2.1 . 2.2 . 3.1 . 3.2 ) is movable. Montagebühne (1) nach einen der Ansprüche 1 bis 15, dadurch gekennzeichnet, dass in verschiedenen Stützmasthochebenen jeweils eine Gruppe von Arbeitskörben (2.1, 2.2, 3.1, 3.2) vorgesehen sind.Assembly platform ( 1 ) according to any one of claims 1 to 15, characterized in that in different Stützmasthöchbenen each a group of work baskets ( 2.1 . 2.2 . 3.1 . 3.2 ) are provided.
DE102015012634.2A 2015-09-30 2015-09-30 Assembly platform for in particular the construction of tower segments of wind turbines Withdrawn DE102015012634A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE102015012634.2A DE102015012634A1 (en) 2015-09-30 2015-09-30 Assembly platform for in particular the construction of tower segments of wind turbines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102015012634.2A DE102015012634A1 (en) 2015-09-30 2015-09-30 Assembly platform for in particular the construction of tower segments of wind turbines

Publications (1)

Publication Number Publication Date
DE102015012634A1 true DE102015012634A1 (en) 2017-03-30

Family

ID=58281299

Family Applications (1)

Application Number Title Priority Date Filing Date
DE102015012634.2A Withdrawn DE102015012634A1 (en) 2015-09-30 2015-09-30 Assembly platform for in particular the construction of tower segments of wind turbines

Country Status (1)

Country Link
DE (1) DE102015012634A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108843518A (en) * 2018-08-23 2018-11-20 三重能有限公司 Wind power generating set and tower plate member pairing device
CN109629815A (en) * 2019-01-15 2019-04-16 江苏金海新能源科技有限公司 Operation platform and construction equipment
CN110998042A (en) * 2017-07-05 2020-04-10 安利马克集团管理公司 Transport system, elevator system, kit, tower section and method for performing an assembly or maintenance operation in a tower

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2450604A1 (en) 1973-10-27 1975-04-30 Simon Eng Dudley Ltd DEVICE THAT ALLOWS ACCESS TO THE INTERIOR OF TANK COMPARTMENTS
FR2458503A1 (en) 1979-06-12 1981-01-02 Potain Sa Adjustable height support for maintenance of buildings - has movable forks mounted on carriage on tower and moving up and down tracks under action of winch
DE4498649T1 (en) 1993-11-11 1996-10-17 Bronto Skylift Oy Ab Personnel lifting device
FR2836680A1 (en) 2002-03-01 2003-09-05 Pinguely Haulotte Lift machine for building facade components has motor to raise and lower load platform supporting height adjustable secondary platform
DE102008055607A1 (en) 2007-11-02 2009-05-14 Cordero Alejandro Cortina Pre-stressed concrete tower for wind-power generator, has pyramidal structure having triangular cross section provided with rounded vertices, where structure is stacked such that tower gradually narrows and ends into circular section
WO2012007226A2 (en) 2010-07-13 2012-01-19 Siemens Aktiengesellschaft An assembly rig for assembling a wind turbine tower or wind turbine tower sections and a respective method
WO2014019852A1 (en) 2012-07-30 2014-02-06 Palfinger Systems Gmbh Maintenance device
EP2735674A1 (en) 2012-11-21 2014-05-28 Siemens Aktiengesellschaft Slipformed concrete tower

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2450604A1 (en) 1973-10-27 1975-04-30 Simon Eng Dudley Ltd DEVICE THAT ALLOWS ACCESS TO THE INTERIOR OF TANK COMPARTMENTS
FR2458503A1 (en) 1979-06-12 1981-01-02 Potain Sa Adjustable height support for maintenance of buildings - has movable forks mounted on carriage on tower and moving up and down tracks under action of winch
DE4498649T1 (en) 1993-11-11 1996-10-17 Bronto Skylift Oy Ab Personnel lifting device
FR2836680A1 (en) 2002-03-01 2003-09-05 Pinguely Haulotte Lift machine for building facade components has motor to raise and lower load platform supporting height adjustable secondary platform
DE102008055607A1 (en) 2007-11-02 2009-05-14 Cordero Alejandro Cortina Pre-stressed concrete tower for wind-power generator, has pyramidal structure having triangular cross section provided with rounded vertices, where structure is stacked such that tower gradually narrows and ends into circular section
WO2012007226A2 (en) 2010-07-13 2012-01-19 Siemens Aktiengesellschaft An assembly rig for assembling a wind turbine tower or wind turbine tower sections and a respective method
WO2014019852A1 (en) 2012-07-30 2014-02-06 Palfinger Systems Gmbh Maintenance device
EP2735674A1 (en) 2012-11-21 2014-05-28 Siemens Aktiengesellschaft Slipformed concrete tower

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110998042A (en) * 2017-07-05 2020-04-10 安利马克集团管理公司 Transport system, elevator system, kit, tower section and method for performing an assembly or maintenance operation in a tower
CN110998042B (en) * 2017-07-05 2021-06-22 安利马克集团管理公司 Transport system, kit and method for performing assembly or maintenance operations in a tower structure
CN108843518A (en) * 2018-08-23 2018-11-20 三重能有限公司 Wind power generating set and tower plate member pairing device
CN108843518B (en) * 2018-08-23 2023-11-24 三一重能股份有限公司 Wind generating set and tower barrel piece type component assembling device
CN109629815A (en) * 2019-01-15 2019-04-16 江苏金海新能源科技有限公司 Operation platform and construction equipment
CN109629815B (en) * 2019-01-15 2024-01-09 江苏金海新能源科技有限公司 Construction platform and construction equipment

Similar Documents

Publication Publication Date Title
DE202012007550U1 (en) Self-propelled aerial work platform
EP3827146A1 (en) Lift drive for a rail-guided climbing system
DE2400313A1 (en) AUXILIARY DEVICE FOR A CABLE NET COOLING TOWER
DE1603179C3 (en) Ferris wheel
DE102015012634A1 (en) Assembly platform for in particular the construction of tower segments of wind turbines
EP3047083B1 (en) Variable protective roof
WO2015090282A1 (en) Retaining, lifting, and securing device for attaching to tall tower-like structures
DE102005053782B4 (en) Self-climbing device
DE102017002525B4 (en) Working platform for the construction of tower segments and towers of wind turbines, for example
DE102015012635B4 (en) Assembly platform for in particular the construction of tower segments of Windkraftanlangen
EP2035314B1 (en) Lifting platform and method for setting up a lifting platform
EP2316754B1 (en) Subterranean waste collection device
AT506952B1 (en) MAINTENANCE SYSTEM
DE10308239A1 (en) Method and device for installing a wind turbine
DE2324843C2 (en) Device for assembling multi-part masts
DE1291079B (en) Collapsible crane with a telescopic mast
DE102014110824B4 (en) A tower-like amusement device and method for constructing an amusement device
DE19704967A1 (en) Portal crane, especially for erecting buildings
DE2504762C3 (en) Working platform for bracket scaffolding
EP3255227B1 (en) Assembly aid and method for replacing a support structure element
DE3911044C2 (en)
DE759687C (en) For the heaviest loads, it can be dismantled and easily erected
DE202007001615U1 (en) Work platform for the formwork of a concrete container wall
DE2132597C3 (en) Method and device for erecting an elongated vertical structure, e.g. a chimney
DE102013003191A1 (en) Combination of a hub trim segment of a wind turbine and a hub trim segment carrying caddy and transport frame and method for transporting a hub trim segment of a wind turbine

Legal Events

Date Code Title Description
R012 Request for examination validly filed
R120 Application withdrawn or ip right abandoned