CN2673944Y - Prestressed pipe pile with large end filled with sand - Google Patents
Prestressed pipe pile with large end filled with sand Download PDFInfo
- Publication number
- CN2673944Y CN2673944Y CN 200320127200 CN200320127200U CN2673944Y CN 2673944 Y CN2673944 Y CN 2673944Y CN 200320127200 CN200320127200 CN 200320127200 CN 200320127200 U CN200320127200 U CN 200320127200U CN 2673944 Y CN2673944 Y CN 2673944Y
- Authority
- CN
- China
- Prior art keywords
- pile
- sand
- concrete
- utility
- pipe pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000004576 sand Substances 0.000 title claims abstract description 15
- 239000004567 concrete Substances 0.000 claims abstract description 12
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 9
- 239000010959 steel Substances 0.000 claims abstract description 9
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 5
- 241000826860 Trapezium Species 0.000 claims description 2
- 230000003601 intercostal effect Effects 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 7
- 239000002689 soil Substances 0.000 abstract description 7
- 230000003247 decreasing effect Effects 0.000 abstract 1
- 230000001737 promoting effect Effects 0.000 abstract 1
- 239000000463 material Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 238000005056 compaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Abstract
As the same as prior art, a pre-stressed pipe pile with large end filled with sand of the utility model also comprises a pipe pile body with pre-stressed reinforced concrete, the utility model is characterized in that the end of the pipe pile is provided with another prefabricated pile large end made of reinforced concrete, or concrete, or steel, and the diameter of the pile large end is larger than the diameter of the pipe pile body by 8-40 cm; the pipe pile body is provided projecting concrete or reinforced concrete ribs with width of 5-25 cm and height of 5-20 cm every 1-7 m, the place between two ribs is filled with sand or grail, the cross-section of the rib is as a trapezoid, an isosceles trapezoid or a right angled trapezoid. Compared with prior art, the utility model has the obvious advantages of greatly improving the bearing capacity of single pile, decreasing pile numbers, reducing construction cost, promoting horizon curing, and improving horizon strength in the equal geological condition. The utility model is applicable for the construction foundation engineering in the soft soil foundation.
Description
Utility model major part back-up sand pile for prestressed pipe relates to the civil construction field, relates in particular to the building foundation engineering field.
As everyone knows, in building foundation engineering, pile for prestressed pipe is low with cost, the duration is short, the construction plant is clean and be widely used.But existing pile for prestressed pipe its internal diameter, external diameter and wall thickness in same joint all equate from top to bottom, China's coastal cities multidigit is in estuary bay, be soft foundation, the soil layer collateral resistance is little, bearing capacity of single pile is not high, make pile shaft material intensity to make full use of and waste, cause the Foundation Design cost high.
The purpose of this utility model provides major part back-up sand pile for prestressed pipe, can improve bearing capacity of single pile significantly under equal geological conditions, pile shaft material intensity can be given full play to, thereby reduce the total amount of pile of building, reaches and reduces the Foundation Design cost.
The purpose of this utility model is achieved through the following technical solutions: major part back-up sand pile for prestressed pipe is the same with prior art, the tubulose pile body that all includes prestressed reinforced concrete, it is characterized in that: at pile tube stake end, the stake major part of prefabricated separately steel concrete or concrete or steel is arranged, and the stake diameter at butt end is greater than tubular pile body diameter 8-40cm; At tubular pile body, every 1-7m, concrete or the steel concrete rib of the wide 5-25cm of a protrusion, high 5-20cm arranged, two intercostal back-up sand or gravels, the cross section of rib are trapezoidal, isosceles trapezoid or right-angled trapezium; The soil compaction effect that causes of piling and discharge soil layer mesopore water pressure as early as possible can be provided with the vertical drainage hole of 1-10 diameter 0.5-3cm in rib.
The utility model compared with prior art has following conspicuous advantage: it can increase substantially bearing capacity of single pile under equal geological conditions, reduce the stake number, reduces construction costs, promotes soil layer to solidify, and improves soil layer intensity.The utility model is applicable to the building foundation engineering of soft foundation.
Description of drawings:
Fig. 1 is the generalized section of the utility model embodiment.
Fig. 2 is the floor map (a is the closing pile point, and c is an opening stake point) and the generalized section (b is the closing pile point, and d is an opening stake point) of steel concrete of the present utility model or concrete pile major part.
Fig. 3 is steel stake major part floor map of the present utility model (a) and generalized section (b).(1) is stake major part end plate among the figure, and (2) are the wing of putting more energy into, and (3) are ring.
An exemplary embodiments of the present utility model such as Fig. 1: produce required pile tube with ribbing (1) by pile tube manufactory earlier, (5) and the stake major part (6), treat to transport the job site to after intensity reaches, stake major part (6) is placed on the stake position, hang first segment pile tube (5) and stand on a major part (6) center, the all heap sands of stake, piling (or piling) limit, limit constantly adds sand, by managing rib (2) with abrasive band underground layer (9), (8), (7) in, form stake all back-up sand layers (3), first segment pile tube (5) is sink to ground, it is placed on it to hang the second pipe joint stake (1), and electric welding joins, and it squeezed into soil layer (9) again, (8) in until design elevation, like this, just finish the making construction of a major part back-up sand pile for prestressed pipe, the pressure pore water that pile sinking causes is discharged ground by the drain hole (4) in back-up sand layer (3) and the rib (2).Go round and begin again, finish the making and the construction of all required major part back-up sand pile for prestressed pipe.
Claims (1)
1. utility model major part back-up sand pile for prestressed pipe is the same with prior art, the tubulose pile body that all includes prestressed reinforced concrete, it is characterized in that: at pile tube stake end, the stake major part of prefabricated separately steel concrete or concrete or steel is arranged, and the stake diameter at butt end is greater than tubular pile body diameter 8-40cm; At tubular pile body, every 1-7m, concrete or the steel concrete rib of the wide 5-25cm of a protrusion, high 5-20cm arranged, two intercostal back-up sand or gravels, the cross section of rib are trapezoidal, isosceles trapezoid or right-angled trapezium.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200320127200 CN2673944Y (en) | 2003-08-19 | 2003-11-28 | Prestressed pipe pile with large end filled with sand |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN03209892.8 | 2003-08-19 | ||
CN03209892 | 2003-08-19 | ||
CN 200320127200 CN2673944Y (en) | 2003-08-19 | 2003-11-28 | Prestressed pipe pile with large end filled with sand |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2673944Y true CN2673944Y (en) | 2005-01-26 |
Family
ID=34523673
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200320127200 Expired - Fee Related CN2673944Y (en) | 2003-08-19 | 2003-11-28 | Prestressed pipe pile with large end filled with sand |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2673944Y (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101812838A (en) * | 2010-04-27 | 2010-08-25 | 天津大学 | Foundation reinforcement method based on curing agent and bucket foundation suction technique |
CN102747724A (en) * | 2011-04-19 | 2012-10-24 | 陈东曙 | Sand-filled composite pile, pile forming device and pile forming method |
CN103362122A (en) * | 2012-04-04 | 2013-10-23 | 邹宗煊 | High-bearing-capacity sand filling pipe pile with pile joints and manufacturing and construction method of pile |
CN105649009A (en) * | 2016-03-08 | 2016-06-08 | 同济大学 | Rigid precast concrete pile with drainability |
CN106013138A (en) * | 2016-07-14 | 2016-10-12 | 苏义民 | Pipe pile with incomplete ribs |
CN110206014A (en) * | 2019-03-27 | 2019-09-06 | 河海大学 | Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure |
CN113266011A (en) * | 2021-04-28 | 2021-08-17 | 李俊飞 | Novel composite pile enclosure device |
-
2003
- 2003-11-28 CN CN 200320127200 patent/CN2673944Y/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101812838A (en) * | 2010-04-27 | 2010-08-25 | 天津大学 | Foundation reinforcement method based on curing agent and bucket foundation suction technique |
CN101812838B (en) * | 2010-04-27 | 2011-08-10 | 天津大学 | Foundation reinforcement method based on curing agent and bucket foundation suction technique |
CN102747724A (en) * | 2011-04-19 | 2012-10-24 | 陈东曙 | Sand-filled composite pile, pile forming device and pile forming method |
CN102747724B (en) * | 2011-04-19 | 2015-12-02 | 陈东曙 | A kind of piling method of back-up sand composite pile |
CN103362122A (en) * | 2012-04-04 | 2013-10-23 | 邹宗煊 | High-bearing-capacity sand filling pipe pile with pile joints and manufacturing and construction method of pile |
CN105649009A (en) * | 2016-03-08 | 2016-06-08 | 同济大学 | Rigid precast concrete pile with drainability |
CN106013138A (en) * | 2016-07-14 | 2016-10-12 | 苏义民 | Pipe pile with incomplete ribs |
CN110206014A (en) * | 2019-03-27 | 2019-09-06 | 河海大学 | Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure |
CN113266011A (en) * | 2021-04-28 | 2021-08-17 | 李俊飞 | Novel composite pile enclosure device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102505684A (en) | Hollow stiffness-core slurry-solidified discrete material pile and construction method thereof | |
CN103510510A (en) | Reinforced long spiral drilling concrete grouting pile and construction method thereof | |
CN208219340U (en) | A kind of new city road permeable pavement structure | |
CN108035423A (en) | Potential energy pressurized rainwater drainage and storage system and method for sponge city | |
CN2673944Y (en) | Prestressed pipe pile with large end filled with sand | |
CN105386610A (en) | Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit | |
CN111676987A (en) | Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method | |
CN105297717A (en) | Composite foundation pile with lower portion enlarged diameter section and construction method of composite foundation pile | |
CN207659986U (en) | A kind of building or structures foundation stabilization underpin pier | |
CN206346221U (en) | The left and right combined type piping lane built using the pavement underground space | |
CN204825867U (en) | As composite pile structure of secretly digging garage stand | |
CN201411687Y (en) | Corrugated plastic sleeve pipe granule grouting pile with hole | |
CN2667005Y (en) | Prestressed pipe pile | |
CN203594023U (en) | Enhanced type long auger drilling pressure-grouting concrete pile | |
CN103195077B (en) | A kind of dam foundation reinforcement frame structure and stabilization of dam foundation method | |
CN108611948A (en) | A kind of urban road permeable pavement structure | |
CN213867907U (en) | Prefabricated expanded packing key type digging foundation for power transmission line | |
CN106939596A (en) | A kind of cast-in-place slub type slurry drilled pile | |
CN203129163U (en) | Reinforcing framework structure for dam foundation | |
CN113152446A (en) | Multi-section type prestressed hollow pile and construction method thereof | |
CN111962632A (en) | Rainwater sewer and construction method thereof | |
CN201943071U (en) | Implantable steel tube anchor rod with stabs | |
CN206521667U (en) | A kind of permeable pavement construction | |
CN205259175U (en) | Lower part enlarges compound foundation pile of diameter section | |
CN200946270Y (en) | Sinking pipe bottom-expanding pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee |
Owner name: ROOM 610, DANFEI FACTORY DORMITORY, NO. 33, XIANGY Free format text: FORMER NAME OR ADDRESS: ROOM 603, NO. 7, LANE 15, XIUSHAN ROAD, XUHUI DISTRICT, SHANGHAI CITY, 200030 |
|
CP03 | Change of name, title or address |
Patentee address after: 350009, Zou Jiezhuan, dormitory 33, nitrogenous fertilizer plant, 610 elephant Road, Taijiang District, Fujian, Fuzhou Patentee address before: 200030 room 7, No. 15, Lane 603, Sau Shan Road, Shanghai, Xuhui District |
|
C19 | Lapse of patent right due to non-payment of the annual fee | ||