CN110206014A - Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure - Google Patents

Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure Download PDF

Info

Publication number
CN110206014A
CN110206014A CN201910239362.9A CN201910239362A CN110206014A CN 110206014 A CN110206014 A CN 110206014A CN 201910239362 A CN201910239362 A CN 201910239362A CN 110206014 A CN110206014 A CN 110206014A
Authority
CN
China
Prior art keywords
pile
prefabricated tubular
sand
outer diameter
caulking groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910239362.9A
Other languages
Chinese (zh)
Inventor
李振亚
高玉峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201910239362.9A priority Critical patent/CN110206014A/en
Publication of CN110206014A publication Critical patent/CN110206014A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • E02D3/106Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by forming sand drains containing only loose aggregates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/72Pile shoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structures.When construction, comprising: (1) after soft soil roadbed determining pile sinking point, place back-up sand steel pile casting;(2) there is the prefabricated tubular pile of opening pile toe to hang to pile sinking point stake end, pile top is pressed by weak soil using pile press machine, until pile top is completely forced into weak soil;Wherein: the outer diameter of opening pile toe is greater than the outer diameter of prefabricated tubular pile, and opening pile toe sinks to soft soil roadbed formation counterbore;(3) dry crude sand is poured into back-up sand steel pile casting;(4) continue pile sinking operation, by the frictional force of dry crude sand in prefabricated tubular pile pile body and back-up sand steel pile casting, dry crude sand is inserted in the gap between prefabricated tubular pile pile body and counterbore hole wall, up to pile sinking to predetermined depth.Therefore, the present invention inserts dry sand in gap, forms drainage channel, to accelerate the dissipation of the excess pore water pressure of pile sinking generation, accelerates the consolidation of foundation soil, is substantially reduced settlement after construction, improve consolidation process effect.

Description

Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure
Technical field
The present invention relates to a kind of fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structures.
Background technique
The coastal region in east China is economically developed, and expressway construction is in urgent need.Due to this area be generally distributed with it is deep soft Soil layer, soil body void ratio is big, water content is high, intensity is low and compressibility is high, and post-construction settlement of subgrade is larger, especially connects in road and bridge Place leads to bumping at bridge-head, pavement cracking since road and bridge relative settlement is big, seriously affects traffic safety.Therefore, it selects Suitable mode carries out consolidation process to Bridgehead by Blastig and is of great significance.Currently, being beaten in many subgrade strengthening processing methods If the rigid pile composite foundation effect that prefabricated tubular pile is formed is the most significant.To such composite foundation, upper load mainly by answering in advance Solenoid stake is shared, and it is less that inter-pile soil shares load, therefore its bearing capacity is higher and settling amount can control well.But due to beating Soil compaction effect during stake, the soil body near pile body generates excess pore water pressure and is difficult to dissipate, to influence stake The consolidation of all soil, it is unfavorable to the development of performance and the sedimentation of its bearing capacity, cause settlement amount after construction excessive.
Summary of the invention
To alleviate, super quiet pore pressure existing for existing rigid pile Bridgehead by Blastig consolidation process is difficult to dissipate and settlement after construction is excessive The problem of, the invention proposes a kind of fill out sand tube stake Bridgehead by Blastig consolidation process technologies.It is greater than outside tubular pole in stake end weld size The pile top of diameter forms the gap between pile body and surrounding soil, dry sand is inserted in gap, it is logical to form draining during piling Accelerate the consolidation of foundation soil to accelerate the dissipation of the excess pore water pressure of pile sinking generation, be substantially reduced settlement after construction, mention in road High consolidation process effect.
To realize that above-mentioned technical purpose, the present invention will take the following technical solution:
A kind of fill out sand tube stake Bridgehead by Blastig reinforced construction method, comprising the following steps:
(1) after soft soil roadbed determining pile sinking point, back-up sand steel pile casting is placed;
(2) there is the prefabricated tubular pile of opening pile toe to hang to pile sinking point stake end, pile top be pressed by weak soil using pile press machine, Until pile top is completely forced into weak soil;Wherein: the outer diameter of opening pile toe is greater than the outer diameter of prefabricated tubular pile, and opening pile toe sinks to weak soil Roadbed forms counterbore;
(3) dry crude sand is poured into back-up sand steel pile casting;
(4) continue pile sinking operation, by the frictional force of dry crude sand in prefabricated tubular pile pile body and back-up sand steel pile casting, will do Coarse sand is inserted in the gap between prefabricated tubular pile pile body and counterbore hole wall, up to pile sinking to predetermined depth;
(5) after being completed to the equal pile sinking in full wafer place, pile cover is first set, one layer of mattress layer is then re-layed.
As the further improvement of above-mentioned fill out sand tube stake Bridgehead by Blastig reinforced construction method, the stake end of the prefabricated tubular pile is logical Nested mode is crossed to connect with pile top.
As the further improvement of above-mentioned fill out sand tube stake Bridgehead by Blastig reinforced construction method, the top of the pile top has ring Shape caulking groove;The internal diameter of annular caulking groove and the outer diameter of prefabricated tubular pile are suitable, and the outer diameter of annular caulking groove is greater than the outer diameter of prefabricated tubular pile, and The outer wall of annular caulking groove has cutting edge;The stake end of prefabricated tubular pile is nested in annular caulking groove.
Another technical object of the present invention is to provide a kind of fill out sand tube stake Bridgehead by Blastig ruggedized construction, including it is counterbore, prefabricated Tubular pole, pile cover and mattress layer;The stake end of prefabricated tubular pile has opening pile toe, and the outer diameter of opening pile toe is greater than the outer of prefabricated tubular pile Diameter, while opening pile toe forms tip by opening up cutting edge in outer wall;Counterbore sinks to pile sinking point by opening pile toe and is formed;In advance There is dry crude sand between the pile body of tubulation stake and the hole wall of counterbore.
As the further improvement of above-mentioned fill out sand tube stake Bridgehead by Blastig ruggedized construction, the top of the pile top has annular embedding Slot;The internal diameter of annular caulking groove and the outer diameter of prefabricated tubular pile are suitable, and the outer diameter of annular caulking groove is greater than the outer diameter of prefabricated tubular pile, and annular The outer wall of caulking groove has cutting edge;The stake end of prefabricated tubular pile is nested in annular caulking groove.
As the further improvement of above-mentioned fill out sand tube stake Bridgehead by Blastig ruggedized construction, the stake end of prefabricated tubular pile and annular caulking groove Between be welded and fixed.
According to above-mentioned technical solution, compared with the existing technology, the present invention has the advantage that:
The present invention fills coarse sand in stake week, on the one hand can be improved the side friction of stake, is on the other hand capable of forming draining Channel accelerates the dissipation of excess pore water pressure and the consolidation of soil around pile, is substantially reduced settlement after construction.
Detailed description of the invention
Fig. 1 is a kind of back-up sand tubular pole pile sinking sectional view.
Fig. 2 is a kind of fill out sand tube stake Bridgehead by Blastig consolidation process effect sectional view.
In figure: prefabricated tubular pile 1, opening pile toe 2, back-up sand steel pile casting 3, coarse sand 4, weak soil 5, pile cover 6, mattress layer 7, embankment are filled out Soil 8.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Whole description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Below Description only actually at least one exemplary embodiment be it is illustrative, never as to the present invention and its application or make Any restrictions.Based on the embodiments of the present invention, those of ordinary skill in the art are not before making creative work Every other embodiment obtained is put, shall fall within the protection scope of the present invention.Unless specifically stated otherwise, otherwise at these The positioned opposite of component and step described in embodiment, expression formula and numerical value do not limit the scope of the invention.Meanwhile it should be bright White, for ease of description, the size of various pieces shown in attached drawing is not to draw according to actual proportionate relationship.It is right The technology known to person of ordinary skill in the relevant, method and apparatus may be not discussed in detail, but in the appropriate case, institute Stating technology, method and apparatus should be considered as authorizing part of specification.In shown here and discussion all examples, appoint What occurrence should be construed as merely illustratively, not as limitation.Therefore, the other examples of exemplary embodiment can With different values.
For ease of description, spatially relative term can be used herein, as " ... on ", " ... top ", " ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy The spatial relation of sign.It should be understood that spatially relative term is intended to comprising the orientation in addition to device described in figure Except different direction in use or operation.For example, being described as if the device in attached drawing is squeezed " in other devices It will be positioned as " under other devices or construction after part or construction top " or the device of " on other devices or construction " Side " or " under other devices or construction ".Thus, exemplary term " ... top " may include " ... top " and " in ... lower section " two kinds of orientation.The device can also be positioned with other different modes and (is rotated by 90 ° or in other orientation).
The invention discloses a kind of fill out sand tube stake Bridgehead by Blastig reinforced construction methods, comprising the following steps:
(1) after soft soil roadbed determining pile sinking point, back-up sand steel pile casting 3 is placed;
(2) there is the prefabricated tubular pile 1 of opening pile toe 2 to hang to pile sinking point stake end, is pressed into pile top using pile press machine soft Soil 5, until pile top is completely forced into weak soil 5;Wherein: the outer diameter of opening pile toe 2 is greater than the outer diameter of prefabricated tubular pile 1, opening pile toe 2 Sink to soft soil roadbed formation counterbore;
(3) dry crude sand 4 is poured into back-up sand steel pile casting 3;
(4) continue pile sinking operation, by the frictional force of dry crude sand 4 in 1 pile body of prefabricated tubular pile and back-up sand steel pile casting 3, Dry crude sand 4 is inserted in the gap between 1 pile body of prefabricated tubular pile and counterbore hole wall, up to pile sinking to predetermined depth;
(4) after being completed to the equal pile sinking in full wafer place, pile cover 6 is first set, one layer of mattress layer 7 is then re-layed.
The invention also discloses a kind of fill out sand tube stake Bridgehead by Blastig ruggedized construction, including counterbore, prefabricated tubular pile 1, pile cover 6 and Mattress layer 7;The stake end of prefabricated tubular pile 1 has opening pile toe 2, and the outer diameter of opening pile toe 2 is greater than the outer diameter of prefabricated tubular pile 1, together When opening pile toe 2 by outer wall open up cutting edge formed tip;Counterbore sinks to pile sinking point by opening pile toe 2 and is formed;It is prefabricated There is dry crude sand 4 between the pile body of tubular pole 1 and the hole wall of counterbore.
As the further improvement of above-mentioned fill out sand tube stake Bridgehead by Blastig ruggedized construction, the top of the pile top has annular embedding Slot;The internal diameter of annular caulking groove is suitable with the outer diameter of prefabricated tubular pile 1, and the outer diameter of annular caulking groove is greater than the outer diameter of prefabricated tubular pile 1, and ring The outer wall of shape caulking groove has cutting edge;The stake end of prefabricated tubular pile 1 is nested in annular caulking groove.
As the further improvement of above-mentioned fill out sand tube stake Bridgehead by Blastig ruggedized construction, the stake end of prefabricated tubular pile 1 and annular are embedding It is welded and fixed between slot.
1 end of prefabricated tubular pile of the present invention is welded with opening pile toe 2, and pile top top is annular caulking groove, annular caulking groove internal diameter with 1 outer diameter of prefabricated tubular pile is suitable, and outer diameter is then greater than 1 outer diameter of prefabricated tubular pile, to keep prefabricated tubular pile 1 nested wherein;Pile top lower part Internal diameter it is suitable with 1 internal diameter of prefabricated tubular pile, outside is provided with cutting edge, in order to pile sinking.Since the size on pile top top is greater than tubular pole Outer diameter can generate gap in pile driving process between pile body and surrounding soil, and it is logical to form draining that dry crude sand 4 is inserted in gap Road, the excess pore water pressure rapid dispersion generated convenient for pile sinking.When construction, it is first determined simultaneously place back-up sand steel shield in pile sinking position Cylinder 3, the pile top for being provided with cutting edge is welded on the stake end of prefabricated tubular pile 1;Then, pile top is pressed into soil with pile press machine, it is past heavy Dry crude sand 4 is poured into sand steel pile casting, is continued pile sinking operation, dry crude sand 4 is filled in stake week gap by pile body frictional force, directly Back-up sand amount is monitored, and compare with back-up sand amount is estimated, it is ensured that back-up sand effect in the process to pile sinking to predetermined depth;Finally, After being completed to full wafer place pile sinking, pile cover 6 is set and is laid with certain thickness mattress layer 7.Subgrade strengthening work is completed, and one After the section time, filling for embankment filled soil 8 can be carried out.
Pipe pile week is filled with coarse sand, and in order to the excess pore water pressure rapid dispersion that pile sinking generates, and it is logical to form draining Road reduces settlement after construction to accelerate the consolidation of pile peripheral earth.

Claims (6)

1. a kind of fill out sand tube stake Bridgehead by Blastig reinforced construction method, which comprises the following steps:
(1) after soft soil roadbed determining pile sinking point, back-up sand steel pile casting is placed;
(2) there is the prefabricated tubular pile of opening pile toe to hang to pile sinking point stake end, pile top is pressed by weak soil using pile press machine, until Pile top is completely forced into weak soil;Wherein: the outer diameter of opening pile toe is greater than the outer diameter of prefabricated tubular pile, and opening pile toe sinks to soft soil roadbed Form counterbore;
(3) dry crude sand is poured into back-up sand steel pile casting;
(4) continue pile sinking operation, by the frictional force of dry crude sand in prefabricated tubular pile pile body and back-up sand steel pile casting, by dry crude sand It inserts in the gap between prefabricated tubular pile pile body and counterbore hole wall, up to pile sinking to predetermined depth;
(5) after being completed to the equal pile sinking in full wafer place, pile cover is first set, one layer of mattress layer is then re-layed.
2. fill out sand tube stake Bridgehead by Blastig reinforced construction method according to claim 1, which is characterized in that the prefabricated tubular pile Stake end connect by way of nested with pile top.
3. fill out sand tube stake Bridgehead by Blastig reinforced construction method according to claim 2, which is characterized in that the pile top it is upper Portion has annular caulking groove;The internal diameter of annular caulking groove and the outer diameter of prefabricated tubular pile are suitable, and the outer diameter of annular caulking groove is greater than prefabricated tubular pile Outer diameter, and the outer wall of annular caulking groove has cutting edge;The stake end of prefabricated tubular pile is nested in annular caulking groove.
4. a kind of fill out sand tube stake Bridgehead by Blastig ruggedized construction, including counterbore, prefabricated tubular pile, pile cover and mattress layer;It is characterized in that, The stake end of prefabricated tubular pile has opening pile toe, and the outer diameter of opening pile toe is greater than the outer diameter of prefabricated tubular pile, while opening pile toe is logical It crosses and opens up cutting edge formation tip in outer wall;Counterbore sinks to pile sinking point by opening pile toe and is formed;The pile body of prefabricated tubular pile and heavy There is dry crude sand between the hole wall in hole.
5. fill out sand tube stake Bridgehead by Blastig ruggedized construction according to claim 4, which is characterized in that the top of the pile top has There is annular caulking groove;The internal diameter of annular caulking groove and the outer diameter of prefabricated tubular pile are suitable, and the outer diameter of annular caulking groove is greater than the outer of prefabricated tubular pile Diameter, and the outer wall of annular caulking groove has cutting edge;The stake end of prefabricated tubular pile is nested in annular caulking groove.
6. fill out sand tube stake Bridgehead by Blastig ruggedized construction according to claim 5, which is characterized in that the stake end of prefabricated tubular pile with It is welded and fixed between annular caulking groove.
CN201910239362.9A 2019-03-27 2019-03-27 Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure Pending CN110206014A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910239362.9A CN110206014A (en) 2019-03-27 2019-03-27 Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910239362.9A CN110206014A (en) 2019-03-27 2019-03-27 Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure

Publications (1)

Publication Number Publication Date
CN110206014A true CN110206014A (en) 2019-09-06

Family

ID=67785094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910239362.9A Pending CN110206014A (en) 2019-03-27 2019-03-27 Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure

Country Status (1)

Country Link
CN (1) CN110206014A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116438353A (en) * 2020-06-23 2023-07-14 拉梅什·钱德拉·古普塔 Rapid consolidation compaction process for soil improvement of various soil layers and intermediate rock-soil material layers in soil deposits

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2673944Y (en) * 2003-08-19 2005-01-26 邹宗煊 Prestressed pipe pile with large end filled with sand
CN102535263A (en) * 2012-02-14 2012-07-04 中铁十九局集团有限公司 Roadbed with pile-net composite structure and construction method thereof
CN104389305A (en) * 2014-11-18 2015-03-04 中淳高科桩业股份有限公司 Sand-filled bamboo-joint pile and construction method thereof
JP2017031783A (en) * 2015-08-03 2017-02-09 有限会社ケミカリング Pile with metal fitting

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2673944Y (en) * 2003-08-19 2005-01-26 邹宗煊 Prestressed pipe pile with large end filled with sand
CN102535263A (en) * 2012-02-14 2012-07-04 中铁十九局集团有限公司 Roadbed with pile-net composite structure and construction method thereof
CN104389305A (en) * 2014-11-18 2015-03-04 中淳高科桩业股份有限公司 Sand-filled bamboo-joint pile and construction method thereof
JP2017031783A (en) * 2015-08-03 2017-02-09 有限会社ケミカリング Pile with metal fitting

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116438353A (en) * 2020-06-23 2023-07-14 拉梅什·钱德拉·古普塔 Rapid consolidation compaction process for soil improvement of various soil layers and intermediate rock-soil material layers in soil deposits

Similar Documents

Publication Publication Date Title
Rujikiatkamjorn et al. Analytical solutions and design curves for vacuum-assisted consolidation with both vertical and horizontal drainage
US20230220649A1 (en) Self-sinking-type deep foundation pit retaining wall structure and construction method for underground space structure
CN101736738B (en) Production method of pressure resistance and pull-out resistance grouted gravel pile
WO2021000387A1 (en) Anti-liquefaction treatment method for high-performance gravel piles of existing building foundations
JP2022517333A (en) Structure construction method
CN109183867A (en) A kind of non-disturbance is adjusted fast short stopping and inclines method
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN111379203B (en) Geogrid reinforcement and membrane bag grouting combined sedimentation device, sedimentation method and application
CN110158585A (en) A kind of device and construction method for cutting down Soft Soil Area pile foundation negative friction force
CN110206014A (en) Fill out sand tube stake Bridgehead by Blastig reinforced construction method and its structure
CN103741690B (en) A kind of soil plug compensates pile tube and extracts construction method and soil plug used compensation pile tube pile pulling device thereof
CN109722967A (en) A kind of road structure preventing soft clay area highway bridgehead vehicle jump and its method
CN103966996A (en) Gravel pile and manufacturing method thereof
CN104975611A (en) Sinking device and method for well point drawdown pipe of liquid soil layer
CN112081158B (en) Construction method for forming reinforced composite pile foundation by advanced grouting of high-rise building
CN105672329B (en) The large size prefabricated building enclosure of deep basal pit and construction method
CN111894027A (en) Open caisson structure and open caisson construction method
CN208501762U (en) A kind of pile foundation sedimentation reinforcing jacking leveling structure
CN109914392A (en) Upper section draining is lower to save not drain combination type prefabricated tubular pile and construction method
CN110144918A (en) Hypogee dewatering well antiseepage plugging construction method
CN104929101B (en) Resistance to plucking prestress anchoraging broken stone pile and construction method that a kind of base expanding and base expanding multistage side is expanded
CN105951874B (en) A kind of retaining wall reinforcement structure and its construction method
CN101545255A (en) Method for manufacturing a PHC tubular pile in soft soil region through chambering and grouting
CN210368927U (en) Bridge head roadbed reinforcing structure of sand filling pipe pile
CN106120523B (en) A kind of integrated application stake and the construction method of vertical earth working material processing highway soft foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190906