CN110144918A - Hypogee dewatering well antiseepage plugging construction method - Google Patents

Hypogee dewatering well antiseepage plugging construction method Download PDF

Info

Publication number
CN110144918A
CN110144918A CN201910429045.3A CN201910429045A CN110144918A CN 110144918 A CN110144918 A CN 110144918A CN 201910429045 A CN201910429045 A CN 201910429045A CN 110144918 A CN110144918 A CN 110144918A
Authority
CN
China
Prior art keywords
partition
pipeline
dewatering well
plugging
hypogee
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910429045.3A
Other languages
Chinese (zh)
Inventor
易启洪
丁力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Tongshen Waterproofing Engineering Co Ltd
Original Assignee
Sichuan Tongshen Waterproofing Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Tongshen Waterproofing Engineering Co Ltd filed Critical Sichuan Tongshen Waterproofing Engineering Co Ltd
Priority to CN201910429045.3A priority Critical patent/CN110144918A/en
Publication of CN110144918A publication Critical patent/CN110144918A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices, or the like
    • E21B33/14Methods or devices for cementing, for plugging holes, crevices, or the like for cementing casings into boreholes

Abstract

The invention discloses hypogee dewatering well antiseepage plugging construction methods, include the following steps specific steps: 1) determining closure site: determining closure site and clear up closure site periphery;2) partition and line treatment: make and install partition and pipeline;3) rigid material plugged zone blocks: rigid plugging material is perfused on the top of partition;4) grouting material plugged zone blocks: grouting material is perfused in the lower part of partition;5) it duct grouting: is in the milk to pipeline;6) pipe plugging and post-processing: leak stopping is carried out to pipeline and cuts extra pipeline, brushing protective layer;Effectively solution blocks long-term seepage problem after dewatering well, has closure speed fast, is not in infiltration situation after closure, there are also to surrounding soil reinforcement effect.

Description

Hypogee dewatering well antiseepage plugging construction method
Technical field
The present invention relates to hypogee waterproofing and leakage-stopping and reinforcement technique fields, are that hypogee dewatering well is anti-specifically Seep plugging construction method.
Background technique
Basement refers to that room floors are lower than half of the height more than the stud of outdoor ground level.Multilayer and High-rise needs deeper basis, to build basement under architecture bottom layer, can both increase use using this height Area, and room heart backfill can be saved, it can be said to be both economical.Basement is built below housing bottom, can be improved for building Ground efficiency.Some skyscraper bases buried depth is very big, makes full use of this depth to build basement, economic effect and use Effect is all good.Basement is divided by function, there is basement without protective requirement and emptying basement;By structural material point, have brick wall structure and Concrete structure basement has full basement and partly-exposed basement by structural form point.
It is in earth work, ground and basic engineering construction in the dewatering well construction environment relatively high for level of ground water An important technique measure, can moisture in drainage base soil, promote soil solidifying, improve foundation strength, while can reduce The lateral displacement of the slight slope soil body and sedimentation, stable side slope, eliminate quicksand, reduce substrate soil protuberance, make positioned at natural groundwater with Under ground and basic engineering construction be avoided that the influence of underground water, provide comparison dry execution conditions, the earthwork can also be reduced It measures, shorten the construction period, improving construction quality and guarantee construction safety.
The construction technology of existing hypogee plugging dewatering well technology is broadly divided into following two kinds:
One, after dewatering well draws water precipitation, penetration concrete is forced to block immediately.
Two, toward pouring into rubble in dewatering well, then concrete closure is filled.
But but there are the following problems for the prior art:
1. blocking time is too long.
2. cannot combine closely between concrete and the soil body, temperature and sedimentation variation be easy to cause displacement, cause to seep water.
3. the permanent time blocks, there is infiltration situation in edge, generation infiltration post-processing construction is complicated, and difficulty of construction is big, It is costly.
Summary of the invention
The purpose of the present invention is to provide hypogee dewatering well antiseepage plugging construction method, effectively solve to block dewatering well Long-term seepage problem afterwards has closure speed fast, is not in infiltration situation after closure, and there are also to surrounding soil reinforcement effect.
The present invention is achieved through the following technical solutions: hypogee dewatering well antiseepage plugging construction method, including following steps Rapid specific steps:
1) it determines closure site: determining closure site and clear up closure site periphery;
2) partition and line treatment: make and install partition and pipeline;
3) rigid material plugged zone blocks: rigid plugging material is perfused on the top of partition;
4) grouting material plugged zone blocks: grouting material is perfused in the lower part of partition;
5) it duct grouting: is in the milk to pipeline;
6) pipe plugging and post-processing: leak stopping is carried out to pipeline and cuts extra pipeline, brushing protective layer.
Further is that the present invention is better achieved, and especially uses following set-up modes: the step 1) specifically: to drop Well periphery substrate surface removes dusting, decortication tilts class defect, and dust, oil removal is clean.
Further is that the present invention is better achieved, and especially use following set-up modes: the step 2 includes following tools Body step:
2.1) it makes and partition and pipeline is installed:
Partition is designed and produced according to dewatering well hole diameter, also designs and produces two pipelines, one is short tube, and one is long tube;
2.2) partition and pipeline are put into:
It according to design height, is marked on pipeline, after the connection of one section of a section and checks, be put into dewatering well, by partition It is arranged at from dewatering well well head 2m, and partition and pipeline is welded together.
It is further for the present invention is better achieved, especially use following set-up modes: the bottom end of the short tube be located at every Plate top or the upper contact with partition.
Further is that the present invention is better achieved, and especially use following set-up modes: the bottom end of the long tube is placed in drop At 0.2 ~ 0.5m of well shaft bottom.
Further is that the present invention is better achieved, and especially uses following set-up modes: the step 3) specifically: will be special Fast type polymer repairing mortar, chance water do not disperse water blockoff grout material and are mixed according to the ratio of 0.9 ~ 1.1:0.45 ~ 0.55 It is even, pour into partition top, and it is closely knit fill to dewatering well well head, check whether meet the requirements after cured, satisfaction then enter under One procedure.
Further is that the present invention is better achieved, and especially uses following set-up modes: the step 4) specifically: will be special Kind of cement, waterglass, latex, micro-expanding agent, expansion type concrete by 0.8 ~ 1.2:0.9 ~ 1.2:0.04 ~ 0.06:0.01 ~ The ratio of 0.03:0.03 ~ 0.05 is mixed evenly, and pours into from long tube, until short tube flows out slurries.
Further is that the present invention is better achieved, and especially uses following set-up modes: the step 5) specifically:
After short tube flows out slurries, short tube is become into Grouting Pipe, connects grouter, long tube and short tube are in the milk simultaneously, control pressure (preferred control pressure is in 1.5 ~ 2.0MPa), makes slurries squeeze the periphery soil body, combines closely to form entirety with the soil body, Bu Nengchao Cross structure ability to bear.
Further is that the present invention is better achieved, and especially use following set-up modes: the step 6) includes following steps Rapid specific steps:
6.1) plugging grouting pipeline:
After the completion of grouting, grouting valve is closed, pipeline opening is blocked;
6.2) pipeline and brushing protective layer are cut
It is to be solidified to reach desired strength, and observe it is impermeable after, cut pipeline, and cut place external coating rubber coating protect Layer.
Further is that the present invention is better achieved, and especially uses following set-up modes: also wrapping before the step 1) Include preparation of construction step: specific aim works out arrangement and method for construction, and is audited, ratifies to complete;Detailed technology tells somebody what one's real intentions are, placing of material, labor Power prepares, tool preparation is both needed to meet the requirements.
Compared with prior art, the present invention have the following advantages that and the utility model has the advantages that
(1) present invention effectively solves long-term seepage problem after closure dewatering well, and with blocking, speed is fast, is not in seep after closure Regimen condition, there are also to surrounding soil reinforcement effect.
(2) effectively dewatering well antiseepage can be blocked using present invention construction gained dewatering well antiseepage plugging structure body and is tied It combines closely between structure and the soil body, avoids the occurrence of causing displacement, further energy when there is temperature or sedimentation variation The case where enough avoiding the occurrence of infiltration.
(3) present invention is formed by dewatering well antiseepage plugging structure and the reinforcement effect of building surrounding soil is better than passing System technique is formed by dewatering well, and the effect for stablizing surrounding ground is more excellent.
Detailed description of the invention
Fig. 1 is dewatering well antiseepage plugging structure body structural schematic diagram of the present invention.
Fig. 2 is dewatering well antiseepage plugging structure body cross-sectional view of the present invention.
Wherein, 1- dewatering well, 2- drainpipe, 3- grout pipe, 4- rigid material plugged zone, 5- partition, 6- grouting material envelope Blocking layer.
Specific embodiment
The present invention is described in further detail below with reference to embodiment, embodiments of the present invention are not limited thereto.
To keep the purposes, technical schemes and advantages of embodiment of the present invention clearer, implement below in conjunction with the present invention The technical solution in embodiment of the present invention is clearly and completely described in attached drawing in mode, it is clear that described reality The mode of applying is some embodiments of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ability Domain those of ordinary skill every other embodiment obtained without creative efforts, belongs to the present invention The range of protection.Therefore, the detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit below and is wanted The scope of the present invention of protection is sought, but is merely representative of selected embodiment of the invention.Based on the embodiment in the present invention, Every other embodiment obtained by those of ordinary skill in the art without making creative efforts belongs to this Invent the range of protection.
It is worth noting that: it is in this application, certain to need to be applied to techniques known or conventional technical means When, applicant there may be do not illustrate the well-known technique specifically in the text or/and conventional technical means be it is a kind of what Technological means, but cannot think the application not announce the technological means in text specifically and not meet Patent Law the 20th The case where six third item.
Embodiment 1:
The present invention designs hypogee dewatering well antiseepage plugging construction method, effectively solves infiltration for a long time after blocking dewatering well and asks Topic has closure speed fast, is not in infiltration situation after closure, there are also to surrounding soil reinforcement effect, especially uses following Set-up mode: include the following steps specific steps:
1) it determines closure site: determining closure site and clear up closure site periphery;
2) partition and line treatment: make and install partition and pipeline;
3) rigid material plugged zone blocks: rigid plugging material is perfused on the top of partition;
4) grouting material plugged zone blocks: grouting material is perfused in the lower part of partition;
5) it duct grouting: is in the milk to pipeline;
6) pipe plugging and post-processing: leak stopping is carried out to pipeline and cuts extra pipeline, brushing protective layer.
Embodiment 2:
The present embodiment is further optimized based on the above embodiments, and the ground of same technique scheme is used with previous embodiment Side will not be described in great detail, as shown in Figure 1 and Figure 2, further for the present invention is better achieved, and especially use following set-up modes: institute State step 1) specifically: dusting is removed to 1 periphery substrate surface of dewatering well, decortication tilts class defect, and by dust, oil removal Completely.
Embodiment 3:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the step 2 includes following specific steps:
2.1) it makes and partition 5 and pipeline is installed:
Partition 5 is designed and produced according to dewatering well hole diameter, also designs and produces two pipelines, one is short tube, and one is long tube;As It is preferable to provide scheme, production 5 size dimension of partition is designed according to 1 hole diameter of dewatering well, and duct length is set according to 1 depth of dewatering well Meter, short tube be drainpipe (preferred Design of length are as follows: enter well location and set to partition position, caliber: 32mm) 2, a root long pipe It (is combined using fastener connection type for grout pipe, length: enters well location and set from 0.2 ~ 0.5m high of shaft bottom, be preferably arranged to from well Bottom 300mm high, caliber: 32mm) 3;Preferably, partition 5 uses the steel plate of 4-6mm.
2.2) partition and pipeline are put into:
It according to design height, is marked on pipeline, after the connection of one section of a section and checks, be put into dewatering well 1, by partition 5 are arranged at from dewatering well well head 2m, and partition and pipeline are welded together;After being put into designated position, fixes and checks, It has been checked that, carry out subsequent processing.
Embodiment 4:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the bottom end of the short tube (drainpipe 2) is located at 5 top of partition or the upper contact with partition 5.
Embodiment 5:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the bottom end of the long tube (grout pipe 3) is placed at 0.2 ~ 0.5m of dewatering well shaft bottom, it is preferred that the bottom end of grout pipe 3 is from precipitation 1 shaft bottom 300mm of well.
Embodiment 6:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the step 3) specifically: special fast type polymer repairing mortar, chance water are not dispersed into water blockoff grout material according to 0.9 ~ 1.1: 0.45 ~ 0.55 ratio is mixed evenly, and pours into partition top, and it is closely knit fill to dewatering well well head, check after cured Whether meet the requirements, meets and then enter next process;
As preferred design scheme, rigid material is that special fast type polymer repairing mortar, chance water are not dispersed water blockoff grout material It is mixed evenly and obtains according to the ratio of 1:0.5, pour into 5 top of partition, it should be noted that pour into closely knit, cannot have cavity, fill To well head, rigid material plugged zone 4 is formed;It is to be solidified to reach desired strength (when preferably 80% or more), carry out next procedure.
Embodiment 7:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the step 4) specifically: by special cement (for example meeting the not distributed cement of water), waterglass, latex, micro-expanding agent, hair Alveolitoid concrete is mixed evenly in 0.8 ~ 1.2:0.9 ~ 1.2:0.04 ~ 0.06:0.01 ~ 0.03:0.03 ~ 0.05 ratio, It is poured into from long tube, until short tube flows out slurries;During pouring into, since grouting material is than water weight, bottom, water can be sunk to Top drainage hole excludes in meeting, therefore needs until drainpipe 2 flows out slurries;As preferred design scheme, special cement (for example meeting the not distributed cement of water), waterglass, latex, micro-expanding agent, expansion type concrete press 1:0.9:0.05:0.02: 0.05 ratio is mixed evenly.
Embodiment 8:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the step 5) specifically:
After short tube (drainpipe 2) flows out slurries, short tube (drainpipe 2) is become into Grouting Pipe, connects grouter, long tube (grout pipe 3) it is in the milk simultaneously with short tube (drainpipe 2), controls pressure (preferred control pressure is in 1.5 ~ 2.0MPa), slurries is made to squeeze week The side soil body, combines closely to form entirety with the soil body, no more than structure ability to bear.
Embodiment 9:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: the step 6) includes the following steps specific steps:
6.1) plugging grouting pipeline:
After the completion of grouting, grouting valve is closed, pipeline opening (pipeline opening of drainpipe 2 and grout pipe 3) is blocked;
6.2) pipeline and brushing protective layer are cut
It is to be solidified to reach desired strength, and observe it is impermeable after, cutting pipeline (flushed with the top of dewatering well 1 carry out drainpipe 2 With the cutting of grout pipe 3), and in cut place external coating rubber coating protective layer.
Embodiment 10:
The present embodiment is to advanced optimize based on any of the above embodiments, uses same technique scheme with previous embodiment Place will not be described in great detail, it is as shown in Figure 1 and Figure 2, further for the present invention is better achieved, especially use following setting sides Formula: further including preparation of construction step before the step 1): specific aim works out arrangement and method for construction, and (this arrangement and method for construction is according to each work The requirement of journey is different and different, and auditor cannot not should specifically disclose the arrangement and method for construction when examining, and think the invention Insufficient disclosure), and audited, ratify to complete;Detailed technology is told somebody what one's real intentions are, placing of material, labour prepares, tool preparation is both needed to accord with It closes and requires.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, it is all according to According to technical spirit any simple modification to the above embodiments of the invention, equivalent variations, protection of the invention is each fallen within Within the scope of.

Claims (10)

1. hypogee dewatering well antiseepage plugging construction method, it is characterised in that: include the following steps specific steps:
1) it determines closure site: determining closure site and clear up closure site periphery;
2) partition and line treatment: make and install partition and pipeline;
3) rigid material plugged zone blocks: rigid plugging material is perfused on the top of partition;
4) grouting material plugged zone blocks: grouting material is perfused in the lower part of partition;
5) it duct grouting: is in the milk to pipeline;
6) pipe plugging and post-processing: leak stopping is carried out to pipeline and cuts extra pipeline, brushing protective layer.
2. dewatering well antiseepage plugging construction method in hypogee according to claim 1, it is characterised in that: the step 1) Specifically: dusting, decortication tilting class defect are removed to dewatering well periphery substrate surface, and dust, oil removal is clean.
3. dewatering well antiseepage plugging construction method in hypogee according to claim 1 or 2, it is characterised in that: the step 2) rapid includes following specific steps:
2.1) it makes and partition and pipeline is installed:
Partition is designed and produced according to dewatering well hole diameter, also designs and produces two pipelines, one is short tube, and one is long tube;
2.2) partition and pipeline are put into:
It according to design height, is marked on pipeline, after the connection of one section of a section and checks, be put into dewatering well, by partition It is arranged at from dewatering well well head 2m, and partition and pipeline is welded together.
4. dewatering well antiseepage plugging construction method in hypogee according to claim 3, it is characterised in that: the short tube Bottom end is located above partition or the upper contact with partition.
5. dewatering well antiseepage plugging construction method in hypogee according to claim 3, it is characterised in that: the long tube Bottom end is placed at 0.2 ~ 0.5m of dewatering well shaft bottom.
6. dewatering well antiseepage plugging construction method in hypogee according to claim 3, it is characterised in that: the step 3) Specifically: special fast type polymer repairing mortar, chance water are not dispersed into water blockoff grout material according to the ratio of 0.9 ~ 1.1:0.45 ~ 0.55 Be mixed evenly, pour into partition top, and it is closely knit fill to dewatering well well head, check whether meet the requirements after cured, it is full It is sufficient then enter next process.
7. dewatering well antiseepage plugging construction method in hypogee according to claim 3, it is characterised in that: the step 4) Specifically: by special cement, waterglass, latex, micro-expanding agent, expansion type concrete by 0.8 ~ 1.2:0.9 ~ 1.2:0.04 ~ The ratio of 0.06:0.01 ~ 0.03:0.03 ~ 0.05 is mixed evenly, and pours into from long tube, until short tube flows out slurries.
8. dewatering well antiseepage plugging construction method in hypogee according to claim 7, it is characterised in that: the step 5) Specifically:
After short tube flows out slurries, short tube being become into Grouting Pipe, connects grouter, long tube and short tube are in the milk simultaneously, pressure is controlled, So that slurries is squeezed the periphery soil body, combines closely to form entirety with the soil body, no more than structure ability to bear.
9. the described in any item hypogee dewatering well antiseepage plugging construction methods of according to claim 1-2,4-8, feature exist In: the step 6) includes the following steps specific steps:
6.1) plugging grouting pipeline:
After the completion of grouting, grouting valve is closed, pipeline opening is blocked;
6.2) pipeline and brushing protective layer are cut
It is to be solidified to reach desired strength, and observe it is impermeable after, cut pipeline, and cut place external coating rubber coating protect Layer.
10. the described in any item hypogee dewatering well antiseepage plugging construction methods of according to claim 1-2,4-8, feature exist In: further include preparation of construction step before the step 1): specific aim works out arrangement and method for construction, and is audited, ratifies to complete;In detail It carefully confides a technological secret, placing of material, labour prepares, tool preparation is both needed to meet the requirements.
CN201910429045.3A 2019-05-22 2019-05-22 Hypogee dewatering well antiseepage plugging construction method Pending CN110144918A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910429045.3A CN110144918A (en) 2019-05-22 2019-05-22 Hypogee dewatering well antiseepage plugging construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910429045.3A CN110144918A (en) 2019-05-22 2019-05-22 Hypogee dewatering well antiseepage plugging construction method

Publications (1)

Publication Number Publication Date
CN110144918A true CN110144918A (en) 2019-08-20

Family

ID=67592604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910429045.3A Pending CN110144918A (en) 2019-05-22 2019-05-22 Hypogee dewatering well antiseepage plugging construction method

Country Status (1)

Country Link
CN (1) CN110144918A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457828A (en) * 2022-01-24 2022-05-10 北京城建设计发展集团股份有限公司 Construction method of open cut fabricated underground structure foundation pit dewatering well
CN117431985A (en) * 2023-12-21 2024-01-23 上海建工二建集团有限公司 Underground diaphragm wall door type emergency plugging device and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201326176Y (en) * 2008-12-15 2009-10-14 上海市第二建筑有限公司 Deep foundation pit dewatering retention well
CN108166517A (en) * 2018-02-10 2018-06-15 中国建筑第五工程局有限公司 For the shut-in well method and well-sealing device of superelevation floor height hydraulic pressure dewatering well of deep well
CN210194655U (en) * 2019-05-22 2020-03-27 四川童燊防水工程有限公司 Seepage-proofing plugging reinforcing structure for dewatering well of underground building

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201326176Y (en) * 2008-12-15 2009-10-14 上海市第二建筑有限公司 Deep foundation pit dewatering retention well
CN108166517A (en) * 2018-02-10 2018-06-15 中国建筑第五工程局有限公司 For the shut-in well method and well-sealing device of superelevation floor height hydraulic pressure dewatering well of deep well
CN210194655U (en) * 2019-05-22 2020-03-27 四川童燊防水工程有限公司 Seepage-proofing plugging reinforcing structure for dewatering well of underground building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王铁记: "奥灰特大突水灾害快速治理技术—峰峰矿区实例研究", 冶金工业出版社, pages: 49 - 54 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457828A (en) * 2022-01-24 2022-05-10 北京城建设计发展集团股份有限公司 Construction method of open cut fabricated underground structure foundation pit dewatering well
CN114457828B (en) * 2022-01-24 2024-02-23 北京城建设计发展集团股份有限公司 Construction method for open cut assembled underground structure foundation pit dewatering well
CN117431985A (en) * 2023-12-21 2024-01-23 上海建工二建集团有限公司 Underground diaphragm wall door type emergency plugging device and method
CN117431985B (en) * 2023-12-21 2024-03-15 上海建工二建集团有限公司 Underground diaphragm wall door type emergency plugging device and method

Similar Documents

Publication Publication Date Title
CN103215960B (en) Grouting method for high polymer vertical support system
CN204530732U (en) A kind of structure of the precipitation based on basement elevator shaft plash
CN106948340B (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN104762955B (en) A kind of Belled Pile construction method based on freezing process
CN202787329U (en) Large leakage treatment structure for underground continuous wall
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN107217676A (en) A kind of steel cylinder with seal groove and occlusion structure or steel sheet pile and steel construction diaphragm wall
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN109797769A (en) A kind of Collapsible Loess District underground pipe gallery foundation structure and its construction method
CN106759133A (en) The mixing structure of dam type and construction method of a kind of homogeneous earth and rockfill dam and rock
CN109024706A (en) A kind of foundation pit waterproof curtain breakthrough inside method for blocking
CN112144559A (en) Well construction method in high water-rich loess sandy gravel stratum transformer tube well
CN110144918A (en) Hypogee dewatering well antiseepage plugging construction method
CN206428707U (en) A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
CN107587502A (en) A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method
CN107687175A (en) The vertical antifouling isolation wall construction of both sides ground local stiffening type and method
CN207862925U (en) A kind of slip casting casing device
CN104963693B (en) Rectangular parallel push pipe connection channel construction method
CN207659986U (en) A kind of building or structures foundation stabilization underpin pier
CN111424695B (en) Seepage-proofing and leakage-stopping method for deep-buried karst pipeline
CN101586341B (en) Water sealing method for civil engineering groundwork
CN107653889A (en) A kind of shaped steel pressure is poured water the construction method of soil curtain support pile
CN202108045U (en) Sleeve pipe with anchor rod penetrating through underground continuous wall
CN209011169U (en) A kind of experimental rig for simulating underground engineering impervious blocking material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination