CN110144918A - Construction method of anti-seepage and plugging of underground building dewatering well - Google Patents

Construction method of anti-seepage and plugging of underground building dewatering well Download PDF

Info

Publication number
CN110144918A
CN110144918A CN201910429045.3A CN201910429045A CN110144918A CN 110144918 A CN110144918 A CN 110144918A CN 201910429045 A CN201910429045 A CN 201910429045A CN 110144918 A CN110144918 A CN 110144918A
Authority
CN
China
Prior art keywords
plugging
pipe
seepage
grouting
partition
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910429045.3A
Other languages
Chinese (zh)
Inventor
易启洪
丁力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Tongshen Waterproofing Engineering Co Ltd
Original Assignee
Sichuan Tongshen Waterproofing Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Tongshen Waterproofing Engineering Co Ltd filed Critical Sichuan Tongshen Waterproofing Engineering Co Ltd
Priority to CN201910429045.3A priority Critical patent/CN110144918A/en
Publication of CN110144918A publication Critical patent/CN110144918A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • E21B33/14Methods or devices for cementing, for plugging holes, crevices or the like for cementing casings into boreholes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Civil Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了地下建筑降水井防渗封堵施工方法,包括下述步骤具体步骤:1)确定封堵部位:确定封堵部位并清理封堵部位周边;2)隔板及管道处理:制作并安装隔板及管道;3)刚性材料封堵层封堵:在隔板的上部灌注刚性堵漏材料;4)灌浆材料封堵层封堵:在隔板的下部灌注灌浆材料;5)管道灌浆:对管道进行灌浆;6)管道封堵及后处理:对管道进行堵漏并切割多余管道、涂刷保护层;有效解决封堵降水井后长期渗水问题,具有封堵速度快,封堵后不会出现渗水情况,还有对周围土体加固作用。

The invention discloses an anti-seepage and plugging construction method for underground building dewatering wells, comprising the following specific steps: 1) determining the plugging location: determining the plugging location and cleaning the periphery of the plugging location; 2) processing partitions and pipelines: making and Install partitions and pipes; 3) Rigid material plugging layer plugging: pour rigid plugging material on the upper part of the partition; 4) Grouting material plugging layer plugging: pour grouting material on the lower part of the partition; 5) Pipeline grouting : Grouting the pipeline; 6) Plugging and post-treatment of the pipeline: Plugging the pipeline, cutting the redundant pipeline, and painting the protective layer; effectively solving the problem of long-term water seepage after blocking the dewatering well, with fast plugging speed, after plugging There will be no water seepage, and it will also reinforce the surrounding soil.

Description

地下建筑降水井防渗封堵施工方法Construction method of anti-seepage and plugging of underground building dewatering well

技术领域technical field

本发明涉及地下建筑防水堵漏及加固技术领域,具体的说,是地下建筑降水井防渗封堵施工方法。The invention relates to the technical field of waterproof plugging and reinforcement of underground buildings, in particular to a construction method for seepage prevention and plugging of underground building dewatering wells.

背景技术Background technique

地下室是指房间地面低于室外地平面的高度超过该房间净高的二分之一。多层和高层建筑物需要较深的基础,为利用这一高度,在建筑物底层下建造地下室,既可增加使用面积,又可省去房心回填土,还算比较经济。在房屋底层以下建造地下室,可以提高建筑用地效率。一些高层建筑基地埋深很大,充分利用这一深度来建造地下室,其经济效果和使用效果俱佳。地下室的按功能分,有普通地下室和放空地下室;按结构材料分,有砖墙结构和混凝土结构地下室,按构造形式分,有全地下室和半地下室。The basement refers to the height of the room floor below the outdoor ground level exceeding half of the clear height of the room. Multi-storey and high-rise buildings need a deep foundation. In order to utilize this height, a basement is built under the bottom of the building, which can increase the usable area and save the backfilling of the house core, which is relatively economical. Building a basement below the ground floor of a house can improve the efficiency of building land use. Some high-rise building bases are deeply buried, and making full use of this depth to build basements has good economic and use effects. According to the function, the basement has ordinary basement and empty basement; according to the structural material, there are brick wall structure and concrete structure basement; according to the structural form, there are full basement and semi-basement.

降水井用于地下水位比较高的施工环境中,是土方工程、地基与基础工程施工中的一项重要技术措施,能疏干基土中的水分、促使土体固结,提高地基强度,同时可以减少土坡土体侧向位移与沉降,稳定边坡,消除流砂,减少基底土的隆起,使位于天然地下水以下的地基与基础工程施工能避免地下水的影响,提供比较干的施工条件,还可以减少土方量、缩短工期、提高工程质量和保证施工安全。The dewatering well is used in the construction environment with relatively high groundwater level. It is an important technical measure in the construction of earthwork, foundation and foundation engineering. It can drain the water in the foundation soil, promote the consolidation of the soil, and improve the strength of the foundation. It can reduce the lateral displacement and settlement of the slope soil, stabilize the slope, eliminate quicksand, reduce the uplift of the base soil, so that the foundation and foundation engineering construction below the natural groundwater can avoid the influence of groundwater, provide relatively dry construction conditions, and It can reduce the amount of earthwork, shorten the construction period, improve the quality of the project and ensure the safety of construction.

现有地下建筑降水井封堵技术的施工工艺主要分为下述两种:The construction technology of existing underground building dewatering well plugging technology is mainly divided into following two kinds:

一、降水井抽水降水后,立即灌入混凝土强制封堵。1. After the dewatering well is pumped and dewatered, concrete is immediately poured into it for forced sealing.

二、往降水井里倒入碎石,再灌混凝土封堵。2. Pour gravel into the dewatering well, and then pour concrete to seal it.

但是现有技术却存在如下问题:However, the prior art has the following problems:

1.封堵时间过长。1. The blocking time is too long.

2.混凝土与土体之间不能紧密结合,温度和沉降变化容易造成位移,导致渗水。2. The concrete and the soil cannot be tightly combined, and changes in temperature and settlement can easily cause displacement and water seepage.

3.长久时间封堵,边缘存在渗水情况,发生渗水后期处理施工复杂,施工难度大,费用高。3. It has been blocked for a long time, and there is water seepage at the edge. The post-treatment construction of water seepage is complicated, difficult and expensive.

发明内容Contents of the invention

本发明的目的在于提供地下建筑降水井防渗封堵施工方法,有效解决封堵降水井后长期渗水问题,具有封堵速度快,封堵后不会出现渗水情况,还有对周围土体加固作用。The purpose of the present invention is to provide an anti-seepage and plugging construction method for underground building dewatering wells, which can effectively solve the problem of long-term water seepage after the dewatering well is blocked. effect.

本发明通过下述技术方案实现:地下建筑降水井防渗封堵施工方法,包括下述步骤具体步骤:The present invention is realized through the following technical solutions: the construction method for anti-seepage and plugging of underground building dewatering wells, comprising the following specific steps:

1)确定封堵部位:确定封堵部位并清理封堵部位周边;1) Determine the blockage site: determine the blockage site and clean up the surrounding areas of the blockage site;

2)隔板及管道处理:制作并安装隔板及管道;2) Partition and pipeline treatment: make and install partitions and pipes;

3)刚性材料封堵层封堵:在隔板的上部灌注刚性堵漏材料;3) Rigid material plugging layer plugging: pour rigid plugging material on the upper part of the partition;

4)灌浆材料封堵层封堵:在隔板的下部灌注灌浆材料;4) Grouting material plugging layer plugging: grouting material is poured into the lower part of the partition;

5)管道灌浆:对管道进行灌浆;5) Pipe grouting: grouting the pipes;

6)管道封堵及后处理:对管道进行堵漏并切割多余管道、涂刷保护层。6) Pipeline plugging and post-processing: plugging the pipeline, cutting excess pipes, and painting the protective layer.

进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤1)具体为:对降水井周边基层表面除去起砂、脱皮翘起类缺陷,并将灰尘、油污清除干净。Further, in order to better realize the present invention, the following setting method is adopted in particular: the step 1) is specifically: remove sanding, peeling and warping defects on the surface of the base layer around the dewatering well, and clean up dust and oil stains.

进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤2)包括下述具体步骤:Further, in order to better realize the present invention, the following setting method is adopted in particular: the step 2) includes the following specific steps:

2.1)制作及安装隔板和管道:2.1) Fabrication and installation of partitions and pipes:

根据降水井井径设计制作隔板,亦设计制作两条管道,一条为短管,一条为长管;According to the design and manufacture of the partition plate according to the diameter of the precipitation well, two pipes are also designed and manufactured, one is a short pipe and the other is a long pipe;

2.2)放入隔板及管道:2.2) Put in the clapboard and pipe:

根据设计高度,在管道上做好标记,一节一节连接后并检查好,放入降水井中,将隔板设置在离降水井井口2m处,并将隔板与管道焊接在一起。According to the design height, mark the pipes, connect and check each section, put them into the dewatering well, set the partition at 2m from the head of the dewatering well, and weld the partition and the pipe together.

进一步的为更好地实现本发明,特别采用下述设置方式:所述短管的底端位于隔板上方或与隔板的上部接触。Further, in order to better realize the present invention, the following arrangement is particularly adopted: the bottom end of the short tube is located above the partition or in contact with the upper part of the partition.

进一步的为更好地实现本发明,特别采用下述设置方式:所述长管的底端置于降水井井底0.2~0.5m处。Further, in order to better realize the present invention, the following setting method is adopted in particular: the bottom end of the long pipe is placed at the bottom of the dewatering well at 0.2-0.5m.

进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤3)具体为:将特快型聚合物抢修砂浆、遇水不分散堵水注浆料按照0.9~1.1:0.45~0.55的比例混合搅拌均匀,灌入隔板上部,并密实灌满至降水井井口,待固化后检查是否满足要求,满足则进入下一道工序。Further, in order to better realize the present invention, the following setting method is adopted in particular: the step 3) is specifically: the super-fast polymer emergency repair mortar and the water-blocking grout that does not disperse in contact with water are adjusted according to the ratio of 0.9 to 1.1: 0.45 to 0.55 The ratio is mixed and stirred evenly, poured into the upper part of the partition, and densely filled to the head of the dewatering well. After curing, check whether it meets the requirements, and then enter the next process.

进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤4)具体为:将特种水泥、水玻璃、乳胶、微膨胀剂、发泡型混凝土按0.8~1.2:0.9~1.2:0.04~0.06:0.01~0.03:0.03~0.05的比例混合搅拌均匀,从长管灌入,直至短管流出浆液为止。Further, in order to better realize the present invention, the following setting method is particularly adopted: the step 4) is specifically: the special cement, water glass, latex, micro-expansion agent, and foamed concrete are mixed according to the ratio of 0.8~1.2: 0.9~1.2 : 0.04~0.06: 0.01~0.03: 0.03~0.05 The ratio is mixed and stirred evenly, poured from the long pipe until the slurry flows out of the short pipe.

进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤5)具体为:Further, in order to better realize the present invention, the following setting method is adopted in particular: the step 5) is specifically:

短管流出浆液后,将短管变为注浆管,接上灌浆机,长管和短管同时灌浆,控制好压力(优选的控制压力在1.5~2.0MPa),使浆液挤压周边土体,与土体紧密结合形成整体,不能超过结构承受能力。After the grout flows out of the short pipe, turn the short pipe into a grouting pipe, connect the grouting machine, grout the long pipe and the short pipe at the same time, and control the pressure (the preferred control pressure is 1.5~2.0MPa), so that the grout squeezes the surrounding soil , closely combined with the soil to form a whole, and cannot exceed the structural bearing capacity.

进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤6)包括下述步骤具体步骤:Further, in order to better realize the present invention, the following setting method is adopted in particular: the step 6) includes the following specific steps:

6.1)封堵灌浆管道:6.1) Plugging grouting pipes:

灌浆完成后,关闭灌浆阀门,对管道口进行封堵;After the grouting is completed, close the grouting valve and seal the pipe opening;

6.2)切割管道及涂刷保护层6.2) Cut the pipe and paint the protective layer

待固化达到要求强度,并观察不渗水后,切割管道,并在切割处表面涂刷橡胶涂料保护层。After curing reaches the required strength and observes that there is no water seepage, cut the pipe and apply a protective layer of rubber paint on the surface of the cut.

进一步的为更好地实现本发明,特别采用下述设置方式:在所述步骤1)之前还包括施工准备步骤:针对性编制施工方案,并经审核、批准完成;详细技术交底、材料堆放、劳动力准备、工具准备均需符合要求。Further, in order to better realize the present invention, the following setting method is specially adopted: before the step 1), the construction preparation step is also included: the construction plan is compiled in a targeted manner, and it is completed after review and approval; detailed technical disclosure, material stacking, Labor preparation and tool preparation must meet the requirements.

本发明与现有技术相比,具有以下优点及有益效果:Compared with the prior art, the present invention has the following advantages and beneficial effects:

(1)本发明有效解决封堵降水井后长期渗水问题,具有封堵速度快,封堵后不会出现渗水情况,还有对周围土体加固作用。(1) The present invention effectively solves the problem of long-term water seepage after blocking the dewatering well, has the advantages of fast blocking speed, no water seepage after sealing, and has the effect of reinforcing the surrounding soil.

(2)利用本发明施工所得降水井防渗封堵结构体能够有效的将降水井防渗封堵结构与土体之间紧密结合,避免当出现温度或沉降变化时造成移位情况的发生,进一步的能够避免出现渗水的情况。(2) The anti-seepage and plugging structure of the dewatering well obtained by the construction of the present invention can effectively combine the anti-seepage and sealing structure of the dewatering well with the soil body, avoiding the occurrence of displacement when there is a change in temperature or settlement, Further, water seepage can be avoided.

(3)本发明所形成的降水井防渗封堵结构对于建筑物周围土体的加固作用优于传统工艺所形成的降水井,且稳定周围地基的效果更优。(3) The anti-seepage and plugging structure of the dewatering well formed by the present invention has a better effect on the reinforcement of the soil around the building than the dewatering well formed by the traditional process, and the effect of stabilizing the surrounding foundation is better.

附图说明Description of drawings

图1为本发明所述降水井防渗封堵结构体结构示意图。Fig. 1 is a schematic diagram of the anti-seepage and plugging structure of the dewatering well according to the present invention.

图2为本发明所述降水井防渗封堵结构体剖视图。Fig. 2 is a cross-sectional view of the anti-seepage and plugging structure of the dewatering well according to the present invention.

其中,1-降水井、2-排水管、3-灌浆管、4-刚性材料封堵层、5-隔板、6-灌浆材料封堵层。Among them, 1-dewatering well, 2-drainage pipe, 3-grouting pipe, 4-rigid material sealing layer, 5-partition plate, 6-grouting material sealing layer.

具体实施方式Detailed ways

下面结合实施例对本发明作进一步地详细说明,但本发明的实施方式不限于此。The present invention will be further described in detail below in conjunction with examples, but the embodiments of the present invention are not limited thereto.

为使本发明实施方式的目的、技术方案和优点更加清楚,下面将结合本发明实施方式中的附图,对本发明实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式是本发明一部分实施方式,而不是全部的实施方式。基于本发明中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。因此,以下对在附图中提供的本发明的实施方式的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施方式。基于本发明中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments It is some embodiments of the present invention, but not all of them. Based on the implementation manners in the present invention, all other implementation manners obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention. Accordingly, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the invention. Based on the implementation manners in the present invention, all other implementation manners obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.

值得注意的是:在本申请中,某些需要应用到本领域的公知技术或常规技术手段时,申请人可能存在没有在文中具体的阐述该公知技术或/和常规技术手段是一种什么样的技术手段,但不能以文中没有具体公布该技术手段,而认为本申请不符合专利法第二十六条第三款的情况。It is worth noting that: in this application, when certain known technologies or conventional technical means need to be applied to this field, the applicant may have not specifically stated in the text what kind of known technology or/and conventional technical means are. However, it cannot be considered that the application does not comply with the third paragraph of Article 26 of the Patent Law because the technical means are not specifically disclosed in the text.

实施例1:Example 1:

本发明设计出地下建筑降水井防渗封堵施工方法,有效解决封堵降水井后长期渗水问题,具有封堵速度快,封堵后不会出现渗水情况,还有对周围土体加固作用,特别采用下述设置方式:包括下述步骤具体步骤:The invention designs an anti-seepage and plugging construction method for underground building dewatering wells, which effectively solves the long-term water seepage problem after the dewatering well is blocked, has the advantages of fast sealing speed, no water seepage after sealing, and has the effect of reinforcing the surrounding soil. In particular, the following setting method is adopted: including the following specific steps:

1)确定封堵部位:确定封堵部位并清理封堵部位周边;1) Determine the blockage site: determine the blockage site and clean up the surrounding areas of the blockage site;

2)隔板及管道处理:制作并安装隔板及管道;2) Partition and pipeline treatment: make and install partitions and pipes;

3)刚性材料封堵层封堵:在隔板的上部灌注刚性堵漏材料;3) Rigid material plugging layer plugging: pour rigid plugging material on the upper part of the partition;

4)灌浆材料封堵层封堵:在隔板的下部灌注灌浆材料;4) Grouting material plugging layer plugging: grouting material is poured into the lower part of the partition;

5)管道灌浆:对管道进行灌浆;5) Pipe grouting: grouting the pipes;

6)管道封堵及后处理:对管道进行堵漏并切割多余管道、涂刷保护层。6) Pipeline plugging and post-processing: plugging the pipeline, cutting excess pipes, and painting the protective layer.

实施例2:Example 2:

本实施例是在上述实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤1)具体为:对降水井1周边基层表面除去起砂、脱皮翘起类缺陷,并将灰尘、油污清除干净。This embodiment is further optimized on the basis of the above-mentioned embodiment, and the place where the same technical solution is used in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, especially adopt The following setting method: the step 1) is specifically: remove sanding, peeling and warping defects on the surface of the base layer around the dewatering well 1, and clean up the dust and oil.

实施例3:Example 3:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤2)包括下述具体步骤:This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: the step 2) includes the following specific steps:

2.1)制作及安装隔板5和管道:2.1) Fabrication and installation of partitions 5 and pipes:

根据降水井井径设计制作隔板5,亦设计制作两条管道,一条为短管,一条为长管;作为优选的设置方案,制作隔板5大小尺寸根据降水井1井径设计,管道长度根据降水井1深度设计,一根短管为排水管(优选的长度设计为:入井位置至隔板位置,管径:32mm)2,一根长管为灌浆管(采用扣件连接方式组合,其长度:入井位置离井底0.2~0.5m高,优选设置为离井底300mm高,管径:32mm)3;优选的,隔板5采用4-6mm的钢板。According to the well diameter of the dewatering well, the dividing plate 5 is designed and manufactured, and two pipelines are also designed and manufactured, one is a short pipe, and the other is a long pipe; as a preferred setting scheme, the size of the dividing plate 5 is designed according to the well diameter of the dewatering well 1, and the length of the pipeline is According to the design of the depth of the dewatering well 1, a short pipe is a drainage pipe (the preferred length is designed from the position of entering the well to the position of the partition, pipe diameter: 32mm) 2, and a long pipe is a grouting pipe (combined by fasteners, Its length: the position of entering the well is 0.2-0.5m high from the bottom of the well, preferably set at a height of 300mm from the bottom of the well, pipe diameter: 32mm) 3; preferably, the partition 5 is made of a steel plate of 4-6mm.

2.2)放入隔板及管道:2.2) Put in the clapboard and pipe:

根据设计高度,在管道上做好标记,一节一节连接后并检查好,放入降水井1中,将隔板5设置在离降水井井口2m处,并将隔板与管道焊接在一起;放入指定位置后,固定好并检查,检查完成,进行下一工序。According to the design height, mark the pipes, connect and check each section, put it into the dewatering well 1, set the partition 5 at 2m from the wellhead of the dewatering well, and weld the partition and the pipe together ; After putting it into the designated position, fix it and check it. After the inspection is completed, proceed to the next process.

实施例4:Example 4:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述短管(排水管2)的底端位于隔板5上方或与隔板5的上部接触。This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following arrangement is adopted: the bottom end of the short pipe (drainage pipe 2 ) is located above the partition 5 or in contact with the upper part of the partition 5 .

实施例5:Example 5:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述长管(灌浆管3)的底端置于降水井井底0.2~0.5m处,优选的,灌浆管3的底端离降水井1井底300mm。This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: the bottom end of the long pipe (grouting pipe 3 ) is placed at the bottom of the dewatering well at 0.2-0.5 m, preferably, the bottom end of the grouting pipe 3 is 300 mm away from the bottom of the dewatering well 1 .

实施例6:Embodiment 6:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤3)具体为:将特快型聚合物抢修砂浆、遇水不分散堵水注浆料按照0.9~1.1:0.45~0.55的比例混合搅拌均匀,灌入隔板上部,并密实灌满至降水井井口,待固化后检查是否满足要求,满足则进入下一道工序;This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: the step 3) is specifically: mix and stir the express polymer emergency repair mortar and the non-dispersible water plugging grout according to the ratio of 0.9~1.1:0.45~0.55, and pour them into the partition The upper part shall be densely filled to the head of the dewatering well. After solidification, check whether it meets the requirements, and if it is satisfied, enter the next process;

作为优选的设计方案,刚性材料是将特快型聚合物抢修砂浆、遇水不分散堵水注浆料按照1:0.5的比例混合搅拌均匀而得,灌入隔板5上部,要注意灌入密实,不能有空洞,灌满至井口,形成刚性材料封堵层4;待固化达到要求强度(优选为80%以上时),进行下道工序。As a preferred design scheme, the rigid material is obtained by mixing and stirring the express-type polymer emergency repair mortar and the non-dispersible water blocking grout according to the ratio of 1:0.5, pouring it into the upper part of the partition 5, and paying attention to the dense filling , there should be no cavities, and it should be filled to the wellhead to form a rigid material plugging layer 4; when the solidification reaches the required strength (preferably above 80%), proceed to the next process.

实施例7:Embodiment 7:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤4)具体为:将特种水泥(比如遇水不分散型水泥)、水玻璃、乳胶、微膨胀剂、发泡型混凝土按0.8~1.2:0.9~1.2:0.04~0.06:0.01~0.03:0.03~0.05的比例混合搅拌均匀,从长管灌入,直至短管流出浆液为止;在灌入的过程中,由于灌浆料比水重,会沉入底部,水会中上方排水孔排除,因此需直至排水管2流出浆液为止;作为优选的设计方案,特种水泥(比如遇水不分散型水泥)、水玻璃、乳胶、微膨胀剂、发泡型混凝土按1:0.9:0.05:0.02:0.05的比例混合搅拌均匀。This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: the step 4) is specifically as follows: special cement (such as water-indispersible cement), water glass, latex, micro-expansion agent, and foamed concrete are divided into 0.8~1.2: 0.9~1.2: 0.04~0.06: 0.01~0.03: 0.03~0.05 The ratio is mixed and stirred evenly, and poured from the long pipe until the short pipe flows out of the slurry; during the pouring process, because the grouting material is heavier than water, it will sink to the bottom, and the water will The drainage hole in the middle and upper part is removed, so it needs to wait until the slurry flows out of the drain pipe 2; as a preferred design scheme, special cement (such as water non-dispersible cement), water glass, latex, micro-expansion agent, and foamed concrete press 1 : 0.9: 0.05: 0.02: 0.05 ratio mixing and stirring.

实施例8:Embodiment 8:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤5)具体为:This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: the step 5) is specifically:

短管(排水管2)流出浆液后,将短管(排水管2)变为注浆管,接上灌浆机,长管(灌浆管3)和短管(排水管2)同时灌浆,控制好压力(优选的控制压力在1.5~2.0MPa),使浆液挤压周边土体,与土体紧密结合形成整体,不能超过结构承受能力。After the short pipe (drainage pipe 2) flows out the grout, change the short pipe (drainage pipe 2) into a grouting pipe, connect the grouting machine, and grout the long pipe (grouting pipe 3) and the short pipe (drainage pipe 2) at the same time, and control it well The pressure (the preferred control pressure is 1.5~2.0MPa) makes the grout squeeze the surrounding soil and combine closely with the soil to form a whole, which cannot exceed the structural bearing capacity.

实施例9:Embodiment 9:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:所述步骤6)包括下述步骤具体步骤:This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: the step 6) includes the following specific steps:

6.1)封堵灌浆管道:6.1) Plugging grouting pipes:

灌浆完成后,关闭灌浆阀门,对管道口(排水管2和灌浆管3的管道口)进行封堵;After the grouting is completed, close the grouting valve and seal the pipe opening (the pipe opening of the drain pipe 2 and the grouting pipe 3);

6.2)切割管道及涂刷保护层6.2) Cut the pipe and paint the protective layer

待固化达到要求强度,并观察不渗水后,切割管道(与降水井1的顶部齐平进行排水管2和灌浆管3的切割),并在切割处表面涂刷橡胶涂料保护层。After the curing reaches the required strength and no water seepage is observed, cut the pipe (cutting the drainage pipe 2 and the grouting pipe 3 flush with the top of the dewatering well 1), and paint a protective layer of rubber paint on the surface of the cut.

实施例10:Example 10:

本实施例是在上述任一实施例的基础上进一步优化,与前述实施例采用相同技术方案的地方将不再赘述,如图1、图2所示,进一步的为更好地实现本发明,特别采用下述设置方式:在所述步骤1)之前还包括施工准备步骤:针对性编制施工方案(此施工方案根据各个工程的要求不同而不同,审查员在审查时,不能应没有具体的公开该施工方案,而认为该发明公开不充分),并经审核、批准完成;详细技术交底、材料堆放、劳动力准备、工具准备均需符合要求。This embodiment is further optimized on the basis of any of the above-mentioned embodiments, and the place where the same technical solution is adopted in the previous embodiment will not be repeated, as shown in Figure 1 and Figure 2, further to better realize the present invention, In particular, the following setting method is adopted: before the above step 1), there is also a construction preparation step: targeted preparation of the construction plan (this construction plan varies according to the requirements of each project, and the examiner should not disclose it without specific disclosure during the review) The construction plan, but it is considered that the disclosure of the invention is not sufficient), and has been reviewed and approved for completion; detailed technical disclosure, material stacking, labor preparation, and tool preparation must meet the requirements.

以上所述,仅是本发明的较佳实施例,并非对本发明做任何形式上的限制,凡是依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化,均落入本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention in any form. Any simple modifications and equivalent changes made to the above embodiments according to the technical essence of the present invention all fall within the scope of the present invention. within the scope of protection.

Claims (10)

1.地下建筑降水井防渗封堵施工方法,其特征在于:包括下述步骤具体步骤:1. The anti-seepage and plugging construction method of underground building dewatering wells is characterized in that: it comprises the following specific steps: 1)确定封堵部位:确定封堵部位并清理封堵部位周边;1) Determine the blockage site: determine the blockage site and clean up the surrounding areas of the blockage site; 2)隔板及管道处理:制作并安装隔板及管道;2) Partition and pipeline treatment: make and install partitions and pipes; 3)刚性材料封堵层封堵:在隔板的上部灌注刚性堵漏材料;3) Rigid material plugging layer plugging: pour rigid plugging material on the upper part of the partition; 4)灌浆材料封堵层封堵:在隔板的下部灌注灌浆材料;4) Grouting material plugging layer plugging: grouting material is poured into the lower part of the partition; 5)管道灌浆:对管道进行灌浆;5) Pipe grouting: grouting the pipes; 6)管道封堵及后处理:对管道进行堵漏并切割多余管道、涂刷保护层。6) Pipeline plugging and post-processing: plugging the pipeline, cutting excess pipes, and painting the protective layer. 2.根据权利要求1所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述步骤1)具体为:对降水井周边基层表面除去起砂、脱皮翘起类缺陷,并将灰尘、油污清除干净。2. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 1, characterized in that: said step 1) is specifically: remove sanding, peeling and warping defects on the surface of the base layer around the dewatering well, and place Dust and oil stains are removed. 3.根据权利要求1或2所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述步骤2)包括下述具体步骤:3. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 1 or 2, characterized in that: said step 2) includes the following specific steps: 2.1)制作及安装隔板和管道:2.1) Fabrication and installation of partitions and pipes: 根据降水井井径设计制作隔板,亦设计制作两条管道,一条为短管,一条为长管;According to the design and manufacture of the partition plate according to the diameter of the precipitation well, two pipes are also designed and manufactured, one is a short pipe and the other is a long pipe; 2.2)放入隔板及管道:2.2) Put in the clapboard and pipe: 根据设计高度,在管道上做好标记,一节一节连接后并检查好,放入降水井中,将隔板设置在离降水井井口2m处,并将隔板与管道焊接在一起。According to the design height, mark the pipes, connect and check each section, put them into the dewatering well, set the partition at 2m from the head of the dewatering well, and weld the partition and the pipe together. 4.根据权利要求3所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述短管的底端位于隔板上方或与隔板的上部接触。4. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 3, characterized in that: the bottom end of the short pipe is located above the partition or in contact with the upper part of the partition. 5.根据权利要求3所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述长管的底端置于降水井井底0.2~0.5m处。5. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 3, characterized in that: the bottom end of the long pipe is placed at 0.2-0.5m from the bottom of the dewatering well. 6.根据权利要求3所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述步骤3)具体为:将特快型聚合物抢修砂浆、遇水不分散堵水注浆料按照0.9~1.1:0.45~0.55的比例混合搅拌均匀,灌入隔板上部,并密实灌满至降水井井口,待固化后检查是否满足要求,满足则进入下一道工序。6. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 3, characterized in that: said step 3) is specifically: injecting express polymer emergency repair mortar and non-dispersible water plugging grout according to The ratio of 0.9~1.1:0.45~0.55 is mixed and stirred evenly, poured into the upper part of the partition, and densely filled to the head of the dewatering well. After curing, check whether it meets the requirements, and then enter the next process. 7.根据权利要求3所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述步骤4)具体为:将特种水泥、水玻璃、乳胶、微膨胀剂、发泡型混凝土按0.8~1.2:0.9~1.2:0.04~0.06:0.01~0.03:0.03~0.05的比例混合搅拌均匀,从长管灌入,直至短管流出浆液为止。7. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 3, characterized in that: said step 4) is specifically: special cement, water glass, latex, micro-expansive agent, and foamed concrete are pressed The ratio of 0.8~1.2: 0.9~1.2: 0.04~0.06: 0.01~0.03: 0.03~0.05 is mixed and stirred evenly, poured from the long pipe until the slurry flows out of the short pipe. 8.根据权利要求7所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述步骤5)具体为:8. The anti-seepage and plugging construction method for underground building dewatering wells according to claim 7, characterized in that: the step 5) is specifically: 短管流出浆液后,将短管变为注浆管,接上灌浆机,长管和短管同时灌浆,控制好压力,使浆液挤压周边土体,与土体紧密结合形成整体,不能超过结构承受能力。After the grout flows out of the short pipe, turn the short pipe into a grouting pipe, connect the grouting machine, grout the long pipe and the short pipe at the same time, and control the pressure so that the grout squeezes the surrounding soil and tightly combines with the soil to form a whole. Structural bearing capacity. 9.根据权利要求1-2,4-8任一项所述的地下建筑降水井防渗封堵施工方法,其特征在于:所述步骤6)包括下述步骤具体步骤:9. According to any one of claims 1-2, 4-8, the anti-seepage and plugging construction method of underground building dewatering wells is characterized in that: the step 6) includes the following specific steps: 6.1)封堵灌浆管道:6.1) Plugging grouting pipes: 灌浆完成后,关闭灌浆阀门,对管道口进行封堵;After the grouting is completed, close the grouting valve and seal the pipe opening; 6.2)切割管道及涂刷保护层6.2) Cut the pipe and paint the protective layer 待固化达到要求强度,并观察不渗水后,切割管道,并在切割处表面涂刷橡胶涂料保护层。After curing reaches the required strength and observes that there is no water seepage, cut the pipe and apply a protective layer of rubber paint on the surface of the cut. 10.根据权利要求1-2,4-8任一项所述的地下建筑降水井防渗封堵施工方法,其特征在于:在所述步骤1)之前还包括施工准备步骤:针对性编制施工方案,并经审核、批准完成;详细技术交底、材料堆放、劳动力准备、工具准备均需符合要求。10. According to any one of claims 1-2, 4-8, the anti-seepage and plugging construction method for underground building dewatering wells is characterized in that: before the step 1), it also includes a construction preparation step: targeted preparation and construction The plan has been reviewed and approved to be completed; detailed technical disclosure, material stacking, labor preparation, and tool preparation must meet the requirements.
CN201910429045.3A 2019-05-22 2019-05-22 Construction method of anti-seepage and plugging of underground building dewatering well Pending CN110144918A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910429045.3A CN110144918A (en) 2019-05-22 2019-05-22 Construction method of anti-seepage and plugging of underground building dewatering well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910429045.3A CN110144918A (en) 2019-05-22 2019-05-22 Construction method of anti-seepage and plugging of underground building dewatering well

Publications (1)

Publication Number Publication Date
CN110144918A true CN110144918A (en) 2019-08-20

Family

ID=67592604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910429045.3A Pending CN110144918A (en) 2019-05-22 2019-05-22 Construction method of anti-seepage and plugging of underground building dewatering well

Country Status (1)

Country Link
CN (1) CN110144918A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457828A (en) * 2022-01-24 2022-05-10 北京城建设计发展集团股份有限公司 Construction method of open cut fabricated underground structure foundation pit dewatering well
CN114561970A (en) * 2022-03-02 2022-05-31 四川童燊防水工程有限公司 Construction method and structure for pit type waterproof plugging
CN116816394A (en) * 2022-12-29 2023-09-29 中交一公局集团有限公司 Shield segment grouting hole plugging method
CN117431985A (en) * 2023-12-21 2024-01-23 上海建工二建集团有限公司 Underground diaphragm wall door type emergency plugging device and method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032057A (en) * 2005-07-26 2007-02-08 Concrete Fukugo Kozo Kenkyu Kiko:Kk Expansion device for bridge joint and joint method for bridge
CN201326176Y (en) * 2008-12-15 2009-10-14 上海市第二建筑有限公司 Deep foundation pit dewatering retention well
CN103334444A (en) * 2013-07-09 2013-10-02 中国一冶集团有限公司 Decompression type blocking method for foundation pit dewatering well
CN203796281U (en) * 2014-03-14 2014-08-27 上海市政工程设计研究总院(集团)有限公司 Grouting pipe structure embedded in composite pipe piece
CN206128099U (en) * 2016-11-01 2017-04-26 山东省城乡建设勘察设计研究院 Novel precipitation well shut -in well device
CN206189431U (en) * 2016-11-02 2017-05-24 天津市津勘岩土工程股份有限公司 Deep well changes device of establishing artesian well and implementing shut -in well
CN207017282U (en) * 2017-07-27 2018-02-16 中国水利水电第八工程局有限公司 A kind of highly permeable scall Quick leak stoppage apparatus
CN108166517A (en) * 2018-02-10 2018-06-15 中国建筑第五工程局有限公司 For the shut-in well method and well-sealing device of superelevation floor height hydraulic pressure dewatering well of deep well
JP2018096071A (en) * 2016-12-12 2018-06-21 大成建設株式会社 Composite building
CN108385705A (en) * 2018-02-08 2018-08-10 江苏鼎达建筑新技术有限公司 A kind of shut-in well technique of pipe well
CN109162660A (en) * 2018-10-30 2019-01-08 中国电建集团成都勘测设计研究院有限公司 Interior anchor formula orifice closing device
CN210194655U (en) * 2019-05-22 2020-03-27 四川童燊防水工程有限公司 Seepage-proofing plugging reinforcing structure for dewatering well of underground building

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032057A (en) * 2005-07-26 2007-02-08 Concrete Fukugo Kozo Kenkyu Kiko:Kk Expansion device for bridge joint and joint method for bridge
CN201326176Y (en) * 2008-12-15 2009-10-14 上海市第二建筑有限公司 Deep foundation pit dewatering retention well
CN103334444A (en) * 2013-07-09 2013-10-02 中国一冶集团有限公司 Decompression type blocking method for foundation pit dewatering well
CN203796281U (en) * 2014-03-14 2014-08-27 上海市政工程设计研究总院(集团)有限公司 Grouting pipe structure embedded in composite pipe piece
CN206128099U (en) * 2016-11-01 2017-04-26 山东省城乡建设勘察设计研究院 Novel precipitation well shut -in well device
CN206189431U (en) * 2016-11-02 2017-05-24 天津市津勘岩土工程股份有限公司 Deep well changes device of establishing artesian well and implementing shut -in well
JP2018096071A (en) * 2016-12-12 2018-06-21 大成建設株式会社 Composite building
CN207017282U (en) * 2017-07-27 2018-02-16 中国水利水电第八工程局有限公司 A kind of highly permeable scall Quick leak stoppage apparatus
CN108385705A (en) * 2018-02-08 2018-08-10 江苏鼎达建筑新技术有限公司 A kind of shut-in well technique of pipe well
CN108166517A (en) * 2018-02-10 2018-06-15 中国建筑第五工程局有限公司 For the shut-in well method and well-sealing device of superelevation floor height hydraulic pressure dewatering well of deep well
CN109162660A (en) * 2018-10-30 2019-01-08 中国电建集团成都勘测设计研究院有限公司 Interior anchor formula orifice closing device
CN210194655U (en) * 2019-05-22 2020-03-27 四川童燊防水工程有限公司 Seepage-proofing plugging reinforcing structure for dewatering well of underground building

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
HE, SH: "Experimental study on CFSC encased shear connectors in steel-concrete composite joints with UHPC grout", CONSTRUCTION & BUILDING TECHNOLOGY, vol. 173, 10 June 2018 (2018-06-10), pages 638 - 649 *
宋景义, 赵常文: "消力池集水井承压条件下灌浆试验研究", 吉林水利, no. 09, 25 September 2002 (2002-09-25), pages 1 - 3 *
张文刚;: "探究地铁区间隧道盾构防水堵漏施工技术", 内江科技, no. 04, 25 April 2016 (2016-04-25), pages 57 *
王铁记: "奥灰特大突水灾害快速治理技术—峰峰矿区实例研究", 冶金工业出版社, pages: 49 - 54 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457828A (en) * 2022-01-24 2022-05-10 北京城建设计发展集团股份有限公司 Construction method of open cut fabricated underground structure foundation pit dewatering well
CN114457828B (en) * 2022-01-24 2024-02-23 北京城建设计发展集团股份有限公司 Construction method for open cut assembled underground structure foundation pit dewatering well
CN114561970A (en) * 2022-03-02 2022-05-31 四川童燊防水工程有限公司 Construction method and structure for pit type waterproof plugging
CN114561970B (en) * 2022-03-02 2025-09-09 四川童燊防水工程有限公司 Hole type waterproof plugging construction method and structure
CN116816394A (en) * 2022-12-29 2023-09-29 中交一公局集团有限公司 Shield segment grouting hole plugging method
CN117431985A (en) * 2023-12-21 2024-01-23 上海建工二建集团有限公司 Underground diaphragm wall door type emergency plugging device and method
CN117431985B (en) * 2023-12-21 2024-03-15 上海建工二建集团有限公司 Underground diaphragm wall door type emergency plugging device and method

Similar Documents

Publication Publication Date Title
CN101768976B (en) Base pit dewatering and water saving device and construction method thereof
CN104929143B (en) A kind of bottom of foundation ditch dewatering well shut-in well method
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN104947700B (en) A kind of sealing method of precipitation well
CN110144918A (en) Construction method of anti-seepage and plugging of underground building dewatering well
CN102839691B (en) Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN112281882A (en) Method for treating water and sand gushing from substrate
CN104099946B (en) Inspection-pit between a kind of Novel top pipeline section
CN103147614B (en) Pool with multi-layer structure and building method thereof
CN110409511A (en) A water-stopping method for joints between occlusal piles and ground-connected walls
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN201567582U (en) A water-saving device for foundation pit dewatering
CN106894431B (en) A method for water-proof construction precipitation treatment of underground building pits in an environment rich in water resources
CN219753314U (en) Plugging device for solving water surge of dewatering well
CN117027033A (en) Construction method for sealing downpipe wells in rafts
CN103205986A (en) Concrete raft foundation construction-joint grouting device and construction method
CN109024640A (en) One kind closing water valve device, shut-in well structure and its construction method
CN103174154A (en) A method and auxiliary dewatering device for solidly sealing underground building floor water gushing well pits
CN202899153U (en) Oblique column type anti-corrosion foundation device for power transmission line of salt-lake region
CN108571330A (en) Method for treating leakage water of post-cast strip of subway bottom plate
CN210113318U (en) Foundation ditch basement gushes water and gushes sand plugging device
CN220644342U (en) A waterproof structure for the bottom of basement exterior walls
CN217949109U (en) Plugging device for dewatering well
CN113175350B (en) A construction method for wastewater pumping station in water-rich sand layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned

Effective date of abandoning: 20250124

AD01 Patent right deemed abandoned