CN206428707U - A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation - Google Patents

A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation Download PDF

Info

Publication number
CN206428707U
CN206428707U CN201720046567.1U CN201720046567U CN206428707U CN 206428707 U CN206428707 U CN 206428707U CN 201720046567 U CN201720046567 U CN 201720046567U CN 206428707 U CN206428707 U CN 206428707U
Authority
CN
China
Prior art keywords
pile
lagging
precipitation
foundation pit
breast boards
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720046567.1U
Other languages
Chinese (zh)
Inventor
孔繁力
杨国富
杨宗
刘辉
林佰春
王诚志
李洪伟
马廷军
崔永胜
李宝昌
丁冶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Original Assignee
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeast Electric Power Design Institute of China Power Engineering Consulting Group filed Critical Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN201720046567.1U priority Critical patent/CN206428707U/en
Application granted granted Critical
Publication of CN206428707U publication Critical patent/CN206428707U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation, it is characterised in that:Including lagging pile, breast boards, pile cover, shore beam, lagging pile is hollow steel pipe structure, lagging pile side is provided with precipitation hole, lagging pile and is connected with breast boards between stake, lagging pile top connection pile cover, beam is shored in relative lagging pile top by pile cover, collectively constitutes force structure system.This structure, which can be produced in batches, to be reduced cost, can freely assemble, dismantle, existing equipment support can be reused, and farthest save duration and saving construction cost, because lagging pile, breast boards can remove recycling after construction, without any pollution, environmental requirement is met, the construction period is saved.Construction method is simple and reliable.

Description

A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
Technical field
The utility model is related to civil engineering technical field, more particularly, to a kind of pattern foundation pit supporting structure, the integrated pile tube of precipitation Dado structure.
Background technology
In urbanization process, underground pipeline project is increasing.At present, foundation ditch lagging pile is in industry and civil buildings foundation ditch Largely used in construction, mostly mixing pile combination anchor rod construction process.But because mixing pile can be made in work progress with anchor pole Into leaving, underground is polluted, and mixing pile belongs to disposable consumption with anchor pole, it is impossible to recycle, cause to waste. In addition, generally, deep foundation pit construction is required for precipitation, and mixing pile combination anchor rod construction process can not play precipitation work With if running into underground water, in addition it is also necessary to additionally implement precipitation, increase construction period and quantities.
Utility model content
To solve existing foundation ditch breast wall technology defect, the utility model provides a kind of pattern foundation pit supporting structure, precipitation integrated pile tube Dado structure, can with repetitive cycling using, do not result in any underground and leave, while having precipitation function.
To realize above-mentioned utility model purpose, the utility model provides a kind of pattern foundation pit supporting structure precipitation integrated pile tube retaining wall knot Structure, it is characterised in that:Including lagging pile, breast boards, pile cover, shore beam, lagging pile is that hollow steel pipe structure, lagging pile side are set Have and breast boards between stake is connected with precipitation hole, lagging pile, lagging pile top connection pile cover, relative lagging pile top passes through pile cover Beam is shored, force structure system is collectively constituted.
Lagging pile is divided between some sections, each section along short transverse to be connected by flange, is easy to be assembled into any total length.
Mounting hook or latch on lagging pile, to connect breast boards between stake.
The utility model beneficial effect is:Because lagging pile, breast boards take factory to make, can produce in batches reduces into Originally, it can freely assemble, dismantle, existing equipment support can be reused, and farthest saving duration and saving construction cost (The processing and fabricating odd-job phase can be realized with the advance stock of factory, distribute on demand);Because lagging pile, breast boards can be in constructions Remove and recycle afterwards, without any pollution, meet environmental requirement;Due to the precipitation hole reserved on the utility model lagging pile and diving Pump and drainpipe do not need extra dewatering process during collectively constituting precipitation system, foundation pit construction, can save the construction period, Raise labour productivity, reduce foundation ditch retaining wall cost, realize that foundation ditch retaining wall pure green is constructed.
Brief description of the drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is lagging pile elevation;
Fig. 3 is the local cross-cutting fault figure of the utility model.
Reference is as follows in figure:1-soil body;2-breast boards;3-lagging pile;4-adpting flange;5-pile cover;6— Shore beam;7-precipitation hole;8-hook;9-immersible pump.
Embodiment
1-3 is described further to the utility model below in conjunction with the accompanying drawings.
Certain underground cable tunnel engineering, cross section out-to-out is 6 meters X6 meters, 1.5 meters of buried depth, 3 meters of groundwater level depth. Lagging pile uses hollow steel pipe structure, 1.02 meters of steel pipe cross-sectional diameter, 10 millimeters of wall thickness.Lagging pile is divided into 3 along short transverse Section, connected between each section by flange, pile cutoff length is respectively 3 meters, 4 meters, 5 meters, 10 meters of total length after splicing.In lagging pile stake Section side is reserved the water energy seepage flow in precipitation hole, the soil body along height and entered in stake, and precipitation hole is blocked with screen cloth, to filter silt. Lagging pile implements mechanical hole building, and immersible pump is transferred into a bottom from top before pile cover is installed carries out dewatering operation(In the soil body Water seepage flow enters in lagging pile, and lagging pile now is equivalent to dewatering well.Silt being taken away together during to prevent that immersible pump from drawing water, being led Stake bottom soil body is caused to loosen, in advance 500 millimeters of high gravels of backfill, to filter silt).Longitudinally spaced 4 meters along piping lane of lagging pile Set, lagging pile is provided with mounting hook, to connect breast boards between stake, pile cover is square, is connected by flange with stake, pile cover Also implement flange with the support beam in stake top portion to be connected.It can apply after foundation pit construction is finished, during pile pulling in pile cover and rotate, to make Stake is given birth to local products to be loosened, and is easy to pile pulling.
Concrete construction method step is as follows:
Step 1:First implement first segment sunk pile, using mechanical hole building mode, 1 meter of preboring diameter, deep 5 meters drilling.So First paragraph pile cutoff hammering 5 meters long is sunk to afterwards retaining wall is carried out in hole,(Because machine drilling is pipe diameter, omited in pile sinking There is soil compaction effect, when being bored under continuation, retaining wall pile cutoff voluntarily will not come off downwards)Continue drilling with machinery again to go after 4 meters, pass through 4 meters of long stakes of second section are connected by flange with first paragraph, 4 meters of hammer piling, such mode again by the 3rd section of stake it is finished after, return Fill out 500 millimeters of high gravels.Immersible pump is finally transferred into a bottom from top and carries out dewatering operation, pile cover is installed, stake top branch is installed Support beam;
Step 2:Start to dig foundation ditch, as excavation of foundation pit is carried out, the mounting hook on lagging pile successively installs breast boards. In this example, 0.5 meter of breast boards width, therefore excavate 0.5 meter of just one layer of breast boards of installation whenever downward;
Step 3:After the completion of excavation of foundation pit, major project construction is carried out, after finishing, backfill.Bottom breast boards is first removed, then Bottom is backfilled, successively the backfill of earth-retaining edges of boards is removed on side successively;
Step 4:After foundation ditch backfill, stake top support beam and pile cover are first dismounted, immersible pump is then dismounted, then pull out retaining wall section by section Stake, difficult for lagging pile pile pulling, pile cover is reinstalled, is reversed by applying at pile cover, lagging pile is given birth to pine with local products It is dynamic.Or into stake the water filling wetted perimeter soil body, reduce frictional force.Pile pulling backfills soil in stake, and compaction in layers simultaneously.

Claims (3)

1. a kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation, it is characterised in that:Including lagging pile, breast boards, pile cover, top Beam is supportted, lagging pile is hollow steel pipe structure, lagging pile side is provided with precipitation hole, lagging pile and is connected with breast boards between stake, retaining wall Stake top end connects pile cover, and relative lagging pile top shores beam by pile cover, collectively constitutes force structure system.
2. the integrated pile tube dado structure of a kind of pattern foundation pit supporting structure precipitation according to claim 1, it is characterised in that:Lagging pile It is divided into along short transverse between some sections, each section and is connected by flange, is easy to be assembled into any total length.
3. the integrated pile tube dado structure of a kind of pattern foundation pit supporting structure precipitation according to claim 1 or 2, it is characterised in that:Shield The upper mounting hook of wall stake or latch, to connect breast boards between stake.
CN201720046567.1U 2017-01-16 2017-01-16 A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation Active CN206428707U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720046567.1U CN206428707U (en) 2017-01-16 2017-01-16 A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720046567.1U CN206428707U (en) 2017-01-16 2017-01-16 A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation

Publications (1)

Publication Number Publication Date
CN206428707U true CN206428707U (en) 2017-08-22

Family

ID=59582420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720046567.1U Active CN206428707U (en) 2017-01-16 2017-01-16 A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation

Country Status (1)

Country Link
CN (1) CN206428707U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964960A (en) * 2017-11-22 2018-04-27 山东电力建设第工程公司 A kind of municipal pipeline groove timbering structure and method for protecting support
CN108914944A (en) * 2018-07-27 2018-11-30 中国冶集团有限公司 Shoal high water level pipeline Support of Foundation Pit Excavation precipitation system and construction method
CN109610476A (en) * 2019-01-31 2019-04-12 上海宝钢工程咨询有限公司 Steel pipe Larsen sheet pile precipitation building enclosure
CN112832253A (en) * 2021-01-07 2021-05-25 青岛理工大学 Treatment method for piping of steel sheet pile support foundation pit

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964960A (en) * 2017-11-22 2018-04-27 山东电力建设第工程公司 A kind of municipal pipeline groove timbering structure and method for protecting support
CN108914944A (en) * 2018-07-27 2018-11-30 中国冶集团有限公司 Shoal high water level pipeline Support of Foundation Pit Excavation precipitation system and construction method
CN109610476A (en) * 2019-01-31 2019-04-12 上海宝钢工程咨询有限公司 Steel pipe Larsen sheet pile precipitation building enclosure
CN112832253A (en) * 2021-01-07 2021-05-25 青岛理工大学 Treatment method for piping of steel sheet pile support foundation pit

Similar Documents

Publication Publication Date Title
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN206428707U (en) A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN108343071A (en) A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN102286984A (en) Water-stop curtain and construction method thereof
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN106351230B (en) Soft clay area basement construction method for supporting
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN107964976A (en) Steel pipe-conversion steel platform tower crane top-down construction method
CN102359112A (en) Method for bracing foundation pit by using steel box piles
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN106480891B (en) A kind of shaft construction method
CN114575355A (en) Soil protection and descent construction method
CN110117959B (en) Construction method for foundation pit support near river
CN110762286B (en) Drainage pipe network artificial pipe jacking construction process
CN101597903B (en) Construction method of cylindrical slurry core pile for retaining and protecting foundation pit
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN106988337A (en) A kind of reinforcement means for being used to reduce bar shaped shallow foundation house differential settlement
CN114809094A (en) Pipe jacking working well for complex stratum and construction process thereof
CN103866787A (en) Process for constructing impervious concrete wall by using open excavation and inverted construction method
CN208023591U (en) A kind of foundation pit supporting construction of steel sheet pile combined deposited pile
CN204435321U (en) A kind of steam power station water intaking open channel
CN106498951A (en) A kind of shaft excavation construction method