CN106498951A - A kind of shaft excavation construction method - Google Patents

A kind of shaft excavation construction method Download PDF

Info

Publication number
CN106498951A
CN106498951A CN201611089425.XA CN201611089425A CN106498951A CN 106498951 A CN106498951 A CN 106498951A CN 201611089425 A CN201611089425 A CN 201611089425A CN 106498951 A CN106498951 A CN 106498951A
Authority
CN
China
Prior art keywords
shaft
guard
construction method
inwall
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611089425.XA
Other languages
Chinese (zh)
Other versions
CN106498951B (en
Inventor
吴欣之
陈晓明
杨宏伟
严时汾
过浩侃
罗鑫
贾宝荣
蒋明星
应晔
吴晓风
李晓娇
刘颖
李操
周铮
周蓉峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201611089425.XA priority Critical patent/CN106498951B/en
Publication of CN106498951A publication Critical patent/CN106498951A/en
Application granted granted Critical
Publication of CN106498951B publication Critical patent/CN106498951B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0076Drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Abstract

The invention provides a kind of shaft excavation construction method, comprises the following steps:Go along with sb. to guard him ground wall construction;Vertical shaft shallow-layer is excavated;Completed shallow-layer excavation vertical shaft in water filling, and in water to vertical shaft remainder implement water in excavate;Pour shaft floor, and the inwall using buoyancy of water construction shaft in vertical shaft;Pour the inwall and the gap that goes along with sb. to guard him between ground wall.The construction method combines base arrangement using steel concrete, solves the problems, such as ultra-deep shaft base plate and the common stress of supporting construction, and improves base plate anti-floating ability, while constructing using buoyancy of water and with reference to jacking equipment, improves efficiency of construction, reliable in quality;Secondly solve the problems, such as needed for Excavation Process, to want drawdown artesian water using not dewatering excavation, and shorten the construction depth for going along with sb. to guard him ground wall, reduce construction risk.

Description

A kind of shaft excavation construction method
Technical field
The invention belongs to Foundation Pit Construction technical field, it is adaptable to ultra-deep shaft engineering construction, relate generally to a kind of perpendicular Well excavation construction method.
Background technology
Ultra-deep shaft structure construction problem is a lot of at present, and what wherein urgent need was to be solved is deeper subsurface water treatment problems.Such as Fruit will necessarily adopt precipitation excavation of foundation pit to shaft perimeter environmental effects, particularly downtown area using dewatering measure, Drop deep water in confined construction risk is big, and conventional measure is the method developed simultaneously using dewatering well, water seal curtain and recharge, but right In special depth major diameter shaft structure construction situation, precipitation is big, and surrounding enviroment affect more prominent, in addition shaft floor and go along with sb. to guard him ground The common stress problem of wall is difficult to solve.
Content of the invention
It is an object of the invention to provide a kind of shaft excavation construction method, to solve underground water during Construction of Silo Affect, and solve shaft floor anti-floating and shaft structure construction problem.
For solving above-mentioned technical problem, the present invention provides a kind of shaft excavation construction method, comprises the following steps:
S1:Go along with sb. to guard him ground wall construction;
S2:Vertical shaft shallow-layer is excavated;
S3:Water filling in the vertical shaft for having completed shallow-layer excavation, and to remaining soil body part reality in vertical shaft foundation ditch in water Shi Shuizhong is excavated;
S4:Pour shaft floor, and the inwall using buoyancy of water construction shaft in vertical shaft;
S5:Pour the inwall and the gap that goes along with sb. to guard him between ground wall.
Optionally, the ground wall of going along with sb. to guard him is reinforced concrete structure, and the construction method of the reinforced concrete structure includes Following steps:
Groove milling or trenching construction is carried out with chute forming machine or slotter to going along with sb. to guard him ground wall place groove fragment position;
Steel reinforcement cage is hung in groove successively, casting concrete is formed goes along with sb. to guard him ground wall.
Optionally, include after the S1 and also before the S2:Tip circle beam is constructed;The tip circle beam is located at described enclosing Shield Di Qiang upper ends, and fix with the ground wall of going along with sb. to guard him.
Optionally, the construction method that the shallow-layer is excavated is comprised the following steps:Using multiple stage excavator to the soil in vertical shaft Body is excavated.
Optionally, the construction method that excavates in the water is comprised the following steps:
Steel truss is set in shaft top, and the steel truss is sling using lifting appliance, to control the position of steel truss Put;
The lower section of the steel truss is filled in vertical shaft, and grabs brill in vertical shaft foundation ditch using hydraulic variable diameter rig or punching Implement to excavate in water in remaining soil body part.
Optionally, the steel truss is to be welded the space truss structure for being formed, the space truss structure by some H profile steels On be provided with some columns.
Optionally, the construction method for pouring shaft floor is comprised the following steps:
Bottom template and side wall template are installed to the bottom and outer circumferential side of steel truss respectively;
Layering, segmentation casting concrete in the bottom template and side wall template.
Optionally, the bottom template is welded to form using steel plate assembly on the outside of the side wall template using die mould punching block Annular punching block, using annular creeping formwork on the inside of the side wall template, and arranges some pegs in the side wall template.
Optionally, in the S4, inwall is poured on the inside of vertical shaft foundation ditch side wall by the way of creeping formwork section by section.
Optionally, in the S4, the inwall, the thickness edge of the variable cross-section formwork are poured using variable cross-section formwork The inwall gradually increases from top to bottom.
Optionally, often section inwall installs bar-mat reinforcement and steel strand wires before pouring in advance.
Optionally, in the S5, the gap point three steps filling between ground wall and inwall is gone along with sb. to guard him,
The first step, go along with sb. to guard him the corresponding base plate bottom concrete position in side and structure base slab bottom injection cement grout within the walls Form the first packed layer;
Second step, steel reinforcement cage is hung in go along with sb. to guard him ground wall and variable cross-section inwall between space, and be located at described first On packed layer;
Casting concrete forms the second packed layer into the steel reinforcement cage;
3rd step, the ground inner wall of going along with sb. to guard him above second packed layer arrange shearing resistance groove, and be put into steel reinforcement cage or Steel truss casting concrete is to top beam.
Optionally, the depth bounds that the shallow-layer is excavated is 12m-18m.
The shaft excavation construction method provided in the present invention possesses following beneficial effect:Combine initially with steel-concrete The structure of the inwall of base arrangement and variable cross-section, solves the problems, such as ultra-deep shaft base plate and the common stress of inwall and base plate anti-floating Ability, while shaft structure (including base plate and inwall) construction is constructed by buoyancy of water and with reference to jacking equipment, raising is applied Work efficiency rate, reliable in quality;Secondly solve the problems, such as needed for Excavation Process, to want drawdown artesian water using not dewatering excavation, Surrounding enviroment are affected to be down to minimum, particular for the excavation of urban central zone;Secondly, opened using not draining Dig, shorten the construction depth for going along with sb. to guard him ground wall, reduce the construction risk of deep gouge.
Description of the drawings
Fig. 1 is the flow chart of the shaft excavation construction method of one embodiment of the application;
Fig. 2 is the schematic diagram that one embodiment vertical shaft shallow-layer of the application is excavated;
Fig. 3 is the schematic diagram of one embodiment vertical shaft steel truss of the application construction;
Fig. 4 is the schematic diagram excavated in one embodiment vertical shaft water of the application;
Fig. 5 be in one embodiment vertical shaft water of the application excavate after the completion of to steel truss mounting base and the schematic diagram of side plate;
Fig. 6 and Fig. 7 are the construction schematic diagrames of one embodiment vertical shaft inwall of the application;
Fig. 8 is the schematic diagram of one embodiment vertical shaft inwall integral sinking of the application;
Fig. 9 is one embodiment vertical shaft inwall of the application and the schematic diagram for going along with sb. to guard him gap construction between ground wall.
In figure:1- goes along with sb. to guard him ground wall;11- top beams;2- inwalls;The first packed layers of 21-;The second packed layers of 22-;23- Three packed layers;The 3- soil bodys;4- steel truss;5- excavators;6- lifting appliances;7- hydraulic variable diameter rigs.
Specific embodiment
The core concept of the application is:For in ultra-deep shaft structure construction procedure using not dropping applying for deep water in confined Work method, while by buoyancy of water and combining jacking equipment construction shaft inwall, improves efficiency of construction, reliable in quality, solution Determine hydraulic balance inside and outside vertical shaft foundation ditch, little to shaft perimeter ambient influnence;Secondly segmentation between ground wall and inwall is being gone along with sb. to guard him Filling, and shear key is set in local location, solve the problems, such as ultra-deep shaft base plate and the common stress of supporting construction.
Shaft excavation construction method proposed by the present invention is made further specifically below in conjunction with the drawings and specific embodiments Bright.According to following explanation and claims, advantages and features of the invention will become apparent from.It should be noted that, accompanying drawing is adopted The form that simplifies very much and using non-accurately ratio, only in order to mesh that is convenient, lucidly aiding in illustrating the embodiment of the present invention 's.
Fig. 1 is referred to, which is illustrated that the shaft excavation construction method flow chart of the present embodiment, mainly includes:Go along with sb. to guard him ground wall 1 Construction;Vertical shaft shallow-layer is excavated;Excavate in vertical shaft water;Construction base plate, base plate is floated on the surface inner lining construction wall, and last segmentation is filled out Fill the gap that goes along with sb. to guard him between ground wall 1 and inwall 2.
Fig. 2 is referred to, which is illustrated that the vertical shaft of the present embodiment, after the ground construction of wall 1 is gone along with sb. to guard him, implements the signal that shallow-layer is excavated Figure.
Wherein, the construction that ground wall 1 gone along with sb. to guard him by vertical shaft is carried out first, and vertical shaft ground wall 1 is first with chute forming machine or slotter to going along with sb. to guard him Ground wall chase section grooving, then hangs in the steel reinforcement cage that makes in groove, and casting concrete is formed goes along with sb. to guard him ground wall 1.Going along with sb. to guard him ground wall 1 The corresponding substrate bottom concrete position in inner side arranges tongue and groove shape steel plate, outer viscous water proof rubber material, and arranges in suitable position Slip casting extends watertight rubber capsule, is in addition going along with sb. to guard him the default sealing Grouting Pipe of ground 1 seam areas of wall, so as to prevent oozing for underground water Enter.Optionally, slotter is German treasured Russia BC40 hydraulic pressure two-wheel flute milling machines.
Preferably, the construction for carrying out top beam 11 after the completion of ground wall 1 is constructed gone along with sb. to guard him by vertical shaft, goes along with sb. to guard him ground wall 1 to improve vertical shaft Integral rigidity, reduce digging process in go along with sb. to guard him ground wall 1 deformation.Top beam 11 be located at go along with sb. to guard him ground wall 1 upper end and with go along with sb. to guard him Ground wall 1 is fixed together, and the mode that optional armored concrete is poured is realized.
Top beam 11 carries out vertical shaft shallow-layer excavation after the completion of constructing, the depth bounds of the shallow-layer of vertical shaft is generally [12,18] (can suitably be adjusted according to local level of ground water situation), preferred depth are 15 meters.Shallow-layer is excavated and adopts dry excavation, i.e., not in vertical shaft Interior water filling, is directly coordinated with multiple stage excavator 5 and is excavated.For convenience of explanation, with natural ground elevation as 0 position, shallow-layer here Excavate and be excavated at -15 meters of vertical shaft for the time being.By theoretical calculation, less to the Water And Earth Pressures for going along with sb. to guard him ground wall 1, go along with sb. to guard him ground wall 1 and become Shape is little, so construction is safer;In addition dry excavation construction is very fast, and excavate native disposable, shorten to a certain extent Duration.
Implement in vertical shaft water, to excavate link.Excavate in water and using hydraulic variable diameter rig 7 and mud disposal system can be coordinated To construct, place hydraulic variable diameter rig 7 for convenience, and consider construction of the later stage to shaft floor, carry out steel truss 4 first Hydraulic variable diameter rig 7, and the part that the later stage constructs can be conveniently placed in construction, steel truss 4 to shaft floor.Refer to Fig. 3, The schematic diagram of steel truss 4 installed by the vertical shaft that it illustrates the present embodiment.Lifting appliance 6 is placed in vertical shaft foundation ditch periphery and slings steel truss Frame 4, the plane of steel truss 4 is circle, is highly designed as 8 meters high according to Force Calculation steel truss, is welded by some H profile steels and formed Space truss structure, steel truss 4 are main assembled by 8 truss structure beams, circular edge have 16 steel pipe columns and a H profile steel welding and Into.Using crawler crane, 4 ends rest of steel truss after the completion of installation on ground, assembly on top beam and passes through hydraulic pressure to steel truss 4 Control device 41 lifts by crane steel truss 4, and fills water toward in foundation ditch to 4 bottom of steel truss.
Fig. 4 is referred to, the schematic diagram excavated in the vertical shaft water of the present embodiment is it illustrates;Two hydraulic variable diameter rigs 5 exist The soil body 3 of deeper is entered on steel truss 4 in water-filling and excavated, and the mud of excavation is retracted to ground, and by mud conditioning system System process, mud disposal system can select BE250 mud disposal systems.Less than -15 meters of the soil body 3 is excavated in water, is dug always Locate to vertical shaft -73m, that is, complete excavation part in water, and carry out deslagging, to vertical shaft bottom of foundation ditch and go along with sb. to guard him after having excavated Ground 1 side wall scarfing cinder of wall, clear bottom.Brill can also be grabbed using punching to implement to excavate in water.
Then, construction base plate inner lining construction wall 2 section by section is combined with, and base plate here most sinks to silo bottom, base plate at last It is the overall structure after casting concrete in steel truss 4.First, structure of the base plate using steel truss 4, the bottom to steel truss 4 Portion, inside and outside side seal template, 4 bottom template of steel truss adopt steel bar girder profiled sheet, 4 framed side wallboard outer steel formwork of steel truss to adopt The assembled welding of 10mm steel plates, and steel plate surfaces externally and internally every uniform distances weld stud, improve concrete with steel plate Bond stress, steel plate as structure in permanent composition component (needing not wait for form removal after concrete some strength), inner side adopt Creeping formwork.Refer to Fig. 4, it can be seen that the bottom template of steel truss and framed side wallboard are assembled good, and in the template of bottom pour bottom Plate 2m, pours framed side wallboard 8m, in order to prevent from, can adopt the method for properly increasing water level, prevent bottom using buoyancy of water Plate sinks, if buoyancy of water is not enough, can lift base plate by lifting appliance 6 simultaneously.
Refering to Fig. 6, the construction of part inwall 2 in figure, is completed, 2 section thickness of vertical shaft inwall is according to soil pressure point Cloth situation is rationally economized on resources using variable cross-section formwork casting concrete, thus most thick below the inwall 2 for ultimately forming, Gradually thinning upwards successively, vertically, lateral surface is in the notch cuttype of certain slope to 2 medial surface of inwall.Therefore liner can be utilized Notch cuttype contact surface on the outside of wall 2 increases the frictional force of inwall 2 and fill concrete, improves concrete snap-in force.
Base plate is poured gradually, certain thickness is reached to base plate thickness, can select to pour every time base plate thickness for 2m, know Road base plate thickness reaches 10m.Coordinate while pouring base plate and pour inwall 2.On the inside of inwall 2, (shaft excavation face) is using climbing The mode of mould is poured under vertical shaft section by section, while installing bar-mat reinforcement and prestress steel twist in advance before every section inwall 2 is poured Line, to improve the rigidity of inwall 2.If the buoyancy in downward work progress section by section of inwall 2 is whole more than base plate and inwall 2 The deadweight of body structure, can on base plate counterweight, counterweight mode can be that water filling auxiliary is sunk in the vertical shaft.
Refer to Fig. 7, it can be seen that at this moment the construction of inwall 2 makes base plate and inwall 2 overall already close to silo bottom Structure is sunk, and refering to Fig. 8, is that the shaft structure diagram after sinking is intended to.At this time base plate has touched the soil body 3, but because There are some residues in silo bottom, still have certain gap unavoidably between the two.
Finally, segmentation pours the gap that goes along with sb. to guard him between ground wall 1 and inwall 2.Fig. 9 is referred to, ground wall 1 and inwall is gone along with sb. to guard him Three steps of gap between 2 point are poured.Three steps pour part and are respectively the first packed layer 21, the second packed layer 22, the 3rd packed layer 23.
The construction method of the first packed layer 21 be between to structural base sediment and soft layer grouting reinforcement.
The construction method of the second packed layer 22 be go along with sb. to guard him ground wall 1 and variable cross-section inwall 2 between space hang in successively Steel reinforcement cage, then casting concrete is consolidated again.Steel reinforcement cage is close to and goes along with sb. to guard him ground wall 1 and sink, in case steel reinforcement cage hangs in advance welding On the peg on outside steel form surface, and steel reinforcement cage section thickness is less than the width in space, is easy to smoothly decentralization.
The construction method of the 3rd packed layer 23 is will to go along with sb. to guard him Foundation ditch carry out shearing resistance construction construction, and clear up ground wall shearing resistance groove, casting concrete arrange top beam 11 by inwall 2 with go along with sb. to guard him ground Wall 1 connects integral.So far, Construction of Silo terminates.
The shaft excavation construction method that the present embodiment is provided possesses following beneficial effect:Combine initially with steel-concrete The structure of the inwall 2 of base arrangement and variable cross-section, solves the problems, such as special deep shaft base plate and goes along with sb. to guard him ground 1 common stress of wall and base plate Anti-floating ability, while shaft structure is constructed by buoyancy of water and with reference to jacking equipment, improves efficiency of construction, reliable in quality;Its Secondary solve the problems, such as needed for Excavation Process, to want drawdown artesian water using not dewatering excavation, on surrounding enviroment affect be down to Minimum, particular for the excavation of urban central zone;Secondly, using not dewatering excavation, shorten and go along with sb. to guard him ground wall 1 Construction depth, reduces the construction risk of deep gouge.
Foregoing description is only the description to present pre-ferred embodiments, not any restriction to the scope of the invention, this Any change that the those of ordinary skill in bright field is done according to the disclosure above content, modification, belong to the protection of claims Scope.

Claims (13)

1. a kind of shaft excavation construction method, it is characterised in that comprise the following steps:
S1:Go along with sb. to guard him ground wall construction;
S2:Vertical shaft shallow-layer is excavated;
S3:Water filling in the vertical shaft for having completed shallow-layer excavation, and water is implemented to remaining soil body part in vertical shaft foundation ditch in water Middle excavation;
S4:Pour shaft floor, and the inwall using buoyancy of water construction shaft in vertical shaft;
S5:Pour the inwall and the gap that goes along with sb. to guard him between ground wall.
2. shaft excavation construction method as claimed in claim 1, it is characterised in that the ground wall of going along with sb. to guard him is armored concrete knot Structure, the construction method of the reinforced concrete structure are comprised the following steps:
Groove milling or trenching construction is carried out with chute forming machine or slotter to going along with sb. to guard him ground wall place groove fragment position;
Steel reinforcement cage is hung in groove successively, casting concrete is formed goes along with sb. to guard him ground wall.
3. shaft excavation construction method as claimed in claim 1 or 2, it is characterised in that after the S1 and the S2 it Front also include:Tip circle beam is constructed;The tip circle beam goes along with sb. to guard him Di Qiang upper ends positioned at described, and fixes with the ground wall of going along with sb. to guard him.
4. shaft excavation construction method as claimed in claim 1, it is characterised in that the construction method that the shallow-layer is excavated includes Following steps:Using multiple stage excavator to the soil excavation in vertical shaft.
5. shaft excavation construction method as claimed in claim 1, it is characterised in that the construction method that excavates in the water includes Following steps:
Steel truss is set in shaft top, and the steel truss is sling using lifting appliance, to control the position of steel truss;
The lower section of the steel truss is filled in vertical shaft, and grabs brill to remaining in vertical shaft foundation ditch using hydraulic variable diameter rig or punching Implement to excavate in water in soil body part.
6. shaft excavation construction method as claimed in claim 5, it is characterised in that the steel truss is to be welded by some H profile steels The space truss structure to be formed is connect, some columns on the space truss structure, are provided with.
7. shaft excavation construction method as claimed in claim 1, it is characterised in that the construction method for pouring shaft floor Comprise the following steps:
Bottom template and side wall template are installed to the bottom and outer circumferential side of steel truss respectively;
Layering, segmentation casting concrete in the bottom template and side wall template.
8. shaft excavation construction method as claimed in claim 7, it is characterised in that the bottom template adopts die mould punching block, Annular punching block is welded to form using steel plate assembly on the outside of the side wall template, using annular creeping formwork on the inside of the side wall template, and In the side wall template, some pegs are set.
9. shaft excavation construction method as claimed in claim 1, it is characterised in that in the S4, in vertical shaft foundation ditch side wall Side pours inwall by the way of creeping formwork section by section.
10. the shaft excavation construction method as described in claim 1 or 9, it is characterised in that in the S4, using variable cross-section Formwork pours the inwall, and the thickness of the variable cross-section formwork gradually increases from top to bottom along the inwall.
11. shaft excavation construction methods as claimed in claim 9, it is characterised in that often section inwall is installed before pouring in advance Good bar-mat reinforcement and steel strand wires.
12. shaft excavation construction methods as claimed in claim 1, it is characterised in that in the S5, go along with sb. to guard him ground wall and inwall Between gap point three steps filling,
The first step, go along with sb. to guard him the corresponding base plate bottom concrete position in side and structure base slab bottom injection cement grout are formed within the walls First packed layer;
Second step, steel reinforcement cage is hung in go along with sb. to guard him ground wall and variable cross-section inwall between space, and be located at described first fill On layer;
Casting concrete forms the second packed layer into the steel reinforcement cage;
3rd step, the ground inner wall of going along with sb. to guard him above second packed layer arrange shearing resistance groove, and are put into steel reinforcement cage or steel truss Frame casting concrete is to top beam.
13. shaft excavation construction methods as claimed in claim 1, it is characterised in that the depth bounds that the shallow-layer is excavated is 12m-18m.
CN201611089425.XA 2016-11-30 2016-11-30 A kind of shaft excavation construction method Active CN106498951B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611089425.XA CN106498951B (en) 2016-11-30 2016-11-30 A kind of shaft excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611089425.XA CN106498951B (en) 2016-11-30 2016-11-30 A kind of shaft excavation construction method

Publications (2)

Publication Number Publication Date
CN106498951A true CN106498951A (en) 2017-03-15
CN106498951B CN106498951B (en) 2019-02-05

Family

ID=58329522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611089425.XA Active CN106498951B (en) 2016-11-30 2016-11-30 A kind of shaft excavation construction method

Country Status (1)

Country Link
CN (1) CN106498951B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118728A (en) * 2017-12-29 2018-06-05 上海建工集团股份有限公司 The efficient earth-moving equipment of special-shaped deep basal pit and shoveling method
CN114606905A (en) * 2022-04-10 2022-06-10 金华市恒通工程检测有限公司 Fastening processing device for hydraulic engineering maintenance and processing method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3850785B2 (en) * 2002-10-15 2006-11-29 東日本旅客鉄道株式会社 Caisson laying method using main foundation pile
CN102322069A (en) * 2011-07-04 2012-01-18 浙江省交通规划设计研究院 Underwater combination base of open caisson and steel pipe piles and construction method
CN102888847A (en) * 2012-10-19 2013-01-23 中国二十二冶集团有限公司 Construction method free from lowering water level for local deep foundation pit of elevator shaft
CN104695456A (en) * 2015-03-27 2015-06-10 济南轨道交通集团有限公司 Construction method novel vertical shaft horizontal rotation jet grouting pile foundation pit lateral wall water stopping curtain

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3850785B2 (en) * 2002-10-15 2006-11-29 東日本旅客鉄道株式会社 Caisson laying method using main foundation pile
CN102322069A (en) * 2011-07-04 2012-01-18 浙江省交通规划设计研究院 Underwater combination base of open caisson and steel pipe piles and construction method
CN102888847A (en) * 2012-10-19 2013-01-23 中国二十二冶集团有限公司 Construction method free from lowering water level for local deep foundation pit of elevator shaft
CN104695456A (en) * 2015-03-27 2015-06-10 济南轨道交通集团有限公司 Construction method novel vertical shaft horizontal rotation jet grouting pile foundation pit lateral wall water stopping curtain

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙智勇: "水下开挖法在市政工程深基坑施工中的应用", 《城市轨道交通研究》 *
张健: "超深竖井水下开挖施工关键技术", 《公路与汽运》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118728A (en) * 2017-12-29 2018-06-05 上海建工集团股份有限公司 The efficient earth-moving equipment of special-shaped deep basal pit and shoveling method
CN108118728B (en) * 2017-12-29 2023-01-24 上海建工集团股份有限公司 Efficient soil excavating device and method for special-shaped deep foundation pit
CN114606905A (en) * 2022-04-10 2022-06-10 金华市恒通工程检测有限公司 Fastening processing device for hydraulic engineering maintenance and processing method thereof

Also Published As

Publication number Publication date
CN106498951B (en) 2019-02-05

Similar Documents

Publication Publication Date Title
CN106522989B (en) The method of ventilating shaft structure and shield driving parallel construction
CN106013053B (en) A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson
LU501539B1 (en) Pumping and drainage method for foundation pit bottom plate construction of deep foundation pit and pumping and drainage structure
CN107218046A (en) Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN108457282A (en) Deep water hard rock is without back cover steel sheet pile cofferdam construction method
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN110219359A (en) A kind of Submersed type inspection well and its construction method
CN106480891B (en) A kind of shaft construction method
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN206428707U (en) A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
CN104164881A (en) Piling wall overlapping cantilever foundation pit support construction method and structure
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN106498951B (en) A kind of shaft excavation construction method
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN104480945B (en) A kind of foundation ditch reversed construction method
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN103806444A (en) Soft soil layer rotary excavating pile construction method
CN217419736U (en) Compensation type construction structure for underground engineering construction
CN108221954B (en) Easy-to-detach prefabricated underground diaphragm wall, lifting appliance and construction method
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN106120853B (en) A kind of inverted construction method of frame bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant