CN114575355A - Soil protection and descent construction method - Google Patents

Soil protection and descent construction method Download PDF

Info

Publication number
CN114575355A
CN114575355A CN202210331946.0A CN202210331946A CN114575355A CN 114575355 A CN114575355 A CN 114575355A CN 202210331946 A CN202210331946 A CN 202210331946A CN 114575355 A CN114575355 A CN 114575355A
Authority
CN
China
Prior art keywords
pile
construction
piles
supporting
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210331946.0A
Other languages
Chinese (zh)
Other versions
CN114575355B (en
Inventor
刘冬雪
张哲�
赵志宏
郭卫
崔海军
于卫海
李芒原
胡鹏
贾剑伟
刘振川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202210331946.0A priority Critical patent/CN114575355B/en
Publication of CN114575355A publication Critical patent/CN114575355A/en
Application granted granted Critical
Publication of CN114575355B publication Critical patent/CN114575355B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及一种土护降施工方法,包括S1:施工准备;S2:进行支护桩施工;S3:在相邻支护桩之间进行旋喷桩施工;S4:在支护桩的顶部进行冠梁施工;S5:在基坑支护桩冠梁顶至地面范围进行挡土墙施工,S6:第一道锚索施工;S7:当第一道锚索施工完成后,进行位于旋喷桩上方的第一桩间土护壁施工;S8:第二道锚索施工;S9:当第二道锚索施工完成后,进行旋喷桩与旋喷桩或者旋喷桩与支护桩之间的第二桩间土护壁施工;通过本发明的支护方法的实施形成了较为完善的支护体系。

Figure 202210331946

The invention relates to a soil protection and descending construction method, including S1: construction preparation; S2: construction of supporting piles; S3: construction of rotary jet piles between adjacent supporting piles; S4: construction on the top of the supporting piles Crown beam construction; S5: Retaining wall construction is carried out from the top of the foundation pit supporting pile crown beam to the ground, S6: The first anchor cable construction; S7: After the first anchor cable construction is completed, the rotary spray pile is carried out. Construction of the soil retaining wall between the first piles above; S8: Construction of the second anchor cable; S9: After the construction of the second anchor cable is completed, carry out the construction between the sprayed piles and the sprayed piles or between the sprayed piles and the supporting piles. The second soil retaining wall between piles is constructed; a relatively perfect supporting system is formed through the implementation of the supporting method of the present invention.

Figure 202210331946

Description

一种土护降施工方法A kind of soil protection and descending construction method

技术领域technical field

本发明属于建筑施工技术领域,尤其涉及一种土护降施工方法。The invention belongs to the technical field of building construction, and in particular relates to a soil protection and descending construction method.

背景技术Background technique

随着我国经济的高速发展,土地资源越来越紧缺,建筑工程越来越趋向地下空间发展,对于黏质粉土素填土层地质,可以根据勘察最大勘探深度(45.00m)范围内的地层,划分为人工堆积层和第四纪沉积层两大类,并按地层岩性及工程特性进一步划分为7个大层及亚层,人工堆积层以下为第四纪沉积的黏质粉土、砂质粉土层,粉质黏土、重粉质黏土层;粉砂层;粉质黏土、重粉质黏土层,黏质粉土、砂质粉土层;黏土、重粉质黏土层及黏质粉土、砂质粉土层;粉质黏土、重粉质黏土层及黏质粉土、砂质粉土层及粗砂层;黏土层;对于黏质粉土素填土层地质,基坑的有效支护将关系工程施工的安全、质量和进度,而该黏质粉土素填土层地质,造成可选择的支护形式有限,同时经试验研究发现,该地质条件下,支护桩成孔、成桩施工时难度大。With the rapid development of my country's economy, land resources are becoming more and more scarce, and construction projects are increasingly developing in underground spaces. For the geology of the clayey silt plain fill layer, the strata within the maximum exploration depth (45.00m) can be investigated according to the It is divided into two categories: artificial accumulation layer and Quaternary sedimentary layer, and is further divided into 7 large layers and sublayers according to the lithology and engineering characteristics of the stratum. Below the artificial accumulation layer is the Quaternary sedimentary clay silt, Sandy silt layer, silty clay, heavy silty clay layer; silt layer; silty clay, heavy silty clay layer, clay silt, sandy silt layer; clay, heavy silty clay layer and clay silt, sandy silt layer; silty clay, heavy silty clay layer and clayey silt, sandy silt layer and coarse sand layer; clay layer; The effective support of the pit will be related to the safety, quality and progress of the project construction, and the geology of the clayey silt fill layer will result in limited support forms that can be selected. It is very difficult for piles to form holes and piles during construction.

发明内容SUMMARY OF THE INVENTION

有鉴于此,本发明的目的在于提供一种土护降施工方法,以解决现有技术中黏质粉土素填土层地质,造成可选择的支护形式有限,同时经试验研究发现,该地质条件下,支护桩成孔、成桩施工时难度大的技术问题。In view of this, the purpose of the present invention is to provide a kind of soil protection and descending construction method, in order to solve the clayey silt plain filling layer geology in the prior art, resulting in limited support forms that can be selected. Under geological conditions, it is a difficult technical problem when supporting piles are formed into holes and piles.

为实现上述目的,本发明一种土护降施工方法所采用的技术方案是:In order to achieve the above object, the technical scheme adopted by a kind of soil protection and descending construction method of the present invention is:

一种土护降施工方法,包括:A soil protection and descending construction method, comprising:

S1:施工准备;S1: construction preparation;

研究施工区域的岩土工程勘察报告,了解土层的构造、分布、性能指标以及地下水分布情况,查明各类地下设施,周边建筑物的空间位置、结构形式、基础埋深、基础类型,判断支护对其影响,机械设备安装到位运转正常,所需各种材料全部按计划到位;Study the geotechnical engineering survey report of the construction area, understand the structure, distribution, performance index and groundwater distribution of the soil layer, identify various underground facilities, the spatial location, structural form, foundation depth, foundation type of the surrounding buildings, and judge The impact of the support on it is that the mechanical equipment is installed in place and operates normally, and all the required materials are in place as planned;

S2:当施工场地满足支护桩开挖条件,进行支护桩施工,安照设计桩位进行支护桩浇筑施工;S2: When the construction site meets the support pile excavation conditions, the support pile construction is carried out, and the support pile pouring construction is carried out according to the design of the pile position;

S3: 支护桩施工完成48h后,在相邻支护桩之间进行旋喷桩施工,旋喷桩顶部低于支护桩顶部下方;S3: 48h after the construction of the supporting piles is completed, the rotary jetting pile construction is carried out between the adjacent supporting piles, and the top of the rotary jetting piles is lower than the bottom of the top of the supporting piles;

S4:在旋喷桩施工完成后,在支护桩的顶部进行冠梁施工,支护桩主筋伸入冠梁且与冠梁S4: After the construction of the rotary jetting pile is completed, the crown beam construction is carried out on the top of the supporting pile, and the main reinforcement of the supporting pile extends into the crown beam and is connected with the crown beam.

钢筋连接,冠梁支撑在支护桩顶部且将各个支护桩连接,且冠梁上方设置预留钢筋;Rebar connection, the crown beam is supported on the top of the supporting piles and each supporting pile is connected, and the reserved steel bars are set above the crown beam;

S5:在基坑支护桩冠梁顶至地面范围进行挡土墙施工,挡土墙包括间隔设置的构造柱,构造柱的主筋与冠梁预留钢筋连接;S5: The retaining wall is constructed from the top of the crown beam of the foundation pit supporting pile to the ground. The retaining wall includes structural columns arranged at intervals, and the main bars of the structural columns are connected with the reserved steel bars of the crown beam;

S6:第一道锚索施工;S6: Construction of the first anchor cable;

S7:当第一道锚索施工完成后,进行位于旋喷桩上方的第一桩间土护壁施工;S7: After the construction of the first anchor cable is completed, carry out the construction of the first soil retaining wall between the piles above the rotary jetted piles;

S8:第二道锚索施工;S8: Construction of the second anchor cable;

S9:当第二道锚索施工完成后,进行旋喷桩与旋喷桩或者旋喷桩与支护桩之间的第二桩间土护壁施工。S9: After the construction of the second anchor cable is completed, carry out the construction of the second inter-pillar soil retaining wall between the rotary jetting pile and the rotary jetting pile or the rotary jetting pile and the supporting pile.

有益效果:本发明的一种土护降施工方法通过支护桩的设置、旋喷桩的施工,然后在支护桩的顶部进行冠梁的浇筑施工,然后在冠梁上砌筑挡土墙,在挡土墙施工完成后,进行锚索施工,锚索施工完成后,通过在旋喷桩上方的第一桩间土护壁的施工以及旋喷桩与旋喷桩或者旋喷桩与支护桩之间的第二桩间土护壁施工,形成基坑的较为完善的支护形式,而且通过本发明的支护方法的实施形成了较为完善的支护体系,保证了基坑具有较佳的支护效果。Beneficial effect: a soil protection and descending construction method of the present invention is through the setting of supporting piles, the construction of rotary jetting piles, the pouring construction of crown beams on the top of the supporting piles, and the building of retaining walls on the crown beams. , After the construction of the retaining wall is completed, the anchor cable construction is carried out. After the anchor cable construction is completed, the construction of the soil protection wall between the first piles above the rotary jetting pile and the rotary jetting pile and the rotary jetting pile or the rotary jetting pile and the support The construction of the second inter-pillar soil retaining wall between the piles forms a relatively complete supporting form of the foundation pit, and a relatively complete supporting system is formed through the implementation of the supporting method of the present invention, which ensures that the foundation pit has a better supporting structure. Support effect.

进一步的,在S2支护桩施工中:Further, in the construction of S2 supporting piles:

(1)先进行作业面高程测量、施工放线,确定支护桩位点;(1) First carry out the elevation measurement of the working face, the construction setting out, and determine the position of the supporting pile;

(2)钢筋笼加工,制作好的钢筋笼分类堆放,使用标识牌标明使用部位,经验收合格后方可使用;(2) Reinforcement cages are processed, and the prepared reinforcement cages are classified and stacked, and signs are used to indicate the parts of use, and they can be used only after they are qualified;

(3)钻进成孔;(3) Drilling into a hole;

根据设计桩长及施工作业面标高计算孔深,在钻机机身或钻杆的相应位置作孔深标记;Calculate the hole depth according to the design pile length and the elevation of the construction work surface, and mark the hole depth at the corresponding position of the drilling rig body or drill pipe;

钻机移至桩位点对准支护桩桩位下放钻头,钻机塔身保持垂直,用经纬仪或线锤量测钻杆垂直度,垂直度偏差控制在1%以内;Move the drilling rig to the pile position and align the supporting pile position, lower the drill bit, keep the tower body of the drilling rig vertical, measure the verticality of the drill pipe with theodolite or line hammer, and control the verticality deviation within 1%;

(4)压灌混凝土;(4) Press-filled concrete;

钻头到达设计标高后,钻杆停止钻动并开始泵送混凝土,泵送混凝土至孔底,一边泵送混凝土一边提钻,提钻速率与泵送量相匹配,保证钻头始终埋在混凝土面以下;成桩过程连续进行,直至桩体混凝土灌至孔口地面;After the drill bit reaches the design elevation, the drill pipe stops drilling and starts to pump concrete, pump the concrete to the bottom of the hole, and lift the drill while pumping the concrete. ; The pile forming process is continuously carried out until the concrete of the pile body is poured into the ground of the orifice;

(5)钢筋笼植入;(5) Reinforcement cage implantation;

混凝土压灌至施工控制标高并清理桩孔周围的弃土后,将钢筋笼对准孔位中心进行植入钢筋笼施工;钢筋笼中心对准桩位中心,控制钢筋笼的垂直度;先通过钢筋笼自重使其下沉,下沉停止时,开动震动器,通过震动器使钢筋笼继续下沉,用水准仪控制钢筋笼放置的高度,到达设计标高后,固定钢筋笼。After the concrete is pressed to the construction control level and the spoil around the pile hole is cleaned, the reinforcement cage is aligned with the center of the hole position for the construction of the reinforcement cage; the center of the reinforcement cage is aligned with the center of the pile position to control the verticality of the reinforcement cage; The self-weight of the rebar cage makes it sink. When the sinking stops, the vibrator is activated, and the rebar cage continues to sink through the vibrator. The height of the rebar cage is controlled by a level. After reaching the design elevation, the rebar cage is fixed.

有益效果:支护桩的施工更加合理,保证了支护桩具有较高的成型质量。Beneficial effects: the construction of the supporting piles is more reasonable, and the high forming quality of the supporting piles is ensured.

进一步的,在S3中,在相邻支护桩之间设置两根旋喷桩,两侧相邻的支护桩施工完成48h后,对旋喷桩进行测量放线,然后旋喷桩机就位,校正孔位、钻杆垂直度,进行引孔操作,然后在引孔中下注浆管,由下而上进行高压旋喷注浆,直至孔口返浆,停止喷射的位置高于帷幕设计顶面lm。Further, in S3, two rotary jetting piles are set between adjacent supporting piles. After the construction of the adjacent supporting piles on both sides is completed for 48 hours, the rotary jetting piles are measured and set out, and then the rotary jetting pile machine is position, correct the hole position and the verticality of the drill pipe, carry out the drilling operation, and then put the grouting pipe in the leading hole, and perform high-pressure rotary jet grouting from bottom to top until the orifice returns to the slurry, and the position of stopping jetting is higher than the curtain. Design top lm.

有益效果:旋喷桩的设置更加合理,旋喷桩的设置具有较高的成型质量,旋喷桩能够与支护桩配合形成基坑周侧结构强度较强的支护基础。Beneficial effects: the setting of the rotary jetting pile is more reasonable, the setting of the rotary jetting pile has high forming quality, and the rotary jetting pile can cooperate with the supporting pile to form a supporting foundation with strong peripheral structure of the foundation pit.

进一步的,在S4冠梁施工中:Further, in the construction of S4 crown beam:

(1)凿桩头及清土;(1) Chisel pile head and clear soil;

凿除支护桩顶浮浆及多余桩身混擬土,剔除支护桩桩主筋上残余混凝土,保证支护桩主筋伸入冠梁的长度满足设计要求,将主筋与冠梁钢筋进行搭接焊接;Chisel off the floating slurry on the top of the supporting pile and the mixed soil of the redundant pile body, remove the residual concrete on the main reinforcement of the supporting pile, ensure that the length of the main reinforcement of the supporting pile extending into the crown beam meets the design requirements, and overlap the main reinforcement with the reinforcement of the crown beam welding;

(2)进行冠梁支模;在支护桩之间进行冠梁支模,并在支模结束后清理模板与混凝土的接触面并涂刷隔离剂;(2) Carry out the crown beam formwork; carry out the crown beam formwork between the supporting piles, and clean the contact surface between the formwork and the concrete and apply the release agent after the formwork is completed;

(3)混凝土浇筑、养护;(3) Concrete pouring and curing;

冠梁混凝土连续浇筑,混凝土浇筑完毕后12h以内对混凝土加以覆盖并保温养护,混凝土保温养护时间大于等于7天。The crown beam concrete is continuously poured, and the concrete is covered within 12 hours after the concrete is poured, and the heat preservation and curing time of the concrete is more than or equal to 7 days.

有益效果:冠梁的设置在支护桩的顶部形成连接,使各个支护桩在顶部形成连接,从而是支护桩、冠梁形成稳定的支护基础。Beneficial effects: the crown beams are arranged at the top of the supporting piles to form a connection, so that each supporting pile is connected at the top, so that the supporting piles and the crown beams form a stable supporting foundation.

进一步的,在S5挡土墙施工中:分层砌筑挡土墙,挡土墙构造柱混凝土强度达到设计强度的70%后进行回填土。Further, in the construction of the S5 retaining wall: the retaining wall is built in layers, and the concrete strength of the structural column of the retaining wall reaches 70% of the design strength before backfilling.

有益效果:保证挡土墙具有较高的结构稳定性。Beneficial effects: ensure that the retaining wall has high structural stability.

在S7第一桩间土护壁施工中:During the construction of the soil retaining wall between the first piles of S7:

(1)第一桩间土护壁施工,在支护桩的相对的一侧钻孔,钻孔与支护桩延伸方向垂直设置,将两段横压筋插入钻孔中再搭接焊接形成横向限位杆,在旋喷桩顶部对应固定竖向限位杆,竖向限位杆与横向限位杆焊接连接形成限位网,然后将钢筋网铺设在限位钢的背向基坑的一面;(1) For the construction of the soil retaining wall between the first piles, drill holes on the opposite side of the supporting piles. The drilled holes are set perpendicular to the extension direction of the supporting piles. The limit rod is fixed on the top of the rotary jet pile correspondingly. The vertical limit rod and the horizontal limit rod are welded and connected to form a limit net, and then the steel mesh is laid on the side of the limit steel that faces away from the foundation pit. ;

(2)面层喷射混凝;(2) Surface spray coagulation;

喷射作业应从上向下分段进行,同一分段喷射顺序应自下而上;喷射时喷头与受喷面应保持垂直,喷射射距0.6~1.0m。喷射厚度为80mm强度为C20的细石混凝土。The spraying operation should be carried out in sections from top to bottom, and the spraying sequence of the same section should be from bottom to top; when spraying, the nozzle and the sprayed surface should be kept vertical, and the spraying distance should be 0.6~1.0m. Fine stone concrete with a thickness of 80mm and a strength of C20 is sprayed.

有益效果:在冠梁下方形成密实的第一桩间土护壁结构,既保证了第一桩间土护壁结构能够对基坑侧壁进行较为完善的支护,而且还能够保证护壁具有较高的支护强度。Beneficial effect: The dense first inter-pile soil retaining wall structure is formed under the crown beam, which not only ensures that the first inter-pile soil retaining wall structure can support the side walls of the foundation pit relatively well, but also ensures that the retaining wall has a higher level of protection. Support strength.

在S9第二桩间土护壁施工中:In the construction of the soil retaining wall between the second piles of S9:

(1)第二桩间土护壁施工时,在支护桩与旋喷桩相对的一侧或者旋喷桩与旋喷桩相对的一侧钻孔,将两段横压筋插入钻孔中再搭接焊接形成横向限位杆,然后将钢筋网铺设在限位钢的背向基坑的一面;(1) During the construction of the soil retaining wall between the second piles, drill holes on the opposite side of the supporting piles and the jetting piles or on the opposite side of the jetting piles and the jetting piles. Lap welding to form a lateral limit rod, and then lay the reinforcing mesh on the side of the limit steel facing away from the foundation pit;

(2)面层喷射混凝;(2) Surface spray coagulation;

喷射作业应从上向下分段进行,同一分段喷射顺序应自下而上;喷射时喷头与受喷面应保持垂直,喷射射距0.6-1.0m。喷射厚度为80mm强度为C20的细石混凝土。The spraying operation should be carried out in sections from top to bottom, and the spraying sequence of the same section should be from bottom to top; when spraying, the nozzle and the sprayed surface should be kept vertical, and the spraying distance should be 0.6-1.0m. Fine stone concrete with a thickness of 80mm and a strength of C20 is sprayed.

有益效果:在冠梁下方形成密实的第二桩间土护壁结构,既保证了第二桩间土护壁结构能够对基坑侧壁进行较为完善的支护,而且还能够保证护壁具有较高的支护强度。Beneficial effect: A dense second inter-pile soil retaining wall structure is formed under the crown beam, which not only ensures that the second inter-pile soil retaining wall structure can better support the sidewall of the foundation pit, but also ensures that the retaining wall has a high Support strength.

在进行支护桩施工前,进行距离支护桩20m以外的土方开挖,由内向外开挖,并进行1:1放坡,以使支护桩满足开挖条件。Before the construction of the supporting piles, excavate the earthwork 20m away from the supporting piles, excavate from the inside to the outside, and carry out 1:1 grading, so that the supporting piles meet the excavation conditions.

有益效果:支护桩施工前进行的土方开挖,保证支护桩满足开挖条件。Beneficial effects: The earthwork excavation carried out before the construction of the support piles ensures that the support piles meet the excavation conditions.

附图说明Description of drawings

图1是本发明的一种土护降施工方法的施工流程图;Fig. 1 is the construction flow chart of a kind of soil protection and descending construction method of the present invention;

图2是本发明的一种土护降施工方法形成的支护结构侧视图;2 is a side view of a supporting structure formed by a soil protection and descending construction method of the present invention;

图3是图2的一种土护降施工方法形成的支护结构的主视图。FIG. 3 is a front view of the support structure formed by the soil protection and descending construction method of FIG. 2 .

附图标记:1-支护桩;2-旋喷桩;3-冠梁;4-挡土墙;5-锚索;6-第一桩间土护壁;7-第二桩间土护壁;8-横向限位杆;9-竖向限位杆;10-钢筋网;11-构造柱;12-横压筋。Reference signs: 1-supporting pile; 2-spraying pile; 3-crown beam; 4-retaining wall; 5-anchor cable; 6-soil protection wall between the first piles; 7-soil protection wall between the second piles; 8- horizontal limit rod; 9- vertical limit rod; 10- steel mesh; 11- structural column; 12- transverse pressure bar.

具体实施方式Detailed ways

下面结合附图及具体实施方式对本发明的一种土护降施工方法作进一步详细描述:=A kind of soil protection and descending construction method of the present invention is described in further detail below in conjunction with the accompanying drawings and specific embodiments:=

如图1所示,本发明的土护降施工方法包括:As shown in Figure 1, the soil protection and descending construction method of the present invention comprises:

S1:施工准备;S1: construction preparation;

研究施工区域的岩土工程勘察报告,了解土层的构造、分布、性能指标以及地下水分布情况,查明各类地下设施,周边建筑物的空间位置、结构形式、基础埋深、基础类型,判断支护对其影响,机械设备安装到位运转正常,所需各种材料全部按计划到位。Study the geotechnical engineering survey report of the construction area, understand the structure, distribution, performance index and groundwater distribution of the soil layer, identify various underground facilities, the spatial location, structural form, foundation depth, foundation type of the surrounding buildings, and judge The support is affected, the mechanical equipment is installed in place and operates normally, and all the required materials are in place as planned.

工程场区台地潜水天然动态类型属渗入-迳流、蒸发型,主要接受地下水侧向迳流、大气降水入渗及管道渗漏等方式补给,以地下水侧向迳流及蒸发为主要排泄方式;其水位年动态变化规律一般为:6月份~9月份水位较高,其他月份水位相对较低,水位年变幅一般为1.0~2.0m左右。The natural dynamic type of platform diving in the project site is infiltration-flow and evaporation type, which is mainly recharged by groundwater lateral flow, atmospheric precipitation infiltration and pipeline leakage, and groundwater lateral flow and evaporation are the main discharge methods; The annual dynamic variation of the water level is generally as follows: the water level is relatively high from June to September, and the water level in other months is relatively low. The annual variation of the water level is generally about 1.0 to 2.0 m.

工程基坑降水的主要目的是将地下水控制在基坑开挖深度以下,以保证土方开挖及结构干槽作业。The main purpose of the foundation pit dewatering is to control the groundwater below the excavation depth of the foundation pit, so as to ensure the earthwork excavation and structural dry groove operations.

基坑地下水控制采用止水帷幕+坑内疏干的方案进行处理,基坑采用高压旋喷桩2止水帷幕止水,成桩直径700mm,间距500mm,桩长13.2m;在基坑内部设置疏干井以疏干基坑内部的地下水,疏干井采用管井,孔径φ600,间距20.0m×20.0m,井深17.0m,井管为直径400mm的水泥砾石滤水管;井管外填入2~10mm砾石滤料。The groundwater control of the foundation pit is treated by the scheme of water-stop curtain + dredging in the pit. The foundation pit adopts the high-pressure rotary jet pile 2 water-stop curtain to stop the water, the pile diameter is 700mm, the spacing is 500mm, and the pile length is 13.2m; The dry well is used to drain the groundwater inside the foundation pit. The drain well is a tube well with a diameter of φ600, a spacing of 20.0m × 20.0m, and a well depth of 17.0m. The well tube is a cement gravel water filter tube with a diameter of 400mm; the outside of the well tube is filled with 2-10mm Gravel filter media.

S2:当施工场地满足支护桩开挖条件,进行支护桩施工,安照设计桩位进行支护桩浇筑施工。在S2支护桩施工中:S2: When the construction site meets the support pile excavation conditions, the support pile construction is carried out, and the support pile pouring construction is carried out according to the design of the pile position. In the construction of S2 supporting piles:

在进行支护桩1施工前,进行距离支护桩20m以外的第一层土方开挖,也即进行基坑四周第一层土方开挖,并由内向外开挖,并进行1:1放坡,以使支护桩1满足施工条件,施工场地满足桩机、罐车等安全行走的要求,作业面标高高于支护桩1设计桩顶标高0.5m。当支护桩1满足施工条件后,按照以下步骤施工:Before the construction of supporting pile 1, excavate the first layer of earthwork 20m away from the supporting pile, that is, excavate the first layer of earthwork around the foundation pit, excavate from the inside to the outside, and carry out a 1:1 excavation. Slope, so that the supporting pile 1 can meet the construction conditions and the construction site can meet the requirements of safe walking of pile drivers and tankers. After the supporting pile 1 meets the construction conditions, the construction shall be carried out according to the following steps:

如图2和图3所示:As shown in Figure 2 and Figure 3:

(1)先进行作业面高程测量、施工放线,确定支护桩1位点。(1) First, carry out the elevation measurement of the working face, and set out the construction line, and determine the 1st position of the supporting pile.

支护桩1施工前,测量施工作业面标高,计算自施工作业面起算的钻孔深度。Before the construction of the support pile 1, measure the elevation of the construction work surface, and calculate the drilling depth from the construction work surface.

支护桩1的定位标志理设应可靠稳固,桩位放线偏差不应大于70mm。放线结束后会同监理共同验线,确认无误并签字认可后方可进行下一工序。The positioning mark of the supporting pile 1 should be reliable and stable, and the deviation of the pile position should not be greater than 70mm. After the line is laid out, the line will be inspected together with the supervisor, and the next process can be carried out only after confirming that it is correct and signing for approval.

(2)钢筋笼加工,制作好的钢筋笼分类堆放,使用标识牌标明使用部位,经验收合格后方可使用。(2) Reinforcement cages are processed, and the prepared reinforcement cages are classified and stacked, and the use part is marked with a signboard, and it can be used only after the acceptance is qualified.

(3)钻进成孔;(3) Drilling into a hole;

根据设计桩长及施工作业面标高计算孔深,在钻机机身或钻杆的相应位置作孔深标记;Calculate the hole depth according to the design pile length and the elevation of the construction work surface, and mark the hole depth at the corresponding position of the drilling rig body or drill pipe;

钻机移至桩位点对准支护桩1桩位下放钻头,钻机塔身保持垂直,用经纬仪或线锤量测钻杆垂直度,垂直度偏差控制在1%以内。Move the drilling rig to the pile position, align the supporting pile 1, and lower the drill bit. The tower body of the drilling rig is kept vertical. Use the theodolite or line hammer to measure the verticality of the drill pipe, and the verticality deviation is controlled within 1%.

(4)压灌混凝土;(4) Press-filled concrete;

钻头到达设计标高后,钻杆停止钻动并开始泵送混凝土,泵送混凝土至孔底,一边泵送混凝土一边提钻,提钻速率与泵送量相匹配,保证钻头始终埋在混凝土面以下;成桩过程连续进行,直至桩体混凝土灌至孔口地面。After the drill bit reaches the design elevation, the drill pipe stops drilling and starts to pump concrete, pump the concrete to the bottom of the hole, and lift the drill while pumping the concrete. ; The pile forming process is continued until the concrete of the pile body is poured to the ground of the orifice.

(5)钢筋笼植入;(5) Reinforcement cage implantation;

混凝土压灌至施工控制标高并清理桩孔周围的弃土后,将钢筋笼对准孔位中心进行植入钢筋笼施工;钢筋笼中心对准桩位中心,控制钢筋笼的垂直度;先通过钢筋笼自重使其下沉,下沉停止时,开动震动器,通过震动器使钢筋笼继续下沉,用水准仪控制钢筋笼放置的高度,到达设计标高后,固定钢筋笼。After the concrete is pressed to the construction control level and the spoil around the pile hole is cleaned, the reinforcement cage is aligned with the center of the hole position for the construction of the reinforcement cage; the center of the reinforcement cage is aligned with the center of the pile position to control the verticality of the reinforcement cage; The self-weight of the rebar cage makes it sink. When the sinking stops, the vibrator is activated, and the rebar cage continues to sink through the vibrator. Use a level to control the height of the rebar cage. After reaching the design elevation, fix the rebar cage.

成型后的支护桩1桩径800mm,桩长18m,桩间距1.5m。The formed supporting pile 1 has a pile diameter of 800mm, a pile length of 18m, and a pile spacing of 1.5m.

S3: 支护桩1施工完成48h后,在相邻支护桩1之间进行旋喷桩2施工,旋喷桩2顶部低于支护桩1顶部下方。S3: 48 hours after the completion of the construction of the supporting pile 1, the construction of the rotary jetting pile 2 is carried out between the adjacent supporting piles 1, and the top of the rotary jetting pile 2 is lower than the bottom of the top of the supporting pile 1.

在相邻支护桩1之间设置两根旋喷桩2,两侧相邻的支护桩1施工完成48h后,对旋喷桩2进行测量放线,然后旋喷桩机就位,校正孔位、钻杆垂直度,进行引孔操作,然后在引孔中下注浆管,由下而上进行高压旋喷注浆,直至孔口返浆,停止喷射的位置高于帷幕设计顶面lm。Two rotary jetting piles 2 are set between adjacent supporting piles 1. After the construction of the adjacent supporting piles 1 on both sides is completed for 48 hours, the rotary jetting pile 2 is measured and set out, and then the rotary jetting pile machine is in place to calibrate The hole position and the verticality of the drill pipe, carry out the drilling operation, and then put the grouting pipe in the leading hole, and perform high-pressure rotary jet grouting from bottom to top until the orifice returns to the slurry, and the position where the jet stops is higher than the top surface of the curtain design lm.

旋喷桩2桩径700mm,桩长13.2m,间距0.5m。Rotary spray pile 2 has a pile diameter of 700mm, a pile length of 13.2m, and a spacing of 0.5m.

帷幕桩堵漏方法包括:Curtain pile plugging methods include:

(1)桩间渗水可采用"支模封堵法"法进行封堵,方法如下所述:(1) The seepage between the piles can be blocked by the "support form plugging method" method. The method is as follows:

在支护桩1中心偏外位置处在桩上打孔植钢筋,桩间设置

Figure DEST_PATH_IMAGE001
16@200单层钢筋网片,渗漏点高度3m以下的采用木模板在外侧进行单侧支模。漏点高度大于3m的采用喷射C20细石混凝土封堵,混凝土强度达到要求后将模板拆除。Drill holes and plant steel bars on the piles at the outer position of the center of the supporting pile 1, and set up between the piles.
Figure DEST_PATH_IMAGE001
16@200 single-layer reinforced mesh, the leakage point height is less than 3m, and the wooden formwork is used for single-side formwork on the outside. If the leak height is greater than 3m, use the sprayed C20 fine stone concrete to block, and remove the formwork after the concrete strength meets the requirements.

(2)止水帷幕渗漏但漏水量不大且夹带少量泥砂时,可采用"内堵"的方法进行封堵,方法如下所述:(2) When the water-stop curtain is leaking but the amount of water leakage is not large and a small amount of mud and sand is entrained, the method of "internal plugging" can be used for plugging, and the method is as follows:

1)漏点处理:清除漏水部位围护桩间的泥土和杂质,将渗漏处凿成反楔型孔洞,两侧凿到围护桩边,将围护桩表面泥土清理干净。1) Leakage point treatment: remove the soil and impurities between the enclosure piles at the leaking site, chisel the leakage area into an inverse wedge-shaped hole, chisel both sides to the side of the enclosure pile, and clean the soil on the surface of the enclosure pile.

2)拌制水泥:快速堵漏必须选用"双快速凝水泥",将水泥与水按1:0.2的比例反复揉捏成团,封口时按水泥:水=1:0.3搅拌成均匀的腻子状,双快水泥初凝时间为0.2h,终凝时间1.5h。2) Mixing cement: "Double quick-setting cement" must be used for quick plugging. The cement and water are repeatedly kneaded into a ball at a ratio of 1:0.2. When sealing, press cement:water=1:0.3 to stir into a uniform putty-like shape. , the initial setting time of double-fast cement is 0.2h, and the final setting time is 1.5h.

3)塞入填充物:如缝隙中泥沙流失较多,内部出现较大孔洞时,将旧棉絮或破布塞入孔洞内,旧棉絮或破布既可以阻止泥沙流失防止孔洞扩大,又可以透水。3) Insert filler: If there is a lot of sediment loss in the gap and there are large holes inside, put old cotton wool or rags into the holes. The old cotton wool or rags can not only prevent the loss of sediment and prevent the holes from expanding, but also Water permeable.

4)插入导管:在楔形孔洞底部将拌制好的水泥平铺一层,厚度约为孔洞的三分之一,快速将事先准备好的长度约1.5m的Φ25塑料管(管径根据漏点水流量调整)一端插入到漏水点深处,将水管压入平铺的水泥内,确认漏水点水流从管内流走时继续铺拌制好的水泥固定导水管。4) Insert the catheter: spread the mixed cement in a layer at the bottom of the wedge-shaped hole, the thickness is about one-third of the hole, and quickly put the prepared Φ25 plastic pipe with a length of about 1.5m (pipe diameter according to the leak point) Water flow adjustment) insert one end into the depth of the leaking point, press the water pipe into the tiled cement, confirm that the water flow at the leaking point flows away from the pipe and continue to lay the mixed cement fixed aqueduct.

5)封住漏水口:将拌好的水泥团迅速塞进渗水口,将插入的导水管周围全部用水泥团封住。确认漏水全部由导水管排出其他部位不再渗水后,在孔洞周围延出10cm的范围再刮压一层,如果流水压力较大时,可采取在围护桩打膨胀螺丝加钢筋网进行加固,固定好导管后在导管端部塞入滤网过滤泥沙,保证管内只流水不带走泥沙。5) Seal the leaking hole: quickly plug the mixed cement mass into the water seepage opening, and seal the surrounding of the inserted aqueduct with cement mass. After confirming that all the leaking water is discharged by the aqueduct and no longer seeping into other parts, extend a range of 10cm around the hole and then scrape a layer. After the pipe is fixed, insert a filter at the end of the pipe to filter the sediment to ensure that only water flows in the pipe and does not take away the sediment.

6)养护:养护不小于4h小时,如天气炎热,适当喷水养护。6) Maintenance: maintenance is not less than 4 hours, such as hot weather, appropriate water spray maintenance.

7)扎管止水:待水泥硬化满足强度(20MPa以上)要求后,将塑料导水管用铅丝扎死止水。有时由于水压力较大,扎管后水可能从其他部位渗漏出来,依照上述方法重新进行引流封堵直至堵为止。7) Tie the pipe to stop the water: After the cement hardens to meet the strength (above 20MPa) requirements, tie the plastic aqueduct with lead wire to stop the water. Sometimes due to the high water pressure, the water may leak out from other parts after tying the pipe, and re-drain and block it according to the above method until it is blocked.

(3)止水帷幕渗漏且漏水量较大且夹带泥沙时,必须采用"外封"的方法进行封堵,具体做法如下:(3) When the water-stop curtain is leaking and the amount of water leakage is large and the sediment is entrained, the method of "outer sealing" must be used for sealing. The specific methods are as follows:

1)在基坑内侧找到漏水源头,清理漏水点里侧及孔洞周边,修挖时把渗漏点挖成里大外小的型式,便于安装干海带等膨胀材料,同时填塞棉絮减小漏水中携带的泥砂。1) Find the source of water leakage on the inside of the foundation pit, clean the inside of the leakage point and the surrounding of the hole, and dig the leakage point into a type with large inside and outside during excavation, so as to facilitate the installation of expanding materials such as dried kelp, and at the same time fill with cotton wool to reduce water leakage Carry mud.

2)回填做围堰:对漏点迅速回填土做围堰,严重漏水时浇筑混凝土做围堰,减少漏水对基坑的破坏。2) Backfill as cofferdam: quickly backfill soil for leakage as cofferdam, and pour concrete as cofferdam in case of serious water leakage to reduce the damage to foundation pit caused by water leakage.

3)钻进成孔:采用汽车吊将钻机在漏水点处就位,调整好垂直度后开始钻孔,钻孔深度为漏水点下1m处。3) Drilling into a hole: use a truck crane to place the drilling rig at the leaking point, adjust the verticality and start drilling, and the drilling depth is 1m below the leaking point.

4)安放注浆管:钻到深度后提升钻杆,安放注浆管(φ25镀锌管),安放注浆管过程中如遇到砂土层出现钻孔塌方,采用改装的平板振捣器将注浆管压入预定深度,在注浆管上连接带有两个阀门的三通,分别用来连接水泥注浆泵和水玻璃注浆泵。4) Placing the grouting pipe: after drilling to the depth, lift the drill pipe and place the grouting pipe (φ25 galvanized pipe). If the sand layer is encountered during the process of placing the grouting pipe and the borehole collapses, use a modified plate vibrator. The grouting pipe is pressed into a predetermined depth, and a tee with two valves is connected to the grouting pipe, which are respectively used to connect the cement grouting pump and the water glass grouting pump.

5)注水泥浆:按照水灰比0.7:1搅拌水泥浆,先注入水泥浆确认注浆管是否在漏水通道附近,如注浆过程中持续注浆未流出水泥浆,可适当提升注浆管15~20cm,漏水点流出水泥浆后才能确认找到漏水通道。5) Cement grouting: Mix the cement slurry according to the water-cement ratio of 0.7:1, and inject the cement slurry first to confirm whether the grouting pipe is near the leaking channel. ~20cm, the leaking channel can only be confirmed after the cement slurry flows out of the leaking point.

6)双液注浆:双液注浆是静压注浆中的一种,即利用液压通过注浆管把水泥溶液和水玻璃短时间内混合均匀生成水泥胶,然后注入地层中。利用水泥胶凝结速度快,强度提高快的特点封堵渗漏通道,达到堵漏目的。6) Two-liquid grouting: Two-liquid grouting is a kind of static pressure grouting, that is, using hydraulic pressure to mix cement solution and water glass evenly in a short time through a grouting pipe to form cement glue, and then inject it into the formation. Using the characteristics of fast setting speed and fast strength improvement of cement glue, the leakage channel is blocked to achieve the purpose of plugging.

7)注浆加固7) Grouting reinforcement

①静压注浆:漏水点堵住后24h后静压注浆加固,加固点布点沿止水帷幕方向距离堵漏点左右各0.5m位置设置一个加固点,注浆深度为漏水点下1m,流量为8~12L/min,加固时注浆压力在1~1.5MPa以上。①Hydrostatic grouting: 24 hours after the water leakage point is blocked, static pressure grouting is used for reinforcement. The reinforcement points are arranged along the direction of the water-stop curtain, and a reinforcement point is set at a distance of 0.5m to the left and right of the leakage point. The grouting depth is 1m below the leakage point. The flow rate is 8~12L/min, and the grouting pressure is above 1~1.5MPa during reinforcement.

②劈裂注浆:静压注浆加固时,由于下部土层密实度大浆液不易扩散,且注浆管与钻孔之间孔隙较大,注浆时返浆严重,因此采用劈裂注浆,钻孔过程中注入陶土粉浆液润滑钻杆、防止堵孔,同时减少放入劈裂注浆管时的阻力,放入劈裂注浆管后再其上部1m处采用水泥浆进行封堵密实,2天后在劈裂管内插入注浆花管,分层(50cm)进行注浆,注浆压力为2MPa,直至注满返浆为止。②Split grouting: When the hydrostatic grouting is used for reinforcement, due to the large density of the lower soil layer, the slurry is not easy to spread, and the pores between the grouting pipe and the borehole are large, and the grouting is serious during grouting. Therefore, split grouting is used. During the drilling process, the clay powder slurry is injected to lubricate the drill pipe, prevent the hole from being blocked, and reduce the resistance when the split grouting pipe is placed. , 2 days later, insert the grouting flower tube into the split tube, and perform grouting in layers (50cm), and the grouting pressure is 2MPa until it is full and returns to the grouting.

S4:在旋喷桩2施工完成后,在支护桩1的顶部进行冠梁施工,支护桩1主筋伸入冠梁3且与冠梁3钢筋连接,冠梁3支撑在支护桩1顶部且将各个支护桩1连接,且冠梁3上方设置预留钢筋。S4: After the construction of the rotary jetting pile 2 is completed, the crown beam construction is carried out on the top of the supporting pile 1. The main reinforcement of the supporting pile 1 extends into the crown beam 3 and is connected with the reinforcement of the crown beam 3, and the crown beam 3 is supported on the supporting pile 1. At the top, each supporting pile 1 is connected, and reserved steel bars are arranged above the crown beam 3 .

具体的,包括:Specifically, including:

(1)凿桩头及清土;(1) Chisel pile head and clear soil;

凿除支护桩1顶浮浆及多余桩身混擬土,剔除支护桩1桩主筋上残余混凝土,保证支护桩1主筋伸入冠梁3的长度满足设计要求,将主筋与冠梁3钢筋进行搭接焊接。Chisel off the floating slurry on the top of the supporting pile 1 and the excess pile body mixed with simulated soil, remove the residual concrete on the main reinforcement of the supporting pile 1, ensure that the length of the main reinforcement of the supporting pile 1 into the crown beam 3 meets the design requirements, and connect the main reinforcement and the crown beam. 3 The steel bars are lap welded.

(2)进行冠梁3支模;在支护桩1之间进行冠梁3支模,并在支模结束后清理模板与混凝土的接触面并涂刷隔离剂。(2) Carry out three forms of crown and beam; carry out three forms of crown and beam between supporting piles 1, and clean the contact surface of formwork and concrete and apply release agent after the end of form support.

(3)混凝土浇筑、养护。(3) Concrete pouring and curing.

冠梁3混凝土连续浇筑,混凝土浇筑完毕后12h以内对混凝土加以覆盖并保温养护,混凝土保温养护时间大于等于7天。The crown beam 3 concrete is continuously poured, and the concrete is covered and maintained within 12 hours after the completion of the concrete pouring.

S5:在基坑支护桩1冠梁3顶至地面范围进行挡土墙4施工,挡土墙4包括间隔设置的构造柱11,构造柱11的主筋与冠梁3预留钢筋连接。S5: The retaining wall 4 is constructed in the range from the top of the crown beam 3 of the foundation pit supporting pile 1 to the ground.

分层砌筑挡土墙4,挡土墙4构造柱11混凝土强度达到设计强度的70%后进行回填土。The retaining wall 4 is built in layers, and the concrete strength of the structural column 11 of the retaining wall 4 reaches 70% of the design strength before backfilling.

在支护桩1施工、旋喷桩2施工、冠梁3施工、挡土墙4施工过程中,进行基坑第一层中心土方开挖。当挡土墙4施工完毕且第一层中心土方开挖完成后,进行基坑中心区域疏干井施工及降水,本发明中,基坑中心区域疏干井施工及降水为现有技术,在此不再赘述。During the construction of the supporting pile 1, the construction of the rotary jetting pile 2, the construction of the crown beam 3, and the construction of the retaining wall 4, the center earth excavation of the first layer of the foundation pit is carried out. When the construction of the retaining wall 4 is completed and the excavation of the first layer of central earthwork is completed, the construction of the dredging well and the dewatering in the central area of the foundation pit are carried out. This will not be repeated here.

S6:第一道锚索5施工;S6: Construction of the first anchor cable 5;

在第一道锚索5施工前,进行第二层四周土方开挖,然后进行第一道锚杆施工。Before the construction of the first anchor cable 5, earthwork excavation is carried out around the second layer, and then the first anchor rod construction is carried out.

在进行第一道锚索5施工时,包括一下步骤:During the construction of the first anchor cable 5, the following steps are included:

(1)成孔,锚索5施工采用套管跟进成孔工艺施工,套管跟进成孔工艺为现有技术,在此不再赘述。(1) Hole forming, the construction of the anchor cable 5 adopts the casing follow-up hole forming process, and the casing follow-up hole forming process is the prior art, which will not be repeated here.

(2)杆体制作,锚索杆体采用1860级Ф15.20钢绞线制作,杆体长度应比孔道长度大约l.0m。(2) The rod body is made. The anchor rod body is made of 1860 grade Ф15.20 steel strand. The length of the rod body should be about 1.0m longer than the length of the tunnel.

(3)杆体安放,挖土速度要与预应力锚索5施工速度相协调,清土至预应力锚索5标高下500mm,严禁超挖。(3) When the rod is placed, the excavation speed should be coordinated with the construction speed of the prestressed anchor cable 5. The soil should be cleared to 500mm below the elevation of the prestressed anchor cable 5. Over-excavation is strictly prohibited.

(4)注浆,锚索5须采用二次高压劈裂注浆工艺,终止注浆的压力不应小于1.5MPa,锚固段水泥用量不少于60kg/m,水泥浆强度为M20。二次高压劈裂注浆在一次注浆后12-24小时进行(具体间隔时间由锚固体强度达到5MPa左右进行控制)。二次高压劈裂注浆管应在锚固段开溢浆孔,溢浆孔的间距在锚固段端部1/3段每隔1.0m左右开一溢浆孔。用防水胶带将底部端口和开孔封闭,避免注浆管在一次注浆时进入浆液,导致二次高压劈裂注浆无法进行。(4) For grouting, the anchor cable 5 must adopt a secondary high-pressure split grouting process, the pressure for termination of grouting should not be less than 1.5MPa, the cement consumption in the anchoring section should not be less than 60kg/m, and the strength of the cement slurry should be M20. The second high pressure split grouting is carried out 12-24 hours after the first grouting (the specific interval is controlled by the anchor strength reaching about 5MPa). The secondary high-pressure splitting grouting pipe shall have an overflow hole in the anchoring section, and the spacing of the overflow hole shall be an overflow hole every 1.0m in the 1/3 section at the end of the anchoring section. Seal the bottom port and opening with waterproof tape to prevent the grouting pipe from entering the grout during the first grouting, resulting in the failure of the second high-pressure split grouting.

(5)腰梁加工与安装,支护桩1桩间的锚索5腰梁为2×I28b工字钢。两工字钢采用缀板连接,间距同支护桩1间距。(5) The waist beam processing and installation, the anchor cable 5 waist beams between the supporting piles 1 piles are 2×I28b I-beams. The two I-beams are connected by slats, and the spacing is the same as that of the supporting pile 1.

锚索5施工完毕后,进行张拉锁定。After the construction of the anchor cable 5 is completed, it is tensioned and locked.

S7:当第一道锚索5施工完成后,进行位于旋喷桩2上方的第一桩间土护壁6施工,第一桩间土护壁6如图3所示。S7: After the construction of the first anchor cable 5 is completed, the construction of the first inter-pile soil retaining wall 6 located above the rotary jetted pile 2 is carried out. The first inter-pile soil retaining wall 6 is shown in FIG. 3 .

(1)第一桩间土护壁6施工,在支护桩1的相对的一侧钻孔,钻孔与支护桩1延伸方向垂直设置,将两段横压筋12插入钻孔中再搭接焊接形成横向限位杆8,在旋喷桩2顶部对应固定竖向限位杆9,竖向限位杆9在上下方向固定在旋喷桩2与冠梁3之间,竖向限位杆9与横向限位杆8焊接连接形成限位网,然后将钢筋网10铺设在限位钢的背向基坑的一面。(1) For the construction of the soil retaining wall 6 between the first piles, drill holes on the opposite side of the supporting piles 1. The drilled holes are set perpendicular to the extension direction of the supporting piles 1, and two sections of transverse pressure bars 12 are inserted into the drilled holes and then erected. The horizontal limit rod 8 is formed by welding, and the vertical limit rod 9 is correspondingly fixed on the top of the rotary jet pile 2. The vertical limit rod 9 is fixed between the rotary jet pile 2 and the crown beam 3 in the up and down direction. The rod 9 is welded and connected with the lateral limit rod 8 to form a limit net, and then the reinforcing mesh 10 is laid on the side of the limit steel facing away from the foundation pit.

(2)面层喷射混凝;(2) Surface spray coagulation;

喷射作业应从上向下分段进行,同一分段喷射顺序应自下而上;喷射时喷头与受喷面应保持垂直,喷射射距0.6-1.0m。喷射厚度为80mm强度为C20的细石混凝土。The spraying operation should be carried out in sections from top to bottom, and the spraying sequence of the same section should be from bottom to top; when spraying, the nozzle and the sprayed surface should be kept vertical, and the spraying distance should be 0.6-1.0m. Fine stone concrete with a thickness of 80mm and a strength of C20 is sprayed.

S8:第二道锚索5施工。S8: Construction of the second anchor cable 5.

第二道锚索5位于第一道锚索5正下方,在第二道锚索5施工前,进行第三层四周土方开挖,同时进行第二层中心土方开挖、四周区域疏干井施工及降水。第二道锚索5施工步骤与第一道锚索施工步骤相同,在此不再赘述。The second anchor cable 5 is located directly below the first anchor cable 5. Before the construction of the second anchor cable 5, earthwork excavation around the third layer is carried out, and at the same time, the center earthwork excavation of the second layer is carried out, and the surrounding area is dredged. construction and precipitation. The construction steps of the second anchor cable 5 are the same as the construction steps of the first anchor cable, and are not repeated here.

S9:当第二道锚索5施工完成后,进行旋喷桩2与旋喷桩2或者旋喷桩2与支护桩1之间的第二桩间土护壁7施工,第二桩间土护壁7如图3所示。S9: After the construction of the second anchor cable 5 is completed, the construction of the second inter-pillar soil retaining wall 7 between the rotary jetting pile 2 and the rotary jetting pile 2 or the rotary jetting pile 2 and the supporting pile 1 is carried out, and the soil between the second piles is constructed. The protective wall 7 is shown in FIG. 3 .

(1)第二桩间土护壁7施工时,在支护桩1与旋喷桩2相对的一侧或者旋喷桩2与旋喷桩2相对的一侧钻孔,将两段横压筋12插入钻孔中再搭接焊接形成横向限位杆8,然后将钢筋网10铺设在横向限位杆8的背向基坑的一面。(1) During the construction of the soil retaining wall 7 between the second piles, drill holes on the opposite side of the supporting pile 1 and the spraying pile 2 or on the side opposite the spraying pile 2 and the spraying pile 2, and pierce the two sections of transverse reinforcement bars. 12 is inserted into the drilled hole and then overlapped and welded to form the lateral limit rod 8, and then the reinforcing mesh 10 is laid on the side of the lateral limit rod 8 facing away from the foundation pit.

(2)面层喷射混凝土;(2) sprayed concrete for the surface layer;

喷射作业应从上向下分段进行,同一分段喷射顺序应自下而上;喷射时喷头与受喷面应保持垂直,喷射射距0.6-1.0m。喷射厚度为80mm强度为C20的细石混凝土。The spraying operation should be carried out in sections from top to bottom, and the spraying sequence of the same section should be from bottom to top; when spraying, the nozzle and the sprayed surface should be kept vertical, and the spraying distance should be 0.6-1.0m. Fine stone concrete with a thickness of 80mm and a strength of C20 is sprayed.

若需要进行第三道锚索施工,则继续进行第四层四周土方开挖,然后继续进行第三道锚索施工,以及土护壁施工,依次循环,直至土护壁的深度达到基坑设计深度。If the third anchor cable construction needs to be carried out, continue to carry out the earthwork excavation around the fourth layer, then continue to carry out the third anchor cable construction, and the soil retaining wall construction, in turn, until the depth of the soil retaining wall reaches the design depth of the foundation pit.

上述实施例中,在相邻支护桩之间设置两根旋喷桩,其他实施例中,在相邻支护桩之间设置一根旋喷桩。In the above-mentioned embodiments, two jetting piles are arranged between adjacent supporting piles, and in other embodiments, one jetting jetting pile is arranged between adjacent supporting piles.

上述实施例中,在进行支护桩施工前,进行距离支护桩20m以外的土方开挖,由内向外开挖,并进行1:1放坡,以使支护桩满足开挖条件;其他实施例中,若进行支护桩施工前,场地满足支护桩施工条件,可以直接进行支护桩的施工。In the above-mentioned embodiment, before carrying out the construction of the supporting piles, excavate the earthwork 20m away from the supporting piles, excavate from the inside to the outside, and conduct 1:1 grading, so that the supporting piles meet the excavation conditions; other In the embodiment, if the site satisfies the construction conditions of the support piles before the construction of the support piles, the construction of the support piles can be directly carried out.

Claims (8)

1. A soil-protecting and descending construction method is characterized by comprising the following steps:
s1: construction preparation;
researching a geotechnical engineering investigation report of a construction area, knowing the structure, distribution, performance indexes and underground water distribution condition of a soil layer, finding out the spatial position, structural form, foundation burial depth and foundation type of various underground facilities and surrounding buildings, judging the influence of support on the underground facilities and the surrounding buildings, installing mechanical equipment in place and operating normally, and putting all required materials in place according to a plan;
s2: when a construction site meets the excavation condition of the supporting piles, carrying out supporting pile construction, and installing design pile positions to carry out supporting pile pouring construction;
s3, after the construction of the supporting piles is finished for 48 hours, carrying out the construction of the jet grouting piles between the adjacent supporting piles, wherein the top of each jet grouting pile is lower than the lower part of the top of each supporting pile;
s4: after the construction of the jet grouting pile is completed, the top of the supporting pile is constructed with a top beam, and the main reinforcement of the supporting pile extends into the top beam and is connected with the top beam
Connecting steel bars, wherein a crown beam is supported at the top of the support piles and connects the support piles, and a reserved steel bar is arranged above the crown beam;
s5: constructing a retaining wall in the range from the top of a crown beam of the supporting pile of the foundation pit to the ground, wherein the retaining wall comprises constructional columns arranged at intervals, and main reinforcements of the constructional columns are connected with reserved reinforcing steel bars of the crown beam;
s6: constructing a first anchor cable;
s7: after the first anchor cable construction is finished, performing first inter-pile soil retaining wall construction above the jet grouting pile;
s8: constructing a second anchor cable;
s9: and after the second anchor cable is constructed, performing second inter-pile soil retaining wall construction between the jet grouting pile and the jet grouting pile or between the jet grouting pile and the support pile.
2. A soil lifting construction method according to claim 1, wherein in the construction of S2 fender piles:
(1) firstly, carrying out height measurement and construction setting-out on an operation surface, and determining a supporting pile site;
(2) processing the reinforcement cage, stacking the manufactured reinforcement cage in a classified manner, marking the use part by using a signboard, and using the reinforcement cage behind an experience folding lattice;
(3) drilling to form a hole;
calculating the hole depth according to the designed pile length and the elevation of the construction working surface, and marking the hole depth at the corresponding position of the body or the drill rod of the drilling machine;
the drilling machine moves to a pile site to align with a pile site of a support pile and lower a drill bit, the tower body of the drilling machine is kept vertical, the verticality of a drill rod is measured by a theodolite or a plumb bob, and the verticality deviation is controlled within 1%;
(4) pressure pouring concrete;
after the drill bit reaches the designed elevation, the drill rod stops drilling and starts to pump concrete, the concrete is pumped to the bottom of the hole, the drill is lifted while the concrete is pumped, the drill lifting speed is matched with the pumping quantity, and the drill bit is guaranteed to be buried below the concrete surface all the time; the pile-forming process is continuously carried out until the pile body concrete is poured to the ground of the hole opening;
(5) implanting a reinforcement cage;
after the concrete is pressure-poured to a construction control elevation and waste soil around the pile hole is cleaned, aligning the reinforcement cage to the center of the hole position to carry out reinforcement cage implantation construction; aligning the center of the reinforcement cage to the center of the pile position, and controlling the verticality of the reinforcement cage; make it sink through the steel reinforcement cage dead weight earlier, when sinking and stopping, start the electromagnetic shaker, make the steel reinforcement cage continue to sink through the electromagnetic shaker, height that the steel reinforcement cage was placed is controlled to the levelling instrument, after reacing the design elevation, fixed steel reinforcement cage.
3. A soil protection and descent construction method as claimed in claim 2, wherein in S3, two jet grouting piles are arranged between adjacent supporting piles, after the construction of the supporting piles adjacent to both sides is completed for 48 hours, the jet grouting piles are measured and paid out, then the jet grouting piles are put in place, the hole site and the drill rod verticality are corrected, the hole leading operation is performed, then grouting pipes are arranged in the holes, high-pressure jet grouting is performed from bottom to top until the hole orifice returns, and the position where the jet stopping is higher than the curtain design top surface lm.
4. A soil drop construction method as claimed in claim 3, wherein in S4 crown beam construction:
(1) drilling a pile head and clearing soil;
chiseling floating slurry on the top of the supporting pile and excess pile body mixed soil, removing residual concrete on a main reinforcement of the supporting pile, ensuring that the length of the main reinforcement of the supporting pile extending into the crown beam meets the design requirement, and lap-welding the main reinforcement and the crown beam steel bar;
(2) performing crown beam formwork support; performing crown beam formwork support between the support piles, cleaning the contact surface of the formwork and the concrete after the formwork support is finished, and coating a separant;
(3) pouring and maintaining concrete;
and (3) continuously pouring the crown beam concrete, covering the concrete within 12 hours after the concrete is poured, and maintaining the concrete in a heat-preservation way for more than or equal to 7 days.
5. A soil drop construction method according to claim 4, wherein in the construction of the S5 retaining wall: and (4) building the retaining wall in layers, and backfilling after the concrete strength of the constructional columns of the retaining wall reaches 70% of the design strength.
6. A soil lifting construction method according to any one of claims 1 to 4, wherein in the first inter-pile soil retaining wall construction of S7:
(1) the construction method comprises the steps of constructing a first inter-pile soil retaining wall, drilling a hole in one opposite side of a support pile, wherein the drilled hole is perpendicular to the extending direction of the support pile, inserting two sections of transverse pressing bars into the drilled hole, then overlapping and welding to form a transverse limiting rod, correspondingly fixing a vertical limiting rod on the top of a jet grouting pile, welding and connecting the vertical limiting rod and the transverse limiting rod to form a limiting net, and then laying a reinforcing mesh on one surface of the limiting steel, which is back to a foundation pit;
(2) spraying and coagulating a surface layer;
the spraying operation is performed from top to bottom in sections, and the spraying sequence of the same section is from bottom to top; when in spraying, the spray head and the sprayed surface are kept vertical, and the spraying distance is 0.6-1.0 m;
spraying the fine stone concrete with the thickness of 80mm and the strength of C20.
7. The soil lifting construction method of claim 6, wherein in the second inter-pile soil retaining wall construction of S9:
(1) during construction of the soil retaining wall between the second piles, drilling holes in one side of the support pile opposite to the rotary jet grouting pile or one side of the rotary jet grouting pile opposite to the rotary jet grouting pile, inserting two sections of transverse pressing bars into the drilled holes, then overlapping and welding the transverse pressing bars to form transverse limiting rods, and then paving a reinforcing mesh on one surface of the limiting steel, which faces away from the foundation pit;
(2) spraying and coagulating the surface layer;
the spraying operation is performed from top to bottom in a segmented mode, and the spraying sequence of the same segment is from bottom to top; when spraying, the spray head and the sprayed surface should be kept vertical, and the spraying distance is 0.6-1.0 m;
spraying the fine stone concrete with the thickness of 80mm and the strength of C20.
8. A method of civil engineering works as claimed in any of claims 1 to 4 wherein, before the construction of the supporting piles, earth excavation is carried out at a distance of 20m from the supporting piles, excavation is carried out from the inside to the outside, and 1: 1, slope releasing so that the supporting piles meet excavation conditions.
CN202210331946.0A 2022-03-31 2022-03-31 Soil protection construction method Active CN114575355B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210331946.0A CN114575355B (en) 2022-03-31 2022-03-31 Soil protection construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210331946.0A CN114575355B (en) 2022-03-31 2022-03-31 Soil protection construction method

Publications (2)

Publication Number Publication Date
CN114575355A true CN114575355A (en) 2022-06-03
CN114575355B CN114575355B (en) 2024-08-23

Family

ID=81778188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210331946.0A Active CN114575355B (en) 2022-03-31 2022-03-31 Soil protection construction method

Country Status (1)

Country Link
CN (1) CN114575355B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059087A (en) * 2022-06-30 2022-09-16 中冶建工集团有限公司 Construction Method of Foundation Pit of Vehicle Ground Passage
CN115652952A (en) * 2022-12-23 2023-01-31 中国建筑第六工程局有限公司 Uplift pile and supporting pile combined inclined-straight pile inner-support-free foundation pit supporting method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102235007A (en) * 2010-04-27 2011-11-09 中国华冶科工集团有限公司 Method for supporting deep foundation with upper nail-lower pile combination
CN109680695A (en) * 2018-12-17 2019-04-26 北京建材地质工程有限公司 Bore forming technique is perfused in anhydrous thickness sand cobble stratum long auger
CN210104758U (en) * 2019-04-16 2020-02-21 华弘建设集团有限公司 A foundation pit support system of soil-nailed cast-in-place pile and anchor-cable combination
CN110924450A (en) * 2019-12-18 2020-03-27 湖北工业大学 Method for protecting existing viaduct friction pile in pit under foundation pit excavation condition
CN111733828A (en) * 2020-07-06 2020-10-02 中铁三局集团建筑安装工程有限公司 Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
WO2021196449A1 (en) * 2020-03-31 2021-10-07 江苏东合南岩土科技股份有限公司 Foundation pit supporting system and construction method therefor
CN113802582A (en) * 2021-10-26 2021-12-17 中国十七冶集团有限公司 Mountain supporting method for near special-shaped buildings in hilly areas

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102235007A (en) * 2010-04-27 2011-11-09 中国华冶科工集团有限公司 Method for supporting deep foundation with upper nail-lower pile combination
CN109680695A (en) * 2018-12-17 2019-04-26 北京建材地质工程有限公司 Bore forming technique is perfused in anhydrous thickness sand cobble stratum long auger
CN210104758U (en) * 2019-04-16 2020-02-21 华弘建设集团有限公司 A foundation pit support system of soil-nailed cast-in-place pile and anchor-cable combination
CN110924450A (en) * 2019-12-18 2020-03-27 湖北工业大学 Method for protecting existing viaduct friction pile in pit under foundation pit excavation condition
WO2021196449A1 (en) * 2020-03-31 2021-10-07 江苏东合南岩土科技股份有限公司 Foundation pit supporting system and construction method therefor
CN111733828A (en) * 2020-07-06 2020-10-02 中铁三局集团建筑安装工程有限公司 Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN113802582A (en) * 2021-10-26 2021-12-17 中国十七冶集团有限公司 Mountain supporting method for near special-shaped buildings in hilly areas

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刘海兵: "凤城国贸工程超深基坑桩锚支护设计与施工", 探矿工程(岩土钻掘工程), vol. 46, no. 5, pages 86 - 91 *
张玉亭: "长螺旋钻孔压灌桩施工监理控制要点", 山西建筑, vol. 46, no. 11, pages 164 - 166 *
王惠: "土建基础施工之深基坑支护施工技术探究", 中国住宅设施, no. 4, pages 101 - 103 *
纪辉: "岩土工程中基坑工程安全施工设计", 中国高新科技, no. 2, pages 95 - 96 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059087A (en) * 2022-06-30 2022-09-16 中冶建工集团有限公司 Construction Method of Foundation Pit of Vehicle Ground Passage
CN115652952A (en) * 2022-12-23 2023-01-31 中国建筑第六工程局有限公司 Uplift pile and supporting pile combined inclined-straight pile inner-support-free foundation pit supporting method

Also Published As

Publication number Publication date
CN114575355B (en) 2024-08-23

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN103741714A (en) Full-cover excavation top-down construction method for underground engineering
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN107938692A (en) A kind of draining and recharge construction method and structure
CN106759379A (en) A kind of construction method of the asymmetric water-stop curtain of foundation ditch
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN114086969B (en) Tunnel entering construction method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN210104758U (en) A foundation pit support system of soil-nailed cast-in-place pile and anchor-cable combination
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN114575355B (en) Soil protection construction method
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN110093971A (en) The Combined water pump house and its construction method of subterranean tunnel
CN110762286B (en) Drainage pipe network artificial pipe jacking construction process
CN113266392A (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN206736963U (en) Ditch millet section high water level district lid tunnel stagnant water structure
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN115977102B (en) Combined construction structure and construction method of upper foundation pit and lower tunnel in saturated soft loess stratum
CN113309526B (en) Construction method for excavation and supporting of buckling arch of subway station
CN113266362B (en) A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area
CN110344418A (en) The structure and its construction technology of support system in a kind of deep basal pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant