CN112144559A - Construction method of piezo-transformer tube well in high water-rich loess sandy pebble formation - Google Patents

Construction method of piezo-transformer tube well in high water-rich loess sandy pebble formation Download PDF

Info

Publication number
CN112144559A
CN112144559A CN202011125006.3A CN202011125006A CN112144559A CN 112144559 A CN112144559 A CN 112144559A CN 202011125006 A CN202011125006 A CN 202011125006A CN 112144559 A CN112144559 A CN 112144559A
Authority
CN
China
Prior art keywords
caisson
well
grouting
construction
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011125006.3A
Other languages
Chinese (zh)
Other versions
CN112144559B (en
Inventor
陈文夫
王相状
沈荣建
张琦
宋宏涛
蒋炎均
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Water Resources Development Co Ltd
Original Assignee
Anhui Water Resources Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Water Resources Development Co Ltd filed Critical Anhui Water Resources Development Co Ltd
Priority to CN202011125006.3A priority Critical patent/CN112144559B/en
Publication of CN112144559A publication Critical patent/CN112144559A/en
Application granted granted Critical
Publication of CN112144559B publication Critical patent/CN112144559B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Public Health (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明给出了一种高富水黄土砂卵石地层变压管井中井施工方法,包括以下步骤:开挖沉孔,在沉孔内制作沉井,沉井两侧侧壁预留有主管道通过的洞口;将两节主管道的管节分别从沉井的洞口顶出;测量定位;检查井下部井筒施工;检查井下部井筒四周回填;检查井上部井筒施工及回填;当沉井回填至道路路床顶面后,沉井内的路基回填,与整体道路的基层一同施工;液浆的制备及注浆加固;成孔采用螺旋钻回转钻机;将水泥:水玻璃:水按质量比例1:0.1:1配比为双液浆,使用前双浆液均匀拌合并经过筛网过滤。本方法优点为:缩短了检查井和管道施工工期,减少顶进扰动,还避免了对地上建筑物直接影响,为道路提前贯通提供了保证,同时工程总体质量大大提高。

Figure 202011125006

The invention provides a method for constructing a well in a transformer tube well in a high water-rich loess sand pebble stratum, comprising the following steps: excavating a counterbore, making a caisson in the counterbore, and reserving two side walls on both sides of the caisson to pass through the main pipeline. Opening of the hole; push the pipe sections of the two main pipes from the opening of the caisson respectively; measure and position; check the construction of the wellbore at the bottom of the well; check the backfill around the wellbore at the bottom of the well; After the top of the bed, the subgrade in the caisson is backfilled and constructed together with the base of the overall road; slurry preparation and grouting reinforcement; auger rotary drilling rig is used to form holes; cement: water glass: water in a mass ratio of 1:0.1: 1. The ratio is double-liquid slurry. Before use, the double-liquid slurry is evenly mixed and filtered through a screen. The advantages of this method are that the construction period of inspection wells and pipelines is shortened, the disturbance of jacking is reduced, and the direct impact on the buildings on the ground is avoided, which provides a guarantee for the advance penetration of the road, and at the same time, the overall quality of the project is greatly improved.

Figure 202011125006

Description

高富水黄土砂卵石地层变压管井中井施工方法Construction method of piezo-transformer tube well in high water-rich loess sandy pebble formation

技术领域technical field

本发明涉及一种高富水黄土砂卵石地层变压管井中井施工方法。The invention relates to a construction method for a pressure-transformer tube well in a high-water-rich loess sand and pebble stratum.

背景技术Background technique

“井中井”是指在沉井中二次制作的检查井。传统市政道路“井中井”施工是沉井中砌筑烧结砖或浇筑钢筋混凝土井,并完成井周回填。但是在高富水黄土-砂卵石区变压管(由于下游出口污水处理厂长期非正常运行,导致管内产生水头压力变化)深井(>10m)沉井中制作检查井受常规机头顶进困难对地层扰动大,检查井井筒两种材料密封性能差和管内水头差发生不定期变化等问题影响,导致井筒、管身与管口接头处,受冲击易产生缝隙,在内外不均衡水压作用下,引起管外深层砂土掏空,黄土沉陷,从而后期路面产生不均匀沉降。A "well in a well" refers to an inspection well that is secondary fabricated in a caisson. The traditional municipal road "well in the well" construction is to build sintered bricks or pour reinforced concrete wells in the caisson, and complete the backfill around the well. However, in the high-water-rich loess-sand-cobble area of the pressure transformer pipe (due to the long-term abnormal operation of the downstream sewage treatment plant, the head pressure changes in the pipe), the inspection well is made in the deep well (>10m) caisson. Due to the poor sealing performance of the two materials in the inspection well and the irregular change in the water head difference in the pipe, the joints between the wellbore, the pipe body and the pipe mouth are prone to cracks due to impact. The deep sand outside the pipe is hollowed out and the loess subsides, resulting in uneven settlement of the pavement in the later stage.

由于地域土层的特点,以及大管径污、污水管(1.5-3.0m)沉井结构一般比较大,不能直接作为检查井使用。缺少一种在高富水黄土砂卵石地层总的变压管井中井施工方法。Due to the characteristics of the regional soil layers, and the large diameter sewage and sewage pipes (1.5-3.0m) caisson structures are generally relatively large, they cannot be directly used as inspection wells. There is a lack of a well-in-the-tube construction method in the high-water-rich loess sand and pebble formation.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题是提供一种工艺合理、施工方便的高富水黄土砂卵石地层变压管井中井施工方法。The technical problem to be solved by the present invention is to provide a well construction method in a piezo-transformer tube well with reasonable technology and convenient construction.

为解决上述技术问题,本发明提供了一种高富水黄土砂卵石地层变压管井中井施工方法,包括以下步骤:In order to solve the above-mentioned technical problems, the present invention provides a construction method for a pressure-transformer tube well in a high-water-rich loess sandy pebble stratum, comprising the following steps:

a)沉井施工a) caisson construction

在预定位置开挖沉孔,沉孔的深度超过主管道的预定深度;Excavate a counterbore at a predetermined position, and the depth of the counterbore exceeds the predetermined depth of the main pipeline;

在沉孔下部井筒四壁和底壁上根据施工图制作钢筋混凝土沉井,沉井采用不排水封底,沉井采用多次制作和下沉,沉井两侧侧壁预留有主管道通过的洞口;The reinforced concrete caisson is made on the four walls and bottom wall of the shaft at the lower part of the caisson according to the construction drawings. The caisson is sealed with no drainage. The caisson is made and sunk many times. The side walls of the caisson are reserved for the passage of the main pipeline. hole;

b)顶管施工b) Pipe jacking construction

依次将主管道的管节吊装至沉井内,通过顶进设备将两节主管道的管节分别从沉井的洞口顶出,两节主管道的管节之间具有间隙;The pipe sections of the main pipeline are hoisted into the caisson in turn, and the pipe sections of the two main pipes are respectively pushed out from the opening of the caisson through the jacking equipment, and there is a gap between the pipe sections of the two main pipes;

c)测量定位c) Measuring and positioning

根据图纸中检查井的中心坐标,通过沉井的结构尺寸及布置方式,推算出沉井四角的坐标;According to the center coordinates of the inspection well in the drawing, the coordinates of the four corners of the caisson are calculated through the structure size and arrangement of the caisson;

d)检查井下部井筒施工d) Check the wellbore construction at the bottom of the well

现场分步施工,第一步施工井室底板,第二步施工井室井壁,第三次施工钢筋混凝土井筒;Step-by-step construction on site, the first step is to construct the well chamber floor, the second step to construct the well chamber wall, and the third step to construct the reinforced concrete wellbore;

将沉井的底板凿毛,再浇筑检查井的底板混凝土,在浇筑底板混凝土时预埋井壁钢筋;Chisel the bottom of the caisson, then pour the bottom concrete of the inspection well, and pre-embed the steel reinforcement of the well wall when pouring the bottom concrete;

检查井壁施工前,根据沉井和检查井之间的距离截取管道,在两侧明接管道,并浇筑基础,同时将管道外壁凿毛,然后加工模板及钢筋,井室井壁上端面预埋井筒的钢筋;Before the construction of the inspection well wall, intercept the pipeline according to the distance between the caisson and the inspection well, connect the pipeline on both sides, and pour the foundation. Rebar of the shaft;

井筒为方形井筒,自下而上搭设支架,提供操作人员的工作平台,管道穿越井壁处用油麻沥青砂填实,迎水面用聚硫密封膏封堵;The wellbore is a square wellbore, and supports are erected from bottom to top to provide a working platform for operators. The pipeline crossing the well wall is filled with linseed tar sand, and the upstream surface is sealed with polysulfide sealant;

e)检查井下部井筒四周回填e) Check the backfill around the wellbore downhole

井四周回填采用水坠砂现场的砂回填,带回填面不再有细微气泡冒出时,可以停止注水;The backfill around the well is backfilled with the sand from the water-falling sand site. When the backfill surface no longer has fine air bubbles, the water injection can be stopped;

现场水坠砂完成后,及时到现场环刀取样,用天平和微波炉烘干法得到相关数据,测出压实度;After the on-site water-falling sand is completed, sample the ring knife at the site in time, obtain the relevant data with the balance and microwave oven drying method, and measure the degree of compaction;

井筒外部平台可将井室部分的四周土提前回填一定高度,回填至支管高程后,安装支管,支管回填时做好成品保护;The external platform of the wellbore can backfill the surrounding soil of the well room to a certain height in advance. After backfilling to the elevation of the branch pipe, install the branch pipe, and protect the finished product when the branch pipe is backfilled;

f)检查井上部井筒施工及回填f) Inspection of upper wellbore construction and backfilling

检查井的上部井筒结构为砖砌体,钢筋混凝土井筒完成后,回填至钢筋混凝土井筒顶部;The upper shaft structure of the inspection well is brick masonry. After the reinforced concrete shaft is completed, it is backfilled to the top of the reinforced concrete shaft;

g)道路路基、底基层施工g) Construction of road subgrade and sub-base

因检查井在道路的路基范围内,当沉井回填至道路路床顶面后,沉井内的路基回填,与整体道路的基层一同施工;Since the inspection well is within the subgrade range of the road, after the caisson is backfilled to the top of the road bed, the subgrade in the caisson is backfilled and constructed together with the base of the overall road;

h)液浆的制备及注浆加固h) Preparation of slurry and grouting reinforcement

钻孔平面位置与沉井内、外处软弱薄弱部位的平面位置应一致,且选取多点布置注浆孔,点与点间距≤1.0m;The plane position of the drilling hole should be consistent with the plane position of the weak and weak parts inside and outside the caisson, and select multiple points to arrange grouting holes, and the distance between points should be ≤1.0m;

成孔采用螺旋钻回转钻机,成孔直径70mm~110mm,垂直度允许偏差为±1%,孔深自路基至顶管管道或软弱薄弱部位;The auger rotary drilling machine is used to form the hole, the diameter of the hole is 70mm to 110mm, the allowable deviation of verticality is ±1%, and the hole depth is from the roadbed to the pipe jacking pipe or weak and weak parts;

将水泥:水玻璃:水按质量比例1:0.1:1配比为双液浆,使用前双浆液均匀拌合并经过筛网过滤;Mix cement: water glass: water into a double-liquid slurry in a mass ratio of 1:0.1:1. Before use, the double-liquid slurry is evenly mixed and filtered through a screen;

双浆液通过注浆管灌注,灌注前应用水泥砂浆封闭注浆管外侧与孔口之间的空隙,待封闭泥浆凝固后,捅去注浆管的活络堵头,注入压力0.4Mpa,注浆过程中双浆液不停缓慢搅拌,搅拌时间小于初凝时间,注浆的流量在5~10L/min,水温控制在0℃~30℃之间,双浆液的初凝时间55min;The double grout is poured through the grouting pipe. Before pouring, the gap between the outside of the grouting pipe and the orifice should be closed with cement mortar. The medium and double slurries are continuously stirred slowly, the stirring time is less than the initial setting time, the flow rate of grouting is 5~10L/min, the water temperature is controlled between 0 ℃ ~ 30 ℃, and the initial setting time of the double slurries is 55min;

i)养护和检查验收i) Maintenance and inspection acceptance

对注浆完成区域采用封闭交通管理,禁止周围大型机械、振动机械通行施工;Closed traffic management is adopted for the area where grouting is completed, and the surrounding large-scale machinery and vibration machinery are prohibited for construction;

注浆结束28天后进行检验,选用标准贯入方法进行检测,注浆检验点为注浆孔数的3%,合格率小于80%时,实施重复注浆。28 days after grouting is completed, the inspection is carried out, and the standard penetration method is used for inspection. The grouting inspection point is 3% of the number of grouting holes. When the pass rate is less than 80%, repeated grouting is performed.

作为本方法的优选,所述步骤d)检查井下部井筒施工,下部井筒一次浇筑高度3m左右,大于3m的可分节施工。As a preference of this method, the step d) inspects the construction of the lower wellbore, and the lower wellbore is about 3m high for one pouring, and the construction can be divided into sections greater than 3m.

作为本方法的优选,所述步骤e)中检查井上部井筒施工,井筒内外井壁采用1:2水泥砂浆加5%防水剂抹面厚20mm。As a preference of the method, in the step e), the construction of the upper wellbore of the inspection well is checked, and the inner and outer walls of the wellbore are plastered with 1:2 cement mortar plus 5% waterproofing agent to a thickness of 20 mm.

作为本方法的优选,所述步骤h)液浆的制备及注浆加固,制备水泥浆中搅拌时间应大于2min,水灰比控制在0.8~1,然后根据泥浆搅拌桶的容积向搅拌桶内掺入定量的水玻璃溶液并搅拌均匀,水玻璃和水泥浆的体积比控制在0.5~0.8之间。As a preference of this method, in the step h) preparation of the slurry and grouting reinforcement, the stirring time in the preparation of the slurry should be greater than 2 minutes, the water-cement ratio should be controlled at 0.8 to 1, and then the volume of the slurry mixing bucket should be adjusted to the mixing bucket. Add a certain amount of water glass solution and stir evenly, and control the volume ratio of water glass to cement slurry between 0.5 and 0.8.

作为本方法的优选,所述步骤h)液浆的制备及注浆加固,根据沉井面积,采用梅花型布置注浆孔,孔深自路基至管节,采用螺旋钻回转钻进,成孔直径70mm~110mm,垂直度允许偏差为±1%。As a preference of this method, in the step h) preparation of the slurry and grouting reinforcement, according to the area of the caisson, the grouting holes are arranged in a plum blossom shape, and the hole depth is from the roadbed to the pipe joint, and the auger is used for rotary drilling to form a hole. The diameter is 70mm~110mm, and the allowable deviation of verticality is ±1%.

作为本方法的优选,预制沉井盖板,沉井盖板上预留有检查井顶部的通孔,在h)液浆的制备及注浆加固后,沉井盖板盖在沉井上侧。As a preference of this method, the caisson cover is prefabricated, and the through hole at the top of the inspection well is reserved on the caisson cover. After h) the preparation of the slurry and the reinforcement by grouting, the caisson cover is covered on the upper side of the caisson.

作为本方法的优选,所述步骤h)中注浆管分为若干第一注浆管和若干第二注浆管,若干第一注浆管分为两组,两组第一注浆管与两侧管节对应,每组第一注浆管下端伸至处于沉井内侧和外侧的管节上侧;若干第二注浆管下端伸至检查井上部井筒与下部井筒连接处的四周。As a preference of this method, in the step h), the grouting pipes are divided into several first grouting pipes and several second grouting pipes, and the several first grouting pipes are divided into two groups, and the two groups of first grouting pipes and The pipe sections on both sides correspond, and the lower ends of the first grouting pipes of each group extend to the upper side of the pipe sections on the inside and outside of the caisson; the lower ends of several second grouting pipes extend to the periphery of the connection between the upper wellbore and the lower wellbore of the inspection well.

采用这样的方法后,采用顶管技术能够在不影响地面设施的前提下,开展管道铺设,避免了作业面对地上建筑物或构筑物的直接影响,通过主动注浆加固措施,最大程度的降低了地面发生沉降的可能性。After this method is adopted, the pipe jacking technology can be used to carry out pipeline laying without affecting the ground facilities, avoiding the direct impact of the operation on the buildings or structures on the ground. The possibility of land subsidence.

在确保沉井质量和检查沉井底板质量后,开始根据管道的位置支模板绑钢筋,浇筑下部混凝土检查井井室,当下部井室完成后,完成上部井室砌筑。下部沉井与检查井之间回填材料选用原中粗砂,分层(20cm)采用水坠砂插入式振捣棒夯打法回填,沉井内设土工布包裹的无砂滤水管抽排水,形成水流循环,砂密实度需达到密实的要求;上部沉井与检查井之间采用3:7灰土均匀回填井四周。After ensuring the quality of the caisson and checking the quality of the caisson floor, start to tie the steel bars to the formwork according to the position of the pipeline, pour the lower concrete inspection well chamber, and complete the masonry of the upper well chamber when the lower well chamber is completed. The backfill material between the lower caisson and the inspection well is the original medium-coarse sand, and the layer (20cm) is backfilled by the water-falling sand insertion vibrating rod tamping method. To form a water flow circulation, the sand density must meet the requirements of compaction; between the upper caisson and the inspection well, 3:7 lime soil is used to evenly backfill around the well.

在路基和底基层完成后,通过螺旋钻机出土留孔,高程和坐标控制,将定向注浆管出口安置在施工的砖砌体与混凝土顶板结合处、沉井预留的洞口和管道的薄弱处和沉井与检查井之间管道处,并通过压力注浆要让双浆液在周围土体中通过注浆管将能强力固化的浆液注入地层中,浆液以充填、渗透、挤密和劈裂等方式,挤走土颗粒中的水分和空气后占据其位置,浆液固结后将原来松散的土粒或裂隙胶结成一个整体,通过渗透、充填、压密扩展形成包裹体。After the subgrade and sub-base are completed, the exit of the directional grouting pipe is placed at the junction of the brick masonry under construction and the concrete roof, the opening reserved for the caisson and the weak point of the pipeline through the auger excavation hole, the elevation and coordinate control. And the pipeline between the caisson and the inspection well, and through the pressure grouting, the double grout should be injected into the formation through the grouting pipe, and the strong solidified grout will be injected into the formation. The grout will fill, penetrate, compact and split In other ways, the water and air in the soil particles are squeezed out and occupy their positions. After the slurry is consolidated, the original loose soil particles or fissures are cemented into a whole, and inclusions are formed through infiltration, filling, and compaction expansion.

由于地层中砂砾层和中、粗砂具均有孔隙,通过钻孔向土层中加压灌入一定浆液,注浆口周围土体被挤压充填,形成塑性包裹区,离浆体较远的土体则发生弹性变形,注浆口周围土体的整个密度得到提高。这种包裹体与压密的地基土形成结合体,共同起到迅速加固补强、填充空洞裂隙、封堵水力冲击导致的裂隙的作用。Since there are pores in the gravel layer and medium and coarse sand tools in the stratum, a certain amount of grout is injected into the soil layer through drilling, and the soil around the grouting port is squeezed and filled to form a plastic wrapping area, which is far away from the grout. The soil mass of the grouting mouth is elastically deformed, and the overall density of the soil mass around the grouting port is increased. This inclusion forms a combination with the compacted foundation soil, which together play the role of rapid reinforcement, filling voids and cracks, and sealing cracks caused by hydraulic shock.

在上、下井筒部位分材料密实回填和薄弱处注浆补强的共同作用下,克服了薄弱部位因“水锤效应”、内外不均衡水压、路面荷载作用下,造成井周路面塌陷等问题。Under the combined action of dense backfilling of some materials in the upper and lower wellbore parts and grouting reinforcement at the weak parts, the collapse of the road around the well caused by the "water hammer effect", the unbalanced water pressure inside and outside, and the load of the road surface caused by the weak parts are overcome. question.

本高富水黄土砂卵石地层变压管井中井施工方法优点为:缩短了检查井和管道施工工期,在减少顶进扰动的情况下,还避免了对地上建筑物直接影响,最大程度的降低了地面发生沉降的可能性。为道路提前贯通提供了保证,同时工程总体质量大大提高,为今后国内类似工程的实施提供了大量的很好借鉴,产生了显著的社会效益。The advantages of the construction method of the piezo-transformer tube well in the high-water-rich loess sand and pebble stratum are: shortening the construction period of inspection wells and pipelines, reducing the disturbance of jacking, avoiding the direct impact on the above-ground buildings, and reducing the ground to the greatest extent. Possibility of subsidence. It provides a guarantee for the road to pass through in advance, and at the same time, the overall quality of the project is greatly improved, which provides a lot of good reference for the implementation of similar projects in the country in the future, and produces significant social benefits.

附图说明Description of drawings

图1是本高富水黄土砂卵石地层变压管井中井施工方法实施例的立面示意图。Fig. 1 is a schematic elevational view of an embodiment of the construction method for a piezo-transformer well in a high-water-rich loess sand and pebble formation of the present invention.

图2是本高富水黄土砂卵石地层变压管井中井施工方法实施例的工艺流程见图。Fig. 2 is the process flow diagram of the embodiment of the construction method of the piezo-transformer well in the high-water-rich loess sand and pebble formation.

具体实施方式Detailed ways

如图1至2所示As shown in Figures 1 to 2

以沣西新城市政道路顶管井中井施工为例,此地,上部地质为高富水黄土层,下部地质为砂卵石地层,本高富水黄土砂卵石地层变压管井中井施工方法,包括以下步骤:Taking the construction of pipe jacking well in Fengxi New City as an example, here, the upper geology is high water-rich loess stratum, and the lower geology is sandy pebble stratum.

a)沉井施工a) caisson construction

在预定位置开挖沉孔,沉孔的深度超过主管道的预定深度;Excavate a counterbore at a predetermined position, and the depth of the counterbore exceeds the predetermined depth of the main pipeline;

在沉孔下部井筒四壁和底壁上根据施工图制作钢筋混凝土沉井2,沉井2采用不排水封底,沉井2采用多次制作和下沉,沉井2两侧侧壁预留有主管道通过的洞口;The reinforced concrete caisson 2 is made on the four walls and bottom wall of the shaft at the lower part of the counterbore according to the construction drawing. The caisson 2 is sealed with undrained bottom. the opening through which the main pipeline passes;

混凝土浇筑前,对模板尺寸、预埋件位置、模板的密封性进行检验,拆模后符合要求后下沉,现场过程中对现场偏差做过程控制检查。Before the concrete is poured, the size of the formwork, the position of the embedded parts, and the tightness of the formwork shall be inspected.

b)顶管施工b) Pipe jacking construction

依次将主管道的管节11吊装至沉井2内,通过导轨安装,后背墙制作,顶进设备安装,顶管机头就位,机头入洞,安放管节11与顶铁,顶进与纠偏,通过顶进设备将两节主管道的管节11分别从沉井2的洞口顶出,两节主管道的管节11之间具有一定距离,顶进作业时,通过地面顶进主控台观察顶管顶进时的偏移情况,防止机头左右摆动,加大对砂卵石层的扰动,在管壁外形成更大的空洞,距接收井还有5m时控制机头出洞速度、洞口中轴线,缓慢将机头顶入接收井内,用汽车吊吊出顶管机头,顶管继续顶进至预定位置。The pipe sections 11 of the main pipeline are hoisted into the caisson 2 in turn, installed through the guide rails, the back wall is fabricated, the jacking equipment is installed, the pipe jacking machine head is in place, the machine head is inserted into the hole, and the pipe section 11 and the top iron are placed. For advancing and correcting deviation, the pipe sections 11 of the two main pipelines are respectively ejected from the opening of the caisson 2 through the jacking equipment. There is a certain distance between the pipe sections 11 of the two main pipelines. The main console observes the deviation of the pipe jacking when the pipe is jacked in, to prevent the head from swinging left and right, increase the disturbance to the sand and pebble layer, and form a larger cavity outside the pipe wall. When there is still 5m from the receiving well, the head is controlled to exit The speed of the hole and the central axis of the hole, slowly push the machine head into the receiving well, lift the pipe jacking head with a truck, and continue to jack the pipe to the predetermined position.

c)测量定位c) Measuring and positioning

根据图纸中检查井的中心坐标,通过沉井2的结构尺寸及布置方式,推算出沉井2四角的坐标,采用墨斗放线,在现场放出坐标点,用木桩标示。According to the center coordinates of the inspection well in the drawings, the coordinates of the four corners of the caisson 2 are calculated through the structural size and arrangement of the caisson 2, and the ink fountain is used to set out the line, and the coordinate points are released on site and marked with wooden stakes.

d)检查井下部井筒33施工d) Check the construction of the wellbore 33 in the lower part of the well

根据设计的检查井的结构形式,现场分步施工,第一步施工井室底板34,第二步施工井室井壁及顶板,第三次施工钢筋混凝土井筒;According to the structural form of the designed inspection well, the on-site construction is carried out step by step, the first step is to construct the well chamber bottom plate 34, the second step to construct the well chamber wall and roof, and the third step to construct the reinforced concrete wellbore;

顶管结束后,清理沉井2内的杂物与淤泥,将检查井井室下方的沉井2的底板凿毛,再浇筑检查井的底板混凝土,在浇筑检查井底板34混凝土时预埋井壁钢筋,需要植筋施工的,植筋后做抗拔试验;After the pipe jacking is completed, the debris and silt in the caisson 2 are cleaned up, the bottom plate of the caisson 2 below the well chamber of the inspection well is chiseled, the bottom plate concrete of the inspection well is poured, and the well is pre-buried when pouring the concrete of the inspection well bottom plate 34. Wall reinforcement, if it is necessary to plant reinforcement for construction, do pullout test after planting reinforcement;

检查井壁施工前,根据沉井2和检查井之间的距离截取管道,在两侧明接管道,并浇筑基础,同时将管道外壁凿毛,然后加工模板及钢筋,预埋爬梯,采用汽车吊垂直运输所需材料,浇筑混凝土时采用泵车输送,振动棒振捣,溜槽混凝土同井壁一起浇筑,顶板上预埋井筒的钢筋;Before the construction of the inspection well wall, intercept the pipeline according to the distance between the caisson 2 and the inspection well, connect the pipeline on both sides, and pour the foundation. The material required for vertical transportation is hoisted, and the concrete is poured by pump truck, vibrated by vibrating rod, the chute concrete is poured together with the well wall, and the steel bars of the wellbore are pre-buried on the roof;

检查井下部井筒33井筒为1m*1m的方形井筒,下部井筒33一次浇筑高度3m左右,大于3m的可分节施工,检查井的井筒的施工时,主要难度是内模板的安装空间受限,井筒内只能单人作业,通过在井室洞口处预埋钢筋,自下而上搭设支架,提供操作人员的工作平台,管道穿越井壁处用油麻沥青砂填实,缝宽50mm,迎水面用聚硫密封膏封堵。The lower wellbore 33 of the inspection well is a square wellbore of 1m*1m. The height of the lower wellbore 33 is about 3m at a time. Sections larger than 3m can be constructed. When constructing the wellbore of the inspection well, the main difficulty is that the installation space of the inner formwork is limited. In the wellbore, only one person can work. By pre-embedding steel bars at the opening of the well chamber and erecting brackets from bottom to top, a working platform for operators is provided. The water surface is sealed with polysulfide sealant.

e)检查井下部井筒33周回填e) 33 weeks of backfilling of wellbore downhole inspection

井四周回填采用水坠砂现场的砂回填(即沉井回填区52),采用汽车吊运土,人工找平回填,每层厚度不大于30厘米(虚铺厚度),在检查井外壁标识标高,注水高出填土高度的20cm,,保持水头,目测水面下沉缓慢,带回填面不再有细微气泡冒出时,可以停止注水;The backfill around the well shall be backfilled with sand from the water-falling sand site (that is, the backfill area 52 of the caisson), the soil shall be transported by trucks, and the backfill shall be manually leveled. The water injection is 20cm higher than the filling height, keep the water head, the water surface sinks slowly, and when the backfill surface no longer has fine air bubbles, the water injection can be stopped;

现场水坠砂完成后,及时到现场环刀取样,用天平和微波炉烘干法得到相关数据,测出压实度,具体为:After the on-site water-falling sand is completed, sample the ring knife at the site in time, obtain the relevant data with the balance and microwave oven drying method, and measure the degree of compaction, specifically:

井下部井筒33外部同时回填中粗砂,每层回填厚度不大于20cm,在检查井外壁标识标高,注水高出填土高度的20cm,保持水头,目测水面下沉缓慢,带回填面不再有细微气泡冒出时,可以停止注水,注水过程中采用插入式振捣棒夯打,沉井内设土工布包裹的无砂滤水管抽排水,形成水流循环,砂密实度需达到密实的要求,及时到现场环刀取样,用天平和微波炉烘干法得到相关数据,测出压实度;The outer wellbore 33 at the bottom of the well is backfilled with medium and coarse sand at the same time, and the thickness of each layer of backfill is not more than 20cm. The elevation is marked on the outer wall of the inspection well. The water injection is 20cm higher than the filling height, and the water head is maintained. When fine air bubbles emerge, water injection can be stopped. During the water injection process, the plug-in vibrating rod is used for tamping. The sand-free water filter pipe wrapped in geotextile is installed in the caisson to pump and drain water to form a water flow circulation. The sand density must meet the requirements of density. , in time to the on-site ring knife to sample, use the balance and microwave oven drying method to obtain relevant data, and measure the degree of compaction;

井筒外部平台可将井室部分的四周土提前回填一定高度,回填至支管35高程后,安装支管35,支管35回填时做好成品保护。The external platform of the wellbore can backfill the surrounding soil of the well room to a certain height in advance. After backfilling to the elevation of the branch pipe 35, install the branch pipe 35, and protect the finished product when the branch pipe 35 is backfilled.

f)检查井上部井筒32施工及回填f) Inspection of the construction and backfilling of the wellbore 32 in the upper part of the well

检查井上部井筒32结构为砖砌体,检查井的井筒完成后,检查井上部井筒32内外井壁采用1:2水泥砂浆加5%防水剂抹面厚20mm,检查井顶部设有上盖31;The structure of the upper wellbore 32 of the inspection well is brick masonry. After the wellbore of the inspection well is completed, the inner and outer walls of the upper wellbore 32 of the inspection well are plastered with 1:2 cement mortar and 5% water repellent with a thickness of 20mm, and the top of the inspection well is provided with an upper cover 31;

砖砌检查井的四周回填采用3:7灰土均匀回填井四周,然后用小型打夯机夯实,分层回填,分层夯实,每层回填虚铺厚度不大于15cm。The backfill around the brick inspection well is backfilled with 3:7 lime soil evenly around the well, and then compacted with a small tamper, backfilled in layers, compacted in layers, and the thickness of each layer of backfill is not more than 15cm.

g)道路路基、底基层施工g) Construction of road subgrade and sub-base

再回填检查井上部井筒四周(即路基回填区51),因检查井在道路的路基范围内,当回填至道路路床顶面后,沉井2内的路基回填,与整体道路的基层一同施工。Then backfill around the upper wellbore of the inspection well (that is, the subgrade backfill area 51), because the inspection well is within the subgrade range of the road, after backfilling to the top surface of the road bed, the subgrade in the caisson 2 is backfilled and constructed together with the base of the overall road .

h)液浆的制备及注浆加固h) Preparation of slurry and grouting reinforcement

考虑到双液浆具有凝固时间较快的特点,需现场测定浆液的初、终凝时间以保证浆液自制备至用完的时间不超过其初凝时间,水玻璃用密闭容器储存,将水泥:水玻璃:水按质量比例1:0.1:1配比制得双液浆,现场设置可移动的钢制拌桨桶配制浆液,桶容量≥800L,使用前双浆液均匀拌合并经过筛网过滤。Considering that the double-liquid slurry has the characteristics of fast setting time, it is necessary to measure the initial and final setting time of the slurry on site to ensure that the time from the preparation to the use of the slurry does not exceed the initial setting time. Glass:water is prepared in a mass ratio of 1:0.1:1 to prepare a double slurry. A movable steel mixing bucket is set up on site to prepare the slurry. The bucket capacity is ≥800L. Before use, the double slurry is evenly mixed and filtered through a screen.

钻孔平面位置与沉井2内、外处软弱薄弱部位的平面位置应一致,且选取多点布置注浆孔,点与点间距≤1.0m。The plane position of the drilling hole should be consistent with the plane position of the weak and weak parts inside and outside the caisson 2, and select multiple points to arrange the grouting holes, and the distance between points should be ≤1.0m.

成孔采用螺旋钻回转钻机,成孔直径70mm~110mm,垂直度允许偏差为±1%,孔深自路基至顶管管道或软弱薄弱部位。The auger rotary drilling machine is used to form the hole, the diameter of the hole is 70mm to 110mm, the allowable deviation of the verticality is ±1%, and the hole depth is from the roadbed to the pipe jacking pipe or weak and weak parts.

双浆液通过孔径为50mm的注浆管灌注,灌注前应用水泥砂浆封闭注浆管外侧与孔口之间的空隙,待封闭泥浆凝固后,捅去注浆管的活络堵头,注入压力0.4Mpa,注浆过程中双浆液不停缓慢搅拌,搅拌时间小于初凝时间,注浆的流量在5~10L/min,水温控制在0℃~30℃之间,双浆液的初凝时间55min;The double grout is poured through a grouting pipe with a diameter of 50mm. Before pouring, cement mortar should be used to close the gap between the outside of the grouting pipe and the orifice. After the closed mud solidifies, remove the active plug of the grouting pipe, and the injection pressure is 0.4Mpa , During the grouting process, the double slurries are continuously stirred slowly, and the stirring time is less than the initial setting time.

当达到终孔要求时,注浆钻孔内填入碎石砾料并补充水泥~水玻璃浆液使之形成微型桩体,孔口采用冷补料恢复。When the final hole requirements are met, the grouting hole is filled with gravel and gravel and supplemented with cement-sodium silicate slurry to form a micro pile body, and the orifice is restored with cold filling materials.

注浆管分为多根第一注浆管41和多根第二注浆管42,多根第一注浆管41分为两组,两组第一注浆管41与两侧管节11对应,每组第一注浆管41下端伸至处于沉井2内侧和外侧的管节11上侧;多根第二注浆管42下端伸至检查井上部井筒32与检查井下部井筒33连接处的四周。The grouting pipe is divided into a plurality of first grouting pipes 41 and a plurality of second grouting pipes 42 , and the plurality of first grouting pipes 41 are divided into two groups, two groups of first grouting pipes 41 and two side pipe sections 11 Correspondingly, the lower ends of the first grouting pipes 41 of each group extend to the upper side of the pipe sections 11 on the inner and outer sides of the caisson 2; the lower ends of the plurality of second grouting pipes 42 extend to the upper wellbore 32 of the inspection well and are connected to the lower wellbore 33 of the inspection well around the place.

注浆钻孔内填入碎石砾料并补充水泥/水玻璃浆液使之形成微型包裹体,孔口采用冷补料恢复。The grouting hole is filled with crushed stone and gravel and supplemented with cement/water glass slurry to form micro-inclusions, and the orifice is restored by cold filling.

预制沉井盖板21,沉井盖板21上预留有检查井顶部的通孔,在h)液浆的制备及注浆加固后,沉井盖板21盖在沉井2上侧。The caisson cover plate 21 is prefabricated, and the through hole at the top of the inspection well is reserved on the caisson cover plate 21 .

i)养护和检查验收i) Maintenance and inspection acceptance

对注浆完成区域采用封闭交通管理,禁止周围大型机械、振动机械通行施工。The closed traffic management is adopted for the area where the grouting is completed, and the surrounding large-scale machinery and vibration machinery are prohibited for construction.

注浆结束28天后进行检验,选用标准贯入方法进行检测;注浆检验点为注浆孔数的3%,合格率小于80%时,实施重复注浆。28 days after the completion of grouting, the inspection shall be carried out, and the standard penetration method shall be selected for inspection; the grouting inspection point is 3% of the number of grouting holes, and when the pass rate is less than 80%, repeated grouting shall be carried out.

本高富水黄土砂卵石地层变压管井中井施工方法施工方便、安全可靠,沉井作为施工检查井工作面,可以有效减少后期施工过程降水量,使管道工程和“井中井”施工可以在干法条件下作业,保证了施工过程操作人员安全,提高了“井中井”的施工质量。The construction method of the well in the piezo-transformed tube well in the loess sand and pebble formation with high water richness is convenient, safe and reliable for construction. The operation under the conditions ensures the safety of the operators during the construction process and improves the construction quality of the "well in the well".

另外,本高富水黄土砂卵石地层变压管井中井施工方法封闭质量好、提高薄弱处结构耐久性,在井身、管身与管口接头等应力最大部位进行双液注浆,对产生疲劳缝隙薄弱处进行充分包裹、加固补强,确保即使下游污水处理厂长期非正常运行,管身受交替升降的水击压力、管道震动,管壁和检查井井身也不会产生裂缝而导致井外水、砂内渗,从而造成井周排水体系崩溃,引起深层砂土掏空、黄土沉陷、井周路面塌陷。In addition, this high-water-rich loess sand and pebble formation piezo-transformer tube well construction method has good sealing quality and improves the structural durability of weak parts. Double-liquid grouting is carried out in the most stressed parts such as the well body, the pipe body and the nozzle joint, so as to prevent fatigue cracks. Weak areas should be fully wrapped and reinforced to ensure that even if the downstream sewage treatment plant operates abnormally for a long time, the pipe body is subject to alternate lifting and lowering water hammer pressure and pipe vibration, and the pipe wall and the inspection well body will not crack and cause water outside the well. , sand infiltration, resulting in the collapse of the drainage system around the well, causing deep sandy soil hollowing, loess subsidence, and road surface collapse around the well.

以上所述的仅是本发明的一种实施方式,应当指出,对于本领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以作出若干变型和改进,这些也应视为属于本发明的保护范围。The above is only an embodiment of the present invention. It should be pointed out that for those of ordinary skill in the art, without departing from the principle of the present invention, several modifications and improvements can be made, and these should also be regarded as It belongs to the protection scope of the present invention.

Claims (7)

1.一种高富水黄土砂卵石地层变压管井中井施工方法,包括以下步骤:1. A method for constructing a piezo-transformer well in a high-water-rich loess sand pebble stratum, comprising the following steps: a)沉井施工a) caisson construction 在预定位置开挖沉孔,沉孔的深度超过主管道的预定深度;Excavate a counterbore at a predetermined position, and the depth of the counterbore exceeds the predetermined depth of the main pipeline; 在沉孔下部井筒四壁和底壁上根据施工图制作钢筋混凝土沉井,沉井采用不排水封底,沉井采用多次制作和下沉,沉井两侧侧壁预留有主管道通过的洞口;The reinforced concrete caisson is made on the four walls and bottom wall of the shaft at the lower part of the caisson according to the construction drawings. The caisson is sealed with no drainage. The caisson is made and sunk many times. The side walls of the caisson are reserved for the passage of the main pipeline. hole; b)顶管施工b) Pipe jacking construction 依次将主管道的管节吊装至沉井内,通过顶进设备将两节主管道的管节分别从沉井的洞口顶出,两节主管道的管节之间具有间隙;The pipe sections of the main pipeline are hoisted into the caisson in turn, and the pipe sections of the two main pipes are respectively pushed out from the opening of the caisson through the jacking equipment, and there is a gap between the pipe sections of the two main pipes; c)测量定位c) Measuring and positioning 根据图纸中检查井的中心坐标,通过沉井的结构尺寸及布置方式,推算出沉井四角的坐标;According to the center coordinates of the inspection well in the drawing, the coordinates of the four corners of the caisson are calculated through the structure size and arrangement of the caisson; d)检查井下部井筒施工d) Check the wellbore construction at the bottom of the well 现场分步施工,第一步施工井室底板,第二步施工井室井壁,第三次施工钢筋混凝土井筒;Step-by-step construction on site, the first step is to construct the well chamber floor, the second step to construct the well chamber wall, and the third step to construct the reinforced concrete wellbore; 将沉井的底板凿毛,再浇筑检查井的底板混凝土,在浇筑底板混凝土时预埋井壁钢筋;Chisel the bottom of the caisson, then pour the bottom concrete of the inspection well, and pre-embed the steel reinforcement of the well wall when pouring the bottom concrete; 检查井壁施工前,根据沉井和检查井之间的距离截取管道,在两侧明接管道,并浇筑基础,同时将管道外壁凿毛,然后加工模板及钢筋,井室井壁上端面预埋井筒的钢筋;Before the construction of the inspection well wall, intercept the pipeline according to the distance between the caisson and the inspection well, connect the pipeline on both sides, and pour the foundation. Rebar of the shaft; 井筒为方形井筒,自下而上搭设支架,提供操作人员的工作平台,管道穿越井壁处用油麻沥青砂填实,迎水面用聚硫密封膏封堵;The wellbore is a square wellbore, and supports are erected from bottom to top to provide a working platform for operators. The pipeline crossing the well wall is filled with linseed tar sand, and the upstream surface is sealed with polysulfide sealant; e)检查井下部井筒四周回填e) Check the backfill around the wellbore downhole 井四周回填采用水坠砂现场的砂回填,带回填面不再有细微气泡冒出时,可以停止注水;The backfill around the well is backfilled with the sand from the water-falling sand site. When the backfill surface no longer has fine air bubbles, the water injection can be stopped; 现场水坠砂完成后,及时到现场环刀取样,用天平和微波炉烘干法得到相关数据,测出压实度;After the on-site water-falling sand is completed, sample the ring knife at the site in time, obtain the relevant data with the balance and microwave oven drying method, and measure the degree of compaction; 井筒外部平台可将井室部分的四周土提前回填一定高度,回填至支管高程后,安装支管,支管回填时做好成品保护;The external platform of the wellbore can backfill the surrounding soil of the well room to a certain height in advance. After backfilling to the elevation of the branch pipe, install the branch pipe, and protect the finished product when the branch pipe is backfilled; f)检查井上部井筒施工及回填f) Inspection of wellbore construction and backfilling in the upper part of the well 检查井的上部井筒结构为砖砌体,钢筋混凝土井筒完成后,回填至钢筋混凝土井筒顶部;The upper shaft structure of the inspection well is brick masonry. After the reinforced concrete shaft is completed, it is backfilled to the top of the reinforced concrete shaft; g)道路路基、底基层施工g) Construction of road subgrade and sub-base 因检查井在道路的路基范围内,当沉井回填至道路路床顶面后,沉井内的路基回填,与整体道路的基层一同施工;Since the inspection well is within the subgrade range of the road, after the caisson is backfilled to the top of the road bed, the subgrade in the caisson is backfilled and constructed together with the base of the overall road; h)液浆的制备及注浆加固h) Preparation of slurry and grouting reinforcement 钻孔平面位置与沉井内、外处软弱薄弱部位的平面位置应一致,且选取多点布置注浆孔,点与点间距≤1.0m;The plane position of the drilling hole should be consistent with the plane position of the weak and weak parts inside and outside the caisson, and select multiple points to arrange grouting holes, and the distance between points should be ≤1.0m; 成孔采用螺旋钻回转钻机,成孔直径70mm~110mm,垂直度允许偏差为±1%,孔深自路基至顶管管道或软弱薄弱部位;The auger rotary drilling machine is used to form the hole, the diameter of the hole is 70mm to 110mm, the allowable deviation of verticality is ±1%, and the hole depth is from the roadbed to the pipe jacking pipe or weak and weak parts; 将水泥:水玻璃:水按质量比例1:0.1:1配比制得双液浆,使用前双浆液均匀拌合并经过筛网过滤;Mix cement: water glass: water in a mass ratio of 1:0.1:1 to prepare a double-liquid slurry. Before use, the double-liquid slurry is evenly mixed and filtered through a screen; 双浆液通过注浆管灌注,灌注前应用水泥砂浆封闭注浆管外侧与孔口之间的空隙,待封闭泥浆凝固后,捅去注浆管的活络堵头,注入压力0.4Mpa,注浆过程中双浆液不停缓慢搅拌,搅拌时间小于初凝时间,注浆的流量在5~10L/min,水温控制在0℃~30℃之间,双浆液的初凝时间55min;The double grout is poured through the grouting pipe. Before pouring, the gap between the outside of the grouting pipe and the orifice should be closed with cement mortar. The medium and double slurries are continuously stirred slowly, the stirring time is less than the initial setting time, the flow rate of grouting is 5~10L/min, the water temperature is controlled between 0 ℃ ~ 30 ℃, and the initial setting time of the double slurries is 55min; i)养护和检查验收i) Maintenance and inspection acceptance 对注浆完成区域采用封闭交通管理,禁止周围大型机械、振动机械通行施工;Closed traffic management is adopted for the area where grouting is completed, and the surrounding large-scale machinery and vibration machinery are prohibited for construction; 注浆结束28天后进行检验,选用标准贯入方法进行检测,注浆检验点为注浆孔数的3%,合格率小于80%时,实施重复注浆。28 days after grouting is completed, the inspection is carried out, and the standard penetration method is used for inspection. The grouting inspection point is 3% of the number of grouting holes. When the pass rate is less than 80%, repeated grouting is performed. 2.根据权利要求1所述的高富水黄土砂卵石地层变压管井中井施工方法,其特征是:2. the high-water-rich loess sand and pebble formation piezo-transformer tube well construction method according to claim 1, is characterized in that: 所述步骤d)检查井下部井筒施工,下部井筒一次浇筑高度3m左右,大于3m的可分节施工。In the step d), the construction of the lower wellbore is checked, and the lower wellbore is about 3m high for one pouring, and the construction can be divided into sections larger than 3m. 3.根据权利要求1所述的高富水黄土砂卵石地层变压管井中井施工方法,其特征是:3. the construction method in a piezo-transformer tube well in a high-water-rich loess sand pebble stratum according to claim 1, is characterized in that: 所述步骤e)中检查井上部井筒施工,上部井筒内外井壁采用1:2水泥砂浆加5%防水剂抹面厚20mm。In the step e), the construction of the upper wellbore of the inspection well is checked, and the inner and outer well walls of the upper wellbore are plastered with 1:2 cement mortar and 5% waterproofing agent with a thickness of 20 mm. 4.根据权利要求1所述的高富水黄土砂卵石地层变压管井中井施工方法,其特征是:4. the high-water-rich loess sand and pebble stratum piezo-transformer tube well construction method according to claim 1, is characterized in that: 所述步骤h)液浆的制备及注浆加固,制备水泥浆中搅拌时间应大于2min,水灰比控制在0.8~1,然后根据泥浆搅拌桶的容积向搅拌桶内掺入定量的水玻璃溶液并搅拌均匀,水玻璃和水泥浆的体积比控制在0.5~0.8之间。In the step h) preparation of slurry and grouting reinforcement, the stirring time in preparing the slurry should be greater than 2 minutes, the water-cement ratio should be controlled at 0.8 to 1, and then a certain amount of water glass should be mixed into the mixing bucket according to the volume of the slurry mixing bucket. The solution is stirred evenly, and the volume ratio of water glass and cement slurry is controlled between 0.5 and 0.8. 5.根据权利要求1所述的高富水黄土砂卵石地层变压管井中井施工方法,其特征是:5. the high-water-rich loess sand and pebble stratum piezo-transformer tube well construction method according to claim 1, is characterized in that: 所述步骤h)液浆的制备及注浆加固,根据沉井面积,采用梅花型布置注浆孔,孔深自路基至管节,采用螺旋钻回转钻进,成孔直径70mm~110mm,垂直度允许偏差为±1%。In the step h) preparation of slurry and grouting reinforcement, according to the area of the caisson, the grouting holes are arranged in a plum blossom shape, and the hole depth is from the roadbed to the pipe joint, and the auger is used for rotary drilling. Degree tolerance is ±1%. 6.根据权利要求1所述的高富水黄土砂卵石地层变压管井中井施工方法,其特征是:6. The construction method for a piezo-transformer tube well in a high-water-rich loess sand pebble stratum according to claim 1, is characterized in that: 预制沉井盖板,沉井盖板上预留有检查井顶部的通孔,在h)液浆的制备及注浆加固后,沉井盖板盖在沉井上侧。The caisson cover is prefabricated, and the through hole at the top of the inspection well is reserved on the caisson cover. After h) slurry preparation and grouting reinforcement, the caisson cover is covered on the upper side of the caisson. 7.根据权利要求1所述的高富水黄土砂卵石地层变压管井中井施工方法,其特征是:7. The construction method for a piezo-transformer tube well in a high-water-rich loess sand pebble stratum according to claim 1, is characterized in that: 所述步骤h)中注浆管分为若干第一注浆管和若干第二注浆管,若干第一注浆管分为两组,两组第一注浆管与两侧管节对应,每组第一注浆管下端伸至处于沉井内侧和外侧的管节上侧;若干第二注浆管下端伸至检查井上部井筒与下部井筒连接处的四周。In the step h), the grouting pipes are divided into several first grouting pipes and several second grouting pipes, and the several first grouting pipes are divided into two groups, and the two groups of first grouting pipes correspond to the pipe joints on both sides, The lower ends of each group of first grouting pipes extend to the upper side of the pipe sections inside and outside the caisson; the lower ends of several second grouting pipes extend to the periphery of the connection between the upper wellbore and the lower wellbore of the inspection well.
CN202011125006.3A 2020-10-20 2020-10-20 Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well Active CN112144559B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011125006.3A CN112144559B (en) 2020-10-20 2020-10-20 Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011125006.3A CN112144559B (en) 2020-10-20 2020-10-20 Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well

Publications (2)

Publication Number Publication Date
CN112144559A true CN112144559A (en) 2020-12-29
CN112144559B CN112144559B (en) 2024-10-29

Family

ID=73954149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011125006.3A Active CN112144559B (en) 2020-10-20 2020-10-20 Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well

Country Status (1)

Country Link
CN (1) CN112144559B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113373980A (en) * 2021-05-27 2021-09-10 合肥市市政设计研究总院有限公司 Concrete inverted hanging well suitable for saturated sand and construction method thereof
CN114411927A (en) * 2022-02-21 2022-04-29 中建八局南方建设有限公司 Waterproof structure of drainage well and construction method thereof
CN115492144A (en) * 2022-09-15 2022-12-20 中国一冶集团有限公司 Construction method of pipe jacking and open caisson in sandbank area

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070058787A (en) * 2005-12-05 2007-06-11 주식회사 우지스건설 Well-order grouting device and well-pipe construction method using the same
AU2016100200A4 (en) * 2015-06-09 2016-03-24 Southern Seawall Solutions Pty Limited Improved caisson emplacement system and method
CN207377561U (en) * 2017-07-25 2018-05-18 马钢(集团)控股有限公司 The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN108277816A (en) * 2018-01-04 2018-07-13 浙江大学城市学院 A kind of digging-free construction method of well foundation
CN108457289A (en) * 2018-03-21 2018-08-28 广州市恒盛建设工程有限公司 A kind of open caisson construction method of complex condition
CN108661650A (en) * 2018-04-23 2018-10-16 中铁隧道局集团有限公司 A kind of rich water magmatic body area depth pozo shaft construction method
CN209854753U (en) * 2019-04-18 2019-12-27 北京市政建设集团有限责任公司 A kind of caisson structure under the condition of pressurized water fine sand layer
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN213417870U (en) * 2020-10-20 2021-06-11 安徽水利开发有限公司 High rich water loess sand cobble stratum vary voltage tube well structure in

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070058787A (en) * 2005-12-05 2007-06-11 주식회사 우지스건설 Well-order grouting device and well-pipe construction method using the same
AU2016100200A4 (en) * 2015-06-09 2016-03-24 Southern Seawall Solutions Pty Limited Improved caisson emplacement system and method
CN207377561U (en) * 2017-07-25 2018-05-18 马钢(集团)控股有限公司 The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN108277816A (en) * 2018-01-04 2018-07-13 浙江大学城市学院 A kind of digging-free construction method of well foundation
CN108457289A (en) * 2018-03-21 2018-08-28 广州市恒盛建设工程有限公司 A kind of open caisson construction method of complex condition
CN108661650A (en) * 2018-04-23 2018-10-16 中铁隧道局集团有限公司 A kind of rich water magmatic body area depth pozo shaft construction method
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN209854753U (en) * 2019-04-18 2019-12-27 北京市政建设集团有限责任公司 A kind of caisson structure under the condition of pressurized water fine sand layer
CN213417870U (en) * 2020-10-20 2021-06-11 安徽水利开发有限公司 High rich water loess sand cobble stratum vary voltage tube well structure in

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113373980A (en) * 2021-05-27 2021-09-10 合肥市市政设计研究总院有限公司 Concrete inverted hanging well suitable for saturated sand and construction method thereof
CN114411927A (en) * 2022-02-21 2022-04-29 中建八局南方建设有限公司 Waterproof structure of drainage well and construction method thereof
CN115492144A (en) * 2022-09-15 2022-12-20 中国一冶集团有限公司 Construction method of pipe jacking and open caisson in sandbank area
CN115492144B (en) * 2022-09-15 2023-08-29 中国一冶集团有限公司 Construction method of pipe-jacking open caisson in sand area

Also Published As

Publication number Publication date
CN112144559B (en) 2024-10-29

Similar Documents

Publication Publication Date Title
CN112253162B (en) Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method
CN106958256B (en) A caisson construction technology with layered pouring and multiple subsidence
CN103343544B (en) Construction method for large-scale open caisson
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN108411802A (en) A kind of underwater method for repairing pile foundation and scour hole
CN206070508U (en) Device for reinforcing foundation
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
CN112144559B (en) Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well
CN107417182A (en) Intumescent high polymer cement mortar, grouting and reinforcing device and grouting strengthening method
CN114622572A (en) Large-scale round foundation pit triaxial mixing pile supporting structure and construction method thereof
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN109706952A (en) Large-scale well-sinking construction method
CN111119128A (en) A kind of natural rockfill dam in dammed lake, reinforcement and anti-seepage method
CN110080248A (en) Nearly depth of water foundation pit supporting construction
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN206736963U (en) Ditch millet section high water level district lid tunnel stagnant water structure
CN103790148A (en) Combined treatment construction method for collapsible loess foundation
CN114575355B (en) Soil protection construction method
CN216920368U (en) A large-scale circular foundation pit three-axis stirring pile support structure
CN112482347A (en) Construction method of soft soil treatment reinforcing layer and soft soil treatment reinforcing layer
CN108035379A (en) A kind of pipe gallery and its construction method
CN107059904A (en) A kind of underground pipe gallery ponding well excavation method
CN112554167A (en) Novel poured large-particle-size aggregate UHPC soft soil road foundation pile
CN213417870U (en) High rich water loess sand cobble stratum vary voltage tube well structure in
CN115095336B (en) Shield construction method for underground railway and bridge pile of subway line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant