CN108035423A - Potential energy pressurized rainwater drainage and storage system and method for sponge city - Google Patents

Potential energy pressurized rainwater drainage and storage system and method for sponge city Download PDF

Info

Publication number
CN108035423A
CN108035423A CN201711319216.4A CN201711319216A CN108035423A CN 108035423 A CN108035423 A CN 108035423A CN 201711319216 A CN201711319216 A CN 201711319216A CN 108035423 A CN108035423 A CN 108035423A
Authority
CN
China
Prior art keywords
motor
pipeline
driven valve
rainwater
water tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711319216.4A
Other languages
Chinese (zh)
Other versions
CN108035423B (en
Inventor
郁文红
王宽
闫辉
张向东
王永华
刘政
石利燕
龚子阳
宋琳
宋影芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Technology
China Railway Construction Group Co Ltd
Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd
Original Assignee
North China University of Technology
China Railway Construction Group Co Ltd
Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Technology, China Railway Construction Group Co Ltd, Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd filed Critical North China University of Technology
Priority to CN201711319216.4A priority Critical patent/CN108035423B/en
Publication of CN108035423A publication Critical patent/CN108035423A/en
Application granted granted Critical
Publication of CN108035423B publication Critical patent/CN108035423B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The system comprises a rainwater tank, a waste water tank, a first overflow pipe, a second overflow pipe, a municipal sewage pipe network, a municipal rainwater pipe network, a filter, a first electric valve, a second electric valve, a third electric valve, a first check valve, a second check valve, a fourth electric valve, a fifth electric valve, a sixth electric valve, a third check valve, a seventh electric valve, a fourth check valve, an eighth electric valve, a ninth electric valve, a fifth check valve, a sixth check valve, a tenth electric valve, a first electric regulating valve, a first piston type water storage tank, a second piston type water storage tank, an eighth check valve, a ninth check valve and a controller. The invention also comprises a potential energy pressurized rainwater storage method for the sponge city. When the rainfall is large in rainy days and the rainwater on the ground is not smoothly discharged, the drainage capacity of the rainwater pipe can be improved by using the rainwater drainage device, and the problem of water accumulation on the ground around a super high-rise or high-rise building can be well solved.

Description

Potential energy pressurization rainwater row for sponge city stores system and method
Technical field
The present invention relates to a kind of potential energy pressurization rainwater row for sponge city to store system and method.
Background technology
Sponge city, is new generation of city storm water man- agement concept, refers to that city is adapting to environmental change and reply rainwater band Natural calamity come etc. has good " elasticity ", also referred to as " water elasticity city ".International term is " low shadow Ring exploitation storm-water system structure ".Water suction when raining, water storage, infiltration, water purification, it is necessary to when by the water stored " release " and be subject to profit With.
Sponge city is built, first has to reverse idea.Mainly set for storm-water system with " slow row's sustained release " and " store and avoid the peak hour " Meter theory, not only avoids flood, but also effectively have collected rainwater.
Roof drain is to be located at the inlet that rain water on roof is entered storm sewer by gutter.Roof drain has flow straightening grid device, Rain water on roof can be excluded rapidly, grid has rectified action, avoids the formation of excessive vortex, stablizes water level before bucket, reduces aeration, It is rapid to exclude rain water on roof, snow-broth, and can effectively stop compared with bigger material.The rainwater that roof drain is collected enters storm sewer, flow to In raintank, when the rainwater of raintank storage exceedes a certain liquid level, discharged through overflow pipe.
Gravity stream refers to rainwater in rain pipe, by the effect of gravity(The gradient)Flow forward, is generally not filled with flowing, Draining when suitable amount of rainfall is smaller;Pressure current refers to by pressurizeing to rainwater, rainwater is formed the state flowing of quick flowing full, It is adapted to use when amount of rainfall is larger.
In many cities in China, all there are rainwater to discharge the problem of not smooth, and specific Producing reason can be roughly divided into The following aspects:
1. dirty block seriously is blocked on ground.When rainy season set, under the influence of compared with heavy showers, urban discharging pipeline is because caliber Etc. reason so that drainage speed can not meet requirement, meanwhile, silt of the storm sewer inner clip band from ground, leaf and part House refuse etc., cleaning and dredging to pipeline, which are safeguarded, brings very big difficulty.
2. storm sewer water outlet is obstructed.The rainwater in current China major part city, is discharged into nearby by storm sewer The water bodys such as river.But much it is located at the city of plains region, because being restricted be subject to position landform, water outlet, which uses, to be flooded No formula so that the position of water outlet will be less than the water level of water body.In rainy season, water body water level generally goes up, and is subject to water body water level Jacking, the water velocity inside storm sewer slow down, and cause the drainability of drainage pipeline and reduce.When rainy season set There is ponding in low-lying land rapid lapse of time, have impact on the current of nearby residents.
3. lack necessary connection between urban rainwater pipeline.Current storm sewer can generally build up several independent drainings System carries out rainwater exclusion, is not connected mutually between each drainage system.But in actual drainage procedure, because rain pipe The time that the charge for remittance of each system in road is how many, catchments has it uncertain, so can not possibly be at the same time in flood season rainwater peak flow Occur, the drainability of each drainage system is also just different.
PHC pile piles, i.e. PHC piles.It is to use pre-tensioned prestressing centrifugal molding process, and passes through 10 atmospheric pressure, 1800 DEG C or so of steam curing, are made a kind of hollow cylinder shape concrete prefabricated element, and standard knot is a length of 10m, diameter is from 300mm~800mm, strength grade of concrete >=C80.PHC pile piles are held jointly by collateral resistance and end resistance By upper load, and it is adaptable to the big geological conditions of supporting course fluctuations, therefore adaptation region is wide, building type is more. In heavy construction, the usage amount of PHC pile piles is very big, and the usage amount of single project is usually up to hundreds if not thousands of roots, pile foundation Depth is up to tens of rice.For protection stake lower end and back cover, prevent from preventing stake from shifting into soil in pipe, effectively improve the list of pile pile Pile bearing capacity, when PHC pile piles carry out pressing pile construction, often installs pile top at the termination position of PHC pile piles.Pile top have it is cross and Tip type etc..Superstructure load friction is undertaken for using the frictional force between end-resistance and pile body side and soil jointly PHC pile piles, its pile top is still in Soft Soil Layer.
The content of the invention
The technical problem to be solved by the invention is to provide one kind when rainy day rainfall is larger, ground rainwater discharge has some setbacks When smooth, rainwater can be carried out to zero energy consumption and pressurizeed, the fluidised form of rainwater in the duct is become filled with stream by being not filled with stream, improve rain The discharge capacity of water pipe, can solve the problems, such as that what ground around Super High or skyscraper produced ponding is used for sponge city well Potential energy pressurization rainwater row store system and method.
The technical solution adopted by the present invention to solve the technical problems is:
The present invention for sponge city potential energy pressurization rainwater row storage system, including raintank, waste water tank, the first overflow pipe, Second overflow pipe, municipal sewage pipe network, municipal Storm Sewer Network and filter, are additionally provided with the first motor-driven valve, the second motor-driven valve, the 3rd Motor-driven valve, first check-valve, second check-valve, the 4th motor-driven valve, the 5th motor-driven valve, the 6th motor-driven valve, the 3rd check-valves, the 7th Motor-driven valve, the 4th check-valves, the 8th motor-driven valve, the 9th motor-driven valve, the 5th check-valves, the 6th check-valves, the tenth motor-driven valve, first Electric control valve, first piston formula water tank, second piston formula water tank, the 8th check-valves, the 9th check-valves and controller;
One end of first motor-driven valve is connected with the pipeline that same outdoor ground discharge outlet is connected, and the other end passes through pipeline and One check-valves is connected, and the first check-valve is connected by pipeline with the right end of second piston formula water tank;Described second The right end of piston type water tank is connected by pipeline second check-valve, and the second check-valve passes through pipeline and the second motor-driven valve It is connected, the pipeline that second motor-driven valve is respectively equipped with the 3rd check-valves by pipeline with both ends is connected, one of them Three check-valves are connected by pipeline with municipal Storm Sewer Network, another the 3rd check-valves is connected by pipeline with the 9th motor-driven valve Connect, the 9th motor-driven valve is connected, by pipeline and same raintank by pipeline with second piston formula water tank left end respectively The first connected overflow pipe is connected;
One end of 8th motor-driven valve is connected with the pipeline that same outdoor ground discharge outlet is connected, and the other end passes through pipeline and Two piston type water tank left ends are connected;
First piston plate is equipped with the first piston formula water tank, the second piston formula water tank is equipped with second piston plate, The first piston plate is connected by connecting rod with second piston plate, and the right end top of the second piston formula water tank is equipped with liquid Bit detector;
One end of 4th motor-driven valve is connected by pipeline with the 6th check-valves, by pipeline and the 7th motor-driven valve phase respectively Connection, the 6th check-valves are connected by pipeline with raintank, and the 7th motor-driven valve passes through pipeline and the 5th check-valves It is connected, the 5th check-valves is connected by pipeline with the right end of first piston formula water tank, the 4th motor-driven valve The other end is connected by pipeline with the 4th check-valves, and the 4th check-valves is by managing the left side with first piston formula water tank End is connected;
One end of 3rd motor-driven valve is connected by pipeline with waste water tank, and the other end passes through pipeline and the tenth motor-driven valve respectively It is connected, is connected by pipeline with the first electric control valve, the tenth motor-driven valve passes through pipeline and the 8th check-valves respectively It is connected, is connected by pipeline with municipal sewage pipe network, first electric control valve passes through pipeline and the 9th check-valves phase Connection, the 9th check-valves are connected by pipeline with the left end of first piston formula water tank, the 8th check-valves difference It is connected by pipeline with the 5th motor-driven valve, is connected by pipeline with the 6th motor-driven valve, the 5th motor-driven valve passes through pipeline It is connected with the left end of first piston formula water tank, the 6th motor-driven valve passes through pipeline and the right end of first piston formula water tank It is connected;
The upper end of the waste water tank is connected with filter by pipeline, is connected by pipeline with the second overflow pipe respectively, institute The second overflow pipe is stated by pipeline with municipal sewage pipe network to be connected.
Further, the second electric control valve, the 7th check-valves, closed water fender and PHC are additionally provided with, described second is electronic One end of regulating valve is connected by the pipeline between pipeline and second check-valve and the second motor-driven valve, second motorized adjustment The other end of valve is connected by pipeline with the 7th check-valves in PHC, and the closed water fender is installed on PHC Interior, below the 7th check-valves, pile top PHC described is equipped with permeability hole, and the first water is equipped with pile top PHC described Pressure sensor.
Further, liquid level sensor and the second hydraulic pressure sensor are equipped with the municipal Storm Sewer Network.
Further, the right end of the second piston formula water tank is equipped with the 3rd hydraulic pressure sensor.
Further, the right end top of the first piston formula water tank is equipped with the first scavenging air valve, the second piston formula storage The left upper part of water pot is equipped with the second scavenging air valve.
Further, the first piston formula water tank, second piston formula water tank are arranged in basement computer room.
Potential energy pressurization rainwater row's storage method for sponge city of the present invention, detailed process are as follows:
Original state:During non-rainfall, there is no water storage in roof rain water case, first piston plate and second piston plate are close to left wall face, All valves are in closed mode, and waste water tank normally collects the waste water in the high area of building, when the waste water of collection exceedes a certain liquid During position, municipal sewage pipe network is expelled to from the second overflow pipe, or open the 3rd motor-driven valve and the tenth motor-driven valve directly by waste water Discharge municipal sewage pipe network;
Operating mode one:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve and the second motor-driven valve are opened, Rainwater is allowed to enter second piston formula water tank by pipeline, second piston formula water tank gradually fills water, when liquid level detector detects When exceeding a certain setting to water level, controller is sent a signal to, controller controls the 3rd motor-driven valve to open, utilizes high-order waste water The static pressure of case promotes first piston plate and second piston plate to add the rainwater of second piston formula water tank to piston wall low order end Pressure is expelled to municipal Storm Sewer Network;Since raintank have collected rainwater at this time, the 7th motor-driven valve, the storage of first piston formula are opened Sewage in water pot drains into municipal sewage pipe network then using the static pressure of high-order raintank through the 5th motor-driven valve;
Operating mode two:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve and the second motor-driven valve are opened, Rainwater is allowed to enter second piston formula water tank by pipeline, second piston formula water tank gradually fills water, when liquid level detector detects When exceeding a certain setting to water level, controller is sent a signal to, controller controls the 4th motor-driven valve to open, at this time high-order rainwater Case have collected rainwater, and using the static pressure of this part rainwater, first piston plate and second piston plate are pushed to piston Wall low order end, municipal Storm Sewer Network is expelled to by the rainwater pressurization of second piston formula water tank;The 7th motor-driven valve is opened, utilizes rain First piston plate and second piston plate are pushed to piston wall high order end by water tank static pressure, the rainwater in first piston formula water tank Discharge, or directly open the 5th motor-driven valve and the rainwater in first piston formula water tank is drained into municipal sewage pipe network;
Operating mode three:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve and the second motor-driven valve are opened, Rainwater is allowed to enter second piston formula water tank by pipeline, second piston formula water tank gradually fills water, when liquid level detector detects When exceeding a certain setting to water level, controller is sent a signal to, controller controls the 8th motor-driven valve to open, and ground rainwater is from the Pipeline enters on the left of two piston type water tanks, second piston plate is pushed directly on to piston wall low order end, by second piston formula water storage The rainwater pressurization of tank is expelled to municipal rain pipe, so, that is, have collected another part ground rainwater, and utilize ground rainwater Static pressure discharges the rainwater collected;Second of rainwater collected can directly be opened when rainwater discharge pressure is reduced 9th motor-driven valve aerial drainage is to municipal Storm Sewer Network.
Further, this method system for use in carrying is additionally provided with the second electric control valve, the 7th check-valves, closed water fender and PHC Stake, one end of second electric control valve are connected by the pipeline between pipeline and second check-valve and the second motor-driven valve, The other end of second electric control valve is connected by pipeline with the 7th check-valves in PHC, the closed gear Water plate is installed in PHC, and positioned at the 7th check-valves lower section, pile top PHC described is equipped with permeability hole, PHC described The first hydraulic pressure sensor is equipped with pile top;
Correspondingly, the method is equipped with operating mode four:On the basis of operating mode one, operating mode two, operating mode three, remaining method of operation is not Become, only by the unlatching that the opening variation of the second motor-driven valve is the first electric control valve, pressurization rainwater is drained into PHC pile piles, and then Drained into by osmosis in underground.
The present invention is using piston type water tank as rain collector, it is intended to when rainy day excess surface water is more, to ground rainwater Collect and carry out pressurised exhaust to municipal rain pipe, improve discharge efficiency, added pressure then comes from high-rise waste water tank or rain Water tank.
Compared with prior art, the present invention has the following advantages:
(1)By the use of the high water tank of Super High or skyscraper as power water tank, piston pressurization is promoted using its static pressure Discharge rainwater, it is not necessary to which consumption electric power drives water pump, realizes that zero energy consumption of rainwater is pressurizeed;
(2)The pressurized discharge of ground rainwater so that the fluidised form of rainwater in the duct is full of stream, unit interval from rheology is not filled with The inflow-rate of water turbine of interior conduit increases, and significantly improves conveyance capacity of the rain pipe in heavy rain, avoids Super High or skyscraper ground Ponding.
In addition, the present invention can utilize the space in the depth and PHC pile piles of pile pile to place pressurization rain pipe, opened up in pile top Permeability hole enables rainwater osmosis into soil, recharge of groundwater.
Brief description of the drawings
Fig. 1 is that the potential energy pressurization rainwater row for sponge city of the present invention stores the structure diagram of system embodiment;
In figure:1st, the first motor-driven valve, the 2, second motor-driven valve, 3, liquid level detector, 4, controller, the 5, the 3rd motor-driven valve, 6, first Check-valves, 7, second check-valve, the 8, the 4th motor-driven valve, the 9, the 5th motor-driven valve, the 10, the 6th motor-driven valve, the 11, the 3rd check-valves, 12, 7th motor-driven valve, the 13, the 4th check-valves, the 14, the 8th motor-driven valve, the 15, the 9th motor-driven valve, the 16, first scavenging air valve, 17, first changes Air valve, the 18, the 5th check-valves, 19, raintank, 20, waste water tank, the 21, first overflow pipe, the 22, second overflow pipe, the 23, the 6th stops Return valve, the 24, first electric control valve, the 25, the 7th check-valves, 26, closed water fender, 27, permeability hole, 28, pile top, 29, PHC Stake, the 30, the tenth motor-driven valve, the 31, second electric control valve, 32, municipal Storm Sewer Network, 33, liquid level sensor, 34, filter, 35th, the first hydraulic pressure sensor, 36, first piston formula water tank, 37, first piston plate, 38, second piston formula water tank, 39, Two piston plates, the 40, the 8th check-valves, the 41, the 9th check-valves, the 42, second hydraulic pressure sensor, the 43, the 3rd hydraulic pressure sensor.
Embodiment
The invention will be further described with reference to the accompanying drawings and embodiments.
With reference to Fig. 1, the potential energy for being used for sponge city pressurization rainwater row's storage system of the present embodiment, including raintank 19, give up Water tank 20, the first overflow pipe 21, the second overflow pipe 22, municipal sewage pipe network, municipal Storm Sewer Network 32 and filter 34, are additionally provided with First motor-driven valve 1, the second motor-driven valve 2, the 3rd motor-driven valve 5, first check-valve 6, second check-valve 7, the 4th motor-driven valve the 8, the 5th Motor-driven valve 9, the 6th motor-driven valve 10, the 3rd check-valves 11, the 7th motor-driven valve 12, the 4th check-valves 13, the 8th motor-driven valve the 14, the 9th Motor-driven valve 15, the 5th check-valves 18, the 6th check-valves 23, the tenth motor-driven valve 30, the first electric control valve 24, the storage of first piston formula Water pot 36, second piston formula water tank 38, the 8th check-valves 40, the 9th check-valves 41 and controller 4;
One end of first motor-driven valve 1 is connected with the pipeline that same outdoor ground discharge outlet is connected, the other end by pipeline with First check-valve 6 is connected, and the first check-valve 6 is connected by pipeline with the right end of second piston formula water tank 38;Institute The right end for stating second piston formula water tank 38 is connected by pipeline second check-valve 7, and the second check-valve 7 passes through pipe respectively Road is connected with the second motor-driven valve 2, and second motor-driven valve 2 is respectively equipped with the pipeline of the 3rd check-valves 11 by pipeline and both ends It is connected, one of them the 3rd check-valves 11 is connected by pipeline with municipal Storm Sewer Network 32, another the 3rd check-valves 11 It is connected by pipeline with the 9th motor-driven valve 15, the 9th motor-driven valve 15 passes through pipeline and second piston formula water tank 38 respectively The first overflow pipe 21 that left end is connected, is connected by pipeline with same raintank 19 is connected;
One end of 8th motor-driven valve 14 is connected with the pipeline that same outdoor ground discharge outlet is connected, the other end by pipeline with 38 left end of second piston formula water tank is connected;
First piston plate 37 is equipped with the first piston formula water tank 36, the second piston formula water tank 38 is equipped with second and lives Seben 39, the first piston plate 37 are connected by connecting rod with second piston plate 39, the second piston formula water tank 38 Right end top is equipped with liquid level detector 3;
One end of 4th motor-driven valve 8 is connected with the 6th check-valves 23 by pipeline, is electronic by pipeline and the 7th respectively Valve 12 is connected, and the 6th check-valves 23 is connected by pipeline with raintank 19, and the 7th motor-driven valve 12 passes through pipeline It is connected with the 5th check-valves 18, the 5th check-valves 18 is connected by pipeline with the right end of first piston formula water tank 36 Connect, the other end of the 4th motor-driven valve 8 is connected by pipeline with the 4th check-valves 13, and the 4th check-valves 13 passes through pipe Reason is connected with the left end of first piston formula water tank 36;
One end of 3rd motor-driven valve 5 is connected by pipeline with waste water tank 20, and the other end passes through pipeline and the tenth electricity respectively Dynamic valve 30 is connected, is connected by pipeline with the first electric control valve 24, the tenth motor-driven valve 30 respectively by pipeline and 8th check-valves 40 is connected, is connected by pipeline with sewage network, and first electric control valve 24 passes through pipeline and Nine check-valves 41 are connected, and the 9th check-valves 41 is connected by pipeline with the left end of first piston formula water tank 36, institute State the 8th check-valves 40 respectively by pipeline with the 5th motor-driven valve 9 to be connected, by pipeline with the 6th motor-driven valve 10 be connected, institute State the 5th motor-driven valve 9 by pipeline with the left end of first piston formula water tank 36 to be connected, the 6th motor-driven valve 10 passes through pipe Road is connected with the right end of first piston formula water tank 36;
The upper end of the waste water tank 20 is connected with filter 34 by pipeline, is connected by pipeline with the second overflow pipe 22 respectively Connect, second overflow pipe 22 is connected by pipeline with municipal sewage pipe network.
In the present embodiment, the second electric control valve 31, the 7th check-valves 25, closed water fender 26 and PHC stakes 29 are additionally provided with; One end of second electric control valve 31 is connected by the pipeline between pipeline and 7 and second motor-driven valve 2 of second check-valve, The other end of second electric control valve 31 is connected by pipeline with the 7th check-valves 25 in PHC stakes 29, described Closed water fender 26 is installed in PHC stakes 29, and positioned at the lower section of the 7th check-valves 25, the pile top 28 of the PHC stakes 29, which is equipped with, oozes Open-work 27, the pile top 28 of the PHC stakes 29 is interior to be equipped with the first hydraulic pressure sensor 35.
In the present embodiment, 33 and second hydraulic pressure sensor 42 of liquid level sensor is equipped with the municipal administration Storm Sewer Network 32.
In the present embodiment, the right end of the second piston formula water tank 38 is equipped with the 3rd hydraulic pressure sensor 43.
In the present embodiment, the right end top of the first piston formula water tank 36 is equipped with the first scavenging air valve 16, and described second The left upper part of piston type water tank 38 is equipped with the second scavenging air valve 17.
In the present embodiment, the first piston formula water tank 36, first piston formula water tank 38 are arranged in basement computer room.
Potential energy pressurization rainwater row's storage method for sponge city of the present embodiment, detailed process are as follows:
Original state:During non-rainfall, there is no water storage in roof rain water case 19, first piston plate 37 and second piston plate 39 are close to a left side Wall, all valves are in closed mode, and waste water tank 20 normally collects the waste water in the high area of building, when the waste water of collection exceedes During a certain liquid level, municipal sewage pipe network is expelled to from the second overflow pipe 22, or open the 3rd motor-driven valve 5 and the tenth motor-driven valve 30 Waste water is directly discharged into municipal sewage pipe network;
Operating mode one:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve 1 and the second motor-driven valve are opened 2, allow rainwater to enter second piston formula water tank 38 by pipeline, second piston formula water tank 38 gradually fills water, works as level sensing Device 3 detects that water level exceedes a certain setting(Such as water surface distance top plate be less than 5 centimetres when)When, controller 4 is sent a signal to, Controller 4 controls the 3rd motor-driven valve 5 to open, and first piston plate 37 and second piston are promoted using the static pressure of high-order waste water tank 20 The rainwater pressurization of second piston formula water tank 38 is expelled to municipal Storm Sewer Network 32 by plate 39 to piston wall low order end;Due to this When raintank 19 have collected rainwater, open the 7th motor-driven valve 12, the sewage in first piston formula water tank 36 then utilizes height The static pressure of position raintank 19, municipal sewage pipe network is drained into through the 5th motor-driven valve 9;
Operating mode two:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve 1 and the second motor-driven valve are opened 2, allow rainwater to enter second piston formula water tank 38 by pipeline, second piston formula water tank 38 gradually fills water, works as level sensing When device 3 detects that water level exceedes a certain setting, controller 4 is sent a signal to, controller 4 controls the 4th motor-driven valve 8 to open, this Shi Gaowei raintanks 19 have collected rainwater, and using the static pressure of this part rainwater, first piston plate 37 and second is lived Seben 39 is pushed to piston wall low order end, and the rainwater pressurization of second piston formula water tank 38 is expelled to municipal Storm Sewer Network 32; The 7th motor-driven valve 12 is opened, first piston plate 37 and second piston plate 39 are pushed to piston wall most using 19 static pressure of raintank Left end, the rainwater discharge in first piston formula water tank 36, or directly the 5th motor-driven valve 9 of unlatching are by first piston formula water tank Rainwater in 36 drains into municipal sewage pipe network;
Operating mode three:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve 1 and the second motor-driven valve are opened 2, allow rainwater to enter second piston formula water tank 38 by pipeline, second piston formula water tank 38 gradually fills water, works as level sensing When device 3 detects that water level exceedes a certain setting, controller 4 is sent a signal to, controller 4 controls the 8th motor-driven valve 14 to open, Ground rainwater enters from 38 left side pipeline of second piston formula water tank, pushes directly on second piston plate 39 to piston wall low order end, By the water of second piston formula water tank 38(Rainwater)Pressurization is expelled to municipal Storm Sewer Network 32, so, that is, have collected another Part ground rainwater, and discharged the rainwater collected using ground rainwater static pressure;Second of rainwater collected can work as When rainwater discharge pressure is reduced, 15 aerial drainage of the 9th motor-driven valve is directly opened to municipal Storm Sewer Network 32;
Operating mode four:On the basis of operating mode one, operating mode two, operating mode three, remaining method of operation is constant, only by the second motor-driven valve 2 Opening variation is the unlatching of the first electric control valve 24, pressurization rainwater is drained into PHC pile piles, and then drain into ground by osmosis In lower soil.
In the course of work of the present invention, it is not necessary to which consumption electric power drives water pump, realizes that zero energy consumption of rainwater is pressurizeed, makes rainwater Fluidised form in the duct is to be increased full of stream, the inflow-rate of water turbine of unit interval interior conduit from rheology is not filled with, and significantly improves rain pipe Conveyance capacity in heavy rain, avoids Super High or skyscraper excess surface water.Simultaneously because using small one and large one two pistons, Discharge pressure enough in the case of, only use smaller size smaller sewage(Rainwater)Discharge larger volume rainwater can be reached Effect, save the sewage in high water tank(Rainwater), the water in the high water tank of unit volume is pressurizeed more volumes Rainwater.The discharge that so rainwater just can be more efficiently.
Such as:A certain high-rise building, its high water tank have the static pressure of 100m water columns, first piston plate 37 and second The area ratio of piston plate 39 is 1:5, pressure=pressure * areas, in the case where static pressure is certain, first piston formula water tank 36 It is 5 with the pressure ratio in second piston formula water tank 38:1, when ignoring the pressure loss, the pressure in second piston formula water tank 38 About 20m water columns.If the pressure head in second piston formula water tank 38 is larger, there is the problem of impact is produced to neighbouring well lid When, a drainpipe can be individually set up, the downstream place that rainwater is led to remotely is discharged, so as to not influence neighbouring rainwater Discharge.
Hydraulic pressure is adjusted:Second electric control valve 31 can be adjusted according to the pressure at 39 right side rainwater extrusion end of second piston plate Save flow and pressure that waste water enters piston.By adjust waste water into piston flow and pressure come adjust rainwater extrude stream Amount and pressure, avoid when municipal 32 heavy rain of rain pipe is formed full of stream, rainwater superpressure enters municipal Storm Sewer Network.Avoid the formation of Anti- excessive phenomenon.
The degree of filling of municipal Storm Sewer Network 32 and the pressure of pressurization rainwater entrance can pass through 33 He of liquid level sensor respectively Second hydraulic pressure sensor 42 of pressurization rainwater entrance is monitored, and in the case of non-extreme heavy rain, municipal Storm Sewer Network 32 is not filled In the case of full, even if rainwater superpressure sprays into municipal rain pipe, rainwater will not be caused to return excessive phenomenon.But when municipal Storm Sewer Network In the case of 32 be full of, the pressure in the pressure ratio municipal administration Storm Sewer Network for the pressurization rainwater for spraying into municipal Storm Sewer Network 32 is high Numerical value not should be greater than buried depth at the top of pipe network, otherwise may result in rainwater return it is excessive.So piston rainwater extrudes cavity and pressurization rainwater Entrance is respectively equipped with the 3rd hydraulic pressure sensor 43, and pressure signal is fed back to controller 4, and municipal rain pipe is discharged into pressurization Under the operating mode in road, controller 4 is controlled the second electric control valve 31 according to default program.
Second electric control valve 31 can according to the hydraulic pressure value of PHC pile piles lower part adjust into PHC pile piles rainwater pressure and Flow, avoids rainwater superpressure from being ejected in pile crown from pile crown and forms cavity, influence pile crown bearing capacity.Under recharge state, piston rainwater Extrude the survey of the 3rd hydraulic pressure sensor 43 in cavity and the first hydraulic pressure sensor 35 in PHC pile pile lower rain recharge cavitys Water pressure feed back to controller 4, and then controller 4 controls the dynamic of the second electric control valve 24 and the first electric control valve 31 Work and aperture so that pressurization recharge pressure is in the reasonable scope.

Claims (10)

1. for sponge city potential energy pressurization rainwater row storage system, including raintank, waste water tank, the first overflow pipe, second overflow Flow tube, municipal sewage pipe network, municipal Storm Sewer Network and filter, it is characterised in that:It is additionally provided with the first motor-driven valve, second electronic Valve, the 3rd motor-driven valve, first check-valve, second check-valve, the 4th motor-driven valve, the 5th motor-driven valve, the 6th motor-driven valve, the 3rd non-return It is valve, the 7th motor-driven valve, the 4th check-valves, the 8th motor-driven valve, the 9th motor-driven valve, the 5th check-valves, the 6th check-valves, the tenth electronic Valve, the first electric control valve, first piston formula water tank, second piston formula water tank, the 8th check-valves, the 9th check-valves and control Device processed;
One end of first motor-driven valve is connected with the pipeline that same outdoor ground discharge outlet is connected, and the other end passes through pipeline and One check-valves is connected, and the first check-valve is connected by pipeline with the right end of second piston formula water tank;Described second The right end of piston type water tank is connected by pipeline second check-valve, and the second check-valve passes through pipeline and the second motor-driven valve It is connected, the pipeline that second motor-driven valve is respectively equipped with the 3rd check-valves by pipeline with both ends is connected, one of them Three check-valves are connected by pipeline with municipal Storm Sewer Network, another the 3rd check-valves is connected by pipeline with the 9th motor-driven valve Connect, the 9th motor-driven valve is connected, by pipeline and same raintank by pipeline with second piston formula water tank left end respectively The first connected overflow pipe is connected;
One end of 8th motor-driven valve is connected with the pipeline that same outdoor ground discharge outlet is connected, and the other end passes through pipeline and Two piston type water tank left ends are connected;
First piston plate is equipped with the first piston formula water tank, the second piston formula water tank is equipped with second piston plate, The first piston plate is connected by connecting rod with second piston plate, and the right end top of the second piston formula water tank is equipped with liquid Bit detector;
One end of 4th motor-driven valve is connected by pipeline with the 6th check-valves, by pipeline and the 7th motor-driven valve phase respectively Connection, the 6th check-valves are connected by pipeline with raintank, and the 7th motor-driven valve passes through pipeline and the 5th check-valves It is connected, the 5th check-valves is connected by pipeline with the right end of first piston formula water tank, the 4th motor-driven valve The other end is connected by pipeline with the 4th check-valves, and the 4th check-valves is by managing the left side with first piston formula water tank End is connected;
One end of 3rd motor-driven valve is connected by pipeline with waste water tank, and the other end passes through pipeline and the tenth motor-driven valve respectively It is connected, is connected by pipeline with the first electric control valve, the tenth motor-driven valve passes through pipeline and the 8th check-valves respectively It is connected, is connected by pipeline with municipal sewage pipe network, first electric control valve passes through pipeline and the 9th check-valves phase Connection, the 9th check-valves are connected by pipeline with the left end of first piston formula water tank, the 8th check-valves difference It is connected by pipeline with the 5th motor-driven valve, is connected by pipeline with the 6th motor-driven valve, the 5th motor-driven valve passes through pipeline It is connected with the left end of first piston formula water tank, the 6th motor-driven valve passes through pipeline and the right end of first piston formula water tank It is connected;
The upper end of the waste water tank is connected with filter by pipeline, is connected by pipeline with the second overflow pipe respectively, institute The second overflow pipe is stated by pipeline with municipal sewage pipe network to be connected.
2. potential energy pressurization rainwater row's storage system according to claim 1 for sponge city, it is characterised in that:It is additionally provided with Second electric control valve, the 7th check-valves, closed water fender and PHC, one end of second electric control valve pass through pipeline Pipeline between second check-valve and the second motor-driven valve is connected, the other end of second electric control valve by pipeline with The 7th check-valves in PHC is connected, and the closed water fender is installed in PHC, below the 7th check-valves, Pile top PHC described is equipped with permeability hole, and the first hydraulic pressure sensor is equipped with pile top PHC described.
3. potential energy pressurization rainwater row's storage system according to claim 1 or 2 for sponge city, it is characterised in that:Institute State in municipal Storm Sewer Network and be equipped with liquid level sensor and the second hydraulic pressure sensor.
4. potential energy pressurization rainwater row's storage system according to claim 1 or 2 for sponge city, it is characterised in that:Institute The right end for stating second piston formula water tank is equipped with the 3rd hydraulic pressure sensor.
5. potential energy pressurization rainwater row's storage system according to claim 3 for sponge city, it is characterised in that:Described The right end of two piston type water tanks is equipped with the 3rd hydraulic pressure sensor.
6. potential energy pressurization rainwater row's storage system according to claim 1 or 2 for sponge city, it is characterised in that:Institute The right end top for stating first piston formula water tank is equipped with the first scavenging air valve, and the left upper part of the second piston formula water tank is equipped with Second scavenging air valve.
7. potential energy pressurization rainwater row's storage system according to claim 5 for sponge city, it is characterised in that:Described The right end top of one piston type water tank is equipped with the first scavenging air valve, and the left upper part of the second piston formula water tank is equipped with second Scavenging air valve.
8. potential energy pressurization rainwater row's storage system according to claim 1 or 2 for sponge city, it is characterised in that:Institute State first piston formula water tank, second piston formula water tank is arranged in basement computer room.
9. a kind of potential energy pressurization rainwater row's storage method for sponge city implemented using system described in claim 1, it is special Sign is that detailed process is as follows:
Original state:During non-rainfall, there is no water storage in roof rain water case, first piston plate and second piston plate are close to left wall face, All valves are in closed mode, and waste water tank normally collects the waste water in the high area of building, when the waste water of collection exceedes a certain liquid During position, municipal sewage pipe network is expelled to from the second overflow pipe, or open the 3rd motor-driven valve and the tenth motor-driven valve directly by waste water Discharge municipal sewage pipe network;
Operating mode one:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve and the second motor-driven valve are opened, Rainwater is allowed to enter second piston formula water tank by pipeline, second piston formula water tank gradually fills water, when liquid level detector detects When exceeding a certain setting to water level, controller is sent a signal to, controller controls the 3rd motor-driven valve to open, utilizes high-order waste water The static pressure of case promotes first piston plate and second piston plate to add the rainwater of second piston formula water tank to piston wall low order end Pressure is expelled to municipal Storm Sewer Network;Since raintank have collected rainwater at this time, the 7th motor-driven valve, the storage of first piston formula are opened Sewage in water pot drains into municipal sewage pipe network then using the static pressure of high-order raintank through the 5th motor-driven valve;
Operating mode two:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve and the second motor-driven valve are opened, Rainwater is allowed to enter second piston formula water tank by pipeline, second piston formula water tank gradually fills water, when liquid level detector detects When exceeding a certain setting to water level, controller is sent a signal to, controller controls the 4th motor-driven valve to open, at this time high-order rainwater Case have collected rainwater, and using the static pressure of this part rainwater, first piston plate and second piston plate are pushed to piston Wall low order end, municipal Storm Sewer Network is expelled to by the rainwater pressurization of second piston formula water tank;The 7th motor-driven valve is opened, utilizes rain First piston plate and second piston plate are pushed to piston wall high order end by water tank static pressure, the rainwater in first piston formula water tank Discharge, or directly open the 5th motor-driven valve and the rainwater in first piston formula water tank is drained into municipal sewage pipe network;
Operating mode three:When rainy day rainfall is larger, and ground rainwater discharge has some setbacks, the first motor-driven valve and the second motor-driven valve are opened, Rainwater is allowed to enter second piston formula water tank by pipeline, second piston formula water tank gradually fills water, when liquid level detector detects When exceeding a certain setting to water level, controller is sent a signal to, controller controls the 8th motor-driven valve to open, and ground rainwater is from the Pipeline enters on the left of two piston type water tanks, second piston plate is pushed directly on to piston wall low order end, by second piston formula water storage The rainwater pressurization of tank is expelled to municipal Storm Sewer Network, so, that is, have collected another part ground rainwater, and utilize ground rain Hydrostatic pressure discharges the rainwater collected;Second of rainwater collected can directly be opened when rainwater discharge pressure is reduced The 9th motor-driven valve aerial drainage is opened to municipal Storm Sewer Network.
10. potential energy pressurization rainwater row's storage method according to claim 9 for sponge city, it is characterised in that the party Method system for use in carrying is additionally provided with the second electric control valve, the 7th check-valves, closed water fender and PHC, second motorized adjustment One end of valve is connected by the pipeline between pipeline and second check-valve and the second motor-driven valve, second electric control valve The other end is connected by pipeline with the 7th check-valves in PHC, and the closed water fender is installed in PHC, position Below the 7th check-valves, pile top PHC described is equipped with permeability hole, and being equipped with the first hydraulic pressure in pile top PHC described passes Sensor;
Correspondingly, the method is equipped with operating mode four:On the basis of operating mode one, operating mode two, operating mode three, remaining method of operation is not Become, only by the unlatching that the opening variation of the second motor-driven valve is the first electric control valve, pressurization rainwater is drained into PHC pile piles, and then Drained into by osmosis in underground.
CN201711319216.4A 2017-12-12 2017-12-12 Potential energy pressurized rainwater drainage and storage system and method for sponge city Active CN108035423B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711319216.4A CN108035423B (en) 2017-12-12 2017-12-12 Potential energy pressurized rainwater drainage and storage system and method for sponge city

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711319216.4A CN108035423B (en) 2017-12-12 2017-12-12 Potential energy pressurized rainwater drainage and storage system and method for sponge city

Publications (2)

Publication Number Publication Date
CN108035423A true CN108035423A (en) 2018-05-15
CN108035423B CN108035423B (en) 2023-05-09

Family

ID=62102541

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711319216.4A Active CN108035423B (en) 2017-12-12 2017-12-12 Potential energy pressurized rainwater drainage and storage system and method for sponge city

Country Status (1)

Country Link
CN (1) CN108035423B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005224A (en) * 2019-04-22 2019-07-12 马诗涵 A kind of environmental protection and energy-saving building
CN110284549A (en) * 2019-06-24 2019-09-27 顾海明 A kind of greening level ground rainwater-collecting reuse means
CN110409559A (en) * 2019-08-23 2019-11-05 陈奕旭 Outdoor catchment of one kind is discharged cooling system
CN112095738A (en) * 2020-09-15 2020-12-18 张金富 Rainwater recycling system leaks in seepage of environmental protection terrace that permeates water
CN112814073A (en) * 2021-02-24 2021-05-18 深圳市恒和装饰设计工程有限公司 Green building for urban sewage circulation
CN118197744A (en) * 2024-05-17 2024-06-14 福建镕宏科技实业有限公司 Outdoor dry-type transformer for photovoltaic power generation inversion

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071736A (en) * 2010-12-08 2011-05-25 江苏中天环境工程有限公司 Rainwater-controlled sewage discharge device
CN203049695U (en) * 2013-01-25 2013-07-10 王文东 Energy-saving high-rise water supply system for secondary pressurization
JP2014118734A (en) * 2012-12-17 2014-06-30 Kiyohide Ishii High quality rainwater acquisition apparatus
CN106400933A (en) * 2016-12-09 2017-02-15 安徽理工大学 Roof rainwater source regulating device based on sponge city concept and running method
CN106836438A (en) * 2017-02-21 2017-06-13 徐光智 Step for municipal Storm Sewer Network blocks water with water system of regulating and storing
CN106996135A (en) * 2017-04-05 2017-08-01 中铁建设集团有限公司 A kind of intelligent peak rain-water accumulating heat-extraction system and method based on city integrated piping lane
WO2017164596A1 (en) * 2015-06-23 2017-09-28 지성산업개발(주) Eco-friendly filtration water-collection tank and rainwater recirculation system using same

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071736A (en) * 2010-12-08 2011-05-25 江苏中天环境工程有限公司 Rainwater-controlled sewage discharge device
JP2014118734A (en) * 2012-12-17 2014-06-30 Kiyohide Ishii High quality rainwater acquisition apparatus
CN203049695U (en) * 2013-01-25 2013-07-10 王文东 Energy-saving high-rise water supply system for secondary pressurization
WO2017164596A1 (en) * 2015-06-23 2017-09-28 지성산업개발(주) Eco-friendly filtration water-collection tank and rainwater recirculation system using same
CN106400933A (en) * 2016-12-09 2017-02-15 安徽理工大学 Roof rainwater source regulating device based on sponge city concept and running method
CN106836438A (en) * 2017-02-21 2017-06-13 徐光智 Step for municipal Storm Sewer Network blocks water with water system of regulating and storing
CN106996135A (en) * 2017-04-05 2017-08-01 中铁建设集团有限公司 A kind of intelligent peak rain-water accumulating heat-extraction system and method based on city integrated piping lane

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005224A (en) * 2019-04-22 2019-07-12 马诗涵 A kind of environmental protection and energy-saving building
CN110005224B (en) * 2019-04-22 2021-02-19 孝感市工程咨询设计集团有限公司 Environment-friendly energy-saving building
CN110284549A (en) * 2019-06-24 2019-09-27 顾海明 A kind of greening level ground rainwater-collecting reuse means
CN110284549B (en) * 2019-06-24 2021-04-27 中交园林(山东)有限公司 Greenery patches rainwater is collected and is recycled device
CN110409559A (en) * 2019-08-23 2019-11-05 陈奕旭 Outdoor catchment of one kind is discharged cooling system
CN112095738A (en) * 2020-09-15 2020-12-18 张金富 Rainwater recycling system leaks in seepage of environmental protection terrace that permeates water
CN112814073A (en) * 2021-02-24 2021-05-18 深圳市恒和装饰设计工程有限公司 Green building for urban sewage circulation
CN112814073B (en) * 2021-02-24 2022-03-29 深圳市恒和装饰设计工程有限公司 Green building for urban sewage circulation
CN118197744A (en) * 2024-05-17 2024-06-14 福建镕宏科技实业有限公司 Outdoor dry-type transformer for photovoltaic power generation inversion
CN118197744B (en) * 2024-05-17 2024-07-30 福建镕宏科技实业有限公司 Outdoor dry-type transformer for photovoltaic power generation inversion

Also Published As

Publication number Publication date
CN108035423B (en) 2023-05-09

Similar Documents

Publication Publication Date Title
CN108035423A (en) Potential energy pressurized rainwater drainage and storage system and method for sponge city
CN100469980C (en) Water taking gallery of self flow type for underground reservoir
CN107542107A (en) The dome type piping lane built using the pavement underground space
CN106759646A (en) A kind of sponge urban pavement rain water collecting system and installation method
CN104499560B (en) Combined rainwater seepage well and construction method
CN201089953Y (en) System for collection and comprehensive utilization of city rainwater
CN207749602U (en) Rainwater seepage well for greenbelts and sidewalks in building community
CN102733448A (en) Small buried multifunctional rainwater collecting and utilizing device
CN203361233U (en) Solar greenhouse surface rainwater collection, filtration and storage facility
CN114557262A (en) Ecological slope construction system based on sponge idea
CN206346221U (en) The left and right combined type piping lane built using the pavement underground space
CN207863099U (en) A kind of potential energy pressurization rainwater for sponge city arranges storage system
CN113356250A (en) Horizontal pressurization long well drainage method for large-diameter dewatering drainage non-dry stratum
CN211172270U (en) Forebay rainwater garden system for large roof
CN210797594U (en) Ecological reinforced structure of side slope
CN110080216B (en) Water storage system utilizing supporting tubular piles and construction method thereof
CN113756349B (en) Foundation pit drainage structure and construction method thereof
CN109356224A (en) A kind of skyscraper rainwater-collecting self-loopa utilizes system
CN204311551U (en) Combined rainwater seepage well
CN213448420U (en) Side slope drainage structure
CN209620125U (en) A kind of underground structure blind drainage system
CN208594095U (en) A kind of wetland structure combined using wetland technology and rainwater storage
CN207176874U (en) A kind of pavement comprehensive pipe network and drainage system
CN220908652U (en) Rainwater garden structure of transportation junction
CN203188255U (en) Pressure relief structure of basement anti-floating board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 100144 Shijingshan Road, Shijingshan District, Shijingshan District, Beijing

Applicant after: CHINA RAILWAY CONSTRUCTION GROUP Co.,Ltd.

Applicant after: NORTH CHINA University OF TECHNOLOGY

Applicant after: CHINA RAILWAY CONSTRUCTION GROUP BEIJING ENGINEERING Co.,Ltd.

Address before: 100144 Beijing City, Shijingshan District Jin Yuan Zhuang Road No. 5

Applicant before: NORTH CHINA University OF TECHNOLOGY

Applicant before: CHINA RAILWAY CONSTRUCTION GROUP BEIJING ENGINEERING Co.,Ltd.

Applicant before: CHINA RAILWAY CONSTRUCTION GROUP Co.,Ltd.

CB02 Change of applicant information
CB03 Change of inventor or designer information

Inventor after: Wang Kuan

Inventor after: Song Yingfang

Inventor after: Yu Wenhong

Inventor after: Yan Hui

Inventor after: Zhang Xiangdong

Inventor after: Wang Yonghua

Inventor after: Liu Zheng

Inventor after: Shi Liyan

Inventor after: Gong Ziyang

Inventor after: Song Lin

Inventor before: Yu Wenhong

Inventor before: Song Yingfang

Inventor before: Wang Kuan

Inventor before: Yan Hui

Inventor before: Zhang Xiangdong

Inventor before: Wang Yonghua

Inventor before: Liu Zheng

Inventor before: Shi Liyan

Inventor before: Gong Ziyang

Inventor before: Song Lin

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant