CN213389723U - Cable tower crossbeam construction bracket pre-compaction structure - Google Patents
Cable tower crossbeam construction bracket pre-compaction structure Download PDFInfo
- Publication number
- CN213389723U CN213389723U CN202021289804.5U CN202021289804U CN213389723U CN 213389723 U CN213389723 U CN 213389723U CN 202021289804 U CN202021289804 U CN 202021289804U CN 213389723 U CN213389723 U CN 213389723U
- Authority
- CN
- China
- Prior art keywords
- bracket
- reaction frame
- triangular
- compaction
- jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model relates to a cable tower crossbeam construction bracket pre-compaction structure installs 2 at least truss-like triangular brackets side by side on the relative lateral wall of two cable towers respectively, and a reaction frame is installed respectively to every triangular bracket top take the altitude to be located, the reaction frame is a reverse triangle bracket of installing, and every triangular bracket top surface is equipped with the jack, and the piston end top of jack is in the bottom surface of reaction frame. The utility model has the advantages that the high-altitude hoisting and the preloading material are not needed, the efficiency is high, and the risk is low; the reaction frame adopts the bracket of reverse installation, and after the pre-compaction was accomplished, the reaction frame pulled down can continue to use as the bracket, need not additionally provide pre-compaction material and equipment, can reduce construction cost.
Description
Technical Field
The utility model belongs to bridge construction field relates to a structure that carries out the pre-compaction to suspension bridge or cable-stay bridge's pylon crossbeam construction bracket.
Background
Because the cable tower of the suspension bridge or the cable-stayed bridge is high, a triangular bracket is usually adopted during the construction of a cross beam between towers. In order to ensure the construction safety, the bracket needs to be pre-pressed before the concrete pouring of the cross beam, so that the inelastic deformation of each component of the bracket is eliminated, and the deformation of the bracket caused by the increase of the load during the concrete pouring is prevented. The method is complex in process, long in time consumption, high in material investment, high in cost and low in efficiency, and construction risks can be increased due to the fact that a large amount of overhead hoisting operation is needed.
Disclosure of Invention
The utility model aims at providing a do not need high altitude hoist and mount operation, with low costs, efficient, the strong cable tower crossbeam construction bracket pre-compaction structure of security to the problem that the pre-compaction of current surcharge-load method exists.
The technical scheme of the utility model as follows:
the utility model provides a cable tower crossbeam construction bracket pre-compaction structure installs 2 at least truss-like triangular brackets that parallel on the relative lateral wall of two cable towers respectively, triangular brackets fixes on the pier through pre-buried connecting piece on the pier body, its characterized in that: a reaction frame is respectively arranged at a certain height above each triangular bracket, the reaction frame has the same structure as the triangular bracket and is opposite to the mounting direction, and each reaction frame is also fixed on the pier body through a connecting piece pre-embedded on the pier body; and a jack is arranged on the top surface of each triangular bracket, and the piston end of the jack is propped against the bottom surface of the reaction frame.
The utility model discloses a jack cooperation reaction frame carries out the pre-compaction, does not need high altitude hoist and mount the preloading material, easy operation, and efficient, the load loading is accurate, and the pre-compaction effect is controllable, has reduced the high altitude construction risk; the reaction frame is directly reversely installed by the triangular bracket, after prepressing is finished, the reaction frame can be continuously used as the bracket after being disassembled, prepressing materials and equipment do not need to be additionally provided, and the construction cost can be reduced.
Drawings
Fig. 1 is a schematic front view of the present invention;
fig. 2 is a schematic side view of the present invention.
Detailed Description
As shown in fig. 1 and 2, at least 2 parallel truss type triangular brackets 2 are respectively installed on the opposite side walls of two cable towers 1, and the triangular brackets 2 are fixed on the pier body through connecting pieces 3 pre-embedded on the pier body; a reaction frame 4 is respectively arranged at a certain height above each triangular bracket 2, the reaction frame 4 has the same structure as the triangular bracket, the installation direction on the pier body is opposite, and the reaction frame is a triangular bracket which is reversely installed; each reaction frame is also fixed on the pier body through a connecting piece pre-embedded on the pier body; a jack 5 is arranged on the top surface of each triangular bracket, and the piston end of the jack 5 is propped against the bottom surface of the reaction frame 4.
The utility model discloses during the implementation, when pier shaft concrete placement, at the pre-buried connecting piece of the predetermined mounted position of bracket and reaction frame. The triangular brackets are fixed on the pier body through the pier body embedded connecting pieces, and a triangular bracket is reversely installed above each triangular bracket through the embedded connecting pieces to serve as a reaction frame. During the bracket pre-compaction, place the jack on the bracket, start the jack and upwards push away the reaction frame, carry out the pre-compaction to the bracket through the counter-force that the reaction frame provided. And controlling the pre-pressure through the reading of the jack until the set pre-pressure load is reached. After the prepressing is finished, the reaction frame is detached and can be used as a bracket for continuous use.
Claims (1)
1. The utility model provides a cable tower crossbeam construction bracket pre-compaction structure installs 2 at least truss-like triangular brackets that parallel on the relative lateral wall of two cable towers respectively, triangular brackets fixes on the pier through pre-buried connecting piece on the pier body, its characterized in that: a reaction frame is respectively arranged at a certain height above each triangular bracket, the reaction frame has the same structure as the triangular bracket and is opposite to the mounting direction, and each reaction frame is also fixed on the pier body through a connecting piece pre-embedded on the pier body; and a jack is arranged on the top surface of each triangular bracket, and the piston end of the jack is propped against the bottom surface of the reaction frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021289804.5U CN213389723U (en) | 2020-07-02 | 2020-07-02 | Cable tower crossbeam construction bracket pre-compaction structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021289804.5U CN213389723U (en) | 2020-07-02 | 2020-07-02 | Cable tower crossbeam construction bracket pre-compaction structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213389723U true CN213389723U (en) | 2021-06-08 |
Family
ID=76199340
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021289804.5U Active CN213389723U (en) | 2020-07-02 | 2020-07-02 | Cable tower crossbeam construction bracket pre-compaction structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213389723U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114855639A (en) * | 2022-06-15 | 2022-08-05 | 保利长大工程有限公司 | High altitude cable tower crossbeam construction bracket pre-compaction subassembly |
-
2020
- 2020-07-02 CN CN202021289804.5U patent/CN213389723U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114855639A (en) * | 2022-06-15 | 2022-08-05 | 保利长大工程有限公司 | High altitude cable tower crossbeam construction bracket pre-compaction subassembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201065511Y (en) | Mobile die carrier bridge fabrication machine for thin wall high frusta | |
CN208815424U (en) | A kind of bridge descending hanging basket | |
CN207986489U (en) | Hang regulating device in large diameter pile foundation steel reinforcement cage aperture | |
CN209397501U (en) | Erection crane | |
CN201553992U (en) | Device for jacking whole body of box girder | |
CN213389723U (en) | Cable tower crossbeam construction bracket pre-compaction structure | |
CN205314542U (en) | Construction liquid die plate device that climbs | |
CN202559302U (en) | Concrete lining finishing machine for ditch slope | |
CN203129025U (en) | Suspension fixing device for hanging basket | |
CN201330377Y (en) | Suspension rope towing device | |
CN205802733U (en) | Machine-roomless lift puts machine beam mounting structure | |
CN101186273A (en) | Method for lowering overweight structure by connecting two jacks in series | |
CN203890904U (en) | Assembly construction platform equipment for steel pipe sheets of large-diameter corrugated steel pipe culvert | |
CN201121427Y (en) | Simple lifting type parking equipment | |
CN2766039Y (en) | Light culvert template trolley | |
CN201334318Y (en) | Hoisting gear for tower crane | |
CN201202236Y (en) | Mounting mechanism for portal type overhead pressure plate | |
CN107487724A (en) | A kind of the large-scale floating crane arm support erecting device and installation method of non-loop wheel machine auxiliary | |
CN209686242U (en) | A kind of suspension cable Bridge High-pier steel mould base dismounting device | |
CN206232270U (en) | A kind of elevator top side beam structure | |
CN202766210U (en) | Cable cover plate lifting device | |
CN207244453U (en) | A kind of suspension bridge light anchorage mast apparatus | |
CN202011709U (en) | Installation work platform for wind turbine generator set | |
CN211945963U (en) | Vehicle-mounted dismounting device | |
CN206033090U (en) | Crowd's hoist device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |