CN206232270U CN201621180365.8U CN201621180365U CN206232270U CN 206232270 U CN206232270 U CN 206232270U CN 201621180365 U CN201621180365 U CN 201621180365U CN 206232270 U CN206232270 U CN 206232270U
Authority
CN
China
Prior art keywords
side beam
sheave
beam structure
elevator
curb girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621180365.8U
Other languages
Chinese (zh)
Inventor
章志成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohm Electromechanical Technology (kunshan) Co Ltd
Original Assignee
Ohm Electromechanical Technology (kunshan) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohm Electromechanical Technology (kunshan) Co Ltd filed Critical Ohm Electromechanical Technology (kunshan) Co Ltd
Priority to CN201621180365.8U priority Critical patent/CN206232270U/en
Application granted granted Critical
Publication of CN206232270U publication Critical patent/CN206232270U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

本实用新型涉及电梯技术领域,尤其涉及一种电梯顶层侧梁结构,包括侧梁本体、槽轮和安装架,所述侧梁本体架设于电梯井道的上端,所述槽轮通过安装架可转动的设于所述侧梁本体的下方。该侧梁结构只需要一根侧梁本体即可实现槽轮的安装,很大程度的节省了井道空间,且槽轮安装在侧梁本体的下方,节省了井道的顶部空间,提高了井道的利用率。

The utility model relates to the technical field of elevators, in particular to a side beam structure on the top floor of an elevator, which comprises a side beam body, a sheave and a mounting frame. is located below the side beam body. The side beam structure only needs one side beam body to realize the installation of the sheave, which greatly saves the space of the hoistway, and the sheave is installed under the side beam body, which saves the top space of the hoistway and improves the safety of the hoistway. utilization rate.

Description

一种电梯顶层侧梁结构A side beam structure on the top floor of an elevator

技术领域technical field

本实用新型涉及电梯技术领域,尤其涉及一种电梯顶层侧梁结构。The utility model relates to the technical field of elevators, in particular to a side beam structure on the top floor of an elevator.

背景技术Background technique

电梯包括轿厢和井道,轿厢设于井道内,通过井道内的侧梁结构实现在井道内的上升和下降。The elevator includes a car and a hoistway. The car is arranged in the hoistway, and the rise and fall in the hoistway are realized through the side beam structure in the hoistway.

如图1所示,现有的侧梁结构一般包括侧梁本体1和槽轮2,侧梁本体1的数量为两根,两根侧梁本体1平行且间隔的架设于井道4内,槽轮2通过穿过槽轮轴心的连接杆架设于连根侧梁本体1之间,连接杆的两端通过U形螺栓3固定在侧梁本体1上,电梯钢丝绳绕过槽轮2与电梯的轿厢相连实现轿厢在井道4内的上升和下降。但是由于该侧梁结构需要两根侧梁本体才能实现槽轮的固定安装,两根侧梁本体间隔设置,会占用有限的井道空间,且这种侧梁结构在安装时,需要先安装侧梁本体,然后再利用U形螺栓将槽轮安装在侧梁本体之间,由于井道的空间有限,在安装时也会造成不方便。As shown in Figure 1, the existing side beam structure generally includes a side beam body 1 and a sheave 2, the number of side beam bodies 1 is two, and the two side beam bodies 1 are erected in the hoistway 4 in parallel and at intervals, and the grooves The wheel 2 is erected between the root side beam body 1 through the connecting rod passing through the axis of the sheave, and the two ends of the connecting rod are fixed on the side beam body 1 through U-shaped bolts 3, and the elevator wire rope goes around the sheave 2 and the elevator. The car is connected to realize the rising and falling of the car in the hoistway 4. However, since this side beam structure requires two side beam bodies to realize the fixed installation of the sheave, the two side beam bodies are arranged at intervals, which will occupy limited hoistway space, and when this side beam structure is installed, the side beam needs to be installed first Body, and then use U-shaped bolts to install the sheave between the side beam bodies, because the space of the hoistway is limited, it will also cause inconvenience during installation.

实用新型内容Utility model content

(一)要解决的技术问题(1) Technical problems to be solved

本实用新型要解决的技术问题是解决现有的电梯顶层侧梁结构占用较多的井道空间和安装不便的问题。The technical problem to be solved by the utility model is to solve the problems that the existing side beam structure on the top floor of the elevator occupies more hoistway space and is inconvenient to install.

(二)技术方案(2) Technical solution

为了解决上述技术问题,本实用新型提供了一种电梯顶层侧梁结构,包括侧梁本体、槽轮和安装架,所述侧梁本体架设于电梯井道的上端,所述槽轮通过安装架可转动的设于所述侧梁本体的下方。In order to solve the above technical problems, the utility model provides a side beam structure on the top floor of an elevator, which includes a side beam body, a sheave and a mounting frame. The rotating one is arranged under the side beam body.

其中,所述槽轮的数量为多个,多个所述槽轮沿所述侧梁本体的长度方向间隔设置。Wherein, there are multiple sheaves, and the sheaves are arranged at intervals along the length direction of the side beam body.

其中,所述安装架的数量与所述槽轮的数量相等且一一对应设置。Wherein, the number of the mounting brackets is equal to the number of the sheaves and they are set in one-to-one correspondence.

其中,所述安装架包括侧板,所述侧板的数量为两块,两块所述侧板相对的设于侧梁本体的两侧,所述槽轮设于所述两块所述侧板之间。Wherein, the mounting frame includes side plates, the number of the side plates is two, and the two side plates are oppositely arranged on both sides of the side beam body, and the groove wheels are arranged on the two sides between the boards.

其中,还包括连接杆,所述连接杆垂直于所述侧板设于两块所述侧板体之间,所述槽轮可转动的套设于所述连接杆上。Wherein, a connecting rod is also included, and the connecting rod is arranged between the two side boards perpendicular to the side boards, and the sheave is rotatably sleeved on the connecting rod.

其中,所述安装架还包括顶板,所述顶板设于所述侧梁本体的上方与所述侧梁本体的上表面贴合,且所述顶板的两端分别与两块所述侧板的上端连接。Wherein, the installation frame also includes a top plate, the top plate is arranged above the side beam body and fits on the upper surface of the side beam body, and the two ends of the top plate are respectively connected to the two side plates. upper connection.

其中,所述侧梁本体由工字钢制成。Wherein, the side beam body is made of I-beam.

其中,所述安装架通过卡合或焊接的方式与所述侧梁本体连接。Wherein, the mounting bracket is connected to the side beam body by snap-fitting or welding.

(三)有益效果(3) Beneficial effects

本实用新型的上述技术方案具有如下优点:本实用新型提供的一种电梯顶层侧梁结构,包括侧梁本体、槽轮和安装架,所述侧梁本体架设于电梯井道的上端,所述槽轮通过安装架可转动的设于所述侧梁本体的下方。该侧梁结构只需要一根侧梁本体即可实现槽轮的安装,很大程度的节省了井道空间,且槽轮安装在侧梁本体的下方,节省了井道的顶部空间,提高了井道的利用率。The above-mentioned technical solution of the utility model has the following advantages: a side beam structure on the top floor of an elevator provided by the utility model includes a side beam body, a sheave and a mounting frame, the side beam body is erected on the upper end of the elevator shaft, and the groove The wheels are rotatably arranged below the side beam body through the mounting frame. The side beam structure only needs one side beam body to realize the installation of the sheave, which greatly saves the space of the hoistway, and the sheave is installed under the side beam body, which saves the top space of the hoistway and improves the safety of the hoistway. utilization rate.

除了上面所描述的本实用新型解决的技术问题、构成的技术方案的技术特征以及有这些技术方案的技术特征所带来的优点之外,本实用新型的其他技术特征及这些技术特征带来的优点,将结合附图作出进一步说明。In addition to the technical problems solved by the utility model described above, the technical features of the technical solutions formed and the advantages brought by the technical features of these technical solutions, other technical features of the utility model and the advantages brought by these technical features The advantages will be further explained in conjunction with the accompanying drawings.

附图说明Description of drawings

图1是现有技术中电梯顶层侧梁结构的结构示意图;Fig. 1 is the structural representation of the side beam structure on the top floor of the elevator in the prior art;

图2是本实用新型实施例提供的电梯顶层侧梁结构的结构示意图。Fig. 2 is a schematic structural view of the side beam structure on the top floor of the elevator provided by the embodiment of the present invention.

图中:1:侧梁本体;2:槽轮;3:U形螺栓;4:井道;5:侧梁本体;6:安装架;7:槽轮;8:连接杆;9:井道;601:侧板;602:顶板。In the figure: 1: side beam body; 2: sheave; 3: U-shaped bolt; 4: hoistway; 5: side beam body; 6: installation frame; 7: sheave; 8: connecting rod; 9: hoistway; 601 : side panel; 602: top panel.

具体实施方式detailed description

为使本实用新型实施例的目的、技术方案和优点更加清楚,下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本实用新型保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the utility model more clear, the technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the utility model. Obviously, the described The embodiments are some embodiments of the present utility model, but not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

在本实用新型的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本实用新型中的具体含义。In the description of the present utility model, it should be noted that, unless otherwise clearly stipulated and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a flexible connection. Detachable connection, or integral connection; it can be mechanical connection or electrical connection; it can be direct connection or indirect connection through an intermediary, and it can be the internal communication of two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present utility model in specific situations.

此外,在本实用新型的描述中,除非另有说明,“多个”、“多根”、“多组”的含义是两个或两个以上,“若干个”、“若干根”、“若干组”的含义是一个或一个以上。In addition, in the description of the present utility model, unless otherwise specified, the meanings of "multiple", "multiple roots" and "multiple groups" are two or more, "several", "several roots", "several "Several groups" means one or more than one.

如图2所示,本实用新型实施例提供的一种电梯顶层侧梁结构,包括侧梁本体5、槽轮7和安装架6,侧梁本体5架设于电梯井道9的上端,侧梁本体5的两端固定在电梯井道9的壁上,槽轮5通过安装架6可转动的设于侧梁本体5的下方。该侧梁结构只需要一根侧梁本体5即可实现槽轮7的安装,很大程度的节省了井道空间,且槽轮7安装在侧梁本体5的下方,节省了井道的顶部空间,提高了井道9的利用率。As shown in Figure 2, a side beam structure on the top floor of the elevator provided by the embodiment of the utility model includes a side beam body 5, a sheave 7 and a mounting frame 6, the side beam body 5 is erected on the upper end of the elevator shaft 9, and the side beam body The two ends of 5 are fixed on the wall of the elevator shaft 9, and the sheave 5 is rotatably arranged below the side beam body 5 through the mounting bracket 6. The side beam structure only needs one side beam body 5 to realize the installation of the sheave 7, which greatly saves the hoistway space, and the sheave 7 is installed under the side beam body 5, saving the top space of the hoistway. The utilization rate of shaft 9 has been improved.

进一步地,槽轮7的数量为多个,多个槽轮7沿侧梁本体5的长度方向间隔设置,安装架6的数量与槽轮7的数量相等且一一对应设置。在本实施例中,槽轮7的数量为两个,钢丝绳绕过两个槽轮7后与轿厢相连,实现轿厢的上升和下降。Further, there are multiple sheaves 7 , and the sheaves 7 are arranged at intervals along the length direction of the side beam body 5 , and the number of mounting brackets 6 is equal to the number of sheaves 7 and arranged in one-to-one correspondence. In this embodiment, there are two sheaves 7, and the wire rope is connected to the car after passing around the two sheaves 7, so as to realize the raising and lowering of the car.

进一步地,安装架6包括侧板601,侧板601的数量为两块,两块侧板601相对的设于侧梁本体5的两侧,槽轮7设于两块侧板601之间。具体地,侧板601竖直设置,槽轮7可转动的设于两块侧板601之间。Further, the installation frame 6 includes two side plates 601 , the two side plates 601 are arranged on opposite sides of the side beam body 5 , and the sheave 7 is arranged between the two side plates 601 . Specifically, the side plates 601 are arranged vertically, and the sheave 7 is rotatably arranged between the two side plates 601 .

进一步地,还包括连接杆8,连接杆8垂直于侧板601设于两块侧板体601之间,槽轮7可转动的套设于连接杆8上。连接杆8穿过槽轮的中心,且连接杆8的两端分别与两块侧板601固定连接。Further, a connecting rod 8 is also included, the connecting rod 8 is arranged between two side board bodies 601 perpendicular to the side board 601 , and the sheave 7 is rotatably sleeved on the connecting rod 8 . The connecting rod 8 passes through the center of the sheave, and the two ends of the connecting rod 8 are respectively fixedly connected to the two side plates 601 .

进一步地,安装架6还包括顶板602,顶板602设于侧梁本体5的上方与侧梁本体5的上表面贴合,且顶板602的两端分别与两块侧板602的上端连接。顶板602与两块侧板601共同形成一个冂字形结构,该冂字形结构的安装架6卡合在侧梁本体5上,或通过焊接的方式与侧梁本体5连接。Further, the installation frame 6 also includes a top plate 602, which is arranged above the side beam body 5 and attached to the upper surface of the side beam body 5, and the two ends of the top plate 602 are respectively connected to the upper ends of the two side plates 602. The top plate 602 and the two side plates 601 together form a Z-shaped structure, and the mounting frame 6 of the Z-shaped structure is engaged with the side beam body 5 or connected with the side beam body 5 by welding.

进一步地,侧梁本体5由工字钢制成。工字钢的强度较大,能承受大重量轿厢。Further, the side beam body 5 is made of I-beam. The I-beam has high strength and can bear the heavy weight of the car.

使用时,先将安装架6、槽轮7与侧梁本体5安装完成安装,再将完成安装后的侧梁结构吊装到井道的上端进行安装,该侧梁结构适用于3000kg以下4:1无机房电梯,能减小井道宽度200mm左右,降低了建筑成本。When in use, first install the installation frame 6, the sheave 7 and the side beam body 5 to complete the installation, and then hoist the installed side beam structure to the upper end of the hoistway for installation. The elevator in the machine room can reduce the width of the shaft by about 200mm, reducing the construction cost.

综上所述,本实用新型实施例提供的一种电梯顶层侧梁结构,包括侧梁本体、槽轮和安装架,槽轮通过安装架安装于侧梁本体的下方,该侧梁结构只需要一根侧梁本体即可实现槽轮的安装固定,很大程度的节省了井道空间,且槽轮安装在侧梁本体的下方,节省了井道的顶部空间,提高了井道的利用率。另外在进行安装时,可以先完成侧梁结构的安装再将侧梁结构安装到井道的上端,便于安装时操作。To sum up, the side beam structure on the top floor of the elevator provided by the embodiment of the utility model includes a side beam body, a sheave and a mounting frame. The sheave is installed under the side beam body through the mounting frame. The side beam structure only needs One side beam body can realize the installation and fixing of the sheave, which greatly saves the space of the hoistway, and the sheave is installed under the side beam body, which saves the top space of the hoistway and improves the utilization rate of the hoistway. In addition, during installation, the installation of the side beam structure can be completed first, and then the side beam structure can be installed on the upper end of the hoistway, which is convenient for operation during installation.

最后应说明的是:以上实施例仅用以说明本实用新型的技术方案,而非对其限制;尽管参照前述实施例对本实用新型进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本实用新型各实施例技术方案的精神和范围。Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present utility model, and are not intended to limit it; although the utility model has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: It is still possible to modify the technical solutions recorded in the foregoing embodiments, or perform equivalent replacements for some of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit of the technical solutions of the various embodiments of the present invention. and range.

Claims (8)

1. a kind of elevator top side beam structure, it is characterised in that:Including curb girder body, sheave and mounting bracket, the curb girder body The upper end of elevator hoistways is set up in, the sheave is by mounting bracket rotatably located at the lower section of the curb girder body.
2. elevator top side beam structure according to claim 1, it is characterised in that:The quantity of the sheave is multiple, many The individual sheave along the curb girder body length direction interval setting.
3. elevator top side beam structure according to claim 2, it is characterised in that:The quantity of the mounting bracket and the groove The quantity of wheel is equal and corresponds setting.
4. the elevator top side beam structure according to claim any one of 1-3, it is characterised in that:The mounting bracket includes side Plate, the quantity of the side plate is two pieces, the relative both sides located at curb girder body of two blocks of side plates, and the sheave is located at described Between two blocks of side plates.
5. elevator top side beam structure according to claim 4, it is characterised in that:Also include connecting rod, the connecting rod Perpendicular to the side plate between two pieces of side plate bodies, the sheave is rotatably sheathed in the connecting rod.
6. elevator top side beam structure according to claim 4, it is characterised in that:The mounting bracket also includes top board, institute Top board is stated to be fitted with the upper surface of the curb girder body located at the top of the curb girder body, and the top board two ends respectively with Two pieces of upper end connections of the side plate.
7. the elevator top side beam structure according to claim any one of 1-3, it is characterised in that:The curb girder body is by work Word steel is made.
8. the elevator top side beam structure according to claim any one of 1-3, it is characterised in that:The mounting bracket is by card Close or the mode of welding is connected with the curb girder body.
CN201621180365.8U 2016-10-27 2016-10-27 A kind of elevator top side beam structure Expired - Fee Related CN206232270U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621180365.8U CN206232270U (en) 2016-10-27 2016-10-27 A kind of elevator top side beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621180365.8U CN206232270U (en) 2016-10-27 2016-10-27 A kind of elevator top side beam structure

Publications (1)

Publication Number Publication Date
CN206232270U true CN206232270U (en) 2017-06-09

Family

ID=58983081

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621180365.8U Expired - Fee Related CN206232270U (en) 2016-10-27 2016-10-27 A kind of elevator top side beam structure

Country Status (1)

Country Link
CN (1) CN206232270U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114212651A (en) * 2021-12-17 2022-03-22 中国建筑第八工程局有限公司 Rear-mounted structure of elevator hook in completed project

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114212651A (en) * 2021-12-17 2022-03-22 中国建筑第八工程局有限公司 Rear-mounted structure of elevator hook in completed project

Similar Documents

Publication Publication Date Title
CN206580442U (en) A kind of hanging apparatus suitable for Assembled Building gangboard prefabricated components
WO2017020539A1 (en) Tower crane with a traveling mechanism
CN109733974B (en) Elevator capable of reducing roof construction quantity
CN116062626A (en) A super high-rise building tower crown part curtain wall hoisting equipment and hoisting method
CN203889843U (en) Connection structure of traction machine of machine-room-less home elevator
CN105016218A (en) Guide rail mechanism fixed to building
CN204980946U (en) Take running gear's tower crane
CN206232270U (en) A kind of elevator top side beam structure
CN104773633A (en) Corner door type home elevator
CN217498457U (en) Single-side double-lifting-point balance lifting beam for hoisting prefabricated plate
CN106429869A (en) Horizontal heavy equipment aerial mounting device and mounting method
CN104355206B (en) A kind of 10 tons of ladders
CN207792434U (en) Machine room right-angled door-opened elevator traction driving device
CN205855727U (en) A kind of machine-roomless lift
CN105236249A (en) Elevator without machine room
CN102408052A (en) Counter-weight-free traction type passenger elevator
CN202465100U (en) Single-beam gantry crane with double V-shaped supporting legs
CN201756422U (en) Two-head-suspension tower crane
CN208980118U (en) A machine room-less elevator rope head fixing device
CN215828103U (en) Host installation structure of elevator without machine room
CN204847680U (en) No computer lab elevator arrangement structure
CN204938801U (en) The tower crane that is connected can be realized with building
CN201850027U (en) Traction passenger elevator without counter weight
CN205099168U (en) Elevator without engine room
CN211393460U (en) Elevator traction system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170609