CN207244453U - A kind of suspension bridge light anchorage mast apparatus - Google Patents
A kind of suspension bridge light anchorage mast apparatus Download PDFInfo
- Publication number
- CN207244453U CN207244453U CN201720335805.0U CN201720335805U CN207244453U CN 207244453 U CN207244453 U CN 207244453U CN 201720335805 U CN201720335805 U CN 201720335805U CN 207244453 U CN207244453 U CN 207244453U
- Authority
- CN
- China
- Prior art keywords
- column
- long
- short
- cable saddle
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本实用新型提供一种悬索桥轻型锚碇门架装置,包括散索鞍支墩、两个立面桁架结构和横梁,立面桁架结构下端与散索鞍支墩上的预埋件连接,两个立面桁架结构上端通过横梁连接,横梁两端均设置有工作平台。立面桁架结构包括长立柱、短立柱、短平联和长平联,所述长立柱和短立柱的上端通过长平联连接,短立柱的下端与长立柱之间通过短平联连接,长立柱下端固定在散索鞍支墩上,短立柱下端固定在散索鞍支墩上的锚墙上。本装置结构简单易组装,既能满足现场吊装要求又能方便运输、安装、加工,实现了简化施工安装,具备足够的强度,满足悬索上部结构施工各个阶段的施工需求,为上部施工提供工作平台,与传统锚锭相比节省大量钢材。
The utility model provides a light-duty anchorage gantry device for a suspension bridge, which comprises a loose cable saddle pier, two facade truss structures and a beam. The upper ends of the façade truss structure are connected by beams, and working platforms are provided at both ends of the beams. The façade truss structure includes long columns, short columns, short parallels and long parallels. The lower end of the column is fixed on the pier of the loose cable saddle, and the lower end of the short column is fixed on the anchor wall on the pier of the loose cable saddle. The structure of this device is simple and easy to assemble, which can not only meet the requirements of on-site hoisting, but also facilitate transportation, installation and processing, realize simplified construction and installation, have sufficient strength, meet the construction needs of each stage of suspension superstructure construction, and provide work for superstructure construction The platform saves a lot of steel compared with the traditional anchor ingot.
Description
技术领域technical field
本实用新型属于桥梁施工领域,尤其涉及一种悬索桥轻型锚碇门架装置。The utility model belongs to the field of bridge construction, in particular to a light-type anchorage door frame device for a suspension bridge.
背景技术Background technique
传统悬索桥锚锭门架的功能包括:散索鞍吊装、平移、就位,在猫道牵引系统、猫道门架承重索架设过程中起支撑转向作用,还包括为猫道承重索的线性调整、猫道承重索拆除时提供主要的工作平台。在悬索桥上部结构安装施工各个阶段都能充分发挥门架的作用。在锚锭门架众多功能中,散索鞍的吊装、平移、就位施工操作由于散索鞍吨位较大对门架的结构强度要求较高,传统的锚锭门架设计较复杂,使用钢材较多,若能使用其他工艺将散索鞍起吊安装到位,将可使锚锭门架的结构大大简化,而且简化后的锚锭门架依然可以满足支撑转向作用或提供工作平台。The functions of the traditional suspension bridge anchor gantry include: hoisting, translation and positioning of loose cable saddles, supporting and steering during the catwalk traction system and catwalk gantry load-bearing cable erection process, and also including linear adjustment of catwalk load-bearing cables, Provides the main working platform when the catwalk load-bearing cables are removed. In all stages of installation and construction of the suspension bridge superstructure, the role of the portal frame can be fully utilized. Among the many functions of the anchor gantry, the hoisting, translation, and in-position construction operations of the loose cable saddle have higher requirements on the structural strength of the gantry due to the larger tonnage of the loose cable saddle. The traditional anchor gantry design is more complicated and uses more steel materials. If other techniques can be used to lift and install the loose cable saddle in place, the structure of the anchor gantry can be greatly simplified, and the simplified anchor gantry can still meet the supporting steering function or provide a working platform.
实用新型内容Utility model content
为了克服传统的锚锭门架设计较复杂,使用钢材较多的问题,本实用新型提供一种悬索桥轻型锚碇门架装置,本装置简单易组装、结构设计合理简易、可满足悬索上部结构施工各个阶段的施工需求,为上部施工提供工作平台,与传统锚锭相比可节省大量钢材的轻型锚碇门架装置。In order to overcome the problem that the traditional anchor gantry design is more complex and uses more steel, the utility model provides a light-weight anchor gantry device for suspension bridges. The device is simple and easy to assemble, and the structure design is reasonable and simple, which can meet the construction requirements of the upper structure of the suspension cable. According to the construction needs of each stage, it provides a working platform for the upper construction, and can save a lot of steel compared with the traditional anchor.
本实用新型采用的技术方案为:The technical scheme that the utility model adopts is:
一种悬索桥轻型锚碇门架装置,包括散索鞍支墩、两个立面桁架结构和横梁,所述立面桁架结构下端与散索鞍支墩上的预埋件连接,所述两个立面桁架结构上端通过横梁连接,横梁两端均设置有工作平台。A light-type anchorage gantry device for a suspension bridge, comprising a scatter-cable saddle pier, two façade truss structures and beams, the lower end of the façade truss structure is connected to a pre-embedded part on the scatter-cable saddle pier, and the two The upper ends of the façade truss structure are connected by beams, and working platforms are provided at both ends of the beams.
所述的立面桁架结构包括长立柱、短立柱、短平联和长平联,所述长立柱和短立柱的上端通过长平联连接,横梁固定在长平联上,短立柱的下端与长立柱之间通过短平联连接,所述长立柱下端固定在散索鞍支墩上,所述短立柱下端固定在散索鞍支墩上的锚墙上。Described façade truss structure comprises long column, short column, short flat connection and long flat connection, and the upper end of described long column and short column is connected by long flat connection, and beam is fixed on long flat connection, and the lower end of short column is connected with The long uprights are connected by short parallel connections, the lower end of the long uprights is fixed on the pier of the scatter saddle, and the lower end of the short uprights is fixed on the anchor wall on the pier of the scatter saddle.
所述长立柱与长平联之间设有斜撑,短立柱与长平联也设有斜撑。Diagonal braces are arranged between the long columns and the long flat joints, and diagonal braces are also provided between the short vertical columns and the long flat joints.
所述工作平台下设有牛腿横撑,所述牛腿横撑与横梁连接,且位于同一水平面上。A corbel is arranged under the working platform, and the corbel is connected with the beam and is located on the same horizontal plane.
所述牛腿横撑与短立柱和长立柱之间均设有牛腿支撑。A corbel support is provided between the corbel horizontal brace and the short column and the long column.
所述立面桁架结构与散索鞍支墩上的预埋件通过地脚螺栓连接。The facade truss structure is connected with the embedded parts on the scatter saddle pier through anchor bolts.
所述横梁为四根。There are four beams.
本实用新型的有益效果为:The beneficial effects of the utility model are:
本实用新型采用提供的轻型锚锭门架装置在悬索桥上部结构施工起到重要作用,此门架装置结构简单,易组装,既能满足现场吊装要求。又能方便运输、安装、加工,实现了简化施工安装,结构具备足够的强度,可满足悬索上部结构施工各个阶段的施工需求,为上部施工提供工作平台,与传统锚锭相比可节省大量钢材。The utility model adopts the provided light anchor gantry device to play an important role in the construction of the upper structure of the suspension bridge. The gantry device has a simple structure and is easy to assemble, which can not only meet the requirements of on-site hoisting. It is also convenient for transportation, installation and processing, which simplifies construction and installation. The structure has sufficient strength to meet the construction needs of each stage of suspension superstructure construction and provide a working platform for superstructure construction. Compared with traditional anchors, it can save a lot steel.
以下将结合附图进行进一步的说明。Further description will be made below in conjunction with the accompanying drawings.
附图说明Description of drawings
图1 本实用新型结构立面示意图。Fig. 1 Schematic diagram of the structure elevation of the utility model.
图2 本实用新型结构A-A截面图。Fig. 2 A-A sectional view of the structure of the utility model.
图3 本实用新型结构B-B截面图。Fig. 3 B-B sectional view of the structure of the utility model.
图中:1、长立柱;2、短立柱;3、短平联;4、斜撑;5、预埋件;6、长平联;7、牛腿斜撑;8、工作平台;9、牛腿横撑;10、横梁。In the figure: 1. Long column; 2. Short column; 3. Short flat connection; 4. Diagonal brace; 5. Embedded parts; 6. Long flat connection; 7. Corbel diagonal brace; 8. Working platform; Corbel cross brace; 10, beam.
具体实施方式Detailed ways
实施例1:Example 1:
为了克服传统的锚锭门架设计较复杂,使用钢材较多的问题,本实用新型提供如图1所示的一种悬索桥轻型锚碇门架装置,本装置简单易组装、结构设计合理简易、可满足悬索上部结构施工各个阶段的施工需求,为上部施工提供工作平台,与传统锚锭相比可节省大量钢材的轻型锚碇门架装置。In order to overcome the problem that the traditional anchor gantry design is more complex and uses more steel, the utility model provides a light anchor gantry device for a suspension bridge as shown in Figure 1. The device is simple and easy to assemble, and the structure design is reasonable and simple. It meets the construction needs of each stage of the suspension superstructure construction, provides a working platform for the superstructure construction, and can save a lot of steel compared with the traditional anchor.
一种悬索桥轻型锚碇门架装置,包括散索鞍支墩、两个立面桁架结构和横梁10,所述立面桁架结构下端与散索鞍支墩上的预埋件5连接,所述两个立面桁架结构上端通过横梁10连接,横梁10两端均设置有工作平台8。A light anchorage gantry device for a suspension bridge, comprising a scatter-cable saddle pier, two façade truss structures and a beam 10, the lower end of the façade truss structure is connected to the embedded part 5 on the scatter-cable saddle pier, the The upper ends of the two façade truss structures are connected by crossbeams 10 , and work platforms 8 are provided at both ends of the crossbeams 10 .
本实施例中,立面桁架结构在门架安装前在加工厂焊接完成,在安装门架时整体吊装就位,与散索鞍支墩上的预埋件5连接。立面桁架结构安装完成后,进行横梁10连接,最后进行工作平台8的施工。完成本实用新型悬索桥轻型锚碇门架装置的组装。In this embodiment, the façade truss structure is welded in the processing factory before the gantry is installed, and it is hoisted in place as a whole when the gantry is installed, and connected with the embedded part 5 on the sling saddle pier. After the façade truss structure is installed, the beams 10 are connected, and finally the working platform 8 is constructed. Complete the assembly of the utility model suspension bridge light anchorage gantry device.
此实用新型在悬索桥上部结构施工起到重要作用,此门架装置结构简单,易组装,既能满足现场吊装要求。又能方便运输、安装、加工,实现了简化施工安装,结构具备足够的强度,可满足悬索上部结构施工各个阶段的施工需求,为上部施工提供工作平台,与传统锚锭相比可节省大量钢材。This utility model plays an important role in the construction of the upper structure of the suspension bridge. The portal frame device has a simple structure and is easy to assemble, which can meet the requirements of on-site hoisting. It is also convenient for transportation, installation and processing, which simplifies construction and installation. The structure has sufficient strength to meet the construction needs of each stage of suspension superstructure construction and provide a working platform for superstructure construction. Compared with traditional anchors, it can save a lot steel.
实施例2:Example 2:
基于上述实施例的基础上,本实施例中,所述的立面桁架结构包括长立柱1、短立柱2、短平联3和长平联6,所述长立柱1和短立柱2的上端通过长平联6连接,横梁10固定在长平联6上,短立柱2的下端与长立柱1之间通过短平联3连接,所述长立柱1下端固定在散索鞍支墩上,所述短立柱2下端固定在散索鞍支墩上的锚墙上。Based on the above embodiments, in this embodiment, the facade truss structure includes long columns 1, short columns 2, short parallels 3 and long parallels 6, and the upper ends of the long columns 1 and short columns 2 are Connected by the long flat joint 6, the crossbeam 10 is fixed on the long flat joint 6, the lower end of the short column 2 is connected with the long vertical column 1 by a short flat joint 3, and the lower end of the long vertical column 1 is fixed on the pier of the scatter saddle, The lower end of the short column 2 is fixed on the anchor wall on the scatter saddle pier.
所述长立柱1与长平联6之间设有斜撑4,短立柱2与长平联6也设有斜撑4。A diagonal brace 4 is provided between the long column 1 and the long parallel link 6 , and a diagonal brace 4 is also provided between the short column 2 and the long parallel link 6 .
如图2所示,所述工作平台8下设有牛腿横撑9,所述牛腿横撑9与横梁10连接,且位于同一水平面上。As shown in FIG. 2 , a corbel 9 is arranged under the working platform 8 , and the corbel 9 is connected with the beam 10 and is located on the same horizontal plane.
所述牛腿横撑9与短立柱2和长立柱1之间均设有牛腿支撑7。A corbel support 7 is arranged between the corbel cross brace 9 and the short column 2 and the long column 1 .
所述立面桁架结构与散索鞍支墩上的预埋件5通过地脚螺栓连接。The facade truss structure is connected with the embedded part 5 on the pier of the loose cable saddle through anchor bolts.
如图3所述,本实施例中,所述横梁10为四根。两个立面桁架结构上端通过四根横梁连接,安全可靠。As shown in FIG. 3 , in this embodiment, there are four beams 10 . The upper ends of the two façade truss structures are connected by four beams, which is safe and reliable.
如图1、2所示,一种悬索桥轻型锚碇门架装置,至少包括一与横梁10通过螺栓连接的立面桁架结构,所述的立面桁架结构包括长立柱1、短立柱2、短平联3、长平联6、斜撑4。所述的横梁10与立面桁架结构通过连接板螺栓连接。还包括两侧工作平台8,所述的工作平台8下部由牛腿斜撑7、牛腿横撑9支撑,上部铺设槽钢纵梁、横梁、护栏等。As shown in Figures 1 and 2, a light-duty anchorage gantry device for a suspension bridge at least includes a facade truss structure connected with a beam 10 by bolts, and the facade truss structure includes a long column 1, a short column 2, a short Pinglian 3, Changpinglian 6, Diagonal brace 4. The beam 10 is connected to the façade truss structure through connecting plate bolts. It also includes working platforms 8 on both sides. The lower part of the working platform 8 is supported by corbel diagonal braces 7 and corbel cross braces 9, and the upper part is laid with channel steel longitudinal beams, beams, guardrails, etc.
在主缆架设过程中,在锚锭门架横梁10下方安装2个导向轮,为主缆牵引系统钢丝绳提供支撑转向功能;在猫道门架承重索架设完成后,在锚锭门架上焊接猫道门架承重索转索鞍,为猫道门架承重索提供支撑转向功能;在猫道拆除施工中,在猫道门架横梁上放置8t卷扬机与塔顶卷扬机组成猫道承重索拆除的提升横移系统,并为猫道承重索拆除提供工作平台8。During the erection of the main cable, two guide wheels are installed under the beam 10 of the anchor gantry to provide support and steering function for the wire rope of the main cable traction system; The load-bearing cable-turning saddle of the portal frame provides support and steering function for the load-bearing cable of the catwalk portal frame; during the demolition construction of the catwalk, an 8t winch is placed on the beam of the catwalk portal frame and the hoist on the top of the tower to form a lifting and lateral movement system for the catwalk load-bearing cable removal , and provide a working platform 8 for the removal of catwalk load-bearing cables.
本实用新型采用提供的轻型锚锭门架装置在悬索桥上部结构施工起到重要作用,此门架装置结构简单,易组装,既能满足现场吊装要求。又能方便运输、安装、加工,实现了简化施工安装,结构具备足够的强度,可满足悬索上部结构施工各个阶段的施工需求,为上部施工提供工作平台,与传统锚锭相比可节省大量钢材。The utility model adopts the provided light anchor gantry device to play an important role in the construction of the upper structure of the suspension bridge. The gantry device has a simple structure and is easy to assemble, which can not only meet the requirements of on-site hoisting. It is also convenient for transportation, installation and processing, which simplifies construction and installation. The structure has sufficient strength to meet the construction needs of each stage of suspension superstructure construction and provide a working platform for superstructure construction. Compared with traditional anchors, it can save a lot steel.
以上例举仅仅是对本实用新型的举例说明,并不构成对本实用新型的保护范围的限制,凡是与本实用新型相同或相似的设计均属于本实用新型的保护范围之内。The above examples are only illustrations of the utility model, and do not constitute a limitation to the protection scope of the utility model. All designs identical or similar to the utility model all belong to the protection scope of the utility model.
Claims (1)
- A kind of 1. suspension bridge light anchorage mast apparatus, it is characterised in that:Including dissipate cable saddle buttress, two facade truss structures and Crossbeam(10), the built-in fitting on the facade truss structure lower end and scattered cable saddle buttress(5)Connection, described two facade truss knots Structure upper end passes through crossbeam(10)Connection, crossbeam(10)Both ends are both provided with workbench(8);The facade truss structure includes Long column(1), short column(2), short lateral(3)With long lateral(6), the long column(1)With short column(2)Upper end pass through length Lateral(6)Connection, crossbeam(10)It is fixed on long lateral(6)On, short column(2)Lower end and long column(1)Between by short flat Connection(3)Connection, the long column(1)Lower end is fixed on scattered cable saddle buttress, the short column(2)Lower end is fixed on scattered cable saddle branch On anchor wall on pier;The long column(1)With long lateral(6)Between be equipped with diagonal brace(4), short column(2)With long lateral(6)Also set There is diagonal brace(4);The workbench(8)Have bracket stull(9), the bracket stull(9)With crossbeam(10)Connection, and position In in same level;The bracket stull(9)With short column(2)With long column(1)Between be equipped with corbels support(7);Institute State facade truss structure and the built-in fitting on scattered cable saddle buttress(5)Connected by foundation bolt;The crossbeam(10)For four.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720335805.0U CN207244453U (en) | 2017-03-31 | 2017-03-31 | A kind of suspension bridge light anchorage mast apparatus |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720335805.0U CN207244453U (en) | 2017-03-31 | 2017-03-31 | A kind of suspension bridge light anchorage mast apparatus |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207244453U true CN207244453U (en) | 2018-04-17 |
Family
ID=61876424
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720335805.0U Expired - Fee Related CN207244453U (en) | 2017-03-31 | 2017-03-31 | A kind of suspension bridge light anchorage mast apparatus |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207244453U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110467113A (en) * | 2019-08-28 | 2019-11-19 | 四川路桥桥梁工程有限责任公司 | Large-tonnage tunnel anchorage dissipates cable saddle hanging apparatus and method |
-
2017
- 2017-03-31 CN CN201720335805.0U patent/CN207244453U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110467113A (en) * | 2019-08-28 | 2019-11-19 | 四川路桥桥梁工程有限责任公司 | Large-tonnage tunnel anchorage dissipates cable saddle hanging apparatus and method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101537976B (en) | Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof | |
| CN205772984U (en) | A kind of hanging apparatus of monolithic steel truss | |
| CN201376848Y (en) | Large-scale double-tower automatic-elevation hoisting equipment | |
| CN106592962A (en) | Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus | |
| CN205205685U (en) | Span wire pier is function portal device at most | |
| CN100587206C (en) | Steel column supported integral self-elevating steel platform scaffolding formwork system | |
| CN205294665U (en) | Jack -up tower crane based on engineering mechanics | |
| CN214573768U (en) | A self-climbing slipform pouring system for the second-stage concrete pouring of the door slot | |
| CN206986743U (en) | A kind of fixed trestle navigable vertical lift device | |
| CN212315371U (en) | Cable installation lifting device for cable-stayed bridge | |
| CN203613467U (en) | Steel pipe bracket for construction of arch tower in oblique arch tower double-cable plane pre-stressed concrete cable-stayed bridge | |
| CN201857761U (en) | Hoisting and sliding device and hoisting and sliding equipment | |
| CN209456892U (en) | Cable-stayed bridge steel overhangs structure of sidewalk | |
| CN204455842U (en) | Bridge precast beam plate girder erection frame | |
| CN207244453U (en) | A kind of suspension bridge light anchorage mast apparatus | |
| CN101695984B (en) | The installation method and spreader of longitudinal and transverse beams under the arch of the half-through concrete-filled steel tube concrete arch bridge | |
| CN204151665U (en) | A kind of cable-stayed type opens trestle | |
| CN108086168A (en) | Ride cable-styled erection crane | |
| CN114084814B (en) | Lifting system suitable for small space | |
| CN219031629U (en) | Lifting equipment for indoor plate installation | |
| CN207878284U (en) | Bailey beam cable saddle hoisting bracket | |
| CN107700363B (en) | A bridge tower platform with self-contained lifting system and its construction method | |
| CN204938801U (en) | The tower crane that is connected can be realized with building | |
| CN201128882Y (en) | Lifting and supporting brackets integrated construction device for bridge arch rib | |
| CN117188760A (en) | Upper suspension and lower bearing combined concrete formwork supporting structure and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20250311 Address after: 210000 No. 396 Binjiang Avenue, Jiangbei new area, Nanjing, Jiangsu Patentee after: East China Construction Co., Ltd. of CCCC Second Highway Engineering Co.,Ltd. Country or region after: China Address before: 710119 No.29, No.1 Enterprise Park, West Avenue, high tech Zone, Xi'an City, Shaanxi Province Patentee before: CCCC-SHEC SECOND ENGINEERING Co.,Ltd. Country or region before: China |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180417 |