CN205205685U - Span wire pier is function portal device at most - Google Patents

Span wire pier is function portal device at most Download PDF

Info

Publication number
CN205205685U
CN205205685U CN201521037677.9U CN201521037677U CN205205685U CN 205205685 U CN205205685 U CN 205205685U CN 201521037677 U CN201521037677 U CN 201521037677U CN 205205685 U CN205205685 U CN 205205685U
Authority
CN
China
Prior art keywords
bridge pier
suspension cable
function
crossbeam
door frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201521037677.9U
Other languages
Chinese (zh)
Inventor
李鸿盛
任威
宾熊
郭永兵
徐厚庆
屈加林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN201521037677.9U priority Critical patent/CN205205685U/en
Application granted granted Critical
Publication of CN205205685U publication Critical patent/CN205205685U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型提供了一种悬索桥墩顶多功能门架装置,属于悬索桥施工装置领域,包括现装门架本体,现装门架本体包括支撑桁架系统和工作平台,工作平台与支撑桁架系统的上端连接,支撑桁架系统的下端通过锚固系统锚固于悬索桥墩顶,现装门架本体还包括猫道转索鞍、提升系统以及牵引系统,猫道转索鞍、提升系统以及牵引系统分别与支撑桁架系统连接。该悬索桥墩顶多功能门架装置通过设置现装门架本体,将门架进行分块,在塔顶进行组装,既能满足现场吊装要求,又能方便运输、安装、加工,实现了简化施工安装,能够与塔顶处的猫道转索鞍组合在一起,受力安全,在悬索桥上部结构安装施工各个阶段都能充分发挥门架的作用,真正实现了一架多用。

The utility model provides a multifunctional gantry device at the top of a suspension bridge pier, which belongs to the field of suspension bridge construction devices, and includes an existing gantry body. The existing gantry body includes a supporting truss system and a working platform, and the upper end of the working platform and the supporting truss system Connection, the lower end of the supporting truss system is anchored to the top of the suspension pier through the anchor system. The existing gantry body also includes the catwalk saddle, lifting system and traction system. system connection. The multifunctional gantry device on the top of the suspension bridge pier is equipped with the existing gantry body, the gantry is divided into blocks, and assembled on the top of the tower, which can not only meet the requirements of on-site hoisting, but also facilitate transportation, installation, and processing, and realize simplified construction and installation. , can be combined with the catwalk cable saddle at the top of the tower, which is safe under force, and can give full play to the role of the portal frame at all stages of the installation and construction of the upper structure of the suspension bridge, truly realizing a multi-purpose.

Description

悬索桥墩顶多功能门架装置Multifunctional gantry device on top of suspension bridge pier

技术领域technical field

本实用新型涉及悬索桥施工装置领域,具体而言,涉及一种悬索桥墩顶多功能门架装置。The utility model relates to the field of suspension bridge construction devices, in particular to a multifunctional portal frame device at the top of a suspension bridge pier.

背景技术Background technique

为满足主索鞍提升安装,同时方便施工猫道、牵引系统、索股张拉系统等临时设施,以及紧缆机、缠丝机、缆载吊机等施工设备安装,同时方便后续架设主缆、索夹及吊索、钢箱梁等永久性结构,在塔顶设置门架。常规门架由于整体重量太大不利于吊装安装,需对门架进行简化设计,达到方便吊装、安装、运输等。In order to meet the lifting and installation of the main cable saddle, it is convenient for the construction of catwalks, traction systems, cable strand tensioning systems and other temporary facilities, as well as the installation of construction equipment such as cable tightening machines, wire winding machines, and cable cranes, and at the same time facilitates the subsequent erection of the main cable , cable clips and slings, steel box girders and other permanent structures, and a door frame is set on the top of the tower. Because the overall weight of the conventional door frame is too large, it is not conducive to hoisting and installation. It is necessary to simplify the design of the door frame to facilitate hoisting, installation, and transportation.

实用新型内容Utility model content

本实用新型提供了一种悬索桥墩顶多功能门架装置,旨在改善上述问题。The utility model provides a multifunctional gantry device on the top of a suspension bridge pier, aiming at improving the above problems.

本实用新型是这样实现的:The utility model is achieved in that:

一种悬索桥墩顶多功能门架装置,包括现装门架本体,所述现装门架本体包括支撑桁架系统和工作平台,所述工作平台与所述支撑桁架系统的上端连接,所述支撑桁架系统的下端通过锚固系统锚固于悬索桥墩顶,所述现装门架本体还包括猫道转索鞍、提升系统以及牵引系统,所述猫道转索鞍、所述提升系统以及所述牵引系统分别与所述支撑桁架系统连接。A multifunctional gantry device on the top of a suspension bridge pier, comprising a ready-to-install gantry body, the ready-to-install gantry body including a supporting truss system and a working platform, the working platform is connected to the upper end of the supporting truss system, and the supporting The lower end of the truss system is anchored to the top of the suspension bridge pier through an anchor system. The existing gantry body also includes a catwalk cable saddle, a lifting system and a traction system. The catwalk cable saddle, the lifting system and the traction system The system is respectively connected with the support truss system.

进一步地,所述支撑桁架系统包括两个相对设置的门架桁片结构,两个所述门架桁片结构通过若干门架横梁连接,所述门架桁片结构包括多根主承载立柱、纵梁、若干横撑、若干小斜撑以及悬挑大斜撑,所述主承载立柱通过所述锚固系统锚固于悬索桥墩顶,所述工作平台设置于所述纵梁上,相邻两个所述主承载立柱通过所述横撑和所述小斜撑连接,所述纵梁的一端为悬挑梁,所述悬挑梁与所述主承载立柱通过悬挑大斜撑连接,所述悬挑梁和所述悬挑大斜撑通过所述横撑和所述小斜撑连接。Further, the supporting truss system includes two oppositely arranged gantry truss structures, the two gantry truss structures are connected by several gantry beams, and the gantry truss structures include a plurality of main bearing columns, Longitudinal beams, several cross braces, several small diagonal braces and overhanging large diagonal braces, the main bearing column is anchored to the top of the suspension pier through the anchor system, the working platform is set on the longitudinal beams, two adjacent The main bearing column is connected by the cross brace and the small diagonal brace, one end of the longitudinal beam is a cantilever beam, and the cantilever beam is connected with the main bearing column by a cantilevered large diagonal brace. The cantilever beam and the cantilevered large diagonal brace are connected through the cross brace and the small diagonal brace.

支撑桁架系统包括主承载立柱、纵梁、横撑等构件,为索鞍安装提升、索股架设牵引、钢箱梁吊装设备安装等提供起重和支撑。支撑桁架系统采用门架桁片结构,支撑桁架系统整体结构受力安全,各构件之间采用栓接为主、焊接为辅的连接方式,简化了施工难度,同时方便运输和周转。由标准型材、栓接连接、组拼速度快、安装精度高、现场焊接作业量少。The supporting truss system includes main bearing columns, longitudinal beams, cross braces and other components, which provide lifting and support for the installation and lifting of cable saddles, the erection and traction of cable strands, and the installation of steel box girder hoisting equipment. The supporting truss system adopts the gantry truss structure, and the overall structure of the supporting truss system is safe under force. The connection between each component is mainly bolted and supplemented by welding, which simplifies the difficulty of construction and facilitates transportation and turnover. It is made of standard profiles, bolted connections, fast assembly speed, high installation accuracy, and less on-site welding work.

进一步地,所述门架横梁包括端横梁、柱间横梁、中横梁以及悬臂间横梁,两个所述纵梁的两端分别通过所述端横梁连接,两个所述纵梁在其与所述主承载立柱的连接处通过柱间横梁连接,两个所述纵梁的中部通过中横梁连接,两个所述悬挑梁通过所述悬臂间横梁连接。Further, the gantry beams include end beams, inter-column beams, middle beams and cantilever beams, the two ends of the two longitudinal beams are respectively connected by the end beams, and the two longitudinal beams are connected to the The joints of the main bearing columns are connected by inter-column crossbeams, the middle parts of the two longitudinal beams are connected by middle crossbeams, and the two cantilever beams are connected by the inter-cantilever crossbeams.

通过设置端横梁、柱间横梁、中横梁以及悬臂间横梁,将两个纵梁的多个对应部位连接起来,结构更加稳固,受力更加安全,为悬索桥上部结构安装施工各个阶段充分发挥门架的作用。By setting the end beams, column beams, middle beams and cantilever beams, multiple corresponding parts of the two longitudinal beams are connected, the structure is more stable, the force is safer, and the portal frame is fully utilized for all stages of the installation and construction of the suspension bridge superstructure. role.

进一步地,所述端横梁与所述纵梁之间、所述柱间横梁与所述纵梁之间分别通过顶面斜撑连接。Further, the end beams and the longitudinal beams, and the inter-column beams and the longitudinal beams are respectively connected by top diagonal braces.

通过设置顶面斜撑,加强了端横梁和纵梁、柱间横梁与纵梁之间的连接,进一步提高了支撑桁架系统的整体结构稳定性,加强了支撑的作用,整体受力更加安全。The connection between the end beam and the longitudinal beam, and the inter-column beam and the longitudinal beam is strengthened by setting the top diagonal brace, which further improves the overall structural stability of the supporting truss system, strengthens the supporting function, and makes the overall stress more secure.

进一步地,所述端横梁与远离所述悬挑梁的一端的所述主承载立柱之间通过横桥向斜撑连接。Further, the end beam is connected to the main load-bearing column at the end far away from the cantilever beam through a cross-bridge diagonal brace.

通过设置横桥向斜撑,增强了横桥向的承受能力,使受力更加安全,结构更加牢靠。By setting the diagonal bracing of the transverse bridge, the bearing capacity of the transverse bridge is enhanced, the force is safer, and the structure is more reliable.

进一步地,所述锚固系统包括预埋螺栓、连接钢板、调平螺母以及加强钢筋,所述连接钢板上设置有螺栓孔,所述主承载立柱通过所述连接钢板和所述预埋螺栓锚固于悬索桥墩顶,所述调平螺母和所述加强钢筋分别设置于所述主承载立柱上。Further, the anchoring system includes embedded bolts, connecting steel plates, leveling nuts and reinforcing steel bars, the connecting steel plates are provided with bolt holes, and the main bearing column is anchored to the On the top of the suspension bridge pier, the leveling nuts and the reinforcing steel bars are respectively arranged on the main bearing column.

主承载立柱通过连接钢板和预埋螺栓与悬索桥墩顶实现锚固,加强钢筋起到加强作用,通过调平螺母能够对主承载立柱进行调平。因此,锚固系统采用预埋螺栓、连接钢板、调平螺母以及加强钢筋等,保证了该门架装置承压、受拉、抗扭、抗风能力。The main load-bearing column is anchored to the top of the suspension pier by connecting steel plates and embedded bolts. Therefore, the anchoring system adopts embedded bolts, connecting steel plates, leveling nuts and reinforcing steel bars, etc., to ensure the pressure, tension, torsion and wind resistance of the mast device.

进一步地,所述猫道转索鞍与所述主承载立柱连接。减少了塔顶混凝土内预埋件的设置。Further, the catwalk cable saddle is connected to the main bearing column. The setting of embedded parts in the concrete on the top of the tower is reduced.

进一步地,所述提升系统包括提升横梁、横梁移动轨道、横移倒链以及滑轮组,所述横梁移动轨道设置于所述纵梁上,所述提升横梁横跨安装于所述横梁移动轨道内,所述提升横梁与移位小车连接,所述横移倒链和所述滑轮组分别固定于所述悬挑梁上的所述横撑上。Further, the lifting system includes a lifting beam, a beam moving track, a traversing chain and a pulley block, the beam moving track is arranged on the longitudinal beam, and the lifting beam is installed across the beam moving track, The lifting beam is connected to the shifting trolley, and the traversing chain and the pulley block are respectively fixed on the cross braces on the cantilever beam.

通过设置在门架顶或地面的各种吨位卷扬机完成各种吨位构件的提升和纵横移动。移动方便快捷,便于运输、安装、加工。横梁移动轨道保证了移位小车沿既有轨道纵向移动。通过横移倒链和滑轮组,可实现人工手动进行提升横梁的纵向移位。The hoisting and vertical and horizontal movement of components of various tonnages are completed by various tonnage hoists installed on the top of the mast or on the ground. It is convenient and quick to move, easy to transport, install and process. The beam moving track ensures that the shifting trolley moves longitudinally along the existing track. Manual vertical displacement of the lifting beam can be realized by moving the chain and the pulley block laterally.

进一步地,所述牵引系统包括导轮组固定架、卷扬机支撑座以及滑车组,所述导轮组固定架设置于所述纵梁远离所述悬挑梁的一端,所述卷扬机支撑座安装于所述纵梁上,所述滑车组安装于所述纵梁上靠近所述卷扬机支撑座的位置。Further, the traction system includes a guide wheel set fixing frame, a winch support base and a block block, the guide wheel set fixation frame is arranged at the end of the longitudinal beam away from the cantilever beam, and the winch support base is installed on On the longitudinal beam, the pulley block is installed on the longitudinal beam at a position close to the support base of the hoist.

在猫道索牵引和索股架设过程中保证索体平滑通过,并利用卷扬机和滑车组提升索股进行垂度和线型调整。During the catway cable traction and cable strand erection process, ensure that the cable body passes smoothly, and use the hoist and pulley group to lift the cable strand to adjust the sag and line shape.

进一步地,所述工作平台上设置有工作平台护栏。通过设置工作平台护栏,能够保证施工人员的人身安全,防止坠落等意外事故。Further, the working platform is provided with a working platform guardrail. By setting the guardrail of the working platform, the personal safety of the construction personnel can be guaranteed and accidents such as falling can be prevented.

本实用新型提供的悬索桥墩顶多功能门架装置的有益效果是:该悬索桥墩顶多功能门架装置在传统门架体系上进行了优化,通过设置现装门架本体,将门架进行分块,在塔顶进行组装,并且通过设置提升系统和牵引系统,既能满足现场吊装要求,又能方便运输、安装、加工,实现了简化施工安装,能够与塔顶处的猫道转索鞍组合在一起。该门架体系结构受力安全,在悬索桥上部结构安装施工各个阶段都能充分发挥门架的作用,真正实现了一架多用。The beneficial effect of the multifunctional gantry device on the top of the suspension bridge pier provided by the utility model is: the multifunctional gantry device on the top of the suspension bridge pier is optimized on the traditional gantry system, and the gantry is divided into blocks by setting the existing gantry body , assembled at the top of the tower, and by setting the lifting system and traction system, it can not only meet the requirements of on-site hoisting, but also facilitate transportation, installation and processing, realize simplified construction and installation, and can be combined with the catwalk on the top of the tower. together. The gantry system structure is safe under force, and the gantry can give full play to the role of the gantry in all stages of the installation and construction of the suspension bridge superstructure, and truly realizes a multi-purpose.

附图说明Description of drawings

为了更清楚地说明本实用新型实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本实用新型的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following drawings will be briefly introduced in the embodiments. It should be understood that the following drawings only show some embodiments of the present invention. Therefore, it should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can also be obtained according to these drawings without creative work.

图1为本实用新型实施例提供的悬索桥墩顶多功能门架装置的整体结构示意图;Figure 1 is a schematic diagram of the overall structure of the multifunctional gantry device on the top of the pier of the suspension bridge provided by the embodiment of the utility model;

图2为本实用新型实施例提供的悬索桥墩顶多功能门架装置的支撑桁架系统的主视结构示意图;Fig. 2 is a schematic diagram of the front view of the supporting truss system of the multifunctional gantry device on the top of the pier of the suspension bridge provided by the embodiment of the utility model;

图3为本实用新型实施例提供的悬索桥墩顶多功能门架装置的支撑桁架系统的侧视结构示意图;Fig. 3 is a side view structural schematic diagram of the supporting truss system of the multifunctional gantry device on the top of the suspension bridge pier provided by the embodiment of the utility model;

图4为本实用新型实施例提供的悬索桥墩顶多功能门架装置的支撑桁架系统的俯视结构示意图;Fig. 4 is a top view structural schematic diagram of the supporting truss system of the multifunctional gantry device on the top of the suspension bridge pier provided by the embodiment of the utility model;

图5为本实用新型实施例提供的悬索桥墩顶多功能门架装置在图2中a处的局部放大图;Fig. 5 is a partial enlarged view of the multifunctional gantry device at the top of the pier of the suspension bridge provided by the embodiment of the utility model at a in Fig. 2;

图6为本实用新型实施例提供的悬索桥墩顶多功能门架装置在图3中b处的局部放大图;Fig. 6 is a partial enlarged view of the multi-functional gantry device at the top of the pier of the suspension bridge provided by the embodiment of the utility model at b in Fig. 3;

图7为本实用新型实施例提供的悬索桥墩顶多功能门架装置的门架桁片结构的桁片的组拼图。Fig. 7 is a jigsaw diagram of the truss structure of the gantry truss structure of the multifunctional gantry device on the top of the suspension bridge pier provided by the embodiment of the utility model.

图中标记分别为:The marks in the figure are:

工作平台101;悬索桥墩顶102;猫道转索鞍103;门架桁片结构104;主承载立柱105;纵梁106;横撑107;小斜撑108;悬挑大斜撑109;悬挑梁110;端横梁111;柱间横梁112;中横梁113;悬臂间横梁114;顶面斜撑115;横桥向斜撑116;预埋螺栓117;连接钢板118;调平螺母119;加强钢筋120;提升横梁121;横梁移动轨道122;滑轮组123;导轮组124;卷扬机125;工作平台护栏126;地面牵引索127。Working platform 101; suspension bridge pier top 102; catwalk turning cable saddle 103; portal truss structure 104; main bearing column 105; longitudinal beam 106; cross brace 107; Beam 110; end beam 111; column beam 112; middle beam 113; cantilever beam 114; top diagonal brace 115; cross bridge diagonal brace 116; embedded bolt 117; connecting steel plate 118; leveling nut 119; reinforcement bar 120; lifting beam 121; beam moving track 122; block pulley 123; guide wheel block 124; winch 125;

具体实施方式detailed description

为满足主索鞍提升安装,同时方便施工猫道、牵引系统、索股张拉系统等临时设施,以及紧缆机、缠丝机、缆载吊机等施工设备安装,同时方便后续架设主缆、索夹及吊索、钢箱梁等永久性结构,在塔顶设置门架。常规门架由于整体重量太大不利于吊装安装,需对门架进行简化设计,达到方便吊装、安装、运输等。In order to meet the lifting and installation of the main cable saddle, it is convenient for the construction of catwalks, traction systems, cable strand tensioning systems and other temporary facilities, as well as the installation of construction equipment such as cable tightening machines, wire winding machines, and cable cranes, and at the same time facilitates the subsequent erection of the main cable , cable clips and slings, steel box girders and other permanent structures, and a door frame is set on the top of the tower. Because the overall weight of the conventional door frame is too large, it is not conducive to hoisting and installation. It is necessary to simplify the design of the door frame to facilitate hoisting, installation, and transportation.

鉴于此,本实用新型的设计者通过长期的探索和尝试,以及多次的实验和努力,不断的改革创新,设计了一种悬索桥墩顶多功能门架装置,通过设置现装门架本体,将门架进行分块,在塔顶进行组装,并且通过设置提升系统和牵引系统,既能满足现场吊装要求,又能方便运输、安装、加工,实现了简化施工安装,能够与塔顶处的猫道转索鞍103组合在一起。该门架体系结构受力安全,在悬索桥上部结构安装施工各个阶段都能充分发挥门架的作用,真正实现了一架多用。In view of this, the designer of the utility model has designed a multifunctional gantry device on the top of a suspended bridge pier through long-term exploration and attempts, as well as many experiments and efforts, and has designed a multifunctional gantry device on the top of a suspended bridge pier. The mast is divided into blocks and assembled on the top of the tower, and by setting up the lifting system and traction system, it can not only meet the requirements of on-site hoisting, but also facilitate transportation, installation and processing, and realize simplified construction and installation. Road turning cable saddle 103 is combined together. The gantry system structure is safe under force, and the gantry can give full play to the role of the gantry in all stages of the installation and construction of the suspension bridge superstructure, and truly realizes a multi-purpose.

为使本实用新型实施例的目的、技术方案和优点更加清楚,下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本实用新型一部分实施例,而不是全部的实施例。通常在此处附图中描述和示出的本实用新型实施例的组件可以以各种不同的配置来布置和设计。因此,以下对在附图中提供的本实用新型的实施例的详细描述并非旨在限制要求保护的本实用新型的范围,而是仅仅表示本实用新型的选定实施例。基于本实用新型中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the utility model more clear, the technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the utility model. Obviously, the described The embodiments are some embodiments of the present utility model, but not all embodiments. The components of the embodiments of the invention generally described and illustrated in the figures herein may be arranged and designed in a variety of different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

实施例Example

请参阅图1~图4,本实施例提供了一种悬索桥墩顶多功能门架装置,该悬索桥墩顶多功能门架装置包括现装门架本体,现装门架本体包括支撑桁架系统和工作平台101,工作平台101与支撑桁架系统的上端连接,支撑桁架系统的下端通过锚固系统锚固于悬索桥墩顶102,现装门架本体还包括猫道转索鞍103、提升系统以及牵引系统,猫道转索鞍103、提升系统以及牵引系统分别与支撑桁架系统连接。Please refer to Figures 1 to 4, the present embodiment provides a multifunctional gantry device at the top of a suspension bridge pier. The multifunctional gantry device at the top of a suspension bridge pier includes an existing gantry body, which includes a support truss system The working platform 101 is connected to the upper end of the supporting truss system, and the lower end of the supporting truss system is anchored to the top of the suspension bridge pier 102 through the anchor system. The catwalk turning saddle 103, the hoisting system and the traction system are respectively connected with the support truss system.

本实施例提供的悬索桥墩顶多功能门架装置在传统门架体系上进行了优化,通过设置现装门架本体,将门架进行分块,在塔顶进行组装,并且通过设置提升系统和牵引系统,既能满足现场吊装要求,又能方便运输、安装、加工,实现了简化施工安装,能够与塔顶处的猫道转索鞍103组合在一起。该门架体系结构受力安全,在悬索桥上部结构安装施工各个阶段都能充分发挥门架的作用,真正实现了一架多用。The multifunctional gantry device on the top of the suspension bridge pier provided in this embodiment is optimized on the traditional gantry system. By setting the ready-to-install gantry body, the gantry is divided into blocks and assembled on the top of the tower, and by setting the lifting system and traction The system can not only meet the requirements of on-site hoisting, but also facilitate transportation, installation and processing, realize simplified construction and installation, and can be combined with the catwalk saddle 103 at the top of the tower. The gantry system structure is safe under force, and the gantry can give full play to the role of the gantry in all stages of the installation and construction of the suspension bridge superstructure, and truly realizes a multi-purpose.

在上述实施例提供的悬索桥墩顶多功能门架装置的技术方案的基础上,进一步地,请参阅图1~图4以及图7,支撑桁架系统包括两个相对设置的门架桁片结构104,两个门架桁片结构104通过若干门架横梁连接,门架桁片结构104包括多根主承载立柱105、纵梁106、若干横撑107、若干小斜撑108以及悬挑大斜撑109,主承载立柱105通过锚固系统锚固于悬索桥墩顶102,工作平台101设置于纵梁106上,相邻两个主承载立柱105通过横撑107和小斜撑108连接,纵梁106的一端为悬挑梁110,悬挑梁110与主承载立柱105通过悬挑大斜撑109连接,悬挑梁110和悬挑大斜撑109通过横撑107和小斜撑108连接。On the basis of the technical solution of the multifunctional gantry device on the top of the suspension bridge pier provided in the above embodiment, please refer to Figures 1 to 4 and 7, the supporting truss system includes two oppositely arranged gantry truss structures 104 , two gantry truss structures 104 are connected by several gantry beams, and the gantry truss structure 104 includes multiple main bearing columns 105, longitudinal beams 106, several cross braces 107, several small diagonal braces 108 and cantilevered large diagonal braces 109, the main load-bearing column 105 is anchored to the top of the suspension bridge pier 102 through the anchor system, the working platform 101 is set on the longitudinal beam 106, and two adjacent main load-bearing columns 105 are connected by cross braces 107 and small diagonal braces 108, and one end of the longitudinal beam 106 The cantilever beam 110 is connected to the main bearing column 105 through a cantilevered large diagonal brace 109 , and the cantilever beam 110 and the cantilevered large diagonal brace 109 are connected through a cross brace 107 and a small diagonal brace 108 .

支撑桁架系统包括主承载立柱105、纵梁106、横撑107等构件,为索鞍安装提升、索股架设牵引、钢箱梁吊装设备安装等提供起重和支撑。支撑桁架系统采用门架桁片结构104,支撑桁架系统整体结构受力安全,各构件之间采用栓接为主、焊接为辅的连接方式,简化了施工难度,同时方便运输和周转。由标准型材、栓接连接、组拼速度快、安装精度高、现场焊接作业量少。The supporting truss system includes main bearing columns 105, longitudinal beams 106, cross braces 107 and other components to provide lifting and support for the installation and lifting of cable saddles, the erection and traction of cable strands, and the installation of steel box girder hoisting equipment. The supporting truss system adopts the gantry truss structure 104, and the overall structure of the supporting truss system is safe under force. The connection between each component is mainly bolted and supplemented by welding, which simplifies the difficulty of construction and facilitates transportation and turnover. It is made of standard profiles, bolted connections, fast assembly speed, high installation accuracy, and less on-site welding work.

作为优选,该门架装置的现装门架本体高8.8m,宽4.9m,沿顺桥方向设计为大悬臂结构,悬臂长度为13m。As a preference, the existing gantry body of the gantry device is 8.8m high and 4.9m wide, and is designed as a large cantilever structure along the direction of the bridge, with a cantilever length of 13m.

请参阅图4,门架横梁包括端横梁111、柱间横梁112、中横梁113以及悬臂间横梁114,两个纵梁106的两端分别通过端横梁111连接,两个纵梁106在其与主承载立柱105的连接处通过柱间横梁112连接,两个纵梁106的中部通过中横梁113连接,两个悬挑梁110通过悬臂间横梁114连接。Please refer to Fig. 4, the gantry crossbeam comprises end crossbeam 111, inter-column crossbeam 112, middle crossbeam 113 and cantilever crossbeam 114, and the two ends of two longitudinal beams 106 are respectively connected by end crossbeam 111, and two longitudinal beams 106 are connected with it The joints of the main bearing columns 105 are connected by an inter-column crossbeam 112 , the middle parts of the two longitudinal beams 106 are connected by a middle crossbeam 113 , and the two cantilever beams 110 are connected by an inter-cantilever crossbeam 114 .

通过设置端横梁111、柱间横梁112、中横梁113以及悬臂间横梁114,将两个纵梁106的多个对应部位连接起来,结构更加稳固,受力更加安全,为悬索桥上部结构安装施工各个阶段充分发挥门架的作用。By setting the end beams 111, the inter-column beams 112, the middle beams 113 and the cantilever beams 114, multiple corresponding parts of the two longitudinal beams 106 are connected, the structure is more stable, and the force is safer. stage to give full play to the role of the mast.

请参阅图4,端横梁111与纵梁106之间、柱间横梁112与纵梁106之间分别通过顶面斜撑115连接。Referring to FIG. 4 , the end beams 111 and the longitudinal beams 106 , and the inter-column beams 112 and the longitudinal beams 106 are respectively connected by top braces 115 .

通过设置顶面斜撑115,加强了端横梁111和纵梁106、柱间横梁112与纵梁106之间的连接,进一步提高了支撑桁架系统的整体结构稳定性,加强了支撑的作用,整体受力更加安全。By setting the top diagonal brace 115, the connection between the end beam 111 and the longitudinal beam 106, and the inter-column beam 112 and the longitudinal beam 106 is strengthened, the overall structural stability of the supporting truss system is further improved, and the supporting function is strengthened. The force is more secure.

请参阅图3,端横梁111与远离悬挑梁110的一端的主承载立柱105之间通过横桥向斜撑116连接。Please refer to FIG. 3 , the end beam 111 is connected to the main bearing column 105 at the end far away from the cantilever beam 110 through a cross-bridge diagonal brace 116 .

通过设置横桥向斜撑116,增强了横桥向的承受能力,使受力更加安全,结构更加牢靠。By arranging the diagonal braces 116 in the direction of the transverse bridge, the bearing capacity in the direction of the transverse bridge is enhanced, the stress is safer, and the structure is more reliable.

请参阅图1~图3、图5和图6,锚固系统包括预埋螺栓117、连接钢板118、调平螺母119以及加强钢筋120,连接钢板118上设置有螺栓孔,主承载立柱105通过连接钢板118和预埋螺栓117锚固于悬索桥墩顶102,调平螺母119和加强钢筋120分别设置于主承载立柱105上。Please refer to Figures 1 to 3, Figures 5 and 6. The anchoring system includes embedded bolts 117, connecting steel plates 118, leveling nuts 119, and reinforcement bars 120. Bolt holes are provided on the connecting steel plates 118, and the main bearing columns 105 are connected through Steel plates 118 and pre-embedded bolts 117 are anchored to the pier top 102 of the suspension bridge, and leveling nuts 119 and reinforcing steel bars 120 are respectively arranged on the main bearing column 105 .

主承载立柱105通过连接钢板118和预埋螺栓117与悬索桥墩顶102实现锚固,加强钢筋120起到加强作用,通过调平螺母119能够对主承载立柱105进行调平。因此,锚固系统采用预埋螺栓117、连接钢板118、调平螺母119以及加强钢筋120等,保证了该门架装置承压、受拉、抗扭、抗风能力。The main bearing column 105 is anchored to the suspension pier top 102 by connecting the steel plate 118 and the embedded bolt 117 , the reinforcing steel bar 120 plays a strengthening role, and the main bearing column 105 can be leveled by the leveling nut 119 . Therefore, the anchoring system adopts embedded bolts 117, connecting steel plates 118, leveling nuts 119, and reinforcing steel bars 120, etc., to ensure the pressure, tension, torsion, and wind resistance of the gantry device.

请参阅图1,猫道转索鞍103与主承载立柱105连接。减少了塔顶混凝土内预埋件的设置。Please refer to FIG. 1 , the catwalk turning saddle 103 is connected with the main bearing column 105 . The setting of embedded parts in the concrete on the top of the tower is reduced.

请参阅图1,提升系统包括提升横梁121、横梁移动轨道122、横移倒链以及滑轮组123,横梁移动轨道122设置于纵梁106上,提升横梁121横跨安装于横梁移动轨道122内,提升横梁121与移位小车连接,横移倒链和滑轮组123分别固定于悬挑梁110上的横撑107上。Referring to Fig. 1, the lifting system includes a lifting beam 121, a beam moving track 122, a traversing chain and a pulley block 123. The crossbeam 121 is connected with the shifting trolley, and the traverse down chain and the pulley block 123 are respectively fixed on the cross braces 107 on the cantilever beam 110 .

通过设置在门架顶或地面的各种吨位卷扬机125完成各种吨位构件的提升和纵横移动。移动方便快捷,便于运输、安装、加工。横梁移动轨道122保证了移位小车沿既有轨道纵向移动。通过横移倒链和滑轮组123,可实现人工手动进行提升横梁121的纵向移位。The hoisting machines 125 of various tonnages arranged on the top of the mast or on the ground complete the lifting and vertical and horizontal movement of components of various tonnages. It is convenient and quick to move, easy to transport, install and process. The crossbeam moving track 122 ensures that the shifting trolley moves longitudinally along the existing track. By traversing the chain and the pulley block 123, the longitudinal displacement of the lifting beam 121 can be realized manually.

请参阅图1,牵引系统包括导轮组固定架、卷扬机支撑座以及滑车组,导轮组固定架设置于纵梁106远离悬挑梁110的一端,导轮组固定架用于安装导轮组124,卷扬机支撑座安装于纵梁106上,滑车组安装于纵梁106上靠近卷扬机支撑座的位置。卷扬机125安装于卷扬机支撑座,并与地面牵引索127连接。Please refer to Fig. 1, the traction system includes a guide wheel set fixing frame, a hoist support seat and a pulley block, the guide wheel set fixing frame is arranged on the end of the longitudinal beam 106 away from the cantilever beam 110, and the guide wheel set fixing frame is used for installing the guide wheel set 124, the winch support seat is installed on the longitudinal beam 106, and the block block is installed on the longitudinal beam 106 near the position of the winch support seat. The winch 125 is installed on the support base of the winch and connected with the traction cable 127 on the ground.

在猫道索牵引和索股架设过程中保证索体平滑通过,并利用卷扬机125和滑车组提升索股进行垂度和线型调整。During the catway cable traction and cable strand erection process, the cable body is guaranteed to pass smoothly, and the hoist 125 and the pulley group are used to lift the cable strands to adjust the sag and line shape.

请参阅图1~图4,工作平台101上设置有工作平台护栏126。通过设置工作平台护栏126,能够保证施工人员的人身安全,防止坠落等意外事故。Referring to FIGS. 1-4 , the working platform 101 is provided with a working platform guardrail 126 . By setting the working platform guardrail 126, the personal safety of construction personnel can be ensured, and accidents such as falling can be prevented.

该门架装置的安装施工要点:Key points for the installation and construction of the door frame device:

1.每个门架均由两个桁片和横向联系组成,在加工厂内将门架分成若干个小的加工杆件单元,单元间采用栓接为主、焊接为辅的连接方式,加工完成经试拼装后运往现场安装。1. Each gantry is composed of two trusses and transverse connections. In the processing plant, the gantry is divided into several small processing rod units. After trial assembly, it will be shipped to the site for installation.

2.在门架安装时,根据索塔处塔吊的起重能力及门架现场拼装条件,在地面上组装成分块组件,以减少高空安装工作量。每组件的重量不超过塔吊的最大起重能力。2. During the installation of the mast, according to the lifting capacity of the tower crane at the cable tower and the on-site assembly conditions of the mast, assemble the block components on the ground to reduce the workload of high-altitude installation. The weight of each component shall not exceed the maximum lifting capacity of the tower crane.

3.门架安装分两次进行:索鞍安装前安装一次,安装除门架顶平车纵移区域内的杆件外,其他构件均一次性安装到位;索鞍安装完成后,完善门架系统,形成完整结构。3. The installation of the door frame is carried out in two steps: one installation before the installation of the cable saddle, except for the rods in the longitudinal movement area of the door frame top flat car, all other components are installed in place at one time; after the installation of the cable saddle, complete the door frame system to form a complete structure.

4.在索鞍吊装前的门架拼装完成后,在门架顶面的纵梁106上设置提索牵引的卷扬机125等设备,并对整个门架系统进行检查及试验,确保所有机具设备均可安全正常工作之后,方可投入使用。4. After the gantry assembly before the cable saddle hoisting is completed, install hoist 125 and other equipment on the longitudinal beam 106 on the top surface of the gantry, and inspect and test the entire gantry system to ensure that all machinery and equipment are in good condition. It can be put into use only after it can work safely and normally.

5.施工期间,注意天气情况预报,应避开在超出设计条件的气象情况下进行施工。5. During the construction period, pay attention to the weather forecast and avoid construction under weather conditions beyond the design conditions.

6.所有施工应遵守设计和现场监理的要求。6. All construction shall comply with the design and on-site supervision requirements.

在本实用新型的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的设备或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In describing the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", Orientation indicated by "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", etc. The positional relationship is based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the referred equipment or elements must have a specific orientation, be constructed and operated in a specific orientation , so it cannot be interpreted as a limitation of the present utility model.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本实用新型的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features. In the description of the present utility model, "plurality" means two or more, unless otherwise specifically defined.

在本实用新型中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本实用新型中的具体含义。In this utility model, unless otherwise specified and limited, terms such as "installation", "connection", "connection" and "fixation" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection. Connection, or integration; it can be mechanical connection or electrical connection; it can be direct connection or indirect connection through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present utility model according to specific situations.

在本实用新型中,除非另有明确的规定和限定,第一特征在第二特征之“上”或之“下”可以包括第一和第二特征直接接触,也可以包括第一和第二特征不是直接接触而是通过它们之间的另外的特征接触。而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。In the present invention, unless otherwise clearly specified and limited, a first feature being "on" or "below" a second feature may include direct contact between the first and second features, and may also include the first and second features being in direct contact with each other. The features are not in direct contact but through another feature between them. Moreover, "above", "above" and "above" the first feature on the second feature include that the first feature is directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature. "Below", "beneath" and "under" the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.

以上所述仅为本实用新型的优选实施例而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the utility model, and are not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.

Claims (10)

1. suspension cable bridge pier function mast apparatus at most, it is characterized in that, comprise existing dress door frame body, the described door frame body that now fills comprises sub-truss system and working platform, described working platform is connected with the upper end of described sub-truss system, the lower end of described sub-truss system is anchored in suspension cable top of bridge pier by anchor system, described now dress door frame body also comprises cat road and turns cable saddle, Hoisting System and trailer system, and described cat road turns cable saddle, described Hoisting System and described trailer system and is connected with described sub-truss system respectively.
2. suspension cable bridge pier according to claim 1 function mast apparatus at most, it is characterized in that, described sub-truss system comprises two door frame purlin chip architectures be oppositely arranged, two described door frame purlin chip architectures are connected by some door frame crossbeams, described door frame purlin chip architecture comprises many main carrying columns, longeron, some stulls, some little diagonal braces and large diagonal brace of encorbelmenting, described main carrying column is anchored in suspension cable top of bridge pier by described anchor system, described working platform is arranged on described longeron, adjacent two described main carrying columns are connected with described little diagonal brace by described stull, one end of described longeron is Cantilever Beams, described Cantilever Beams is connected by large diagonal brace of encorbelmenting with described main carrying column, described Cantilever Beams is connected with described little diagonal brace by described stull with described large diagonal brace of encorbelmenting.
3. suspension cable bridge pier according to claim 2 function mast apparatus at most, it is characterized in that, described door frame crossbeam comprises crossbeam between end floor beam, intercolumniation crossbeam, middle cross beam and cantilever, the two ends of two described longerons connect respectively by described end floor beam, two described longerons are connected by intercolumniation crossbeam in its junction with described main carrying column, the middle part of two described longerons is connected by middle cross beam, and two described Cantilever Beams are connected by crossbeam between described cantilever.
4. suspension cable bridge pier according to claim 3 function mast apparatus at most, is characterized in that, between described end floor beam with described longeron, described intercolumniation crossbeam is connected respectively by end face diagonal brace with between described longeron.
5. suspension cable bridge pier according to claim 4 function mast apparatus at most, is characterized in that, is connected between described end floor beam and the described main carrying column of the one end away from described Cantilever Beams by direction across bridge diagonal brace.
6. suspension cable bridge pier according to claim 2 function mast apparatus at most, it is characterized in that, described anchor system comprises pre-embedded bolt, junction steel plate, leveling nut and stiffener, described junction steel plate is provided with bolt hole, described main carrying column is anchored in suspension cable top of bridge pier by described junction steel plate and described pre-embedded bolt, and described leveling nut and described stiffener are arranged on described main carrying column respectively.
7. suspension cable bridge pier according to claim 2 function mast apparatus at most, is characterized in that, described cat road turns cable saddle and is connected with described main carrying column.
8. suspension cable bridge pier according to claim 2 function mast apparatus at most, it is characterized in that, described Hoisting System comprises lifting crossbeam, cross beam movement track, traversing jack and assembly pulley, described cross beam movement track is arranged on described longeron, described lifting crossbeam is across being installed in described cross beam movement track, described lifting crossbeam is connected with displacement dolly, and described traversing jack and described assembly pulley are individually fixed in the described stull on described Cantilever Beams.
9. suspension cable bridge pier according to claim 2 function mast apparatus at most, it is characterized in that, described trailer system comprises guide wheel group fixed mount, hoist engine supporting seat and tackle pulley, described guide wheel group fixed mount is arranged at described longeron one end away from described Cantilever Beams, described hoist engine supporting seat is installed on described longeron, and described tackle pulley is installed on the position near described hoist engine supporting seat on described longeron.
10. suspension cable bridge pier according to claim 1 function mast apparatus at most, is characterized in that, described working platform is provided with working platform guardrail.
CN201521037677.9U 2015-12-14 2015-12-14 Span wire pier is function portal device at most Expired - Lifetime CN205205685U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521037677.9U CN205205685U (en) 2015-12-14 2015-12-14 Span wire pier is function portal device at most

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521037677.9U CN205205685U (en) 2015-12-14 2015-12-14 Span wire pier is function portal device at most

Publications (1)

Publication Number Publication Date
CN205205685U true CN205205685U (en) 2016-05-04

Family

ID=55843413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521037677.9U Expired - Lifetime CN205205685U (en) 2015-12-14 2015-12-14 Span wire pier is function portal device at most

Country Status (1)

Country Link
CN (1) CN205205685U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105386411A (en) * 2015-12-14 2016-03-09 中交一公局第三工程有限公司 Multifunctional portal device of suspension bridge pillar top
CN107761572A (en) * 2017-11-24 2018-03-06 中交路桥华南工程有限公司 Stayed cable suspension system and its installation method
CN112144393A (en) * 2020-10-23 2020-12-29 新疆北新路桥集团股份有限公司 Installation and construction method for water collecting pipe under bridge
CN114855631A (en) * 2022-05-26 2022-08-05 中交路桥建设有限公司 Method for installing multi-beam steel cable tower
CN117923355A (en) * 2024-03-25 2024-04-26 贵州省公路工程集团有限公司 Method and device for reducing friction and positioning by longitudinally moving hoisting roller of heavy component of suspension bridge

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105386411A (en) * 2015-12-14 2016-03-09 中交一公局第三工程有限公司 Multifunctional portal device of suspension bridge pillar top
CN105386411B (en) * 2015-12-14 2017-06-30 中交一公局第三工程有限公司 Suspension cable top of bridge pier multifunction gate rack device
CN107761572A (en) * 2017-11-24 2018-03-06 中交路桥华南工程有限公司 Stayed cable suspension system and its installation method
CN107761572B (en) * 2017-11-24 2024-02-23 中交路桥华南工程有限公司 Stay cable hanging system and installation method thereof
CN112144393A (en) * 2020-10-23 2020-12-29 新疆北新路桥集团股份有限公司 Installation and construction method for water collecting pipe under bridge
CN114855631A (en) * 2022-05-26 2022-08-05 中交路桥建设有限公司 Method for installing multi-beam steel cable tower
CN117923355A (en) * 2024-03-25 2024-04-26 贵州省公路工程集团有限公司 Method and device for reducing friction and positioning by longitudinally moving hoisting roller of heavy component of suspension bridge
CN117923355B (en) * 2024-03-25 2024-06-04 贵州省公路工程集团有限公司 Method and device for reducing friction and positioning by longitudinally moving hoisting roller of heavy component of suspension bridge

Similar Documents

Publication Publication Date Title
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN202936736U (en) Cable-stayed bridge composite beam construction bridge floor crane
CN105386411B (en) Suspension cable top of bridge pier multifunction gate rack device
CN105421249A (en) Novel dragging- hoisting combined type hanging basket structure and construction method
CN205205685U (en) Span wire pier is function portal device at most
CN208055880U (en) A kind of crane's major girder hoisting frame
CN105113803B (en) A high-altitude sliding hoisting device and its implementation method for a mountain corridor truss
CN104695337A (en) Self-lifting sliding and turnover construction system and construction method
CN101787678A (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
CN101481903B (en) The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane
CN108518071B (en) Installation method of double-layer large-span steel structure corridor
CN108004932A (en) Constructed the method for steel reinforced concrete combination beam using beam mode is transported under beam
CN114476962A (en) A steel-concrete composite beam erection system based on bridge deck crane
CN110656570A (en) A telescopic pedestrian bridge, construction device and construction method
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN210288140U (en) Simple and easy prefabricated decking hoist and mount platform truck
CN116853963A (en) A hoisting device and hoisting method for the main beam of a cable-stayed bridge
CN207987749U (en) Ride cable-styled erection crane
CN112030777B (en) A down-type mobile formwork support bracket spanning transfer construction method
CN201722621U (en) Integral hoisting frame of pre-fabricated box beam
CN205382425U (en) Railway T type bridge adds builds sound barrier beam mold plate girder unwheeling
CN205329549U (en) Corbel frame device is deposited to steel case roof beam temporarily
CN201245817Y (en) Hoisting equipment for box girder integral steel reinforcement framework
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method