Tower with suspended cable available for Large-span Steel Box Beam construction
Technical field
A kind of Large-span Steel Box Beam construction is the utility model is related to, in particular, the utility model relates generally to one kind
Tower with suspended cable available for Large-span Steel Box Beam construction.
Background technology
Steel box girder incremental launching method construction is so that its construction cost is low, speed of application is fast, construction stationarity is good, construction period controllability
By force, in constructing need not in obtain more and more extensive application many advantages, such as traffic under bridge cut-off, be particularly suitable for use in across busy
The bridge of traffic route, shipping river.But with the development of Bridges in Our Country cause, due to being influenceed and design form by landform
Variation, part steel box girder bridge beam span is larger, across road or river because traffic or geology, hydrologic condition reason can not be set
Put Temporary Piers.Bridge linear of this kind of steel box-girder in work progress controls, the reaction of supports controls, steel box-girder itself Stress Control
Very high requirement is proposed etc. many aspects.Thus it is necessary for the push construction method of Large-span Steel Box Beam and with being arranged
The structure applied further is studied and improved.
Utility model content
One of the purpose of this utility model is to be directed to above-mentioned deficiency, there is provided a kind of to can be used for what Large-span Steel Box Beam was constructed
Tower with suspended cable, it is expected that to solve that in Large-span Steel Box Beam work progress Temporary Piers can not be set, cause bridge linear and steel box-girder
The technical problems such as itself stress is uncontrollable.
To solve above-mentioned technical problem, the utility model uses following technical scheme:
A kind of tower with suspended cable available for Large-span Steel Box Beam construction provided by the utility model, including pylon column,
The lower end of pylon column is fixed with free bearing, and upper free bearing is arranged on lower free bearing, and lower free bearing is fixed on steel box-girder;The pylon
The both sides of column are mounted on anchor case and the case that casts anchor, and the inside of the upper anchor case and the case that casts anchor is respectively and fixedly provided with hoist cable, described to hang
Rope is used between pylon column and steel box-girder to be connected.
Preferably, further technical scheme is:Bearing beam, the pad are further fixed between the lower free bearing and steel box-girder
Beam is welded as a whole with lower free bearing, steel box-girder.
Further technical scheme is:The upper anchor case and the case that casts anchor are multiple, and each upper anchor case and case that casts anchor
In be respectively and fixedly provided with hoist cable.
Further technical scheme is:The bottom of the pylon column is also equipped with extending beam, and the extending beam passes through
Bearing is arranged on walking beam;The near middle of the extending beam and pylon column is also equipped with overturning-preventing hawser.
Further technical scheme is:The walking beam is perpendicular with steel box-girder in the horizontal plane.
Further technical scheme is:Be also equipped with top removal device on the steel box-girder, the top removal device with it is described
The bottom of extending beam is corresponding, and the bottom of the extending beam is additionally provided with the footstock corresponding with the top removal device.
Further technical scheme is:The upper anchor case is connected with the case that casts anchor by respective hoist cable with steel box-girder
Connect.
Further technical scheme is:The pylon column is the purlin with more transverse directions, longitudinal direction and skewed horizontal load bar
Frame structure.
Compared with prior art, one of the beneficial effects of the utility model are:By the erection tower column on steel box-girder,
It is attached, and then is played fixed by the extended position of hoist cable and steel box-girder with the case that casts anchor by the upper anchor case on pylon column
Under effect, avoid being turned under discounting as making steel box-girder from one caused by steel box-girder is hanging because of front end during the reach
Branch pier base remains horizontal when being moved forward to another branch pier base, even if distance is excessive without therefore setting between branch pier base
Temporary Piers, be advantageous to be lifted the convenience of Large-span Steel Box Beam construction, at the same it is provided by the utility model a kind of available for big
The tower with suspended cable of span steel box girder construction is simple in construction, and stability is good, suitable in the Large-span Steel Box Beam construction field of all kinds of specifications
Used in institute, application is wide.
Brief description of the drawings
Fig. 1 is the structural representation for illustrating the utility model one embodiment;
Fig. 2 is Fig. 1 lateral structure schematic diagram;
In figure, 1 it is pylon column, 2 is upper free bearing, 3 is lower free bearing, 4 is steel box-girder, 5 is upper anchor case, 6 to cast anchor case, 7
It is bearing beam for hoist cable, 8,9 be extending beam, 10 be walking beam, 11 be overturning-preventing hawser, 12 be top removal device, 13 has been footstock.
Embodiment
The utility model is further elaborated below in conjunction with the accompanying drawings.
With reference to shown in figure 1, the proud one embodiment of the utility model is a kind of hanging available for Large-span Steel Box Beam construction
Sarasota frame, including pylon column 1, the lower end of the pylon column 1 is fixed with free bearing 2, and upper free bearing 2 need to be arranged on lower free bearing 3
On, lower free bearing 3 is fixed on steel box-girder 4, that is, is placed in the top of steel box-girder 4;What is more important, in the both sides of pylon column 1
It is both needed to install anchor case 5 and two upper anchor casees 5, the both sides of near middle is installed in the case 6 that casts anchor, the i.e. both sides on the top of pylon column 1
Two casees 6 that cast anchor are installed, need to also be in the fixed hoist cable 7 in the inside of upper anchor case 5 and the case 6 that casts anchor, the effect of the hoist cable 7 is by pylon
It is connected between column 1 and steel box-girder 4, for being entered by pylon column 1 by hoist cable 7 to the steel box-girder 4 of the both sides of pylon column 1
Row drawing is hung.
In the present embodiment, by the erection tower column 1 on steel box-girder 4, by the upper anchor case 5 on pylon column 1 with
Anchor case 6 is attached by the extended position of hoist cable 7 and steel box-girder 4, so play it is fixed in the presence of, avoid steel box-girder 4 from existing
It is turned under discounting as making steel box-girder 4 from a branch pier base to another buttress caused by front end is hanging during reach
Remain horizontal during seat reach, even if distance is excessive without therefore Temporary Piers are set between branch pier base, be advantageous to be lifted
The convenience of Large-span Steel Box Beam construction.
Referring again to shown in Fig. 1, in another embodiment of the present utility model, to make pylon column 1 be arranged on steel box-girder 4
The upper uniformity with stress, can also fix a bearing beam 8 between above-mentioned lower free bearing 3 and steel box-girder 4, also can by bearing beam 8 with
Lower free bearing 3, steel box-girder 4 are welded as a whole;So as to further lift the stability that pylon column 1 is arranged on steel box-girder 4.Simultaneously
Drawn for raising sling 7 and hang the stability of steel box-girder, can realized by way of increasing the quantity of hoist cable 7, this mode is also more
It is easy;With reference to shown in Fig. 2, the upper anchor case 5 on pylon column 1 is specially disposed as multiple, Ran Hou with the case 6 that casts anchor first
Each upper anchor case 5 is with being respectively and fixedly provided with hoist cable 7 in the case 6 that casts anchor, and the steel with the both sides diverse location of pylon column 1 respectively of hoist cable 7
Box beam 4 is attached, and then the stability that further lifting steel box-girder 4 moves forward on the whole.
Referring still to shown in Fig. 1, in utility model is used to solve the more preferred one embodiment of technical problem, in order to
Prevent pylon column 1 from toppling over after being arranged on steel box-girder, can be on the basis of said structure, in the bottom of pylon column 1
One extending beam 9 is installed, gone out as shown, extending beam 9 is starting point with pylon column 1, is extended to its both sides;And this prolongs
Beam 9 also needs to be arranged on walking beam 10 by bearing;So as to each at the both ends of extending beam 9 and the near middle of pylon column 1
One or one group of installation overturning-preventing hawser 11 are installed;And for the convenience of the installation of lifting pylon column 1, above-mentioned walking beam 10 is pacified
The angle of dress is to make it perpendicular with steel box-girder 4 in the horizontal plane;, can be in pylon column by the walking beam 10 of foregoing angle
During 1 installation, by it from the side of steel box-girder 4, the position at lower free bearing 3 is pushed into along walking beam 10, by the upper of the bottom of pylon column 1
Free bearing 2 is arranged on lower free bearing 3 by bearing pin, and then simplifies the mounting means of pylon column 1.
Further, for ease of adjusting its upper-lower position when pylon column 1 is installed, it is easy to enter upper free bearing 2 and lower free bearing 3
It row alignment, because the weight of pylon column 1 itself is larger, therefore need to typically use outside crane gear to be aided in, and send out
A person of good sense considers the limitation of Large-span Steel Box Beam construction site, the top removal device 12 directly installed on steel box-girder 4, top lifting dress
Putting 12 can be directly using conventional jack, according to the jack of the weight of pylon column 1 selection dimension.Foregoing top lifting
The installation site of device 12 need to be corresponding with the bottom of extending beam 9, and also needs to set and top removal device 12 in the bottom of extending beam 9
Corresponding plays footstock 13, as shown, is preferably respectively mounted a top lifting on the steel box-girder 4 of the lower both sides of free bearing 3
Device 12.
As mentioned here above, as shown in Fig. 2 tower with suspended cable upper anchor case 5 need to be with the case 6 that casts anchor by each in use
From hoist cable 7 be connected with steel box-girder 4;And pylon column 1 can use truss structure, i.e., at it more with vertical for ease of removing
There is more transverse directions, longitudinal direction and skewed horizontal load bar between post, while being easy to be lifted pylon 1 intensity of column, reduce its own
Weight.
Than that described above, it is also necessary to which explanation is " one embodiment ", " another implementation spoken of in this manual
Example ", " embodiment " etc., refer to that the specific features, structure or the feature that combine embodiment description are included in the application summary
Property description at least one embodiment in.It is not necessarily to refer to same reality that statement of the same race, which occur, in multiple places in the description
Apply example.Furthermore, it is understood that when describing a specific features, structure or feature with reference to any embodiment, what is advocated is knot
Other embodiment is closed to realize that this feature, structure or feature also fall in the scope of the utility model.
Although reference be made herein to the utility model is described multiple explanatory embodiments of the present utility model, still,
It should be understood that those skilled in the art can be designed that a lot of other modifications and embodiment, these modifications and embodiment
It will fall within spirit disclosed in the present application and spirit.More specifically, in disclosure, drawings and claims
In the range of, a variety of variations and modifications can be carried out to the building block and/or layout of theme combination layout.Except to building block