CN211736432U - Building construction device - Google Patents
Building construction device Download PDFInfo
- Publication number
- CN211736432U CN211736432U CN201922489712.5U CN201922489712U CN211736432U CN 211736432 U CN211736432 U CN 211736432U CN 201922489712 U CN201922489712 U CN 201922489712U CN 211736432 U CN211736432 U CN 211736432U
- Authority
- CN
- China
- Prior art keywords
- self
- propelled
- crane
- track
- assembly platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model provides a building construction device belongs to construction technical field. The construction device comprises a self-propelled crane, a track of the self-propelled crane, a self-propelled assembly platform and a track of the self-propelled assembly platform; the self-propelled crane is installed on the track of the self-propelled crane, and the self-propelled assembly platform is installed on the track of the self-propelled assembly platform. The self-propelled crane and the self-propelled assembly platform are both arranged on the track, so that the requirement degree on the roadbed is reduced; the self-propelled crane can be arranged between buildings on two sides and can lift a component to be installed with a larger tonnage, so that the construction efficiency is improved. In addition, the construction device can be used as an assembly, transportation and installation integrated device, the dependence on external hoisting machinery is reduced, the restriction caused by field factors is reduced, and the assembly, transportation and installation efficiency is improved.
Description
Technical Field
The utility model relates to a construction technical field, in particular to building construction device.
Background
Some buildings are close to each other, and the space between two adjacent buildings is relatively long and narrow, so that the buildings are sometimes required to be constructed in the long and narrow area, for example, steel structures are installed on the buildings on two sides.
The installation method of the steel structure for the narrow space generally adopts the following two methods: the method comprises the steps of firstly, arranging an assembling jig frame in a middle span, carrying out refute transportation of components in place by a truck, assembling and hoisting along the middle span by adopting a truck crane or a crawler crane, reinforcing a roadbed on the ground in the middle span in a construction process to meet the driving requirements of the truck and a crane, repeatedly arranging and dismantling the assembling jig frame along with the installation position for many times, and when facing a complex foundation ground, the roadbed reinforcing difficulty and the assembling jig frame arrangement difficulty are large, meanwhile, the model of the truck crane or the crawler crane is limited by a narrow space, and the steel structure hoisting with high height and large span is difficult to meet. And secondly, the assembling jig frames are arranged outside the two sides in a crossing mode, the hoisting machinery is adopted to carry out outer hoisting, when buildings on two sides of a long and narrow space are high, the tonnage of the hoisting machinery is large, the hoisting machinery occupies a large space during working, the site traffic organization is not facilitated, meanwhile, the hoisting efficiency is low, and the requirement of the construction period of hoisting a large-size steel structure is difficult to meet.
SUMMERY OF THE UTILITY MODEL
The utility model provides a building construction device to solve current construction device and require high and the lower technical problem of efficiency of construction to the road bed.
In order to solve the technical problem, the utility model provides a building construction device, which comprises a self-propelled crane, a track of the self-propelled crane, a self-propelled assembly platform and a track of the self-propelled assembly platform;
the self-propelled crane is installed on the track of the self-propelled crane, and the self-propelled assembly platform is installed on the track of the self-propelled assembly platform.
Optionally, the track of the self-propelled crane and the track of the self-propelled assembly platform are the same track.
Optionally, the self-propelled crane and the self-propelled assembly platform are connected through a detachable rod.
Optionally, the self-propelled crane and the self-propelled assembly platform share one driving unit to move back and forth.
Optionally, the self-propelled crane and the self-propelled assembly platform respectively utilize a driving unit to move back and forth.
Optionally, the self-propelled assembly platform is provided with a jig frame for assembling a steel structure.
Optionally, the construction device is laid above a basement, the basement is provided with a beam column which is vertically installed, and the track of the self-propelled crane and the track of the self-propelled assembly platform are laid on the beam column.
The utility model provides a building construction device, which installs a self-propelled crane and a self-propelled assembly platform on a track, thereby reducing the required degree of a roadbed; the self-propelled crane can be arranged between buildings on two sides and can lift a component to be installed with a larger tonnage, so that the construction efficiency is improved. In addition, the construction device can be used as an assembly, transportation and installation integrated device, the dependence on external hoisting machinery is reduced, the restriction caused by field factors is reduced, and the assembly, transportation and installation efficiency is improved.
Drawings
Fig. 1 is a schematic structural diagram of a building construction device provided by the present invention;
FIG. 2 is a schematic view of the erection of the hoist unit on the self-propelled erection platform;
FIG. 3 is a schematic view of the self-propelled crane and self-propelled construction platform being launched from a construction area to a lifting area;
FIG. 4 is a schematic view of a hoist unit;
FIG. 5 is a schematic view of the construction apparatus installed in an elongated region;
FIG. 6 is a schematic view of the construction apparatus installed in an elongated region;
fig. 7 is a top view of fig. 5.
[ reference numerals are described below ]:
1-self-propelled crane; 2, self-propelled assembly platform; 3-a track of the self-propelled crane; 4-a track of the self-propelled assembly platform; 5-a detachable rod; 6-a jig frame; 7-a member to be hoisted; 8, hoisting a unit; 9-beam column; a, B-buildings.
Detailed Description
In order to make the objects, advantages and features of the present invention clearer, the following description of a construction device according to the present invention will be made in detail with reference to the accompanying drawings. It should be noted that the drawings are in simplified form and are not to precise scale, and are provided for convenience and clarity in order to facilitate the description of the embodiments of the present invention.
As shown in fig. 1-4, the utility model provides a building construction device, which comprises a self-propelled crane 1, a track 3 of the self-propelled crane, a self-propelled assembly platform 2 and a track 4 of the self-propelled assembly platform; self-propelled loop wheel machine 1 is installed on self-propelled loop wheel machine's track 3, self-propelled assembly platform 2 is installed on self-propelled assembly platform's track 4. Wherein, self-propelled loop wheel machine also can be called self-propelled tower crane.
The utility model provides a building construction device, which installs a self-propelled crane 1 and a self-propelled assembly platform 2 on a track, thereby reducing the required degree of a roadbed; the self-propelled crane 1 can be arranged between buildings on two sides and can lift a component to be installed with a larger tonnage, so that the construction efficiency is improved.
Optionally, as shown in fig. 5, the rail 3 of the self-propelled crane and the rail 4 of the self-propelled assembly platform are the same rail. The track 3 of the self-propelled crane and the track 4 of the self-propelled assembly platform are designed into the same track, and only two parallel tracks can be laid, so that the cost and the space occupied by the tracks are saved.
Optionally, as shown in fig. 1, the self-propelled crane 1 and the self-propelled assembly platform 2 are connected through a detachable rod 5. After the self-propelled crane 1 is connected with the self-propelled assembly platform 2 through the detachable rod 5, the self-propelled crane 1 can be driven by power of the self-propelled crane to move back and forth together with the self-propelled assembly platform 2.
Optionally, the self-propelled crane 1 and the self-propelled assembly platform 2 share one driving unit to move back and forth. The driving cost can be saved by sharing one driving unit, and the driving unit can be an electric motor.
The self-propelled crane 1 and the self-propelled assembly platform 2 respectively utilize a driving unit to move back and forth. The self-propelled crane 1 and the self-propelled assembly platform 2 are respectively provided with a driving unit, and the motion states of the self-propelled crane 1 and the self-propelled assembly platform 2 can be freely controlled.
Optionally, as shown in fig. 1 to 4, a jig frame 6 for assembling a steel structure is arranged on the self-propelled assembling platform 2. When the member 7 to be hoisted is a steel structure, most of the steel structures need to be assembled into the hoisting unit 8 on the ground and then hoisted to the preset installation position. Be equipped with the bed-jig 6 that is used for assembling the steel construction on the self-propelled assembly platform 2, can make bed-jig 6 along with the shown self-propelled assembly platform 2 round trip movement together, bed-jig 6 need not arrange and demolish along with the mounted position is repeated many times like prior art to construction efficiency has been improved.
Alternatively, as shown in fig. 5, the construction apparatus is laid above a basement having a beam column 9 vertically installed, and the rail 3 of the self-propelled crane and the rail 4 of the self-propelled racking platform are laid on the beam column 9. Will the track 3 of self-propelled loop wheel machine with the track 4 of self-propelled assembly platform is laid on the beam column 9, can be in construction equipment's gravity dispersion on the beam column 9, so not only can improve the security, can also reduce the required degree to the road bed.
The utility model provides a pair of building construction equipment not only is applicable to independent building structure, is applicable to the more long and narrow scene of space between the building of both sides moreover. As shown in fig. 5 to 7, the construction apparatus may be disposed in a span between buildings a and B on both sides, and hoist a steel structure or other construction materials to be hoisted.
Based on the same technical concept with above-mentioned building construction equipment, the utility model also provides a building construction method, construction method includes:
installing any one of the construction devices;
hoisting a component 7 to be hoisted to the self-propelled assembly platform 2 by using the self-propelled crane 1;
the self-propelled crane 1 and the self-propelled splicing platform 2 are driven to a construction area of a preset installation position;
and hoisting the member 7 to be hoisted to the preset installation position by using the self-propelled crane 1.
To the steel construction that needs to assemble, the utility model provides a building construction method, construction method includes:
installing the construction device, wherein a jig frame 6 for assembling a steel structure is arranged on a self-propelled assembling platform 2 of the construction device;
hoisting a component 7 to be hoisted to the self-propelled assembly platform 2 by using the self-propelled crane 1;
assembling a plurality of members 7 to be hoisted into a hoisting unit 8 by using the jig frame 6;
the self-propelled crane 1 and the self-propelled splicing platform 2 are driven to a construction area of a preset installation position;
and hoisting the hoisting unit 8 to the preset installation position by using the self-propelled crane 1.
During specific construction, self-propelled loop wheel machine 1 and self-propelled assembly platform 2 stop in track starting point department, hang to self-propelled assembly platform 2 by the direct component on with the storage yard of self-propelled loop wheel machine 1 on, then assemble into hoist and mount unit 8 on bed-jig 6, assemble the back of accomplishing, self-propelled loop wheel machine 1 and self-propelled assembly platform 2 are opened to the installation area together, hoist and mount unit 8 on the platform 2 is assembled to the self-propelled assembly by self-propelled loop wheel machine 1 and hang to the installation elevation and accomplish taking one's place, self-propelled loop wheel machine 1 pine hook, self-propelled loop wheel machine 1 and self-propelled assembly platform 2 are opened again to track starting point department and are assembled, transportation and installation work next round.
To sum up, the self-propelled crane 1 and the self-propelled assembly platform 2 are both arranged on the track, so that the required degree of the roadbed is reduced; the self-propelled crane 1 can be arranged between buildings on two sides and can lift a component to be installed with a larger tonnage, so that the construction efficiency is improved. In addition, the construction device can be used as an assembly, transportation and installation integrated device, the dependence on external hoisting machinery is reduced, the restriction caused by field factors is reduced, and the assembly, transportation and installation efficiency is improved.
The above description is only for the purpose of describing the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention, and any variations and modifications made by those skilled in the art based on the above disclosure are within the scope of the claims of the present invention.
Claims (7)
1. A building construction device is characterized in that the construction device comprises a self-propelled crane, a track of the self-propelled crane, a self-propelled assembly platform and a track of the self-propelled assembly platform;
the self-propelled crane is installed on the track of the self-propelled crane, and the self-propelled assembly platform is installed on the track of the self-propelled assembly platform.
2. The construction device according to claim 1, wherein the rail of the self-propelled crane and the rail of the self-propelled splicing platform are the same rail.
3. The building construction device according to claim 1, wherein the self-propelled crane and the self-propelled splicing platform are connected through a detachable rod.
4. The construction device according to claim 1, wherein the self-propelled crane and the self-propelled construction platform share a single driving unit for back and forth movement.
5. The construction device according to claim 1, wherein the self-propelled crane and the self-propelled splicing platform are moved back and forth by a driving unit, respectively.
6. A building construction device according to any one of claims 1-5 wherein a jig frame for assembling a steel structure is provided on the self-propelled assembly platform.
7. The construction device of claim 1, wherein the construction device is laid above a basement having a beam column mounted vertically, the rail of the self-propelled crane and the rail of the self-propelled racking platform being laid on the beam column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922489712.5U CN211736432U (en) | 2019-12-31 | 2019-12-31 | Building construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922489712.5U CN211736432U (en) | 2019-12-31 | 2019-12-31 | Building construction device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211736432U true CN211736432U (en) | 2020-10-23 |
Family
ID=72867272
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922489712.5U Active CN211736432U (en) | 2019-12-31 | 2019-12-31 | Building construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211736432U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005580A (en) * | 2019-12-31 | 2020-04-14 | 上海市机械施工集团有限公司 | Building construction device and method |
-
2019
- 2019-12-31 CN CN201922489712.5U patent/CN211736432U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005580A (en) * | 2019-12-31 | 2020-04-14 | 上海市机械施工集团有限公司 | Building construction device and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103215894B (en) | Portable interim prestressed stretch-draw anchor block | |
CN105401582A (en) | Hanging type unearthing device for bidirectional synchronous reversed construction and construction method | |
CN106245919A (en) | A kind of assembled architecture Automated assembly platform | |
CN211736432U (en) | Building construction device | |
CN110468743B (en) | Movable hanging bracket for transformation of old bridge pier cap and construction method | |
CN102777037B (en) | Simple and practical hoisting construction method of long-span steel girder | |
CN103601078B (en) | Suspension type hanging device | |
CN104291222A (en) | Rigid protection and crane integration system inside super high-rise building core tube | |
CN211141349U (en) | Track panel well gantry crane foundation fixing structure | |
CN112160246B (en) | Method for installing composite beam | |
CN204023336U (en) | A kind of subway track-laying machine | |
CN105544546A (en) | Waste clearing and transporting device and method for underground engineering | |
CN211647239U (en) | Lower hanging device for steel platform | |
CN211141313U (en) | Portal crane suitable for hoisting low-height underground continuous wall reinforcement cage | |
CN210597630U (en) | Net rack integral lifting structure | |
CN205421264U (en) | A suspension type device that is unearthed that is used for contrary work of two way synchronization to be under construction | |
CN111005580A (en) | Building construction device and method | |
CN103147401A (en) | Construction method and structure of self-climbing portal frame | |
CN106988344B (en) | Construction method of assembled trolley for cast-in-place section of fabricated station | |
CN207047703U (en) | A kind of beam piece prestressed stretch-draw jack easy device in place | |
CN216889750U (en) | Detachable movable portal frame for improving hoisting operation safety | |
CN207110599U (en) | A kind of under(-)chassis of up-down cross sliding type multi-storied garage | |
CN216549362U (en) | Assembling and hoisting device for components above foundation pit | |
CN112431397B (en) | High-rise building construction system and installation and use method thereof | |
CN201817201U (en) | Trolley slippage construction device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |