CN207934392U - The quick conveying device of skyscraper rubbish - Google Patents

The quick conveying device of skyscraper rubbish Download PDF

Info

Publication number
CN207934392U
CN207934392U CN201820405451.7U CN201820405451U CN207934392U CN 207934392 U CN207934392 U CN 207934392U CN 201820405451 U CN201820405451 U CN 201820405451U CN 207934392 U CN207934392 U CN 207934392U
Authority
CN
China
Prior art keywords
rubbish
tube body
garbage transporting
channel
pour spout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820405451.7U
Other languages
Chinese (zh)
Inventor
郑建国
张雪伟
郭玉波
张恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongqi Jiaojian Group Corp Ltd
Original Assignee
Zhongqi Jiaojian Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongqi Jiaojian Group Corp Ltd filed Critical Zhongqi Jiaojian Group Corp Ltd
Priority to CN201820405451.7U priority Critical patent/CN207934392U/en
Application granted granted Critical
Publication of CN207934392U publication Critical patent/CN207934392U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to building waste transportation arts,The especially quick conveying device of skyscraper rubbish,Including more vertical tube bodies,And multiple bending tube bodies that garbage transporting channel is formed for connection that vertical tube body turns round repeatedly,The corresponding rubbish pour spout of floor is equipped on garbage transporting channel,Garbage transporting vias inner walls in rubbish pour spout are equipped with the baffle for stopping airborne dust,It is equipped with rubbish delivery outlet in garbage transporting the bottom of the channel,The adjacent tube body of rubbish delivery outlet is equipped with spray port,Building waste transport at present is mostly to use construction elevator,It is transformed based on lift well,It is time-consuming and laborious,And the volume of building waste and it is in irregular shape etc. due to,Airborne dust is easily caused in transportational process and ground or cleaning equipment are damaged,The utility model effectively buffers rubbish sinking speed,Prevent airborne dust from endangering,And it is simple in structure,It can be widely popularized.

Description

The quick conveying device of skyscraper rubbish
Technical field
The utility model is related to building waste transportation arts, the especially quick conveying device of skyscraper rubbish.
Background technology
At present in architectural engineering, especially when tier building is constructed, the building waste of generation needs timely to be transported to ground Then face is transported, not then can occupy construction site, make originally limited construction site become narrow, hinder normal construction into Row.If building waste directly thrown to ground, not only there is serious security risk, but also in throwing process, can also produce Raw a large amount of airborne dust and noise, in particular with increasing for floor, adverse effect caused by the mode of this direct throwing is more Add obviously, so the requirement of apparent improper current safe construction, civilized construction and environmental protection construction, so, in current multilayer Three kinds of modes below rubbish generally use in building in work progress:One is using construction elevator, that is, passes through installation Elevator, by building waste by elevator gradually be transported to ground, be labor intensive first in this way, need worker first By refuse bag or frame up, then again in movement to elevator, then ground be transported to by elevator, building waste be transported to ground it Afterwards, it is also necessary to which rubbish is moved out elevator and is transported at stacking by worker;Secondly as being by elevator traffic, single freight volume is small, And transportational process is also and discontinuous, so that the transporting velocity of rubbish is slower;Furthermore, it should be noted that building at present Engineering in general floor construct to eight layers just start installation elevator, could usually be used in eleventh floor, construction elevator just Before being often used, the cleaning of floor rubbish cannot be kept up in time, still influence civilized construction and airborne dust prevention.Another way is profit Rubbish transfer passage is established with skyscraper lift well, that is, elevator doorway is transformed into rubbish pour spout, it can per floor It is corresponding be provided with it is at least one be thrown into mouth, in use, each floor rubbish is directly thrown into elevator shaft, rubbish is in elevator shaft Interior free-falling is to ground, is that elevator needs to install first in this way, when elevator being stopped using to dump rubbish, The peak period that positive value building waste is formed, so still without solving the problems, such as clearing for rubbish at all.And rubbish rehandling It is time-consuming.Moreover it is to affect elevator to be installed to the prospecting in elevator, transformation, Secondary Design time early period.The third Mode be use garbage chute, that is, by be arranged garbage chute, opened up on garbage chute it is multiple be thrown into mouth, keep every floor all corresponding Have it is at least one be thrown into mouth, in use, can directly directly be thrown into the building waste of each floor in garbage chute, building waste exists Free-falling is to ground in garbage chute.In this way, it is that of avoiding the generation of airborne dust first;Secondly as can be continuous Construction can make rubbish constantly toward falling, greatly improve the speed of garbage transporting.But since building waste is in rubbish Rubbish falls vertically in road, and when being fallen to the ground under rubbish, speed is larger, also, since the big hardness of building waste intensity itself is high, Shape is also irregular, all can to garbage chute itself and the transporting equipment being disposed below, or even to the ground below garbage chute Greater impact is caused, with increasing for floor, this impact is bigger, so, garbage chute is limited in tier building construction Using height, and then cause in current construction, garbage chute is substantially use in low-rise building engineering, CN104234388A discloses a kind of garbage chute for high-building construction, although solving skyscraper rubbish using construction Elevator and using skyscraper lift well establish rubbish transfer passage there are the problem of, but use straight barrel type structure, even if Buffer board is set up, but in actual application, still buffer board can have been caused to impact if encountering larger building waste, It is of long duration fragile, and then ground is formed and is impacted, and structure is complex, and installation is inconvenient, airborne dust caused by building waste Larger, which cannot control airborne dust, also will produce adverse effect to construction life.
Invention content
In view of the deficiencies of the prior art, the quick conveying device of skyscraper rubbish is provided, is realizing high-rise rubbish conveying While, building waste can be effectively reduced and topple over the impact caused by transport system bottom, and effectively control airborne dust, structure letter It is single, it can wide popularization and application.
The technical scheme adopted by the utility model is that the quick conveying device of skyscraper rubbish, including outside skyscraper The more vertical tube bodies and multiple connections that are used to repeatedly turn round the vertical tube body that wall is arranged from top to bottom form rubbish fortune The bending tube body in defeated channel is equipped with multiple rubbish pour spouts corresponding with floor, the rubbish successively on garbage transporting channel Garbage transporting vias inner walls in pour spout are equipped with is used to prevent top garbage transporting with what garbage transporting channel was rotatablely connected Rubbish, which falls, in channel there is the baffle of airborne dust, and the rubbish for being delivered to rubbish outside channel is equipped in garbage transporting the bottom of the channel Rubbish delivery outlet, the adjacent tube body of the rubbish delivery outlet are equipped with the spray port for reducing airborne dust.
The above-mentioned quick conveying device of skyscraper rubbish, the bending tube body include that one end is connect with the vertical tube body in top The first metal bends and the lateral tube body that is connect with the first metal bends other end of one end, the transverse direction tube body it is another One end connects the vertical tube body of lower part by the second metal bends, and the rubbish pour spout is set on lateral tube body.
The above-mentioned quick conveying device of skyscraper rubbish, the rubbish pour spout are equipped with for closing rubbish pour spout Door body, hinge for connecting the two is equipped between the door body and rubbish pour spout, is equipped in door body for opening The handle of door body is equipped with the bolt for preventing rubbish from overflowing for closing door body in handle both sides.
The above-mentioned quick conveying device of skyscraper rubbish, the short transverse of the tube body adjacent along rubbish delivery outlet are uniformly set There are multiple spray ports.
The advantageous effect of the quick conveying device of the utility model skyscraper rubbish is, by more bending tube bodies by more Vertical tube body connection, forms garbage transporting channel, avoids when toppling over building waste into straight barrel type garbage chute, is caused to bottom Impact, be equipped with multiple rubbish pour spouts being correspondingly arranged with floor successively on transport channel, facilitate each floor rubbish Rubbish is toppled over, and the gear to raise up for stopping airborne dust being rotatablely connected with tube body is equipped on the adjacent inboard wall of tube body of rubbish pour spout Plate avoids when dumping rubbish, and airborne dust is endangered caused by the person of worker, is equipped in transport channel bottom for rubbish is defeated The rubbish delivery outlet to outside channel is sent, the spray port for reducing airborne dust is equipped on the adjacent tube body of rubbish delivery outlet, due to Bottom airborne dust is larger, and spray port is arranged on the tube body of bottom, can effectively reduce bottom airborne dust, and processing is cleared convenient for rubbish.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram of door body;
Fig. 3 is the structural schematic diagram for being bent tube body.
Specific implementation mode
Below in conjunction with attached drawing, elaborate to the utility model.
As shown in Figure 1, 2, 3, the quick conveying device of skyscraper rubbish, including be arranged from top to bottom along external wall of high-rise building More vertical tube bodies 1 and multiple form the bending tube body in garbage transporting channel for vertical tube body 1 to turn round repeatedly to connect 2, it avoids when toppling over building waste into straight barrel type garbage chute, hard modeling can be used in the impact caused by bottom, vertical tube body 1 Expects pipe, plastic conduit tubing is light, and convenient for construction, price is low, economical and beautiful, cost-effective, bending tube body include one end with it is upper The lateral tube body that first metal bends 3 of the vertical tube body connection in portion and one end are connect with the first metal bends other end 4, transverse direction 4 other end of tube body connects the vertical tube body of lower part, the first metal bends 3 and second by the second metal bends 5 45 ° of metal bends can be used in metal bends 5, and metal material can effectively prevent transfer passage to be punctured by heavy construction rubbish, vertically By flanged joint on tube body 1 and bending tube body 2 and lateral tube body 4, flange is easily attached, easy to disassemble, can be reused, Material has been saved, multiple rubbish pour spouts 6 being correspondingly arranged with floor has been equipped with successively on garbage transporting channel, facilitates each building The rubbish of layer is toppled over, and rubbish pour spout 6 is equipped with one and is used for 6 closed door body 7 of rubbish pour spout, and is used for door body 7 The handle 8 of unlatching can incline rubbish for ease of dumping rubbish in the bolt 9 that 8 both sides of handle are equipped with for preventing rubbish from overflowing Mouth 6 is set on lateral tube body 4, the upper hinge 10 being equipped with for connecting the two between door body 7 and rubbish pour spout 6, It prevents rubbish from excessively being overflowed out of rubbish pour spout, makes troubles to construction site, relative to installation elevator conveying rubbish, In this way, it is time saving and energy saving first, first by refuse bag or frames up without worker, then again in movement to elevator, Ground is transported to by elevator again, after building waste is transported to ground, it is also necessary to which rubbish is moved out elevator and is transported at stacking by worker; Secondly as being by elevator traffic, single freight volume is small, and transportational process is also and discontinuous, so that rubbish Transporting velocity is slower;Just start to install to apply to eight layers furthermore, it should be noted that architectural engineering at present is generally constructed in floor Work elevator could usually be used in eleventh floor, and before construction elevator normal use, the cleaning of floor rubbish cannot be kept up in time, Still influence civilized construction and airborne dust prevention, the utility model can be according to story height, using metal bends by plastic conduit The height being adapted with story height is connected into, not by story height lower limit, while without transformation skyscraper lift well Rubbish transfer passage is established, it is time-consuming and laborious, it is equipped in the garbage transporting vias inner walls in rubbish pour spout logical with garbage transporting There is the baffle 11 of airborne dust for preventing in the garbage transporting channel of top rubbish to fall in road rotation connection, in garbage transporting channel Equipped with the shaft for sub-barrier rotation being connect with baffle 11, garbage transporting channel is equipped with the hole for limit rotary shaft, , can be simple in structure by baffle plate setting on the adjacent inboard wall of tube body of rubbish pour spout to achieve the effect that good blocking airborne dust, It is easy to manufacture, it avoids when dumping rubbish, airborne dust is endangered caused by the person of worker, is equipped with for by rubbish in transfer passage bottom Rubbish is delivered to the rubbish delivery outlet 12 outside channel, can be positioned over garbage transporting equipment at rubbish delivery outlet 12, rubbish is directly fallen On transporting equipment, convenient for directly transporting, it is not necessarily to rehandling, manpower is saved, is set on the adjacent tube body of rubbish delivery outlet 12 The spray port 13 for being useful for reducing airborne dust can be along the height of the adjacent tube body of rubbish delivery outlet to reach good spraying effect Direction is uniformly arranged multiple spray ports 13, and since bottom airborne dust is larger, spray port is arranged on the tube body of bottom, can effectively reduce bottom Portion's airborne dust clears processing convenient for rubbish, and the utility model is simple and practical in structure, facilitates installation, easy to disassemble, can widely popularize It uses.
Certainly, the above description is not intended to limit the present invention, and the utility model is also not limited to the example above, this The those of ordinary skill of technical field, in the essential scope of the utility model, the variations, modifications, additions or substitutions made, all The scope of protection of the utility model should be belonged to.

Claims (4)

1. the quick conveying device of skyscraper rubbish, which is characterized in that include be arranged from top to bottom along external wall of high-rise building it is more The vertical tube body of root and multiple bending tube bodies that garbage transporting channel is formed for connection that the vertical tube body turns round repeatedly, It is equipped with multiple rubbish pour spouts corresponding with floor, the garbage transporting in the rubbish pour spout successively on garbage transporting channel Vias inner walls are equipped with is used to prevent rubbish whereabouts in the garbage transporting channel of top from occurring with what garbage transporting channel was rotatablely connected The baffle of airborne dust is equipped with the rubbish delivery outlet for being delivered to rubbish outside channel, the rubbish in garbage transporting the bottom of the channel The adjacent tube body of delivery outlet is equipped with the spray port for reducing airborne dust.
2. the quick conveying device of skyscraper rubbish according to claim 1, characterized in that the bending tube body includes one The transverse direction for holding the first metal bends being connect with the vertical tube body in top and one end to be connect with the first metal bends other end Tube body, the transverse direction tube body other end connect the vertical tube body of lower part, the rubbish pour spout setting by the second metal bends In on lateral tube body.
3. the quick conveying device of skyscraper rubbish according to claim 1, characterized in that set on the rubbish pour spout It is useful for the door body of closing rubbish pour spout, the hinge for connecting the two is equipped between the door body and rubbish pour spout, It is equipped with the handle for opening door body in door body, the bolt for preventing rubbish from overflowing for closing door body is equipped in handle both sides.
4. the quick conveying device of skyscraper rubbish according to claim 1, characterized in that adjacent along rubbish delivery outlet The short transverse of tube body is uniformly provided with multiple spray ports.
CN201820405451.7U 2018-03-13 2018-03-13 The quick conveying device of skyscraper rubbish Expired - Fee Related CN207934392U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820405451.7U CN207934392U (en) 2018-03-13 2018-03-13 The quick conveying device of skyscraper rubbish

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820405451.7U CN207934392U (en) 2018-03-13 2018-03-13 The quick conveying device of skyscraper rubbish

Publications (1)

Publication Number Publication Date
CN207934392U true CN207934392U (en) 2018-10-02

Family

ID=63655894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820405451.7U Expired - Fee Related CN207934392U (en) 2018-03-13 2018-03-13 The quick conveying device of skyscraper rubbish

Country Status (1)

Country Link
CN (1) CN207934392U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111946023A (en) * 2020-08-12 2020-11-17 鹏程建设集团有限公司 Automatic waste collecting device for building construction
CN115110715A (en) * 2022-06-29 2022-09-27 国网宁夏电力有限公司银川供电公司 Building rubbish discharging equipment for floor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111946023A (en) * 2020-08-12 2020-11-17 鹏程建设集团有限公司 Automatic waste collecting device for building construction
CN115110715A (en) * 2022-06-29 2022-09-27 国网宁夏电力有限公司银川供电公司 Building rubbish discharging equipment for floor

Similar Documents

Publication Publication Date Title
CN208830666U (en) A kind of skyscraper vertical garbage transportation system
CN111749430B (en) Automatic conveying system for construction waste of high-rise building
CN107916765B (en) A kind of construction rubbish conveyer
CN207934392U (en) The quick conveying device of skyscraper rubbish
CN104234388B (en) Garbage chute for high-building construction
CN110295723A (en) A kind of buffer-type construction garbage shaft
CN112576273A (en) Muck transportation system for shield tunneling machine and transportation method thereof
CN207934393U (en) A kind of dust-proof transportation system of skyscraper rubbish
CN207917764U (en) Lane device for skyscraper rubbish quick drain
CN208533965U (en) Building waste clears device in high-building construction floor
CN207776364U (en) The conveyer of construction rubbish can be crushed
CN206707203U (en) Building refuse collection passage
CN107938996A (en) Building waste clears device in a kind of high-building construction floor
CN208347245U (en) A kind of construction site floor refuse collection channel
CN207568138U (en) For the building waste vertical transit system of high-rise building
CN207032786U (en) A kind of atomized dust settling energy dissipating garbage chute
CN211114625U (en) Vertical transport system of building rubbish assembled
CN113233032A (en) Building rubbish conveying and temporary storage device between floors
CN214942027U (en) High-rise building rubbish transfer passage
CN101439868B (en) Method for preventing red slurry from scouring storage yard slope and used hopper
CN207245099U (en) The interim rubbish blanking system of Core Walls Structure
CN210164190U (en) Building site floor rubbish clearance passageway
CN209353632U (en) A kind of super high-rise building utilizes the refuse collection channel of former ventilating shaft structure
CN204098438U (en) A kind of refuse chute for high-building construction
CN216888339U (en) Building rubbish conveying and temporary storage device between floors

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181002

Termination date: 20190313

CF01 Termination of patent right due to non-payment of annual fee