CN205743040U - A kind of integrated form material hoisting platform - Google Patents
A kind of integrated form material hoisting platform Download PDFInfo
- Publication number
- CN205743040U CN205743040U CN201620501618.0U CN201620501618U CN205743040U CN 205743040 U CN205743040 U CN 205743040U CN 201620501618 U CN201620501618 U CN 201620501618U CN 205743040 U CN205743040 U CN 205743040U
- Authority
- CN
- China
- Prior art keywords
- platform
- seat
- guide rail
- wall
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The open a kind of integrated form material hoisting platform of this utility model, relates to the realm of building construction.Described material hoisting platform includes: pulley seat;Guide rail;Promote hanging seat;Electric block hanging seat;Wall-attached supporting seat;Brace;Windrow platform;Operating platform.Described pulley seat, is connected with guide rail by bolt, and pulley assembly is arranged in base, and steel wire rope is connected with electric block by pulley seat one end, and the other end is connected with promoting hanging seat;Described guide rail is coupled together by truss frame for connecting, is arranged on skin by wall-attached supporting seat;Described lifting hanging seat is fixed on skin by through-wall bolt, is used for fixing steel wire rope one end, it is achieved the climbing or decline of material hoisting platform;Described electric block hanging seat is welded on guide rail, is connected with steel wire rope by electric block;On described windrow platform, guardrail board is installed, is attached by brace and bolt with guide rail;Described operating platform, is positioned at below windrow platform, and guide rail is with bolts.
Description
Technical field
This utility model relates to a kind of discharging platform, particularly to one for integrated form material hoisting platform.
Background technology
In recent years, along with developing rapidly of national economy, high level, construction of super highrise building the most widely, match therewith
The construction discharging platform that set uses also gets more and more, more and more important.
Currently used construction discharging platform is typically overhanging unloading platform, uses steel wood mixed form, connects not
Firm, discharging platform bad sealing is close, and by steel wire rope off-load, discharging platform is directly installed on the floor inside balcony or window opening
On, poor stability;Every layer of construction completes to need tower crane cooperation to be lifted on superstructure and reinstalls, and installing/dismounting operation is numerous
Trivial, labor intensity is big, reduces the efficiency of construction.
Utility model content
(1) to solve the technical problem that
The technical problems to be solved in the utility model is: provide a kind of convenient to assemble and disassemble, safe and reliable integration type liter
Fall material platform.
(2) technical scheme
For solving above-mentioned technical problem, the present utility model one integrated form material hoisting platform, including: pulley seat, lead
Rail, promotes hanging seat, electric block hanging seat, wall-attached supporting seat, brace, truss frame for connecting, guardrail board, windrow platform, operating platform.
Described pulley seat, is connected with guide rail by bolt, and pulley assembly is arranged in base, steel wire rope by pulley seat one end with
Electric block connects, and the other end is connected with promoting hanging seat;Described guide rail is coupled together by truss frame for connecting, is pacified by wall-attached supporting seat
It is contained on skin;Described lifting hanging seat is fixed on skin by through-wall bolt, is used for fixing steel wire rope one
End, it is achieved the climbing or decline of material hoisting platform;Described electric block hanging seat is welded on guide rail, by electric block and steel wire
Rope is connected;On described windrow platform, guardrail board is installed, is attached by brace and bolt with guide rail;Described operation
Platform, is positioned at below windrow platform, and guide rail is with bolts.
Preferably, described pulley seat uses shaped steel welding, and pulley seat is provided with two φ 30 holes, is used for installing assembly pulley
Part.Pulley seat is located at guide rail bottom, is connected with guide rail by two M24 high-strength bolts.
Preferably, described guide rail uses I14 section steel manufacture, and two guide rails are connected together by truss frame for connecting, and guide rail passes through
Regulation on wall-attached supporting seat is shored and is connected with wall-attached supporting seat.
Preferably, described lifting hanging seat is shaped steel welding support, is fixed on skin by through-wall bolt.Promote
Hanging seat front end is provided with φ 30 hole, uses bearing pin to be connected with promoting hanging seat by steel wire rope rope sling.
Preferably, described electric block hanging seat is section bar welding support, is arranged on below windrow platform, and weldering is such as right respectively
Require the integrated form material hoisting platform described in 1, it is characterised in that be connected on two side rails.Electric block is adopted with electric block hanging seat
Connect with pillar pulling force sensor.
Preferably, described wall-attached supporting seat is section bar welding support, is fixed on skin by through-wall bolt.Attached wall
Bearing is provided with φ 35, φ 20 hole, is fixed on wall-attached supporting seat by catching device by bearing pin;Guiding Overthrow preventing device is located at attached wall and props up
The front end of seat;Regulation is shored and is located at wall-attached supporting seat top.
Preferably, described brace, use vertical masonry joint electric welded steel pipe to make with T32 bolt.It is located at guardrail board both sides, respectively
With bearing pin, guide rail and windrow platform are coupled together.
Preferably, described truss frame for connecting, use 25 × 25 × 2.5mm rectangular square tube to be welded.Truss frame for connecting is provided with φ
17 holes, use M16 bolt to be coupled together by two guide rails.
Preferably, described guardrail board, use 50 × 50 × 4mm rectangular square tube, expanded metal lath and δ 3mm steel plate to be made.
Guardrail board divides 3, is assembled integrally with bolt and windrow platform.
Preferably, described windrow platform uses channel-section steel, angle steel and checkered steel plate to be welded.Windrow platform is provided with protection
Breast board, guardrail board is with bolts with windrow platform.Windrow platform uses bolt and brace to be connected with guide rail.
(3) beneficial effect
With through-wall bolt (11), wall-attached supporting seat (5) and lifting hanging seat (3) are fixed on skin, simultaneously on ground
On pulley seat (1), guide rail (2), truss frame for connecting (7), operating platform (10) are connected into entirety, utilize building site tower crane to be lifted into
Wall-attached supporting seat (5) place, shores (16) by the regulation on wall-attached supporting seat (5) and guides Overthrow preventing device (17) by guide rail (2) admittedly
Determine to live;On the ground brace (6), guardrail board (8) and windrow platform (9) are assembled integrally, in windrow platform (9) extension
Use steel wire rope snapping respectively at four hoisting rings, four steel wire ropes are merged into a suspension centre, be lifted into by building site tower crane and lead
Rail (2) place, connects into entirety with guide rail (2) with M16 bolt respectively by windrow platform (9) and brace (6), and after connection, structure is such as
Shown in Fig. 1.Then electric block hanging seat (4) place being fixed on guide rail (2) by gravity sensor by electric block (13), is led
Rail (2) lower end is provided with pulley seat (1), and pulley is arranged in pulley seat (1), steel wire rope (14) one end and electric block (13)
Being connected, the other end is fixed in lifting hanging seat (3) through bottom pulley base (1).After installing, carry out load test, full
Foot is supplied to operating personnel and uses after requiring.This utility model novel structure, easy for installation, simple to operate, there is fall arrest dress
Put safe and reliable, there is guiding Overthrow preventing device and can effectively control to expect that platform topples;Prefabrication standardized production, ground once group
Dress, relatively conventional material platform every layer is installed and is saved manually, reduces high-altitude and pacify the operation dangerous matter sources torn open;Capable of circulation reuse, have
Well economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is the integrated form material hoisting platform axonometric chart described in this utility model embodiment;
Fig. 2 is the integrated form material hoisting platform front view described in this utility model embodiment;
Fig. 3 is the integrated form material hoisting platform side view described in this utility model embodiment;
Fig. 4 is joint front view under the integrated form material hoisting platform guide rail described in this utility model embodiment;
Fig. 5 is joint front view on the integrated form material hoisting platform guide rail described in this utility model embodiment;
Fig. 6 is the integrated form material hoisting platform brace front view described in this utility model embodiment;
Fig. 7 is the integrated form material hoisting platform wall-attached supporting seat mounting structure schematic diagram described in this utility model embodiment;
Fig. 8 is that the integrated form material hoisting platform described in this utility model embodiment guides Overthrow preventing device installation enlarged drawing;
Fig. 9 is that the integrated form material hoisting platform described in this utility model embodiment promotes hanging seat mounting structure schematic diagram;
Detailed description of the invention:
Below in conjunction with the accompanying drawings and example, detailed description of the invention of the present utility model is described in further detail.Following reality
Execute example for this utility model is described, but be not limited to scope of the present utility model.
Fig. 1 is that described in this utility model embodiment, integrated form material hoisting platform regulation top bracing mechanism axonometric chart includes: at the bottom of pulley
Seat (1), guide rail (2), lifting hanging seat (3), electric block hanging seat (4), wall-attached supporting seat (5), brace (6), truss frame for connecting (7),
Guardrail board (8), windrow platform (9), operating platform (10).
Fig. 3 is that described in this utility model embodiment, integrated form material hoisting platform guider side view includes: through-wall bolt
(11), hoisting ring (12), electric block (13), steel wire rope (14).
Fig. 7 is that described in this utility model embodiment, integrated form material hoisting platform wall-attached supporting seat mounting structure schematic diagram includes: adjust
Joint is shored (16), guides Overthrow preventing device (17), falling proof device (18).
Fig. 9 is that described in this utility model embodiment, integrated form material hoisting platform lifting hanging seat mounting structure schematic diagram includes: carry
Rise hanging seat (3), through-wall bolt (11), steel wire rope (14).
This integration type material hoisting platform includes: pulley seat (1), guide rail (2), promotes hanging seat (3), electric block hanging seat
(4), wall-attached supporting seat (5), brace (6), truss frame for connecting (7), guardrail board (8), windrow platform (9), operating platform (10).Collection
Accepted way of doing sth material hoisting platform is arranged on skin by wall-attached supporting seat, utilizes self power equipment to drive the lifting of support body
And decline.
Specific works principle is as follows:
With through-wall bolt (11), wall-attached supporting seat (5) and lifting hanging seat (3) are fixed on skin, simultaneously on ground
On pulley seat (1), guide rail (2), truss frame for connecting (7), operating platform (10) are connected into entirety, utilize building site tower crane to be lifted into
Wall-attached supporting seat (5) place, shores (16) by the regulation on wall-attached supporting seat (5) and guides Overthrow preventing device (17) by guide rail (2) admittedly
Determine to live;On the ground brace (6), guardrail board (8) and windrow platform (9) are assembled integrally, in windrow platform (9) extension
Use steel wire rope snapping respectively at four hoisting rings, four steel wire ropes are merged into a suspension centre, be lifted into by building site tower crane and lead
Rail (2) place, connects into entirety with guide rail (2) with M16 bolt respectively by windrow platform (9) and brace (6), and after connection, structure is such as
Shown in Fig. 1.Then electric block hanging seat (4) place being fixed on guide rail (2) by gravity sensor by electric block (13), is led
Rail (2) lower end is provided with pulley seat (1), and pulley is arranged in pulley seat (1), steel wire rope (14) one end and electric block (13)
Being connected, the other end is fixed in lifting hanging seat (3) through bottom pulley base (1).After installing, carry out load test, full
Foot is supplied to operating personnel and uses after requiring.
All items in windrow platform (9) is removed clean by this utility model before promoting, start electricity by controlling end
Dynamic calabash (13) shrinks chain and pulls steel wire rope (14) to shrink simultaneously, drives the whole of discharging platform by electric block (13)
Body climbs.After rising to superstructure plate face height, regulation is shored (16) and pushes up the off-load block (15) being affixed on guide rail (2)
On.Start the loosening chain of electric block (13) and discharge steel wire rope (14) simultaneously, remove and promote hanging seat (3) and through-wall bolt (11),
It is installed to superstructure structure.Remove undermost wall-attached supporting seat (5) and through-wall bolt (11), be installed to the building knot of the superiors
On structure.Repeat above-mentioned flow process after treating superstructure discharging, be repeatedly lifted up.
After the construction discharging of all floors terminates, according to hanging method when installing whole material platform hung and tear open on ground
Carry out parts disintegration.
Claims (10)
1. an integrated form material hoisting platform, it is characterised in that including: pulley seat (1), guide rail (2), promote hanging seat (3), electronic
Calabash hanging seat (4), wall-attached supporting seat (5), brace (6), truss frame for connecting (7), guardrail board (8), windrow platform (9), operation is flat
Platform (10), described pulley seat (1), it is connected with guide rail (2) by M24 bolt, pulley assembly is arranged in pulley seat (1),
Steel wire rope (14) is connected with electric block (13) by pulley seat (1) one end, and the other end is connected with promoting hanging seat (3);Described
Guide rail (1) is coupled together by truss frame for connecting (7), is arranged on skin by wall-attached supporting seat (5);Described lifting hanging seat
(3) it is fixed on skin by through-wall bolt (11), is used for fixing steel wire rope (14) one end, it is achieved climbing of material hoisting platform
Rise or decline;Described electric block hanging seat (4) is welded on guide rail, is connected with steel wire rope (14) by electric block (13);
On described windrow platform (9), guardrail board (8) is installed, is attached by brace (6) and M16 bolt with guide rail (2);Institute
State operating platform (10), be positioned at windrow platform (9) lower section, and guide rail (2) uses M16 bolt to connect.
2. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described pulley seat (1) uses shaped steel welding,
Pulley seat is provided with two φ 30 holes, is used for installing pulley assembly, and pulley seat (1) is located at guide rail (2) bottom, by two
M24 high-strength bolt is connected with guide rail (2).
3. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described guide rail (2) uses I14 section steel manufacture,
Two guide rails are connected together by truss frame for connecting (7), and guide rail (2) shores (16) and attached wall by the regulation on wall-attached supporting seat (5)
Bearing (5) connects.
4. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described lifting hanging seat (3) is shaped steel welding
Frame, is fixed on skin by through-wall bolt (13), promotes hanging seat (3) front end and is provided with φ 30 hole, uses bearing pin by steel
Cord (14) rope sling is connected with promoting hanging seat (3).
5. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described electric block hanging seat (4) is section bar weldering
Connect support, be arranged on windrow platform (9) lower section, be respectively welded on two side rails (2), electric block (13) and electric block
Hanging seat (4) uses gravity sensor to connect.
6. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described wall-attached supporting seat (5) is section bar welding
Frame, is fixed on skin by through-wall bolt (11), is provided with falling proof device (18) and is fixed on attached in wall-attached supporting seat (5)
On wall bearing (5);Guide Overthrow preventing device (17) and be located at the front end of wall-attached supporting seat (5);Regulation is shored (16) and is located at wall-attached supporting seat
(5) top.
7. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described brace (6), uses φ 48 vertical masonry joint electricity
Coiling Welded Pipe makes with T32 bolt, is located at guardrail board (8) both sides, guide rail (2) and windrow platform (9) is connected with bearing pin respectively
Get up.
8. integrated form material hoisting platform as claimed in claim 1, it is characterised in that described windrow platform (9), uses channel-section steel, angle
Steel and checkered steel plate are welded, and windrow platform (9) is provided with guardrail board (8), and guardrail board (8) uses with windrow platform (9)
M16 bolt connects, and windrow platform (8) uses M16 bolt and brace (6) to be connected with guide rail (2).
9. integrated form material hoisting platform as claimed in claim 3, it is characterised in that described truss frame for connecting (7), use 25 × 25 ×
2.5mm rectangular square tube is welded, and truss frame for connecting (7) is provided with φ 17 hole, uses M16 bolt two guide rails (2) to be coupled together.
10. integrated form material hoisting platform as claimed in claim 8, it is characterised in that described guardrail board (8), uses 50 × 50
× 4mm rectangular square tube, expanded metal lath and δ 3mm steel plate are made, and guardrail board (8) is divided into 3, with M16 bolt and windrow platform
(9) it is assembled integrally.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620501618.0U CN205743040U (en) | 2016-05-19 | 2016-05-19 | A kind of integrated form material hoisting platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620501618.0U CN205743040U (en) | 2016-05-19 | 2016-05-19 | A kind of integrated form material hoisting platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205743040U true CN205743040U (en) | 2016-11-30 |
Family
ID=57362216
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620501618.0U Active CN205743040U (en) | 2016-05-19 | 2016-05-19 | A kind of integrated form material hoisting platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205743040U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108661181A (en) * | 2017-12-07 | 2018-10-16 | 扬州通利冷藏集装箱有限公司 | A kind of container |
CN111519754A (en) * | 2020-05-08 | 2020-08-11 | 黄炳江 | Detachable green terrace for multi-storey building and manufacturing method thereof |
CN114197851A (en) * | 2021-12-14 | 2022-03-18 | 济南一建集团绿色建筑产业有限公司 | Climbing frame body system with safety protection mechanism |
CN114204161A (en) * | 2021-12-13 | 2022-03-18 | 国网山东省电力公司禹城市供电公司 | Novel uninterrupted power source for transformer substation |
-
2016
- 2016-05-19 CN CN201620501618.0U patent/CN205743040U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108661181A (en) * | 2017-12-07 | 2018-10-16 | 扬州通利冷藏集装箱有限公司 | A kind of container |
CN111519754A (en) * | 2020-05-08 | 2020-08-11 | 黄炳江 | Detachable green terrace for multi-storey building and manufacturing method thereof |
CN114204161A (en) * | 2021-12-13 | 2022-03-18 | 国网山东省电力公司禹城市供电公司 | Novel uninterrupted power source for transformer substation |
CN114197851A (en) * | 2021-12-14 | 2022-03-18 | 济南一建集团绿色建筑产业有限公司 | Climbing frame body system with safety protection mechanism |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208518310U (en) | All steel type attachment type raise scaffold | |
CN205743040U (en) | A kind of integrated form material hoisting platform | |
CN106065661A (en) | Large span unsettled steel corridor construction engineering method | |
CN207144449U (en) | A kind of hoistway operation platform | |
CN201598820U (en) | Single point suspension external hanging bracket | |
CN102444271B (en) | Suspended scaffolding | |
CN204850497U (en) | Promote no lower hem material platform | |
CN213418441U (en) | Safety protection and operation platform for light production well | |
CN106904538A (en) | A kind of installation method of cucurbit gantry crane | |
CN102287045B (en) | Square steel tube lifting outside scaffold | |
CN210460016U (en) | Integrated form single power lift material platform | |
CN112177309A (en) | Assembled protection platform used in building elevator shaft | |
CN108946542A (en) | A kind of small gun carriage and its construction method | |
CN208686053U (en) | A kind of elevator well sizing climbing platforms device | |
CN205076637U (en) | Derrick material hoist | |
CN205000656U (en) | From over -and -under type material cycling platform | |
CN204238537U (en) | A kind of elevated hoistway operation platform | |
CN202718380U (en) | Hydraulic climbing frame for construction of high-rise building | |
CN202767493U (en) | Lifting scaffold of high-rise balcony | |
CN205955160U (en) | Antiskid lattice formula elevartor shaft removes operation platform | |
CN205873594U (en) | Special construction elevator of cooling tower section of thick bamboo wall | |
CN205577451U (en) | Instrument formula protection frame suitable for assemble integral concrete horizontal element | |
CN105060124B (en) | Intra-frame portal crane system and hoisting use method thereof | |
CN209367692U (en) | It is a kind of to rise gantry type two-way lifter device certainly | |
CN204357138U (en) | Simple steel structure lifting upending frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 276017 Lake East Road, Luozhuang District, Linyi, Shandong Province, No. 18 Patentee after: Shandong Tianyuan Engineering Technology Co., Ltd. Address before: 276017 Lake East Road, Luozhuang District, Linyi, Shandong Province, No. 18 Patentee before: SHANDONG TIANYUAN HOISTING MACHINERY INSTALLATION CO., LTD. |