CN205577381U - Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting - Google Patents

Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting Download PDF

Info

Publication number
CN205577381U
CN205577381U CN201620304030.6U CN201620304030U CN205577381U CN 205577381 U CN205577381 U CN 205577381U CN 201620304030 U CN201620304030 U CN 201620304030U CN 205577381 U CN205577381 U CN 205577381U
Authority
CN
China
Prior art keywords
platform
girder
enough
meet
landing slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620304030.6U
Other languages
Chinese (zh)
Inventor
李之伟
刘得志
苏新河
宫兴华
毛见平
石志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620304030.6U priority Critical patent/CN205577381U/en
Application granted granted Critical
Publication of CN205577381U publication Critical patent/CN205577381U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to an overhanging type platform field of unloading in the building engineering construction, in particular to can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting. The trilateral welding of equidistance has the girder bracket on the stage mechanism's of this platform the girder, and the secondary beam is connected perpendicularly on the girder bracket through upper and lower each two high strength bolt, and the upper portion of landing slab, lower part are provided with rib, vertical fossil fragments respectively, and the post leg of four angles end lower parts of landing slab is placed in on the stopper of girder, protection machanism's protection pole setting equipartition in the both sides and the platform mouth department of landing slab, the perpendicular equipartition of horizontal railing is abound with close mesh safety net on each fender rod in each protection pole setting, and gravity sensor is arranged in the stopper, the rings of mechanism of encorbelmenting are connected in the both sides of girder, and wire rope connects between tower built -in fitting and rings, unload the platform collar extension of platform a little more than the internal orifice. The utility model discloses the installation is dismantled simple swiftly, and the transportation turnover of being convenient for is used, appears in the use overloading and accessible time reports to the police, prevents the phenomenon that overloads.

Description

Assembled overload warning overhanging unloading platform can be had enough to meet the need
Technical field
This utility model relates to overhanging type discharging platform field in building engineering construction, can have enough to meet the need spelling particularly to one Formula overload warning overhanging unloading platform.
Background technology
Along with high building project development rapidly, set up overhanging unloading platform and have also been obtained and be widely applied.How to protect Card discharging platform bearing capacity, weld strength and on-the-spot spelling are convenient, are urgent problems.At high-building construction During, overhanging type discharging platform serves vital effect in material, material tool, the transmission of building waste are transported, but The on-the-spot integral type discharging platform processed being traditional also exists the defect transporting difference inconvenient, revolving;Traditional discharging platform In work progress, there is no concrete weight-measuring device due to only weight limit sign, workman in practical operation with being difficult to directly judgement Go out discharging platform to have overloaded, thus cause great potential safety hazard, cause thing because the discharging platform caused that overloads falls Therefore example too numerous to enumerate.
Utility model content
For solving the problems referred to above, this utility model provides one can have enough to meet the need assembled overload warning overhanging unloading platform, this Planting overhanging unloading platform installing/dismounting simple and fast, only need to be linked in sequence by several parts fastens, it is simple to transport and week Turn and use, in use occur overload condition can and alarm, thus prevent the appearance of overloading.
For achieving the above object, the technical solution adopted in the utility model is as follows: can have enough to meet the need assembled overload warning and encorbelment Discharging platform, including platform mechanism, protection mechanism and mechanism of encorbelmenting, it is characterised in that: platform mechanism includes girder, secondary beam, master Beam bracket, landing slab, on girder, equidistant three faces are welded with girder bracket, and secondary beam is vertically connected by the most each two high-strength bolts On girder bracket, the top of landing slab, bottom are respectively arranged with lateral keel, longitudinal Os Draconis, under four angle ends of landing slab The post lower limb in portion is placed on the stop of girder, limits its motion by angle steel outside four angle ends of landing slab;Protection mechanism bag Including protective upright rod, horizontal rails, safety net, gravity sensor, protective upright rod is distributed at both sides and the platform mouth of landing slab, anti- The lower end protecting vertical rod is bolted with two edge-beams, and horizontal rails is vertically distributed on each protective upright rod, at each fender rod On be abound with close mesh safety net, gravity sensor is positioned in stop, and gravity sensor is connected with check weighing display screen;Encorbelment mechanism bag Enclosing wire rope, suspension ring, suspension ring are connected to the both sides of girder, and steel wire rope is connected between high building built-in fitting and suspension ring, every steel wire Rope is provided with no less than 3 steel wire rope ram's horns;The platform collar extension of discharging platform is slightly above internal orifice.
Described girder uses 16~20# I-steel.
A length of the 150~300mm of described girder bracket, the distance that arranges of girder bracket (3) is 300~600mm.
Described secondary beam uses 12~18# channel-section steels, and landing slab uses 3~8mm steel plates.
The platform collar extension of described discharging platform is higher than internal orifice 10~50mm.
Described lateral keel uses anti-slip steel, longitudinal Os Draconis to use square steel.
The height of described angle steel is 50~150mm.
Described protective upright rod square steel tube, the height of protective upright rod is 1~1.5m.
The mesh number of described safety net is 800-1200 mesh.
The quantity of described every side steel wire rope is more than 2, and specification is more than 216#, the company between steel wire rope and discharging platform The place of connecing arranges rubber blanket.
This utility model is compared conventional discharging platform and is had the advantage that
1, detachably transport, increase and recycle number of times, reduce transport number of times, reduce cost;
2, it is bolted, on the premise of proof strength, reduces the working time;
3, check weighing system can effectively ensure discharging platform security performance.
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present utility model;
Fig. 2 is the schematic diagram that platform mechanism of the present utility model assembles with protection mechanism;
Fig. 3 is the schematic diagram of landing slab of the present utility model;
Fig. 4 is schematic diagram at divider node of the present utility model;
Fig. 5 is schematic diagram at bracket node of the present utility model;
Fig. 6 is schematic diagram at angle steel node of the present utility model;
Fig. 7 is the schematic diagram of guard rail of the present utility model and landing slab junction;
In figure: 1-girder, 2-secondary beam, 3-girder bracket, 4-landing slab, 5-stop, 6-angle steel, 7-protective upright rod, 8- Horizontal rails, 9-safety net, 10-steel wire rope, 11-suspension ring, 12-gravity sensor.
Detailed description of the invention
Below in conjunction with embodiment, this utility model is described in detail:
Embodiment 1
As shown in Fig. 1-Fig. 7, assembled overload warning overhanging unloading platform can be had enough to meet the need, including platform mechanism, protection mechanism With mechanism of encorbelmenting.
Platform mechanism includes girder 1, secondary beam 2, girder bracket 3, landing slab 4, and girder 1 uses 16# I-steel, on girder 1 Being welded with girder bracket 3 every equidistant three faces of 300mm, a length of 150mm of girder bracket 3, secondary beam 2 uses 12# channel-section steel, secondary beam 2 are vertically connected on girder bracket 3 by the most each two high-strength bolts, and landing slab 4 uses 3mm steel plate, landing slab 4 upper Portion, bottom are respectively arranged with lateral keel, longitudinal Os Draconis, and lateral keel uses anti-slip steel, longitudinal Os Draconis to use square steel, landing slab The post lower limb of the end bottom, four angles of 4 is placed on the stop 5 of girder 1, and passing through height outside four angle ends of landing slab 4 is 50mm Angle steel 6 limit its motion;
Protection mechanism includes protective upright rod 7, horizontal rails 8, safety net 9, gravity sensor 12, protective upright rod 7 side of employing Steel pipe, the height of protective upright rod 7 is 1m, and protective upright rod 7 is distributed at both sides and the platform mouth of landing slab 4, protective upright rod 7 times End is bolted with two edge-beams 1, and horizontal rails 8 is vertically distributed on each protective upright rod 7, is abound with mesh on each fender rod Number is the safety net 9 of 800 mesh, and gravity sensor 12 is positioned in stop 5, and gravity sensor 12 is connected with check weighing display screen;
Mechanism of encorbelmenting includes steel wire rope 10, suspension ring 11, and suspension ring 11 are connected to the both sides of girder 1, and steel wire rope 10 is connected to tower Between building built-in fitting and suspension ring 11, the quantity of every side steel wire rope 10 is 2, and specification is 20#, and every steel wire rope 10 is provided with 3 Steel wire rope ram's horn, the junction between steel wire rope 10 and discharging platform arranges rubber blanket;The platform collar extension of discharging platform is slightly above Internal orifice 10mm.
Before discharging platform feeding, discharging platform is shown and carries out return-to-zero, reading to gravity sensor in time during shipment Number is checked, if overloading;Or after being provided directly as overloading weight, when overweight, send alarm.
Embodiment 2
Had enough to meet the need assembled overload warning overhanging unloading platform Each part described in the present embodiment and annexation The most in the same manner as in Example 1, different technical parameters is:
1) girder 1 uses 18# I-steel;
2) girder bracket 3 equidistantly it is welded with every 450mm on girder 1;
3) a length of 225mm of girder bracket 3;
4) secondary beam 2 uses 16# channel-section steel;
5) landing slab 4 uses 5mm steel plate;
6) height of angle steel 6 is 100mm;
7) height of protective upright rod 7 is 1.2m;
8) the mesh number of safety net 9 is 1000 mesh;
9) quantity of every side steel wire rope 10 is 3, and specification is 18#;
10) every steel wire rope 10 is provided with 4 steel wire rope ram's horns;
11) the platform collar extension of discharging platform is slightly above internal orifice 30mm.
Embodiment 3
Had enough to meet the need assembled overload warning overhanging unloading platform Each part described in the present embodiment and annexation All the most identical with embodiment 1, embodiment 2, different technical parameters is:
1) girder 1 uses 20# I-steel;
2) girder bracket 3 equidistantly it is welded with every 600mm on girder 1;
3) a length of 300mm of girder bracket 3;
4) secondary beam 2 uses 18# channel-section steel;
5) landing slab 4 uses 8mm steel plate;
6) height of angle steel 6 is 150mm;
7) height of protective upright rod 7 is 1.5m;
8) the mesh number of safety net 9 is 1200 mesh;
9) quantity of every side steel wire rope 10 is 4, and specification is 16#;
10) every steel wire rope 10 is provided with 5 steel wire rope ram's horns;
11) the platform collar extension of discharging platform is slightly above internal orifice 50mm.

Claims (10)

1. can have enough to meet the need assembled overload warning overhanging unloading platform, including platform mechanism, protection mechanism and mechanism of encorbelmenting, its feature It is: platform mechanism includes girder (1), secondary beam (2), girder bracket (3), landing slab (4), upper equidistant three welding of girder (1) Having girder bracket (3), secondary beam (2) is vertically connected on girder bracket (3) by the most each two high-strength bolts, landing slab (4) Top, bottom be respectively arranged with lateral keel, longitudinal Os Draconis, the post lower limb of the end bottom, four angles of landing slab (4) is placed in girder (1), on stop (5), outside four angle ends of landing slab (4), its motion is limited by angle steel (6);Protection mechanism includes preventing Protecting vertical rod (7), horizontal rails (8), safety net (9), gravity sensor (12), protective upright rod (7) is distributed in the two of landing slab (4) At side and platform mouth, the lower end of protective upright rod (7) is bolted with two edge-beams (1), and horizontal rails (8) is vertically distributed in On each protective upright rod (7), being abound with close mesh safety net (9) on each fender rod, gravity sensor (12) is positioned in stop (5), Gravity sensor (12) is connected with check weighing display screen;Mechanism of encorbelmenting includes steel wire rope (10), suspension ring (11), and suspension ring (11) are connected to The both sides of girder (1), steel wire rope (10) is connected between high building built-in fitting and suspension ring (11), and every steel wire rope (10) is provided with not Less than 3 steel wire rope ram's horns;The platform collar extension of discharging platform is slightly above internal orifice.
The most according to claim 1 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described girder (1) 16~20# I-steel are used.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described A length of the 150~300mm of girder bracket (3), the distance that arranges of girder bracket (3) is 300~600mm.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described Secondary beam (2) uses 12~18# channel-section steels, and landing slab (4) uses 3~8mm steel plates.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described The platform collar extension of discharging platform is higher than internal orifice 10~50mm.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described Lateral keel uses anti-slip steel, longitudinal Os Draconis to use square steel.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described The height of angle steel (6) is 50~150mm.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described Protective upright rod (7) uses square steel tube, and the height of protective upright rod (7) is 1~1.5m.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described The mesh number of safety net (9) is 800-1200 mesh.
The most according to claim 1 and 2 have enough to meet the need assembled overload warning overhanging unloading platform, it is characterised in that: described The quantity of every side steel wire rope (10) is more than 2, and specification is more than 16#, the junction between steel wire rope (10) and discharging platform Rubber blanket is set.
CN201620304030.6U 2016-04-13 2016-04-13 Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting Expired - Fee Related CN205577381U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620304030.6U CN205577381U (en) 2016-04-13 2016-04-13 Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620304030.6U CN205577381U (en) 2016-04-13 2016-04-13 Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting

Publications (1)

Publication Number Publication Date
CN205577381U true CN205577381U (en) 2016-09-14

Family

ID=56865708

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620304030.6U Expired - Fee Related CN205577381U (en) 2016-04-13 2016-04-13 Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting

Country Status (1)

Country Link
CN (1) CN205577381U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812294A (en) * 2016-12-14 2017-06-09 上海建工集团股份有限公司 The intelligent bracket system and its installation and application of integral steel platform
CN107152169A (en) * 2017-07-07 2017-09-12 中建二局第二建筑工程有限公司华东分公司 Overhanging unloading platform
CN107165427A (en) * 2017-06-28 2017-09-15 中国冶集团有限公司 A kind of intelligent overhanging unloading platform
CN107386662A (en) * 2017-08-29 2017-11-24 四川省第十五建筑有限公司 Construction lift tool formula is encorbelmented escape way
CN108301630A (en) * 2017-12-30 2018-07-20 中建三局第建设工程有限责任公司 A kind of turnable assembled protection shed device and its application method
CN109024885A (en) * 2018-06-25 2018-12-18 安徽海螺建材设计研究院有限责任公司 A kind of conveying gallery security structure
CN109457980A (en) * 2018-12-11 2019-03-12 上海建工五建集团有限公司 A kind of installation method of bracket device and overhanging unloading platform
CN111441568A (en) * 2020-04-08 2020-07-24 台州宏丰建设有限公司 Hanging basket for high-altitude operation in building engineering
CN112196248A (en) * 2020-09-25 2021-01-08 昆山市经协建筑装璜有限责任公司 Cantilever scaffold system and construction method thereof
CN114541462A (en) * 2022-03-10 2022-05-27 长江勘测规划设计研究有限责任公司 Offshore wind power foundation outer platform and manufacturing and mounting method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812294A (en) * 2016-12-14 2017-06-09 上海建工集团股份有限公司 The intelligent bracket system and its installation and application of integral steel platform
CN107165427A (en) * 2017-06-28 2017-09-15 中国冶集团有限公司 A kind of intelligent overhanging unloading platform
CN107152169A (en) * 2017-07-07 2017-09-12 中建二局第二建筑工程有限公司华东分公司 Overhanging unloading platform
CN107386662A (en) * 2017-08-29 2017-11-24 四川省第十五建筑有限公司 Construction lift tool formula is encorbelmented escape way
CN108301630A (en) * 2017-12-30 2018-07-20 中建三局第建设工程有限责任公司 A kind of turnable assembled protection shed device and its application method
CN109024885A (en) * 2018-06-25 2018-12-18 安徽海螺建材设计研究院有限责任公司 A kind of conveying gallery security structure
CN109457980A (en) * 2018-12-11 2019-03-12 上海建工五建集团有限公司 A kind of installation method of bracket device and overhanging unloading platform
WO2020119068A1 (en) * 2018-12-11 2020-06-18 上海建工五建集团有限公司 Support device and method for mounting cantilevered material unloading platform
CN111441568A (en) * 2020-04-08 2020-07-24 台州宏丰建设有限公司 Hanging basket for high-altitude operation in building engineering
CN111441568B (en) * 2020-04-08 2021-07-27 台州宏丰建设有限公司 Hanging basket for high-altitude operation in building engineering
CN112196248A (en) * 2020-09-25 2021-01-08 昆山市经协建筑装璜有限责任公司 Cantilever scaffold system and construction method thereof
CN114541462A (en) * 2022-03-10 2022-05-27 长江勘测规划设计研究有限责任公司 Offshore wind power foundation outer platform and manufacturing and mounting method

Similar Documents

Publication Publication Date Title
CN205577381U (en) Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting
CN204418022U (en) Full bolt connects assembled tool type steel pipe post pylon
CN107165062A (en) A kind of method for removing Existing Railway Line gate-type pier capping beam protecting canopy frame
CN201420385Y (en) Overhanging type unloading platform for building construction
CN105603884A (en) Safety protection platform for bridge cap beam construction
CN204745416U (en) Railway landing stage safety belt lift kits
CN104692261A (en) Symmetrical dismounting construction method for attachment device of tower crane
Cimer et al. Control of major-accidents involving dangerous substances relating to combined terminals
CN103967263A (en) Novel hydraulic automatic climbing discharging platform
CN104213511B (en) A kind of bridge construction platform structure and building method thereof
CN103523665B (en) A kind of transport device and method of high pedestal jib crane
CN205838325U (en) Fabricated construction superimposed sheet string hangs construction special hanger
CN208734101U (en) A kind of high-building construction overhanging unloading platform device
CN209280115U (en) A kind of dynamic weighing device for vehicle
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN216616897U (en) Overload alarm type overhanging discharging platform
CN206706580U (en) A kind of guardrail template for being easy to Fast Installation to dismantle
CN205000659U (en) Discharging platform
CN203782582U (en) Device used for mounting bridge crash barrier
CN203020404U (en) Vehicle with operating platform
CN210858055U (en) Convenient type construction platform of unloading
CN204571302U (en) A kind of assembling discharging platform with weighing device
CN204098493U (en) The dismantled and assembled input and output material movable platform of a kind of modular for building
CN204162999U (en) A kind of bridge construction platform structure
CN202831668U (en) Combined type high attitude falling buffering and protective device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

CF01 Termination of patent right due to non-payment of annual fee