CN208734101U - A kind of high-building construction overhanging unloading platform device - Google Patents

A kind of high-building construction overhanging unloading platform device Download PDF

Info

Publication number
CN208734101U
CN208734101U CN201821215645.7U CN201821215645U CN208734101U CN 208734101 U CN208734101 U CN 208734101U CN 201821215645 U CN201821215645 U CN 201821215645U CN 208734101 U CN208734101 U CN 208734101U
Authority
CN
China
Prior art keywords
girder
weighing
weighing plate
anchor bolt
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821215645.7U
Other languages
Chinese (zh)
Inventor
赵新龙
张秀芬
杨金灿
孙虎跃
李江平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Jian Jian Thirteenth Construction Co Ltd
Original Assignee
Yunnan Jian Jian Thirteenth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Jian Jian Thirteenth Construction Co Ltd filed Critical Yunnan Jian Jian Thirteenth Construction Co Ltd
Priority to CN201821215645.7U priority Critical patent/CN208734101U/en
Application granted granted Critical
Publication of CN208734101U publication Critical patent/CN208734101U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of high-building construction overhanging unloading platform devices, including floor plates, brace and weighing plate top frame, girder is provided with above the floor plates, and U-shaped anchor bolt is fixed on the left of girder, L-type anchor bolt is fixed at the girder and the side bar of floor plates, and the lower right of L-type anchor bolt is equipped with snap-gauge, connecting plate is provided with above the girder, and connecting plate is fixedly arranged above secondary beam, the brace is installed on the upper left side of connecting plate, and weighing plate bottom frame is provided with above brace, weighing sensor is installed above the weighing plate bottom frame, and sideboard is fixed on the outside of weighing plate bottom frame, the weighing plate top frame is set to the top of weighing sensor, and the upper right of weighing plate top frame is equipped with alarm lamp, the weighing plate top frame is fixedly arranged above steel plate.The high-building construction overhanging unloading platform device is provided with the weight of material that weight display screen is convenient for worker's observation platform, avoids the occurrence of overload scene.

Description

A kind of high-building construction overhanging unloading platform device
Technical field
The utility model relates to construction discharging platform technical field, specially a kind of high-building construction overhangs discharging Stage apparatus.
Background technique
Discharging platform is that various provisional stations and crosshead are often set up in construction site, can be carried out various masonry finishings It in general can be within certain duration for carrying material, and in the framework type for wherein carrying out various operations with the operations such as painting Platform, referred to as operating platform.It is a variety of that operating platform is divided into movable operation platform, console mode and overhanging type operating platform, It can be referred to as transfer platform.
Existing overhanging unloading platform is done interior bed board, railing using the wooden scaffold board and is set up simultaneously using the shelf pipe of construction site It is gone along with sb. to guard him with close mesh safety net or waste and old timber layer plate, stability is poor and load bearing effect is weaker, and components are easy corrosion, and constructor Member can not accurately grasp the weight of the preloading of platform, be easy overload generation safety accident and assembling parts mostly use welding, tear open Dress is inconvenient, is unfavorable for being used in turn, for this purpose, it is proposed that a kind of high-building construction overhanging unloading platform device.
Utility model content
The purpose of this utility model is to provide a kind of high-building construction overhanging unloading platform devices, to solve above-mentioned back The overhanging unloading platform proposed in scape technology is done interior bed board, railing using the wooden scaffold board and is set up simultaneously using the shelf pipe of construction site It is gone along with sb. to guard him with close mesh safety net or waste and old timber layer plate, stability is poor and load bearing effect is weaker, and components are easy corrosion, and constructor Member can not accurately grasp the weight of the preloading of platform, be easy overload generation safety accident and assembling parts mostly use welding, tear open Dress is inconvenient, is unfavorable for the problem of being used in turn.
To achieve the above object, the utility model provides the following technical solutions: a kind of high-building construction overhanging discharging is flat Platform device, including floor plates, brace and weighing plate top frame are provided with girder, and the left side of girder above the floor plates It is fixed with U-shaped anchor bolt, is fixed with L-type anchor bolt at the side bar of the girder and floor plates, and the lower right of L-type anchor bolt is equipped with card Plate, be provided with connecting plate above the girder, and connecting plate is fixedly arranged above secondary beam, and the brace is installed on connecting plate Upper left side, and be provided with weighing plate bottom frame above brace, weighing sensor be installed above the weighing plate bottom frame, And sideboard is fixed on the outside of weighing plate bottom frame, the weighing plate top frame is set to the top of weighing sensor, and weighing plate top The upper right of frame is equipped with alarm lamp, and the weighing plate top frame is fixedly arranged above steel plate, and the upper left installation of steel plate There is weight display screen, the bottom outside of the girder is welded with steel cable hanging point, and is provided with wirerope above steel cable hanging point, institute The middle lower section for stating wirerope is fixed with flower basket bolt, and hanging ring is equipped at the top of wirerope, the outside setting of the connecting plate There is aperture, the two sides up and down of the secondary beam are mounted on secondary beam connecting plate, and the two sides of secondary beam connecting plate are fixed with connection bolt, Nut is installed above the U-shaped anchor bolt, and is fixed with hard-wood wedge on the inside of U-shaped anchor bolt, the top setting of the hard-wood wedge There is rubber mat, and is fixed with reinforcing rib below hard-wood wedge.
Preferably, perpendicular shape structure between the secondary beam and girder, and secondary beam passes through structure between connection bolt and girder At detachable structure.
It preferably, is in parallel shape structure between the brace, and the central axes between brace about girder are symmetrical.
Preferably, the rectangular structure of weighing plate top frame, and the symmetrical centre of weighing plate top frame and weighing plate bottom frame Symmetrical centre be overlapped.
Preferably, between the steel plate and weighing plate top frame for welding, and steel plate with a thickness of 3cm.
Preferably, the reinforcing rib is provided with four groups, and the vertical centerline between reinforcing rib about U-shaped anchor bolt is opposite Claim.
Compared with prior art, the utility model has the beneficial effects that the high-building construction overhanging unloading platform device It is provided with the weight of material that weight display screen is convenient for worker's observation platform, avoids the occurrence of overload scene, alarm lamp can be in platform Heap loading capacity is more than limit for tonnage using flashing when weight and song is warned, and obtains worker's violation operation in time convenient for field pipes personnel Information is conducive to prevent its unsafe behavior, avoids many construction safety accidents, girder and secondary beam mutually solid by connection bolt Surely it is combined convenient for on-site consolidation, so that the mutual connection of the two, clinching are more easy to be reliable, brace is convenient for secondary beam and master Support and fixed effect are played between beam, reinforces the bearing capacity of girder, so that platform structure rigidity, intensity, stability meet The bearing capacity requirement of safe handling, and have certain safe clearance, the aperture of connecting plate side is easily installed bolt, so that Construction and installation speed is fast, operational safety is high, can be by discharging platform Integral lifting to ground loose bolts, structure after construction Part number storage is stacked to be used to next time, is conducive to improve the rate that is used in turn, U-shaped anchor bolt and L-type anchor bolt convenient for anchoring overhanging master Beam, so that anchor bolt is firm, hard-wood wedge and rubber mat play the tight effect that serves as a contrast, and nut hangs convenient for reinforcing U-shaped anchor bolt and L-type anchor bolt Ring and steel cable hanging point are convenient for drawknot to tighten the wirerope of oblique pull, stretch tight so that wirerope is straight for fixing wirerope, flower basket bolt Tightly, be conducive to play the role of reinforcing to outrigger platform.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model secondary beam structural schematic diagram;
Fig. 3 is the U-shaped anchor bolt structural schematic diagram of the utility model.
In figure: 1, floor plates;2, girder;3, U-shaped anchor bolt;4, L-type anchor bolt;5, snap-gauge;6, connecting plate;7, secondary beam;8, tiltedly Pull rod;9, weighing plate bottom frame;10, weighing sensor;11, sideboard;12, alarm lamp;13, weighing plate top frame;14, steel plate;15, flower Basket bolt;16, wirerope;17, hanging ring;18, steel cable hanging point;19, weight display screen;20, aperture;21, secondary beam connecting plate;22, Connect bolt;23, nut;24, rubber mat;25, hard-wood wedge;26, reinforcing rib.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of high-building construction overhanging unloading platform dress It sets, including floor plates 1, girder 2, U-shaped anchor bolt 3, L-type anchor bolt 4, snap-gauge 5, connecting plate 6, secondary beam 7, brace 8, weighing plate bottom frame 9, weighing sensor 10, sideboard 11, alarm lamp 12, weighing plate top frame 13, steel plate 14, flower basket bolt 15, wirerope 16, hanging ring 17, steel cable hanging point 18, weight display screen 19, aperture 20, secondary beam connecting plate 21, connection bolt 22, nut 23, rubber mat 24, hardwood Wedge 25 and reinforcing rib 26, the top of floor plates 1 is provided with girder 2, and the left side of girder 2 is fixed with U-shaped anchor bolt 3, girder 2 and building L-type anchor bolt 4 is fixed at the side bar of laminate 1, and the lower right of L-type anchor bolt 4 is equipped with snap-gauge 5, the top of girder 2 is provided with company Fishplate bar 6, and connecting plate 6 is fixedly arranged above secondary beam 7, perpendicular shape structure between secondary beam 7 and girder 2, and secondary beam 7 passes through connection Detachable structure is constituted between bolt 22 and girder 2, perpendicular shape structure makes weighing plate bottom frame 9 can between secondary beam 7 and girder 2 Steady to install, secondary beam 7 is by constituting detachable structure between connection bolt 22 and girder 2, convenient for tearing open for secondary beam 7 and girder 2 Dress, facilitates recycling, brace 8 is installed on the upper left side of connecting plate 6, and the top of brace 8 is provided with weighing plate bottom frame 9, it is in parallel shape structure between brace 8, and the central axes between brace 8 about girder 2 are symmetrical, are between brace 8 Parallel shape structure is convenient for reinforcing the bearing capacity of girder 2, brace to support and fixed effect is played between secondary beam 7 and girder 2 The symmetrical support force for making brace 8 in central axes between 8 about girder 2 is more balanced, the top installation of weighing plate bottom frame 9 There is weighing sensor 10, and the outside of weighing plate bottom frame 9 is fixed with sideboard 11, weighing plate top frame 13 is set to weighing sensor 10 Top, and the upper right of weighing plate top frame 13 is equipped with alarm lamp 12, the rectangular structure of weighing plate top frame 13, and weighs The symmetrical centre of plate top frame 13 is overlapped with the symmetrical centre of weighing plate bottom frame 9, and the rectangular structure of weighing plate top frame 13 is convenient for Material is placed thereon, and weighing plate top frame 13 is fixedly arranged above steel plate 14, and the upper left of steel plate 14 is equipped with weight and shows Screen 19 is welding between steel plate 14 and weighing plate top frame 13, and steel plate 14 with a thickness of 3cm, steel plate 14 and weighing plate top frame 13 Between for welding so that the fixation of steel plate 14 is more firm, steel plate 14 makes steel plate 14 have good carrying with a thickness of 3cm Property, the bottom outside of girder 2 is welded with steel cable hanging point 18, and the top of steel cable hanging point 18 is provided with wirerope 16, wirerope 16 Middle lower section be fixed with flower basket bolt 15, and the top of wirerope 16 is equipped with hanging ring 17, and the outside of connecting plate 6 is provided with aperture 20, the two sides up and down of secondary beam 7 are mounted on secondary beam connecting plate 21, and the two sides of secondary beam connecting plate 21 are fixed with connection bolt 22, U The top of type anchor bolt 3 is equipped with nut 23, and the inside of U-shaped anchor bolt 3 is fixed with hard-wood wedge 25, and the top of hard-wood wedge 25 is provided with Rubber mat 24, and the lower section of hard-wood wedge 25 is fixed with reinforcing rib 26, reinforcing rib 26 is provided with four groups, and about U between reinforcing rib 26 The vertical centerline of type anchor bolt 3 is symmetrical, and reinforcing rib 26, which is provided with four groups, can increase intensity and rigidity, closes between reinforcing rib 26 It can play the role of limit to U-shaped anchor bolt 3 U-shaped anchor bolt 3 is avoided to generate displacement in the vertical centerline of U-shaped anchor bolt 3 is symmetrical.
Working principle: U-shaped anchor bolt is used by girder 2 first for this kind of high-building construction overhanging unloading platform device 3 anchors are pressed in floor plates 1, are then filled in hard-wood wedge 25 in the inside of U-shaped anchor bolt 3 and are served as a contrast tightly, and add in the upper end of hard-wood wedge 25 Entering rubber mat 24, further lining is tight, is then fastened on the top of U-shaped anchor bolt 3 using nut 23, girder 2 is similarly then used L 4 anchor of type anchor bolt is pressed on the structure side bar of floor plates 1, subsequently will be passed through secondary beam connecting plate 21 between secondary beam 7 and girder 2, be connected Connecting bolt 22 is fixed up, then brace 8 is connected by connecting plate 6 and bolt with girder 2 and secondary beam 7, then will block Plate 11 is connected by screw bolts with platform, and the steel wire that steel cable hanging point 18 hangs oblique pull is subsequently arranged on the outside of platform overhanging girder 2 Rope 16, the wirerope 16 of oblique pull is tightened with 15 drawknot of flower basket bolt, is tightened so that wirerope 16 is straight, while in structure top The hanging ring 17 of pre-buried wirerope 16 on 1 structure side bar of floor plates or abutment wall, then by the upper section drawknot of platform wirerope 16 in hanging ring On 17, then the setting weighing platen on the secondary beam of platform 7, successively installs weighing plate bottom frame 9, weighing sensor 10 and claims Weight plate top frame 13, and need to be paved with the steel plate 14 of 3cm thickness in the top of weighing plate top frame 13, and make steel plate 14 and weighing Plate top frame 13 weld it is smooth, discharging platform composition each block assembly surface can be set derusting anti-corrosive japanning, avoid use process Middle generation corrosion phenomena then installs weight display screen 19 on the upper left side of weighing plate top frame 13, and makes weight display screen 19 It is connected by signal transmssion line with weighing sensor 10, alarm lamp finally is set in the outermost end edge of overhanging unloading platform 12, once the practical preloading of platform is more than the specified preloading numerical value of platform, alarm lamp 12 flashes song immediately, and field pipes personnel can be with The information of worker's violation operation is obtained in time, and prevents its unsafe behavior in time, avoids the overload of discharging platform from stacking and makes At many construction safety accidents, effectively prevented the security risk during construction material is had bad luck, greatly improve building site peace Full civilized construction image, and the platform assembly of this process can ground once assemble in place Integral lifting to design position Installation, can also be in bulk in design platform position, so that constructing operation is convenient, assembling speed is fast, while convenient for being repeated as many times week Turn to use, completes the use process of entire high-building construction overhanging unloading platform device like this.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of high-building construction overhanging unloading platform device, including floor plates (1), brace (8) and weighing plate top frame (13), it is characterised in that: be provided with girder (2) above the floor plates (1), and be fixed with U-shaped anchor bolt on the left of girder (2) (3), it is fixed with L-type anchor bolt (4) at the side bar of the girder (2) and floor plates (1), and the lower right of L-type anchor bolt (4) is equipped with Snap-gauge (5) is provided with connecting plate (6) above the girder (2), and connecting plate (6) is fixedly arranged above secondary beam (7), described Brace (8) is installed on the upper left side of connecting plate (6), and weighing plate bottom frame (9), the title are provided with above brace (8) It is equipped with weighing sensor (10) above weight board bottom frame (9), and is fixed with sideboard (11), institute on the outside of weighing plate bottom frame (9) The top that weighing plate top frame (13) is set to weighing sensor (10) is stated, and the upper right of weighing plate top frame (13) is equipped with report Warning lamp (12), the weighing plate top frame (13) are fixedly arranged above steel plate (14), and the upper left of steel plate (14) is equipped with weight It measures display screen (19), the bottom outside of the girder (2) is welded with steel cable hanging point (18), and the top setting of steel cable hanging point (18) Have wirerope (16), the middle lower section of the wirerope (16) is fixed with flower basket bolt (15), and the top installation of wirerope (16) Have hanging ring (17), be provided with aperture (20) on the outside of the connecting plate (6), the two sides up and down of the secondary beam (7) are mounted on secondary Beam connecting plate (21), and the two sides of secondary beam connecting plate (21) are fixed with connection bolt (22), the top peace of the U-shaped anchor bolt (3) Equipped with nut (23), and it is fixed with hard-wood wedge (25) on the inside of U-shaped anchor bolt (3), is provided with glue above the hard-wood wedge (25) It pads (24), and is fixed with reinforcing rib (26) below hard-wood wedge (25).
2. a kind of high-building construction overhanging unloading platform device according to claim 1, it is characterised in that: the secondary beam (7) the perpendicular shape structure between girder (2), and secondary beam (7) is detachable by constituting between connection bolt (22) and girder (2) Structure.
3. a kind of high-building construction overhanging unloading platform device according to claim 1, it is characterised in that: the oblique pull It is in parallel shape structure between bar (8), and the central axes between brace (8) about girder (2) are symmetrical.
4. a kind of high-building construction overhanging unloading platform device according to claim 1, it is characterised in that: the weighing Plate top frame (13) rectangular structure, and the symmetrical centre weight of the symmetrical centre of weighing plate top frame (13) and weighing plate bottom frame (9) It closes.
5. a kind of high-building construction overhanging unloading platform device according to claim 1, it is characterised in that: the steel plate (14) between weighing plate top frame (13) for welding, and steel plate (14) with a thickness of 3cm.
6. a kind of high-building construction overhanging unloading platform device according to claim 1, it is characterised in that: the reinforcement Muscle (26) is provided with four groups, and the vertical centerline between reinforcing rib (26) about U-shaped anchor bolt (3) is symmetrical.
CN201821215645.7U 2018-07-30 2018-07-30 A kind of high-building construction overhanging unloading platform device Active CN208734101U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821215645.7U CN208734101U (en) 2018-07-30 2018-07-30 A kind of high-building construction overhanging unloading platform device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821215645.7U CN208734101U (en) 2018-07-30 2018-07-30 A kind of high-building construction overhanging unloading platform device

Publications (1)

Publication Number Publication Date
CN208734101U true CN208734101U (en) 2019-04-12

Family

ID=66027553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821215645.7U Active CN208734101U (en) 2018-07-30 2018-07-30 A kind of high-building construction overhanging unloading platform device

Country Status (1)

Country Link
CN (1) CN208734101U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177325A (en) * 2020-09-25 2021-01-05 山西二建集团有限公司 Large-span concrete construction template structure of encorbelmenting
CN113404312A (en) * 2021-07-29 2021-09-17 中建八局第四建设有限公司 Temporary unloading platform for building construction floor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177325A (en) * 2020-09-25 2021-01-05 山西二建集团有限公司 Large-span concrete construction template structure of encorbelmenting
CN113404312A (en) * 2021-07-29 2021-09-17 中建八局第四建设有限公司 Temporary unloading platform for building construction floor

Similar Documents

Publication Publication Date Title
CN110886237B (en) Arch bridge construction method
CN107419894B (en) Adhesion type lifting type aluminium alloy scaffold
US5730245A (en) Safety cable deck anchor
CN103556823B (en) The construction method of lamina tecti form bracing system made by silo sliding formwork operating platform
CN205577381U (en) Can have enough to meet need spelling formula overload alarm platform of unloading of encorbelmenting
CN208734101U (en) A kind of high-building construction overhanging unloading platform device
CN202755634U (en) Suspension type operational platform
CN210975865U (en) Structure of high-rise building cross I-shaped steel rib embedded column base
CN215254604U (en) Template support system encorbelments
CN205012666U (en) High altitude steel construction vestibule integrally lift up support structure
CN201420385Y (en) Overhanging type unloading platform for building construction
AU2013212529A1 (en) Automated formwork climbing system
CN101892736A (en) High altitude moving hanging basket construction method
CN207974601U (en) A kind of large size earthing concrete tank dome steel support structure
CN113605771A (en) Prestress assembly type frame structure system
CN206581577U (en) Using housing construction builder's jack
CN102251666B (en) Overhanging type discharging platform
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN207227957U (en) Pier construction security protection platform
CN109594477A (en) A kind of big bent cap strutting system construction technology of only pier
CN102953344A (en) Climbing cone type triangular cantilever bracket
CN110904854B (en) Arch bridge construction method adapting to removal progress
CN209685125U (en) A kind of overhead large-span steel structure vestibule Integral synchronous lifting device
CN208152549U (en) A kind of monoblock type large-scale composite form system
CN109911755A (en) A kind of overhead large-span steel structure vestibule Integral synchronous hoisting frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant